Date post: | 19-Jan-2023 |
Category: |
Documents |
Upload: | khangminh22 |
View: | 0 times |
Download: | 0 times |
9/21/2019
1
Integrity Commitment Passion Seamlessness Speed 1© Confederation of Indian Industry
Hindalco Industries Ltd, Hirakud
Prabhat Kumar Dip – Deputy. Manager(Energy)
Md. Imroz Ahmad – Manager(Technical Cell)
Abhijit Kumar Debata- Dy. Manager (Rectifier Station)
Integrity Commitment Passion Seamlessness Speed 2© Confederation of Indian Industry
INTRODUCTION TO HINDALCO, HIRAKUD
2
The Hirakud aluminium
smelter, located in
Sambalpur district, is
the oldest operating
smelter in India
Production capacity
increased to 216 KTPA
via brownfield
expansion of GAMI
technology based 235
kA potline, in 2013
Consistent efforts to
uphold sustainability
and consistent value
creation for all
stakeholders
Journey of our smelter
Operations based on old
Soderberg Pot (HSS) technology
Upgraded operations to prebake
technology
Completed brownfield
expansion by addition of 80
pots 1959-05
2006-12
2013-1985 kA
165 kTPA 235 kA216 kTPA
55 kA
10 kTPA
Rated smelting capacity
Operating Amperage
9/21/2019
2
Integrity Commitment Passion Seamlessness Speed 3© Confederation of Indian Industry
1a. Sp. Energy Consumption in last 3 years
9.5
1
10.9
0
11.7
5
0
2
4
6
8
10
12
14
FY'17 FY'18 FY'19
Thermal Energy(TOE) FO used in Cast House is high
due to higher quantity of
scrap melting
Integrity Commitment Passion Seamlessness Speed 4© Confederation of Indian Industry
1b. Sp. Energy Consumption in last 3 years
14
,83
9
14
,72
3
14
,89
1
14
,76
7
14600
14650
14700
14750
14800
14850
14900
14950
FY'17 FY'18 FY'19 FY'19 after
normalisation
DC Specific Energy KWH/MT 66 nos pots failed
due to flooding in
July-2018
9/21/2019
3
Integrity Commitment Passion Seamlessness Speed 5© Confederation of Indian Industry
1c. Sp. Energy Consumption in last 3 years4
.57
4.4
4
4.4
7
4.4
6
4.35
4.4
4.45
4.5
4.55
4.6
FY-16 FY-17 FY-18 FY'19
AC SEC (TOE/MT)
AC SEC (TOE/MT)
Linear (AC SEC (TOE/MT))
Specific Energy as per
Form-1
Integrity Commitment Passion Seamlessness Speed 6© Confederation of Indian Industry
National & Global benchmark
56
.30
55.8
6
56
.51
52.4
1
48
.81
FY-17 FY-18 FY-19 Indian Benchmark Global Benchmark
AC SEC(GJ/MT)
Source : CII https://www.keralaenergy.gov.in/files/Resources/Aluminium_Sector_2018.pdf
However we have
no reference of low
kA old technology
Smelter Worldwide
9/21/2019
4
Integrity Commitment Passion Seamlessness Speed 7© Confederation of Indian Industry
3a. Energy Saving projects implemented in FY ‘17
DescriptionSl. No Savings
Use of new design copper inserted collector bar to save 70 mv/pot(72pots/yr) 1 260610 KWH
Cathode lining optimization to reduce 25 mv / pot(72pots/yr) 2 1340280 KWH
Install FTP fan with VFD in FTP 13 2190000 KWH
Energy reduction in Anode Assembly (Yoke to Carbon Drop) and design
change of depth of stub hole to reduce 10 mv/pot 4 1608336 KWH
Integrity Commitment Passion Seamlessness Speed 8© Confederation of Indian Industry
3b. Energy Saving projects implemented in FY ‘18
DescriptionSl. No Savings
Use of new design copper inserted collector bar to save 70 mv/pot(72pots/yr) 1 1563660 KWH
Cathode lining optimization to reduce 25 mv / pot(72pots/yr) 2 1340280 KWH
Replacement of RS-III CT cold well pumps with Energy Efficient Pumps3 350400 KWH
Energy reduction in Anode Assembly (Yoke to Carbon Drop) and design
change of depth of stub hole to reduce 10 mv/pot 4 3909150 KWH
Current density equalization by anode change for saving 20 mv/pot5 7818300 KWH
9/21/2019
5
Integrity Commitment Passion Seamlessness Speed 9© Confederation of Indian Industry
3c. Energy Saving projects implemented in FY 2018-19
DescriptionSl. No Savings
Magnetic Compensation Bus bar Implementation 1 1298512 KWH
Anode stub hole modification in Rodding plant2 101353 KWH
Installation of 25MVAR Harmonic Filter (132KV ) at Rectifier station-43 1027898 KWH
100 % CI Rodding through Aditya CSS IN 235kA5 5072390 KWH
Use of new design copper inserted collector bar to save 70 mv/pot 4 5457480 KWH
Integrity Commitment Passion Seamlessness Speed 10© Confederation of Indian Industry
Summary of Energy Saving Projects(FY16-FY19)
Year No.of Proposal Investments Savings Payback years
2016-17 4 1800000 20409074.3 1.058352755
2017-18 5 20900000 64721332.8 3.875074711
2018-19 5 13710000 57013585.2 2.885628038
9/21/2019
6
Integrity Commitment Passion Seamlessness Speed 11© Confederation of Indian Industry
OVERVIEW
Cross-sectional schematic diagram of CellTop view of a potline
(in series)
Energy - the largest cost component
High SEC(14200kWh/mt) compare to
modern technology Plant
Low CE-93.2%
11
Rectifier
Room
-A
Room
-B
Cu
rrent o
ut
Cu
rrent in
Cathode Cathode
Anode rod
Al2O3+C 13-15kwh/kg Al+CO2
Integrity Commitment Passion Seamlessness Speed 12© Confederation of Indian Industry
CHALLENGES ENCOUNTERED
12
Hot spots Sludge and muck
Designed for 1,800 days
Started failing early
Poor flow profile
Poor alumina distribution
Resulting in
GAMI (technology supplier) also tried operating the pot for a year but failed
Sludge & MuckLoss in production man-days
High energy consumption
Difficulties in pot operation
i. Poor metal flow profile
ii. High peripheral temperature
9/21/2019
7
Integrity Commitment Passion Seamlessness Speed 13© Confederation of Indian Industry
Magnetic field measurementAnode current distributionSuperheat measurement
MEASUREMENT AND ANALYSIS
13
Joint venture of Hirakud &
JNARDDC Continuous measurement is in
progress in both the potlines
since December, 2018
Quick actions for controlling
bath chemistry
Joint venture of Hirakud &
Maesteria
To improve CV and standard
deviation of ACD
To achieve 0.5% gain in
current efficiency
Hirakud & ABSTC
To measure magnitude and
direction of magnetic field at
different location
To see actual impact of design
and simulation
Integrity Commitment Passion Seamlessness Speed 14© Confederation of Indian Industry
MEASUREMENT AND ANALYSIS
Ledge profile measurement Thermal image steel shell
Key challenges were evaluated through the below analysis
Metal velocity measurement
The above methods aided in identifying the shortcomings in design
14
9/21/2019
8
Integrity Commitment Passion Seamlessness Speed 15© Confederation of Indian Industry
Gap Analysis (Design vs actual)
15
Discovered an underlying energy saving potential of ~600kWh/T
0.380 V 0.400 VAnode Voltage
1.545 + 1.850 V 1.560 + 1.850 VElectrolyte Voltage
0.250 V 0.320 VCathode Voltage
0.240 V 0.240 VFixed Voltage
4.265 V 4.37 VTotal Voltage
13,600 kWh/T 14,200 kWh/TSpecific energy
GAMI - Specification Actual
Cathode
Insulation and refractories
Metal
(+)
Current in
Riser
Anode beam
Anode rod
Anode cover
(-)(-)
Cathode beam
Current Out Current Out
Collector bars
Anode
Integrity Commitment Passion Seamlessness Speed 16© Confederation of Indian Industry
Project No:1 MAGNETIC COMPENSATION
Modelling and simulation
Magnetic field, metal velocity
16
Rectifier
&
Transformer
In
Out
Potline
9/21/2019
9
Integrity Commitment Passion Seamlessness Speed 17© Confederation of Indian Industry
MAGNETIC COMPENSATION (Contd.)
17
Velocity profile
Average velocity reduced from 5.1 to 4.8 cm/s
Maximum velocity reduced from 20 to 12 cm/s
Eliminated dead zone at centerPlant challenges!
Integrity Commitment Passion Seamlessness Speed 18© Confederation of Indian Industry
Key milestones
MAGNETIC COMPENSATION (Contd.)
18
Executed project in 5 months (in-house)
Ensured 100% safety compliance
Extended measurement of pots to avoid any incident
Validated model predictions
First time in India and first in co-current in the
world, patent filing under progress.
Current efficiency gain of 0.5%.
Welding job under -2.5 level
Placement of busbarBusbar transfer from
warehouse
Energy saving of 170 kWh/T in the entire plant
9/21/2019
10
Integrity Commitment Passion Seamlessness Speed 19© Confederation of Indian Industry
PROJECT2:ANODE DESIGN MODIFICATION
19
Voltage used to drop to ~30% of total anode voltage
The pin to carbon voltage was reduced by increasing the pin diameter while
keeping the pin hole diameter unchanged
Increased the contact pressure between pin and carbon, reducing the voltage
drop.
Energy saving of 100 kWh/T
Pin to carbon voltage reduction
132
100
50
60
70
80
90
100
110
120
130
140
Hirakud (before
modification)
Hirakud (after
modification)
Volt
age d
rop
(m
V)
Pin diameter increased by 10 mm
150160160 160
Integrity Commitment Passion Seamlessness Speed 20© Confederation of Indian Industry
Project No: 3 132kV Harmonic Filter
Objective: To improve the power factor from 0.945 to 0.995 & reduce
generator VAR generation.
Rectifier sub-station - 4 is equipped with 2 Nos of harmonic filters of total capacity 37.22
MVAR and present power factor is 0.945 lagging. Therefore it was clear that there is a scope
of further improvement of power factor by installing an additional bank till 0.995 lagging or
better. Additional reactive load requirement is estimated to be 25 MVAR to achieve the
desired power factor.
9/21/2019
11
Integrity Commitment Passion Seamlessness Speed 21© Confederation of Indian Industry
Harmonic Filter Cont.
❖Harmonic Spectrum Consider as below.
Bank-1 Bank-2
Tuning 4.08 10.40
Frequency(Hz) 204 520
Generation (MVAr) 10 15
Proposed Filter Bank.
.132kV,10MVAr,BP Harmonic Filter bank.
132kV,15MVAr,BP Harmonic Filter bank
THDV is with-in IEEE limits with the above proposed filter banks along with the existing 5th & 11th
harmonic filter bank subject to the harmonics considered in the design basis and with min fault MVA of
5000 MVA and max of 9200 MVA with frequency variation of +/- 5%.
Integrity Commitment Passion Seamlessness Speed 22© Confederation of Indian Industry
Tangible Benefits
INPUT SECTION
❖Maximum Load(kW) 89000
❖Existing P.F. 0.945
❖Desired P.F. 0.995
❖Operating Voltage 132000
OUTPUT SECTION
❖kVA of Existing P.F. 92037
❖kVA at improved P.F. 89447
❖Saving in (kVA) 2590
❖KVAr at existing P.F.(KVAr) 28448
❖KVAr at improved P.F(KVAr) 3448
❖KVAr required(KVAr) 25000
❖Load current at existing P.F(Amp) 403
❖Load current at improved P.F(Amp) 391
❖Reduction in load current (Amp) 12
❖Additional benefit is relief of 2.59 MVA in apparent power on TG in normal operation and in demand when
operating on Grid supply. Also there will be reduction in energy consumption of cooling system of the
generator.
9/21/2019
12
Integrity Commitment Passion Seamlessness Speed 23© Confederation of Indian Industry
14,282
13,850
13600
13,500
13,900
14,300
14,700
Ap
r'18
Ma
y'1
8
Ju
n'1
8
Ju
l'18
Au
g'1
8
Sep
'18
Oct'
18
No
v'1
8
Dec'1
8
Jan
'19
Feb
'19
Ma
r'1
9
Ap
r'19
Au
g'1
9
Fy
'20
Fy
'21
Actual P&B Projected
IMPACT - ENERGY SAVINGS(235kA)
23
14,282
13,742
170
210
60 100
FY'18 Energy External busbar CuCB * Cathode sealing Anode drop Energy FY'20
Project/Area Energy saving potential (kWh/T)
Magnetic
compensation loop 170
Cathode voltage
reduction 210
Anode Voltage
reduction 100
Current
Efficiency
Increase by 0.5%;
production will increase by
270MT/year
Energy Reduction through projects
Yearly energy trend (kWh/T)
* Copper inserted collector bar
Energy savings break-up (kWh/T)
Integrity Commitment Passion Seamlessness Speed 24© Confederation of Indian Industry
IMPACT - COST SAVINGS(235kA)
24
Project/Area Investment
(in Cr.)
Maximum potential for financial
gain (Cr. per annum)
Realized financial gain
(in Cr.) @ Rs. 4/unit
Magnetic
compensation loop 4.00 3.35 1.67 (for 6 months)
Cathode voltage reduction 11.7 4.26
1.88 (will increase
after full potline
conversion)
Anode Voltage reduction 1.30 2.03 1.70 (for 10 months)
Harmonic filter 2.27 0.45 0.45
Current Efficiency NA Cost savings of Rs. 3.39 Cr. /year
Total annual savings potential of Rs. 15 Cr.
9/21/2019
13
Integrity Commitment Passion Seamlessness Speed 25© Confederation of Indian Industry
In house
development
Process control
initiatives –
JNARDDC,
MAESTERIA,
ROCKWELL
Concept
replication
from peers
First in India
initiatives through
ABSTC
COLLABORATI
ON &
SEAMLESSNES
S
SUSTAINABLE WAY FORWARD
25
Copper inserted collector bar replicated at Aditya & Mahan unit
Renukoot plant is planning to Implement compensating busbar (sustainable solution for any old potline without hampering production)
External busbar concept implemented in 6 pots of 85kA potline after completion, energy will be 13400kWh/MT
Anode stub modification in-house developed through DOE initiative
Forced cooling is a sustainable solution for any high kA GAMI potline
Technical knowledge of the team has increased; motivated to carry out other sustainable energy reduction projects
Increased collaboration across all Hindalco plants & ABSTC
Integrity Commitment Passion Seamlessness Speed 26© Confederation of Indian Industry
2018 -2020
Commissioning
2013 -15
Developmental
zone
Energy Consumption
DC-kWh/ton
SUSTAINABLE WAY FORWARD (Contd.)
26
Changes call for innovation and innovation leads to progress
VISION 2022
Achieve
14,250
2022 onwards
13,750
9/21/2019
14
Integrity Commitment Passion Seamlessness Speed 27© Confederation of Indian Industry
Established in the year1958 and with continuous capacity enhancement in limited
space, therefore no major actions could be taken on Renewable Energy Sources
except partially installed solar light. However we purchase REC’s as a part of RPO
obligations
5. Utilisation of renewable energy sources
Integrity Commitment Passion Seamlessness Speed 28© Confederation of Indian Industry
6. Utilisation of waste material as fuel
Pro
ject
1
Uses of waste wood for bath recovery in calciner
Pro
ject
2
Uses of used carbon anode butt for metal recovery from Dross(First time in India).
9/21/2019
15
Integrity Commitment Passion Seamlessness Speed 29© Confederation of Indian Industry
7. GHG20.3
6
19.8
20.6
3
FY-17 FY-18 FY'19
GHG (tCO2/t)
Target is to reduce by 35% taking 2005 as base.
The figures of Hindalco is disclosed in the yearly
sustainability report
30
,92
,70
4
32
,06
,27
3
34
,39
,39
2
FY-17 FY-18 FY'19
GHG Absolute tCO2
1. considered Scope-1 and Scope-2,
addition of Scope-3 is in process
GHG increased due to
flooding in July’2019
where we lost 66 pots
Integrity Commitment Passion Seamlessness Speed 30© Confederation of Indian Industry
8. Green Supply Chain
Alumina used in the process is transported by rakes.
Anodes used in the process is purchased from Adityawhich was earlier imported from China.
No loading/unloading vehicle is entered in the plant premises without valid pollution certificate.
9/21/2019
16
Integrity Commitment Passion Seamlessness Speed 31© Confederation of Indian Industry
1.We monitor SEC in terms of ACE,DC, Conversion Loss,FTP & Auxillary on daily basis.
2.Review meeting chaired by Mr.J.P. Nayak(Smelter Head) monthly.
3 Separate budget for Energy Conservation via Galaxy projects
4. Energy efficiency / awareness training program at Business, Cluster as well as Plant Level
organised by Corporate Energy cell and Plant Energy cell.
5. Projects are being implemented through Kaizens ( Workers and Supervisor level)
• Timer control of Plant Lighting
• Occupancy Sensor for offices.
9. Team work, Employee Involvement & Monitoring
Integrity Commitment Passion Seamlessness Speed 32© Confederation of Indian Industry
Daily Energy Monitoring
ABSOLUTE ENERGY (KWH) Potline
Average Dc
Voltage in
Volts
Potline
Average DC
Current in
kA
Metal
Production
in KGAC EnergyAC For
ElectrolysisDC Energy
Conversion
lossFTP Energy
Total
AuxiliaryCast House
Total aux
excluding
cast house
SPECIFIC ENERGY (KWH/MT)
AC Energy AC For Electrolysis DC Energy Conversion loss FTP Energy Total AuxiliaryTotal Auxiliary
excluding CH
We monitor the absolute as well as the specific energy consumption daily &
monthly for all the potlines as well as total plant.
Cast House Daily MIS Format
Date
Productio
n(T)
FRP
scrap(T)
Process
scrap(T)
Hot
metal(T) FO Consumption(KL)
Solid Ratio
(%)
Sp fuel
consumption(L/T) Remarks
9/21/2019
17
Integrity Commitment Passion Seamlessness Speed 33© Confederation of Indian Industry
We are ISO 50001:2011 certified organization
10. Implementation of ISO 50001/Green Co/IGBC rating
We are certified with ISO50001:2011.
Outcomes of Stage 2 Audit.
1. Luxmeter was not calibrated
2. All Cast Houses not included in SEU’s.
3. EOT crane not considered as SEU.
4. Strengthening Lighting Control
% Investment on turnover FY’19 – 0.1658 %
Integrity Commitment Passion Seamlessness Speed 34© Confederation of Indian Industry
11. Other Innovative Technology
AlF3 prediction model with the help of AI is being tested in one pot and is in
progress.
Electronic Pot Controller is being
replaced with PLC’s
MES Digitalization of plant data for AI
through Aspen –Tech
9/21/2019
18
Integrity Commitment Passion Seamlessness Speed 35© Confederation of Indian Industry
12. Long term vision on EE
PLC based pot controllers have been installed which will give us flexibility in process change
Coal gasification project is under progress which will be used instead of FO in Cast Houses
Graphitized cathode block to reduce DC energy
Integrity Commitment Passion Seamlessness Speed 36© Confederation of Indian Industry
THANK YOU