8/13/2019 Rate Analysis -RCC
http://slidepdf.com/reader/full/rate-analysis-rcc 1/15
Rate analysis of R.C.C
MANDEEP KAUR A/1501 ADITI ZUTSHI A/1543
8/13/2019 Rate Analysis -RCC
http://slidepdf.com/reader/full/rate-analysis-rcc 2/15
ANALYSIS OF RATE OF R.C.C
A correct and reasonable rate per unit work or supply, for a particular item
following its specification and detailed survey of materials, labour, equipments
etc.as required for the unit.work and their prevailing rates may be called as ananalysis of rate.
How to fix up rate per Unit of an item-
(Unit means unit of rate viz, cost of 1 cu m brickwork. 1 cu m concrete work
etc.).
The following five sub-heads are estimated and a summation of these is therate per unit of an item.
(a) Quantity of materials and cost
(b) Labour costs
(c} Costs of equipments or Tools and Plants (T. and P.)
(d) Overhead or Establishment charges (including incidental)
(e) Profit.
8/13/2019 Rate Analysis -RCC
http://slidepdf.com/reader/full/rate-analysis-rcc 3/15
8/13/2019 Rate Analysis -RCC
http://slidepdf.com/reader/full/rate-analysis-rcc 4/15
ANALYSIS OF RATES FOR CONCRETE WORKS
1) Lime concrete in foundation with 25mm down brick chips
( jhama chips)with 1 lime and two surkhi mortar.
Prop . 1:2: 5.5
Consider first 10 cu m . unit = 1 cu m
Calculation of materials:
summation of proportion = 1+2+5.5 = 8.5
Following the procedure given in article 11-5, SI 32
Lime = 15.5/ 8.5= 1.8 cu m ,
Surki = 1.8 * 2 = 3.6 cu m ,
Brick Chips = 1.8 * 5.5 = 9.9 (say 10 cu m)
8/13/2019 Rate Analysis -RCC
http://slidepdf.com/reader/full/rate-analysis-rcc 5/15
8/13/2019 Rate Analysis -RCC
http://slidepdf.com/reader/full/rate-analysis-rcc 6/15
2) Lime concrete in foundation with 40mm down stone ballast ,lime and
sand.
Prop . 1:2: 4
Consider first 10 cu m . unit = 1 cu m
Calculation of materials:
Summation of proportion = 7
Following the procedure given in article 11-5, SI 32
Lime = 15.4/ 7
= 2.2 cu m,
Sand = 2.2* 2
= 4.4 cu m ,
Stone ballast = 2.2* 4
= 8.8 cu m
8/13/2019 Rate Analysis -RCC
http://slidepdf.com/reader/full/rate-analysis-rcc 7/15
ANALYSISPARTICULARS QUANTITY RATE AMOUNT
a) Materials -
Stone ballast(local) 8.8cu m 140.00 per cu m 1232.00
Sand (local) 4.4cu m 98.00 per cu m 431.00
Stone lime (slaked) 2.2cu m 398.00 per cu m 875.00
b) Labour- head
mason
0.5 no. 38.00 each per day 19.00
Mason 1 35.00 each per day 35.00
Mazdoor ( beldar) 20 20.00 each per day 400.00
(2 Bhishti)
Contingencies,T& P L.S 0.5% ( a+b) 14.64 L.S 14.64
c) Water charges @ 1% Total = 3007.44
= 30.07
d) profit incl.
overheads
@10% Total =
=
3037.51
303.75
Rate per cu m : Rs. 334.13 Grand Total : Rs.3341.26
8/13/2019 Rate Analysis -RCC
http://slidepdf.com/reader/full/rate-analysis-rcc 8/15
3) Cement concrete 1 : 5: 10 with graded brick ballast ( jhama chips) , 40mm down
in foundation
Calculation of materials: As given in article 11-5, SI 32
PARTICULARS QUANTITY RATE AMOUNT
a) Materials -
Brick ballast 9.8cu m 140.00 per cu m 1372.00
Sand (medium) 4.9cu m 130.00 per cu m 637.00
Cement 0.98cu m=29.4 bags 73.00 per bag 2146.20
b) Labour- head
mason
0.5 no. 38.00 each per day 9.50
Mason 2 20.00 each per day 40.00
Mazdoor ( beldar) 12 20.00 each per day 240.00
(2 Bhishti)
Mazdoor (female)
8 20.00 each per day 160.00
Contingencies,T& P L.S 0.5% ( a+b) 23.02 L.S 23.02
c) Water charges @ 1% Total = 4627.72
= 46.28
d) profit incl. overheads @10% Total =
=
4674.00
46.74
Rate per cu m : Rs. 472.07 Grand Total : Rs.4720.74
8/13/2019 Rate Analysis -RCC
http://slidepdf.com/reader/full/rate-analysis-rcc 9/15
SUPPLYING, FITTING, FIXING AND REMOVING SHUTTERING AND STAGING
Consider a room = 5m*4m with an intermediate T beam 25 cm*20cm wide web.
Height of the room = 3.5 m.
Area Of Shuttering for
a) Beam (20cm + 2* 25cm)*4m
= 2.8 sq m
b) Slab : 5m*4m- (20cm*4m)
= 19.2 sq m
Total area = 22 sq m.
8/13/2019 Rate Analysis -RCC
http://slidepdf.com/reader/full/rate-analysis-rcc 10/15
PARTICULARS NO. L B THKNESS QTY RATE AMOUNT
a) Materials- ( cu m)
1) for beam -
Side planks 2 4m 25 2.5 0.050
Side cleats @1m c/c 2*4 30cm 8 4 0.008
Bottom plank 1 4m 25 5 0.050
Base beam (at prop
only)
4 50cm 10 5 0.010
Brackets (2 nos at
prop)
2*4 50cm 5 4 0.008
2) for slab -
Planks = (5m- 20cm -2*
25cm)
1 4.75m 4 2.5 0.475
Beam @1m
c/c=0.5*4.75
2*4 2.375m 5 15 0.143
ANALYSIS
3) for beam and slab
braces -
a) Short side 7 4m 10 4 0.112
b) Long side 4 5m 10 4 0.080
Wedges under props 28 22cm 10 8 0.049
Bearing planks under
wedges
28 50cm 22 5 0.154
Total = 1.139 3250.00 3701.75
8/13/2019 Rate Analysis -RCC
http://slidepdf.com/reader/full/rate-analysis-rcc 11/15
10cm avg. dia. Bailey
props @ 1m c/c (ht. of
props under beam =
3.33m but taken as
3.45m to have a grip of
7.5cm with beams.
28 3.45m --- --- 96.6rm 500r.m 483.00
Total =
=
Rs.4184.75
418.47
Total = Rs.4503.22
Deduct the scrap value of timber @8 %
Assuming that this set of shuttering and staging becomes unserviceable after being used 12 times
(time of usage is governed by the availability of work, cutting the frame work to suit different dimensions, damage
for nailing etc.) cost for using once.
3499.13\ 12 = 375.27
8/13/2019 Rate Analysis -RCC
http://slidepdf.com/reader/full/rate-analysis-rcc 12/15
b) Labour- Quantity Rate Amount
head mason 0.5 nos 38 ea. 19.00
Carpenter 3 nos 40 120.00
Mazdoor (beldar) 6 nos 20 120.00
Carriage within town 2 times 50 100.00
Nails L.S 25 L.S 25.00
Contingencies T&P L.S 4 L.S 4.00
Total = 763.27
e) profit & overhead = 76.33
Rate per sq m. = 839.68\ 22 = Rs.38.16 Grand total = Rs.839.60
8/13/2019 Rate Analysis -RCC
http://slidepdf.com/reader/full/rate-analysis-rcc 13/15
PLAN OF SHUTTERING
4M
8/13/2019 Rate Analysis -RCC
http://slidepdf.com/reader/full/rate-analysis-rcc 14/15
NOTE:
In case span exceeds 4.5m and height exceeds 3.5m, horizontal and diagonal
braces are provided.
8/13/2019 Rate Analysis -RCC
http://slidepdf.com/reader/full/rate-analysis-rcc 15/15
Note :R.C.C works are paid separately -
a) For cement concrete work
b) For M.S reinforcement work
c) For shuttering and staging
( as per the practice of C.P.W.D and also the procedure as adopted by the
All India Standard schedule of Rates.)