Date: June 6, 2018
To: Project File
From: S. Dixon
Re: Construction Package Cost Estimate
Proton Improvement Plan II (PIP-II)
PIP-II-doc-581
This memo documents the results of the construction schedule duration estimate for the conventional
facilities portion of the PIP-II project.
Background
In April 2015, the construction durations for the conventional facilities portion of the PIP-II project was
estimated based on a parametric scaling of known work scope at the time. This scaling was accomplished
with minimal technical input at the time and was instead based on design assumptions and expected
durations from preliminary designs for PIP-II precursor machines (Project X, Proton Driver).
As part of preparation for Critical Decision 1 (CD-1) a better defined conceptual design for the
conventional facilities was developed based on detailed discussions with the stakeholders. This design
and the accompanying text and estimate basis assumptions was used by an architect/engineer consultant
team to develop an expected construction cost and schedule estimate. This cost/schedule estimate was
completed in May 2017.
In May 2018, the project team revisited the construction packages and revised the anticipated work to
include a Linac Complex that combined the previous High Bay Building, Linac Tunnel, Linac Gallery and
Beam Transfer Line.
Process
The architect/engineer (A/E) for the PIP-II conventional facilities was tasked with developing a
construction cost estimate based on the drawings and text developed as part of the CD-1 process. This
construction duration estimate was broken down by the anticipated WBS construction package and
submitted in May 2017.
In May 2018, the A/E developed a construction duration for a combined Linac Complex.
Steven Dixon Conventional Facilities PIP-II Division P.O. Box 500, MS 312 Kirk Road and Pine Street Batavia, Illinois 60510-5011 USA Office: 630.840.8501 [email protected]
2
Schedule Estimate Summary
The table below provides a breakdown of the construction package duration estimates for the major
construction milestones as well as working days from Notice To Proceed:
Summary
This memo describes the process and results for developing the construction duration estimates for the
PIP-II conventional facilities. These estimates are considered planning packages and will be revised and
updated in subsequent design phases.
Update History
May 2018 with revised WBS
Encl: Gensler tasking information
May 2017 construction schedule estimate May 2018 updated linac complex schedule estimate
Cc: L. Merminga, PIP-II
M. Kaducak, PIP-II L. Lari, PIP-II PIP-II-doc-581
121.06.02 Site Preparation 1-Jun-17 0 31-Jul-17 43 30-Nov-18 392 3-Dec-18 393121.06.03 Cryo Plant Building 1-Jun-17 0 31-Jul-17 43 24-Aug-18 322 19-Nov-18 383121.06.04 Utility Plant Building 1-Jun-17 0 30-Jun-17 22 21-Mar-18 210 14-Jun-18 271121.06.05 Linac Complex 1-Jun-17 0 31-Jul-17 43 12-Mar-19 464 2-Jul-19 544121.06.06 Booster Connection 1-Jun-17 0 30-Jun-17 22 7-Aug-18 309 31-Oct-18 370
Based on 19MAY17 Schedule Information
Based on 04MAY18 Schedule Information
DateWork Days from NTP
Notice To Proceed Start Construction Benefical Occupancy Project Complete
DateWork Days from NTP Date
Work Days from NTP Date
Work Days from NTP
1
Date: February 20, 2017
To: J. King, FI/Procurement
From: S. Dixon, PIP-II
Re: Request for Professional A/E Services
Cost Estimate/Schedule Preparation (WBS 121.6.1.1.4.4)
Proton Improvement Plan II (PIP-II)
Please request a Not-To-Exceed proposal for professional A/E services from Gensler for professional architectural/engineering services to provide Cost Estimating and Schedule development services for the Proton Improvement Plan – II (PIP-II) project. Background/Description Fermilab has developed a conceptual design for the Proton Improvement Plan-II (PIP-II) which is a high-intensity proton facility to support a world-leading neutrino program over the next two decades at Fermilab. PIP-II is an integral part of the U.S. Intensity Frontier Roadmap as described in the Particle Physics Project Prioritization Panel (P5) report of May 2014, with a short term goal focused on upgrades to the Fermilab accelerator complex capable of providing a beam power in excess of 1 MW on target at the initiation of LBNF operations. In a broader sense, PIP-II is a part of a longer-term concept for a sustained campaign of upgrades and improvements to achieve multi-MW capabilities at Fermilab. Fermilab has developed conceptual design drawings and text that describe, in general terms, the site arrangement, building layouts, material choices and design assumptions of the conventional facilities needed to support construction, installation and operation of the physics apparatus for PIP-II. The next step in the project lifecycle is to develop a preliminary cost estimate and schedule for the conceptual design. Scope This tasking will develop preliminary cost estimates and preliminary construction schedules for the conventional facilities for PIP-II. In general, the construction cost estimate should be prepared in accordance with DOE’s Cost Estimating
Guide (G413.3-21) and GAO Cost Estimating and Assessment Guide (GOA-09-3SP) as well as current industry best practices. For the purposes of this tasking the preliminary cost estimate should assume a 10%-40% project definition based on the conceptual design documentation and therefore a Class 3 estimate classification as defined by DOE G 413.3-21. Variations should be documented in the final report.
Steve Dixon APM for Civil Construction AD/PIP-II P.O. Box 500, MS 312 Kirk Road and Pine Street Batavia, Illinois 60510-5011 USA Office: 630.840.8501 [email protected]
2
The preliminary cost estimates and preliminary construction schedule will be broken down by functional area as listed below: 121.06.02: Site Preparation 121.06.03: Linac 121.06.03.01: Linac Enclosure (below grade) 121.06.03.02: Linac Service Building (above grade) 121.06.04: Transport Line Enclosure 121.06.04.01: South Transport Line Enclosure 121.06.04.02: Booster Connection 121.06.05: Cryogenics Plant 121.06.06: Mechanical Plant
While the funding profile for the PIP-II conventional facilities is subject to change, the cost estimate for all construction packages should be completed in 2017 dollars. Once a funding profile is better defined, an appropriate construction escalation will be applied. The preliminary construction schedule will provide a reasonable basis for the expected construction durations of the PIP-II conventional facilities construction packages. It is recognized that at this point in the project life cycle, the details of the construction activities and schedule contain uncertainties. The preliminary construction schedule should instead focus on the completion of major milestones (eg: excavation complete, foundation complete, building shell complete, beneficial occupancy, etc.) within the overall schedule to provide a reasonable prediction of one possible construction scenario. This schedule information will be included in the PIP-II resource loaded schedule as a planning package that will be updated with further information and details as they become available. Escalation for conventional facilities is a critical part of the planning process. This task will include the development of a recommended escalation rate for conventional facilities for the next five (5) years. Since escalation prediction, is by nature, based on economic conditions, this recommendation will be revisited and updated in future years. PIP-II has developed a preliminary set risks and opportunities related to conventional facilities. This task will include a review of the current risk register and provide comments on the existing items and well as identification of additional risks and opportunities to be pursued in subsequent project phases. Fermilab Provided Services/Information Fermilab will provide the following services: 1. Conceptual design report; 2. Conceptual drawings;
3
3. Estimate assumption documents; 4. Recent purchase orders for similar equipment including overhead bridge cranes, major electrical
equipment, precast concrete shield blocks and Johnson Control Metasys equipment; 5. Risk register for conventional facilities; 6. Examples of previously completed projects;
Deliverables At a minimum, the deliverables will consist of the following:
Preliminary cost estimate by functional area; Preliminary construction schedule by functional area; Recommended escalation rate by year; Suggested opportunities/risks for conventional construction;
Schedule Start: March 2017 Complete: Start + 2 Months Requirements The requirements included in the Master Ordering Agreement will apply to this task order including the following: 2.1.6 – Reporting Requirements In lieu of the Reporting Requirements in the Master Ordering Agreement, for this task order, the tailored reporting requirements will include the following for each subtask:
Prior to the start of the task, provide a projection of expenditures by month; A monthly report submitted with the invoice will include 1) a description of out of scope work (if
any) and anticipated cost/schedule impact, 2) an analysis if the remaining work scope can be completed within the remaining budget/schedule.
2.3 – Quality Requirements Gensler should include with the proposal a statement that the Quality Requirements for this task will comply with the Corporate Quality Control Plan submitted as part of the Master Ordering Agreement or alternatively, submit a specific Quality Control Plan. Please forward this information to Gensler and ask that they contact me with any questions. Please request that they return their proposal by March 17, 2017. Please contact me at x8501 with questions. Cc: S. Holmes, PIP-II P. Derwent, PIP-II T. Powers, FI/Procurement J. Hunt, FESS/E
170307
March 7, 2017 Jerry King Sr. Procurement Advisor Fermi National Accelerator Laboratory Procurement/Finance Section P.O. Box 500, MS 210 Kirk Road & Pine Street Batavia, IL 60510-5011 USA Subject: Agreement for Architectural Services
For Fermi National Accelerator Laboratory Cost Estimate/Schedule Preparation (WBS 121.6.1.1.4.4), Proton Improvement Plan-II (PIP-II)
Dear Jerry: This Agreement is between Fermi National Accelerator Laboratory (“Client”) and Gensler Architecture, Design & Planning, P.C. (“Gensler”), located at 11 E Madison St., Chicago, Illinois for architectural, engineering, and construction management services. A. PROJECT
A.1 Project Description. The project includes developing preliminary cost estimates and preliminary cosrtuction schedules for the conventional facilities for the PIP-II (the “Project”). A.2 Project Budget. Client and Gensler with its consultant team will review Client’s budget goals for the Project at the commencement of the work. The Project Budget shall include appropriate amounts for design and construction contingencies, consistent with the nature of the Project. A.3 Project Schedule. The following milestones are presently projected: a) Project Kick-Off/Commencement of Basic Services: March 17, 2017 b) 50% Budget/Schedule In-Progress Review: April 21, 2017 c) 95% Budget/Schedule Submit for Review: May 19, 2017 d) Final Budget/Schedule Package: June 12, 2017
Agreement for Architectural Services March 7, 2017 Page 2
170307
B. SCOPE OF SERVICES PROVIDED BY GENSLER
Prior to commencement of Services, Client and Gensler will each provide the names of their key Project team members, including the primary contact person and the person authorized to make decisions. B.1 Gensler’s Basic Services Gensler’s Basic Services include services for the review of the conceptual design drawings and text that describe, in general terms, the site arrangement, buildings layouts, material choices and design assumptions of the conventional facilities needed to support construction, installation and operation of the physics apparatus for PIP-II as provided by the Client and develop preliminary cost estimate and schedule for the Project. Gensler will engage sub-consultants to provide design review, cost estimating, and construction scheduling services for the conventional facilities for PIP-II. The preliminary cost estimate will assume a 10%-40% project definition based on conceptual design documentation and Class 3 estimate classification as defined by DOE G 413.3-21 with variations documented in the final report. B.1.1 Cost Estimate and Schedule Breakdown: The preliminary cost estimates and preliminary construction schedule will be broken down by functional area listed below:
121.06.02: Site Preparation; 121.06.03: Linac;
121.06.03.01: Linac Enclosure (below grade) 121.06.03.02: Linac Enclosure (above grade)
121.06.04: Transport Line Enclosure; 121.06.04.01: South Transport Line Enclosure
121.06.04.02: Booster Connection 121.06.05: Cryogenics Plant; 121.06.06: Mechanical Plant;
Throughout the project, Gensler will attend one kick-off meeting and one in-progress review meeting with Client to review project design and estimate/schedule status. B.2 Optional/Additional Services. Gensler will provide services beyond Basic Services described in Section B.1 (“Additional Services”) if requested by Client and confirmed in writing by Gensler. Additional Services include, but are not limited to: additional design studies beyond those provided in the conceptual design package; models or renderings; Client-requested revisions that are inconsistent with prior approvals or instructions; out of sequence services or preparing documentation; increase in duration of services; demobilization and remobilization of Project team due to Project suspension or delay for reasons beyond Gensler’s control.
Agreement for Architectural Services March 7, 2017 Page 3
170307
C. COMPENSATION Compensation to Gensler for Basic Services, Additional Services, and Reimbursable Expenses shall be as described below. When Gensler’s compensation is based on hourly rates, the rates shall be those set forth in existing on-call agreements between the Client and Gensler as well as agreements between Gensler’s Consultants and the Client. D.1 Basic Services. Compensation for Basic Services shall be the lump sum of one-hundred five thousand, four-hundred, thirty-seven and 80/100 dollars ($105,437.80) for labor and an estimated two thousand dollars ($2,000) for reimbursable expenses. This fee is broken down by discipline and consultant as follows:
Fee Breakdown
1 Gensler (PM and Architecture) Estimated Hours
Rate/Hour Estimated Cost ($)
Project Principal/Director $ 260.00 $ -
Project Manager 32 $ 200.00 $ 6,400.00
Senior Architect $ 175.00 $ -
Project Architect 20 $ 160.00 $ 3,200.00
Architect $ 145.00 $ -
Technician (draftsperson) $ 95.00 $ -
TOTAL ARCH/PM HOURS 52
TOTAL ARCH/PM LABOR $ 9,600.00
2 Turner (Construction Manager) Estimated Hours
Rate/Hour
Estimated Cost ($)
Principal-In-Charge1 0 $ 260.39 $ -
Senior Project Manager 60 $ 178.44 $ 10,706.40
Chief Estimator 100 $ 171.90 $ 17,190.00
Lead Estimator 60 $ 104.26 $ 6,255.60
Senior Estimator (Sitework) 0 $ 170.69 $ -
Senior Estimator (Structural) 80 $ 167.77 $ 13,421.60
Estimator (Architectural) 60 $ 113.11 $ 6,786.60
Senior Estimator (Mechanical) 80 $ 156.71 $ 12,536.80
Senior Estimator (Electrical) 80 $ 153.15 $ 12,252.00
Scheduler 40 $ 144.32 $ 5,772.80
Senior Estimator $ 161.54 $ -
Senior Estimator $ 167.98 $ -
TOTAL CM HOURS 560
TOTAL CM LABOR $ 84,921.80
1 Exclusion of Principal's Hours is for this task order only.
2 Rates include Turner Federal Multiplier & Payroll Taxes
3 Exclusion of Fee in the Rates is for this task order only
Agreement for Architectural Services March 7, 2017 Page 4
170307
4 Fees based on One Schedule & Estimate deliverable reviewed at 95% complete
5 Schedule limited to construction phase activities for the seven WBS codes: Site Prep; Cryo Plant Building; Utility Plant Building; Linac Tunnel; Linac Gallery; Beam Transfer Line; Booster Connection
6 All deliverables will be provided digitally.
3 KJWW (MEP) (rates per Fermi on-call agreement)
Estimated Hours
Rate/Hour
Estimated Cost ($)
Senior Mechanical Engineer 8 $ 186.00 $ 1,488.00
Senior Electrical Engineer 8 $ 186.00 $ 1,488.00
Revit Staff $ 85.00 $ -
Engineering Assistant $ 69.00 $ -
$ -
TOTAL MEP ENG. HOURS 16
TOTAL MEP ENG. LABOR $ 2,976.00
4 TGRWA (Structural) Estimated Hours
Rate/Hour
Estimated Cost ($)
Principal 4 $ 225.00 $ 900.00
Associate Principal 16 $ 190.00 $ 3,040.00
Project Engineer $ 145.00 $ -
$ -
$ -
TOTAL STRUCTURAL ENG. HOURS 20
TOTAL STRUCTURAL ENG. LABOR $ 3,940.00
5 CMT (Civil) Estimated Hours
Rate/Hour
Estimated Cost ($)
PRINCIPAL 0 $ 206.00 $ -
SENIOR PROJECT ENGINEER/MANAGER 20 $ 200.00 $ 4,000.00
SENIOR ENGINEER/ARCHITECT 0 $ 138.00 $ -
TOTAL CIVIL ENG. HOURS 20
TOTAL CIVIL ENG. LABOR $ 4,000.00
6 Project Totals
TOTAL HOURS 668
TOTAL LABOR $ 105,437.80
7 Estimate Reimbursables
TOTAL Estimated Reimbursable Expenses $ 2,000.00
Agreement for Architectural Services March 7, 2017 Page 5
170307
D.2 Additional Services. Compensation for Additional Services (if not agreed upon as a lump sum amount) shall be based on Gensler’s Standard Hourly Billing Rates. D.3 Reimbursable Expenses. Reimbursable Expenses are in addition to compensation for Basic and Additional Services and include expenses incurred by Architect and Architect’s consultants in the interest of the Project, including, but not limited to the following:
a. Reproduction, shipping, handling, and delivery. b. Mileage, tolls, cab fares, and parking. c. Renderings, models, mock-ups, and photography. d. Sales taxes and other transactional taxes, and fees paid for securing approval of authorities
having jurisdiction over the Project. e. Authorized out-of-town travel, including travel time and out-of-town living expenses. f. Additional insurance coverage or limits requested by Client in excess of that normally provided
by Architect and Architect’s consultants. Compensation for Reimbursable Expenses incurred by Gensler in connection with the Project, including without limitation, reproduction costs for providing copies of the deliverables described in Section B.1 of this Letter of Agreement, shall be based on amounts invoiced to Gensler with no mark-up. D.4 Consultants. Consultants’ fees shall be compensated based on amounts invoiced to Gensler with no mark-up. D.5 Progress Payments. Progress payments shall be made monthly. Where Gensler’s fee is based on a lump sum, progress payments for Basic Services shall be based on the percentage of services provided during the previous month. E. AGREEMENT AND ACCEPTANCE
E.1 Agreement. This Agreement is comprised of and incorporates the following documents, in order of precedence:
a) Amendments and modifications signed by both parties; b) This Letter of Agreement; c) The attached Standard Terms and Conditions (STC July 2016); d) Exhibits referenced in this Letter of Agreement.
Where a portion of one document is amended by another of higher precedence, all unmodified portions shall remain in effect. The terms and conditions of this Agreement, the STC and any Work Authorization hereunder, are integral parts of this Agreement and are fully incorporated herein by this reference. No conflicting or supplemental pre-printed provisions on Client forms (including without limitation terms on purchase orders) shall be binding on the parties.
Agreement for Architectural Services March 7, 2017 Page 6
170307
E.2 Effective Date. The effective date of this Agreement is March 17, 2017. By Gensler By Client Grant C. Uhlir (Printed Name of Signatory) By By (Signature) (Signature) Principal, (Title) (Date) (Title) (Date) cc: Bernie Woytek Bob Clough Ryan Mayhugh
Gensler - STC 160711 Page 1 of 3
STANDARD TERMS AND CONDITIONS OF THE
AGREEMENT BETWEEN CLIENT AND GENSLER FOR
ARCHITECTURAL / INTERIORS SERVICES (“STC”)
Article 1 - Definitions and General Provisions 1.1 Parties. The terms “Client” and “Gensler” include each party’s authorized representatives, officers, directors, shareholders, and employees. 1.2 Days or Time. Time periods refer to calendar days, unless otherwise stated. 1.3 Work. The term “Work” means the construction, by Contractor or others engaged by Client, of the Project elements designed or specified by Gensler, including all labor, materials, equipment and services. 1.4 Project Budget. The “Project Budget” includes the Client’s budget for performing the Work, as well as furniture, furnishings, equipment and all other goods and services to be furnished by Client, Contractor, and any of their subcontractors or consultants, including allowances for design and construction contingencies. Article 2 – Gensler’s Services 2.1 Gensler’s services shall be performed as expeditiously as is consistent with the orderly progress of the Work and with the professional skill and care ordinarily provided by architects practicing in the same locality under similar circumstances (“Standard of Care”). 2.2 Limitation of Construction Responsibilities. Gensler shall not have control over, or charge of, and shall not be responsible for, construction means, methods, schedules, or delays, or for safety precautions and programs in connection with the Work. Article 3 – Client’s Responsibilities 3.1 Information. Client shall provide full information regarding the requirements for the Project. 3.2 Legal and Financial Information. Client shall furnish Gensler with: a legal description of the property; the name/address of the property owner; and the name/address of any construction lender(s). 3.3 Surveys. Client shall furnish surveys in electronic format fully describing physical characteristics, legal limitations, and utility locations for the Project site. 3.4 Existing or Base Building Information. To the extent applicable to the Project, Client shall provide information, drawings, specifications, and other documents that describe the existing utility services, site conditions, build-out and base building construction, and any systems with which the Project is to be coordinated. 3.5 Client’s Consultants. When requested by Gensler, or required by authorities having jurisdiction over the Project, Client shall furnish the services of geotechnical, civil, and environmental engineers and any other services required by the scope of the Project. 3.6 Tests. Client shall furnish structural, mechanical, chemical, air, and water pollution and hazardous materials tests, and other laboratory and environmental tests, inspections, and reports required by law or by authorities having jurisdiction over the Project, or reasonably requested by Gensler. 3.7 Legal, Accounting, and Insurance Services. Client shall furnish all legal, accounting, and insurance counseling services as may be necessary for the Project.
3.8 Client’s Services and Information. Gensler shall be entitled to rely upon the accuracy and completeness of the services, information, surveys, and reports provided by Client, Contractor, or any of their subcontractors or consultants. Gensler’s coordination of its services with Client’s and Contractor’s subcontractors or consultants shall be limited to that necessary for consistency of Gensler’s documents with those of such subcontractors or consultants. Article 4 - Construction Cost 4.1 Construction Cost. The Construction Cost shall be the total cost or estimated cost to Client for performing the Work. 4.2 Estimates. Gensler cannot and does not warrant or represent that bids or negotiated prices will not vary from Client’s Project Budget or from any cost estimate or evaluation prepared or reviewed by Gensler. 4.3 Fixed Limit. No fixed limit of Construction Cost shall be established as a condition of this Agreement by the furnishing, proposal, or establishment of a Project Budget. Article 5 - Use of Gensler’s Documents and Data 5.1 The Drawings, Specifications, and other documents (collectively “Documents”) and any computer tapes, disks, models, CAD files, or other electronic data (collectively “Digital Media”) prepared by Gensler are instruments of service and shall remain Gensler’s property. Gensler grants Client a nonexclusive license to use the Documents and Digital Media in connection with the Project, provided that Client substantially performs its contract obligations, including prompt payment of all sums when due. 5.2 Upon completion of Gensler’s services and payment of all amounts due Gensler, Client may retain copies or reproducibles of the Documents and/or Digital Media for information and reference in connection with Client’s use and occupancy of the completed Project. 5.3 Client agrees to indemnify and hold Gensler harmless from and against any and all claims, liabilities, suits, demands, losses, damages, costs, and expenses (including reasonable attorneys’ fees and costs of defense), together with interest thereon, accruing or resulting to any persons, firms, or other legal entities, on account of any damages or losses to property or persons, including death or economic loss, arising out of the unauthorized use, re-use, transfer or modification of the Documents and/or Digital Media. 5.4 Aggregate Data. Gensler may gather statistical data, analytics, trends and other aggregated or otherwise de-identified data derived from Gensler’s services to Client, including, but not limited to, data related to Gensler’s Workplace Performance Index® (“WPI”), further detailed in the Letter of Agreement (“Aggregate Data”). Aggregate Data, as well as any resulting research, know-how, processes, algorithms or other methodology related to the Aggregate Data, shall remain Gensler’s property. Client hereby acknowledges and consents to Aggregate Data being stored and processed by Gensler for general research purposes, such as Gensler’s ongoing exploration of how employees work and how workspaces and space usage continue to evolve. 5.5 Confidentiality. All information disclosed by Gensler relating to Gensler’s Aggregate Data and WPI, including, but not limited to, benchmarking research, marketing data, surveys, reports, analysis and other data in any medium shall be considered Gensler’s “Proprietary Information.” Client will, at all times and notwithstanding any termination or expiration of this Agreement, hold the Proprietary Information in strict
Gensler - STC 160711 Page 2 of 3
confidence and will take reasonable precautions to safeguard the Proprietary Information from unauthorized disclosure. Article 6 - Claims and Disputes 6.1 Mediation. Claims, disputes, or other matters in question between the parties shall be subject to mediation under the auspices of a recognized professional mediation service prior to undertaking any legal action. The cost of the mediation service shall be borne equally by the parties. 6.2 Attorneys’ Fees. In any proceeding following unsuccessful mediation, the prevailing party shall be entitled, in addition to such other relief as may be granted, to a reasonable sum for attorneys’ fees and costs of defense. 6.3 Mutual Indemnification. Gensler agrees to indemnify and hold Client harmless from and against any and all liabilities, losses, damages, costs, and expenses (including reasonable attorneys’ fees and costs of defense), together with interest thereon, to the extent caused by the negligent acts, errors, or omissions of Gensler, its consultants, or anyone for whose acts either of them may be legally liable. Client agrees to indemnify and hold Gensler harmless from and against any and all liabilities, losses, damages, costs, and expenses (including reasonable attorneys’ fees and costs of defense), together with interest thereon, to the extent caused by the negligent acts, errors, or omissions of Client, its contractors or consultants, or anyone for whose acts any of them may be legally liable. 6.4 Mutual Limitation of Liability. The parties hereby agree that either party’s total liability to the other for any and all injuries, claims, losses, costs, expenses, or damages whatsoever arising out of or in any way related to the Project or this Agreement, from any cause or causes including, but not limited to, negligence and/or breach of contract, shall not exceed the total compensation received by Gensler under this Agreement. Article 7 - Termination 7.1 Termination by Either Party. This Agreement may be terminated by either party upon not less than seven (7) days written notice should the other party fail substantially to perform in accordance with the terms of this Agreement. 7.2 Failure to Make Payments. Client’s failure to make payments to Gensler in accordance with this Agreement shall constitute substantial nonperformance and cause for termination or suspension. 7.3 Termination for Convenience. Client may terminate this Agreement for its convenience upon not less than seven (7) days written notice to Gensler. 7.4 Compensation upon Termination. In the event of termination, Gensler shall be compensated for services performed prior to termination, together with Reimbursable Expenses then due, and Termination Expenses, which shall be defined as Gensler’s expenses directly attributable to termination. Article 8 - Payments to Gensler 8.1 Hourly Rates. Where services are to be compensated on an hourly basis, compensation shall be based on the hourly rates set forth in Gensler’s and Gensler’s consultants’ standard rate schedules. 8.2 Progress Payments. Progress payments for Basic and Additional Services and Reimbursable Expenses shall be due and payable upon receipt of Gensler’s invoices. Disputes or questions regarding an invoice or a portion of an invoice shall not be cause for withholding payment for the remaining portions due. Amounts unpaid thirty (30) days after the issue date of Gensler’s invoice shall be assessed a service charge of one and one-half percent (1-1/2%) per month. 8.3 Time Extensions. This Agreement anticipates that Gensler’s services will proceed continuously in accordance with the Project
schedule. If the Project is suspended or delayed for reasons beyond Gensler’s control, Gensler shall be compensated for expenses incurred due to the interruption and resumption of its services, and the Parties shall mutually agree upon an equitable adjustment of Gensler’s fees and the duration for the remaining services. 8.4 Change in Project Scope. If portions of the Project are deleted or otherwise not constructed, compensation for those portions of the Project shall be payable to the extent services are performed on those portions. Article 9 - Miscellaneous Provisions 9.1 Governing Law. This Agreement shall be governed by the law of the jurisdiction where the Project is located. 9.2 Property Insurance Waivers. Client shall cause Gensler and Gensler’s consultants to be named as Additional Insureds on Contractor’s General Liability Policy and any property insurance purchased for the period of construction of the Project. Such insurance shall be endorsed to provide a waiver of the insurers’ rights of subrogation against Gensler and Gensler’s consultants. 9.3 Mutual Waiver of Consequential Damages. The parties hereby waive, as against each other, any claims for incidental, special, exemplary or consequential damages. 9.4 Assignment and Third Parties. Neither party shall assign this Agreement, any right arising out of it, or the performance of obligations hereunder, without the written consent of the other. Nothing contained in this Agreement shall create a contractual relationship with, or a cause of action in favor of, any third party. 9.5 Royalties. Client acknowledges that Gensler designs products manufactured by others for which Gensler receives royalties based on sales volume. Prior to recommending any such product for use on a Project, Gensler will endeavor to notify Client that Gensler may receive royalties from the sale of the product. Client agrees that inadvertent failure to advise Client of any such product designed by Gensler, for which Gensler receives royalties, shall not be the basis of any claim in law. 9.6 Professional Credits. Gensler shall have the right to include representations of the design of the Project, including photographs, among Gensler’s professional materials, including, but not limited to, promotional materials, professional publications, and competition submissions. Client shall provide professional credit for the Gensler in Client’s promotional materials for the Project. 9.7 Latent Conditions. In the event that the Project includes any remodeling, alteration, or rehabilitation work, Client acknowledges that certain design and technical decisions shall be made on assumptions based on available documents and visual observations of existing conditions. 9.8 Areas and Measurements. Areas and measurements provided by Gensler are derived from drawing dimensions or field measurements and are not intended to be used as the basis for calculating rent or for other similar purposes. 9.9 Hazardous Materials. Client acknowledges that Gensler has no expertise in, and is not being retained for the purposes of, investigating, detecting, abating, replacing, remediating, or removing any items, products, or materials containing hazardous substances. 9.10 Design/Build by Contractor. Gensler and its consultants shall have no responsibility for the design, technical adequacy or accuracy, installation, or performance of any Design/Build portions of the Project. 9.11 Anti-Bribery and Anti-Corruption Commitment. Client and Gensler acknowledge their responsibilities and commitment to abide by and comply with both domestic and international anti-corruption laws, including but not limited to the United States Foreign Corrupt Practices Act and the United Kingdom Anti-Bribery Act, and any amendments and related regulations, in addition to their own ethical guidelines. Either
Gensler - STC 160711 Page 3 of 3
party may terminate this Agreement at any stage of the Project, if it has a good faith basis to believe that the other party failed to comply with the provisions of this Section 9.11, including any non-compliance prior to the effective date of this Agreement. The non-compliant party shall indemnify the other party from and against any and all liabilities, losses, damages, costs, and expenses (including reasonable attorneys’ fees and costs of defense), together with interest thereon, arising out of or resulting from such non-compliance. 9.12 Entire Agreement and Non-Waiver. This Agreement represents the entire and integrated agreement between Client and Gensler and supersedes all prior negotiations, representations, or agreements. No failure to act by either Party hereto shall be deemed to constitute a waiver of such Party’s rights or remedies hereunder.
Activity ID Activity Name Original
Duration
Start Finish TotalFloat
Fermilab Proton Improvement Plan - II 17.05.19Fermilab Proton Improvement Plan - II 17.05.19 440 01-Jun-17 27-Feb-19 0
Site PreparationSite Preparation 440 01-Jun-17 27-Feb-19 0
PreconstructionPreconstruction 70 01-Jun-17 11-Sep-17 330
Contract AdministrationContract Administration 40 01-Jun-17 31-Jul-17 0
SITE-CA-1000 Notice to Proceed - Site Preparation 0 01-Jun-17* 0
SITE-CA-1100 Bonds & Insurance, Initial Engineering, Safey Plans & Permits 40 02-Jun-17 28-Jul-17 0
SITE-CA-1200 Start Construction - Site Preparation 0 31-Jul-17 0
EngineeringEngineering 60 16-Jun-17 11-Sep-17 330
SITE-ENGR-1010 Construction Access Bridge Submittals & Fabrication 40 16-Jun-17 11-Aug-17 20
SITE-ENGR-1100 Box Culvert & E/WRS Submittals & Fabrication 50 16-Jun-17 25-Aug-17 220
SITE-ENGR-1200 Site Utilities Submittals, Coordination (BIM) & Fabrication 60 16-Jun-17 11-Sep-17 50
SITE-ENGR-1000 Field Office Trailers Submittals & Fabrication 60 16-Jun-17 11-Sep-17 330
ConstructionConstruction 300 31-Jul-17 03-Oct-18 100
MobilizationMobilization 255 31-Jul-17 31-Jul-18 145
SITE-MOB-0010 Mobilization 30 31-Jul-17 11-Sep-17 0
SITE-MOB-0100 Install Construction Access Bridge & Roadway 25 12-Sep-17 16-Oct-17 0
SITE-MOB-1000 Setup Field Office Complex & Construction Parking 40 12-Sep-17 06-Nov-17 330
SITE-MOB-1100 Install Fencing 5 17-Oct-17 23-Oct-17 0
SITE-MOB-1200 Install Site Erosion Controls 10 24-Oct-17 06-Nov-17 0
SITE-MOB-1300 Grub & Strip Topsoil at Roadways & Utilities 10 07-Nov-17 20-Nov-17 0
SITE-MOB-1400 Install Construction Overhead Electrical 15 11-Jul-18 31-Jul-18 65
Box CulvertsBox Culverts 80 28-Aug-17 20-Dec-17 300
SITE-BOX-1000 Install North E/WRS 15 28-Aug-17 18-Sep-17 220
SITE-BOX-1100 Install South E/WRS 15 19-Sep-17 09-Oct-17 220
SITE-BOX-1200 Construct North Box Culvert 20 19-Sep-17 16-Oct-17 345
SITE-BOX-1300 Construct South Box Culvert 20 10-Oct-17 06-Nov-17 220
SITE-BOX-1400 Regrade Existing Main Ring Ponds 30 07-Nov-17 20-Dec-17 220
UtilitiesUtilities 220 21-Nov-17 03-Oct-18 0
Site UtilitiesSite Utilities 220 21-Nov-17 03-Oct-18 0
SITE-UTL-1000 Start Site Utilities 0 21-Nov-17 0
SITE-UTL-1100 Install Storm Piping 40 21-Nov-17 19-Jan-18 180
SITE-UTL-1200 Install Sanitary Sewer Piping & Connection at Main Ring 160 21-Nov-17 10-Jul-18 60
SITE-UTL-1500 Install ICW Piping, Fire Hydrants & Connection at Main Ring 160 21-Nov-17 10-Jul-18 60
SITE-UTL-1400 Install Domestic Water Piping & Connection at Main Ring 160 21-Nov-17 10-Jul-18 60
SITE-UTL-1300 Install Natural Gas Piping & Connection at Main Ring 160 21-Nov-17 10-Jul-18 60
SITE-UTL-1600 Install Power & Communications Ductbank & Manholes 220 21-Nov-17 03-Oct-18 0
SITE-UTL-1700 Site Utilities Completed 0 03-Oct-18 0
Mechanical Site UtilitiesMechanical Site Utilities 160 21-Nov-17 10-Jul-18 40
SITE-MECH-1000 Start Mechanical Site Utilities 0 21-Nov-17 40
SITE-MECH-1100 Install PCWS/R 160 21-Nov-17 10-Jul-18 40
SITE-MECH-1300 Install LWS/R 160 21-Nov-17 10-Jul-18 40
SITE-MECH-1200 Install LCSW/R 160 21-Nov-17 10-Jul-18 40
SITE-MECH-1500 Install CHWS/R 160 21-Nov-17 10-Jul-18 40
SITE-MECH-1400 Install GCHWS/R 160 21-Nov-17 10-Jul-18 40
SITE-MECH-1600 Mechanical Site Utilities Completed 0 10-Jul-18 40
Grading & RoadsGrading & Roads 40 11-Jul-18 05-Sep-18 40
SITE-ROAD-1000 Cut to Subgrade at Roads, Swales & Temporary Haul Road 20 11-Jul-18 07-Aug-18 40
SITE-ROAD-1100 Install Stone Sub & Aggregate Courses at Roads & Temporary Haul Road 35 18-Jul-18 05-Sep-18 40
CloseoutCloseout 100 04-Oct-18 27-Feb-19 0
SITE-CLOSE-1100 Punchlist 20 04-Oct-18 31-Oct-18 20
SITE-CLOSE-0100 Final Coordination & Completion of Existing Utility Tie-Ins 40 04-Oct-18 30-Nov-18 0
SITE-CLOSE-1000 Beneficial Occupancy - Site Preparation 0 30-Nov-18 0
SITE-CLOSE-1010 Project Closeout 60 03-Dec-18 27-Feb-19 0
SITE-CLOSE-1020 Project Complete 0 27-Feb-19 0
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
2017 2018 2019
Fermilab Proton Improvement Plan - II 17.05.19
Site Preparation
Preconstruction
Contract Administration
Notice to Proceed - Site Preparation
Bonds & Insurance, Initial Engineering, Safey Plans & Permits
Start Construction - Site Preparation
Engineering
Construction Access Bridge Submittals & Fabrication
Box Culvert & E/WRS Submittals & Fabrication
Site Utilities Submittals, Coordination (BIM) & Fabrication
Field Office Trailers Submittals & Fabrication
Construction
Mobilization
Mobilization
Install Construction Access Bridge & Roadway
Setup Field Office Complex & Construction Parking
Install Fencing
Install Site Erosion Controls
Grub & Strip Topsoil at Roadways & Utilities
Install Construction Overhead Electrical
Box Culverts
Install North E/WRS
Install South E/WRS
Construct North Box Culvert
Construct South Box Culvert
Regrade Existing Main Ring Ponds
Utilities
Site Utilities
Start Site Utilities
Install Storm Piping
Install Sanitary Sewer Piping & Connection at Main Ring
Install ICW Piping, Fire Hydrants & Connection at Main Ring
Install Domestic Water Piping & Connection at Main Ring
Install Natural Gas Piping & Connection at Main Ring
Install Power & Communications Ductbank & Manholes
Site Utilities Completed
Mechanical Site Utilities
Start Mechanical Site Utilities
Install PCWS/R
Install LWS/R
Install LCSW/R
Install CHWS/R
Install GCHWS/R
Mechanical Site Utilities Completed
Grading & Roads
Cut to Subgrade at Roads, Swales & Temporary Haul Road
Install Stone Sub & Aggregate Courses at Roads & Temporary Haul Road
Closeout
Punchlist
Final Coordination & Completion of Existing Utility Tie-Ins
Beneficial Occupancy - Site Preparation
Project Closeout
Project Complete
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Fermilab SITE
Fermilab Proton Improvement Plan - II 17.05.19 - SITE PREPARATION
Page 1 of 1
Activity ID Activity Name Original
Duration
Start Finish TotalFloat
Fermilab Proton Improvement Plan - II 17.05.19Fermilab Proton Improvement Plan - II 17.05.19 373 01-Jun-17 19-Nov-18 67
Cryo Plant BuildingCryo Plant Building 373 01-Jun-17 19-Nov-18 67
PreconstructionPreconstruction 130 01-Jun-17 06-Dec-17 205
Contract AdministrationContract Administration 40 01-Jun-17 31-Jul-17 67
CRYO-CA-1000 Notice to Proceed - Cryo Plant Building 0 01-Jun-17* 0
CRYO-CA-1100 Bonds & Insurance, Initial Engineering, Safey Plans & Permits 40 02-Jun-17 28-Jul-17 67
CRYO-CA-1200 Start Construction - Cryo Plant Building 0 31-Jul-17 67
EngineeringEngineering 120 16-Jun-17 06-Dec-17 205
CRYO-ENGR-1000 Foundations & Concrete Submittals & Fabrication 40 16-Jun-17 11-Aug-17 97
CRYO-ENGR-1100 MEP Submittals & Coordination (BIM) 40 16-Jun-17 11-Aug-17 117
CRYO-ENGR-1500 OFCI 25-Ton & 15-Ton Crane Submittals & Fabrication 80 16-Jun-17 09-Oct-17 110
CRYO-ENGR-1400 Structural Steel Submittals & Fabrication 80 16-Jun-17 09-Oct-17 110
CRYO-ENGR-1200 Exterior Skin Submittals & Fabrication 90 16-Jun-17 23-Oct-17 170
CRYO-ENGR-1600 OFCI Transformer & Electrical Equipment Submittals & Fabrication 100 16-Jun-17 06-Nov-17 225
CRYO-ENGR-1300 Generator Submittals & Fabrication 100 16-Jun-17 06-Nov-17 225
CRYO-ENGR-1700 MEP Major Equipment Fabrication 80 14-Aug-17 06-Dec-17 180
ConstructionConstruction 253 31-Jul-17 27-Jul-18 147
MobilizationMobilization 20 31-Jul-17 25-Aug-17 67
CRYO-MOB-1000 Mobilization 20 31-Jul-17 25-Aug-17 67
Foundations & StructureFoundations & Structure 118 28-Aug-17 14-Feb-18 67
CRYO-F&S-1000 Grub, Strip & Prepare Building Pad 20 28-Aug-17 25-Sep-17 67
CRYO-F&S-1200 Piping Trench with Inserts 30 26-Sep-17 06-Nov-17 67
CRYO-F&S-1100 Grade Beams & Footings 45 26-Sep-17 29-Nov-17 67
CRYO-F&S-1300 Building Underground Utilities 20 24-Oct-17 20-Nov-17 67
CRYO-F&S-1400 Form, Rebar & Place SOG 10 21-Nov-17 06-Dec-17 67
CRYO-F&S-1500 SOG Sealer 3 07-Dec-17 11-Dec-17 67
CRYO-F&S-1600 Erect Structural Steel & Cranes, Decking & Detailing 45 12-Dec-17 14-Feb-18 67
Exterior SkinExterior Skin 50 04-Jan-18 14-Mar-18 122
CRYO-EXT-1000 Install Parapet, Roofing & Skylights 30 04-Jan-18 14-Feb-18 67
CRYO-EXT-1100 Install Metal Panels & Curtainwall 50 04-Jan-18 14-Mar-18 122
CRYO-EXT-1200 Install Overhead Door 10 18-Jan-18 31-Jan-18 122
InteriorInterior 130 25-Jan-18 27-Jul-18 147
CRYO-INT-1000 Paint Structural Steel 20 25-Jan-18 21-Feb-18 67
CRYO-INT-1100 MEP / FP Overhead Rough-In & Partitions 50 08-Feb-18 18-Apr-18 67
CRYO-INT-1200 Control Room, Tech Space & Toilet Rooms Buildout 50 22-Mar-18 31-May-18 187
CRYO-INT-1300 Form & Place Equipment Pads 10 19-Apr-18 02-May-18 77
CRYO-INT-1400 Paint MEP / FP Piping 30 19-Apr-18 31-May-18 67
CRYO-INT-1500 Set Equipment 10 03-May-18 16-May-18 77
CRYO-INT-1600 Install Lights, Power, Fire Alarm & Security 30 01-Jun-18 13-Jul-18 77
CRYO-INT-1700 MEP Rough-In & Hookups 40 01-Jun-18 27-Jul-18 67
Exterior Equipment & YardExterior Equipment & Yard 118 30-Nov-17 16-May-18 117
CRYO-EQ-1000 Install Pipe Supports Drilled Piers 5 30-Nov-17 06-Dec-17 130
CRYO-EQ-1100 Site Utilities 20 07-Dec-17 05-Jan-18 130
CRYO-EQ-1200 Form, Rebar & Place Transformer & Generator Pads 15 15-Feb-18 07-Mar-18 102
CRYO-EQ-1300 Set Transformers & Generator 5 08-Mar-18 14-Mar-18 142
CRYO-EQ-1400 Form, Rebar & Place Dewar Foundations & Pads 20 08-Mar-18 04-Apr-18 102
CRYO-EQ-1600 Generator Electrical Rough-In and Pull & Terminate Wire 20 15-Mar-18 11-Apr-18 142
CRYO-EQ-1500 Transformer Electrical Rough-In and Pull & Terminate Wire 20 15-Mar-18 11-Apr-18 142
CRYO-EQ-1700 Dewar Piping & Electrical Work 15 05-Apr-18 25-Apr-18 117
CRYO-EQ-1800 Prep & Construct Dewar Hardstand Area 15 26-Apr-18 16-May-18 117
SiteworkSitework 45 05-Apr-18 07-Jun-18 102
CRYO-SITE-1000 Cut Roadways to Subgrade 10 05-Apr-18 18-Apr-18 102
CRYO-SITE-1100 Install Stone Sub & Aggregate Base 10 19-Apr-18 02-May-18 102
CRYO-SITE-1200 Install Light Poles 10 03-May-18 16-May-18 102
CRYO-SITE-1300 Remove Erosion Controls & Landscaping 10 17-May-18 31-May-18 102
CRYO-SITE-1400 Asphalt Paving 5 01-Jun-18 07-Jun-18 102
CloseoutCloseout 80 30-Jul-18 19-Nov-18 67
CRYO-CLOSE-1100 Punchlist 20 30-Jul-18 24-Aug-18 67
CRYO-CLOSE-1000 Testing & Balancing 20 30-Jul-18 24-Aug-18 67
CRYO-CLOSE-1200 Beneficial Occupancy - Cryo Plant Building 0 24-Aug-18 67
CRYO-CLOSE-1300 Project Closeout 60 27-Aug-18 19-Nov-18 67
CRYO-CLOSE-1400 Project Complete - Cryo Plant Building 0 19-Nov-18 67
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
2017 2018 2019
Fermilab Proton Improvement Plan - II 17.05.19
Cryo Plant Building
Preconstruction
Contract Administration
Notice to Proceed - Cryo Plant Building
Bonds & Insurance, Initial Engineering, Safey Plans & Permits
Start Construction - Cryo Plant Building
Engineering
Foundations & Concrete Submittals & Fabrication
MEP Submittals & Coordination (BIM)
OFCI 25-Ton & 15-Ton Crane Submittals & Fabrication
Structural Steel Submittals & Fabrication
Exterior Skin Submittals & Fabrication
OFCI Transformer & Electrical Equipment Submittals & Fabrication
Generator Submittals & Fabrication
MEP Major Equipment Fabrication
Construction
Mobilization
Mobilization
Foundations & Structure
Grub, Strip & Prepare Building Pad
Piping Trench with Inserts
Grade Beams & Footings
Building Underground Utilities
Form, Rebar & Place SOG
SOG Sealer
Erect Structural Steel & Cranes, Decking & Detailing
Exterior Skin
Install Parapet, Roofing & Skylights
Install Metal Panels & Curtainwall
Install Overhead Door
Interior
Paint Structural Steel
MEP / FP Overhead Rough-In & Partitions
Control Room, Tech Space & Toilet Rooms Buildout
Form & Place Equipment Pads
Paint MEP / FP Piping
Set Equipment
Install Lights, Power, Fire Alarm & Securi ty
MEP Rough-In & Hookups
Exterior Equipment & Yard
Install Pipe Supports Drilled Piers
Site Utilities
Form, Rebar & Place Transformer & Generator Pads
Set Transformers & Generator
Form, Rebar & Place Dewar Foundations & Pads
Generator Electrical Rough-In and Pull & Terminate Wire
Transformer Electrical Rough-In and Pull & Terminate Wire
Dewar Piping & Electrical Work
Prep & Construct Dewar Hardstand Area
Sitework
Cut Roadways to Subgrade
Install Stone Sub & Aggregate Base
Install Light Poles
Remove Erosion Controls & Landscaping
Asphalt Paving
Closeout
Punchlist
Test ing & Balancing
Beneficial Occupancy - Cryo Plant Building
Project Closeout
Project Complete - Cryo Plant Building
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Fermilab CRYO
Fermilab Proton Improvement Plan - II 17.05.19 - CRYO PLANT BUILDING
Page 1 of 1
Activity ID Activity Name Original
Duration
Start Finish TotalFloat
Fermilab Proton Improvement Plan - IIFermilab Proton Improvement Plan - II 263 01-Jun-17 14-Jun-18 157
Utility Plant Building (PUB)Utility Plant Building (PUB) 263 01-Jun-17 14-Jun-18 157
PreconstructionPreconstruction 130 01-Jun-17 06-Dec-17 175
Contract AdministrationContract Administration 20 01-Jun-17 30-Jun-17 157
PUB-CA-1000 Notice to Proceed - PUB 0 01-Jun-17* 0
PUB-CA-1100 Bonds & Insurance, Initial Engineering, Safey Plans & Permits 20 02-Jun-17 29-Jun-17 157
PUB-CA-1200 Start Construction - PUB 0 30-Jun-17 157
EngineeringEngineering 120 16-Jun-17 06-Dec-17 175
PUB-ENGR-1000 Foundations & Concrete Submittals & Fabrication 40 16-Jun-17 11-Aug-17 167
PUB-ENGR-1100 MEP Submittals & Coordination (BIM) 40 16-Jun-17 11-Aug-17 175
PUB-ENGR-1300 Structural Steel Submittals & Fabrication 80 16-Jun-17 09-Oct-17 160
PUB-ENGR-1200 Exterior Skin Submittals & Fabrication 90 16-Jun-17 23-Oct-17 185
PUB-ENGR-1500 OFCI Transformer Submittals & Fabrication 100 16-Jun-17 06-Nov-17 195
PUB-ENGR-1600 MEP Major Equipment Fabrication 80 14-Aug-17 06-Dec-17 175
ConstructionConstruction 163 30-Jun-17 21-Feb-18 237
MobilizationMobilization 20 30-Jun-17 28-Jul-17 157
PUB-MOB-1000 Mobilization 20 30-Jun-17 28-Jul-17 157
Foundations & StructureFoundations & Structure 68 31-Jul-17 02-Nov-17 157
PUB-F&S-1000 Grub, Strip & Prepare Building Pad 20 31-Jul-17 25-Aug-17 157
PUB-F&S-1100 Building Grade Beams & Footings 15 28-Aug-17 18-Sep-17 157
PUB-F&S-1200 Building Underground Utilities 10 19-Sep-17 02-Oct-17 157
PUB-F&S-1300 Form, Rebar & Place SOG 5 03-Oct-17 09-Oct-17 157
PUB-F&S-1400 SOG Sealer 3 10-Oct-17 12-Oct-17 157
PUB-F&S-1500 Erect Structural Steel, Decking & Detailing 15 13-Oct-17 02-Nov-17 157
Exterior SkinExterior Skin 25 03-Nov-17 11-Dec-17 177
PUB-EXT-1000 Install Parapet, Roofing & Skylights 15 03-Nov-17 27-Nov-17 157
PUB-EXT-1100 Install Metal Panels & Curtainwall 25 03-Nov-17 11-Dec-17 177
PUB-EXT-1200 Install Overhead Door 5 10-Nov-17 16-Nov-17 192
InteriorInterior 60 28-Nov-17 21-Feb-18 237
PUB-INT-1000 Paint Structural Steel 10 28-Nov-17 11-Dec-17 157
PUB-INT-1100 MEP / FP Overhead Rough-In 20 12-Dec-17 10-Jan-18 157
PUB-INT-1200 Form & Place Equipment Pads 5 11-Jan-18 17-Jan-18 252
PUB-INT-1300 Paint MEP / FP Piping 10 11-Jan-18 24-Jan-18 157
PUB-INT-1400 Control & Electrical Room Buildout 30 11-Jan-18 21-Feb-18 157
PUB-INT-1500 Set Equipment 10 18-Jan-18 31-Jan-18 252
PUB-INT-1600 Install Lights, Power, Fire Alarm & Security 15 25-Jan-18 14-Feb-18 162
PUB-INT-1700 MEP Rough-In & Hookups 20 25-Jan-18 21-Feb-18 157
Exterior Equipment & YardExterior Equipment & Yard 80 19-Sep-17 12-Jan-18 185
PUB-EQ-1000 Install Pipe Supports Drilled Piers 5 19-Sep-17 25-Sep-17 190
PUB-EQ-1100 Site Utilities 20 03-Oct-17 30-Oct-17 185
PUB-EQ-1200 Form, Rebar & Place Transformer Pad 5 03-Nov-17 09-Nov-17 182
PUB-EQ-1300 Form, Rebar & Place Cooling Tower Pads 10 10-Nov-17 27-Nov-17 182
PUB-EQ-1400 Set Transformer & Cooling Towers 5 07-Dec-17 13-Dec-17 175
PUB-EQ-1500 Transformer Electrical Rough-In and Pull & Terminate Wire 20 14-Dec-17 12-Jan-18 185
PUB-EQ-1600 Cooling Tower Piping & Electrical Work 20 14-Dec-17 12-Jan-18 185
SiteworkSitework 30 14-Dec-17 26-Jan-18 175
PUB-SITE-1000 Cut Roadways to Subgrade 5 14-Dec-17 20-Dec-17 175
PUB-SITE-1100 Install Stone Sub & Aggregate Base 5 21-Dec-17 28-Dec-17 175
PUB-SITE-1200 Install Light Poles 5 29-Dec-17 05-Jan-18 175
PUB-SITE-1300 Remove Erosion Controls & Landscaping 10 08-Jan-18 19-Jan-18 175
PUB-SITE-1400 Asphalt Paving 5 22-Jan-18 26-Jan-18 175
CloseoutCloseout 80 22-Feb-18 14-Jun-18 157
PUB-CLOSE-1000 Testing & Balancing 20 22-Feb-18 21-Mar-18 157
PUB-CLOSE-1100 Punchlist 20 22-Feb-18 21-Mar-18 157
PUB-CLOSE-1200 Beneficial Occupancy - PUB 0 21-Mar-18 157
PUB-CLOSE-1300 Project Closeout 60 22-Mar-18 14-Jun-18 157
PUB-CLOSE-1400 Project Complete - PUB 0 14-Jun-18 157
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
2017 2018
Fermilab Proton Improvement Plan - II
Utility Plant Building (PUB)
Preconstruction
Contract Administration
Notice to Proceed - PUB
Bonds & Insurance, Initial Engineering, Safey Plans & Permits
Start Construction - PUB
Engineering
Foundations & Concrete Submittals & Fabrication
MEP Submittals & Coordination (BIM)
Structural Steel Submittals & Fabrication
Exterior Skin Submittals & Fabrication
OFCI Transformer Submittals & Fabrication
MEP Major Equipment Fabrication
Construction
Mobilization
Mobilization
Foundations & Structure
Grub, Strip & Prepare Building Pad
Building Grade Beams & Footings
Building Underground Utilities
Form, Rebar & Place SOG
SOG Sealer
Erect Structural Steel, Decking & Detailing
Exterior Skin
Install Parapet, Roofing & Skylights
Install Metal Panels & Curtainwall
Install Overhead Door
Interior
Paint Structural Steel
MEP / FP Overhead Rough-In
Form & Place Equipment Pads
Paint MEP / FP Piping
Control & Electrical Room Buildout
Set Equipment
Install Lights, Power, Fire Alarm & Security
MEP Rough-In & Hookups
Exterior Equipment & Yard
Install Pipe Supports Drilled Piers
Site Utilities
Form, Rebar & Place Transformer Pad
Form, Rebar & Place Cooling Tower Pads
Set Transformer & Cooling Towers
Transformer Electrical Rough-In and Pull & Terminate Wire
Cooling Tower Piping & Electrical Work
Sitework
Cut Roadways to Subgrade
Install Stone Sub & Aggregate Base
Install Light Poles
Remove Erosion Controls & Landscaping
Asphalt Paving
Closeout
Testing & Balancing
Punchlist
Beneficial Occupancy - PUB
Project Closeout
Project Complete - PUB
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Fermilab PUB
Fermilab Proton Improvement Plan - II - UTILITY PLANT BUILDING
Page 1 of 1
| Fermilab PIP II VE Report71
Activity ID Activity Name OriginalDuration
Start Finish TotalFloat
Fermilab Proton Improvement Plan - II 18.04.27Fermilab Proton Improvement Plan - II 18.04.27 528 01-Jun-17 02-Jul-19 0
High Bay Building, Linac Tunnel, Linac Gallery, Beam Transfer Line & Booster ConnectionHigh Bay Building, Linac Tunnel, Linac Gallery, Beam Transfer Line & Booster Connection 528 01-Jun-17 02-Jul-19 0
PreconstructionPreconstruction 160 01-Jun-17 19-Jan-18 368
Contract AdministrationContract Administration 40 01-Jun-17 31-Jul-17 0
HIGH-CA-1000 Notice to Proceed 0 01-Jun-17* 0
HIGH-CA-1100 Bonds & Insurance, Initial Engineering, Safey Plans & Permits 40 02-Jun-17 28-Jul-17 0
HIGH-CA-1200 Start Construction 0 31-Jul-17 0
EngineeringEngineering 120 31-Jul-17 19-Jan-18 368
High Bay BuildingHigh Bay Building 120 31-Jul-17 19-Jan-18 368
HIGH-ENGR-1000 Foundations & Concrete Submittals & Fabrication 40 31-Jul-17 25-Sep-17 0
HIGH-ENGR-1100 MEP Submittals & Coordination (BIM) 40 31-Jul-17 25-Sep-17 215
HIGH-ENGR-1300 Structural Steel Submittals & Fabrication 80 31-Jul-17 20-Nov-17 178
HIGH-ENGR-1400 OFCI 20-Ton Crane Submittals & Fabrication 80 31-Jul-17 20-Nov-17 178
HIGH-ENGR-1600 Precast Shielding Block Submittals & Fabrication 80 31-Jul-17 20-Nov-17 408
HIGH-ENGR-1200 Exterior Skin Submittals & Fabrication 90 31-Jul-17 06-Dec-17 213
HIGH-ENGR-1500 Elevator Submittals & Fabrication 100 31-Jul-17 20-Dec-17 238
HIGH-ENGR-1700 MEP Major Equipment Fabrication 80 26-Sep-17 19-Jan-18 368
Linac TunnelLinac Tunnel 100 31-Jul-17 20-Dec-17 298
TUN-ENGR-1000 Foundations & Concrete Submittals & Fabrication 40 31-Jul-17 25-Sep-17 35
TUN-ENGR-1100 MEP Submittals & Coordination (BIM) 40 31-Jul-17 25-Sep-17 333
TUN-ENGR-1200 Coax & Waveguide Enclosures Submittals & Fabrication 100 31-Jul-17 20-Dec-17 298
Linac GalleryLinac Gallery 120 31-Jul-17 19-Jan-18 263
GAL-ENGR-1000 Foundations & Concrete Submittals & Fabrication 40 31-Jul-17 25-Sep-17 95
GAL-ENGR-1100 MEP Submittals & Coordination (BIM) 40 31-Jul-17 25-Sep-17 195
GAL-ENGR-1200 Structural Steel Submittals & Fabrication 80 31-Jul-17 20-Nov-17 183
GAL-ENGR-1300 1-Ton Monorail Submittals & Fabrication 80 31-Jul-17 20-Nov-17 183
GAL-ENGR-1400 Exterior Skin Submittals & Fabrication 90 31-Jul-17 06-Dec-17 223
GAL-ENGR-1500 Generator Submittals & Fabrication 100 31-Jul-17 20-Dec-17 283
GAL-ENGR-1600 OFCI Trans former & Electr ic al Equipment Submi ttals & Fabr icati on 100 31-Jul-17 20-Dec-17 283
GAL-ENGR-1700 MEP Major Equipment Fabrication 80 26-Sep-17 19-Jan-18 243
Beam Transfer LineBeam Transfer Line 80 31-Jul-17 20-Nov-17 403
BEAM-ENGR-1000 Box Culvert & E/WRS Submittals & Fabrication 40 31-Jul-17 25-Sep-17 193
BEAM-ENGR-1100 Foundations & Concrete Submittals & Fabrication 40 31-Jul-17 25-Sep-17 198
BEAM-ENGR-1200 MEP Submittals & Coordination (BIM) 40 31-Jul-17 25-Sep-17 198
BEAM-ENGR-1300 OFCI Road Shielding Steel Submittals & Fabrication 80 31-Jul-17 20-Nov-17 258
BEAM-ENGR-1400 OFCI Abort Steel Submittals & Fabri cation 80 31-Jul-17 20-Nov-17 403
Booster ConnectionBooster Connection 80 31-Jul-17 20-Nov-17 378
BOOST-ENGR-1000 Micropile & ERS Submittals & Fabrication 40 31-Jul-17 25-Sep-17 178
BOOST-ENGR-1100 Foundations & Concrete Submittals & Fabrication 40 31-Jul-17 25-Sep-17 218
BOOST-ENGR-1200 MEP Submittals & Coordination (BIM) 40 31-Jul-17 25-Sep-17 418
BOOST-ENGR-1300 OFCI Road Shielding Steel Submittals & Fabrication 80 31-Jul-17 20-Nov-17 283
M Jun Jul A S Oct N Dec Jan F Mar Apr M Jun Jul Aug S Oct N D Jan F Mar Apr M Jun Jul A S Oct2017 2018 2019
Fermilab Proton Improvement Plan - II 18.04.27
High Bay Building, Linac Tunnel, Li nac Gal lery, Beam Transfer Line & Booster Connection
Preconstruction
Contract Admi nistrat ion
Notice to Proceed
Bonds & Insurance, Initial Engineering, Safey Plans & Permits
Start Construction
Engineering
High Bay Building
Foundations & Concrete Submittals & Fabrication
MEP Submittals & Coordination (BIM)
Structural Steel Submittals & Fabrication
OFCI 20-Ton Crane Submittals & Fabrication
Precast Shielding Block Submittals & Fabrication
Exterior Skin Submittals & Fabrication
Elevator Submittals & Fabrication
MEP Major Equipment Fabrication
Linac Tunnel
Foundations & Concrete Submittals & Fabrication
MEP Submittals & Coordination (BIM)
Coax & Waveguide Enclosures Submittals & Fabrication
Linac Gallery
Foundations & Concrete Submittals & Fabrication
MEP Submittals & Coordination (BIM)
Structural Steel Submittals & Fabrication
1-Ton Monorail Submittals & Fabrication
Exterior Skin Submittals & Fabrication
Generator Submittals & Fabrication
OFCI Trans former & Electr ical Equipment Submi ttals & Fabr icati on
MEP Major Equipment Fabrication
Beam Trans fer Line
Box Culvert & E/WRS Submittals & Fabrication
Foundations & Concrete Submittals & Fabrication
MEP Submittals & Coordination (BIM)
OFCI Road Shielding Steel Submittals & Fabrication
OFCI Abort Steel Submittals & Fabri cation
Booster Connection
Micropile & ERS Submittals & Fabrication
Foundations & Concrete Submittals & Fabrication
MEP Submittals & Coordination (BIM)
OFCI Road Shielding Steel Submittals & Fabrication
Actual WorkRemaining WorkCritical Remaining WorkMilestoneSummaryHigh Bay, Linac Tunnel & Linac Gallery
Fermilab Proton Improvement Plan - II 18.04.27
HIGH BAY BUILDING, LINAC TUNNEL, LINAC GALLERY,
BEAM TRANSFER LINE & BOOSTER CONNECTION
Page 1 of 10
| Fermilab PIP II VE Report72
Activity ID Activity Name OriginalDuration
Start Finish TotalFloat
ConstructionConstruction 408 31-Jul-17 11-Mar-19 80
MobilizationMobilization 70 31-Jul-17 06-Nov-17 198
HIGH-MOB-1000 Mobilization 20 31-Jul-17 25-Aug-17 0
HIGH-MOB-1100 Grub & Strip Topsoi l - High Bay 10 28-Aug-17 11-Sep-17 0
TUN-MOB-1100 Grub & Strip Topsoi l - Linac Tunnel 10 12-Sep-17 25-Sep-17 15
GAL-MOB-1100 Grub & Strip Topsoi l - Linac Gallery 10 26-Sep-17 09-Oct-17 70
BEAM-MOB-1100 Grub & Strip Topsoi l - Beam Transfer Line 10 10-Oct-17 23-Oct-17 133
BOOST-MOB-1100 Grub & Strip Topsoi l - Booster Connection 10 24-Oct-17 06-Nov-17 198
High Bay BuildingHigh Bay Building 225 12-Sep-17 31-Jul-18 233
High BayHigh Bay 200 12-Sep-17 25-Jun-18 258
Foundations & StructureFoundations & Structure 115 12-Sep-17 23-Feb-18 193
BAY-F&S-1000 Excavate Below Grade Area 20 12-Sep-17 09-Oct-17 0
BAY-F&S-1100 Pour 3" Mud Slab 10 26-Sep-17 09-Oct-17 0
BAY-F&S-1200 ***Prep & Place Base Mat 5 10-Oct-17 16-Oct-17 0
BAY-F&S-1300 Form, Rebar & Place Foundation Walls with Inserts, Buttresses & Stairs #1, #2 & #5 40 17-Oct-17 13-Dec-17 153
BAY-F&S-1400 Install Underdrain, Dampproofing, Insulation & Backfill Foundation Walls 30 14-Nov-17 28-Dec-17 153
BAY-F&S-1500 Grade Beams, Footings & SOG at Receiving / Staging 20 30-Nov-17 28-Dec-17 153
BAY-F&S-1600 Erect Structural Steel & Cranes, Mezzanine, Decking & Detailing 30 29-Dec-17 09-Feb-18 153
BAY-F&S-1700 Rub & Patch Concrete Walls 10 12-Feb-18 23-Feb-18 193
Exterior SkinExterior Skin 50 12-Feb-18 20-Apr-18 303
BAY-EXT-1000 Install Parapet, Roofing, Skylights & Roof Hatch 25 12-Feb-18 16-Mar-18 178
BAY-EXT-1100 Install Metal Panels & Curtainwall 50 12-Feb-18 20-Apr-18 168
BAY-EXT-1200 Install Overhead Door 10 12-Mar-18 23-Mar-18 323
BAY-EXT-1300 Stair #5 Enclosure 30 12-Mar-18 20-Apr-18 168
InteriorInterior 70 19-Mar-18 25-Jun-18 258
BAY-INT-1000 Paint Structural Steel & Exposed Concrete 10 19-Mar-18 30-Mar-18 178
BAY-INT-1100 MEP / FP Overhead Rough-In 30 02-Apr-18 11-May-18 178
BAY-INT-1200 Paint MEP / FP Piping 10 14-May-18 25-May-18 178
BAY-INT-1300 Epoxy Flooring 10 14-May-18 25-May-18 278
BAY-INT-1400 Install Lights, Power, F ire Alarm & Security 15 29-May-18 18-Jun-18 263
BAY-INT-1500 MEP Rough-In & Hookups 20 29-May-18 25-Jun-18 178
Adjacent BuildingAdjacent Building 170 30-Nov-17 31-Jul-18 153
Foundations & StructureFoundations & Structure 65 30-Nov-17 02-Mar-18 153
ADJ-F&S-1000 Grade Beams & Footings 20 30-Nov-17 28-Dec-17 160
ADJ-F&S-1100 Building Underground Utilities 20 14-Dec-17 12-Jan-18 160
ADJ-F&S-1200 Form, Rebar & Place SOG 10 15-Jan-18 26-Jan-18 160
ADJ-F&S-1300 SOG Sealer 3 29-Jan-18 31-Jan-18 160
ADJ-F&S-1400 Erect Structural Steel, Decking & Detailing 15 12-Feb-18 02-Mar-18 153
Exterior SkinExterior Skin 30 05-Mar-18 13-Apr-18 173
ADJ-EXT-1000 Install Parapet, Roofing & Skylights 20 05-Mar-18 30-Mar-18 153
ADJ-EXT-1100 Install Metal Panels & Curtainwall 30 05-Mar-18 13-Apr-18 173
InteriorInterior 85 02-Apr-18 31-Jul-18 153
M Jun Jul A S Oct N Dec Jan F Mar Apr M Jun Jul Aug S Oct N D Jan F Mar Apr M Jun Jul A S Oct2017 2018 2019
Construction
Mobilization
Mobilization
Grub & Strip Topsoi l - High Bay
Grub & Strip Topsoi l - Linac Tunnel
Grub & Strip Topsoi l - Linac Gallery
Grub & Strip Topsoi l - Beam Transfer Line
Grub & Strip Topsoi l - Booster Connection
High Bay Building
High Bay
Foundations & Structure
Excavate Below Grade Area
Pour 3" Mud Slab
***Prep & Place Base Mat
Form, Rebar & Place Foundation Walls with Inserts, Buttresses & Stairs #1, #2 & #5
Install Underdrain, Dampproofing, Insulation & Backfill Foundation Walls
Grade Beams, Footings & SOG at Receiving / Staging
Erect Structural Steel & Cranes, Mezzanine, Decking & Detailing
Rub & Patch Concrete Walls
Exterior Skin
Install Parapet, Roofing, Skylights & Roof Hatch
Install Metal Panels & Curtainwall
Install Overhead Door
Stair #5 Enclosure
Interior
Paint Structural Steel & Exposed Concrete
MEP / FP Overhead Rough-In
Paint MEP / FP Piping
Epoxy Flooring
Install Lights, Power, F ire Alarm & Security
MEP Rough-In & Hookups
Adjacent Building
Foundations & Structure
Grade Beams & Footings
Building Underground Utilities
Form, Rebar & Place SOG
SOG Sealer
Erect Structural Steel, Decking & Detailing
Exterior Skin
Install Parapet, Roofing & Skylights
Install Metal Panels & Curtainwall
Interior
Actual WorkRemaining WorkCritical Remaining WorkMilestoneSummaryHigh Bay, Linac Tunnel & Linac Gallery
Fermilab Proton Improvement Plan - II 18.04.27
HIGH BAY BUILDING, LINAC TUNNEL, LINAC GALLERY,
BEAM TRANSFER LINE & BOOSTER CONNECTION
Page 2 of 10
| Fermilab PIP II VE Report73
Activity ID Activity Name OriginalDuration
Start Finish TotalFloat
ADJ-INT-1000 Paint Structural Steel 5 02-Apr-18 06-Apr-18 153
ADJ-INT-1100 Install Elevator 70 02-Apr-18 10-Jul-18 168
ADJ-INT-1200 MEP / FP Overhead Rough-In 30 09-Apr-18 18-May-18 153
ADJ-INT-1300 Tech Space, Control Room, Conference, Toilets & Lobby Buildout 60 07-May-18 31-Jul-18 153
ADJ-INT-1400 Paint MEP / FP Piping 10 21-May-18 04-Jun-18 173
ADJ-INT-1500 MEP Rough-In, Set Equipment & Hookups 20 05-Jun-18 02-Jul-18 173
SiteworkSitework 55 23-Apr-18 10-Jul-18 168
HIGH-SITE-1000 Cut Roadways to Subgrade 10 23-Apr-18 04-May-18 168
HIGH-SITE-1100 Install Stone Sub & Aggregate Base 10 07-May-18 18-May-18 168
HIGH-SITE-1200 Install Light Poles 10 21-May-18 04-Jun-18 168
HIGH-SITE-1300 Remove Erosion Controls & Landscaping 20 05-Jun-18 02-Jul-18 168
HIGH-SITE-1400 Asphalt Paving 5 03-Jul-18 10-Jul-18 168
Linac TunnelLinac Tunnel 200 17-Oct-17 31-Jul-18 153
Sequence #1Sequence #1 120 17-Oct-17 06-Apr-18 233
Foundations & TunnelFoundations & Tunnel 90 17-Oct-17 23-Feb-18 263
TUN-F&S1-1000 ***Excavate Tunnel 20 17-Oct-17 13-Nov-17 0
TUN-F&S1-1100 Pour 3" Mud Slab 10 31-Oct-17 13-Nov-17 0
TUN-F&S1-1200 Form, Rebar & Place Base Slab, Walls & Roof with Inserts 40 14-Nov-17 12-Jan-18 0
TUN-F&S1-1300 ***Install Underdrain, Dampproofing, Insulation & Backfill Foundation Walls 30 07-Dec-17 19-Jan-18 0
TUN-F&S1-1400 Install Coax Carrier Pipes, PVC Ducts & Backfill 25 08-Jan-18 09-Feb-18 263
TUN-F&S1-1500 Set Coax Enclosures 10 12-Feb-18 23-Feb-18 263
InteriorInterior 60 15-Jan-18 06-Apr-18 233
TUN-INT1-1000 Rub & Patch Concrete Walls 10 15-Jan-18 26-Jan-18 233
TUN-INT1-1100 Paint Tunnel Walls & Roof 10 29-Jan-18 09-Feb-18 233
TUN-INT1-1200 Fire Alarm, Cable Tray, Power & Lighting 30 12-Feb-18 23-Mar-18 233
TUN-INT1-1300 Epoxy Flooring 10 26-Mar-18 06-Apr-18 233
Sequence #2Sequence #2 120 14-Nov-17 04-May-18 213
Foundations & TunnelFoundations & Tunnel 90 14-Nov-17 23-Mar-18 243
TUN-F&S2-1000 Excavate Tunnel 20 14-Nov-17 13-Dec-17 38
TUN-F&S2-1100 Pour 3" Mud Slab 10 30-Nov-17 13-Dec-17 153
TUN-F&S2-1200 Form, Rebar & Place Base Slab, Walls & Roof with Inserts 40 14-Dec-17 09-Feb-18 153
TUN-F&S2-1300 Install Underdrain, Dampproofing, Insulation & Backfill Foundation Walls 30 08-Jan-18 16-Feb-18 243
TUN-F&S2-1400 Install Coax Carrier Pipes, PVC Ducts & Backfill 25 05-Feb-18 09-Mar-18 243
TUN-F&S2-1500 Set Waveguide Enclosures 10 12-Mar-18 23-Mar-18 243
InteriorInterior 60 12-Feb-18 04-May-18 213
TUN-INT2-1000 Rub & Patch Concrete Walls 10 12-Feb-18 23-Feb-18 213
TUN-INT2-1100 Paint Tunnel Walls & Roof 10 26-Feb-18 09-Mar-18 213
TUN-INT2-1200 Fire Alarm, Cable Tray, Power & Lighting 30 12-Mar-18 20-Apr-18 213
TUN-INT2-1300 Epoxy Flooring 10 23-Apr-18 04-May-18 213
Sequence #3Sequence #3 120 14-Dec-17 04-Jun-18 193
Foundations & TunnelFoundations & Tunnel 110 14-Dec-17 18-May-18 203
TUN-F&S3-1000 Excavate Tunnel 20 14-Dec-17 12-Jan-18 38
M Jun Jul A S Oct N Dec Jan F Mar Apr M Jun Jul Aug S Oct N D Jan F Mar Apr M Jun Jul A S Oct2017 2018 2019
Paint Structural Steel
Install Elevator
MEP / FP Overhead Rough-In
Tech Space, Control Room, Conference, Toilets & Lobby Buildout
Paint MEP / FP Piping
MEP Rough-In, Set Equipment & Hookups
Sitework
Cut Roadways to Subgrade
Install Stone Sub & Aggregate Base
Install Light Poles
Remove Erosion Controls & Landscaping
Asphalt Paving
Linac Tunnel
Sequence #1
Foundations & Tunnel
***Excavate Tunnel
Pour 3" Mud Slab
Form, Rebar & Place Base Slab, Walls & Roof with Inserts
***Install Underdrain, Dampproofing, Insulation & Backfill Foundation Walls
Install Coax Carrier Pipes, PVC Ducts & Backfill
Set Coax Enclosures
Interior
Rub & Patch Concrete Walls
Paint Tunnel Walls & Roof
Fire Alarm, Cable Tray, Power & Lighting
Epoxy Flooring
Sequence #2
Foundations & Tunnel
Excavate Tunnel
Pour 3" Mud Slab
Form, Rebar & Place Base Slab, Walls & Roof with Inserts
Install Underdrain, Dampproofing, Insulation & Backfill Foundation Walls
Install Coax Carrier Pipes, PVC Ducts & Backfill
Set Waveguide Enclosures
Interior
Rub & Patch Concrete Walls
Paint Tunnel Walls & Roof
Fire Alarm, Cable Tray, Power & Lighting
Epoxy Flooring
Sequence #3
Foundations & Tunnel
Excavate Tunnel
Actual WorkRemaining WorkCritical Remaining WorkMilestoneSummaryHigh Bay, Linac Tunnel & Linac Gallery
Fermilab Proton Improvement Plan - II 18.04.27
HIGH BAY BUILDING, LINAC TUNNEL, LINAC GALLERY,
BEAM TRANSFER LINE & BOOSTER CONNECTION
Page 3 of 10
| Fermilab PIP II VE Report74
Activity ID Activity Name OriginalDuration
Start Finish TotalFloat
TUN-F&S3-1100 Pour 3" Mud Slab 10 29-Dec-17 12-Jan-18 153
TUN-F&S3-1200 Form, Rebar & Place Base Slab, Walls & Roof with Inserts 40 15-Jan-18 09-Mar-18 153
TUN-F&S3-1300 Form, Rebar & Place Side Ai sle / Stai r #3 & Stair #4 30 29-Jan-18 09-Mar-18 193
TUN-F&S3-1400 Install Underdrain, Dampproofing, Insulation & Backfill Foundation Walls 30 05-Feb-18 16-Mar-18 168
TUN-F&S3-1500 Install Coax Carrier Pipes, PVC Ducts, Cyro Piping & Backfill 25 05-Mar-18 06-Apr-18 168
TUN-F&S3-1600 Piping Trench with Ins er ts 20 19-Mar-18 13-Apr-18 228
TUN-F&S3-1700 Set Waveguide Enclosures 10 09-Apr-18 20-Apr-18 223
TUN-F&S3-1800 Stair #4 Enclosure 30 09-Apr-18 18-May-18 178
InteriorInterior 60 12-Mar-18 04-Jun-18 193
TUN-INT3-1000 Rub & Patch Concrete Walls 10 12-Mar-18 23-Mar-18 193
TUN-INT3-1100 Paint Tunnel Walls & Roof 10 26-Mar-18 06-Apr-18 193
TUN-INT3-1200 Fire Alarm, Cable Tray, Power & Lighting 30 09-Apr-18 18-May-18 193
TUN-INT3-1300 Epoxy Flooring 10 21-May-18 04-Jun-18 193
Sequence #4Sequence #4 120 15-Jan-18 02-Jul-18 173
Foundations & TunnelFoundations & Tunnel 90 15-Jan-18 18-May-18 203
TUN-F&S4-1000 Excavate Tunnel 20 15-Jan-18 09-Feb-18 38
TUN-F&S4-1100 Pour 3" Mud Slab 10 29-Jan-18 09-Feb-18 153
TUN-F&S4-1200 Form, Rebar & Place Base Slab, Walls & Roof with Inserts 40 12-Feb-18 06-Apr-18 153
TUN-F&S4-1300 Install Underdrain, Dampproofing, Insulation & Backfill Foundation Walls 30 05-Mar-18 13-Apr-18 203
TUN-F&S4-1400 Install Coax Carrier Pipes, PVC Ducts & Backfill 25 02-Apr-18 04-May-18 203
TUN-F&S4-1500 Set Waveguide Enclosures 10 07-May-18 18-May-18 203
InteriorInterior 60 09-Apr-18 02-Jul-18 173
TUN-INT4-1000 Rub & Patch Concrete Walls 10 09-Apr-18 20-Apr-18 173
TUN-INT4-1100 Paint Tunnel Walls & Roof 10 23-Apr-18 04-May-18 173
TUN-INT4-1200 Fire Alarm, Cable Tray, Power & Lighting 30 07-May-18 18-Jun-18 173
TUN-INT4-1300 Epoxy Flooring 10 19-Jun-18 02-Jul-18 173
Sequence #5 - ExtensionSequence #5 - Extension 120 12-Feb-18 31-Jul-18 153
Foundations & TunnelFoundations & Tunnel 80 12-Feb-18 04-Jun-18 193
TUN-F&S5-1000 Excavate Tunnel 20 12-Feb-18 09-Mar-18 38
TUN-F&S5-1100 Pour 3" Mud Slab 10 26-Feb-18 09-Mar-18 153
TUN-F&S5-1200 Form, Rebar & Place Base Slab, Walls & Roof with Inserts 40 12-Mar-18 04-May-18 153
TUN-F&S5-1300 Form, Rebar & Place Stair #6 30 26-Mar-18 04-May-18 153
TUN-F&S5-1400 Install Underdrain, Dampproofing, Insulation & Backfill Foundation Walls 30 02-Apr-18 11-May-18 193
TUN-F&S5-1500 Sand Fill Enclosure Extension 10 16-Apr-18 27-Apr-18 153
TUN-F&S5-1600 Backfill to Grade 15 14-May-18 04-Jun-18 193
InteriorInterior 60 07-May-18 31-Jul-18 153
TUN-INT5-1000 Rub & Patch Concrete Walls 10 07-May-18 18-May-18 153
TUN-INT5-1100 Paint Tunnel Walls & Roof 10 21-May-18 04-Jun-18 153
TUN-INT5-1200 Fire Alarm, Cable Tray, Power & Lighting 30 05-Jun-18 17-Jul-18 153
TUN-INT5-1300 Epoxy Flooring 10 18-Jul-18 31-Jul-18 153
SiteworkSitework 65 09-Apr-18 10-Jul-18 168
TUN-SITE-1000 Install Berms & Fine Grading 30 09-Apr-18 18-May-18 168
M Jun Jul A S Oct N Dec Jan F Mar Apr M Jun Jul Aug S Oct N D Jan F Mar Apr M Jun Jul A S Oct2017 2018 2019
Pour 3" Mud Slab
Form, Rebar & Place Base Slab, Walls & Roof with Inserts
Form, Rebar & Place Side Ai sle / Stai r #3 & Stair #4
Install Underdrain, Dampproofing, Insulation & Backfill Foundation Walls
Install Coax Carrier Pipes, PVC Ducts, Cyro Piping & Backfill
Piping Trench with Ins er ts
Set Waveguide Enclosures
Stair #4 Enclosure
Interior
Rub & Patch Concrete Walls
Paint Tunnel Walls & Roof
Fire Alarm, Cable Tray, Power & Lighting
Epoxy Flooring
Sequence #4
Foundations & Tunnel
Excavate Tunnel
Pour 3" Mud Slab
Form, Rebar & Place Base Slab, Walls & Roof with Inserts
Install Underdrain, Dampproofing, Insulation & Backfill Foundation Walls
Install Coax Carrier Pipes, PVC Ducts & Backfill
Set Waveguide Enclosures
Interior
Rub & Patch Concrete Walls
Paint Tunnel Walls & Roof
Fire Alarm, Cable Tray, Power & Lighting
Epoxy Flooring
Sequence #5 - Extension
Foundations & Tunnel
Excavate Tunnel
Pour 3" Mud Slab
Form, Rebar & Place Base Slab, Walls & Roof with Inserts
Form, Rebar & Place Stair #6
Install Underdrain, Dampproofing, Insulation & Backfill Foundation Walls
Sand Fill Enclosure Extension
Backfill to Grade
Interior
Rub & Patch Concrete Walls
Paint Tunnel Walls & Roof
Fire Alarm, Cable Tray, Power & Lighting
Epoxy Flooring
Sitework
Install Berms & Fine Grading
Actual WorkRemaining WorkCritical Remaining WorkMilestoneSummaryHigh Bay, Linac Tunnel & Linac Gallery
Fermilab Proton Improvement Plan - II 18.04.27
HIGH BAY BUILDING, LINAC TUNNEL, LINAC GALLERY,
BEAM TRANSFER LINE & BOOSTER CONNECTION
Page 4 of 10
| Fermilab PIP II VE Report75
Activity ID Activity Name OriginalDuration
Start Finish TotalFloat
TUN-SITE-1100 Install Light Poles 10 21-May-18 04-Jun-18 168
TUN-SITE-1200 Remove Erosion Controls & Landscaping 25 05-Jun-18 10-Jul-18 168
Linac GalleryLinac Gallery 288 22-Jan-18 11-Mar-19 80
Sequence #1Sequence #1 213 22-Jan-18 19-Nov-18 75
Foundations & StructureFoundations & Structure 88 22-Jan-18 23-May-18 75
GAL-MOB-1200 ***Excavate & Prep Building Pad 70 22-Jan-18 27-Apr-18 0
GAL-F&S1-1000 Building Grade Beams, Footings & Walls 25 12-Feb-18 16-Mar-18 0
GAL-F&S1-1100 Install 5" PVC Ducts, Dampproofing, Insulation & Backfill Walls 20 05-Mar-18 30-Mar-18 93
GAL-F&S1-1200 Building Underground Utilities 20 19-Mar-18 13-Apr-18 75
GAL-F&S1-1300 Form, Rebar & Place SOG 5 16-Apr-18 20-Apr-18 75
GAL-F&S1-1400 SOG Sealer 3 23-Apr-18 25-Apr-18 75
GAL-F&S1-1500 Erect Structural Steel, Monorail, Decking & Detailing 20 26-Apr-18 23-May-18 75
GAL-F&S1-1600 Structure Complete 0 23-May-18 75
Exterior SkinExterior Skin 40 24-May-18 20-Jul-18 105
GAL-EXT1-1000 Install Parapet, Roofing & Skylights 20 24-May-18 21-Jun-18 75
GAL-EXT1-1100 Install Metal Panels & Curtainwall 30 24-May-18 06-Jul-18 105
GAL-EXT1-1200 Install Coax Carrier Pipes 10 09-Jul-18 20-Jul-18 105
InteriorInterior 105 22-Jun-18 19-Nov-18 75
GAL-INT1-1000 Paint Structural Steel & Concrete 10 22-Jun-18 06-Jul-18 75
GAL-INT1-1100 MEP / FP Overhead Rough-In 40 09-Jul-18 31-Aug-18 75
GAL-INT1-1200 Form & Place Equipment Pads 10 04-Sep-18 17-Sep-18 75
GAL-INT1-1300 Paint MEP / FP Piping 10 04-Sep-18 17-Sep-18 90
GAL-INT1-1400 Set Equipment 15 18-Sep-18 08-Oct-18 75
GAL-INT1-1500 Install Lights, Power, F ire Alarm & Security 20 18-Sep-18 15-Oct-18 100
GAL-INT1-1600 MEP Rough-In & Hookups 30 09-Oct-18 19-Nov-18 75
Sequence #2Sequence #2 198 19-Mar-18 28-Dec-18 50
Foundations & StructureFoundations & Structure 73 19-Mar-18 28-Jun-18 50
GAL-F&S2-1000 Building Grade Beams, Footings & Walls 25 19-Mar-18 20-Apr-18 0
GAL-F&S2-1100 Install 5" PVC Ducts, Dampproofing, Insulation & Backfill Walls 20 09-Apr-18 04-May-18 68
GAL-F&S2-1200 Building Underground Utilities 20 23-Apr-18 18-May-18 50
GAL-F&S2-1300 Form, Rebar & Place SOG 5 21-May-18 25-May-18 50
GAL-F&S2-1400 SOG Sealer 3 29-May-18 31-May-18 50
GAL-F&S2-1500 Erect Structural Steel, Monorail, Decking & Detailing 20 01-Jun-18 28-Jun-18 50
GAL-F&S2-1600 Structure Complete 0 28-Jun-18 50
Exterior SkinExterior Skin 40 29-Jun-18 24-Aug-18 80
GAL-EXT2-1000 Install Parapet, Roofing & Skylights 20 29-Jun-18 27-Jul-18 50
GAL-EXT2-1100 Install Metal Panels & Curtainwall 30 29-Jun-18 10-Aug-18 80
GAL-EXT2-1200 Install Waveguide Steel Carrier 10 13-Aug-18 24-Aug-18 80
InteriorInterior 105 30-Jul-18 28-Dec-18 50
GAL-INT2-1000 Paint Structural Steel & Concrete 10 30-Jul-18 10-Aug-18 50
GAL-INT2-1100 MEP / FP Overhead Rough-In 40 13-Aug-18 08-Oct-18 50
GAL-INT2-1200 Form & Place Equipment Pads 10 09-Oct-18 22-Oct-18 50
M Jun Jul A S Oct N Dec Jan F Mar Apr M Jun Jul Aug S Oct N D Jan F Mar Apr M Jun Jul A S Oct2017 2018 2019
Install Light Poles
Remove Erosion Controls & Landscaping
Linac Gallery
Sequence #1
Foundations & Structure
***Excavate & Prep Building Pad
Building Grade Beams, Footings & Walls
Install 5" PVC Ducts, Dampproofing, Insulation & Backfill Walls
Building Underground Utilities
Form, Rebar & Place SOG
SOG Sealer
Erect Structural Steel, Monorail, Decking & Detailing
Structure Complete
Exterior Skin
Install Parapet, Roofing & Skylights
Install Metal Panels & Curtainwall
Install Coax Carrier Pipes
Interior
Paint Structural Steel & Concrete
MEP / FP Overhead Rough-In
Form & Place Equipment Pads
Paint MEP / FP Piping
Set Equipment
Install Lights, Power, F ire Alarm & Security
MEP Rough-In & Hookups
Sequence #2
Foundations & Structure
Building Grade Beams, Footings & Walls
Install 5" PVC Ducts, Dampproofing, Insulation & Backfill Walls
Building Underground Utilities
Form, Rebar & Place SOG
SOG Sealer
Erect Structural Steel, Monorail, Decking & Detailing
Structure Complete
Exterior Skin
Install Parapet, Roofing & Skylights
Install Metal Panels & Curtainwall
Install Waveguide Steel Carrier
Interior
Paint Structural Steel & Concrete
MEP / FP Overhead Rough-In
Form & Place Equipment Pads
Actual WorkRemaining WorkCritical Remaining WorkMilestoneSummaryHigh Bay, Linac Tunnel & Linac Gallery
Fermilab Proton Improvement Plan - II 18.04.27
HIGH BAY BUILDING, LINAC TUNNEL, LINAC GALLERY,
BEAM TRANSFER LINE & BOOSTER CONNECTION
Page 5 of 10
| Fermilab PIP II VE Report76
Activity ID Activity Name OriginalDuration
Start Finish TotalFloat
GAL-INT2-1300 Paint MEP / FP Piping 10 09-Oct-18 22-Oct-18 65
GAL-INT2-1400 Set Equipment 15 23-Oct-18 12-Nov-18 50
GAL-INT2-1500 Install Lights, Power, F ire Alarm & Security 20 23-Oct-18 19-Nov-18 75
GAL-INT2-1600 MEP Rough-In & Hookups 30 13-Nov-18 28-Dec-18 50
Sequence #3Sequence #3 248 12-Feb-18 04-Feb-19 105
Foundations & StructureFoundations & Structure 123 12-Feb-18 03-Aug-18 25
GAL-F&S3-1000 Side Ais le & Stai r #3 60 12-Feb-18 04-May-18 15
GAL-F&S3-1100 Building Grade Beams, Footings & Walls 25 23-Apr-18 25-May-18 0
GAL-F&S3-1200 Install 5" PVC Ducts, Dampproofing, Insulation & Backfill Walls 20 14-May-18 11-Jun-18 43
GAL-F&S3-1300 Building Underground Utilities 20 29-May-18 25-Jun-18 25
GAL-F&S3-1400 Form, Rebar & Place SOG 5 26-Jun-18 02-Jul-18 25
GAL-F&S3-1500 SOG Sealer 3 03-Jul-18 06-Jul-18 25
GAL-F&S3-1600 Erect Structural Steel, Monorail, Decking & Detailing 20 09-Jul-18 03-Aug-18 25
GAL-F&S3-1700 Structure Complete 0 03-Aug-18 25
Exterior SkinExterior Skin 40 06-Aug-18 01-Oct-18 190
GAL-EXT3-1000 Install Parapet, Roofing & Skylights 20 06-Aug-18 31-Aug-18 25
GAL-EXT3-1100 Install Metal Panels & Curtainwall 30 06-Aug-18 17-Sep-18 55
GAL-EXT3-1200 Install Overhead Door 5 27-Aug-18 31-Aug-18 210
GAL-EXT3-1300 Install Waveguide Steel Carrier 10 18-Sep-18 01-Oct-18 55
InteriorInterior 105 04-Sep-18 04-Feb-19 25
GAL-INT3-1000 Paint Structural Steel & Concrete 10 04-Sep-18 17-Sep-18 25
GAL-INT3-1100 MEP / FP Overhead Rough-In 40 18-Sep-18 12-Nov-18 25
GAL-INT3-1200 Form & Place Equipment Pads 10 13-Nov-18 28-Nov-18 25
GAL-INT3-1300 Paint MEP / FP Piping 10 13-Nov-18 28-Nov-18 40
GAL-INT3-1400 Set Equipment 15 29-Nov-18 19-Dec-18 25
GAL-INT3-1500 Install Lights, Power, F ire Alarm & Security 20 29-Nov-18 28-Dec-18 50
GAL-INT3-1600 MEP Rough-In & Hookups 30 20-Dec-18 04-Feb-19 25
Sequence #4Sequence #4 198 29-May-18 11-Mar-19 80
Foundations & StructureFoundations & Structure 73 29-May-18 10-Sep-18 0
GAL-F&S4-1000 Building Grade Beams, Footings & Walls 25 29-May-18 02-Jul-18 0
GAL-F&S4-1100 Install 5" PVC Ducts, Dampproofing, Insulation & Backfill Walls 20 19-Jun-18 17-Jul-18 18
GAL-F&S4-1200 Building Underground Utilities 20 03-Jul-18 31-Jul-18 0
GAL-F&S4-1300 Form, Rebar & Place SOG 5 01-Aug-18 07-Aug-18 0
GAL-F&S4-1400 SOG Sealer 3 08-Aug-18 10-Aug-18 0
GAL-F&S4-1500 Erect Structural Steel, Monorail, Decking & Detailing 20 13-Aug-18 10-Sep-18 0
GAL-F&S4-1600 Structure Complete 0 10-Sep-18 0
Exterior SkinExterior Skin 40 11-Sep-18 05-Nov-18 165
GAL-EXT4-1000 Install Parapet, Roofing & Skylights 20 11-Sep-18 08-Oct-18 0
GAL-EXT4-1100 Install Metal Panels & Curtainwall 30 11-Sep-18 22-Oct-18 30
GAL-EXT4-1200 Install Overhead Door 5 02-Oct-18 08-Oct-18 185
GAL-EXT4-1300 Install Waveguide Steel Carrier 10 23-Oct-18 05-Nov-18 30
InteriorInterior 105 09-Oct-18 11-Mar-19 0
M Jun Jul A S Oct N Dec Jan F Mar Apr M Jun Jul Aug S Oct N D Jan F Mar Apr M Jun Jul A S Oct2017 2018 2019
Paint MEP / FP Piping
Set Equipment
Install Lights, Power, F ire Alarm & Security
MEP Rough-In & Hookups
Sequence #3
Foundations & Structure
Side Ais le & Stai r #3
Building Grade Beams, Footings & Walls
Install 5" PVC Ducts, Dampproofing, Insulation & Backfill Walls
Building Underground Utilities
Form, Rebar & Place SOG
SOG Sealer
Erect Structural Steel, Monorail, Decking & Detailing
Structure Complete
Exterior Skin
Install Parapet, Roofing & Skylights
Install Metal Panels & Curtainwall
Install Overhead Door
Install Waveguide Steel Carrier
Interior
Paint Structural Steel & Concrete
MEP / FP Overhead Rough-In
Form & Place Equipment Pads
Paint MEP / FP Piping
Set Equipment
Install Lights, Power, F ire Alarm & Security
MEP Rough-In & Hookups
Sequence #4
Foundations & Structure
Building Grade Beams, Footings & Walls
Install 5" PVC Ducts, Dampproofing, Insulation & Backfill Walls
Building Underground Utilities
Form, Rebar & Place SOG
SOG Sealer
Erect Structural Steel, Monorail, Decking & Detailing
Structure Complete
Exterior Skin
Install Parapet, Roofing & Skylights
Install Metal Panels & Curtainwall
Install Overhead Door
Install Waveguide Steel Carrier
Interior
Actual WorkRemaining WorkCritical Remaining WorkMilestoneSummaryHigh Bay, Linac Tunnel & Linac Gallery
Fermilab Proton Improvement Plan - II 18.04.27
HIGH BAY BUILDING, LINAC TUNNEL, LINAC GALLERY,
BEAM TRANSFER LINE & BOOSTER CONNECTION
Page 6 of 10
| Fermilab PIP II VE Report77
Activity ID Activity Name OriginalDuration
Start Finish TotalFloat
GAL-INT4-1000 Paint Structural Steel & Concrete 10 09-Oct-18 22-Oct-18 0
GAL-INT4-1100 MEP / FP Overhead Rough-In 40 23-Oct-18 19-Dec-18 0
GAL-INT4-1200 Form & Place Equipment Pads 10 20-Dec-18 07-Jan-19 0
GAL-INT4-1300 Paint MEP / FP Piping 10 20-Dec-18 07-Jan-19 15
GAL-INT4-1400 Set Equipment 15 08-Jan-19 28-Jan-19 0
GAL-INT4-1500 Install Lights, Power, F ire Alarm & Security 20 08-Jan-19 04-Feb-19 25
GAL-INT4-1600 MEP Rough-In & Hookups 30 29-Jan-19 11-Mar-19 0
Exterior EquipmentExterior Equipment 130 24-May-18 28-Nov-18 70
Sequence #1Sequence #1 65 24-May-18 24-Aug-18 135
GAL-EQ1-1000 Site Utilities 20 24-May-18 21-Jun-18 135
GAL-EQ1-1100 Form, Rebar & Place Transformer & Generator Pad 20 22-Jun-18 20-Jul-18 135
GAL-EQ1-1200 Set Transformers & Generator 5 23-Jul-18 27-Jul-18 135
GAL-EQ1-1300 Transformers & Generator Electrical Rough-In and Pull & Terminate Wire 20 30-Jul-18 24-Aug-18 135
Sequence #2Sequence #2 80 06-Aug-18 28-Nov-18 70
GAL-EQ2-1000 Site Utilities 30 06-Aug-18 17-Sep-18 60
GAL-EQ2-1100 Form, Rebar & Place Transformer & Generator Pad 25 18-Sep-18 22-Oct-18 70
GAL-EQ2-1200 Set Transformers 5 23-Oct-18 29-Oct-18 70
GAL-EQ2-1300 Transformers Electrical Rough-In and Pull & Terminate Wire 20 30-Oct-18 28-Nov-18 70
SiteworkSitework 113 03-Jul-18 12-Dec-18 60
GAL-SITE-1000 Form, Rebar & Place Retaining Walls 40 03-Jul-18 28-Aug-18 73
GAL-SITE-1100 Cut Roadways to Subgrade 10 18-Sep-18 01-Oct-18 60
GAL-SITE-1200 Install Berms 30 18-Sep-18 29-Oct-18 60
GAL-SITE-1300 Install Stone Sub & Aggregate Base 10 02-Oct-18 15-Oct-18 60
GAL-SITE-1400 Install Light Poles 10 16-Oct-18 29-Oct-18 60
GAL-SITE-1500 Remove Erosion Controls & Landscaping 25 30-Oct-18 05-Dec-18 60
GAL-SITE-1600 Asphalt Paving 5 06-Dec-18 12-Dec-18 60
Beam Transfer LineBeam Transfer Line 315 26-Sep-17 21-Dec-18 133
Sequence #1Sequence #1 95 12-Mar-18 24-Jul-18 158
Foundations & TunnelFoundations & Tunnel 60 12-Mar-18 04-Jun-18 143
BEAM-F&S1-1000 ***Excavate Tunnel 15 12-Mar-18 30-Mar-18 38
BEAM-F&S1-1100 Pour 3" Mud Slab 10 19-Mar-18 30-Mar-18 68
BEAM-F&S1-1200 Form, Rebar & Place Base Slab, Walls & Roof with Inserts & Sealer 30 02-Apr-18 11-May-18 68
BEAM-F&S1-1300 Install Underdrain, Dampproofing, PVC Ducts & Backfill Foundation Walls 20 23-Apr-18 18-May-18 143
BEAM-F&S1-1400 Backfill to Grade 20 07-May-18 04-Jun-18 143
InteriorInterior 50 14-May-18 24-Jul-18 158
BEAM-INT1-1000 Rub & Patch Concrete Walls 10 14-May-18 25-May-18 158
BEAM-INT1-1100 Paint Tunnel Walls & Roof 10 29-May-18 11-Jun-18 158
BEAM-INT1-1200 Fire Alarm, Cable Tray, Power & Lighting 30 12-Jun-18 24-Jul-18 158
BEAM-INT1-1300 Enclosure Air Barr ier 5 11-Jul-18 17-Jul-18 158
Sequence #2Sequence #2 225 26-Sep-17 14-Aug-18 143
Foundations & TunnelFoundations & Tunnel 190 26-Sep-17 25-Jun-18 128
BEAM-F&S2-1000 Install E/WRS 10 26-Sep-17 09-Oct-17 193
M Jun Jul A S Oct N Dec Jan F Mar Apr M Jun Jul Aug S Oct N D Jan F Mar Apr M Jun Jul A S Oct2017 2018 2019
Paint Structural Steel & Concrete
MEP / FP Overhead Rough-In
Form & Place Equipment Pads
Paint MEP / FP Piping
Set Equipment
Install Lights, Power, F ire Alarm & Security
MEP Rough-In & Hookups
Exterior Equipment
Sequence #1
Site Utilities
Form, Rebar & Place Transformer & Generator Pad
Set Transformers & Generator
Transformers & Generator Electrical Rough-In and Pull & Terminate Wire
Sequence #2
Site Utilities
Form, Rebar & Place Transformer & Generator Pad
Set Transformers
Transformers Electrical Rough-In and Pull & Terminate Wire
Sitework
Form, Rebar & Place Retaining Walls
Cut Roadways to Subgrade
Install Berms
Install Stone Sub & Aggregate Base
Install Light Poles
Remove Erosion Controls & Landscaping
Asphalt Paving
Beam Trans fer Line
Sequence #1
Foundations & Tunnel
***Excavate Tunnel
Pour 3" Mud Slab
Form, Rebar & Place Base Slab, Walls & Roof with Inserts & Sealer
Install Underdrain, Dampproofing, PVC Ducts & Backfill Foundation Walls
Backfill to Grade
Interior
Rub & Patch Concrete Walls
Paint Tunnel Walls & Roof
Fire Alarm, Cable Tray, Power & Lighting
Enclosure Air Barr ier
Sequence #2
Foundations & Tunnel
Install E/WRS
Actual WorkRemaining WorkCritical Remaining WorkMilestoneSummaryHigh Bay, Linac Tunnel & Linac Gallery
Fermilab Proton Improvement Plan - II 18.04.27
HIGH BAY BUILDING, LINAC TUNNEL, LINAC GALLERY,
BEAM TRANSFER LINE & BOOSTER CONNECTION
Page 7 of 10
| Fermilab PIP II VE Report78
Activity ID Activity Name OriginalDuration
Start Finish TotalFloat
BEAM-F&S2-1100 Install Box Culvert 20 10-Oct-17 06-Nov-17 193
BEAM-F&S2-1200 Excavate Tunnel 15 02-Apr-18 20-Apr-18 38
BEAM-F&S2-1300 Pour 3" Mud Slab 10 09-Apr-18 20-Apr-18 68
BEAM-F&S2-1400 Form, Rebar & Place Base Slab, Walls & Roof with Inserts & Sealer 30 23-Apr-18 04-Jun-18 68
BEAM-F&S2-1500 Install Underdrain, Dampproofing & Backfill Foundation Walls 20 14-May-18 11-Jun-18 128
BEAM-F&S2-1600 Install Road Shielding w/ Sand, Backfill to Grade & Restore PIP II Road 20 29-May-18 25-Jun-18 128
InteriorInterior 50 05-Jun-18 14-Aug-18 143
BEAM-INT2-1000 Rub & Patch Concrete Walls 10 05-Jun-18 18-Jun-18 143
BEAM-INT2-1100 Paint Tunnel Walls & Roof 10 19-Jun-18 02-Jul-18 143
BEAM-INT2-1200 Fire Alarm, Cable Tray, Power & Lighting 30 03-Jul-18 14-Aug-18 143
Sequence #3Sequence #3 150 23-Apr-18 21-Nov-18 153
Foundations & TunnelFoundations & Tunnel 135 23-Apr-18 31-Oct-18 168
BEAM-F&S3-1000 Excavate Tunnel 30 23-Apr-18 04-Jun-18 38
BEAM-F&S3-1100 Pour 3" Mud Slab 20 07-May-18 04-Jun-18 53
BEAM-F&S3-1200 Demo Main Ring 20 05-Jun-18 02-Jul-18 63
BEAM-F&S3-1300 Form, Rebar & Place Base Slab, Walls Roof with Inserts, Abort, Main Ring, Stair #7 & Sealer 70 05-Jun-18 12-Sep-18 53
BEAM-F&S3-1400 Install Underdrain, Dampproofing & Backfill Foundation Walls 55 03-Jul-18 19-Sep-18 58
BEAM-F&S3-1500 Install Road Shielding w/ Sand, Backfill to Grade & Restore Main Ring Road 55 18-Jul-18 03-Oct-18 58
BEAM-F&S3-1600 Set Abort Steel 5 01-Aug-18 07-Aug-18 228
BEAM-F&S3-1700 Stair #7 Enclosure 30 20-Sep-18 31-Oct-18 88
InteriorInterior 50 13-Sep-18 21-Nov-18 73
BEAM-INT3-1000 Rub & Patch Concrete Walls 10 13-Sep-18 26-Sep-18 73
BEAM-INT3-1100 Paint Tunnel Walls & Roof 10 27-Sep-18 10-Oct-18 73
BEAM-INT3-1200 Fire Alarm, Cable Tray, Power & Lighting 30 11-Oct-18 21-Nov-18 73
BEAM-INT3-1300 Gate Access Controls 10 08-Nov-18 21-Nov-18 73
Sequence #4Sequence #4 140 05-Jun-18 21-Dec-18 53
Foundations & TunnelFoundations & Tunnel 120 05-Jun-18 21-Nov-18 73
BEAM-F&S4-1000 Excavate Tunnel 15 05-Jun-18 25-Jun-18 38
BEAM-F&S4-1100 Pour 3" Mud Slab 10 12-Jun-18 25-Jun-18 98
BEAM-F&S4-1200 Form, Rebar & Place Base Slab, Walls & Roof with Inserts, Stair #8 & Sealer 30 29-Aug-18 10-Oct-18 53
BEAM-F&S4-1300 Install Underdrain, Dampproofing & Backfill Foundation Walls 20 13-Sep-18 10-Oct-18 63
BEAM-F&S4-1400 Install Road Shielding w/ Sand & Backfill to Grade 20 27-Sep-18 24-Oct-18 63
BEAM-F&S4-1500 Stair #8 Enclosure 30 11-Oct-18 21-Nov-18 73
InteriorInterior 50 11-Oct-18 21-Dec-18 53
BEAM-INT4-1000 Rub & Patch Concrete Walls 10 11-Oct-18 24-Oct-18 53
BEAM-INT4-1100 Paint Tunnel Walls & Roof 10 25-Oct-18 07-Nov-18 53
BEAM-INT4-1200 Fire Alarm, Cable Tray, Power & Lighting 30 08-Nov-18 21-Dec-18 53
SiteworkSitework 50 04-Oct-18 14-Dec-18 58
BEAM-SITE-1000 Rough & Fine Grading 25 04-Oct-18 07-Nov-18 58
BEAM-SITE-1100 Remove Erosion Controls & Landscaping 25 08-Nov-18 14-Dec-18 58
Booster ConnectionBooster Connection 275 22-Jan-18 20-Feb-19 93
SE Booster BuildingSE Booster Building 275 22-Jan-18 20-Feb-19 93
M Jun Jul A S Oct N Dec Jan F Mar Apr M Jun Jul Aug S Oct N D Jan F Mar Apr M Jun Jul A S Oct2017 2018 2019
Install Box Culvert
Excavate Tunnel
Pour 3" Mud Slab
Form, Rebar & Place Base Slab, Walls & Roof with Inserts & Sealer
Install Underdrain, Dampproofing & Backfill Foundation Walls
Install Road Shielding w/ Sand, Backfill to Grade & Restore PIP II Road
Interior
Rub & Patch Concrete Walls
Paint Tunnel Walls & Roof
Fire Alarm, Cable Tray, Power & Lighting
Sequence #3
Foundations & Tunnel
Excavate Tunnel
Pour 3" Mud Slab
Demo Main Ring
Form, Rebar & Place Base Slab, Walls Roof with Inserts, Abort, Main Ring, Stair #7 & Sealer
Install Underdrain, Dampproofing & Backfill Foundation Walls
Install Road Shielding w/ Sand, Backfill to Grade & Restore Main Ring Road
Set Abort Steel
Stair #7 Enclosure
Interior
Rub & Patch Concrete Walls
Paint Tunnel Walls & Roof
Fire Alarm, Cable Tray, Power & Lighting
Gate Access Controls
Sequence #4
Foundations & Tunnel
Excavate Tunnel
Pour 3" Mud Slab
Form, Rebar & Place Base Slab, Walls & Roof with Inserts, Stair #8 & Sealer
Install Underdrain, Dampproofing & Backfill Foundation Walls
Install Road Shielding w/ Sand & Backfill to Grade
Stair #8 Enclosure
Interior
Rub & Patch Concrete Walls
Paint Tunnel Walls & Roof
Fire Alarm, Cable Tray, Power & Lighting
Sitework
Rough & Fine Grading
Remove Erosion Controls & Landscaping
Booster Connection
SE Booster Building
Actual WorkRemaining WorkCritical Remaining WorkMilestoneSummaryHigh Bay, Linac Tunnel & Linac Gallery
Fermilab Proton Improvement Plan - II 18.04.27
HIGH BAY BUILDING, LINAC TUNNEL, LINAC GALLERY,
BEAM TRANSFER LINE & BOOSTER CONNECTION
Page 8 of 10
| Fermilab PIP II VE Report79
Activity ID Activity Name OriginalDuration
Start Finish TotalFloat
BOOST-BLDG-1000 ***Temporary Partitions, New Overhead Door & Remove Precast Shielding Blocks 10 22-Jan-18 02-Feb-18 73
BOOST-BLDG-1100 Remove / Demo Existing Areas , incl uding Toilet & HVAC Equipment 10 05-Feb-18 16-Feb-18 73
BOOST-BLDG-1200 Sawcut & Remove Existing Slab 5 19-Feb-18 23-Feb-18 73
BOOST-BLDG-1300 Micropiles & ERS 40 26-Feb-18 20-Apr-18 73
BOOST-BLDG-1400 Pile Caps & Grade Beams 10 23-Apr-18 04-May-18 73
BOOST-BLDG-1500 Prep & Place SOG 10 10-Dec-18 21-Dec-18 93
BOOST-BLDG-1600 Existing Areas Repai r / Buildout 40 26-Dec-18 20-Feb-19 93
BOOST-BLDG-1700 Window Replacement 10 03-Jan-19 16-Jan-19 118
Sequence #1Sequence #1 100 26-Jun-18 14-Nov-18 158
Foundations & TunnelFoundations & Tunnel 65 26-Jun-18 26-Sep-18 193
BOOST-F&S1-1000 ***Start Excavation 0 26-Jun-18 38
BOOST-F&S1-1100 Excavate Tunnel 15 26-Jun-18 17-Jul-18 38
BOOST-F&S1-1200 Pour 3" Mud Slab 10 03-Jul-18 17-Jul-18 38
BOOST-F&S1-1300 Form, Rebar & Place Base Slab, and Walls & Roof with Inserts & Sealer 30 25-Jul-18 05-Sep-18 38
BOOST-F&S1-1400 Install Underdrain, Dampproofing & Backfill Foundation Walls 20 15-Aug-18 12-Sep-18 193
BOOST-F&S1-1500 Backfill to Grade 20 29-Aug-18 26-Sep-18 193
InteriorInterior 50 06-Sep-18 14-Nov-18 78
BOOST- INT1-1000 Rub & Patch Concrete Walls 10 06-Sep-18 19-Sep-18 78
BOOST- INT1-1100 Paint Tunnel Walls & Roof 10 20-Sep-18 03-Oct-18 78
BOOST- INT1-1200 Fire Alarm, Cable Tray, Power & Lighting 30 04-Oct-18 14-Nov-18 78
Sequence #2Sequence #2 125 18-Jul-18 16-Jan-19 118
Foundations & TunnelFoundations & Tunnel 115 18-Jul-18 02-Jan-19 128
BOOST-F&S2-1000 Excavate Tunnel 25 18-Jul-18 21-Aug-18 48
BOOST-F&S2-1100 Pour 3" Mud Slab 20 25-Jul-18 21-Aug-18 218
BOOST-F&S2-1200 Interior Shoring, Demo Existing Enclosure Wall & Stair #3, and Cap & Cut Piping 10 22-Aug-18 05-Sep-18 48
BOOST-F&S2-1300 Form, Rebar & Place Base Slab, and Walls & Roof with Inserts, Stair #9 / Exit Passage & Sealer 50 22-Aug-18 31-Oct-18 38
BOOST-F&S2-1400 Micropiles 5 06-Sep-18 12-Sep-18 48
BOOST-F&S2-1500 Form, Rebar & Place Grade Beam 5 13-Sep-18 19-Sep-18 48
BOOST-F&S2-1600 Install Underdrain, Dampproofing, PVC Ducts & Backfill Foundation Walls 30 27-Sep-18 07-Nov-18 48
BOOST-F&S2-1700 Install Road Shielding w/ Sand, Flowable Fill, & Backfill to Grade 30 25-Oct-18 07-Dec-18 48
BOOST-F&S2-1800 Stair #9 Enclosure 30 15-Nov-18 02-Jan-19 48
BOOST-F&S2-1900 Conventional Construction Completed - Ready to Start Technical Component Installation 0 07-Dec-18 143
InteriorInterior 50 01-Nov-18 16-Jan-19 38
BOOST- INT2-1000 Rub & Patch Concrete Walls 10 01-Nov-18 14-Nov-18 38
BOOST- INT2-1100 Paint Tunnel Walls & Roof 10 15-Nov-18 30-Nov-18 38
BOOST- INT2-1200 Fire Alarm, Cable Tray, Power & Lighting 30 03-Dec-18 16-Jan-19 38
SiteworkSitework 40 10-Dec-18 06-Feb-19 103
BOOST-SITE-1000 Restore South Booster Road & Parking Lot 15 10-Dec-18 02-Jan-19 103
BOOST-SITE-1100 Rough & Fine Grading 15 26-Dec-18 16-Jan-19 103
BOOST-SITE-1200 Remove Erosion Controls & Landscaping 15 17-Jan-19 06-Feb-19 103
CloseoutCloseout 233 01-Aug-18 02-Jul-19 0
HIGH-CLOSE-1000 Testing & Balancing - High Bay Building 20 01-Aug-18 28-Aug-18 153
M Jun Jul A S Oct N Dec Jan F Mar Apr M Jun Jul Aug S Oct N D Jan F Mar Apr M Jun Jul A S Oct2017 2018 2019
***Temporary Partitions, New Overhead Door & Remove Precast Shielding Blocks
Remove / Demo Existing Areas , incl uding Toilet & HVAC Equipment
Sawcut & Remove Existing Slab
Micropiles & ERS
Pile Caps & Grade Beams
Prep & Place SOG
Existing Areas Repai r / Buildout
Window Replacement
Sequence #1
Foundations & Tunnel
***Start Excavation
Excavate Tunnel
Pour 3" Mud Slab
Form, Rebar & Place Base Slab, and Walls & Roof with Inserts & Sealer
Install Underdrain, Dampproofing & Backfill Foundation Walls
Backfill to Grade
Interior
Rub & Patch Concrete Walls
Paint Tunnel Walls & Roof
Fire Alarm, Cable Tray, Power & Lighting
Sequence #2
Foundations & Tunnel
Excavate Tunnel
Pour 3" Mud Slab
Interior Shoring, Demo Existing Enclosure Wall & Stair #3, and Cap & Cut Piping
Form, Rebar & Place Base Slab, and Walls & Roof with Inserts, Stair #9 / Exit Passage & Sealer
Micropiles
Form, Rebar & Place Grade Beam
Install Underdrain, Dampproofing, PVC Ducts & Backfill Foundation Walls
Install Road Shielding w/ Sand, Flowable Fill, & Backfill to Grade
Stair #9 Enclosure
Conventional Construction Completed - Ready to Start Technical Component Installation
Interior
Rub & Patch Concrete Walls
Paint Tunnel Walls & Roof
Fire Alarm, Cable Tray, Power & Lighting
Sitework
Restore South Booster Road & Parking Lot
Rough & Fine Grading
Remove Erosion Controls & Landscaping
Closeout
Testing & Balancing - High Bay Building
Actual WorkRemaining WorkCritical Remaining WorkMilestoneSummaryHigh Bay, Linac Tunnel & Linac Gallery
Fermilab Proton Improvement Plan - II 18.04.27
HIGH BAY BUILDING, LINAC TUNNEL, LINAC GALLERY,
BEAM TRANSFER LINE & BOOSTER CONNECTION
Page 9 of 10
| Fermilab PIP II VE Report80
Activity ID Activity Name OriginalDuration
Start Finish TotalFloat
TUN-CLOSE-1000 Testing & Balancing - Linac Tunnel 20 01-Aug-18 28-Aug-18 153
BEAM-CLOSE-1000 Testing & Balancing - Beam Transport Line 20 26-Dec-18 23-Jan-19 53
BOOST-CLOSE-1000 Testing & Balancing - Booster Connection 20 17-Jan-19 13-Feb-19 38
HIGH-CLOSE-1100 Punchlist 20 12-Mar-19 08-Apr-19 0
GAL-CLOSE-1000 Testing & Balancing - Linac Gallery 20 12-Mar-19 08-Apr-19 0
HIGH-CLOSE-1200 Beneficial Occupancy 0 08-Apr-19 0
HIGH-CLOSE-1300 Project Closeout 60 09-Apr-19 02-Jul-19 0
HIGH-CLOSE-1400 Project Complete 0 02-Jul-19 0
M Jun Jul A S Oct N Dec Jan F Mar Apr M Jun Jul Aug S Oct N D Jan F Mar Apr M Jun Jul A S Oct2017 2018 2019
Testing & Balancing - Linac Tunnel
Testing & Balancing - Beam Transport Line
Testing & Balancing - Booster Connection
Punchlist
Testing & Balancing - Linac Gallery
Beneficial Occupancy
Project Closeout
Project Complete
Actual WorkRemaining WorkCritical Remaining WorkMilestoneSummaryHigh Bay, Linac Tunnel & Linac Gallery
Fermilab Proton Improvement Plan - II 18.04.27
HIGH BAY BUILDING, LINAC TUNNEL, LINAC GALLERY,
BEAM TRANSFER LINE & BOOSTER CONNECTION
Page 10 of 10
Activity ID Activity Name Original
Duration
Start Finish TotalFloat
Fermilab Proton Improvement Plan - IIFermilab Proton Improvement Plan - II 360 01-Jun-17 31-Oct-18 60
Booster ConnectionBooster Connection 360 01-Jun-17 31-Oct-18 60
PreconstructionPreconstruction 100 01-Jun-17 23-Oct-17 290
Contract AdministrationContract Administration 20 01-Jun-17 30-Jun-17 60
BOOST-CA-1000 Notice to Proceed - Booster Connection 0 01-Jun-17* 0
BOOST-CA-1100 Bonds & Insurance, Initial Engineering, Safey Plans & Permits 20 02-Jun-17 29-Jun-17 60
BOOST-CA-1200 Start Construction - Booster Connection 0 30-Jun-17 60
EngineeringEngineering 80 30-Jun-17 23-Oct-17 290
BOOST-ENGR-1000 Micropile & ERS Submittals & Fabrication 40 30-Jun-17 25-Aug-17 65
BOOST-ENGR-1100 Foundations & Concrete Submittals & Fabrication 40 30-Jun-17 25-Aug-17 105
BOOST-ENGR-1200 MEP Submittals & Coordination (BIM) 40 30-Jun-17 25-Aug-17 330
BOOST-ENGR-1300 OFCI Road Shielding Steel Submittals & Fabrication 80 30-Jun-17 23-Oct-17 160
ConstructionConstruction 260 30-Jun-17 10-Jul-18 140
MobilizationMobilization 30 30-Jun-17 11-Aug-17 125
BOOST-MOB-1000 Mobilize & Fencing 20 30-Jun-17 28-Jul-17 60
BOOST-MOB-1100 Grub & Strip Topsoil 10 31-Jul-17 11-Aug-17 125
SE Booster BuildingSE Booster Building 240 31-Jul-17 10-Jul-18 60
BOOST-BLDG-1000 Temporary Part it ions , New Overhead Door & Remove Precast Shielding Blocks 10 31-Jul-17 11-Aug-17 60
BOOST-BLDG-1100 Remove / Demo Existing Areas, including Toilet & HVAC Equipment 10 14-Aug-17 25-Aug-17 60
BOOST-BLDG-1200 Sawcut & Remove Existing Slab 5 28-Aug-17 01-Sep-17 60
BOOST-BLDG-1300 Micropiles & ERS 40 05-Sep-17 30-Oct-17 60
BOOST-BLDG-1400 Pile Caps & Grade Beams 10 31-Oct-17 13-Nov-17 60
BOOST-BLDG-1500 Prep & Place SOG 10 30-Apr-18 11-May-18 60
BOOST-BLDG-1600 Existing Areas Repair / Buildout 40 14-May-18 10-Jul-18 60
BOOST-BLDG-1700 Window Replacement 10 21-May-18 04-Jun-18 85
Sequence #1Sequence #1 100 14-Nov-17 06-Apr-18 205
Foundations & TunnelFoundations & Tunnel 65 14-Nov-17 16-Feb-18 240
BOOST-F&S1-1000 Start Excavation 0 14-Nov-17 60
BOOST-F&S1-1100 Excavate Tunnel 15 14-Nov-17 06-Dec-17 60
BOOST-F&S1-1200 Pour 3" Mud Slab 10 21-Nov-17 06-Dec-17 60
BOOST-F&S1-1300 Form, Rebar & Place Base Slab, and Walls & Roof with Inserts & Sealer 30 14-Dec-17 26-Jan-18 60
BOOST-F&S1-1400 Install Underdrain, Dampproofing & Backfill Foundation Walls 20 08-Jan-18 02-Feb-18 240
BOOST-F&S1-1500 Backfill to Grade 20 22-Jan-18 16-Feb-18 240
InteriorInterior 50 29-Jan-18 06-Apr-18 125
BOOST-INT1-1000 Rub & Patch Concrete Walls 10 29-Jan-18 09-Feb-18 125
BOOST-INT1-1100 Paint Tunnel Walls & Roof 10 12-Feb-18 23-Feb-18 125
BOOST-INT1-1200 Fire Alarm, Cable Tray, Power & Light ing 30 26-Feb-18 06-Apr-18 125
Sequence #2Sequence #2 125 07-Dec-17 04-Jun-18 165
Foundations & TunnelFoundations & Tunnel 115 07-Dec-17 18-May-18 175
BOOST-F&S2-1000 Excavate Tunnel 25 07-Dec-17 12-Jan-18 70
BOOST-F&S2-1100 Pour 3" Mud Slab 20 14-Dec-17 12-Jan-18 265
BOOST-F&S2-1200 Interior Shoring, Demo Existing Enclosure Wal l & Stair #3, and Cap & Cut Piping 10 15-Jan-18 26-Jan-18 70
BOOST-F&S2-1300 Form, Rebar & Place Base Slab, and Walls & Roof with Inserts, Stair #9 / Exit Passage & Sealer50 15-Jan-18 23-Mar-18 60
BOOST-F&S2-1400 Micropiles 5 29-Jan-18 02-Feb-18 70
BOOST-F&S2-1500 Form, Rebar & Place Grade Beam 5 05-Feb-18 09-Feb-18 70
BOOST-F&S2-1600 Install Underdrain, Dampproofing, PVC Ducts & Backfill Foundation Walls 30 19-Feb-18 30-Mar-18 60
BOOST-F&S2-1700 Install Road Shielding w/ Sand, Flowable Fill, & Backfill to Grade 30 19-Mar-18 27-Apr-18 60
BOOST-F&S2-1800 Stair #9 Enclosure 30 09-Apr-18 18-May-18 95
BOOST-F&S2-1900 Conventional Construction Completed - Ready to Start Technical Component Installation0 27-Apr-18 190
InteriorInterior 50 26-Mar-18 04-Jun-18 85
BOOST-INT2-1000 Rub & Patch Concrete Walls 10 26-Mar-18 06-Apr-18 85
BOOST-INT2-1100 Paint Tunnel Walls & Roof 10 09-Apr-18 20-Apr-18 85
BOOST-INT2-1200 Fire Alarm, Cable Tray, Power & Light ing 30 23-Apr-18 04-Jun-18 85
SiteworkSitework 40 30-Apr-18 25-Jun-18 70
BOOST-SITE-1000 Restore South Booster Road & Parking Lot 15 30-Apr-18 18-May-18 70
BOOST-SITE-1100 Rough & Fine Grading 15 14-May-18 04-Jun-18 70
BOOST-SITE-1200 Remove Erosion Controls & Landscaping 15 05-Jun-18 25-Jun-18 70
CloseoutCloseout 105 05-Jun-18 31-Oct-18 60
BOOST-CLOSE-1000 Test ing & Balanc ing 20 05-Jun-18 02-Jul-18 85
BOOST-CLOSE-1100 Punchlist 20 11-Jul-18 07-Aug-18 60
BOOST-CLOSE-1200 Beneficial Occupany - Booster Connection 0 07-Aug-18 60
BOOST-CLOSE-1300 Project Closeout 60 08-Aug-18 31-Oct-18 60
BOOST-CLOSE-1400 Project Complete - Booster Connection 0 31-Oct-18 60
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
2017 2018 2019
Fermilab Proton Improvement Plan - II
Booster Connection
Preconstruction
Contract Administration
Notice to Proceed - Booster Connection
Bonds & Insurance, Initial Engineering, Safey Plans & Permits
Start Construction - Booster Connection
Engineering
Micropile & ERS Submittals & Fabrication
Foundations & Concrete Submittals & Fabrication
MEP Submittals & Coordination (BIM)
OFCI Road Shielding Steel Submittals & Fabrication
Construction
Mobilization
Mobilize & Fencing
Grub & Strip Topsoil
SE Booster Building
Temporary Part it ions , New Overhead Door & Remove Precast Shielding Blocks
Remove / Demo Existing Areas, including Toilet & HVAC Equipment
Sawcut & Remove Existing Slab
Micropiles & ERS
Pile Caps & Grade Beams
Prep & Place SOG
Existing Areas Repair / Buildout
Window Replacement
Sequence #1
Foundations & Tunnel
Start Excavation
Excavate Tunnel
Pour 3" Mud Slab
Form, Rebar & Place Base Slab, and Walls & Roof with Inserts & Sealer
Install Underdrain, Dampproofing & Backfill Foundation Walls
Backfill to Grade
Interior
Rub & Patch Concrete Wal ls
Paint Tunnel Walls & Roof
Fire Alarm, Cable Tray, Power & Light ing
Sequence #2
Foundations & Tunnel
Excavate Tunnel
Pour 3" Mud Slab
Interior Shoring, Demo Existing Enclosure Wal l & Stair #3, and Cap & Cut Piping
Form, Rebar & Place Base Slab, and Walls & Roof with Inserts, Stair #9 / Exit Passage & Sealer
Micropiles
Form, Rebar & Place Grade Beam
Install Underdrain, Dampproofing, PVC Ducts & Backfill Foundation Wal ls
Install Road Shielding w/ Sand, Flowable Fill, & Backfill to Grade
Stair #9 Enclosure
Conventional Construction Completed - Ready to Start Technical Component Installation
Interior
Rub & Patch Concrete Walls
Paint Tunnel Walls & Roof
Fire Alarm, Cable Tray, Power & Light ing
Sitework
Restore South Booster Road & Parking Lot
Rough & Fine Grading
Remove Erosion Controls & Landscaping
Closeout
Test ing & Balanc ing
Punchlist
Beneficial Occupany - Booster Connection
Project Closeout
Project Complete - Booster Connection
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Fermilab BOOSTER
Fermilab Proton Improvement Plan - II - BOOSTER CONNECTION
Page 1 of 1