+ All Categories
Home > Documents > WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional...

WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional...

Date post: 28-Jul-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
47
WELCOME! Steering Committee Meeting JUNE 14, 2017
Transcript
Page 1: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

WELCOME!

Steering Committee Meeting JUNE 14, 2017

Page 2: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

AGENDA JUNE 14, 2017 6pm – 8pm

Presentation Project Updates Process and Schedule

Presentation Review Input from Open House and Survey

Discussion Conceptual Design Review and Comment

Public Comment

Action Endorsement of Preferred Concept

Discussion Next Steps

Submit PC package on June 27

Submit BAR submittal package on August 1

PC Meeting on August 8

BAR Presentation August 15

SC/TC Meeting Series #5 August 16

Key Objectives

• Review feedback received

• Review conceptual design

• Obtain endorsement of preferred concept

Page 3: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept for submittal to PC and BAR.

Three Decisions Pedestrian Circulation Crossing 9th Street south of the railroad

Graves Street Access Turning movements

Vertical Circulation Concepts Movements from bridge to Water Street north of railroad

Recommended Concept

Preferred Concept

Page 4: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

Project Updates Process and Schedule/Next Steps

Page 5: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

Process/Schedule

June 1

We are here!

June 14

Next Steps

• Planning Commission Meeting August 8

• BAR Meeting August 15

• Steering Committee and Technical Committee Meetings August

Page 6: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

Review Input from Open House and Survey

Page 7: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

   

                

                 

            

Open House Takeaways June 1, 2017

Supported: Overall Corridor Plan: closing Old Avon at Garrett

Supported: Protected bike lane and wide sidewalks

Supported: Minimal medians – enhanced perimeter landscape on approaches

Supported: West Main Street light fixtures – supplemented lighting where needed

More Discussion: Options for at‐grade crosswalk and passageway under 9th Street

More Discussion: Turning movements at Graves Street and 9th Street

More Discussion: Stairs on east and west sides with mezzanine connection – study ADA ramp options

Page 8: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

Conceptual Design Decisions

1

2

3

Pedestrian Circulation Crossing 9th Street south of the railroad

Graves Street Access Turning movements

Vertical Circulation Concepts Movements from bridge to Water Street north of railroad

Page 9: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

32.2%

22.1%

45.7%

Pedestrian Circulation

Option 1. Construct a pedestrian underpass

Option 2 Maintain existing at-grade crossing

Option 3 Do both

Page 10: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

Pedestrian Circulation Potential At Grade Crossing near Graves St.

Pedestrian Passageway Opening

Section Key

View Looking North within passageway

Page 11: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

47.5%

52.5%

Graves Street Access

Alternative 1

Restrict left turns from southbound 9th Street to Graves Street; Allow right turns onto and from Graves Street (but prohibit left turns from Graves Street to southbound 9th Street)

Alternative 1A

Allow left turns from southbound 9th Street to Graves Street; Allow right turns onto and from Graves Street (but prohibit left turns from Graves Street to southbound 9th Street)

Page 12: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

Graves St. Access

Alternative 1 This alternative includes a concrete median that prevents vehicles from turning onto Graves St. from southbound 9th St. Vehicles also are permitted to turn right in and out of Graves St. Vehicles cannot turn left from Graves St.

Alternative 1A This alternative allows vehicles to turn left onto Graves St. from southbound 9th St. Vehicles are also permitted to turn right in and out of Graves St. Vehicles cannot turn left from Graves St.

Page 13: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

Vertical Circulation Concepts

Concept 1 Stairs on east and west side with a mezzanine connection between 9th Street and Water Street

Concept 2 Stairs on east and west side (no mezzanine connection)

Concept 3 Stairs on east side with a mezzanine connection between 9th Street and Water Street. No west side stairs to Water Street.

65.8%

20.1%

14.1%

Page 14: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

Vertical Circulation Option 1 – Stairs on east side and west side with Mezzanine connection • East and West stairs to Water St.• Mezzanine connection to west side stairs

Option 2 – Stairs on east side and west side (NO Mezzanine connection) • East and West stairs to Water St.

Option 3 – Stairs on east side and with Mezzanine connection • East and West stairs to Water St.• Mezzanine connection to West stairs

VIEW LOOKING NORTH FROM WATER ST

Page 15: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

Vertical Circulation

Page 16: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

Rendering – Water St. Looking Northeast

             

Update

Vertical Circulation North Abutment Preferred: Central and West Stairs w/ Mezz

Page 17: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

Vertical Circulation

ADA Ramp to Mezzanine ADA Ramp from 9th St. to Water St. • 215 Linear Feet of Ramp • 440 Linear Feet of Ramp

• Requires 2,200 SF of ROW Purchase • Requires 4,000 SF of ROW Purchase

• Would be necessary to replace the Water St. retaining wall

Page 18: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

Conceptual Design Decisions – Questions?

1

2

3

Pedestrian Circulation Crossing 9th Street south of the railroad

Graves Street Access Turning movements

Vertical Circulation Concepts Movements from bridge to Water Street north of railroad

Page 19: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

Concept Design Review and Comment Updated Images

Page 20: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

Corridor Plan

Page 21: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

Roadway Sections

Looking North on 9th St. from Graves St.

Looking North on 9th St. from North of Bridge

Looking North on 9th St. on Belmont Bridge

Page 22: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

             

Rendering – Aerial Looking West

Vertical Circulation North Abutment Preferred: Central and West Stairs w/ Mezz

Page 23: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

             

Renderings - Looking East to Bridge

Vertical Circulation North Abutment Preferred: Central and West Stairs w/ Mezz

Page 24: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

             

Rendering –Water Street looking West

Vertical Circulation North Abutment Preferred: Central and West Stairs w/ Mezz

Page 25: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

Update –no skirt

Rendering – Looking Southeast from Water Street

Piers

Page 26: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

3D Rendering – Looking East from Water St. Street

Railroad Fencing

Page 27: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

3D Rendering – Looking West from 9th Street

Railroad Fencing

Page 28: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

 

Landscape Forms FGP Pedestrian Light Landscape Forms Ashbery Pedestrian Light

Lighting Types

Lighting Pedestrian Walkway

Page 29: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

 

Landscape Forms FGP Pedestrian Light

Perspective Views

Lighting Pedestrian Walkway

Page 30: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

   

Recessed Wall Fixture at Parapet

Lighting Types

Lighting Site and Accent

Recessed Handrail Fixture

Page 31: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

   

Update

Lighting Site and Accent

Perspective Views

Rendering – From Mall Looking South East – Recessed Wall Fixtures

Page 32: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

   

Update

Lighting Site and Accent

Perspective Views

Rendering – From Mall Looking South East – Railing Fixture

Page 33: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

   

Update

Lighting Site and Accent

Perspective Views

Rendering – From Mall Looking East (w/Art Installation)

Page 34: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

Model Views

   

Walls Formed Precast

Blue Ridge Mountain Outcropping Intermittent Shadows Produced by Convex /Concave Faceted Panels

Precast Concrete: Modular Panel System

Precast Panels - Modules

Page 35: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

Model Views

 Walls Green Screen

Trellis Panel: 3’ - 4’ module Precast mounting Detail Trellis Panel mtd. to Masonry Wall

Page 36: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

Walls: North Abutment

South Elevation

Water St West

Page 37: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

Walls: North Abutment

Perspective from South

Water St West

Page 38: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

Walls: South Abutment

West Elevation

Flat and Beveled Modular Precast Panels

3’ modular Green Screen Panels

Location for Mural or Graffiti

West Elevation - Typical Components West Elevation @ Tunnel

Water St West

Page 39: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

– –

Walls: South Abutment

East Elevation

Flat and Beveled Modular Precast Panels

3’ modular Green Screen Panels

Location for Mural or Graffiti

East Elevation Elevation Tunnel Access East Elevation @ Tunnel

Water St West

Page 40: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

Walls: South Abutment

Perspective from Southwest

Water St West

Page 41: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

Public Comment

Page 42: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

Endorsement of Preferred Concept

Page 43: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

Conceptual Design Decisions

1

2

3

Pedestrian Circulation Crossing 9th Street south of the railroad

Graves Street Access Turning movements

Vertical Circulation Concepts Movements from bridge to Water Street north of railroad

Page 44: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

32.2%

22.1%

45.7%

Pedestrian Circulation – SC Direction

Option 1. Construct a pedestrian underpass

Option 2 Maintain existing at-grade crossing

Option 3 Do both

Page 45: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

47.5%

52.5%

Graves Street Access – SC Direction

Alternative 1

Restrict left turns from southbound 9th Street to Graves Street; Allow right turns onto and from Graves Street (but prohibit left turns from Graves Street to southbound 9th Street)

Alternative 1A

Allow left turns from southbound 9th Street to Graves Street; Allow right turns onto and from Graves Street (but prohibit left turns from Graves Street to southbound 9th Street)

Page 46: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

Vertical Circulation Concepts – SC Direction

Concept 1 Stairs on east and west side with a mezzanine connection between 9th Street and Water Street

Concept 2 Stairs on east and west side (no mezzanine connection)

Concept 3 Stairs on east side with a mezzanine connection between 9th Street and Water Street. No west side stairs to Water Street.

65.8%

20.1%

14.1%

Page 47: WELCOME! Steering Committee Meeting...The goal of this meeting is to obtain guidance, additional feedback, and endorsement, with any recommended changes, of a final preferred concept

Thank you….


Recommended