Wilson Street Reconstruction
Upgrading Wilson Street from Gordon / Norfolk Street to Macdonell Street
will generally include:
· Streetscape upgrades outlined in the Downtown
Streetscape Manual
· Replacement of asphalt
· Sidewalk upgrades
· Cycling facilities
· On-Street parking
· Streetlighting
· Watermain, Sanitary, and Storm Sewer replacement
· Pedestrian refuge island at MacDonell
· Review of grading at building entrances
The City of Guelph has reviewed feedback from the previous public
meeting and has conducted a number of background studies in order to
develop a Preferred Design Concept for Wilson Street.
The City of Guelph is now looking for feedback from the public on the
Preferred Design Concept before proceeding with final design.
Please provide your written feedback using the comment sheet provided.
July 20th Public Meeting
Wilson Street Reconstruction Macdonell Street to Gordon/Norfol k Stree t
Evaluation Matrix
Evaluation Criteria
Alternative 1
Existing Traffic Flow Two-Way
(Macdonell to Northumberland) One-Way Northbound
(Gordon / Norfolk to Northumberland)
Alternative 2
Reverse One-Way Section Two-Way
(Macdonell to Northumberland) One-Way Southbound
(Gordon / Norfolk to Northumberland)
One-Way Northbound
(Gordon / Norfolk to Macdonell)
Alternative 4
One-Way Southbound
(Macdonell to Gordon / Norfolk)
Alternative 5
Tec
hn
ical
Traffic Performance (based on forecast 2031 traffic conditions)
Lower Level of Service (LOS) during peak hours for: -Norfolk and Paisley -Macdonell and Wilson -Macdonell and Wyndham
Lower Level of Service (LOS) during peak hours for: -Norfolk and Paisley
Lower Level of Service (LOS) during peak hours for: -Norfolk and Paisley -Macdonell and Wilson -Macdonell and Wyndham
Lower Level of Service (LOS) during peak hours for: -Norfolk and Paisley
Road network continuity
-Maintains current access to downtown through Wilson Street -Maintains two-way section for access to businesses and residences
-Removes access to downtown via Wilson -Maintains two-way section for access to businesses and residences
-Maintains current access to downtown through Wilson Street -Only one-way access to businesses between Carden and Macdonell
-Removes access to downtown via Wilson -Only one-way access to businesses between Carden and Macdonell -One-way connection at Carden forces movement out of downtown
Cycling/Walking Impacts Provides for two-way cycling and sidewalks along full length of Wilson
Provides for two-way cycling and sidewalks along full length of Wilson
Provides for two-way cycling and sidewalks along full length of Wilson
Provides for two-way cycling and sidewalks along full length of Wilson
Summary
Nat
ura
l En
viro
nm
ent Natural Area Impact Minimal impacts to natural environment Minimal impacts to natural environment Minimal impacts to natural environment Minimal impacts to natural environment
Air Quality Impact Minimal impacts to air quality Minimal impacts to air quality Minimal impacts to air quality Minimal impacts to air quality
Stormwater Impact Improvements to be made to stormwater collection Improvements to be made to stormwater collection Improvements to be made to stormwater collection Improvements to be made to stormwater collection
Summary
So
cial
/ Cu
ltu
ral
Heritage/Cultural Landscape Impacts No anticipated impacts No anticipated impacts No anticipated impacts No anticipated impacts
Neighbourhood/Community Impacts -Maintains movement toward downtown -Minimal additional streetscaping opportunities
-Reverses movement from downtown -Provides streetscape & parking opportunity at Gordon / Wilson intersection
-Maintains movement toward downtown -Provides additional streetscaping opportunities
-Reverses movement from downtown -Provides additional streetscaping opportunities -Provides streetscape & parking opportunity at Gordon / Wilson intersection
Noise Impacts No change in noise levels No change in noise levels No change in noise levels No change in noise levels
Summary
Eco
no
mic
/Fin
anci
al
Capital Cost Minimal change in capital costs Some additional costs at Gordon / Norfolk intersection
Minimal change in capital costs Some additional costs at Gordon / Norfolk intersection
Operating & Maintenance Cost Minimal change in maintenance costs Minimal change in maintenance costs Minimal change in maintenance costs Minimal change in maintenance costs
Economic Impacts for Downtown Businesses and Residents
-Maintains movement toward downtown -Lower traffic performance reduces access to business and parking
-Reverses movement from downtown -Maintains traffic performance for access to business and parking
-Maintains movement toward downtown -Lower traffic performance reduces access to business and parking
-Reverses movement from downtown -Maintains traffic performance for access to business and parking
Property Acquisition None Required None Required None Required None Required
Summary
Preferred Overall Evaluation
Note: Alternative 3 (Two-Way traffic along the full length of Wilson Street from Macdonell to Gordon / Norfolk) was screened out based input received during the first public meeting as well as input from City staff which noted that a number of project objectives would not be satisfied by the alternative.
Date March January
7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 6 13 20 27 3 10 17 24
Consultant Appointment
Phase 1 - Design Build RFP
Project Initiation
Preparation of RFP Package and Performance Specs
Class D cost estimate
Update cost estimate
Design-Build Prequalification Process
Issue Pre-qualification request to design build contractors May 20, 2016
Pre-qualification tender period
Pre-qualification Evaluation period
Selection of pre-qualified Design Build Contractor
Issue Design-Build RFP to pre-qualified contractors July 15, 2016
Design-Build RFP Bid Period
Bid submission Aug 22, 2016
Proposals evaluation period
Presentation and Recommendation to Council Sept 19, 2016
Wilson Street - Design Phase
Public Consultation #1 (Options)
Stage 1 Archaeology Study
Heritage Impact Assessment
Socio-Economic Impact Assessment
Traffic Study
Geotechnical Investigation
Wilson Street - Develop Design Alternatives
Public Consultation #2 (Preferred Alternative)
Wilson Street - Final Design
Class EA Report Preparations
City Staff - Internal Review of EA Report
Council Approval to File Class EA Report
30-day Notice Period for Class EA Filing
Wilson Street Construction Tender Period (Surface Works Provisional)
Wilson Street Tender Analysis and Recommendation
Council Award of Wilson Street Tender
Wilson Street - Construction Phase
Wilson Street - Underground Infrastructure Construction
Wilson Street - Surface Works Construction May 2017
Phase 2A - Design Compliance Review
Design Build Team design phase
Design Compliance Review at 50%
Design Compliance Review at 100%
Phase 2B Construction Compliance Review TO WINTER 2017
Parking Garage Construction Phase
Project ScheduleWilson Street Reconstruction
(Macdonell Street to Gordon/Norfolk Street)
Wilson Street Parkade
WE
AR
E H
ER
E
DecemberMay June July August September
2017
Activity AprilMarchOctober FebruaryApril
2016
November
Legend
Parkade Task
Milestone
Street Task
~1.8m
Conc. S/W
~0.2m Barrier Curb
~2.0m Conc. S/W
~5.6m
Lane
~1.7m Conc. S/W
~2.6m
Conc. S/W
~2.9m
Parallel Parking
~3.9m
Lane
~3.5m
Lane
~5.7m
Angled Parking
~2.8m
Conc. S/W
~0.2m Barrier Curb
~
2
.
4
m
C
o
n
c
.
S
/
W
~
5
.
9
m
L
a
n
e
~
1
.
7
m
C
o
n
c
.
S
/
W
~0.5m Curb & Gutter
~0.5m Curb & Gutter
~1.3m Bike Lane
~
1
.
3
m
B
i
k
e
L
a
n
e
LegendProperty Line
Mac
done
ll
Str
eet
Car
den
Str
eet
C.N
. R
ailw
ay
Norfolk Street
Wilson Street
Gordon Street
City Hall
Wilson Street Reconstruction
Existing Conditions
July 20th Public Meeting
Nor
thum
berl
and
Str
eet
F
a
r
m
e
r
s
M
a
r
k
e
t
Existing Tree
Existing Concrete
Existing Interlocking Brick
Existing Asphalt
Existing Grass Boulevard
Existing Parking
East - 5 Parallel
West - 13 Angled
- 1 Barrier Free
Total - 19 Spaces
Approx. 21.8m
TrenchDrain
EastProperty Line
WestProperty Line
2.3mParallelParking
~2.8mConcreteSidewalk
3.35mShared Lane
3.35mShared Lane
TrenchDrain
~4.0mConcreteSidewalk
0.3mEdge Zone
0.3mEdge Zone
2.3mParallelParking
2.5mPlanting &Furnishing
Zone
LS
Wilson StreetTypical Section - Northumberland to Gordon / Norfolk
Approx. 13.4m
EastProperty Line
WestProperty Line
3.2mOne-Way
Lane
1.5mContraFlowBikeLane
~1.8mConcreteSidewalk
Curb &Gutter
1.5mBikeLane
~1.8mConcreteSidewalk
ExistingRetaining
Wall
ExistingRetaining
Wall
0.3mBufferStrip
0.5mBufferStrip
Curb &Gutter
0.5mBufferStrip
R
6
.
0
m
R
3
7
.4
m
R
1
2
.
2
m
R
6
.
0
m
R
6
.
0
m
Stop Sign
Stop Sign
Stop Sign
Do Not Enter
Bicycles Excepted
R
1
.
7
m
0.3m Trench Drain
0.3m Trench Drain
0.3m Edge Zone
0.3m Edge Zone
Match Existing
Match Existing
Match Existing
2.8m
Conc. S/W
2.3m Parallel Parking (x4)
3.35m
Shared Lane
3.35m
Shared Lane
2.3m Parallel Parking (x7)
~4.0m
Conc. S/W
2.5m Planting &
Furnishing Zone
End Protection Sign
Do Not Enter
R
6
.
0
m
R
9
.
0
m
~1.8m Conc. S/W
1.5m Bike Lane
0.3m Painted
Buffer Strip
~1.8m Conc. S/W
1.5m Bike Lane
Taper 0.5m Buffer
Pedestrian
Crossing Sign
~1.8m
Conc. S/W
0.5m Curb & Gutter
~
1
.
8
m
C
o
n
c
.
S
/
W
3.2m
One Way
0.5m Buffer
~
1
.
8
m
C
o
n
c
.
S
/
W
0.5m Curb & Gutter
R
6
.
0
m
Pedestrian
Crossing Sign
0.5m Buffer
R
5
.
0
m
R
2
.
0
m
Northumberland Street Design
& Construction By Parking
Garage Design Build Team
Proposed Parking
East - 4 Parallel
West - 7 Parallel
Total - 11 Spaces
Wilson StreetTypical Section - Macdonell to Northumberland
Legend
Proposed Concrete
Proposed Asphalt
Property Line
Proposed Trench Drain
Proposed Bike Box
Mac
done
ll
Str
eet
Car
den
Str
eet
C.N
. R
ailw
ay
Norfolk Street
Wilson Street
Gordon Street
City Hall
Wilson Street Reconstruction
Preferred Design Concept
July 20th Public Meeting
Nor
thum
berl
and
Str
eet
For Gordon St & Waterloo Ave Works
See Gordon/Waterloo Panel
Norfolk Street
F
a
r
m
e
r
s
M
a
r
k
e
t
Future
Parking Garage
Entry/Exit
Future
Parking Garage
Entry/Exit
Match Existing
Match Existing
Existing Tree
Proposed Tree
Proposed LandscapedBoulevard
Proposed Paver Brick
~
1
.
7
m
C
o
n
c
.
S
/
W
Proposed Parking
4 Parallel
C.N
. R
ailw
ay
Waterloo AvenueRealignment
Wilson Street Reconstruction
Gordon Street & Waterloo Avenue Road Works
July 20th Public Meeting
Norfolk Street
Farmers Market
Wils
on
Stre
et
Farmers Market
Wils
onSt
reet
Nor
folk
Str
eetC.N. Railway
Gordon StreetRight Turn Lane Replacement
and Streetscaping Concept
Esse
x S
tree
t
Do Not Enter
Do Not Enter
Bicycles Excepted
Existing Lane Markings On
Waterloo Avenue To Be Adjusted
Existing Right Turn Lane On
Gordon Street To Be Removed and
Replaced With Parallel Parking
Gor
don
Str
eet
Do Not Enter
Do Not Enter
Bicycles Excepted
Legend
Proposed Concrete
Proposed Asphalt
Property Line
Proposed Trench Drain
Proposed Bike Box
Existing Tree
Proposed Tree
Proposed LandscapedBoulevard
Proposed Paver Brick
Approx. 21.8m
TrenchDrain
EastProperty Line
WestProperty Line
2.3mParallelParking
~2.8mConcreteSidewalk
3.35mShared Lane
3.35mShared Lane
TrenchDrain
~4.0mConcreteSidewalk
0.3mEdge Zone
0.3mEdge Zone
2.3mParallelParking
2.5mPlanting &Furnishing
Zone
Wilson Street - Preferred Design ConceptTypical Section - Macdonell to Northumberland
2.0mPedestrianClearway
~4.0mMarketing Zone
LS
Wilson Street - Flexible Streetscape OptionTypical Section - Macdonell to Northumberland
Approx. 21.8m
TrenchDrain
EastProperty Line
WestProperty Line
2.3mParallelParking
~2.8mConcreteSidewalk
3.35mShared Lane
3.35mShared Lane
TrenchDrain
~3.6mConcreteSidewalk
0.3mEdge Zone
Layout 15.2m Angled Parking
0.3mEdge Zone
MovableBollards
Layout 2Parallel Parking
MovableBollards
~3.0m SeasonalMarketing Zone
2.0mPedestrianClearway
LS
Wilson StreetExisting Conditions - Macdonell to Northumberland
Approx. 21.8m
BarrierCurb
EastProperty Line
WestProperty Line
~2.9mParallelParking
~2.6mConcreteSidewalk
~3.9m Lane ~3.5m Lane~2.8m
ConcreteSidewalk
~5.7mAngled Parking
BarrierCurb
Wilson Street Reconstruction
Macdonell to Northumberland
Streetscape Alternative
July 20th Public Meeting
Proposed Parking
East - 4 Parallel
West - 7 Parallel
Total - 11 Spaces
Proposed Parking
(Angled Layout)
East - 4 Parallel
West - 12 Angled
- 1 Barrier Free
Total - 17 Spaces
Existing Parking
East - 5 Parallel
West - 13 Angled
- 1 Barrier Free
Total - 19 Spaces