Date post: | 14-Jan-2016 |
Category: |
Documents |
Upload: | joella-ellis |
View: | 218 times |
Download: | 3 times |
www.regouniversity.comPPM Educational Community
(half day)Building Solutions with Open Workbench
2 PPM Educational Community
Course Goals and Objectives
• Goal: To learn the advanced functionality of Open Workbench (OWB) to build, schedule and control a project.
• Objectives: At the end of this course you will have the knowledge to:
– Access and Navigate in Open Workbench
– Use and Manipulate Views
– Manipulate the Work Breakdown Structure
– Build Task Dependencies
3 PPM Educational Community
Goals & Objectives Continued….
– Assign Resources to Tasks
– Use Autoschedule– Baseline your Project – Transfer Assignments– Understand the role of timesheets in the tracking and
control cycle.– Manage Pending Actuals and ETCs– Accept or Reject Pending ETCs– Update Task and Project Status
4 PPM Educational Community
Module One: Getting Started
• Learn about Open Workbench options.• Learn about Open Workbench defaults.• Learn how to navigate in Open Workbench.
5 PPM Educational Community
Accessing OWB From PPM• Logon to PPM• Open a project • From Project Properties Main - General, select either
Read/Write or Read Only and click Go to open the project in OWB.
• This is the preferred method of opening plans in OWB.
6 PPM Educational Community
Couple of Things to Remember:
• Project will Lock in PPM when it’s “checked out” – so no one can update the plan when it’s open in Workbench. The lock is retained until the project is “checked back in” to PPM and you close out of OWB.
• There is no Autosave in OWB – so remember to click on Save periodically to save the plan back to PPM.
7 PPM Educational Community
Things to Remember…
• Actuals will not post to the project while the project is in “locked status”.
• Resources are controlled by PPM – do not manipulate resource data (Resource ID) or the plan will not be accepted back into PPM.
• You can work offline – File, Save As *rmp file type. (still locked)
8 PPM Educational Community
Open Workbench Navigation
• Have a project open in memory– File pull-down menus and icons– Resource and WBS filters– Time Scale and Gantt Chart – View Shortcut Bar, Views and View Groups– Header/Task/Resource Sections– Project and View Tabs (multiple projects and/or multiple
views)
9 PPM Educational Community
Current Application NameProject Name
ViewsView Groups
Pane Separators
Header Buttons aka Row Selectors
Project and/or View Tabs
Column TitlesTime scaled Data
Task Detail
Resource Detail
Navigation
10 PPM Educational Community
Module Two: Using Views
• Discuss Corporate and User view libraries• Amend the layout of an existing view• Use Open Workbench standard Views• Format elements in a view• Use level of analysis and filters on views• Customizing the Timescale• Formatting Quantity Fields• Multiple Timescales• Creating Permanent Filters
11 PPM Educational Community
Using Views
• Corporate View Library – Corporate View Libraries reside on the network. – Your access to the library is read-only.
• User View Library – User View Libraries reside on your workstation
(note that location may differ due to security rights)
– You create and customize your own views.
12 PPM Educational Community
Using Views
• Modifying the Gantt Chart• How to customize a View
– F3 on the keyboard– Or View, Edit View– Or the Edit View Icon
• Deleting and Adding Columns• Formatting Data Elements • Time Scales
• Filters and Sorts • Saving a View into a View Group
12
13 PPM Educational Community
Highlights
• Modifying the existing highlights• How to create highlights
– Add line at location for hierarchy– Set look and feel for results– Establish conditions for new highlight
• Double click condition field• Fill in filter elements
– Save with new file name• Switch highlight files
13
14 PPM Educational Community
Entering Task Dependencies• Terminology: Predecessor is the task that comes before and
the Successor task is the one that comes after. • Using the Dependencies View• How to Break Dependencies – Dialog box only! Note: OWB and PPM only support dependencies at the lowest
level of the Work Breakdown Structure (Task)• OWB supports the following dependency types:
– Finish to Start (most commonly used)– Finish to Finish– Start to Start – Start to Finish
15 PPM Educational Community
Module Three: Resource Planning
• Look at resource properties.• Use a resource’s calendar to view availability.• Assign roles and estimates to tasks.
16 PPM Educational Community
Resource Assignment to Task
• Accessing Resource Information: Right click on a resource name and select Modify to review properties and the resource calendar.
• Assigning Resources to Tasks– Spreadsheet View: Resource Assignment– Spreadsheet View: Drag and Drop – Task Dialog Box – Task Dialog Box: Releasing a Resource
17 PPM Educational Community
Resource Calendars
• When actual resources are added to a plan, the PM needs to addressed planned time off for the project team.
• Resource Calendars can be accessed via Open Workbench as well as CA PPM.
18 PPM Educational Community
• Fixed duration tasks are time constrained
• Variable duration tasks are resource constrained
Task Duration
19 PPM Educational Community
Loading Patterns
Front Back Contour
Uniform Fixed
20 PPM Educational Community
0 0 7 3 0 7 7 7 7 7Unused Availability
Where’s the first availability of 15 hours?
1 2 3 4 5 6 7 8 9 10
Availability
21 PPM Educational Community
0 0 7 3 0 7 7 7 7 7Unused Availability
Days 3 through 6 contain at least 15 hours of
availability
1 2 3 4 5 6 7 8 9 10
Availability
22 PPM Educational Community
0 0 7 3 0 7 7 7 7 71 2 3 4 5 6 7 8 9 10
Unused Availability
Fixed
Uniform
Contour
Front
Back
7 7 1
5 5 5
1 7 7
5 5 5
5 0 5 0 5
Variable Duration
23 PPM Educational Community
0 0 7 3 0 7 7 7 7 71 2 3 4 5 6 7 8 9 10
Unused Availability
Fixed
Uniform
Contour
Front
Back
7 7 1
5 5 5
1 7 7
5 5 5
5 0 5 0 5
7 3 0 5
Variable Duration
24 PPM Educational Community
0 0 7 3 0 7 7 7 7 71 2 3 4 5 6 7 8 9 10Unused Availability
Fixed
Uniform
Contour
Front
Back
7 7 1
5 5 5
1 7 7
5 5 5
5 0 5 0 5
7 3 0 5
6 3 0 6
Variable Duration
25 PPM Educational Community
0 0 7 3 0 7 7 7 7 71 2 3 4 5 6 7 8 9 10
Unused Availability
Fixed
Uniform
Contour
Front
Back
7 7 1
5 5 5
1 7 7
5 5 5
5 0 5 0 5
7 3 0 5
6 3 0 6
5 3 0 7
Variable Duration
26 PPM Educational Community
0 0 7 3 0 7 7 7 7 71 2 3 4 5 6 7 8 9 10Unused Availability
Fixed
Uniform
Contour
Front
Back
7 7 1
5 5 5
1 7 7
5 5 5
5 0 5 0 5
7 3 0 5
6 3 0 6
5 3 0 7
5 5 5
Variable Duration
27 PPM Educational Community
0 0 7 3 0 7 7 7 7 71 2 3 4 5 6 7 8 9 10Unused Availability
Fixed
Uniform
Contour
Front
Back
7 7 1
5 5 5
1 7 7
5 5 5
5 0 5 0 5
7 3 0 5
6 3 0 6
5 3 0 7
5 5 5
5 0 5 0 5
Variable Duration
28 PPM Educational Community
0 0 7 3 0 7 7 7 7 71 2 3 4 5 6 7 8 9 10
Unused Availability
Fixed
Uniform
Contour
Front
Back
7 7 1 0 0
3 3 3 3 3
0 0 1 7 7
3 3 3 3 3
5 0 5 0 5
Fixed Duration
29 PPM Educational Community
0 0 7 3 0 7 7 7 7 71 2 3 4 5 6 7 8 9 10Unused Availability
Fixed
Uniform
Contour
Front
Back
7 7 1 0 0
3 3 3 3 3
0 0 1 7 7
3 3 3 3 3
5 0 5 0 5
7 3 0 5 0
Fixed Duration
30 PPM Educational Community
0 0 7 3 0 7 7 7 7 71 2 3 4 5 6 7 8 9 10
Unused Availability
Fixed
Uniform
Contour
Front
Back
7 7 1 0 0
3 3 3 3 3
0 0 1 7 7
3 3 3 3 3
5 0 5 0 5
7 3 0 5 0
4 3 0 4 4
Fixed Duration
31 PPM Educational Community
0 0 7 3 0 7 7 7 7 71 2 3 4 5 6 7 8 9 10Unused Availability
Fixed
Uniform
Contour
Front
Back
7 7 1 0 0
3 3 3 3 3
0 0 1 7 7
3 3 3 3 3
5 0 5 0 5
7 3 0 5 0
4 3 0 4 4
0 5 3 0 7
Fixed Duration
32 PPM Educational Community
0 0 7 3 0 7 7 7 7 71 2 3 4 5 6 7 8 9 10
Unused Availability
Fixed
Uniform
Contour
Front
Back
7 7 1 0 0
3 3 3 3 3
0 0 1 7 7
3 3 3 3 3
5 0 5 0 5
7 3 0 5 0
4 3 0 4 4
0 5 3 0 7
3 3 3 3 3
Fixed Duration
33 PPM Educational Community
0 0 7 3 0 7 7 7 7 71 2 3 4 5 6 7 8 9 10
Unused Availability
Fixed
Uniform
Contour
Front
Back
7 7 1 0 0
3 3 3 3 3
0 0 1 7 7
3 3 3 3 3
5 0 5 0 5
7 3 0 5 0
4 3 0 4 4
0 5 3 0 7
3 3 3 3 3
5 0 5 0 5
Fixed Duration
34 PPM Educational Community
Module Four: Schedule Development
• Calculate task durations• Calculate the critical path• Create a basic schedule using automated methods
35 PPM Educational Community
Calculating Critical Path
DB
C
A
How many paths are there through this
network?
36 PPM Educational Community
Calculating Critical Path
DB
C
A2 8 4
6
Which path is the longest?
37 PPM Educational Community
Calculating Critical Path
37
DBA2 8
6
4
Critical Path: The longest path through the network based on task duration and
dependencies.
C6
38 PPM Educational Community
Module Five: Autoschedule • To effectively create a schedule, a manager must take into
account:– The tasks to be performed– The relationships between those tasks, and– The availability of the resources to do the work
• Autoschedule is a automated way to create project schedules. • Tasks are scheduled sequentially as they appear in the WBS, or
in order of priority.
39 PPM Educational Community
Autoschedule
• Each task is scheduled to start at the earliest or latest possible time, subject to constraints. Before scheduling, Autoschedule automatically calculates the project’s critical path.
• Autoschedule uses an internal set of rules to create a schedule that takes task constraints, dependencies, priority, and optionally, resource constraints into account.
40 PPM Educational Community
Autoschedule Continued…
• By default, Autoschedule operates on the entire project, but does not change tasks that meet the following conditions:– Tasks starting earlier than the date in the Ignore Before
text box– Tasks starting later than the date in the Ignore After text
box– Tasks marked as Locked or Completed– Tasks that have actuals, except for the time period
between the last actuals thru date and the finish date.• Autoschedule performs three passes of the project to create a
schedule that satisfies all dependencies and does not over-allocate selected resources. Each includes a forward pass and a backward pass.
41 PPM Educational Community
Autoschedule Continued…
• To develop a schedule, the following three passes are performed whether you schedule from the project start or finish date:
– During the first pass, Autoschedule creates a baseline schedule and performs a priority sort to resolve potential scheduling conflicts.
– During the second pass, the schedule is created. (Availability, Allocation, Calendars, ETCs, Loading Patterns, Resource Constraints, Task Constraints, etc.)
– During the third pass, Autoschedule recalculates the critical path based on the schedule developed in the second pass.
42 PPM Educational Community
Autoschedule Rules
• Autoschedule does not reschedule tasks that are locked, have a fixed loading pattern or are completed.
• The start date of started tasks is not changed. • Started tasks are given a higher scheduling priority
than non-started tasks.• The duration of a fixed-duration task is not changed.• The date constraints Must Start On and Must Finish
On for forward and backward scheduling respectively will override dependencies.
43 PPM Educational Community
Autoschedule Rules
• Tasks are scheduled at a daily level (e.g. resource conflicts are resolved on a day by day basis).
• Loading patterns for each resource on each task into account.
• Note: It is possible to set dependencies, constraints, and resource availability so that it is impossible for Autoschedule to produce a schedule free of dependency violations or resource over allocations
44 PPM Educational Community
Establishing a Baseline
• Applies when the “plan” or portions of the plan have been approved.
• Allows a “snapshot” of the project to be taken.• Enables revisions to be compared against the original
plan.• The only way to track planned vs. actual
45 PPM Educational Community
• Baseline duration• Baseline start• Baseline finish• Baseline total usage• Baseline resource usage
What Is Baselined
46 PPM Educational Community
Module Six: Execution• Review the tracking cycle• Review pending actuals• Review pending estimates• Review posted actuals• Update task status• Complete the tracking cycle in OWB
47 PPM Educational Community
Pending Actuals
47
48 PPM Educational Community
Pending Actuals
• Build a Filter to see only those tasks with Pending Actuals
49 PPM Educational Community
Pending Estimates
50 PPM Educational Community
Pending Estimates
51 PPM Educational Community
Module Seven: Managing Multiple Projects
• External Dependencies• Master Projects• Creating subprojects from project parts
52 PPM Educational Community
External Dependencies
• Select the task in your project to which you want to establish an external dependency.
• Select the Projects tab in OWB• In the External sub tab, select Dependencies.• Select Insert in the dialog box.• Browse to the external project.• Browse to the desired task and click on it.• Press Select.
53 PPM Educational Community
Master Projects
• Start with an existing project or a null project to serve as the Master.
• Add subprojects using the Open command with the Create Subprojects option.
54 PPM Educational Community
Master Projects From Project Parts
• Start with an existing project or a null project to serve as the Master.
• On the External sub tab of the Project tab in OWB, select Subprojects.
• Click on Insert in the dialog box.• Browse to the desired project and select.• Browse to the part of the project to be included and
select it.• Click the Select button.
55 PPM Educational Community
Module Eight: Controlling
• Analyze the current status of the project.• Identify problem areas within the plan.• Reschedule and re-plan where necessary.
56 PPM Educational Community
Analyzing Progress
• The project managers focus is on measuring progress, identifying variances and identifying corrective action
57 PPM Educational Community
Analyzing Progress
• The project manager needs to review the project plan for:
–Tasks which were scheduled to start but did not.–Tasks which were scheduled to be completed but did
not.–Unplanned tasks and assignments (scope changes).–Resource overcommitment.–Dependency violations.
58 PPM Educational Community
Analyzing Progress
• To Evaluate plan progress the PM must identify: – Duration Variance– Start or End Date Variance– Usage (Cost) Variance
59 PPM Educational Community
Ensuring A Successful Project• Clear definition of the project (documented)• Customer/client commitment• Involvement of a high-level project champion• Realistic expectations of the project• Control of the project scope • Identification of potential risks and establishment of
contingency plans• Good project communications
60 PPM Educational Community
Questions
Phone888.813.0444
Websitewww.regouniversity.com
We hope that you found this session informative and worthwhile. Our primary goal was to increase your understanding of the topic and CA PPM in general.
There were many concepts covered during the session, if you would like to contact any presenter with questions, please reach out to us.
Thank you for attending regoUniversity 2015!