+ All Categories
Home > Documents > World Bank Document · 2016. 7. 11. · KPI Key Project Indicators M&E Monitoring and Evaluation...

World Bank Document · 2016. 7. 11. · KPI Key Project Indicators M&E Monitoring and Evaluation...

Date post: 13-Feb-2021
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
97
Document of The World Bank Report No: ICR00002005 IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-35670, IDA-3567A) ON A CREDIT IN THE AMOUNT OF SDR 19 MILLION (US$23.8 MILLION EQUIVALENT TO THE REPUBLIC OF MADAGASCAR FOR THE SECOND PRIVATE SECTOR DEVELOPMENT PROJECT June 30, 2011 Finance and Private Sector Development AFCS4 Africa Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized
Transcript
  • Document of

    The World Bank

    Report No: ICR00002005

    IMPLEMENTATION COMPLETION AND RESULTS REPORT

    (IDA-35670, IDA-3567A)

    ON A

    CREDIT

    IN THE AMOUNT OF SDR 19 MILLION

    (US$23.8 MILLION EQUIVALENT

    TO THE

    REPUBLIC OF MADAGASCAR

    FOR THE

    SECOND PRIVATE SECTOR DEVELOPMENT PROJECT

    June 30, 2011

    Finance and Private Sector Development

    AFCS4

    Africa Region

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

  • CURRENCY EQUIVALENTS

    (Exchange Rate Effective December 31, 2010

    Currency Unit = Malagasy Ariary (MGA)

    US$1.00 = MGA 2,174

    FISCAL YEAR

    January 1 – December 31

    ABBREVIATIONS AND ACRONYMS

    ACM Aviation Civile de Madagascar / Civil Aviation Authority

    ADEMA Aéroports de Madagascar / Madagascar Airports

    ADF Airport Development Fund

    AGOA African Growth and Opportunity Act

    ATI African Trading Insurance

    BPI Business Partners International

    CAPE Comité d‘Appui au Pilotage de la relance de l‘Entreprise / Support

    Committee for Enterprise Relaunch Pilot

    CAS Country Assistance Strategy

    CFEC Center for Facilitation of Enterprise Creation

    CP Comité de Privatisation / Interministerial Privatization Committee

    CRC Comité de Réflexion pour la Compétitivité / Competitiveness Review

    Committee

    DCA Development Credit Agreement

    EDBM Economic Development Board of Madagascar

    EMP Environmental Management Plan

    EPZ Export Processing Zone

    FASP Fonds d'Appui au Secteur Privé / Private Sector Support Fund

    FDI Foreign Direct Investment

    FIAS Foreign Investment Advisory Services

    FMI Financial Management Initiative

    FSADR Fond Social d'Appui au Développement Régional / Social and Regional

    Development Fund

    GDP Gross Domestic Product

    GOTICOM Groupement des Opérateurs des Technologies de l'Information et

    Communication / Private Sector Association of ICT Operations

    GOM Government of Madagascar

    GUIDE Guichet Unique des Investissements et du Développement des Entreprises /

    One-Stop Shop for Business Development and Investment Promotion

    HASYMA Hasy Malagasy / Cotton Company

    HIPC Heavily Indebted Poor Country

    ICB International Competitive Bidding

  • ICR Implementation Completion and Results

    ICT Information and Communication Technology

    IDA International Development Agency

    IFC International Finance Corporation

    IMF International Monetary Fund

    IMS Information Management System

    IPP Independent Power Producer

    I-PRSP Interim Poverty Reduction Strategy Paper

    IVATO International Airport of Antananarivo

    JIRAMA Jiro Sy Rano Malagasy / Power and Water Company

    KPI Key Project Indicators

    M&E Monitoring and Evaluation

    MAP Madagascar Action Plan

    MDSPP Ministère du Développement du Secteur Privé et de la Privatisation /

    Ministry of Private Sector Development and Privatization

    MSE Micro and Small Enterprises

    NBC National Competitive Bidding

    NPV Net Present Value

    OECD Organisation for Economic Cooperation and Development

    ONE Office National de 1'Environnement / National Environment Agency

    OMERT Office Malgache pour l'Etude et la Régulation des Télécommunications /

    Telecoms Regulator

    OMH Office Malgache des Hydrocarbures / Petroleum Regulator

    OPCS Operations Policy and Country Services

    PAD Project Appraisal Document

    PASERP Programme d'Appui Social et Economique pour la Réinsertion

    Professionnelle /

    Retraining Program

    PATESP Private Sector and Capacity Building Project

    PCU Program Coordination Unit

    PDO Project Development Objective

    PIU Project Implementation Unit

    PMR Project Monitoring Reports

    PNSP Programme National d'Appui au Secteur Privé / Private Sector Support

    National Program

    PPP Public Private Partnership or Purchasing Power Parity

    PSD Private Sector Development

    PSDP2 Second Private Sector Development Project

    PTF / FPP Privatization Trust Fund / Fonds de Portage et de Privatisation

    SADC Southern Africa Development Community

    SIRAMA Siramamy Malagasy / Sugar Company

    SME Small and Medium-sized Enterprises

    SODIP Société pour le Développement Industriel des Plantes de Madagascar /

    Madagascar Company for the Industrial Development of Plants

    SOE State-Owned Enterprise

    SOLIMA Solitany Malagasy / National Oil company of Madagascar

  • STP Secrétariat Technique à la Privatisation / Privatization Secretariat

    TELMA Telecom Malagasy

    TOR Terms of Reference

    UCP Unité de Coordination du Projet / Project Implementation Unit

    USF Universal Service Fund

    VOIP Voice over Internet Protocol

    Vice President: Obiageli Katryn Ezekewesili

    Country Director: Haleh Bridi

    Sector Manager: Michael J. Fuchs

    Task Team Leader: Josiane V. Raveloarison

    ICR Team Leader: Michael O. Engman

  • MADAGASCAR

    SECOND PRIVATE SECTOR DEVELOPMENT PROJECT

    CONTENTS

    Data Sheet

    A. Basic Information

    B. Key Dates

    C. Ratings Summary

    D. Sector and Theme Codes

    E. Bank Staff

    F. Results Framework Analysis

    G. Ratings of Project Performance in ISRs

    H. Restructuring

    I. Disbursement Graph

    Contents

    1. Project Context, Development Objectives and Design ............................................................... 1

    2. Key Factors Affecting Implementation and Outcomes .............................................................. 9

    3. Assessment of Outcomes .......................................................................................................... 17

    4. Assessment of Risk to Development Outcome ......................................................................... 23

    5. Assessment of Bank and Borrower Performance ..................................................................... 24

    6. Lessons Learned........................................................................................................................ 27

    Annex 1. Project Costs and Financing .......................................................................................... 30

    Annex 2. Outcome by Component................................................................................................ 32

    Annex 3. Economic and Financial Analysis ................................................................................. 58

    Annex 4. Bank Lending and Implementation Support/Supervision Processes ............................. 61

    Annex 5. Beneficiary Survey Results ........................................................................................... 64

    Annex 6. Privatization transactions supported by the Project in 2002-2010 ................................ 66

    Annex 7. Summary of Borrower‘s ICR and/or Comments on Draft ICR .................................... 69

    Annex 8. Comments of Co-financiers and Other Partners/Stakeholders ...................................... 78

    Annex 9. List of Supporting Documents ...................................................................................... 79

    Annex 10. Map of Madagascar ..................................................................................................... 80

  • A. Basic Information

    Country: Madagascar Project Name: MG - Prviate Sector

    Development II

    Project ID: P072160 L/C/TF Number(s): IDA-35670,IDA-3567A

    ICR Date: 06/30/2011 ICR Type: Core ICR

    Lending Instrument: SIL Borrower: REPUBLIC OF

    MADAGASCAR

    Original Total

    Commitment: XDR 19.0M Disbursed Amount: XDR 15.7M

    Revised Amount: XDR 15.7M

    Environmental Category: B

    Implementing Agencies:

    Secretariat Technique a la Privatisation (STP)

    Cofinanciers and Other External Partners:

    B. Key Dates

    Process Date Process Original Date Revised / Actual

    Date(s)

    Concept Review: 08/07/2000 Effectiveness: 11/12/2002 11/12/2002

    Appraisal: 01/12/2001 Restructuring(s):

    11/12/2002

    03/06/2003

    04/28/2005

    06/14/2006

    12/21/2007

    05/03/2010

    Approval: 08/28/2001 Mid-term Review: 07/18/2005 07/25/2005

    Closing: 06/30/2006 12/31/2010

    C. Ratings Summary

    C.1 Performance Rating by ICR

    Outcomes: Moderately Unsatisfactory

    Risk to Development Outcome: Moderate

    Bank Performance: Moderately Unsatisfactory

    Borrower Performance: Moderately Unsatisfactory

    C.2 Detailed Ratings of Bank and Borrower Performance (by ICR)

    Bank Ratings Borrower Ratings

    Quality at Entry: Moderately Satisfactory Government: Moderately

    Unsatisfactory

    Quality of Supervision: Moderately

    Unsatisfactory

    Implementing

    Agency/Agencies: Moderately Satisfactory

  • Overall Bank

    Performance:

    Moderately

    Unsatisfactory Overall Borrower

    Performance:

    Moderately

    Unsatisfactory

    C.3 Quality at Entry and Implementation Performance Indicators

    Implementation

    Performance Indicators

    QAG Assessments (if

    any) Rating

    Potential Problem Project

    at any time (Yes/No): No

    Quality at Entry

    (QEA): None

    Problem Project at any time

    (Yes/No): Yes

    Quality of Supervision

    (QSA): None

    DO rating before

    Closing/Inactive status:

    Moderately

    Satisfactory

    D. Sector and Theme Codes

    Original Actual

    Sector Code (as % of total Bank financing)

    Central government administration 95 67

    General finance sector 2 5

    General industry and trade sector 2 26

    Micro- and SME finance 1 2

    Theme Code (as % of total Bank financing)

    Regulation and competition policy 40 17

    Small and medium enterprise support 20 33

    State enterprise/bank restructuring and privatization 40 50

    E. Bank Staff

    Positions At ICR At Approval

    Vice President: Obiageli Katryn Ezekwesili Callisto E. Madavo

    Country Director: Haleh Z. Bridi Hafez M. H. Ghanem

    Sector Manager: Michael J. Fuchs Demba Ba

    Project Team Leader: Josiane V. Raveloarison Marie-Ange Saraka-Yao

    ICR Team Leader: Michael Olavi Engman

    ICR Primary Author: Michael Olavi Engman

  • F. Results Framework Analysis

    Project Development Objectives (from Project Appraisal Document)

    The objective of the project is to assist the Borrower to improve access, reliability and

    affordability of key utilities, through completion of the divestiture program of key state-owned

    enterprises, and capacity building initiatives to strengthen the capacity of autonomous regulators

    and privatization agencies, and facilitate entry of new operators in the deregulated sectors.

    (DCA).

    To enable the Government of Madagascar (GOM) to improve access, reliability, and

    affordability of key utilities, including transport (PAD).

    Revised Project Development Objectives (as approved by original approving authority)

    The objective of the Project is to assist the Borrower to improve access, reliability and

    affordability of key utilities, through completion of the divestiture program of key state-owned

    enterprises, and capacity building initiatives to strengthen the capacity of autonomous regulators

    and privatization agencies, and facilitate entry of new operators in the deregulated sectors and

    increase the competitiveness of Malagasy companies. (as approved by the Board in November

    2002)

    (a) PDO Indicator(s)

    Indicator Baseline Value

    Original Target

    Values (from

    approval

    documents)

    Formally

    Revised

    Target Values

    Actual Value

    Achieved at

    Completion or

    Target Years

    Indicator 1 : Private investment in the targeted sectors increased by US$100 million annually from

    2004 to 2007

    Value

    quantitative or

    Qualitative)

    NA Annual increase by

    $100 million

    Private investment in

    telecoms increased

    from $13 million in

    2004 to $120 million

    in 2007. Data for

    private investment in

    the petroleum sector

    were not available

    but anecdotal

    evidence indicates

    that the target was

    not reached.

    Date achieved 08/01/2001 12/31/2007 12/31/2010

    Comments

    (incl. %

    achievement)

    Political uncertainty made investment a poor indicator of success. Roughly one-third of

    the target was achieved in telecoms. Team monitored FDI/GDP but there was

    insufficient causality between this measure and project for it to be considered in ICR.

    Indicator 2 : Improve access to reliable, affordable, and quality services for key utilities

    Value

    quantitative or

    Qualitative)

    # of telephone lines (mobile

    + fixed) per 100 inhabitants:

    0.8 percent in 2000.

    # of Internet users 10,000 in

    # of telephone lines

    (mobile + fixed) per

    100 inhabitants: 1.5

    percent in 2004

    # of telephone lines

    per 100 inhabitants:

    2.3 percent in 2004,

    26.2 percent in 2008.

  • Indicator Baseline Value

    Original Target

    Values (from

    approval

    documents)

    Formally

    Revised

    Target Values

    Actual Value

    Achieved at

    Completion or

    Target Years

    2000

    Telecom services rates as

    for 2000

    # of Internet users

    60,000 in 2005

    Telecom services

    rates reduced by

    2006 in line with the

    average rate of

    telecom services of

    other countries in

    region

    # of internet users

    100,000 in 2005 and

    316,000 in 2008.

    Price of a 3-min local

    call in 2006

    (Mada/SSA):

    $045/0.68 for mobile

    and $0.18/0.09 for

    fixed, down from

    $3.19/

    Date achieved 08/01/2001 12/31/2006 12/31/2009 12/31/2010

    Comments

    (incl. %

    achievement)

    Access: targets exceeded - 100%.

    Affordability: achieved for mobile but nor fixed services.

    Indicator 3 : Strengthen the capacity of autonomous regulators and privatization agencies and

    facilitate entry of new operators

    Value

    quantitative or

    Qualitative)

    Insufficient capacity of

    Privatization Secretariat

    (STP) and Telecom

    regulator (OMERT)

    Capacity building of

    Privatization

    Secretariat (STP)

    and Telecom

    regulator (OMERT)

    The STP was

    strengthened

    significantly during

    the course of the

    project and became

    the de facto PIU in

    2006. OMERT

    received training.

    Date achieved 08/01/2001 12/31/2010

    Comments

    (incl. %

    achievement)

    STP was dismantled upon project closing. Industry insiders and civil servants argue that

    the technical capacity of OMERT is rather good but it lacks meaningful autonomy.

    Indicator 4 : Complete divestiture program of key state-owned enterprises

    Value

    quantitative or

    Qualitative)

    Complete/Implement

    divestiture strategy for

    TELMA, HASYMA,

    JIRAMA and SIRAMA

    Privatize TELMA

    by 2002;

    SIRAMA by 2002;

    International Airport

    of Antananarivo

    (IVATO) by 2003;

    HASYMA by 2003

    The

    Government

    made several

    changes to the

    list, including

    dropping and

    adding

    companies.

    TELMA and

    HASYMA privatized

    in 2004. JIRAMA

    partly under private

    management

    contract. SIRAMA:

    no

    launch of

    privatization

    process; 15 public

    enterprises liquidated

    and 12 partly

    liquidated.

    Date achieved 08/01/2001 12/31/2010

    Comments

    (incl. %

    The work of preparing and executing this process was satisfactory but the lack of

    commitment by the Government made it impossible to complete the agenda.

  • Indicator Baseline Value

    Original Target

    Values (from

    approval

    documents)

    Formally

    Revised

    Target Values

    Actual Value

    Achieved at

    Completion or

    Target Years

    achievement) Significant achievements still made.

    Indicator 5 : Increase competitiveness of Malagasy companies

    Value

    quantitative or

    Qualitative)

    None (Total value of

    investments. Job

    created. Job sustained

    Number of MSMEs assisted

    - were mentioned)

    Number of

    investments in

    SMEs: Year 1

    (2007): 15 Year 2:

    18; Year 3: 18 Year

    4 24 and Year 5: 27)

    There is little

    evidence that the

    activities helped

    increase the

    competitiveness of

    Malagasy companies.

    EDBM helped to

    significantly reduce

    the transaction costs

    of starting a business

    and obtaining

    permits. It is

    impossible to

    establish any causal

    link

    Date achieved 11/12/2002 12/31/2010

    Comments

    (incl. %

    achievement)

    The indicators for this sub-section of the PDO were ill-defined and causality unclear.

    Data were often not available or collected.

    (b) Intermediate Outcome Indicator(s)

    Indicator Baseline Value

    Original Target

    Values (from

    approval

    documents)

    Formally

    Revised Target

    Values

    Actual Value

    Achieved at

    Completion or

    Target Years

    Indicator 1 :

    Carry out environmental audit of petroleum sites in order to assess environmental

    impact, identify risk sharing arrangements, and propose a remedial action plan and risk

    mitigation measures

    Value

    (quantitative

    or Qualitative)

    No baseline audit available

    Core team of trained

    qualified individuals

    in place at OMH

    (petroleum

    regulator). Establish

    procedures to

    monitor

    environmental

    hazards

    Target partly

    achieved. 2005:

    environmental audit

    for phase I delivered.

    2006: committee

    decides to develop an

    action plan to protect

    and minimize risk.

    2007: 79% of service

    stations cleaned up.

    2008: Galana

    Refinery terminal is

    renovated.

    Date achieved 08/01/2001 12/31/2004 12/31/2010

  • Indicator Baseline Value

    Original Target

    Values (from

    approval

    documents)

    Formally

    Revised Target

    Values

    Actual Value

    Achieved at

    Completion or

    Target Years

    Comments

    (incl. %

    achievement)

    The output targets were largely met but the Government did not adequately address all

    the recommendations of the audit.

    Indicator 2 : Reduce the steps to create a firm (60 days and 10 steps at mid term review)

    Value

    (quantitative

    or Qualitative)

    157 days and 17 steps in

    2002

    Ease of doing

    business ranking in

    2010 report is better

    than 144th (in DB

    report 2009)

    The project was

    catalytic in achieving

    these results during

    the first years when it

    established the one

    stop shop (GUIDE)

    that was later

    incorporated into

    EDBM, which

    reformed the process

    significantly.

    Date achieved 12/01/2003 12/31/2009 12/31/2010

    Comments

    (incl. %

    achievement)

    Indicator 3 : Reduce the steps to create a firm (60 days and 10 steps at mid term review)

    Value

    (quantitative

    or Qualitative)

    157 days and 17 steps in

    2002

    Ease of doing

    business ranking in

    2010 report is better

    than 144th (in DB

    report 2009)

    Date achieved 12/01/2003 12/31/2009 12/31/2010

    Comments

    (incl. %

    achievement)

    Sources: Doing Business report and EDBM

    Indicator 4 : Facilitate growth exports through setting up EPZ. Implementation of the pilot zone in

    Tsarakofafa - Tamatave

    Value

    (quantitative

    or Qualitative)

    Off-site infrastructure

    investments are completed:

    electricity, water and

    telecommunication network

    Partnership

    agreement between

    GoM and developer

    concluded

    Date achieved 08/01/2005 12/31/2009 12/31/2010

    Comments

    (incl. %

    achievement)

    Sources: Ministry of Economy and Industry. FILATEX

    Indicator 5 : Encourage participation of nationals in the privatization process

    Value

    (quantitative

    or Qualitative)

    Shares not shared.

    a) 10% of shares of

    the targeted private

    enterprises have

    been transferred to

    the Privatization

    This activity did

    neither achieve

    significant results not

    its targets

  • Indicator Baseline Value

    Original Target

    Values (from

    approval

    documents)

    Formally

    Revised Target

    Values

    Actual Value

    Achieved at

    Completion or

    Target Years

    Trust Fund (PTF) at

    the closing of each

    transaction;

    b) PTF has offered

    these shares for sale

    to local small

    investors.

    Date achieved 08/01/2001 12/31/2010

    Comments

    (incl. %

    achievement)

    Privatization Trust Fund was created, and staffed with a Fund Manager. Although

    GOM took years to make progress on this activity, since its creation a few Government

    shares in privatized companies have been transferred to PTF.

    Indicator 6 : Increase ROI of the targeted companies: ADEMA. HASYMA, SIRAMA and TELMA

    Value

    (quantitative

    or Qualitative)

    None None

    Unclear. ISR:

    HASYMA ROI: -

    0.2% in 2004; -

    55.5% in 2005; -

    3426% in 2006; 1.3%

    in 2007 and -31.7%

    in June 2008.

    TELMA ROI: -

    84.2% in 2004;

    10.5% in 2005; 2.8%

    in 2006; 1.2% in

    2007; -5.4% in 2008

    and 0.6% in 2009.

    Date achieved 12/31/2010

    Comments

    (incl. %

    achievement)

    This indicator was insufficiently estimated and monitored

  • G. Ratings of Project Performance in ISRs

    No. Date ISR

    Archived DO IP

    Actual Disbursements

    (USD millions)

    1 01/29/2002 Satisfactory Satisfactory 0.00

    2 05/20/2002 Satisfactory Unsatisfactory 0.00

    3 12/19/2002 Unsatisfactory Unsatisfactory 0.00

    4 05/28/2003 Satisfactory Satisfactory 0.75

    5 11/25/2003 Satisfactory Unsatisfactory 3.00

    6 05/05/2004 Satisfactory Satisfactory 6.12

    7 06/17/2004 Satisfactory Satisfactory 6.12

    8 06/18/2004 Satisfactory Satisfactory 6.12

    9 12/16/2004 Satisfactory Satisfactory 9.07

    10 06/23/2005 Satisfactory Satisfactory 11.98

    11 12/28/2005 Satisfactory Satisfactory 14.41

    12 02/04/2006 Satisfactory Satisfactory 15.14

    13 07/18/2006 Satisfactory Satisfactory 16.79

    14 12/21/2006 Satisfactory Satisfactory 20.44

    15 06/28/2007 Satisfactory Satisfactory 22.27

    16 11/15/2007 Satisfactory Satisfactory 22.20

    17 12/19/2007 Satisfactory Satisfactory 22.20

    18 05/30/2008 Satisfactory Satisfactory 23.24

    19 12/23/2008 Satisfactory Satisfactory 24.12

    20 05/15/2009 Satisfactory Satisfactory 24.47

    21 12/23/2009 Moderately Satisfactory Moderately Satisfactory 24.47

    22 06/30/2010 Moderately Satisfactory Moderately Satisfactory 24.47

    23 01/11/2011 Moderately Unsatisfactory Moderately Unsatisfactory 24.84

  • H. Restructuring (if any)

    Restructuring

    Date(s)

    Board

    Approved PDO

    Change

    ISR Ratings at

    Restructuring

    Amount

    Disbursed at

    Restructuring

    in USD millions

    Reason for Restructuring & Key

    Changes Made DO IP

    11/12/2002 Y S U 0.00

    03/06/2003 N U U 0.75

    Second order restructuring for

    amending project description,

    allocation of funds to credit

    components, and the financial and

    institutional arrangements

    governing project implementation

    04/28/2005 N S S 11.69

    Second order restructuring for

    utilizing project savings to fund a

    technical assistance facility

    targeting local SMEs, to finance

    an insurance facility component of

    the Project, following

    Madagascar# s admission as

    member of ATI, and amending

    various procurement thresholds

    06/14/2006 S S 16.79

    Second order restructuring for

    extending the closing date of the

    Project to December 31, 2007, and

    reallocating some project funds

    12/21/2007 N S S 22.20

    Second order restructuring for

    extending the closing date of the

    Project to December 31, 2009, and

    reallocating project funds

    05/03/2010 MS MS 24.47

    Second order restructuring for

    extending the closing date of the

    Project to December 31, 2010

    within the framework of OP 7.30

    Dealing with de facto government.

    If PDO and/or Key Outcome Targets were formally revised (approved by the original approving body)

    enter ratings below:

    Outcome Ratings

    Against Original PDO/Targets Unsatisfactory

    Against Formally Revised PDO/Targets Moderately Unsatisfactory

    Overall (weighted) rating Moderately Unsatisfactory

  • I. Disbursement Profile

  • 1

    1. Project Context, Development Objectives and Design

    1.1 Context at Appraisal

    1. Country context: Madagascar was one of the poorest countries in the world at the turn of the century. In 2001, the country‘s gross domestic product (GDP) per capita at purchasing

    power parity (PPP) was US$848; or 59 percent of the average value in Sub-Saharan Africa.1

    Following Board approval of the Second Private Sector Development project (PSDP2) (or, the

    Project), on August 28, 2001, the economy has mostly expanded, partly as a result of increased

    exports of agricultural and garments products, debt service relief under the enhanced Heavily

    Indebted Poor Countries (HIPC) Initiative, and two major investments in the mining industry.2 In

    the past decade, the Malagasy economy stood up reasonably well to environmental and economic

    shocks, such as devastating cyclones and deteriorating terms of trade, as well as currency

    volatility. In 2002-2008, the country embarked on an ambitious reform path that brought

    improvements in social, economic and governance indicators. However, the Malagasy economy

    contracted in 2002 and 2009 due to political turmoil.

    2. Rationale for Bank assistance: The Project‘s interventions aimed to lock in earlier achievements and to strengthen the reform process embarked upon by the country in the second

    half of the 1990s. An earlier reform program, supported by the (first) Private Sector

    Development and Capacity Building Project (PATESP, CR.2956, 1997-2002), encouraged

    private sector development through changes in the legal business environment. Markets were

    liberalized and some 50 companies privatized, including eight of the largest state-owned

    enterprises (SOEs) and two financial institutions, and the Government of Madagascar (GOM)

    established regulatory agencies before the transactions of the privatization process were

    concluded. Hence, the Project was prepared and designed in a positive environment categorized

    by expectations that the Second Private Sector Development Project would be able to capitalize

    on the momentum enjoyed by the Private Sector Development and Capacity Building Project.

    3. The Project‘s interventions were designed to support the objectives of the Country Assistance Strategy (CAS) (16249-MAG), of January 17, 1997, which aimed to reduce poverty

    through high growth and ―quantum leaps in investment‖. According to the Interim Poverty

    Reduction Strategy Paper (I-PRSP), of November 28, 2000, economic performance was expected

    to improve by completing the GOM‘s ongoing financial and economic reform program. It

    included the implementation of a new legal framework that would promote transparent business

    rules, private investment, and local enterprise development in sectors with high growth potential

    such as tourism, mining, manufacturing, telecommunications and seafood. It also covered the

    finalization of the privatization program and the expansion of infrastructure. The Project

    supported these goals and aimed to improve efficiency and expansion of key infrastructure

    services that were identified in the I-PRSP as the main constraints to potential sources of growth.

    1 World Bank (2011a).

    2 IMF (2000), IMF (2004).

  • 2

    1.2 Original Project Development Objectives (PDO) and Key Indicators (as approved)

    4. According to the Project Appraisal Document (PAD), the principal objective of the project was ―to enable the Government of Madagascar to improve access, reliability, and

    affordability of key utilities, including transport‖. The Development Credit Agreement (DCA)

    dated October 5, 2001, was somewhat more comprehensive in definition and stated that the PDO

    was ―to assist the Borrower to improve access, reliability and affordability of key utilities,

    through completion of the divestiture program of key state-owned enterprises, and capacity

    building initiatives to strengthen the capacity of autonomous regulators and privatization

    agencies, and facilitate entry of new operators in the deregulated sectors.‖

    5. The Project was designed to achieve two specific goals. The first goal was to complete the divestiture of four key state-owned enterprises (SOEs) and 30 small and medium-sized

    enterprises (SMEs) as well as to liberalize the agro-industry, air transport, energy, finance, and

    telecommunications markets. This was meant to improve efficiency of the companies and create

    opportunities for new private entry and investment. The second goal was to strengthen the

    capacity of GOM to regulate privatized sectors. See Table 1 for the original key indicators to

    assess the achievement of the development objectives.

    1.3 Revised PDO and Key Outcome Indicators

    6. Shortly after the Project was approved by the Board of Directors on August 28, 2001, a lengthy political crisis erupted that paralyzed the public sector, plunged the economy into

    decline, and delayed Project effectiveness. Following the installation of a new Government and

    upon its request to the World Bank, on October 22, 2002, the President of the World Bank called

    for the Board of Executive Directors to approve several proposed changes to the World Bank

    portfolio in the post-conflict environment, including the DCA of the Project, through the

    approval of the Regional Vice President.3

    7. The Project‘s DCA was thus amended on November 12, 2002 to better reflect the priorities of the new Government. The amendment led to Project effectiveness and was the actual

    starting point for the Project as no disbursements had been made prior to the restructuring. The

    Project Development Objective (PDO) was amended with a slight addition to the original PDO

    with the final words in bold: ―to assist the Borrower to improve access, reliability and

    affordability of key utilities, through completion of the divestiture program of key state-owned

    enterprises, and capacity building initiatives to strengthen the capacity of autonomous

    regulators and privatization agencies, and facilitate entry of new operators in the deregulated

    sectors and increase the competitiveness of Malagasy companies‖. In addition, the outcome

    indicator on ‗transport‘ was dropped from the Project at the restructuring mission and this change

    was thereafter reflected in the second amendment to the DCA.

    8. On May 6, 2003, the Country Director and the Government agreed to amend the DCA a second time with modifications to introduce miscellaneous changes to the project description, the

    allocation of funds to credit components, and financial and institutional arrangements governing

    project implementation. These amendments were not resubmitted to the Board but they followed

    3 World Bank (2002).

  • 3

    the requests outlined by the World Bank President and that had been submitted to the Board of

    Directors in the fall of 2002.

    Table 1. Key performance indicators

    Outcome indicators

    Private investment in the targeted sectors increased by US$100 million annually from 2004 to 2007

    Telecommunications

    The number of telephone lines (fixed line + mobile) per 100 inhabitants (penetration rate) increased from 0.8

    percent in 2000 to 1.5 percent in 2004;

    Internet users increased from 10,000 in 2000 to 40,000 in 2004, and 60,000 in 2005;

    Telecom services rates will be reduced by end 2006 in line with the average rate of telecom services of

    countries in the region facing a level of competition in their telecom sector similar to that of Madagascar

    Transport

    Cost of international and regional airline tickets reduced in line with published economy and charter fares for

    competing destinations (such as Reunion) by 2004;

    Ground handling fees will be reduced by 8 to 10% by 2004

    Output Indicators

    Regulatory framework

    The regulatory framework for the insurance sector comprising of application decrees mentioned in the

    insurance code has been adopted in 2003

    Capacity Building

    The regulatory agencies responsible for civil aviation, petroleum, and telecommunications are fully

    operational by December 2003 and have established monitoring procedures to ensure compliance with

    technical and economic regulations and national environmental norms and World Bank Group (WBG)

    policies;

    The council of insurance and the authority in charge of oversight and monitoring of the insurance sector are

    fully operational in 2004, have established yearly procedures to ensure compliance of insurance institutions

    to international standards and are disclosing a yearly statistics report on the sector's activities by Dec. 2004;

    The Center for Facilitation of Enterprise Creation (CFEC) is adequately funded, staffed and fully operational

    by December 2003

    Privatization

    Privatization transactions are completed in the time-frame below, in compliance with transparency and competition

    rules acceptable to the WBG:

    Telecoms Malagasy (TELMA) completed by 2002;

    Sugar Company (SIRAMA) completed by 2002;

    International Airport of Antananarivo (IVATO) completed by 2003;

    Cotton Company (HASYMA) completed by 2003;

    Ten percent of shares of the targeted private enterprises have been transferred to the Privatization

    Trust Fund (PTF) at the closing of each transaction; and

    PTF has offered these shares for sale to local small investors

    New PSD activities

    New strategies in priority sectors identified by Government adopted by 2003;

    The Center for the promotion of micro and small enterprises (OMPE) is fully operational in 2003, adequately

    staffed and has established adequate procedures to support MSEs;

    Product development and training services provided to ten local start-ups by 2005

  • 4

    1.4 Main Beneficiaries

    9. The PAD did not identify specific beneficiaries. The rationale was that the Project would benefit the overall economy through increased competition, adoption of productivity enhancing

    initiatives by the private sector, and investments boosting access and lowering prices of utility

    services. The ceding of control of loss-making companies to the private sector was expected to

    generate cost savings that could be reinvested to expand basic services. For the local private

    sector, benefits were expected to be significant as the reforms would facilitate the development

    of local entrepreneurship. By targeting backbone services, such as transport and telecoms, the

    PAD explicitly assumed that the benefits of improved access and competitive rates would spill

    over into other sectors, thereby giving rise to a significant multiplier effect. Simplified

    procedures for enterprise registration, and easier and cheaper access to key business services,

    would benefit entrepreneurship.

    1.5 Original Components

    10. The PAD outlined three broad project components: (i) regulatory capacity building; (ii) transaction implementation; and (iii) ‗new Private Sector Development (PSD) activities‘. These

    project components are summarized below with a brief assessment of the causal linkages

    between component activities and PDO outcomes.

    (i) Regulatory Capacity Building

    11. The first component would strengthen the regulatory capacity of autonomous sector regulators for air transport, petroleum and telecoms, and in particular: (i) improve their

    efficiency in undertaking technical and economic regulation; and (ii) monitor environmental

    hazards in compliance with national legislation, sector standards and World Bank Group (WBG)

    policies. In addition, it would build in-house capacity of the Center for Facilitation of Enterprise

    Creation (CFEC), and strengthen the insurance sector.

    12. From a causality perspective, strengthening regulatory capacity to enhance competition, improve policy and monitor markets was an essential requirement in order to achieve the PDOs

    of enhancing access, reliability and affordability of targeted utility sectors. It was also a key pre-

    condition for a successful outcome from the privatization and reform program of public

    enterprises. The CFEC was a worthwhile initiative to support market entry in the newly

    liberalized and other sectors.

    (ii) Transaction Implementation

    13. The second component would provide support for institutional capacity building, a local ownership development scheme, and privatization implementation. First, it would strengthen the

    Privatization Secretariat (STP) through technical assistance, including for environmental

    screening and auditing, retraining through the Programme d'Appui Social et Economique pour la

    Réinsertion Professionnelle (PASERP), and through arbitration. Second, it would help divest of

    Privatization Trust Fund (PTF) shares to local investors, provide financial advisory services to

    PTF to implement regulations and safeguards, hire a private fund manager to oversee and

    manage the fund, create a registry for shares, explore the feasibility of developing mutual funds,

    and launch a communications campaign. Third, it would support completion of the remaining

  • 5

    key companies and small and medium-size enterprises (SMEs) of the ongoing privatization

    program (telecoms, the main airports, sugar and cotton). It would also provide financing to assist

    in the structuring and closing of the transactions, including legal advisory support to resolve land

    and title issues pertaining to ownership transfers, and carry out environmental audits of select

    companies.

    14. The successful implementation of the activities in this component was essential in boosting competition, freeing up GOM time and resources wasted on mostly unproductive and/or

    failing enterprises to be invested elsewhere, and in allowing for the restructuring of these

    businesses. By attacking some of the vested interests, including between civil servants,

    politicians and executives, and imperfect markets, the proposed activities were likely to reduce

    inefficiencies and waste, boost competition, provide a fairer and more conducive investment

    climate, and strengthen the Malagasy economy in the long-term.

    (iii) Developing new PSD activities

    15. The third and final component would: (i) provide support to the operational set up and efficient development of a center (OMPE) created to coordinate activities of micro and small

    enterprises (MSE); and (ii) develop strategies to support the implementation of activities

    identified in the I-PRSP. In addition, it would provide advisory services to develop a strategy to

    promote MSEs and use OMPE to allow MSEs to access market information and technology. It

    was also expected to help jump-start the development of priority sectors identified by GOM

    using pilot projects, including by assisting GOM in developing new PSD strategies, and provide

    assistance to new local business start-ups.

    16. The causal link between the activities in this third component and in facilitating entry of new operators in the deregulated sectors—the relevant part of the PDO—was clear. Yet the

    anticipated reduction of transaction and information costs would have benefited in particular

    MSEs. The large investments and expertise generally required to enter utility markets indicate

    that the activities in component 3 were insufficient to have any significant contribution to

    achieving the PDO.

    17. In summary, successful implementation of the activities would have improved access and reliability to services critical in achieving higher growth (CAS objective).

    4 It is also highly likely

    that they would have helped reduce poverty through private sector-led growth (CAS goal) in the

    long-term. The link to affordability was not obvious, however. Effective regulation—a high

    priority in the PAD—would help alleviate some of the potentially negative effects and so would

    the training program aimed at facilitating the transfer of retrenched workers into new productive

    activities. The activities and selected outputs are therefore likely to have had a positive impact on

    achieving some of the PDO outcomes, as analyzed in detail below. Causality for the

    interventions of the transport component and its associated outcome indicators were not

    convincing given the limited investment and technical assistance interventions as well as

    ambitious price reduction targets (see Table 1 for indicators and Annex 1 for budget allocation).

    This component was cancelled before implementation begun; thus it is not explored in this

    report.

    4 World Bank (2003).

  • 6

    1.6 Revised Components

    18. The three headline components remained unchanged during the course of the Project. However, modifications were made to sub-components: some were dropped and others added as

    the management team sought to adjust the project design to reflect evolving political and

    economic priorities, simplify a comprehensive and complex undertaking, and incorporate new

    development tools that were perceived as effective means to achieve the objectives. The

    restructuring in November 2002 was initiated by a formal letter sent by the President of the

    World Bank in which he requested approval for a number of modifications, as noted in the

    previous section. These and some other modifications were then recorded in the amended DCA

    of May 2003. The amendment to the DCA at the mid-term review in 2005 was minor and added

    two sub-components to the third component. Table 2 presents and explains the changes made to

    individual subcomponents during the course of the Project. Table 3 then presents a summary of

    the three components and the changes in their sub-components.

    Table 2. Revised project components

    Original component New component and nature of

    modification [year]

    Comment

    1 – REGULATORY AND CAPACITY BUILDING

    Telecoms:

    (i) technical assistance to OMERT to strengthen

    its regulatory capacity (training and advisory

    assistance),

    (ii) acquisition of frequency spectrum

    management equipment, and

    (iii) advisory services to design a rural telecom

    policy and funding mechanism

    Item (ii) dropped [2002]

    A TF (PPIAF) financed most of

    the TA identified for (i).

    (ii) was to be self-financed by

    OMERT. (iii) Project financed the

    rural telecom strategy. DCA

    amendment in 2002. Requested

    by WBG President.

    Air transport:

    (i) technical assistance for designing and

    implementing an information management

    system to improve monitoring/regulatory

    capacity and

    (ii) training for the utilization of the IMS and

    enhancement of the regulatory capability of the

    personnel.

    Component dropped [2003]

    The decision by GOM to

    restructure Air Madagascar via a

    management contract with

    Lufthansa Consulting made this

    component irrelevant.

    Center for facilitating enterprise creation:

    (i) advisory services for training of staff,

    (ii) purchases of equipment for center set-up

    One stop shop for business development

    and investment promotion [2002]:

    (i) recruitment of staff;

    (ii) technical assistance for design of most

    adequate structure,

    (iii) equipment for center set-up,

    (iv) promotion to companies

    Creation of GUIDE, one stop

    shop for business facilitation.

    Strengthening the financial system

    Provision of TA and other material support to

    establish a regulatory framework governing the

    insurance sector, strengthen capacity to control

    and supervise the insurance sector, and

    undertake reform of the CNaPS

    Component dropped [2002]

    Requested by WBG President

    Sequence of events: (i) decision

    made to undertake first the joint

    Bank IMF FSAP (2004) and (ii)

    launch the financial sector reform

    with the current Financial

    Services Project.

  • 7

    Original component New component and nature of

    modification [year]

    Comment

    2 – TRANSACTION IMPLEMENTATION / PRIVATIZATION5

    Privatization capacity building:

    (i) TA for streamlining procedures of PA

    capacity building to carry out complex

    transactions,

    (ii) TA for legal assistance,

    (iii) international environmental expert for in

    the field training at STP, and

    (iv) liaison environmental expert at ONE.

    Supporting the privatization process

    [2002]:

    (i) operating expenses of STP,

    (ii) TA for legal assistance,

    (iii) TA for environmental assistance,

    (iv) communication campaign on

    privatization.

    Original component had budgeted

    too much for the privatization unit

    while ignoring public

    communication. Requested by

    WBG President

    3 – DEVELOPING NEW PSD ACTIVITIES

    OPME is operational

    Component dropped [2002] Support to micro enterprises is

    done through existing and

    separate projects. Requested by

    WBG President.

    Strategies to support PRSP and incubators in

    place

    Component dropped [2002] Activities to support business

    incubators were not considered a

    priority. Strategy work was

    considered part of CAPE (below).

    Requested by WBG President.

    New component: Developing Export

    Processing Zones [2002]:

    (i) feasibility studies,

    (ii) TA to implement strategy on EPZs,

    (iii) infrastructure investments

    The objective was to support the

    Malagasy export industry

    following the crisis that had a

    negative effect on investment,

    including some 80,000 lost jobs in

    EPZs and build an industrial zone

    close to the country‘ s main port.

    Requested by WBG President.

    New component: Strengthening

    Madagascar’s image to attract FDI

    [2002]:

    (i) hiring of an international expert to

    represent Malagasy interests abroad,

    (ii) marketing and promotion actions,

    (iii) set-up of an internet based database

    Requested by WBG President.

    New component: Supporting the tourism

    industry [2002]: design and implementation

    of a tourism master plan.

    Requested by WBG President.

    New component: Developing a long-term

    strategy on PSD issues [2002]:

    (i) assistance to CAPE,

    (ii) animation of a private/public sector

    dialogue forum.

    CAPE was a forum established by

    GOM to articulate reform

    strategies within the framework of

    a public private dialogue.

    Requested by WBG President.

    New component: Insurance facility [2005]:

    Provision of support for an insurance

    facility against Covered Risks that will be

    implemented by ATI in accordance with the

    Agreement Establishing ATI

    As approved by the Board and

    recorded in DCA amendment

    letter dated May 18, 2005.

    New component: SME Risk Capital Fund

    [2005]:

    Provision of support to the Risk Capital

    Fund through provision of TA Loans to the

    Fund‘s SME beneficiaries

    As approved by the Board and

    recorded in DCA amendment

    letter dated May 18, 2005.

    5 In the WBG President‘s request for Project restructuring in October 2002, it was suggested that section (iii) ‗TA

    for executing a large communication campaign‘ under the ‗Local ownership development scheme (PTF)‘ sub-

    component would be dropped; however, this activity was kept.

  • 8

    1.7 Other significant changes

    19. In addition to the Project restructuring in November 2002, the DCA was amended on: (i) May 6, 2003, by the Country Director for amending project description, allocation of funds to

    credit components, and the financial and institutional arrangements governing project

    implementation; (ii) April 18, 2005, by the Board for utilizing project savings to fund a technical

    assistance facility targeting local SMEs, to finance an insurance facility component of the

    Project, following Madagascar‘s admission as member of Africa Trading Insurance (ATI), and

    amending various procurement thresholds; (iii) June 14, 2006, by the Country Director for

    extending the closing date of the Project to December 31, 2007, and reallocating some project

    funds; (iv) December 21, 2007 by the Regional Vice-President for extending the closing date of

    the Project to December 31, 2009, and reallocating project funds; and (v) May 3, 2010, by the

    Vice President of Operations for extending the closing date of the Project to December 31, 2010

    within the framework of OP 7.30 Dealing with de facto government. The extensions of the

    closing dates were requested by the Government to lend support to ongoing activities (see Figure

    1).

    Table 3. Summary table of changes to sub-components

    Project

    Appraisal

    Project

    restructuring

    12/11/2002

    Mid-term

    review

    18/04/2005

    1 - Regulatory capacity building

    Petroleum regulator (OMH) X X X

    Telecoms regulator (OMERT) X X X

    Civil aviation authority X - -

    CFEC X - -

    Strengthening of the financial system X - -

    2 - Transaction implementation

    Institutional capacity (STP) X X X

    Local ownership scheme (PTF) X X X

    Privatization transactions X X X

    3 - New PSD Activities

    Center for the promotion of micro and

    small enterprises (OMPE)

    X - -

    PSD Strategies in support of PRSP X - -

    One Stop Shop (GUIDE) - X X

    Develop EPZs - X X

    Trade and Investment promotion - X X

    Support to the tourism sector - X X

    CAPE / PPD forum - X X

    African Trading Insurance (ATI) - - X

    SME support (BPI) - - X

    Note: ‗X‘ implies that the sub-component was included and ‗-‗ implies that the sub-component was excluded.

  • 9

    Figure 1. Project timeline

    2. Key Factors Affecting Implementation and Outcomes

    2.1 Project Preparation, Design and Quality at Entry

    20. The background analysis was sound, lessons learned from the first project were stressed in project design, private sector consultations were organized and recorded, and the rationale for

    the Bank‘s intervention was clear. The Government had prior to project design developed a

    strategic vision for private sector development as part of its National Support Program for the

    Private Sector. Project preparation and design also benefitted from the extensive expertise

    developed in the PATESP Project that was approved by the Board on May 29, 1997, which

    closed on December 31, 2002.6 The Project focused on deepening the market deregulation and

    divestiture activities that were undertaken in PATESP. Concerns and priorities were well

    identified, and several analytical reports underpinned the project, including on environmental

    safeguard issues.7 The volatile political context and the fragility of local institutions were

    prominently acknowledged in the PAD as political turmoil had affected PATESP.

    21. The PAD stressed the importance of ensuring improved transparency and increased local participation in the privatization process but also highlighted the significant risk associated with

    political instability and limited capacity of local institutions. The PAD dedicated significant

    attention to improving transparency in the reform process: for example by proposing separation

    of the policy-making and regulatory functions of public agencies, by providing modern

    management information systems, by moving toward financial autonomy of the regulatory

    agencies, and by applying best practices in the privatization process. The Project also intended to

    scale up local private participation in the divestiture program to make necessary reforms

    palatable to a public audience who too often associated privatization with foreign takeovers of

    domestic assets. It proposed that local investors would be invited to bid in a joint venture with

    foreign equity and technical partners. It also aimed at establishing procedures for distributing

    shares or mutual funds which would contain a stipulated share of each divested firm. Finally, it

    would facilitate the expansion of indigenous local firms, in particular micro-enterprises which

    would be provided start-up services. These initiatives were taken amid great political uncertainty

    and with acknowledged weaknesses in governance.

    6 World Bank (2003).

    7 World Bank (2000).

    2001 2002 2003 2004 2005 2006 2007 2008 2009 2010

    Board

    approval

    1st political

    crisis erupts

    Restructuring

    & Project

    effectiveness

    DCA

    amendment

    Mid-term

    review

    DCA

    amendment

    and PIU

    restructuring

    DCA

    amendment

    DCA

    amendment

    Project

    closing

    2nd political

    crisis erupts:

    OP/BP 7.30

  • 10

    22. The high complexity and comprehensive scope of the Project coupled with its sensitive nature required a high level of government commitment and collaboration between several

    public institutions. The project was highly demanding of the Government and the

    implementation team and it came at a high political cost. The privatization agenda was unpopular

    among many stakeholders and the Government was concerned about the loss of labor. The

    incumbent Government was committed at least on paper at the time of project preparation and

    project design but reform pressure was also applied by the International Monetary Fund (IMF)

    through its programs. Project documentation highlighted the high risk associated with reform

    fatigue. Key issues such as political fragility, political economy concerns, and limited

    government capacity to build solid institutions within tight deadlines were indicators that the

    risks were high. The significant complexity of the Project could have been reduced if the new

    PSD activities component had been left out at the design stage and left aside for another Project

    that focused on SME support. The project did not include external partners and co-financiers

    outside of GOM and the attention to environmental and social safeguards was high.

    23. The PDO of improving access, reliability and affordability of key utilities was highly relevant for private sector development, investment promotion and shared growth. The

    regulatory capacity building and privatization components were both essential building blocks in

    GOM‘s development agenda. Market liberalization, competition and effective regulation are

    necessary components to improve market performance. By focusing on key factor markets

    (finance, telecoms, transport) as well as inefficient monopolies (airports, cotton, sugar), GOM

    would have been well placed to achieve its development objectives if reforms were properly

    implemented with attention to competition and effective regulation. Significant progress had

    already been made in the 1990s, particularly through the PATESP project, to prepare and start

    the liberalization process. Thus, the main objective was consistent with the prevailing economic

    priorities of the Government.

    24. The ‗new PSD activities‘ component was not closely associated with the PDO before it was restructured in November 2002. The title of the third component, ‗New PSD Activities‘, was

    somewhat misleading: ‗SME promotion‘ could have been more appropriate. One of the three

    sub-components—‗New strategies in priority sectors identified by Government‘—for ‗New PSD

    Activities‘ was not defined at the start. While the establishment of the one stop shop (GUIDE)

    was a targeted and practical sub-component that benefited all prospective entrepreneurs, the aim

    to train only ten local startups was largely irrelevant and the aim to support future priority sectors

    of the Government offered flexibility but limited guidance to the team. While this added

    flexibility to adapt part of the Project to GOM‘s evolving agenda may have been appreciated by

    the client, this component that performed particularly poorly as the new activities were weak

    either in design or implementation. The initial resources allocated for the third component were

    less than 6 percent of total resources. In addition, the limited resource allocation (US$0.28

    million) for the transport sub-component covering some narrow technical assistance

    interventions was unlikely to achieve the ambitious outcome indicators on transport prices. In

    transport, it would also have been difficult to determine causality between identified

    interventions and the two outcome indicators (Table 1).

  • 11

    25. Some targets should have been more specific and performance indicators more comprehensive. The combined targets of improving access, lowering prices and improving

    quality/reliability were ambitious despite the lack of quality and poor access as well as relatively

    high prices of services. While the experiences from many other countries show that access and

    quality often improve substantially as a result of market liberalization, absolute price changes are

    often marginal. Large improvements in access, choice, and quality raise the utility for

    consumers. Competition facilitates price segmentation which by extension can result in both

    lower and higher prices depending on the service in question. Price is also closely related to

    taxation as illustrated in the petroleum sector. Potential efficiency gains can therefore be

    captured by increased rents and increased taxes can neutralize any efficiency gains and even

    raise the overall price. The retail price is therefore an imperfect target. There was furthermore no

    performance indicator defined for reliability. In addition, the outcome indicator of significantly

    increasing private investment in targeted sectors was not a useful measurement of the successful

    reforms because political uncertainty scared off investors for years following each crisis.

    26. Proactive measures to ensure competitive markets could have been more prominent in project design. Market liberalization and privatization do not necessarily ensure competitive

    markets. Proper phasing and sequencing of reform measures are critical and so is the autonomy

    of regulatory bodies. The existing literature on market liberalization does pay much attention to

    ensuring a healthy dose of competition in order to boost reliability and affordability. While an

    important body of this literature was developed in the years subsequent to project launch, the

    project could have highlighted these issues more upfront in the design. The PAD mentioned

    competition as a byproduct resulting from a strengthened regulator; however, ensuring autonomy

    was arguably just as important as building technical expertise in order to induce a higher level of

    market competition. In addition, the design of the privatization process could have promoted the

    breakup of national monopolies into two or more providers in order to stimulate competition.

    Transparency clauses could have conditioned transaction support: openness and simplicity would

    have been the key principles in an approach that particularly stressed competitive markets. Clear

    rules and punishments would have been established. Price caps could have been considered for

    some sectors. These types of initiatives are often necessary but not sufficient to promote

    competition.

    2.2 Implementation

    27. Political developments beyond the control of the Project team had serious implications for the Project. Project implementation was severely delayed at the start due to the unraveling of

    a political crisis that paralyzed the Government and the civil service; and at the end due to a

    similar political crisis. In December 2001, shortly after the Project was approved by the Board of

    Directors and the signing of the Credit Agreement, the incumbent President (Didier Ratsiraka)

    and his main opponent (Marc Ravalomanana) both claimed victory in the presidential elections.

    In April 2002, after months of sporadic violence and considerable economic disruption, the High

    Constitutional Court pronounced Ravalomanana as President following a recount of votes. In

    July 2002, Ratsiraka left the country and Ravalomanana effectively gained control of power. The

    new political context and harsh economic environment left the new Government unwilling to

    implement painful new reforms and divest politically sensitive enterprises.

  • 12

    28. In November 2002, soon after the new cabinet had been installed, the country project portfolio was restructured, including the Project, to better reflect the priorities of the new

    administration. This was a necessary step to enhance Project ownership in the new

    administration. Significant reallocation of funds was made and some components were dropped

    and others introduced. The outcome was a project that better responded to the priorities in the

    aftermath of the crisis with a less ambitious agenda on privatization and a more ambitious

    agenda on rebuilding the private sector and promoting business. At the time, these initiatives

    must have been regarded as rather drastic but it would turn out that these amendments did not go

    far enough to reflect the evolving priorities of the new administration. In particular the

    Government‘s commitment to the privatization agenda was weak.

    29. The supervision reports reveal a sense of frustration of progress: on privatization in general and on New PSD Activities in particular. The project faced significant challenges in

    building new institutions such as the One Stop Shop for Investment and Business Development

    (GUIDE) and CAPE (see Annex 2, component 3); in strengthening the existing implementation

    units; and in creating an environment conducive to collaboration between public agencies. The

    willingness by the Government to take difficult decisions was often lacking. The new

    Government hesitated over further privatization and supervision records raise questions of

    ownership in this process. No doubt, the privatization of enterprises took longer than anticipated

    and Madagascar Airports (Aéroports de Madagascar, ADEMA), Madagascar Power and Water

    Company (Jiro Sy Rano Malagasy, JIRAMA) and Madagascar Sugar Industry (Siramamy

    Malagasy, SIRAMA) were never privatized. The fact that several of the public enterprises were

    poorly managed did not help. For example, SIRAMA was already bankrupt, many companies did

    not have accounts, environmental audits had to be done, assets identified and recorded, etc. In

    addition, a combination of insufficiently allocated counterpart funding and bureaucratic

    procurement procedures adopted by the Project Implementation Unit (PIU) led to significant

    arrears that slowed down progress as contractors and consultants faced great uncertainty about

    remuneration. The economic crisis left the Government short of funds and the International

    Development Association (IDA) credit was therefore increased to 100 percent.

    30. To regain momentum, the Client and the World Bank developed a short-term action plan to closely monitor progress and new staff was recruited to accelerate implementation. The results

    achieved under this plan in six months were to decide the future of the Project and in December

    2003, the supervision team concluded that this initiative had brought significant improvements.

    The supervision reports indicate that several experts were hired to help alleviate shortages of

    manpower and guidance was provided in action plans, including several recommendations to

    establish frequent meetings and bring all parties to the table. The initiatives to enhance the

    institutional capacity of the Privatization Secretariat (Secrétariat Technique à la Privatisation,

    STP) in the fall of 2003—following resignations of key staff members transferred from PATESP

    to PSDP2 due to salary reductions—were decisive to complete the privatization of the Cotton

    Company (Hasy Malagasy, HASYMA) and the Telephone Company (Telecom Malagasy,

    TELMA). A program of staff training in privatization and public-private partnerships (PPPs) was

    launched and study tours organized with focus on practical aspects of implementing programs

    and divestiture. The capacity building activities at STP was later key for the success of the public

    enterprise reform program.

  • 13

    31. Project implementation was impeded by the organizational structure during the first half of the Project. The initial project management structure could have been more supportive to

    effectively address the multitude of challenges that the complex project posed to the team. The

    Government official who was appointed head of the Implementation Agency (or Unité de

    Coordination du Projet, UCP) could have been more proactive and results oriented (PIU = UCP

    + STP + PSD units). The first professional who was hired to be in charge of the crucial

    monitoring and evaluation (M&E) activities did not have the training and experience for the role.

    The two advisory and implementation units—STP for components 1-2 and the PSD unit for

    component 3—that the UCP oversaw did not communicate and coordinate as necessary (see

    Figure 2). STP, a ministry unit, was more responsive to the Ministry of Finance and Budget than

    to the head of PIU. It worked closely with the ministries in charge of the state-owned enterprises

    (SOEs) during divestiture preparation. The PSD unit—an implementation unit created inside the

    Project—was more responsive to the Ministry of Economy and Industry (previously Ministry of

    Industry, Trade and Private Sector Development) than UCP. This organizational structure was

    implemented to strengthen the commitment of various ministries but it also imposed high

    coordination costs, as highlighted in the government Report in Annex 7.

    32. The PIU was initially over staffed and bureaucratic and the organization was drastically restructured to a slimmer and more efficient implementation unit in June 2006. Each unit (UCP,

    STP, PSD) in the PIU had its own procurement and accounting team; and the PIU counted 69

    staff on renewable one-year contracts by the end of 2005. Many of these staff members were

    government officials transferred to the new institutions originally hosted under the PIU umbrella.

    They were not paid by the PIU and performed public services, such as issuing work permits and

    business licenses at the GUIDE. This arrangement was meant to offer flexibility in future staff

    decisions. While the supervision records highlight organizational weaknesses, and there was

    some trimming of unnecessary staff that was transferred from PATESP to PSDP2 and more

    reliance was transferred to World Bank staff, decisive action to correct the situation would take

    until early 2006. As the Project was heading towards closing in December 2005, and there was

    significant uncertainty whether the Project would be extended or not, some high-level officials

    left the PIU, including the head of UCP. Many staff members also left as a natural result of the

    completion of sub-components such as the Support Committee for the Enterprise Relaunch Pilot

    (Comité d‘Appui au Pilotage de la Relance de l‘Entreprise, CAPE) (11 staff) and GUIDE (13

    staff). The PSD unit (AGEX B in Figure 2) was removed from the organizational chart and the

    government-sponsored civil servants at UCP were transferred back to the Ministry of Finance

    and Budget. The team took this opportunity to significantly restructure the organization, which

    resulted in a much slimmer organization (see Figure 2). Several sub-components in the PSD unit

    were also removed and none of the Project staff associated with this unit had their contracts

    renewed. The number of staff was thus cut from 69 to 11.

  • 14

    Figure 2: Organizational structure in 2002-2006 (left) vs. 2006-2010 (right)

    Source: STP Director‘s report (2011).

    33. The mid-term review was used to add two new sub-components and provide advice on how to reactivate some non-performing sub-components. It offered an opportunity to the Project

    to disassociate itself from some sub-components that were not progressing and focus support on

    those that were more promising. However, no sub-component was removed and the opportunity

    to cut losses was not seized at this time. Instead, the supervision records of the mission following

    the mid-term review (January 2006) were more candid, emphasizing disappointments and lack of

    achievements, and suggesting more drastic measures to address existing problems. For example,

    the Privatization Trust Fund (PTF) was a non-performing sub-component and the supervision

    mission in January 2006 recommended dropping this sub-component from the project. The same

    held for the privatization of SIRAMA. It also recommended GOM to cancel the contract with the

    Export Processing Zone (EPZ) property developer (GETIM) given a number of irregularities and

    weaknesses in performance (see Annex 2, component 3). It advised that EDBM would take over

    GUIDE and implicitly adopt the role of CAPE, which had exhausted its effort in enhancing

    public private dialogue.

    34. The most recent political crisis and the ensuing non-replenishment of the project special account under OP/BP 7.30 led to a standstill of the project‘s implementation from March 17,

    2009, to the project closing date of December 31, 2010. This development led to a freeze of most

    Project activities and necessary action to conclude ongoing initiatives could not be taken. During

    this crisis, the country was suspended by the African Union (AU, then the Organisation of

    African Unity) and the Southern African Development Community (SADC). Another outcome

    was that as of January 1, 2010, Madagascar is no longer designated as beneficiary of U.S. trade

    preferences offered in the African Growth and Opportunity Act (AGOA).8 The country‘s

    eligibility of AGOA preferences, starting October 2000, helped it establish a significant textiles

    and clothing sector—export processing zone (EPZ) exports were worth US$0.82 billion in 2008

    (EIU, 2010)—that has been seriously damaged in the last two years. As of April 2011, the

    international community including several governments, bilateral and multilateral donors still

    does not recognize the current de facto Government (i.e. Haute Autorité de la Transition).

    8 U.S. Government (2009).

  • 15

    2.3 Monitoring and Evaluation (M&E) Design, Implementation and Utilization

    35. The design of the M&E framework should have been better tailored to the PDO and to existing baseline data sources. While performance in the telecom sector was adequately

    measured, outcome indicators for other sectors were left out from the M&E framework,

    including the petroleum sector. To measure progress on access, reliability and affordability of

    key utility services, a more comprehensive set of indicators would have been required and more

    independent data collection would have been necessary. The restructuring in November 2002

    partly addressed this issue as a number of new performance indicators were added to the

    monitoring framework and others modified. The PIU also modified the M&E framework to keep

    it more relevant and easier to monitor. The M&E framework remained weak, however, and the

    supervision teams struggled with the M&E function. Most aide-memoires of supervision

    missions did not measure performance according to the pre-defined performance indicators.

    36. The M&E framework could have been used more extensively during the first half of the Project. Data for several of the key project indicators (KPIs) were not systematically collected,

    partly due to the fact that they were not easily accessible in standard databases. For example, one

    of the KPIs was sector specific inflows of private investment. While these variables are reported

    in central World Bank databases and by the Central Bank, the information is not available for all

    years and it is particularly lacking for Madagascar. Many KPIs were output indicators and to

    measure progress on competitiveness, the project could have made more use of indicators on

    enterprise creation and private sector productivity. The first person who was hired for the M&E

    activities had no prior experience or training in monitoring or evaluation. The M&E function

    suffered as a result. It was not until a new person was recruited in the mid-term of the Project

    that the PIU became more proactive in collecting data and monitoring project performance

    according to the indicators. But it was then too late to retrieve some of the historical data and the

    complexity of some of the existing indicators and a general lack of data left the M&E function

    underutilized.

    2.4 Safeguard and Fiduciary Compliance

    37. The respect of safeguard issues is rated satisfactory. The Project was originally rated as environmental category B (partial assessment). Three main provisions were incorporated in

    Project design to ensure compliance with safeguards. First, the Project would prepare

    environmental partial and full audits for listed candidates. Second, the project would offer

    capacity building to the privatization agency and the national environmental agency. Third, the

    project would support public involvement through comprehensive consultations and a

    communications campaign. Safeguard policies were deemed applicable only to environmental

    assessment (OP 4.01, BP 4.01, GP 4.01). An environmental pre-audit was conducted for each

    listed privatization candidate following a comprehensive consultation process.

    38. Environmental audits were conducted for ADEMA, HASYMA, SIRAMA and the National Oil Company of Madagascar (Solitany Malagasy, SOLIMA) (post-audit) as planned in

    project design. They were approved by World Bank teams with technical assessments provided

    by the World Bank‘s Environment and Natural Resource Management Unit for the Africa

    Region (AFTEN) and publicly discussed and disclosed. These environmental audits were very

  • 16

    large undertakings that recorded and assessed the situation in reports several hundred pages long.

    For example, the SOLIMA report was 833 pages long not including addendums. In the

    privatization of SOLIMA, which had by far the most critical environmental impact, the

    environmental cleanup was assigned to the new private companies, in particular by Galana,

    which was required to take care of the issues linked to the main pipeline and old refinery and this

    was arguably a good solution.

    39. The PAD dedicated significant attention in assessing the client‘s procurement and financial management capacity, and in providing recommendations to boost this capacity.

    Procurement is rated satisfactory because the PIU followed the rules, procedures and guidelines

    according to the World Bank‘s Procurement Specialist. Financial Management is rated

    moderately satisfactory because payment schedules were not adequately respected for parts of

    the Project; in particular during the first years when the inflow of counterpart funding was

    irregular and the PIU organization contained two layers of procurement and financial

    management personnel. The PIU cleared outstanding arrears during the last two years of the

    Project and it also expediently produced detailed and exhaustive accounts requested by the

    Implementation Completion and Results (ICR) Report author. Disbursement lagged due to the

    political crises of 2001/2002 and 2009/2010 but disbursement caught up rapidly once the Project

    was allowed to operate.

    2.5 Post-completion Operation/Next Phase

    40. There is no proposal to implement a third PSD project. The World Bank‘s Finance and Private Sector Development Department in the Africa Region is implementing a US$170 million

    Integrated Growth Poles Project (effective September 28, 2005; closing December 31, 2012) that

    is covering several activities that both complement and sustain some of the Project‘s previous

    activities (e.g. EDBM). A second Growth Poles Project would be particularly relevant given the

    priorities of private sector-led growth. The Government still holds a portfolio of poorly

    performing public enterprises that would benefit from initiatives that would strengthen

    management. Some of them need to be financially restructured or closed down. Developing a

    stronger public private partnership framework is a high priority that the World Bank currently is

    being drafted into providing support for.

    41. Continuing efforts to strengthen the regulatory capacity of key sectors would be useful to lock in the Project‘s achievements in building institutions. Capacity building of the telecom

    regulator is part of the IDA financed Madagascar Communications Infrastructure Project

    (PICOM). Future activities may benefit from conditions that regulators are made meaningfully

    independent, that competition plays a greater role in its objectives, and that revenues are

    accounted for transparently. The establishment of the EDBM, which incorporated GUIDE and

    role of CAPE, is an institution that has achieved very positive results and sustaining this

    institution through permanent staff and a financial commitment by GOM is essential for

    promoting entrepreneurship and investment.

  • 17

    3. Assessment of Outcomes

    3.1 Relevance of Objectives, Design and Implementation

    42. The relevance of objectives, design and implementation is rated moderately satisfactory.

    43. The PDO of improving access and reliability of key utilities was highly relevant for private sector development, investment promotion and shared growth. It remains highly relevant

    until this day. Market liberalization, competition and effective regulation are necessary

    components to improve market performance. By focusing on key factor markets (energy,

    finance, telecoms, transport) as well as inefficient monopolies (airports, cotton, sugar), GOM

    would have been well placed to achieve its development objectives in case reforms were

    properly implemented. The current CAS (2007-2011)9 is organized around two main pillars:

    activities that will help remove constraints to investment; and activities geared toward improving

    the scope and quality of service delivery. Both pillars were the focus of the Project. In addition,

    the CAS supports the Government‘s Madagascar Action Plan (MAP) 2007-2012, which was

    prepared through extensive dialogue with the private sector and civil society, and includes eight

    commitments of which the second commitment ―connected infrastructure‖ and sixth

    commitment ―high growth economy‖ commensurate with the Project. Significantly increasing

    investment to promote high growth is one of the key priority areas in this plan.10

    Finally, the

    World Bank Country Economist noted in April 2011 that achieving this PDO will remain a high

    priority in the years to come.

    44. The original design of focusing primarily on strengthening regulatory capacity and divesting of poorly performing public enterprises was also highly relevant but the case for

    including the new PSD activities component was less apparent to achieve the PDO. These first

    two components were essential for achieving the PDO and the project design reflected proper

    diagnosis of a development priority that remains relevant. The design could have included more

    concrete provisions for mechanisms controlling for market competition and ensuring that

    regulatory agencies gained sufficient autonomy. The third component, in the PAD, ―New PSD

    activities‖, was a weak and vaguely designed component. While establishing a center for the

    promotion of MSEs (GUIDE) was useful in general, the design of the enlarged ‗New PSD

    Activities‘ component following both the 2002 restructuring and the 2005 mid-term review

    lacked in terms of demand analysis and few interventions did effectively address the

    ―competitiveness‖ of Malagasy companies. The redesign of this component affected the Project

    negatively during implementation. In addition, the causality of some activities and PDO

    achievement was vague and the PAD lacked an economic and financial analysis section.

    45. The actions taken in the implementation process were proactive and flexible but some difficult decisions could have been taken earlier. The World Bank‘s implementation assistance

    was adaptive to change, as the Project underwent one major and several minor restructurings,

    and it was responsive to the needs of the country, as the priority of private sector competitiveness

    was elevated. However, the willingness to add sub-components resulted in a Project that lost

    9 World Bank (2007).

    10 Government of Madagascar (2006).

  • 18

    some focus and covered too many activities. The focus on output indicators and limited

    usefulness of the M&E framework led to lenient ratings of progress

    3.2 Achievement of Project Development Objectives

    46. The achievement of the PDO, as summarized and derived in Tables 4-5, and analyzed in detail in Annex 2, is rated moderately unsatisfactory. This rating is in line with the final

    Implementation Status Report (ISR) rating that stressed that no progress towards PDO

    achievement had been recorded following the implementation of OP/BP 7.30 in March 2009.

    Table 4 presents a summary of achievements of the PDO based on the lengthy analysis in Annex

    2. The first column divides the PDO up into five separate sections and presents the perceived

    level of importance. The second column presents the achievement of key indicators while the

    third column summarizes the achievement of PDOs and the ICR author‘s ratings.

    Table 4. Summary of ratings and achievements of PDOs

    PDO Achievement of indicators (see

    Annex 2 for details)

    Achievement of PDO (see Annex 2 for details)

    1. Assist the

    Borrower to improve

    access, reliability

    and affordability of

    key utilities

    [High relative

    importance]

    1.) Telecoms

    The KPI targets on access and


Recommended