Yolanda Recovery and Rehabilitation Plan Immediate Interventions 1 November 27, 2013
Transcript
Page 1: Yolanda Recovery and Rehabilitation Plan Immediate Interventions 1 November 27, 2013.

1

Yolanda Recovery and Rehabilitation Plan

Immediate Interventions

November 27, 2013

Page 2: Yolanda Recovery and Rehabilitation Plan Immediate Interventions 1 November 27, 2013.

2

Page 3: Yolanda Recovery and Rehabilitation Plan Immediate Interventions 1 November 27, 2013.

3

Rapid Start-Up InitiativesCluster Activity Immediate activities Shelter and Reconstruction/ Power Generation

Priority Infrastructure Repairs

Roads, bridges, airports, ports, LGU facilities, DepED, DoH, water supply, power, NIA

Social Services, Health and Education

Enhance Provision of Social Services

Continuing support to critical services, including: On-going relief operations (food/water) Cash transfers Medical supplies, services

Livelihood and Employment

Priority Assistance to Agriculture Sector

Provide immediate assistance to farmers to start next season planting (the Agriculture Early Recovery program, used after Typhoon Ondoy)

All sectors

Expand Existing Programs

Existing programs (such as “Pag-Ibig” housing) that can be expanded and/or redirected

New Programs Such as “housing kits” (Lead Agency? Targeting? Logistics?)

Page 4: Yolanda Recovery and Rehabilitation Plan Immediate Interventions 1 November 27, 2013.

4

Resettlement and Housing• Resettle affected families previously living in “no

build” zones Construction of temporary housing (bunkhouses) of P150,000 for 315,000 families = P47.3B

• Rebuilding houses of affected families in “ok to build” areas Housing grant of P30,000 for 218,958 families = P6.6B

• Repair damaged houses of affected families in “ok to build” areas Housing materials assistance (NHA model) of P10,000 for 551,674 families = P5.5B

Page 5: Yolanda Recovery and Rehabilitation Plan Immediate Interventions 1 November 27, 2013.

5

Critical Public Infrastructure• Roads, bridges, flood control, public buildings

(DPWH) = P1.0B• LGU infrastructure – local roads clearing, water

supply, municipal halls, police/fire station, public markets, health facilities, multi-purpose (DPWH, DILG) = P10.9B

• Water supply (LWUA) = P0.2B• Power transmission and distribution = P5.9B• Ports, airports, LGU ports, coast guard, LTO,

LTFRB (DOTC, PPA, CAAP) = P0.8B

Page 6: Yolanda Recovery and Rehabilitation Plan Immediate Interventions 1 November 27, 2013.

6

Re-establishing and Scaling Up Social Services

Page 7: Yolanda Recovery and Rehabilitation Plan Immediate Interventions 1 November 27, 2013.

7

Restarting Agriculture

• Immediate – Total = P4.6B– Clearing operations = P0.4B– Fuel subsidy = P0.1B– Farm tools = P0.1B– Seeds (rice, corn) = P0.1B– Coconut rehabilitation = P1.8B– Banca and fishing paraphernalia = P2.2B

• Medium to long-term = P2.3B– Coconut rehabilitation = P2.0B– Irrigation (NIA) = P0.3B

Page 8: Yolanda Recovery and Rehabilitation Plan Immediate Interventions 1 November 27, 2013.

8

Short-term Employment Opportunities

• Cash for work programs– DOLE = P0.1B– DSWD = P7.2B

• Livelihood programs– DOLE = P0.09B– DSWD (Sustainable livelihood program) = P2.9B

Page 9: Yolanda Recovery and Rehabilitation Plan Immediate Interventions 1 November 27, 2013.

9

Re-establishing Private Assets

• Expand access to finance to recapitalize enterprises in affected areas:– GFIs – Land Bank, DBP– Microfinance institutions – one-off subsidies

for loan restructuring and micro-loans– Limited government guarantees to private

banks

Page 10: Yolanda Recovery and Rehabilitation Plan Immediate Interventions 1 November 27, 2013.

10

Restoring LGU Operations

• Options for enhanced LGU response and participation based on a supportive, performance-based framework– Offer and provide range of support to LGUs

(technical assistance, grants, loans)– NGA-LGU “post-disaster recovery and

rehabilitation compacts” with targeted LGUs

Page 11: Yolanda Recovery and Rehabilitation Plan Immediate Interventions 1 November 27, 2013.

11

Tapering Relief

• Relief Operations for next three months (DSWD) = P30.3B

• Relief will become increasingly focused on people from areas that were catastrophically or severely affected– in situ, displaced within home LGU– migrants (temporary/permanent)

• Moderately affected areas will tend to recover with a natural decline in the need for relief

Page 12: Yolanda Recovery and Rehabilitation Plan Immediate Interventions 1 November 27, 2013.

12

Preliminary Indicative Estimate of Total Budget Requirements for Yolanda Recovery and Rehabilitation

Resettlement and Housing 59.4Critical Public Infrastructure 18.8Re-establishing and Scaling Up Social Services 13.5Re-starting Agriculture 4.6Short-term employment 10.3Re-establishing Private Assets n.a.Restoring LGU operations n.a.Tapering Relief 30.3(Billion pesos) 136.8


Recommended