Page 1: Possible Run 10 plan based on 25 Nov Revised Plan

Possible Run 10 plan based on 25 Nov Revised Plan

• Run10, 25 cryo-weeks (my guesses after Jan 12)

– Dec. 1, Begin cool down to 4.5K – Dec. 4, Cooldown to 4.5K complete in both rings!– Dec. 5, beam setup in RHIC begins.– Dec 16, 20 hr unplanned Maintenance day– Dec 20 (AM)-21(PM), blizzard 09 shut us down– Dec. 27, RHIC Setup complete, begin Ramp Up for Physics (was 14 Dec, late)– Dec 31 (midnight-store 11340), Machine (and PHENIX?) Physics declared s=200 GeV/n Au-Au– Jan 2 (midnight) STAR in Physics Mode– Jan 8 (0600) PHENIX in Physics Mode– Jan 12, Rebucketing not yet routine, stochastic cooling still to come.– Jan 22, changed beta* from 0.6 to 0.7 meters, rebucketing ~established, yellow transverse stochastic cooling on– Mar. 11, End 10 week s = 200 GeV/n Run, begin s = 62.4 GeV/n setup– Mar. 13, Begin 4 week s = 62.4 GeV/n run– Apr. 10, End 4 week s = 62.4 GeV/n Run, begin s = 39 GeV/n setup– Apr. 12, Begin 1.5 week s = 39 GeV/n run– Apr 18-22, Satogata is away– Apr. 23, End 1.5 week s = 39 GeV/n Run, begin s = 7.7 GeV/n setup– Apr. 25, Begin 4 week s = 7.7 GeV/n run– May 20, End 4 week s = 7.7 GeV/n Run, begin s = 5.0 GeV/n setup– May 23, End 4 week s = 7.7 GeV/n Run, begin s = 5.0 GeV/n setup – May 23 – 28 IPAC (Kyoto)– May 25, begin 0.5 week beam studies at s = 5 GeV/n and n ~ 0.67 - – 25 CRYO WEEK– This is it unless we have $’s to run longer – revisit in March– May 29, end 0.5 week studies– May 31, begin s = 11.5 GeV/n for STAR– Jun 15, end 2 week s = 11.5 GeV/n run– Jun 15 , Begin Cryo Warm-up– Jun 16, Warm-up complete, Run 10 ends – 28.2 CRYO WEEKS

Page 2: Possible Run 10 plan based on 25 Nov Revised Plan

0

1000

2000

3000

4000

5000

6000

7000

0 1 2 3 4 5 6 7 8 9 10

mb-1

Weeks of Physics collisions

Run 10 100 x 100 GeV/n Au Delivered Luminosity

MinMaxSTAR-PhysicsPHENIX-PhysicsMachine (PHENIX ZDC)

as of 1 Feb, through store 11595PHENIX Goal*

PHENIX Minimum Goal*

STAR Goal

* With 20 cm sigma IR diamond

Page 3: Possible Run 10 plan based on 25 Nov Revised Plan

0

200

400

600

800

1000

1200

1400

1600

0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5

mb-1

Weeks of Physics collisions

Run 10 100 x 100 GeV/n Au Delivered Luminosity

MinMaxSTAR-PhysicsPHENIX-PhysicsMachine (PHENIX ZDC)

as of 1 Feb , through store 11595

Page 4: Possible Run 10 plan based on 25 Nov Revised Plan

0

20

40

60

80

100

120

140

160

0 1 2 3 4 5 6 7 8 9 10

mb-1

/day

Weeks of Physics collisions

Run 10 100 x 100 GeV/n Au Delivered Luminosity per day

Min

Max

STAR

PHENIX

Yellow Transverse Stochastic Cooling onRebucketing ~on (22 Jan)

as of 1 Feb, through store 11595

Page 5: Possible Run 10 plan based on 25 Nov Revised Plan

71.3

178.9

588.6

359.5

72.4

179.4

599.7

358.8

80.3 43.0 107.2 76.2

0

100

200

300

400

500

600

700

800

12/31 to 1/07

1/08 to 1/14

1/15 to 1/21

1/22 to 1/28

period

inte

grat

ed lu

mni

osity

[mb^

-1]

0

24

48

72

96

120

Run 10 (AuAu) -- Integrated Luminosity by week

hour

s pe

r wee

k at

sto

re

Phenix STAR (lumi) hours at store

thru store 11573ending 20:28 28 January Goal

Min

Max

Page 6: Possible Run 10 plan based on 25 Nov Revised Plan

Last three fills

Page 7: Possible Run 10 plan based on 25 Nov Revised Plan

Last three fills

PHENIX ~ at trigger rate limit

Page 8: Possible Run 10 plan based on 25 Nov Revised Plan

Last three fills

Page 9: Possible Run 10 plan based on 25 Nov Revised Plan

Through 1/31/10

RHIC Cryo Operations FY09-10

0.00

1.00

2.00

3.00

4.00

5.00

6.00

7.00

8.00

-30 -10 10 30 50 70 90 110 130 150 170 190

Days since beginning of Run

MW

RHIC Cryo 10

RHIC Cryo 09

Page 10: Possible Run 10 plan based on 25 Nov Revised Plan

Through 1/31/10

RHIC Operations FY09-10

0.00

5.00

10.00

15.00

20.00

25.00

30.00

-30 -10 10 30 50 70 90 110 130 150 170 190

Days since beginning of Run

MW

CAD P ower 09

CAD P ower 10

Page 11: Possible Run 10 plan based on 25 Nov Revised Plan

Future Topics• Toward Smaller beta* - new quad triplets – D. Trbojevic

Page 12: Possible Run 10 plan based on 25 Nov Revised Plan

Archive

Page 13: Possible Run 10 plan based on 25 Nov Revised Plan

Ring Bunches/Cycles

Avg Bunch in RHIC (10^6 ions)

Avg Efficiency XCBM to RHIC XCBM to Uxf1 Uxf1 to Wxf Wxf to Arc Arc to RHIC

Blue 56/56 909 0.836 1.056 0.963 0.992 0.828

Yellow 56/56 990 0.971 1.085 0.962 0.959 0.970

Injected Beam Statistics for Fill number 11340Started filling RHIC: Thu Dec 31 22:51:52 2009, Fill complete: Thu Dec 31 22:59:50 2009, Minutes to fill: 7

31 Dec 1st Physics Store

Ring Bunches/Cycles

Avg Bunch in RHIC (10^6 ions)

Avg Efficiency XCBM to RHIC XCBM to Uxf1 Uxf1 to Wxf Wxf to Arc Arc to RHIC

Blue 68/68 1031 0.906 1.053 0.964 1.001 0.892

Yellow 68/68 991 0.938 1.050 0.964 0.993 0.934

Injected Beam Statistics for Fill number 11370Started filling RHIC: Tue Jan 5 03:22:19 2010, Fill complete: Tue Jan 5 03:32:02 2010, Minutes to fill: 9

5 Jan Physics Store

Ring Bunches/Cycles

Avg Bunch in RHIC (10^6 ions)

Avg Efficiency

XCBM to RHIC XCBM to Uxf1 Uxf1 to Wxf Wxf to Arc Arc to RHIC

Blue 111/28 1160 0.936 1.036 0.961 1.000 0.940

Yellow 111/28 1150 0.917 1.034 0.960 0.991 0.932

Injected Beam Statistics for Fill number 11493Started filling RHIC: Tue Jan 19 12:20:17 2010, Fill complete: Tue Jan 19 12:25:12 2010, Minutes to fill: 4Newfill time: Tue Jan 19 12:09:38 2010, Minutes from newfill to accramp: 16

17Jan Physics Store

Page 14: Possible Run 10 plan based on 25 Nov Revised Plan

26 Jan-2 Feb

Page 15: Possible Run 10 plan based on 25 Nov Revised Plan

26 Jan-2 Feb

Page 16: Possible Run 10 plan based on 25 Nov Revised Plan

26 Jan-2 Feb

Page 17: Possible Run 10 plan based on 25 Nov Revised Plan

5 June 07 17

(w/o stochactic cooling)1.02 x 109 /bunch

0.97 x 109 /bunch

Run 7 Fill 8878 Injected Beam Statistics from ELOGBlue = 103 bunches 1.04x109/bunchYellow= 103 bunches 1.13x109/bunch

Page 18: Possible Run 10 plan based on 25 Nov Revised Plan

5 June 07 18

Store 8849 (w/stochactic cooling)1.02 x 109 /bunch

0.97 x 109 /bunch

Run 7 Fill 8849 Injected Beam Statistics from ELOGBlue = 103 bunches 1.23x109/bunchYellow= 103 bunches 1.15x109/bunch

Page 19: Possible Run 10 plan based on 25 Nov Revised Plan

5 June 07 19

Run7 AuAu ZDC rates with and without stochastic cooling, with equal initial Au ions/bunch in each ring

0

5,000

10,000

15,000

20,000

25,000

30,000

0.00 0.50 1.00 1.50 2.00 2.50 3.00 3.50 4.00 4.50 5.00 5.50 6.00

Time (hours)

ZDC

(Hz)

ZDC 25 May Store 8849 w/ stochastic cooling

ZDC 30 May Store 8878 w/o stochastic cooling

Poly. (ZDC 30 May Store 8878 w/o stochasticcooling)Poly. (ZDC 25 May Store 8849 w/ stochasticcooling)

Physics ON

Loss in 3 hrs= 3.1= 3.7

Page 20: Possible Run 10 plan based on 25 Nov Revised Plan

Physics production or beam studies weekssNN (GeV) 25-cryoweek run 27-cryoweek run

200 10 1062.4 4 439 1.5 1.527 0 018 0 0

11.5 @ STAR 0 27.7 4 4

Beam studies @ 5 GeV and @ n 0.67

0.5 0.5

Revised Run 10 Plan, Nov 25, 2009

Page 21: Possible Run 10 plan based on 25 Nov Revised Plan

Run 10 Au-Au Goals11/19/09

• STAR– s = 200 GeV/n

• Luminosity Sampled/Delivered = 2/4 nb-1

• 250M Central Events• 300M Min-bias events

• PHENIX– s = 200 GeV/n

• Luminosity Recorded/Delivered = 1.4/>6 nb-1

• Minimum Goal: – Luminosity Recorded/Delivered = 1.1/3.9 nb-1

Page 22: Possible Run 10 plan based on 25 Nov Revised Plan

Run 03 Run 04 Run 05 Run 06 Run 07 Run 08 Run 09 Run 100

1

2

3

4

5

6

7

8

9

Time from start of 4.5 deg cooldown to Physics

Run 10 Actual

Goal

Actual

Wee

ks to

Phy

sics

Page 23: Possible Run 10 plan based on 25 Nov Revised Plan

Run 7

Fill 8544

Page 24: Possible Run 10 plan based on 25 Nov Revised Plan

BNL Energy Cost

$(20)

$-

$20

$40

$60

$80

$100

$120O

ct-0

0

Oct

-01

Oct

-02

Oct

-03

Oct

-04

Oct

-05

Oct

-06

Oct

-07

Oct

-08

Oct

-09

Oct

-10

$/M

Whr

Billed Cost/MWhrWithout Balanced BillingBalanced Billing ProjectionRHIC ONAGS SEB/FEBNSRL

Through 30 Nov 09

Page 25: Possible Run 10 plan based on 25 Nov Revised Plan

– Oct. 5, N2 scrubbing– Oct. 30, Temp. Control devices in and ready

(required for 45 K wave cooldown).– Nov. 2, 45 K wave begins.– Nov. 12, AGS Testing.– Nov. 12-13, APEX Workshop – Nov. 16, beam setup in Booster and AGS– Nov. 16-20, RHIC Dry Run – Nov 22, Beam extracted from AGS to W dump

Run 10 Setup

Page 26: Possible Run 10 plan based on 25 Nov Revised Plan

Wednesday midnight

Thursday midnight

Page 27: Possible Run 10 plan based on 25 Nov Revised Plan

http://www.bnl.gov/cad/esfd

AGS-Booster-Tandem/Linac Startup

RHIC Cryo Cooldown to 45 deg K

RHIC Cryo Cooldown/Warm-up

RHIC Cryo Operation

RHIC Cryo off

RHIC STAR & PHENIX

RHIC Research with s = 200 GeV /n AuAu

RHIC Research with s = 8-62 GeV /n AuAu

Beam Studies at s = 5 GeV /n AuAu

NSRL (NASA Radiobiology)

Shutdown (RHIC)

C-A Operations-FY10

Program Element Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

FY 2010

6 Jan 10

setup with beams in both rings As Run/Planned

Sep

concurrent with RHIC

ramp up luminosity

21 Sep

≥ 25 weeks

1 Dec

20 Nov

setup as required

10 weeks physics

End Date TBD

10 weeks

NSRL Schedule TBD

25 cryo weeks

25 Cryo Weeks

Page 28: Possible Run 10 plan based on 25 Nov Revised Plan