The World Bank Implementation Status & Results Report WATER AND SANITATION SERVICE IMPROVEMENT PROJECT (P096367) 10/28/2015 Page 1 of 21 Public Disclosure Copy Public Disclosure Copy WATER AND SANITATION SERVICE IMPROVEMENT PROJECT (P096367) AFRICA | Kenya | Water Global Practice | IBRD/IDA | Specific Investment Loan | FY 2008 | Seq No: 15 | ARCHIVED on 28-Oct-2015 | ISR20643 | Implementing Agencies: Key Dates Key Project Dates Board Approval date:20-Dec-2007 Effectiveness Date:02-Sep-2008 Planned Mid Term Review Date:14-Aug-2015 Actual Mid-Term Review Date:28-Jul-2015 Original Closing Date:31-Dec-2012 Revised Closing Date:15-Dec-2017 Project Development Objectives Project Development Objective (from Project Appraisal Document) The development objectives of the project are to: (a) increase access to reliable, affordable and sustainable water supply andsanitation services; and (b) to improve the water and wastewater services in the areas served by AWSB, LVNWSB and CWSB. This willbe achieved by (i) rehabilitating selected existing water production, transmission, storage and distribution facilities andwastewater collection, treatment and disposal facilities, (ii) expanding piped water supply services to under-served areas throughthe extension of primary and secondary distribution pipes where required (this would include service expansion into urban slums /informal settlementsthrough a balanced program including the involvement of communities in decision making), and (iii) refiningand strengthening the institutional structure, emphasizing on increasing accountability and transparency of the institutional andgovernance and management framework. The current Project's development objective is to increase access to water supply andsanitation services in the project entities' service areas. Has the Project Development Objective been changed since Board Approval of the Project Objective? Yes Board Approved Revised Project Development Objective (If project is formally restructured)PHRPDODEL The Projects development objective is to increase access to water supply and sanitation services in the project implementing entitiesservice areas. Name Previous Rating Current Rating Components Name 1. Support to the Athi Water Services Board (AWSB):(Cost $252.83 M) 2. Support to the Coast Water Services Board (CWSB):(Cost $125.04 M) 3. Support to the Lake Victoria North Water Services Board (LVNWSB):(Cost $74.00 M) Overall Ratings Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized
Transcript
Page 1: World Bank Documentdocuments.worldbank.org/curated/en/... · 10/28/2015  · Project Development Objective (from Project Appraisal Document) The development objectives of the project

The World Bank Implementation Status & Results ReportWATER AND SANITATION SERVICE IMPROVEMENT PROJECT (P096367)

10/28/2015 Page 1 of 21

Public Disclosure Copy

Public Disclosure Copy

WATER AND SANITATION SERVICE IMPROVEMENT PROJECT (P096367)

AFRICA | Kenya | Water Global Practice | IBRD/IDA | Specific Investment Loan | FY 2008 | Seq No: 15 | ARCHIVED on 28-Oct-2015 | ISR20643 |

Implementing Agencies:

Key Dates

Key Project Dates

Board Approval date:20-Dec-2007 Effectiveness Date:02-Sep-2008

Planned Mid Term Review Date:14-Aug-2015 Actual Mid-Term Review Date:28-Jul-2015

Original Closing Date:31-Dec-2012 Revised Closing Date:15-Dec-2017

Project Development Objectives

Project Development Objective (from Project Appraisal Document)The development objectives of the project are to: (a) increase access to reliable, affordable and sustainable water supply andsanitation services; and (b) to improve the water and wastewater services in the areas served by AWSB, LVNWSB and CWSB. This willbe achieved by (i) rehabilitating selected existing water production, transmission, storage and distribution facilities andwastewater collection, treatment and disposal facilities, (ii) expanding piped water supply services to under-served areas throughthe extension of primary and secondary distribution pipes where required (this would include service expansion into urban slums /informal settlementsthrough a balanced program including the involvement of communities in decision making), and (iii) refiningand strengthening the institutional structure, emphasizing on increasing accountability and transparency of the institutional andgovernance and management framework. The current Project's development objective is to increase access to water supply andsanitation services in the project entities' service areas.

Has the Project Development Objective been changed since Board Approval of the Project Objective? Yes

Board Approved Revised Project Development Objective (If project is formally restructured)PHRPDODELThe Project’s development objective is to increase access to water supply and sanitation services in the project implementing entities’ service areas.

Name Previous Rating Current Rating

Components

Name1. Support to the Athi Water Services Board (AWSB):(Cost $252.83 M)

2. Support to the Coast Water Services Board (CWSB):(Cost $125.04 M)

3. Support to the Lake Victoria North Water Services Board (LVNWSB):(Cost $74.00 M)

Overall Ratings

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: World Bank Documentdocuments.worldbank.org/curated/en/... · 10/28/2015  · Project Development Objective (from Project Appraisal Document) The development objectives of the project

The World Bank Implementation Status & Results ReportWATER AND SANITATION SERVICE IMPROVEMENT PROJECT (P096367)

10/28/2015 Page 2 of 21

Public Disclosure Copy

Public Disclosure Copy

Progress towards achievement of PDO Satisfactory Satisfactory

Overall Implementation Progress (IP) Satisfactory Satisfactory

Overall Risk Rating Substantial Substantial

Implementation Status and Key Decisions

Implementation of the project is generally proceeding as planned, and the project is on track to achieve its objectives. As of March 2015, an estimated 358,000 additional people are receiving water from improved sources compared with June 2011 (the baseline for Additional Financing), bringing the total number of people benefiting from improved water sources since inception to about 726,300. This is slightly below the end 2015 target of 736,000 people. About 211,500 people living in Nairobi have so far benefitted from new sewer connections.[1] About 53,000 people living in informal settlements in Nairobi have so far benefitted from new household water connections. Some 7,680 students are benefiting from improved shared sanitation services provided under the project. Altogether, about 945,500 people are benefiting from the project, 50 percent of whom are female. This exceeds the 2015 target of 740,000 beneficiaries. .

Page 3: World Bank Documentdocuments.worldbank.org/curated/en/... · 10/28/2015  · Project Development Objective (from Project Appraisal Document) The development objectives of the project

The World Bank Implementation Status & Results ReportWATER AND SANITATION SERVICE IMPROVEMENT PROJECT (P096367)

10/28/2015 Page 3 of 21

Public Disclosure Copy

Public Disclosure Copy

Page 4: World Bank Documentdocuments.worldbank.org/curated/en/... · 10/28/2015  · Project Development Objective (from Project Appraisal Document) The development objectives of the project

The World Bank Implementation Status & Results ReportWATER AND SANITATION SERVICE IMPROVEMENT PROJECT (P096367)

10/28/2015 Page 4 of 21

Public Disclosure Copy

Public Disclosure Copy

Page 5: World Bank Documentdocuments.worldbank.org/curated/en/... · 10/28/2015  · Project Development Objective (from Project Appraisal Document) The development objectives of the project

The World Bank Implementation Status & Results ReportWATER AND SANITATION SERVICE IMPROVEMENT PROJECT (P096367)

10/28/2015 Page 5 of 21

Public Disclosure Copy

Public Disclosure Copy

Page 6: World Bank Documentdocuments.worldbank.org/curated/en/... · 10/28/2015  · Project Development Objective (from Project Appraisal Document) The development objectives of the project

The World Bank Implementation Status & Results ReportWATER AND SANITATION SERVICE IMPROVEMENT PROJECT (P096367)

10/28/2015 Page 6 of 21

Public Disclosure Copy

Public Disclosure Copy

Risks

Systematic Operations Risk-rating Tool

Page 7: World Bank Documentdocuments.worldbank.org/curated/en/... · 10/28/2015  · Project Development Objective (from Project Appraisal Document) The development objectives of the project

The World Bank Implementation Status & Results ReportWATER AND SANITATION SERVICE IMPROVEMENT PROJECT (P096367)

10/28/2015 Page 7 of 21

Public Disclosure Copy

Public Disclosure Copy

Risk Category Rating at Approval Previous Rating Current Rating

Political and Governance -- Substantial Substantial

Macroeconomic -- Moderate Moderate

Sector Strategies and Policies -- Moderate Moderate

Technical Design of Project or Program -- Moderate ModerateInstitutional Capacity for Implementation and Sustainability -- Moderate Moderate

Fiduciary -- Moderate Moderate

Environment and Social -- Moderate Moderate

Stakeholders -- High High

Other -- Moderate Moderate

Overall -- Substantial Substantial

Results

Project Development Objective IndicatorsPHINDPDOTBL

Number of people in urban areas provided with access to Improved Water Sources under the project (Number, Core)

Baseline Actual (Previous) Actual (Current) End Target

Value 368328.00 710000.00 726300.00 736000.00

Date 30-Jun-2011 31-Dec-2014 31-Mar-2015 31-Dec-2015

CommentsPeople benefiting include those those with new connections and those receiving better services (more hours of service, more reliable service, and better quality water) due to expansion and upgrading of water treatment works and water distriibution networks.

PHINDPDOTBL

Operations and maintenance costs of WSBs recovered from customers (percentage) (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 80.00 120.00 116.00 100.00

Date 30-Jun-2007 31-Dec-2014 31-Mar-2015 31-Dec-2015

CommentsPeople benefiting include those those with new connections and those receiving better services (more hours of service, more reliable service, and better quality water) due to expansion and upgrading of water treatment works and water distriibution networks.

Page 8: World Bank Documentdocuments.worldbank.org/curated/en/... · 10/28/2015  · Project Development Objective (from Project Appraisal Document) The development objectives of the project

The World Bank Implementation Status & Results ReportWATER AND SANITATION SERVICE IMPROVEMENT PROJECT (P096367)

10/28/2015 Page 8 of 21

Public Disclosure Copy

Public Disclosure Copy

PHINDPDOTBL

AWSB (Percentage, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value 100.00 -- 153.00 100.00

Date 31-Dec-2007 -- 31-Mar-2015 31-Dec-2015

PHINDPDOTBL

CWSB (Percentage, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value 80.00 -- 102.00 100.00

Date 31-Dec-2007 -- 31-Mar-2015 31-Dec-2015

PHINDPDOTBL

LVNWSB (Percentage, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value 60.00 -- 65.00 100.00

Date 31-Dec-2007 -- 31-Mar-2015 31-Dec-2015

PHINDPDOTBL

Direct project beneficiaries (Number, Core)

Baseline Actual (Previous) Actual (Current) End Target

Value 372328.00 715050.00 945500.00 740000.00

Date 30-Jun-2011 31-Dec-2014 31-Mar-2015 31-Dec-2015

Page 9: World Bank Documentdocuments.worldbank.org/curated/en/... · 10/28/2015  · Project Development Objective (from Project Appraisal Document) The development objectives of the project

The World Bank Implementation Status & Results ReportWATER AND SANITATION SERVICE IMPROVEMENT PROJECT (P096367)

10/28/2015 Page 9 of 21

Public Disclosure Copy

Public Disclosure Copy

PHINDPDOTBL

Female beneficiaries (Percentage, Core Supplement)

Baseline Actual (Previous) Actual (Current) End Target

Value 186164.00 357525.00 472750.00 376500.00

PHINDPDOTBL

People provided with access to "improved sanitation facilities” under the proj. (Number, Core)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 20900.00 211500.00 85000.00

Date 30-Jun-2011 31-Dec-2014 31-Mar-2015 31-Dec-2015

CommentsShared sanitation facilities are being supported under the project for CWSB and LVNWSB, which is captured elsewhere in the results framework.

PHINDPDOTBL

People provided with access to “improved sanitation facilities” - urban (Number, Core Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 20900.00 211500.00 85000.00

Date 30-Jun-2011 31-Dec-2014 31-Mar-2015 31-Dec-2015

Overall Comments

Intermediate Results Indicators

Page 10: World Bank Documentdocuments.worldbank.org/curated/en/... · 10/28/2015  · Project Development Objective (from Project Appraisal Document) The development objectives of the project

The World Bank Implementation Status & Results ReportWATER AND SANITATION SERVICE IMPROVEMENT PROJECT (P096367)

10/28/2015 Page 10 of 21

Public Disclosure Copy

Public Disclosure Copy

PHINDIRITBL

Water Produced (Cubic Meter(m3), Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 520000.00 654100.00 313270.00 692000.00

Date 30-Jun-2007 31-Dec-2014 31-Mar-2015 31-Dec-2015

CommentsThe baseline and targets presented in the Project Paper for WaSSIP AF incorrectly included water from all sources, not just from the systems that WaSSIP is supporting. These have been corrected in the current draft. Baricho works are expected to be complete by December 2017. The increase in production for Mumias depends on demand from the sugar factory.

PHINDIRITBL

AWSB (Cubic Meter(m3), Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value 453000.00 -- 196000.00 600000.00

Date 31-Dec-2007 -- 31-Mar-2015 31-Dec-2015

PHINDIRITBL

CWSB (Cubic Meter(m3), Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value 57000.00 -- 53000.00 92000.00

Date 31-Dec-2007 -- 31-Mar-2015 31-Dec-2015

PHINDIRITBL

LVNWSB (Cubic Meter(m3), Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value 3500.00 -- 64270.00 3500.00

Date 31-Dec-2007 -- 31-Mar-2015 31-Dec-2015

Page 11: World Bank Documentdocuments.worldbank.org/curated/en/... · 10/28/2015  · Project Development Objective (from Project Appraisal Document) The development objectives of the project

The World Bank Implementation Status & Results ReportWATER AND SANITATION SERVICE IMPROVEMENT PROJECT (P096367)

10/28/2015 Page 11 of 21

Public Disclosure Copy

Public Disclosure Copy

PHINDIRITBL

Water delivered to customers (billed) (Cubic Meter(m3), Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 307000.00 403450.00 493756.00 467000.00

Date 30-Jun-2007 31-Dec-2014 31-Mar-2015 31-Dec-2015

PHINDIRITBL

Unaccounted for water in the system (proportion of water that water service providers supply to their distribution system that is not reflected in customer billing volumes) (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 46.00 38.20 38.00 34.00

Date 30-Jun-2007 31-Dec-2014 15-Dec-2014 31-Dec-2015

CommentsThe above indicator shown is for Nairobi; for others WSPs the indicators are shown below. The baseline and target vaules presented in the Project Paper for Mombasa were based on estimates. New meters have permitted the WSPs to compute an accurate figure. The high rate of unaccounted for water in the LVNWSB service area is due to an old water distribution network that frequently bursts when faced with the higher pressures made possible by rehabilitating and expanding the water treatment works.

PHINDIRITBL

Malindi (Percentage, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value 25.00 -- 31.00 25.00

Date 31-Dec-2007 -- 31-Mar-2015 31-Dec-2015

Page 12: World Bank Documentdocuments.worldbank.org/curated/en/... · 10/28/2015  · Project Development Objective (from Project Appraisal Document) The development objectives of the project

The World Bank Implementation Status & Results ReportWATER AND SANITATION SERVICE IMPROVEMENT PROJECT (P096367)

10/28/2015 Page 12 of 21

Public Disclosure Copy

Public Disclosure Copy

PHINDIRITBL

Eldoret (Percentage, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value -- -- 42.00 --

Date -- -- 15-Mar-2015 --

PHINDIRITBL

Mumias (Percentage, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value 60.00 -- 62.00 35.00

Date 31-Dec-2007 -- 31-Mar-2015 31-Dec-2015

PHINDIRITBL

Kimilili (Percentage, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value 60.00 -- 72.00 40.00

Date 31-Dec-2007 -- 31-Mar-2015 31-Dec-2015

PHINDIRITBL

Boreholes constructed under the project and put into operation to supply water during droughts (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 65.00 14.00

Date 30-Jun-2011 31-Dec-2014 31-Mar-2015 31-Dec-2015

CommentsAWSB is drilling 65 boreholes in its service area, and an additional 27 for other WSBs. CWSB is drilling 15 boreholes in its service area. LVNWSB is drilling 17 boreholes in its service area.

Page 13: World Bank Documentdocuments.worldbank.org/curated/en/... · 10/28/2015  · Project Development Objective (from Project Appraisal Document) The development objectives of the project

The World Bank Implementation Status & Results ReportWATER AND SANITATION SERVICE IMPROVEMENT PROJECT (P096367)

10/28/2015 Page 13 of 21

Public Disclosure Copy

Public Disclosure Copy

PHINDIRITBL

AWSB (Number, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value -- -- 52.00 14.00

Date -- -- 31-Mar-2015 31-Dec-2015

PHINDIRITBL

CWSB (Number, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value -- -- 13.00 14.00

Date -- -- 31-Mar-2015 31-Dec-2015

PHINDIRITBL

LVNWSB (Number, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value -- -- 0.00 14.00

Date -- -- 31-Mar-2015 31-Dec-2015

PHINDIRITBL

Improved community water points constructed or rehabilitated under the project (Number, Core)

Baseline Actual (Previous) Actual (Current) End Target

Value 606.00 1209.00 1150.00 620.00

Date 30-Jun-2011 31-Dec-2014 31-Mar-2015 31-Dec-2015

CommentsNo community waterpoints originally planned for CWSB under WaSSIP. However, three planned kiosks were cancelled because no available land could be found for it. The funds were instead used for yard taps.

Page 14: World Bank Documentdocuments.worldbank.org/curated/en/... · 10/28/2015  · Project Development Objective (from Project Appraisal Document) The development objectives of the project

The World Bank Implementation Status & Results ReportWATER AND SANITATION SERVICE IMPROVEMENT PROJECT (P096367)

10/28/2015 Page 14 of 21

Public Disclosure Copy

Public Disclosure Copy

PHINDIRITBL

AWSB (Number, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 -- 1100.00 614.00

Date 30-Dec-2011 -- 31-Mar-2015 31-Dec-2015

PHINDIRITBL

CWSB (Number, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value -- -- 22.00 0.00

Date -- -- 31-Mar-2015 31-Dec-2015

PHINDIRITBL

New piped household water connections that are resulting from the project intervention (Number, Core)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 103850.00 40300.00 51000.00

Date 30-Jun-2007 31-Dec-2014 31-Mar-2015 31-Dec-2015

CommentsThese figures presented for AWSB are for Nairobi, those for the CWSB are for Malindi and Mombasa, and for LVNWSB are for Eldoret, Mumias, and Kimilili water service providers. However, estimating the number of connections resulting from the project’s interventions is proving to be extremely difficult, because the project is directly responsible only for connections in informal settlements.

PHINDIRITBL

AWSB (Number, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 -- 33700.00 51000.00

Date 31-Dec-2007 -- 31-Mar-2015 31-Dec-2015

Page 15: World Bank Documentdocuments.worldbank.org/curated/en/... · 10/28/2015  · Project Development Objective (from Project Appraisal Document) The development objectives of the project

The World Bank Implementation Status & Results ReportWATER AND SANITATION SERVICE IMPROVEMENT PROJECT (P096367)

10/28/2015 Page 15 of 21

Public Disclosure Copy

Public Disclosure Copy

PHINDIRITBL

CWSB (Number, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 -- 640.00 --

Date 30-Dec-2011 -- 31-Mar-2015 --

PHINDIRITBL

LVNWSB (Number, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value -- -- 5200.00 --

Date -- -- 31-Mar-2015 --

PHINDIRITBL

People in informal settlements with access to improved water sources under the project (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 104600.00 104600.00 8600.00

Date 30-Jun-2011 31-Dec-2014 31-Mar-2015 31-Dec-2015

CommentsThe figures for Malindi and Eldoret include people benefiting from rehabilitation of a water main and water distribution network, which has brought water to taps that wer previously dry.

PHINDIRITBL

AWSB (Number, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value -- -- 67000.00 8600.00

Date -- -- 31-Mar-2015 31-Dec-2015

Page 16: World Bank Documentdocuments.worldbank.org/curated/en/... · 10/28/2015  · Project Development Objective (from Project Appraisal Document) The development objectives of the project

The World Bank Implementation Status & Results ReportWATER AND SANITATION SERVICE IMPROVEMENT PROJECT (P096367)

10/28/2015 Page 16 of 21

Public Disclosure Copy

Public Disclosure Copy

PHINDIRITBL

Mumias (Number, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value -- -- 240.00 --

Date -- -- 31-Mar-2015 --

PHINDIRITBL

Number of other water service providers that the project is supporting (Number, Core)

Baseline Actual (Previous) Actual (Current) End Target

Value 15.00 21.00 21.00 14.00

Date 30-Jun-2011 31-Dec-2014 31-Mar-2015 31-Dec-2015

PHINDIRITBL

Revenue collection efficiency (proportion of amount billed collected each year) (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value -- 95.00 91.00 90.00

Date 30-Jun-2007 31-Dec-2014 31-Mar-2015 31-Dec-2015

CommentsAboce shown indicator is for Nairobi; the indicator for the other WSPs is shown below.

PHINDIRITBL

Mombasa (Percentage, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value 95.00 -- 77.00 97.00

Date 31-Dec-2007 -- 31-Mar-2015 31-Dec-2015

Page 17: World Bank Documentdocuments.worldbank.org/curated/en/... · 10/28/2015  · Project Development Objective (from Project Appraisal Document) The development objectives of the project

The World Bank Implementation Status & Results ReportWATER AND SANITATION SERVICE IMPROVEMENT PROJECT (P096367)

10/28/2015 Page 17 of 21

Public Disclosure Copy

Public Disclosure Copy

PHINDIRITBL

Malindi (Percentage, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value 95.00 -- 97.00 97.00

Date 31-Dec-2007 -- 31-Mar-2015 31-Dec-2015

PHINDIRITBL

Mumias (Percentage, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value 50.00 -- 100.00 95.00

Date 31-Dec-2007 -- 31-Mar-2015 31-Dec-2015

PHINDIRITBL

Kimilili (Percentage, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value 72.00 -- 86.00 95.00

Date 30-Dec-2011 -- 31-Mar-2015 31-Dec-2015

PHINDIRITBL

Eldoret (Percentage, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value -- -- 95.00 --

Date -- -- 31-Mar-2015 --

Page 18: World Bank Documentdocuments.worldbank.org/curated/en/... · 10/28/2015  · Project Development Objective (from Project Appraisal Document) The development objectives of the project

The World Bank Implementation Status & Results ReportWATER AND SANITATION SERVICE IMPROVEMENT PROJECT (P096367)

10/28/2015 Page 18 of 21

Public Disclosure Copy

Public Disclosure Copy

PHINDIRITBL

Annual statutory audits for all three WSBs demonstrating transparent and accountable financial management (clean and timely audit) (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 3.00 3.00 3.00 3.00

Date 30-Jun-2007 31-Dec-2014 31-Mar-2015 31-Dec-2015

PHINDIRITBL

Northern collector tunnel constructed and operational (Kilometers, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 0.00 11.00

Date 30-Jun-2011 31-Dec-2014 31-Mar-2015 31-Dec-2015

PHINDIRITBL

New bulk water supplied under the project (Cubic Meter(m3), Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 6300.00 6300.00 198000.00

Date 30-Jun-2011 31-Dec-2014 31-Mar-2015 31-Dec-2015

PHINDIRITBL

Proportion of bills based on meter readings (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 75.00 78.00 99.00 96.00

Date 30-Jun-2011 30-Jun-2014 31-Mar-2015 31-Dec-2015

CommentsAbove shown indicator is for Nairobi; other WSPs are shown below

Page 19: World Bank Documentdocuments.worldbank.org/curated/en/... · 10/28/2015  · Project Development Objective (from Project Appraisal Document) The development objectives of the project

The World Bank Implementation Status & Results ReportWATER AND SANITATION SERVICE IMPROVEMENT PROJECT (P096367)

10/28/2015 Page 19 of 21

Public Disclosure Copy

Public Disclosure Copy

PHINDIRITBL

Mombasa (Percentage, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value 51.00 -- 69.00 95.00

Date 30-Dec-2011 -- 31-Mar-2015 31-Dec-2015

PHINDIRITBL

Malindi (Percentage, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value 62.00 -- 92.00 95.00

Date 30-Dec-2011 -- 31-Mar-2015 31-Dec-2015

PHINDIRITBL

People provided with improved access to water sources during droughts (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 80206.00 --

Date 30-Jun-2011 31-Dec-2014 31-Mar-2015 31-Dec-2015

PHINDIRITBL

AWSB (Number, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value -- -- 80200.00 --

Date -- -- 31-Mar-2015 --

Page 20: World Bank Documentdocuments.worldbank.org/curated/en/... · 10/28/2015  · Project Development Objective (from Project Appraisal Document) The development objectives of the project

The World Bank Implementation Status & Results ReportWATER AND SANITATION SERVICE IMPROVEMENT PROJECT (P096367)

10/28/2015 Page 20 of 21

Public Disclosure Copy

Public Disclosure Copy

PHINDIRITBL

People provided with access to improved shared sanitation services under the project (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 4000.00 5680.00 7680.00 5800.00

Date 30-Jun-2011 31-Dec-2014 31-Mar-2015 31-Dec-2015

CommentsAWSB: ten VIP latrines have been constructed at schools. CWSB: Two ablution blocks have been constructed at a school in Malindi. Two ablution blocks are under construction in in an informal settlement Mombasa. One ablution blocks is under construction in Mumias

PHINDIRITBL

AWSB (Number, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value 4000.00 -- 5680.00 5800.00

Date 30-Dec-2011 -- 31-Mar-2015 31-Dec-2015

PHINDIRITBL

CWSB (Number, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value -- -- 2000.00 --

Date -- -- 31-Mar-2015 --

Overall Comments

Data on Financial Performance

Disbursements (by loan)

Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed

Page 21: World Bank Documentdocuments.worldbank.org/curated/en/... · 10/28/2015  · Project Development Objective (from Project Appraisal Document) The development objectives of the project

The World Bank Implementation Status & Results ReportWATER AND SANITATION SERVICE IMPROVEMENT PROJECT (P096367)

10/28/2015 Page 21 of 21

Public Disclosure Copy

Public Disclosure Copy

P096367 IDA-43760 Closed XDR 96.60 96.18 0.42 96.18 0.00 100%

P096367 IDA-51030 Effective XDR 192.80 192.80 0.00 74.78 118.02 39%

Key Dates (by loan)

Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date

P096367 IDA-43760 Closed 20-Dec-2007 04-Jun-2008 02-Sep-2008 31-Dec-2012 31-Dec-2013

P096367 IDA-51030 Effective 10-May-2012 21-Jun-2012 14-Dec-2012 31-Dec-2015 15-Dec-2017

Cumulative Disbursements

Restructuring History

Level Approved on 23-Oct-2012

Related Project(s)

P126637-WATER AND SANITATION SERVICE IMPROVEMENT PROJECT - Additional Financing


Recommended