+ All Categories
Home > Documents > 10 Reasons of Collapse

10 Reasons of Collapse

Date post: 03-Jun-2018
Category:
Upload: adnan-ahmed
View: 221 times
Download: 0 times
Share this document with a friend

of 23

Transcript
  • 8/12/2019 10 Reasons of Collapse

    1/23

    10 Reasons of Collapse

    of

    Feature WallAt Anushriya Villa, Noida Sector 128

  • 8/12/2019 10 Reasons of Collapse

    2/23

    COVER NOTE

    Structural Failures occur due to a combination of reasons.

    Structures are anyways designed with factors of safety, by all structural consultants,

    So, a failure of this type, is due to many factors, which work in tandem.

    Our team visited site the same day (May 16) when the client informed us of the wall

    Failure. What the team found was that the structural failure was cased due to lack of

    Basic structural norms being followed, despite intimations on several past occasions.

    The details hereunder have been put together methodically to explain and pinpoint the

    Cause of the failure on faulty workmanship and lack of procedural norms in civil const-

    Ruction.

    The following slides are easy to understand and can establish without any doubt that

    The civil contractor and supervisor need to be pulled up.

  • 8/12/2019 10 Reasons of Collapse

    3/23

    Drawing Title: Feature Wall Column and Beam DetailDate of Issue: 10thSep. 2012

    This is the Structural Drawing showing details of Structural members for the said wall.

  • 8/12/2019 10 Reasons of Collapse

    4/23

    This is the Architectural Drawings for the said wall showing all structural members in elevation.

  • 8/12/2019 10 Reasons of Collapse

    5/23

    Proposed Foundation Design

    of the Feature wall, which is

    showing it starting from1metre below the Natural

    Good earth Level.

    The executed foundation to

    be re-excavated & checked /

    verified for adherence to this

    drawing.

    There are serious doubts of

    unsettlement in this

    foundation, due to

    foundations not being on

    compacted earth, as per

    norms. Also the grade of

    concrete used therein, may

    need to be examined at a lab

    to see if it matches norms.

    1. The FOOTINGS

  • 8/12/2019 10 Reasons of Collapse

    6/23

    ON SITE STATUS

    Photograph taken on 31st

    Aug. 2012.

    Earth Filling where the

    Feature wall to come is

    half done without proper

    Compression of soil.

    Good Earth is far below

    this filling, from where

    the foundation wasproposed.

    This leads to the doubt in

    Slide 1.

  • 8/12/2019 10 Reasons of Collapse

    7/23

    Proposed Column detail

    and Elevation with all the

    structural members &

    levels marked, can be

    seen.

    Please note there are 4

    columns proposed and

    several tie beams

    between columns and to

    the 90 Degree adjacent

    wall.

    Drawing Title:

    Feature Wall Column & Beam Layout

    Date of Issue: 10thSep. 2012

    2. Number of

    Columns & Tie Beams

  • 8/12/2019 10 Reasons of Collapse

    8/23

    Photograph taken on 15th

    May. 2013.

    a. Shocking to note even

    plaster is intact and no tie

    up, even in brick work, is

    visible; also no bar

    connectivity with existing

    columns is visible.

    b. Site showed ONLY THREE,

    instead of FOUR Columns

    proposed.

    c. One of these 3 Visible

    Columns was wrongly

    erected from above the

    Plinth beam, WITHOUT

    necessary foundation.

    ON SITE STATUS

  • 8/12/2019 10 Reasons of Collapse

    9/23

    Photograph taken on 15thMay.

    2013

    a. Plinth Beam not connected

    with Existing Column

    b. Plinth beam level is not as

    per drawing . Top of plinth

    beam and internal road levelshould match as per drawing.

    WITHOUT THESE THE WALL

    WOULD ALWAYS SHEAR AWAY

    & FALL.

    3. No PLINTH BEAM

    with Adjacent wall

  • 8/12/2019 10 Reasons of Collapse

    10/23

    Photograph taken on 15th

    May. 2013

    1. Plinth beam

    terminates here. Not

    connected with

    Existing Column

    2. The weight seems to

    be on a brick

    foundation that was

    hastily made; but as

    mentioned earlier,excavation would

    need to be done, to

    know the exact

    picture.

  • 8/12/2019 10 Reasons of Collapse

    11/23

    Photograph taken on 15th

    May. 2013

    All overlaps of steel rods

    in column placed at same

    place, contrary to the

    norms that overlapping

    should be at different

    places for proper

    strength.

    This explains how thecolumns have separated

    so easily, as encircled and

    shown here.

    4. Reinforcement

    against Structural

    Norms

  • 8/12/2019 10 Reasons of Collapse

    12/23

    Photograph taken on 15th

    May. 2013

    Forget Rod Lapping not

    done here. .. The fact is

    that there is NO

    CONNECTION at all.

    With an inexplicable gap

    of 6 atleast between the

    two rods!

    This is not at allacceptable and is a

    serious breach of

    established norms.

  • 8/12/2019 10 Reasons of Collapse

    13/23

    Photograph taken on 15th

    May. 2013

    Ring distance and

    overlapping are uneven

    and deviated from

    drawings. 150mm c/c

    In some cases, it is

    200mm and in some

    more Proper chiselling

    of concrete will show theexact spacing.

    These appear to be

    methods of saving cost

    and steel, at the cost of

    structure.

    5. Ring Distance not

    as per norms

  • 8/12/2019 10 Reasons of Collapse

    14/23

    Photograph taken on 15th

    May. 2013

    Ring Distance and Main

    Vertical rods distance not

    as per drawings.

  • 8/12/2019 10 Reasons of Collapse

    15/23

    Photograph taken on 15th

    May. 2013

    Steel development length

    where column meet

    beam not provided as per

    norms.

    This results in weakness

    at joints and ease of

    shearing off, resulting in

    structural failure.

    6. No Steel

    development

  • 8/12/2019 10 Reasons of Collapse

    16/23

    Photograph taken on 15th

    May. 2013

    Middle Beam, on

    Adjacent wall, was not

    connected properly with

    the Existing Column.

    Picture shows that

    middle beam was merely

    touching the Adjacent

    wall. No hooking or

    welding of steel

    reinforcement at all

    noticed; maybe wire or

    even that was not used.

    7. Middle beam not tied up.

  • 8/12/2019 10 Reasons of Collapse

    17/23

    Photograph taken on 15thMay. 2013

    Top Beam was not

    connected properly with

    the Existing Column and

    Beam.

    Picture shows that no rod

    extension provided and

    lapped with the adjacent

    wall.

    8. Top beam not tied up

  • 8/12/2019 10 Reasons of Collapse

    18/23

    This is the Column detail

    as per drawing issued.

    Please Note: This tie rod

    is missing in Column

    reinforcement, in some

    places.

    Drawing Title: Feature Wall Column and Beam Detail

    Date of Issue: 10thSep. 2012

    9. The Tie rod Missing

  • 8/12/2019 10 Reasons of Collapse

    19/23

    Photograph taken on 15th

    May. 2013

    Apart from structural RCC

    issues, the contained infill

    brickwork is also not

    acceptable.

    Material cement : sand ratiois not at all proper, as visible.

    Curing not done at all,

    apparently, as all bricks

    appear to have separated

    from each other very simply.

    Also, note that the Concrete

    quality is very poor. Lab

    analysis of this may be done

    to analyse crushing strength.

    10. No Curing

  • 8/12/2019 10 Reasons of Collapse

    20/23

  • 8/12/2019 10 Reasons of Collapse

    21/23

  • 8/12/2019 10 Reasons of Collapse

    22/23

  • 8/12/2019 10 Reasons of Collapse

    23/23

    Contractors will always want to cut corners and find ways of saving money.

    Apart from this, all the evidence shows that there was:

    1. Lack of Supervision at Site During execution.

    (It Has been always suggested & advised, by us often, to appoint dedicated Project

    Managers / Supervisors)

    2. Poor workmanship and lack of acceptable level of expertise in Construction

    (An on site engineer would have ensured the basics of construction are enforced)

    3. No attention was paid to Curing of the Structure during and after the construction.

    (Attachment and sense of ownership to project may be lacking due to constant

    useage of different teams and labour contractors)

    4. Cost Constraints given to Contractors, as informed by contractors, on site.

    (This results in compromise in cement sand mixes, steel, curing and several other

    malpractices)

    5. Non adherence to and / or Comprehension of the Drawings, provided.

    The End Note


Recommended