OTIS ACD2 MRL
Field Installation Manual
3.2 Check of Run -Direction
ERO
UP
OTIS ACD2 MRL
Field Installation Manual
3.3 Manual Brake Release check See Reference about SPBC and details of MRO.
BRB2 Press BRB1
BRB2 Key-
switched
Press BRB1
BRB2 BRB1 not pressed
/
/
OTIS ACD2 MRL
Field Installation Manual
4 PREPARE FIRST NORMAL RUN Attention: The elevator must be fully completed (wiring and mechanical assembly) before going beyond this point.
4.1 Position DSBD (connect 4T with 5T)
OTIS ACD2 MRL
Field Installation Manual
Unpublished Work Copyright © OTIS Elevator Company
4.2 Check of Hoistway Signals (PRS with RLEV/ADO)
Start
ERO
ACD2 MRL
Field Installation Manual
4.3 Check of Hoistway Signals (PRS without RLEV/ADO)
ERO
Start
OTIS ACD2 MRL
Field Installation Manual
4.4 Start up of the door system
4.4.1 NGSOK startup:
Reference: KAA31328AAA_SUR NGSOK Start up routine
OTIS ACD2 MRL
Field Installation Manual
4.4.2 Start up of DCSS5E
To startup the DCSS5 Operator please refer to the corresponding Field Installation Manual in Appendix.
4.5 Learn run
OTIS ACD2 MRL
Field Installation Manual
Press CHCS
Press DDO
NORM
ERO
NORM
Press “1” for calibration Press “0” for maintain
OTIS ACD2 MRL
Field Installation Manual