Date post: | 27-Nov-2023 |
Category: |
Documents |
Upload: | khangminh22 |
View: | 0 times |
Download: | 0 times |
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 1 of 58
EXECUTIVE SUMMARY ES-A Project Fact Sheet The Provincial Government of Samar proposes to develop a reclamation project in Barangay Mercedes, Catbalogan City. This project has an area of approximately 35 hectares. The Executive Summary briefly discusses the fundamentals of the proposed project including the Environmental Impact Assessment (EIA) process documentation and its key findings that are essential to the formulation of the Environmental Management Plan. Table ES - 1. Basic Project Information
Project Name Barangay Mercedes Reclamation Project Project Location Along the coastal waters of Barangay Mercedes,
Poblacion 3, Poblacion 4, and Poblacion 5, Catbalogan City, Samar
Project Classification per EMB MC 2014-005
Category A-1 (Reclamation Project)
Scope of the Project Horizontal development only (Note: separate ECCs will be applied for vertical development and for source of reclamation materials)
Summary of Project components 1. Land Mass 2. Coastal Dike and Drainage Improvement 3. Internal Road Network 4. Utilities
Project Area 35 hectares Project/Investment Cost PhP 328,445,099.93 Project Duration 15 months Profile of the Proponent Name of Proponent Provincial Government of Samar Address Provincial Capitol, Catbalogan City, Samar Authorized Signatory/Representative
Governor Reynolds Michael Tan
Contact Details Cellphone number: 0939 990 2021 E-mail: [email protected]
Profile of the Preparer EIA Preparer Engr. John Gilbert Gopez, EnP Address 27 Unit F, Mayaman St., UP Village, Quezon City, 1101 Contact Details Landline: (02) 247 3477
E-mail: [email protected] ES-B Process Documentation B.1. The EIA Team The Preparer’s field of expertise and the EIA module assigned to each member are shown on Table ES - 2.
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 2 of 58
Table ES - 2. EIA Team Members Team Member Field of Expertise/ Module IPCO No.
John Gilbert W. Gopez Team Leader / Water Quality Expert
Application with EMB Filed
Jean Ravelo Geologist / Land Application with EMB
Filed Emerson Darroles Oceanography /Water IPCO-153
Benjamin Francisco Marine and Freshwater Ecology Expert / Water
IPCO-038
Victor Pantaleon Coral Reef, Seagrass Expert / Water
Application with EMB Filed
Michael Francisco Fisheries / Water IPCO-040 Nazario Sabello Air Quality Expert / Air IPCO-240 Nadia Conde People Module Expert / People IPCO-102
B.2. EIA Study Schedule The activities undertaken and completed by the team as part of the preparation of EIS Report are detailed in Table ES - 3. Table ES - 3. Summary of EIA Study Schedule
Activity Date IEC Activities December 17-18, 2019, January
16, 2020, and February 27, 2020 Conduct of Perception Survey January 2021 Public Scoping May 10, 2021 Technical Scoping May 26, 2021 Secondary Data Gathering May 27 – June 15, 2021 Marine and Freshwater Ecology Survey June 4-7, 2021 Water Quality and ambient Air and Noise Sampling and Testing
June 10-16, 2021
Oceanographic Survey and Coastal Modeling Study June 11-13, 2021 Conduct of Geotechnical Investigation June 16-22, 2021 Preparation of EIS June 16-29, 2021
B.3. EIA Study Area The Study Area is where the Reclamation Project is expected to be constructed in Barangays Mercedes, Poblacion 3, Poblacion 4 and Poblacion 5, Catbalogan City, and neighboring barangays that is expected to have a direct and indirect impact from the project.
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 3 of 58
B.4. EIA Methodology The approach and methodology undertaken to prepare this EIS Report is in accordance with the prescribed methods and procedural manual (DAO 2003-30) mandated by the DENR-Environmental Management Bureau. Table ES - 4 provides the methodology used for each module. Table ES - 4. The EIA Methodology
Environmental Components Methodology and Approach on Baseline Survey Methodology and Approach on Impact Assessment
Land Land Use and Classification
• The updated Comprehensive Land Use Plan (CLUP) of Catbalogan City will be main source of information on land use and land compatibility. The preparers will secure map showing the project area in relation to existing land use.
• Identify areas vulnerable/susceptible to natural hazards where the project is located or near the project area (include map/s).
• Coordinate with relevant government agencies (i.e. NCIP, DAR, DENR, BFAR, MGB) to determine if the project area is under CARP or with CADC / CADT / CALC/ CALT, with IFMA/CBFMA, within COC, within MPSA or other tenurial instruments and identify corresponding existing tenure issues including presence of informal settlers.
• Discuss the project and secure clearances from the Bureau of Fisheries and Aquatic Resources (BFAR), Department of Public Works and Highways (DPWH), Department of Tourism (DOT), Philippine Ports Authority (PPA), and Philippine Reclamation Authority (PRA)
• Assessment of the compatibility of the proposed project vis-a-vis actual land use and the approved comprehensive land use plan/zoning classification, ECA Classification and/or the coastal resource management plan of the LGU if any.
• Identify and assess impact in terms of land tenure issues in relation to project implementation
• Identify and assess impact of the project on these visually significant landforms / landscape / structures
• Identify and assess impacts of the estimated generation of solid wastes in terms of amount and characteristics (hazardous or domestic).
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 4 of 58
Environmental Components Methodology and Approach on Baseline Survey Methodology and Approach on Impact Assessment
• Secure the updated Ecological Solid Waste Management Plan of Catbalogan City to determine existing solid waste management.
Geology • The consultant will conduct geotechnical investigation to determine the soil engineering and geotechnical properties of the project site.
• The slope map will be sourced from the CLUP while and bathymetric map will be generated based on the bathymetry survey.
• Regional/General Geological Map Natural Hazard Map will be secured from NAMRIA, NDRRMC, MGB, PHIVOLCS, PAGASA.
• The following maps will also be provided: 1. Storm Surge Hazard Map 2. Tsunami Hazard Map 3. Earthquake generators 4. Ground shaking
• Identify and assess project impact in terms of the changes in surface landform / topography / terrain / slope /bathymetry including existing hazard as maybe aggravated by climate change as projected by PAGASA
• Identify and assess project impact in terms of the changes in sub-surface geology and inducement of subsidence, liquefaction, landslides, mud/debris flow to the environment including the possibility of aggravating existing natural hazards
• Discuss and assess the impacts of geologic hazards and planned earthworks on the project facilities.
• Discuss the potential impacts of these hazards and include proposed mitigation measures.
Pedology • Summary of Soil Investigation Report on soil type and quality
• Soil map showing soil types, sampling stations, topography, streams, built-up areas, and planned project features
• Water and wind erodibility potential • Sediment sources, and • Riverbank stability • Laboratory results on soil sample analysis for N, P,
K, pH, organic matter, micronutrients and trace metals e. g. Pb, Hg, As, Cd, Cr hexavalent, etc.
• Describe capability of the land to accommodate the proposed development with minimal or without soil erosion/loss of topsoil/overburden
• Describe the physical properties and erodibility potential of the soil, ongoing erosion processes and assess the erosional impacts of the project. The Universal Soil Loss Equation (USLE) and its variants may be used in the modeling.
• Assess the impact of the project activities including the possibility of spills on soil quality and fertility
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 5 of 58
Environmental Components Methodology and Approach on Baseline Survey Methodology and Approach on Impact Assessment
Terrestrial Ecology • Map showing land cover; sampling sites; location of observed important, endangered, and keystone species; ecologically sensitive sites; planned land development works
• Flora and fauna species inventory or survey report to cover species listing, abundance, richness, dominance, diversity, evenness, ecological status, and uses
• Loss of species – Of special interest are the keystone, endangered, and endemic species.
• Pollution effects on species – The stressors include dust, noise, chemical/ petrochemical spills, eroded sediment, increased temperature, etc.
• Relate discussions to estimated GHG emissions and possible carbon sequestration program/s
• Water Hydrology & Hydrogeology
• Drainage map (also showing local drainage system/infrastructures);
• Historical flooding/drought occurrences, stream flow measurements/estimates;
• Delineation of watershed /sub watersheds/ floodplain; and identification of aquifers if any
• Regional hydrogeological map
• Identify and assess project impact on the change in drainage morphology/local drainage system and resulting effects of flooding pattern in the project area and surrounding. Include climate projections effects on flooding.
• Identify and assess project impact in terms of change in stream, lake water depth.
Oceanography • Bathymetric survey and map • Measurement of water currents • Hydrodynamic modeling • Particle dispersion modeling • Storm surge hazard, exposure, • vulnerability, risk maps
• Assess based on cumulative impacts with Pier Uno to Brgy. Bunuanan Reclamation Project
• Identify and assess project impact on the degree of change/disruption of circulation pattern and the potential for coastal erosion
• Build a hydrodynamic model based on the measured bathymetry and currents and tidal analysis and then validate the model.
• Use the hydrodynamic model to assess the impacts of the bathymetric changes. Discuss how the impacts may be affected by climate change. Compare projected new bathymetry as a result of the project with the existing.
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 6 of 58
Environmental Components Methodology and Approach on Baseline Survey Methodology and Approach on Impact Assessment
Water Quality • Water quality sampling and testing will be employed by the EIA preparer through the engagement of an EMB-accredited laboratory. The sampling stations should be outside the area to be reclaimed. The following water quality parameters will be tested: Color, DO, Fecal Coliform, Nitrate, pH, Phosphate, Temperature, TSS, Ammonia, Boron, Fluoride, Selenium, Sulfate, Arsenic, Barium, and Cadmium
• Identify and assess project impact in terms of degradation of groundwater, coastal surface water and coastal/marine water quality. Use DENR standard methods and procedures for sampling and analysis.
• Assess impact on siltation of surface and coastal/marine waters.
Freshwater Biology • Summary of endemicity / conservation status • Abundance of ecologically and economically
important species (fishes, benthos, planktons); • Presence of pollution indicator species;
• Identify and assess project impact in terms of threats to existence/and or loss of species, abundance frequency and distribution species and include discussions on overall impact to freshwater ecology.
Marine Biology • Abundance/densities/distribution of ecologically and economically important species (mangroves, fishes, benthos, planktons, coral reefs, algae, seaweeds, sea grasses);
• Quadrat, transect, line intercept, spot dive, manta tow, marine resource characterization (e.g. municipal and commercial fisheries data) for baseline gathering.
• Conduct interview with key stakeholders to validate results of the data gathering and assessment.
• Identify and assess project impact in terms of threats to existence, loss of important local species, threat to abundance, frequency and distribution and include discussions on overall impact to marine ecology. Relate discussions to air, water and oceanography
• Use BMB Technical Bulletin 2017- 05 and 2019-04 as guide for the assessment
• Map showing the area to be reclaimed and coastal resources (mangroves, seagrasses and coral reef areas) inside and on the areas surrounding the area to be reclaimed.
Air Meteorology/ Climatology
• Data from PAGASA like the monthly average rainfall and temperature in Catbalogan will be ;
• Identify and assess project impact in terms of change in the local micro- climate change. Also discuss effects of
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 7 of 58
Environmental Components Methodology and Approach on Baseline Survey Methodology and Approach on Impact Assessment
Climatological Normal/extremes; Wind rose diagrams;
• Frequency of Tropical cyclones • Data on Greenhouse gasses (i.e. carbon dioxide,
nitrous oxide);
climate change using PAGASA medium to long term projections
• Estimate projected greenhouse gases (GHG) (i.e. carbon dioxide, nitrous oxide) using IPCC guidelines; include mitigation and/or sequestration for both construction and operation phases.
Air Quality • Ambient air quality sampling and testing will be employed by the EIA preparer through the engagement of an EMB-accredited laboratory. Two (2) additional sampling stations will be identified to measure the air quality where the trucks will haul the embankment materials from the source of fill going to the reclamation area. The TSP, PM10, SOx, and NOx will be sampled and tested.
• Use DENR standard methods and procedures for sampling and analysis.
Noise • Ambient noise sampling will be employed by the EIA preparer through the engagement of an EMB-accredited laboratory. Two (2) additional sampling stations will be identified to measure the ambient noise level where the trucks will haul the embankment materials from the source of fill going to the reclamation area.
• Use DENR standard methods and procedures for sampling and measurement.
• Conduct rapid assessment for noise
• People Demography • Latest demographic data on the impact area such as
number of households and household size, land area, population, population density /growth, gender and age profile, literacy rate, profile of educational attainment, settlements map will be
• Identify and assess project impacts on demography of affected communities. Use assessment in the formulation of Social Development Plan/IEC
• Assess availability of alternative public access and housing options for displaced settlers
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 8 of 58
Environmental Components Methodology and Approach on Baseline Survey Methodology and Approach on Impact Assessment
sourced out from City Planning and Development Office (CPDO)
• Census of population / property that will be displaced / disturbed
• Housing ownership profile / availability of housing/ number of informal settlers
• For project with displacement/ disturbance of properties/settlers, change/conflict in land ownership and change/conflict right of way, formulate resettlement framework plan or RAP
• Identify and assess project impact due to in-migration patterns including proliferation of informal settlers
Indigenous People • Demographic data on Indigenous People (if any) and existing Culture/Lifestyle that may be significantly affected
• Identity and assess project impact in terms of Culture/Lifestyle that may be affected and/or introduced
Historical and Cultural Heritage
• Inventory and description of physical cultural resources and landscapes that have archaeologic, palaeontologic, historical, religious, aesthetic, or cultural significance.
• Identify all potential project impacts in an integrated manner considering the type, significance, and value/importance of the physical cultural resource/s
Basic Infrastructure and Services
• Availability of public services (water supply, power supply, and communications /transportation
• Peace and order / crime • Statistical data / information related to public
services
• Identify and assess project impact in terms of threats to delivery of basic services including potential for resource competition in the area including effects of in-migration
Environmental Health and Sanitation Profile
• Availability of public services in terms of: health resources (Government and Private)
• Statistical data / information related to public services - morbidity and mortality rates (infants and adults – 5-year trend)
• Common diseases in the including endemic diseases.
• Identify and assess specific threats to public health and safety due to project impacts.
• Analysis of the impact of project implementation on existing disease profile including weather sensitive diseases and impact aggravation as a result of climate change.
• Include impacts on health and sanitation Generation of Local Benefits from the project
• Socioeconomic data:
• Identify and assess local benefits of the project in terms of enhancement of employment and livelihood opportunities, increased business opportunities and
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 9 of 58
Environmental Components Methodology and Approach on Baseline Survey Methodology and Approach on Impact Assessment
associated economic activities and increased revenue of LGU
Existing Traffic Condition
• Road network/ systems • Existing Transportation/traffic situation (traffic for
land and water)
• Identify and assess project impact on the traffic situation in the area including congestion based on existing capacity of road system
Perception Survey • Perception survey questionnaires will be prepared by the EIA preparers and conduct primary data gathering.
• The result of the perception survey will be used to substantiate the findings and impacts under the People module.
B.5. Public Participation As per the DENR Administrative Order (DAO) 2017-15, Public Participation is mandatory in preparing the Environmental Impact Statement (EIS) Report to ensure its viability. It should be imposed as early as conducting the Information and Education Campaign (IEC) prior to public scoping. A summary of the public consultation meetings held throughout the formulation of this EIS can be seen on the table below. Table ES - 5. Summary of Public Consultation Meetings Held
Activity Date Venue Key Participants
Information Education and Communication (IEC) meeting with the Provincial Government of Samar and City Government of Catbalogan
December 17, 2019 (1:00 - 4:00 PM)
Conference Room, 2nd Floor, Capitol Building, Catbalogan City, Samar
Project Technical Working Group
IEC meeting with the Barangay Officials of Barangay Mercedes, Catbalogan City
December 18, 2019 (9:00AM to 11:00 AM)
Catbalogan V Central Elementary School
Barangay Officials of Barangay Mercedes
IEC meeting with the Provincial Government of Samar and City Government of Catbalogan
January 16, 2020 (1:00 PM - 3:00 PM)
Conference Room, 2nd Floor, Capitol Building, Catbalogan City, Samar
Project Technical Working Group
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 10 of 58
Activity Date Venue Key Participants
IEC meeting with DENR Region VIII and EMB Region VIII
February 27, 2020 (9:00AM to 11:00 AM)
Sangguniang Panlalawigan Conference Room, 2nd Floor, Capitol Building, Catbalogan City, Samar
Project Technical Working Group
Public Scoping May 10, 2021 (9:00AM to 12:00 PM)
Zoom Application and an on-site venue at Old Tia Anita’s
Project Technical Working Group & Barangay Officials of Barangay Mercedes
Public Hearing October 15, 2021 (9:00AM to 12:00 PM)
Zoom Application and an on-site venue at 2nd floor, Session Hall, Provincial Capitol Building in Catbalogan City
Government offices, Barangay officials, Business group and Fisherfolk Organization
Prior to the public consultation meetings held, the participants’ comments, issues raised, and their suggestions are summarized on the table below, greatly taken into consideration and integrated for the main report of the EIS. Table ES - 6. Summary of Issues, Concerns and Suggestions raised during Consultation Meetings
Activity, Date and Location Aspect Issues, Concerns, and
Suggestions Participant Response
Public Scoping, May 10, 2021 via Zoom Application and an on-site venue at Old Tia Anita’s
Land What is the total land area percentage? Are the roads
included in these?
Diomedes Tan (Philippine Reclamation
Authority)
The total land area is 100% and the roads are included in the
said project.
Land Is the PLGU of Samar aware of the greenspace requirement of PRA
which is at least 5%?
There is an allotted 30-40% of the total area for the open space
network.
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 11 of 58
Activity, Date and Location Aspect Issues, Concerns, and
Suggestions Participant Response
Land Is PD 1586 considered when planning for the no build zone?
Gerry Malinao (Public Sector)
Yes, it is. Especially since the commercial space is near the
sea while the resettlement area is situated between the
commercial spaces.
People Is the distance for the fisher folk village considered in the plan?
Yes, it was considered but the city has a project for its tidal
wall and flood control design which we had to take into
consideration as well.
People What will happen to the reservation of SSU Mercedes
Campus (formerly Samar Regional School of Fisheries)? We are not talking about the existing
building and area of the said agency; we are talking about the reservation area for Samar State
University Mercedes campus (formerly Samar Regional School of Fisheries) which I think will be
affected by the said proposed development?
Ricardeo Severo
(Campus Director, SSU Mercedes Campus)
We don’t have any plans on changing anything in the
existing campus nor it would directly affect the reservation
area. However, a meeting between the provincial, city
government and representatives from SSU will
be conducted to discuss further the matter.
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 12 of 58
Activity, Date and Location Aspect Issues, Concerns, and
Suggestions Participant Response
Water Is there a comprehensive flood control and sewerage plan for the proposed reclamation area? We are in the process of preparation
of plans and program of works for the existing canals and sewer
system.
Grace Lyneil (DPWH)
The hydrology study is part of the whole project and one of the
deliverables is the to come up with the flood control and
sewerage plan.
Water Is there a designated fish landing point?
Gualberto Alcober (DA-BFAR Region 8)
Yes, there is.
People In fishermen village allocated areas, what is the individual
household area to be allocated and the terms and conditions? Is
there any provision of fish landing points intended to the fishermen's sector fronting the sea adjacent to
the fishermen’s village? So that fishermen in the village can access
their fishing implements and be protected if natural and manmade
calamities will occur.
This will be finalized once the meeting with the local
government and fisherfolk organization is completed.
Water Is the comprehensive flood control a separate project from the
reclamation in terms of fund
Diomedes Tan
Yes, we also hired a separate consultant regarding this. The
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 13 of 58
Activity, Date and Location Aspect Issues, Concerns, and
Suggestions Participant Response
source and implementation schedule?
(Philippine Reclamation Authority)
surveys and report is currently ongoing.
Public Hearing, October 15, 2021 via Zoom Application and an on-site venue at 2nd floor, Session Hall, Provincial Capitol Building in Catbalogan City
Project Description
Meron po bang private proponent for this project?
Isabel Calantoc (DIPH)
As of now ay wala tayong private proponent since the
project is initiated by the Provincial Government of
Samar.
Project Description
Meron na bang contractor for this project to do the reclamation?
Meron po bang bidding process?
Isabel Calantoc (DIPH)
Meron pong bidding process na ginawa dito, at meron na din po
tayong contractor. Pero ulitin ko lang po, this project is Provincial Government of
Samar initiated and funded.
Project Description
If awarded na yung project, may we know kung sino po yung
contractor to do the reclamation project?
Isabel Calantoc (DIPH)
Awarded na po siya sa Northern Builders. [Based po sila] sa Catarman, Northern
Samar.
Project Description
Na-implement na daw po ba o nagstart na yung project as of
today?
On-site stakeholder Kanina po nasagot na ng UPMO yan, ang ongoing pong
works ay para sa dike. Eto pong reclamation na ito ay for
implementation pa, at wala hindi pa pwedeng iimplement dahil wala pa tayong Notice to Proceed from PRA at ang ECC.
Kaya po tayo andito ngayon para sa ECC. Under DPWH po yung nakikita niyong works sa
ngayon.
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 14 of 58
Activity, Date and Location Aspect Issues, Concerns, and
Suggestions Participant Response
Project Description
Sana ho ma-coordinate ni proponent sa barangay kung ano
mang activities or related activities na meron yung project,
especially daw itong implemented by the DPWH, kasi for example
daw po, eto ngayon ay hindi nila alam.
On-site stakeholder Actually po, nagkaroon kami recently lang ng Public Hearing
din po para doon sa works natin.
Project Description
Na-coordinate na ba City Government of Catbalogan?
On-site stakeholder Sa question po ninyo kung nagcoordinate ba sa City
[Government], nag-coordinate po tayo; meron po silang
representative na present sa meeting na ito at meron din po kaming nirequest sa kanila na No Objection Resolution para sa project na ito. Isa po yun sa
mga requirements na hinihingi.
Project Description
Please clarify, is this a PLGU proposal or from the PRA?
BFAR FRMD Province of Samar initiated and funded po, sir.
Project Description
Saan po kukunin ang filling material?
Ma’am Christine On-site po, sa Catbalogan City.
Land My next question ay doon sa pinresent kanina ni Ar. Gascon, about the masterplan. Kasi she
mentioned about the open space and green space. Included po ba
ang mga road sa kanyang computation?
Sir Mark John Pineda, PRA The green and open space computation includes all roads, retention ponds, and esplanade.
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 15 of 58
Activity, Date and Location Aspect Issues, Concerns, and
Suggestions Participant Response
Irereiterate lang po namin ang
policy ng PRA, AO 2019-05, requiring all proposed
reclamation na magkaroon ng 5% open space. Excluded po dyan
ang roads sa green space. You can check po our policy para sa
provision na yan.
Land There was some mention of the connecting bridge from the reclamation site at sa road. Was that part of the development? Na-cover din ba siya ng application ng ECC?
Sir Mark John Pineda, PRA As of now, hindi pa siya nasali sa application namin for ECC kasi yung project pa lang po
natin na gagawin at ang priority is the reclamation. Kung meron na po kaming
pondo, then yun po yung time na mag-aapply kami for
another ECC for the separate project.
Land Hindi po kakailangain ang bridge sa pagtambak? Kasi po land-
based ang quarry natin.
Sir Mark John Pineda, PRA Yes po. Yung bridge po required lang siya para maka-connect ang Mercedes to the other proposed reclamation
site, which is located sa Pier 1 to Bunuanan.
Land Nakita ko po sa mapa na malawak pa ang land area ng Catbalogan.
So bakit po magrereclaim e malawak naman ang area?
Magkukumpulan tayo dito sa
Sir Rene Zaldy Porlaje, BFAR-CO
Ang structure po ng Catbalogan, mula po sa
shoreline, hindi po aabot ng isang kilometro ay bundok na
kaagad. So yung bundok po na
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 16 of 58
Activity, Date and Location Aspect Issues, Concerns, and
Suggestions Participant Response
coastal area na maraming masisira na marine resources at
maapektuhan ang communities. Pwede pong pakipaliwanag sa
aming lahat kung bakit kailangan natin magreclaim e hindi pa naman po siksikan kagaya sa
Maynila?
yun, mas mahirap po tanggalin yun kesa mag-reclaim. Kung
andito po kayo sa Catbalogan, makikita niyo po na yung inexplain niyo ngayon na
malawak ang Catbalogan City, hindi po yun tugma in a way na ang Catbalogan po ay bundok-bundok, hindi po pwedeng i-
develop kaagad. So etong option po namin ay
reclamation, which is allowed naman po sa batas. So kung ang
sinasabi po ninyo ay mas madaling i-develop ang sa
bundok, hindi po kami agree doon, sir, dahil kung nakikita po ninyo ang topography dito
ay bundok po talaga.
Land Saan po kukunin ang filling materials for this project?
Ms. Nikka Oquias, Oceana Ma’am, the source of fill materials would be on-site po.
Water May cost-benefit analysis ba na ginawa for this project looking into its long-term effects on the
fragile marine ecosystem and the livelihood of the fisherfolks?
Ms. Nikka Oquias, Oceana Yes po, may ginawa pong cost-benefit analysis for this project.
Water Na-delineate na po ba ang Catbalogan City, ang kanila pong city waters? Na-mapa na po ba ito
ng NAMRIA?
Sir Rene Zaldy Porlaje, BFAR-CO
Hindi po natin masasagot yan sir, kung na-delineate na ang
city waters ng Catbalogan, pero I can assure you na ang
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 17 of 58
Activity, Date and Location Aspect Issues, Concerns, and
Suggestions Participant Response
coverage ng project is well within the waters ng
Catbalogan. Whether or not may delineation po yun ay
hindi po affected ang nearby municipal waters.
Water Kaya ko po natanong ay kasi 35 hectares po itong project,
maapektuhan po ang municipal waters, mag-eextend po siya kasi shoreline po ang ating baseline.
Paano po ma-resolve ang issue na ito?
Sir Rene Zaldy Porlaje, BFAR-CO
The definition of the municipal waters is that its coverage is measured at 90 degrees from the shoreline, 15 kilometers
outward. So, our reclamation project is less than 1 kilometer. What can I say is that it is well within the municipal waters of
Catbalogan City.
Water Gusto ho malaman kung ano ang plano nila para sa waterways, kasi po affected daw sila ng flooding
even before the implementation of the reclamation project.
On-site stakeholder Ito pong project na ito ay isa sa ginawa para maiwasan yung current flooding sa Mercedes.
Kung napansin po ninyo kanina, mayroon po doon sa
plano na mga waterways, tapos yung tubig po doon ay
mapupunta sa isang water pump. Mayroon po tayong
consultants na nagstudy kung ano po ang current status ng
flooding doon para ma-incorporate siya sa project.
Water Nakakasigurado ba ang project na hindi magagaya ang Barangay
On-site stakeholder Yung pagtatagpo po ng highest level ng lupa at tubig, yun po
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 18 of 58
Activity, Date and Location Aspect Issues, Concerns, and
Suggestions Participant Response
Mercedes sa mga nangyaring baha sa Malabon?
ay act of God. Pero sinisigurado po ng Province na gagawin po namin lahat ng precautionary measures para hindi mangyari
yung pagbabaha ngayon sa Malabon. Kung sakali mang dumating yung panahon na
magbaha pa din, hindi po natin mapipigilan yun kasi ang ulan ay hindi po natin hawak. Pero yung project po natin ay may
ginagawang mga study, kasama po doon ang drainage
improvement, master development plan upang
matanggal ang problema sa pagbaha. Ang magagawa lang
po natin ay gawing leksyon kung ano man ang nangyayari
sa Malabon para ma-apply natin dito upang maiwasan
yun.
Ang maisasagot ko po, sa part ng DPWH, ay yung tide
embankment po na ginagawa natin ay nagkaroon po ng study
sa Bureau of Design na naka-design po siya na kahit
magkaroon po ng storm surge o di kaya ay highest tide na
sinasabi ninyo, naka-design po siya na i-withstand po yung
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 19 of 58
Activity, Date and Location Aspect Issues, Concerns, and
Suggestions Participant Response
ganung klaseng sakuna. Pagkatapos po nitong coastal dike, may proposed po ang
DPWH doon po sa pumping stations. Ang mangyayari po
doon, ang magiging mechanics po ng pumping station, kapag
nagkaroon po ng baha sa reclamation area, i-pupump out
po ng pumping station yung tubig palabas para lahat po ng tubig na ma-iimpound doon sa loob ay mailabas po. Actually po yung coastal dike po natin
ay naka-design siya para sa 50-year return period, ibig sabihin
po ay doon po sa 50 years na yun, more or less ay kaya niya
i-withstand ang mga phenomena na pwede
mangyari.
Water Ilan po ba ang total area ng city waters ng Catbalogan at ilang percent po ang mababawas for
this project? The proponent po is requesting for a resource person
from the City Government.
Sir Rene Zaldy Porlaje, BFAR-CO
Para lang po ma-clarify and additional information for Sir
Rene ng BFAR-CO, last January, Gov. Mike Tan
requested BFAR R8 to conduct a rapid resource assessment sa proposed reclamation area dito sa Catbalogan. Yung result ng
rapid resource assessment, finorward na po sa BFAR-CO, baka po Sir Rene hindi niyo pa
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 20 of 58
Activity, Date and Location Aspect Issues, Concerns, and
Suggestions Participant Response
nakikita, last March 2021. Makikita niyo po doon ang coral assessment, yung fish biodiversity and biomass,
nandoon po.
Water I think you have to present din, in a powerpoint presentation, yung
assessment na nagawa. At sa source of filling materials, sinagot
naman siya dito, nakalagay sa Catbalogan City. Ang alam ko
dapat ito may ECC din. May ECC din ang area na pagkukuhanan
ninyo ng filling materials.
Ma’am Anita, DENR-BMB For the question ng kasamahan natin for BFAR, nagkaroon po ng rapid resource assessment
ang BFAR, as requested by the Provincial Government, and the
result of the assessment was forwarded to Director Bayate.
Then again, the Provincial Government, ni-reinforce po
nila ang resource assessment na ginawa ni BFAR; nagconduct
po ng another resource assessment yung preparer.
Basically, the methodology na ginamit po for the benthic
lifeforms is yung manta-tow and spot-dive surveys. Based po sa suggestion po ni Ma’am Anita, we shall include that in the powerpoint presentation
para po mas ma-appreciate ng participants dito sa Public
Hearing yung naging resulta po ng assessment. Tapos sa filling materials naman po, tama po
kayo doon na dapat may application yan ng ECC; but
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 21 of 58
Activity, Date and Location Aspect Issues, Concerns, and
Suggestions Participant Response
dito po, for this reclamation project, hindi na po namin siya isinama. It will have a separate ECC application. Basically, the
coverage of the ECC application is yung reclamation lang po. Pero yung members po ng Review Committee, pina-
include lang po kung saan ang source of filling material para lang po ma-identify kung saan
dadaan yung mga hauling trucks para po makuhanan
namin ng air quality baseline data. We’ll closely coordinate with the PLGU regarding the
matter po, salamat.
People My question is paano yung mga kagaya namin na affected ng
project?
Raul, Vice Chairman of an organization of fisherfolks
As presented po by Ar. Gascon kanina, magkakaroon po tayo ng fisherman’s village, yung color orange. Maglalagay po
tayo ng area ng market para sa mga fresh catch natin. Actually po sir, magkausap kami ni Sir Gerry, at magcocoordinate po
kami para ma-address ang concern ni sir regarding the
project.
People Ano po ba ang plano ng project proponent during construction
para sa mga madidisplace o
On-site stakeholder Kung mapapansin niyo po sa presentation kanina, hindi po
siya one-time big-time na
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 22 of 58
Activity, Date and Location Aspect Issues, Concerns, and
Suggestions Participant Response
maapektuhan ng trabaho? Saan po pupunta yung mga
madidisplace na fishermen temporarily, habang kino-
construct?
gagawin lahat. We shall be doing this po phase by phase.
Okay, to answer your question,
sir, hindi naman po lahat ay matatambakan. Sabi nga po si
Atty. Allan, by phasing po itong projects. So ang ginagawa
po ni contractor ay ito po munang sa isang side; at ongoing po ang aming
assessment para po sa right-of-way. Hindi naman po
matatambakan ito, so pwede po sa part na yun.
People Meron po kaya kayong listahan ng fisherfolks na maapektuhan? Tsaka kasama ang kanilang mga
bangka? Pwede po kami makakuha ng listahan?
Sir Rene Zaldy Porlaje, BFAR-CO
Yes sir, meron po kaming listahan from BFAR R8, kasi
prior to our request sa DENR-EMB for the ECC Clearance, humingi tayo ng certification
from BFAR. Nagconduct po ang BFAR-RO ng assessment,
validation, and thankfully ang recommendation nila is okay to
construct the reclamation project. Kung wala po kayong
kopya sir, bibigyan namin kayo. Thank you.
People May cost-benefit analysis ba na ginawa for this project looking into its long-term effects on the
Ms. Nikka Oquias, Oceana Yes po, may ginawa pong cost-benefit analysis for this project.
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 23 of 58
Activity, Date and Location Aspect Issues, Concerns, and
Suggestions Participant Response
fragile marine ecosystem and the livelihood of the fisherfolks?
People Yung mga residents daw from the Barangay Mercedes are worried
na baka sila ay maisali sa reclamation proponent.
Nanghihingi po si sir ng response or comment from the proponent.
On-site stakeholder Kagaya po ng sinabi ko kanina sir, yung mga residente po dito,
whether legal or illegal, hindi po sila kasama sa project na ito.
So kung ano po ang inookupahan nila dun ngayon, ay sasagutin nila sa PRA. Pero hindi po sila sakop sa area ng project na ito. So kung may
pag-aalala po sila sir, siguro po dapat ay makipagcoordinate na sila sa PRA tulad ng na-discuss natin kanina at yung discussion
ng CENRO at PRA regarding pending applications. Thank
you po.
Other Ano daw po ang magiging status ng occupancy ng mga existing land owners on the area which
will be affected by this proposed reclamation? Yung mga
nagreclaim na daw po, kasi meron na daw pong nagreclaim.
On-site stakeholder Yung mga private individuals na nagreclaim na, hindi po yun kasama dito sa project na ito.
PRA po ang may jurisdiction sa private individuals na
nagreclaim na; pero sa tanong niyo po ay magiging ano ang
status ng area na nireclaim nila, hindi po namin masasagot iyon
dahil hindi po namin sakop yun. Outside po iyan sa area of
this project.
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 24 of 58
Activity, Date and Location Aspect Issues, Concerns, and
Suggestions Participant Response
That’s true – existing and unauthorized reclamations in
the area will be under the jurisdiction of PRA. We intend to undertake a survey of these
illegal reclamations in Mercedes. The survey and the Presidential Proclamation that
will be secured by PRA will cover the entire area that is
illegally reclaimed. The occupants or reclaimers can avail of the existing policy of
PRA on how to legally acquire the ownership of these
reclaimed lands. That’s all.
Other May concern lang po ako since na-mention po kanina na sa
reclamation, ang in charge po doon ay PRA. So, ang concern ko lang po ay anong mangyayari sa
may existing foreshore lease application sa office that are still
pending due to lack of certification from DPWH and CPDO since na-deny ang mga
application/certification nila since may proposed yung Province
natin for the reclamation. Although matagal na kasi yung ibang application doon sa table namin, hindi kasi namin siya
Ma’am Cherry Grace Ungab, CENRO
Our advice to the DENR-CENRO is that applications should be held in abeyance
because PRA is going to apply for the titling and ownership of those reclaimed lands, in behalf
of the national government. That’s the law, and that’s the
existing policy of the PRA. So, the applicant that can claim the ownership of those reclaimed lands will be the PRA. We’ll
just be complicating the process if DENR will have to
act/approve those applications for foreshore lease agreement,
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 25 of 58
Activity, Date and Location Aspect Issues, Concerns, and
Suggestions Participant Response
maproprocess because of that lack of certification. Itatanong ko lang
sana kung pwede na ba namin ma-proceed yung processing o
kailangan po bang pending muna yun?
because at the end, PRA is going to apply for Presidential
Proclamation for those reclaimed lands, and PRA is
going to ask DENR to exclude those areas for the tenurial
instrument, so that the survey plan of those areas can be
approved in favor of the PRA. Maybe CENRO can process an irrevocable permit application, which is one-year renewable to
legalize the occupancy of the people residing in those areas.
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 26 of 58
ES-C EIA SUMMARY • Summary of alternatives considered in terms of siting, technology selection/operation processes and design • Summary of baseline characterization • Concise integrated summary of the main impacts and residual effects after applying mitigation. • Risks and uncertainties relating to the findings and implications for decision making Alternatives
The following criteria were considered for the selection of the proposed site for the area to be
reclaimed:
1. No sensitive area (presence of mangroves, coral reefs, MPAs or any rich biodiversity
area
The proposed reclamation project is not within a Marine Protected Area (MPA) nor
there are presence of mangroves within the project site.
2. Minimal displacement of fishing access and communities
There are two barangays which have affected residents due to the Project – Poblacion
3 and Mercedes. These residents shall be relocated to the fisherman’s village, which is
one of the delineated zones within the proposed development. Additionally, there are
no permanent fishing structures within the project site.
3. Bathymetry of the area
Based from the bathymetry data, once the Mercedes Reclamation Project is in place,
changes in the coastal configurations and topography of the coastline, and hence
changes in bathymetry due to the Project, are expected. However, the result shows
that the computed changes will not significantly alter the existing bathymetry of the
whole Bay.
4. Land Use Plan
The proposed Barangay Mercedes Reclamation Project is aligned with the proposed
land use plan of the City Government. This means that the project is part of the
development goal of Catbalogan. It should also be noted that the Project Site has a
clearance with the Philippine Reclamation Authority (PRA) in a Memorandum of
Understanding dated October 3, 2018. PRA is the primary responsible agency for
integrating, directing and coordinating all reclamation projects for and on behalf of
the National Government and all reclamation projects shall be approved by the
President upon the recommendation of the PRA. Philippine government has given the
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 27 of 58
go signal to the PRA to engage in massive land reclamation all over the country
through Public-Private Partnerships (PPP) with the adoption of the Philippine
Reclamation Authority Resolution 4161 (Approval of the National Reclamation Plan)
on February 25, 2011.
5. Economic growth
Considering the whole stretch of the Catbalogan City shoreline facing the Samar Sea,
there are other possible sitting of the project. These possible reclamation sites are the
barangays Maulong and Payao which are located north of Mercedes and barangays
Guinsorongan and Bunuuan which are situated in the southern part of Mercedes. But
only Barangay Mercedes site has been found which will provide a significant economic
progress since Barangay Mercedes is the nearest barangay in the central business
district of Catbalogan City and Two (2) ports are adjacent to Barangay Mercedes and
these are Pier Uno and Pier Dos. This allows to maximize the use of these 2 ports since
they are near the proposed reclamation site.
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 28 of 58
Baseline Characterization The summary of baseline characterization is presented in the table below. Chapter 2 of this EIA Report provides a more detailed discussion. Table ES - 7. Summary of Baseline Characterization
Module Summary of Baseline Environmental Conditions/ Key Findings
Land
Land Use and Classification The City of Catbalogan having a mountainous and rugged terrain with small plain areas mostly found along the seacoast directed its expansion areas to seaward or reclamation. The increasing needs of additional areas for residential, commercial, industrial and institutional spaces to meet the demand to sustain the economic growth of the city led to the plan to expand areas seaward to barangays Mercedes, Maulong and Guinsorongan for residential, commercial and institutional while northern barangays for industrial uses.
Geology/Geomorphology Rugged terrain (with relatively high mountains) characterizes the general topography. Only two percent (2%) of its land area is plain while forty percent (40%) is hilly and fifty five percent (55%) upland. Due to its rugged terrain, the northern and eastern portions of the city revealed angular hills with deep gorges. While in its central portion, its upland surface is cut by many gullies, narrow ravines and canyons that reach the depth of two hundred (200) feet or more. The topography can be described as rolling to mountainous area towards the hinterland – plain to slightly sloping towards the coastal areas.
Pedology Catbalogan has two types of soil based on the records of the Bureau of Soil and Water Management (BSWM). The first type is Catbalogan Clay Loam – it is formed from shale and sandstones. Its topsoil is usually light brown to grey when dry, and appears grayish brown to dark grey when moist. Its texture is slightly sticky and its depth is about ten to 20 centimeters.
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 29 of 58
Module Summary of Baseline Environmental Conditions/ Key Findings
The second type is Faraon Clay Loam – a residue of coralline limestone. Its characteristic is its surface oil when wet, appears black grey to dark grey. It is soft, sticky medium granules and appears slightly hard and brittle when dry. It is fair medium in organic contents. Its depth ranges from 15 to 30 centimeters. Covering vegetation to date on the said type of soil are primary and secondary forests. Palay, corn and root crops are suited to this kind of soil type.
Terrestrial Ecology The project is to be constructed within a marine water space. Therefore, vegetation removal, loss of habitat of plant species, loss of important species, abundance, frequency and distribution of the species are very minimal. During the construction, the invasion of non-native species is not expected to occur from vehicles that transport the materials for the project which since the adjacent areas are characterized as built-up areas.
Water
Hydrology & Hydrogeology The Antiao river, commonly called Salug River, is the main river of Catbalogan City. However, along the periphery of the city, there are at least fourteen (14) identified smaller catchment basins that significantly contributes to surface runoff during heavy rainfall and sometimes caused heavy damages to properties and inconvenience to the residents. Catchment basin numbers 1 to 4 are found in Barangay Mercedes, number 5 to 7 are directly affecting the city proper and numbers 8 to 14 are affecting the Pier 1 to Barangay Bunuanan areas.
Water Quality Sea water and surface (fresh) water samples were collected on June 16, 2021 from the sea and Anitao River. Ten (10) sampling stations were identified and selected to establish water quality of the said water bodies that may be affected by the proposed project. Samples were then brought to University of San Carlos Water Laboratory in Cebu City for laboratory analysis of Color, Dissolved Oxygen (DO), Fecal Coliform, Nitrate, pH, Phosphate, Temperature, Total Suspended Solids (TSS), Ammonia, Boron, Fluoride, Selenium, Sulfate, Arsenic, Barium, Cadmium, Chromium, Copper, Iron, Lead, Manganese, Mercury, Nickel, and Zinc. The samples were analyzed in accordance with the Standard Method for
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 30 of 58
Module Summary of Baseline Environmental Conditions/ Key Findings
the Examination of Water and Wastewater, 22nd ed. Water quality survey was conducted to serve as baseline data in monitoring the effect of the project in the water quality.
Freshwater Biology Assessment of freshwater biota was conducted on 05 June 2021 in three sampling stations in the Antiao River in conjunction with marine ecology baseline assessments for the Brgy. Mercedes Reclamation Projects. Due to extremely polluted and turbid river water, the freshwater ecology surveys focused on (i) conduct of key informant interviews to determine fish species still present in the river system, (ii) sampling of benthic macro-invertebrates, if any, and (iii) identification of plankton communities. Sampling locations were distributed in upstream portion of the river, in midstream portion closest and in the Antiao River estuary. A total of three stations were surveyed for plankton communities, fish biota and macro-invertebrates. Four (4) key informants were interviewed for fish biota and macro-benthos.
Marine Biology The baseline assessment was conducted to characterize habitat types, diversity, spatial distribution and current condition of coastal habitats and resources in the Project’s impact area in conjunction with an estimation of potential negative issues and stressor pathways resulting from reclamation activities. In the absence of coral life forms, seagrass and mangrove resources in the impact area of the proposed reclamation project, the survey was conducted employing standard scientific assessment tools in-situ to determine the nature of the benthic environment and validate the absence of corals and seagrass beds, determine plankton community structure, catalogue presence of macro-invertebrates of commercial importance to local communities and census of pelagic fish resources and the fisheries that it supports. Drawing from results of the baseline assessment, the EIA attempts to predict the most likely impacts of anthropogenic origin on susceptible fragile coastal resources within the impact area, and prescribes the most suitable mitigating measures that can be adopted in order to maintain ecological integrity during all phases of project establishment and operation.
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 31 of 58
Module Summary of Baseline Environmental Conditions/ Key Findings
Air
Meteorology/Climatology The climate of Catbalogan City belongs to Type IV, wherein rainfall is more or less distributed equally throughout the year. The area is relatively hot and humid; with mean daily temperature of 28.8 °C (range is 23.77 °C and 33.41 °C). The annual rainfall averages about 2,178 mm. There is hardly any month without rainfall. Typhoons are very frequent during the months of August, September, October, November and December. Hence, Samar is popularly known as typhoon area because PAGASA uses the place as weather reference point.
Air Quality An ambient air quality survey was undertaken to check whether ambient air quality before and after the construction phase of the project are up to par with the National Ambient Air Quality Standards (NAAQS) of the Department of Environment and Natural Resources (DENR); and (2) to come up with potential mitigating measures to decrease the chances of exceeding the parameters set by DENR. As the project involves civil works, it is expected that total suspended particulates (TSP) and noise are to be generated by the project during the construction stage. Observation areas were selected based on the magnitude of civil works involve and proximity to nearest receptors such built up areas, schools and other crowded areas. There were four (4) sampling points for air and noise. In the reclamation area, source of fill materials and route of the hauling trucks.
Noise Noise level monitoring was conducted at four (4) locations within the vicinity. The measurement was performed for about one (1) hour and 24 hours. Noise sampler was handheld at about thirty degrees (30°) from the plane directly pointing at four (4) compass points to evaluate the noise level within the area.
People
Demography Historically, data from the Philippine Statistics Authority (PSA) showed that Catbalogan has a total population of 7,758 in the year 1903. In the year 1918 it gained an increase of 57%. Thus, reflecting an average annual growth rate (AAGR) of 4.97% annually then. In the year 1939, the population tripled
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 32 of 58
Module Summary of Baseline Environmental Conditions/ Key Findings
compare to the Census Year of 1903. The significant increase in population continues until the Census year of 1980 and by 1995, it ballooned into 76,324 or about ten times than that of 1903. Using the AAGR of 1.81% AGR for the 20-year period from 1995 to 2015, the projected population of the City of Catbalogan in 2020 is 113,599.
Migration Catbalogan is a migration and in-migration LGU, local folks look for greener pasture for employment opportunity in highly urbanizes areas while neighboring municipalities finds Catbalogan as an employment generator. However, both these are not included or not counted as population of the city as per guidelines of PSA. Investors finds the city’s population as unique having a smaller population count while actual population are greater (daytime population) in the Poblacion. This is supported by data from DTI that shows that Catbalogan has the biggest investment in terms of money and number one employment generator in the Province of Samar than Calbayog City.
Historical and Cultural Heritage and Indigenous People
The reclamation project aims to create new land that will develop the newest and most vibrant destination in the province merging tourism, business & leisure. Hence, with respect to this purpose, cultural/lifestyle change will be introduced to the residents of Barangay Mercedes or the whole Catbalogan as tourist may flock in the new destination this will create new jobs for the community. Based from the latest Ecological Profile of the City, there are no identified indigenous people nor indigenous cultural community (ICC) within the project site.
Basic Infrastructure and Services Water. According to the Ecological Profile, 2021 of Catbalogan City, the city has a potable water supply. Previously, LUWA was the water provider of the locality. Due to its inefficient services due to grossly inadequate water supply and losing operation, the management was transferred to what is now the Catbalogan Water District (CWD). Today, only 40% of the populace is being served. Immense water shortage/salty water supply is a perennial problem during dry spell.
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 33 of 58
Module Summary of Baseline Environmental Conditions/ Key Findings
Power. In terms of power supply, Catbalogan City has 88.46% of the total Household connections were already energized and 100% barangays wherein forty-nine (49) barangays connected to the main grid and eight (8) island barangays connected to Off-grid thru a genset owned by the NPC-SPUG.
Environmental Health and Sanitation Profile
The Samar Provincial Hospital is situated in the Poblacion of the city, being the capital town of the Province of Samar handles more complicated medical needs of the populace. The City’s Rural Health Unit has a complete personnel and Barangay Health Stations in almost all barangays. Presently, the Integrated Provincial Health Office (IPHO) is not totally equipped to meet the standard to serve the patients in the area. Sometimes, patients are referred to Tacloban City Hospitals for further check-up/consultations and medical need.
Economic Profile The local economy in Catbalogan is divided into three parts: the primary, secondary and tertiary sectors. The primary sector is made up of agriculture, fishery, livestock, and forestry. The secondary sector is composed of mining and quarrying, manufacturing, construction and energy generation/distribution. While, the tertiary sector consists of all service activities and commerce, real estate, finance, personal and community services, and transportation and communications.
Existing Traffic Condition Baseline traffic surveys were conducted during the feasibility study stage of the proposed project in order to assess the existing road network capacity and its capability to accept the combined traffic that will be generated from the proposed reclamation project and by natural traffic growth in the future. For the traffic study, only the Daang Maharlika National Road was examined as it is the only road which gives access to the proposed reclamation project. Daang Maharlika is a primary road that links the City of Catbalogan to Calbayog. This road will also be the main road that will be used to access the Proposed Catbalogan Airport in Buri Island. Its total carriageway width is 7 meters which is divided into two (2) lanes, and it is made of asphalt. It is bordered by mostly residential houses and is characterized by light traffic flows. Notable establishments within the are a distribution center for San Miguel Brewery, Samar State University, and Samar Doctor’s Hospital.
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 34 of 58
Module Summary of Baseline Environmental Conditions/ Key Findings
Perception Survey There were 500 respondents in total whom answered the socio-economic survey for the proposed Barangay Mercedes Reclamation. They were made to voluntarily accomplish a socio-economic survey form composed of the following questions organized into four (4) categories: (a) Household Profile; (b) Economic Profile; (c) Related to the Reclamation Project; and (d) Information regarding gender impact of the project.
Impact Assessment and Environmental Management Plan The summary of impact assessment and environmental management plan the proposed project are presented in Table 8. Chapter 2 of this EIA report presents a more detailed discussion. Table ES - 8. Summary of Impact Assessment and Environmental Management Plan
Environmental Component Likely to be Affected
Potential Impact Prevention/Mitigation/Enhancement Measures Residual Effects
The Land Terrestrial Ecology Earth moving during reclamation
works can generate sediment streams that, when not contained adequately, result to further river water discoloration and siltation, depth reduction and alteration, scouring and consequently the disturbance and modification of river habitat.
The primary mitigation strategy to prevent escape of sediments and terrigenous material disturbed during reclamation excavation and filling is the establishment of a series of silt curtains around the reclamation sites. Control measures will also include a series of sediment mitigation structures, including catchment and diversion canals to ensure that silt and sediments will not flow into the river estuary and enter the river system.
No residual effects
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 35 of 58
Environmental Component Likely to be Affected
Potential Impact Prevention/Mitigation/Enhancement Measures Residual Effects
Heavy equipment areas will be located away from waterways where erosion control measures can be easily applied. Reclamation operation material stockpiles shall be covered. As a precautionary approach, slurry walls will be built around areas where such slurries can emanate extensively.
During the project’s operations phase, poorly-managed domestic waste disposal system can lead to solid and liquid wastewater contamination in the river, with uncontained waste streams generated from personnel quarters and offices potentially carried by run-off water into river gullies.
Modern wastewater treatment facilities and a solid waste management plan will be implemented and strictly enforced as mitigation to potential waste disturbances in the reclamation sites. State-of-the art modern sanitation facilities with 3-chambered septic tanks will be installed in all project latrines.
No residual effects
The risk of oil and grease contamination of the river during incoming tides can only occur if disposal of fuel-based wastes is not undertaken properly and accidental spills near waterways that drain into the river happens. From portions of the river, oily sludge, processing slurry and hazardous wastes can be inadvertently carried to coastal waters if containment, recovery and
An oil and grease containment and oily waste containment and recovery plan will be formulated and enforced in all aspects of project operations. Remediation will include recovery and treatment of sludge. Carpools will be located farthest from the coast and driver system and all vehicle oil discards will be recovered.
No residual effects
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 36 of 58
Environmental Component Likely to be Affected
Potential Impact Prevention/Mitigation/Enhancement Measures Residual Effects
treatment systems are not efficiently established and maintained. Such fugitive wastes will have far-reaching and irreversible impacts on benthic communities in the estuary, resulting to contamination of grazing areas that may further depress fish growth and recruitment, loss of fish habitats and reduction of primary productivity.
Geology/Geomorphology Inducement of liquefaction A detailed geotechnical investigation must be undertaken in case of construction of tall buildings (more than 3-storey) is planned to be erected at the site. This is necessary to determine the most suitable foundation scheme and the net bearing capacity as well as to identify any ground stability problem within the area.
No residual effects
Geology/Geomorphology Earthquake Induced Landslide: Based on the earthquake- induced landslide susceptibility map from PHIVOLCS, the coastal areas where the project site is situated is unlikely to be susceptible to earthquake- induced landslides since it has flat terrain. However, the reclamation project is highly susceptible to lateral spread and flow failure since
A properly anchored retaining structure that could hold in-place the reclaimed land should be constructed to mitigate this hazard. The slope of the fill should not be overly steepened to minimize slope failures.
No residual effects
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 37 of 58
Environmental Component Likely to be Affected
Potential Impact Prevention/Mitigation/Enhancement Measures Residual Effects
its offshore perimeter will form a steep slope rising above the seabed.
Geology/Geomorphology Settlement: AMH study indicates that the reclaimed land would not settle uniformly.
To avoid excessive settlement in the reclaimed land, the fill should be engineered to improve its consistency. The fill should be designed to have the characteristic of a vibrocompacted sand fill. The soil that should be used for reclamation should not contain high amount of silty and clayey materials. Preferably, well-graded sand and gravel materials should be used. It should be mixed with stabilizing material such as cement.
No residual effects
Geology/Geomorphology Ground Subsidence, Collapse, Heave:
Ground subsidence should be monitored continuously from the start of the reclamation, during construction of buildings in the industrial park, and even after all constructions are finished.
No residual effects
Geology/Geomorphology Other Geo Hazards Awareness and preparedness raising of construction managers on each of the known hazards to include drills, proper signages and alarm systems
No residual effects
Geology/Geomorphology
Aggravated flooding in nearby coast due to the reclaimed area which at inease siltation and erosion and impede tidal flushing
Adequate and efficient drainage design is recommended to prevent localized flooding at the site especially during heavy downpours. The drainage lines in the area should regularly be cleaned and maintained of waste materials. Proper waste management should be implemented.
No residual effects
Geology/Geomorphology Sea reclamation is simply filling the area with large amounts of heavy rock and/or cement, then filling with clay and soil until the desired height is
No residual effects
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 38 of 58
Environmental Component Likely to be Affected
Potential Impact Prevention/Mitigation/Enhancement Measures Residual Effects
reached. The earthfilling procedures should conform to engineering application standards that requires materials to be properly compacted. Compaction of soil should be 95% of maximum dry density (MDD) and should be done at every lift thickness of 20 centimeters. The same requirement should be applied when compacting disturbed natural soil such as those directly below the foundation and floor slabs where a 10-centimeter thick clean gravel should be placed. Only granular or sandy soils should be used as backfill materials. Retaining walls that will hold the earthfill materials in place must be of high integrity (founded on rigid bedrock and can resist impact of waves during tropical cyclones) with good drainage. The ground elevation must be high enough to minimize the effects of coastal flooding.
Land Use and Classification Solid waste littering on terrestrial environment. Reclamation activities do not generate debris and wastes, except domestic garbage from construction crews, which might be disposed on shore. However, there may be accidental spillage.
Littering, accidental spillage of any construction wastes should be avoided by pre- planning ways of their transportation and/or unloading at the temporary storage. Careful planning of the work activities can also reduce the amount of waste generated.
No residual effects
Geology/Geomorphology Possible flooding due to the limited, narrow and shallow drainages along the road and through the built-up areas along the coastal community
The existing drainage system in the built-up coastal areas should be improved to accommodate floodwaters. There should be a properly designed
No residual effects
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 39 of 58
Environmental Component Likely to be Affected
Potential Impact Prevention/Mitigation/Enhancement Measures Residual Effects
drainage network that is sufficient to channel the flood to the sea.
Geology/Geomorphology Increase in Ground Water Demand - The influx of workers and their families in the residential area outside the reclamation site will lead to an increase in the consumption of groundwater. If the groundwater provided by the local water district is not sufficient, there would possibly be an increase in groundwater wells in the area. This could lead to over extraction of groundwater and would contribute to ground subsidence.
The extraction of groundwater in the existing residential and industrial areas should be monitored and regulated to avoid the negative effects of subsidence due to over extraction of groundwater. Regular ground survey should be conducted to monitor ground subsidence. Rainwater harvesting during the rainy season could be done to augment the water source. The community should also be trained on how to conduct rainwater harvesting and on proper water management.
No residual effects
Geology/Geomorphology Siltation and transport of silt to other areas that may have marine resources
Silt curtains shall be installed in the reclamation area. This shall hold the silt within the area
No residual effects
Geology/Geomorphology Soil erosion The edge of the reclamation area shall be placed with armor rocks that shall prevent waves to erode the soils being dumped.
No residual effects
The Water Marine Ecology Enhanced silt and sediment
intrusion into coastal waters. Earthmoving, dredging, reclamation filling and construction of reclamation facilities in the proposed Brgy. Mercedes
Wall containment structure will be installed around the perimeter of the proposed reclamation area. The general procedure in the installation of sheet pile is the choice of a suitable driving system which is of fundamental importance.
No residual effects
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 40 of 58
Environmental Component Likely to be Affected
Potential Impact Prevention/Mitigation/Enhancement Measures Residual Effects
Reclamation Project Reclamation Project will likely lead to cumulative sediment discharges into coastal waters, spilled directly from reclamation works or carried down through waterways, in ditches, canals and carried by rainwater outfall.
Marine Ecology Wastewater from heightened personnel presence in the project’s operation and land-based facilities, combined with organic wastes and nutrients stirred up during soil-moving activities, can exacerbate seawater pollution and in extreme cases lead to hyper-nutrient loading that can trigger algal blooms. The immediate impacts can include biotoxins in shellfish populations, particularly filter-feeding mussels and oysters found in Catbalogan coastal waters.
Wastewater from the reclamation works will not be disposed in waterways that ultimately contribute to coastal water pollution. Temporary containment ponds will be built, and the use of 3-chambered septic tanks shall be installed in all project facilities where wastewaters and other effluents are generated. A network of canals to divert fugitive wastewater spills will be set up to divert all waters into a containment area where that can be re-used or collected and disposed properly. Waste minimization will be practiced in all aspects of project operation. The objective is to ensure that pollution-causing effluents that can be potentially carried downstream are treated at the source.
No residual effects
Marine Ecology Oil and grease contamination. While this issue is not anticipated to be severe, oil slicks from spills and
Potential risks of small oil spills will be addressed through strict fuel and oil dispersal protocols backed-up by an oil/fuel spill contingency plan.
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 41 of 58
Environmental Component Likely to be Affected
Potential Impact Prevention/Mitigation/Enhancement Measures Residual Effects
vehicle maintenance can be very detrimental not only to benthic organisms in the shelf but can also cause migration of fish and crustaceans to other areas, leading to lower fisheries productivity. Macro-invertebrates are susceptible to immediate mortality. The detrimental effects can be irreversible.
Oil depots will be located a good distance from the coastline. No oil wastes will be disposed into waterways or canals. An oil and grease containment and recovery plan will be formulated in accordance with MARPOL protocols and enforced in all aspects of project operations. Prohibition of wanton disposal of oily wastes will be absolute and a rigid monitoring system around the reclamation works will be carried out constantly.
Marine Ecology Impacts on crab habitats from dredging and soil filling activities. Sustained sediment and silt loading can result to habitat alteration and the emigration of some crab population. Growth and recruitment overfishing can also seriously affect resiliency of the population and can lead to irreversible loss. Nevertheless, in as much as the reclamation area is small and does not host sizeable crab populations, dredging and reclamation filling will result only to temporary and shallow disturbance of crab habitats and feeding regimen.
Fisheries management should be at the forefront of programs by both the LGU of Catbalogan and management of the four reclamation projects in Catbalogan City. This should be pursued through the Ecosystem Approach to Fisheries Management. The fishery must have an effective basis for the implementation of rules for conserving all species involved in the fishery, ensuring a harvest threshold for mature species. Along this view the fishery must also ensure that juvenile fish (i.e. below age of maturity) are subject to low fishing mortality and species retained by the fishery – like mature and undersize crabs - must be managed in a way as to minimize the risk of over-exploitation.
No residual effects
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 42 of 58
Environmental Component Likely to be Affected
Potential Impact Prevention/Mitigation/Enhancement Measures Residual Effects
The establishment of Marine Protected Ares (MPAs) will be at the forefront of fisheries management.
Marine Ecology Wastewater from heightened personnel presence in the project’s operation and land-based facilities, combined with organic wastes and nutrients stirred up during soil-moving activities, can exacerbate seawater pollution and in extreme cases lead to hyper-nutrient loading that can trigger algal blooms. The immediate impacts can include biotoxins in shellfish populations, particularly filter-feeding mussels and oysters found in Catbalogan coastal waters.
Wastewater from heightened personnel presence in the project’s operation and land-based facilities, combined with organic wastes and nutrients stirred up during soil-moving activities, can exacerbate seawater pollution and in extreme cases lead to hyper-nutrient loading that can trigger algal blooms. The immediate impacts can include biotoxins in shellfish populations, particularly filter-feeding mussels and oysters found in Catbalogan coastal waters.
No residual effects
Water Quality Degradation of surface water quality due to Local and temporal re-suspension of sediments causing increased turbidity.
Silt curtains, using geo-textile materials, shall be installed in the reclamation area. This shall hold the silts within the area.
No residual effects
Degradation of surface water quality due to potential accidents and damages/injury to another vessel/structure or cetacean
This is of low impact with minor consequence/severity because it is unlikely to happen with only 1 or 2 vessels/barges.
No residual effects
Contamination of water / Possible oil spills/leaks
Regular checking of all equipment including vessels or barges for leakage will be done.
No residual effects
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 43 of 58
Environmental Component Likely to be Affected
Potential Impact Prevention/Mitigation/Enhancement Measures Residual Effects
Moreover, oil spill kits will be ready in case there will be accidental spills. Institute and implementation of oil spill containment protocols should be followed during development in cases of occurrence.
No residual effects
Contamination of water brought by heavy equipment and vessels
Regular checking of all equipment (including sea vessels) for leakage will be done. Moreover, oil spill kits will be ready in case there will be accidental spills.
No residual effects
Marine water quality Solid and Hazardous waste management shall be strictly implemented in compliance with RA 9003 and RA 6969. A centralized treatment facility can be established to ensure wastewater has been treated before discharging to any bodies of water
No residual effects
Water availability and competition for use
· IEC should be conducted by the MDRRMC and the barangay for water conservation program and water reuse and recycling.
No residual effects
· Adaptation measures include protection of water aquifer, conduct of massive information and education campaign, establishment of protection measures for coastal areas, and strengthening the protection of ecosystems.
No residual effects
The Air Air Quality Degradation of air quality due to
dust and particulate matter generation and GHG generation.
Minimize heavy machinery during reclamation works. Regularly maintain diesel driven engines of transport vehicles, equipment and barges and ensure they meet required emission levels for diesel vehicles.
No residual effects
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 44 of 58
Environmental Component Likely to be Affected
Potential Impact Prevention/Mitigation/Enhancement Measures Residual Effects
Noise Increase in noise pollution during operation of various construction equipment and vehicles
Proper scheduling of high noise generating construction activities during the daytime to avoid sensitive periods; Installation of temporary noise barriers such as galvanized iron shields will also be used particularly in noise-sensitive areas such as churches, schools and hospitals in the immediate vicinities of the construction area; Positioning of temporary site compounds as far as reasonably practicable from sensitive receptors.
No residual effects
Meteorology/Climatology Contribution in terms of greenhouse gas emissions (or GHG mitigation potential)
It is recommended that the proponent initiate enhancement programs related to carbon sink sequestration in line with the government’s greening program considering that a 100-hectare land mass will be generated as a result of the reclamation project.
No residual effects
The People People Possible accidents for workers Orientations and strict implementation of safety
practices will be done. No residual effects
Health hazard to Workers (Increased Dust Generation)
Use of protective gears No residual effects
Social unrest of sectors in the community, psycho-social impacts on communities surrounding the project and disturbance in their socio- economic activities
The proponent initiate intensive IEC activities to update stakeholders on the status of the project, initiate programs that will promote livelihood, skills development, health and nutrition, disaster risk reduction and response and other similar
No residual effects
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 45 of 58
Environmental Component Likely to be Affected
Potential Impact Prevention/Mitigation/Enhancement Measures Residual Effects
activities as part of the proponent’s Social Development Plan. Proponent with the LGU to Implement appropriate sectoral consultations and IEC programs to raise project knowledge and awareness an community engagement
Employment generation · Priority jobs for the men and women of direct and indirect impact areas
· IEC on nature of jobs · Consultation on job requirements and qualification · Local hiring priority for qualified Barangay residents · Skills training to upgrade local skills of residents that can be hired by the project · Engagement of residents as manpower for the preliminaries and implementation pf the Coastal Resource Management Program · Generation of livelihood opportunities by putting-up food stalls, variety stores and other services near the Project
Positive effects in terms of employment, livelihood
People Risk to flooding after the development of the reclamation project. Storm surge hazard and other Hazards
Storm surges are one of the many natural hazards that are difficult to control. Break waters and barriers may help or minimize the effect of coastal waves. Vigilance and awareness about storm surges must be undertaken with the help of PAGASA that regularly give weather information on the direction and strength of typhoon. It is very important that the people and the local leaders in
No residual effects
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 46 of 58
Environmental Component Likely to be Affected
Potential Impact Prevention/Mitigation/Enhancement Measures Residual Effects
the coastal areas know of the basic things that they should undertake if they experience the effects of the storm surges.
For offshore earthquakes capable of generating tsunami
Even if the future tsunami has a low impact to the proposed project site, vigilance and sustained community-level public education on tsunami awareness, preparedness and mitigation are still very important. Coastal communities must be aware of tsunami facts and must react appropriately during an earthquake at any time. It is very important that the people and the local leaders in the coastal areas are aware of the basic things that they should know and do if they experience a very strong earthquake.
No residual effects
Impact of Climate Change Vulnerability mapping should be conducted to identify priority households for evacuation.
No residual effects
Non-structural disaster mitigation measures should be implemented in line with the LGUs Disaster Risk Reduction and Management (DRRM) plans.
No residual effects
Peace and Order Unauthorized entry of outsiders and establishments which might cause problems in peace and order
· Coordination with the Barangay LGU Tanods to ensure authorized establishments and control of unauthorized entry of outsiders. Buffer zones should be established around the perimeter of the reclamation area during construction
No residual effects
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 47 of 58
Environmental Component Likely to be Affected
Potential Impact Prevention/Mitigation/Enhancement Measures Residual Effects
Health and Safety · Entry of migrant workers with families, which might cause problems of congestion, peace and order and security, breaches. · In like manner, cause health problems due to diseases, overuse of public utilities /services, competition of resources, social conflicts, peace and order, increase in pollution due to solid, liquid and toxic wastes. · Possible Health and safety risk in the operation of the reclaimed area due to noise and air pollution · Increase in traffic flow causing air (dust) and noise pollution
· Management of entry of migrant workers. · Increase and train Barangay tanods to be deployed in areas where migrant workers reside as well as the management of waste. · Proponent provide Health clinic with a Doctor, Nurse and Health workers · Health certificate for workers prior to hiring into the project · Implementation of the Social Development Program · IEC on proper scheduling of hauler trucks and construction operations to avoid entry and dismissal of school children as well as late hours. · Environment Risk Management for the operation of the Plant and surrounding communities
No residual effects
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 48 of 58
Environmental Monitoring Plan Table ES - 9 presents the summary of environmental monitoring plan, which contains the environmental concerns, parameters to be monitored, sampling measurement plan and estimated cost. Table ES - 9. Summary of Environmental Monitoring Plan
Environmental Aspect
Potential Impacts Parameters
Environmental Monitoring Form Lead
Person
Annual Estimate
d Cost
Environmental Quality Performance Level (EPQL) Management
Method Frequency
Location EPQL Range Management Measure
Alert Action Limit Alert Action Limit
Construction Phase (Reclamation and Land Development) Water Quality
Coastal (Marine) water quality degradation caused by reclamation activities
pH Grab sampling
Monthly All stations
considered in this
study
Proponent’s /
Contractor’s PCO
Included in the
project cost
4.2 – 5.1 (60% of Std.)
5.3 – 6.4 (75% of Std.)
7.0-8.5 (Std. Class SB)
Report actual status on a periodic basis, document results and continue monitoring. Identify source of pollution / exceedance. Increase sampling frequencies. Conduct clean up activities along streams that discharge to the sea.
Revalidate results and continue monitoring. Revalidate previously identify source of pollution / exceedance. If source of exceedance are leaks or spills, implement spill containment and clean up measures.
Compare how values of results escalated relating each result to actual occurring situation during sampling and validate identified sources. As necessary, temporary stoppage of concerned activities may be needed until remedial measures are in place.
Temperature
15.6 - 18.0
19.5-22.5 26-30
Oil and grease, mg/L
1.8 2.25 3
TSS, mg/L 30 37.5 80
DO, mg/L 3.6 4.5 6
Cr (VI), mg/L
0.03 0.0375 0.05
As, mg/L 0.006 0.0075 0.01
Cd, mg/L 0.0018 0.00225 0.003
Pb, mg/L 0.006 0.0075 0.01
Hg, mg/L 0.0006 0.00075 0.001
Cu, mg/L 0.012 0.015 0.02
Total Coliform, MPN/100mL
6000 7500 10000
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 49 of 58
Environmental Aspect
Potential Impacts Parameters
Environmental Monitoring Form Lead
Person
Annual Estimate
d Cost
Environmental Quality Performance Level (EPQL) Management
Method Frequency
Location EPQL Range Management Measure
Alert Action Limit Alert Action Limit Strict implementation of good house-keeping practices / measures at the site.
Water Quality
Change in species composition and abundance of marine, freshwater, and riparian biota due to reclamation and dredging activities within the immediate vicinity of the reclamation area, the dredge area and the
Density of fish catch per unit effort (Kilos of fish caught/person/ trip)
Interview Annual Immediate fishing areas around the project
Proponent Included in project cost
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 50 of 58
Environmental Aspect
Potential Impacts Parameters
Environmental Monitoring Form Lead
Person
Annual Estimate
d Cost
Environmental Quality Performance Level (EPQL) Management
Method Frequency
Location EPQL Range Management Measure
Alert Action Limit Alert Action Limit area study for the Tungkop Fish Sanctuary
Threat to Abundance / Degradation of mangrove area
- Mangrove growth including its height, basal area and its diameter-at- breast height
Census or manual count Physical Measurement
Quarterly
Open Area /mangrove park within the project
Proponent Included in project cost
assessment in abundance and taxa richness of aquatic biota
baseline assessment in abundance and taxa richness of aquatic biota; Decreasing trend across three monitoring periods.
abundance and taxa richness of aquatic biota across monitoring periods accompanied by exceedances in water quality parameters being monitored
Investigate and identify possible cause of decline. Conduct initial inspection of control measures being implemented
Values Check results of the aquatic biota analyses against the water quality status. Improve or enhance existing control measures to improve water quality
Sediment Deposition
May adversely affect ecosystem
Heavy metals and nutrients
Grab sampling
Quarterly
Area near mouth of the rivers and other stations that the MMT may further recommend
Proponent / Contractor
Included in project cost
Same levels as in Water Quality (TSS)
Same levels as in Water Quality (TSS)
Same levels as in Water Quality (TSS)
Report results to Project Manager
If values are exceeded transfer to another location
Management remedial measures if necessary
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 51 of 58
Environmental Aspect
Potential Impacts Parameters
Environmental Monitoring Form Lead
Person
Annual Estimate
d Cost
Environmental Quality Performance Level (EPQL) Management
Method Frequency
Location EPQL Range Management Measure
Alert Action Limit Alert Action Limit Waste management Hazardous substances Chemical storage areas
Impacts on sanitation and water pollution Risk to human health
Type and volume of waste Present in harmful quantities and safe storage
Visual inspection
Daily Reclamation site and Staging Area
Proponent / Contractor
Included in project cost
Report results to Project Manager
Adopt remedial actions and safety measures
There should not be any untoward incident
Air Quality Possible degradation of air quality due to reclamation activities
SO2, ug/NCM
Gas Bubbler and Pararosaniline Method
Quarterly
Stations considered in the report
Proponent’s / Contractor’s PCO
50,000 204 255 340 Report actual status on a periodic basis, document results. Investigate possible cause of pollution and continue monitoring. Conduct dust suppression measures.
Prepare statistical report highlighting the findings. Regular maintenance of all fuel-burning equipment.
Revisit /audit the functionality of air pollution control installations. Replace all non- conforming equipment / machineries.
NO2, ug/NCM
Gas Bubbler and Pararosaniline Method
156 195 260
PM10, mg/L High Volume Sampler
120 150 200
TSP, ug/NCM
High Volume and Gravimetric Method
180 225 300
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 52 of 58
Environmental Aspect
Potential Impacts Parameters
Environmental Monitoring Form Lead
Person
Annual Estimate
d Cost
Environmental Quality Performance Level (EPQL) Management
Method Frequency
Location EPQL Range Management Measure
Alert Action Limit Alert Action Limit Possible increase in ambient noise level due to reclamation activities
Noise, dbA Noise meter
Quarterly or as required in response to any noise complaints.
Stations considered in the report
Proponent’s / Contractor’s PCO
Minimal cost; Included in the project cost
55 60 65 Report actual status on a periodic basis, document results and continue monitoring. Investigate possible cause of exceedance.
Fix broken equipment or machine, as necessary. Regularly maintain equipment to keep these working at their optimum and minimize noise. Continue noise level monitoring and increase frequency as necessary .
Conduct site noise audit of equipment and machineries. Install noise suppression structures and/or equipment appropriate to mitigate the situation.
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 53 of 58
Environmental Aspect
Potential Impacts Parameters
Environmental Monitoring Form Lead
Person
Annual Estimate
d Cost
Environmental Quality Performance Level (EPQL) Management
Method Frequency
Location EPQL Range Management Measure
Alert Action Limit Alert Action Limit Community consultation
Socio-economic status of the host communities vis- à-vis the project operations Community benefits from the project due to taxes, employment, and social development programs (SDP)
Efficiency of SDP programs, employment generation (in terms of local engagement on the project itself) and tax revenues Number of beneficiaries and other parameters required under SDP (i.e. involvement of locals in CRM programs, Health statistics, etc)
Review of complaints records and outcome of dredging events to community to guide future management strategy.
Weekly Barangay Mercedes
HR, CSR Staff (contractor) or authorized department of the municipal government, affected barangays
Included in the SDP fund
Negative feed- back to the company
Formal com- plaint lodged by the community
Multiple complaints feed to local media organizations
Company to investigate/ inspect subject of negative feedback Coordinate with the barangay and MMT
Validate previous findings in coordination with stakeholders Coordinate with the concerned LGUs and MMT
Immediate consultation with the MMT and the LGU to resolve issue/s Release an official statement to clarify the issue/s. Monitor and report results on implementation of resolution.
Key informant interviews; Census and surveys in Coordination with the affected barangays;
Quarterly
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 54 of 58
Health and safety impacts from reclamation activities
Safe man-hours
Incident reporting, regular monitoring integrated in the Health and Safety Plan of the company
Daily inspection of work conditions, PPEs and compliance to the company’s Health and Safety Plan
Project site and vicinity
Safety Officer
Minimal cost
Negative feed- back to the company
Formal com- plaint lodged by the community and/or employees
Multiple complaints feed to local media organizations
Company to investigate/ inspect subject of negative feedback;. Improvement of health and safety measures to address negative feedback
Revalidate previous investigation results- reason for complaint and address complaint immediately through consultations with employees, contractors or affected stake- holders Improvement of health and safety measures to address negative feedback
Immediately conduct consultations or dialogues with complainants and affected stake-holders to determine reason for complaints. Address the complaints and document the responses and actions that will be done Release an official statement to media to clarify the issue Make improvements on health and safety plan to reflect the
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 55 of 58
actions that were conducted so a repeat of the incident or complaints will not happen.
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 56 of 58
Environmental Aspect
Potential Impacts Parameters
Environmental Monitoring Form Lead
Person
Annual Estimate
d Cost
Environmental Quality Performance Level (EPQL) Management
Method Frequency
Location EPQL Range Management Measure
Alert Action Limit Alert Action Limit Navigational restriction and Traffic congestion
Visual inspection to ensure navigation is not restricted and land traffic situation
Adjust vessel movement and location accordingly and Implement the necessary traffic management scheme
Daily Project site and vicinity
Contractor / Proponent
Included in the project cost
Negative feed- back
Formal com- plaint lodged by the community and/or other stake-holders (e.g. other business centers in the area)
Multiple complaints
Proponent to investigate/ inspect subject of negative feedback; Improvement of traffic management plan / measures to address negative feedback
Revalidate previous investigate result on reason for complaint and address complaint immediately through consultations with affected stake-holders Improvement of traffic management plan / measures to address negative feedback
Immediately conduct consultations or dialogues with complainants and affected stakeholders to determine reason for complaints. Address the complaints and document the responses and actions that will be done; Release an official statement to media to clarify the issue; Improvement of traffic management plan / measures to address
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 57 of 58
Environmental Aspect
Potential Impacts Parameters
Environmental Monitoring Form Lead
Person
Annual Estimate
d Cost
Environmental Quality Performance Level (EPQL) Management
Method Frequency
Location EPQL Range Management Measure
Alert Action Limit Alert Action Limit negative feedback and to reflect the actions that were conducted so a repeat of the complaints will not happen.
EIS for the Proposed Barangay Mercedes Reclamation Project
Executive Summary | Page 58 of 58
Environmental Management Fund and Environmental Guarantee Fund Commitments Upon the issuance of the ECC, a financial grant to support the multi-partite monitoring team is distributed in accordance with the approved Work Plan and Financial Plan by the Proponent. A summary of the Environmental Management Plan is shown below. The Proponent will also set aside a fund to support the immediate clean-up and rehabilitation of areas directly affected by the Project during the construction, operation and abandonment phase. This includes compensations to communities afflicted by the project, not limited to the parties’ preparedness programs, and environmental-related projects to sustain any impending risks that may deteriorate the environment in direct consequence of the project phases.
EIS for the Proposed Barangay Mercedes Reclamation Project
1 Project Description |
Table of Contents
1 PROJECT DESCRIPTION ............................................................................................................ 4 1.1 Project Location and Area 4
1.1.1 Direct Impact Area (DIA) ............................................................................................ 11 1.1.2 Indirect Impact Area (IIA) ........................................................................................... 11
1.2 Project Rationale 14 1.3 Project Alternatives 15
1.3.1 Project Siting .................................................................................................................. 15 1.3.2 Without Project Scenario .............................................................................................. 16
1.4 Project Components 16 1.4.1 General Layout of Facilities ......................................................................................... 16
1.4.1.1 Land Mass ............................................................................................................. 21 1.4.1.1.1 Dredging/ Filling ............................................................................................. 21 1.4.1.1.2 Soil Stabilization ............................................................................................... 23
1.4.1.2 Coastal Dike and Drainage Improvement ........................................................ 23 1.4.1.3 Internal Road Network ........................................................................................ 24 1.4.1.4 Utilities ................................................................................................................... 27
1.4.1.4.1 Drainage System .............................................................................................. 27 1.4.1.4.2 Water Supply System ...................................................................................... 28 1.4.1.4.3 Sewerage Collection System ........................................................................... 28 1.4.1.4.4 Power Supply System ..................................................................................... 30
1.4.1.5 Pollution Control Devices ................................................................................... 30 1.4.1.5.1 Water Pollution ................................................................................................ 30 1.4.1.5.2 Air Pollution ..................................................................................................... 30 1.4.1.5.3 Noise Pollution ................................................................................................. 30
1.5 Process/Technology 31 1.5.1 Reclamation Methodology .......................................................................................... 31
1.5.1.1 Dredging Equipment ........................................................................................... 32 1.5.1.2 Quarrying Methodology ..................................................................................... 32 1.5.1.3 Embankment Construction ................................................................................. 32 1.5.1.4 Construction Requirements ................................................................................ 33 1.5.1.5 Methods ................................................................................................................. 33 1.5.1.6 Protection During Construction ......................................................................... 34 1.5.1.7 Protection of Structure ......................................................................................... 34
1.6 Project Size 35
EIS for the Proposed Barangay Mercedes Reclamation Project
2 Project Description |
1.7 Development Plan, Description of Project Phases and Corresponding Timeframes 36 1.7.1 Project Duration and Schedule ................................................................................... 36 1.7.2 Description of Project Phases ...................................................................................... 37
1.7.2.1 Pre-Construction Phase ....................................................................................... 37 1.7.2.2 Construction/Development Phase ..................................................................... 38 1.7.2.3 Operational Phase ................................................................................................ 38 1.7.2.4 Abandonment Phase ............................................................................................ 38
1.8 Manpower 38 1.9 Project Cost 39
EIS for the Proposed Barangay Mercedes Reclamation Project
3 Project Description |
List of Tables
Table 1.1. Geographical coordinates of the proposed reclamation project (WGS 84 UTM Zone 51N) ......................................................................................................................................................... 4 Table 1.2. Description of Project Components ................................................................................ 19 Table 1.3. Summary of Major Construction Equipment ............................................................... 21 Table 1.4. Summary of Project Components and corresponding Process/Technology ............ 34 Table 1.5. Summary of Major Equipment ....................................................................................... 34 Table 1.6. Land Area of Facilities ...................................................................................................... 35 Table 1.7. Project Time Frame ........................................................................................................... 37 Table 1.8. Manpower Requirement during Construction Phase of the Project ......................... 39 Table 1.9. Summary of Quantities .................................................................................................... 40
List of Figures
Figure 1.1. Administrative Map .......................................................................................................... 7 Figure 1.2. Barangay Classification Map ........................................................................................... 8 Figure 1.3. Location Map of the proposed Barangay Mercedes Reclamation Project ................ 9 Figure 1.4. Location Map showing the Barangay Mercedes Reclamation Project .................... 10 Figure 1.5. Direct Impact Area Map ................................................................................................. 12 Figure 1.6. Indirect Impact Area Map .............................................................................................. 13 Figure 1.7. Project Component Map ................................................................................................ 18 Figure 1.8 Map showing the location of the site for the disposal of ............................................ 22 Figure 1.9. Typical design plan for the coastal dike component ................................................. 24 Figure 1.10. Road Network for the Barangay Mercedes Reclamation Project ........................... 25 Figure 1.11. Road Design: Typical Cross Section of Bypass Road ............................................... 25 Figure 1.12. Circulation Plan - Vehicular Route for the Barangay Mercedes ............................ 26 Figure 1.13. Circulation Plan - Main Pedestrian Route for the Barangay Mercedes Reclamation Project ................................................................................................................................................... 26 Figure 1.14. Circulation Plan - Bike Route for the Barangay Mercedes Reclamation Project .. 27 Figure 1.15. Infrastructure Map ........................................................................................................ 27 Figure 1.16. Drainage Map ................................................................................................................ 28 Figure 1.17. Green and Open Space Network ................................................................................ 28 Figure 1.18. Schematic Flow Diagram of the Membrane Aerated Biofilm Reactor and Aeration Basin ...................................................................................................................................................... 29 Figure 1.19. Proposed Land Use Plan of Barangay Mercedes Reclamation Project .................. 36
EIS for the Proposed Barangay Mercedes Reclamation Project
4 Project Description |
1 PROJECT DESCRIPTION
1.1 Project Location and Area The City of Catbalogan is the capital of the Province of Samar. It is located in the western seacoast of the said province, with the coordinates of 11 4636.83” north latitude and 124 5306.63” east latitude. It is approximately 800 kilometers southeast of Manila, the national capital, and 107 kilometers north of Tacloban City, the regional capital. It is bounded on the western side by Maqueda Bay; on its north by the municipalities of Tarangnan and San Jorge; and on the east by Jiabong. The Maharlika Highway traverses the City from the south thru Barangay Lagundi; while it enters thru Barangay San Vicente from the north. The total land area of the City is 274.22 square kilometers Its city proper covers an area of 130 hectares. There are 57 barangays in the entire city – twenty-one (21) of which are situated in the Poblacion; another 21 in the coastal area; while 15 barangays are in the interior and/or upland area. The proposed reclamation project covers an area of 35 hectares. It is located along the coastline of Barangays Mercedes, Poblacion 3, Poblacion 4, and Poblacion 5 in Catbalogan City, Samar as shown in Figure 1-1. Table 1.1. Geographical coordinates of the proposed reclamation project (WGS 84 UTM Zone 51N)
Point Longitude Latitude
1 124.867733 11.785858
2 124.867757 11.785628
3 124.867057 11.785272
4 124.869158 11.782533
5 124.871152 11.783234
6 124.870971 11.783878
7 124.871125 11.783971
8 124.870943 11.784424
9 124.871104 11.78453
10 124.871237 11.784324
11 124.872272 11.784712
12 124.872339 11.7849
13 124.872408 11.785042
14 124.872775 11.785088
15 124.873257 11.784911
16 124.873259 11.784619
17 124.873207 11.784331
EIS for the Proposed Barangay Mercedes Reclamation Project
5 Project Description |
Point Longitude Latitude
18 124.873834 11.784075
19 124.87421 11.784543
20 124.874516 11.78439
21 124.874765 11.78426
22 124.874955 11.78408
23 124.875153 11.783963
24 124.875416 11.78381
25 124.875507 11.783691
26 124.875457 11.782981
27 124.875248 11.7831
28 124.876002 11.783234
29 124.876244 11.783168
30 124.876546 11.782707
31 124.87568 11.781948
32 124.876364 11.78117
33 124.877451 11.781974
34 124.877675 11.781661
35 124.877068 11.781212
36 124.877562 11.7805
37 124.877901 11.780712
38 124.877972 11.780576
39 124.877023 11.779927
40 124.877274 11.779643
41 124.878424 11.780482
42 124.878547 11.780242
43 124.878524 11.780057
44 124.878697 11.779915
45 124.87857 11.779682
46 124.878678 11.779512
47 124.87857 11.779423
48 124.878742 11.779442
49 124.878745 11.779233
50 124.879253 11.779038
51 124.879114 11.778928
EIS for the Proposed Barangay Mercedes Reclamation Project
6 Project Description |
Point Longitude Latitude
52 124.879138 11.7787
53 124.879291 11.778801
54 124.879291 11.778638
55 124.879387 11.778756
56 124.879455 11.778431
57 124.878199 11.778411
58 124.86921 11.781867
59 124.869032 11.781936
60 124.869013 11.782365 61 124.866815 11.785294
EIS for the Proposed Barangay Mercedes Reclamation Project
7 Project Description |
Source: City Planning and Development Office of Catbalogan City, Samar
Figure 1.1. Administrative Map
EIS for the Proposed Barangay Mercedes Reclamation Project
8 Project Description |
Figure 1.2. Barangay Classification Map
EIS for the Proposed Barangay Mercedes Reclamation Project
9 Project Description |
Source: City Planning and Development Office of Catbalogan City, Samar Figure 1.3. Location Map of the proposed Barangay Mercedes Reclamation Project
EIS for the Proposed Barangay Mercedes Reclamation Project
10 Project Description |
Source: Google Earth, 2021
Figure 1.4. Location Map showing the Barangay Mercedes Reclamation Project
EIS for the Proposed Barangay Mercedes Reclamation Project
11 Project Description |
1.1.1 Direct Impact Area (DIA) Based on the revised procedural manual of DAO 2003-03, the direct impact area (DIA) is the area where all project facilities are proposed to be constructed and/or situated and where all operations are proposed to be undertaken. For most projects, the DIA is equivalent to the total area applied for an ECC. Given this,, the primary impact area is the total land and water area covered by the implementation and operation of the said project, which is within Barangay Mercedes. The following are considered as the DIA, as shown in Figure 1-5:
a. The total 35-hectare land mass to be built, wherein all the construction activities will take place
b. Barangays Mercedes, Poblacion 3, Poblacion 4 and Poblacion 5 in Catbalogan City, wherein the reclamation area will be constructed;
c. The location of borrow fill materials, designated by the PLGU of Samar; and d. The site for the disposal of the dredged out unsuitable bed materials.
1.1.2 Indirect Impact Area (IIA)
Generally, this refers to the influence area that could be indirectly affected by the proposed project. These include various industries and establishments such as industrial, commercial, medical, education, food chains, supermarket, gasoline stations, hotels and inns, restaurants and other shops and stores. The following are considered as the IIA, as shown in Figure 1-6:
a. Adjacent barangays and the whole City of Catbalogan, wherein construction materials and equipment will be sourced;
b. Access roads for hauling of construction materials, equipment mobilization, and the place from which most of the construction workers will come; and
c. The Social Impact Area (SIA) – which is the whole City of Catbalogan as it would benefit in terms of employment and livelihood opportunities, taxes paid, and an additional land area for development purpose.
EIS for the Proposed Barangay Mercedes Reclamation Project
12 Project Description |
Figure 1.5. Direct Impact Area Map
EIS for the Proposed Barangay Mercedes Reclamation Project
13 Project Description |
Figure 1.6. Indirect Impact Area Map
EIS for the Proposed Barangay Mercedes Reclamation Project
14 Project Description |
1.2 Project Rationale Coastal cities have long struggled to accommodate urban growth given the difficulties of finding space within geographically constrained and densely populated areas. However, because of innovative dredging techniques introduced over the last few decades, land can nowadays be reclaimed under advantageous economic conditions. Having to cope with pressing urbanization trends, coastal cities have a lot to gain from the more competitive costs of reclamation. Reclaimed areas can make strategic spatial development plans feasible in overcrowded areas and can be used to accommodate the demand for new housing, employment, transport, and other urban facilities. This enables the alleviation of congestion and the enhancement of urban services so as to remain attractive locations to both people and businesses. These functions are of relevance for the entire community, since they produce positive returns not only for investors and users, but for the overall quality of life and competitiveness of the locality. The objective of the Provincial Government of Samar in reclaiming and developing additional areas is to provide much needed space for business, residential, and government facilities. It will support the accelerated and balanced growth of Catbalogan City and the Province of Samar, and will also help generate much-needed employment and additional revenues for the continuous development and provision of basic social services for the residents. This creation of new land through reclamation aims to develop the newest and most vibrant destination in the Province – thus merging tourism, business, and leisure in order to become the center for growth in the commercial, residential and recreational sectors. The Mercedes Reclamation Project will benefit the Province of Samar through the following:
a. Catbalogan City will have additional land areas for expansion and development; b. The City will have new saleable and leasable prime properties; c. The reclamation project will generate opportunities for local employment; d. The construction and eventual operation of the project will generate additional
revenues through taxation, permits, and licenses; e. The project will become a new destination for local and international tourists; f. The project is envisioned to be an ecologically-friendly city destination which gives
importance to the conservation of local flora and fauna; and g. The reclamation project will serve as a buffer, thus protecting adjacent inland
properties from storm surge.
EIS for the Proposed Barangay Mercedes Reclamation Project
15 Project Description |
1.3 Project Alternatives
1.3.1 Project Siting The following criteria were considered for the selection of the proposed reclamation site:
1. No sensitive area (presence of mangroves, coral reefs, MPAs or any rich biodiversity area
The proposed reclamation project is not within a Marine Protected Area (MPA) nor are there presence of mangroves within the project site.
2. Minimal displacement of fishing access and communities There are two barangays which have affected residents due to the Project – Poblacion 3 and Mercedes. These residents shall be relocated to the fisherman’s village, which is one of the delineated zones within the proposed development. Additionally, there are no permanent fishing structures within the project site.
3. Bathymetry of the area Based from the bathymetry data, once the Mercedes Reclamation Project is in place, changes in the coastal configurations and topography of the coastline, and hence changes in bathymetry due to the project, are expected. However, the result shows that the computed changes will not significantly alter the existing bathymetry of the whole bay.
4. Land Use Plan The proposed Barangay Mercedes Reclamation Project is aligned with the proposed land use plan and development goals of the City Government. It should also be noted that the Philippine Reclamation Authority (PRA) has issued a clearance for the project site in a Memorandum of Understanding dated October 3, 2018. PRA is the primary agency responsible for the integration, direction, and coordination of all reclamation projects for and on behalf of the National Government. Given this, all reclamation projects shall be approved by the President upon the recommendation of the PRA. The former has given the go signal to the PRA to engage in massive land reclamation all over the country through Public-Private Partnerships (PPP) with the adoption of the Philippine Reclamation Authority Resolution 4161 (Approval of the National Reclamation Plan) on February 25, 2011.
5. Economic growth Considering the whole stretch of the Catbalogan City shoreline facing the Samar Sea, there are other possible sites for the reclamation project – Barangays Maulong and Payao, which are located north of Mercedes; and Barangays Guinsorongan and Bunuanan, which are located to the south of Mercedes.
EIS for the Proposed Barangay Mercedes Reclamation Project
16 Project Description |
However, only the Barangay Mercedes site has been found suitable for two reasons: it is the nearest barangay to the central business district of Catbalogan City; and there are two ports are adjacent to it – namely, Pier Uno and Pier Dos.
1.3.2 Without Project Scenario
Without the project, the area will remain part of the Samar Sea. Economic activity as well as the local population will continue to increase within the next decade. While the government has been trying to decongest economic activities, the Poblacion parts of the City will remain as the central economic zone. Traffic congestion will also worsen since no new roads will be constructed along the seaside portion of Barangay Mercedes. Furthermore, as the population growth continues to correlate with the economic activities in the City, there will be a lack of urban spaces to accommodate the urban development requirements. The absence of this additional spaces will also reduce the City’s attractiveness as a tourism spot and as an investment haven, thus resulting in deterred business and livelihood opportunities.
1.4 Project Components The major components of this project are the following:
1. Land mass 2. Infrastructure
a. Coastal Dike/Containment Structure and Drainage Improvement b. Internal road network
3. Utilities a. Water supply system b. Drainage system c. Sewerage collection system d. Power distribution system
1.4.1 General Layout of Facilities
The footprint of proposed project layout facilities is shown in Figure 1-7. During the Operation Phase, locators should follow the design concept of the reclaimed area based on its containment and/or carrying capacity. Given this, the proposed island has designated areas – the middle of the island is designated as a high-density area; the waterfront area is a low-density area; and the in-between areas are classified as mid density. All locators should also comply with all the following: existing ordinances of the City Government of Catbalogan; P.D. No. 1096, the 1977 National Building Code of the Philippines (NBCP) and with its 2004 Revised Implementing Rules and Regulations (IRR); the Electrical Code of the Philippines; the Clean Water Act; the Clean Air Act; the Safety Code of the
EIS for the Proposed Barangay Mercedes Reclamation Project
17 Project Description |
Philippines; and all recent and new issuances by the Department of Public Works and Highways (DPWH) pertaining to buildings and grounds. The design criteria of the structures should comply with the following:
1. The building height (including spires/towers and parapet walls) should not exceed 30-storeys or 90 meters, as duly qualified by CAAP aerodrome restrictions;
2. The Gross Floor Area (GFA) and Total Gross Floor Area (TGFA) must both be based on the Floor Area Ratio (FAR) 6 to 12;
3. Seismicity factors should be only as allowed under the 2016 National Structural Code of the Philippines (NSCP) or its most recent edition;
4. The 2015 Philippine Green Building Code; and 5. The Implementing Rules and Regulation of P.D. No. 957 of the Housing and Urban
Development Coordinating Council, including new issuances by the Housing and Land Use Regulatory Board (HLURB).
EIS for the Proposed Barangay Mercedes Reclamation Project
18 Project Description |
Figure 1.7. Project Component Map
EIS for the Proposed Barangay Mercedes Reclamation Project
19
Project Description |
Description of project components for the proposed project is presented in Table 1-2.
Table 1.2. Description of Project Components
Component Materials Size/Capacity Safety Features (during project implementation)
Land mass Filling materials 35 hectares (approximately 517,440.12 cubic meters estimated volume of filling materials)
Use of proper navigational equipment; use of safety gears and well-maintained equipment
Coastal dike and drainage improvement
Concrete, steel bars and structures
1,250 linear meters Use of proper equipment and Personal Protective Equipment (PPE)
Internal road network
Sub-base materials, concrete and asphalt pavement materials
1. Bypass Road: a. 4 Main Vehicular Lanes (2 each way) – 3.30 meters lane width b. One way designated bike lane – 3.00 meters lane width 2. Coastal Road: 4 Vehicular lanes a. Fast lane (1 each way) – 3.30 meters lane width b. Slow lane (1 each way) – 2.50 meters lane width 3. Waterway Boulevard: a. 4 Vehicular Lanes (2 each way) – 3.00 meters lane width b. One way designated bike lane – 1.25 meters lane width 4. Promenade Road: a. 4 Vehicular Lanes: Fastlane (1 each way) – 3.50 meters lane width; Slow lane (1 each way) – 2.50 meters lane width b. Two way designated bike lane – 2.50 meters lane width 5. Secondary Road: a. 3 Vehicular Lanes: Fast
Use of Personal Protective Equipment (PPE)
EIS for the Proposed Barangay Mercedes Reclamation Project
20
Project Description |
Component Materials Size/Capacity Safety Features (during project implementation)
lane (1 each way) – 3.30 meters lane width; Slow lane (1 way) – 2.50 meters lane width b. One way designated bike lane – 1.20 meters lane width (Final quantities are to be determined after the detailed design)
Utilities 1. Water supply
system 2. Drainage
system 3. Sewerage
system 4. Power
distribution system
Reinforced conc. pipes, UPVC pipes, UPVC or PE pipes, poles and power lines
1. Water reservoir: four units, 200,000 gallons each
2. Six catchment basins and two retention ponds
3. Wastewater treatment plant: two units, 500,000 gallons each
4. Power interconnection: five electrical service points, 13.8 kV RMU
(Final quantities and sizes to be determined after the detailed design)
Use of proper equipment and Personal Protective Equipment (PPE); use of highly skilled linemen/electrician and protective/safety gears
EIS for the Proposed Barangay Mercedes Reclamation Project
21
Project Description |
Table 1.3. Summary of Major Construction Equipment
Major Construction Equipments Quantity/Size
Dredging vessels 3
Backhoe 0.8 m3
Pay loader 1.5 m3
Vibratory roller 10 tons
Water truck 16 m3
Bulldozer 20 tons
Dump truck 12 yd3
Road grader 140 HP
Concrete screed 5.5 HP
Concrete transit mixer 5 m3
One bagger mixer 4-6 ft3/min
Concrete vibrator 5.5 HP
Plate compactor 5 HP
Bar Cutter and Concrete Saw 7.5 HP
Standby generator set 700 kW
1.4.1.1 Land Mass
The area to be utilized for the project is approximately 35 hectares, located along the coastline
of Barangays Mercedes, Poblacion 3, Poblacion 4 and Poblacion 5. The estimated volume of
filling material is approximately 517,440.12 cubic meters, wherein the bulk of the materials
will be sourced out from land.
With Catbalogan City’s history of being susceptible to flooding, the development will utilize
a design grade elevation of +4.00 meters above sea level. To develop the island mass for the
proposed reclamation project, the following components/activities will be done:
1.4.1.1.1 Dredging/ Filling
The dredging operation shall involve the removal of 67,058 cubic meters of unsuitable
materials within the project area, while the filling operation shall involve the extraction of
suitable borrow materials from the source which are to be utilized in the reclamation area.
There shall be continuous extraction, transport, and placement activities in the project area
until the desired construction level is obtained to allow for installation of steel sheet piles and
the continuous filling up of the enclosed area until the final elevation is achieved.
EIS for the Proposed Barangay Mercedes Reclamation Project
22
Project Description |
Considering that the Mercedes coastline is made up of silted and clay sediment materials,
cutter suction dredgers are commonly used in dredging works because of their productivity
and mobility; and given that the coastline of Barangay Mercedes has both a confined area and
a shallow water area, the use of barge mounted clamshell crane or backhoe will be effective
in dredging for the extraction of the contaminated mud, and silted soil.
The identified site for the disposal of excavated materials is located inland, in Barangay
Bununan, with the distance between the project site and the disposal area being 2.72
kilometers.
Sea transportation is highly recommended for the transportation of excavated materials in
dredging works; an alternative can be the use of dump trucks for land transportation.
However, the latter can worsen the traffic flow of within the project site; thus, a traffic
management plan is necessary to ease the traffic congestion of the area.
Created b y Md S aiful A lam Saiffrom the Noun Project
Figure 1.8 Map showing the location of the site for the disposal of
excavated materials
EIS for the Proposed Barangay Mercedes Reclamation Project
23
Project Description |
Commonly-used equipment for digging and/or excavation are backhoes, payloaders, and
dozers; while the blasting method would require dippers, jumpers, priming needles, scraping
spoons, and tamping bars.
There are many local quarries which can be utilized as sources of filling materials in and
around the City of Catbalogan; still, the hauling cost should be considered, as it depends on
the travel distance required. The filling source in Barangay Lagundi is the closest, but it cannot
sufficiently fill the overall volume for the reclamation project.
The recycled materials (soft materials of fine sediment components such as clay and silt) are
not suitable for use directly in reclamation work without treatment; nevertheless, there is
reason to consider recycling soft materials obtained by dredging works for reclamation since
the procurement of good quality mountain sand is assumed to be difficult due to the limitation
of resources or productivity at the quarry.
For the transportation of filling materials, the quarry site is located inland 5 km southwest
from the city. The road to the site is narrow, with flat to rolling terrain. There are two ways to
access the project site: one is via the national road, while the second is via the by-pass road.
Therefore, construction of a temporary working road or access road should be considered in
the construction schedule.
1.4.1.1.2 Soil Stabilization
The current technique which is widely adopted in soil stabilization of reclaimed areas is the
surcharge loading with vertical drains method. It should be anticipated that the project area
will require soil stabilization with tolerable settlement required, or no settlement at all.
1.4.1.2 Coastal Dike and Drainage Improvement
The construction of the coastal dike aims to protect the western seaboard of Catbalogan City
against storm/tidal surge, while the drainage improvement will enhance the city’s existing
drainage system capacity in mitigating local flooding.
EIS for the Proposed Barangay Mercedes Reclamation Project
24
Project Description |
Figure 1.9. Typical design plan for the coastal dike component
1.4.1.3 Internal Road Network
The road network – which includes the main roads, interior secondary roads,
esplanades/promenades, coastal roads, sidewalks and curb & gutters – will service vehicular
traffic generated by the proposed developments within the area.
The Project is planned to:
1. Increase the transport system capacity and relieve traffic congestion in the City;
2. Open up the project site to additional land for commercial development; and
3. Improve road safety for vehicles and pedestrians
EIS for the Proposed Barangay Mercedes Reclamation Project
25
Project Description |
Figure 1.10. Road Network for the Barangay Mercedes Reclamation Project
Figure 1.11. Road Design: Typical Cross Section of Bypass Road
The proposed circulation system seeks to attain efficient mobility and connectivity for the
Mercedes Reclamation Project. A hierarchy of routes that loop within each respective zone
and which are strategically connected to the other zones and external areas is envisioned to
facilitate traffic.
EIS for the Proposed Barangay Mercedes Reclamation Project
26
Project Description |
Figure 1.12. Circulation Plan - Vehicular Route for the Barangay Mercedes
Reclamation Project
One special consideration is the green ‘walkable’ neighborhood throughout the development.
The major pedestrian routes shall connect the existing developments to the Waterfront Project.
Designated bike lanes shall also be introduced in all major roads, which shall loop throughout
the whole site.
These areas are compliant with the PRA Administrative Order 2019-15 which states that 5%
of the whole project area should be designated as green spaces.
Figure 1.13. Circulation Plan - Main Pedestrian Route for the Barangay Mercedes
Reclamation Project
EIS for the Proposed Barangay Mercedes Reclamation Project
27
Project Description |
Figure 1.14. Circulation Plan - Bike Route for the Barangay Mercedes Reclamation Project
1.4.1.4 Utilities
Figure 1.15. Infrastructure Map
1.4.1.4.1 Drainage System
The drainage system consists of network of pipelines (reinforced concrete pipe), covered
canals, box culvert, manholes, inlets and other appurtenant structures. These are generally
sited along the roadside and under the sidewalks. Retention ponds were designed as
impounding areas for the stormwater outfall from the barangays, before being discharged to
conveying canals and to the sea.
EIS for the Proposed Barangay Mercedes Reclamation Project
28
Project Description |
Figure 1.16. Drainage Map
Figure 1.17. Green and Open Space Network
1.4.1.4.2 Water Supply System
The proposed water supply system shall be connected to the Catbalogan City Water District.
As shown in Figure 1-14, there will be four (4) water reservoir areas, each having a capacity
of 200,000 gallons.
1.4.1.4.3 Sewerage Collection System
The proposed project will have two (2) units of wasterwater treatment plants, with the
capacity of 500 gallons each, as shown in Figure 1-15. The recommended technology to be
used is an advanced aerobic biological treatment based on Membrane Aerated Biofilm Reactor
EIS for the Proposed Barangay Mercedes Reclamation Project
29
Project Description |
(MABR) because of its cost-effectiveness, as compared to the conventional fine bubble aeration
system.
During the pre-treatment process, the raw wastewater is pumped into a pretreatment unit
where it is screened by an automatic coarse screen followed by a FOG separator. Wastewater
then flows to the EQ tank. The proposed sewerage system will be designed with an
equalization tank to allow the MABR unit to safely treat up to 120% of its average hourly
capacity. The pretreated wastewater then flows into a selector tank where the influent and
RAS streams are mixed and flow by gravity to the concrete tanks wherein the submerged
MABR modules allow for simultaneous nitrification and denitrification process removing
organic matter, total nitrogen and total phosphorous pollutants from the wastewater.
The solids content of the waste activated sludge pumped from the secondary settling tank
with a content of 1% solids will be thickened via belt press. It is expected that a fivefold
decrease in sludge volume will be achieved thru this process. Sludge produced after treatment
is further dewatered via addition of polymers and mechanical compaction for stabilization
and subsequent reduction of volume.
Figure 1.18. Schematic Flow Diagram of the Membrane Aerated Biofilm Reactor and
Aeration Basin
EIS for the Proposed Barangay Mercedes Reclamation Project
30
Project Description |
1.4.1.4.4 Power Supply System
The power supply requirement of the reclamation area shall be supplied by Samar Electric
Cooperative Inc. (SAMELCO) from their nearest existing transmission lines. Five (5) electrical
service points with a capacity of 13.8kV shall be installed, as shown in Figure 1-14.
1.4.1.5 Pollution Control Devices 1.4.1.5.1 Water Pollution
Dredging operations both in the reclamation and borrow materials site will create
environmental concerns regarding the generation of unsuitable materials. As a result,
disturbance in the nearby ocean and marine ecosystems may be observed caused by the
increase in turbidity and other possible suspended materials. One way of mitigating this
concern is through the use of appropriate dredging methodology and equipment. In line with
this, a containment structure shall be installed in the project site to ensure the prevention of
the spread of any unsuitable materials from the area of operations. Wall containment
structures consist of sheet piles installed around the perimeter. The general procedure in the
installation of sheet pile is the choice of a suitable driving system which is of fundamental
importance to ensure successful pile driving operation with due regards to safety.
1.4.1.5.2 Air Pollution
Air pollution for the reclamation project is expected to be minimal, but mitigating measures
are still listed as follows:
● The use of well-maintained equipment and vehicles/vessels. The sea vessels will be
utilizing internationally-accepted fossil-fuel driven equipment and will have their
individual smoke stacks;
● The use of efficient fuels; and
● The use of devices for fuel efficiency and Air Pollution Control Device (APCD)
onboard the vessels. The APCDs will be in accordance with maritime protocols such
as MARPOL 73/78 and applicable sections of the Philippine Clean Air Act (RA 8749)
1.4.1.5.3 Noise Pollution
Noise pollution is considered a minimal concern, as noise generating activities will be
confined during the day. As an effort to keep the noise at the lowest possible working levels,
equipment must be well-maintained and equipped with noise reduction devices.
The use of environmentally safe materials, construction methods that minimize waste, and
the collection of waste materials and their removal from site to a place of proper disposal will
be specified by the construction contract.
EIS for the Proposed Barangay Mercedes Reclamation Project
31
Project Description |
1.5 Process/Technology
Land reclamation demands extensive and elaborate planning. This will include identifying
suitable fill at a borrow area, selecting the appropriate equipment, executing extensive site
investigations and collecting hydrographic data.
1.5.1 Reclamation Methodology
Reclamation is a process of converting foreshore land, submerged areas or bodies of water
into land by filling or other means using dredge fill and other suitable materials. There are
several methods of land reclamation, depending upon the type of fill material, foundation
soil, topography of the seabed, the availability of equipment, and allowable fine material for
reclamation. The list of priorities when considering the feasibility of a land reclamation project
is selecting a borrow area, evaluations have to be made and these are based on the availability,
the suitability and the quality of the potential fill material. The nature of the fill and its in-situ
characteristics will influence the type of equipment, the means of transport, the method of
reclamation and the possible need for ground improvement techniques.
1. Sailing to the discharge / dumping point – As soon as the hopper dredge is fully
loaded, the suction tubes will be hoisted back on board and course will be set towards
the area for unloading the hopper dredge where it will sail as a regular cargo vessel.
2. Discharging and Dumping – There are several ways to discharge the hopper head:
a. Bottom dumping – The fastest way to unload is by discharging the load through
the opened bottom doors of the hopper. The vessel is exactly at the area where the
load will be discharged, the bottom doors open and the material is directly
dumped on site. A new cycle commences as soon as the load is fully dumped by
sailing back to the fill source.
b. Pumping – Some hopper dredgers are equipped with pumping facilities. This
enables them to pump the load on a floating pipeline directly into the reclamation
area. The hopper dredger will be connected via the bow connection on board to
this floating pipeline.
In this method, jets in the hopper will fluidize the sand in the hopper and pumps
will convey the mixture through the pipelines to the reclamation area.
For sections where pipeline route has to cover large/long distances over water
where it has to cross a surf zone or shipping channel, a submersible pipe resting
on the seabed is chosen.
c. Reclamation with a spray-pontoon – If bottom dumping is not possible, the
unloading done using a spray-pontoon. The spray-pontoon is connected to the
hopper dredge using a similar pipeline system, which will be moved over
prescribed tracks to deposit the load evenly over the required surface area.
EIS for the Proposed Barangay Mercedes Reclamation Project
32
Project Description |
1.5.1.1 Dredging Equipment
Dredging works are commonly described as removal of sediments from underwater which
involving excavation process. Unsuitable materials, silted sand and contaminated soil are
excavated for channel and harbor deepening and for land reclamation. Mechanical and
hydraulic dredgers are commonly used in construction and trenching purposes.
Mechanical dredging is conducted using a barge-mounted clamshell crane or backhoe, which
excavate materials and places them into waiting barges, which are then towed to disposal
areas it is used in narrow and shallow wet areas.
Hydraulic dredging by using cutter suction dredger or Trailing Suction Hopper Dredger
(TSHD) is used mainly for then maintenance dredging of channels and specializes in dredging
‘soft and loose’ deposit materials in a wide range area.
The total volume to be extracted for the Mercedes coastline reclamation project (Phase 1) is
about 162,168.08 cubic meters With an area of 108,112.05 square meters and a depth of 1.5
meter contaminated mud and silted sand.
1.5.1.2 Quarrying Methodology
Quarrying is the process of removing rock, sand, gravel or other minerals from the ground in
order to use them to produce materials for construction or other uses.
There are several types of methodology in quarrying (i.e., digging, heating, wedging, and
blasting) but the commonly used in locality are digging or excavation and blasting.
• Digging: In this method, granular materials are excavated with the help of suitable
instruments. This method is useful when soft stones occur at low levels in the ground.
• Blasting,: This method is used when hand rocks having no fissures or cracks are to be
broken down the rocks and convert into small pieces by using explosive devices.
The total volume to be hauled out for quarry is about 517,436 cubic meters to reclaimed the
102,112.05 square meters with an average height of 3.83 meters.
1.5.1.3 Embankment Construction
The construction of embankment in accordance with the specifications of the plans or as
established by the engineer will be utilized for the project. Borrow selected should be soil of
such gradation that all particles will pass a sieve with 0.75 millimeter square openings and
not more than 15 mass percent will pass the 0.075 millimeter sieve, as determined by AASHTO
T 11. In addition to that, the materials shall have a plasticity index of not more than 5, as
determined by AASHTO T 90, and liquid limit of not more than 30, as determined by
AASHTO T 65.
EIS for the Proposed Barangay Mercedes Reclamation Project
33
Project Description |
1.5.1.4 Construction Requirements
Prior to construction of embankment, all cleaning and grubbing shall have been performed in
conformity with the standards; with the area containing no deleterious matter upon
commencement of operations. The surface of the existing ground shall be compacted to a
depth of 150 millimeters and to the specified requirements, as shown on the Plans or as
directed by the engineer. Along with that, the top portions of the roadbed in both cuts and
embankments, shall consist of selected borrow for topping from excavations also as indicated.
Embankment construction shall consist of constructing roadway embankments, including
preparation of the areas upon which they are to be placed; the construction of dikes within or
adjacent to the roadway; and the placing and compacting of approved material.
1.5.1.5 Methods
a. Where there is evidence of discrepancies on the actual elevations and that shown on
the plans, a preconstruction survey referred to the datum plane used in the approved
plan shall be undertaken under the control of the engineer to serve as a basis.
b. Embankment of earth material shall be placed in horizontal layers not exceeding 200
millimeters, and shall be compacted as specified before the next layer is placed.
However, a thicker layer maybe placed if vibratory roller with high compactive effort
is used provided that density requirement is attained and as approved by the engineer.
c. When excavated material contains more than 25 mass percent of rock larger than 150
millimeters in greatest diameter and cannot be placed in layers of the thickness
prescribes without further breaking down the pieces resulting from excavation
methods, such materials may be placed on the embankment in layers not exceeding in
thickness the approximate average size of the larger rocks but no greater than 600
millimeters.
d. The placing of individual rocks and boulders greater than 600 millimeters in diameter
will be permitted provided that they do not exceed 1200 millimeters in height when
placed and are carefully distributed to form a dense and compact mass
e. Each level shall be leveled and smoothed with suitable leveling equipment and by
distribution of spalls and finer fragments of earth.
f. Dumping and rolling areas shall be kept separate, with no lift covered by another until
compaction complies with the requirements.
g. Hauling and leveling equipment shall be so routed and distributed over each layer of
the fill in such a manner as to make use of compaction effort afforded thereby and to
minimize rutting and uneven compaction.
Before commencing the formation of embankment, an approval in writing should be
submitted by the contractor to the engineer containing his proposals for the compaction of
each type of fill material to be used. The proposal should also include the relationship between
the types of compaction equipment, the number of passes required, and the method of
adjusting moisture content. Compaction trials with the main types of fill materials to be used
in the project shall be completed before work with the corresponding materials will be
allowed to commence.
EIS for the Proposed Barangay Mercedes Reclamation Project
34
Project Description |
When the compaction is in progress, the contractor shall adhere to compaction procedures
found from the compaction trials for every type of material and equipment utilized, as well
as, each degree of compaction specified.
1.5.1.6 Protection During Construction
During the construction, embankments shall be maintained in such condition that it will be
well drained at all times. Side ditches or gutters emptying from cuts to embankments or
otherwise shall be so constructed as to avoid damage by erosion.
1.5.1.7 Protection of Structure
If embankments can be deposited on one side only of abutments, wing walls, piers, or culvert
headwalls, care shall be taken that the area immediately adjacent to the structure is not
compacted to the extent that it will cause overturning of, or excessive pressure against the
structure.
Table 1.4. Summary of Project Components and corresponding Process/Technology
Project Component Process/Technology Land mass Reclamation method
Infrastructure 1. Coastal Dike and Drainage
Improvement
2. Road Network
Construction
Utilities 1. Water Supply System
2. Drainage System
3. Sewerage Collection System
4. Power Distribution System
Distribution and construction
Table 1.5. Summary of Major Equipment
Major Equipment Estimated Quantity/Size
Dredging vessels 3Backhoe 0.8 m3Pay loader 1.5 m3Vibratory roller 10tWater truck 16 m3Bulldozer 20tDump truck 12 yd3Road grader 140hpConcrete screed 5.5hp
EIS for the Proposed Barangay Mercedes Reclamation Project
35
Project Description |
Major Equipment Estimated Quantity/Size
Concrete transit mixer 5m3One bagger mixer 4-6 ft3/minConcrete vibrator 5.5hpPlate compactor 5hpBar cutter, concrete saw 7.5hpStandby generator set 700kW
1.6 Project Size
The proposed reclamation project covers an area of 35 hectares. It is located along the coastline
of barangays Mercedes, Poblacion 3, Poblacion 4, and Poblacion 5 in Catbalogan City, Samar.
The estimated volume of filling material is approximately 517,440.12 cubic meters.
The Mixed-Use Institutional Zone can carry sports and civic buildings (e.g. arena, MICE
buildings, museum, theatre); the Mixed-Use Commercial Zone is comprised of the high-
density commercial/office and residential areas; while the first-class commercial areas and
business hotels will be in the Mixed-Use Tourism Zone. The Fisherman’s Village is the
resettlement site and marketplace for the public.
Table 1.6. Land Area of Facilities
Project Facilities Area (ha)
A. Saleable
Mixed-Use Institutional 3.71
Mixed-Use Commercial 6.79
Mixed-Use Tourism 7.42
Industrial 1.89
Sub-total A 19.81 B. Non-Saleable Utility & Transportation 2.00
Parks & Open Spaces 7.23
RROWs 4.00
Fisherman’s Village 1.96
Sub-total B 15.19 Grand Total 35.00
EIS for the Proposed Barangay Mercedes Reclamation Project
36
Project Description |
Figure 1.19. Proposed Land Use Plan of Barangay Mercedes Reclamation Project
1.7 Development Plan, Description of Project Phases and Corresponding Timeframes
1.7.1 Project Duration and Schedule
The implementation of the reclamation projects and its components has a four (4) year
construction period.
• Preparatory works such as detailed engineering design would take place right at the
start of the implementation schedule.
• The procurement of civil works will require three (3) months to complete. Reclamation
works would commence on the middle of the same year.
• A two (2) year period would be needed to allow the embankment to consolidate to
attain the allowable compaction of the land mass.
• The last activity that will be undertaken is the development of the site. Construction
of road network, coastal dike and drainage improvement and installation of different
utilities such as water, power, drainage, sewage, and telecommunication systems
would commence on the middle of fourth year.
EIS for the Proposed Barangay Mercedes Reclamation Project
37
Project Description |
Table 1.7. Project Time Frame
Project Description Year 1 Year 2 Year 3 Year 4
Quarter Quarter Quarter Quarter
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
A. Detailed Engineering Design
B. Procurement of Civil Works
C. Construction Phase
C.1. Reclamation (or construction)
C.2. Consolidation/stabilization
C.3. Site development (horizontal)
1.7.2 Description of Project Phases
1.7.2.1 Pre-Construction Phase
During the pre-construction phase, the Provincial Government of Samar is currently
conducting the following activities:
1. Preparation of the Project Feasibility Study;
2. Conduct of geotechnical investigation;
3. Conduct of marine and freshwater ecology assessment;
4. Conduct of hydrodynamic modelling;
5. Completion of the Detailed Engineering Design;
6. Conduct of the required Environmental Impact Assessment (EIA) and the subsequent
securing of an Environmental Compliance Certificate (ECC) for the project (the subject
of this application/study) and Area Clearance;
7. Securing of relevant permits, endorsements and clearances;
8. Procurement of construction services and of facilities;
The securing of clearances, permits, and all other administrative requirements of concerned
agencies will also be completed. The list of such concerned agencies are as follows:
1. Philippine Reclamation Authority
2. Philippine Ports Authority
3. Philippine Coast Guard
4. National Historic Commissions of the Philippines
5. Bureau of Fisheries and Aquatic Resources
6. Department of Public Work and Highways
7. Department of Information and Communications Technology
EIS for the Proposed Barangay Mercedes Reclamation Project
38
Project Description |
8. Philippine Navy
9. Department of Energy
10. Department of Tourism
11. National Mapping and Resource Information Authority
12. Department of Health
1.7.2.2 Construction/Development Phase
All activities during construction phase will involve the construction of components of the
project. Project features and components to be constructed include the road network, coastal
dike and drainage improvement, and the installation of different utilities such as water,
power, drainage, and sewerage collection system. The Barangay Mercedes reclamation project
is projected to be completed in four (4) years.
The detailed activities, potential impacts and proposed mitigating measures during the
construction phase is presented in Section 3 of this report.
1.7.2.3 Operational Phase
Once all the reclamation/construction activities are completed, an evaluation of all
construction activities will be undertaken as to whether improvements in schedule and
costing have been implemented.
The Operations Phase involves the construction of buildings and structures by various
locators and the operation of their activities. This phase is not included in the scope of this EIS
and in the application for an ECC.
1.7.2.4 Abandonment Phase
Given the nature of the project has a perpetual lifespan, the proponent must continue to
maintain and enhance the project components so that the project will be environmentally-
compliant and safe. Structures and equipment will be assessed regularly as the project
continues its operation.
However, in case abandonment of the project is necessary, all waste materials and garbage
left behind will be sorted for recycling and then will be sold to interested buyers, while the
residual wastes will be dumped in landfills (for non-hazardous wastes) or treated by third-
party waste treaters (for hazardous wastes).
1.8 Manpower
During the construction phase, the project will require about 184 personnel consisting of
experts and laborers. The manpower requirement during reclamation (or construction),
consolidation/stabilization, and site development (horizontal only) of the project is presented
in Table 1-8.
EIS for the Proposed Barangay Mercedes Reclamation Project
39
Project Description |
Table 1.8. Manpower Requirement during Construction Phase of the Project
Manpower Requirement Expertise/Skills Total Reclamation (or construction) Resident Engineer Structural Engineer Specialist 1
Material Testing Engineer Material Testing 1
Construction Engineer Civil/Structural 1
Geologist (on call basis) Engineering Geology 1
Laborers Skilled and Unskilled 100
Consolidation/stabilization Resident Engineer Structural Engineer Specialist 1
Geologist (on call basis) Engineering Geology 1
Heavy Equipment Operator Skilled labor 5
Laborers Skilled and Unskilled 20
Site development (horizontal) Resident Civil Engineer Structural Engineer Specialist 1
Resident Electrical Engineer Power Distribution 1
Resident Mechanical Engineer Sewerage/Septage Design 1
Laborers Skilled and Unskilled 50
Total 184
1.9 Project Cost
All expenses that will be incurred in the construction of the reclamation project, including its
supporting structures and facilities, are considered as implementation costs on the part of the
government.
The estimated project costs were based on the quantities using design drawings and
specifications prepared by the Provincial Engineering Office of Samar in conjunction with the
most appropriate scheme among alternative options that was considered in the study. The
cost estimates were based on the average prevailing prices of labor, materials and equipment
rentals in the area. The basic costs include all the relevant charges, which are usually borne by
the Contractor. The labor costs are inclusive of the minimum wage and of the cost of fringe
benefits required by Philippine laws and regulations. The costs of materials are inclusive of
supply, loading, sea and land transportation, unloading, storage and possible wastage.
The cost of the proposed Reclamation Project in Barangay Mercedes is estimated at
approximately 328.445 Million Pesos. This includes the direct and indirect costs of the project
accumulated within the different stages of construction.
EIS for the Proposed Barangay Mercedes Reclamation Project
40
Project Description |
Table 1.9. Summary of Quantities
Item No. Description Uni
t Quantity Unit cost Total Cost
PART I FACILITIES OF THE ENGINEER
A.1 Provide and Maintain Engrs. Office and Laboratory
L.s. 1.00 283,834.98 283,835
SUBTOTAL: 283,835 PART II OTHER GENERAL REQUIREMENTS
B.7 Construction Safety and Health L.s. 1.00 351,377.19 351,377 B.8 Reimbursables L.s. 1.00 5,832.08 5,832 B.9 Mobilization & Demobilization L.s. 1.00 93,704.00 93,704
SUBTOTAL: 450,913 PART III EMBANKMENT FROM BORROW (COMMON SOIL)
Embankment from Borrow (common soil) m3 517,440.12 633.33 327,710,352 SUBTOTAL: 327,710,352 TOTAL COST 328,445,100
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | i
Table of Contents 3 Environmental Management Plan ............................................................................................. 1
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 1
3 ENVIRONMENTAL MANAGEMENT PLAN In the previous chapter, all the environmental impacts on land, water, air and people during the construction of land mass and land development phase have been presented, the summary of the Environmental Management Plan (EMP) that was derived from baseline data, on impact wherein mitigation measures are required and impacts raise during the Public Scoping. All the mitigating measures will be implemented by the proponent, some of which will be monitored and supervised by other concerned government agencies. The cost of implementation for all the mitigating measures will be integrated in the operational budget of the proponent to make sure that the proper structures or systems are fully implemented. The impact analysis and proposed mitigation/management measures for the project phases are presented in the table below:
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 2
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity
Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
Pre-Construction Phase The Land Conduct of Environmental Impact Assessment and other related studies
Land Use and Classification
The proposed project is within ECA given that it is near the Maqueda Bay and a major river, the area is prone to flooding and storm surge.
The proponent will conduct a flood study and hydrodynamic modelling study to show the flood scenario without and with project. Appropriate alignment as well as tidal wall height will be incorporated in the detailed engineering design.
Presence of a flood study and hydrodynamic modelling study Incorporation of the recommendations on the actual design of the reclamation project.
Proponent Part of Feasibility and design cost
Compliance to requirements of the DENR and the National Building Code
Prior to Construction
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 3
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
Preparation of Detailed Engineering Design
Geology/Geomorphology
Geohazards (Liquefaction, risk due to earthquakes, inducement of subsidence), Storm surge, typhoons, tsunami Structural integrity of the project Climate Change and Sea Level Rise
The structural design of buildings should strictly follow other specifications set by the National Structural Code for Buildings (NSCB) and other relevant requirements specified in the National Building Code of the Philippines (NBCP). Maximum wave heights to be considered in the design of structures. For safety purposes, the higher PGA values should be considered in the design of the structures to be built.
With a detailed engineering design incorporating the results of the geotechnical study.
Proponent Part of Feasibility and design cost
Compliance to requirements of the PRA and the National Building Code
Prior to Construction
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 4
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
Consider factors and result in the hydrodynamic modeling and in the detailed engineering design.
The People Processing of all regulatory permits and clearances
People Safety and Compliance
Compliance to all Permitting and Clearance requirements with the LGUs and concerned government regulatory agencies (i.e. PRA, PCG, etc.)
All required permits must be secured before the implementation of the project.
Proponent/Contractor
Part of the initial cost project
Incorporated in the work and financial plan of the company
Start of Admin operations
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 5
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
Procurement of Infrastructure Project
Generation of local benefits/enhancement of emplyment
Employment Pooling and pre- qualification of possible contractors and manpower. Priority will be given to qualified residents of the host barangays/city.
Numbers of residents from the host barangays/city that were hired during the construction and operation of the project.
Construction Phase (Reclamation and Land Development) The Land Mobilization of personnel and offshore equipment/vessel and heavy equipment
Land Use and Classification
Solid waste generated from construction crews, which might be disposed on shore.
Littering, accidental spillage of any construction wastes should be avoided by pre-planning ways of their transportation and/or unloading at the temporary storage. Careful planning of the work activities can also reduce the
Presence of solid waste management plan and contigency plan prepared by the contractor and/or LGU. With hazardous waste generator ID secured from EMB Region 8
Proponent/PCO/ Contractor
Included as part of development Cost
Part of the project cost
To be implemented upon commencement of reclamation through land development.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 6
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
amount of waste generated.
Mobilization of personnel and offshore equipment/vessel and heavy equipment
Geology/Geomorphology
Increase in Ground Water Demand due to the influx of workers and their families in the residential area outside the reclamation site will lead to an increase in the consumption of groundwater. This could lead to over extraction of groundwater and would
The extraction of groundwater in the existing residential and industrial areas should be monitored and regulated to avoid the negative effects of subsidence due to over extraction of groundwater. Regular ground survey should be conducted to monitor ground subsidence. Rainwater harvesting during the rainy
Water consumption report from Catbalogan water district showing it is within the average monthly water consumption. Presence of rainwater harvesting facility
Proponent in coordination with the Local Water Providers
Included as part of development Cost
Part of the project cost
To be implemented upon commencement of reclamation through land development.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 7
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
contribute to ground subsidence.
season could be done to augment the water source. The community should also be trained on how to conduct rainwater harvesting and on proper water management.
Removal and Disposal of unsuitable materials
Terrestrial Ecology Oil and grease contamination of grazing areas that may further depress fish growth and recruitment, loss of fish habitats and reduction of primary productivity.
An oil and grease contingency, containment and recovery plan will be formulated in accordance with MARPOL protocols and enforced in all aspects of project operations. Remediation will include recovery
Presence oil and grease contingency, containment and recovery plan prepared by the contractor and/or LGU. Passed an environmental audit to show that the proponent and contractor are following the
Proponent/PCO/ Contractor
Included as part of development Cost
Part of the project cost
To be implemented upon commencement of reclamation through land development.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 8
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
and treatment of sludge. Carpools will be located farthest from the coast and driver system and all vehicle oil discards will be recovered.
conditions set by the DENR.
Removal and Disposal of unsuitable materials
Geology/Geomorphology
Siltation and transport of silt to other areas that may have marine resources
Silt curtains shall be installed in the reclamation area. This shall hold the silt within the area
Presence of silt curtains Zero or minimal siltation/sedimentation
Proponent/PCO/ Contractor
Part of the development budget of the project
Part of the project cost
To be implemented upon commencement of reclamation through land development.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 9
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
Fill of suitable materials to land mass level
Terrestrial Ecology Earth moving during reclamation works can generate sediment streams that, when not contained adequately, result to further river water discoloration and siltation, depth reduction and alteration, scouring and consequently the disturbance and modification of river habitat.
Establishment of series of silt curtains around the reclamation sites to prevent escape of sediments and terrigenous material disturbed during reclamation excavation and filling. Control measures will also include a series of sediment mitigation structures, including catchment and diversion canals to ensure that silt and sediments will not flow into the river estuary and enter the river system.
Presence of silt curtains Zero or minimal siltation/sedimentation
Proponent/PCO/ Contractor
Part of the development budget of the project
Part of the project cost
To be implemented upon commencement of reclamation through land development.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 10
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
Heavy equipment areas will be located away from waterways where erosion control measures can be easily applied. Reclamation operation material stockpiles shall be covered. As a precautionary approach, slurry walls will be built around areas where such slurries can emanate extensively.
Fill of suitable materials to land mass level
Geology/Geomorphology
Occurrence of ground subsidence, collapse, and heave.
Ground subsidence should be monitored continuously from the start of the reclamation and even after all constructions
No ground subsidence or settlement experienced.
Proponent/PCO/ Contractor
Part of the development budget of the project
Part of the project cost
To be implemented upon commencement of reclamation through land development.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 11
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
are finished. Proper compaction to be done by the contractor to reach the minimum allowable net bearing capacity
Fill of suitable materials to land mass level
Geology/Geomorphology
Aggravated flooding in nearby coast due to the reclaimed area which at inease siltation and erosion and impede tidal flushing
Adequate and efficient drainage design is recommended to prevent localized flooding at the site especially during heavy downpours. The drainage lines in the area should regularly be cleaned and maintained of waste materials. Proper waste management should be implemented.
Exisitng drainage system rehabilitated and new drainange constructed based on the result of the flood study.
Proponent/PCO/ Contractor
Part of the development budget of the project
Part of the project cost
To be implemented upon commencement of reclamation through land development.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 12
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
Construction of containment Wall/Sheet pile driving
Geology/Geomorphology
Though the project is not much affected by earthquake- induced landslides since it has flat terrain but the it is highly susceptible to lateral spread and flow failure since its offshore perimeter will form a steep slope rising above the seabed.
A properly anchored retaining structure that could hold in-place the reclaimed land should be constructed to mitigate this hazard. The slope of the fill should not be overly steepened to minimize slope failures.
Well constructed retaining structure Zero or minimal siltation/sedimentation
Proponent/PCO/ Contractor
Part of the development budget of the project
Part of the project cost
To be implemented upon commencement of reclamation through land development.
Construction of containment Wall/Sheet pile driving
Geology/Geomorphology
Soil erosion The edge of the reclamation area shall be placed with armor rocks that shall prevent waves to erode the soils being dumped.
Presence of armor rocks
Proponent/PCO/ Contractor
Part of the development budget of the project
Part of the project cost
To be implemented upon commencement of reclamation through land development.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 13
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
Compaction and Soil Stabilization
Geology/Geomorphology
Inducement of liquefaction
A detailed geotechnical investigation must be undertaken in case of construction of tall buildings (more than 3-storey) is planned to be erected at the site to determine the most suitable foundation scheme and the net bearing capacity as well as to identify any ground stability problem within the area.
No ground subsidence or settlement experienced.
Proponent/PCO/ Contractor
Part of the development budget of the project
Part of the project cost
To be implemented upon commencement of reclamation through land development.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 14
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
Compaction and Soil Stabilization
Geology/Geomorphology
Settlement: AMH study indicates that the reclaimed land would not settle uniformly.
To avoid excessive settlement in the reclaimed land, the fill should be engineered to improve its consistency. The fill should be designed to have the characteristic of a vibrocompacted sand fill. The soil that should be used for reclamation should not contain high amount of silty and clayey materials. Preferably, well-graded sand and gravel materials should be used. It should be mixed with stabilizing material such as cement.
No ground subsidence or settlement experienced.
Proponent/PCO/ Contractor
Part of the development budget of the project
Part of the project cost
To be implemented upon commencement of reclamation through land development.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 15
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
Installation of drainage system, sewer line system, water line system, construction of sewerage treatment plant and road network.
Land Use and Classification
Solid and hazardoues waste generated from construction crews, which might be disposed on shore.
Littering, accidental spillage of any construction wastes should be avoided by pre- planning ways of their transportation and/or unloading at the temporary storage. Careful planning of the work activities can also reduce the amount of waste generated.
Presence of solid waste management plan and contigency plan prepared by the contractor and/or LGU. With hazardous waste generator ID secured from EMB Region 8
Proponent/PCO/ Contractor
Included as part of development Cost
Part of the project cost
To be implemented upon commencement of reclamation through land development.
The Water Mobilization of personnel and offshore equipment/vessel and heavy equipment
Water Quality Degradation of marine water quality due to generation of solid and hazardous wastes brought by the reclamation
Solid and Hazardous waste management shall be strictly implemented in compliance with RA 9003 and RA 6969. A centralized treatment facility
Presence of solid waste management plan and contigency plan prepared by the contractor and/or LGU. With hazardous waste generator ID
Proponent/PCO/ Contractor
Part of the development budget of the project
Part of the project cost
To be implemented upon commencement of reclamation through land development.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 16
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
project activities.
can be established to ensure wastewater has been treated before discharging to any bodies of water
secured from EMB Region 8
Mobilization of personnel and offshore equipment/vessel and heavy equipment
Water Ecology Water availability and competition for use
IEC should be conducted by the City Government and the barangay for water conservation program and water reuse and recycling. Adaptation measures include protection of water aquifer, conduct of massive information and education campaign, establishment of protection
Water consumption report from Catbalogan water district showing it is within the average monthly water consumption.
LGU / Proponent as apart of their IEC and SDP program
Included in the IEC and SDP funding
Part of the project cost
May be initiated prior to construction
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 17
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
measures for coastal areas, and strengthening the protection of ecosystems.
Removal and Disposal of unsuitable materials and fill of suitable materials to land mass level
Marine Ecology and Water Quality
Oil and grease contamination from spills and vehicle maintenance can be very detrimental to benthic organisms in the shelf and may also cause migration of fish and crustaceans to other areas, leading to lower fisheries productivity.
An oil and grease contingency, containment and recovery plan will be formulated in accordance with MARPOL protocols and enforced in all aspects of project operations. Regular checking of all equipment including vessels or barges for leakage will be done.
Presence oil and grease contingency, containment and recovery plan prepared by the contractor and/or LGU. Passed an environmental audit to show that the proponent and contractor are following the conditions set by the DENR.
Proponent/PCO/ Contractor
Included as part of development Cost
Part of the project cost
To be implemented upon commencement of reclamation through land development.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 18
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
Carpools will be located farthest from the coast and driver system and all vehicle oil discards will be recovered.
Removal and Disposal of unsuitable materials and fill of suitable materials to land mass level
Marine Ecology Sustained sediment and silt loading can result to habitat alteration and the emigration of some crab population. Since the project is small and does not host sizeable crab populations, dredging and reclamation filling will
Implementation of Ecosystem Approach to Fisheries Management (EAFM) of the City Government of Catbalogan. Concervation of marine resources through the establishment of a Marine Protected Ares (MPAs).
Presence of a fisheries management plan incorporating the basic concepts of EAFM and prepared with the consutlation of affected fisherfolk organization. With a city ordinance for the establishment of an MPA. With an MPA management plan and functioning
Proponent/PCO/ Contractor
Included as part of development Cost
Part of the project cost
To be implemented upon commencement of reclamation through land development.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 19
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
result only to temporary and shallow disturbance of crab habitats and feeding regimen.
MPA management body.
Removal and Disposal of unsuitable materials and fill of suitable materials to land mass level
Water Quality High sedimentation rate during the dredging and reclamation operations and may lead to exceedance in the range of 5 to 10 mg/L total suspended solids. This will result to poor water quality.
Confinement of the suspended material to prevent accidental spillage during the transport and hauling of dredged materials for maintaining the environmental integrity of the coast zone. Individual dredgers should not be deployed near each other to lessen the concentration of
Presence of contingency plan prepared by the contractor and/or LGU. Passed an environmental audit to show that the proponent and contractor are following the conditions set by the DENR.
Proponent/PCO/ Contractor
Included as part of development Cost
Part of the project cost
To be implemented upon commencement of reclamation through land development.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 20
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
suspended sediments. The dredging track should be east-west and vice versa and as much as possible, should not run parallel to the shore as this area has shallower depths. Limit the dredging or reclamation activities in project areas near the shore especially during periods of calm wind or during low water levels.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 21
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
Compaction and Soil Stabilization
Marine Ecology Reclamation works can lead to sediment spills in the river estuary that may cause shallowing of navigational lane of the Catbalogan-Daram-ferry route.
Re-vegetation and stabilization of the reclaimed area will be a major strategy and a continuing program of the propoenent and this is designed to reinforce post-reclamation sediment management and will significantly help to minimize soil erosion and improve natural sediment accretion so that sediment spills into coastal waters are reduced even during construction of facilities and structures inside the reclaimed area.
Presence of open green space within the reclaimed area.
Proponent/PCO/ Contractor
Included as part of development Cost
Part of the project cost
To be implemented upon commencement of reclamation through land development.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 22
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
Installation of drainage system, sewer line system, water line system, construction of sewerage treatment plant and road network.
Water Quality Contamination of water / possible oil spills/leaks
Regular checking of all equipment including vessels or barges for leakage will be done. Moreover, oil spill kits will be ready in case there will be accidental spills. Institute and implementation of oil spill containment protocols should be followed during development in cases of occurrence.
Presence oil and grease contingency, containment and recovery plan prepared by the contractor and/or LGU. Passed an environmental audit to show that the proponent and contractor are following the conditions set by the DENR.
Proponent/PCO/ Contractor
Included as part of development Cost
Part of the project cost
To be implemented upon commencement of reclamation through land development.
Installation of drainage system, sewer line system, water line system, construction of sewerage treatment
Marine Ecology Wastewater from heightened personnel presence in the project’s operation and land-based facilities, combined
Wastewater from the reclamation works will not be disposed in waterways that ultimately contribute to coastal water pollution.
Water quality test result must be within the effluent standards set by DENR.
Proponent/PCO/ Contractor
Included as part of development Cost
Part of the project cost
To be implemented upon commencement of reclamation through land development.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 23
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
plant and road network.
with organic wastes and nutrients stirred up during soil-moving activities, can exacerbate seawater pollution.
Temporary containment ponds will be built, and the use of 3-chambered septic tanks shall be installed in all project facilities where wastewaters and other effluents are generated.
The Air
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 24
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
Removal and Disposal of unsuitable materials and fill of suitable materials to land mass level
Noise Increase in noise pollution during removal/dospisal of dredge materaials and filling of suitable materials.
Proper scheduling of high noise generating construction activities during the daytime to avoid sensitive periods; Maintaining equipment in good working order and fitting with appropriate noise control at all times; Ensure deliveries arrive and depart so as not to disturb residents at inconvenient times; Workers exposed to high-level noise will be issued with, and required to wear,
Presence of contingency plan prepared by the contractor and/or LGU. Passed an environmental audit to show that the proponent and contractor are following the conditions set by the DENR.
Proponent/PCO/ Contractor
Part of the development budget of the project
Part of the project cost
To be implemented upon commencement of reclamation through land development.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 25
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
appropriate Personal Protective Equipment (PPE); Undertaking construction activities in accordance with good practice; Setting noise limits.
Removal and Disposal of unsuitable materials and fill of suitable materials to land mass level
Air Quality Degradation of air quality due to dust and particulate matter generation and GHG generation.
Minimize heavy machinery during reclamation works. Regularly maintain diesel driven engines of transport vehicles, equipment and
Ambient air quality test result must be within the National Ambient Air Quality Standards set by DENR.
Proponent/PCO/ Contractor
Part of the development budget of the project
Part of the project cost
To be implemented upon commencement of reclamation through land development.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 26
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
barges and ensure they meet required emission levels for diesel vehicles.
Site preparation, excavation, and foundations construction
Meteorology/Climatology
Contribution in terms of greenhouse gas emissions (or GHG mitigation potential)
It is recommended that the proponent initiate enhancement programs related to carbon sink sequestration in line with the government’s greening program considering that a 35 hectare land mass will be generated as a result of the reclamation project.
With programs and projects implemented by the City and Provincial Govrenment that are aligned with the National Greening Program of DENR.
Proponent Included as part of development Cost
Project Cost To be implemented upon commencement of reclamation through land development.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 27
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
Construction of containment Wall/Sheet pile driving
Noise Increase in noise pollution during construction of contaimnment wall/sheet pile driving
Installation of temporary noise barriers such as galvanized iron shields will also be used particularly in noise-sensitive areas such as churches, schools and hospitals in the immediate vicinities of the construction area; Positioning of temporary site compounds as far as reasonably practicable from sensitive receptors; Use of site terrain, material stockpile and suitable work locations so as to screen work locations and
Noise level results must be within the NPCC maximum allowable noise level in general areas
Proponent/PCO/ Contractor
Part of the development budget of the project
Part of the project cost
To be implemented upon commencement of reclamation through land development.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 28
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
maximize the distance between work activities and receptors; Maintaining equipment in good working order and fitting with appropriate noise control at all times; Workers exposed to high-level noise will be issued with, and required to wear, appropriate Personal Protective Equipment (PPE); Undertaking construction activities in accordance with good practice.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 29
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
Removal and Disposal of unsuitable materials and fill of suitable materials to land mass level
Air Quality Degradation of air quality due to dust and particulate matter generation and GHG generation.
Minimize heavy machinery during reclamation works. Regularly maintain diesel driven engines of transport vehicles, equipment and barges and ensure they meet required emission levels for diesel vehicles.
Ambient air quality test result must be within the National Ambient Air Quality Standards set by DENR.
Proponent/PCO/ Contractor
Part of the development budget of the project
Part of the project cost
To be implemented upon commencement of reclamation through land development.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 30
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
Compaction and Soil Stabilization
Noise Increase in noise pollution during compaction and soil stabilization that may affect the receptors near the project.
Proper scheduling of high noise generating construction activities during the daytime to avoid sensitive periods; Maintaining equipment in good working order and fitting with appropriate noise control at all times; Ensure deliveries arrive and depart so as not to disturb residents at inconvenient times; Workers exposed to high-level noise will be issued with, and required to wear,
Noise level results must be within the NPCC maximum allowable noise level in general areas
Proponent/PCO/ Contractor
Part of the development budget of the project
Part of the project cost
To be implemented upon commencement of reclamation through land development.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 31
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
appropriate Personal Protective Equipment (PPE); Undertaking construction activities in accordance with good practice; Setting noise limits.
Removal and Disposal of unsuitable materials and fill of suitable materials to land mass level
Air Quality Degradation of air quality due to dust and particulate matter generation and GHG generation.
Minimize heavy machinery during reclamation works. Regularly maintain diesel driven engines of transport vehicles, equipment and
Ambient air quality test result must be within the National Ambient Air Quality Standards set by DENR.
Proponent/PCO/ Contractor
Part of the development budget of the project
Part of the project cost
To be implemented upon commencement of reclamation through land development.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 32
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
barges and ensure they meet required emission levels for diesel vehicles.
Site preparation, excavation, and foundations construction
Meteorology/Climatology
Contribution in terms of greenhouse gas emissions (or GHG mitigation potential)
It is recommended that the proponent initiate enhancement programs related to carbon sink sequestration in line with the government’s greening program considering that a 35 hectare land mass will be generated as a result of the reclamation project.
With programs and projects implemented by the City and Provincial Govrenment that are aligned with the National Greening Program of DENR.
Proponent Included as part of development Cost
Project Cost To be implemented upon commencement of reclamation through land development.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 33
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
Installation of drainage system, sewer line system, water line system, construction of sewerage treatment plant and road network.
Noise Increase in noise pollution during construction of contaim=nment wall/sheet pile driving
Installation of temporary noise barriers such as galvanized iron shields will also be used particularly in noise-sensitive areas such as churches, schools and hospitals in the immediate vicinities of the construction area; Positioning of temporary site compounds as far as reasonably practicable from sensitive receptors; Use of site terrain, material stockpile and suitable work locations so as to screen work locations and
Noise level results must be within the NPCC maximum allowable noise level in general areas
Proponent/PCO/ Contractor
Part of the development budget of the project
Part of the project cost
To be implemented upon commencement of reclamation through land development.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 34
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
maximize the distance between work activities and receptors; Maintaining equipment in good working order and fitting with appropriate noise control at all times; Workers exposed to high-level noise will be issued with, and required to wear, appropriate Personal Protective Equipment (PPE); Undertaking construction activities in accordance with good practice.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 35
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
Removal and Disposal of unsuitable materials and fill of suitable materials to land mass level
Air Quality Degradation of air quality due to dust and particulate matter generation and GHG generation.
Minimize heavy machinery during reclamation works. Regularly maintain diesel driven engines of transport vehicles, equipment and barges and ensure they meet required emission levels for diesel vehicles.
Ambient air quality test result must be within the National Ambient Air Quality Standards set by DENR.
Proponent/PCO/ Contractor
Part of the development budget of the project
Part of the project cost
To be implemented upon commencement of reclamation through land development.
The People
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 36
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
Mobilization of personnel and offshore equipment/vessel and heavy equipment
People Employment generation. Priority jobs for the men and women of direct and indirect impact areas
IEC on nature of jobs Consultation on job requirements and qualification Local hiring priority for qualified Barangay residents Skills training to upgrade local skills of residents that can be hired by the project Engagement of residents as manpower for the preliminaries and implementation pf the Coastal Resource Management Program Generation of
Numbers of residents from the host barangays/city that were hired during the construction and operation of the project.
Proponent/Contractor LGU / Barangay TESDA
Part of the operations budget of the project
Part of the project cost
To be implemented upon commencement of reclamation through land development.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 37
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
livelihood opportunities by putting-up food stalls, variety stores and other services near the Project
Removal and Disposal of unsuitable materials and fill of suitable materials to land mass level
People Impact of Climate Change
Vulnerability mapping should be conducted to identify priority households for evacuation. Non-structural disaster mitigation measures should be implemented in line with the
Presence of vulnerability asseessment and action plan to be implemented by the proponent.
Proponent / CRU / LGU
Included in the IEC and SDP funding
Part of the project cost
May be initiated prior to construction
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 38
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
LGUs Disaster Risk Reduction and Management (DRRM) plans.
Removal and Disposal of unsuitable materials and fill of suitable materials to land mass level
Peace and Order Unauthorized entry of outsiders and establishments which might cause problems in peace and order
Coordination with the Barangay LGU Tanods to ensure authorized establishments and control of unauthorized entry of outsiders Buffer zones should be established around the perimeter of the reclamation area during construction
Zero or minimal cases of unauthorized entry of outsiders.
MMMRP Community Relations Officer Security Force Barangay LGU & Tanods
Part of the operations budget of the project
Part of the project cost
Prior and during construction/reclamation
Removal and Disposal of unsuitable materials and fill of suitable materials to
Health and Safety Entry of migrant workers with families, which might cause
Management of entry of migrant workers.
Zero or minimal cases of migrant workers related problems.
• MHO Part of the operations budget of the project
Part of the project cost
Prior and during construction/reclamation
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 39
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
land mass level
problems of congestion, peace and order and security, breaches.
Removal and Disposal of unsuitable materials and fill of suitable materials to land mass level
Health and Safety The project may cause health problems due to diseases, overuse of public utilities /services, competition of resources, social conflicts, peace and order, increase in pollution due to solid, liquid and toxic wastes.
Increase and train Barangay tanods to be deployed in areas where migrant workers reside as well as the management of waste.
Zero or minimal cases of project related health problems.
• MMRLDP Community Relations • Barangay LGU • Barangay Tanod • Barangay Health Workers
Part of the operations budget of the project
Part of the project cost
Prior and during construction/reclamation
Removal and Disposal of unsuitable materials and fill of suitable materials to
Health and Safety Possible Health and safety risk in the operation of the reclaimed area due to
Proponent provide Health clinic with a Doctor, Nurse and Health workers
Zero or minimal cases of project related health problems.
• MMRLDP Community Relations • Barangay LGU • Barangay Tanod • Barangay Health Workers
Part of the operations budget of the project
Part of the project cost
Prior and during construction/reclamation
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 40
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
land mass level
noise and air pollution
Removal and Disposal of unsuitable materials and fill of suitable materials to land mass level
Health and Safety Possible accidents for workers
Orientations and strict implementation of safety practices will be done.
Zero or minimal cases of project related health problems.
Proponent/PCO/ Contractor
Part of the development budget of the project
Part of the project cost
To be implemented upon commencement of reclamation through land development.
Removal and Disposal of unsuitable materials and fill of suitable materials to land mass level
Health and Safety Health hazard to workers due to increased dust generation
Use of protective gears
Zero or minimal cases of project related health problems.
Proponent/PCO/ Contractor
Part of the development budget of the project
Part of the project cost
To be implemented upon commencement of reclamation through land development.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 41
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
Removal and Disposal of unsuitable materials and fill of suitable materials to land mass level
People Social unrest of sectors in the community, psycho-social impacts on communities surrounding the project and disturbance in their socioeconomic activities
The proponent initiate intensive IEC activities to update stakeholders on the status of the project, initiate programs that will promote livelihood, skills development, health and nutrition, disaster risk reduction and response and other similar activities as part of the proponent’s Social Development Plan. Alignment of the city resettlement program for settlers along the coastline with the preparation of a Resettlement Action Plan
With approved Resettlment Action Plan and implemented before the project commence.
Proponent/PCO/ Contractor LGU
Part of the project / IEC-SDP
Part of the project cost
To be implemented upon commencement of reclamation through land development.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 42
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
following R.A. 7279. and RA 10752. Proponent with the LGU to Implement appropriate sectoral consultations and IEC programs to raise project knowledge and awareness an community engagement
Construction of containment Wall/Sheet pile driving
People For offshore earthquakes capable of generating tsunami
Sustained community-level public education on tsunami awareness, preparedness and mitigation are still very important. Coastal communities must be aware of
Zero or minimal cases of project related tsunami hazards.
Proponent / CRU / LGU
Included in the IEC and SDP funding
Part of the project cost
May be initiated prior to construction
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 43
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
tsunami facts and must react appropriately during an earthquake at any time.
Compaction and Soil Stabilization
People Risk to flooding after the development of the reclamation project. Storm surge hazard and other Hazards
Storm surges are one of the many natural hazards that are difficult to control. Break waters and barriers may help or minimize the effect of coastal waves. Vigilance and awareness about storm surges must be undertaken with the help of PAGASA that regularly give weather information on the direction and strength of typhoon.
Zero or minimal cases of project related flood hazards.
Proponent / CRU / LGU
Included in the IEC and SDP funding
Part of the project cost
May be initiated prior to construction
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 44
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
Installation of drainage system, sewer line system, water line system, construction of sewerage treatment plant and road network.
People Increase in traffic flow causing air (dust) and noise pollution
Health certificate for workers prior to hiring into the project Implementation of the Social Development Program IEC on proper scheduling of hauler trucks and construction operations to avoid entry and dismissal of school children as well as late hours. Environment Risk Management for the operation of the Plant and surrounding communities
Noise level results must be within the NPCC maximum allowable noise level in general areas Ambient air quality test result must be within the National Ambient Air Quality Standards set by DENR.
• MMRLDP Community Relations • Barangay LGU • Barangay Tanod • Barangay Health Workers
Part of the operations budget of the project
Part of the project cost
Prior and during construction/reclamation
Demobilization Phase The Land
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Management Plan | 45
Activity Environmental
Component Likely to be Affected
Potential Impact
Options for Prevention or Mitigation or Enhancement
Efficiency of Measures
Responsible Entity Cost
Guarantee /Financial
Arrangements
Schedule of Implementation
Demobilization and clean up
Land : Sanitation Contamination due to improper waste disposal
Proper disposal of wastes, and as necessary/applicable through accredited waste transporters
Presence of plan prepared by the contractor and/or LGU. Passed an environmental audit to show that the proponent and contractor are following the conditions set by the DENR.
Proponent/Contractor/ PCO
Part of the environment al budget of the project
Part of the abandonment cost
To be implemented one (1) year prior and during demobilization phase
The Water Demobilization and clean up
Water Possible discrepancies with the baseline conditions
Mitigating measures will be done in case any damage was done in the area
Water quality test result must be within the effluent standards set by DENR.
Proponent/Contractor/ PCO
Part of the environment al budget of the project
Part of the abandonment cost
To be implemented one (1) year prior and during demobilization phase
The People Demobilization and clean up
People Possible damage on private properties, loss of employment for workers
Proper monetary compensation will be given in accordance to provisions of the law.
Presence of an Environmental Guarantee Fund
Proponent/Contractor/ PCO
Part of the environment al budget of the project
Part of the abandonment cost
To be implemented one (1) year prior and during demobilization phase
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Risk Assessment & Emergency Response Policy and Guidelines | i
Table of Contents
4 Environmental Risk Assessment (ERA) & Emergency Response Policy and Guidelines . 1
4.1 General Guidelines 1
4.2 Objective 1
4.3 Scope and Limitation 1
4.4 ERA Conceptual Framework 2
4.4.1 Environmental Risk Assessment Process .................................................................... 2
4.4.2 Methodology ................................................................................................................... 2
4.5 Environmental Risk Management Program 4
4.6 Emergency Response Procedure 4
4.6.1 Emergency Response and Preparedness Program .................................................... 5
4.6.2 Summary of Emergency Procedure ............................................................................. 5
4.6.3 Emergency Response Team ........................................................................................... 5
4.6.4 Emergency Plan ............................................................................................................... 5
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Risk Assessment & Emergency Response Policy and Guidelines | 1
4 ENVIRONMENTAL RISK ASSESSMENT (ERA) & EMERGENCY RESPONSE
POLICY AND GUIDELINES This Environmental Risk Assessment (ERA) was prepared for the proposed reclamation project. The ERA was undertaken in compliance with the scoping agreement between the Environmental Management Bureau (EMB), Provincial Government of Samar, City Government of Catbalogan and the Environmental Impact Statement (EIS) report preparer. 4.1 General Guidelines
1. One of the major decision points during the Scoping Process is the determination of the need by the project to undertake an Environmental Risk Assessment (ERA) or not.
2. As defined by DAO 2003-30, ERA is the use of universally accepted and scientific methods to assess the risks associated with a project. It focuses on determining the probability of occurrence of accidents and their magnitude (e.g., failure of containment or exposure to hazardous materials or situations.)
3. An ERA is not an entirely separate assessment but deals with the further analysis of hazards identified in the EIA. It builds upon the EIA such that risks are impacts where the likelihood of occurrence and magnitude of consequences are uncertain.
4. It should be noted that the ERA, within the context of Philippine EIS System, is concerned primarily with safety risks (characterized by low probability, high consequence, accidental nature and acute effects [human safety focus]). In contrast, geological risks are covered by the EGGAR requirement under the MGB while health risks (characterized by high probability, low consequence, ongoing or continuing exposure and chronic human health effects) are assessed in the environmental health impact assessment under the DOH mandate.
4.2 Objective This ERA aims to identify the hazards associated with the project, characterize the associated risks, and recommend measures to manage the identified risks. 4.3 Scope and Limitation The various physical and chemical environmental hazards associated with the project were analyzed. The ERA focused on safety risks, which are characterized by low probability, high consequence, accidental nature and acute effects, in compliance with the Procedural Guidelines for Scoping of Environmental Risk Assessment, Annex 2-7e of the Revised Procedural Manual of DAO 03-30) (EMB-EIAMD, 2007). The PAGASA- predicted climate changes, as expected by the years 2020 and 2050, were also taken into consideration. Risks from hazardous substances expected to be utilized and stored at the project site were qualitatively and quantitatively characterized. The scope of this ERA included the following aspects:
1. Hazard Identification;
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Risk Assessment & Emergency Response Policy and Guidelines | 2
2. Risk screening activity that included all identified hazardous substances projected to be used, handled, or stored at the proposed plant site to determine the type of environmental risk assessment to be conducted, and the focus of analysis;
3. Worst-case accident scenario analysis based on projected plant conditions and actual hazardous substance properties;
4. Application of appropriate modeling tools in consequence analysis; 5. Determination of the extent of hazard radii and areas; 6. Characterization of environmental risks associated with the project; and 7. Recommend measures to manage identified environmental risks.
4.4 ERA Conceptual Framework 4.4.1 Environmental Risk Assessment Process Environmental Risk Assessment (ERA), as defined in the Procedural Manual for DAO 2003-30, is “the use of universally accepted and scientific methods to assess the risks associated with a project. It focuses on determining the probability of occurrence of accidents and their magnitude (e.g. failure of containment or exposure to hazardous materials or situations.)”. Risk is defined as a measure of potential human injury/death, economic loss, or environmental damage in terms of the probability of the loss, injury/death or damage occurring and the magnitude of the loss, injury/ death or damage if it occurs. Risk involves two measurable parameters: consequence and probability. It is the integrated result or product of the calculated consequence of a postulated accident scenario and the calculated probability or frequency of occurrence of such event. 4.4.2 Methodology 4.4.2.1 Hazard Identification The various hazardous processes, activities and substances associated with the project were identified at this stage. Risk screening that included all substances to be used, handled and stored at the proposed reclamation site was conducted. The potential of each substance to pose hazards to the environment, the public and the facility was analyzed based on a thorough review of its intrinsic physical and hazard characteristics. Risk screening was done according to the process and criteria described in the Revised Procedural Manual of DAO 2003-30: Guidelines for the Conduct of Environmental Risk Assessment, particularly Annex 2-7e. The risk screening process determines the level of risk assessment that must be conducted. 4.4.2.2 Hazard Identification Environmental hazards associated with reclamation project are fire/explosion accident due to lube oil; inherent presence of high voltage electricity from equipment use in dredging; and occupational hazards (exposure heavy equipment use, extreme temperatures in work site, high voltage electricity, etc.). Liquefaction in the area is controlled by the intensity and duration of ground shaking, geological formation and amount of civil structure development in the area. It can occur near
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Risk Assessment & Emergency Response Policy and Guidelines | 3
or far (>100 km) from the epicentre. Liquefaction occurs in water-saturated unconsolidated sediment due to shaking. In areas underlain by such material, the ground shaking causes the grains to lose grain to grain contact, and thus the material tends to flow. Earthquakes, with magnitude as small as 5.5, can induce liquefaction hazard and can affect areas hundreds of kilometers away from its epicenter. Mitigation of the risks from liquefaction can be undertaken through engineering interventions: The expected impact of PAGASA’s predictions on climate change was also integrated in the risk analysis. The highest single month recorded during said period has a precipitation of 1,885.3 mm recorded in July 1972. Such amount of rainfall can raise the water table and can cause flooding and soaking of the overlying material that may possibly cause differential settlement aggravated by the weight of civil structures erected and may also trigger liquefaction. The rains are brought in mainly by the southwest monsoons, the inter-tropical convergence zone, local thunderstorms, and tropical cyclones. A comprehensive design of drainage system as mitigation for flooding will be prepared and implemented by the project proponent taking into consideration the mean amount of rainfall and the effect of PAGASA projection of 2050 climate change in the project area. Based on data provided by the project proponent, the substances that will be stored and used at the project site is lubrication oil use in the maintenance of equipment use in dredging/filling, pile driving, infrastructures and horizontal construction. 4.4.2.3 Risk Screening of Hazardous Substances at the Reclamation Site A risk screening procedure was undertaken to determine the type of environmental risk assessment to be undertaken and to prioritize the environmental risks presented by the hazardous substances and activities. The criteria and process used in risk screening was primarily based on Annex 2-7e (Guidelines for the Conduct of Environmental Risk Assessment) of the Revised Procedural Manual of DAO 2003-30. The screening criteria for hazardous substances are (1) inherent hazardous characteristics of the substance and (2) maximum quantity involved. After classifying the substances according to defined categories (i.e. flammable, oxidizing, toxic, etc.), their respective maximum inventories were compared to DENR’s threshold inventory levels (Levels 1 and 2), which are defined in the Revised DAO 2003-30 guideline. A facility that will manufacture, process or store any hazardous substance in excess of DENR’s Threshold Inventory Level 2 is required to undertake a quantitative risk assessment. Those with any hazardous substance exceeding Level 1 threshold inventory but below Level 2 threshold inventory is required to undertake Hazard Analysis Study, and Emergency/Contingency Plan based on the study and worst-case scenario.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Risk Assessment & Emergency Response Policy and Guidelines | 4
Figure 4-1. ERA Scoping Guidelines (Revised Procedural Manual for DAO 2003-30)
Referring to the above discussions there are no major hazards associated with the project, as presently planned, that will require a Quantitative Risk Assessment (QRA). Further, the threshold limits prescribed to require an ERA are not exceeded. Initial estimate of the heavy fuel oil inventory of the prospective dredging vessel and pile driving equipment is approximately 300 tons much lower than the threshold of 5,000 tons for “flammable substances”. 4.5 Environmental Risk Management Program The ERA was able to show that both societal and individual fatality risks from the reclamation project are low and are expected to be within acceptable limits based on DENR environmental risk criteria. Notwithstanding this positive ERA result, however, it would be for the interest of both the project proponent and the public that appropriate environmental measures and plan are formulated and implemented to further reduce risks. Identified environmental hazards and associated risks should be appropriately addressed. With due consideration to the balance between environmental protection/safety/lives protected and the costs of risk mitigation, risks should be reduced to as low as reasonably practicable. Major considerations in risk reduction are appropriate embankment/structural design; compliance with standards in the design, construction and maintenance of equipment and facilities; well- maintained safety systems; well-trained and motivated workforce; and the establishment of an appropriate emergency response and contingency systems. Table 4.2 below lists the recommended risk management measures for particular identified hazards. 4.6 Emergency Response Procedure
Scoping
MaterialinventoryexceedsLEVEL2
threshold?
MaterialinventoryexceedsLEVEL1
threshold?
Istheac<vitylistedincoveredprojectforrisk
screening
ProjectnotcoveredbyERA
PrepareQuan<ta<veRiskAssessment
PrepareEmergencyPlanbasedonHazardAnalysis
PrepareRiskScreening
Doesriskscreeningwarrantprepara<onof
emergencyplan?
yes
yes
no
yes
yes
no
no
no
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Risk Assessment & Emergency Response Policy and Guidelines | 5
This presents the emergency preparedness and response procedure of the Proponent during disaster scenario within and around the proposed project site. This guideline will also serve as the project’s framework in ensuring alertness and safety of all its staff and employees during untoward incidences that may happen while in the implementation of reclamation. Proponent should properly respond to emergencies caused by the process itself and/or natural occurrences. 4.6.1 Emergency Response and Preparedness Program Proponent has prepared an ERP to act as an administrative guide outlining the procedures for individuals that provide essential services should a major emergency occur. Its main purpose is to mitigate, control and avoid the damage of events that could negatively affect the organization’s ability to function. It also includes provisions to assess the severity of an incident and implement procedures to eliminate or lessen the problem. The responsibility of initiating emergency procedures that need to be implemented lies on the Plant Manager. The Construction Manager, together with all supervisors concerned and the Emergency Response Team (ERT) ensure that procedures are carried out with appropriate work instructions. The proponent coordinates closely with local authorities such as the police, fire department, hospital, and other concerned agencies during emergencies. 4.6.2 Summary of Emergency Procedure It is recommended that all employees should adopt these instructions to ensure safety among individuals. 4.6.3 Emergency Response Team An Emergency Response Team (ERT) shall be organized by the Proponent to ensure safety of its employees and property. The ERT shall implement all the necessary procedure for each kind of emergency that occurs within and around the work area. 4.6.4 Emergency Plan 4.6.4.1 Fires The objective of this plan is to ensure the safety of personnel as well as reduce if not to totally avoid damage to property and equipment. Likewise, it is intended to prevent or control the spread of fire. The alert notification system for fire incidents shall be based either on information received from the seafarers on board or the sounding of fire alarms. The following measures shall be established to ensure the safety of persons on the vessels in the event of a potential incident to which this regulation applies.
1. An alarm system shall be installed and a procedure has been established for activating the system;
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Risk Assessment & Emergency Response Policy and Guidelines | 6
2. A procedure shall be established for the prompt notification of rescue and firefighting teams;
3. A procedure shall be established for evacuating personnel; 4. All seafarers shall be adequately trained and retrained in emergency procedures and 5. The use of emergency equipment and facilities; and 6. Emergency drills shall be conducted on a regular basis.
4.6.4.1.1 Prevention The proponent shall hold a regular meeting to constantly monitor the strict implementation and assess the system’s efficiency to manage emergency situations. Besides the regular meetings, all engaged contractors shall be required to conduct their own monthly safety briefing discussing government mandated and company safety requirements. 4.6.4.1.2 Safety Inspection As a general rule, all vessels to be engaged are required to conduct a safety inspection at least once every quarter. On an annual basis, the Company shall inspect the whole facility for fire hazards and inefficiencies of the fire safety equipment installed. 4.6.4.1.3 Preventive Maintenance 4.6.4.1.3.1 Vessel All ship components that may pose fire hazard will be inspected for fire risk by a competent person. This inspection should include a check of:
1. the fuel system (integrity of the fuel tank filler cap, fuel lines and their connections as applicable);
2. electrical harness (adequacy of protection from rub and wear damage); 3. the emergency engine shutdown device (if operates in accordance with manufacturer's
specifications and is fail safe); 4. replacement of parts that are defective or that may pose fire hazard; and 5. the battery (integrity and is effectively protected from any adverse effects of heat).
Where a blow torch, welding, cutting or other hot work equipment is used in a location where a fire may endanger or may jeopardize the safety of persons, implementation of standard written procedures for the safe use of such equipment is essential. 4.6.4.1.4 Fire safety and Fire Fighting Facilities Procedures and suitable firefighting facilities should be in place and notices placed close to electrical installations to ensure correct procedures are followed in case of fire. Firefighting equipment is best located on the ventilation intake side of the hazard. 4.6.4.1.5 Training
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Risk Assessment & Emergency Response Policy and Guidelines | 7
A regular and effective training program is probably the most crucial factor in determining the success of personnel protection strategies. The management shall ensure that all personnel including those of the contractor shall have an understanding of the appropriate action to take in a fire emergency. Scheduled and random drills shall also be implemented within the project site. 4.6.4.1.6 Safety Awareness Information and education materials on safety will be posted on all boards and will regularly be provided to all personnel. Postings will also include the contact number/s that have to be contacted during emergencies. 4.6.4.1.7 Fire Emergency Response
1. Evacuate according to established company procedures, and obtain a head count confirming location of those accounted for and those missing.
2. Notify the captain or other senior official. 3. Any person who detects smoke or locates a fire shall attempt to extinguish it with the
closest available extinguisher. 4. If the fire cannot be immediately extinguished, the person shall raise the alarm by
shouting “fire” and initiating the nearest fire alarm pull station. 5. Check the evacuation plan and procedures for the vessel. 6. A vessel official or other senior official will conduct a head count and advise the
Central Health and Safety Office. 7. Evacuate to the predetermined safe area, record all names of workers, and check
numbers to determine whether any individuals are missing. 4.6.4.2 Storm / Typhoon 4.6.4.2.1 Preparedness All seafarers are required to participate in drills that will be conducted. These exercises may or may not have prior notice. 4.6.4.2.2 Emergency Response The alert for such situation shall be based on weather forecasts from PAGASA. Alert Levels will be designated to determine appropriate response procedures to be followed:
1. Public Storm Signal No. 1 – Level 1 2. Public Storm Signal No. 2 – Level 2 3. Public Storm Signal No. 3 – Level 3 4. Public Storm Signal No. 4 – Level 4 (Major Emergency)
4.6.4.2.2.1 Level 1
1. Regular updates shall be provided to all personnel through their supervisors.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Risk Assessment & Emergency Response Policy and Guidelines | 8
2. Employees and vessel personnel will be briefed on the course of actions to be done if the typhoon signal has elevated.
3. Level 2 procedure numbers 1, 2 and 3 may be initiated if typhoon is directly towards the vessel.
4.6.4.2.2.2 Level 2
1. Activation of the Emergency Response Team. 2. An initial meeting shall be initiated by the captain and land based officer, to plan the
overall actions required. The agenda should include: a. evaluation of possible evacuation of personnel; b. the evacuation planning for all personnel, vessel and equipment and other items;
and c. planning for the provision and protection of required resources of the evacuees
(food, water, medicines, standby power, fuel, transport and other basic needs) and other logistics such as hand held radios, laptop computers (for typhoon updates), cellular phones, satellite phones, standby vehicles and other required resources.
3. After the preliminary meeting, the Emergency Response Team shall ensure that coordinators are provided with an official communication to distribute to their supervisors and personnel.
4. In the event that the vessel needs to dock to a safe port, all personnel shall ensure that all equipment is evacuated or secured to designate areas. Non-priority resources may also be evacuated as time permits.
5. All electrical equipment should be waterproofed and moved away from possible wet areas (if any).
6. Equipment shall be securely anchored in a protected area. 7. All personnel should prepare for possible evacuation.
4.6.4.2.2.3 Level 3 and 4
1. The Emergency Response Team will determine the possible course of action to be
undertaken. Evacuate measures or to remain in the originally assigned areas shall be based on the assessment done during the preliminary meeting.
2. The Emergency Response Team leader shall only call for an evacuation upon confirmation by the Manager and/or the Head Office.
3. As a general rule, a first aider and a standby electrician should be stationed in preparation for possible emergencies.
4.6.4.2.3 Post Emergency Procedure Inspection after major storms shall be undertaken as the weather conditions permits to be able to evaluate the extent of possible storm damage. 4.6.4.3 Tsunami
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Risk Assessment & Emergency Response Policy and Guidelines | 9
The main damage from tsunami comes from the destructive nature of the waves themselves causing loss of lives and property. Secondary effects include debris acting as projectiles which then run into objects, erosion that can undermine the foundation of structures built along coastlines, and fires that result from disruption of gas and electrical lines. Other effects include loss of crops and water and electrical systems that could lead to famine and disease depending on the extent and gravity of the tsunami. Within the last century there have been 94 destructive tsunamis, which have resulted in more than 51,000 deaths. This statistics does not include the destructive tsunami effect brought about by the Japan earthquake in recent years. Despite the fact that tsunami warnings have been in place at most tsunami prone regions since 1950, loss of lives due tsunamis specially when the source earthquake is close to the shore where there is very little time for people to heed warnings and follow instructions associated with warnings. 4.6.4.3.1 Preparedness The vessel shall establish onboard emergency procedures posted or filed for the shipmaster to initiate upon receipt of the notice or warning. The ship’s communication system will be maintained to always have connection with the designated regional or local channel that releases tsunami warnings. All seafarers are required to participate in drills that will be conducted. These exercises may or may not have prior notice. 4.6.4.3.2 Emergency Response The alert for such situation shall be based on warnings from PHIVOLCS, PAGASA or other government designated agencies. 4.6.4.4 Hazardous / Noxious Liquid Material Spills (including Oil as applicable) 4.6.4.4.1 Prevention 4.6.4.4.1.1 Storage and Handling All hazardous materials must have a corresponding Material Safety Data Sheet (MSDS). The MSDS should be readily available in areas where the material is stored and/or handled. Hazardous materials should be properly labeled, stored and handled. Storage shall be at designated areas in accordance with specified separation distance and inventory limits (as applicable). Only duly approved containers or storage vessels shall be used for storage and handling. 4.6.4.4.1.2 Drills
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Risk Assessment & Emergency Response Policy and Guidelines | 10
All personnel are required to participate in drills that shall be conducted by the HSU. These exercises may or may not have prior notice. This exercise shall be conducted at least twice a year. 4.6.4.4.1.3 Personal Protective Equipment (PPE) The proponent shall eliminate the identified occupational hazards through the introduction of hierarchy control measures whereby the use of personal protective equipment shall be monitored and strictly implemented. The proponent shall comply, as provided for under the existing Safety and Health Standards, to provide employees free of charge personal protective equipment to ensure that their physical well being are amply protected while performing their assigned tasks. Employee shall be issued personal protective equipment in accordance with the type of occupational hazards that they may likely be continuously exposed to as determined by the Safety and Health Office. 4.6.4.4.2 Emergency Response Any spills shall be reported, contained and cleaned up promptly and properly in accordance with prescribed procedures particularly in accordance with the Marine Environment Protection Policies of the PCG.
1. Every ship of 150 gross tonnages and above certified to carry noxious liquid substances in bulk shall carry on board a shipboard marine pollution emergency plan for noxious liquid substances approved by the MEPCOM.
2. Such a plan shall be based on the Guidelines developed by the MEPCOM and written in a working language or languages understood by the master and officers. The plan shall consist at least of:
a. The procedure to be followed by the master or other persons having charge of
the ship to report a noxious liquid substances pollution incident based on the Guidelines developed by the MEPCOM;
b. The list of authorities or persons to be contacted in the event of a noxious liquid substances pollution incident;
c. A detailed description of the action to be taken immediately by persons on board to reduce or control the discharge of noxious liquid substances following the incident to include provision of a stand-by spill boom; and
d. The procedures and point of contact on the ship for coordinating shipboard action with national and local authorities in combating the pollution.
3. In the case of ships to which Chapter II also applies, such a plan may be combined with
the shipboard oil pollution emergency plan. In this case, the title of such a plan shall be ‘‘Shipboard Marine Pollution Emergency Plan’’.
4.6.4.5 Shipboard Oil Pollution
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Risk Assessment & Emergency Response Policy and Guidelines | 11
1. All oil tankers of 150 tonnes deadweight and above and every ship other than an oil tanker of 400 tonnes deadweight and above shall carry on board a Shipboard Oil Pollution Emergency Plan (SOPEP) approved by the MEPCOM.
2. Ensure the availability of SOPEP for inspection and evaluation at all times. 3. Prior to approval of the SOPEP, the MEPCOM shall conduct an Emergency Readiness
Evaluation (ERE) on the ship’s crew to determine their knowledge of the provisions of the SOPEP and if the procedures indicated therein are enough to combat an oil spill. Likewise, the crew should conduct regular drills/exercises and periodic review of the plan at least every year to keep up with changes in these Regulations. To ensure compliance of this requirement, MEPCOM shall supervise the aforesaid drills/exercise and shall certify thereon.
4. SOPEP of every ship shall consist at least of:
a. Procedures to be followed by the master or other persons having charge of the ship to report an oil pollution incident.
b. List of authorities or persons to contact in the event of an oil pollution incident. c. Detailed description of actions to be taken immediately by persons on board to
reduce or control the discharge of oil spill incident. d. Procedures and point of contact on the ship for coordinating shipboard action
with national and local authorities in combating pollution. e. Necessary assistance to the master in meeting the demands of a Tier III spill
should it involved one. f. Arrangement of SOPEP Provisions:
i. MEPCOM report on actual and probable discharge ii. Ship’s lay-out and plans appendices.
iii. National and local coordination entities and their roles in case of emergencies falling within their jurisdiction.
5. Ship-owners or shipping companies shall submit a copy of the proposed Plan in
writing to the Commander, MEPCOM for evaluation and approval prior to its implementation aboard ship.
4.6.4.5.1 Decontamination Procedure Decontamination will make an individual and/or their equipment safe by physically removing toxic substances quickly and effectively. Extra care should be taken during decontamination, because absorbed agent can be released from clothing and skin as a gas. 4.6.4.5.2 Spill Emergency
1. Notify all personnel in the area of the spill immediately 2. Cordon off the area. A spill boom shall always be made available (on stand-by) for
containment of accidental spills; 3. Do not touch or swim through the spilled material as much as possible. However, if
this cannot be avoided, the response personnel should wear the appropriate PPE during environmental decontamination. Adequate protective equipment must be worn.
4. Stop the spillage if it is possible to do so without risk to personnel. 5. Avoid contact of water runoff to the spilled material.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Risk Assessment & Emergency Response Policy and Guidelines | 12
6. Remove other materials, equipment or containers in the path of the spill. 7. All spilled material must be disposed properly. 8. Adequate location of first aid kit should be adhered and available in strategic locations. 9. Adequate locations of Eyewash facilities must be available.
4.6.4.5.2.1 Post Emergency Procedure Likewise, an incident report shall be made with the corresponding assessment on the cause of the incident which will be prepared to prevent future occurrences and/or determine lapses or efficiency of control and handling procedures. A risk assessment will be undertaken and included in subsequent reviews of this document to ensure the controls are adequate for management of all material handling and disposal options. 4.6.4.6 Security Related Emergencies (Bomb Threats and Security Issues) 4.6.4.6.1 Prevention Simple activities that can reduce the threat shall be established and implemented. The following practices are an aid to reducing the potential places in which articles can be hidden:
1. Keep rooms, stairways, corridors and halls clean and tidy. 2. Lock unoccupied rooms and areas. 3. Encourage project members to know the vessel well. 4. Encourage project members to look out for and report suspicious or unusual behavior. 5. Challenge unknown persons who are in an area in which they should not be. Ensure
that packages and parcels are delivered under observation and are being checked.
4.6.4.6.2 Emergency Response The Safety/Security officer is responsible for directing the action to be taken in response to any bomb threat. Such incidences shall be immediately reported to the local police unit of the PNP. Responsibilities include the following:
1. Producing a risk assessment; 2. Devising and maintaining a search plan of the vessel; 3. Devising and maintaining an evacuation plan; 4. Liaising with the responsible authorities; and 5. Arranging project members awareness and bomb threat practices
Evacuation routes should be identified and clearly marked allowing the free movement of personnel in the event of an emergency. A responsible individual should be identified to expedite evacuation if ordered. Muster drills should be conducted at all locations so that all personnel are fully conversant with the evacuation procedures. 4.6.4.6.3 Post Emergency Procedure
1. Review all actions and procedures. 2. Implement improvements from the lessons learned.
EIS for the Proposed Barangay Mercedes Reclamation Project
Social Development Plan/Framework (SDP) and IEC Framework| i
Table of Contents
5 Social Development Plan/Framework (SDP) and IEC Framework ....................................... 1 5.1 Principles and Objectives of the SDP 1
5.1.1 Guiding principles .......................................................................................................... 1
5.1.2 Operating Principles ....................................................................................................... 1
5.1.3 Objectives ......................................................................................................................... 1
5.2 Social Development Plan/ Framework 2
5.3 Information, Education, and Communication Campaign (IEC) 3
EIS for the Proposed Barangay Mercedes Reclamation Project
Social Development Plan/Framework (SDP) and IEC Framework| 1
5 SOCIAL DEVELOPMENT PLAN/FRAMEWORK (SDP) AND IEC FRAMEWORK
5.1 Principles and Objectives of the SDP
5.1.1 Guiding principles
The social development plan adopts the following development principles: Condition of living or quality of life of the project affected persons (PAPs) should at least equal or improved after the project’s full development. These principles equally applied to both the adversely affected families and the project-beneficiaries, and geared towards the protection of their rights in order to attain the desired optimum benefits for the project. 5.1.2 Operating Principles
To attain a successful SDP, the following operating principles can be adopted: Transparency. The conduct of a truthful and culture-sensitive IEC enables stakeholders particularly the adversely affected sectors to fully understand the messages and benefits to be derived from the project and the guiding policies related to its implementation. This enables free-flowing communication between the proponent and the stakeholders in order to develop responsible feedback mechanisms to the eventual successful project implementation. Equity. Equal rights shall be provided to all concerned regardless of status and social affiliation, subject to qualifications and considering agreed norms and regulations. Accountability. Responsibilities shall be clearly identified, sanctions spelled out, and mechanisms for sanctions are likewise installed. Empowerment. When the people are well-informed on the project situation, they are keen enough and enticed to actively participate in the formation of policies and decision making relative to the project implementation and operations. Governance. Participatory involvement of stakeholders in major decision-making, planning, implementation that is useful in addressing concerns and issues taking place. In accordance with these principles, and in view of the inevitable and valuable involvement of key stakeholders to pursue an improved quality of life of the people along with development, the SDP shall attend to the aforementioned issues involving: adversely affected families/persons, the beneficiaries, the implementing organization and the support organizations/groups. Hence, convergence of key stakeholders shall be the main approach. 5.1.3 Objectives
The project’s SDP aims to mitigate adverse impacts of the project mainly restoration of income and livelihood, promote optimum benefits to target beneficiaries, and provide mechanism for
EIS for the Proposed Barangay Mercedes Reclamation Project
Social Development Plan/Framework (SDP) and IEC Framework| 2
convergence and/or mobilization of other stakeholders in support to the project objectives and activities. Specifically, the proposed SDP aims to:
1. For the Project-affected Persons/Families (PAPs/PAFs):
• Prevent/mitigate project’s adverse impacts on the well-being of adversely affected persons/families (PAPs/PAFs); and
• Provide interventions/support to help restore income and improve the socio-economic situation of PAPs/PAFs.
2. For other stakeholders:
• Sustain/enhance stakeholder coordination in support to the project, its activities,
the PAPs/PAFs and the beneficiaries. The SDP of the project shall be derived from and aligned with LGUs existing SDP. The cost requirement shall be finalized once the specific projects have been processed and identified thru consultation with the concerned LGUs and sectors in the potentially affected communities. NIA shall share in the cost of the selected projects found to be relevant to the attainment of compliance or socially responsible EMP implementation. 5.2 Social Development Plan/ Framework
The social development plan framework (SDP) seeks to address the issues, concerns under impacts and mitigating measures. It incorporates the proposed interventions of the project proponent in favor of the various stakeholders of the project. As part of its social responsibility, the proponent aims to empower stakeholders, especially the affected residents as partners of development. As an active player in society, the proponent seeks to alleviate the low standard of living residents through programs that will harness their productive potentials to the fullest and reinforce their self-reliance and dignity as equal members of society. The following issues and concerns identified by the stakeholders during the consultation meetings, perception survey and Focus Group Discussions within the concerned barangays. The issues and concerns raised by the stakeholders will be the priority of the proponent in its Social Development Program. The framework seeks to establish the parameters in intervention to the host communities and to the various stakeholders. The social development plan framework is discussed in the following paragraphs to guide the proponent in the formulation of the SDP. These are the major features of the social development plan framework. Proper mechanisms should be put in place to ensure that livelihood projects will continue to exist and be viable. It is an opportunity for the residents to pursue self-sustaining livelihood activities and be self-reliant in the future.
EIS for the Proposed Barangay Mercedes Reclamation Project
Social Development Plan/Framework (SDP) and IEC Framework| 3
Coordination should be undertaken to identify the priority needs of the residents of the host barangay, the rest of the barangays in City of Catbalogan. A mechanism should be put in place to ensure the timely payment of the taxes, fees, permits and license. Table 5-1. Social Development (SDP) Plan/Framework
Concern Responsible
Community Member / Beneficiary
Government Agency/ NGOs
Proponent Indicative Timeline
Source of fund
Impact on Fishing and
Livelihood
Fisher folks within the
area / Qualified
identified workers
within the area who
will be affected by the
project / Qualified
identified
beneficiaries in the
vicinity of the project
area that might be
adversely affected. /
BFARMC President
and qualified
identified affected
fisher folks
LGU, BFAR
Community
Relations
officer
Pre-
construction
Construction
-Operation
LGU-IRA/
Proponent
Gender Responsive
Livelihood/employment
and Credit Facilities
Association
Chairperson/Qualified
Project Affected Men,
Women, Youth and
Elderly
MPDO,
MSWD,
TESDA
Community
Relations
officer
Pre-
construction
Construction
-Operation
LGU-IRA/
Proponent
Health and safety
Barangay Kagawad
for Health
MHO,
Barangay
Disaster
Management
Community
Relations
officer
Pre-
construction
Construction
-Operation
LGU-IRA/
Proponent
Environment and
Sanitation
Barangay Kagawad
for Education and
Environment
DepEd
Community
Relations
officer
Pre-
construction
Construction
Operation
LGU-IRA/
Proponent
Peace and Order Barangay Kagawad
for Peace & Order LGU, PNP
Community
Relations
officer
Pre-
construction
Construction
-Operation
LGU-IRA/
Proponent
5.3 Information, Education, and Communication Campaign (IEC)
The IEC calls for transparency on the part of the proponent in dealing with the stakeholders on environmental issues which affect them. Community relations will be proactive and social development activities will be institutionalized. Central to the IEC Campaign of the Project implementer will be an environmental awareness program initially designed for workers but later adapted to various community members
EIS for the Proposed Barangay Mercedes Reclamation Project
Social Development Plan/Framework (SDP) and IEC Framework| 4
interested in environmental protection and enhancement. Topics that will be covered include construction process, improvement of water and air quality, health and safety practices. An IEC Plan prior to the approval of the unsolicited proposal were held through a series of discussion and consultation by the City Government of Catbalogan and the Barangay Mercedes officials. The location, component of the project, construction schedule and the benefits to the City of Catbalogan and Barangay were discussed. Also in compliance of DENR DAO 2017-15 a series of focus group discussion were held, first group discussion focus on the requirement of the said DENR Administrative order and the implementation of the Perception Survey, another discussion were held both with the representative of the City Government, Barangay officials, Environmental consultants and the proponent of the original proposal. Discussed were some detail of the project, content of the perception survey and the schedule of Project presentation. For the proposed project, the IEC will be a continuing process. The generic IEC Plan/Framework is shown in Table 5-2.
EIS for the Proposed Barangay Mercedes Reclamation Project
Social Development Plan/Framework (SDP) and IEC Framework| 0
Table 5-2. Generic IEC Plan/Framework
Target Sector Major Topic/s of concern in Relation to Project IEC Scheme/ Strategy/ Method Information Medium
Indicative Time/
Frequency
Indicative Cost
Barangay (Mercedes, Poblacion 3, 4 and 5) and Municipal council members
• Project Description • Impacts on environment and
health • Risks • Socio-Economic benefits • Socio-Economic impacts
particularly to fisher folks and vendors Climate Change Mitigation/Adaptation
Group Method Consultations with Stakeholders
Focus Group Discussion / Power Point Presentation Printed Materials Media releases
After receipt of NTP from PRA
To be determined
Barangay Council/association and City Officials
• Disaster Risk Reduction and Management/ Emergency Plan
City wide IEC Emergency Drills Participation by NDRRMC and PHIVOLCS
Visual Actual Drills (Fire, Earthquake, storm surges)
Prior to Project Implementation
To be determined
Impact Barangays Senior Citizens, Youth group and Fisher folks
• Health and Safety • Locally prevalent diseases
Group Method Consultations
Roundtable Discussions Prior to Project Implementation
To be determined
The Impact Barangays • Garbage Management • Plastic wastes
Technical Discussions Printed Materials
Invite experts on solid wastes
Prior to Project Implementation
To be determined
NGOs and Religious Groups • Nature of the Proposed Project
• Impacts on environment o Floods o Liquefaction o Marine Ecology
• Impacts on health • Socio-Economic impacts and
benefits to existing establishments
Group Method Consultations • Send invitations to various
barangay council members and impact sectors
• Continuous discussion and
consultation with the stakeholders to know their issues and concerns
Focus Group Discussion / Power Point Presentation Printed Materials
Before construction Phase
To be determined
Prospective MMT Members (if formed) PENRO
Environment and Health Group Method Focus Group Discussion Power Point Presentations
Same Same
MMT Members (if formed) The Project EIA Water and Marine Ecology Quality Management
Group method Individual
Printed materials Focus Group Discussions
Same
To be determined
EIS for the Proposed Barangay Mercedes Reclamation Project
Social Development Plan/Framework (SDP) and IEC Framework| 1
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Compliance Monitoring| i
Table of Contents
6 Environmental Compliance Monitoring ................................................................................... 1
6.1.1 Self-Monitoring Plan ...................................................................................................... 1 6.1.2 Multi-Sectoral Monitoring Framework ....................................................................... 2 6.1.3 Environmental Guarantee and Monitoring Fund Commitments ............................ 3
List of Tables Table 6-1. Summary of Multi-Sectoral Monitoring Framework .................................................... 2 Table 6-2. Summary Matrix of the Environmental Monitoring Plan (EMoP) with Quality Performance Levels (EQPLs) .............................................................................................................. 4
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Compliance Monitoring| 1
6 ENVIRONMENTAL COMPLIANCE MONITORING 6.1.1 Self-Monitoring Plan The proposed SMP as shown in Table 6-2 using the recommended format in Annex 2-20 of RPM DAO 2003-30. The Provincial Government of Samar is primarily responsible for monitoring the approved Environmental Monitoring Plan (EMoP) based on the Environmental Management Plan. The proponent will commission third party testing firm to conduct monitoring activities. The proponent will submit Self-Monitoring Report which includes detailed report on compliance to environmental standard specific to environmental laws to EMB Regional Office on a quarterly basis. They will also submit a Compliance Monitoring Report (CMR) semi-annually to EMB CO which includes a trend analysis of Environmental Standards, cumulative summary of annual and historical performance/compliance analysis on key environmental and social parameters. Report will also include percentage exceedance to standard and total violation if any. Multipartite Monitoring Team (MMT) on the basis of Proponent ECC and submitted SMR/CMR will validate project compliance per ECC Condition and Environmental Management Program, validate the conduct of self-monitoring by the proponent and received complaints, determine the validity of said complaints and monitor action taken by the proponent on EMB recommended measures to address the complaints. They will submit a Compliance Monitoring and Validation Report (CMVR) to EMB CO semi-annually. Environmental Management Bureau is responsible for the overall evaluation/audit of the proponent monitoring and MMT’s validation. They shall prepare a Compliance Evaluation Report (CER) based on the submitted proponent SMR/CMR and MMT’s CMVR. EMB will also conduct field validation semi-annually or whenever there are complaints, exceedance on standard and if there are any suspicious data.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Compliance Monitoring| 2
6.1.2 Multi-Sectoral Monitoring Framework
The planned reclamation project which qualifies to an Environmental Critical Project (ECP) will necessitate the formation of Multipartite
Monitoring Team (MMT). The Provincial Government is responsible for inviting stakeholders to be members of the MMT. It actually encourages
groups from the community to nominate their representatives. A general committee composed of these representatives will be established.
Table 6-1. Summary of Multi-Sectoral Monitoring Framework
Stakeholder Basis for Selection Specific Organization
Proposed Role in the MMT / scope of MMT
responsibilities/activities
Strategy in establishing and Monitoring EQPLs
Barangay LGU’s from the
impacted Coastal
Barangay of Mercedes
RHU and Chairpersons
Direct jurisdiction
of the area
LGU Suggest/Provide Inputs in the
implementation of mitigating
and enhancement programs
Participate in actual monitoring
Regularly conduct quarterly
meetings/consultations and
annual assessment
City Government of
Catbalogan
(MENRO/MPDO)
Provide reports and information
regarding proponent’s violation,
compliances and inputs
Provincial Government of
Samar (PENRO/PPDO)
Registered POs / NGOs Direct and Indirect
Affected Area
Sectoral
Representatives
Suggest/Provide Inputs in the
implementation of mitigating
and enhancement programs
Participate in actual monitoring
work, and concur with and/or
sign the monitoring reports, or
take exception to them as the
case may be.
Regularly conduct quarterly
meetings/consultations and
annual assessment
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Compliance Monitoring| 3
6.1.3 Environmental Guarantee and Monitoring Fund Commitments
The proponent will commit an Environmental Guarantee Fund of One Million Pesos (Php
500,000) intended to rehabilitate components of the environment and compensate damage/s
to properties adversely affected by the project. The proponent will also allocate
Environmental Monitoring Funding in the amount of One Hundred Fifty Thousand Pesos
(Php 150,000) for activities to be done by the MMT and replenish the same when necessary.
However the stated amounts on the said funds are only indicative, EMB will evaluate and
recommend the final amount of EMF and EGF fund.
Annex 3-6 of the Revised Procedural Manual provides the guidelines for the determination of
the EGF and is summarized hereunder with the more relevant provisions. There is no explicit
provision under DAO 2003-30 requiring valuation of potential impacts that may arise as a
result of changes in the use of natural and environmental resources. Impact valuation is
particularly crucial in estimating the EGF to derive estimates on the potential damage that
may occur, and the corresponding amount to be set aside through the EGF for such purpose.
Procedures for arriving at such estimates in a more rational and systematic manner will have
to be based on experiences that shall have been generated on Philippine examples and other
developing countries.
In the absence of such information, more recent experiences of projects of similar nature with
provisions for EGF may be utilized. The amount to be allocated for the EGF shall be
determined through negotiations between the proponent and the EMB (EMB-CO or EMB-
RO). It should take into consideration the following factors in determining the appropriate
amount for specific projects.
● the EIS committed programs
● the degree of environmental risk involved (based on number and extent of
potential
● damage)
● valuation of resources that would most likely to be affected
● the proponent’s ability to provide funds for the EGF
At the end of the project life, a sufficient amount should be left from the EGF to ensure that
rehabilitation, restoration, decommissioning, or abandonment shall be adequately financed.
Such amount may be increased during the project life span to ensure that the balance shall be
sufficient for the abandonment phase. In such case, the EGF Committee may require an
adjustment of such amount to cover inflation and other factors. The required submission to
the DENR-EMB of the project’s Abandonment Plan shall have a corresponding fund
commitment subject to the approval of the DENR or the lead government agency with direct
approving authority on the Abandonment/Decommissioning Plan of the project.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Compliance Monitoring| 4
Table 6-2. Summary Matrix of the Environmental Monitoring Plan (EMoP) with Quality Performance Levels (EQPLs)
Environmental Aspect
Potential Impacts
Parameters
Environmental Monitoring Form
Lead Person Annual
Estimated Cost
Environmental Quality Performance Level (EPQL) Management
Method Frequency Location EPQL Range Management Measure
Alert Action Limit Alert Action Limit
Construction Phase (Reclamation and Land Development) Water Quality Coastal
(Marine) water quality degradation caused by reclamation activities
pH Grab sampling Monthly All stations considered
in this study
Proponent’s / Contractor’s
PCO
Included in the project
cost
4.2 – 5.1 (60% of Std.)
5.3 – 6.4 (75% of Std.)
7.0-8.5 (Std. Class SB)
Report actual status on a periodic basis, document results and continue monitoring. Identify source of pollution / exceedance. Increase sampling frequencies. Conduct clean up activities along streams that discharge to the sea. Strict implementation of good house-keeping practices / measures at the site.
Revalidate results and continue monitoring. Revalidate previously identify source of pollution / exceedance. If source of exceedance are leaks or spills, implement spill containment and clean up measures.
Compare how values of results escalated relating each result to actual occurring situation during sampling and validate identified sources. As necessary, temporary stoppage of concerned activities may be needed until remedial measures are in place.
Temperature 15.6 - 18.0 19.5-22.5 26-30
Oil and grease, mg/L
1.8 2.25 3
TSS, mg/L 30 37.5 80
DO, mg/L 3.6 4.5 6
Cr (VI), mg/L 0.03 0.0375 0.05
As, mg/L 0.006 0.0075 0.01
Cd, mg/L 0.0018 0.00225 0.003
Pb, mg/L 0.006 0.0075 0.01
Hg, mg/L 0.0006 0.00075 0.001
Cu, mg/L 0.012 0.015 0.02
Total Coliform, MPN/100mL
6000 7500 10000
Water Quality
Change in species composition and abundance of marine, freshwater, and riparian
Density of fish catch per unit effort (Kilos of fish caught/person/ trip)
Interview Annual Immediate fishing areas around the project
Proponent Included in project cost
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Compliance Monitoring| 5
Environmental Aspect
Potential Impacts Parameters
Environmental Monitoring Form
Lead Person Annual
Estimated Cost
Environmental Quality Performance Level (EPQL) Management
Method Frequency Location EPQL Range Management Measure
Alert Action Limit Alert Action Limit biota due to reclamation and dredging activities within the immediate vicinity of the reclamation area, the dredge area and the area study for the Tungkop Fish Sanctuary Threat to Abundance / Degradation of mangrove area
- Mangrove growth including its height, basal area and its diameter-at- breast height
Census or manual count Physical Measurement
Quarterly Open Area /mangrove park within the project
Proponent Included in project cost
assessment in abundance and taxa richness of aquatic biota
baseline assessment in abundance and taxa richness of aquatic biota; Decreasing trend across three monitoring periods.
abundance and taxa richness of aquatic biota across monitoring periods accompanied by exceedances in water quality parameters being monitored
Investigate and identify possible cause of decline. Conduct initial inspection of control measures being implemented
Values Check results of the aquatic biota analyses against the water quality status. Improve or enhance existing control measures to improve water quality
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Compliance Monitoring| 6
Environmental Aspect
Potential Impacts Parameters
Environmental Monitoring Form
Lead Person Annual
Estimated Cost
Environmental Quality Performance Level (EPQL) Management
Method Frequency Location EPQL Range Management Measure
Alert Action Limit Alert Action Limit Sediment Deposition
May adversely affect ecosystem
Heavy metals and nutrients
Grab sampling Quarterly Area near mouth of the rivers and other stations that the MMT may further recommend
Proponent / Contractor
Included in project cost
Same levels as in Water Quality (TSS)
Same levels as in Water Quality (TSS)
Same levels as in Water Quality (TSS)
Report results to Project Manager
If values are exceeded transfer to another location
Management remedial measures if necessary
Waste management Hazardous substances Chemical storage areas
Impacts on sanitation and water pollution Risk to human health
Type and volume of waste Present in harmful quantities and safe storage
Visual inspection
Daily Reclamation site and Staging Area
Proponent / Contractor
Included in project cost
Report results to Project Manager
Adopt remedial actions and safety measures
There should not be any untoward incident
Air Quality Possible degradation of air quality due to reclamation activities
SO2, ug/NCM Gas Bubbler and Pararosaniline Method
Quarterly Stations considered in the report
Proponent’s / Contractor’s PCO
50,000 204 255 340 Report actual status on a periodic basis, document results. Investigate possible cause of pollution and continue monitoring. Conduct dust suppression measures.
Prepare statistical report highlighting the findings. Regular maintenance of all fuel-burning equipment.
Revisit /audit the functionality of air pollution control installations. Replace all non- conforming equipment / machineries.
NO2, ug/NCM Gas Bubbler and Pararosaniline Method
156 195 260
PM10, mg/L High Volume Sampler
120 150 200
TSP, ug/NCM High Volume and Gravimetric Method
180 225 300
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Compliance Monitoring| 7
Environmental Aspect
Potential Impacts Parameters
Environmental Monitoring Form
Lead Person Annual
Estimated Cost
Environmental Quality Performance Level (EPQL) Management
Method Frequency Location EPQL Range Management Measure
Alert Action Limit Alert Action Limit Possible increase in ambient noise level due to reclamation activities
Noise, dbA Noise meter Quarterly or as required in response to any noise complaints.
Stations considered in the report
Proponent’s / Contractor’s PCO
Minimal cost; Included in the project cost
55 60 65 Report actual status on a periodic basis, document results and continue monitoring. Investigate possible cause of exceedance.
Fix broken equipment or machine, as necessary. Regularly maintain equipment to keep these working at their optimum and minimize noise. Continue noise level monitoring and increase frequency as necessary .
Conduct site noise audit of equipment and machineries. Install noise suppression structures and/or equipment appropriate to mitigate the situation.
Community consultation
Socio-economic status of the host communities vis- à-vis the project operations Community benefits from the project due to taxes, employment, and social
Efficiency of SDP programs, employment generation (in terms of local engagement on the project itself) and tax revenues Number of beneficiaries and other parameters
Review of complaints records and outcome of dredging events to community to guide future management strategy.
Weekly Barangay Mercedes
HR, CSR Staff (contractor) or authorized department of the municipal government, affected barangays
Included in the SDP fund
Negative feed- back to the company
Formal com- plaint lodged by the community
Multiple complaints feed to local media organizations
Company to investigate/ inspect subject of negative feedback Coordinate with the barangay and MMT
Validate previous findings in coordination with stakeholders Coordinate with the concerned LGUs and MMT
Immediate consultation with the MMT and the LGU to resolve issue/s Release an official statement to clarify the issue/s. Monitor and report results on
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Compliance Monitoring| 8
Environmental Aspect
Potential Impacts Parameters
Environmental Monitoring Form
Lead Person Annual
Estimated Cost
Environmental Quality Performance Level (EPQL) Management
Method Frequency Location EPQL Range Management Measure
Alert Action Limit Alert Action Limit development programs (SDP)
required under SDP (i.e. involvement of locals in CRM programs, Health statistics, etc)
Key informant interviews; Census and surveys in Coordination with the affected barangays;
Quarterly implementation of resolution.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Compliance Monitoring| 9
Environmental Aspect
Potential Impacts Parameters
Environmental Monitoring Form
Lead Person Annual
Estimated Cost
Environmental Quality Performance Level (EPQL) Management
Method Frequency Location EPQL Range Management Measure
Alert Action Limit Alert Action Limit Health and safety impacts from reclamation activities
Safe man-hours
Incident reporting, regular monitoring integrated in the Health and Safety Plan of the company
Daily inspection of work conditions, PPEs and compliance to the company’s Health and Safety Plan
Project site and vicinity
Safety Officer
Minimal cost
Negative feed- back to the company
Formal com- plaint lodged by the community and/or employees
Multiple complaints feed to local media organizations
Company to investigate/ inspect subject of negative feedback;. Improvement of health and safety measures to address negative feedback
Revalidate previous investigation results- reason for complaint and address complaint immediately through consultations with employees, contractors or affected stake- holders Improvement of health and safety measures to address negative feedback
Immediately conduct consultations or dialogues with complainants and affected stake-holders to determine reason for complaints. Address the complaints and document the responses and actions that will be done Release an official statement to media to clarify the issue Make improvements on health and safety plan to reflect the actions that were conducted so a repeat of the incident or complaints will not happen.
EIS for the Proposed Barangay Mercedes Reclamation Project
Environmental Compliance Monitoring| 10
Environmental Aspect
Potential Impacts Parameters
Environmental Monitoring Form
Lead Person Annual
Estimated Cost
Environmental Quality Performance Level (EPQL) Management
Method Frequency Location EPQL Range Management Measure
Alert Action Limit Alert Action Limit Navigational restriction and Traffic congestion
Visual inspection to ensure navigation is not restricted and land traffic situation
Adjust vessel movement and location accordingly and Implement the necessary traffic management scheme
Daily Project site and vicinity
Contractor / Proponent
Included in the project cost
Negative feed- back
Formal com- plaint lodged by the community and/or other stake-holders (e.g. other business centers in the area)
Multiple complaints
Proponent to investigate/ inspect subject of negative feedback; Improvement of traffic management plan / measures to address negative feedback
Revalidate previous investigate result on reason for complaint and address complaint immediately through consultations with affected stake-holders Improvement of traffic management plan / measures to address negative feedback
Immediately conduct consultations or dialogues with complainants and affected stakeholders to determine reason for complaints. Address the complaints and document the responses and actions that will be done; Release an official statement to media to clarify the issue; Improvement of traffic management plan / measures to address negative feedback and to reflect the actions that were conducted so a repeat of the complaints will not happen.
EIS for the Proposed Barangay Mercedes Reclamation Project
Decommissioning / Abandonment / Rehabilitation Policy| i
Table of Contents
7 Decommissioning / Abandonment / Rehabilitation Policy .................................................... 1 7.1 Objectives of Decommissioning / Abandonment / Rehabilitation Policy 1
7.2 Indicative Demobilization Plan 1
7.3 Risk Assessment 1
7.4 General Description of Demobilization Activities 2
EIS for the Proposed Barangay Mercedes Reclamation Project
Decommissioning / Abandonment / Rehabilitation Policy| 1
7 DECOMMISSIONING / ABANDONMENT / REHABILITATION POLICY 7.1 Objectives of Decommissioning / Abandonment / Rehabilitation Policy The objectives of the decommissioning planning for the project are:
1. To provide an overall framework in terms of abonnement of the project including rehabilitation and decommissioning strategies that are consistent with national and local standards and regulatory requirements;
2. To establish selection criteria to be used as guide in the decommissioning or cessation of all project activities;
3. To minimize and/or eliminate adverse environmental impacts once the project cease operation;
4. To ensure that cessation of all activities is complete and in accordance with good industry practice and did not pose an unacceptable risk to public health and safety; and
5. To provide the local communities with long-term sustainable opportunities following closure.
7.2 Indicative Demobilization Plan The project is designed to become a high urban land uses for institutional, commercial, recreational, and industrial operations and is expected to retain such use in perpetuity. Collectively, ownership will eventually be shared by lot buyers (locators) and the Provincial Government of Samar. 7.3 Risk Assessment A risk assessment will be undertaken during the preparation of demobilization plan to ensure that risks are identified and appropriate mitigating measures are properly implemented. Before the conduct of demobilization, the Provincial Government of Samar will prepare a monitoring tool to ensure that all demobilization criteria are taken into consideration. Finding generated from the preparation of self-monitoring report (SMR), compliance monitoring report (CMR) and MMTs documents will be part of the monitoring program. Monitoring will be done continuously throughout the demobilization phase to demonstrate that the demobilization protocols and compliances are attained, that the environmental impacts and risks have been appropriately addressed and that any areas requiring remedial works are identified. Periodic reviews of monitoring data will be done to assess trends and the efficiency of the management activities. Monitoring will also prompt maintenance if necessary. For off-shore operations, there are no equipment or structures that will require dismantling except for the fixed maroon points which may be needed during development. Corresponding clearances from the LGU, the PRA, the local port authority and the Philippine Coast Guard shall be secured prior to vessel and off-shore facility decommissioning.
EIS for the Proposed Barangay Mercedes Reclamation Project
Decommissioning / Abandonment / Rehabilitation Policy| 2
7.4 General Description of Demobilization Activities The formulation of the detailed abandonment plan will be done by the Provincial Government of Samar within the specified timeframe as part of the post-ECC requirement. It will be submitted for approval to the EMB and other concerned government agencies on the activities such as Environmental Site Assessment to determine contaminants left by the operation, method and equipment to be used for dismantling of structures, clean-up or remediation plan and demobilization scheme before proceeding. Demobilization during post construction will be conducted by the contractors as per Provincial Government requirements which include all activities and costs for transport of all construction equipment used, all excess materials, disassembly and transport of temporary facilities (office, stock room, quarters, etc.) used during construction, removal and disposal of all construction debris and general clean-up of construction site. Considering that the project has no lifespan, continuous proper maintenance, enhancement and upgrading will be done to ensure high standard of the developed areas, environmentally compliant, sound and safe. Structures will be assessed regularly for the project to ensure continuous sound and safe area of development.
EIS for the Proposed Barangay Mercedes Reclamation Project
Institutional Plan for EMP Implementation | i
Table of Contents 8 Institutional Plan for EMP Implementation ............................................................................. 1
8.1 Designation of the Environmental Officer 1
8.2 Institutional Plan for Effective Project Implementation 1
8.3 Multi-Partite Monitoring Team (MMT) 2
8.3.1 Roles of MMT .................................................................................................................. 2
8.3.2 MMT Team Composition .............................................................................................. 2
8.3.3 Environmental Guarantee Fund (EGF) and Environmental Monitoring Fund (EMF) ...... 2
8.4 Grievance Redress Mechanism 3
8.4.1 Objectives and Advantages of Developing a Grievance Redress Mechanism ...... 3
8.4.2 Procedures of Grievance Redress ................................................................................. 3
EIS for the Proposed Barangay Mercedes Reclamation Project
Institutional Plan for EMP Implementation | 1
8 INSTITUTIONAL PLAN FOR EMP IMPLEMENTATION 8.1 Designation of the Environmental Officer The Institutional Plan is equally important. The purpose of the plan is to clearly delineate the functions of each of the players in this project, especially the function of Environmental Officer (EO) or Pollution Control Officer (PCO). The position entails the overall management and planning of all environment-related issues and concerns that may arise during the preconstruction, construction, operation and abandonment stages of the proposed Barangay Mercedes Reclamation Project. The proponent shall closely coordinate with the Department of Environment Natural Resources – Environmental Management Bureau (DENR-EMB) for the project’s environmental compliance. For an effective coordination, the proponent will designate an Environmental Officer or Pollution Control Officer (PCO) who will be responsible for all environmental matters regarding the project. This is in compliance with DAO 2014-02 that requires the appointment/designation of an Environmental Officer or Pollution Control Officer. Specifically, the following are the responsibilities of the Environmental Officer or Pollution Control Officer:
1. Coordinates with DENR - EMB Regional Office on the environmental aspects of the operation/activities of the project;
2. Coordinates with all concerned agencies on the solid waste collection and disposal of the project;
3. Ensure the compliance with the requirements of PD 1586, RA 6969, RA 8749, RA 9003, RA 9275, their respective implementing rules and regulations (IRRs), and other pertinent rules and regulations.
4. Assist in the identification of significant environmental aspects and impacts of the project’s operation activities and recommend possible mitigating measures in the formulation/preparation and/or review of the Environmental Management Plan and Contingency Plan
5. Attend to all permitting and registration requirements of the project prior to the construction, installation, or operation of pollution sources and control facilities.
6. Ensure the proper performance, operation, and maintenance of environmental management facilities or systems of the project
7. Monitor compliance to the requirements specified in the Environmental Compliance Certificate and the commitments stipulated in the Environmental Performance Report and Management Plan (EMRMP)
8. Submit the CMRs and SMRs to EMB on a timely manner. 8.2 Institutional Plan for Effective Project Implementation The Provincial Government of Samar in coordination with other concerned government agencies and other government unit/s will conduct monitoring of the project. This is necessary
EIS for the Proposed Barangay Mercedes Reclamation Project
Institutional Plan for EMP Implementation | 2
in order to determine if the Provincial Government is implementing the prescribed mitigating measures recommended in the Environmental Compliance Certificate (ECC) of the project. The Provincial Government in compliance with the requirement of the DENR-EMB and other concerned government agencies, shall appoint fulltime regular Pollution Control Officer (PCO)/Safety Officer, who will lead the Environment, Safety and Health Department. His/her responsibility is for the formulation and implementation of environmental conservation and health/safety programs. The PCO is responsible for the monitoring not only the construction area but also of the machineries, equipment and utilities being installed. He/she makes representation with other government units and non- government organizations and submits the required reports on the filling operation and structures, roads, utilities being constructed, machineries, equipment used with the regional office of DENR- EMB. The implementation of the project’s entire environmental management and monitoring program shall fall under his/her direct supervision. He/she reports to the Construction Manager. Also under his department are a Community Relations and Development Officer who will oversee the community assistance program of the Provincial Government in relation with the reclamation project. 8.3 Multi-Partite Monitoring Team (MMT) 8.3.1 Roles of MMT A Multi-Partite Monitoring Team (MMT) shall be formed immediately. The main goal of the MMT is to monitor the Provincial Government of Samar as well as its Contractor’s compliance to the ECC conditions, the Environmental Management Plan (EMP), and other applicable laws, rules, and regulations. In addition to these, the MMT shall also:
1. Gather relevant data to determine possible causes of unavoidable and residual adverse impacts and validity of public complaints or concerns about the project; and
2. Prepare, integrate, and disseminate monitoring reports and submit recommendations to the DENR.
8.3.2 MMT Team Composition The Provincial Government of Samar shall set-up a Multipartite Monitoring Team (MMT) composed of its own representatives, concerned LGUs, NGO, stakeholders, DENR/EMB R-VIII immediately. an Environmental Monitoring Fund (EMF) and Environmental Guarantee Fund (EGF) to cover all costs attendant to the operation of the MMT and damages and compensation cost shall be established. 8.3.3 Environmental Guarantee Fund (EGF) and Environmental Monitoring Fund (EMF) The ECC requires that a readily available and replenishable Environmental Guarantee Fund (EGF) be set up amounting to PhP 50 Million. The EGF is intended to cover the following:
1. Expenses for further environmental assessments;
EIS for the Proposed Barangay Mercedes Reclamation Project
Institutional Plan for EMP Implementation | 3
2. Compensation/indemnification for whatever damages to life and property that may be caused by the project; and
3. Rehabilitation and/or restoration of areas affected by the project’s implementation. It also requires the establishment of Environmental Monitoring Fund (EMF) amounting to PhP 10 Million to cover all costs attendant to the operation and monitoring activities of the MMT.
The amount and mechanics of the above-mentioned funds shall be determined by EMB and PLGU of Samar in consultation with stakeholders and EMB Regional Office through a Memorandum of Agreement which shall be submitted to the EMB Central Office as expected to be stated on the ECC. 8.4 Grievance Redress Mechanism 8.4.1 Objectives and Advantages of Developing a Grievance Redress Mechanism A well-designed grievance redress mechanism can help ensure the sound implementation of the project. The mechanism shall provide the project affected persons (PAPs) a platform to lodge their complaints, if any, towards the project especially on matters relating to environmental protection. It shall facilitate accessible and efficient delivery of concerns directly to the decisionmakers as compared to the formal judicial process. This mechanism shall also allow the proponent to get hold of the concerns immediately so that corresponding response measures can be formed and implemented in a timely manner. Recognizing and addressing grievances early on makes them more manageable and resolvable, and will therefore benefit both parties. A good grievance redress mechanism also helps build trust between the parties. Thus, a proper grievance redress mechanism shall be established for this project. A person within the PLGU of Samar shall be assigned to receive and process the grievances. His/her name and contact information shall be shared with all PAPs. The PLGU of Samar shall also ensure that the PAPs know and understand the mechanism including the people involved, the procedure, and the time and costs needed in order for it to be functional and effective. Special consideration shall be given to vulnerable people such as the illiterate, for which the PLGU of Samar may wish to explain the mechanism in a different manner (e.g. verbally instead of by paper). Grievances received must then be properly treated and discussed, and the resolution or conclusion delivered to the complainants within a reasonable time. 8.4.2 Procedures of Grievance Redress Grievances related to any aspect of the project will be dealt with through dialogue and negotiations with the aim of rapidly and amicably addressing the concerns in a less costly manner compared to those dealt with as legal cases. The Environmental Officer (EO) or Pollution Control Officer (PCO) has the responsibilities to receive and record the voices, complaints, opinions and suggestions provided by the PAPs, and address them as the first level of decisionmakers. If the response to the complaint is
EIS for the Proposed Barangay Mercedes Reclamation Project
Institutional Plan for EMP Implementation | 4
deemed inadequate in the view of the PAPs, the PAPs may elevate their grievance to the Office of the Governor. Should the grievance still not be settled, the PAPs may finally resort to filing a case with the court. Under this project, grievances from the PAPs shall be handled in the following manner:
1. Grievance shall be filed by the PAP with the PCO. The PCO shall act on the grievance within 15 days upon receipt, with the exception of complaints and grievances that specifically pertain to the valuation of affected assets, since such will be decided upon by the proper courts;
2. If no understanding or amicable solution can be reached, or if the PAP does not receive
a response from the MRIC within 15 days of the filing of the complaint, he or she can appeal to the Office of the Governor which should then act on the complaint or grievance within 15 days from the day of its filing;
3. If the PAP is still not satisfied with the decision of Office of the Governor, he/she, as a
last resort, can submit the complaint to any court of law. PAPs shall be exempted from all administrative and legal fees incurred. All complaints received in writing (or written when received verbally) from PAPs will be documented and shall be acted upon immediately according to the procedures detailed above.
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes | 1
Annex 1. Proof of Authority over the Project Site (Notice to Proceed with EIA Process by the DENR Region 8)
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes | 2
Annex 2. Accountability Statements of Preparers
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes | 4
Annex 3. Accountability Statements of Proponent
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes | 5
Annex 4. Duly Accomplished Project Environmental Monitoring & Audit Prioritization Scheme (PEMAPS) Questionnaire
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes | 14
Annex 5. Land Use Compatibility Certification
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes | 15
Annex 6. Letter Of No Objection from BFAR
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes | 16
Annex 7. Letter Of No Objection from DPWH Region 8
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes | 17
Annex 8. Letter Of No Objection from PPA
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes | 18
Annex 9. Letter Of No Objection from PRA
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes | 19
Annex 10. Letter Of No Objection from DOT Region 8
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes | 20
Annex 11. Wind Rose Data and Models
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes
Annex 2. A3 Maps
Figure 1 Administrative Map
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes
Figure 2 Barangay Classification Map
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes
Figure 4 Ground Shaking Hazard Map
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes
Figure 5 Rain-Induced Landslide Hazard Map
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes
Figure 6 Storm Surge Hazard Susceptibility Map (Advisory 1)
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes
Figure 7 Storm Surge Hazard Susceptibility Map (Advisory 2)
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes
Figure 8 Storm Surge Hazard Susceptibility Map (Advisory 3)
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes
Figure 9 Storm Surge Hazard Susceptibility Map (Advisory 4)
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes
Figure 10 Tsunami Prone Areas Map
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes
Figure 11 Liquefaction Susceptibility Map
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes
Figure 12 PGA Map of the Philippines 500-YR Period on Rock Site
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes
Figure 14 Land Classification Map
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes
Figure 19 Topographic and Bathymetric Map
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes
Figure 23 Indirect Impact Area Map
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes
Figure 24 Air and Noise Sampling Survey Map
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes
Figure 25 Air and Noise Sampling Survey Map Station 1
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes
Figure 26 Air and Noise Sampling Survey Map Station 2
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes
Figure 27 Air and Noise Sampling Survey Map Station 3
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes
Figure 28 Air and Noise Sampling Survey Map Station 4
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes
Figure 30 Water Sampling Survey Map
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes
Figure 31 Water Sampling Survey Map Station 1
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes
Figure 32 Water Sampling Survey Map Station 2
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes
Figure 33 Water Sampling Survey Map Station 3
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes
Figure 34 Water Sampling Survey Map Station 4
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes
Figure 35 Water Sampling Survey Map Station 5
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes
Figure 36 Water Sampling Survey Map Station 6
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes
Figure 37 Water Sampling Survey Map Station 7
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes
Figure 38 Water Sampling Survey Map Station 8
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes
Figure 39 Water Sampling Survey Map Station 9
EIS for the Proposed Barangay Mercedes Reclamation Project
Annexes
Figure 40 Water Sampling Survey Map Station 10
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
i
Annex 3. Public Hearing Report
Table of Contents
Table of Contents .............................................................................................................................. i
List of Tables ................................................................................................................................... ii
List of Figures .................................................................................................................................. ii
1 Proof of Conduct of Public Hearing ..................................................................................... 1
2 Transcription of the Proceedings .......................................................................................... 3
3 Issues and Concerns raised during the Open Forum ....................................................... 20
3.1 Project Description ........................................................................................................ 20
3.2 Land ................................................................................................................................ 21
3.3 Water ............................................................................................................................... 23
3.4 People ............................................................................................................................. 27
3.5 Other Concerns ............................................................................................................. 28
4 Annexes ................................................................................................................................... 30
4.1 Proof of Newspaper Publications ............................................................................... 30
4.2 Received Invitation Letters .......................................................................................... 32
4.3 Presentation during the Public Hearing .................................................................... 55
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
ii
List of Tables
Table 1.1. List of Attendees per Municipality ............................................................................. 1 Table 2.1. Issues and Concerns on Project Description ............................................................ 20 Table 2.2. Issues and Concerns on Land ................................................................................... 21 Table 2.3. Issues and Concerns on Water .................................................................................. 23 Table 2.4. Issues and Concerns on People .................................................................................. 27 Table 2.5. Issues and Concerns Raised (Others) ........................................................................ 28
List of Figures
Figure 1.1. Attendance sheet at the Public Hearing venue, page 1 .......................................... 1 Figure 1.2. Attendance sheet at the Public Hearing Venue, page 2 ......................................... 2 Figure 1.3. Screenshots taken during the Public Hearing via Zoom ........................................ 1 Figure 1.4. Photos taken on-site during the Public Hearing ..................................................... 1 Figure 1.5. More on-site photos of the Public Hearing .............................................................. 2 Figure 4.1. Affidavit of Publication ............................................................................................. 30 Figure 4.2. Proof of first publication ........................................................................................... 31 Figure 4.3. Proof of second publication ...................................................................................... 31 Figure 4.4. Received Invitation Letter-Poblacion 1 ................................................................... 32 Figure 4.5. Received Invitation Letter-City Mayor ................................................................... 33 Figure 4.6. Received Invitation Letter-DTI ................................................................................ 34 Figure 4.7. Received Invitation Letter-DOT ............................................................................... 35 Figure 4.8. Received Invitation Letter-Poblacion 4 ................................................................... 36 Figure 4.9. Received Invitation Letter-BFAR Region 8 ............................................................ 37 Figure 4.10. Received Invitation Letter-PPA/PMO Eastern Leyte/Samar ............................. 38 Figure 4.11. Received Invitation Letter-Poblacion 2 ................................................................. 39 Figure 4.12. Received Invitation Letter-PPA ............................................................................. 40 Figure 4.13. Received Invitation Letter-Poblacion 5 ................................................................. 41 Figure 4.14. Received Invitation Letter-DPWH Regional Office 8 ......................................... 42 Figure 4.15. Received Invitation Letter-Samar State University ............................................. 43 Figure 4.16. Received Invitation Letter-Business Group in Catbalogan City ....................... 44 Figure 4.17. Received Invitation Letter-District Representative ............................................. 45 Figure 4.18. Received Invitation Letter-Two Eco, Inc. ............................................................. 46 Figure 4.19. Received Invitation Letter-Poblacion 3 ................................................................. 47 Figure 4.20. Received Invitation Letter-Samar Chamber of Commerce and Industry ........ 48 Figure 4.21. Received Invitation Letter-Philippine Reclamation Authority ......................... 49 Figure 4.22. Received Invitation Letter-Poblacion 10 ............................................................... 50
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
iii
Figure 4.23. Received Invitation Letter-GIOS-Samar, Inc. ....................................................... 51 Figure 4.24. Received Invitation Letter-PENRO ....................................................................... 52 Figure 4.25. Received Invitation Letter-PCG ............................................................................. 53 Figure 4.26. Received Invitation Letter-CENRO ....................................................................... 54
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
1
1 Proof of Conduct of Public Hearing
The Public Hearing for the Proposed Barangay Mercedes Reclamation Project was
spearheaded by the Project Proponent, the Provincial Government of Samar, with the
assistance of the Project Consultant, Envia Consultancy. The notice of the Public Hearing
released by the DENR-Environmental Management Bureau – Central Office was published in
newspaper publications by the proponent on September 28 and October 5, 2021 (Annex 3.1) and the invitation letters for the government offices, the barangay officials, a business group
and a fisherfolk organization were likewise prepared and distributed on September 27, 2021
(Annex 3.2).
The Public Hearing proper for the affected stakeholders was held last October 15, 2021, 9:00
AM – 12:00 noon via Zoom Application and on-site venue at the 2nd floor, Session Hall,
Provincial Capitol Building in Catbalogan City. The briefing and orientation on the purpose
of the Public Hearing was presented by Engr. Jason Paolo Esguerra, case handler from EMB
Central Office; the rules on the conduct of Public Hearing were explained by Mr. Sherwin
Avestruz, Public Hearing Officer from EMB Regional Office 8; the description of the project
alternatives and EIA study process and results as well as the latest master development plans
were presented by Mr. Von Czar Meneses from Envia Consultancy, Inc. and Architect Berlin
Gaile Gascon from Two Eco, Inc.
Prior to this, the activities conducted were as follows:
• The Information, Education, and Communication (IEC) Campaigns were
conducted on December 17 to 18, 2019, January 16, 2020, and February 27, 2020;
• The Public Scoping was conducted on May 10, 2021; and
• The Technical Scoping was conducted on May 26, 2021.
The detailed list of the attendance for the Public Hearing can be found in the table below:
Table 1.1. List of Attendees per Municipality
Name Company/Affiliation Position
Engr. Victor Tingzon Philippine Ports Authority -
PMO Tacloban Senior Engineer A
Kristine Dator San Lorenzo EMS II
Hannah Jane Atole Philippine Reclamation
Authority -
Cherry Grace Ungab DENR-CENRO, Catbalogan
City Government Employee
CG ENS Jabin M. Castellano
Allen Avenue, City Proper Serviceman
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
2
Name Company/Affiliation Position Ann Geron Loyola Heights, QC Research Associate
Eleno Edwin C. Nuevo Brgy. Cinco Government Employee
Mabel Barroga Poblacion, Kabacan, North
Cotabato Student
Jason Esguerra EMB Site Engineer Pablo G. de los Reyes, Jr. QC Govt employee
Mark John Pineda PRA Makati PRA Makati
Meilou C. Macabare Brgy. Munoz, Catbalogan
City, Samar Government Employee
Nadia Conde N/A EIA CONSULTANT Gelleene Casino Lagutan Brgy 34 - Tacloban City Government employee
Jean N/A EIA Consultant for ENVIA Azyleah Ignacio-Ibaviosa San Lorenzo, Makati Lawyer
Danika Astilla - Researcher and Social Science Practitioner
Wilfredo L. Lacambra Mercedes Government Employee-
PLGU Samar
Angelito B. Villanueva Brgy. Guinadpunan,
Catbalogan City Government Employee
Dakila Kim P Yee Pawing, Palo, Leyte Assistant Professor Isabel Calantoc Makati Resident Officer
Antonio Angeles Sumague
Barangay Amihan, Project 3 QC
Civil Engineer
Lucy D. Francisco Poblacion 04 ENGINEER II Marlon C. Sale BFAR-PFO Samar Provincial Fishery Officer Arnaldo Aroza LGU-Catbalogan City CPDC
Elizabeth Illlavera NCR BFAR Staff
Adrian P. De Jesus Mercedes Senior Ecosystem
Management Specialist Emerson B. Darroles Manila Consultant Rene Zaldy Porlaje Quezon City Government employee
Balilia Winnievir S Biodiversity Management
Bureau-DENR Government Employee
Oskar D. Cruz Quezon City EIARC Nelieta Baguna Catbalogan City Chief of Staff
Elsie M. Borja Poblacion 7 Government Official - CENR
Officer Catbalogan Label Jude Edgar G. Brgy. Savinte e-II-u9mo FLML
Alcres B. Golong BUS or BAW Lucita S. Uy Brgy. Mercedes Kagawad
Mercedes G. Sedorante Brgy. Mercedes Brgy. Secretary Medilisa M. Picludo Brgy. or Pob. Brgy. Kagawad
Michael L. Cruz PLGU-PEO CM6F
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
3
Name Company/Affiliation Position Rajul M. Jucaton Brgy. 10 Brgy. Kagawad Sonny Boy Cinko Brgy. 10 Brgy. Kagawad Caesar M. Ragae Brgy. 10 Punong Barangay
Ruben Tillie -do- Kagawad Antonio L. Juy LGU Punong Barangay
Kyuho G. Uyagullo LGU Mercedes Lupon Virgie A. Machate - P3 Amos D. Estrebor LGU Mercedes Lupon
Postura L. Phehapurru LGU Lupon Eden H. Pinjcas LGB P-Pres
Jujus Bobon EMB 8 Trom Staff Dave Eden Niedo EMB 8 Sr. EMS Bea Mae Albarig EMB 8 EMSI Sheryin Alesireb EMB 8 SITU
Armando Dupio Jr. EMB 8 Chief ELA Qamilo O. Belasmido Brgy. 08 Kagawad
Nilo Maurk LGU Lupon Muardo M. Villa LGU Lupon Chairman
Benjiento Beleniju LGU Kagawad Justin T. Uy LGU Kagawad
Julius Uy Brgy. 02 Kapitan Alex N. De Luna PLGU-Samar PFO AT
Luzviminda G. Naga LGU PB Canolyn A. Fabon PEO Provincial Engineer
Roel C. Bohol GIOS SAMAR Vice Chair Rocky C. Adap LGU Kagawad Janet R. Pitato President -
Mariano N. Trozoar Jr. Brgy. 05 Barangay Secretary Maris R. Picazor SPTU PLGU
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
1
Figure 1.1. Attendance sheet at the Public Hearing venue, page 1
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
2
Figure 1.2. Attendance sheet at the Public Hearing Venue, page 2
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
1
Figure 1.3. Screenshots taken during the Public Hearing via Zoom
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
1
Figure 1.4. Photos taken on-site during the Public Hearing
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
2
Figure 1.5. More on-site photos of the Public Hearing
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
3
2 Transcription of the Proceedings
SIR BRETT: Ito pong proyekto ng Provincial Government ay ang Brgy. Mercedes Reclamation
Project. Magpapasalamat din kami kay Cong. Sharee Ann Tan dahil since Day 1 ay nasa likod
siya ng Provincial Government para tumulong na matapos ang project na ito. We hope na
itong dialogue na ito ay magiging platform para masagot ang issues and concerns na hindi
nasagot before at na sana within the next few hours ay magiging healthy and fruitful ang
discussions natin with our stakeholders. So, in behalf of Gov. Mike Tan and the rest of the
PLGU of Samar, I welcome you all, all the way here from the Catbalogan City of Samar, to the
Public Hearing of the Proposed Brgy. Mercedes Reclamation Project. Damo nga salamat and
Spark Samar.
ENGR. DEXTER: The next part of our program would be the presentation on the objectives of
the Public Hearing. For this, may I call on Engr. Jason Esguerra to present. Sir Jason, please go
ahead.
ENGR. JASON: Thank you po, sir. I-present ko lang po itong objectives ng Public Hearing
natin ngayon. Ang Public Hearing ay isang parte ng EIA Process, isa din po siyang form ng
public participation, at ginagawa po siya pursuant to PD 1586 and DENR AO 2003-30. So ang
EIA, o ang Environmental Impact Assessment, ay isang planning and management tool na
nakakatulong sa gobyerno, sa proponent, sa mga maapektuhang komunidad, at sa mga iba
pang decision makers para malaman natin kung ang mga benepisyo ng project ay mas
matimbang kesa sa mga negatibong epekto nito sa ating kalikasan.
Dito naman po ay ipapakita ko ang steps sa ating EIA Process. Kapag nagawa na po ng
proponent ang EIA Study ay magsusubmit po sila sa EMB CO, at doon po ay magkakaroon
tayo ng procedural screening. Sa procedural screening po ay titignan natin kung ang kanilang
sinubmit ay kumpleto, at kung ito po ay pumasa na, magkakaroon po tayo ng Review &
Evaluation. Mayroon po tayong experts from different fields, at sila po ang EIA Review
Committee na tutulong po sa atin na ma-review ang EIA Document na na-submit. Currently
po ay andito po tayo sa stage na ito, yung Public Hearing po ay sa Review & Evaluation Stage
na din po. Dito rin po malalaman kung ang kanilang project ay iissuehan ng ECC o idedeny.
Dito naman po tayo sa objectives ng Public Hearing. So, ang una pong objective ay ma-verify
po natin kung accurate po ba ang kanilang mga nakuhang data in relation po sa project site;
dito din po natin makukumpirma kung ang affected stakeholders po ba ay nakonsulta ng
mabuti at naging parte ng pagdedesisyon; nag-ooffer din po tayo ng platform para
magkaroon ng dialogue at para magbigay ng komento o opinyon ang mga stakeholders sa
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
4
project; eto din po ay para ma-promote ang effective public participation at ma-ensure ang
confidence sa proseso ng EIA tapos po ang suporta po sa magiging project.
Nabanggit ko po kanina ang ECC. So ang ECC po ay ang Environmental Compliance
Certificate. Ito po ay isang decision document na ini-issue ng office sa proponent pagkatapos
ng thorough review ng EIA Report. Dito po ipapakita ang commitment ng proponent, para
po makapagcomply sila sa mga existing na environmental regulations, at para makapag-
operate sila within the best environmental practice. Yun lang po, maraming salamat po.
ENGR. DEXTER: Maraming salamat po, Engr. Jason Esguerra. So, yun po ang objectives ng
ating Public Hearing. For next part po ng ating program, proceed po tayo sa presentation ng
project at results ng EIA Study. Hinihingi ko po sa ating mga participants na for now ay
makinig po tayo sa presentation ng ating proponent, ng kanilang consultant, at kung may
mga katanungan po tayo ay pwedeng isulat lang muna, at mamaya po sa ating Open Forum
ay doon po natin itanong sa ating proponent. Okay so, for the presentation po ng Project
Description, sa consultant po, please go ahead.
KATE: Let us welcome po Sir Von Meneses of Envia Consultancy. Good morning, Sir Von.
VON: Good morning po. Eto po ang Public Hearing ng Brgy. Mercedes Reclamation Project.
For today’s meeting, eto po ang agenda natin – meeting objectives, project overview, project
area, timeline, EIA Process and results, project benefits, and open forum.
So eto po ang ating meeting objectives – we shall be discussing the project overview, EIA
study process and results, then gather stakeholders’ comments and suggestions, and gain
stakeholders’ support for the project. Yun po ang ating pinaka-main objective para sa Public
Hearing na ito.
Eto naman po ang overview natin – context, the project, goals and objectives, facilities and
components, and alternatives. Alam naman po natin na under President Duterte’s
administration, patuloy ang pagulong natin sa imprastruktura under the Build Build Build
Infrastructure Plan. Alinsunod din po ito sa ating Philippine Development Plan para sa taong
2017-2022. Dito po ay gusto natin mapabilis ang development ng mga imprastruktura dahil
alam po natin na may benepisyo ito sa ating ekonomiya. Ang lokasyon po nito ay sa coastal
waters ng Barangay Mercedes, Poblacion 3, Poblacion 4, and Poblacion 5. Ang project
proponent po ay ang Provincial Government of Samar. Ilan po ang mga ito sa mga kinonsider
nating guidelines para sa proyektong ito: EO 543 – Delegating to the PRA the Power to
Approve Reclamation Projects; EO 146 – Delegating to the NEDA Board the Power of the
President to Approve Reclamation Projects; EO 74 – Repealing EO 798 and EO 146,
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
5
Transferring the PRA to the Office of the President, Delegating to the PRA Governing Board
the Power of the President to Approve Reclamation Projects, and for Other purposes; and
DAO 2018-14 – Guidelines on the Issuance of Area Clearance for Reclamation Projects and
Proclamation and Special Patents over Reclaimed Area.
Ang ating project goal and objective is to establish a large contiguous area to contain
residential and commercial development without having to face the problems on land
consolidation, high land value, and right-of-way acquisition. Pero sa pagsulong po ng
economic boost, ayaw po natin na may nasasagasaang tao.
Para naman sa ating project facilities and components, magkakaroon tayo ng commercial and
residential lots, institutional offices and facilities, road network, water distribution system,
drainage system, sewage collection system, centralized sewage treatment facility, power
distribution system, telecommunication system, at land mass.
Kinonsider din po natin ang project alternatives. Nagbase po tayo sa lokasyon, kung saan ba
ang area na irereclaim, at yung site selection na tinatawag. Ito po ba ay suitable na tayuan ng
ating reclamation project, gaano po ito kalapit sa City, sino po ba ang matatamaang mga
residente, meron pa tsyong masisira.
Meron po tayong irereclaim na 35 hectares for this project, along Barangays Mercedes,
Poblacion 3, Poblacion 4, and Poblacion 5. Eto po ang ating location map. So eto pong affected
areas natin, ginather po natin ang kanilang mga concern at comments para ilagay sa EIS
Report at para ma-address po natin.
Inaasahan po natin na itong project natin, kasama na ang construction, ay magtatagal po ng
48 months. Medyo matagal po ang proseso natin, pero pagkatapos po ng construction ay
magkakaroon naman po tayo ng economic boost, na magbebenefit ang lahat.
So, iprepresent ko na po ang results ng ating EIA. Based po ito sa EMB MC 2014-005 – Revised
Guidelines for Coverage Screening and Standardized Requirements. Ito pong proyekto natin
ay nagfafall under Category A – Environmentally Critical Projects, since 35 hectares po yung
area na irereclaim natin. Under po siya sa Projects/Description 3.3. Reclamation and other land
restoration projects. So eto pong public consultation/participation ay pangatlo na po nating
pagkikita – nauna na po ang IEC, at sumunod po ang Public Scoping, at ngayon po ay andito
na tayo sa Public Hearing.
Eto naman po ang nakikita naming mga suliranin ng proyektong ito: presence of critical slope;
geohazards; land use change; impact on existing waterways; impact on air, noise, and
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
6
vibration; and impact on existing road traffic and linkages. Nagpropropose naman po kami
ng mitigation measures na gagawin ni proponent para po ma-lessen ang mga ganitong
impact.
Eto naman po ang mga EIA Survey na kinonduct namin: una po ang soil quality survey,
tinignan po namin kung magkakaroon ba ng soil compaction; flora and fauna survey, tinignan
po namin ang biodiversity na madidisplace at abrupt changes po ecological system;
groundwater quality survey, tinignan po namin kung posible bang ma-contaminate ang
groundwater sources natin pwede iyong makaapekto sa kalusugan ng tao; surface/marine
water quality survey; freshwater/marine ecology survey; air quality survey and noise and
vibration level survey, ano po ba ang posibleng maging epekto ng ingay at malapit po ba sa
ating kabahayan, opisina, paaralan, at simbahan; initial perception survey naman po ay
kinonduct natin during the IEC meeting upang ma-gather ang mga concerns ninyo; and
finally, ang perception survey na kinonduct natin during the public scoping.
So eto po ang resulta ng aming pag-aaral. Para po sa land, maaari tayong magkaroon ng mga
sumusunod:
• Impacts on compatibility with existing land use classification;
• Impact on compatibility with classification as an ECA;
• Only minimal impairment of visual aesthetics due to similar adjacent land use and
lack of tourist spots near the site;
• Reduction of coastal waters and permanent change;
• Possible devaluation of land value as a result of improper solid waste management
during construction phase;
• Change in geomorphology due to the formation of new land mass;
• Change in subsurface geology/underground conditions;
• Inducement of geologic hazards;
• Disturbance of soil where the project is near may lead to soil erosion;
• Change in soil quality/fertility;
• Minimal loss of habitat and vegetation; and
• Noise generated during construction will impact behavior of different species.
Para naman po sa water, eto po ang mga results:
• The project site is devoid of wetlands or marshes and will therefore not aggravate the
flooding in the area;
• Depletion of water resources;
• Change/disruption in water circulation pattern, littoral current, and coastal erosion
and disposition;
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
7
• Degradation of water quality due to generated waste and discharges during
construction activities;
• Impact on freshwater ecology not that significant due to the lack of water uses
including fishing and species with commercial value within the impact area;
• Threats to existence and/or loss of important marine local species and habitat;
• Possible wastewater contamination caused by improper disposal system;
• Increase in seawater turbidity due to the flow of sediment streams brought about by
reclamation activities; and
• Mangrove planting will be implemented in suitable areas to be identified.
Sa air and noise naman po ay ito:
• Minimal changes in local micro-climate;
• Contribution in the locality’s greenhouse emission mainly during the construction and
operation phase;
• Degradation of air quality; and
• Increase in ambient noise level.
Under people module naman po:
• Improve road capacity and safety for pedestrians;
• Traffic congestion within the impact area will worsen during construction phase;
• Development of a walkable neighborhood;
• Creation of new jobs for the community and boost the local economy;
• The project will utilize other means of resources and thus will not create competition;
• The Proposed Reclamation Project does not pose a threat on the existing peace and
order as all construction activities will be confined at sea and managed by the
proponent; and
• Minimal impact on public health because the activities and the small number of
persons involved will be based on the sea vessels.
Eto naman po ang project benefits: una, to improve and continue Catbalogan City as the
primary economic hub of the Province; to provide easier access to the tourist and investment
destinations; and to provide jobs and employment benefits during project construction and
operations. Yun lamang po. Maraming salamat.
KATE: Thank you po. Ngayon po let’s all welcome Ar. Berlin Gascon from Two Eco.
AR. BERLIN: This presentation is for the proposed waterfront projects in Brgy. Mercedes. Eto
po yung project data ng Mercedes site, which is envisioned to be a modern central business
district that will provide competitive business and job opportunities for the residents. The
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
8
land use is dominantly mixed-use in nature; ang mixed-use po ay type ng land use na
pwedeng magsama ang commercial and residential; or commercial and institutional.
Pinapakita ko po ngayon itong land use plan, at makikita ninyo na divided siya into
development zones, which are based on existing development in the area. We have three
major development zones: mixed-use commercial in red, mixed-use tourism in yellow, and
mixed-use institutional in blue. The remaining smaller zones naman po sa masterplan are
introduced as support to the main development – light industrial in brown, utilities in grey,
and fisherman’s village in orange.
ENGR. DEXTER: Before po tayo magproceed sa ating Open Forum, may I request our Hearing
Officer to present yung mga house rules para po maging maayos ang daloy ng ating Open
Forum. Kaunting reminder na lang din po para sa ating mga on-site participants, pwede tayo
magpakilala in Waray, Tagalog, o English, kung saan tayo komportable. Sir Sherwin, kindly
facilitate po.
SIR SHERWIN: First of all po, I would like to welcome everyone to this Public Hearing. I
would like to formally open the Public Hearing. Unang-una po sa lahat, my name is Sherwin
Avestruz, ako po ay taga-EMB Office, at na-designate po ako bilang Hearing Officer para sa
Public Hearing na ito, by the EMB CO. Bilang Hearing Officer po, it is my job to ensure na
orderly and peaceful ang conduct of this Public Hearing; therefore, meron po tayong kaunting
rules and regulations na kailangan i-observe. I would like to emphasize that above all, if there
are any untoward incidents, I reserve my right to remove anyone na magcacause ng untoward
incident in this meeting. First and foremost, I would like to emphasize that for everyone in
the zoom meeting, please ensure that your audio is muted. Another thing is for your mobile
phones to be switched to silent mode. The comments should be based on correct data and
information, so ibig ko pong sabihin ay sana walang mga fake news; the discussion should be
directly relevant to the issue at hand; comments should be made on the behalf of public
interest and not on personal interest; and of course, proper decorum, so no catcalls, booing,
etcetera. Since it’s about 11am na din, I would like to ask the stakeholders to state your name
and representation ninyo, before the question, for documentation purposes. Thank you.
RAUL: Ako po si Raul, Vice-Chairman ng [inaudible] Samar. My question is paano yung mga
kagaya namin na affected ng project?
SIR BRETT: As presented po by Ar. Gascon kanina, magkakaroon po tayo ng fisherman’s
village, yung color orange. Maglalagay po tayo ng area ng market para sa mga fresh catch
natin. Actually po sir, magkausap kami ni Sir Gerry, at magcocoordinate po kami para ma-
address ang concern ni sir regarding the project.
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
9
SIR SHERWIN: Let’s proceed sa next question po.
VON: May question po dito sa chat box, babasahin ko lang po: Good morning, meron po bang
private proponent for this project?
SIR BRETT: As of now ay wala tayong private proponent since the project is initiated by the
Provincial Government of Samar.
VON: Next question po natin ay: Can we ask for a copy of the EIA. Sasagutin ko na po: yes,
you can ask for a copy of the EIA natin, yung presentation kanina. We can send that thru
email. Kindly provide us with your email, and we can send a copy.
ENGR. DEXTER: To add lang po doon sa nagtanong, meron po tayong softcopy na available
sa ating website. Andun po ang softcopy ng EIS as well as notice sa Public Hearing. Punta
lang po tayo sa EIA website – eia.emb.gov.ph. For those naman po na nasa on-site, meron
pong hardcopy ng EIS Report ang LGU ng Catbalogan City, pwede po ninyo tignan.
SIR SHERWIN: So ulitin ko lang po ang next question natin, from ma’am. Ang tanong po ni
ma’am ay ano po ba ang plano ng project proponent during construction para sa mga
madidisplace o maapektuhan ng trabaho? We would like to recognize Atty. Allan Rambano,
Legal Officer; he is to answer the question.
ATTY. ALLAN: Kung mapapansin niyo po sa presentation kanina, hindi po siya one-time
big-time na gagawin lahat. We shall be doing this po phase by phase.
SIR SHERWIN: One follow up question po, ma’am. Tinatanong po ni ma’am kung saan po
pupunta yung mga madidisplace na fishermen temporarily, habang kino-construct?
SIR BRETT: Para maklaro po ang lahat, kasi po ang iba, ang alam lang nila ay reclamation
project lang ang meron sa Mercedes. So andito po ang representative po ng implementing
office na gumagawa ng isang project na ongoing na ngayon, yung Brgy. Mercedes Coastal
Dike. Andito po si Engr. Jun.
ENGR. JUN: Good morning po, I am from the implementing office in DPWH. To answer
ma’am’s question where will be the temporary place for the fisherfolks while the project is
ongoing, the ongoing embankment is under the implementation of the contractor. There are
allowances for the access of the equipments going to the project. So yun po, ma’am.
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
10
SIR SHERWIN: Eto po bang embankment ay project din ng Provincial Government? May
pagtatambak na po ba?
ENGR. JUN: Yes po. Eto pong pagtatambak sa site ay para po gawing access ng contractor
pagpunta dito sa reclamation.
STAKEHOLDER (name is inaudible): Sa ngayon ay ongoing ang embankment for the access
road going to the reclamation project. Now there are fisherfolks that are being affected.
Ngayon saan sila lulugar? Nagrereklamo ang fisherfolks.
SIR SHERWIN: Ibig ninyo sabihin sir may mga madidisplace?
STAKEHOLDER (name is inaudible): Yes. Meron pong mga affected dahil sa ginagawang
embankment project. Saan temporarily ilalagay ang mga fisherfolks na affected nitong
project?
ENGR. JUN: Okay, to answer your question, sir, hindi naman po lahat ay matatambakan. Sabi
nga po si Atty. Allan, by phasing po itong projects. So ang ginagawa po ni contractor ay ito
po munang sa isang side; at ongoing po ang aming assessment para po sa right-of-way. Hindi
naman po matatambakan ito, so pwede po sa part na yun.
STAKEHOLDER (name is inaudible): Pinaaalis daw sila ng contractor, yun ang sabi ni
Kapitana. Saan po sila pwede ilagay?
ENGR. JUN: Sige po sir, i-verify po muna namin. Salamat po.
SIR SHERWIN: To the proponent, please take note of the issue.
STAKEHOLDER (name is inaudible): Hindi po namin alam sa barangay na may ganitong
project pala na iniimplement.
SIR SHERWIN: I-tatake note po ito ng proponent, kasi po sir, napapansin ko na this is a
separate project. Para ho hindi tayo mag-do away sa purpose nitong Public Hearing na ito,
which is the Mercedes Reclamation Project. I suggest we move forward, pero duly noted po
itong issue. Bigyan naman ho natin ng chance those mga nasa zoom meeting.
ENGR. DEXTER: Sir, naka-raise hand po si Sir Mark John Pineda from PRA.
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
11
SIR MARK: Good morning, sir. Question lang po. Saan po ang location nung nagface-to-face?
Saan po exact location ninyo?
REPRESENTATIVE FROM THE PLGU: Sir, ang venue po ng face-to-face meeting ay nasa
Session Hall ng Sangguniang Panlalawigan ng Samar. Catbalogan po, Capitol Building,
second floor.
SIR MARK: Tapos po my next question ay doon sa pinresent kanina ni Ar. Gascon, about the
masterplan. Kasi she mentioned about the open space and green space. Included po ba ang
mga road sa kanyang computation?
AR. BERLIN: The green and open space computation includes all roads, retention ponds, and
esplanade.
SIR MARK: Irereiterate lang po namin ang policy ng PRA, AO 2019-05, requiring all proposed
reclamation na magkaroon ng 5% open space. Excluded po dyan ang roads sa green space.
You can check po our policy para sa provision na yan. We are stating po this early para po
ma-consider ng proponent sa planning stage. And then last, sir, there was some mention of
the connecting bridge from the reclamation site at sa road. Was that part of the development?
Na-cover din ba siya ng application ng ECC?
SIR BRETT: As of now, hindi pa siya nasali sa application namin for ECC kasi yung project pa
lang po natin na gagawin at ang priority is the reclamation. Kung meron na po kaming pondo,
then yun po yung time na mag-aapply kami for another ECC for the separate project. Thank
you.
SIR MARK: Hindi po kakailangain ang bridge sa pagtambak? Kasi po land-based ang quarry
natin.
SIR BRETT: Yes po. Yung bridge po required lang siya para maka-connect ang Mercedes to
the other proposed reclamation site, which is located sa Pier 1 to Bunuanan.
SIR SHERWIN: Gusto ko lang po basahin yung nagchat ng question nila, for the benefit of
those in the zoom meeting. This one is from DIPH, Ma’am Isabel Calantoc. Ma’am Calantoc
is asking: Meron na bang contractor for this project to do the reclamation? Meron po bang
bidding process?
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
12
ENGR. BOYET: Meron pong bidding process na ginawa dito, at meron na din po tayong
contractor. Pero ulitin ko lang po, this project is Provincial Government of Samar initiated and
funded. Wala pong private proponent dito.
SIR SHERWIN: I would like to move on to the next question in the chat box. This one is from
Ma’am Nikka Oquias. Ma’am Nikka is asking: may cost-benefit analysis ba na ginawa for this
project looking into its long-term effects on the fragile marine ecosystem and the livelihood of
the fisherfolks?
VON: Yes po, may ginawa pong cost-benefit analysis for this project.
SIR SHERWIN: Is this available po ba? Sa EIA Study po ba ay na-report na ito?
VON: Yes po, meron po sa EIS Report natin. Kung gusto po nila ma-access, we can send the
copy of the cost-benefit analysis for this project.
SIR SHERWIN: Ang question po ni sir [on-site stakeholder] ay ano daw po ang magiging
status ng occupancy ng mga existing land owners on the area which will be affected by this
proposed reclamation? Yung mga nagreclaim na daw po, kasi meron na daw pong
nagreclaim.
ATTY. ALLAN: Yung mga private individuals na nagreclaim na, hindi po yun kasama dito
sa project na ito. PRA po ang may jurisdiction sa private individuals na nagreclaim na; pero
sa tanong niyo po ay magiging ano ang status ng area na nireclaim nila, hindi po namin
masasagot iyon dahil hindi po namin sakop yun. Outside po iyan sa area of this project.
ENGR. DIOMEDES: This is Engr. Diomedes Tan from PRA, Reclamation Department. That’s
true – existing and unauthorized reclamations in the area will be under the jurisdiction of
PRA. We intend to undertake a survey of these illegal reclamations in Mercedes. The survey
and the Presidential Proclamation that will be secured by PRA will cover the entire area that
is illegally reclaimed. The occupants or reclaimers can avail of the existing policy of PRA on
how to legally acquire the ownership of these reclaimed lands. That’s all.
ENGR. BOYET: Affected po kayo dahil nasa isang coastal area kayo. Kung ano po ang
mangyayari sa implementation sa Mercedes, there is a possibility na yung effects, for example
po sa water quality, ay mapupunta din sa coastal area ninyo kasi ilang metro lang ang haba.
Part po ng public consultation ay kailangan namin kayo isali dahil concern din namin kayo.
Directly or indirectly ay maapektuhan po kayo, kaya po kailangan aware din kayo na may
ganito tayong project.
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
13
SIR RENE: Ako po si Rene Zaldy Porlaje, from BFAR-CO. Yung una ko pong question: nakita
ko po sa mapa na malawak pa ang land area ng Catbalogan. So bakit po magrereclaim e
malawak naman ang area? Magkukumpulan tayo dito sa coastal area na maraming masisira
na marine resources at maapektuhan ang communities. Pwede pong pakipaliwanag sa aming
lahat kung bakit kailangan natin magreclaim e hindi pa naman po siksikan kagaya sa
Maynila?
REPRESENTATIVE FROM THE PLGU: Taga-Catbalogan po ba kayo, sir?
SIR RENE: Ah, hindi po, sa Northern Samar po ako. Pero sa Maynila po ako nagtrabaho, sa
Central Office.
REPRESENTATIVE FROM THE PLGU: Ah, ganito po kasi yun, sir. Ang structure po ng
Catbalogan, mula po sa shoreline, hindi po aabot ng isang kilometro ay bundok na kaagad.
So yung bundok po na yun, mas mahirap po tanggalin yun kesa mag-reclaim. Kung andito
po kayo sa Catbalogan, makikita niyo po na yung inexplain niyo ngayon na malawak ang
Catbalogan City, hindi po yun tugma in a way na ang Catbalogan po ay bundok-bundok,
hindi po pwedeng i-develop kaagad. So etong option po namin ay reclamation, which is
allowed naman po sa batas. So kung ang sinasabi po ninyo ay mas madaling i-develop ang sa
bundok, hindi po kami agree doon, sir, dahil kung nakikita po ninyo ang topography dito ay
bundok po talaga.
SIR RENE: Ang next ko pong tanong ay meron po kaya kayong listahan ng fisherfolks na
maapektuhan? Tsaka kasama ang kanilang mga bangka? Pwede po kami makakuha ng
listahan?
SIR BRETT: Yes sir, meron po kaming listahan from BFAR R8, kasi prior to our request sa
DENR-EMB for the ECC Clearance, humingi tayo ng certification from BFAR. Nagconduct po
ang BFAR-RO ng assessment, validation, and thankfully ang recommendation nila is okay to
construct the reclamation project. Kung wala po kayong kopya sir, bibigyan namin kayo.
Thank you.
SIR RENE: Ang concern po namin ay paano naman po ang hanapbuhay ng ating fisherfolks
kung sila ay ma-displace? Malawak po itong project ninyo. Next ko pong tanong ay: na-
delineate na po ba ang Catbalogan City, ang kanila pong city waters? Na-mapa na po ba ito
ng NAMRIA?
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
14
ENGR. BOYET: Hindi po natin masasagot yan sir, kung na-delineate na ang city waters ng
Catbalogan, pero I can assure you na ang coverage ng project is well within the waters ng
Catbalogan. Whether or not may delineation po yun ay hindi po affected ang nearby
municipal waters.
SIR RENE: Kaya ko po natanong ay kasi 35 hectares po itong project, maapektuhan po ang
municipal waters, mag-eextend po siya kasi shoreline po ang ating baseline. Paano po ma-
resolve ang issue na ito?
ENGR. DIOMEDES: The definition of the municipal waters is that its coverage is measured at
90 degrees from the shoreline, 15 kilometers outward. So, our reclamation project is less than
1 kilometer. What can I say is that it is well within the municipal waters of Catbalogan City
ENGR. DEXTER: Sir, naka-raise po ang virtual hand ni Ma’am Cherry Grace Ungab, from the
CENRO.
MA’AM CHERRY: Good morning po. I am Cherry Grace Ungab of CENRO Catbalogan. May
concern lang po ako since na-mention po kanina na sa reclamation, ang in charge po doon ay
PRA. So, ang concern ko lang po ay anong mangyayari sa may existing foreshore lease
application sa office that are still pending due to lack of certification from DPWH and CPDO
since na-deny ang mga application/certification nila since may proposed yung Province natin
for the reclamation. Although matagal na kasi yung ibang application doon sa table namin,
hindi kasi namin siya maproprocess because of that lack of certification. Itatanong ko lang
sana kung pwede na ba namin ma-proceed yung processing o kailangan po bang pending
muna yun?
ENGR. DIOMEDES: Our advice to the DENR-CENRO is that applications should be held in
abeyance because PRA is going to apply for the titling and ownership of those reclaimed
lands, in behalf of the national government. That’s the law, and that’s the existing policy of
the PRA. So, the applicant that can claim the ownership of those reclaimed lands will be the
PRA. We’ll just be complicating the process if DENR will have to act/approve those
applications for foreshore lease agreement, because at the end, PRA is going to apply for
Presidential Proclamation for those reclaimed lands, and PRA is going to ask DENR to exclude
those areas for the tenurial instrument, so that the survey plan of those areas can be approved
in favor of the PRA.
MA’AM CHERRY: Okay sige po, we will arrange that in our office kasi merong iba kasi na
foreshore lease applicants, na although hindi ganun kalakihan ang application nila, gusto pa
din nila mag-apply ng foreshore lease siguro para ma-legalize ang occupation nila.
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
15
ENGR. DIOMEDES: Maybe CENRO can process an irrevocable permit application, which is
one-year renewable to legalize the occupancy of the people residing in those areas.
MA’AM CHERRY: Yes po, since illegal na nga po ang pag-occupy nila ng area, hindi pa po
sila nagbabayad sa government. Yun lang naman po ang concern ko.
SIR SHERWIN: Ma’am Cherry Grace, sorry po, but I believe this can be best addressed if you
directly coordinate na lang po with the PRA. Pasensya na po, so that we can move forward
with the next question. Basahin ko po yung nasa chat box, galing po ito again kay Ma’am
Nikki Oquias: Saan po kukunin ang filling materials for this project?
ENGR. BOYET: Ma’am, the source of fill materials would be on-site po. Yun lang po, ma’am.
SIR SHERWIN: Another question po from the chat box. Sir, follow up po: if awarded na yung
project, may we know kung sino po yung contractor to do the reclamation project?
REPRESENTATIVE FROM THE PLGU: Awarded na po siya sa Northern Builders.
SIR SHERWIN: Saan po based ito?
REPRESENTATIVE FROM THE PLGU: Catarman, Northern Samar.
SIR SHERWIN: Tinatanong po ni sir (on-site stakeholder) kung na-implement na daw po ba
o nagstart na yung project as of today?
REPRESENTATIVE FROM THE PLGU: Kanina po nasagot na ng UPMO yan, ang ongoing
pong works ay para sa dike. Eto pong reclamation na ito ay for implementation pa, at wala
hindi pa pwedeng iimplement dahil wala pa tayong Notice to Proceed from PRA at ang ECC.
Kaya po tayo andito ngayon para sa ECC. Under DPWH po yung nakikita niyong works sa
ngayon.
SIR SHERWIN: For the information po for those in the zoom meeting, ang sabi po ni sir ay
sana ho ma-coordinate ni proponent sa barangay kung ano mang activities or related activities
na meron yung project, especially daw itong implemented by the DPWH, kasi for example
daw po, eto ngayon ay hindi nila alam.
REPRESENTATIVE FROM THE PLGU: Actually po, nagkaroon kami recently lang ng Public
Hearing din po para doon sa works natin.
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
16
SIR SHERWIN: For the record po, ang sabi po ni sir (another on-site stakeholder) ay yung
mga residents daw from the Barangay Mercedes are worried na baka sila ay maisali sa
reclamation proponent. Nanghihingi po si sir ng response or comment from the proponent.
ATTY ALLAN: Magandang umaga po, sir. Kagaya po ng sinabi ko kanina sir, yung mga
residente po dito, whether legal or illegal, hindi po sila kasama sa project na ito. So kung ano
po ang inookupahan nila dun ngayon, ay sasagutin nila sa PRA. Pero hindi po sila sakop sa
area ng project na ito. So kung may pag-aalala po sila sir, siguro po dapat ay
makipagcoordinate na sila sa PRA tulad ng na-discuss natin kanina at yung discussion ng
CENRO at PRA regarding pending applications. Thank you po.
SIR SHERWIN: For the record po, ang tanong ni sir (different on-site stakeholder) is na-
coordinate na ba City Government of Catbalogan? Kasi ang inemphasize ni sir ay ang
importance ng comprehensive land use program, so he’s asking if na-cooordinate daw ba ito
sa City Government?
ATTY ALLAN: Klaruhin ko lang, sir, kasi sabi po ninyo “nag-umpisa,” pero hindi pa po tayo
nag-umpisa. For the information ng lahat, wag po tayo macoconfuse, hindi pa po ito nag-
umpisa. Ngayon, sa pangalawang question po ninyo kung nagcoordinate ba sa City
[Government], nag-coordinate po tayo; meron po silang representative na present sa meeting
na ito at meron din po kaming nirequest sa kanila na No Objection Resolution para sa project
na ito. Isa po yun sa mga requirements na hinihingi.
SIR SHERWIN: (Talking to the on-site stakeholder asking a question) So gusto ho ninyo
malaman kung ano ang plano nila para sa waterways, kasi po affected daw sila ng flooding
even before the implementation of the reclamation project.
ATTY ALLAN: Ito pong project na ito ay isa sa ginawa para maiwasan yung current flooding
sa Mercedes. Kung napansin po ninyo kanina, mayroon po doon sa plano na mga waterways,
tapos yung tubig po doon ay mapupunta sa isang water pump. Mayroon po tayong
consultants na nagstudy kung ano po ang current status ng flooding doon para ma-
incorporate siya sa project.
SIR SHERWIN: For the benefit po ng mga nasa zoom meeting and for the record na po din,
ang tanong po ni sir (another on-site stakeholder) is nakakasigurado ba ang project na hindi
magagaya ang Barangay Mercedes sa mga nangyaring baha sa Malabon?
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
17
REPRESENTATIVE FROM THE PLGU: Yung pagtatagpo po ng highest level ng lupa at tubig,
yun po ay act of God. Pero sinisigurado po ng Province na gagawin po namin lahat ng
precautionary measures para hindi mangyari yung pagbabaha ngayon sa Malabon. Kung
sakali mang dumating yung panahon na magbaha pa din, hindi po natin mapipigilan yun
kasi ang ulan ay hindi po natin hawak. Pero yung project po natin ay may ginagawang mga
study, kasama po doon ang drainage improvement, master development plan upang
matanggal ang problema sa pagbaha. Ang magagawa lang po natin ay gawing leksyon kung
ano man ang nangyayari sa Malabon para ma-apply natin dito upang maiwasan yun.
REPRESENTATIVE FROM DPWH: Ang maisasagot ko po, sa part ng DPWH, ay yung tide
embankment po na ginagawa natin ay nagkaroon po ng study sa Bureau of Design na naka-
design po siya na kahit magkaroon po ng storm surge o di kaya ay highest tide na sinasabi
ninyo, naka-design po siya na i-withstand po yung ganung klaseng sakuna. Pagkatapos po
nitong coastal dike, may proposed po ang DPWH doon po sa pumping stations. Ang
mangyayari po doon, ang magiging mechanics po ng pumping station, kapag nagkaroon po
ng baha sa reclamation area, i-pupump out po ng pumping station yung tubig palabas para
lahat po ng tubig na ma-iimpound doon sa loob ay mailabas po. Actually po yung coastal dike
po natin ay naka-design siya para sa 50-year return period, ibig sabihin po ay doon po sa 50
years na yun, more or less ay kaya niya i-withstand ang mga phenomena na pwede mangyari.
SIR SHERWIN: For those in the zoom meeting, basahin ko po muna yung nasa chat box: from
Ma’am Nikka Oquias, nanghihingi po si ma’am ng access sa list of affected fisherfolks. To the
proponent, please take note po. From Sir Rene again: ilan po ba ang total area ng city waters
ng Catbalogan at ilang percent po ang mababawas for this project? The proponent po is
requesting for a resource person from the City Government.
REPRESENTATIVE FROM THE PLGU: Kasi po kung ang tinatanong ay city waters of
Catbalogan, hindi po namin masasagot yun, sir, the exact area of the city waters.
SIR SHERWIN: Any representative po from Catbalogan Planning [and Development Office]?
Okay po, we shall ask the preparer na lang po to take note of this question. Another question
po from BFAR, sabi po ni sir: Please clarify, is this a PLGU proposal or from the PRA?
REPRESENTATIVE FROM THE PLGU: Province of Samar initiated and funded po, sir.
SIR SHERWIN: For those raising their hands po, from PRA, Ma’am Christine?
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
18
MA’AM CHRISTINE: Yung question ko po ay regarding the source of filling material. Saan
po kukunin ang filling material? Parang hindi po nasagot kanina. Request ko na lang po sana
yung ibang information kasi hindi po clear yung audio.
SIR SHERWIN: For the preparer po, kindly take note of this, salamat po. From Sir Marlon
Sale, PFO.
SIR MARLON: Good morning, everyone. By the way, I am Marlon Sale, OIC-PFO ng Province
of Samar. Yung office namin is nasa Catbalogan. Para lang po ma-clarify and additional
information for Sir Rene ng BFAR-CO, last January, Gov. Mike Tan requested BFAR R8 to
conduct a rapid resource assessment sa proposed reclamation area dito sa Catbalogan. Yung
result ng rapid resource assessment, finorward na po sa BFAR-CO, baka po Sir Rene hindi
niyo pa nakikita, last March 2021. Makikita niyo po doon ang coral assessment, yung fish
biodiversity and biomass, nandoon po. Regarding naman po sa registered fisherfolks sa
Barangay Mercedes at Bunuanan, actually kami sa RO, yung available data po ay yung nasa
system, pero mas accurate po kung kukuha tayo ng list of fisherfolks sa City Agriculture
Office ng Catbalogan. Yun ang mas accurate kasi every year yung registration nila.
SIR SHERWIN: For the last question siguro, from Ma’am Anita, from DENR-BMB po.
MA’AM ANITA: Dapat po kasi ang sumasagot sa question sa assessment ay ang proponent,
but then again ay wala na tayong time. But then may comment po dito si sir na nasa EIS
[Report], pero hindi naman kasi lahat ay nakakabasa doon. I think you have to present din, in
a powerpoint presentation, yung assessment na nagawa. At sa source of filling materials,
sinagot naman siya dito, nakalagay sa Catbalogan City. Ang alam ko dapat ito may ECC din.
May ECC din ang area na pagkukuhanan ninyo ng filling materials. Yun lang naman for now.
SIR SHERWIN: We would like to recognize Mr. John Gopez, from the preparer.
ENGR. JOHN: Ma’am Anita, good morning. For the question ng kasamahan natin for BFAR,
nagkaroon po ng rapid resource assessment ang BFAR, as requested by the Provincial
Government, and the result of the assessment was forwarded to Director Bayate. Then again,
the Provincial Government, ni-reinforce po nila ang resource assessment na ginawa ni BFAR;
nagconduct po ng another resource assessment yung preparer. Basically, the methodology na
ginamit po for the benthic lifeforms is yung manta-tow and spot-dive surveys. Based po sa
suggestion po ni Ma’am Anita, we shall include that in the powerpoint presentation para po
mas ma-appreciate ng participants dito sa Public Hearing yung naging resulta po ng
assessment. Tapos sa filling materials naman po, tama po kayo doon na dapat may application
yan ng ECC; but dito po, for this reclamation project, hindi na po namin siya isinama. It will
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
19
have a separate ECC application. Basically, the coverage of the ECC application is yung
reclamation lang po. Pero yung members po ng Review Committee, pina-include lang po
kung saan ang source of filling material para lang po ma-identify kung saan dadaan yung
mga hauling trucks para po makuhanan namin ng air quality baseline data. We’ll closely
coordinate with the PLGU regarding the matter po, salamat.
SIR SHERWIN: Hindi naman po nagtatapos dito; for those po na may issues or concerns, you
may submit a position paper or send us an email. At this point, I would like to take it upon
myself yung next portion, which is the recap of issues and concerns, for lack of material time.
ENGR. DEXTER: Yes, sir, we can proceed with the recap of issues and concerns. May isa pa
naman po tayong Public Hearing, which is for the Pier 1 Reclamation Project, later po ng 2pm.
SIR SHERWIN: Given there are no more concerns, I move to adjourn the Public Hearing. Are
there any violent reactions po? Given there are none, the Public Hearing is adjourned po at
exactly 12:20 PM.
ENGR. DEXTER: Sir, quick na next steps lang po. Ididiscuss po ito ni Engr. Joel.
ENGR. JOEL: Thank you, Dexter. For our next steps and way forward. Currently we are
already in the conduct of Public Hearing, the proponent has already presented the Mercedes
Reclamation Project. Later po we shall have the one for Pier 1 to Bunuanan Reclamation
Project, considering po na adjacent yung mga lugar kaya we are doing the review
simultaneously. Yung documentation po nito, we shall provide sa ating website; and at the
same time, yung updated po na EIS incorporating the issues and concerns raised during this
Public Hearing para ma-address po nila further. You may visit our website at emb.gov.ph and
kindly click lang po yung “Environmental Impact Assessment”, and look for the “Notice of
Online Public Hearing/Consultation,” and then hanapin niyo lang po yung project na ito,
since andun naman po ang schedules ng lahat ng mga hearing na pinapagawa sa amin ng
aming office. Makikita niyo din po doon ang Revised EIA Report.
Sa mga stakeholders po na hindi naka-join ng ating Public Hearing, kindly send an email and
address it to our director, Engr. William Cunado, and attention to our Division Chief, Engr.
Esperanza Sajul. Our email address is [email protected] and [email protected]. You may
also contact us at (02) 8539 4378 loc. 116. Happy lunch po, and thank you po sa pag-attend
nitong Public Hearing.
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
20
3 Issues and Concerns raised during the Open Forum
After the presentation of the Project Description and EIA process, an Open Forum was
conducted and was facilitated by Mr. Sherwin Avestruz, Public Hearing Officer, from EMB
Regional Office 8 to maintain the peace and order.
The issues/concerns raised during the open forum are presented verbatim in the tables
below:
3.1 Project Description Table 3.1. Issues and Concerns on Project Description
Issues and Concerns
Sector or Persons who raised the issues/concerns
Proponent response/ DENR response to the issues and
concern
EIS page number
Good morning, meron po bang
private proponent for this
project?
Isabel Calantoc,
DIPH
As of now ay wala tayong
private proponent since the
project is initiated by the
Provincial Government of
Samar. (Sir Brett, PLGU of
Samar)
Meron na bang contractor for
this project to do the
reclamation? Meron po bang
bidding process?
Isabel Calantoc,
DIPH
Meron pong bidding process
na ginawa dito, at meron na
din po tayong contractor. Pero
ulitin ko lang po, this project is
Provincial Government of
Samar initiated and funded.
(Engr. Boyet, PLGU of Samar)
If awarded na yung project, may
we know kung sino po yung
contractor to do the reclamation
project?
Isabel Calantoc,
DIPH
Awarded na po siya sa
Northern Builders. [Based po
sila] sa Catarman, Northern
Samar. (Representative of the
PLGU of Samar)
Na-implement na daw po ba o
nagstart na yung project as of
today?
On-site
stakeholder
Kanina po nasagot na ng
UPMO yan, ang ongoing pong
works ay para sa dike. Eto
pong reclamation na ito ay for
implementation pa, at wala
hindi pa pwedeng iimplement
dahil wala pa tayong Notice to
Proceed from PRA at ang ECC.
Kaya po tayo andito ngayon
para sa ECC. Under DPWH po
yung nakikita niyong works sa
ngayon. (Representative of the
PLGU of Samar)
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
21
Issues and Concerns
Sector or Persons who raised the issues/concerns
Proponent response/ DENR response to the issues and
concern
EIS page number
Sana ho ma-coordinate ni
proponent sa barangay kung ano
mang activities or related
activities na meron yung project,
especially daw itong
implemented by the DPWH, kasi
for example daw po, eto ngayon
ay hindi nila alam.
On-site
stakeholder
Actually po, nagkaroon kami
recently lang ng Public
Hearing din po para doon sa
works natin. (Representative
of the PLGU of Samar)
Na-coordinate na ba City
Government of Catbalogan?
On-site
stakeholder
Sa question po ninyo kung
nagcoordinate ba sa City
[Government], nag-coordinate
po tayo; meron po silang
representative na present sa
meeting na ito at meron din po
kaming nirequest sa kanila na
No Objection Resolution para
sa project na ito. Isa po yun sa
mga requirements na hinihingi.
(Atty. Allan, PLGU of Samar)
Please clarify, is this a PLGU
proposal or from the PRA?
BFAR FRMD Province of Samar initiated
and funded po, sir.
(Representative from the
PLGU of Samar)
Saan po kukunin ang filling
material?
Ma’am Christine On-site po, sa Catbalogan City.
(Engr. Boyet, PLGU of Samar)
3.2 Land
Table 3.2. Issues and Concerns on Land
Issues and Concerns
Sector or Persons who raised the issues/concerns
Proponent response/ DENR response to the issues and
concern
EIS page number
My next question ay doon sa
pinresent kanina ni Ar. Gascon,
about the masterplan. Kasi she
mentioned about the open space
and green space. Included po ba
ang mga road sa kanyang
computation?
Irereiterate lang po namin ang
policy ng PRA, AO 2019-05,
requiring all proposed
reclamation na magkaroon ng
Sir Mark John
Pineda, PRA
The green and open space
computation includes all roads,
retention ponds, and
esplanade. (Ar. Berlin, Two
Eco)
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
22
Issues and Concerns
Sector or Persons who raised the issues/concerns
Proponent response/ DENR response to the issues and
concern
EIS page number
5% open space. Excluded po
dyan ang roads sa green space.
You can check po our policy
para sa provision na yan.
There was some mention of the
connecting bridge from the
reclamation site at sa road. Was
that part of the development?
Na-cover din ba siya ng
application ng ECC?
Sir Mark John
Pineda, PRA
As of now, hindi pa siya nasali
sa application namin for ECC
kasi yung project pa lang po
natin na gagawin at ang
priority is the reclamation.
Kung meron na po kaming
pondo, then yun po yung time
na mag-aapply kami for
another ECC for the separate
project. (Sir Brett, PLGU of
Samar)
Hindi po kakailangain ang
bridge sa pagtambak? Kasi po
land-based ang quarry natin.
Sir Mark John
Pineda, PRA
Yes po. Yung bridge po
required lang siya para maka-
connect ang Mercedes to the
other proposed reclamation
site, which is located sa Pier 1
to Bunuanan. (Sir Brett, PLGU
of Samar)
Nakita ko po sa mapa na
malawak pa ang land area ng
Catbalogan. So bakit po
magrereclaim e malawak naman
ang area? Magkukumpulan tayo
dito sa coastal area na maraming
masisira na marine resources at
maapektuhan ang communities.
Pwede pong pakipaliwanag sa
aming lahat kung bakit
kailangan natin magreclaim e
hindi pa naman po siksikan
kagaya sa Maynila?
Sir Rene Zaldy
Porlaje, BFAR-CO
Ang structure po ng
Catbalogan, mula po sa
shoreline, hindi po aabot ng
isang kilometro ay bundok na
kaagad. So yung bundok po na
yun, mas mahirap po tanggalin
yun kesa mag-reclaim. Kung
andito po kayo sa Catbalogan,
makikita niyo po na yung
inexplain niyo ngayon na
malawak ang Catbalogan City,
hindi po yun tugma in a way na
ang Catbalogan po ay bundok-
bundok, hindi po pwedeng i-
develop kaagad. So etong
option po namin ay
reclamation, which is allowed
naman po sa batas. So kung ang
sinasabi po ninyo ay mas
madaling i-develop ang sa
bundok, hindi po kami agree
doon, sir, dahil kung nakikita
po ninyo ang topography dito
ay bundok po talaga.
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
23
Issues and Concerns
Sector or Persons who raised the issues/concerns
Proponent response/ DENR response to the issues and
concern
EIS page number
(Representative from the PLGU
of Samar)
Saan po kukunin ang filling
materials for this project?
Ms. Nikka Oquias, Oceana
Ma’am, the source of fill
materials would be on-site po.
(Engr. Boyet, PLGU of Samar)
3.3 Water
Table 3.3. Issues and Concerns on Water
Issues and Concerns
Sector or Persons who raised the issues/concerns
Proponent response/ DENR response to the issues and
concerns
EIS Page Number
May cost-benefit analysis ba na
ginawa for this project looking
into its long-term effects on the
fragile marine ecosystem and
the livelihood of the fisherfolks?
Ms. Nikka
Oquias, Oceana
Yes po, may ginawa pong cost-
benefit analysis for this project.
(Von, Envia Consultancy)
Na-delineate na po ba ang
Catbalogan City, ang kanila
pong city waters? Na-mapa na
po ba ito ng NAMRIA?
Sir Rene Zaldy
Porlaje, BFAR-CO
Hindi po natin masasagot yan
sir, kung na-delineate na ang
city waters ng Catbalogan,
pero I can assure you na ang
coverage ng project is well
within the waters ng
Catbalogan. Whether or not
may delineation po yun ay
hindi po affected ang nearby
municipal waters. (Engr. Boyet,
PLGU of Samar)
Kaya ko po natanong ay kasi 35
hectares po itong project,
maapektuhan po ang municipal
waters, mag-eextend po siya
kasi shoreline po ang ating
baseline. Paano po ma-resolve
ang issue na ito?
Sir Rene Zaldy
Porlaje, BFAR-CO
The definition of the municipal
waters is that its coverage is
measured at 90 degrees from
the shoreline, 15 kilometers
outward. So, our reclamation
project is less than 1 kilometer.
What can I say is that it is well
within the municipal waters of
Catbalogan City. (Engr.
Diomedes, PRA)
Gusto ho malaman kung ano
ang plano nila para sa
waterways, kasi po affected daw
sila ng flooding even before the
implementation of the
reclamation project.
On-site
stakeholder
Ito pong project na ito ay isa sa
ginawa para maiwasan yung
current flooding sa Mercedes.
Kung napansin po ninyo
kanina, mayroon po doon sa
plano na mga waterways,
tapos yung tubig po doon ay
mapupunta sa isang water
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
24
Issues and Concerns
Sector or Persons who raised the issues/concerns
Proponent response/ DENR response to the issues and
concerns
EIS Page Number
pump. Mayroon po tayong
consultants na nagstudy kung
ano po ang current status ng
flooding doon para ma-
incorporate siya sa project.
(Atty. Allan, PLGU of Samar)
Nakakasigurado ba ang project
na hindi magagaya ang
Barangay Mercedes sa mga
nangyaring baha sa Malabon?
On-site
stakeholder
Yung pagtatagpo po ng highest
level ng lupa at tubig, yun po
ay act of God. Pero
sinisigurado po ng Province na
gagawin po namin lahat ng
precautionary measures para
hindi mangyari yung
pagbabaha ngayon sa
Malabon. Kung sakali mang
dumating yung panahon na
magbaha pa din, hindi po natin
mapipigilan yun kasi ang ulan
ay hindi po natin hawak. Pero
yung project po natin ay may
ginagawang mga study,
kasama po doon ang drainage
improvement, master
development plan upang
matanggal ang problema sa
pagbaha. Ang magagawa lang
po natin ay gawing leksyon
kung ano man ang nangyayari
sa Malabon para ma-apply
natin dito upang maiwasan
yun. (Representative from the
PLGU of Samar)
Ang maisasagot ko po, sa part
ng DPWH, ay yung tide
embankment po na ginagawa
natin ay nagkaroon po ng
study sa Bureau of Design na
naka-design po siya na kahit
magkaroon po ng storm surge
o di kaya ay highest tide na
sinasabi ninyo, naka-design po
siya na i-withstand po yung
ganung klaseng sakuna.
Pagkatapos po nitong coastal
dike, may proposed po ang
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
25
Issues and Concerns
Sector or Persons who raised the issues/concerns
Proponent response/ DENR response to the issues and
concerns
EIS Page Number
DPWH doon po sa pumping
stations. Ang mangyayari po
doon, ang magiging mechanics
po ng pumping station, kapag
nagkaroon po ng baha sa
reclamation area, i-pupump
out po ng pumping station
yung tubig palabas para lahat
po ng tubig na ma-iimpound
doon sa loob ay mailabas po.
Actually po yung coastal dike
po natin ay naka-design siya
para sa 50-year return period,
ibig sabihin po ay doon po sa 50
years na yun, more or less ay
kaya niya i-withstand ang mga
phenomena na pwede
mangyari. (Representative
from DPWH)
Ilan po ba ang total area ng city
waters ng Catbalogan at ilang
percent po ang mababawas for
this project? The proponent po
is requesting for a resource
person from the City
Government.
Sir Rene Zaldy
Porlaje, BFAR-CO
We shall ask the preparer na
lang po to take note of this
question. (Sir Sherwin, EMB)
Para lang po ma-clarify and
additional information for Sir
Rene ng BFAR-CO, last
January, Gov. Mike Tan
requested BFAR R8 to conduct
a rapid resource assessment sa
proposed reclamation area dito
sa Catbalogan. Yung result ng
rapid resource assessment,
finorward na po sa BFAR-CO,
baka po Sir Rene hindi niyo pa
nakikita, last March 2021.
Makikita niyo po doon ang
coral assessment, yung fish
biodiversity and biomass,
nandoon po. (Sir Marlon,
PLGU of Samar)
I think you have to present din,
in a powerpoint presentation,
yung assessment na nagawa. At
sa source of filling materials,
sinagot naman siya dito,
nakalagay sa Catbalogan City.
Ma’am Anita,
DENR-BMB
For the question ng kasamahan
natin for BFAR, nagkaroon po
ng rapid resource assessment
ang BFAR, as requested by the
Provincial Government, and
the result of the assessment
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
26
Issues and Concerns
Sector or Persons who raised the issues/concerns
Proponent response/ DENR response to the issues and
concerns
EIS Page Number
Ang alam ko dapat ito may ECC
din. May ECC din ang area na
pagkukuhanan ninyo ng filling
materials.
was forwarded to Director
Bayate. Then again, the
Provincial Government, ni-
reinforce po nila ang resource
assessment na ginawa ni BFAR;
nagconduct po ng another
resource assessment yung
preparer. Basically, the
methodology na ginamit po for
the benthic lifeforms is yung
manta-tow and spot-dive
surveys. Based po sa
suggestion po ni Ma’am Anita,
we shall include that in the
powerpoint presentation para
po mas ma-appreciate ng
participants dito sa Public
Hearing yung naging resulta
po ng assessment. Tapos sa
filling materials naman po,
tama po kayo doon na dapat
may application yan ng ECC;
but dito po, for this reclamation
project, hindi na po namin siya
isinama. It will have a separate
ECC application. Basically, the
coverage of the ECC
application is yung reclamation
lang po. Pero yung members
po ng Review Committee,
pina-include lang po kung saan
ang source of filling material
para lang po ma-identify kung
saan dadaan yung mga hauling
trucks para po makuhanan
namin ng air quality baseline
data. We’ll closely coordinate
with the PLGU regarding the
matter po, salamat. (Engr. John,
Envia Consultancy)
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
27
3.4 People Table 3.4. Issues and Concerns on People
Issues and Concerns
Sector or Persons who raised the issues/concerns
Proponent response/ DENR response to the issues and
concerns
EIS Page Number
My question is paano yung mga
kagaya namin na affected ng
project?
Raul, Vice
Chairman of an
organization of
fisherfolks
As presented po by Ar. Gascon
kanina, magkakaroon po tayo
ng fisherman’s village, yung
color orange. Maglalagay po
tayo ng area ng market para sa
mga fresh catch natin. Actually
po sir, magkausap kami ni Sir
Gerry, at magcocoordinate po
kami para ma-address ang
concern ni sir regarding the
project. (Sir Brett)
Ano po ba ang plano ng project
proponent during construction
para sa mga madidisplace o
maapektuhan ng trabaho? Saan
po pupunta yung mga
madidisplace na fishermen
temporarily, habang kino-
construct?
On-site
stakeholder
Kung mapapansin niyo po sa
presentation kanina, hindi po
siya one-time big-time na
gagawin lahat. We shall be
doing this po phase by phase.
(Atty. Allan, PLGU of Samar)
Okay, to answer your question,
sir, hindi naman po lahat ay
matatambakan. Sabi nga po si
Atty. Allan, by phasing po
itong projects. So ang ginagawa
po ni contractor ay ito po
munang sa isang side; at
ongoing po ang aming
assessment para po sa right-of-
way. Hindi naman po
matatambakan ito, so pwede
po sa part na yun. (Engr. Jun,
DPWH)
Meron po kaya kayong listahan
ng fisherfolks na maapektuhan?
Tsaka kasama ang kanilang mga
bangka? Pwede po kami
makakuha ng listahan?
Sir Rene Zaldy
Porlaje, BFAR-CO
Yes sir, meron po kaming
listahan from BFAR R8, kasi
prior to our request sa DENR-
EMB for the ECC Clearance,
humingi tayo ng certification
from BFAR. Nagconduct po
ang BFAR-RO ng assessment,
validation, and thankfully ang
recommendation nila is okay
to construct the reclamation
project. Kung wala po kayong
kopya sir, bibigyan namin
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
28
Issues and Concerns
Sector or Persons who raised the issues/concerns
Proponent response/ DENR response to the issues and
concerns
EIS Page Number
kayo. Thank you. (Sir Brett,
PLGU of Samar)
May cost-benefit analysis ba na
ginawa for this project looking
into its long-term effects on the
fragile marine ecosystem and
the livelihood of the fisherfolks?
Ms. Nikka
Oquias, Oceana
Yes po, may ginawa pong cost-
benefit analysis for this project.
(Von, Envia Consultancy)
Yung mga residents daw from
the Barangay Mercedes are
worried na baka sila ay maisali
sa reclamation proponent.
Nanghihingi po si sir ng
response or comment from the
proponent.
On-site
stakeholder
Kagaya po ng sinabi ko kanina
sir, yung mga residente po
dito, whether legal or illegal,
hindi po sila kasama sa project
na ito. So kung ano po ang
inookupahan nila dun ngayon,
ay sasagutin nila sa PRA. Pero
hindi po sila sakop sa area ng
project na ito. So kung may
pag-aalala po sila sir, siguro po
dapat ay makipagcoordinate
na sila sa PRA tulad ng na-
discuss natin kanina at yung
discussion ng CENRO at PRA
regarding pending
applications. Thank you po.
(Atty. Allan, PLGU of Samar)
3.5 Other Concerns Table 3.5. Issues and Concerns Raised (Others)
Issues and Concerns Sector or Persons
who raised the issues/concerns
Proponent response/ DENR response to the issues and
concerns
EIS Page Number
Ano daw po ang magiging
status ng occupancy ng mga
existing land owners on the
area which will be affected
by this proposed
reclamation? Yung mga
nagreclaim na daw po, kasi
meron na daw pong
nagreclaim.
On-site stakeholder Yung mga private individuals na
nagreclaim na, hindi po yun
kasama dito sa project na ito.
PRA po ang may jurisdiction sa
private individuals na
nagreclaim na; pero sa tanong
niyo po ay magiging ano ang
status ng area na nireclaim nila,
hindi po namin masasagot iyon
dahil hindi po namin sakop yun.
Outside po iyan sa area of this
project. (Atty. Rambano, PLGU
of Samar)
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
29
That’s true – existing and
unauthorized reclamations in the
area will be under the
jurisdiction of PRA. We intend to
undertake a survey of these
illegal reclamations in Mercedes.
The survey and the Presidential
Proclamation that will be
secured by PRA will cover the
entire area that is illegally
reclaimed. The occupants or
reclaimers can avail of the
existing policy of PRA on how to
legally acquire the ownership of
these reclaimed lands. That’s all.
(Engr. Diomedes Tan, PRA)
May concern lang po ako
since na-mention po kanina
na sa reclamation, ang in
charge po doon ay PRA. So,
ang concern ko lang po ay
anong mangyayari sa may
existing foreshore lease
application sa office that
are still pending due to lack
of certification from DPWH
and CPDO since na-deny
ang mga
application/certification
nila since may proposed
yung Province natin for the
reclamation. Although
matagal na kasi yung ibang
application doon sa table
namin, hindi kasi namin
siya maproprocess because
of that lack of certification.
Itatanong ko lang sana
kung pwede na ba namin
ma-proceed yung
processing o kailangan po
bang pending muna yun?
Ma’am Cherry
Grace Ungab,
CENRO
Our advice to the DENR-CENRO
is that applications should be
held in abeyance because PRA is
going to apply for the titling and
ownership of those reclaimed
lands, in behalf of the national
government. That’s the law, and
that’s the existing policy of the
PRA. So, the applicant that can
claim the ownership of those
reclaimed lands will be the PRA.
We’ll just be complicating the
process if DENR will have to
act/approve those applications
for foreshore lease agreement,
because at the end, PRA is going
to apply for Presidential
Proclamation for those reclaimed
lands, and PRA is going to ask
DENR to exclude those areas for
the tenurial instrument, so that
the survey plan of those areas
can be approved in favor of the
PRA. Maybe CENRO can
process an irrevocable permit
application, which is one-year
renewable to legalize the
occupancy of the people residing
in those areas.
(Engr. Diomedes, PRA)
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
30
Figure 4.1. Affidavit of Publication
4 Annexes
4.1 Proof of Newspaper Publications
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
31
Figure 4.3. Proof of second publication
Figure 4.2. Proof of first publication
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
32
4.2 Received Invitation Letters
Figure 4.4. Received Invitation Letter-Poblacion 1
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
33
Figure 4.5. Received Invitation Letter-City Mayor
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
34
Figure 4.6. Received Invitation Letter-DTI
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
35
Figure 4.7. Received Invitation Letter-DOT
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
36
Figure 4.8. Received Invitation Letter-Poblacion 4
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
37
Figure 4.9. Received Invitation Letter-BFAR Region 8
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
38
Figure 4.10. Received Invitation Letter-PPA/PMO Eastern Leyte/Samar
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
39
Figure 4.11. Received Invitation Letter-Poblacion 2
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
40
Figure 4.12. Received Invitation Letter-PPA
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
41
Figure 4.13. Received Invitation Letter-Poblacion 5
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
42
Figure 4.14. Received Invitation Letter-DPWH Regional Office 8
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
43
Figure 4.15. Received Invitation Letter-Samar State University
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
44
Figure 4.16. Received Invitation Letter-Business Group in Catbalogan City
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
45
Figure 4.17. Received Invitation Letter-District Representative
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
46
Figure 4.18. Received Invitation Letter-Two Eco, Inc.
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
47
Figure 4.19. Received Invitation Letter-Poblacion 3
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
48
Figure 4.20. Received Invitation Letter-Samar Chamber of Commerce and Industry
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
49
Figure 4.21. Received Invitation Letter-Philippine Reclamation Authority
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
50
Figure 4.22. Received Invitation Letter-Poblacion 10
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
51
Figure 4.23. Received Invitation Letter-GIOS-Samar, Inc.
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
52
Figure 4.24. Received Invitation Letter-PENRO
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
53
Figure 4.25. Received Invitation Letter-PCG
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
54
Figure 4.26. Received Invitation Letter-CENRO
Proposed Barangay Mercedes Reclamation Project | Public Hearing Report
55
4.3 Presentation during the Public Hearing