Physical Design Challenges in the Chip Power Distribution Network

Farid N. Najm Professor & Chair

ECE Dept, University of Toronto f.najm@utoronto.ca

Outline

■  Introduction ●  Power grid topology ●  Physical design challenges

■  Power grid verification ●  EDA: simulation, vectorless verification ●  Engineering solution: over-design, and over-kill

■  Constraints-based verification ●  Voltage variations ●  Electromigration

■  Constraints generation ■  Conclusion

F. N. Najm Challenges in Power Grid 2

Power Grid Topology

■  ~ a Billion nodes ■  ~ 2,000 C4 pads

●  1,000 Vdd, 1,000 Vss

■  All levels of metal stack

■  Hundreds of millions of instances of logic cells

F. N. Najm Challenges in Power Grid 3

RLC RLC RLC

RC Layer

RC Layer

RC Layer

Vdd

Pads

Circuit current sources

Pkg, PCB

Power Grid Topology

■  Package, motherboard, and VRM model; inductance!

F. N. Najm Challenges in Power Grid 4

Power-Managed Chip Grid

■  Gated supplies

■  Voltage islands

■  Active devices!

F. N. Najm Challenges in Power Grid 5

RLC RLC RLC

M7 (RC Layer)

M6 (RC Layer)

M1 (RC Layer)

Vdd

Pads

Circuit current sources

Pkg, PCB

M5 (RC Layer)

M4 (RC Layer)M4

M3 (RC Layer)M3

M2 (RC Layer)M2

M1

Gate FET

M1 (RC Layer)

Circuit current sources

M4 (RC Layer)M4

M3 (RC Layer)M3

M2 (RC Layer)M2

M1

Gate FET

RLC RLC RLC

Vdd

Pads

Pkg, PCB

Glo

bal (

un-g

ated

) Grid

Loca

l (ga

ted)

Grid

Mesh Layer Structure

■  In every layer, the grid is mostly a regular mesh.

F. N. Najm Challenges in Power Grid 6

Metal 3

Metal 4

Vdd

Vdd

Vdd

Gnd

Gnd

Gnd

■  Note: ●  Many variations on this central theme ●  Top layer C4 pads typically on a ~200µm grid ●  Local non-uniformities make room for signal routing

Physical Design

■  With hundreds of millions of instances on die and clocks running at GHz rates, the total power is high ●  High performance SOCs might consume over 150 Watts ●  Very hard to keep supply regulated under such conditions

■  Physical design of the grid can have big impact: ●  Voltage variations in bottom layers impact circuit timing ●  Voltage overshoot (inductive kick) impact I/O signal noise ●  Electromigration damage can be catastrophic throughout

■  Nightmare: ensure circuit is safe from all this while distributing over 150 Amps to >400 million instances

F. N. Najm Challenges in Power Grid 7

Power Grid Verification

F. N. Najm Challenges in Power Grid 8

Power Grid Verification

■  Verification is needed to check the grid design: ●  Early high-level grid verification and planning ●  Incremental verification during redesign cycles ●  Detailed grid verification at sign-off time

■  Key problem: ●  The circuit currents are unknown or highly uncertain!

■  Need reliable verification in the face of uncertainty.

F. N. Najm Challenges in Power Grid 9

Existing Commercial Solutions

■  Simulation ●  Decouple grid from underlying circuit ●  Simulate the grid for given current source stimulus ●  Expensive and incomplete; inconclusive

■  Existing solutions for vectorless verification ●  Voltage variations: timing windows, random scenarios ●  Electromigration: Black’s model, current density check ●  Questionable results

■  Engineering solution: over-design, but also over-kill ■  Problem: running out of metal area for signal routing!

F. N. Najm Challenges in Power Grid 10

Constraints-Based Verification

F. N. Najm Challenges in Power Grid 11

Constraints-Based Verification

■  Given: ●  Power Grid (DC, RC, or RLC netlist) ●  Tolerance for grid node voltage fluctuations (Vth) ●  Tolerance for grid branch current densities (EM) ●  Peak budgets (current constraints) for block currents

■  Find: ●  Worst-case voltage variations for every grid node ●  Worst-case current variations in every grid branch

■  Features: ●  Based on user-provided current constraints (budgets) ●  Search/optimization (LP) approach for verification ●  Allows vectorless early high-level power grid verification

F. N. Najm Challenges in Power Grid 12

Current Constraints - Example

■  Local Constraints

■  Global Constraints

F. N. Najm Challenges in Power Grid 13

1 2

4 5

3

6

9 7 8

+ -

I3

I5

I2

I7 I9

Vdd

Global Constraint 1

Global Constraint 2

Voltage Drop: The RC Case

■  Define as the vector of worst-case voltage drops, at all nodes, over all transient currents in space

■  Define: shorthand notation for element-wise max:

■  Use upper-bound:

F. N. Najm Challenges in Power Grid 14

emax

i2F[v(i)] =

2

666664

max

i2F[v1(i)]

max

i2F[v2(i)]

.

.

.

max

i2F[vn(i)]

3

777775

Performance

F. N. Najm Challenges in Power Grid 15

Voltage Drop/Rise: The RLC Case

F. N. Najm Challenges in Power Grid 16

Electromigration: The Mesh Model

■  Traditional EM model is “series” ●  But power grid has

much redundancy

■  Vector-based mesh model approach ●  3-4X lifetime! ●  Can be 30-40X

■  Vectorless Mesh model approach

F. N. Najm Challenges in Power Grid 17

Chatterjee 2013, Fawaz 2013

Progress Towards Failure

F. N. Najm Challenges in Power Grid 18

Progress towards failure

F. N. Najm Challenges in Power Grid 19

Series  

Progress towards failure

F. N. Najm Challenges in Power Grid 20

Series  

Progress towards failure

F. N. Najm Challenges in Power Grid 21

Series  

Progress towards failure

F. N. Najm Challenges in Power Grid 22

Series  

Failure when v(t) > vth

F. N. Najm Challenges in Power Grid 23

Series   Mesh  

Results: MTF Comparisons

F. N. Najm Challenges in Power Grid 24

■  MTF estimation for the largest grid, with 1M nodes required 97 Monte Carlo iterations and 13.5 hrs.

But … there is a Problem

■  Ongoing development: ●  Electromigration verification

◆  Physical models to further reduce pessimism ●  Fast hierarchical/modular verification

◆  Boundary conditions to ensure sub-grid safety

■  But there is a fundamental issue with usability of the constraints-based approach:

F. N. Najm Challenges in Power Grid 25

The constraints are hard to specify

Constraints Generation

F. N. Najm Challenges in Power Grid 26

Alternative Approach

■  Constraints Generation (the “inverse” problem): ●  Generate circuit current constraints which, if satisfied by the

underlying circuitry, would guarantee grid safety

■  Applications: ●  Encapsulate much useful information about the grid,

captured in useful quality metrics (peak power, other) ●  Provides power budgets to drive design process, allowing

rebudgeting, or early hints for grid redesign or new floorplan ●  During low level physical design, allow local checks for block

compliance with grid safety constraints w/o grid simulation ●  Local checks in safety “islands” may be enough

F. N. Najm Challenges in Power Grid 27

Voltage Islands (RC case)

■  Typically, we find the constraints decoupled into “islands”

■  Checking of the local regions, independently

■  Parallel flow for verification

F. N. Najm Challenges in Power Grid 28

Container

■  Definition:

F. N. Najm Challenges in Power Grid 29

Safe Container

■  Rewriting the upper-bound on the exact worst-case voltage drop:

where and

■  We want to generate such that , from which and the grid is safe!

■  Definition: A container is said to be safe if:

F. N. Najm Challenges in Power Grid 30

All Safe Containers

■  Let and define the two sets:

■  Lemma: is safe for any , and: ●  All possible safe containers may be found as either specific

instances of , or as subsets of such instances.

F. N. Najm Challenges in Power Grid 31

Vth

Maximal Container

■  It’s enough to look at the set of all safe containers:

■  Define a safe container to be maximal if it’s not a subset of any other safe container.

F. N. Najm Challenges in Power Grid 32

■  We are interested in maximal containers!

All Maximal Containers

■  Theorem:

F. N. Najm Challenges in Power Grid 33

Maximal

Irreducible

Safe

Vth

Desirable Maximal Containers

■  The space of maximal safe containers represents a quality assessment for a power grid ●  What levels of current will this grid safely distribute?

■  Example: suppose the chip is expected to draw a peak power of 150W at 1V supply ●  A grid may be deemed unacceptable if no safe container for it

can be found that allows a peak total supply current of 150A

■  Design objectives must drive the choice of container!

F. N. Najm Challenges in Power Grid 34

Container Generation Algorithms

■  Peak Power Problem (P1): ●  Generate a container that

allows the largest possible peak power dissipation (instantaneous, total)

■  Uniform Current Problem (P2): ●  Generate a container that does

not severely limit the allowed supply current anywhere on the die

F. N. Najm Challenges in Power Grid 35

Algorithms

■  P1: peak power ●  One LP

■  P2: uniform budgets ●  One LP

F. N. Najm Challenges in Power Grid 36

■  We can prove that both resulting are maximal!

Performance (P1)

F. N. Najm Challenges in Power Grid 37

(Based on 65nm technology parameters and 1.1 Volt supply)

Grid   Nodes   Sources  CPU  Time   Peak  Power  

(mW)  M'   LP  G1   8K   500   2  sec   0.4  sec   1.7  G2   19K   1K   7  sec   1  sec   3.7  G3   33K   2K   17  sec   2  sec   6.8  G4   50K   3K   37  sec   5  sec   10  G5   113K   7K   3  min   10  sec   22  G6   201K   13K   9  min   28  sec   41  G7   312K   19K   22  min   57  sec   60  G8   449K   28K   44  min   2  min   85  G9   1M   63K   3.6  hr   9  min   198  

Power Density (P1)

F. N. Najm Challenges in Power Grid 38

0 25 50 75 100 125Number of Windows

0

0.5

1

1.5

2

2.5

3

3.5

4

4.5

µ = 1.73 mA/cm2

σ = 0.8 mA/cm2

(G4)

Performance (P2)

F. N. Najm Challenges in Power Grid 39

Grid   Nodes   Sources  CPU  Time  

Radius  (uA)  M'   LP  

G1   8K   500   2  sec   0.7  sec   1.8  G2   19K   1K   7  sec   2  sec   2.1  G3   33K   2K   17  sec   3  sec   1.5  G4   50K   3K   37  sec   6  sec   1.8  G5   113K   7K   3  min   20  sec   1.4  G6   201K   13K   9  min   40  sec   2.1  G7   312K   19K   22  min   1  min   2.0  G8   449K   28K   44  min   2  min   1.6  G9   1M   63K   3.6  hr   5  min   1.9  

Power Density (P2)

F. N. Najm Challenges in Power Grid 40

0 25 50 75 100 125Number of Windows

0

0.5

1

1.5

2

2.5

3

3.5

4

4.5

µ = 1.3 mA/cm2

σ = 0.2 mA/cm2

(G4)

Combined Objective (P3)

■  A combined objective gives the best of both worlds:

■  We can prove that the resulting is maximal! F. N. Najm Challenges in Power Grid 41

0 5 10 15I1 (mA)

0

5

10

15

I 2(m

A)

Performance (P3)

F. N. Najm Challenges in Power Grid 42

Grid   Nodes   Sources  CPU  Time  

Peak  Power  (mW)  Radius  (uA)  M'   LP  G1   8K   500   2  sec   2  sec   1.7   1.7  G2   19K   1K   7  sec   8  sec   3.4   2.0  G3   33K   2K   17  sec   17  sec   6.4   1.4  G4   50K   3K   37  sec   29  sec   5.6   1.8  G5   113K   7K   3  min   2  min   22   1.4  G6   201K   13K   9  min   5  min   37   2.0  G7   312K   19K   22  min   8  min   55   2.0  G8   449K   28K   44  min   15  min   84   1.6  G9   1M   63K   3.6  hr   56  min   184   1.9  

Power Density (P3)

F. N. Najm Challenges in Power Grid 43

0 25 50 75 100 125Number of Windows

0

0.5

1

1.5

2

2.5

3

3.5

4

4.5

µ = 1.56 mA/cm2

σ = 0.46 mA/cm2

(G4)

Conclusion

■  Physical design challenges in the power grid relate to impact on voltage drop/rise and electromigration ●  Predicting these effects is hard, due to stimulus uncertainty ●  Given budgets (constraints), there are ways to overcome the

uncertainty, but still expensive and under development ■  Constraints generation is possible and practical, and

is a rich area of study, previously unexplored ●  Quality metrics for the power grid provide a rigorous

approach for early grid design/planning ●  Voltage drop-aware placement and routing?

■  Future work: ●  Automatic safe grid generation, along with constraints?

F. N. Najm Challenges in Power Grid 44