ANALISA HARGA SATUAN PEKERJAAN Kode Analisa : C.5.b Jenis Pekerjaaan Asumsi Pekerjaan : 1 M² HSP : Rp 515,135.00 No. URAIAN SATUAN KUANTITAS HARGA SATUAN JUMLAH HARGA (Rp) (Rp) A. UPAH a. Menganyam 1 Pekerja Org/Hari 2.1600 45,000.00 97,200.00 2 Mandor Org/Hari 0.0960 55,000.00 5,280.00 3 Tukang Ayam Org/Hari 2.6400 50,000.00 132,000.00 b. Mengisi 1 Pekerja Org/Hari 4.5000 45,000.00 202,500.00 2 Mandor Org/Hari 0.0750 55,000.00 4,125.00 JUMLAH A. 441,105.00 B. BAHAN 1 Batu Kali M3 3.6000 115,500.00 415,800.00 2 Kawat Beronjong Ø 4 mm Kg 54.0000 12,750.00 688,500.00 JUMLAH B. 1,104,300.00 C. JUMLAH A + B = 1,545,405.00 Untuk 1 M3 Beronjong = 1/3 x 0.333 515,135.00 D. DIBULATKAN 515,135.00 Painan, 19 Oktober 2009 Kontraktor Pelaksana: CV. RAISYAH KARYA HASAN SYURYA DINATA, A.Md Direktur : PASANGAN BERONJONG KAWAT Ø 4 mm / 3 M³
Transcript

ANALISA HARGA SATUAN PEKERJAAN

Kode Analisa : C.5.bJenis Pekerjaaan Asumsi Pekerjaan : 1 M²HSP : Rp 515,135.00

No. URAIAN SATUAN KUANTITAS HARGA SATUAN JUMLAH HARGA(Rp) (Rp)

A. UPAHa. Menganyam

1 Pekerja Org/Hari 2.1600 45,000.00 97,200.002 Mandor Org/Hari 0.0960 55,000.00 5,280.003 Tukang Ayam Org/Hari 2.6400 50,000.00 132,000.00

b. Mengisi1 Pekerja Org/Hari 4.5000 45,000.00 202,500.002 Mandor Org/Hari 0.0750 55,000.00 4,125.00

JUMLAH A. 441,105.00

B. BAHAN1 Batu Kali M3 3.6000 115,500.00 415,800.002 Kawat Beronjong Ø 4 mm Kg 54.0000 12,750.00 688,500.00

JUMLAH B. 1,104,300.00

C. JUMLAH A + B = 1,545,405.00Untuk 1 M3 Beronjong = 1/3 x 0.333 515,135.00

D. DIBULATKAN 515,135.00

Painan, 19 Oktober 2009Kontraktor Pelaksana:CV. RAISYAH KARYA

HASAN SYURYA DINATA, A.MdDirektur

: PASANGAN BERONJONG KAWAT Ø 4 mm / 3 M³

ANALISA HARGA SATUAN PEKERJAAN

Kode Analisa : C.51.cJenis Pekerjaaan : SIARAN CAMP 1 : 2Asumsi Pekerjaan : M²HSP : Rp

No. URAIAN SATUAN KUANTITAS HARGA SATUAN JUMLAH HARGA(Rp) (Rp)

A. UPAH1 Pekerja Org/Hari 0.3600 45,000.00 16,200.002 Tukang Batu Org/Hari 0.1200 50,000.00 6,000.003 Kepala Tukang Org/Hari 0.1200 55,000.00 6,600.004 Mandor Org/Hari 0.0200 55,000.00 1,100.00

JUMLAH A. 29,900.00

B. BAHAN1 Semen Zak 0.1050 72,500.00 7,612.502 Pasir M³ 0.0085 108,500.00 922.25

JUMLAH B. 8,534.75

C. JUMLAH A + B = 38,434.75

D. DIBULATKAN 38,434.75

Painan, 19 Oktober 2009Kontraktor Pelaksana:CV. RAISYAH KARYA

HASAN SYURYA DINATA, A.MdDirektur

ANALISA HARGA SATUAN PEKERJAAN

Kode Analisa : G.50Jenis Pekerjaaan : PLESTERAN CAMP 1 : 3Asumsi Pekerjaan : M²HSP : Rp

No. URAIAN SATUAN KUANTITAS HARGA SATUAN JUMLAH HARGA(Rp) (Rp)

A. UPAH1 Pekerja Org/Hari 0.4000 45,000.00 18,000.002 Mandor Org/Hari 0.0200 55,000.00 1,100.003 Tukang Batu Org/Hari 0.2000 50,000.00 10,000.004 Kepala Tukang Batu Org/Hari 0.0200 55,000.00 1,100.00

JUMLAH A. 30,200.00

B. BAHAN1 Semen @ 50 Kg Zak 0.1632 72,500.00 11,832.002 Pasir M³ 0.0194 108,500.00 2,104.90

JUMLAH B. 13,936.90

C. JUMLAH A + B = 44,136.90

D. DIBULATKAN 44,136.90

Painan, 19 Oktober 2009Kontraktor Pelaksana:CV. RAISYAH KARYA

HASAN SYURYA DINATA, A.MdDirektur

ANALISA HARGA SATUAN PEKERJAAN

Kode Analisa : G.32.hJenis Pekerjaaan : PAS. BATU KALI CAMP 1 : 4Asumsi Pekerjaan : M³HSP : Rp

No. URAIAN SATUAN KUANTITAS HARGA SATUAN JUMLAH HARGA(Rp) (Rp)

A. UPAH1 Pekerja Org/Hari 3.6000 45,000.00 162,000.002 Mandor Org/Hari 0.1800 55,000.00 9,900.003 Tukang Batu Org/Hari 1.2000 50,000.00 60,000.004 Kepala Tukang Batu Org/Hari 0.1200 55,000.00 6,600.00

JUMLAH A. 238,500.00

B. BAHAN1 Batu Kali M³ 1.2000 115,500.00 138,600.002 Semen @ 50 Kg Zak 3.2572 72,500.00 236,147.003 Pasir M³ 0.5220 108,500.00 56,637.00

JUMLAH B. 431,384.00

C. JUMLAH A + B = 669,884.00

D. DIBULATKAN 669,884.00

Painan, 19 Oktober 2009Kontraktor Pelaksana:CV. RAISYAH KARYA

HASAN SYURYA DINATA, A.MdDirektur

ANALISA HARGA SATUAN PEKERJAAN

Kode Analisa : A.16Jenis Pekerjaaan : TANAH TIMBUNAN DIPADATKAN / DIRATAKANAsumsi Pekerjaan : M³HSP : Rp 11,800.00

No. URAIAN SATUAN KUANTITAS HARGA SATUAN JUMLAH HARGA(Rp) (Rp)

A. UPAH1 Pekerja Org/Hari 0.2500 45,000.00 11,250.002 Mandor Org/Hari 0.0100 55,000.00 550.00

JUMLAH A. 11,800.00

B. BAHAN

JUMLAH B.

C. JUMLAH A + B = 11,800.00

D. DIBULATKAN 11,800.00

Painan, 19 Oktober 2009Kontraktor Pelaksana:CV. RAISYAH KARYA

HASAN SYURYA DINATA, A.MdDirektur

ANALISA HARGA SATUAN PEKERJAAN

Kode Analisa : A.15Jenis Pekerjaaan Asumsi Pekerjaan : M³HSP : Rp 62,325.00

No. URAIAN SATUAN KUANTITAS HARGA SATUAN JUMLAH HARGA(Rp) (Rp)

A. UPAH1 Analisa A.1 1.0000 35,125.00 35,125.002 Analisa A.16 1.0000 11,800.00 11,800.003 Analisa A.6 1.0000 15,400.00 15,400.00

JUMLAH A. 62,325.00

B. BAHAN

JUMLAH B.

C. JUMLAH A + B = 62,325.00

D. DIBULATKAN 62,325.00

Painan, 19 Oktober 2009Kontraktor Pelaksana:CV. RAISYAH KARYA

HASAN SYURYA DINATA, A.MdDirektur

: TIMBUNAN TANAH DIANGKUT SEJAUH 30 M' / M³

ANALISA HARGA SATUAN PEKERJAAN

Kode Analisa : A.3Jenis Pekerjaaan : GALIAN TANAH BERBATUAsumsi Pekerjaan : M³HSP : Rp

No. URAIAN SATUAN KUANTITAS HARGA SATUAN JUMLAH HARGA(Rp) (Rp)

A. UPAH1 Pekerja Org/Hari 1.5000 45,000.00 67,500.002 Mandor Org/Hari 0.0500 55,000.00 2,750.00

JUMLAH A. 70,250.00

B. BAHAN

JUMLAH B.

C. JUMLAH A + B = 70,250.00

D. DIBULATKAN 70,250.00

Painan, 19 Oktober 2009Kontraktor Pelaksana:CV. RAISYAH KARYA

HASAN SYURYA DINATA, A.MdDirektur

ANALISA HARGA SATUAN PEKERJAAN

Kode Analisa : A.1Jenis Pekerjaaan : GALIAN TANAH BIASAAsumsi Pekerjaan : M³HSP : Rp 35,125.00

No. URAIAN SATUAN KUANTITAS HARGA SATUAN JUMLAH HARGA(Rp) (Rp)

A. UPAH1 Pekerja Org/Hari 0.7500 45,000.00 33,750.002 Mandor Org/Hari 0.0250 55,000.00 1,375.00

JUMLAH A. 35,125.00

B. BAHAN

JUMLAH B.

C. JUMLAH A + B = 35,125.00

D. DIBULATKAN 35,125.00

Painan, 19 Oktober 2009Kontraktor Pelaksana:CV. RAISYAH KARYA

HASAN SYURYA DINATA, A.Md

Direktur

ANALISA HARGA SATUAN PEKERJAAN

Kode Analisa : A.6Jenis Pekerjaaan : TANAH DIANGKUT SEJAUH 30 M'Asumsi Pekerjaan : M³HSP : Rp 15,400.00

No. URAIAN SATUAN KUANTITAS HARGA SATUAN JUMLAH HARGA(Rp) (Rp)

A. UPAH1 Pekerja Org/Hari 0.3300 45,000.00 14,850.002 Mandor Org/Hari 0.0100 55,000.00 550.00

JUMLAH A. 15,400.00

B. BAHAN

JUMLAH B.

C. JUMLAH A + B = 15,400.00

D. DIBULATKAN 15,400.00

Painan, 19 Oktober 2009Kontraktor Pelaksana:CV. RAISYAH KARYA

HASAN SYURYA DINATA, A.MdDirektur

ANALISA HARGA SATUAN PEKERJAAN

Kode Analisa : Prt.w-1Jenis Pekerjaaan : FOTO DOKUMENTASI : Sebelum, Sedang, dan SelesaiAsumsi Pekerjaan : LsHSP : Rp

No. URAIAN SATUAN KUANTITAS HARGA SATUAN JUMLAH HARGA(Rp) (Rp)

A. UPAH1 Pekerja Org/Hari 1.0000 45,000.00 45,000.002 Photografer Org/Hari 1.0000 55,000.00 55,000.003 Pembantu Photografer Org/Hari 1.0000 35,500.00 35,500.00

JUMLAH A. 135,500.00

B. BAHAN1 Camera Buah 1.0000 300,000.00 300,000.002 Film Rol 3.0000 45,000.00 135,000.003 Album Buah 3.0000 30,000.00 90,000.00

JUMLAH B 525,000.00

C. PROSES1 Cuci Rol 3.0000 9,000.00 27,000.002 Cetak Photo Lembar 108.0000 1,000.00 108,000.00

JUMLAH C. 135,000.00

D. JUMLAH A + B + C = 795,500.00

E. DIBULATKAN 795,500.00

Painan, 19 Oktober 2009Kontraktor Pelaksana:CV. RAISYAH KARYA

HASAN SYURYA DINATA, A.MdDirektur

ANALISA HARGA SATUAN PEKERJAAN

Kode Analisa : Jenis Pekerjaaan : Pengukuran Band Meeting (Meteran Rantai)Asumsi Pekerjaan : M'HSP : Rp

No. URAIAN SATUAN KUANTITAS HARGA SATUAN JUMLAH HARGA(Rp) (Rp)

A. UPAH1 Mandor Org/Hari 0.2500 45,000.00 11,250.002 Pekerja Org/Hari 3.0000 55,000.00 165,000.003 0.00

176,250.00JUMLAH A. 0.0005 88.13

B. BAHAN1 Kayu Patok Btg 41.000 5,000.00 205,000.002 Cat Menie Kg 0.0100 25,000.00 250.003 Paku Kg 0.0100 11,500.00 115.00

205,365.00JUMLAH B 0.0005 102.68

C. PERALATAN1 Meteran, Kwas dan Alat Ban Ls 1.0000 25,000.00 25,000.00

Lainnya 0.0025,000.00

JUMLAH C. 0.0005 12.50

C. JUMLAH A + B + C = 203.31

D. DIBULATKAN 203.31

Painan, 19 Oktober 2009Kontraktor Pelaksana:CV. RAISYAH KARYA

HASAN SYURYA DINATA, A.MdDirektur

ANALISA HARGA SATUAN PEKERJAAN

Kode Analisa : Jenis Pekerjaaan : Pengukuran Polygon Untuk menentukan Arah SaluranAsumsi Pekerjaan : M'HSP : Rp

No. URAIAN SATUAN KUANTITAS HARGA SATUAN JUMLAH HARGA(Rp) (Rp)

A. UPAH1 Pengawas Ukur Org/Hari 0.2000 55,000.00 11,000.002 Juru Ukur Org/Hari 1.0000 55,000.00 55,000.003 Mandor Org/Hari 0.2500 55,000.00 13,750.004 Pekerja Org/Hari 5.0000 45,000.00 225,000.00

304,750.00JUMLAH A. 0.0017 518.07

B. BAHAN1 0.002 0.003 0.00

JUMLAH B 0.00

C. PERALATAN1 Theodolite/Waterpass (sewa Unti 1.0000 150,000.00 150,000.002 0.00

150,000.00

JUMLAH C. 0.0017 255.00

C. JUMLAH A + B + C = 773.07

D. DIBULATKAN 773.07

Painan, 19 Oktober 2009Kontraktor Pelaksana:CV. RAISYAH KARYA

HASAN SYURYA DINATA, A.MdDirektur

ANALISA HARGA SATUAN PEKERJAAN

Kode Analisa :Jenis Pekerjaaan : Pengukuran Waterpass, untuk penentuan ElevasiAsumsi Pekerjaan : M'HSP : Rp

No. URAIAN SATUAN KUANTITAS HARGA SATUAN JUMLAH HARGA(Rp) (Rp)

A. UPAH1 Pengawas Ukur Org/Hari 0.2000 55,000.00 11,000.002 Juru Ukur Org/Hari 1.0000 55,000.00 55,000.003 Mandor Org/Hari 0.2500 55,000.00 13,750.004 Pekerja Org/Hari 3.0000 45,000.00 135,000.00

214,750.00JUMLAH A. 0.0009 193.28

B. BAHAN1 0.002 0.003 0.00

JUMLAH B 0.00

C. PERALATAN1 Waterpass Unit 1.0000 100,000.00 100,000.00

2 0.00100,000.00

JUMLAH C. 0.0009 90.00

C. JUMLAH A + B + C = 283.28

D. DIBULATKAN 283.28

Painan, 19 Oktober 2009Kontraktor Pelaksana:CV. RAISYAH KARYA

HASAN SYURYA DINATA, A.MdDirektur

ANALISA HARGA SATUAN PEKERJAAN

Kode Analisa : Jenis Pekerjaaan : Pengukuran Cross Section, untuk Penentuan Elevasi dan

: Bentuk Penampang ExistingAsumsi Pekerjaan : M'HSP : Rp

No. URAIAN SATUAN KUANTITAS HARGA SATUAN JUMLAH HARGA(Rp) (Rp)

A. UPAH1 Juru Ukur Org/Hari 0.2000 55,000.00 11,000.002 Pembantu Juru Ukur Org/Hari 1.0000 35,500.00 35,500.003 Pekerja Org/Hari 5.0000 45,000.00 225,000.004 Mandor Org/Hari 0.2500 55,000.00 13,750.00

285,250.00JUMLAH A. 0.0040 1,141.00

B. BAHAN1 0.002 0.003 0.00

JUMLAH B 0.00

C. PERALATAN1 Theodolite Unit 1.0000 150,000.00 150,000.002 0.00

150,000.00JUMLAH C. 0.0040 600.00

C. JUMLAH A + B + C = 1,741.00

D. DIBULATKAN 1,741.00

Painan, 19 Oktober 2009Kontraktor Pelaksana:CV. RAISYAH KARYA

HASAN SYURYA DINATA, A.MdDirektur

ANALISA HARGA SATUAN PEKERJAAN

Kode Analisa : Jenis Pekerjaaan : Pengambaran & Blue Print Hasil PengukuranAsumsi Pekerjaan : M'HSP : Rp

No. URAIAN SATUAN KUANTITAS HARGA SATUAN JUMLAH HARGA(Rp) (Rp)

A. UPAH1 Pengawas Gambar Org/Hari 1.0000 55,000.00 55,000.002 Drfman / Juru Gambar Org/Hari 1.0000 55,000.00 55,000.003 Quantity Org/Hari 1.0000 55,000.00 55,000.00

165,000.00JUMLAH A. 0.0020 330.00

B. BAHAN1 Kertas Mili Meter Block Rol 0.0002 50,000.00 10.002 Kertas Kalkir Rol 0.0002 85,000.00 17.003 Blue Print M' 0.0300 40000 1200.00

1227.00JUMLAH B 1.0000 1227.00

C. PERALATAN1 Alat-alat Tulis/gambar Ls 1.0000 75,000.00 75,000.002 0.00

75,000.00JUMLAH C. 0.0020 150.00

C. JUMLAH A + B + C = 1,707.00

D. DIBULATKAN 1,707.00

Painan, 19 Oktober 2009Kontraktor Pelaksana:CV. RAISYAH KARYA

HASAN SYURYA DINATA, A.MdDirektur

ANALISA HARGA SATUAN PEKERJAAN

Kode Analisa : A. 15 ( b )Jenis Pekerjaaan : Timbunan Tanah Dari Tanah Bekas Galian / M3Asumsi Pekerjaan : M³HSP : Rp

No. URAIAN SATUAN KUANTITAS HARGA SATUAN JUMLAH HARGA(Rp) (Rp)

A. UPAH1 Analisa A.1 diambil 2/3 0.6670 35,125.00 23,428.382 Analisa A. 16 1.0000 11,800.00 11,800.00

JUMLAH A. 35,228.38

B. BAHAN

JUMLAH B.

C. JUMLAH A + B = 35,228.38

D. DIBULATKAN 35,228.38

Painan, 19 Oktober 2009Kontraktor Pelaksana:CV. RAISYAH KARYA

HASAN SYURYA DINATA, A.MdDirektur

ANALISA HARGA SATUAN PEKERJAAN

Kode Analisa : L. 4Jenis Pekerjaaan : BONGKARAN PASANGAN LAMAAsumsi Pekerjaan : M³HSP : Rp

No. URAIAN SATUAN KUANTITAS HARGA SATUAN JUMLAH HARGA(Rp) (Rp)

A. UPAH1 Pekerja Org/Hari 2.0000 45,000.00 90,000.002 Mandor Org/Hari 0.1000 55,000.00 5,500.00

JUMLAH A. 95,500.00

B. BAHAN

JUMLAH B.

C. JUMLAH A + B = 95,500.00

D. DIBULATKAN 95,500.00

Painan, 19 Oktober 2009Kontraktor Pelaksana:CV. RAISYAH KARYA

HASAN SYURYA DINATA, A.MdDirektur

ANALISA HARGA SATUAN PEKERJAAN

Kode Analisa : L.4Jenis Pekerjaaan : BONGKARAN PASANGAN BERONJONG LAMAAsumsi Pekerjaan : 10 M²HSP : Rp

No. URAIAN SATUAN KUANTITAS HARGA SATUAN JUMLAH HARGA(Rp) (Rp)

A. UPAH1 Pekerja Org/Hari 2.0000 45,000.00 90,000.002 Mandor Org/Hari 0.1000 55,000.00 5,500.00

JUMLAH A. 95,500.00

B. BAHAN

JUMLAH B. 0.00

C. JUMLAH A + B = 95,500.00Diambil 2/3 0.667 63,698.50

D. DIBULATKAN 63,698.50

Painan, 19 Oktober 2009Kontraktor Pelaksana:CV. RAISYAH KARYA

HASAN SYURYA DINATA, A.MdDirektur

ANALISA HARGA SATUAN PEKERJAAN

Kode Analisa : G.41Jenis Pekerjaaan : COR BETON CAMPURAN 1 : 2 : 3Asumsi Pekerjaan HSP : Rp

No. URAIAN SATUAN KUANTITAS HARGA SATUAN JUMLAH HARGA(Rp) (Rp)

A. UPAH1 Pekerja Org/Hari 6.0000 45,000.00 270,000.002 Tukang Batu Org/Hari 1.0000 50,000.00 50,000.003 Kepala Tukang Org/Hari 0.1000 55,000.00 5,500.004 Mandor Org/Hari 0.3000 55,000.00 16,500.00

: M³

JUMLAH A. 342,000.00

B. BAHAN1 Semen Zak 6.8000 72,500.00 493,000.002 Pasir 0.5400 108,500.00 58,590.003 Kerikil 0.8200 115,000.00 94,300.00

JUMLAH B. 645,890.00

C. JUMLAH A + B = 987,890.00

D. DIBULATKAN 987,890.00

Painan, 19 Oktober 2009Kontraktor Pelaksana:CV. RAISYAH KARYA

HASAN SYURYA DINATA, A.MdDirektur

ANALISA HARGA SATUAN PEKERJAAN

Kode Analisa : F. 8Jenis Pekerjaaan Asumsi Pekerjaan : M²HSP : Rp

No. URAIAN SATUAN KUANTITAS HARGA SATUAN JUMLAH HARGA(Rp) (Rp)

A. UPAH1 Pekerja Org/Hari 1.0000 45,000.00 45,000.002 Tukang Kayu Org/Hari 5.0000 50,000.00 250,000.00

M³M³

: CETAKAN BETON 10 M² / 1 M³ BETON

3 Kepala Tukang Org/Hari 0.5000 55,000.00 27,500.004 Mandor Org/Hari 0.1000 55,000.00 5,500.00

JUMLAH A. 328,000.00

B. BAHAN1 Besi Paku Kg 4.0000 11,500.00 46,000.002 Kayu Bekisting 0.4000 1,010,000.00 404,000.00

JUMLAH B. 450,000.00

C. JUMLAH A + B = 778,000.00

D. DIBULATKAN 778,000.00

Painan, 19 Oktober 2009Kontraktor Pelaksana:CV. RAISYAH KARYA

HASAN SYURYA DINATA, A.MdDirektur

ANALISA HARGA SATUAN PEKERJAAN

Kode Analisa : 1. 2Jenis Pekerjaaan : PEMBESIANAsumsi Pekerjaan HSP : Rp

No. URAIAN SATUAN KUANTITAS HARGA SATUAN JUMLAH HARGA(Rp) (Rp)

A. UPAH

: 100 Kg/ M³

1 Pekerja Org/Hari 0.4000 45,000.00 18,000.002 Tukang Besi Org/Hari 0.2000 50,000.00 10,000.003 Kepala Tukang Org/Hari 0.0200 55,000.00 1,100.00

JUMLAH A. 29,100.00

B. BAHAN1 Besi Beton Kg 110.0000 12,000.00 1,320,000.002 Kawat Beton Kg 2.0000 12,500.00 25,000.00

JUMLAH B. 1,345,000.00

C. JUMLAH A + B = 1,374,100.00

D. DIBULATKAN 1,374,100.00

Painan, 19 Oktober 2009Kontraktor Pelaksana:CV. RAISYAH KARYA

HASAN SYURYA DINATA, A.MdDirektur

ANALISA HARGA SATUAN PEKERJAAN

Kode Analisa : G.41 + F. 8 + 1. 2Jenis Pekerjaaan : COR BETON BERTULANG CAMP 1 : 2 : 3Asumsi Pekerjaan HSP : Rp

No. URAIAN SATUAN KUANTITAS HARGA SATUAN JUMLAH HARGA(Rp) (Rp)

: M³

A. UPAH1 Analisa G.41 1.0000 987,890.00 987,890.002 Analisa F. 8 1.0000 778,000.00 778,000.003 Analisa I. 2 1.0000 1,374,100.00 1,374,100.00

JUMLAH A. 3,139,990.00

B. BAHAN

JUMLAH B. 0.00

C. JUMLAH A + B = 3,139,990.00

D. DIBULATKAN 3,139,990.00

Painan, 19 Oktober 2009Kontraktor Pelaksana:CV. RAISYAH KARYA

HASAN SYURYA DINATA, A.MdDirektur

ANALISA HARGA SATUAN BAHAN PEKERJAAN

KEGIATAN : REHABILITASI / PEMELIHARAAN JARINGAN IRIGASI PEKERJAAN : REHABILITASI IRIGASI BANDA GADANG PANCUNG TEBALLOKASI : KEC. BAYANG UTARA KAB. PESISIR SELATANTAHUN ANGGARAN : 2009

No. URAIAN STN

HARGA TRANSPORMASI TRANSP. DGN KUDA/ PAJAK HARGAQUARY MOBIL GEROBAK/T. MANUSIA GALIAN C SATUAN

(Rp)JARAK BIAYA JARAK BIAYA

(Rp) (Rp)(Km) (Rp) (Km) (Rp)

1 SEMEN Zak 52,000.00 15.00 Rp 3,000.00 0.20 Rp 17,500.00 Rp 72,500.00 2 BATU KALI M³ 60,000.00 10.00 Rp 20,000.00 0.20 Rp 30,000.00 Rp 5,500.00 Rp 115,500.00 3 BATU PECAH M³ 60,000.00 15.00 Rp 20,000.00 0.20 Rp 30,000.00 Rp 5,500.00 Rp 115,500.00 4 KERIKIL COR M³ 60,000.00 15.00 Rp 20,000.00 0.20 Rp 30,000.00 Rp 5,000.00 Rp 115,000.00 5 PASIR PASANGAN M³ 55,000.00 5.00 Rp 20,000.00 0.20 Rp 30,000.00 Rp 3,500.00 Rp 108,500.00 6 BESI BETON Kg 11,500.00 20.00 Rp 500.00 Rp 12,000.00 7 BESI PAKU Kg 11,000.00 20.00 Rp 500.00 Rp 11,500.00 8 Kawat Beronjong Ø 4 mm Kg 12,000.00 69.00 Rp 500.00 0.20 Rp 250.00 Rp 12,750.00 9 KERIKIL TIMBUNAN M³ 50,000.00 15.00 Rp 10,000.00 0.20 Rp 2,000.00 Rp 3,000.00 Rp 65,000.00

10 TANAH TIMBUNAN M³ 37,500.00 17.00 Rp 10,000.00 Rp 3,000.00 Rp 50,500.00 11 KAYU BEKISTING M³ 950,000.00 20.00 Rp 50,000.00 0.20 Rp 10,000.00 Rp 1,010,000.00 12 RUMPUT LEMPENG M² 10,000.00 10.00 Rp 5,000.00 Rp 15,000.00 13 KAWAT BETON M³ 12,000.00 69.00 Rp 500.00 Rp 12,500.00 14 TIANG PANCANG M³ 900,000.00 20.00 Rp 50,000.00 0.20 Rp 10,000.00 Rp 960,000.00 15 CAMERA Bh 300,000.00 Rp 300,000.00 16 FILM Rol 45,000.00 Rp 45,000.00 17 ALBUM Bh 30,000.00 Rp 30,000.00 18 KALKIR Rol 85,000.00 Rp 85,000.00 19 ATK Unt 75,000.00 Rp 75,000.00 20 SEWA ALAT WATERPAS Hari 100,000.00 Rp 100,000.00 21 SEWA ALAT THEODOLIT Hari 150,000.00 Rp 150,000.00 22 KAYU PATOK Btg 5,000.00 Rp 5,000.00 23 CAT Kg 25,000.00 Rp 25,000.00 24 KERTAS MILIMETER Rol 50,000.00 Rp 50,000.00 25 BLUE PRINT M' 40,000.00 Rp 40,000.00 26

Painan, 19 Oktober 2009Kontraktor Pelaksana:CV. RAISYAH KARYA

HASAN SYURYA DINATA, A.MdDirektur

DAFTAR HARGA SATUAN UPAH, BAHAN DAN PEKERJAAN

KEGIATAN : REHABILITASI / PEMELIHARAAN JARINGAN IRIGASI PEKERJAAN : REHABILITASI IRIGASI BANDA GADANG PANCUNG TEBALLOKASI : KEC. BAYANG UTARA KAB. PESISIR SELATANTAHUN ANGGARAN : 2009

No. URAIAN TENAGA DAN UPAH HARGA SATUAN (Rp) SATUAN

I. UPAH TENAGA1 Pekerja 45,000.00 Org/Hari2 Mandor 55,000.00 Org/Hari3 Kepala Tukang 55,000.00 Org/Hari4 Tukang Batu , Kayu 50,000.00 Org/Hari5 Tukang Anyam dan Tukang Besi 50,000.00 Org/Hari6 Juru Ukur/Drafman/Quantity/Photografer 55,000.00 Org/Hari7 Pembantu 35,500.00 Org/Hari

II. BAHAN1 Semen 72,500.00 Zak2 Batu Kali 115,500.00 M33 Pasir 108,500.00 M3

Painan, 19 Oktober 2009Kontraktor Pelaksana:CV. RAISYAH KARYA

HASAN SYURYA DINATA, A.MdDirektur

ANALISA HARGA SATUAN PEKERJAAN

REKAPITULASI PENGUKURAN

Asumsi Pekerjaan : 1 M'HSP : Rp

No. URAIAN SATUAN KUANTITASHARGA SATUAN JUMLAH HARGA(Rp) (Rp)

1 Pengambaran dan Blue Print M' 1.000 1,707.00 1,707.00

2 Pengukuran Cross Section M' 1.000 1,741.00 1,741.00

3 Pengukuran Waterpass M' 1.000 283.28 283.28

4 Pengukuran Polygon M' 1.000 773.07 773.07

5 Pengukuran Band Meeting M' 1.000 203.31 203.31

Jumlah 4,707.66

Dibulatkan 4,707.66

Painan, 19 Oktober 2009Kontraktor Pelaksana:CV. RAISYAH KARYA

HASAN SYURYA DINATA, A.MdDirektur

ANALISA HARGA SATUAN PEKERJAAN

REKAPITULASI PERSIAPAN

Asumsi Pekerjaan : 1 M'HSP : Rp

No. URAIAN SATUAN KUANTITASHARGA SATUAN JUMLAH HARGA(Rp) (Rp)

1 Uizetten Pengkuran Kembali, M' 500.000 4,707.66 2,353,828.75actual check,mutual check,penggambaran, administrasi,asbult drawing, dll

2 Foto Dokumentasi : Ls 1.000 795,500.00 795,500.00Sebelum, sedang dan sesudah

Jumlah 3,149,328.75

Dibulatkan 3,149,328.75

Painan, 19 Oktober 2009Kontraktor Pelaksana:CV. RAISYAH KARYA

HASAN SYURYA DINATA, A.MdDirektur

HARGA SATUAN PEKERJAANPEKERJAAN : REHABILITASI / PEMELIHARAAN JARINGAN IRIGASI KEGIATAN : REHABILITASI IRIGASI BANDA GADANG PANCUNG TEBALLOKASI : KEC. BAYANG UTARA KAB. PESISIR SELATANTAHUN ANGGARAN : 2009

No. URAIAN PEKERJAAN SATUANH. SATUAN

KET(Rp)

1 Uitzetten Pengukuran Kembali, Aktual CheckMutual Check, Penggambaran Fotto, Dokumentasi, Administrasi, Asbuilt Drawing, Dll Ls Rp 4,707.66

2 Pekerjaan Kisdam / Pengeringan Ls Rp 5,250,000.00

3 Pekerjaan Galian Tanah Berbatu Rp 70,250.00

4 Pekerjaan Galian Tanah Biasa Rp 35,125.00

5 Pekerjaan Pas. Batu Kali Camp 1 : 4 Rp 669,884.00

6 Pekerjaan Plesteran Camp 1 : 3 Rp 44,136.90

7 Rp 515,135.00

9 Timbunan Tanah dari Tanah Bekas Galian Rp 35,228.38

Painan, 19 Oktober 2009Kontraktor Pelaksana:CV. RAISYAH KARYA

HASAN SYURYA DINATA, A.MdDirektur

Pekerjaan Pas. Beronjong Kawat Ø 4 mm M³

RENCANA ANGGARAN BIAYA (RAB)

KEGIATAN : REHABILITASI / PEMELIHARAAN JARINGAN IRIGASI PEKERJAAN : REHABILITASI IRIGASI BANDA GADANG PANCUNG TEBALLOKASI : KEC. BAYANG UTARA KAB. PESISIR SELATANTHN ANGGARAN : 2009

No. URAIAN PEKERJAAN SATUAN VOLUME H. SATUAN JUMLAH(Rp)

I. PEKERJAAN PENDAHULUAN1 Uitzetten, Pembuatan Matual Check, Actual

Check, Gambar Asbuil Drawing, Foto Dokumentasi dll Ls 1.00 Rp 3,149,328.75 Rp 3,149,328.75

II. PEKERJAAN PELIMPAH DAN PENGURAS1 Pek. Kisdam dan Pengeringan Ls 1.00 Rp 5,250,000.00 Rp 5,250,000.00 2 Pek. Galian Tanah Berbatu M3 29.79 Rp 35,125.00 Rp 1,046,373.75 3 Pek. Pasangan Batu Kali Camp 1 : 4 M3 63.28 Rp 669,884.00 Rp 42,390,259.52 4 Pek. Plesteran Camp 1 : 3 M3 104.20 Rp 44,136.90 Rp 4,599,064.98 5 Pek.Timbunan Tanah dari Tanah Bekas Galian M2 27.68 Rp 35,228.38 Rp 975,121.42

III. PEKERJAAN SALURAN PASANGAN1 Pek. Galian Biasa M3 34.50 Rp 35,125.00 Rp 1,211,812.50 2 Pek. Pasangan Batu Kali Camp 1 : 4 M3 59.70 Rp 669,884.00 Rp 39,992,074.80 3 Pek. Plesteran Camp 1 : 3 M3 149.35 Rp 44,136.90 Rp 6,591,846.02 4 Pek.Timbunan Tanah dari Tanah Bekas Galian M2 19.60 Rp 35,228.38 Rp 690,476.15

JUMLAH KESELURUHAN Rp 105,896,357.89 PPN 10% 10% Rp 10,589,635.79 TOTAL KESELURUHAN Rp 116,485,993.67 DIBULATKAN Rp 116,485,000.00

TERBILANG : SERATUS ENAM BELAS JUTA EMPAT RATUS DELAPAN PULUH LIMA RIBU RUPIAH

Painan, 19 Oktober 2009Mengetahui : Kontraktor Pelaksana:

KUASA PENGGUNA ANGGARAN CV. RAISYAH KARYA

DEVITRA, S.ST HASAN SYURYA DINATA, A.MdNIP : 410 012 994 Direktur

117,510,000.00116,485,993.67

0.99129100.0000

99.12860.87

ANALISA TEKNIS

KEGIATAN : REHABILITASI / PEMELIHARAAN JARINGAN IRIGASI PEKERJAAN: REHABILITASI IRIGASI BANDA GADANG PANCUNG TEBALLOKASI : KEC. BAYANG UTARA KAB. PESISIR SELATANTHN ANGGA: 2009

I Pekerjaan Persiapan1. Pengukuran trase saluran, Profil memanjang dan Profil Melintang

serta PenggambaranA Penggambaran dan Blue Print Hasil Pengukurana Volume Pekerjaan = 500.00 M'b Banyak Kelompok Kerja = 1.00 Groupc Kemampuan Perkelompok perhari = 500.00 M'd Jam Kerja = 8.00 Jame Tenaga Yang dibutuhkan Perhari

Pengawas Gambar = 1.00 OrangDrafman = 1.00 OrangQuantity = 1.00 Orang

f Bahan Yang DibutuhkanKertas Mili Meter Block = 0.10 Rol PerhariKertas Kalkir = 0.10 Rol PerhariBlue Print = 15.00 M'

g Alat Yang dibutuhkanPensil Gambar = 1.00 UnitPena Standler = 1.00 Unit

500.00 =h Waktu Pelaksanaan = 500.00

Dibulatkan = 1.00 Hari

B Pengukuran Band Meeting ( Meteran Rantai )a Volume Pekerjaan = 500.00 M'b Banyak Kelompok Kerja = 1.00 Groupc Kemampuan Perkelompok perhari = 2,000.00 M'd Jam Kerja = 8.00 Jame Tenaga Yang dibutuhkan Perhari

Mandor = 1.00 OrangPekerja = 1.00 Orang

f Bahan Yang DibutuhkanKayu Patok = 11.00 NuahCat Menie = 0.003 KgPaku = 0.003 Kg

g Alat Yang dibutuhkanMeteran = 1.00 BuahKuwas = 1.00 BuahParang = 1.00 Buah

500.00h Waktu Pelaksanaan = 2,000.00 =

= 0.25Dibulatkan = 1.00 Hari

C Pengukuran Cross Section, untuk menentukan elevasia Volume Pekerjaan = 500.00 M'b Banyak Kelompok Kerja = 1.00 Group

c Kemampuan Perkelompok perhari = 250.00 M'd Jam Kerja = 8.00 Jame Tenaga Yang dibutuhkan Perhari

Juru Ukur = 1.00 OrangPembantu Juru Ukur = 1.00 OrangMandor = 5.00 OrangPekerja = 0.25 Orang

f Bahan Yang dibutuhkan Tidak adag Alat Yang dibutuhkan

Theodolite = 1.00 Buah

h Waktu Pelaksanaan = 500.00= 250.00

Dibulatkan = 2.00 Hari

D Pengukuran Polygon Untuk Menentukan arah Salurana Volume Pekerjaan = 500.00 M'b Banyak Kelompok Kerja = 1.00 Groupc Kemampuan Perkelompok perhari = 600.00 M'

d Jam Kerja = 8.00 Jame Tenaga Yang dibutuhkan Perhari

Pengawas Ukur = 1.00 OrangJuru Ukur = 1.00 OrangMandor = 1.00 OrangPekerja = 5.00 Orang

f Bahan Yang dibutuhkan Tidak adag Alat Yang dibutuhkan

Theodolite (sewa ) = 1.00 Unit

h Waktu Pelaksanaan = 500.00

= 600.00Dibulatkan = 0.83

= 1.00 Hari

E Pengukuran Waterpass untuk Penentuan Elevasia Volume Pekerjaan = 500.00 M'

b Banyak Kelompok Kerja = 1.00 Groupc Kemampuan Perkelompok perhari = 1,155.00 M'd Jam Kerja = 8.00 Jam

e Tenaga Yang dibutuhkan PerhariJuru Ukur = 1.00 OrangPembantu Juru Ukur = 1.00 OrangMandor = 1.00 OrangPekerja = 1.00 Orang

f Bahan Yang dibutuhkan Tidak adag Alat Yang dibutuhkan

Waterpass = 1.00 Unit

h Waktu Pelaksanaan = 500.00= 1,155.00

Dibulatkan = 0.43

1.00 Hari

I PEKERJAAN PELIMPAH DAN PENGURAS

1 Pek. Galian Tanah Berbatua Volume Pekerjaan = 29.79 M3

b Banyak Kelompok Kerja = 1.00 Groupc Kemampuan Perkelompok perhari = 6.00 M3d Jam Kerja = 8.00 Jame Tenaga Yang dibutuhkan Perhari

Pekerja = 4.00 OrangMandor = 1.00 Orang

f Bahan Yang Dibutuhkan Tidak adag Alat Yang dibutuhkan

Cangkul = 8.00 BuahKeranjang = 10.00 BuahLinggis = 4.00 Buah

29.79h Waktu Pelaksanaan = 6.00

= 4.97

Dibulatkan = 5.00 Hari

2 Pek. Pasangan Batu Kali Camp 1 : 4a Volume Pekerjaan = 63.28 M3b Banyak Kelompok Kerja = 1.00 Groupc Kemampuan Perkelompok perhari = 2.00 M3d Jam Kerja = 8.00 Jame Tenaga Yang dibutuhkan Perhari

Pekerja = 4.00 Orang

Tukang = 2.00 OrangKepala Tukang = 1.00 OrangMandor = 1.00 Orang

f Bahan Yang DibutuhkanSemen = 202.50 ZakBatu Kali = 75.94 M3Pasir = 31.64 M3

g Alat Yang dibutuhkanCangkul = 8.00 BuahGerobak = 5.00 BuahSeperangkat Alat Tukang = 4.00 set

Skop = 8.00 Buah

63.28

h Waktu Pelaksanaan = 2.00= 31.64

Dibulatkan = 32.00 Hari

3 Pek. Plesteran Camp 1 : 3a Volume Pekerjaan = 104.20 M2b Banyak Kelompok Kerja = 1.00 Groupc Kemampuan Perkelompok perhari = 10.00 M2d Jam Kerja = 8.00 Jame Tenaga Yang dibutuhkan Perhari

Pekerja = 4.00 OrangTukang = 2.00 OrangKepala Tukang = 1.00 Orang

Mandor = 1.00 Orangf Bahan Yang Dibutuhkan

Semen = 16.67 Zak

Pasir = 1.98 M3g Alat Yang dibutuhkan

Cangkul = 8.00 BuahEmber = 10.00 Buah

104.20h Waktu Pelaksanaan = 10.00

= 10.42

Dibulatkan = 11.00 Hari

4 Pek.Timbunan Tanah dari Tanah Bekas Galiana Volume Pekerjaan = 27.68 M3

b Banyak Kelompok Kerja = 1.00 Groupc Kemampuan Perkelompok perhari = 15.00 M3d Jam Kerja = 8.00 Jam

e Tenaga Yang dibutuhkan PerhariPekerja = 6.00 OrangMandor = 1.00 Orang

f Bahan Yang DibutuhkanTanah Bekas Galian = 27.68 M3

=g Alat Yang dibutuhkan

Cangkul = 2.00 Buah

Keranjang = 6.00 BuahGerobak = 1.00 Buah

27.68h Waktu Pelaksanaan = 15.00

= 1.85Dibulatkan = 2.00 Hari

II PEKERJAAN SALURAN PASANGAN

1 Pek. Galian Biasaa Volume Pekerjaan = 34.50 M3b Banyak Kelompok Kerja = 1.00 Groupc Kemampuan Perkelompok perhari = 8.00 M3d Jam Kerja = 8.00 Jame Tenaga Yang dibutuhkan Perhari

Pekerja = 4.00 OrangMandor = 1.00 Orang

f Bahan Yang Dibutuhkan Tidak ada

g Alat Yang dibutuhkanCangkul = 8.00 BuahKeranjang = 10.00 BuahLinggis = 4.00 Buah

34.50h Waktu Pelaksanaan = 8.00

= 4.31

Dibulatkan = 5.00 Hari

2 Pek. Pasangan Batu Kali Camp 1 : 4a Volume Pekerjaan = 59.70 M3b Banyak Kelompok Kerja = 1.00 Group

c Kemampuan Perkelompok perhari = 2.00 M3d Jam Kerja = 8.00 Jame Tenaga Yang dibutuhkan Perhari

Pekerja = 4.00 OrangTukang = 2.00 OrangKepala Tukang = 1.00 OrangMandor = 1.00 Orang

f Bahan Yang DibutuhkanSemen = 191.04 ZakBatu Kali = 71.64 M3Pasir = 29.85 M3

g Alat Yang dibutuhkanCangkul = 8.00 BuahGerobak = 5.00 Buah

Seperangkat Alat Tukang = 4.00 setSkop = 8.00 Buah

59.70h Waktu Pelaksanaan = 2.00

= 29.85

Dibulatkan = 30.00 Hari

3 Pek. Plesteran Camp 1 : 3a Volume Pekerjaan = 149.35 M2b Banyak Kelompok Kerja = 1.00 Groupc Kemampuan Perkelompok perhari = 10.00 M2d Jam Kerja = 8.00 Jam

e Tenaga Yang dibutuhkan PerhariPekerja = 4.00 OrangTukang = 2.00 Orang

Kepala Tukang = 1.00 OrangMandor = 1.00 Orang

f Bahan Yang DibutuhkanSemen = 23.90 ZakPasir = 2.84 M3

g Alat Yang dibutuhkanCangkul = 8.00 Buah

Ember = 10.00 Buah

149.35h Waktu Pelaksanaan = 10.00

= 14.93

Dibulatkan = 15.00 Hari

4 Pek.Timbunan Tanah dari Tanah Bekas Galiana Volume Pekerjaan = 19.60 M3b Banyak Kelompok Kerja = 1.00 Groupc Kemampuan Perkelompok perhari = 15.00 M3d Jam Kerja = 8.00 Jame Tenaga Yang dibutuhkan Perhari

Pekerja = 6.00 OrangMandor = 1.00 Orang

f Bahan Yang Dibutuhkan

Tanah Bekas Galian = 19.60 M3=

g Alat Yang dibutuhkan

Cangkul = 2.00 BuahKeranjang = 6.00 BuahGerobak = 1.00 Buah

19.60h Waktu Pelaksanaan = 15.00

= 1.31Dibulatkan = 2.00 Hari

Painan, 19 Oktober 2009Kontraktor Pelaksana:

CV. RAISYAH KARYA

HASAN SYURYA DINATA, A.MdDirektur

JADWAL PELAKSANAAN PEKERJAAN (TIME SCHEDULE)

KEGIATAN : REHABILITASI / PEMELIHARAAN JARINGAN IRIGASI PEKERJAAN : REHABILITASI IRIGASI BANDA GADANG PANCUNG TEBALLOKASI : KEC. BAYANG UTARA KAB. PESISIR SELATANTHN ANGGARAN : 2009

No. URAIAN PEKERJAAN STN VOLUMEBOBOT

JADWAL PELAKSANAANKETMINGGUAN

(%) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18100%

I PEKERJAAN PENDAHULUAN1 Uitzetten, Pembuatan Matual Check, Actual

Check, Gambar Asbuil Drawing, Foto Dokumen Ls 1.00 2.97 0.99 0.99 0.99

II PEKERJAAN PELIMPAH DAN PENGURAS1 Pek. Kisdam dan Pengeringan Ls 1.00 4.96 4.962 Pek. Galian Tanah Berbatu M3 29.79 0.99 0.993 Pek. Pasangan Batu Kali Camp 1 : 4 M3 63.28 40.03 8.01 8.01 8.01 8.01 8.014 Pek. Plesteran Camp 1 : 3 M3 104.20 4.34 2.17 2.17 50%5 Pek.Timbunan Tanah dari Tanah Bekas Galian M2 27.68 0.92 0.92

III PEKERJAAN SALURAN PASANGAN1 Pek. Galian Biasa M3 34.50 1.14 1.142 Pek. Pasangan Batu Kali Camp 1 : 4 M3 59.70 37.77 7.55 7.55 7.55 7.55 7.553 Pek. Plesteran Camp 1 : 3 M2 149.35 6.22 3.11 3.114 Pek.Timbunan Tanah dari Tanah Bekas Galian M3 19.60 0.65 0.65 0

JUMLAH 100.00JUMLAH 5.95 0.99 8.01 8.01 8.01 8.01 8.01 2.17 2.17 3.06 7.55 7.55 7.55 7.55 7.55 3.11 3.76 0.99KOMULATIF 5.95 6.94 14.94 22.95 30.96 38.96 46.97 49.14 51.31 54.37 61.92 69.47 77.03 84.58 92.13 95.24 99.01 100.0

Masa Pelaksanaan 120 (Seratus Dua Puluh) Hari KalenderMinggu ke 18 = 1 (satu) Hari Kalender

Painan, 19 Oktober 2009 Mengetahui : Kontraktor Pelaksana:

KUASA PENGGUNA ANGGARAN CV. RAISYAH KARYA

DEVITRA, S.ST HASAN SYURYA DINATA, A.Md NIP : 410 012 994 Direktur

Rp 3,149,328.75 0.031291 100 ###

Rp 1,046,373.75 0.010 100 ###

Rp 42,390,259.52 0.421 100 ###

Rp 4,599,064.98 0.046 100 ### Rp 975,121.42 0.010 100 ###

0.000 100 ###0.000 100 ###

0.000 100 ###0.000 100 ###

Rp 1,211,812.50 0.012 100 ### Rp 39,992,074.80 0.397 100 ### Rp 6,591,846.02 0.065 100 ### Rp 690,476.15 0.007 100 ###

0.000 100 ###0 100 ###

Rp 100,646,357.89

JADWAL PEDATANGAN MATERIAL

KEGIATAN : REHABILITASI / PEMELIHARAAN JARINGAN IRIGASI PEKERJAAN : REHABILITASI IRIGASI BANDA GADANG PANCUNG TEBALLOKASI : KEC. BAYANG UTARA KAB. PESISIR SELATANTHN ANGGARAN : 2009

No. URAIAN PEKERJAAN STNJADWAL PELAKSANAAN

KETMINGGUAN1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

1 SEMEN

2 BATU

3 PASIR

JUMLAH

Painan, 19 Oktober 2009Kontraktor Pelaksana:CV. RAISYAH KARYA

HASAN SYURYA DINATA, A.MdDirektur

JADWAL PENDATANGAN PERSONIL (TENAGA KERJA)

KEGIATAN : REHABILITASI / PEMELIHARAAN JARINGAN IRIGASI PEKERJAAN : REHABILITASI IRIGASI BANDA GADANG PANCUNG TEBALLOKASI : KEC. BAYANG UTARA KAB. PESISIR SELATANTHN ANGGARAN : 2009

No. URAIAN PEKERJAAN STN

JADWAL PELAKSANAAN

KETMINGGUAN1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

1 PEKERJA

2 TUKANG

3 KEPALA TUKANG

4 MANDOR

JUMLAH

Painan, 19 Oktober 2009Kontraktor Pelaksana:CV. RAISYAH KARYA

HASAN SYURYA DINATA, A.MdDirektur

JADWAL PENDATANGAN ALAT (PERALATAN)

KEGIATAN : REHABILITASI / PEMELIHARAAN JARINGAN IRIGASI PEKERJAAN : REHABILITASI IRIGASI BANDA GADANG PANCUNG TEBALLOKASI : KEC. BAYANG UTARA KAB. PESISIR SELATANTHN ANGGARAN : 2009

No. URAIAN PEKERJAAN STN

JADWAL PELAKSANAAN

KETMINGGUAN1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

1 PERALATAN TUKANG

2 CANGKUL

3 GEROBAK

4 LINGGIS

JUMLAH

Painan, 19 Oktober 2009Kontraktor Pelaksana:CV. RAISYAH KARYA

HASAN SYURYA DINATA, A.MdDirektur