Page 1: WEEKLY REPORT - Alamo Colleges DistrictWEEKLY REPORT SPC Health & Wellness Building June 1—June 7th This week activities: Next week activities: • Continue pumping water from crawl

WEEKLY REPORT SPC Health & Wellness Building

August 17—23rd

This week activities: Next week activities:

• PMU #02: Continue with duct banks and pouring out both trenches in with flowable fill.

• Continue excavation and installing chill water piping.

• PMU #04—Finished trenching and in-stalling fire line.

• Continue pumping out ground water

• PMU #02: Continue installing steel piping and welding fittings for the chill water and continue excavating trench and hauling out spoils. Con-tinue installing asphalt at both trenches in Mittman.

• Continue with ground water investi-gation

Click here for drone footage!

Page 2: WEEKLY REPORT - Alamo Colleges DistrictWEEKLY REPORT SPC Health & Wellness Building June 1—June 7th This week activities: Next week activities: • Continue pumping water from crawl

Wellness PMU #02

PMU #02