7/27/2019 Progress Photo (March 2013).pdf
1/11
Project Monthly Report (March 1 ~ March 31, 2013)
New Era University
1
PHILIPPINE ARENA
PROJECT NAME Philippine Arena
Location Aerial View
Description Site Scenery
Date March 13
Photo File Name Photo 001. jpeg
Activity Code GENERAL OVERVIEW
Monthly Progress Photograph
7/27/2019 Progress Photo (March 2013).pdf
2/11
Project Monthly Report (March 1 ~ March 31, 2013)
New Era University
2
PHILIPPINE ARENA
PROJECTNAME
PhilippineArena
Location Site / ChillerPlant
Description Installation of r
ebars at ground floor prior toschedule of pouring
Date Mar.13
Photo FileName
Photo 002.jpeg
ActivityCode
RMC
7/27/2019 Progress Photo (March 2013).pdf
3/11
Project Monthly Report (March 1 ~ March 31, 2013)
New Era University
3
PHILIPPINE ARENA
PROJECTNAME
PhilippineArena
Location Site/ chillerplant
Description Status of
chiller plantbuilding
Date Mar.13
Photo FileName
Photo 003.Jpeg
ActivityCode
RMC
7/27/2019 Progress Photo (March 2013).pdf
4/11
Project Monthly Report (March 1 ~ March 31, 2013)
New Era University
4
PHILIPPINE ARENA
PROJECTNAME
PhilippineArena
Location Site
Description Installation ofSpace frame &
tension truss
Date Mar.13
Photo FileName
Photo 004.jpeg
ActivityCode
Steel structure
7/27/2019 Progress Photo (March 2013).pdf
5/11
Project Monthly Report (March 1 ~ March 31, 2013)
New Era University
5
PHILIPPINE ARENA
PROJECTNAME
PhilippineArena
Location Site
Description Installation ofring truss at
Zone H
Date Mar.13
Photo FileName
Photo 005.jpeg
ActivityCode
Steel structure
7/27/2019 Progress Photo (March 2013).pdf
6/11
Project Monthly Report (March 1 ~ March 31, 2013)
New Era University
6
PHILIPPINE ARENA
PROJECTNAME
PhilippineArena
Location Site/Level 2
Description CHB Laying at2nd Floor toilet
walls
Date Mar.13
Photo FileName
Photo 006.Jpeg
ActivityCode
ArchitecturalWorks
7/27/2019 Progress Photo (March 2013).pdf
7/11Project Monthly Report (March 1 ~ March 31, 2013)
New Era University
7
PHILIPPINE ARENA
PROJECTNAME
PhilippineArena
Location Site/Level 2
Description Skimcoat finishing of beams
and slab soffitat level 2
Date Mar.13
Photo FileName
Photo 007.Jpeg
ActivityCode
Finishing Works
7/27/2019 Progress Photo (March 2013).pdf
8/11Project Monthly Report (March 1 ~ March 31, 2013)
New Era University
8
PHILIPPINE ARENA
PROJECTNAME
PhilippineArena
Location Site
Description Installed sak bioduct at roof
Grid Line 16-20
Date Mar.13
Photo FileName
Photo 008.jpeg
ActivityCode
Mechanical
7/27/2019 Progress Photo (March 2013).pdf
9/11Project Monthly Report (March 1 ~ March 31, 2013)
New Era University
9
PHILIPPINE ARENA
PROJECTNAME
PhilippineArena
Location Site / ChillerPlant
Description Deliveredpumps on site
Date Mar.13
Photo FileName
Photo 009.jpeg
Activity
Code
Mechanical
works
7/27/2019 Progress Photo (March 2013).pdf
10/11Project Monthly Report (March 1 ~ March 31, 2013)
New Era University
10
PHILIPPINE ARENA
PROJECTNAME
PhilippineArena
Location Site /Level 2
Description Installed Drainand Soil Pipe a
t Grid Line 1 ~9
Date Mar.13
Photo FileName
Photo 010.jpeg
Activity
Code
Mechanical
works
7/27/2019 Progress Photo (March 2013).pdf
11/11Project Monthly Report (March 1 ~ March 31, 2013)
New Era University
11
PHILIPPINE ARENA
PROJECTNAME
PhilippineArena
Location Site
Description Assembly of520 tons
crawler crane
Date Mar.13
Photo FileName
Photo 011.jpeg
ActivityCode
Steel Structure