n°44UJ57

23 Mar. 2005Fall from a scaffolding 1.3m

Broken collar-boneHandrail not fitted, wheels not blocked, personnel not trained

(interim)

n°45Sector 7-8

30 Mar. 2005Cutting of a power cable

No serious injuryTask description not

completed, personnel not trained, not supervised

(interim)

n°46RB 26

11 May 2005Release of toxic vapour in

UX25Painting of the guiding line of

the MAFI vehiclePainting done outside the

closed perimeter

n°47UA 83

30 May 2005A person touched the

extremity of a powered cableNon respect of lock-out tag-

out rules (consignation)Reinforcement of safety rules for electrical commissioning

n°48RR 53

2 Jun. 2005Helium release in the LHC

tunnelInjection of helium in a non

commissioned lineLine should be isolated when

not commissioned

n°49UX45

7 Jul. 2005When removing a 45kg

cryogenic safety valve it hit the head of the worker

Broken valveLack of competence of the

firm, activity not planned, no procedure

n°50UX65

22 Aug. 2005When cutting a tube the

operator got his finger caughtFinger tip cut

Machine is not conform, self certification, similar accident

happened before

n°51UX15

7 Sep. 2005Fall when climbing down a

scaffolding ladderScratch on wrist

Scaffolding not conform, no verification, difficult access,

climbing down the ladder the wrong way round

n°52US25

21 Sep. 2005 A plug of the MAFI vehicle

explodedDestruction of plug

Short circuit in the plug and non functioning of the electrical protections

n°53US25

28 Sep. 2005When installing a circuit

breaker the power came backNo damage

Lock-out tag-out procedure not respected.

n°54US45

29 Sep. 2005Strong electrical shock when

touching cable in the false floor

Electrical shockOld LEP cables not protected, not grounded. Circuit breaker

difficult to find

n°55SD18

6 Oct. 2005When pulling cable in PM18,

the cable slipped in the machine and the drum came

off its axleDoor of SD18 damaged

Inadequate machine for the work being performed

n°56Sector 4-5

22 Nov. 2005A finger got caught when

centring manually the EU on the OTU

Finger crushedProcedure not followed, the

correct tool at the work place

Other Accidents Fatal Accident in

RR13,2 fingers cut in

RE62,Fingers between

soldering machine and support,

Fingers squashed by trailer wheel,

Etc.

•45 accidents or incidents were declared in 2005, 14 were followed by an inquiry, and probably many more were not declared.

•Manual handling, falls, incidents or accident of electrical origin, etc.

•Procedures badly applied, changed at the last minute, not followed or non existing.

•Personnel involved: sub-contractors, interim or experts who are over-confident.

Recurrent Problems

•PPSPS not done, or at the last minute, generic, copy-paste, not adapted to the situation

•Works not declared, or continuing beyond what is declared or authorised

•Safety perimeters not respected

•Lack of supervision and preparation

•No smoking and personal protection

Safety coordination procedure

•PGC - contractual document

•Bidders’ conference - rules are presented

•PPSPS - 30 days before start of work with precise and full task description

•Work Package Analysis, experimental zones

•Joint inspection (VIC) - one week before start of work

Work at height

•Accident of the Queen Mary in St. Nazaire: 15 dead (Endel)

•Decree of Sept. 2004 : Scaffolding, platforms, work at height

•Structure calculations, qualification of personnel (erection, control, etc.), training, work with harness, etc.

•New European rules in 2006

Working rules for firms

•Night and Sunday work is forbidden in France and Switzerland

•Derogation only for safety reason (transport, X-rays) or continuity of work (Site guards)

•Strictly forbidden to lend personnel (CERN, company, collaboration, etc.)

Consequences of an accident at SLAC

• Electrical arc when installing a circuit breaker in an electrical cabinet.

• 2nd and 3rd degree burn of a person from a outside sub-contractor.

• Stop of all activities during a month and all accelerators for 6 months.

MANQUEMENT

MANQUEMENT DELIBERE

NEGLIGENCE

INATTENTION

IMPRUDENCE

MALADRESSE

Gravity

Sentence

Gravity of faults

Gravity of faultsLE DELIT DE MISE EN DANGER DE

LA PERSONNEExpose directly somebody to an

immediate risk of death or wound which could be invalidating or

mutilating.Example 1: work at height without collective or individual protection.

Example 2: work on a machine or process without protection.

Example 3: use of dangerous substances without adequate protection

Example 4: use of a faulty device

Line of responsibility

The line of responsibility IS the hierarchical line

Director General

Department Leader

Group Leader

Project Engineer

•Note that the Safety Commission, DSO, TSO, etc. are not in the line

Integration of safety

•Schedule, Quality, Safety

•Optimisation of the installation and maintenance at the design level

•Take into account the work environment

•Work not well prepared or difficult = loss of time, quality and risk of an accident.

•ISO 9000, ISO 14000, OSHAS 18000

Reinforced Safety Coordination Team

•3 safety coordinators (Jean Weber, John Etheridge, Emmanuel Paulat)

•3 more since Jan. 2006 (Hervé Buret, Patrick Thévenon, X)

•1 more Safety Engineer starting Mar. 2006(Stefano Fratianni)

Conclusion

•An accident may have catastrophic consequences on the whole project

•The level of safety revels the respect of the schedule, of quality and of the environment

•Everybody shall be involved

•Compression of the planning must be done without compromise on safety

No project is worth the life of somebody