Document of The World Bank Report No: ICR00004003 IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF-13140) ON A GLOBAL PARTNERSHIP FOR EDUCATION FUND GRANT IN THE AMOUNT OF US $75.5 MILLION TO THE REPUBLIC OF GHANA FOR A GHANA PARTNERSHIP FOR EDUCATION GRANT PROJECT February 28, 2017 Education Global Practice AFCW1 Africa Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized
Transcript
Page 1: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

Document of

The World Bank

Report No: ICR00004003

IMPLEMENTATION COMPLETION AND RESULTS REPORT

(TF-13140)

ON A

GLOBAL PARTNERSHIP FOR EDUCATION FUND GRANT

IN THE AMOUNT OF US $75.5 MILLION

TO THE

REPUBLIC OF GHANA

FOR A

GHANA PARTNERSHIP FOR EDUCATION GRANT PROJECT

February 28, 2017

Education Global Practice

AFCW1

Africa Region

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

CURRENCY EQUIVALENTS

(Exchange Rate Effective 1/31/2017)

Currency Unit = New Ghana Cedi

New Ghana Cedi 1.00 = US$0.23

US$1.00 = 4.37 New Ghana Cedi

FISCAL YEAR

January 1 – December 31

ABBREVIATIONS AND ACRONYMS

ADEOP Annual District Education Operational Plan MoF Ministry of Finance

AESOP Annual Education Sector Operational Plan MTR Mid Term Review

APW Annual Programs of Work NAR Net Admission Rate

BECE Basic Education Certificate Examination NCTE National Council for Tertiary Education

CBI Cluster Based In-service Training NEA National Education Assessment

CSO Civil Society Organization NER Net Enrolment Ratio

DED District Education Directorate NESAR National Education Sector Annual Report

DFID UK Department for International Development NGO Non-Governmental Organization

DP Development Partner NIB National Inspectorate Board

EDSEP Education Sector Project

EFA-FTI Education for All Fast Track Initiative PBME Planning, Budgeting, Monitoring and Evaluation Dept

EGRA Early Grade Reading Assessment PTA Parent Teacher Association

EGMA Early Grade Mathematics Assessment PTR Pupil Teacher Ratio

EMIS Education Management Information System PTTR Pupil Trained Teacher Ratio

ESP Education Sector Plan RED Regional Education Directorate

ESPR Education Sector Performance Report SBI School Based In-service Training

GAR Gross Admission Rate SHS Senior High School

GDHS Ghana Demographic and Health Survey SMC School Management Committee

GDP Gross Domestic Product SPAM School Performance Assessment Meeting

GER Gross Enrolment Ratio SPIP School Performance Implementation Plan

GES Ghana Education Service SRC School Report Cards

GEU Girls Education Unit TED Teacher Education Division

GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

GoG Government of Ghana TVET Technical and Vocational Education and Training

GNECC Ghana National Education Campaign Coalition UNICEF United Nations Children’s Fund

GPASS Girls Participatory Approach to Student Success USAID United States Agency for International Development

GPE Global Partnership for Education UTDBE Untrained Teachers Diploma in Basic Education

GPI Gender Parity Index VIPs Ventilated Improved Pit-Latrines

IE Impact Evaluation WFP World Food Program

INSET In-Service Education and Training

JHS Junior High School

JICA Japan International Cooperation Agency

MDG Millennium Development Goal

MMDAs Metropolitan, Municipal and District Assemblies

MoE Ministry of Education

Senior Global Practice Director: Amit Dar

Practice Manager: Halil Dundar

Project Team Leader: Deborah Newitter Mikesell

ICR Team Leader: Deborah Newitter Mikesell

Page 3: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

i

GHANA

Ghana Partnership for Education Grant

CONTENTS

Data Sheet .................................................................................................................... ii

A. Basic Information ................................................................................................ ii B. Key Dates ............................................................................................................ ii C. Ratings Summary ................................................................................................ ii

D. Sector and Theme Codes .................................................................................... iii E. Bank Staff ........................................................................................................... iii

F. Results Framework Analysis .............................................................................. iii G. Ratings of Project Performance in ISRs ........................................................... vii H. Restructuring (if any) ........................................................................................ vii I. Disbursement Profile...................................................................................... viii

1. Project Context, Development Objectives and Design ............................................ 1

2. Key Factors Affecting Implementation and Outcomes ............................................ 7

3. Assessment of Outcomes ....................................................................................... 18

4. Assessment of Risk to Development Outcome ...................................................... 29

5. Assessment of Bank and Borrower Performance .................................................. 31

6. Lessons Learned ..................................................................................................... 34

Annex 1. Project Costs and Financing ................................................................... 37

Annex 2. Outputs by Component ........................................................................... 38 Annex 3. Economic and Financial Analysis .......................................................... 49

Annex 4. Grant Preparation and Implementation Support/Supervision Processes 60 Annex 5. Beneficiary Survey Results Summary .................................................... 62 Annex 6. Stakeholder Workshop Report and Results ............................................ 65

Annex 7. Summary of Grantee's ICR and/or Comments on Draft ICR ................. 69 Annex 8. Comments of Cofinanciers and Other Partners/Stakeholders ................ 85

Annex 9. List of Supporting Documents .............................................................. 86 MAP of Ghana – IBRD 33411 ................................................................................... 88

Page 4: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

ii

GHANA

Ghana Partnership for Education Grant

Data Sheet

A. Basic Information

Country: Ghana Project Name: Ghana Partnership for Education

Project ID: P129381 L/C/TF Number(s): TF-13140

ICR Date: 10/27/2016 ICR Type: Core ICR

Lending

Instrument: SIL Grantee:

GHANA MINISTRY OF

FINANCE AND ECONOMIC

PLANNING

Original Total

Commitment: USD 75.50M Disbursed Amount: USD 75.50M

Revised Amount: USD 75.50M

Environmental Category: B

Implementing Agencies:

Ministry of Education

B. Key Dates

Process Date Process Original Date Revised / Actual

Date(s)

Concept

Review: 02/14/2012 Effectiveness: 02/20/2013 02/15/2013

Appraisal: 05/08/2012 Restructuring(s): 1st Restructuring:

2nd Restructuring:

05/14/2013

08/25/2015

Approval: 10/11/2012 Mid-term

Review: 01/19/2015 02/23/2015

Closing: 10/31/2015 08/31/2016

C. Ratings Summary

C.1 Performance Rating by ICR

Outcomes: Satisfactory

Risk to Development Outcome: Moderate

Bank Performance: Satisfactory

Grantee Performance: Satisfactory

C.2 Detailed Ratings of Bank and Borrower Performance (by ICR)

Bank Ratings Borrower Ratings

Quality at Entry: Highly Satisfactory Government: Satisfactory

Quality of Supervision: Satisfactory Implementing

Agency/Agencies: Satisfactory

Page 5: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

iii

Overall Bank Performance: Satisfactory Overall Borrower

Performance: Satisfactory

C.3 Quality at Entry and Implementation Performance Indicators

Implementation Performance Indicators QAG Assessments (if

any) Rating

Potential Problem Project at

any time (Yes/No): No

Quality at Entry

(QEA): None

Problem Project at any time

(Yes/No): No

Quality of Supervision

(QSA): None

DO rating before

Closing/Inactive status: Satisfactory

D. Sector and Theme Codes

Original Actual

Sector Code (as % of total Bank financing)

Public administration - Education 7 7

Tertiary Education 22 22

Primary Education 71 71

Theme Code (as % of total Bank financing)

Education for all 83 83

Gender 17 17

E. Bank Staff

Positions At ICR At Approval

Vice President: Makhtar Diop Makhtar Diop

Country Director: Henry G. R. Kerali Yusupha B. Crookes

Practice Manager/Manager: Halil Dundar Peter Nicolas Materu

Project Team Leader: Deborah Newitter Mikesell Deborah Newitter Mikesell

ICR Team Leader: Deborah Newitter Mikesell

ICR Primary Author: Christin McConnell

F. Results Framework Analysis

Project Development Objectives (from Project Appraisal Document)

The Project Development Objective is to improve the planning, monitoring, and delivery

of basic education services in deprived districts of the Recipient’s territory.

Revised Project Development Objectives (as approved by original approving authority)

The PDO was not revised during the life of the Project.

Page 6: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

iv

(a) PDO Indicator(s)

Indicator Baseline Value

Original Target

Values (from

approval

documents)

Formally

Revised

Target

Values

Actual Value Achieved

at Completion or Target

Years

Deprived districts disbursing 75% or more of their district education grants as planned in their

APW (Percentage)

Value 0 80 N/A 100

Date Achieved 10/10/12 10/31/15 N/A 8/31/2016

Comment

Target exceeded. Source: APW reports collated annually and reported in Financial

Analysis Report under supervision of Financial Controller of the Ghana Education

Service.

Public basic schools in deprived districts with up-to-date School Report Cards (Percentage)

Value 0 75 N/A 98

Date Achieved 10/10/12 10/31/15 N/A 8/31/2016

Comment

Target exceeded. Source: School Report Card Reports prepared annually capturing

and collating data from districts bi-annual school grant status reports. Note:

Additional sample surveys also conducted to verify findings (conducted by the

Ministry’s PBME monitoring team). Internal and external audits were also

conducted.

P3 students achieving proficiency in English and Mathematics (NEA results for deprived

districts) (Percentage)

Value English: 12.4

Mathematics: 9

English: 15

Mathematics: 11 N/A

English: 16

Mathematics: 13

Date Achieved 10/10/11 10/31/15 N/A 09/15/2013

Comment

The project target was achieved by 2013 with the 2013 NEA results. Source: NEA

report 2014. Note: A confirmation of further improvements in learning outcomes

through additional data at endline was not available as the 2015 NEA was postponed

to 2016 and the level of assessment was moved from P3 to P4 level.

However, EGRA/EGMA assessments were also conducted in 2013 and 2015 (with

USAID support) which confirms that there were statistically significant

improvements in number identification, letter sounds in English, oral reading in

English, and letter sounds for local languages in the GPEG deprived districts.

The project outputs of improved percentage of qualified teachers in deprived districts,

in-service teacher training and the purchase of teaching and learning materials from

district and school grants contributed to improved learning outcomes observed within

the deprived districts targeted by the project. Improvements of 29% for English and

44% for Mathematics in NEA between 2011 and 2013 are significant and compare

favorably to other countries in the region.

Teachers trained under the project in deprived districts who obtain satisfactory rating or

higher in the SBI/CBI Lesson Observation Sheet for (a) lesson planning (b) teaching

methodology (c) classroom organization and management (Percentage)

Page 7: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

v

Value Average: 36

Average: 50

N/A

Average: 75.7

Lesson Planning: 69

Teaching Method.: 80

Classroom Org: 78

Date Achieved 10/10/10 10/31/15 N/A 8/31/2016

Comment

Target exceeded. Source: Baseline data collected from JICA supported pilot of the

Lesson Observation Survey. Three surveys conducted since baseline by independent

firm (Associates for Change) hired to implement survey drawn from a representative

sample of schools. The highest values for satisfactory performance for lesson

observation actually occurred during midline data collection in 2015 with Lesson

Planning at 85%, Teaching Methodology at 87%, and Classroom Organization and

Management at 90%.

Direct Project Beneficiaries (Number), of which female (Percentage)

Value 0

Of which female: 0

1.6 million

Of which female:

40

N/A 1,991,030

Of which female: 48

Date Achieved 10/10/12 10/31/15 N/A 8/31/2016

Comment

Target exceeded. Source: Project status reports and EMIS. Note: Beneficiaries

included students, teachers, head teachers, Circuit supervisors, district officers,

regional officers, PTA/SMC.

(b) Intermediate Outcome Indicator(s)

Indicator Baseline Value

Original

Target Values

(from approval

documents)

Formally

Revised

Target

Values

Actual Value Achieved

at Completion or Target

Years

Head teachers and Circuit Supervisors in deprived districts trained under the project in the use

of School Report Cards (Number)

Value 0 6,930 N/A 7,087

Date Achieved 10/10/12 10/31/15 N/A 8/31/2016

Comment

Target exceeded. Note: This included 5,993 Head Teachers and 1,094 Circuit

Supervisors. Source: Training Reports from districts, collated by Teacher

Education Department, Ghana Education Service.

Regional and District Education officers trained under the project (eg. Financial management,

data collection and analysis, etc.) (Number)

Value 0 500 N/A 2,288

Date Achieved 10/10/12 10/31/15 N/A 8/31/2016

Comment

Target exceeded. Note: This included 1,568 District and regional officers

trained in work planning and school report cards, 83 district gender officers

trained in guidance and counseling, 308 regional officers trained in reporting,

monitoring and evaluation, and 329 regional and district officers trained in

internal controls and auditing. Source: Training Reports from districts, collated

by Teacher Education Department, Ghana Education Service.

Teachers trained under the project (disaggregated by UTDBE and INSET) (Number)

Page 8: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

vi

Value UTDBE: 0

INSET: 0

UTDBE: 5,000

INSET: 30,000 N/A

UTDBE: 6,480

INSET: 42,541

Date Achieved 10/10/12 10/31/15 N/A 8/31/2016

Comment

Target exceeded. Source: These figures are based on information collected

through the monitoring and evaluation system, Teacher Education Department

Training Reports and District and School Grant reports. Note: Reporting

collected yearly participants in each INSET in which it is impossible to know if

the same teacher was trained more than once in different areas. The cumulative

number of INSET trainings was calculated to be 94,827. As a proxy, in 2015

28,056 teachers participated in the core Mathematics INSET, and 14,485 in

non-core subjects of KG and Gender, indicating that the target was met – for

both UTDBE and INSET.

District Education Directorates collating School Report Cards from at least 70% of schools

within the district (Percentage)

Value 0 70 N/A 100

Date Achieved 10/10/12 10/31/15 N/A 8/31/2016

Comment Target exceeded. Source: District- level School Report Card Reports submitted

with School Grant Report.

Basic schools in deprived districts participating in all INSET core courses supported by the

project (Percentage)

Value 0 65 N/A 97.8

Date Achieved 10/10/12 10/31/15 N/A 8/31/2016

Comment Target exceeded. Source: School Grant Report. Note: INSET annual report

used to verify findings.

Schools that have received and displayed the most recent School Report Card on their notice

board (Percentage)

Value 0 75 N/A 93

Date Achieved 10/10/12 10/31/15 N/A 8/31/2016

Comment Target exceeded. Source: School Grant Report.

Schools visited by Circuit Supervisors at least two times in a year (Percentage)

Value 0 100 N/A 100

Date Achieved 10/10/12 10/31/15 N/A 8/31/2016

Comment

Target met. Source: District Education Directorate annual report based on

Circuit Supervisors Reports. Note: Also reported in School Grant Reports for

cross validation.

Regional Education Directorates submitting annual M&E reports to GES HQ & PBME by

incorporating data from all districts in the region (Percentage)

Value 0 100 N/A 100

Date Achieved 10/10/12 10/31/15 N/A 8/31/2016

Comment Target met. Source: Annual M&E reports using the regional consolidation

templates.

Schools in deprived districts with completed SPIPs approved by SMCs using the revised

template (Percentage)

Value 0 75 N/A 100

Page 9: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

vii

Date Achieved 10/10/12 10/31/15 N/A 8/31/2016

Comment Target exceeded. Source: School Grant Report Template. Note: Districts also

verify with Circuit Supervisor Reports.

G. Ratings of Project Performance in ISRs

No. Date ISR

Archived DO IP

Actual

Disbursements

(USD millions)

1 04/28/2013 Satisfactory Satisfactory 10.00

2 12/14/2013 Satisfactory Satisfactory 22.68

3 06/01/2014 Satisfactory Satisfactory 34.21

4 12/24/2014 Satisfactory Satisfactory 46.60

5 06/27/2015 Satisfactory Satisfactory 60.48

6 12/31/2015 Satisfactory Satisfactory 70.49

7 06/22/2016 Satisfactory Satisfactory 75.50

8 08/31/2016 Satisfactory Satisfactory 75.50

H. Restructuring (if any)

Restructuring

Date(s)

Board

Approved

PDO

Change

ISR Ratings at

Restructuring

Amount

Disbursed at

Restructuring

in USD

millions

Reason for Restructuring

& Key Changes Made DO IP

05/14/2013 S S 14.96

To amend the legal

agreement to add "works" as

a category under District

Grants.

08/25/2015 N S S 60.48

To extend the Project for 10

months from October 31,

2015 to August 31, 2016 and

to introduce a reallocation of

funding among categories,

particularly from the

unallocated category to

category 2 (district grants).

Page 10: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

viii

I. Disbursement Profile

Page 11: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

1

1. Project Context, Development Objectives and Design

1.1 Context at Appraisal

Country Context

1. Ghana, a lower middle income country with sustained economic growth, was

considered a strong Sub-Saharan African economy at the time the Ghana Partnership for

Education Grant (GPEG) Project was appraised. Just prior to Project appraisal, the

beginning of oil production and high global commodity prices and good rains had boosted

the economy; real gross domestic product (GDP) growth was expected to reach 12.2

percent in 2011 and projected to remain greater than 7 percent in 2012 and 2013.

2. Ghana’s performance in terms of human development outcomes had been

improving and steady progress had been made with respect to the education Millennium

Development Goals (MDGs). The proportion of children completing primary school had

increased to 89 percent by 2012 from 70 percent in 1991. Progress on gender parity also

showed improvement (92 percent ratio of girls to boys in primary and lower secondary

education). However, Ghana was not on track to fully achieve these two MDGs by 2015.

At appraisal, the share of the population living in poverty was reduced by half between the

early 1990s and 2005-2006, but significant regional disparities remained between the

poorer regions in the north compared to the rest of the country.

Sector Context

3. The education sector in Ghana is divided into three levels: basic education

(including kindergarten, primary school, and junior secondary school), secondary

education (including senior high school and technical and vocational education), and

tertiary education, all under the jurisdiction of the Ministry of Education (MoE). The Ghana

Education Service (GES), an agency under MoE, is responsible for pre-tertiary education

service delivery while the National Council on Tertiary Education (NCTE) is responsible

for tertiary education. Ghana has been operating using a decentralized system since 1988

when local governments began to play a central role in administering greater resources and

taking on new functions. In education, basic schools are overseen by the District Education

Directorates (DED), which are local offices of the GES.

4. At the time of project appraisal, access to education in Ghana had improved

substantially. Between 2002 and 2012, gross enrollment rates (GER) increased from 49 to

99 percent in kindergarten, from 76 to 96 percent in primary, and from 63 to 81 percent in

junior high school (JHS). These improvements were driven by efforts to improve supply

of education as well as the elimination of school fees which led to the provision of school

capitation grants starting in 2004. In terms of learning outcomes, the National Education

Assessment (NEA) showed some improvements in English and Mathematics between 2005

and 2009 and some progress on the Trends in International Math and Science Study

(TIMSS) assessment of Grade 8 pupils between 2003 and 2007.

Page 12: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

2

5. Despite this progress, key challenges in the education sector remained including

disparities in learning outcomes, insufficient number of qualified teachers, and inequitable

access. There were significant disparities in learning outcomes between the north and

south of the country and between rural and urban schools. Education outcomes largely

followed regional poverty trends with poor districts challenged by weaker education

outcomes, untrained teachers, and fewer financial resources for education spending. In

2009, despite observed improvements, less than a quarter of Grade 3 students in public

schools were able to read a single word in English. The 2011 NEA and Basic Education

Certificate Examination (BECE) exams reflected wide gaps in learning between Northern,

Upper West, and Upper East Regions and the rest of the country. While net enrollment

rates increased1, a sizeable group of children (about 400,0002) were not in school (either

never entered or having dropped out). In 2008, over 65 percent of girls over the age of 15

in the Northern region had not received any formal education compared with a national

average of 21 percent. Trained teachers were more likely to work in urban or peri-urban

schools; at the time of the Project appraisal there were over 155 students per qualified

teacher in districts in the Northern, Upper West, Upper East, and Western regions.

Project Context

6. During the preparation of the Global Partnership for Education Fund Grant (GPEG),

the IDA Education Sector Project (EdSeP- US$78 million) was drawing to a close (October

31, 2011). The EdSeP aimed to improve (i) equitable access to and completion of basic

education in deprived districts; and (ii) quality of teaching and learning, management

efficiency, and relevance of post-basic education. In addition to the EdSeP which began

in 2004, the Education for All-Fast Track Initiative (EFA-FTI) approved a US$32.2 million

Catalytic Fund allocation for Ghana that was to be processed as three separate grants. The

first two grants (US$8 million in 2005 and US$11 million in 2007) were for direct budget

support to improve the quality of basic education. The third grant (in the amount of

US$14.2 million) in 2009 was a sector investment loan3 and unlike the first two grants

which were considered satisfactory, this operation experienced significant challenges with

large procurement packages and a short implementation period4.

7. While work had been done under the EdSeP in sector capacity building at the

central and decentralized levels, and piloting budgetary support to deprived districts – there

1 From 2011-2015 improvements are evident across all levels of education (from 4.2 percent to 80 percent

in kindergarten, 81.7 percent to 91.5 percent at primary and 46.1 percent to 50.3 percent in JHS). 2 UNICEF projections 2015. 3 The use of the Sector Investment Loan instrument conformed to the new EFA-FTI guidelines 4 By late 2008, presidential and parliamentary elections occupied the attention of key Ministry of Finance

and Economic Planning (MOFEP) officials which delayed final execution of the grant agreement to 2009.

Between the close of the second grant and the signing of the third, the Ministry of Education (MOE), in

anticipation of signing a third EFA-FTI grant, initiated a textbook procurement that they expected to be

financed with the new grant without Bank prior review of procurement documents or a no objection from the

Bank. This set the stage for many of the problems that occurred during the implementation of the third EFA-

FTI grant.” (ICR, Education Sector Development Project, December 2011, page 2).

Page 13: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

3

was still a need to mainstream these decentralized processes (e.g., district and school

grants) and further improve the existing monitoring and evaluation (M&E) systems.

Moreover, the importance of ensuring targeted resource allocation and significant capacity-

building in less endowed districts were lessons that had been learned from previous projects.

At the time of appraisal, the UK Department for International Development (DfID) had

also begun planning a scholarship program for girls in JHS with a plan to overlap this

program’s targeting with that used by GPEG. In addition, the United States Agency for

International Development (USAID) had begun planning and designing a learning project

which focused on early grade literacy and numeracy.

8. While the introduction of district and school grants under EdSeP was quite

promising for the education system, particularly with the political push to implement

decentralization to the district level, additional resources would be needed. This was

particularly the case in those areas of the country where there are significant disparities in

economic and social opportunities. While public spending on education was roughly 6

percent of GDP and Ghana compared favorably to higher middle income countries who

spend on average 5 percent of GNP on education,5 there was often little funding available

outside of financing salaries. In 2010, roughly 97 percent of the education budget was

allocated to salaries, leaving little for non-salary recurrent spending.

9. Since 2004, capitation grants (GH¢ 4.50 per student per academic year) had been

supplied in order to provide non-salary resources directly to schools by the Government.

The Government had also introduced the Untrained Teachers Diploma in Basic Education

(UTDBE) program in 2004 to upgrade the skill sets of unqualified teachers through

distance education. While the program had been successful in upgrading 16,000 untrained

teachers in rural schools, the portion of trained teachers in public basic education had been

steadily declining from 65 percent in 2001 to 48 percent in 2009 as enrollment increased.

As such, the UDTBE program needed to be accelerated in order to increase the number of

trained teachers in rural and underserved communities. The use of school report cards

(SRCs) was introduced in 2010 as a pilot (with USAID support) to provide greater

accountability in the areas of attendance and student learning outcomes while school

management structures existed (e.g., School Management Committees (SMCs), School

Performance Appraisal Meetings) but needed strengthening. A 2010 World Bank Survey6

found that even though SMCs existed in over 80 percent of schools, they were only active

in just over 61 percent of schools and members had not been adequately trained in

preparing a School Performance Improvement Plan (SPIP).

10. In 2010, The Ministry of Education (MoE) developed the Ghana Education Sector

Plan (ESP) for 2010-2020 as well as the three-year rolling Annual Education Sector

Operational Plan (AESOP) for 2011-2013 in close partnership with the Local Education

5 UNESCO Monitoring Report, 2015 comparison shows higher income countries such as Cambodia and the

Philippines spending about 2.7 and 2.2 percent respectively of their GNP on education and only 14 percent

and 15 percent of their total budgets for education. 6 Impact Evaluation of School Based Management Committees, 2010. M-H Cloutier (A survey of 300

primary schools).

Page 14: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

4

Group (LEG). The main priorities in the ESP were to: (i) improve equitable access to and

participation in quality education at all levels; (ii) bridge the gender gap in access to

education; (iii) improve the quality of teaching and learning; and (iv) improve the

management of education service delivery. The GPEG Project, financed by the Global

Partnership for Education (GPE) (formerly EFA-FTI), provided direct support for this ESP

while the Bank was selected as the Project supervising entity. Following on the heels of

the EdSeP – a large operation which had piloted support for district grants – the GPEG

provided an opportunity to expand and strengthen the district grant processes that were

considered successful under the EdSeP.

11. Rationale: In the context of Ghana’s geographic disparities and recent economic

growth, opportunities for equitable growth and shared prosperity were largely contingent

on improving the level of education and employability of the workforce in deprived regions

of the country. Education was considered one of the main mechanisms to allow individuals

living in poverty to share in Ghana’s economic growth. The support was consistent with

the World Bank Country Assistance Strategy (CAS) (2008-2012) objectives to focus on

targeted programs to the poor and improve basic health and education systems through a

decentralized system. The Project was also aligned with the GPE Global Strategic

Objectives of 2012-2015, and as noted above, provided direct support to Ghana’s 2010-

2020 ESP. The Project aimed to achieve its project development objective (PDO) by: (i)

making non-salary financial resources available to schools and districts in deprived areas

to improve education service delivery by local actors; (ii) improving decentralized

decision-making for school-based management and accountability; (iii) funding the

upgrading of skill sets of untrained teachers already teaching in underserved areas;; and

(iv) integrating and further developing ongoing and donor-led management tools such as

the SRC activity.

1.2 Original Project Development Objectives (PDO) and Key Indicators

12. The Project Development Objective was to improve the planning, monitoring, and

delivery of basic education services in deprived districts of the Recipient’s territory.

Successful achievement of the PDO would be measured by the PDO-level indicators

presented in Table 1 below.

Page 15: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

5

Table 1. PDO-level Indicators

PDO-level Indicators Baseline

(2010/2011) End of Project Target

(2015/2016)

1. Deprived districts disbursing 75% or more of their

district education grants as planned in their Annual

Program of Works (%)

0 80

2. Public basic schools in deprived districts with up-to-

date School Report Cards (%) 0 75

3. P3 student achieving proficiency in English and

Mathematics (using National Education Assessment

results for deprived districts) (%)

English 12.4

Mathematics 9

English 15

Mathematics 11

4. Teachers trained under the project in deprived

districts who obtain satisfactory rating or higher in the

SBI/CBI Lesson Observation Sheet for lesson

planning, teaching methodology, and classroom

organization and management (%)

36 50

5. Direct project beneficiaries (number) of which

female (%) CORE 0

1.6 million of which 40%

female

1.3 Revised PDO (as approved by original approving authority) and Key Indicators, and

reasons/justification

13. The PDO and Key Indicators were not revised during the life of the Project.

1.4 Main Beneficiaries

14. The project beneficiaries identified at appraisal were the students, teachers and

administrators (all disaggregated by gender) targeted by project interventions in the

deprived districts. The targets for beneficiaries were disaggregated by gender and tracked

throughout implementation. Under the Project, students, teachers, and administrators in

over 7,000 project-supported schools in 75 deprived districts (out of 216 districts) had

benefitted from Project activities. Secondary beneficiaries of the Project included the

Colleges of Education responsible for the UTDBE program, SMCs, Parent Teacher

Associations (PTAs), Regional Education Officers (REOs), District Education Officers

(DEOs), GES central staff, National Inspectorate Board (NIB) and senior MoE staff

involved in the implementation and M&E of the project. The targeted beneficiaries of the

Project did not change during the life of the Project, with the exception of additional

district-level staff which were included as a result of incorporating 18 newly created

districts (in the same geographic area) that had been formed during the national

redistricting exercise in 2014.7

7 In 2014, there was a re-delineation of Ghana’s 170 districts to 216 districts, leading to an increase of 18

targeted deprived districts (carved out of the original 57 deprived districts) for the Project during

implementation and bringing to the total number of beneficiary districts to 75.

Page 16: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

6

1.5 Original Components

15. Component 1: Sub-Grants to Deprived Districts to support key education

objectives (Appraisal estimate: US$44.86 million; Actual: US$48.41 million). The goal

of this component was to provide annual non-salary supplemental resources to deprived

districts to support districts’ annual programs of work (APW) focused on local needs as

well as government strategic priorities of improving access, equity, quality and

management of basic education. Under this component, the government planned to

increase accountability and participation by districts, schools, and communities through:

(i) earmarked funding for the upgrading of unqualified teachers’ skills sets through the

UTDBE program; (ii) mandatory in-service teacher training in literacy, numeracy, and

science; (iii) capacity building for GES staff, regional and district officials, Circuit

Supervisors, SMCs, head teachers, etc.; (iv) facilitation and knowledge sharing by regional

and central governments; (v) M&E activities; and (vi) continuous sensitization activities to

maintain social accountability.

16. Component 2: School Sub-Grants (Appraisal estimate: US$24.06 million;

Actual: US$20.38 million). The goal of this component was to improve teaching and

learning through supplements to the capitation grants at all basic education schools in

deprived districts. The component aimed to improve the management and accountability

of resources at the school level and to strengthen the School Performance Improvement

Plan (SPIP) process and community engagement in approximately 6,600 schools across

the deprived districts. Component 2 was to fund training on the school grant process,

monitoring visits, communication campaigns, school grants, and an impact evaluation (IE)

of school grants (this IE was later combined with the district grant evaluation and funded

under Component 3).

17. Component 3: Project Management and Institutional Strengthening

(Appraisal estimate: US$6.58 million; Actual: US$6.71 million). The purpose of this

Component was to strengthen government systems for the implementation and supervision

of decentralized education services in the deprived districts. This component would fund

consultancy services, training and operational costs, materials, IEs, and external and

internal audits.

1.6 Revised Components

18. There were no major changes in the components other than reallocation of

resources following the mid-term review (MTR) in February 2015.

1.7 Other significant changes

19. The project was restructured twice. The first restructuring was approved on May

14, 2013 in order to add “works” to Category 2 which supported sub-grants to the deprived

districts (District Grants).

20. The second restructuring was approved on August 25, 2015 in order to extend the

project closing date by ten months from October 31, 2015 to August 31, 2016, and to

Page 17: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

7

reallocate funding among expenditure categories. The extension would allow additional

time to: (i) provide support to teacher trainees in the UTDBE program to complete their

diploma program; (ii) start-up support for the 18 additional districts (carved from the

original 57 districts); and (iii) complete the IEs.

21. With respect to the teacher trainees in the UTDBE program, the project had

intended to support the trainees through their third year only;8 however, once a project

extension was requested by the Ministry of Finance, it was agreed that the project could

continue its support to the program participants for their fourth and final year of the

program. There were significant savings under the project as a result of exchange rate gains,

lower costs than estimated, and efficient procurement of goods and consultancies. As

mentioned previously, the expected re-delineation of Ghana’s districts in 2014 led to the

eventual establishment of 18 additional deprived districts carved out of the original 57,

bringing the total number of project districts to 75. This increased administrative functions

as the number of district offices involved increased by 18, but did not alter the targeted

project beneficiaries (schools, teachers) as the same population was being captured within

the 75 districts. The extension and reallocation under the restructuring supported capacity-

building for the new district officers, technical assistance and training on project processes,

and start-up funding to equip the new offices and support implementation monitoring.

2. Key Factors Affecting Implementation and Outcomes

2.1 Project Preparation, Design and Quality at Entry

22. Project Preparation. Project design was in alignment with key education sector

priorities for the country. As described earlier, its design was harmonized with the ESP for

2010-2020 as well as the three-year rolling AESOP for 2011-2013 in close partnership with

the LEG. The project reflected the ESP strategic goal to provide “equitable access to good-

quality child-friendly universal basic education” and as such focused on targeting

improvements in the deprived areas of Ghana which were lagging behind the rest of the

country in terms of education outcomes. The Project design was also in line with the CAS

2008-2012 which focused on targeted programs for the poor and improving basic health

and education services through the decentralized system. Moreover, the GPEG was

consistent with the GPE Global Strategic Objectives (2012-2015) of supporting basic

education for girls, improving literacy and numeracy skills, improving teacher

effectiveness, and expanding the volume, effectiveness, efficiency, and equitable

allocation of education funding.

23. Project preparation relied extensively on significant analytical work by both the

World Bank and the LEG. A significant strength of the GPEG was the participatory nature

of the preparatory process. The Project was prepared in close partnership between the

Government and the LEG, which included the DfID, the United Nations Children’s Fund

(UNICEF), the Japan International Cooperation Agency (JICA), USAID, and the World

8 As mentioned in the PAD, additional donor funding or government budget was expected to cover the costs

of the UTDBE beneficiaries in the fourth year.

Page 18: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

8

Food Program (WFP) among others, through joint missions, monthly development partner

(DP) meetings, and weekly preparation meetings starting in October 2011. The appraisal

of the ESP coincided with the preparation and design of the GPEG Project, allowing close

involvement of key partners and a strong focus on supporting the objectives of the ESP.

Project preparation also included stakeholder workshops and multi-donor missions to

ensure strong ESP alignment and wider ownership of the Project.

24. Project Design. The Project is Ghana’s fourth EFA-FTI (now GPE) grant. While

the first two grants provided budget support and were rated Satisfactory, the third grant

(which was a SIL) aimed to procure textbooks and learning materials and provide

incentives to attract and retain teachers in deprived districts, was rated Unsatisfactory. This

rating was attributed to the operation’s overly ambitious timeline, implementation delays,

misunderstandings of new guidelines, post-election government changes, and ultimately

the repayment of ineligible expenses to the GPE Fund.9 As a result of this experience, the

GPEG project application was prepared in a more collaborative and comprehensive manner

and avoided centralized procurement of goods or works. In addition, the production of a

detailed Project Implementation Manual (PIM) by the Government enhanced

accountability among all stakeholders. The lessons learned from the experiences with the

EFA-FTI grants on strong government ownership and leadership, strong project

supervision, and realistic implementation period and targets were critical in informing the

design of GPEG.

25. The GPEG design also benefitted from other investments in the sector and in Ghana.

Activities and approaches that were piloted under the EdSeP became the evidence-base for

the GPEG (e.g., equity-based targeting, district and school grants, local capacity-building

for planning and monitoring) 10. The GPEG design was informed by lessons learned from

EdSeP including the importance of: (i) having a simplified project design; (ii) setting

realistic ambitions for decentralized delivery of education services of district grants; (iii)

ensuring indicators are linked to Project interventions and are measurable; (iv) ensuring

transparent and objective targeting of Project support to more economically disadvantaged

regions; (v) establishing more integrated and comprehensive M&E systems to collect data,

measure impact, and influence decision making; (vi) ensuring the timely release of funds

along with capacity-building at the district level to improve success of district grants

against APWs; and (vii) providing capacity-building support at the school level to include

circuit supervisors, head teachers, and SMCs. The GPEG revised the criteria for selection

of “deprived” districts to include both Ghana’s poverty index as well as key education

9 The implementation period of just over one year also coincided with the long transition period after the

2008 election and substantial confusion about the change in fiduciary rules from budget support to investment

project. The large centrally procured packages were problematic and the remaining activities (civil works for

teacher accommodations) required a longer implementation period. In addition, supervision was inconsistent

and led to misunderstandings between the Ministry and the Supervising Entity which led to a neglect of

World Bank procurement guidelines with respect to the textbook component. These expenditures were

declared ineligible and were repaid to the EFA-FTI Fund. 10 Details of lessons learned were included in the PAD as an optional Annex (PAD, Annex 8, page 106) and

included a literature review of school-based management interventions and evaluations to inform the school

grant component.

Page 19: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

9

indicators11. The bottom third of the districts, ranked according to the new criteria were

then selected to benefit from the GPEG. All basic schools within these districts would be

supported under the Project, and upgraded teachers (through training under the Project)

would be assigned to the schools in the targeted districts.

26. Project Risks. During preparation, risks were rated substantial related to

stakeholders, implementing agency capacity and overall decentralized service delivery.

Part of the rating reflected the upcoming 2012 elections and concerns about staff turnover,

but most of the issues highlighted were potential risks related to consistent leadership and

coordination and the participation of local communities to ensure that education services

would be delivered. The extensive GPEG consultations combined with the well-vetted and

publicized ESP helped maintain and foster consensus among a large number of

stakeholders. In addition, the PIM guided implementation at both the central and

district/school levels. A separate (and simple) school grant manual was also developed and

widely disseminated during frequent monitoring visits. In feedback from Impact

Evaluation (IE) surveys, the use of GPEG management and planning tools was highly

evident as was the involvement and satisfaction of parents/communities.12 Institutional

assessments had found an overall low capacity at the district and school levels, especially

in deprived regions/districts, so this posed a potential risk. It was decided, therefore, that,

intensive supervision would be provided over the first 18 months of project implementation

(at a significant cost to the Bank supervision budget) to help encourage technical support

and address challenges quickly.

27. Involving the REDs provided additional resources at the local level and helped

build capacity; having developed simplified data monitoring and reporting templates

during project preparation helped to improve M&E systems. In addition, the Project

budgeted for significant training at the local level and monitored this training through the

Project’s Result Framework. Multiple monitoring tools already in use or recently

developed under the GPEG helped mitigate risks to delivery monitoring. The risk of

sustainability, while rated moderate, was highlighted during preparation (and throughout

implementation) and only partially mitigated because of the fiscal crisis that emerged by

2014. The most significant mitigation measure to address these aforementioned risks under

the GPEG was the use of government systems which ensured ownership, political

leadership and adoption of standardized management tools.

28. Quality at Entry. As mentioned above, the preparation of the GPEG was launched

from the ongoing ESP process. The ESP process included considerable technical guidance

and support from the GPE, the LEG, and DP-funded consultancies in the areas of girls’

education, teacher training, learning assessment, decentralization, and kindergarten roll out.

11 Education indicators looked at performance in retention in the basic cycle, share of girls enrolled in P6 and

JHS 3, pass rate in BECE English and share of trained teachers in all public primary schools. 12 The GPEG impact evaluation surveyed 353 schools out of the over 7,000 schools in the 75 GPEG districts.

See sampling design and findings in the 2016 report “Impact evaluation and monitoring of the District Grant

and School Grant component of the Ghana Partnership for Education Grant.” by Edburgh consultants and

Innovative Services consortium.

Page 20: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

10

The additional analytical work from these activities as well as the Bank’s sector work

provided a sound framework for the GPEG components.13 The selection of the Bank as

supervising entity for the Project preparation also introduced the Bank’s quality assurance

process to complement GPE’s processes. The LEG played a particularly critical role, under

the leadership of the Coordinating Agency (UNICEF) in ensuring consistency of the

objectives with the ESP and donor-supported programs.

29. Several rounds of quality-at-entry assessment were carried out as part of Project

Preparation. This included two rounds of Quality Assurance Review (QAR) from the GPE

Secretariat as well as a Quality Enhancement Review (QER) with the World Bank. The

GPE was using new procedures for the processing of projects and there was considerable

confusion about how to align the new GPE guidelines with Bank project processing

guidelines. The GPEG navigated these challenges by carrying out both quality assurance

reviews. Both the QAR and QER endorsed the design and approach of the Project, its

consistency with the ESP, and provided guidance on issues related to the PDO, RF,

selection of project activities, elaborated implementation arrangements, and greater donor

harmonization. Similarly, the Bank’s QER assessment provided further feedback on the

PDO, RF, M&E arrangements and activities, and readiness for implementation. The final

design reflects the guidance received, although with two separate quality assessments, the

team had to navigate through some contradictions in guidance.14 Overall, the ICR team

found the process to be technically sound and operationally appropriate, with strong

collaboration from the LEG.

2.2 Implementation

30. Implementation of the project was satisfactory – as a result of focused yet relevant

project design (supporting a limited number of activities) which built on ongoing

investments, strong donor coordination, use of existing government mechanisms, and

strong Project M&E, management, and supervision.

31. By limiting activities to those which had already received support (and had been

field-tested) in Ghana, the Project was able to disburse all funds and complete project

activities within a four-year period (the large majority of activities were completed by Year

3). The school capitation grants, district grants, and UTDBE program had all been

previously (and recently) implemented in Ghana, allowing for easier uptake of improved

and expanded versions of those programs through GPEG.

13 Documents included the 2012 PFM Review, JICA; 2011 Ghana Education Report “Improving Equity,

Efficiency and Accountability of Education Service Delivery”, World Bank; Education Sector Development

Project Implementation Completion Report 2012, World Bank; Education Support to Education Strategic

Plan and KG operational plan, DFID. 14 For example, the GPE QAR placed emphasis on showing a contribution to improved student learning,

while the Bank QER suggested that PDO indicators be in the scope of the Project and attributable to the

Project. In the end, the Project compromised with a PDO indicator on student learning kept but a PDO on

teacher absenteeism dropped.

Page 21: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

11

32. Harmonization among DPs was strong throughout GPEG implementation and this

greatly aided successful implementation. Progress under the Project was monitored and

reported at monthly LEG meetings, allowing for frequent status updates. The project was

launched and closed by the same Minister of Education. Six formal joint implementation

support missions were held since effectiveness, occurring approximately every 6 months.

These missions included joint field visits with other DPs (most of whom provided parallel

financing) including DfID, UNICEF, and USAID which led to greater coordination,

collaboration, and technical support to GPEG. The Bank and LEG supported four

Government-led National Education Sector Annual Reviews (NESAR) during the Project

where an expanded group of education stakeholders participated in discussions on the

sector. GPEG was also highlighted in the Government’s Annual Education Sector

Performance Report (ESPR), published at the time of each NESAR. Moreover, the US$10

million DfID-financed Girls Participatory Approach to Student Success (GPASS)

Scholarship program was operating in GPEG districts, aligning with GPEG APWs and

using the same structures as GPEG. This allowed both projects to complement each other

for shared achievement of outcomes.

33. The use of existing government structures was an important feature of the operation

and strengthening decentralized models of governance in the education sector was an

important objective of the GPEG. By working through existing government mechanisms,

GPEG fostered strong project ownership within the MoE and GES. The beneficiary

assessment credited the GPEG for empowering the existing systems and helping to make

them better functioning.

34. The project also benefited from dedicated project management and supervision and

this facilitated the effective implementation of the project. MoE/GES and Bank teams

closely supervised the Project, and regular and candid dialogue between the Bank and the

Ministry on implementation helped resolve implementation bottlenecks in an efficient

manner. On the Bank side, having in-country core team members and a team task leader

who prepared and implemented the project allowed for sustained and consistent support

and supervision. The Project’s funding of a video conference facility at GES further

supported strong communication between the Ministry and Bank teams.

35. Despite having an overall satisfactory implementation, GPEG encountered a

number of challenges including the collection and validation of large amounts of data and

high staff turnover (especially at the local level), as well as reporting challenges and

attrition in the UTDBE training program. The collection and validation of data at district

and school levels experienced some delays throughout the project period as districts

struggled to capture and code all school level data (including individual teacher training).

There was a significant amount of data to collate. Further, staff turnover in districts and

schools was high. While the project design included trainings for SMCs, Head Teachers,

Circuit Supervisors, District and Regional officers, the high turnover resulted in schools

and districts not always well versed in guidelines and procedures. New head teachers faced

difficulties in preparing SPIPs which led to mistakes and delays in vetting. At the district

level, high turnover was especially challenging for procurement officers. This was partially

alleviated through support from REDs, the availability of refresher trainings and well as ad

Page 22: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

12

hoc trainings for new staff. When district directors had an increased awareness of GPEG,

district grants ran smoothly.

36. The Government committed significant resources (human and financial) to twice

yearly district collation exercises to bring staff together to go over key financial and

monitoring reports. These workshops also served as opportunities for additional capacity-

building and training of key project staff/officers, especially those that may have been

newly appointed at the district level. The School Grants activity also provided ample

resources for ongoing training/capacity building for head teachers and teachers so new staff

could better acquaint themselves with the GPEG processes.

37. The Project also faced some initial eligibility concerns and reporting challenges on

the UTDBE program which were largely resolved during implementation. There were

initial misunderstandings within the UTDBE program on the eligibility requirements

particularly as a result of the parallel Northern UTDBE program (sponsored by the

Colleges of Education) that had been launched just prior to GPEG effectiveness without

the knowledge of the Bank team. This other program (held in the Colleges of Education

based in the Northern regions) had enrolled many teachers in GPEG districts but without

application of the GPEG eligibility criteria. With the strict eligibility criteria being applied

under the GPEG, and many trainees already enrolled in the Northern program, there was

considerable confusion about the initial intake.

38. Further, there was some degree of attrition with the numbers of trainees enrolled in

the program with 7,027 UTDBE participants sponsored by GPEG in 2013 and by 2016

only 6,480 had completed the full training. Some of these participants dropped out of the

program, passed away, or failed to pass (among other reasons).15 In addition, the inability

of the GPEG to use the Colleges of Education in the North for the residential coursework

(they were oversubscribed with the initial Northern program) meant that trainees had to

travel long distances to attend their face-to-face sessions at other Colleges of Education.

This increased transaction costs and made it more difficult for tutors to provide the in-

school coaching and support required. GPEG was able to resolve some of the eligibility

concerns during the first year through an extensive verification and cleaning exercise

conducted by the quality assurance consultants hired to support the UTDBE program.

These consultants were also expected to provide additional recommendations to improve

the face-to-face sessions as well as the in-school and in between coaching sessions and

they produced a monitoring report after the MTR when concerns were raised about the lack

of regular and high-quality reporting on UTDBE program beneficiaries. However, the

quality of the TA provided by these consultants could have been better. The team expressed

its dismay at the level of assistance as well as the lack of proactivity by the consultants.

The team hired two additional consultants to provide direct support to the Teacher

Education Department on revising the UTDBE materials for both the residential college

course and for the in-between trainings in order to ensure technical and quality assurance

was provided.

15 The ICR does not yet have the final data on these graduates with regard to their inclusion on the

Government’s teacher payroll.

Page 23: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

13

39. Mission field visits and other monitoring visits found some cases of poor record

keeping by head teachers, SMCs not operating as effectively as they should, and other

challenges at the school level (including overcrowding from increases in attendance, need

for additional teachers and resources beyond the school grant, difficulties monitoring

remote schools, etc.). The project team set out to better understand the issues by conducting

two in-depth fiduciary reviews in addition to the regular internal and external audits.

Mitigation measures were identified from these reviews such as continual training for new

staff, simplified school level templates and greater support from circuit supervisors. The

latest management response to the audit report indicates actions that were taken to address

the issues raised. 16 At the MTR stage, it was noted that additional attention to

communication and sensitization of GPEG would be needed for greater Project

effectiveness; by early 2016 the mobile SRCs piloted with support from UNICEF and

USAID held promise for enhancing community engagement and accountability.

2.3 Monitoring and Evaluation (M&E) Design, Implementation and Utilization

40. Design. The system as described in the PAD, PIM and impact evaluations was

sound and capable of collecting information on all performance indicators. One of the great

strengths of the M&E design, and ultimately the GPEG Project, was the richness and

diversity of M&E data built into the Project design. While Ghana had an Education

Management Information System (EMIS) system in place for a decade, its credibility

continued to be an issue and the GPEG helped to strengthen the integrity of EMIS data and

cross-verify how schools were reporting. GPEG included APW analyses, SRC analyses,

quality assurance on the UTDBE program, a beneficiary study, internal and external audits,

an extensive MTR report, and two IEs. Given the focus on better planning and monitoring,

the GPEG set up standardized systems for better analysis of data from schools and districts.

The systems evolved over the course of implementation as it became clear when reporting

was too burdensome, or school heads had difficulties inputting data. The PIM served as a

roadmap, offering explicit instructions on M&E reporting, and has since been used as a

sample for other donor-funded projects.

41. The quality of the RF was good overall. The PDO-level and intermediate results

indicators were linked to the PDO, with at least one PDO-level indicator for each sub-

objective. There are a reasonable number of PDO-level and intermediate results indicators

and realistic targets for a three-year project – all of which benefitted from QAR/QER

feedback. This allowed for regular reporting on Project progress and accurate indications

that the Project was performing well throughout implementation. The causal chain in the

RF is good with all intermediate indicators supporting a PDO indicator with only a couple

of exceptions. There is perhaps an overemphasis on SRCs in the RF indicators; the RF may

have benefitted from greater emphasis on the development of SPIPs from SRC data and

the funding of activities according to what had been planned in SPIPs.

16 This issue of school-level non-compliance was quite low considering that the GPEG reached over 7,000

deprived schools with low levels of capacity at the start of the Project.

Page 24: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

14

42. The PDO-level indicator of “P3 students achieving proficiency in Math and English”

was ambitious for a three-year project. Attribution for learning is difficult to apply only to

GPEG given the other interventions going on in these districts during the Project period

(e.g., non-formal education, school feeding, etc). While the GPE requested that the RF

include a learning outcome indicator, a more appropriate PDO-level indicator for improved

service delivery could have been included such as improvements in teacher/student

attendance rates or improvements to access or retention. While not in the RF, these

indicators were tracked through the SRC analysis and improvements were observed

throughout the project period. However, this data is self-reported, and therefore is less

reliable than assessment data that was conducted through a standardized national education

assessment. Targets for some indicators (disbursement of grants, up to date SRCs) were

exceeded. Given the significant challenges in disbursement of grants under the EdSeP,

these targets appear to be realistic for GPEG at the design stage. The RF design may have

been enhanced if more information had been provided on how targets were calculated. For

example, providing information on how targets were set based on observed trends and

assumptions on the reach of the intervention.

43. In addition to regular monitoring instruments, two IEs were conducted that assessed

the UTDBE diploma program as well as the district and school grant programs. The aim

of the UTDBE IE was to: (i) assess the extent to which the distance training program had

achieved its objective of upgrading the skill sets of untrained teachers and impacted

learning outcomes; (ii) compare the classroom performance and content knowledge of

UTDBE trainees with teachers from the conventional teacher training program in Ghana;

and lastly to (iii) make an assessment of cost-effectiveness of the program. The district and

school grant IE was designed in order to: (i) estimate the impacts of the district and school

grants on higher-order outcomes as well as intermediate outcomes at the district and school

level; and (ii) to carry out a survey amongst a sample of schools to report on a selection of

RF indicators and verify and validate the ongoing M&E system. This IE faced

implementation challenges as it became very delayed owing to the slow procurement

process in selecting and contracting the consultant and the difficulties redesigning an

evaluation after implementation had already commenced. Ultimately the scope had to be

reduced which limited the quality of evidence produced from the evaluation.17 The low

capacity of MoE to manage a difficult contractor hired for the evaluation was one challenge

which ultimately affected the timeline and scope. Limited knowledge of technical aspects

of IEs further delayed implementation. Most IEs had been managed by donor partners in

the past. Nevertheless, GPEG adopted mitigation measures to improve their capacity, by

seeking technical support from the Bank and local research firms (e.g., Innovations for

Poverty Action), and conducting IE training for Planning, Budget, Monitoring, and

Evaluation (PBME) staff. The PBME is now managing and supporting two IEs under the

current IDA-funded Secondary Education Improvement Project (SEIP) project.

17 The study was conducted without a control group and baseline data collection, but rather through a desk

review, discontinuity analysis and endline data collection in July 2016. See the 2016 report “Impact

evaluation and monitoring of the District Grant and School Grant component of the Ghana Partnership for

Education Grant.” by Edburgh consultants – Innovative Services Consortium. 2016.

Page 25: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

15

44. M&E Implementation: GPEG M&E implementation had some impressive

successes and only minor shortcomings. Led by GES, the strong implementation of M&E

activities was integral to the overall success of GPEG. This included the well-prepared

annual performance reporting on GPEG, the APW analysis, regular monitoring visits

(including joint sector field visits by LEG members) during the lifetime of the GPEG

project, internal and external audits, a beneficiary study, and management of two IEs.

Examples of strong M&E implementation also included the use of detailed M&E templates,

developed in close collaboration with the Government and stakeholders, with key staff in

the education system trained in their use. The APW analysis for GPEG was the first time

the central Ministry had a clear sense of what activities (and their cost) were being

implemented by schools using their capitation grants. Further, annual analyses allowed for

a feedback loop between the central Ministry, districts, and schools; results were

incorporated into capacity building and outreach activities to best ensure relevant grant

activities.18 The coding used for the district grants also allowed better understanding of

district priorities. In addition, the IEs provided extremely rich data on management at the

district/school levels, parent and community involvement, teacher behavior in the

classroom, UTDBE cost-effectiveness, student learning outcomes, and access and

completion rates at schools, among other results. The extensive data from the IE, annual

progress reports/missions, and the collection of such detailed data (at the decentralized

level) were among the standout successes of GPEG.

45. The implementation of M&E under GPEG faced some challenges in terms of RF

indicator reporting and IE management. The collection and validation of decentralized data

on teacher training, from over 7,000 schools and 75 districts was difficult and could have

been improved with computerization of reporting. The number of teachers trained in In-

Service Education and Training (INSET) was being reported as the cumulative values of

trainings given each year. As a result, the exact number of teachers trained can only be

calculated through a proxy indicator for trainings conducted in one subject over one year

at the end of the Project. This also led to overly complicated reporting on direct project

beneficiaries. 19 In addition, the endline value for the PDO indicator on “P3 students

achieving proficiency in English and Mathematics” could not be calculated in the final year

of the project as the 2016 NEA changed the grade level tested to P4.20 Unfortunately the

team did not learn of this change until July 2016 (one month prior to closing). However,

the project benefitted from additional learning assessments conducted during

implementation- the USAID supported EGRA and EGMA rollout in 2013 and 2015 and

these results are discussed below in section 3.

46. In the end, the MoE was successful in implementing the district and school grant

study in a short period, and the Bank team mobilized international experts to support the

18 For example, officers from GES headquarters held quarterly meetings with district officers to check and

discuss project activities and status report of the districts. This high quality reporting prior to

implementation support missions allowed focused mission discussions to address bottlenecks. 19Reporting could have been simplified by using the EMIS count of teachers and students in Project

districts, as all were direct beneficiaries. 20 The NEA receives funding and technical support from USAID.

Page 26: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

16

Ministry. While the IE results have informed project performance, there were some missed

opportunities for learning from baseline results and a more robust study design because of

delays and challenges in procuring the survey firm by the Government. The problems in

contracting were not immediately communicated to the Bank, however once the Bank

learned of the difficulties in reaching agreement on deliverables and scope of the research,

the team mobilized international experts to help support the evaluation and get the most

out of the more limited study design.

47. Utilization: Active monitoring of Project activities were critical to the overall

success of GPEG. In general, GPEG did an excellent job of developing feedback loops to

inform and improve the quality of GPEG activities and ultimately the impact of the Project.

The APW analysis is an excellent model which could serve as a best practice for other

Projects using a similar decentralized model of non-salary resource provision. The joint

review missions used these APW reports in order to discuss improvements, provide

recommendations and determine next steps and Project adjustments. These reports evolved

over the course of GPEG with constructive adjustments. Following the MTR, additional

monitoring was contracted including a second in-depth fiduciary review and a separate in-

depth procurement review. Moreover, the Lesson Observation Sheets (LOS) as part of the

UTDBE IE provided a very rich source of data on UTDBE trainee performance throughout

GPEG’s implementation. The UTDBE and district and school grant IEs are providing key

lessons for the Government and other key stakeholders. For example, the IE findings on

the similar performance of UTDBE and DBE-trained teachers but the greater cost-

effectiveness of the UTDBE program will be extremely valuable in advocating for the

continuation of the UTDBE program beyond GPEG. At the time of Project closing, the

Government is considering subsidizing UTDBE trainees for kindergarten teachers since

this is still an area where there are huge deficits of qualified teachers.

2.4 Safeguard and Fiduciary Compliance

48. Safeguards: The project was classified as a Category B given the potential

environmental and social impacts of district and school grants that might involve minor

rehabilitation of existing buildings or construction of new buildings on existing sites. An

Environmental and Social Management Framework (ESMF) was developed through

consultation and disclosed by the time of project appraisal. The ESMF proposed specific

institutional arrangements to enable sustainable execution of all measures identified in the

ESMF. The PIM included a negative list of items that could not be funded through district

or school sub-grants to discourage items/activities that could trigger additional

environmental and social safeguards. Safeguards reviews were conducted during

implementation in May 2014 and March 2016. During the May 2014 review,

recommendations for screening of minor civil works at the district level were provided and

an Environmental Management Plan (EMP) checklist was developed and circulated.

Despite the initial delays of undertaking environmental and social screening of the sub-

projects, the March 2016 mission confirmed that all minor rehabilitation works undertaken

under the project had been screened and were well documented using the Rehabilitation

and Construction Works Mitigation Measures Checklist provided in the PIM. The

interventions undertaken by GPEG did not trigger additional Safeguards policies nor

additional instruments aside from the approved ESMF for the project.

Page 27: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

17

49. Fiduciary: Fiduciary compliance is rated Satisfactory. Overall the client has

complied with all legal covenants related to FM arrangements - there were no outstanding

audits and annual audit reports were received on time and were of unqualified opinion.

Interim unaudited financial reports were also submitted in a timely manner and in

accordance with Bank procedures. Interim Financial Reports were provided on a quarterly

basis. An internal auditor performed independent and objective internal audit activities

including inspections and verification of the use of funds at the district and school levels.

Procurement under the Project was sound but the delay in collating the district level

procurement plans was raised by the project team. Procurement related to project-

supported activities at the central level were adequately implemented and documented. At

the decentralized levels, while monitoring was adequate, reporting was not comprehensive.

After the MTR, the project was able to report on district level procurement and more

recently captured school-level information through an in-depth procurement audit.

50. The GPEG also conducted two in-depth fiduciary reviews, one in December 2014

and the subsequent review in August 2016. The most recent in-depth review (conducted by

an independent consultant) found overall good FM performance based on a sampling of 35

districts and at least 3 schools per district. The fiduciary review attributed the quality of

FM performance to the mainstreaming of FM arrangements with existing Government

processes complimented by strict procedures and processes highlighted in the PIM. While

capacity of district internal auditors was variable and there was some uneven collation of

data by Regional offices, the reviews concluded that the FM systems were in place and

being effectively utilized. There were some challenges related to FM which included: (i)

changes in the accounting personnel, particularly at the district level; (ii) delays in making

payment for district claims (for procurement related activities) which required travel from

the districts to Accra; and (iii) poor filing systems in some districts and schools.

2.5 Post-completion Operation/Next Phase

51. Ghana has experienced a number of external and domestic shocks since 2013/2014

due to the decline in the price of oil, gas, and gold which has limited its prospects for

revenues. The Government, as a result of the oil crisis, has faced fiscal pressure and may

not be able to sustain the level of district and school grants under GPEG. This has had a

direct impact on the ability for the Government to sustain certain GPEG activities in its

budget, such as grant allocations to districts and base grants for schools. That being said,

by working within Government systems and building capacity for better monitoring,

planning, and management, GPEG-supported systems have the institutional knowledge to

continue to employ activities at the school, district, and headquarters levels without

additional budget support. At the closure of the Project, several GPEG activities are

expected to continue while others remain uncertain. A sustainability workshop was held

and attended by representatives at the central, regional, and district levels. During this

workshop it was discussed which GPEG activities and procedures do not require funding

to be implemented. The new Government elected in January, 2017 promises to resolve the

fiscal gap and ensure more predictable funding at decentralized levels.

Page 28: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

18

52. At the activity level, continued GPEG interventions include school and cluster-

based INSETs, teacher mentors, empowering SMCs and PTAs, SRC evaluation and APW

analyses, and encouraging the use of local teaching and learning materials, amongst others.

At a procedural level, there are many no-cost aspects of GPEG that would continue,

including appraising performance and promotion of head teachers, more efficient

deployment of teachers, simplifying the format of Circuit Supervisor reporting, and

continuation of the UTDBE program. The use of supervision and monitoring templates at

the district-level, capacity-building trainings on SPIPs and APWs, reliable and predictable

release of capitation grants, efficient deployment of teachers, are all capacities created

under GPEG which continue to be implemented by the Government. Section 4, Risk to

Development Outcome, provides more details on the sustainability of project outcomes

and activities.

53. No new GPE grants are currently planned for Ghana but the Government will

continue to engage with the GPE on potential opportunities if and when additional

allocations become available. In addition, the Bank will be preparing a new Country

Partnership Framework (CPF) in which new investments in education are expected to be

considered in basic and post-basic education.

3. Assessment of Outcomes

3.1 Relevance of Objectives, Design and Implementation

Relevance of Objectives

54. As described earlier, the Project was aligned with the sector priorities of the

Government, LEG, Bank, and GPE at appraisal. At closing the Project continues to be

very strongly tied with Ghana’s education sector priorities. As the GPEG Project was

designed while the ESP of 2010-2020 was being appraised -- it is highly aligned with the

ESP goal of providing “equitable access to good-quality child-friendly universal basic

education”. The Project was also very relevant medium-term objectives in the Ghana

Shared Growth and Development Agenda II (2014-2017), which were to: (i) increase

inclusive and equitable access to, and participation in quality education at all levels; (ii)

improve the quality of teaching and learning; (iii) promote the teaching and learning of

science, mathematics, and technology at all levels; and (iv) improve the management of

education service delivery. Similarly, Ghana’s National Action Plan for Education (2016-

2030) identifies three sub-objectives for basic education, which all very closely align with

the GPEG’s objectives. These sub-objectives include: (i) improving equitable access to

participation in quality basic education; (ii) improving quality of teaching and learning

outcomes; and (iii) promoting sustainable and efficient basic education management and

accountability systems for education service delivery.

55. The Project also continues to be aligned with the World Bank’s Country Partnership

Strategy (CPS) for Ghana (2013-2016) which was recently extended to 2018. The CPS

places emphasis on human capital development as being central to the country’s growth

and shared economic prosperity. Consistent with Pillars II and III, the Project focuses on

improving competitiveness and job creation while also protecting the poor and vulnerable

Page 29: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

19

by targeting improvements in the deprived areas of Ghana which are lagging behind in

human development indicators. Between the time that the CPS was designed in 2013 and

its extension in 2016, the serious external and domestic shocks Ghana experienced as a

result of the decline in the global prices of gold, oil, and gas has limited Ghana’s prospects

for revenue. As a result, the priorities of the CPS continue to be relevant.

56. The Project also remains relevant to the World Bank and GPE strategies. The vision

of the World Bank Group is the eradication of extreme poverty and promotion of shared

prosperity by fostering income growth of the bottom 40 percent in each country. As

education is considered essential to achieving this goal, the World Bank Education Strategy

2020 shifts the approach from an emphasis on input-driven programs to a focus on

improving learning outcomes, increasing accountability and targeting results, and

strengthening the knowledge base on education. The goals of the GPE Strategic Plan for

2016-2020 are three-fold with a focus on: (i) improving and promoting more equitable

learning outcomes; (ii) increasing equity, gender equality and inclusion; and (iii)

supporting more effective and efficient education systems. With a focus on improving

education service delivery in the most deprived areas of Ghana through decentralized

decision-making, the GPEG is well in line with the current strategic priorities of many

development actors in the education sector.

57. The Project’s relevance of objectives is rated substantial given that the Project’s

objectives were and continue to be consistent with the overall goals and sector priorities of

the Government and the World Bank.

Relevance of Design/Implementation

58. Given the country context at the time of Project design, the strong alignment with

Government priorities, and the development of GPEG and the ESP with the LEG, the areas

on which the Project focused were appropriate. These project-supported activities were

selected and designed to improve the planning, monitoring, and delivery of education

services in underserved areas in the country – in alignment with the PDO. The use of

district or school-sub grants was highly relevant given the Government and Bank priorities

to use and, in turn, to strengthen decentralized systems. Working through district and

school systems more directly supported education stakeholders and mainstreamed the

mechanisms and tools for managing service delivery. The project supported existing

processes and introduced enhancements to strengthen planning, reporting and supervision

at all levels. Project activities were highly relevant given that they all had been

piloted/taken to scale in Ghana, including the UTDBE program, use of SRCs, and provision

of district grants and school capitation grants. The choice of activities was strategic given

the original short implementation period of 3 years.

59. The Project’s targeting of “deprived districts of the Recipient’s territory” reflects

key priorities of the Government, Bank, and GPE. The Project’s design reflects the

situational analysis of wide regional disparities in poverty and human development by

enforcing a clear selection criteria for project beneficiaries. The transparent selection

criteria for districts included both the district-level poverty index (share of population

Page 30: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

20

below the poverty line), weighted at one-third, as well as education indicators (retention in

primary education, retention in the basic cycle, share of girls enrolled in P6, share of girls

enrolled in JHS3, pass rate in BECE English, and share of trained teachers in public

primary schools), weighted at two-thirds. The targeting criteria captures the social context,

individual education results, and student flow indicators of schools well, but may have

benefitted from additional information on resources available to schools in order for

targeting to take into account cost effectiveness.

60. On the basis of the information above, the Project’s relevance of design and

implementation is rated substantial.

3.2 Achievement of Project Development Objectives

61. Overall efficacy for this Project is rated as substantial. As shown in the section

below – and in greater detail in Annex 2 – the Project delivered all of the expected outputs.

At the outcome level, indicators related to all three sub-objectives of improved planning,

monitoring, and service delivery were met or exceeded. Outcomes for planning, monitoring,

and service delivery are all extremely intertwined as the achievements in education service

delivery are largely dependent on good planning and monitoring. The following section

provides an assessment of achievement by the sub-objectives of improved planning,

monitoring, and delivery of basic education services in deprived districts.

Sub-objective 1.1: Improve the Planning of Basic Education in Deprived Districts

62. The GPEG contributed to improvements in basic education planning in deprived

districts as evidenced by the successful completion of yearly district annual work planning,

school planning activities (School Performance Assessment Meetings, SPAMs, and SPIPs)

to access school grants, and more systematic in-school teacher training. Planning activities

supported by the project were implemented at the school, district, and central levels and

project reporting indicated that plans were implemented to support key education

objectives. Progress in this area is captured in PDO indicator 1 as well as Intermediate

indicators 4 and 9, all of which were exceeded. Achievement of this sub-objective is

rated as substantial.

63. At the school level, GPEG’s objective to strengthen planning was met through the

SPAMs, development and implementation of the SPIPs, and management of the school

sub-grants. At project close, 100 percent of schools in deprived districts were reported as

having completed SPIPs that had been approved by their School Management Committees

(SRCs), exceeding the Project target of 75 percent. Furthermore, the execution rate of the

school grants increased as the project progressed, from 72 percent in 2012-2013 to 88

percent in 2014-2015 and to 92 percent by project closing. This was achieved through

special assistance to head teachers in the preparation of SPIPs and close involvement of

SMCs in the preparation and approval of SPIPs. When surveyed, Circuit Supervisors

thought that the quality of SPIP preparation had improved since 2012 and over 80 percent

Page 31: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

21

of head teachers were able to show a SPIP in the official template with all fields completed

when asked.21

64. For grant activities, schools could choose activities from a pre-designed Menu of

Activities that provided a list of activities that were eligible for expenditure. The spending

of school grants was based upon a SPIP and schools were unable to access their funds if

their SPIP was not approved and signed by the Chairperson of the SMC. According to SRC

analyses, schools primarily used the grants for facilitating SMC meetings, small repairs,

building of toilets and to improve the overall school environment. A fiduciary assessment

conducted in a sample of 105 schools found that projects undertaken by the school were

inspected by the district office and the expenditure of school grant funds were tracked at

the district level. The execution rate of the funds within the same fiscal year increased as

the project progressed from 72.3 percent in 2013, to 88.0 percent in 2014, and finally to

92.4 percent in 2015/16.

65. The development and implementation of APWs and management of district sub-

grants fueled the achievement of planning objectives at the district level. District Education

Directorates were well set up to administer GPEG with 84 percent of districts having

established a technical working group; roughly half of which met at least three times per

year. The Project exceeded its target for District officers trained with over 2,250 officers

trained (of a target of 500), including 308 in reporting, monitoring, and evaluation and 329

in internal controls and auditing. Moreover, all District offices entered SRCs into the

district’s software to improve planning, exceeding the target of 70 percent. The impact

evaluation of the program found that District Directors and Circuit Supervisors, who visited

schools to observe teaching practices and provide advice on school management at the

primary level, are frequently using the GPEG funded management tools including SRCs,

SPIPs, school assessment meetings, annual training plans, and GPEG working groups.

There was a substantial increase in the number of districts which have district SRC

summaries available – from 73 percent in 2012-2013 to 99 percent in 2014-2015.

66. Ultimately, 100 percent of deprived districts disbursed 75 percent or more of their

district education sub-grants according to their APWs, exceeding the PDO-level target of

80 percent. In fact, the average total disbursement against planned activities in the APWs

was over 98 percent at Project closing. District Annual Programs of Work were created by

districts from a Ministry of Education approved Menu of Activities (included in the Project

Implementation Manual). The APWs were created in workshops wherein districts were

assisted by District Education Directorate staff, MOE and GES headquarters planning staff

and Regional Directorates and district level education statistics from EMIS were used to

inform decision making. According to APW analysis, the most popular district activity by

count and expenditure was the provision of school supplies (chalkboards, desks, chairs,

etc.) with other facility/supply related activities also ranked highly. Provision of teaching

and learning materials and gender-friendly toilet and urinal facilities were among the top

five activities by both count and expenditure. Management and training activities were

particularly popular, especially related to providing support to school grant planning and

21 GPEG District and School Grant Impact Evaluation, 2016.

Page 32: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

22

expenditure, training officers in Excel, operational expenses, and training for heads of

schools in the use of the school grant. More detailed information on district grant activities

can be found in Annex 2.

67. Achievements at the central level were also considerable with capacity-building

provided for the management of project components. The APW analysis, for example, in

which district grant activities and spending were consolidated and analyzed on a yearly

basis, allowed GES/Ministry staff to properly monitor both spending and activity choices

at the district level in line with their APWs. Quarterly workshops/meetings with district

directors contributed to the feedback loop and informed the preparation of the following

year APW. This process allowed GES/Ministry staff to both advise and ensure purchases

were of good quality and of relevance to the schools. Project reporting in GPEG was noted

as a best practice by the GPE Secretariat.

Sub-objective 1.2: Improve the Monitoring of Basic Education in Deprived Districts

68. Available data also indicate improvements in monitoring of basic education at all

levels through SRCs, district analysis and M&E reports. Achievement of this sub-

objective under the Project is rated substantial – with progress in this area captured in

PDO-level indicator 2 as well as intermediate-level indicators 1, 2, 6, 7, and 8. Out of 1

PDO-level indicator and 5 intermediate-level indicators for this sub-objective, all 6

indicators were met or exceeded.

69. At the school level, the GPEG aimed to improve monitoring through better

implementation of SRCs, which would then inform SPIPs and ultimately the use of school

grants. This was achieved with 98 percent of schools in deprived areas with up-to-date

report cards (PDO-level indicator 2) and 93 percent of schools displaying their SRCs on

public notice boards by the last year of the Project (intermediate-level indicator 6).

Improvements in the updating and utilization of SRCs were driven by the Project’s training

of 5,993 head teachers and 1,094 circuit supervisors in the utilization of SRCs

(intermediate-level indicator 1) as well as increased visits by Circuit Supervisors

(intermediate-level indicator 7). An analysis of EMIS data from 2008 indicated that circuit

supervisors visited schools more than once a year in only 77 percent of schools22. In

comparison, all GPEG schools (confirmed by district reports) were visited over 7 times per

year on average in 2016.

70. The project activities also led to improved monitoring at the regional levels (REDs).

Although compliance was low for the initial two years of the GPEG at only 13 percent in

early 2015, by the end of the Project all REDs submitted adequate reports capturing data

from all districts in their region (Intermediate Indicator 8). This was achieved through the

training of 2,288 regional and district officers on financial management, data collection,

and other key areas (Intermediate indicator 2). In addition, districts aggregated SRC results,

helping them to have consistent information about all basic education schools and

22 Analysis was conducted by WB and GES and reported in “Basic Education Beyond the MDGS in Ghana”

Balwanz and Darvas, World Bank, May 2013

Page 33: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

23

ultimately make more informed decisions about their district priorities (and APW

expenditures). The survey from the impact evaluation found that 97 percent of District

Education Directorates agreed or strongly agreed that data from the SRC had helped them

in improving girls’ school attendance by an increased focus on gender in their APW

activities. District Education Departments collating SRCs from at least 70 percent of

schools within the district (Intermediate Indicator 4) was also exceeded as 100 percent was

reported in the final year of the project.

71. At the central level, improved education monitoring of deprived districts was

evidenced through twice-yearly monitoring visits by central level staff members as well as

through the APW analysis, the incorporation of a Lesson Observation Sheet monitored by

the UTDBE IE to measure teacher performance, and the implementation of two impact

evaluations of the Project. Apart from GES/Ministry staff, there was also project

monitoring by civil society in which two independent reviews were conducted during the

life of the Project. The GPEG project generated an impressive volume of education data

which were incorporated into the annual Education Sector Performance Reports and

presented at annual NESAR events during the lifetime of the Project. Sub-objective 1.3: Improve the Service Delivery of Basic Education in Deprived Districts

72. Achievement of the sub-objective of improving basic education service

delivery in deprived districts under the Project is rated substantial. The level of

achievement of this sub-objective is determined on the basis of RF indicators met or

exceeded, impact evaluation reports for the UTDBE and grants to districts/schools,

education indicators as reported by EMIS, as well as proxy indicators from other sources.

The annual Education Sector Performance Reviews (based on annual school census data)

also confirmed improvements in basic education indicators with regard to enrollment,

trained teachers, completion and girls’ participation. As education service delivery can

encompass many different types of activities, this report will view them in terms of the

quality of teaching, quality of learning, access, and school management. All 3 PDO

indicators related to this sub-objective were achieved/exceeded. For the two intermediate

indicators, one was exceeded and the other was met through a proxy indicator for training.

73. The Project had many significant gains in terms of improving the quality of

teaching in deprived areas. The percentage of trained teachers in deprived districts

increased between 10-18 percent in kindergarten, primary, and junior high-levels between

2012-2013 and 2015-2016. While the percentage of trained teachers also increased in non-

GPEG districts, the GPEG districts received between 3-5 percentage point gains over the

non-GPEG districts allowing deprived districts to narrow the gap for this indicator. For

example, the percentage of trained junior high school teachers jumped from 72 to 82

percent in GPEG districts, compared with 87 to 92 percent in non-GPEG districts. This can

partially be attributed to the influx of 6,480 (of a targeted 5,000) teachers trained by the

UTDBE program (Intermediate indicator 3).

74. As part of an impact evaluation on the UTDBE program, a representative sample

of UTDBE teachers were observed teaching in their classrooms and rated based on their

lesson planning and preparation, teaching methodology, and classroom organization and

Page 34: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

24

management. UTDBE trainees’ scores in all three areas improved from participation in the

course and exceeded Project targets, although performance was highest at the time of the

midline survey. PDO indicator 4 measured the percentage of teachers trained who obtained

a satisfactory rating or higher in the lesson observation sheet. At midline, 87 percent of

UTDBE trainees (of a targeted 50 percent, and baseline of 69 percent) had obtained a

satisfactory rating in their lesson observation assessment.

75. Compared with traditionally trained teachers in the DBE program, UTDBE trainees

under the Project showed higher levels of content knowledge by out-performing their

Diploma in Basic Education peers in the examination results of the “Trends in Education,

School Management, and Integrated Science” course. The performance of the UTDBE

teachers in this Project is of additional significance given that these teachers are from the

local school communities and therefore speak local languages, are more integrated within

the community, and have a much higher likelihood of remaining to teach in the deprived

areas. As a result of the success of the UTDBE program through GPEG, the Government

is considering subsidizing UTDBE trainees for kindergarten teaching as this is an area with

large deficits in qualified teachers. The knowledge base of teachers was also improved in

the Project through in-service trainings (INSET) in the core strategic areas of numeracy,

literacy, and science as well as other areas such as early childhood education and gender

sensitivity. Over the course of the Project, over 94,000 INSETs were provided with at least

42,541 teachers (of a targeted 30,000) trained in at least one core INSET subject

(Intermediate indicator 3). Similarly, it is estimated that over 6,500 of basic schools in

GPEG districts participated in all INSET core courses as part of GPEG (Intermediate

indicator 5).

76. The Project showed some progress at the student learning outcome level, although

given the short project timeline it is quite unlikely that advances in student learning

outcomes would be attributable to the Project. The third PDO indicator related to the

National Education Assessment results for P3 students was achieved during the

implementation of the project in 2013, surpassing the target, [16 percent (of a targeted 15

percent) of P3 children achieved proficiency in English and 13 percent (of a targeted 11

percent) in Mathematics]. Such improvements of 29 percent for English and 44 percent for

Mathematics in NEA over the project lifetime are significant and compare favorably to

other countries in the region. Unfortunately a confirmation of further improvements in

learning outcomes through additional data at endline was not available as the 2015 NEA

was postponed to 2016 and the level of assessment was moved from P3 to P4 level. This

was an unexpected change that was communicated in the last month of the project. As

mentioned earlier, this initiative is funded by USAID and Government followed the

technical advice on improving the assessment.

77. However, Early Grade Reading Assessment (EGRA) and Early Grade Mathematics

Assessment (EGMA) for P2 students in GPEG districts between 2013 and 2015 were also

conducted during the project period (with USAID support) and confirmed that there

were statistically significant improvements in number identification, letter sounds in

English, oral reading in English, and letter sounds for local languages in the GPEG

deprived districts. The District and School Grants Impact Evaluation provides an analysis

Page 35: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

25

of the results. This study also analyzed results of the BECE23 exam (end of basic education-

grade 9), even though project effects on student performance at the end of basic schooling

would only be measurable with a much longer project duration. The results showed that

the number of students taking the exam between 2012 and 2015 increased by 26 percent in

GPEG districts in comparison to only 12 percent in non-GPEG districts. BECE pass rates

in GPEG districts have declined and the gender gap in BECE pass rates have widened in

comparison with non-GPEG districts during this time. One explanation for these results is

the effect the GPEG project has had on increasing access to education, allowing for larger

class sizes, fewer textbooks, and increased burden on teachers at that level. It would be

interesting to follow BECE results in GPEG districts over a longer time period in order to

see if those trends reverse.

78. The project outputs of improved percentage of qualified teachers in deprived

districts, in-service teacher training and the purchase of teaching and learning materials

from district and school grants contributed to improved learning outcomes observed within

the deprived districts targeted by the project. While the proportion of trained teachers has

increased nationally at all levels, the increase in GPEG districts has outpaced that of non-

GPEG districts across all levels. The rate of increase in GPEG districts is 4 percentage

points higher than the non-GPEG districts for KG, 3 percentage points higher for Primary,

and 5 percentage points higher for JHS (EMIS 2016).

79. Gains in student access and retention in GPEG districts can also be attributed, at

least in part, to the Project. The District and School Grants IE found that the Project had a

positive impact on access, in comparison with similar non-GPEG districts at the

Kindergarten, Primary, and JHS levels. For example, compared with similar non-GPEG

districts, GPEG districts saw an additional 5 percentage point increase in Kindergarten net

admission rate (NAR). The Net Enrollment Rate (NER) for Kindergarten, Primary, and

JHS improved by 17, 4, and 2 percentage points respectively more in GPEG districts than

in non-GPEG districts. In GPEG districts, dropout rates for Kindergarten increased during

the time period, while staying constant at the P5 level (and slightly decreased in comparable

non-GPEG districts) and decreased at the JHS2 level (but at a lower rate than in non-GPEG

districts). Specifically related to gender, the APW analysis of this Project shows that on

average, one-third of all district grant activities were supporting gender related-activities,

the most popular of which was providing gender friendly sanitary facilities in basic schools.

80. There is also some evidence of improvements in school management as a result of

the GPEG Project. Nearly 90 percent of head teachers reported that they provided coaching

to teachers at their school with 75 percent reporting that lesson plans were reviewed weekly.

It was also found that Lesson Observation Sheets were being used in approximately 70

percent of schools in a combination of self-evaluation and evaluation activities. According

to the APW analysis, nearly 40 percent of all district grant activities were management

related.

23 BECE is the Basic Education Certificate Examination at the end of Junior high school- a normative exam

that determines placement in secondary education.

Page 36: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

26

3.3 Efficiency

81. Overall efficiency of the project has been rated as Substantial. The findings that

are detailed below and in Annex 3 indicate that the Project benefitted from exchange rate

gains and cost effective implementation of activities, allowing the project to achieve and

exceed many of its targets.

82. In terms of efficiency of district and school grants, the analysis found that district

grants were allocated based on relative deprivation (the targeting mechanism worked). Two

district level activities (accounting for 24.81 percent of overall district level expenditure)

– construction of urinals and toilets and in-service teacher training - were analyzed and

both activities were found to be relatively cost effective in comparison with government

and other donor led initiatives in Ghana. At the school level, school grant disbursements

were found to be highly correlated with improved planning (through SPIPs) and monitoring

(through SRCs). A difference in differences analysis showed that in line with the available

literature on district and school grants, districts that received grants witnessed substantial

improvements in gross and age-appropriate enrolment (as compared to non GPEG districts

over the same period). However, not all the improvements in access can be attributed to

the project as other programs were operating in deprived districts during the same period.

In terms of efficiency of the UTDBE program, the following was determined: UTDBE and

the traditional teacher training (Diploma in Basic education, or DBE) model produce

teachers with similar skillsets though UTDBE is more cost-effective. The program has led

to a convergence in the percentage of trained teachers within GPEG and non GPEG

districts though so far, the upgrade of teacher skills has not translated into vastly improved

completion or transition rates.

83. As outlined in the PAD, to receive district grants, each district submitted an APW

which detailed their planned activities. Districts planned for activities along four cross

cutting thematic areas: Access, Quality, Gender, and Management found in a pre-approved

Menu of Activities. At the end of each year, districts reported on the progress in

implementing their activities within their APW, and were reported on actual expenditure,

timeframe and quantity. The analysis of the executed APWs reveals that districts conducted

4,983 activities over the project period. These were comprised of 76 unique activities.

84. A comparison was made between the unit cost of construction of toilets and urinals

under GPEG with identical models constructed under UNICEF and under government

procurement, an activity that accounted for 18 percent of district grant expenditure (see

Annex 3 for more details). The average cost for a 4 unit VIP was GH¢ 32,801 under

GPEG’s decentralized process as opposed to GH¢ 36,083 under UNICEF and GH¢ 40,100

under the Government’s Funds and Procurement Management Unit (FPMU). Construction

of urinals under GPEG was also found to be the most cost-efficient at GH¢ 5,665 per unit

in comparison with GH¢ 6,368 under UNICEF and GH¢ 5,950 under FPMU.

85. The cost of providing in-service teacher trainings were also most cost-efficient

using the INSET model under the GPEG. For example, under the GPEG Project the unit

cost per participant in an INSET Mathematics training was GH¢ 39.48 in comparison with

Page 37: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

27

the same training administered by the government in a non-GPEG district at GH¢ 45.8.

Cost-comparisons of INSET trainings in literacy and science followed similar patterns.

More details are available in Annex 3.

86. Analysis of the UTDBE program found the program to have an efficiency ratio of

1.6 in comparison to the traditional teachers’ diploma program, DBE. After cost sharing

with the student, the cost of the training to the program was US$2,130 in comparison with

US$3,409 per trainee in the DBE program. The attrition rate of 20.43% was also similar to

the attrition rate of the DBE program. Training UTDBE teachers has sharply increased the

percentage of trained teachers and the Pupil Trained Teacher Ratio in deprived districts.

This convergence in the percentage of trained teachers between GPEG and non GPEG

districts is likely to remain persistent as most UTDBE teachers had been teaching in GPEG

districts for several years prior to being selected for the program and have roots within the

communities in which they reside.

87. Several aspects of project design and implementation also attributed to project

efficiency include strong project targeting and focus on equity and the mainstreaming of

project activities through government systems. At the end of the project, districts were re-

ranked per the original selection criteria applied during the design of the GPEG to see

whether deprived districts have changed in ranking. Using the more updated indices, 57

of the 75 GPEG districts remain in the top 75 most deprived districts (or bottom third of

the 216 districts). However, 18 districts (24% of the original deprived districts) can be

considered to have transitioned from the deprived districts list.

88. To summarize, the GPEG project was able to successfully complete all project

activities within a 3 and half-year period. Internal and external audits concluded that district

and school funds were used for their intended purposes and in an efficient and cost-

effective manner. Component level expenditure was in line with the budgetary allocations

made during appraisal and cost savings from currency depreciation were redirected towards

increased allocation for district grants.

3.4 Justification of Overall Outcome Rating

89. Rating: Satisfactory. Given the Project’s substantial ratings in Relevance,

Efficacy, and Efficiency, the overall outcome rating of Satisfactory is appropriate.

Project Relevance Achievement of PDO

(Efficacy)

Efficiency Overall Rating

Substantial Satisfactory Substantial Satisfactory

3.5 Overarching Themes, Other Outcomes and Impacts

(a) Poverty Impacts, Gender Aspects, and Social Development

90. Largely a result of the targeting mechanism that took into account poverty and

education outcomes, the GPEG Project has meant better education opportunities for

children in the most deprived areas of Ghana. As a result of the Project, children from

Page 38: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

28

GPEG districts have improved access to education and an improved school environment

and there are significantly more trained teachers then prior to the project. Since some of

their trained teachers are graduates of the UTDBE program – it is likely that teachers will

speak their local languages and remain teaching in these communities far longer than other

trained teachers at the school. In addition to funding teacher training, the school and district

grants were used to rehabilitate school infrastructure, such as bathrooms, making it easier

for girls to remain in school.

91. The complementarity of the DfID-funded GPASS program24 and the GPEG project

further supported and enhanced achievements under the GPEG operation, particularly with

regards to increasing girls’ access to and retention in schools. The decline in girls’ dropout

rates at the JHS level in GPEG districts outweighed the decline observed in comparable

non-GPEG districts. This may be due in part to the GPEG as well as to the GPASS program

which covered, among other costs (school fees), sanitary and other personal items needed

for girls to remain in school. The Gender Parity Index (GPI) for GPEG districts was

maintained at the kindergarten level, slightly decreased at the primary level, and increased

at the JHS level.25

92. As a result of the systematic school performance improvement planning and school

grant implementation, SMCs were re-energized under the GPEG. While SMCs existed in

most schools across Ghana, their functionality varied widely. The School Grant manual

and SPIP process (planning, sign-off and vetting of the plans) promoted more active

engagement of SMCs in the schools in deprived districts. As mentioned before, a 2010

World Bank survey had found that SMC members did not have enough information about

their roles and responsibilities or about SPIP and SPAM mechanisms. The GPEG aimed to

address this by supporting training for all project SMCs given their key role in designing,

vetting and ultimately approving the SPIP (a requirement for any school to receive a grant

under the Project).

(b) Institutional Change/Strengthening

93. By using the existing government structures and building capacity at the district

and school levels, the Project has strengthened management procedures and mechanisms

at the decentralized levels. GPEG has directly supported the Government’s

decentralization agenda and the 75 participating GPEG districts now have a much stronger

capacity in key functional areas, including budgeting, planning, and monitoring. For

example, district staff are able to effectively carry out supervision and monitoring of

activities, including capitations grants, and are able collate and evaluate SRCs and generate

their APWs. This is likely to continue to have an impact beyond the GPEG Project with

potential spillovers into other sectors. Furthermore, the graduation from deprived category

24 The scholarship program, spanning from 2013 to 2018, was designed to target 55,000 needy girls in the 75

deprived districts. In the 2016-17 academic year an additional 5,000 JHS3 girls will receive a scholarship

package, bringing the total number of beneficiaries to 60,000 JHS girls. 25 As the GPASS program is still underway, an impact evaluation of the GPASS program in 2018 will help

to better understand achievements in attracting and retaining girls in GPEG districts.

Page 39: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

29

of 18 GPEG districts out of the 75 deprived districts in Ghana speaks to the institutional

growth in those districts during the life of the GPEG Project.

94. Targeting for the Project had a lasting impression on Ministry staff. With a

substantial risk of political influence in the selection of districts for the Project, it was

important that the targeting be transparent and fully owned by the Government. In

interviews for this ICR, Ministry staff were proud of the targeting mechanism for GPEG

because it used clear education and poverty indicators as criteria for selection. Joint

ownership of the process has allowed the Government to continue to use a robust targeting

mechanism in other projects, such as SIEP and the USAID supported Ghana Partnership

for Education Project. The policy discussions on the new ESP (2016-2030) and new

programs includes more debate about equity and targeted interventions than had previously

been considered during the 2010 ESP.

95. Capacity-building at the central level of the MoE has further facilitated the

preparation and implementation of other large projects. The Ministry and GES have

negotiated several large new programs since the GPEG rollout. Central Ministry staff

reported that their experience under the GPEG Project was useful in the efficient

preparation of the PIM for the SEIP.

(c) Other Unintended Outcomes and Impacts (positive or negative)

96. An unintended positive impact has been the interest generated by the NGO/CSO

community to track grant financing and independently review district and school grant

activities. During the GPEG, there were several reviews conducted (GNECC 2013 and

SEND Ghana 2015) that verified grant allocations, utilization, and community satisfaction.

3.6 Summary of Findings of Beneficiary Survey and/or Stakeholder Workshops

97. A Beneficiary Survey was undertaken with key stakeholders involved in the Project

and a Stakeholders Workshop was held on September 28, 2016. A summary of the results

of each activity are presented in Annexes 5 and 6.

4. Assessment of Risk to Development Outcome

Rating: Moderate

98. The risk to development outcome is rated moderate for a number of reasons. First,

the mainstreaming of activities into government systems allows for Project activities to

continue beyond the life of the GPEG Project. However, the fiscal crisis slowed growth

and reduced revenues that had been anticipated for continuation of district and school

grants and elections in late 2016 made it difficult to forecast funds available for education

without an approved budget. The financial cost of continuing the school and district grants

in the deprived districts is estimated at US$19.3 million annually26. The government has

26 No school grants have been disbursed in 2016 apart from the preexisting Government-funded capitation

grant (of approximately US$0.49 per student per semester).

Page 40: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

30

no plans to increase the capitation grants provided to schools or increase district grants,

leading to no recurrent fiscal implications for the government. Nevertheless, because

GPEG was embedded within existing Government systems and not through a Project

Implementation Unit, many of the outcomes and gains can be maintained in the post-

project phase. A sustainability forum was held in February 2016 to discuss and determine

which GPEG-funded activities could be continued beyond the life of the Project with

minimal or no external funding. At the school level, SPAMs are now functioning and

districts are able to enforce the preparation of SPIPs regardless of the level of funding in

terms of school grants. However, there is real concern that continued delay in the release

of the capitation grants will make it difficult for schools to implement their annual

performance plans. While the scale and timeliness of grants are much more uncertain after

the closing of the GPEG, with the systems established by GPEG, any mobilization of

resources could be quickly channeled to schools. Moreover, districts are equipped to collate

and evaluate SRCs and generate their APWs based on the needs of their districts. At the

central level, MoE and GES institutions have been strengthened and staff are well versed

in project targeting, M&E, and reporting which will continue to enhance management.

99. Additionally, some elements of GPEG are already being expanded by other donors.

The strong collaboration and wider ownership of the GPEG project amongst development

partners has led to the continuation of scholarships for girls in GPEG districts through 2017

(DfID) and the introduction of more efficient mobile monitoring tools for local level

activities (USAID and UNICEF). That being said, there are sustainability concerns around

the GPASS program as survey results have indicated that most of the GPASS girls are

unlikely to be able to afford Senior high school education and continue their education

beyond the GPASS scholarship27. The Bank-supported Secondary Education Improvement

Project (funded with an IDA credit of US$156 million) is working to link the scholarship

recipients from the GPASS with the scholarship program under the SEIP.

100. The high turnover of district staff and teachers who have been trained raises some

sustainability concerns, while the UTDBE program shows great promise for retaining

qualified teachers in underserved areas. Results from the IE showed that one-fourth of

District Directors were a year away from retirement. With the median age of District

Directors at 57 years old, skills gained by these district staff will be lost to the districts

unless proactive steps are taken for refresher trainings and transfer of skills to new staff

members. At the school level, the IE found that Head Teachers trained by GPEG have been

at their post for an average of 3 years. Because teachers may not be keen to remain at

remote posts, and/or as head teachers are close to retirement, it is expected that some of the

school-level institutional strengthening will be lost when Head Teachers either retire or

transfer out to schools in non-deprived areas of the country. On the other hand, the Project

demonstrated that the UTDBE-trained teachers are of similar quality to DBE teachers. The

large number of UTDBE teachers trained under the GPEG Project are not only more cost-

effective, but they are able to provide mother-tongue instruction, and are bonded to their

27 This situation may change with the introduction of free senior high school education currently proposed

by the new Government to commence September 2017.

Page 41: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

31

schools for 4-6 years following the program with a high likelihood of staying longer due

to personal ties to the community.

5. Assessment of Bank and Borrower Performance

5.1 Bank Performance

(a) Bank Performance in Ensuring Quality at Entry

Rating: Highly Satisfactory

101. The Bank’s performance in ensuring quality at entry is rated Highly Satisfactory

based on the following:

a. The PDO was highly relevant and remained so throughout the Project, as discussed

in Section 3. The PDO was well aligned to Ghana’s ESP, the Bank’s CPS, and GPE

strategies. While the focus was on processes and less on learning outcomes, the

project tried to incorporate assessment of quality by tracking performance for the

deprived districts on the NEA as well as the EGRA/EGMA instruments.

b. The preparation task team incorporated lessons learned from previous GPE grants

in Ghana, the recently closed EdSeP, other donor funded programs and

comprehensive analytical work under the ESP. The GPEG built upon programs that

had already been piloted in Ghana and further strengthened their implementation

with additional capacity-building and adopted objective criteria to support pro-poor

targeting. The preparation team also incorporated the guidance received through

the QAR and QER in 2011. Technical aspects of the Project were well developed

and appropriate for the sectoral, institutional, and policy context in Ghana. The

Bank team benefitted from extensive quality assurance through the ESP preparation

and the GPE application process. The additional support from DPs included

additional studies conducted by USAID and DFID with regard to M&E systems

and gender issues respectively.

c. The strong engagement with the country partners (including the LEG) and the

strategic decisions to mainstream project management facilitated excellent

collaboration. Parallel systems were not established, thereby strengthening the

existing systems, capacities and roles of key education agencies.

d. M&E arrangements designed for the Project were strong, with very rich and diverse

M&E data, from both internal and third-party sources, built into GPEG design. The

comprehensive project implementation manual included sample templates for all

monitoring activities to help guide implementation.

e. Risks identified at entry were appropriate, and the mitigation measures proved to

be adequate.

f. Fiduciary and social and environmental aspects of the Project were well designed

with extensive guidance included in the project implementation manual, school

grants manual and Environmental and Social Management Framework.

Page 42: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

32

(b) Quality of Supervision

Rating: Satisfactory

102. The Bank’s performance with regards to quality of supervision is rated Satisfactory

based on the following:

a. The Bank team possessed an appropriate skills mix (education, fiduciary,

environmental and safeguards expert, procurement) for supporting and supervising

the Project. Joint missions (with the LEG and Government) were conducted

regularly and Bank staff was commended for their availability to support GPEG.

There was minimal staff turnover allowing for enhanced continuity. The same Bank

team prepared, implemented, and closed the project. The team received consistent

and constructive support from the country office, in particular from the country

management and fiduciary/safeguards staff. A generous preparation and

supervision budget provided by the GPE contributed to the ability of the team to

mobilize support on an as needed basis.

b. Risks and implementation issues were identified and addressed in a proactive

manner, and highlighted and discussed in detailed supervision documentation (e.g.

Implementation Status Reports, Aide Memoires, MTR report). Project ratings were

realistic and in line with implementation progress. The Bank team maintained a

strong focus on the achievement of the PDO throughout the life of the Project. The

Bank team was commended in the Government’s Project Completion Report (PCR,

a summary can be found in Annex 7) for securing all approvals (e.g. for IFRs, no

objections, work plans, budgets, etc.,) with minimal delays and for prompting the

Government to submit relevant documentation at the appropriate time. Reacting to

Project needs, the Bank provided intensive support during the first year of the

Project, as seen in supervision missions and costs) to ensure the Government was

ready to implement. The Bank also supported regular communication with the

Government by supporting the establishment of a videoconference facility within

the MoE.

c. The Bank team was of significant support in helping the Ministry overcome

capacity challenges in managing the school and district grant IE. Nevertheless,

additional attention to RF calculations and reporting during supervision missions

may have prevented some challenges in reporting.

d. The Bank worked with a number of the other DPs – including working closely with

the LEG while also benefitting from GPE Secretariat support and advice throughout

project supervision. As mentioned previously, the degree of local donor

involvement in GPEG preparation and supervision was greatly appreciated by the

Government.

(c) Justification of Rating for Overall Bank Performance

Rating: Satisfactory

Page 43: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

33

5.2 Borrower Performance

(a) Government Performance

Rating: Satisfactory

103. Overall, the Government demonstrated a high level of commitment to the

achievement of the PDO as well as ownership of activities supported under the Project. At

the design stage, the Government helped facilitate the targeting mechanisms for the Project,

allowing GPEG to be truly focused on supporting the most underserved areas of the country

without political interference. The Government also helped ensure that Project preparation

and appraisal were jointly conducted with the LEG to ensure that the GPEG was well

aligned with ongoing and new commitments of development partners. During

implementation, the Ministry maintained close oversight of the Project and met regularly

with the local Bank team and during missions. GPEG was reported on at monthly LEG

meetings. Four Government-led NESARs were held during the Project period and GPEG

was also highlighted in the Government’s annual ESPR. A Project Steering Committee

including the Ministries of Finance and Local Government and Rural Development

provided additional oversight to GPEG, although they did not meet as frequently as

expected, with only four meetings during the Project lifetime.

104. The Ministry of Finance was supportive of GPEG and ensured a quick turnaround

on legal and formal requests to the Bank. However, the delayed disbursement of capitation

grants throughout the project period reduced the ability of the school grants to be

supplementary.

(b) Implementing Agency or Agencies Performance

Rating: Satisfactory

105. The main implementing agency was the MoE and GES. Within the MoE and GES,

various department were responsible for specific activities and the PBME unit played an

overarching role in coordination and data collection and analysis. FM and Procurement

were handled by units within MoE and GES. Overall, MoE/GES demonstrated strong

commitment and a high level of ownership of GPEG with the Project embedded within

MoE systems. A Project Coordinator was appointed by GES to work across all of the

implementing agencies and reported to the Director General of GES. The Director of the

Teacher Education Division (TED) was responsible for management and reporting on

UTDBE and INSET. In its role as implementing agency, MoE and GES achieved the

following:

a. Disbursed 80 percent of all Project funds and delivered on nearly all Project

activities within the original 3 year period. The project extension of 10 months

allowed for disbursement of remaining project funds and delivery of all planned

assessments.

b. Development of the PIM which remained a reference document throughout the

GPEG project at headquarters, district, and school levels.

c. Compliance with Bank’s fiduciary and safeguards requirements.

Page 44: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

34

d. Effectively verified, analyzed and reported on extensive data collected from the

Regions and third-parties as well as conducted their own analyses (APW analysis,

beneficiary study, SRC analysis, etc.). The sheer quantity of monitoring and

evaluation data provided strong feedback loops and detailed analysis. The team also

created four GPEG documentaries which are available on the GPE website.

e. Proactively identified, resolved, and reported implementation challenges during the

Project. In particular, GES is commended for quarterly meetings with district

officers to check and discuss project activities and status report of the districts, as

well as the high quality project status reporting by the Ministry prior to

implementation support missions.

f. The GES and MOE provided comprehensive annual status reports on GPEG

implementation, organized joint supervision missions with the LEG, conducted

annual NESARs, and published annual ESRPs which included special

disaggregation for GPEG districts.

106. MoE and GES performed consistently well during the lifetime of the Project, with

only some minor shortcomings in M&E. These shortcomings included identifying and

addressing challenges in calculating a few RF indicators (teachers trained under INSET,

P3 student outcomes with the switch of NEA to measure P4 achievement) prior to the end

of the GPEG and handling of the district and school grant impact evaluation procurement

to avoid a de-scoping of the evaluation design.

(c) Justification of Rating for Overall Borrower Performance

Rating: Satisfactory

6. Lessons Learned

107. Lessons learned from previous projects can play an important role in

designing and implementing a short three-year project. Building on lessons learned

from the prior EFA-FTI grants and the Bank-supported EdSeP allowed smooth and

expedited transition/uptake of the GPEG Project. GPEG’s decentralized model worked

well because it had benefitted from piloting under the EdSeP. Capacity building under

EdSeP and other DP supported operations helped ensure institutional readiness. The

inclusion of a lessons learned annex in the PAD (with evidence from other countries as

well) also informed the design of the activities. Most importantly, the GPEG focused on

the piloted and field tested activities. GPEG PDO-level and intermediate indicators

were realistic and consistent with the Project timeframe.

108. GPEG capitalized on the consistency of political leadership. The Education

Minister and other key policymakers remained constant throughout GPEG preparation and

implementation. The Minister of Education was appointed just prior to the GPEG launch

and participated in the closing workshop of the project held in September 2016. Since there

was no parallel structure established to manage the GPEG, the responsibilities were

embedded within the structures of the MOE and GES. Therefore, at the technical levels

there also was minimal turnover of staff.

Page 45: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

35

109. Strong project ownership and accountability can be strengthened by

embedding the project in regular processes and within the government system. The

level of ownership of the Project by the Government and stakeholders can play an

important role in determining an operation’s overall success and long-term impact. The

beneficiary assessment acknowledged the success of the GPEG Project in empowering the

existing systems and helping to make them better functioning. Further, the capacity-

building under the GPEG Project followed a “learning by doing” approach which allowed

for more direct involvement of the stakeholders. The implementation arrangements were

further influenced by past challenges when responsibilities were not in direct correlation

to roles of the government agencies. For example, under previous projects, (e.g., EdSeP)

implementation often faced challenges because the Ministry of Education was tasked with

implementation, yet is not set up for playing such a role. Under the GPEG, the bulk of

implementation rested with the GES which has the mandate for implementation

particularly at the local level. GPEG also aimed to strengthen the decentralized system by

empowering the Regions and Districts as they were critical in supporting the collection and

collation of data.

110. More investments in project preparation can lead to subsequent efficiency

savings through enhanced cooperation between the Bank, the Government and donor

partners. Significant analytical work conducted just prior and during GPEG preparation

provided a strong technical foundation for the selected activities. GPEG was also greatly

advantaged by consistent Bank support and adequate preparation and supervision

budgets. During the project preparation phase of GPEG, audio conference meetings were

held weekly, which ensured that all stakeholders were aligned and roles and responsibilities

was clear, leading to smooth flow of disbursements throughout the project period.

111. Investing in engagement with donor partners can lead to greater synergies

between donor efforts and the project. For example, cooperation with DFID during

project preparation led to the Girls PASS program prioritizing the GPEG deprived districts

for the JHS scholarship and enhanced cooperation in monitoring and supervision. Joint

supervision missions allowed for greater engagement among development partners around

GPEG objectives.

112. Through transparent and objective targeting of deprived districts, incentives

can be shifted to allocate resources where they are most needed. Despite initial

concerns about political capture of district selection, the scientific approach of using

poverty and education indicators as criteria in the selection and targeting of districts

received full political support and was a source of pride at project closing.

113. Expenditure tracking at the district and school level can provide valuable

information on education needs at the decentralized level. The project was able to

collect detailed information on district and school expenditure priorities in the deprived

districts and whether actual expenditures were in line with the budgeted amounts. Apart

from improving capacities in decentralized forecasting, this information on expenditure

priorities is useful to the Ministry and for academic research.

Page 46: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

36

114. The UTDBE program is a cost-effective alternative to the DBE teacher

diploma program and holds the most promise for increasing the numbers of trained

teachers in underserved areas. The impact evaluation found that UTDBE-trained

teachers perform at similar levels as conventionally trained teachers, but with a significant

cost savings to the Government. UTDBE teachers are from local school communities and,

therefore, speak local languages, are more integrated within the community, and have a

much higher likelihood of working and remaining in the deprived areas of the country.

115. Systems need resources and strong M&E to work. The Project had a rich variety

of internal and external data sources to measure the project’s performance and to identify

challenges. GPEG made significant improvements to the frequency and quality of M&E in

the system and strengthened supervision at the school and district levels. It is equally

critical that adequate financial resources are provided to carry out the responsibilities and

activities required within the M&E system.

7. Comments on Issues Raised by Grantee/Implementing Agencies/Donors N/A (a) Grantee/Implementing agencies

(b) Cofinanciers/Donors (c) Other partners and stakeholders (e.g. NGOs/private sector/civil society)

Page 47: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

37

Annex 1. Project Costs and Financing

(a) Project Cost by Component (in USD Million equivalent)

Components Appraisal Estimate

(USD millions)

Actual/Latest

Estimate (USD

millions)

Percentage of

Appraisal

Sub-Grants to Deprived Districts 42.36 48.41 114.3

School Sub-Grants 22.06 20.38 92.4

Project Management and

Institutional Strengthening 4.58 6.71 146.5

Total Baseline Cost 69.0 75.5

Physical Contingencies 3.25 0.00

Price Contingencies 3.25 0.00

Total Project Costs 75.5 75.5

Total Financing Required 75.5 75.5

(b) Financing

Source of Funds Type of

Cofinancing

Appraisal

Estimate

(USD

millions)

Actual/Latest

Estimate

(USD

millions)

Percentage of

Appraisal

Global Partnership for Education

Program Grant 75.5 75.5 100

Page 48: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

38

Annex 2. Outputs by Component

1. According to the Ghana Partnership for Education Fund Grant Agreement, the

Project Development Objective (PDO) was to improve the planning, monitoring, and

delivery of basic education services in deprived districts of the Recipient’s territory

(Ghana). The PDO as described in the PAD is identical. There were a total of 5 PDO

indicators and 9 intermediate indicators at Appraisal. Project restructuring had no effect on

indicators or targets.

2. The PDO was not revised during the lifetime of the project. There were two minor

restructurings of the project in 2013 and 2015 in order to add works category to the district

grants (2013), extend the project closing date by ten months and introduce reallocation of

funding among expenditure categories (2015). The project consisted of three components

with a total project cost of $75,500,000. In 2014, a re-delineation of districts in Ghana

increased the number of project districts for GPEG to 75. This did not alter the project

target group as the 18 new administrative offices were carved out of the original 57 targeted

districts. There were no major changes in the components and only minor changes in

project activities and allocations across categories.

3. Reallocation of Proceeds. The allocation of loan proceeds from the second

restructuring was revised as follows:

Category of Expenditure Allocation % of Financing

At Appraisal Revised

Goods, non-consultants’

services, consultants’ services,

Training and Operating costs

under the Project (other than

for Sub-grants)

19,700,000.00 14,936,759.52 100%

Goods, works, and services

for Sub-projects to be

financed out of the proceeds

of District Sub-grants

27,300,000.00 38,941,702.00 100%

Goods, works, and services

for Sub-projects to be

financed out of the proceeds

of School Sub-grants

22,100,000.00 21,621,538.48 100%

UNALLOCATED

(contingencies) 6,400,000.00 0.00

Designated Account 0.00 0.00

Total: 75,500,000.00 75,500,000.00 75,500,000.00

4. Activities and their relationship to the PDO. The Project activities were selected

and designed to improve the three sub-objectives of planning, monitoring, and education

service delivery in deprived districts of Ghana. See Figure 1 below for examples of key

GPEG activities and how they fit with the sub-objectives.

Page 49: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

39

Figure 1: Activities and their Relationship to the PDO

Component 1: Sub-Grants to Deprived Districts to support key education objectives

5. The goal of this component was in line with the PDO’s sub-objectives of- planning,

monitoring, and delivery of basic education services in deprived districts. At Appraisal,

this component was to provide annual non-salary resources to 57 deprived districts as a

supplement to existing resource flows, support districts’ annual programs of work and

government strategic priorities under the ESP and AESOP. This included district grants to

fund activities related to the four key policy areas of (i) equitable access and participation,

(ii) gender, (iii) teaching and learning quality, and (iv) management of education service

delivery, as well as the upgrading of 5,000-8,000 untrained teachers in those districts. To

complement this component and harmonize with GPEG, DfID provided parallel grant

funding of US$10 million for girls’ education packages (scholarships for JHS students,

girls network/mentoring, capacity building for district girl education officers) in the same

GPEG districts. Under the second restructuring, additional funding was allocated to the

district sub-grants from unallocated funds (contingencies) as well as from exchange rate

savings and a reduced number of teacher trainees in the UTDBE program. The additional

funding increased district grant support and in particular, start up expenditures for the

newly created districts. Tables 1 and 2 highlight achievements of results and outputs under

Page 50: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

40

Component 1.1 and 1.2, respectively, organized by the sub-objectives of improved

planning, monitoring, and education service delivery.

Table 1: Achievements of Results and Outputs under Component 1.1 – District Sub-

Grants

Results and Outputs

PD

O-l

evel

ind

ica

tor

Inte

rmed

iate

ind

ica

tor

Comment on Indicators

Planning

75 districts drafted, finalized, and implemented

APWs.

100% of deprived districts disbursed more than 75%

of their district education grants as planned in their

APW

X At appraisal, the end target was 80%

PDO-level indicator exceeded

DEDs collating SRCs from 100% of schools within

the district

X At appraisal, the end target was 70%

Intermediate indicator exceeded

Average total disbursement of district education

grants as planned at 98.6%

GH125,945,572 spent on APW activities by deprived

districts

Monitoring

5,993 head teachers trained on school report cards

1,094 Circuit supervisors trained on school report

cards

X At appraisal, the end target was 6,930

head teachers and Circuit

Supervisors trained on school report

cards

Intermediate indicator exceeded

1,568 officers trained on ADEOP and school report

cards

308 regional and district officers trained in reporting,

monitoring and evaluation

329 regional and district officers trained in internal

controls and auditing

X At appraisal, the end target was 500

district education officers trained

under the project

Intermediate indicator exceeded

Service Delivery

1,059 activities (44% of total expenditure) conducted

related to equitable access

639 activities (20% of total expenditure) conducted

related to bridging the gender gap

1,878 activities (17% of total expenditure) conducted

related to improving management of education service

delivery

1,407 activities (19% of total expenditure) conducted

related to improving the quality of teaching and

learning.

Page 51: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

41

889 district gender officers trained in guidance and

counseling

94,827 INSET teacher trainings (cumulative

throughout the Project)

28,056 teachers trained in core INSET Math

14,485 teachers trained in non-core INSET

(Kindergarten, Gender)

X At appraisal, the end target was

30,000 teachers trained under INSET

Intermediate indicator met through

proxy calculation

Table 2: Achievements of Results and Outputs under Component 1.2 – Teacher

Development and Skill Upgrading

Results and Outputs

PD

O-l

evel

ind

ica

tor

Inte

rmed

iate

ind

ica

tor

Comment on Indicators

Planning

More cost effective teacher training program

implemented

Service Delivery

75.7% of UTDBE-trained teachers obtained a

satisfactory rating or higher in the LOS

X At appraisal, the end target was 50%

PDO-level indicator exceeded

6,480 unqualified teachers upgraded their skill sets

through the UTDBE training program

X At appraisal, the end target was 5,000

UTDBE teachers trained under the

project

Intermediate indicator exceeded

Percentage of trained teachers in deprived districts

increased between 10-18 percent in KG, Primary, and

JHS between 2012-2013 and 2015-2016.

6. Achievement of Component 1 PDO Indicators:

The project successfully met the target of this PDO indicator – Deprived districts

disbursing 75% or more of their district education grants as planned in their APW.

At project closing, 100% of deprived districts had disbursed 75% or more against

planned activities, exceeding the end target of 80%. In fact, the average total

disbursement was 99% against planned activities in the APW.

The project also successfully met the target of this PDO indicator – Teachers trained

under the project in deprived districts who obtain satisfactory rating or higher in

the SBI/CBI lesson observation sheet for lesson planning, teaching methodology,

and classroom organization and management. While midline scores were higher

overall than endline scores, endline scores were still improvements from both pre-

project scores and the project baseline scores (conducted in year 2) and higher than

the target of 50%.

Page 52: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

42

While not listed as an indicator in the results framework, the increase in percentage

of trained teachers in the deprived districts is a natural PDO-level indicator under

this component. The school and district grant IE provides some key figures on this.

The percentage of trained teachers in deprived districts increased between 10-18

percent in kindergarten, primary, and junior high-levels between 2012-2013 and

2015-2016. While the percentage of trained teachers also increased in non-GPEG

districts, the GPEG districts saw greater gains (3-5 percentage points higher)

allowing deprived districts to narrow the gap in this indicator. In addition, the

percentage of trained junior high school teachers jumped from 72 to 82 percent in

GPEG districts, compared with 87 to 92 percent in non-GPEG districts.

7. Table 3 below shows the most popular activities executed within a year by count.

The ten most popular activities account for 51.9% of the total number of activities selected

across all districts. Note that many of these were mandatory activities.

Table 3: APW Most Popular Activities Executed by Count

Code Activity Count Proportion

A2 Provide schools with essential supplies - chalkboards, mono desks, dual

desks, teacher’s tables, chairs, cupboards, KG furniture etc.

337

7.1%

Q9 Provide teaching and learning materials, learning kits etc. 335 7.0%

M11 Monitor and support school grants planning and expenditure 306 6.4%

A4 Provide gender friendly sanitary facilities in basic schools (Urinals and

toilets)

301 6.3%

Q1 Organize INSET – Mathematics, Science & Lit 278 5.8%

M27 Provide operational expenses 267 5.6%

M3 Conduct training for Head teachers on the use of school grants 211 4.4%

Q15 Organize School Appraisal Meetings (SPAMs) at the district level 155 3.3%

M5 Train district officers in Excel forecasting etc. 141 3.0%

M16 Conduct regular school inspection and disseminate reports in a timely

manner

138 2.9%

TOTAL 2,469 51.9%

TOTAL FOR ALL ACTIVITIES 4,758 100%

8. Table 4 below presents the most popular activities executed within a year by

expenditure. The top ten most popular activities by expenditure account for 79.32% of the

overall budget, with the top three alone accounting for nearly 50% of the overall

expenditure in a given year. All of the top three activities were procurement related and

hence it is reasonable to expect higher costs for these activities. Other activities that were

popular were the mandatory activities including INSETs and trainings for Head teachers.

Page 53: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

43

Table 4: APW Most Popular Activities Executed by Expenditure (Ghana Cedis)

Code Activity Expenditure Proportion

A2 Provide schools with essential supplies - chalkboards, mono

desks, dual desks, teacher’s tables, chairs, cupboards, KG

furniture etc.

24,236,945 20.10%

A4 Provide gender friendly sanitary facilities in basic schools

(Urinals and toilets)

21,730,847 18.02%

A13 Provide material support to children who are orphaned in order

for them to complete their education

12,388,831 10.28%

Q1 Organize INSET – Mathematics, Science & Lit 8,181,657 6.79%

Q9 Provide teaching and learning materials, learning kits etc. 8,155,606 6.76%

M11 Monitor and support school grants planning and expenditure 7,051,981 5.85%

A1 Rehabilitate school buildings – minor repairs 4,461,588 3.70%

M31 Start Up Costs 3,805,586 3.16%

M3 Conduct training for Head teachers on the use of school grants 3,033,697 2.52%

Q15 Organize School Appraisal Meetings (SPAMs) at the district

level

2,586,374 2.15%

TOTAL 95,633,111 79.32%

TOTAL FOR ALL ACTIVITIES 120,571,004 100.00%

9. Achievement of intermediate Indicators under Sub-Component 1.1: There were

three intermediate indicators linked to the sub-grants to deprived districts which were all

met and surpassed: (i) Head teachers and circuit supervisors trained in the use of School

Report Cards; (ii) Regional and District Education officers trained under the project; and

(iii) DEDs collating School Report Cards from at least 70% of schools within the district.

At project closing, 5,993 Head Teachers and 1,094 Circuit Supervisors were trained,

exceeding the target of 6,930. A total of 2,457 Regional and District officers were trained

under the project, far surpassing the end target of 500. And 100% of DEDs had collated

SRCs, exceeding the target of 70%. A fourth intermediate indicator, number of teachers

trained in INSET, is linked to Sub-Component 1.1. While this indicator was not properly

tracked throughout Project implementation (trainings rather than persons trained were

counted), proxy measures of the number of Mathematics INSETs conducted (28,056)

allows for some assurance that the indicator was close to being met, if not met and exceeded.

10. Achievement of Intermediate indicators under Sub-Component 1.2: At project

closing, 6,480 teachers (of 7,800 initially enrolled) completed the UTDBE training,

surpassing the minimum target of 5,000.

Component 2: School Sub-Grants

11. The goal of this component was in line with the PDO sub-objectives of improving

planning, monitoring, and delivery of basic education services in deprived districts. At

Appraisal, this component was expected to improve teaching and learning through

supplements to the capitation grants at all basic education schools in deprived districts. The

component would improve the management and accountability of resources at the school

level and strengthen the SPIP process and community engagement. Component 2 funded

training on the school grant process, monitoring visits, communication campaigns, and the

Page 54: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

44

school grant itself. Table 5 highlights the achievements of results and outputs under

Component 2 within the sub-objectives of improved monitoring and education service

delivery.

Table 5: Achievements of Results and Outputs under Component 2 – School Sub-

Grants

Results and Outputs

PD

O-l

evel

ind

ica

tor

Inte

rmed

iate

ind

ica

tor

Comment on Indicators

Monitoring

98% of schools in deprived districts with up-

to-date SRCs

X At appraisal, the target was for

75% of schools to have updated

SRCs

PDO-level indicator exceeded

93% of schools received and displayed the

most recent SRC on their notice board

X At appraisal, the target was for

75% of schools to have

displayed their most recent SRC

on their notice board.

Intermediate indicator exceeded

Service Delivery

Approximately 98% of basic schools in

deprived districts participating in all INSET

core courses

X At appraisal, the target for this

indicator was 65%

Intermediate indicator exceeded

1,991,030 estimated beneficiaries reached, of

which 48% are female.

X At appraisal, the end target was

1.6 million direct project

beneficiaries, of which 40% are

female.

PDO-level indicator exceeded

16% of P3 students achieving proficiency in

English

13% of P3 students achieving proficiency in

Mathematics

X At appraisal, the end targets

were 15% in P3 English and

11% in P3 Mathematics

PDO-level indicator using

midline data.

12. Achievement of Component 2 PDO Indicators: The project successfully exceeded

the targets of these PDO indicators::

The PDO indicator –Public basic schools in deprived districts with up-to-date SRCs.

At project closing, 98% of schools had an up-to-date report card according to

School Grant Reports, exceeding the end target of 75%.

The PDO indicator – P3 Students achieving improved proficiency in English and

Math in deprived districts was achieved. The 2013 NEA results listed P3 English

scores at 16%, exceeding the end target of 15%, and P3 Mathematics scores at 13%,

above the end target of 11%. Just prior to project closing, the 2016 NEA had

switched to collecting proficiency scores for P4 Math and English, for which there

Page 55: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

45

were no project targets set for baseline and closing. EGRA and EGMA for P2

students in GPEG districts between 2013 and 2015 confirmed that there

were statistically significant improvements in number identification, letter sounds

in English, oral reading in English, and letter sounds for local languages in the

GPEG deprived districts.28

The PDO indicator – direct project beneficiaries reached was exceeded with an

estimated 1.9 million beneficiaries at project closing, 300,000 more beneficiaries

than the project target of 1.6 million. It is estimated that the project beneficiaries

comprised of roughly 912,000 females, or 48% of the total, exceeding the project

target of 40%.

The intermediate indicator – basic schools in deprived districts participating in all

INSET courses supported under the project was achieved with an estimated 98% of

the required INSET carried out. While this is a proxy calculation, it still exceeds

the project target of 65%.

The intermediate indicator – schools that have received and displayed the most

recent SRC on their notice board – exceeded its end target of 75% with an estimated

93% of schools displaying their SRC.

Component 3: Project Management and Institutional Strengthening

13. The goal of this component was in line with the PDO’s sub-objectives of improved

planning and monitoring in deprived districts. The purpose of this component was to

strengthen government systems for the implementation and supervision of decentralized

education services in the deprived districts. This component funded consultancy services,

training and operational costs, materials, IEs, and external and internal audits. Table 6

displays the achievements of results and outputs under Component 3 within the sub-

objectives of improved planning and monitoring.

28 GPEG District and School Grant Impact Evaluation, 2016.

Page 56: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

46

Table 6: Achievements of Results and Outputs under Component 3—Project

Management and Institutional Strengthening

Results and Outputs

PD

O-l

evel

ind

ica

tor

Inte

rmed

iate

ind

ica

tor

Comment on Indicators

Planning

100% of schools in deprived districts with

SPIPs approved by SMCs

X At appraisal, the end target was

75% of schools with SPIPs

approved by SMCs

Intermediate target exceeded by

25%

Monitoring

On average schools were visited 7.8 times

and no school was visited fewer than 2 times

per year.

100% of schools visited by Circuit

Supervisors at least two times in a year

X At appraisal, the end target was

100% of schools visited by Circuit

Supervisors at least two times in a

year

Intermediate indicator met

100% of Regional Education Directors

submitting acceptable annual reports,

incorporating data from all districts in the

region

X At appraisal, the end target was

100% of REDs submitting

acceptable annual reports

Intermediate indicator met

Impact Evaluation on UTDBE teachers

conducted

Impact Evaluation on district and school

grants conducted

External and internal audits carried out

14. Achievement of Component 3 Indicators: The project successfully met the targets

of all indicators, as outlined below:

At project closing, 100% of Regional Education Directors submitted acceptable

annual reports, incorporating data form all districts in the region – meeting the

target for this intermediate indicator.

The intermediate indicator – Schools visited by Circuit Supervisor at least two

times in a year – was met as 100% of schools were reported as doing more than two

times per year.

The intermediate indicator – Schools in deprived districts with completed SPIPs

approved by SMCs using the revised template – exceeded the project target of 75%

with 100% of schools in compliance by project closing.

Page 57: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

47

Additional findings from Fiduciary Review and Procurement Review

15. In depth fiduciary reviews were conducted to assess performance at central and

local levels with respect to financial management and procurement. The findings from the

various fiduciary reviews confirmed the following strengths:

a) Strong technical competences of the financial controller (GES) and the accounts

team at head office;

b) Qualified and capable financial officers at the district levels;

c) Quarterly financial management supervision visits by HQ Accounts team of all the

participating districts to review their systems and validate expenditure;

d) Regular capacity building on fiduciary related topics to address fiduciary capacity

challenges of the districts and also to mitigate issues such as transfers of key staff,

lack of full complement of internal audit staff etc;

e) Strong management and supervisory oversight by the technical staff of GES and

those responsible for their respective component in ensuring that budgets are

adhered to and costs are reasonably controlled;

f) A good and timely reporting mechanism in place channeling up from districts to

regions and HQ. The Project Financial management reviews by the World Bank

were conducted in 2013 and 2015. Implementation Manual also included specific

templates for schools to report on the grants; and

g) Release of funds only when conditions spelled out in the PIM were met.

16. Although FM performance was very steady, the fiduciary reviews also noted some

room for improvement. The strict procedures required that district finance and

administration had to submit hard copy of all claims made by the districts in order to receive

payment (for procurement related activities).This often required travel to Accra which

delayed payments and increased transaction costs for district staff. Electronic submission

would be a preferred method. The FM reviews also recommended a standard template for

internal auditor reporting at the district level, and more training at this level as capacity

seemed to prevent the district auditors from supervising school heads more effectively. In

some of the new districts, internal auditors had not been hired and this contributed to poor

supervision. Filing systems in some districts were weak and similarly at some schools the

filing systems were quite poor.

17. The most recent audit was completed in June 2016. In instances in which minor

issues were identified, corrective actions were enacted by the Bank and the Government.

FM reviews by the World Bank were also conducted in 2013 and 2015.

Safeguards

18. Safeguards compliance was not well monitored until the second year when District

Education Directors were trained and briefed about their responsibility and role in ensuring

safeguard compliance throughout project implementation. Moreover, the project developed

Page 58: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

48

a simple checklist that was shared with the Government, included in the PIM and all minor

civil works bidding and contract documents going forward. The most recent safeguards

review in 2016 found minor impacts from the rehabilitation and minor construction works

as well as the adherence to the applicable guidelines provided in the Safeguards

Instruments especially the mitigation measures provided in the checklist for construction

and rehabilitation activities.

19. The applicable Safeguards instruments were prepared and approved for the project

but proved to be a large and unwieldly document. The ESMF from previous projects was

used with additional information provided related to the GPEG. The document may have

provided adequate guidelines for the rehabilitation of classroom blocks and construction

of basic sanitary facilities for the beneficiary schools, but the quality of the document could

have been improved. Use of the Environmental Management Plan (EMP) checklist has

ensured safeguards compliance and holding contractors accountable for following EMP for

minor civil works projects.

Page 59: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

49

Annex 3. Economic and Financial Analysis

1. Following the economic and financial analysis presented in the Project Appraisal

Document, the Economic and Financial Analysis is similarly divided into two parts: (a)

District and School Grants; and (b) teacher upgrading (Untrained Teachers Diploma in

Basic Education - UTDBE). For both sections, the economic and financial analysis presents

the following sections: (i) efficiency of implementation; and (ii) financial sustainability.

2. The overall findings that are detailed below indicate that GPEG benefitted from

exchange rate gains and cost effective implementation of activities, allowing the project to

achieve and exceed the project targets.

3. Component level expenditure was in line with the assessments made during

appraisal and cost savings from currency depreciation were redirected towards

increased allocations for district grants. The table below compares the component level

project costs as budgeted in the PAD with the actual expenditure (in US dollars). The

Ghanaian Cedi (GHc) depreciated by 115% against the US dollar during the Project

Period29 and savings generated from depreciation of the Ghanaian currency were redirected

towards Component 1. 30 Also, 67.2% of the funds allocated to Physical and Price

Contingencies were directed towards additional support for districts and expansion of the

in-service teacher training program. The remaining contingency amount was directed

towards Project Management and Institutional Strengthening. Due to exchange rate gains,

actual expenditure for school grants was lower than projected even though the base grant

and per capita amounts were increased over the project period.

Table 1. Project Costs and Financing by Component (Budgeted in PAD and Actual

Expenditure) in US$

Project Costs and Financing Budgeted Actual

Component 1 District Grants, Teacher Development & Skills Upgrading 42,360,000 48,407,527

Component 2 School Grants 22,060,000 20,382,339

Component 3 Project Management and Institutional Strengthening 4,580,000 6,710,134

Physical and Price Contingencies 6,500,000

Total 75,500,000 75,500,000

Source: Author’s calculations based on Financial Management Reports, Ghana Education Service

29 The ICR uses 3.05 as the exchange rate for the GH¢ to the US dollar. This is average exchange rate over

the lifetime of the project weighted by the amounts at each withdrawal. The exchange rate during the drafting

of the PAD was 1.90. 30 An additional supplementary grant was provided to districts in 2016.

Page 60: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

50

1.1 District and School Grants

Efficiency

4. In terms of efficiency of district and school grants the analysis found that district

grants were allocated based on relative deprivation. Two district level activities

(accounting for 24.81 percent of overall district level expenditure) – construction of urinals

and toilets and in-service teacher training - were analyzed and both activities were found

to be relatively cost effective in comparison with government and other donor led

initiatives in Ghana. At the school level, school grants disbursements were found to be

highly correlated with improved planning (through school performance improvement

plans) and monitoring (through school report cards). A difference in differences analysis

showed that in line with the available literature on district and school grants, districts that

received grants witnessed substantial improvements in gross and age-appropriate

enrolment (as compared to non GPEG districts over the same period). However, not all the

improvements in access can be attributed to the project as other programs were operating

in deprived districts during the same period.

5. District grants were allocated based on relative deprivation among the GPEG

districts maintaining a strong equity focus. Resources to districts were allocated based

on a consistent, transparent and deprivation based allocation formula that provided

additional funding to more deprived districts31. The model was updated annually using the

latest EMIS data. Thus, funds were equitably allocated using a resource allocation model

developed during project preparation. Districts were also provided with summary statistics

highlighting their performance on key indicators (GERs, NERs, BECE pass rates etc.).

Since then, the model has become a part of the GES planning toolkit and is used to also

disburse government funds to non GPEG districts.

6. District grant budgeting and expenditure was tracked. As outlined in the PAD,

to receive district grants, each district submitted an Annual Programme of Work (APW)

which detailed their planned activities. Districts planned for activities along four cross

cutting thematic areas: Access, Quality, Gender, and Management found in a pre-approved

Menu of Activities. At the end of each year, districts reported on the progress in

implementing their activities within their APW, and were reported on actual expenditure,

timeframe and quantity. The analysis of the executed APWs reveals that districts conducted

4,983 activities over the project period. These comprised of 76 unique activities.

31 The allocation formula consists of a base grant component and additional allocation was based on the

number of schools, students, teachers and the level of deprivation (lower retention rates, lower share of girls’

enrolment, lower share of trained teachers and lower pass rates in BECE Mathematics and English).

Page 61: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

51

Table 2. District level Expenditure (in GH¢)

Cross Cutting Pillar Count of Activities Expenditure % Of Expenditure

Access 1,059 65,100,932.86 44.16%

Gender 639 30,069,127.40 20.40%

Management 1,878 24,392,645.01 16.55%

Quality 1,407 27,850,547.05 18.89%

Total 4,983 147,413,252.32 100.00%

Source: Annual Program of Work Expenditure data. The pillar level allocations include GPEG and DFID’s

Girls PASS Program.

7. As seen from the table below five activities accounted for more than 60% of the

expenditure for district grants. Among the five, the unit cost of two activities (construction

of gender friendly toilets and urinals and provision of INSET) are subsequently examined

in greater detail32.

Table 3. District level activities with the highest level of expenditure (in GH¢)

Activity

Count

Expenditure

%

Expenditure

Provide schools with essential supplies - desks, tables chairs 337 24,236,945 20.10%

Construct gender friendly toilets and urinals 301 21,730,847 18.02%

Provide material support to children in need 89 12,388,831 10.28%

Organize INSET – Mathematics, Science & Lit 278 8,181,657 6.79%

Provide teaching and learning materials, learning kits etc. 335 8,155,606 6.76%

8. Unit cost of construction for toilets and urinals funded under the GPEG

district grants was lower than both the government’s own procurement unit and

UNICEF. The Ministry of Education mandates that all toilets and urinals constructed at

the school level follow a standard design33 allowing for a cost comparison of identical units.

Using GPEG funds, districts constructed 871 2- unit urinals and 609 4-unit Kumasi

Ventilated Improved Pit-Latrines (KVIPs) at an approximate cost of US$7.12 million

dollars. As the table below shows, the average cost of construction for both the toilets and

the urinals were lower than the costs of 300 toilets being constructed with UNICEF funding

and 41 newly constructed toilets under the government’s Funds and Procurement

Management Unit of Ghana (FPMU) in the same period. Thus, the decentralized GPEG

financed toilets were more cost efficient than other construction at the school level.

However, the standards and the cost of construction for school toilets is higher than

UNICEF’s mud walled community based toilets34 . A relaxation of strict construction

32 These items are selected because information regarding quantities for the highest expenditure item of

providing schools with essential supplies (disaggregated by type of furniture) was not available. 33 Kumasi Ventilated Improved Pit-Latrines (KVIPs) 34 Community based toilets have a unit cost of Gh¢8,490

Page 62: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

52

norms in the design of toilets at the school level may lead to significant generation of cost

savings (cost ratio of 4:1).

Table 4. Unit Cost of Construction (in GH¢) GPEG UNICEF FPMU

Toilet (4 Unit KVIP) 32,801 36,083 40,100

Urinal (2 Unit) 5,665 6,368 5,950

Source: Author’s calculations based on GPEG Annual Programs of Work and data provided by the MOE and

UNICEF

9. Unit cost of providing in-service teacher training under GPEG compares

favorably to non-GPEG districts. In-service teacher training in core subjects (Math,

Science and Literacy) accounted for 6.79% percent of the district grants budget. As part of

the reporting requirements, districts submitted training reports on all the training activities

conducted during each data collection cycle. Delivery of modules through GPEG compared

favorably with the delivery of identical modules in non GPEG districts. For example,

delivering a module in Mathematics under GPEG cost the project GH¢ 39.48 per

beneficiary (approximately US$13) as compared to GH¢ 45.8 (approximately US$15) in a

non GPEG district.

Table 5. Unit Cost of core INSET (in GH¢) GPEG districts Non GPEG districts

Mathematics 39.48 45.8

Science 34.41 48.8

Literacy 37.57 42.7

Source: Author’s calculations based on INSET training reports for 2013, 2015 and 2016 and

reports from non-GPEG districts from GES. Disaggregated data for INSET isn’t available for

2014 as not all districts submitted reports for that year.

School Grants

10. School Grant allocations were based on annual EMIS data and were open and

transparent. The joint monitoring visits conducted by MOE/PBME and GES found that

funds transferred to bank accounts of each school were displayed on a notice board in the

district education office. An impact evaluation of the district and school grant found that

only 3% of the sampled Head Teachers reported that they had not received the full grant

entitlement.

11. Schools primarily used the grants for facilitating of SMC meetings, small

repairs, building of toilets and the overall improvement of the school environment35. A fiduciary assessment conducted in a sample of 105 schools found that projects

undertaken by the school were inspected by the district office and the expenditure of school

grant funds were tracked at the district level. The execution rate of the funds within each

35 Endline Impact Assessment

Page 63: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

53

fiscal year increased as the project progressed from 72.3% in 2013, to 88.0% in 2014, and

finally 92.4% in 2015/16.

12. Improvements were seen in planning and monitoring at the school level. On

average, across the duration of the project, 86.9% of schools displayed the School Report

Cards36 on their noticeboard. This proportion has been increasing steadily across the years:

in 2013, the figure was 79.0%, which increased to 87.6% in 2014 and noted a further

improvement in 2015/16 at 93.0%. Thus, improvements in planning and monitoring at the

school level (as envisaged in the PAD) were evident. Though the data to analyse if the

investments made using school grants fund were cost effective is not available.

13. There has been a substantial improvement in gross and age appropriate

enrolment in deprived districts over the project period. Though non GPEG (the

remaining 141 districts that did not receive GPE funding) and GPEG districts have seen

improvements in enrolment over the project period, improvements in districts receiving

school and district grants have been appreciably higher than non GPEG districts across all

sub levels of basic education.

14. As Table 6 shows, at the Kindergarten and Primary level, GPEG and non GPEG

districts had comparable Gross Enrolment Rates (GER), Net Enrolment Rates (NER),

Gross Admissions Rate (GAR) and Net Admission Rates (NAR) at baseline. For example,

in 2012, GAR in non GPEG districts was 107.9 as compared to 107.7 in GPEG districts.

However, by endline, GAR in non GPEG districts had risen only to 115.4 while in non

GPEG districts, GAR had risen to 124.4 (a 16.7 percentage point increase and a 9.2

percentage point improvement above non GPEG districts). The differences are particularly

pronounced at the KG level wherein improvements in GER and NER over the project

period are 24.2 and 16.6 percentage points higher than improvements in non GPEG districts

(see Figure 1).

36 The School Report Card (SRC) collects information from schools concerning pupil and teacher attendance

and student test performance

Page 64: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

54

Table 6. Difference in differences between GPEG and non GPEG districts

Non GPEG Districts GPEG districts

Difference

in

differences

(6-3)

Baseline

(2012)

Endline

(2016)

Change

from

baseline

to endline

Baseline

(2012)

Endline

(2016)

Change

from

baseline

to

endline

(1) (2) (3) (4) (5) (6) (7)

Kindergarten

GER (%) 114.8 117.8 3.0 111.6 138.8 27.2 24.2

NER (%) 74.5 74.5 0.0 75.6 92.2 16.6 16.6

Primary

GER (%) 107.4 111.2 3.8 98.8 111.4 12.6 8.8

NER (%) 85.2 90.7 5.5 81.1 93.7 12.6 7.1

GAR (%) 107.9 115.4 7.5 107.7 124.4 16.7 9.2

NAR (%) 79.3 80.6 1.3 79.3 84 4.7 3.4

Junior High School

GER (%) 86.6 92.0 5.4 68.9 76.5 7.6 2.2

NER (%) 52.1 52.7 0.6 34.8 43.2 8.4 7.8

GAR (%) 93.5 101.6 8.1 67.5 85.4 17.9 9.8

NAR (%) 46.1 47.3 1.2 27.2 40.2 13 11.8

Source: EMIS (2012 – 2016)

Figure 1. Kindergarten Gross Enrolment Rates (2012 – 2016)

Source: EMIS (2012 – 2016)

114.8

117.8

138.8

111.6

114.6

110

115

120

125

130

135

140

Baseline (2012) Endline (2016)

KG GER(%)

Non GPEG districts GPEG districts GPEG (assumed prior trajectory)

Page 65: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

55

15. However, DFID’s GPASS program (at the JHS level) and the government’s

Complementary Basic Education program that supports mainstreaming of out-of-school

children also operated in GPEG districts during the project period and so it would be

difficult to isolate the improvements in access attributable only to the provision of district

and school grants.

Fiscal Sustainability

16. The financial cost of continuing the school and district grants in the deprived

districts is a recurrent expenditure of US$19.3 million annually. During project

implementation, the fiscal impact of the district and school grants was limited to the

opportunity cost of staff time involved in planning, implementing and monitoring both

district and school grants. The financial cost to the Government of continuing the school

and district grants to the deprived districts is US$19.3 million a year (higher than the

US$16 million a year estimated in the PAD as the allocation for district and school grants

increased over this period). However, with limited sector financing for capitation grants

and other education investments because of fiscal constraints, no school grants have been

disbursed in 2016 apart from the preexisting capitation grant (of approximately US$0.49

per student per semester). So far, the government has no plans to increase the capitation

grants provided to schools or increase district grants, leading to no recurrent fiscal

implications for the government.

17. Donor partners plan to provide gap financing to complement existing public

recurrent education spending for basic schools. USAID is committed to expanding the

district grants while DFID will continue to fund girls’ scholarships to all GPEG districts.

UNICEF and USAID also plan to introduce more efficient mobile monitoring tools to help

track local level expenditure.

1.2 Untrained Teachers Diploma in Basic Education (UTDBE)

Efficiency

18. In line with the PAD, the Project’s four year in-service Untrained Teachers

Diploma in Basic Education (UTDBE) program is compared to Ghana’s conventional

Diploma in Basic Education (DBE) model. The DBE model uses the same curriculum for

training teachers as UTDBE through a three year pre – service residential program and was

the prevailing program of choice to upgrade teacher skills prior to GPEG.

19. In terms of efficiency, the following was determined: UTDBE and the DBE model

produce teachers with similar skillsets though UTDBE is more cost-effective with a cost

ratio of 1.6. The program has led to a convergence in the percentage of trained teachers

within GPEG and non GPEG districts though the upgrade of teacher skills has not

translated into vastly improved completion or transition rates to date.

Page 66: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

56

20. Following participation in training, UTDBE- and DBE-trained teachers have

comparable skillsets. In the UTDBE impact evaluation (IE) study comparing the two

programs, 400 of the UTDBE trainees and 185 of the DBE graduates were observed in a

classroom setting and graded on lesson planning and preparation, classroom methodology

and delivery and class management and organization. The UTDBE trainees showed mean

scores within the same range as DBE teachers on 14 out of 17 skills in lesson planning/

preparation, teaching methodology and classroom organization and management 37 .

However, UTDBE and DBE trainees were also tested on content knowledge. DBE teachers

displayed a better understanding of Integrated Science, a result which is statistically

significant at the 1% level. UTDBE trainees showed better results on Classroom

Management techniques. Overall, the assessment concluded that following their trainings,

UTDBE and DBE teachers have a comparable level of skills.

21. UTDBE is more cost-effective than DBE with an efficiency ratio of 1.6. The

Project Appraisal Document estimated the cost of the UTDBE program to be US$2,268

per trainee. However, the IE study estimated the final cost of the program to be US$4,278

(for all four years) per trainee even after the depreciation of the Ghanaian currency. After

cost sharing with the student, the cost of the training to the program was US$2,130 (102%

higher than the estimate of US$1,052 in the PAD). However, the attrition rate of 20.43%

was lower than the modelled 40% and similar to the attrition rate of the DBE program.

22. During the time of project conception, the cost of training a DBE teacher used to

be significantly higher because it included a stipend for each student. In 2012, Murphy

found the cost of training a DBE trainee to be GHc 15,350 (US$5,033)38. However, this

stipend has recently been abolished and the cost of a DBE student has reduced to US$3,409

per trainee (a 32% decline)39. With the new government assuming office in January 2017,

the stipend may be reintroduced.

Table 7. Estimated Government and Project Costs for training UTDBE and DBE trainees

UTDBE DBE

Cost to government per year (GHc) 1,624 3,466

Cost to government per year (US$) 532 1,136

Duration of program (years) 4 3

Total Cost to government (GHc) 6,496 10,398

Total Cost to government (US$) 2,130 3,409

Source: “Impact Assessment of the Untrained Teacher Diploma in Basic Education (UTDBE) Trainees:

Endline Study.” by Associates for Change (2016).

37 “Impact Assessment of the Untrained Teacher Diploma in Basic Education (UTDBE) Trainees: Endline

Study.” by Associates for Change (2016). 38 Murphy, P (2012) ‘The Untrained Teacher Diploma in Basic Education in Ghana: Analysis and

Recommendations: Second Draft’ 39 “Impact Assessment of the Untrained Teacher Diploma in Basic Education (UTDBE) Trainees: Endline

Study.” by Associates for Change (2016).

Page 67: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

57

23. At endline, the cost to the government of providing training for one teacher under

UTDBE was US$2,130 as compared to US$3,409 under the DBE model (which continues

to remain in use in Ghana). Effectively, training a student using the conventional mode of

training costs the government 60% more than the cost of training a teacher using the

UTDBE modality. This is a cost ratio of 1:1.6 or conversely, for every US$100 spent on

the UTDBE program, US$160 would need to be spent on the DBE program (or higher if

the allowance is reinstituted). This cost ratio of 1.6 is lower than the one projected in the

PAD (the estimate was 4.3 primarily due to the inclusion of the stipend and the

underestimation of the cost of the UTDBE program). However, the UTDBE program

remains more cost effective while training teachers to achieve the same skills and

certificate at similar levels of attrition.

24. Training UTDBE teachers increased the percentage of trained teachers and

the PTTR in deprived districts. As the difference in differences table below shows, while

the proportion of trained teachers has increased nationwide during the duration of the

project, the increase in GPEG districts has outpaced that of non-GPEG districts across all

levels of basic education40. The rate of increase in GPEG districts is 17 percentage points

higher than the non-GPEG districts for KG and 12 percentage points higher for Primary

and JHS from baseline to endline. The subsequent improvement in PTTR is much higher

for GPEG districts as compared to non-GPEG districts for all levels. At the KG level, the

rate of change at the KG level is particularly noteworthy where the PTTR decreased by 62

more pupils to a trained teacher in GPEG districts compared to non GPEG districts.

25. The convergence in the percentage of trained teachers between GPEG and non

GPEG districts is likely to remain persistent. Most UTDBE teachers had been teaching

in GPEG districts for several years prior to being selected for the program and have roots

within the communities in which they reside.41 Moreover, UTDBE teachers are bonded to

stay within the same school in the deprived areas for at least another two years after the

successful completion of their training. Thus, the reduction in disparity between GPEG and

non GPEG districts in terms of percentage of trained teachers is likely to persist, especially

if all UTDBE trained teachers are put on the GES payroll.

26. However, so far, these improvements have not yet translated into substantial

improvements in indicators of internal efficiency. Though GPEG districts have shown

improvements in completion rates (for example completion rate at JHS rose from 59.9%

to 65.1%), improvements in non GPEG districts outpaced GPEG districts in primary

completion rates and transition rates from primary to Junior High School (JHS) at endline

(both the levels for which data is available). However, given the fact that the UTDBE

teachers hadn’t graduated from the program while the data on transition and completion

rates was collected, the difference in differences between GPEG and non GPEG districts

40 The absolute number of untrained teachers has risen over the project period in both GPEG and non GPEG

districts allaying concerns that the shift in percentage of trained teachers may be partially credited to net

migration of untrained teachers from GPEG districts to non GPEG districts. 41 “Impact Assessment of the Untrained Teacher Diploma in Basic Education (UTDBE) Trainees: Endline

Study.” by Associates for Change (2016).

Page 68: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

58

in terms of repetition, transition and completion rates should be observed over the next few

years as the impact of the increased proportion of qualified teachers may take longer to

materialize in terms of results in completion.

Table 8. Difference in differences between GPEG and non GPEG districts

(improvements in percentage of teachers trained, Pupil Trained Teacher Ratio

(PTTR), completion rates and transition rates)

Non GPEG Districts GPEG districts Difference

in

differences

(6-3)

Baseline

(2012)

Endline

(2016)

Change

from

baseline

to endline

Baseline

(2012)

Endline

(2016)

Change

from

baseline

to endline

(1) (2) (3) (4) (5) (6) (7)

Kindergarten

% Trained Teachers 57.00 71 14 34 65 31 17

PTTR 56 39 -16 159 81 -78 -62

Primary

% Trained Teachers 77 85 8 50 70 20 12

PTTR 41 37 -4 78 57 -21 -17

Junior High School (JHS)

% Trained Teachers 87 92 5 72 89 17 12

PTTR 17 16 -1 27 22 -5 -4

Completion rate (%) 73.2 80.0 6.8 59.9 65.1 5.2 -1.6

P6 to JHS1 transition

(%) 97.8 98.7 0.9 83.5 83.2 -0.3 -1.2

Source: EMIS (2015 – 16) and authors' estimates from the final number of successful UTDBE graduates as

EMIS (2015 – 16) was conducted prior to the graduation of UTDBE teachers.

Fiscal Sustainability

27. The upgrading of skills for UTDBE teachers has a recurrent fiscal implication

of US$12.48 million. The PAD estimated the fiscal impact of upgrading up to 8,000

teachers to be around US$20 million per year given current salary levels.' The significant

depreciation of the Cedi over the lifetime of the project and a revision in Ghana’s civil

service salary structure has led to a substantial decline in the recurrent fiscal implications

to an annual recurrent expenditure of US$12.48 million.42

28. However, these higher costs are already foreseen in the cost projections

prepared by the Ministry of Education for the annual budget hearings. In meetings

42 Prior to their graduation, UTDBE teachers were drawing a salary of US$158 per month, which rose to

US$322 per month (an increase of 103%) as of November 2016.

Page 69: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

59

with the Ministry of Finance, the MoE has asked for an increased allocation for the 2017-

2018 financial year based on the additional recurrent cost.

Page 70: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

60

Annex 4. Grant Preparation and Implementation Support/Supervision Processes

(a) Task Team members

Names Title Unit Responsibility/

Specialty

Lending/Grant Preparation

Deborah Newitter Mikesell Senior Operations Officer AFTED Team Lead

Qaiser M. Khan Sector Lead Economist AFTSE Sector Lead Economist

Eunice Yaa Brimfah Ackwerh Senior Education Specialist AFTED Education Specialist

Peter Darvas Senior Education Econ. AFTED Education Economist

Kirsten Majgaard Education Economist AFTED Economist

Patrick D. Murphy Consultant GED13 Teacher Education

Daniela Anna B. D. Junqueira Legal Counsel LEGAM Counsel

Robert Wallace DeGraft- Hanson Financial Management Specialist AFTME Financial Management

Shwetlena Sabarwal Economist AFTED Economist

Adu-Gyamfi Abunyewa Senior Procurement Specialist AFTPE Procurement

Anders Jensen M&E Specialist AFTOS Results Framework

Bernardo da Cruz Vasconcellos Education Specialist AFTED Monitoring/ Evaluation

Luis M. Schwarz Sr. Finance Officer CTRLD Disbursements

Rose-Claire Pakabomba Program Assistant AFTED Program Assistant

Beatrix Allah-Mensah Social Development Specialist AFTSD Safeguards

Robert West Consultant AFTED ESP /Grant application

Jessica Dodoo Team Assistant AFCW1 Team Assistant

Supervision/ICR

Deborah Newitter Mikesell Senior Education Specialist GED13 Team leader

Charles John Aryee Ashong Senior Procurement Specialist GGOO1 Procurement

Robert Wallance DeGraft-Hanson Sr. Financial Management Specialist GGO31 Financial Management

Eunice Yaa Brimfah Ackwerh Senior Education Specialist GED13 Education Specialist

Peter Darvas Senior Economist GED 13 Economist

Christin McConnell ICR consultant GED13 ICR author

Patrick D. Murphy Consultant GED13 Teacher Education

Juvenia Lidia Mapilele Cohen Finance Analyst CAFE5 Financial Management

Lydia Sam Procurement Assistant AFCW1 Procurement Assistant

Franklin Kuma Kwasi Gavu Environmental Specialist GEN01 Safeguards

Janet Adebo Program Assistant GED13 Program Assistant

Stephen Kwaku Tettevie Team Assistant AFCW1 Team Assistant

Kabira Namit Consultant GED13 Economic/Fin Analysis

Kathleen Beegle Program Leader AFCW1 Impact Evaluation

GPE Country Leads

Kouassi Soman Sr. Operations Officer DFPGE GPE Country lead

Sven Baeten Sr. Education Specialist DFPGE GPE Country lead

Prema Clarke Sr. Education Specialist DFPGE GPE Country lead

Josephine Lutta Kiyenje Sr. Education Specialist DFPGE GPE country lead

Page 71: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

61

(b) Staff Time and Cost

Stage of Project Cycle

Staff Time and Cost (Bank Budget and TF)

No. of staff weeks USD (including travel and

consultant costs)

Lending

BB Total 10 76,436

Trust Fund Total 37 309,489

Supervision/ICR

BB Total 19 131,494

Trust Fund Total 84 503,504

Page 72: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

62

Annex 5. Beneficiary Survey Results Summary

1. A beneficiary assessment survey was carried out in June 2016 by the Ghana

Education Service (GES) to help identify successes and issues arising from the Ghana

Partnership Education Grant (GPEG) project implementation and collect recommendations

from stakeholders. The main objectives of the GPEG beneficiary assessment were to: (i)

collect recommendations and lessons learned from stakeholders and; (ii) produce

recommendations to sustain the gains made by GPEG in the future and address the

challenges identified moving forward.

2. Fieldwork was undertaken in June 2016 and a total of 16 districts across all GPEG

regions were visited. In total, 377 GPEG beneficiaries were interviewed at central,

regional, district and school levels. Two schools were visited in each of the 16 districts.43

3. Overall findings indicated that (i) beneficiaries were highly familiar with GPEG at

project initiation; (ii) expectations from the GPEG were broadly met and consistent across

respondent groups and regions; (iii) GPEG was found to be a success with 82% of the

sample rating the project 8 or above on a scale from 1 to 10 (where 1 is ‘very unfamiliar’

and 10 is ‘very familiar’); (iv) GPEG was deemed very necessary and timely by

respondents at all levels- on a scale from 1 to 10, respondents on average ranked 9.8 when

asked about the necessity of GPEG; (v) trainings held under GPEG helped in the effective

execution of the project; and (vi) GPEG reduced the financial burden on parents of having

to pay additional fees for miscellaneous expenditure to schools.

4. Closer study of the qualitative data by each respondent group level revealed several

key lessons including the optimism that: (i) decentralization can be achieved under the right

circumstances and with the right amount of training; (ii) targeting as a resource allocation

tool is effective and the base grant component is an equitable way of getting funds to

schools; (iii) leadership, good record keeping and accountability mechanisms are essential

for successful outcomes and; (iv) capacity building at several levels simultaneously was a

key component to the success of GPEG.

5. In the absence of further GPEG funding, respondents highlighted the need to

continue empowering districts to plan and prioritize their needs, ensuring community and

stakeholder engagement in school management structures as well as facilitating continuous

teacher skills upgrading. A minimum amount of funding would be necessary for re-training

officers and keeping institutional structures in place. These activities could be sustained

through capitation grants and dedicated leadership in the future.

43 Focus groups were held with JHS3 pupils (and where possible included at least one GPASS beneficiary).

In primary/KG schools, the focus group was held with upper primary (P4-P6) pupils. In addition, where

possible, at least one UTDBE teacher was interviewed per district.

Page 73: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

63

Figure 1: GPEG Success Ranking by Respondent Group

6. Closer study of the qualitative data by each respondent group level (central,

regional, district and school) revealed several key lessons from Project implementation

challenges including:

Frequent staff turnover – particularly at district level – hampered the

implementation as institutional memory and transferred skills were lost. Moving

forward, a new system addressing the frequency of transferals may need to be

elaborated.

Lack of coordination between regional offices and districts delayed some activities.

Difficulty in providing effective oversight of the implementation at the district and

school levels due to inadequate human capacity in the most deprived districts and

schools.

Lack of sound and timely report writing at regional and district level.

Short project implementation period which in some cases seemed to rush

implementation.

Key challenges under UTDBE noted by teachers included the late payment of fees

thereby delaying some training courses.

7. Key lessons learned emerging from a review of the beneficiary assessment data

included:

Decentralization can be achieved. Giving officers training and funds to manage

leads to tangible results and shows that decentralization is possible under the right

circumstances and with the right amount of training. At school level, where there is

adequate and regular funding, teaching and learning will improve and enrolment

figures will be enhanced.

Targeting as a resource allocation tool is effective and the base grant component is

an equitable way of getting funds to schools.

8.71

7.578.33 8.62

9.45

0

1

2

3

4

5

6

7

8

9

10

Total average(143)

HQ Average(7)

REO Average(15)

DistrictAverage (92)

School Average(48)

Succ

ess

Sca

le

GPEG Success

Page 74: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

64

Leadership, good record keeping and accountability mechanisms are essential for

successful outcomes. Capacity building in particular led to improved record-keeping

and accountability through strengthened monitoring activities.

Capacity training at several levels simultaneously was a key component to the

success of GPEG. Involving various stakeholders in decision making increases

supervision at school level. Head teachers, SMCs and PTAs should therefore be well

sensitized and orientated before any new programs in the future.

Most teachers strongly agreed that participants in the UTDBE program had

improved their lesson delivery. Over 85% of teachers estimated that their students’

performance had improved as a result of their UTDBE training.

8. In the absence of further GPEG funding, respondents added the following lessons

and activities which could be sustained through capitation grants and dedicated

leadership in the future:

Empowering districts to plan and prioritize their needs by applying and transferring

skills learned in terms of planning and executing activities at district and school

level. A minimum amount of funding would be necessary for re-training officers

and keeping institutional structures in place.

Ensuring community and stakeholder engagement in school management.

Continuous stakeholder involvement in decision making would improve

supervision and monitoring at low or no cost.

Teacher skills upgrading through INSETs could be envisioned with minimal

funding.

Page 75: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

65

Annex 6. Stakeholder Workshop Report and Results

A half-day workshop was held on February 8, 2016 among the key implementers of GPEG

to discuss lessons learned, sustainability, and arrangements for the future. The workshop

was attended by District Directors of Education, Regional Directors of Education, various

implementers at the MOE/GES level, and Development Partners. Some of the key

recommendations for future sustainability are highlighted below by indicating the project

activities that are to be continued with minimal to no incremental funding requirements as

well as those activities that would require additional budget allocations.

1. INSET

Funding not required

The following processes / procedures do not require funding to be institutionalised:

Promotion and performance appraisal for Heads should be reviewed and new

guidelines issued. Part of the appraisal guidelines should involve whether an INSET

has been organised and the relevance of the INSET.

More school and cluster based INSETs should be held.

2. Trained teachers, teacher retention, and UTDBE

Funding not required

Transfer/posting policy should be reviewed to ensure that, especially in the case of

interventions, transfers/postings are maintained for a minimum of three years. This is

to counteract the loss of knowledge that results from frequent turnover of staff

following training/implementation experience.

The UTDBE programme should be continued to ensure that those teachers who are

willing to work in deprived communities can be provided with opportunities to become

certified teachers. However, it was agreed that this should no longer be funded by the

GOG as there is an excess of unemployed trained teachers who need to apply for

vacancies in deprived communities.

An analysis should be conducted on trained teachers in the system (employed and

unemployed) and compared to how many teachers are needed to reduce the PTTR level

to GES acceptable norms.

New teachers in schools should have mentors from within the school who are selected

(and trained in mentoring).

There should be a clear set of guidelines on the conditions required for a school to be

established (i.e. teacher accommodation, etc.). This can increase teacher retention.

Funding required

It is essential that UTDBE trained teachers who are not on Government payroll are

prioritised to be placed on payroll.

Page 76: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

66

3. Community involvement and participation

Funding not required

It is important to empower SMCs by recognizing local champions, engaging them in

school activities, and sensitising them on their responsibilities. This should be the

responsibility of the DEO, particularly the Circuit Supervisor and the School Heads

and should be incorporated in their guidelines.

4. School supervision

Funding not required

In order to ensure that findings from the Circuit Supervisors are addressed, the format

for Circuit Supervisors to report should be simplified and a concise template should be

designed. These findings can then be communicated to the DDE in a digestible format

for further follow-up.

Funding required

The mobile School Report Card being funded by UNICEF should be expanded to

include additional districts, which will eliminate the need for printed information. This

will help ensure more reliable and timely production of SRC.

Supervision of schools is necessary to ensure that they are performing and adhering to

standards. Hence, it is essential that DEOs receive money for supervision duties.

5. SPIPs, SPAMs, SRCs

Funding not required

To ensure that SPIPs are functional, it is essential to enforce preparation of them

regardless of funding. It was found that many schools prepare SPIPs only when they

are aware of the amount of money they will be receiving. Instead, the SPIP should be

regarded as a plan for the school that should be completed regardless of funding. When

the funding becomes available, the school can then draw up an action plan based on

their SPIPs to prioritise the activities captured within the allocated budget.

To ensure that SPAMs are functional, it should be enforced that BECE results for JHS

and EGRA/EGMA/NEA results for KG/Primary are the basis for holding SPAMs.

SPIP guidelines should be reinforced to ensure that schools are preparing one SPIP per

academic year.

It is important to ensure vertical linkages in planning throughout the system. SPIPs

should be linked to the ADEOP which should feed into regional plans and subsequently

national level plans.

6. Girls PASS

Funding not required

There should be sensitisation of the DGEOs in deprived districts on the scholarship

opportunities for GPASS girls to attend SHS. Possible scholarships include the

Page 77: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

67

Secondary Education Improvement Project (SEIP) scholarship, the Northern

scholarship, etc.

A selection committee for scholarships should be retained at the district level so that if

other scholarship opportunities arise (outside of GPASS), DEO staff have the requisite

skills to select the neediest students.

More research should be conducted on better targeting scholarships including tracking

the current GPASS beneficiaries through SHS.

Funding required

Continued targeted scholarships are necessary to ensure that those who are the neediest

have access to education.

7. Other

Funding not required

Posting of staff needs to be reviewed to ensure that HR staff at the DEOs have the

requisite background to perform their duties. It has been observed that teachers often

become HR staff at the DEOs and may not have the appropriate training.

It is important to recognise hard working teachers and high performing pupils to

motivate them to continue performing.

It should be the responsibility of the Circuit Supervisor to encourage the use of local

TLMs developed by teachers. This can also feature as part of the teacher appraisal for

promotion.

Recognising the lack of funding flowing from the Government to DEOs, it is important

that districts are incentivised to generate funds internally (IGF) so that education

outcomes are not compromised. Potential use of these funds will help to address

inadequacy of school resources, support needy students, etc.

It was found that where there was exchange of information and ideas across DEOs,

more innovative approaches and advanced project implementation was observed. It is

thus encouraged that there be a network of communication across DEOs apart from the

frequent training which brought DEOs together.

To ensure that capacity building activities are coordinated, it is necessary to have a

yearly plan for GES on training activities that is coordinated with MOE. It is also

necessary for the activities of NGOs working in the education sector be coordinated.

To address the problem of high attrition, information should be placed on DEO

noticeboards and regular meetings should be held with the DEO staff to ensure that

knowledge is being transferred.

It is important that data is used to make decisions and is shared and communicated

appropriately.

Funding required

Continuing to ensure that toilets in basic schools are gender friendly and potable water

is available is essential for safeguarding student health and continuing to improve

access.

Page 78: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

68

Districts should administer standardised exams for their district. The policy of creating

item banks at the district level should be enforced to ensure the sustainability of

initiatives like EGRA/EGMA/NEA.

The capitation grant amount should be reviewed regularly to ensure the maintenance

of the economic value of the grant.

The structure of school grants should be changed to include a base and capitation grant

so that even schools with low enrolment have some resources available.

Consistent ICT training for DEO staff in Microsoft Office is essential to ensure that

reporting is of a high quality. This training should also include training on the SRCs.

It is important for schools to receive additional capacity building for financial

management and proper filing. It was found that record keeping at the school level was

not always adequate; hence, providing them with training on cash books and recording

information is necessary.

It is essential that Heads are provided with orientation prior to assignment and

leadership training to ensure a conducive learning environment and help bring about

improvements in education results.

Page 79: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

69

Annex 7. Summary of Grantee's ICR and/or Comments on Draft ICR

Aim of the Report and Project Background

1. The Ghana Partnership for Education Grant (GPEG) closed on August 31st, 2016. The

following Project Completion Report (PCR) assesses the GPEG objectives, design,

implementation and operational experience from the perspective of the Government of

Ghana (GoG). It provides an evaluation of the program throughout its implementation

and identifies lessons.

Background at Project Initiation

2. Country context: Ghana as a strong performer in sub-Saharan Africa reached the status

of lower middle income economy in 2011 after years of sustained economic growth

with ambitions for further rapid growth and development in the coming years.

However, high public expenditure arrears remained a challenge even with new oil

revenues. Despite the overall reduction in poverty, wide regional disparities in poverty

and human development indicators remained, mainly between the northern Savannah

regions and the rest of the country. Since 1988, Ghana had put in place comprehensive

local government and decentralization reform. Districts reported to regional offices

which played a coordinating role. District Education Directorates (DED) which would

eventually become part of the Metropolitan / Municipal / District Assemblies

(MMDAs), oversee the operation of the basic schools.

3. Education Sector context: Public spending on education was around 6 percent of

Ghana’s GDP indicating a high budget priority for education. Districts mainly

concentrated in the north had weaker education outcomes than other parts of the

country. Children from the three Northern Regions, particularly girls, had lower rates

of school participation and weaker learning outcomes. With unsatisfactory learning

outcomes in basic schools, improving learning was definitely a Government priority.

The percentage of trained teachers had declined in public basic schools from 65 percent

to 48 percent between 2001 and 2009. As a result, teacher upgrading had to be

accelerated to meet Ghana’s goal of 95 percent.

4. Government introduced the Untrained Teachers Diploma in Basic Education (UTDBE)

program in 2004, to upgrade eligible untrained teachers in schools in rural communities

and there was the need to increase the number of teachers participating in this program.

There was also the need to strengthen School-based management approaches to

promote transparency and accountability for education service delivery. These included

School Management Committees (SMCs), Parent Teacher Associations (PTAs) and

local traditional authorities. School Report Cards (SRC) and School Performance

Appraisal Meetings (SPAM).

5. Project Rationale: The GPEG project was designed to improve the planning,

implementation and monitoring capacity of ongoing government efforts to decentralize

education resources to the district and school levels. The project sought to catalyze

Page 80: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

70

funding for education service delivery in the deprived areas in Ghana, which were

lagging behind the rest of the country in terms of educational outcomes.

Project Development Objectives and Results Indicators

6. The PDO of the GPEG project was to improve the planning, monitoring and delivery

of basic education services in deprived districts in Ghana. This was aligned with the

Education Strategic Plan 2010-2020. Progress towards the achievement of GPEG’s

development objective was measured by the following results indicators: Improved

Planning - Deprived districts disbursing 75% or more of their districts’ grants as

planned in their APW; Improved Monitoring - Public basic schools in deprived districts

with up-to-date School Report Cards; Improved service delivery - P3 students

achieving proficiency in English and Math (National Education Assessment results for

deprived districts), Teachers trained under the project in deprived districts who obtain

a satisfactory rating or higher in the SBI/CBI Lesson Observation Sheet for (a) lesson

planning (b) teaching methodology (c) classroom organization and management; and

direct project beneficiaries (disaggregated by female beneficiaries).

7. Main Beneficiaries: The project was expected to benefit 75 deprived districts,

approximately 6,600 schools and 1.7 million pupils (47% female), over 5000

untrained and 40,000 teachers. District, Regional and Headquarters Education

Directorates, National Inspectorate Board (NIB), officers in the MOE as well as the

Colleges of Education responsible for the UTDBE program. Ultimately, the

beneficiaries were the pupils in public basic schools (over 7,000) in deprived districts

who benefitted from an improved and equitable learning environment.

8. GPEG was prepared in very close partnership between the Government and the Local

Education Group (LEG) and was aligned with the Education Strategic Plan 2010-2020

(ESP) which had a strong emphasis on the expansion of educational opportunities to

disadvantaged populations as well as the enhancement of the quality of education and

students’ learning outcomes. Out of the 170 districts in Ghana, 57 (approximately a

third) were selected from 8 regions with a selection criterion which included district-

level poverty index (weighted at one-third) and some aggregated education indicators

(weighted at two-thirds). In the course of the project, the GPEG beneficiary districts

increased to 75 from 57 in June 2012 after re-delineation of districts to 216.

9. In collaboration with the World Bank, the MOE and GES developed a Project

Implementation Manual (PIM), an Environmental and Social Management Framework

(ESMF) and a social assessment.

Project Components

10. Component 1: Sub-Grants to Deprived Districts to support key education

objectives: This was annual non-salary resources to deprived districts provided as a

supplement to existing resource flows, to support districts APW and government

strategic priorities identified under the ESP.

Page 81: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

71

11. Sub component 1.1: District Sub-Grants: This was provided annually to the districts

to implement their APW. Activities in the APWs were focused on local priority needs

but aligned with government strategic priorities of improving access, equity, quality

and management of basic education. Activities financed under the grant included: in-

service training, capacity building, monitoring and evaluation and continuous

sensitization to maintain social accountability. DFID provided additional district grant

funding of GBP 7 million for girls’ education scholarships packages to the deprived

districts under their Girls Participatory Approach to Student Success (GPASS) program.

12. Sub-component 1.2: Teacher Development and Skill Upgrading: The objectives of

this sub-component was to support the upgrading through UTDBE of approximately

5,000 and no more than 8,000 untrained teachers in deprived districts. .

13. Component 2: School Sub-Grants: Under GPEG, school grants were provided

annually to all public basic schools in the 75 districts to finance activities identified in

School Performance Improvement Plans (SPIPs) prepared jointly by parents, teachers,

and head teachers. A base grant formula in addition to the per capita grant formula was

used to ensure that smaller schools were able to leverage financial resources.

14. Component 3: Project Management and Institutional Strengthening: This

component provided the necessary resources for management, monitoring and

evaluation of GPEG activities at the headquarters, regional, district and school levels.

The objective was to strengthen Government systems for the implementation and

supervision of decentralized education services in the deprived districts. Major

activities included consultancy and capacity building among others.

Girls Participatory Approach to Student Success (GPASS)

15. The Girls Participatory Approach to Student Success (GPASS) Scholarship program is

a GBP 7 million project funded by the Department for International Development

(DFID). GPASS is not a component of GPEG, but is aligned with the GPEG APWs

and uses the same structures and also targets the GPEG target districts. With an overall

objective of increasing the enrolment, retention, completion and performance of girls

at Junior High School (JHS) level, the GPASS provides material support in a form of

scholarships to girls and support to enhance the capacity of the Girls Education Unit

(GEU) Head Office as well as District and Regional education officers.

Agencies and Responsibilities

16. GPEG was overseen by the Ministry of Education (MOE) and actual implementation

was by GES at all its levels of management with responsibilities for: - Planning Budget

Monitoring and Evaluation (PBME) Division of the MOE (Project monitoring), -

Project Coordinator (Overall coordination), - Director of Basic Education (reporting on

Project Implementation and Operational) - Financial Controller (financial management

reporting), The Director of the Teacher Education (TED) (management and reporting

on UTDBE and INSET). The project avoided establishment of parallel structures and

integrated all operations with existing structures based on country systems. The World

Page 82: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

72

Bank was the supervising entity while the LEG provided external oversight on behalf

of the GPE and Project Steering Committee (PSC) provided oversight on

implementation.

17. Project restructuring: Two project restructurings were undertaken. The first

introduced works as a category to allow for minor rehabilitation under the District

Grant component. The second restructuring extended the closing date from October 31,

2015 to August 31, 2016 and reallocated funds as shown below.

Table 1: Re-allocated Project proceeds

Project Implementation Performance

Table 2: Overview of Project Financing as of December 30, 2016

Details Project

Funding

Budget Withdrawals Expenditure Budget

USD $ USD $ USD $ USD $ Execution

75,500,000.00

2013 22,685,456.66 22,684,769.62 18,232,577.00 80%

2014 23,815,833.94 23,913,975.38 25,261,151.00 106%

2015 24,100,000.00 23,887,951.82 23,455,773.60 97%

2016 4,898,709.40 5,013,303.18 8,550,498.40 175%

Total 75,500,000.00 75,500,000.00 75,500,000.00 75,500,000.00 100%

% of Project Funding 100% 100% 100%

Detailed Disbursement

Table 3: Project Disbursement Status, 2013-2016

Year School Grant District Grant UTDBE HQ Total

USD$ USD$ USD$ USD$ USD$

2013 6,686,797.71 8,000,037.78 2,113,469.62 1,432,271.88 18,232,577.00

2014 6,200,521.85 14,475,526.99 2,521,510.51 2,063,591.65 25,261,151.00

2015 8,734,218.44 10,861,579.47 2,021,485.09 1,838,490.61 23,455,773.60

2016 - 5,604,557.76 1,728,354.92 1,217,585.72 8,550,498.40

TOTAL 21,621,538.00 38,941,702.00 8,384,820.14 6,551,939.86 75,500,000.00

Categories Budget (USD) Re-Allocation

(USD)

CATEGORY 1 (HQ +

UTDBE)

19,700,000.00 14,936,759.52

CATEGORY 2 (District

Grant)

27,300,000.00 38,941.702.00

CATEGORY 3 (School

Grant)

22,100,000.00 21,621,538.48

UNALLOCATED 6,400,000.00

TOTAL 75,500,000.00 75,500,000.00

Page 83: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

73

Audits

18. Annual audits were conducted to express independent opinion on the financial

statements prepared by GES. The exercise reported on the extent of compliance with

various financial requirements and project guidelines. The Ghana Audit Service was

appointed the independent external auditor for the project. Three annual audits were

conducted for the fiscal years 2013, 2014 and 2015. The 2016 audit will be conducted

by June 2017 with funds escrowed under the project.

19. As part of the World Bank’s Financial Management Supervision, two comprehensive

Financial Management (FM) reviews were conducted by the World Bank supervision

team in 2013 and 2015 and rated the GPEG’s FM’s systems highly satisfactory and

satisfactory respectively. Independent Fiduciary Review: During the course of the

project, two independent fiduciary reviews were undertaken in 2014 and 2016.

20. 2014 Fiduciary Review: Observations and Conclusions. Adequate capacity existed

at the GES headquarters. At all levels of implementation; record keeping,

documentation and reconciliations were up to date, there was clear evidence of regular

inspection and pre-auditing. Proper authorization and controls were exercised.

However, there were lapses in some schools that were brought to the attention of

Management. To strengthen the fiduciary environment, the review suggested more

training in basic bookkeeping for School Heads and there should be clearly defined

basis for distributing items procured. With regard to procurement, there were strong

controls in place and implementation at central level followed all applicable guidelines.

21. 2016 Fiduciary Review. The use of country systems for project management as well

as the development of project implementation manuals to guide project execution was

a key strength of the GPEG/GPASS project. Weaknesses included variations in

documentation of monitoring at the district-level, delayed processing of claims since

district supporting documents often required in-person delivery to Accra.

Procurement

22. Most procurement activities were conducted at district level and were in accordance

with Ghana’s country systems as well as the World Bank procurement guidelines.

Procurement trainings were conducted for participants from all districts. There was

periodic monitoring of district procurement activities. All planned procurements under

goods, works (district level) and consultancy services earmarked under the grant

facility were executed to completion. Again the Bank provided the required supervision

and offered constructive suggestions during implementation support missions.

Procurement under GPEG was rated as satisfactory by the World Bank. The project

undertook an independent procurement audit with the objective to review the

procurement, contracting, and implementation processes which have been followed for

contracts in the project to confirm consistency with the Legal Agreement.

23. The main findings of the In-depth Procurement Review are as follows:

Compliance – most districts had approved procurement plans for all the years.

While all the entities reviewed and adhered to advertising requirements for

Page 84: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

74

applicable contracts. Districts conformed to standard bidding document for goods,

works and services. 65 percent of districts visited showed evidence of complying

will all evaluation procedures and award of contract.

Contract Administration and Performance – 78 percent of District’s goods in the

sample were supplied according to specifications. Similarly, physical works

constructed were executed in accordance with bills of quantities, as evidenced from

the goods delivery notes and certificates of payments reviewed under the contracts.

Record-keeping - Filing system for most of the Districts visited was unsatisfactory.

Separate procurement files were not kept for each contract reviewed. 52 percent of

procurement files were incomplete and lacked proper and sequential arrangements

depicting the procurement cycle.

24. The Procurement Review noted the following recommendations:

Publications - Contract awards should be published on PPA Website in addition to

placing copies on the Notice Board of the Districts.

Awards - Communicating to unsuccessful bidders should be made by the Districts

who are not fulfilling this requirement under the Public Procurement Act 2003.

Implementation - Copies of goods delivery note and certificate of completion of

work should be kept in the procurement file as an evidence of supply of goods or

contractor completing the contract in accordance with the specifications in the

contract agreement.

Compliance - Appropriate procurement procedures as stipulated in the World

Bank’s guidelines and the PPA rules and regulations should be strictly adhered to

by all the Districts. The Districts should also comply fully with the terms and

provisions in the contract agreement signed with contractors providing various

works for the Districts.

Record-keeping - There should be systematic filing of all documents under each

contract in separate files to give a clear audit trail of procurement processes and

documentation. All documents at every stage of the procurement cycle should be

kept in the procurement file.

Capacity Assessment - All the Districts should train and encourage the procurement

officers to be responsible for undertaking and coordinating all detailed procurement

activities within the Districts.

APW Analysis

25. To receive district grants, each district submitted an Annual Program of Work (APW)

which detailed their planned activities along four thematic areas: Access, Quality,

Gender, and Management. Districts reported on the progress on implementing their

activities, actual expenditure and timeframe twice a year. District grants were allocated

based on a resource allocation model which is updated every year and takes into

consideration a number of education indicators weighted with disadvantage criteria to

ensure equity in the allocation of budget ceilings to districts.

Page 85: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

75

26. Average total expenditure for the districts across all years is 95.7%. This increased

through the years from 89 percent in 2013 to 94 percent in 2014 to 99 percent in 2015-

2016.Regional expenditure covered mostly capacity building, monitoring, and

operational activities. Average total expenditure for the regions was 89.4 percent across

all years with 2015-2016 recording over 100 percent due to rolled over activities from

2014. Table 4 details the count of activities along the thematic areas that were executed

under project.

Table 4: Count of Activities Executed in APW by Thematic Area

27. In terms actual expenditure, the largest amount was spent on access, at 54 percent with

the least amount on gender activities at 2.7 percent. (Excluding expenditure on UTDBE

and GPASS). 23.1 percent and 20.2percent of the district budget were spent on quality

and management thematic areas respectively. Most of the access activities were gender

oriented especially the provision of gender friendly sanitation facilities.

Untrained Teacher Diploma in Basic Education

28. The UTDBE activities commenced in August 2012 and ended in August 2016 with

6,480 trainees (from the original 7,027) who are bonded to teach in the districts for at

least 3 years. GPEG supported Capacity Building for the selected institutions delivering

modules, distance learning courses and in-school support and mentoring. A consultant

was engaged to support writers from the COEs and the Universities to write field

support modules and a handbook for Tutor Counselors, Mentors and Coordinators.

In-Service Training

29. GPEG supported the institutionalization of In-service training of teachers for

continuous professional development and capacity building for school management

committees. A core activity for all districts for funding under the AWP was INSET and

over 96,000 trainings over the project period. Some of the trainings included, INSETs

in Literacy, Mathematics and Science, Braille,and ICT, as well as trainings for head

teachers and SMC members. The project also funded capacity building for the key

officers at the districts managing the conduct and monitoring of INSET and also funded

TA for the development of INSET manuals and teacher mentorship guides.

2013 2014 2015/16 TOTAL

Count Count Count Count Proportion

Access 181 283 596 1,059 22.3%

Quality 317 448 639 1,407 29.5%

Gender 146 126 142 414 8.7%

Management 340 651 889 1,878 39.5%

TOTAL 984 1,508 2,266 4,758 100.0%

Page 86: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

76

30. Girls Participatory Approach to Student Success (GPASS) included the following

activities:

Scholarship Package: A total of 60,000 girls have received the scholarship

package which included: exam fees, school uniform, and school supplies and

stationery; in some cases this also included a bicycle and solar lamp.

Training, Capacity Building and Review: A series of trainings were held for

District Education Officials and School Based Facilitators. Districts and GEU

headquarters were provided with ICT packages along with ICT training.

Furthermore, a budget was provided for administration, communication and

maintenance at all levels. Annual reviews discussed implementation and provided

feedback which helped to facilitate smoother implementation.

Community Sensitization: This was done to help adults better appreciate the

importance of girl’s education and support the program. In some cases, the outreach

activities encouraged out of school girls to return to school.

Monitoring: This occurred at all levels and focused on the distribution of

scholarship packages, performance and attendance. Reports were submitted to the

GEU head office, shared with GES management and DFID, and were also

incorporated in GPEG annual reports.

School Grants

31. The school grant comprised a base and a per-capita grant formula paid in two tranches.

See Table 5 for information on school grant allocations throughout the project period.

A total of 7,465 public basic schools were benefiting from the grant as of the end of the

project covering a total of 1,930,878 students. Over the project period, an average of

85 percent execution rate was recorded in school grant utilization, improving from 72

percent in 2013 to 92 percent by project closing.

Table 5: School grant allocation (per school)

32. In order to receive in School Grants, schools performed the following:

SPIPs: School Performance Improvement Plan (SPIP) was the basis of spending

for the school grants. It was developed by the schools in collaboration with the

SMC informed by the SRC.

SPAMs: The School Performance Appraisal Meeting was used as an

accountability mechanism to relay school performance back to stakeholders and

feeds into SPIP preparation.

Type of Grant 2013

GHC

2014 GHC 2015 GHC

Base Grant KG 650 800 1150

Prim 1000 1200 1650

JHS 800 1000 1350

Per-Capita 3.62 4.00 4.50

Page 87: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

77

School Report Cards (SRC): The SRC collected information from schools

concerning pupils, teachers and management at the school level. The school

communicated the analysis through the SPAM, and used it in the preparation of

the SPIP. GPEG made funds available to collect the information for SRCs,

generate reports, and feed them back to schools. GPEG monitored that SPAMs

were being held regularly to discuss the data with the community. The

percentage of school with up-to-date SRCs increased from 95 percent in 2013

to 98 percent in 2015-2016. The percentage of schools with SRCs displayed on

their notice board rose from 79 percent in 2013 to 93 percent in 2016.

33. Circuit Supervisor Visits: The average number of school visits by circuit supervisors

was 7.1 per school/year across all districts over the project implementation period.

There has been steady improvement across the years. 2013 recorded an average of 5.9

circuit supervisor visits per school, 2014 at 7.4 and 2015/16 at 7.8.

Monitoring and Data Collection for Reporting

34. Monitoring by PBME: Seven monitoring trips were undertaken during the project

period. The visits confirmed: the status of implementation and spending performance

on APWs and SPIPs; the approval process and challenges with SPIP; the collaboration

between Districts and Colleges of Education; and status of a sampled on-going projects.

Some of the main findings at the district level included: reporting had improved over

time; SRCs were not always distributed on time to the schools; Districts were not

always able to obtain regular reports from COEs. At the school level: Improvements in

school management; supply of TLMs; Non-availability of reputable vendors in most

localities; Lack of capacity in book-keeping; and problems in understanding and

interpreting SRCs by school staff.

35. Monitoring Activities by Districts: In an effort to provide standardized feedback from

DEOs, a template for a Performance and Monitoring Report was introduced. The

reports indicated that district officials ensured judicious use of school grants and

contractors on site used quality materials and completed their work on schedule.

Supervision improved in all GPEG districts. Data Collection: Headquarters met

district officers twice a year, to collect data on APW, financial, procurement, SGRs,

and training reports using predetermined templates. As the years went on, reporting as

well as cash book entries at the district level improved substantially.

Project Management

36. The project management, monitoring and evaluation was carried out through

collaboration between the GPEG technical implementation team made up of GES

Finance, Basic Education, Supply and Logistics, Teacher Education, Girls Education

Unit, and the PBME Division of the MoE. GES management was responsible for the

overall project administration supported by a project coordinator. The central Ministry

executed Component 3 of the project and prepared an annual work plan covering four

major areas: (i) operations - to cater for the day-to-day overhead cost for running the

project; (ii) monitoring- checking and following up on project execution to provide

feedback into implementation; (iii) training- providing capacity building to support

Page 88: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

78

project implementation; and (iv) consultancy- technical assistance to support capacity

for key areas and also independent external reviews and impact evaluation.

37. Steering Committee Meetings: A Project Steering Committee chaired by the Chief

Director of the MoE met five times to review annual plans and implementation status.

The PSC also had LEG and civil society representation.

38. Mid-Term Review: A project Mid-Term Review (MTR) involving all stakeholders

was conducted from February 23-March 6, 2015. The MTR report and the MTR

Mission concluded that: Project implementation was progressing; disbursements were

in line with projections; project indicator targets were being met; GPEG had

strengthened the participation of stakeholders in planning and management; enrolment

had increased while intensified monitoring and evaluation had improved both teacher

and pupil attendance; teaching and learning materials were provided to basic schools

and INSET in key areas were available to teachers. Areas for improvement included

the timely allocation and implementation of school and district grants, strengthening

SMCs, providing more timely collated reporting on school and district activities and

improving support for UTDBE trainees.

Achievement of Project Development Objectives and Impact

39. The PDO was to “improve the planning, monitoring and delivery of basic education

services in deprived districts” in Ghana. The Results Framework tracked progress made

against indicators on an annual basis. The PDO was achieved as all indicators were met.

40. UTDBE Quality Assurance: An independent training and research institution, Center

for Continuing Education, University of Education, at Winneba was contracted to

provide quality assurance on the delivery of the UTDBE program. This consultancy

provided feedback and recommendations for improvement to the Colleges of Education

delivering the UTDBE program and the Teacher Education Division over the program

implementation period. The main reasons for dropout (majority for which occurred in

the first year) were, death, withdrawal due to underachievement and leaving the

teaching profession for other professions. Many of the coordinators did not keep up to

date records of the trainees. Heads of the schools offered both academic and

professional support to the trainees. These included in-service training, lesson notes

preparation, lesson observations and demonstration lessons. However, there remained

inadequate resources to engage adequate facilitators for school-based INSET. The

District Coordinators were not able to support student teachers with the organization of

cluster meetings and tutorials due to inadequate allowance paid to teachers for cluster

meeting, poor attendance of tutors, ineffective communication channels and late

releases of results from the examining body.

41. UTDBE Impact Assessment and Lesson Observation Survey: An impact evaluation

was carried out to assess the extent to which the distance training program had achieved

its objective of upgrading the quality of teaching skills among untrained teachers in the

deprived districts and the extent to which this had impacted on learning outcomes. A

comparison at baseline and endline was also made in terms of cost efficiency. The

Page 89: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

79

assessment also explored whether training while teaching results in teacher retention in

deprived districts.

42. Field work: The impact evaluation was carried out over a two-year period between

2014 and 2016. The baseline, midline and endline reports present findings on the

content knowledge and skills gained by UTDBE trainees compared to the trained DBE

teachers across the core areas of lesson planning/preparation, teaching methodology,

classroom organization and management. The endline assessment also explored the

retention status of teachers in rural deprived areas. The study used both qualitative and

quantitative approaches and included single face-to-face interviews and questionnaires.

However, the main data collection instrument was a well-tested instrument - the

Classroom Lesson Observation Schedule (LOS).

43. The UTDBE IE had the following key findings:

Performance of UTDBE Trainees: It was affirmed that the trainees have had their

knowledge and experience deepened as a result of the UTDBE program. The

baseline and endline comparison reveals that the UTDBE trainees had improved

remarkably in performance over that of the baseline. However, when the endline is

compared to the midline there was some decline in performance.

Comparative Analysis of UTDBE and DBE Teachers: The comparison of

examination results showed that, while the DBE trainees performed better in the

core subject area of Integrated Science, the UTDBE trainees performed better in

the professional field course of Trends in Education and School Management. The

endline findings showed that more DBEs were ranked satisfactorily compared to

the UTDBEs in relation to the use of generic skills; however, the UTDBE trainees

scored better in relation to the use of teaching and learning materials.

Cost Efficiency and Effectiveness: The endline study revealed that the UTDBE

program is more cost effective relative to the DBE model of training even without

allowance for conventional trainees. Thus, training a teacher on the conventional

mode (DBE) cost the government 60 percent more than the cost of training a teacher

using the UTDBE modality

Retention in Deprived Districts: The endline findings suggested that a higher

proportion of UTDBE trainees compared to DBE teachers are willing to stay in

rural deprived areas due to community affiliation.

44. As a result of the UTDBE IE, the following key recommendations were made on

the UTDBE program:

Efforts should be made to reduce the high incidence of drop out;

UTDBE program course content should be reviewed to ensure that basic literacy

and numeracy content meet current needs of the basic school teachers and be made

more relevant to the levels of education where they are expected to teach;

More involvement of Colleges in district cluster meetings;

Circuit Supervisors and Head teachers should be empowered to intensify their

mentoring, coaching, monitoring and supervision of UTDBE trainees;

Page 90: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

80

Government should adopt the UTDBE training mode to increase teacher retention

and assume a less expensive approach;

CoEs need to prepare well for the face to face sessions with UTDBE trainees;

The trainees should be on the Government payroll once they graduate.

Project Impact Evaluation:

45. Edburgh Consultants, based in the Netherlands, were contracted for the overall

impact evaluation of the GPEG intervention. Their work can be divided into two main

tasks: Task 1 covers impact evaluation of higher order outcomes whiles Task 2 covers

Survey at the school and district levels in all 75 GPEG districts. This section gives an

overview of the results.

46. Impact evaluation of higher order outcomes: This involves a desk review of higher

order outcomes specifically related to BECE and EGRA/EGMA examination results,

Primary to JHS transition rates, dropout rates, Net Admission Rate, Net Enrolment Rate,

Gender Parity Index, etc. It relies on the collection of data from secondary sources such

as EMIS, BECE examination results, EGRA/EGMA results (latest year: 2014/15), and

SRCs. Outcomes in GPEG districts were compared to a subset of 75 non-GPEG

districts that were closest to the cut-off ranking for selection as a GPEG district. The

results were combined with the results of Task 2 to prepare the final evaluation report.

47. The main findings from task 1included:

Access: The GPEG had a positive impact on access and participation in GPEG

districts in comparison to comparable non-GPEG districts at all levels in relation to

NAR,NER, proportion of disabled children enrolled and Primary to JHS transition.

However, GPEG districts did not record an improvement in overall dropout rates

at any of the levels compared to comparable non-GPEG districts.

Gender: Dropout rates of girls and the dropout GPI at all levels as well as GPI at

the JHS level improved substantially more for GPEG districts compared to

comparable non-GPEG districts.

Quality: While it is too early to measure the full impact of GPEG on BECE, it is

worth stating that it has encouraged a higher number of children to take the exam,

and more are passing now than before. However, relative to comparable non-GPEG

districts, BECE pass rates in GPEG districts have declined while the gender gap in

BECE pass rates have widened. Poorer performance in BECE results in GPEG

districts could be attributed to negative effects of increased access which could

reverse in future as a result of the benefit from improvements in teaching and

education management that have been brought about by the GPEG. GPEG districts

registered statistically significant improvements in some areas of EGRA/EGMA

between 2013 and 2015, with no decline in performance noted.

Page 91: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

81

48. The survey at the school and district level in all 75 GPEG districts looked deeper into

the findings in Task 1 to understand the impact of GPEG in the deprived districts. The

survey took place in all 75 districts and 353 schools representatively sampled, with the

support of questionnaires responded to by District Education Officers, Circuit

Supervisors, Head Teachers and School Management Committees. The survey found

that in general, there has been improved management at the district level with DDEs

and Circuit Supervisors frequently using management tools such as the SRCs, SPIPs,

etc. Respondents at the district level were satisfied with the training provided during

the project; however, the frequent retirement and transfers of DDEs remains a concern.

SMCs and Head teachers require more training in the production and use of SRCs.

School level management has also improved as head teachers seem to be satisfied with

the circuit supervisors visits in terms of frequency and feedback provided, and the

involvement of parents and communities in school matters has increased. Additionally,

teacher motivation has increased and teachers spent more time teaching, and the study

found that INSET trainings were appreciated by the teacher trainees.

Update of district rankings

49. At the end of GPEG, the selection criteria to all of Ghana’s 216 districts was reapplied

to see whether the deprived districts have moved up in ranking. The poverty headcount

was obtained from an updated ranking that combines the Population and Housing

Census (PHC) 2010 and the Ghana Living Standards Survey (GLSS) 6 conducted in

2012. Education indicators were obtained from the 2015/16 EMIS data. The new

rankings show that, 57 of the 75 GPEG districts remain in the top 75 most deprived

districts while 18 are no longer in them. The most deprived district is Gushiegu in the

Northern region. Juaboso in the Western region has made the most progress and now

ranks 152 out of the 216 in terms of being deprived.

Girls PASS

50. GPASS data from schools is collected through Excel templates by district officers

District databases showed the following positive results:

a. Overall, the GPASS girls are ranked in the top 43% of their class and are

achieving aggregate 36 in BECEs.

b. Non-GPASS students are performing slightly better than PASS girls, as

expected due to the type of student selected for GPASS.

c. On average GPASS girls are attending school 91 percent of the time with 4

percent higher average attendance than non-GPASS students. Monitoring trips

also consistently show high attendance rates for the GPASS girls.

d. District level data shows that the transition rate to SHS or TVET for GPASS

girls is on average 78 percent, compared to a national average of 69 percent

(EMIS, 2014/15).

51. The following areas remain challenges for the GPASS program:

a. Dropouts due to pregnancy and marriage. The current dropout rate of GPASS

full phase is 0.83 percent (394 cases), with 33 percent of those dropouts caused

by pregnancy. Marriage led to 51 dropouts. Results also showed that 73 percent

Page 92: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

82

of all pregnancy cases on GPASS lead to dropout. Only 14% of teachers in the

GPASS schools were female, and 48% of SBFs were female.

b. Girl-friendly infrastructure. A recent monitoring visit suggests there has been

an improvement in child-friendly environments in the GPASS schools over

time with 19 out of 21 schools having separate toilets for boys and girls (90%),

and the majority having access to hand washing. However only 6 out of 22

schools had a bin for sanitary pads, and only 6 out of 21 had flushing facilities

for the toilets. Results show that 20 out of 23 schools had access to electricity

(87%), and 19 out of 22 had access to water (86%).

GPEG Lessons Learned and Sustainability

52. The data revealed key lessons and project implementation challenges including:

frequent staff turnover, lack of coordination between regional offices and districts,

difficulty in providing effective oversight of the implementation at the district and

school levels, and lack of sound and timely report writing at regional and district level.

53. Key lessons learned from the Beneficiary Assessment are that decentralization can be

achieved, and targeting as a resource allocation tool is effective. Leadership, good

record keeping and accountability mechanisms are essential for successful outcomes,

capacity training at several levels was a key component to the success of GPEG.

Empowering districts to plan and prioritize their needs, ensuring community and

stakeholder engagement in school management and teacher skills upgrading through

INSETs could be achieved with minimal funding.

54. Key recommendations on lessons learned, sustainability, and future arrangements:

INSET: New guidelines issued to include organization of relevant INSET as a

mandatory activity.

Trained teachers, teacher retention, and UTDBE: Transfer/posting policy should

be reviewed. The UTDBE program should be continued but should no longer be

funded by the GOG. Again an analysis should be conducted to determine how many

teachers are needed to reduce the PTTR level to GES acceptable norms and new

teachers should have trained mentors. UTDBE trainees who are not on Government

payroll should be prioritized in recruitment of teachers.

Community involvement and participation: Local champions should be

recognized and be empowered to engage in school activities.

School supervision: A concise template should be designed to simplify the format

Circuit Supervisors use to report. The mobile School Report Card should also be

expanded to include all districts.

SPIPs, SPAMs, SRCs: SPIP must be prepared regardless of funding to make it

functional. BECE results for JHS and EGRA/EGMA/NEA results for KG/Primary

should be the basis for holding SPAMs. It is important to ensure vertical linkages

in planning throughout the system between SPIPs, ADEOP regional plans and

national level plans.

Page 93: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

83

Girls PASS: A selection committee for scholarships should be retained at the

district level. More research should be conducted on better targeting scholarships

including tracking the current GPASS beneficiaries through SHS. Scholarships

must be targeted to the neediest.

Staffing and Capacity Building: HR staff at the DEOs must have the requisite

background, hardworking teachers and high performing pupils should be motivated,

there should be a network of communication across DEOs, capacity building

activities must be coordinated, DEO staff should be given consistent ICT training,

Heads should be provided with leadership training.

Planning: data should be the bases of decisions and this must be shared and

communicated appropriately.

Testing/Assessment: Districts should administer standardized exams for their

district. The policy of creating item banks at the district level should be enforced to

ensure the sustainability of initiatives like EGRA/EGMA/NEA.

School Financing: the capitation grant amount should be reviewed regularly and

must include a base grant.

Stakeholders Assessment of Project

LEG’s Assessment of GPEG Implementation

55. The GPE grant has played a significant role in expanding quality access and

participation especially where and for whom it matters most:

Targeting: The focus on 75 districts primarily in the deprived districts located in

the northern Ghana ensured the availability of adequate and predictable funds for

those most in need and demonstrated the utility of targeting in making education

accessible especially for girls and boys in poor communities.

Better alignment and coordination: The targeted focus has also influenced

development partners to invest in the deprived districts; and also align and

coordinate their activities. For instance the alignment between DfID supported

Girls Pass scholarship program and the GPE grant in the 75 districts has allowed

for effective coordination, capacity-building, implementation and monitoring by

the Girls Education Unit at both the national and district level.

Systems Strengthening: The use of GPE funds to improve on planning, monitoring

and delivery of basic education services in districts also highlights the importance

of systemic change and the need to strengthen the entire education systems and not

just individual elements; and empowering districts to choose and lead on their own

pathways to progress;

Introducing new ideas and innovation: For example the district grants and school

grants, the latter as a combination of a base grant as well as a per-capita school

grant so as not to short-change smaller and remote schools; & practice of school

report cards at scale for increased management accountability, and which UNICEF

is now supporting the expansion through mobile School Report Cards.

Page 94: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

84

Government Assessment of the Supervising Entity’s Performance

56. The World Bank served as the supervising entity for the GPEG project. The

Government greatly benefitted from the World Bank’s support in financial

management, procurement and understanding World Bank guidelines. Additionally,

the Government commends the bank on granting approvals with minimal delays. The

Government found that support missions were extremely useful in ironing out

challenges. The Bank’s procedures and systems lent itself to the use of country systems

which made project implementation smoother.

57. The Government were particularly appreciative of the World Bank’s support in

reviewing documentation by the impact evaluation firm, Edburgh, and assisting with

technical support for the evaluation as well as advice.

Page 95: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

85

Annex 8. Comments of Cofinanciers and Other Partners/Stakeholders

N/A

Page 96: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

86

Annex 9. List of Supporting Documents

Aide Memoires and Implementation Status Reports (April 28, 2013 –August 31, 2016).

Basic Education Beyond the MDGs in Ghana, 2014- World Bank, Darvas and Balwanz.

Beneficiary Assessment, MOE/GES October 2016.

DFID annual reviews of Girls’ PASS program 2014-2016.

Documentaries on MOE and GPE websites 2016.

Ruhainatu dreams of becoming a nurse.

https://www.youtube.com/watch?v=qBA3X7NQDNM

GPE helps strengthen Ghana’s education system (short).

https://www.youtube.com/watch?v=epkJ9j-uKFo

Empowered to Learn – Learn to be Empowered (long video).

https://www.youtube.com/watch?v=X39v_sFNETo

Education Sector Performance Reports, MOE (ESPRs 2011-2016).

EGRA/EGMA reports 2013, 2015.

Final Main Procurement Audit Report, February 2017. Benning, Anang and Partners.

Ghana Project Completion Report, GES/MOE December 2016.

GPEG Project Implementation Manual, January 2013 Ghana Education Service/Ministry

of Education.

GPEG Government status reports 2013, 2014, 2015, and 2016.

GPEG Fiduciary Reviews 2014 and 2016.

GPEG Procurement Audit 2016.

GPEG MTR reports February 2015.

GPEG PAD, October 2012.

GPEG application to GPE June 2012.

GPE Tracking by the Social Enterprise Development Foundation of West Africa (SEND)

2015.

Page 97: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

87

ICR for EdSeP 2013 World Bank.

ICR for EFA-FTI 2012 World Bank.

“Impact Assessment of the Untrained Teacher Diploma in Basic Education (UTDBE)

Program.” Baseline, Midline and Endline Surveys, Prepared by Associates for

Change, 2014, 2015 and 2016.

“Impact evaluation and monitoring of the District Grant and School Grant component of

the Ghana Partnership for Education Grant.” by Edburgh consultants and Innovative

Services consortium August 2016.

Impact Evaluation of School Based Management Committees, 2010. M-H Cloutier,

World Bank.

Murphy, Paud (2012) “The Untrained Teacher Diploma in Basic Education in Ghana:

Analysis and Recommendations: Second Draft”.

National Education Assessment (NEA) reports.

NDPC Citizen’s Assessment Survey on Capitation Grant Policy, NDPC and UNICEF

June 2015.

SABER on Student Assessment- World Bank November 2013

“Transparency and Accountability Processes in the Utilization of Grant Support Under

GPEG Project Tracking Survey” Ghana National Education Campaign Coalition

(GNECC) July 2014.

Page 98: World Bank Document · 2/27/2017  · GEU Girls Education Unit TED Teacher Education Division GLSS Ghana Living Standards Survey TIMSS Trends in International Math and Science Study

88

MAP of Ghana – IBRD 33411


Recommended