+ All Categories
Home > Documents > STEPS NEEDED TO OPERATE & MAINTAIN THE SUB-SLAB ...

STEPS NEEDED TO OPERATE & MAINTAIN THE SUB-SLAB ...

Date post: 24-Feb-2023
Category:
Upload: khangminh22
View: 1 times
Download: 0 times
Share this document with a friend
28
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY REGION III 1650 Arch Street Philadelphia, Pennsylvania 19103-2029 MEMORANDUM FROM: Eduardo Rovira (3HS31) On Scene Coordinator TO: Chem-Fab File RE: Steps Needed to Operate and Maintain the Sub-slab Depressurization System Installed By EPA at the Chem-Fab Property DATE: May 9, 2017 EPA installed a sub-slab depressurization system (“Depressurization System”) in the main commercial building at 300 N. Broad Street, Doylestown, Pennsylvania (part of the Chem-Fab Superfund Site) in response to the potential for an imminent and substantial endangerment to human health presented by the migration of hazardous substances (volatile organic contaminants) from soils beneath the building into office suites. The system installed at the property is described in further detail in Attachment 1. This system prevents VOC- contaminated vapors from migrating from sub-slab soils into the commercial building by drawing sub-slab vapor from beneath the foundation using a system of fans, forcing the vapors through PVC pipes, and emitting the vapors into the air outside the building where the vapors will not concentrate into unacceptable levels (as they would in the confined space of an office). In my best professional judgment, the following actions associated with operation of the system, periodic indoor sampling, and notice to EPA are necessary to prevent an imminent and substantial endangerment to human health that would otherwise exist because of the potential for the migration of hazardous substances into the office suites: 1. Operation of the Depressurization System: Ensure that the Depressurization System runs continuously (24 hours per day/7 days per week/365 days per year), subject only to periodic maintenance and unanticipated power interruptions. The Depressurization System should be run until EPA notifies the AR000662
Transcript

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY REGION III

1650 Arch Street Philadelphia, Pennsylvania 19103-2029

MEMORANDUM FROM: Eduardo Rovira (3HS31) On Scene Coordinator TO: Chem-Fab File RE: Steps Needed to Operate and Maintain the Sub-slab Depressurization System Installed By EPA at the Chem-Fab Property DATE: May 9, 2017 EPA installed a sub-slab depressurization system (“Depressurization System”) in the main commercial building at 300 N. Broad Street, Doylestown, Pennsylvania (part of the Chem-Fab Superfund Site) in response to the potential for an imminent and substantial endangerment to human health presented by the migration of hazardous substances (volatile organic contaminants) from soils beneath the building into office suites. The system installed at the property is described in further detail in Attachment 1. This system prevents VOC-contaminated vapors from migrating from sub-slab soils into the commercial building by drawing sub-slab vapor from beneath the foundation using a system of fans, forcing the vapors through PVC pipes, and emitting the vapors into the air outside the building where the vapors will not concentrate into unacceptable levels (as they would in the confined space of an office). In my best professional judgment, the following actions associated with operation of the system, periodic indoor sampling, and notice to EPA are necessary to prevent an imminent and substantial endangerment to human health that would otherwise exist because of the potential for the migration of hazardous substances into the office suites:

1. Operation of the Depressurization System: Ensure that the Depressurization System runs continuously (24 hours per day/7 days per week/365 days per year), subject only to periodic maintenance and unanticipated power interruptions. The Depressurization System should be run until EPA notifies the

AR000662

ERovira
Approved

Printed on 100% recycled/recyclable paper with 100% post-consumer fiber and process chlorine free.

Customer Service Hotline: 1-800-438-2474

property owner that the Depressurization System is no longer needed to ensure that TCE concentrations are below 8 µg/m3

VOCs within the building.

2. Maintenance of the Depressurization System: Maintain the Depressurization System to ensure its continued effectiveness until EPA determines that the Depressurization System is no longer needed to ensure that TCE concentrations are below 8 µg/m3 VOCs within the building. Such maintenance shall include, but shall not be limited to, the following:

a. No less frequently than once every three (3) months, check each magnehelic gauge installed in the Depressurization System to determine whether the gauge reads within 25% of its initial vacuum reading which is posted on the gauge. The 10 gauges installed by EPA are depicted in Figure 2 of Attachment 1. In the event one or more gauges are found to read outside its initial vacuum reading by 25% or more, notify EPA within 48 hours of such finding(s) and provide information as requested by EPA regarding the circumstances of the reading.

b. No less frequently than once every three (3) months, check each of the fans installed in the Depressurization System. The fans installed by EPA are depicted in Figure 7 of Attachment 1. In the event one or more fans ceases operation completely, operates in a manner that does not keep its magnehelic gauge reading within 25% of the initial reading, or operates in a manner that evidences imminent failure (e.g., noisy operation), notify EPA within 48 hours of becoming aware of such condition, replace such fan with a unit that has specifications that are substantially identical to those described for the fans in Attachment 1 and notify EPA within 48 hours after such replacement.

3. Sampling: Conduct air sampling, as specified below, to monitor the effectiveness of the Depressurization System until EPA determines that the Depressurization System is no longer needed to ensure that TCE concentrations are below 8 µg/m3VOCs within the building. Such sampling shall include the following:

AR000663

Printed on 100% recycled/recyclable paper with 100% post-consumer fiber and process chlorine free.

Customer Service Hotline: 1-800-438-2474

a. Perform indoor air sampling in each existing and future tenant space (whether in use or not) in the building during January or February of each year. Samples should be taken at the locations indicated in Attachment 2 unless the interior configuration of the tenant spaces is changed. If the existing configuration is changed (e.g., walls added or removed), notify EPA and EPA will make modifications as necessary to the sampling locations. Sample all locations within the building as approved by EPA.

b. Analyze air samples for the contaminants identified in Attachment 3 using the following parameters:

Sampling Device: Summa Canister (24-hour regulator) Matrix: Air Parameter: VOCs Method: TO-15 + TICs

c. Send copies of samples results to EPA no later than ten (10) business days after the validated data have been received.

4. Notice of Changes to Existing Floorplans, Status of the Foundation, or Factors Which Cause Indoor VOC Levels to Exceed Acceptable Levels. Notify EPA of any construction at the building or other event or condition which results in any of the following:

a. a significant change to the layout or size of any existing or future tenant space within the building;

b. damage to or penetration of the foundation of the building; or

c. TCE levels are below 8 µg/m3 within the building.

5. Records. Maintain records documenting all actions taken to comply with the above actions including, but not limited to, records documenting (1) maintenance of the Depressurization System, (2) sampling, including dates and results and (3) changes to the building triggering the above-described notice requirement.

AR000664

Printed on 100% recycled/recyclable paper with 100% post-consumer fiber and process chlorine free.

Customer Service Hotline: 1-800-438-2474

Attachment 1: Active Soil Depressurization System Report (WPB Enterprises, Inc.)(May 18, 2016)

Attachment 2: Sampling Locations Attachment 3: Sampling Analytes

AR000665

Printed on 100% recycled/recyclable paper with 100% post-consumer fiber and process chlorine free.

Customer Service Hotline: 1-800-438-2474

ATTACHMENT 1

AR000666

Chem Fab ASD Installation Report rev1 page 1 of 18 5/18/16

For

NorthStar Federal Services, Inc.

55 Progress Place, Unit 1 Jackson, NJ 08527

By

WPB Enterprises, Inc.

2844 Slifer Valley Rd.

Riegelsville, PA 18077

610 346-8004

[email protected]

300-330 NORTH BROAD ST.,

DOYLESTOWN, PA

ACTIVE SOIL DEPRESSURIZATION

SYSTEM REPORT

AR000667

Chem Fab ASD Installation Report rev1 page 2 of 18 5/18/16

1.0 System Description

The 300-330 Broad St., Doylestown building will hereafter be referred to as Chem-Fab. Chem-

Fab is a slab on grade structure about 150 feet long by 75 feet wide, covering about 10,200 square

feet. The building is occupied by six tenants. Each of the occupied units has finished floor

coverings that limit the access to check sub-slab communication and to install a vapor intrusion

mitigation (VIM) system. Different areas of the building are identified by either their street

number or the type of business occupying the space. See Figure 1 and Figure 2

A sub-slab depressurization system was determined to be the most appropriate way to reduce

occupant exposure to chemicals under the slab. Sub-slab communication testing was performed at

eight different locations in the building. The test results indicated limited pressure field extension

with varying requirements. Nine separate systems were installed with a total of 15 suction points.

Two styles of fans were used a high flow AMG Fury fan and a high vacuum GBR76SOE fan. The

GBR76SOE fan had the advantage of being able to adjust the fan voltage to allow the system to be

optimized for system effectiveness and system efficiency.

During the installation the soil in System Eight suction pit was wet clay. After the system was

activated the fan at System Eight started exhausting water. The suction pit was relocated closer to

an existing sump pit. The new suction pit was dry just below the bottom of the slab where the

suction piping was re-routed to. The sump pump in the pit outside was replaced with a unit that

had a lower water table set point to assure there would be good drainage from the under slab to the

pit.

.

Figure 1: Aerial view

Figure 1: Chem-Fab over view

AR000668

Chem Fab ASD Installation Report rev1 page 3 of 18 5/18/16

2.0 Sub-Slab Depressurization System Installation & Maintenance

The Chem-Fab VIM system consisted of ten separate fan systems. Each system had piping routed

from the fan to one to three suction pits. The fans all exhaust above the existing roof. Typical fan

installation detail for the GBR76 SOE fans is depicted in Figure 4, 5 and 6. Table 1 lists all the

fans

System

# Fan

Fan

Wattage

Fan

Location

Number

Suctions CFM Mag

Suction

Type

Sys #1 Festa Fury 138 Outside 2 136 -1.3” Fig 6

Sys #2 GBR76 SOE 240 Roof 2 67 -10.0” Fig 4

Sys #3 Festa Fury 138 Roof 2 133 -1.5” Fig 4

Sys #4 GBR76 SOE 210 Roof 2 33 -9.5” Fig 4

Sys #5 Festa Fury 138 Roof 2 139 -1.25” Fig 4

Sys #6 GBR76 SOE 288 Outside 1 106 -4.0” Fig 6

Sys #7 GBR76 SOE 252 Outside 1 96 -3.5” Fig 6

Sys #8 GBR76 SOE 294 Outside 1 112 -3.5” Fig 6

Sys #9 GBR76 SOE 102 Outside 1 82 -2.0” Fig 6

Sys #10 GBR76 SOE 180 Outside 2 90 -5.0” Fig 6

The fan electrical usage is approximately 876 Kw/hrs per 100 watts of fan consumption. If the

current electrical utility rate is about $ 0.15 / Kw/hr, the year long cost for each 100 watts of fan

electrical consumption would be $131.40 per year or about $10.95 per month. The total wattage is

about 2000 watts or $219 per month at $ 0.15 / Kw/hr rate.

System maintenance is to twice a year check the magnehelic gauges to determine if reading is

within 25% of their initial vacuum reading. Note that there can be some variation in the

magnehelics reading due to periods of rain that saturate the soil and reduce system airflow which

would increase the vacuum reading. Within a few days after the rain period the magnehelic gauge

readings should return to their original vacuum reading.

Table 1: System Fan List

AR000669

Chem Fab ASD Installation Report rev1 page 4 of 18 5/18/16

20'-0"

330 N Broad

328 N.Broad

324 N.Broad

320-322 N.Broad314 N.Broad

310 N.Broad

300 N.Broad

Inside Sub-Slab Suction

Solid PVC vent piping

Sub-Slab Suction from Outside

Fan Location

3" PVC

Fury1.15 amps

GBR76 SOE2.0 amps

Fury-1.15 amps

Fury-1.15 amps

GBR76 SOE1.75 amps

3" PVC

GBR76 SO2.4 amps

Sys #1

Sys #2

Sys #3

Sys #4

Sys #5

Sys #6

Sys #7

Sys #8

Mag #8-3.5"

Mag #7-3.5"

Mag #6-4.0"

Mag #4-9.5"

Mag #5-1.25"

Mag #1-1.3"

Mag #2-10.0"

Mag#3-1.5"

GBR76 SOE

2.4 amps

GBR76 SOE2.1 amps

Sys #9

GBR76 SOE

0.85 amps

Mag #9-2.0"

GBR76SOE1.5 amps

Sys #10

Mag#10-5.0"

Figure 2: Mitigation System as built Layout

Ell

0

Q

I 0

o : O : o i 0

0 I

I :o ===,·,1@0

0 0 I :o :CJ

~== _=====::______:::71@ :o

------7

o : I

I I I

AR000670

Chem Fab ASD Installation Report rev1 page 5 of 18 5/18/16

3" or 4 Inch PVC

Typical 4 inch slab

Excavate at least 1 cubic of soil

Backer rod

Non-shrink Mortar

Figure 3: Detail of Sub-Slab Suction

~ a q C) C, v' Cl 0

q 0 q q d C)

v' (l v' q v' 0

q C, v' v' 0

() q q C, 0

C,

v' v' C, q q q 0 0 v'

C) C,

q C, C, 0

q <) 0 q <) C,

C, C, q C, q d 0 C, 0 0

AR000671

Chem Fab ASD Installation Report rev1 page 6 of 18 5/18/16

GBR 76 SOEFan

½” by ½” vinyl

coated mesh inside coupling

East Side Building

Wall

Water Tight Switch

3" PVC

3" to 3" Rubber

boot

Pipe flashing

Conduit

Roof Deck

3" PVC

Pipe Pier Classic if needed

Figure 4: GBR76 SOE Roof Mount Details

0 0

[;]

AR000672

Chem Fab ASD Installation Report rev1 page 7 of 18 5/18/16

Uni-strut brackets

Magnehelic pressure gauge

Sloped ¼” id

tubing

Exterior wall

½” by ½” screened open cap

Roof Fascia

Inside Slab

Fan Height To be

determined on site

3x3 Rubber

Boot

GBR 76 SOE Fan

Fan Disconnect

Switch

Offset 3" PVC pipe as necessary to meet brackets

Figure 5: Front Detail of East Side Outside Fan

AR000673

Chem Fab ASD Installation Report rev1 page 8 of 18 5/18/16

Outside

3X3 rubber boots

½” by ½”

stainless screen

Sub-Slab Soil

3" PVC elbow sealed in foundation

Slab

Inside

Excavate 1.0 Ft3 of sub-slab material

GBR76 SOEfan

3 ¼”

unistrut

1 5/8"” unistrut

Exhaust 12" above roof

Two 45 degree elbows offset to match 1 5/8" unistrut

Fan can be mounted directly on

wall or use Obar Fan Swivel support

Figure 6: Side Detail of East Side Outside Fan

-\

AR000674

Chem Fab ASD Installation Report rev1 page 9 of 18 5/18/16

330 N Broad

328 N.Broad

324 N.Broad

320-322 N.Broad

314 N.Broad

310 N.Broad

300 N.Broad

Inside Sub-Slab Suction

Sub-Slab Suction from Outside

Fan Location

Sys #1

Sys #2

Sys #3

Sys #4

Sys #5

Sys #6

Sys #7

Sys #8

Test Holes

T2

T1

T3

T4

T6

T7T8T10

T11

T14

T13

T15

- 39 pa-38.0 pa

- 3.8 pa

- 0.1 pa

- 47.0 pa

- 4.0 pa - 28.0 pa

- 3.2 pa

- 1.5 pa

- 25.0 pa

- 135 pa

- 0.8 pa

T5

T9

T12

Sys #9

Sys #10

- 29.0 pa

- 9.5 pa

Figure 7: Sub-Slab Vacuum

0 0 . El)

0 0

Q . I

@ 0

@

@ El)

El) 0 @

0 0 0 I •

0 0 @

0

0 @

0

@ 0 0

0 0 @ El)

0 . o ~ . • I 0 I I l 0

u 0

I I

O · d Do ·

AR000675

Chem Fab ASD Installation Report rev1 page 10 of 18 5/18/16

Test Hole Sub-Slab Vacuum

T1 - 39.0 pa / - 0.156”

T2 - 38.0 pa / - 0.152”

T3 - 9.5 pa / - 0.038”

T4 - 29.0 pa / - 0.116”

T5 - 47.0 pa / - 0.188”

T6 - 5.2 pa / - 0.021”

T7 - 3.8 pa / - 0.015”

T8 - 0.1 pa / - 0.0004”

T9 - 28.0 pa / - 0.112”

T10 - 4.0 pa / - 0.016”

T11 - 3.2 pa / - 0.013”

T12 - 1.5 pa / - 0.006”

T13 - 25.0 pa / - 0.100”

T14 - 135.0 pa / - 0.006”

T15 - 0.8 pa / - 0.003”

Table 8: Final Sub-Slab Vacuum

Figure 8: Measuring System Airflow & Amperage

AR000676

Chem Fab ASD Installation Report rev1 page 11 of 18 5/18/16

Figure 9: System One

Figure 10: System Four

AR000677

Chem Fab ASD Installation Report rev1 page 12 of 18 5/18/16

Figure 11: System Five

Figure 12: System Six and Seven

AR000678

Chem Fab ASD Installation Report rev1 page 13 of 18 5/18/16

Figure 14: System Eight

Figure 13: System Six and Seven Mufflers

AR000679

Chem Fab ASD Installation Report rev1 page 14 of 18 5/18/16

Figure 15: System Nine

Figure 16: System Nine pipe routed through interior to roof

AR000680

Chem Fab ASD Installation Report rev1 page 15 of 18 5/18/16

Figure 17: System Ten

Figure 18: System Two, Three, Four, Five gauges

AR000681

Chem Fab ASD Installation Report rev1 page 16 of 18 5/18/16

THE OBAR GBR76 COMPACT RADIAL BLOWER

Based on 25 years of experience

and 2 years of research and

development, the patent pending GBR

series of compact radial blowers

provide the perfect combination of

performance and design.

PERFORMANCE

• GBR76 SOE 16” WC @ 0 Max flow 155 CFM.

• GBR76 UD 40” WC @ 0 Max flow 195 CFM.

• Built in speed control to customize performance.

• Condensate bypass built in.

• 12 month warranty 40,000 hr sealed bearings.

DESIGN

• Our modular design means the blower and manifold assembly can be removed and replaced as

a unit.

This makes repairs cost effective and easy and allows contractors to upgrade systems simply

by

swapping assemblies.

• The GBR series is based on a bypass blower designed to handle combustible materials.

The housing is not required to be air tight so you can add gauges and alarms without

compromising the

system.

• Built in condensate bypass.

• Built in speed control.

• Quick disconnect electrical harness.

• All UL listed components including UL listed enclosure for outside use.

• Wall fastening lugs included.

• GBR series roof and wall mounts available to quickly configure the blowers for your

installation while

• providing a custom built look.

• Compact design 16”x 14”x 8” weighing only 18 lbs.

• 3” schedule 40 inlet and exhaust.

• Universal Drive accepts voltage from 120-240V without alteration

Wattage 150-320 @ 16” WC, 110-200 @ 12” WC, 60-120 @ 8” WC, 37-50 @ 4” WC

Blower Specifications

AR000682

Chem Fab ASD Installation Report rev1 page 17 of 18 5/18/16

OBAR SYSTEMS INC 117 POCANTECS ROAD HIGHLAND LAKES NJ 07422 800 949 6227

Figure 19: Obar GBR76 SOE Warranty

No tes~ • lnpu:t Volg9• Ran~: 10!1 132 Varu I\C. RM5- so.. 60 HL ~ p~ • lnl""f Cu,..,_t: 6 Jmp1 AC R,1,0,S • Opuar.ln9 TftTlpwau, ,. (Ambl•nt Airu,d Wodlift9 Alrl: O''C 10 SO'C • s~ Tvl'TU>'lnturr. -'O"t IQ ~"C • °'"'*'ric. Tffl.i119: I !>00 Volu N:. fl.1,.IS -,(I H, ..,.,io«,J foe ,111111, ="c bt:t¥oeet> in!)ul Dtn~ and QIOUnd, 3mJ\ 1r .. ~~ m.1»1mu.rn • Spttd Cont:J'c>I ,...,U,.xh; 1-'WM (f'-11<.-WKllt, MO<lul,.119nlt I •Hilo IU lo.ttl:

o co 1ovnc oprl'd conuol Mie.:hitn ,,_,I: "p0t .. ,.11~'-"\'" •\ ohs1 t~llllt,for >P=icon~D( ll'>t-blowr< Tt..-po1r-n11-ran bt-pr-tfo, • ~~.ptt<l ACC,e\\ b~ ,odj1J\t"""11loo~ In mi>tOt MIJMl\q

• Ap,woxinata W«l9ht .I 81 b<. , J , 1<-9 • RegulaUIJ')I Ag.ti>q, ~fiati<>re Undffwr lr!"i t...boGitoltes In<' ULidl? ~ ww1et r.1.,_£9,4.UD M\CC<>mpll.vit - tlleCflowllalta,g;;~ ?OO!Y951£C. - 04slgn FtilWres-; O~gnod r;c l'lt:hlkli-- vrhd>I .... ,nn,.., f11t r- t lO,, S. CD.....,h,lon in hfgh ~ g¥ fu?d tombum '"¥/~U"l'U. B,.,nr w,th rn:><H,-lung "''"""'iiiu. m_... ~ng auembl)I ton.muC19<1 ot doe ca,:i llllumlnum lmpelll!r conuiucted Crom l>atdaved awtTIIIWffl Rlibbef KOlatiOfl ffl<lunntu,,lt Into blo,""' co,,UtW:tJo,, to~ v,br.u,qn w,th-01hP....r.w Tv-o ~.blawer'1omlng .issemblt W!il.U<dWlthO-rfng ~t forc.ombunfcmappllciruam. C.u11mmen~ 11!1:por,s.l..ue_ ;od:9!dl.fow-.any l:Ubgeona 1he blawer i,ist;;ill,d '1l!O tbe tin.u ap,:,r,cai.oon.

• MlKJtl~ Bknn!t !'"Ila. dddarg?. and . I mcmrniol"19 inh-1 ar•chi,Kharg,, ..mus rmra notJ~ obmuaai. "4umr wn~laDoi> •m I» fn.'1!! al ah-.md otlu!r fonjg,, IDJUda. (ie. bt<'ott,lng qLL&! 1y Ill·) Blo.wni le:, bemou'1t<d M>ventll:rl'Of'•lru.,_ ho; n:,-c,ro.,La~d POWERCONHKTlON! Bluwll,ro,,,-:mr AA'PU..~M.AT.E-NLOl\.pill'Tna. I .lSO'J.!J.(l S-PEW CONNECTION! ~ «Jfll"'<!t'.Ot r.i,.o,..-,. Mln• Frt r J»rt no. 39-30-3:>56 Mn1il1'1 ~ ,.,.,.. , IJPOII rvq\H.Cd.

~nclosure Specifications ~3tin.g:

ngress Protection (EN 60529): 66/67

15,51 [393,8 ]

r ~. Screw cover

AR000683

Chem Fab ASD Installation Report rev1 page 18 of 18 5/18/16

Figure 20: Festa AMG Fury Fan Warranty

Installation & Wiring Instructions for AMG In Line Centrifugal Duct Fans

® Model: AMG Spirit, Fury, Legend, Hawk, Maverick, Prowler, Eagle

IMPORTANT NOTE : DO NOT CONNECT THE POWER SUPPLY UNTIL THE FAN IS COMPLETELY INSTALLED. MAKE SURE THE ELECTRICAL SERVICE TO THE FAN IS LOCKED IN "OFF" POSITION.

PLEASE READ AND SAVE THESE INSTRUCTIONS:

Warning - To reduce the risk of fire, electric shock or injury .to person:1, observe the following.

1. This unit is only for use in the manner intended by the manufacturer. If you have any questions contact the manufacturer Festa Manufacturing Enterprises LLC. 2. Installation work and electrical wiring must be done by qualified person'(s} in accordance with all applicable codes and standards, including fire-rated construction. 3. Sufficient air is needed for proper combustion and exhausting of gases through the flue, (chimney} of fuel burning equipment to prevent back drafting. Follow the heating equipment manufacturer's guideline and safety standards such as those published by the National Fire Protection Association (NFPA}, and the American Society for Heating, Refrigeration and Air Conditioning Engineers (ASHRAE}, and the local code authorities. 4. When cutting or drilling into wall or ceiling, do not damage electrical wiring and other hidden utilities. 5. Ducted fans must always be vented to the outdoors. 6. These units can be mounted indoors or outdoors .. 7. Do not use these fans with solid state speed controllers. 8. The electric motor is protected by an internal O'(erheat device to prevenUminimize motor damage. If the motor stops working, immediate inspection should be carried out by suitably qualified persons. 9. Before servicing or cleaning the unit,! switch power off at service panel and lock the service disconnecting means to prevent power from being switched on accidentally. When the service disconnecting means cannot be locked, securely fasten a prominent warning device, such as a tag, to the service panel. · 10. Do not use in a window. · I 11 . If this unit is to be installed over a tu,b or shower, it must be marked as aI>propriate for the application and be connected to a GFCI (Ground Fault Circuit Interrupter) - protected branch circuit. 12. Never place a switch where it can be reached from a tub or shower. 13. CAUTION: For General Ventilating Use Only. Do Not use to Exhaust Hazardous Or Explosive Materials and Vapours. 1

12. CAUTION: This unit has an unguarded impeller. Do Not Use in Locations Readily Accessible To People or Animals.

Installation of FME AMG PATRIOT Radon Fans. The FME AMG PATRIOT Fan can be 111ounted indo.ors or outdoors. We suggest that EPA recommendations be used in choosing the fan location. The AMG Fans may be mounted directly onto the piping system or fastened to a supporting structure. When mounting directly onto a vertical piping system, it is the installers responsibility to make provision to prevent the pipe ;system sliding -into and onto the fan motor and impeller. When installing a system with short doct runs terminating close to the fan i.e. within 60" (1 .5m} suitable guards should be incorporated. It is the responsibility of the installer to ensure that all aspects of the system are taken into consideration. Rigid ducting sections should be connected to fan spigots by flexible connectors and clips. The flexible connectors used should be suitable for routine servicing and vibration isolation. ·

AR000684

Printed on 100% recycled/recyclable paper with 100% post-consumer fiber and process chlorine free.

Customer Service Hotline: 1-800-438-2474

ATTACHMENT 2

AR000685

$1

!(

!(

")

!(

") !(

!(

") !(

")

!(

!(

")

!(

!(

!(

Chem-Fab RemovalDoylestown, Bucks County, Pennsylvania

TDD#: WS01-14-04-001Contract: EP-S3-15-02

Figure 3Air Sampling Locations

File: Y:\EPA_Region_III\ChemFab\MXD\Broad_St_bldg_results.mxd, 2/17/2016 11:51:08 AM, ricksc

Legend!( Indoor Air") Sub Slab$1 Ambient

´

I 300 N.Broad I

)-1

I 314 N.Broad I ---,

I 330 N Broad I

I 328 N.Broad I

I 324 N.Broad I

lp==~--=-~~~~I ~2~;;!~ I

)'.:2Q:0---+-----'ceKI

AR000686

Printed on 100% recycled/recyclable paper with 100% post-consumer fiber and process chlorine free.

Customer Service Hotline: 1-800-438-2474

ATTACHMENT 3

AR000687

chemical_name1,1,1-TRICHLOROETHANE1,1,2,2-TETRACHLOROETHANE1,1,2-TRICHLORO-1,2,2-TRIFLUOROETHANE1,1,2-TRICHLOROETHANE1,1-DICHLOROETHANE1,1-DICHLOROETHENE1,2,4-TRICHLOROBENZENE1,2,4-TRIMETHYLBENZENE1,2-DIBROMOETHANE (ETHYLENE DIBROMIDE)1,2-DICHLOROBENZENE1,2-DICHLOROETHANE1,2-DICHLOROPROPANE1,3,5-TRIMETHYLBENZENE (MESITYLENE)1,3-BUTADIENE1,3-DICHLOROBENZENE1,4-DICHLOROBENZENE1,4-DIOXANE (P-DIOXANE)2-HEXANONE4-ETHYLTOLUENEACETONEBENZENEBENZYL CHLORIDEBROMODICHLOROMETHANEBROMOFORMBROMOMETHANECARBON DISULFIDECARBON TETRACHLORIDECHLOROBENZENECHLOROETHANECHLOROFORMCHLOROMETHANECIS-1,2-DICHLOROETHYLENECIS-1,3-DICHLOROPROPENECYCLOHEXANEDIBROMOCHLOROMETHANEDICHLORODIFLUOROMETHANEDichlorotetrafluoroethaneETHANOLETHYL ACETATEETHYLBENZENEHEXACHLOROBUTADIENEISOPROPANOLM,P-XYLENE (SUM OF ISOMERS)METHYL ETHYL KETONE (2-BUTANONE)METHYL ISOBUTYL KETONE (4-METHYL-2-PENTANONE)METHYLENE CHLORIDE

I

I

I

AR000688

N-HEPTANEN-HEXANEO-XYLENE (1,2-DIMETHYLBENZENE)PropeneSTYRENETERT-BUTYL METHYL ETHERTetrachloroethylene (PCE)TETRAHYDROFURANTOLUENETRANS-1,2-DICHLOROETHENETRANS-1,3-DICHLOROPROPENETRICHLOROETHYLENE (TCE)TRICHLOROFLUOROMETHANEVINYL ACETATEVINYL CHLORIDE

I

I

I

I

AR000689


Recommended