WEEKLY REPORT SPC Health & Wellness Building
August 17—23rd
This week activities: Next week activities:
• PMU #02: Continue with duct banks and pouring out both trenches in with flowable fill.
• Continue excavation and installing chill water piping.
• PMU #04—Finished trenching and in-stalling fire line.
• Continue pumping out ground water
• PMU #02: Continue installing steel piping and welding fittings for the chill water and continue excavating trench and hauling out spoils. Con-tinue installing asphalt at both trenches in Mittman.
• Continue with ground water investi-gation
Click here for drone footage!
Wellness PMU #02
PMU #02