+ All Categories
Home > Documents > World Bank Documentdocuments.worldbank.org/curated/en/419471468042574431/...The length of the...

World Bank Documentdocuments.worldbank.org/curated/en/419471468042574431/...The length of the...

Date post: 10-Jul-2020
Category:
Upload: others
View: 2 times
Download: 1 times
Share this document with a friend
311
REPUBLIC OF IRAQ MINISTRY OF CONSTRUCTION AND HOUSING ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT STUDY (ESIA) OF THE REHABILITATION OF EXPRESSWAY NO. 1 IN IRAQ (ERRP.CON.SSS.ESIA EW-1) DRAFT FINAL REPORT August 19, 2013 Partners in building an emerging world Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized
Transcript
  • REPUBLIC OF IRAQ

    MINISTRY OF CONSTRUCTION AND HOUSING

    ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT STUDY

    (ESIA)

    OF

    THE REHABILITATION OF EXPRESSWAY NO. 1 IN IRAQ

    (ERRP.CON.SSS.ESIA EW-1)

    DRAFT FINAL REPORT

    August 19, 2013

    Partners in building an emerging world

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    Final ESIA Report S-i Consolidated Consultants

    EXECUTIVE SUMMARY

    TABLE OF CONTENTS

    Page

    1. INTRODUCTION S-1

    2. LEGAL AND ADMINISTRATIVE FRAMEWORK S-1

    3. PROJECT DESCRIPTION S-2

    4. ENVIRONMENTAL AND SOCIAL BASELINE CONDITIONS S-4

    5. PUBLIC CONSULTATION S-5

    6. ENVIRONMENTAL AND SOCIAL IMPACT ANALYSIS S-6

    7. MITIGATION MEASURES S-7

    8. ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN (ESMP) S-8

    9. MONITORING AND INSTITUTIONAL STRENGTHENING S-9

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    EXECUTIVE SUMMARY

    Final Revised ESIA Report S-1 Consolidated Consultants

    EXECUTIVE SUMMARY

    1. INTRODUCTION

    This executive summary aims at presenting the main findings of the Environmental and Social

    Impact Assessment (ESIA) conducted for the Rehabilitation of the Expressway no.1. The objective

    of the environmental and social assessment is to examine the environmental, and social impacts of

    the project (both construction and maintenance phase), and to propose mitigation measures, as well

    as providing the management plan of the proposed project.

    This specific project activity is mandated by Iraqi Environmental Law and its guidelines for ESIA

    preparation. The Transport Corridors Project is categorized as an A, requiring an environmental and

    social assessment in accordance with the World Bank's Operational Policy on Environmental

    Assessment (OP 4.01) and Involuntary Resettlement Policy (OP4.12).

    The document consists of the following chapters: legal and administrative framework, project

    description, environmental and social baseline conditions, public consultation, environmental and

    social impact analysis, mitigation measures, monitoring, and environmental and social management

    plan.

    2. LEGAL AND ADMINISTRATIVE FRAMEWORK

    A desk study was carried out by the study team to assess and prepare the most applicable legal and

    administrative framework to the proposed project. The assessment has taken into consideration, both

    the potential Iraqi environmental laws and those policies and procedures of the World Bank related

    to the subject project.

    Iraqi Environmental Laws

    Regulations no. 2 for the year 2001: Preservation of Water Resources

    Law no. 27 for the year 2009: Protection and Improvement of Environment

    Law no. 37 for the year 2008: The Ministry of Environment

    Law no. 55 for the year 2002: The Law of Antiquities and Heritage

    World Bank's Policies and Procedures

    The World Bank has 10 current Operational Policies and Procedures:

    - Pest Management (OP/BP 4.09)

    - Environmental Assessment (OP/BP 4.01)

    - Natural Habitats (OP/BP 4.04)

    - Safety of Dams (OP/BP 4.37)

    - Projects on International Waterways (OP/BP 7.50)

    - Projects in Disputed Areas (OP/BP 7.60)

    - Forests (OP/BP 4.36)

    - Involuntary Resettlement (OP/BP 4.12)

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    EXECUTIVE SUMMARY

    Final Revised ESIA Report S-2 Consolidated Consultants

    - Indigenous Peoples (OP/BP 4.10)

    - Physical Cultural Resources (OP/BP 4.11)

    The policies that apply and are triggered for this project are:

    - Environmental Assessment (OP/BP 4.01).

    - Involuntary Resettlement (OP/BP 4.12).

    3. PROJECT DESCRIPTION

    One of the Components proposed under the Iraq Transport Corridors Project is the rehabilitation of

    Sections 7, 8 and 9 of Expressway No. 1 (See Table 1). The investments under this Component will

    cover the installation of guardrails, signage, road marking, chain link fence and patching and paving

    as needed along the 3 sections. However, it was agreed that the World Bank Safeguard Policies will

    apply to all other sections to be rehabilitated in parallel irrespective of the source of funding;

    therefore they are included in this ESIA. Table I gives the details of all sections of Expressway I to

    be rehabilitated. All the project activities are within the right of way of existing road alignments and

    there is no land acquisition involved of any kind.

    Table I: Expressway 1 Sections

    Section Part Length [km]

    R4: Baghdad West – Hilla Southern 105

    R5: Hilla – Diwaniya Southern 77

    R6: Diwaniya-Nasiria Southern 145

    R7: Nasiria – Rumaila Southern 145

    R8A: Rumaila – Basra

    R8B: Rumaila – Safwan

    Southern

    Southern

    31

    81

    R9A: Baghdad West – Habbaniya

    R9B: Habbaniya – Hit

    Western

    Western

    63

    61

    R10: Hit – Tullaha Western 134

    R11: Tullaha – Rutba Western 137

    R12: Rutba - Jordanian border Western 129

    R13: Jordanian junction-Syrian border Western 76

    The Expressway is more than twenty years old. The length of the Southern Part of the road (from

    Baghdad to Safwan-Basra interchange) is about 510 km of 3x3 lanes with standing lane (15.5m

    width), then the road splits into a 51 km 2X2 lane heading to Basra, and 64 km 2X2 lane heading to

    Safwan. The southern part includes a section from Diwaniya to Nasiriya (R6) that is 145 km long

    and under construction with funding from the Government of Iraq. There is no ESIA and ESMP

    done for this section, it has been in construction on and off for several years.

    The Government of Iraq has committed to applying the World Bank Safeguards Policies to the

    entire Expressway 1. This includes the segments of Expressway 1 that are not supported by the

    World Bank and under rehabilitation or construction. As such the environmental and social due

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    EXECUTIVE SUMMARY

    Final Revised ESIA Report S-3 Consolidated Consultants

    diligence of these road segments will include the preparation of environmental audits and

    resettlement audits prior to the end of the appraisal period of the World Bank funded road segments.

    These environmental and social audits will assess the non-Bank funded road segments compliance

    with the safeguards policies, identify any gaps in terms of environmental and social management

    and develop corrective action plans, if needed.

    Whereas, the Western Part of the road starting from Bagdad to Rutbah is a 455 km 3X3 lane with

    standing lane (15.5m width), splitting into two 2X2 lane roads, from Rutbah to Tribel ( Jordanian

    Border), and Rutbah to Al Walid ( Syrian Border). Figure A below shows the Expressway path

    (both western and southern). The expressway passes through several governorates of Iraq such as Al

    Anbar, Baghdad, Babel, Al Qadisiya, Al Muthanna, Dhi Qar and Basra.

    The existing features of Expressway No. 1 include:

    Length (including interchanges length): 1250 km

    6-lane sections: 800 km (except for the Diwaniya – Nasiriya section that is currently under

    construction)

    4-lane sections: 450 km

    Number of interchanges: 25

    Number of expressway branches: 3

    80 expressway bridges with total length: 9230 m

    117 road overpasses with total length: 6820 m

    Number of rest areas with fuel station: 18

    Number of parking areas: 200

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    EXECUTIVE SUMMARY

    Final Revised ESIA Report S-4 Consolidated Consultants

    Figure A: Map of Iraq showing the path of Expressway No. 1

    The proposed Project works will include the following road maintenance/rehabilitation type of

    activities:

    Road marking

    Installation of guardrails between both sides and on sides where necessary

    Installation of signs and road furniture

    Installation of a chain link fence on both sides of the road

    Rehabilitation of the asphalt as needed

    Other rehabilitation works as determined necessary by the technical assessment

    4. ENVIRONMENTAL AND SOCIAL BASELINE CONDITIONS

    The expressway spans most of the western, central and southern territories of Iraq. It crosses flat

    land, primarily desert and semi-desert. The western section of the road crosses sparsely populated

    area; the central and southern part crosses more densely populated agricultural land. Most of the

    expressway passes through agricultural land within 6 governorates and 17 population centres. The

    total population of the urban centres affected by the project is approximately 5.6 million inhabitants.

    The present road conditions ranges from good to moderate. There is effectively no road signage and

    road furniture. Lighting is available on very limited stretches. There is no currently fence on either

    side or in the middle of the expressway as major parts of the fences have been demolished by the

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    EXECUTIVE SUMMARY

    Final Revised ESIA Report S-5 Consolidated Consultants

    occupation forces and others by inhabitants.

    The western section of the expressway crosses Mesopotamian shrub desert, while the southern

    section crosses the Arabian Desert and shrublands. The most southern section of the road runs

    parallel to the Tigris-Euphrates Alluvial Salt Marshes. The road is occasionally crossed by wild

    mammals as there is currently no fencing. The road passes 2km from the boundary of the Important

    Bird Area (IBA) of Habbaniya.

    The land use along expressway consists of sparsely populated or exploited plains, agricultural lands,

    and some urbanized areas. The predominant land use is agriculture. Some sections of the

    expressway are close to protected ecosystems, in particular areas designated as IBAs by the World

    Wildlife Fund and Birdlife International. Prominent among these IBAs in terms of birds and

    diversity of species is the Haur Al-Hammar critical wetlands. Industrial land use is rare or almost

    non-existent. The establishments are mainly public administration (governorate offices, formal army

    and police posts); farms; shops and services; licensed retail including small kiosks and restaurants;

    and small and informal businesses and vendors that sometimes encroach on the ROW (tire shops,

    car washers etc.).

    Considerable encroachment on the Expressway ROW has occurred over the years. An inventory of

    the encroaching entities was undertaken in August 2012 and was augmented in June, 2013. These

    inventories informed the Baseline Census conducted for the Resettlement Action Plan (RAP) which

    identifies PAPs adversely affected by the project and details mitigation and compensation measures.

    The RAP Baseline Census identified 151 entities encroached on the Expressway ROW. None of

    these were dwellings. Almost all are small businesses serving passing traffic, some of which appear

    to operate only on a seasonal basis. Twenty six of the entities are public, including police stations,

    check points and other public services such as fuel stations. Hence, a total of 125 entities

    encroached on the Expressway will need to be relocated. Relocation of these entities will be

    handled under the RAP.

    No site specific Environmental data along the road alignment have been collected but monitoring

    data collected by the Ministry of Environment from Bagdad and Al-Zubair stations have been

    presented. The noise levels are elevated when heavy trucks are located.

    5. PUBLIC CONSULTATIONS

    Extensive public consultations were undertaken along the full length of the alignment and with a

    wide array of stakeholders including, public sector officials at the community and local government

    level; owners and workers in licenced establishments operating along the roadway including gas

    stations, restaurants, shops, vehicle workshops, and vendors; operators of unlicensed and

    encroaching entities (larger- and smaller-scale) along the Expressway including tire repair shops,

    vendors, food services, etc.; farmers and herders; and individual community members, including

    .men, women and youth.

    Public consultations occurred through two modes. One method used was one-on-one or small group

    discussions and interviews. Annex 1 lists the 25 points along the Expressway where these

    interviews were held. The second method of consultation was via larger town hall-type meetings.

    Two such meetings were held, one towards the western end of the Expressway and one towards the

    eastern end. Direct and open invitations were issued to these meetings and transportation to the

    venues were facilitated for those wishing to participate. Over 60 participants participated in each of

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    EXECUTIVE SUMMARY

    Final Revised ESIA Report S-6 Consolidated Consultants

    the town halls.

    Annex 2 contains detailed information about the town hall consultations.

    The consultations revealed that there was widespread support for the improvement and upgrading of

    Expressway 1. PAPs acknowledged the danger presented to both travellers and roadside entities by

    the poor road quality and fast moving traffic. PAPs were also strongly supportive of the proposed

    relocation of roadside business entities to conglomerates on lay-bys which would have new services

    and be clustered around gas stations; they felt that this would significantly improve their business

    opportunities, plus it would provide them with access to new, important facilities such as WCs and

    waste disposal. No concerns were expressed about movement of facilities to the new lay-bys or to

    daily travel to the new lay-by sites since the relocation sites will be in close proximity to their

    existing concerns and will, in many cases, assist the entities in improving the standard of their

    structures. PAPs working in smaller, unlicensed concerns which have encroached on the ROW were

    very supportive of the relocation since their facilities would be upgraded and they would be

    allocated a formal site on which to operate. Stakeholders were also very supportive of road work

    opportunities being provided to local residents given the prevailing high unemployment rate.

    The consultations highlighted a number of concerns and interests of PAPs which are being acted

    upon by the MOCH. These included: the need for establishment of formal parking areas adjacent to

    the new lay-bys for vehicles, and particularly freight trucks, to ensure order and safety; the

    relocation of police and security centres along the Expressway as their current inappropriate

    locations are widely considered to cause accidents; provision of lighting at the lay-bys for security

    and safety; provision of adequate numbers of overpasses to serve community members who need to

    cross the road; rehabilitation of underpasses for agricultural and herding enterprises along the road;

    reduce the opportunities for vehicles to make u-turns since this is causing accidents; and need for

    improved signage and traffic control (including for speeding) on the road.

    6. ENVIRONMENTAL AND SOCIAL IMPACT ANALYSIS

    The environmental and social impact assessment started with the scoping analysis where the key

    potential impacts were identified followed by more details impact analysis. The negative

    environmental and social impacts of the construction activities of the project are expected to be

    relatively minor and short-term. None of the identified negative impacts of individual construction

    activities was scored as particularly significant.

    The project activities with the highest number of identified negative impacts are:

    - relocation of small businesses which have encroached on the ROW;

    - traffic diversion and construction of access points;

    - installation of fence on both sides of the road;

    - restoration of road surface;

    - rehabilitation of bridges and underpasses;

    - generation and disposal of construction waste; and

    - operation of the workers camps.

    Predicted negative environmental impacts:

    Physical aspects mostly affected by the construction phase are: noise level and air quality.

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    EXECUTIVE SUMMARY

    Final Revised ESIA Report S-7 Consolidated Consultants

    The most sensitive physical and ecological aspects of the receiving environment are found to

    be noise emission and ecosystem fragmentation.

    The ecological aspects mostly affected by the construction phase include impacts of fencing

    and rehabilitation (resulting in very temporary closures) of underpasses on grassland and

    desert ecosystems.

    The potential impact that might affect the IBA is noise during the construction activities.

    However, the distance to the IBA is sufficient to render the noise impact minor. Thus, the

    impact level is considered “low”.

    Predicted negative social impacts:

    Negative social impacts of the construction phase of the project are related primarily to

    relocation of small businesses which have encroached on the ROW, road and labour safety,

    and operation of the labour camps.

    The social aspects related to encroachers on the ROW will be addressed through the

    implementation of a Resettlement Action Plan (RAP).

    The relocation of small businesses on the ROW is planned to be undertaken only after

    completion of alternative dedicated lay-bys which will provide vending areas, easy access

    for passing traffic with parking, and provision of basic services. The provision of completed

    lay-bys before relocation is being done to minimize livelihood losses by small businesses

    during the actual relocation.

    The most sensitive social aspects of the project are: relocation of small business located on

    the ROW, provision of local employment on the road works, maintenance of integrity of the

    local community, and clearing of the existing underpasses for farmers and farm equipment,

    herders and livestock, and other persons to facilitate easy access from one side of the

    Expressway to the other.

    Predicted combined negative impacts:

    The most significant negative impacts – which are still of relatively minor significant –

    resulting from the combination of impact significance, weight of the construction activities,

    and sensitivity of the receiving environment and social context are: impact of road fencing

    on agricultural activities spread across both sides of the Expressway, relocation of small

    businesses encroaching on the ROW, impact of road resurfacing on noise levels, and impacts

    of labour camps operation on the integrity of the local communities.

    Predicted positive impacts:

    The single positive impacts of the project construction phase relate primarily to generation

    of local employment.

    The most significant positive impacts of the construction phase of the project resulting from

    the combined effect of impact significance, weight of the construction activities, and

    sensitivity of the receiving environment and social context are: the safety impacts of road

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    EXECUTIVE SUMMARY

    Final Revised ESIA Report S-8 Consolidated Consultants

    fencing and safety barriers, the positive effects of improved signage and road furniture, the

    improved, dedicated, and much safer facilities provided for small businesses originally

    located on the ROW, road resurfacing and labour camps on local employment; the labour

    opportunities created by road rehabilitation works.

    The short-term, negative impacts of the construction phase will be offset by long term

    positive impacts after completion of the works, including from relocation of small

    businesses encroaching on the ROW.

    One of the positive impacts of the project during operation is improved road safety due to

    the installation of side and median guardrails, signs and road furniture, installation of fence

    on both sides of the road, and provision of dedicated vendor lay-bys off the ROW. All these

    features are protective measures and will reduce the projected number of fatalities and

    injuries despite the growth in traffic and increase in vehicle operating speed.

    7. MITIGATION MEASURES

    The mitigation section addressed the key environmental and social impacts identified. The key

    mitigation measures for the construction phase of the project include:

    Avoid noisy operations at the night.

    Minimise noisy operations in road sections that are located close to the IBAs. In such sections noise machines should be replaced by manual workers wherever practicable.

    Apply road watering during construction works and after heavy movements.

    Maintain vehicles and machinery in good condition in order to minimize gas emissions and noise.

    Avoid bitumen melting activities in open spaces.

    Ensure that construction preparations are located away from populated areas.

    Confining vehicle maintenance and refuelling to areas in construction camps designed to contain spilled lubricants and fuels.

    Animal crossing structures should be regularly maintained to avoid closure.

    Monitoring and maintaining paths and underpasses to ensure safety and ease of movement

    for wildlife and livestock.

    Minimizing waste generation.

    General waste must be collected and transported to local council approved disposal sites.

    Refuse containers must be located at each worksite.

    Where practical, waste must be segregated and reused / recycled (e.g. scrap metal).

    Provision of alternative, safer, dedicated lay-bys for small businesses currently encroaching

    on the ROW and, as necessary, compensation for any losses in income/livelihoods incurred

    during the relocation (although measures are planned to minimize the chances of any such

    losses occurring).

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    EXECUTIVE SUMMARY

    Final Revised ESIA Report S-9 Consolidated Consultants

    Clearing of underpasses to accommodate movement of farmers and farming equipment,

    herders and livestock, and other persons from one side of the Expressway to the other.

    Personal protection equipment such as eyeglasses, gloves, hard heads and safety belts must

    be supplied.

    Road maintenance is associated with relatively minor negative impacts, most of which are of a

    temporary nature and can be alleviated with good practice. Contractors are responsible for adhering

    to these mitigation measures and implementing them throughout the duration of their contracts. The

    relocation of vendors and small businesses currently located on the ROW is the responsibility of the

    Government.

    8. ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN (ESMP)

    The following table summarizes the expected impacts, their mitigation measures, monitoring plan,

    and the responsible authority to follow up the action plan for each monitoring activity.

    The measures in the ESMP are based on the assessment of potential impacts as stated in this ESIA

    document and are summarized in the Table A and Table B below. Majority of the cost of

    implementing the ESMP will be integrated into the contactor’s cost for each section; however the

    project envisages that about US$ 7,152,900 will be needed to cover the following: ESMP

    construction phase; monitoring (construction and operation phases) and capacity building and

    institutional aspects of the ESMP.

    9. MONITORING & INSTITUTIONAL STRENGTHENING

    The monitoring activities will ensure the proper implementation of the environmental and social

    mitigation measures. The monitoring program will focus on noise impact and air quality, water

    quality, and relocation and re-establishment of small businesses and vendors within the project area.

    The monitoring activities will rely on the supervising consultant of all environmental and social

    impacts to determine contractor and government entity compliance or otherwise with the ESMP.

    The consultant will monitor the application of environmental and social mitigation measures and the

    result of monitoring activities shall be reflected on the monthly report. See Tables C, D & E.

    Institutional strengthening and Training Implantation are presented in Table F.

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    EXECUTIVE SUMMARY

    Final Revised ESIA Report S-10 Consolidated Consultants

    Table A: ESMP during the Construction Phase

    Project

    Activity

    Potential

    Environmental

    and Social

    Impacts

    Proposed Mitigation

    Measures

    Frequency

    of

    Measurement

    Institutional

    Responsibilities

    (Incl. Enforcement &

    Coordination)

    Cost

    Estimates

    Comments

    (E.G.

    Secondary

    Impacts)

    Traffic Diversion And

    Construction Site Access

    Points

    * Air Quality And

    Noise

    * Reduce Working Night Shifts

    As Much As Possible In

    Populated Areas.

    * Apply The Iraqi Regulation For

    Ambient Noise Levels During

    This Phase As A Major Tool In

    Designing The Construction

    Activities Schedule.

    *Apply Road Watering After

    Heavy Movements

    Continuous

    Weekly

    * The Project

    Contractor

    In Coordination

    With The

    Supervision

    Consultant.

    * MoCH in close

    coordination with

    MoI

    *Included

    Within

    Contractor's

    Fees

    *This will be

    incorporated

    in the lump

    sum of

    $150,000 for

    air quality

    monitoring

    Road and labour

    safety

    * Use Personal Protective Gear

    by workers, and make first aid

    available onsite.

    *provide warning signs at

    suitable distance around

    working areas

    *Continuous

    during

    construction

    * The Project

    Contractor

    in coordination with

    the Supervision

    Consultant / TBD

    *Included

    within

    contractor's

    fees

    Relocation of small businesses

    encroaching on ROW

    Economic loss and

    hardship

    * Establishment of dedicated rest

    areas outside the ROW with

    services provided. Completion

    of rest areas will be done

    before relocation of small

    businesses to minimize loss of

    income during relocation.

    * Compensation will be provided

    for loss of income resulting

    from relocation

    Once for each

    road segment MoCH/SCRP

    US$

    6,192,900

    for the whole

    road

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    EXECUTIVE SUMMARY

    Final Revised ESIA Report S-11 Consolidated Consultants

    Project

    Activity

    Potential

    Environmental

    and Social

    Impacts

    Proposed Mitigation

    Measures

    Frequency

    of

    Measurement

    Institutional

    Responsibilities

    (Incl. Enforcement &

    Coordination)

    Cost

    Estimates

    Comments

    (E.G.

    Secondary

    Impacts)

    Installation of side, median

    guardrails and fence on both

    sides of the road

    * Grassland and

    desert ecosystems

    * Mapping of home range of wild

    life to enable establishment of

    baseline and select locations

    for underpasses

    *Periodic cleaning and

    maintenance of service culverts

    used for wildlife passage

    * Re-cultivating affected

    vegetations to the extent

    possible

    * Final design

    documents

    * After

    construction

    * The Project

    Contractor

    in coordination with

    the Supervising

    Consultant / TBD

    * Included

    within

    contractor's fees

    * Varies with

    sub-projects

    depending on

    its

    characteristic

    Relocation

    after

    completion

    of work

    Relocation of small

    businesses

    Provide access road to the new

    rest areas

    Once at the

    beginning of

    the project

    MoCH/SCRP Included within

    contractors fee

    Delivery of construction

    materials

    Air Quality and

    Noise

    * Covering of delivered

    materials.

    * Proper storage of construction

    materials

    * Avoid noisy operations at night

    * Apply road watering after

    heavy movements

    Continuous

    during

    construction

    * The Project

    Contractor

    in coordination with

    the Supervising

    Consultant / TBD

    * Included

    within

    contractor's

    fees

    Very short

    term

    Road and labour

    safety

    *Limit speed of the vehicles

    *Avoid working near populated

    centres

    *Proper warning system within

    delivery sites

    *Provide Personal safety devices

    for workers

    Continuous

    during

    construction

    The Project

    Contractor

    in coordination with

    the Supervising

    Consultant / TBD

    Included within

    contractor's fees

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    EXECUTIVE SUMMARY

    Final Revised ESIA Report S-12 Consolidated Consultants

    Project

    Activity

    Potential

    Environmental

    and Social

    Impacts

    Proposed Mitigation

    Measures

    Frequency

    of

    Measurement

    Institutional

    Responsibilities

    (Incl. Enforcement &

    Coordination)

    Cost

    Estimates

    Comments

    (E.G.

    Secondary

    Impacts)

    Restoration of road surface

    (including current paving of

    the Diwaniya-Nasiriya section)

    Air Quality and

    Noise

    *Avoid bitumen melting

    activities in open spaces

    *Ensure that construction

    preparations are located away

    from populated areas

    *Maintain vehicles and

    machinery in good condition in

    order to minimize gas

    emissions and noise

    Continuous

    during

    construction

    The Project

    Contractor

    in coordination with

    the Supervising

    Consultant / TBD

    Included within

    contractor's fees

    Cumulative

    Impacts

    Road and Labour

    safety

    *Limit speed of the vehicles

    *Proper warning system within

    delivery sites

    *Provide Personal safety devices

    for workers

    Rehabilitation of bridges and

    Underpasses

    Noise Level

    *Avoid working at night

    *Maintain vehicles and

    machinery in good condition in

    order to minimize gas

    emissions and noise

    Continuous

    during

    construction

    The Project

    Contractor

    in coordination with

    the Supervising

    Consultant / TBD

    Included within

    contractor's fees

    Long term

    positive

    Grassland / desert

    Eco System

    *Mapping of home range of wild

    life to enable establishment of

    baseline and select locations

    for underpasses

    *Periodic cleaning and

    maintenance of service culverts

    used for wildlife passage

    * Ensure crossing structures

    located appropriately to

    minimize movement barrier

    effect. Suitable habitats are

    Quarterly

    The Project

    Contractor

    in coordination with

    the Supervising

    Consultant / TBD

    Included within

    contractor's fees

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    EXECUTIVE SUMMARY

    Final Revised ESIA Report S-13 Consolidated Consultants

    Project

    Activity

    Potential

    Environmental

    and Social

    Impacts

    Proposed Mitigation

    Measures

    Frequency

    of

    Measurement

    Institutional

    Responsibilities

    (Incl. Enforcement &

    Coordination)

    Cost

    Estimates

    Comments

    (E.G.

    Secondary

    Impacts)

    covered by associated

    vegetation cover and where

    crossed by the fenced road

    should be connected via

    crossing structures to ensure

    habitat continuity

    *Ensure underpasses are cleared

    to facilitate movement of

    farmers, herders, and other

    persons needing ready access to

    the other side of the Expressway.

    * Re-cultivating affected

    vegetations to the extent

    possible

    Road and labour

    Safety

    * Limit speed of the vehicles

    * Proper warning system within

    delivery sites

    * Provide Personal safety devices

    for workers

    Continuous

    during

    construction

    The Project

    Contractor

    in coordination with

    the Supervising

    Consultant / TBD

    Included within

    contractor's fees

    Generation and disposal of

    construction wastes

    Agricultural soil

    Confining vehicle maintenance and refuelling

    to areas in construction

    camps designed to contain

    spilled lubricants and fuels,

    - Using special containers with complete labelling,

    - Using second containment tanks for oil

    collection and handling,

    Collecting, storing and

    Continuous

    during

    construction

    The Project

    Contractor

    in coordination with

    the Supervising

    Consultant / TBD

    Included within

    contractor's fees

    Assume

    good

    Practice * Air Quality and

    Noise

    * Landscape value

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    EXECUTIVE SUMMARY

    Final Revised ESIA Report S-14 Consolidated Consultants

    Project

    Activity

    Potential

    Environmental

    and Social

    Impacts

    Proposed Mitigation

    Measures

    Frequency

    of

    Measurement

    Institutional

    Responsibilities

    (Incl. Enforcement &

    Coordination)

    Cost

    Estimates

    Comments

    (E.G.

    Secondary

    Impacts)

    disposing to approved

    disposal sites, according to

    MOE requirements, and,

    To the extent possible, reusing, recycling and

    properly disposing of all

    construction materials

    Collecting rehabilitation material and transferring it to

    a licensed dumping site. It is

    recommended managing the

    rehabilitation materials for

    further utilization in the road

    construction.

    Labour camps

    Agricultural soil Avoid camp construction over

    agricultural land

    Once / before

    construction

    The Project Contractor

    in coordination with the

    Supervising Consultant /

    TBD

    Included within

    contractor's fees

    Location

    specific Landscape value

    Avoid waste disposal in

    unspecified areas Continuous

    The Project Contractor

    in coordination with the

    Supervising Consultant /

    TBD

    Included within

    contractor's fees

    Integrity of the

    Local Community

    Ensure local employment and

    ensure labour camps are not

    located inside communities

    Continuous

    The Project Contractor

    in coordination with the

    Supervising Consultant /

    TBD

    Included within

    contractor's fees

    Combined Activities Noise

    Avoid noisy parallel construction

    activities, especially near to IBA.

    Replace noise equipment by

    manual work near IBAs.

    Continuous

    The Project Contractor

    in coordination with the

    Supervising Consultant /

    TBD

    Included within

    contractor's fees

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    EXECUTIVE SUMMARY

    Final Revised ESIA Report S-15 Consolidated Consultants

    Table B: ESMP during Maintenance Phase

    Project

    Activity

    Potential Environmental

    and Social Impacts

    Proposed Mitigation

    Measures

    Frequency

    of

    Measurement

    Institutional

    Responsibilities

    (incl. enforcement

    & coordination)

    Cost

    Estimates

    Comments

    (e.g.

    secondary

    impacts)

    Road Marking

    Road Safety

    Air Quality and Noise

    Waste Management

    Use proper warning signs at

    suitable distance

    during

    maintenance

    MoCH

    As needed /

    per unit

    Only in

    maintenance

    areas

    Maintenance of side and

    median guardrails Avoid working at night

    during

    maintenance

    Repair of fence Proper collection of waste in

    working areas.

    during

    maintenance

    Maintenance of road surface Avoid bitumen melting activities

    in open spaces

    during

    maintenance

    Maintenance of bridges and

    cleaning of underpasses

    Regular Cleaning of underpasses

    and culverts Winter season

    Maintenance of service areas

    for relocated small businesses Waste Management

    Periodic cleaning and

    maintaining services areas Quarterly

    Municipality As needed

    Only in lay-

    bys

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    EXECUTIVE SUMMARY

    Final Revised ESIA Report S-16 Consolidated Consultants

    Table C: Monitoring During Construction

    Parameters

    To Be

    Monitored

    Proposed

    Mitigation

    Measure

    Location

    Measurements

    (Incl. Methods &

    Equipment)

    Frequency

    Of

    Measurement

    Responsibilities

    (Incl. Review And

    Reporting)

    Cost Of

    (Equipment &

    Individuals)

    Air Quality

    * Concentrations of

    Particulate Matter (PM10,

    PM2.5), NOx, SOx, and

    VOCs

    * Apply (spray) water to

    the construction surface

    and other piled

    materials such as sand

    as much as needed.

    * Perform periodical

    check and maintenance

    for the construction

    machinery

    * Monitor/measure

    concentrations of

    particulate matter

    Along the Road,

    especially near

    intersections with

    population

    centres

    In cities and

    governorates with

    fixed and mobile

    air quality

    monitoring

    stations close to

    the expressway 1

    * Site inspection

    * Measuring

    concentrations of

    air pollutants using

    monitoring

    equipment and

    appropriate

    monitoring methods

    Daily

    Weekly

    * Included in

    Contractors

    offer

    *Contractor/Supervising

    Consultant in

    coordination with

    dedicated engineer

    * MocH/MOE staff

    using existing fixed and

    mobile air quality

    stations

    *Third party

    monitoring

    by trained

    MOE staff.

    Cost: Lump

    sum of

    $ 150,000 to

    cover

    allowances,

    transport and

    equipment

    maintenance

    and

    calibration

    Noise Level

    * Hearing

    * Reduce working night

    shifts as much as

    possible in populated

    areas.

    * Apply the Iraqi

    Regulation for ambient

    noise levels during this

    phase as a major tool in

    designing the

    construction activities

    schedule.

    Along the Road,

    especially near

    intersections with

    population

    centres

    * Site inspection

    * Measuring of noise

    levels using

    monitoring

    equipment and

    appropriate

    monitoring methods

    Daily

    * Contractor

    * Included in

    Contractors

    offer

    *Supervising

    Consultant / TBD in

    coordination with

    dedicated engineer

    *Equivalent of

    one full time

    environmenta

    l monitoring

    specialist

    who shall

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    EXECUTIVE SUMMARY

    Final Revised ESIA Report S-17 Consolidated Consultants

    Parameters

    To Be

    Monitored

    Proposed

    Mitigation

    Measure

    Location

    Measurements

    (Incl. Methods &

    Equipment)

    Frequency

    Of

    Measurement

    Responsibilities

    (Incl. Review And

    Reporting)

    Cost Of

    (Equipment &

    Individuals)

    report to

    Supervising

    Consultant /

    Included in

    the rate

    above

    Biodiversity

    Site clearance-vegetation

    removal and habitat

    disturbance

    Good site management

    practices to be observed

    to ensure minimal

    disturbance of habitats

    and sites

    Along the Road,

    especially near

    intersections with

    population

    centres, base

    camps and

    borrow sites

    Site inspection During

    construction

    * Contractor

    * Supervising

    Consultant / TBD in

    coordination with

    dedicated engineer

    * Included in

    Contractors

    offer

    Waterways

    Contamination of waterways

    due to spillages and disposal

    of liquid wastes

    Maintenance of well-kept

    construction site and no

    discharge of effluents into

    waterways

    Waterways/water

    bodies close to

    work sites and

    base camp

    Visual inspection During

    construction

    * Contractor

    * Supervising

    Consultant / TBD in

    coordination with

    dedicated engineer

    * Included in

    Contractors

    offer

    Drainage System

    * Readiness of ditches and

    culverts for rainy season

    * Periodic cleaning and

    maintenance of ditches

    and culverts

    * Periodic inspection for

    solid waste disposal in

    culverts

    culverts across

    the road

    * Site inspection

    * Enforcing waste

    disposal regulations

    During

    construction

    * Contractor

    * Supervising

    Consultant / TBD in

    coordination with

    dedicated engineer

    *Included in

    Contractors

    offer

    * equivalent of

    one full time

    environmental

    monitoring

    engineer /

    specialist who

    shall

    coordinate

    and report to

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    EXECUTIVE SUMMARY

    Final Revised ESIA Report S-18 Consolidated Consultants

    Parameters

    To Be

    Monitored

    Proposed

    Mitigation

    Measure

    Location

    Measurements

    (Incl. Methods &

    Equipment)

    Frequency

    Of

    Measurement

    Responsibilities

    (Incl. Review And

    Reporting)

    Cost Of

    (Equipment &

    Individuals)

    Supervising

    Consultant /

    Included in

    the rate above

    Relocation of small

    businesses currently located

    on ROW

    Relocation to new

    designated lay-bys

    provided with services

    and off the ROW

    Near intersections

    and overpasses

    Site Inspection and

    interviews;

    Grievance redress

    mechanism and ex-

    post relocation audit

    During

    construction MoCH/SCRB

    Included in

    contractor’s

    offer

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    EXECUTIVE SUMMARY

    Final Revised ESIA Report S-19 Consolidated Consultants

    Table D: Monitoring during Maintenance

    Parameters

    To Be

    Monitored

    Proposed

    Mitigation

    Measure

    Location

    Measurements

    (Incl. Methods &

    Equipment)

    Frequency

    Of

    Measurement

    Responsibilities

    (Incl. Review And

    Reporting)

    Cost Of

    (Equipment

    &

    Individuals)

    Air Quality

    * Apply (spray) water to

    the construction surface

    as needed.

    * Perform periodical check

    and maintenance for the

    construction machinery

    * Monitor/measure

    concentrations of

    particulate matter

    Along the

    maintained section

    of the road

    especially near

    population centres

    In Cities and

    governorates with

    fixed and portable

    air quality

    monitoring

    stations close to

    expressway 1

    * Visual Site

    inspection

    *periodic check

    During

    maintenance

    Weekly

    * MoCH/MOE staff

    using existing fixed

    and mobile air

    quality stations

    * MoCH

    staff and

    equipment

    * Lump sum

    of

    $250,000

    to cover

    allowances

    , transport

    and

    equipment

    maintenan

    ce and

    calibration

    Noise Level

    * No night shifts as much

    as possible in populated

    areas.

    Along the

    maintained section

    of the road

    especially near

    population centres

    * Site inspection

    During

    maintenance

    * MoCH

    * MoCH

    staff and

    equipment

    Biodiversity

    * Good site management

    practices to be observed

    Along the Road, in

    particular near

    intersections with

    population centres,

    base camps and

    borrow sites

    * Site inspection During

    maintenance

    * MoCH * MoCH

    staff and

    equipment

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    EXECUTIVE SUMMARY

    Final Revised ESIA Report S-20 Consolidated Consultants

    Waterways

    * No discharge of used

    oils/effluents into

    waterways

    Waterways/water

    bodies close to

    work sites and

    base camp

    * Site inspection During

    maintenance

    * MoCH * MoCH

    staff and

    equipment

    Drainage System

    * Periodic cleaning and

    maintenance of ditches and

    culverts

    * Periodic inspection for

    solid waste disposal in

    culverts

    culverts across the

    road

    * Site inspection

    * Enforcing waste

    disposal regulations

    During

    maintenance

    * MoCH

    * MoCH

    staff and

    equipment

    Maintenance of new vendor

    lay-bys and associated

    services

    Periodic maintenance and

    waste management New lay-bys Visual inspection Quarterly Municipality

    Municipality

    staff and

    equipment

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    EXECUTIVE SUMMARY

    Final Revised ESIA Report S-21 Consolidated Consultants

    Table E: Scheduling and Reporting

    Activity

    Year 1 Year 2 Subsequent years

    Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

    Mitigation Measure

    Air Quality

    Noise Level

    Waterways

    Biodiversity

    Socio-economy

    Monitoring

    Air Quality

    Noise Level

    Waterways

    Biodiversity

    Socio-economy

    Institutional Strengthening

    Mitigation

    Monitoring

    Training

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    EXECUTIVE SUMMARY

    Final Revised ESIA Report S-22 Consolidated Consultants

    Table F: Institutional Strengthening and Training for Implementation

    Institutional

    Strengthening

    Activity

    Position(s)

    (institutions, contractors, construction

    supervision consultant)

    Scheduling Responsibilities Cost Estimates

    ESIA and

    requirements of

    OP4.01 and

    OP4.12

    Project owner (Iraqi Ministry of

    Construction and Housing and involved

    governorates: Anbar, Babel, Al-

    Qadisiya, Al-Muthanna, Dhi-Qar, and

    Al-Basra)

    Throughout

    project

    implementation

    and first year of

    operation

    Project owner 5,000 USD for once + 5,000 USD first

    year of operation – per governorate

    (Total budget is a multiplication for the

    6 governorates)

    Mitigation Project owner (Iraqi Ministry of

    Construction and Housing and involved

    governorates)

    Throughout

    project

    implementation

    and operation

    Project owner 5,000 USD per year of construction +

    5,000 USD per year of operation– per

    governorate

    (Total budget is a multiplication for the

    6 governorates)

    Construction Supervisor Throughout

    construction

    period

    Consultant 5,000 USD per year of construction–

    per governorate

    (Total budget is a multiplication for the

    6 governorates)

    Contractor Throughout

    construction

    period

    Consultant 5,000 USD per year of construction–

    per governorate

    (Total budget is a multiplication for the

    6 governorates)

    Monitoring Project owner (Iraqi Ministry of

    Construction and Housing and involved

    governorates)

    Throughout

    project

    implementation

    and operation

    Project owner 5,000 USD per year of construction +

    5,000 USD per year of operation– per

    governorate

    (Total budget is a multiplication for the

    6 governorates)

    Construction Supervisor Throughout

    construction

    period

    Consultant 5,000 USD per year of construction–

    per governorate

    (Total budget is a multiplication for the

    6 governorates)

    Contractor Throughout construction

    period

    Consultant 5,000 USD per year of construction– per governorate

    (Total budget is a multiplication for the

    6 governorates)

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    EXECUTIVE SUMMARY

    Final Revised ESIA Report S-23 Consolidated Consultants

    Institutional

    Strengthening

    Activity

    Position(s)

    (institutions, contractors, construction

    supervision consultant)

    Scheduling Responsibilities Cost Estimates

    Training Participants Types of

    Training

    Contents Scheduling Cost Estimates

    Consultation

    sessions -

    preparation and

    management.

    * Staff of the 6 involved governorates:

    Anbar, Babel, Al-Qadisiya, Al-

    Muthanna, Dhi-Qar, and Al-Basra

    * Staff of Iraqi Ministry of Construction

    and Housing

    * On-the-job

    training

    workshops

    * Preparing for a

    consultation session

    * Audience

    nomination (focus

    groups)

    * Consultation

    communication skills

    * Effective

    management of

    consultation output

    During real time

    conduction of

    scoping session

    and public

    disclosure session

    1,000 USD per

    trainee

    (Total budget is a

    multiplication for

    nominated

    trainees from the

    6 involved

    governorates)

    * ESIA

    Implementation

    * ESMP

    Implementation

    * Staff of the 6 involved governorates:

    Anbar, Babel, Al-Qadisiya, Al-

    Muthanna, Dhi-Qar, and Al-Basra

    * Staff of Iraqi Ministry of Construction

    and Housing

    * Off-the-job

    training

    workshops

    * Core value of

    implementing a ESIA

    * Key elements of

    ESIA and systematic

    approach

    * Regulatory

    framework and

    literature review

    * Identifying target

    groups and valued

    environmental and

    social components

    * Analyzing impacts

    and putting pollution

    prevention measures

    * Key elements of

    environmental and

    social management

    plans

    * Effective monitoring

    plan (approaches and

    fund resources)

    Twice a year

    during construction

    and operation

    35,000 USD to

    50,000 USD

    depending upon

    number of

    trainees from the

    Ministry and

    from the 6

    involved

    governorates +

    venue expenses

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    Final Revised ESIA Report Consolidated Consultants

    FINAL ESIA REPORT (MAIN REPORT)

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    Final Revised ESIA Report i Consolidated Consultants

    TABLE OF CONTENTS

    Page

    Table of Contents i

    List of Tables iv

    List of Figures iv

    List of Abbreviations vi

    EXECUTIVE SUMMARY S-1

    1. Introduction S-1

    2. Legal and Administrative Framework S-1

    3. Project Description S-2

    4. Environmental and social baseline conditions S-4

    5. Public Consultations S-5

    6. Environmental and social impact analysis S-6

    7. Mitigation measures S-8

    8. Environmental and Social Management Plan (ESMP) S-9

    9. Monitoring & Institutional Strengthening S-9

    FINAL ESIA REPORT (MAIN REPORT)

    1.2 Objectives of the ESIA 1

    2.1 Introduction 3

    2.2 World Bank's Policies and Procedures 3

    2.2.1 Environmental Policies 4

    2.2.2 Social Policies 5

    2.2.3 Mandatory Bank Procedures 6

    2.2.4 WB Safeguard Guidelines 7

    2.3 Environmental International and Regional Conventions and Treaties 7

    2.4 Iraqi Environmental Laws 9

    3.1 Background and Project Rationale 12

    3.2 Project Description 12

    3.3 Project Works 23

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    Final Revised ESIA Report ii Consolidated Consultants

    3.4 Construction Activities 28

    4.1 Project Setting 29

    4.2 Land Use 31

    4.3 Population Centres 33

    4.3.1 Demography 36

    4.4 Present conditions of Expressway No. 1 37

    4.4.1 Road Condition 37

    4.4.2 Safety Devices 39

    4.4.3 Water Crossings 41

    4.4.4 Structures, Establishments and Commercial Activities along Alignment 41

    4.5 Physical Environment 42

    4.5.1 Air Quality and Noise 42

    4.5.2 Surface Water Resources 44

    4.6 Ecological and Biological Resources 46

    4.6.1 Biogeography 46

    4.6.2 Biodiversity of the Terrestrial Ecosystems along Expressway No. 1 47

    4.6.2.2 Arabian Desert and East Saharo-Arabian Xeric Shrublands 50

    5.1 Public Consultations Process 55

    5.2 Results of consultations carried out along the Expressway No. 1 63

    5.3 Results of Public Consultation Sessions 64

    5.3.1 Western Consultation Session 64

    5.3.2 Southern Consultation Session 65

    5.4 Grievance Redress Mechanism 66

    6.1 Introduction 67

    6.3 Environmental and Social Impacts during the Construction Phase of the Project 70

    6.3.1 Introduction 70

    6.3.2 Physical Aspects 71

    6.3.3 Ecological Aspects 76

    6.3.4 Social Aspects 77

    6.3.5`Combined impacts of parallel construction activities 82

    6.4 Maintenance Phase 83

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    Final Revised ESIA Report iii Consolidated Consultants

    6.4.1 Physical Aspects 84

    6.4.2 Ecosystem Aspects 84

    7.2 Construction Phase 85

    7.2.1 Physical Aspects 85

    7.2.2 Ecological Aspects 87

    7.2.3 Social Aspects 87

    7.3 Maintenance Phase 89

    7.3.1 Physical 89

    Introduction 117

    1 Western Part: Public Consultation at Al Anbar Governorate-Ramadi 117

    1.1 Workshop Participants 117

    1.2 Workshop Components and Presentations Outline 117

    1.3 Summary of Session Findings 119

    2 Southern Part: Public Consultation held in Babel Governorate 119

    2.1 Workshop Participants 120

    2.2 Workshop Components and Presentations Outline 120

    2.3 Summery of Session Findings 121

    Annex 3 – Full Inventory 112

    Annex 4 – Proposed Lay-bys for PAPs along Expressway No.1 263

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    Final Revised ESIA Report iv Consolidated Consultants

    LIST OF TABLES

    Table 1: Summary of the relevant World Bank Safeguard Policies ..................................................... 7 Table 2: Existing Iraqi Environment-related Legislation ................................................................... 10 Table 3: Recent Iraqi Environmental legislation ................................................................................ 11 Table 4: Location of Main Cities along the Expressway and Relevant Distances ............................. 14 Table 5: The Expressway No.1 Contract Documents and its Updates ............................................... 23 Table 6: Carriageway Marking Quantities ......................................................................................... 24 Table 7: Interchanges Ramps Marking Quantities ............................................................................. 25 Table 8: Access Roads Marking Quantities ....................................................................................... 26 Table 9: Guardrails Quantities Estimation ......................................................................................... 27 Table 10: Fencing Quantities Estimation ........................................................................................... 27 Table 11: Area of Land Use ............................................................................................................... 33 Table 12: Population Information over Governorate ......................................................................... 34 Table 13: Relative Distances and Population of Localities in the Project Area ................................. 34 Table 14: Age group Distribution ...................................................................................................... 36 Table 15: Family Sizes According to Districts................................................................................... 36 Table 16: TSP Data- Baghdad 3 Stations (2009) ............................................................................... 42 Table 17: TSP Data - Al-Basra (2009) ............................................................................................... 43 Table 18: Air Quality Data collected from Al-Basra Station ............................................................. 43 Table 19Air Quality Data from Al-Zubair Station ............................................................................. 44 Table 20: Survey and Consultation Points along the Road ................................................................ 56 Table 21: Impact Scoping Matrix for the Construction Phase of the Expressway No. 1 ................... 69 Table 22 USEPA Emission Factors for Construction Works ............................................................. 72 Table 23 Cut and Cut and Filling Volume during Construction ........................................................ 72 Table 24 Daily traffic volumes: 2012 and 2032 (prediction) - Vehicle/Day...................................... 73 Table 25: Total vehicular emissions from Expressway No. 1 according to the HDM-IV - model. (Tonnes over

    2013 -2034 period) ..................................................................................................................... 75 Table 26: Expected Numbers of Employment during Construction .................................................. 81 Table 27: ESMP for Construction Phase ............................................................................................ 91 Table 28: ESMP for Maintenance Phase ............................................................................................ 96 Table 29 : Environmental and Social Management Plan Cost Estimate ............................................ 98 Table 30: Monitoring Plan during Construction ................................................................................ 99 Table 31: Monitoring Plan during Maintenance .............................................................................. 102 Table 32: Institutional Strengthening and Training for Implementation .......................................... 104 Table 33: Scheduling and Reporting ................................................................................................ 107

    LIST OF FIGURES

    Figure 1: Map of Iraq showing the path of Expressway No. 1 ........................................................... 13

    Figure 2: Al Anbar Governorate - Ar Rutba ...................................................................................... 15

    Figure 3: Al Anbar Governorate - Ramadi ......................................................................................... 16

    Figure 4: Al Anbar Governorate - Fallujah ........................................................................................ 17

    Figure 5: Baghdad Governorate - Abu Ghraib ................................................................................... 18

    Figure 6: Babylon Governorate - Hillah ............................................................................................. 19

    Figure 7: Al Qadisiyyah Governorate - Al Diwaniyah ...................................................................... 20

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    Final Revised ESIA Report v Consolidated Consultants

    Figure 8: Dhi Qar Governorate - Nasiriyah ........................................................................................ 21

    Figure 9: Basra Governorate – Basra ................................................................................................. 22

    Figure 10: Topography of Iraq ........................................................................................................... 29

    Figure 11: Historical image of an overpass bridge of the newly build Expressway No. 1. ............... 30

    Figure 12: Historical image of the newly built Expressway No.1 ..................................................... 30

    Figure 13: Mapping Vegetation Cover Percentages ........................................................................... 31

    Figure 14: Distribution of Land Use (part I) ...................................................................................... 32

    Figure 15: Distribution of Land Use (part II) ..................................................................................... 33

    Figure 16: Distribution of Population Centres along the Road .......................................................... 33

    Figure 17: Age Distribution ............................................................................................................... 36

    Figure 18: Road Conditions ............................................................................................................... 38

    Figure 19: Missing Single Guardrails ................................................................................................ 39

    Figure 20: Missing Double Guardrails ............................................................................................... 39

    Figure 21: Missing Fence and Ordinary Post ..................................................................................... 40

    Figure 22: Missing Fence ................................................................................................................... 40

    Figure 23: Expressway Crossing Waterways ..................................................................................... 41

    Figure 24: Expressway Intersection with Euphrates River near Ramadi ........................................... 45

    Figure 25: Expressway Intersection with Irrigation Channel near Diwaniyah .................................. 45

    Figure 26: Expressway Intersection with Euphrates River near Nasiriyah ........................................ 46

    Figure 27: Terrestrial Ecoregions recognized in Iraq ......................................................................... 47

    Figure 28: Consultation Points (1-23) ................................................................................................ 59

    Figure 29: Consultation points (24 – 35) ............................................................................................ 60

    Figure 30: Consultation points (36 – 39) ............................................................................................ 60

    Figure 31: Consultation points (40 – 53) ............................................................................................ 61

    Figure 32: Consultation points (54 – 74) ............................................................................................ 61

    Figure 33: Consultation Points (75-86) .............................................................................................. 62

    Figure 34: Consultation with owners of affected People ................................................................... 62

    Figure 35: Buildings, shops and services along the Expressway ....................................................... 63

    Figure 36: Entities along the Iraq Expressway 1 ................................................................................ 78

    Figure 37: Entities along the Iraq Expressway 1 ................................................................................ 78

    Figure 38: Entities along the Iraq Expressway 1 ................................................................................ 79

    Figure 39: Entities along the Iraq Expressway 1 ................................................................................ 79

    Figure 40: Entities along the Iraq Expressway 1 ................................................................................ 80

    Figure 41: Entities along the Iraq Expressway 1 ................................................................................ 80

    Figure 42: Sample pictures during Consultation session at Al Ramadi ........................................... 118

    Figure 43: Sample pictures during Consultation session at Babel ................................................... 121

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    Final Revised ESIA Report vi Consolidated Consultants

    List of Abbreviations

    ESIA Environmental and Social Impact Assessment Study

    BP Bank Policy Bank Procedure

    CC Consolidated Consultants Engineering and Environment

    ESCWA Economic Commission for Western Asia

    EC European Countries

    IBAs Important Birds Areas

    IPM Integrated Pest Management

    IFC International Finance Corporation

    MoCH Ministry of Construction and Housing

    MoE Ministry of Environment

    MoI Ministry of Interior

    NGOs Non Governmental Organization

    NA Not Available

    OP Operational Policy

    PM Particulate matter

    PCR Physical Cultural Resources

    PPAH Pollution Prevention and Abatement Handbook

    ROW Right of Way

    TOR Terms of Reference

    TSP Total Suspended Particulates

    USD United States Dollars

    USA United States of America

    WB Word Bank

    WHO World Health Organization

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    Final Revised ESIA Report 1 Consolidated Consultants

    1. INTRODUCTION

    Environmental and Social Impact Assessment (ESIA) is a process where the potential future

    environmental and social consequences of a proposed project or undertaking are identified and

    mitigated before irrevocable decisions are made. A well-constructed ESIA provides the basis for

    responsible corporate decision-making that is forward-looking and globally participatory. Potential

    issues are identified as early in the process as possible and solutions are developed to maximize

    project benefit while minimizing both front-end and downstream to avoid, minimize, and/or mitigate

    negative impacts.

    Consolidated Consultants Engineering and Environment (CC) services have been retained for the

    preparation of Terms of References (TOR) Environmental and Social Impact Assessment (ESIA) for

    the rehabilitation of an existing road "Expressway No.1", and a team of experienced practitioners

    has been assembled to prepare a high quality TOR and ESIA for the proposed project.

    The rehabilitation of the road will include:

    1. Road marking.

    2. Installation of guardrails between both sides and on sides where necessary.

    3. Installation of signs and road furniture.

    4. Installation of a chain link fence on both sides of the road.

    5. Rehabilitation of the asphalt as needed.

    6. Other rehabilitation works as determined necessary by the technical assessment.

    This specific project activity is mandated by Iraqi Environmental Law and its guidelines for ESIA

    preparation. The Transport Corridors project is categorized as an A, requiring an environmental and

    social assessment in accordance with the World Bank's Operational Policy on Environmental

    Assessment (OP 4.01) and Involuntary Resettlement Policy (OP4.12).

    The Government of Iraq has committed to applying the World Bank Safeguards Policies to the

    entire Expressway 1. This includes the segments of Expressway 1 that are not supported by the

    World Bank and are under rehabilitation or construction. As such the environmental and social due

    diligence of these road segments will include the preparation of environmental audits and

    resettlement audits prior to the end of the appraisal period of the World Bank funded road segments.

    These environmental and social audits will assess the non-Bank funded road segments compliance

    with the safeguards policies, identify any gaps in terms of environmental and social management

    and develop corrective action plans, if needed.

    1.2 Objectives of the ESIA

    The overall purpose is to prepare an ESIA in compliance with the applicable regulations, policies

    and guidelines. The specific objectives of the ESIA are:

    a. Ensuring that potential significant positive and adverse environmental and social impacts are identified.

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    Final Revised ESIA Report 2 Consolidated Consultants

    b. Capitalize on positive aspects and benefits, mitigate negative impacts and avoid serious and irreversible damage to the environment and people.

    c. Prepare environmental and social management and monitoring plan to be abided by the proposed project to help ensure the stated above.

    d. Ensuring that environmental and social factors are considered in the decision-making process of the proposed road upgrade including through effective consultation with potentially affected

    persons and stakeholders.

    e. Where necessary, provide guidelines for Project Design to ensure its fulfillment with the compliance and mitigation measures to help ensure good environmental performance.

    f. Informing the public about the proposed project and ensuring effective participation and involvement by all related stakeholders.

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    Final Revised ESIA Report 3 Consolidated Consultants

    2 LEGAL AND ADMINISTRATIVE FRAMEWORK

    A desk study was carried out by the study team to assess and present the most applicable legal and

    administrative framework to the proposed project. The study has taken into consideration, both the

    potential Iraqi environmental laws and those policies and procedures of the World Bank introduced

    in the project's TOR. Additionally, the foreseen legal and administrative framework by the TOR has

    been further enriched and narrowed to suit the requirements of the Valued Environmental

    Components arose from the public consultation. This chapter aims at providing a register for the

    most applicable legal and administrative regulations that mandates and governs the conduction of

    ESIA for the proposed project. The register overviews and encompasses the following:

    Requirements of the Funding Agency (World Bank Policies and Procedures).

    Related Environmental International and Regional Conventions and Treaties.

    Laws and Regulations/by-laws for Iraq.

    The legal framework described in this chapter spans the whole project cycle:

    The planning and design process itself is conducted in accordance with the environmental and social legal and regulatory guidelines.

    Design complies with the environmental and social legal and regulatory requirements.

    Construction planned in a way to adhere to the requirements.

    The ESIA fulfils the requirements in terms of imposed mitigation and environmental social management measures.

    The following sections provide a description of the applicable laws and regulations.

    2.2 World Bank's Policies and Procedures

    The World Bank has 10 current Operational Policies and Procedures:

    - Pest Management (OP/BP 4.09)

    - Environmental Assessment (OP/BP 4.01)

    - Natural Habitats (OP/BP 4.04)

    - Safety of Dams (OP/BP 4.37)

    - Projects on International Waterways (OP/BP 7.50)

    - Projects in Disputed Areas (OP/BP 7.60)

    - Forests (OP/BP 4.36)

    - Involuntary Resettlement (OP/BP 4.12)

    - Indigenous Peoples (OP/BP 4.10)

    - Physical Cultural Resources (OP/BP 4.11)

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    Final Revised ESIA Report 4 Consolidated Consultants

    The policies that apply and are triggered for this project are:

    - Environmental Assessment (OP/BP 4.01).

    - Involuntary Resettlement (OP/BP 4.12).

    2.2.1 Environmental Policies

    OP/BP 4.01 Environmental Assessment

    OP 4.01 is the key Operational Policy describing the environmental assessment procedure. The

    Bank requires environmental assessment of projects proposed for Bank financing. The objectives of

    the EA are to:

    Ensure that projects proposed for Bank financing are environmentally and socially sound and sustainable.

    Inform decision makers of the nature of environmental and social risks.

    Increase transparency and participation of stakeholders in the decision-making process

    Role of Bank and Borrower

    Roles of both Bank and Borrowers stated by this operational policy are summarized as follows:

    A. Bank:

    Screens and sets Environmental Assessment Category

    Advises Borrower on the Banks Environmental Assessment requirements

    Reviews and determines adequacy of Environmental Assessment reports

    Makes report available in Info-shop

    Supervises implementation of Environmental Assessment/Environment Management Plan

    B. Borrower:

    Assists the bank in proper screening

    Responsible for carrying out Environmental Assessment under Bank rules and national laws

    Consults project-affected groups and local NGOs

    Discloses draft/final documents

    Responds to Bank and public

    Supervises under Bank rules

    Ensures compliance under national laws

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    Final Revised ESIA Report 5 Consolidated Consultants

    Environmental Screening

    The policy includes a classification for the proposed project into four categories, depending on the

    type, location, sensitivity and nature of environmental impacts. The four categories include:

    Category A: Significant adverse environmental impacts, board, irreversible, major resettlement or habitat. The subject project is included in this category "New construction or major upgrading

    of expressways or rural roads"

    Category B: its impacts are less adverse than those of Category A projects

    Category C: likely to have minimal or no adverse environmental impacts

    Category FI: when it involves investments through a financial intermediary, in subprojects undefined by appraisal with adverse impacts.

    OP 4.04 Natural Habitats

    The Operational Policy addresses the following main principles:

    Safeguarding natural habitats and their biodiversity; avoiding significant conversion or degradation of critical natural habitats

    Ensuring sustainability for services and products which natural habitats provide to human society.

    2.2.2 Social Policies

    OP 4.11 Physical Cultural Resources

    This Operational Procedure is regulated by the World Bank to be implemented as an element of the

    Environmental Assessment; it is regulated in order to:

    Ensure that Physical Cultural Resources (PCR) are identifies and protected in World Bank financed projects

    Ensure that National laws governing the protection of physical cultural property are complied with

    Ensure that PRC includes archaeological and historical sites, historic urban areas, scared sites, graveyards, burial sites, unique natural values

    OP 4.12 Involuntary Resettlement

    The World Bank’s Involuntary Resettlement Policy (IRP) Operational Policy (OP) 4.12 requires that

    environmental and social impacts of all projects it supports, be mitigated according to operational

    polices that spell out the principles and planning methods for mitigation work. The Word Bank’s

    IRP applies whenever property must be acquired, or its use modified, for a project, and that

    acquisition or modification results in the loss of income, residence or access to resources, either

    permanent or temporary and whether the occupation is legal or illegal. Resettlement of project

    affected persons (PAPs) in the project site will therefore be carried out in accordance with laws,

    regulations and guidelines for Resettlement/Land Acquisition Policy Framework of the Republic of

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    Final Revised ESIA Report 6 Consolidated Consultants

    Iraq and World Bank’s Operational Policy (O.P) 4.12, which has resulted in the preparation of a full

    resettlement Action Plan (RAP).

    World Bank OP 4.12 highlighted three major principles:

    Involuntary resettlement is avoided wherever feasible, or minimized, exploring all viable alternative project designs;

    Where it is not feasible to avoid involuntary resettlement, activities are conceived and executed as sustainable development programs. Displaced persons are to be meaningfully

    consulted and have opportunities to participate in the planning and implementing of

    resettlement programs affecting them; and

    Displaced persons are assisted in their efforts to improve their livelihoods and standards of living, or at least to restore them, in real terms, to pre-displacement levels or to levels

    prevailing prior to the beginning of project implementation, whichever is higher. The

    mechanism of assisting displaced persons is based on full and prior mitigation and

    compensation for loss of assets or livelihoods.

    OP 4.12 applies whenever, in a Bank-financed project, land is acquired involuntarily or access is

    restricted in legally designated parks or protected areas. If resettlement for the project begins before

    initial discussions with the Bank and the acquisition of the area is directly linked to the Bank project,

    then the substantive aspects of OP 4.12 apply retroactively. In other words, if an area is being

    cleared in anticipation of, or preparation for, a project, OP 4.12 would apply.

    Grievance redress/ Public Complaints Centre

    The Bank requires that RPs specify grievance procedures available to displaced persons (DPs). A

    checklist of issues to be considered in design of grievance procedures includes the following:

    An inventory of any reliable conflict mediation organizations or procedures in the project area and an assessment to determine if any can be used instead of having to create new ones.

    A review of grievance redresses mechanisms for simplicity, accessibility, affordability, and accountability. Good practice is to ensure that DPs can apply orally and in the local language

    and to impose explicit time limits for addressing grievances. Appeal procedures need to be

    specified, and that information needs to be made available to the DPs.

    Any new committee created to address grievances will need to be given the authority to resolve complaints. Such committees normally include representatives of DPs or NGOs, as well as

    project officials and staff from other agencies with a substantial role in resettlement activities.

    2.2.3 Mandatory Bank Procedures

    BP 17.50 Bank Disclosure Policies

    This mandatory Bank Procedure (BP) supports decision making through the Borrower and Bank by

    allowing the public access to information on environmental and social aspects of projects.

    It is mandated by six safeguard policies that have specific requirements for disclosure.

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    Final Revised ESIA Report 7 Consolidated Consultants

    In country: before project appraisal in local language and in English

    Wold Bank INFO-Shop: before project appraisal in English (documents can be in draft but must meet World Bank standards)

    2.2.4 WB Safeguard Guidelines

    Environmental, Health and Safety (EHS) General Guidelines

    Occupational Health and Safety Guidelines – IFC

    Environmental Assessment Sourcebook (and updates)

    WB Participation Sourcebook

    Electronic Resettlement Guidebook

    Safeguard Policy Basics – Redbook

    Table 1 summarises the applicable World Bank Safeguard Policies.

    Table 1: Summary of the relevant World Bank Safeguard Policies Safeguard Policies

    OP/BP 4.01 Environmental Assessment

    OP 4.04 Natural Habitats

    OP 4.11 Physical Cultural Resources

    OP 4.12 Involuntary Resettlement

    BP 17.50 Bank Disclosure Policy

    WB Safeguard Guidelines

    Pollution Prevention and Abatement Handbook – PPAH

    Occupational Health and Safety Guidelines – IFC

    Environmental Assessment Sourcebook (and updates)

    WB Participation Sourcebook

    Electronic Resettlement Guidebook

    Safeguard Policy Basics – Redbook

    2.3 Environmental International and Regional Conventions and Treaties

    Basel Convention on the Control of Trans-boundary Movements of Hazardous Waste and

    Their Disposal

    The convention sets out the baseline guidance towards governing and managing hazardous waste

    moving across international boundaries. Applicability of this international convention to the subject

  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) EXPRESSWAY NO.1

    Final Revised ESIA Report 8 Consolidated Consultants

    projects emerges from the possibility of affecting the environment through a variety of hazardous

    waste materials generated from construction and operational phases. According to the Convention, it

    is prohibited by any means the movement/export/import of hazardous waste through a boundary

    country, boundary movements. Reduction of hazardous waste generation should be ensured to the

    minimum, taking into account social, technological and economic aspects.

    With regard to hazardous waste management, countries involved should take practical steps, to the

    extent possible, to provide adequate facilitations, for the environmentally sound management of

    hazardous waste and other wastes. Furthermore, prevention measures and practical steps should be

    ensured by the involved workers while managing wastes and hazardous wastes, this would also

    include minimization of consequences affecting human health and environment.

    Climate Convention and Kyoto Protocol


Recommended