+ All Categories
Home > Documents > 500 Mw Familiarisation

500 Mw Familiarisation

Date post: 09-Oct-2015
Category:
Upload: david-randall
View: 239 times
Download: 42 times
Share this document with a friend
Description:
gf
Popular Tags:

of 338

Transcript
  • IG/

    For restricted Circulation Only

    500 MW FAMILIARISATION

    Power Management Institute Noida

  • CONTENTS

    S. No. Subject Page No.

    1. Salient Features of Boiler 1

    2. Boiler Pressure Parts 8

    3. Once through Boiler 25

    4. Fuel Firing System 35

    5. Air/Draught System 60

    6. Furnace Safeguard and Supervisory System 80

    7. Soot Blowing System 99

    8. Data Sheet of 500 MW Boiler and Auxiliaries. 106

    9. Salient Features and Constructional details of KWU Steam

    Turbine. 113

    10. Turbine Oil System 127

    11. Turbine Control Fluid System 135

    12. Constructional Features of Turbine Governing System and

    H.P./ L.P. Bypass System 143

    13. Turbine Tripping Devices and Turbine Metal Temp. limit

    Curves 158

  • S. No. Subject Page No.

    14. Automatic Turbine RUN UP System-(ATRS) 164

    15. Data Acquisitions System (DAS) 177

    16. Feed Regenerative System 193

    17. Boiler Feed Pump and Condensate Pump 200

    18. Data-Sheet of 500 MW Turbine and its Auxiliaries Turbine

    Metal Temp. Limit curves. 217

    19. Design and Constructional Feature of 176 500 MW Generator 227

    20. Excitation System and Auto Voltage Regulator 247

    21. Protections of Generator 268

    22. Generator Auxiliaries 273

    23. Data Sheet of Generator 284

    24. Unit Start up and Shut-Down Procedures 285

    25. Major Differences between 210 MW and 500 MW Units 332

  • PMI, NTPC 1

    1. Salient Features Of Boiler

    BOILER UNITS

    The boiler is a radiant reheat, controlled, circulation. Single drum, dry-bottom type unit.

    The general arrangement of boiler and its auxiliaries is shown in the Figure no 1. The

    boiler units are designed for the following terminal conditions (MCR):

    Evaporation a) SH Outlet : 1.725 t/hr

    b) RH Outlet : 1.530 t/hr

    Working Pressure after stop valve : 178 kg/cm (g)

    Steam Temperature at SH

    Outlet : 540oC

    Steam Temperature at RH inlet : 344.1o C

    Steam Temperature at RH Outlet : 540o C

    Steam pressure at RH inlet : 42.85 kg/cm (g)

    Steam Pressure at RH Outlet : 43.46 kg/cm (g)

    Feed water Temperature at ECO : 256o C

    Furnace Design Pressure : + 660 mmwc (g)

    The boilers are of single furnace design, circulating pumps to provide assisted

    circulation.

  • PMI, NTPC 2

  • PMI, NTPC 3

    Each boiler corner is fitted with tilting tangential burner boxes comprising four high

    energy arc igniters, four light-up heavy oil fired burners and eight pulverised coal

    burners. The angle of tilt from the horizontal is about-30 to +30.

    Feed water to the boiler passes through HP feed heaters into the economiser and then

    to the steam drum from where it flows into the suction manifold and furnace wall circuits

    via the three boiler circulating pumps, returning to the steam drum as a water/steam

    mixture. This mixture is separated in three stages, the first two stages are incorporated

    into the turbo separators and the final stage takes place at the top of the drum just

    before the steam enters the connecting tubes comprising of first stage superheating,

    Within the steam circuit there are a further four stages of (superheating, making five in

    total. There are also three stages of reheat.

    Superheater temperature control is provided by spray attemperation situated in the

    connecting link between the superheater low temp. pendant outlet header and the

    superheater division panel inlet headers.

    Reheat temperature control is provided by titling burners or spray attemperators

    installed prior to the first stage reheater.

    PULVERISED COAL SYSTEM

    The system for direct firing of pulverised coal utilises bowl mills to pulverise the coal and

    a tilling tangential firing system to admit the pulverised coal together with the air

    required for combustion (secondary air) to the furnace.

    AS crushed coal is fed to each pulveriser by its feeder, primary air is supplied from the

    primary air fans which dries the coal as it is being pulverised and transports the

    pulverised coal through the coal piping system to the coal nozzles in the wind box

    assemblies.

  • PMI, NTPC 4

    The pulverised coal and air discharged from the nozzles is directed towards the center

    of the furnace to form firing circle.

    Fully preheated secondary air for combustion enters the furnace around the pulverised

    coal nozzles and through the auxiliary air compartments directly adjacent to the coal

    nozzle compartments. The pulverised coal and air streams entering the furnace are

    initially ignited by suitable ignition source at the nozzle exit. Above a predictable

    minimum loading condition the ignition becomes self sustaining. Combustion is

    completed as the gases spiral up in the furnace.

    PRIMARY AIR SYSTEM

    The primary air (P.A.) draught plant supplies hot air to the coal mills to dry and convey

    pulverised coal to the burners. Cold air ducts, however, are included in the system to

    regulate mill temperatures and seat mill components against any ingress of coal dust.

    The P.A. system comprises two P.A. fans, two Steam Coil Air Preheater (SCAPH) and

    two regenerative type primary air preheaters. Each fan, which is of sufficient rating to

    support 60% MCR load, discharges through a SCAPH into a common bus duct that has

    four outlets, two directing air into the primary air preheater for heating, two direct cold air

    straight to the pulverising mills. On the other side of the primary air preheaters, the

    outlet ducts combine to form a hot air crossover duct which outlets to the mills at the

    L.H.S. and R.H.S. of the boiler furnace, This arrangement of bus duct and cross over

    duct ensures continued plant operation even if one fan and/or one primary air preheater

    is out of service. The SCAPHs located in the fan discharge ducts, ensure that the

    primary air preheaters combined cold end temperature (gas leaving temperature plus air

    entering temperature) does not fall below the specified minimum to avoid "Cold End

    Corrosion'.

    Seal air fans boost up the primary air pressure and are provided for supplying sealing

    air to each mill to maintain sufficient differential between primary air and seal air thereby

  • PMI, NTPC 5

    safeguarding the lub oil from being contaminated by coal dust.

    SECONDARY AIR SYSTEM

    The secondary air draught plant supplies the balance of air required for pulverised coal

    combustion, air for fuel oil combustion, and overfire air to minimise the production of

    nitrous oxides(NOx).

    The Secondary air system comprises two forced draft (F.D.) fans, two steam coil air

    preheaters (SCAPH) and two regenerative type secondary air preheaters. Each fan.

    which is of sufficient rating to support 60% boiler MCR load, discharges through a

    SCAPH into a common bus duct that has two outlets each directing air through a

    secondary air preheater. Hot air from secondary air preheaters is sent to wind boxes at

    each side of the boiler furnace for proper combustion as secondary and overfire air.

    Overfire air can be admitted to the furnace through the upper levels of furnace wind

    boxe nozzles to assist in reducing the amount of NOx formed in the furnace. Control of

    unit air flow is obtained by positioning the FD fans blades while the distribution of

    secondary air from wind box compartment to furnace is controlled by secondary air

    dampers.

    The SCAPHs are located in the FD fan discharge ducts to ensure that the secondary

    airpreheaters combined cold end temperature (gas leaving temperatures plus air

    entering temperature) does not fall below the specified minimum to protect against cold

    end corrosion.

    FLUE GAS HANDLING SYSTEM

    The flue gas handling plant draws hot flue gases from the furnace and discharges them

    to atmosphere through the chimney. During its passage to the chimney, flue gas is

    passed through a feed water economiser and four regenerative airpreheaters to

  • PMI, NTPC 6

    improve boiler efficiency, and through four electrostatic precipitators to keep dust

    emission from chimney within prescribed limits.

    Flue gases travel upward in the furnace and downward through the rear gas pass to the

    boiler outlet (boiler rear gas pass below the economiser). It then passes through the

    primary and secondary air preheaters, the electrostatic precipitators and induced

    draught (I.D.) fans to the chimney. Since primary and secondary streams are provided

    with separate bisector regenerative air heaters, control dampers at the outlet of the air

    preheaters are provided to regulate the gas flow through these streams to get same gas

    outlet temperature.

    Three I.D. Fans, each of which is of sufficient rating to support 60% boiler MCR load,

    are served by a common inlet bus duct to ensure that plant operation continues even

    when two fans are out of service. During normal usage, two ID fans will be operational

    and one available as standby.

    SOOT BLOWING SYSTEM

    On load, gas side cleaning of boiler tubes and regenerative air heaters is achieved

    using 126 electronically controlled soot blowers which are disposed around the plant as

    follows.

    88 - Furnace Wall Blower - Steam

    34 - Long Retractable Soot Blower - Steam

    4 - Air heater Soot Blowers for - Steam

    Primary and Secondary Air

    heaters

    The boiler water wall panels are provided with suitable wall boxes for future

    accommodation of an extra sixteen furnace wall blowers and twenty-four long-

    retractable soot blowers for upper furnace, arch and rear pass zone, if necessary.

  • PMI, NTPC 7

    Steam for soot blowing is taken from division panels superheater outlet header. Steam

    is then passed through a pressure control valves where the steam pressure is reduced

    to the required limit of soot blowing. However, to soot blow the regenerative air

    preheaters during boiler start up, a separate connection is also provided from the

    auxiliary Steam System.

    FURNACE SAFEGUARD SUPERVISORY SYSTEM

    The Furnace Safeguard Supervisory System (F.S.S.S) is a major component of station

    safety monitoring equipment. It permits the remote (Control Equipment Room) and

    partly local (adjacent to the boiler) light-up and shut down of all oil burners and igniters

    together with continuous monitoring, fault detection and associated shut down of any or

    all burners upon fault disclosure.

    The system also incorporates the logic sequences required for enforcing proper purging

    of the steam generator and for tripping the master fuel relay system.

    The pulverised coal burners and their associated mills are controlled by a separate mill

    control sequencing system which is provided with essential information regarding milling

    plant status from loc. instrumentation as well as start and run permissives for each mill

    system from the F.S.S.S.

    Both systems integrate with the Analogue Control System (A.C.S.) to provide full on-line

    firing safety, optimum operational control and in-depth system awareness.

  • PMI, NTPC 8

    2. Boiler Pressure Parts INTRODUCTION

    The boiler units are of the balanced draught single drum radiant furnace type that

    include an arch between the furnace and the rear gas pass. The water circuit is of

    controlled circulation design incorporating boiler circulating pumps in unheated down

    comers at the front of the boiler and utilising refill bore tubing in sections of the furnace

    wall panels. Boiler units of 500 MW units are identical in design and comprise a single

    furnace, three superheater stages, three reheater stages and a feed water economiser,

    BARE TUBE ECONOMISER

    The Function of the economiser is to preheat the boiler feed water before it is

    introduced into the Steam drum by recovering some of the heat of the flue gas leaving

    the boiler.

    The economiser is located in the boiler back pass. It is composed of two banks of 156

    parallel tube elements arranged in horizontal rows in such a manner that each row is in

    line with the row above and below. All tube circuits originate from the inlet header and

    terminate at outlet headers which are connected with the economiser outlet headers

    through three rows of hanger tubes.

    Feed water is supplied to the economiser inlet head via feed stop and check valves.

    The feed water flow is upward through the economiser, that is, counter flow to the hot

    flue gases. Most efficient heat transfer is, thereby, accomplished, while the possibility of

    steam generation within the economiser is minimised by the upward water flow. From

    the outlet header the feed water is lead to the steam drum through the economiser

    outlet links.

  • PMI, NTPC 9

    The economiser recirculalting line, which connects the economiser inlet header with the

    furnace lower rear drum, provide a means-of ensuring a water flow through the

    economiser during startups. This helps prevent steaming. The valves in these lines

    must be open during unit startup until continuous feed water flow is established.

    WATER COOLED FURNACE Welded Wall Construction

    The furnace walls are composed of tubes. The space between the tubes are fusion

    welded to form a complete gas tight seal. Some of the tube ends are swaged to a

    smaller diameter while other tubes are bifurcated where they are welded to the outlet

    headers and lower drum nipples.

    The furnace arch is composed of fusion welded tubes.

    The back pass walls and roof are composed of, fin welded tubes.

    The furnace extended side walls are composed of fin welded tubes.

    The back pass front (furnace) roof is composed of tubes peg fin welded.

    All peg finned tubes are normally backed with a plastic refractory and skin casing which

    is seal welded to form a gas tight envelope.

    Where tubes are spread out to permit passage of superheater elements, hanger tubes,

    observation ports, soot blowers, etc., the spaces between the tubes and openings are

    closed with fin material so a completely metallic surface is exposed to the hot furnace

    gases.

  • PMI, NTPC 10

    Poured insulation is used at each horizontal buckstay to form a continuous band around

    the furnace thereby preventing flue action of gases between the casing and water walls.

    Bottom Construction

    Bottom designs used in these coal fired units are of the open hopper type, often

    referred to as the dry bottom type. In this type of bottom construction two furnace water

    walls, the front and rear walls, slope down toward the centre of the furnace to form the

    inclined sides of the bottom. Ash and/or slag from the furnace is discharged through the

    bottom opening into an ash hopper directly below it. A seal is used between the furnace

    and hopper to prevent ambient air being drawn into the furnace and disturbing

    combustion fuel/air ratios. The seal is effected by dipping seal plates, which are

    attached around the bottom opening of boiler furnace, into a water trough around the

    top of the ash hopper. The depth of the trough and seal plates will accommodate

    maximum downward expansion of the boiler (predicated 320.3 mms).

    WATER AND SATURATED STEAM CIRCUITS

    In a controlled circulation Boiler, circulating pumps placed in the downcomer circuits

    ensure proper circulation of water through the waterwalls. Orifices installed in the inlet of

    each water circuit maintain an appropriate flow of water through the circuit. Feed water

    enters the unit through the economizer elements and is mixed with boiler water in the

    steam drum. Water flows from the drum through the downcomers to the pumps suction

    manifold. The boiler circulating pumps take water from the suction manifold and

    discharge it. via the pump discharge lines, into the furnace lower front inlet header.

    Furnace lower waterwall right and left side headers assure proper distribution to the rear

    header.

    In the waterwall inlet headers the boiler water passes through strainers and then

    through orifices which feed the furnace wall tubes, the economiser recirculating lines.

  • PMI, NTPC 11

    The water rises through furnace wall tubes where it absorbs heat. The front wall tubes,

    rear tubes, rear wall hanger tubes, rear arch tubes, rear screen tubes, extended side

    wall tubes and side wall tubes from parallel flow paths.

    The resulting mixture of water and steam collects in the waterwall outlet headers and is

    discharged into the steam drum through the riser tubes. In the steam drum the steam

    and water are separated, the steam goes to the superheater, and the water is returned

    to the water side of the steam drum to be recirculated.

    BOILER CIRCULATION SYSTEM

    Boiler water circulates from the steam drum into unheated down comer pipes, then from

    the down comers into heated furnace wall tubes back into the drum. The furnace walls

    will absorb radiant heat from the furnace and then discharge a saturated steam /water

    mixture into the drum. Inside the drum, saturated steam is separated from the water,

    then directed into superheater tubing for further temperature increase. Water separates

    from the steam will combine with incoming boiler feed water, then re-enter the down

    comers to repeat the cycle.

  • PMI, NTPC 12

    Fig No 2. FLOW PATH IN DRUM

    The boilers are designed with a controlled circulation system which incorporates boiler

    water circulation pumps, smooth and rifled bore furnace wall tubing, and orifice plates

    at the inlet to furnace wall tubing.

    Water flows from the bottom of the steam drum via six large bore downcomers into a

    suction manifold common to three parallel mounted boiler water circulation pumps. The

    manifold has connections at both ends to the chemical clean pipework, and at three

    points along its length to feed individual circulation pump suctions. Water will flow from

    the pumps through two discharge pipes into the front leg of the water wall inlet headers

    at the bottom of the furnace. Each discharge pipe is fitted with a circulating pump

    Discharge Stop/Check Valves which are controlled via sequence equipment to open

  • PMI, NTPC 13

    and close as the pump is taken in and out of service. If, however all three pumps are

    out of service all of the valves will open to enable thermosyphonic circulation to take

    place. Initiating any pump to restart will cause them all to close again then continue with

    the in and out of service regime. Controls for the pumps are located in the U.C.B. and

    comprise a SEQUENCE pushbutton, ammeter and a DUTY/ STANDBY selector. Pump

    status is indicated on RUN/STOP lamps on Panel. The operating regime for the boiler

    water circulation pumps is two duty/one standby.

    From the Waterwall inlet headers, water travels upward through furnace wall tubing via

    furnace upper front rear and side headers into riser tubes which direct a saturated

    steam/water mixture into the steam drum. Furnace wall tubing is manufactured from a

    combination of both smooth and rifled bore tubing which permits the use of lower tube

    flow rate whilst still retaining full tube protection. The required distribution of water to

    give the correct flow rates through the various furnace wall circuits is achieved and

    maintained by the use of suitably sized orifices installed inside the water wall inlet

    headers at the inlet to each furnace wall tube. Orifice size varies for different circuits or

    groups of circuits depending on the circuits length, arrangement and heat absorption.

    Perforated panel strainers are also located inside the water wall inlet headers to prevent

    the orifices blocking and to ensure an even distribution of water around the other inlet

    headers. Refer to fig no.2.

    The saturated steam/water mixture enter the steam drum on both sides behind a water

    tight inner plate baffle which directs the mixture around the inside surface of the drum to

    provide uniform heating of the drum shell. This eliminates thermal stresses from

    temperature differences through the thick wall of the drum, between the submerged and

    unsubmerged portions. Having travelled around this baffle the mixture enters two rows

    of steam separators where a spin is imparted. This forces the water to enter the outer

    edge of the separator where it is separated from the steam. Nearly dried, the steam

    leaves the separators and passes through four rows of corrugated plate baskets where

    by low velocity surface contact, the remaining moisture is removed by wetting action on

    the plates. From the baskets, steam flows out of the drum into superheater pipework.

  • PMI, NTPC 14

    Water which separates from the saturated steam

    drains back to combine with incoming boiler feed

    water from the economiser then re-enters the

    downcomers to repeat the cycle.

    Boiler Water Circulation Pumps

    Each boiler-Water Circulation pump consists of a

    single stage centrifugal pump on a wet stator

    induction motor mounted within a common

    pressure vessel. The vessel consists of three

    main parts, a pump casing, motor housing and

    motor cover as shown in Fig No. 3.

    The motor is suspended beneath the pump

    casing and is filled with boiler water at full system

    pressure. No seal exists between the pump and

    motor, but provisions is made to thermally isolate

    the pump from the motor in the following respect:

    a) Thermal Conduction: To minimize heat conduction a simple restriction in

    the form of thermal neck is provided

    b) Hot Water Diffusion: To minimize diffusion of boiler water, a narrow

    annulus surrounds the rotor shaft, between the hot

    and cold regions. A baffle ring restricts solids entering

    the annulus

    c) Motor Cooling: The motor cavity is maintained at a low temperature

    by a heat exchanger and a closed loop water

    circulation system, thus extracting the heat conducted

    from the pump.

  • PMI, NTPC 15

    In addition this water circulates through the stator and bearing extracting the heat

    generated in the windings and also provides bearing lubrication. An internal filter

    is incorporated in the circulation system.

    d) In emergency conditions if low-pressure coolant to the heat exchanger fails, or is

    inadequate to cope with heat flow from the pump case, a cold purge can be

    applied to the bottom of the motor to limit the temperature rise

    The pump comprises a single suction and dual discharge branch casing. The case is

    welded into the boiler system pipe work at the suction and discharge branches with the

    suction upper most.

    Within the pump cavity rotates a key driven, fully shrouded, mixed flow type impeller,

    mounted on the end of the extended -motor shaft. Renewable wear rings are fitted to

    both the impellers and pump case. The impeller wear ring is the harder component to

    prevent galling.

    The motor is a squirrel cage, wet stator. Induction motor, the stator, wound with a

    special water-tight insulated cable. The phase joints and lead connections are also

    moulded in an insulated material. The motor is joined to the pump casing by a pressure-

    tight flange joint and a motor cover completes the pressure tight shell.

    The motor shell contains all the moving parts, except for the impeller. Below the impeller

    is situated an integral heat baffle which reduces the heat flow, a combination of

    convection and conduction, down the unit. A baffle wear ring cum-sleeve above the

    baffle forms a labyrinth with the underside of the impeller to limit sediment penetration

    into the motor. Should foreign matter manage to pass the labyrinth device into the motor

    enclosure, it is strained out by a filter located at the base of the cover-end bearing

    housing.

  • PMI, NTPC 16

  • PMI, NTPC 17

    The motor design is such that for ease of maintenance, the stator shell, complete with

    the stator pack, the rotor assembly, can be withdrawn from the motor in sequence, after

    removal of the motor from the pump case. Removal lifting lugs are supplied for

    attachment to permanent lugs on the side of the motor case for securing hoists for the

    raising and lowering of the motor.

    SUPERHEATER AND REHEATER

    The arrangement, tube size and spacing of the Superheater and Reheater elements are

    shown in the Figure No. 4.

    Superheaters

    The superheater is composed of three basic stages of sections; a finishing Pendant

    section (34), a Division Panel Section (30) and a Low Temperature Section including

    LTSH (23), the Backpass Wall and Roof Sections (12)(13)(14)(19)(21)(17)(7)(8).

    The finishing Section (34) is located in the horizontal gas path above the furnace rear

    arch tubes.

    The Division panel Section (30) is located in the furnace between the front wall and the

    Pendant Platen Section. It consists of six front and six rear panel.

    The Low Temperature Section (23) and (24) are located in the furnace rear backpass

    above the Economiser Section.

    The Backpass wall and Roof Section forms the side (7) (8) front (12) and rear (19) walls

    and roof (14) of the vertical gas pass.

  • PMI, NTPC 18

    Reheater

    The reheater is composed of 3 stages or sections, the Finishing Section (46) the Front

    Platen Section (47) and the Radiant Wall Section (40)(41).

    The Finishing Section (46) is located above the furnace arch between the furnace

    screen tubes and the Superheater Finish (34).

    The Reheater Front and side Radiant Wall (40) & (41) is composed of tangent tubes on

    the furnace width.

    Steam Flow

    The course taken by steam from the steam drum to the superheater finishing outlet

    header can be seen in Fig. No. 4. The elements, which make up the flow path, are

    essentially numbered consecutively. Where parallel paths exist, first one and then the

    other circuit is numbered. The main steam flow is:

    Steam drum - SH connecting tubes (1)- Radiant roof inlet header (2) - First pass roof

    front (3) - Rear (4) Radiant tube outlet header (5)-SH SCW inlet header side (G)-

    Backpass sidewall tubes (7) & (8)-Backpass bottom headers (9), (10) & (11)- backpass

    Front, and rear (12) (21)-Backpass screen (13) Backpass roof (14)-Backpass SH &

    Eco.. supports(15) SH & Eco support headers(16)-LTSH support tubes (17)-SH Rear

    Roof tubes (18)-SHSC Rear wall tubes (19)-LTSH inlet header (22)-LTSH banks

    (23)(24)-LTSH outlet header(25)-SH DESH link (26). SH DESH (27)-Division panel (30)-

    Division panel (30)-Division panel outlet header (31)-SH Pendent assembly (34)-SH

    outlet header (35).

    After passing through the high pressure stages of the turbine, steam is returned to the

  • PMI, NTPC 19

    reheater via the cold reheat lines. The reheater desuperheaters are located in the cold

    reheat lines. The reheat flow is.

    Reheater radiant wall inlet header (38) (39)- radiant wall tubes (40) (41) reheater

    assemblies (46) (47)-reheater outlet header (48)-Reheater load (49).

    After being reheated to the design temperature, the reheated steam is returned to the

    intermediate pressure section of the turbine via the hot reheat line.

    Protection and Control

    As long as there is a fire in the furnace, adequate protection must be provided for the

    Superheater and Reheater elements. This is especially important during periods when

    there is no demand for steam, such as when starting up and when shutting down.

    During these periods of no steam flow through the turbine, adequate flow through the

    superheater is assured by means of drains and vents in the headers, links and main

    steam piping. Reheater drains and vents provide means to boil off residual water in the

    reheater elements during initial firing of the boiler.

    Safety valves on the superheater main steam lines set below the low set drum safety

    valve provide another means of protection by assuring adequate flow through the

    superheater if the steam demand should suddenly and unexpectedly drop Reheater

    safety valves, located on the hot and cold reheat piping serve to protect the reheater if

    steam flow through the reheater is suddenly interrupted.

    A power control valve on the superheater main steam line set below the low ser super

    heater safety valve is provided as a working valve to give an initial indication of

    excessive steam pressure. This valve is equipped with a shut off valve to permit

    isolation for maintenance. The relieving capacity of the Power Control Valve is not

    included in the total relieving capacity of the safety valves required by the Boiler Code.

    During all start-ups, care must be taken not to overheat the superheater or reheater

  • PMI, NTPC 20

    elements. The firing rate must be controlled to keep the furnace exit gas temperature

    from exceeding 540 C. A thermocouple probe normally located the upper furnace side

    wall should be used to measure the furnace exit gas temperatures.

    NOTE

    1. Gas temperature measurements will be accurate only if a shielded, aspirated

    probe is used. If the probe consists of a simple bare thermocouple, there will be

    an error, due to radiation, resulting in a low temperature indication. At 588 C

    actual gas temperature, the thermocouple reading will be approximately 10

    degrees low. Unless very careful traverses are made to locate the point of

    maximum temperature, it is advisable to allow another 10 degrees tolerance,

    regardless what type of thermocoupie probe is used.

    2. The 540 C gas temperature limitation is based on normal start-up conditions,

    when steam is admitted to the turbine at the minimum allowable pressure

    prescribed by the turbine manufacturer. Should turbine rolling be delayed and

    the steam pressure to permitted to build up the gas temperature limitation should

    be reduced to 510 C when the steam pressure exceeds two-thirds of the design

    pressure before steam flow through the turbine is established.

    Thermocouples are installed on various Superheaters and Reheater terminal

    tubes, above the furnace roof, serve to give a continuous indication of element

    metal temperatures during start-ups (Superheater) and when the unit is carrying

    load (Superheater and Reheater). In addition to the permanent thermocouples,

    on some units temporary thermocouples provide supplementary means of

    establishing temperature characteristics during initial operation.

    Steam temperature control for Superheater and Reheater outlet is provided by

    means of windbox nozzle tilts and desuperheaters.

  • PMI, NTPC 21

    DESUPERHEATERS

    General

    Desuperheaters are provided in the superheater connecting link and the reheater inlet

    leads to permit reduction of steam temperature when necessary and to maintain the

    temperatures at design values within the limits of the nozzle capacity. Temperature

    reduction is accomplished by spraying water into the path of the steam through a nozzle

    at the entering end of the desuperheater. The spray water comes from the boiler feed

    water system. It is essential that the spray water be chemically pure and free of

    suspended and dissolved solids, containing only approved volatile organic treatment

    material, in order to prevent chemical deposition in the desuperheaters and reheater

    and carry-over of solids to the turbine.

    CAUTION

    During start-up of the unit. if desuperheating is used to match the outlet steam

    temperature to the turbine metal temperatures, care must be exercised so as not to

    spray down below a minimum of 10 above the saturation temperature at the existing

    operating pressure. Desuperheating spray is not particularly effective at the low steam

    flows of start-up. Spray water may not be completely evaporated but be carried through

    the heat adsorbing sections to the turbine where it can be the source of considerable

    damage. During start-up, alternate methods of steam temperature control should be

    considered.

    The location of the desuperheater helps to ensure against water carry-over to the

    turbine. It also eliminates the necessity for high temperature resisting materials in the

    desuperheaters construction.

  • PMI, NTPC 22

    Superneater Desuperheaters

    Two spray desuperheaters are installed in the connecting link between the superheater

    low temperature pendant outlet header and the superheater division panel inlet

    headers.

    Reheater Desuperheaters

    Two spray type desuperheaters are installed in the reheater inlet leads near the

    reheater radiant wall front inlet header.

    STEAM DRUM INTERNALS

    The function of the steam drum internals is to separate the water from the steam

    generated in the furnace walls and to reduce the dissolved solids contents of the steam

    to below the prescribed limit. Separation is generally performed in three stages, the first

    two stages are incorporated into the turbo-separators, the final stage takes place at the

    top of the drum just before the steam enters the connecting tubes.

    The steam-water mixture entering the top of the drum from the furnace riser tubes as

    shown in Fig No. 5 sweeps down along both sides of the drum through the narrow

    annulus formed by a baffle extending over the length of the drum. The baffle is

    concentric with the drum shell and effects adequate velocity and uniform heat transfer,

    thereby maintaining the entire drum surface at a uniform temperature. At the lower end

    of the baffle, the steam-water mixture is forced upward through two rows of turbo

    separators.

    Each turbo separator consists of a primary stage and a secondary stage. The primary

    stage is formed by two concentric cans. Spinner blades impart a centrifugal motion to

  • PMI, NTPC 23

    the mixture of steam and water flowing upward through the inner can, thereby throwing

    the water to the outside and forcing the steam to the inside. The water is arrested by a

    skim-off lip above the spinner blades and returned to the lower part of the drum through

    the annulus between the two cans. The steam proceeds up to the secondary separator

    stage.

    The secondary stage consists of two opposed banks of closely spaced thin, corrugated

    matel plates which direct the steam through tortuous path and force entrained water

    against the corrugated plates. Since the velocity is relatively low, this water does not get

    picked up again, but runs down the plates and off the second stage lips at the two

    steam outlets.

    From the secondary separators, the steam flow is upward to the third and final stage of

    separators. These consists of rows of corrugated plate dryers extending the length of

    the drum with a drain through between me rows. The steam flows with relatively low

    velocity through the tortuous path formed by the closely spaced layers of corrugated

    plates, the remaining entertained water is deposited on the corrugated plates, the water

    is not picked up again but runs down the plates into the drain through Suitably located

    drain pipes return this water to the water side of the drum.

  • PMI, NTPC 24

    STEAM DRUM INTERNALS ARRANGEMENT

    Figure No. 5

    RECOMMENDED

    OPERATING RANGE

  • PMI, NTPC 25

    3. Once Through Boiler GENERAL PRINCIPLE

    In a drum boiler, the flow rate of water passing through the steam generating tube walls

    is different from the flow rate of steam produced. It passes through a loop consisting of

    the drum, the downcomers and the steam generating tube walls, and it is far greater

    than the flow rate of steam produced because of the recirculating of the circuit: In the

    drum type circulation: the recirculating coefficient is high (generally) between 3 and 10):

    the tubes and piping have relatively large diameters and the water velocities are low.

    The drum constitutes a fixed point the thermodynamically speaking, the steam

    generating tube walls are at the saturation temperature and all the steam superheat

    must be performed in the heat exchangers independent of the steam generating tube

    walls.

    In a once through boiler, the steam generating tube walls are in series with the

    economiser and the superheaters, and the same flow rate of water passes successively

    through the economiser, the evaporator and the super heaters.

    In the once through circulation; there is no recirculating, the tubes are of small diameter

    and the water velocities are high.

    Different Types Of Once Through Boilers

    There are three types of once through boilers as shown in Fig. No. 6 and the difference

    between them lies in the principle of circulation in the evaporator. Let us examine them

    successively.

    In the first type. the same flow rate of water passes through the economiser, the

    evaporator and the superheaters at normal ratings, but at low loads a minimum flow of

  • PMI, NTPC 26

    water is maintained constant in the economiser and evaporators by the use of

    recirculalting pumps installed beneath the separator.

    In the second type we have the same operating principle, but the minimum water flow

    rate of the low ratings is obtained by the use of the feed water pumps themselves; the

    non-vaporized excess water, i.e. the drains from the separator being sent to the

    deaerator via a heat exchanger called the "Starting exchanger".

    In the third type, the circulation in the evaporator is performed at all loads by the boiler

    circulating pumps which are installed at the evaporator inlet after the water coming from

    the economiser has been mixed with the saturated water from the separator.

    Thus, in the evaporators of these three types of boilers, the proportion of steam in the

    emulsion is very high (up to 100% for the first and second types, up to 80-90% for the

  • PMI, NTPC 27

    third type) and it is impossible to aviod calefaction or D.N.B (departure from nucleate

    boiling). We have to live with this, and it is therefore necessary to have a large speed

    per unit mass in the evaporator tubes (3.50 m/sec. for the water at the inlet) and

    consequently a high-pressure drop in this apparatus (15 to 20 bars).

    Furthermore, the diagrams of the first two types eliminate the (thermodynamically

    speaking) fixed point created by the drum. Which makes it possible to carry out the start

    of superheat in the final part of the steam generating tube walls. The superheaters are

    reduced in consequence, and this has a very beneficial effect on the cost of the boiler,

    especially in high-pressure cycles where the evaporation part is reduced and the

    superheat part amply increased due to the rapid decrease in the enthalpy of the

    saturated steam for pressures greater than 140 bars.

    Design Of Once Through Boiler

    Let us examine, especially with regard to operation with low loads and during startups.

    The Figure No. 7 represents the boiler circulation system during these special types of

    operation.

    At full load, the final part of the evaporator corresponds to a first superheat stage with a

    final temperature of 395, i.e. about 30C above the saturation temperature. Between 35

    and 100% of load, the separator plays no role at all since only dry steam passes

    through it.

    The separator operates as an emulsion separator only for ratings where the steam

    flowrate is below 35%. as the water flowrate passing through the evaporator is then

    maintained constant, and the difference between the feedwater flowrate and the

    flowrate of steam produced must be recirculated via the feedwater pumps (which then

    function as controlled circulation boiler pumps).

  • PMI, NTPC 28

    Fig No. 7

    FLOW DIAGRAM THROUGH STEAM GENERATOR The starting heat exchanger is sized so as to obtain a water temperature the inlet of the

    feedwater tank which is very close to-the saturation temperature present there

    (difference of about 12C.

    The figure shows the control valves designated as AA, AN and ANB:

    Valve AA is sized solely for cold start-ups and low-pressure start-ups; it is closed and blocked in the off position at a pressure of 60 bars.

    Valves AN and ANB are sized for high- and medium-pressure Start-ups and for low ratings (below 35% of full load).

    ANB is sized so that it can cope alone with the low ratings between 35 and 11 % (technical minimum with fuel oil alone):

    AN is used for all start-ups (cold and hot) so as to send to the condenser the flowrate of water coming from the expansion of the evaporator water at the start

  • PMI, NTPC 29

    of evaporation: this flowrate is high for 5 to 6 minutes.

    For this same reason AA is used for cold start-ups. AN is also used for cleaning the boiler circuit water in the condensate treatment

    station at start-ups and at low loads, when the quality of the feedwater is

    inadequate.

    This type of one through circulation has the following advantages:

    Elimination of the boiler circulating pumps, which tends to reduce the maintenance expenses.

    No risk of leakage into the starting heat exchanger which operates with a very slight pressure difference between the two circuits (25 bars maximum).

    The terminal part of the evaporator is in fact a superheater, which represents an economical solution since it avoids covering the upper part of the tube walls of a

    superheater or a wall reheater (bringing a very expensive double

  • PMI, NTPC 30

    Operation On Sliding Pressure

    One of the characteristic features of the once-through boiler is its small storage

    capacity, which permits sliding pressure operation (i.e. with constant opening of the

    turbine inlet safety valves) by maintaining possibilities of sufficiently rapid load

    variations. In addition, this characteristic is further improved by limiting the opening of

    the turbine inlet safety valves to 90%.

    Sliding pressure operation has the following advantages:

    The turbine operating conditions are better since the HP body operates in the same way as the IP or LP body. with much lower mechanical stresses:

    At partial loads, the mechanical stresses in the boiler are also lower since the pressure is lower:

    At partial loads, the steam consumption per kW of the turbine is slightly smaller. It is easy to obtain the reheated steam temperature a the intermediate loads

    because of the virtually constant steam temperature at the HP body outlet:

    It is easy to obtain the nominal superheated steam temperature at the intermediate loads because of the lower service pressure.

    START UP

    One of the main advantages of once through boiler lies in the possibility of performing

    rapid and frequent start-ups and rapid load variations. This is particularly useful for

    disturbed or small electric networks.

    The start-up of a once through boiler can be much more rapid than that of a natural or

    controlled circulation boiler because of the elimination of the large, thick drum which are

    the origin of unacceptable heat stresses during the rapid pressure variations which

    occur when rapid start-ups are desired.

  • PMI, NTPC 31

    In the once through boilers, the pressure parts have been sized so that the thicknesses

    are at all points less than 70 mm. The temperature gradients can then rise by up to 5 C

    per minute for a total of 5000 cycles.

    Moreover, these requirements for rapid start-ups have led the boiler constructor to

    review certain more traditional parts of the equipment.

    Boiler Supports

    To withstand a temperature gradiant of 5C per minute during the planned 5000 cycles,

    the support of the furnace consist of a large number of vertical flats of small size fixed

    against the tubes of the steam generating tube walls by a large number of welded flats

    so as to improve contact between the vertical flats and the tubes and to permit the

    vertical flats to follow without delay the temperature of the tubes. Laboratory fatigue

    tests have confirmed the appropriateness of the design chosen.

    Steam Piping

    Large thick nesses must be avioded by paying attention either to the number of pipes in

    parallel or to the quality of the steel.

    From the economical point of view, the ideal arrangement would be to have a single

    connecting pipe between the boiler and the turbine. But in a 500 MW unit, this would

    lead to thicknesses greater than 80 mm, which is not acceptable.

    We therefore installed two pipes and we determined a trace which gives the assurance

    of having the some temperature in both of these pipes in all cases of operation.

  • PMI, NTPC 32

    Hp By-Pass

    During hot start-ups, the first steam supplied by the boiler is at a temperature much

    lower than that of the pipes.

    To avoid problems of heat stress in the pipes, the HP by-pass must be installed close to

    the boiler and before the piping connecting pieces.

    Start-Up Times

    The start-up times which are summarized in the table below can thus be achieved with

    this type of boiler.

    Time after first lgnition First coupling Full load

    Cold start-up 50 min 3 to 4 hours

    After 36 hours week-end shut-down 30 min 1 to 2 hours

    After 8 hours overnight shut-down 25 min 45 to 75 minutes

    CONSTRUCTION OF BOILER AND HEAT EXCHANGERS

    With regard to boiler construction, the major differences between natural or controlled

    circulation boiler and once through boiler lie in the spiral design of the tube walls.

    The spiral tube zone between the end of the ash pit hopper and the start of the superheater zone : it consists of 404 tubes of 33.7 mm diameter which each

    encircle the furnace twice. So that there is a good homogeneity of the steam

    temperature at the outlet of these tubes. From this point of view, the temperature

    homogeneity thus achieved is certainly better than that which would be obtained

    with vertical tubes which take account of the differences in heat flow at the

  • PMI, NTPC 33

    various points of the furnace; homogeneity of the steam temperatures is esential

    with once through boiler when the steam is superheated at the furnace outlet.

    two parts consisting of vertical tubes - one in the lower part of the furnace and the other in the upper part of the boiler - to form the box around the

    superheaters, reheater and economiser.

    The number of vertical tubes is three times the number of spiral tubes. The junction is

    performed with forged and drilled pieces forming a three-legged pipe. as shown in the figure No, 8.

    The arrangement of the furnace supports consists of:

    - The system of structures which maintain the furnace tube walls and the fixation

    of these structures onto the comer pieces by rods permitting horizontal

    expansion.

    - The system of hangers for the spiral tube walls consisting of vertical flats which

  • PMI, NTPC 34

    remain at the same temperature as the tubes.

    The vertical tubes in the upper part of the boiler are designed to support the weight of

    the spiral parts of the tube walls via junction pieces.

    Generally speaking, the superheaters and reheaters are sized in the same way as in a

    drum boiler.

    Nevertheless, there is a slight difference for the superheaters which are calculated here

    with an additional steam temperature margin of 20 degree to take account of the

    regulation of the steam temperature at the separator outlet in the feedwater control

    system.

    CONCLUSION

    The once through system and the type of operation of the control systems and the

    precautions taken in tie construction of the boiler enable high temperature gradients to

    be achieved in full safety for a large number of cycles.

    Finally this type of boiler, which operates with a high-characteristic water-steam cycle,

    thus enables peak electricity to be produced with low fuel consumption.

  • PMI, NTPC 35

    4. Fuel Firing System INTRODUCTION

    This chapter relates to the fuel (oil & Coal) systems and fuel/combustion equipment

    under supply of BHEL for 500 MW boiler.

    Fuel Oil System

    The Fuel Oil System prepares any of the two designated fuel oil for use in oil burners

    (16 per boiler, 4 per elevation) to establish initial boiler light up of the main fuel

    (pulverized Coal) and far sustaining boiler low load requirements up to 15% MCR load.

    To achieve this, the system incorporate fuel oil pumps, oil heaters, filters, steam tracing

    lines which together ensure that the fuel oil in progressively filtered, raised in

    temperature, raised in pressure and delivered to the oil burners at the requisite

    atomising viscosity for optimum combustion efficiency in the furnace.

    Coal System

    The coal system prepares the main fuel (pulverised coal) for main boiler furnace firing.

    To achieve this the raw coal from overhead hopper is fed through pressurised coal

    valve, SECOAL nuclear monitor, gravimetric feeder and into mills where it in crushed

    and reduced to a pulverised state for optimum combustion efficiency. The pulverised

    coal is mixed with a primary air flow which carries the coal air mixture with a primary air

    flow which carries the Coal Air mixture to each of 4 corners of the furnace burner

    nozzles and into furnace.

    Burner Nozzles

  • PMI, NTPC 36

    Both the oil and coal burner nozzles fire at a tangent to an imaginary circle at the

    furnace centre. The turbulent swirling action this produces, promotes the necessary

    mixing of the fuels and air to ensure complete combustion of the fuel. A vertical tilt

    facility of the burner nozzles, which in controlled by the automatic control system of

    boiler ensures a constant reheat outlet steam temperature at varying boiler loads.

    TILTING TANGENTIAL FIRING SYSTEM

    General

    In the tangential firing system the furnace itself constitutes the burner. Fuel and air

    introduced to the furnace through four windbox assemblies located in the furnace

    comers. The fuel and air streams from the wind box nozzles are directed to a firing

    circle in the centre of the furnace. The rotative or cyclonic action that is characteristic of

    this type of firing is most effective in turbulently mixing the burning fuel in a constantly

    changing air and gas atmosphere.

    Air And Fuel Nozzle Tilts

    The air and fuel streams are vertically adjustable by means, of movable air deflectors

    and nozzles tips, which can be tilted upward or downward through a total of approx. 60

    degrees. These movements effected through connecting rods and tilting mechanism in

    each windbox compartment, all of which are connected to a drive unit at each corner

    operated by automatic control. Provision is given in UCB to know the position of nozzle

    tips during operation. The tilt drive units in all four corners operate in unison so that all

    nozzles have identical tilt positions,

    Windbox Assembly

    The fuel firing equipment consist of four windbox assemblies located in the furnace

    corners.

  • PMI, NTPC 37

    Each windbox assembly is divided in its height into number of sections or compartment.

    The coal compartments (fuel air compartment) contain air (intermediate air

    compartments). Combustion air (secondary air) is admitted to the intermediate air

    compartments and each fuel compartment (around the fuel nozzle) through sets of

    lower dampers. Each set of dampers is operated by a damper drive cylinder located at

    the side of the windbox. The drive cylinders at each elevation are operated either

    remote manually or automatically by the Secondary Air Damper Control System in

    conjunction with the Furnace Safeguard Supervisory System.

    Some of the (auxiliary) intermediate air compartments between coal nozzles contains oil

    gun.

    Retractable High energy Arc (HEA) ignitors are located adjacent to the retractable oil

    guns. These ignitors directly light up the oil guns.

    Optical flame scanners are installed in flame scanner guide pipe assemblies in the

    auxiliary air compartments. The scanners sense the ultraviolet (UV) radiation given off

    by the flame and thereby prove the flame. They are used by Furnace safeguard

    Supervisory System to initiate a master fuel top upon detection of flame failure in the

    furnace,

    AIR FLOW CONTROL AND DISTRIBUTION

    Total air (tow control is accomplished by regulating fan dampers or fan speed. Air

    distribution is accomplished by means of the individual compartment dampers. The

    airflow to the air boxes can be equalised by observing-and equalising the reading of the

    flow meters located in the hot air duct to windbox.

    TOTAL AIR FLOW

  • PMI, NTPC 38

    In order to ensure safe light-off conditions, the pre-optional purge air flow (at least 30%

    of full load volumetric air flow) is maintained during the entire warm-up period until the

    unit is on the line and the unit load has reached the point where the air flow must be

    increased to accommodate further load increase. To provide proper air distribution for

    purging and suitable air velocities for lighting off, all auxiliary air dampers should be

    open during the purge period, the lighting-off and the warm-up period.

    After the unit is on the line, the total required amount of air (total air flow) is a function of

    the unit load. Proper air flow at a given load depends on the characteristics of the fuel

    fired and the mount of excess air required to satisfactory burn the fuel. Excess air can

    best be determined through flue gas analysis (Orsat measurements).

    The optimum excess air is normally defined as the 02 at the economiser outlet produces

    the minimum capacity. Operation below the optimum excess air will result in high

    capacity due to unburned carbon where as operation above the optimum excess air will

    result in high capacity due to excessive H2 S04 condensation. Operation below

    recommended range will result in excessive black smoke and operation above this

    range will result in excessive white smoke.

    NOTE

    The most suitable amount of excess air for a particular unit, at a given load and with a

    given fuel must be determined by experience. This is best done from observation of

    furnace slagging conditions. Slagging tendency of a particular fuel may dicatate an

    increase of operating excess air.

    AIR FLOW DISTRIBUTION

    The function of the windbox compartment dampers is to proportion the amount of

    secondary air admitted to an elevation of fuel compartments in relationship to that

    admitted to adjacent elevation of auxiliary air compartments.

  • PMI, NTPC 39

    Windbox compartment damper positioning affects the air distribution as follows:

    Opening up the fuel-air dampers or closing down the auxiliary air dampers increases the

    air flow around the fuel nozzle. Closing down the fuel air dampers and opening the

    auxiliary air dampers decreases the air flow directly around the fuel stream.

    Proper distribution of secondary air is important for furnace stability when lighting off

    individual fuel nozzle, when firing at low rates and for achieving optimum combustion

    conditions in the furnace at all loads.

    Proper distribution of secondary air also has an effect on the emission of pollutants from

    coal tired units. As the unit load increases the quantity of Nitrogen Oxide (NO) Produces

    in a furnace (due to the oxidation of nitrogen in the fuel) increases and the upper

    elevations of fuel nozzles are placed in service. The quantity of NO produced can be

    reduced by limiting the amount of air admitted to the furnace adjacent to the fuel and

    increasing the quantity of air admitted above the fire (over fire air). When the unit has

    reached a predetermined load (app.50%) the over-fire air dampers should open and

    modulate as a function of unit load until, at maximum continuous rating (MCR) when up

    to 15% of the total air is admitted to the furnace as over fire air. The optimum ratio of

    over fire air to fuel and auxiliary air, as well as the optimum tilt position of the over-fire

    air nozzles, to produce a minimum NO emission consistent with satisfactory furnace

    performance must be determined through flue gas testing (i.e measurement of NO)

    during intial operation of the unit.

    The correct proportion of air between fuel compartment and auxiliary air compartments

    depends primarily on the burning characteristics of the fuel. It influences the degree of

    mixing, the rapidity of combustion and the flame pattern within the furnace. The

    optimum distribution of air for each individual installation and for the fuel used must be

    determined by experience

    The wind-box compartments are normally provided with drive (except end air

    compartments) so they may be operated by a secondary air damper and overfire air

  • PMI, NTPC 40

    control system in conjunction with the furnace safeguard supervisory system. When on

    automatic control the system should provide modulation of the auxiliary air dampers as

    required to maintain a pre-set windbox-to-furnace differential pressure. The fuel air

    dampers should be closed prior to and during light off. When the fuel elevation is proven

    in service, the associated fuel air dampers should open and be positioned in proportion

    to the elevation firing rate. Normally the end air compartments are provided with manual

    adjustment which can be kept in the required position during commissioning of the unit.

    FUEL OIL FIRING SYSTEM

    Fuels

    A coal tired unit incorporates oil burners also to a minimum oil firing capacity of 15% of

    boiler load for the reasons of:

    a. To provide necessary ignition energy to light-off coal burner

    b. To stabilise the coal flame at low boiler/burner loads

    c. As a safe startup fuel and for controlled heat input during light-off.

    Auxiliary steam is utilised in boiler for following purposes:

    a. For atomising the HFO at the cil gun

    b. For tank heating, main heating and heat tracing of HFO

    c. To preheat the combustion air at the steam coil air heater and to warm up the

    main air heater (this reduces Sulphuroxide condensation and thus cold end

    corrosion of main air heater)

    With above provisions and with proper oil steam and combustion air parameters at the

    burner, HFO is safely fired in a cold furnace.

  • PMI, NTPC 41

    Burner Arrangement

    In a tangentially fired boiler, four tall windboxes (combustion air boxes) are arranged,

    one at each corner of the furnace as shown in Figure No. 9. The coal burners or coal

    nozzles are located at different .levels on elevations of the windboxes. The number of

    coal nozzle elevations are equivalent to the number of coal mills. The same elevation of

    coal nozzle at 4 corners .are led from a single coal mill.

    The coal nozzles are sandwitched between air nozzles or air compartments. That is, air

    nozzles are arranged between coal nozzles, one below the bottom coal nozzle and one

    above the top coal nozzle. If there are 'Q' numbers of coal nozzles per corner there will

    be (n+1) numbers of air nozzle per corner.

    Air Nozzles - 9 Lower 7 + 2

    3 AA EA

    The coal fuel and combustion air streams from these nozzles or compartments are

    directed tangential to an imaginary circle at the centre of the furnace. This creates a

    turbulent vortex motion of the fuel air and hot gases which promotes mixing ignition

    energy availability, combustion rate and combustion efficiency.

    The coal and air nozzles are tillable 30 about horizontal, in unison, at all elevations

    and corners. This shifts the flame zone across the furnace height for the purpose of

    steam temperature control.

    The air nozzles in between coal nozzles are termed as Auxiliary Air Nozzles, and the

    top most and bottom most air nozzles as End Air Nozzles.

    The coal nozzle elevations are designated as A.B.C.D etc., from bottom to top, the

    bottom end air nozzle as AA and the top end air nozzles as XX. The auxiliary air

  • PMI, NTPC 42

    nozzles are designated by the adjacent coal nozzles, like AB. BC.CD.DE. etc. from

    bottom to top.

    The four furnace corners are designated as 1,2.3 and 4 in clockwise dilection looking

    from top and counting front water wall left corner as '1'.

    Each par of coal nozzle elevations is served by one elevation of oil burners located in

    between. For example in a boiler with 8 mills or 8 elevations of coal nozzles, there are

    16 oil guns arranged in 4 elevations, at auxiliary air nozzles AB.CD.EF, & GH.

    Heavy fuel oil can be fired at the oil guns of all elevations.

    Each oil gun is associated with an high energy are ignitor.

    Combustion Air Distribution

    Of the total combustion air a portion is supplied by primary air fans that goes to coal mill

    for drying and pulverising the coal and carrying it to the coal nozzles. This 'Primary Air'

    flow quantity is decided by the coal mill load and the number of coal mills in service. The

    primary air flow rate is controlled at the air inlet to the individual mills by dampers

    The balance of the combustion air, referred as 'Secondary Air" is provided by FD fans.

    A portion of secondary air (normally 30% to 40%) called 'Fuel Air' is admitted

    immediately around the coal fuel nozzles (annular space around the casting insert) into

    the furnace. The rest of the secondary air called 'Auxiliary Air' is admitted through the

    auxiliary air nozzles and end air nozzles. The quantity of secondary air (fuel air+auxiliary

    air) is dictated by boiler load and controlled by FD fan blade pitch.

    The proportioning of air flow between the various coal fuel nozzles and auxiliary air

    nozzles is done based on boiler load, individual burner load, and the coal/oil burners in

    service, by a series of air damper. Each of the coal fuel nozzles and auxiliary and end

  • PMI, NTPC 43

    air nozzles is provided with a knock knee type regulating dampers, at the air entry to

    individual nozzle or compartment. On a unit with 8 mills there will be 8 fuel air dampers,

    7 auxiliary air dampers, 2 end air dampers and 2 over fire air dampers per corner.

    Each damper is driven by an air cylinder positioner set, which receives signal from

    'Secondary Air Control System'. The dampers regulate on elevation basis, in unison, at

    all corners.

    Furnace Purge

    Traces of unburnt fuel air mixture might have been left behind inside the furnace of

    some fuel or might have entered the furnace through passing valves during shutdown of

    the boiler.

    Lighting up a furnace with such fuel air accumulation leads to high rate of combustion,

    furnace pressurisation and to explosions at the worst. This is avoided by the "Furnace

    Purge' operation during which 30% of total air flow is maintained for above 6 minutes to

    clear off such fuel accumulations and fill the furnace with clean air, before lighting up.

    During furnace purge, all the elevations of auxiliary and end air dampers are opened to

    have a uniform and thorough purging across the furnace volume.

  • PMI, NTPC 44

  • PMI, NTPC 45

    Fuel Air Dampers

    Its operation is independent of boiler load.

    All fuel air dampers are normally closed. They open fifty seconds after the associated

    feeder is started and a particular speed reached; that it modulates as function of feeder

    speed.

    Fifty seconds after the feeder is removed from service, the associated fuel air dampers

    close.

    The fuel air dampers will open fully when both FD fans are off.

    Fuel Oil Atomisation

    Atomisation is a process of spraying the fuel oil into fine mist, for better mixing of the

    fuel with the combustion air. While passing through the spray nozzles of the oil gun, the

    pressure energy of the atomising steam breaks up the oil stream into fine particles.

    Poorly atomised fuel oil would mean bigger spray particles, which takes longer burining

    time results in carryovers and make the flame unstable due to low rate of heat liberation

    and incomplete combustion.

    Viscosity of the oil is another major parameter which decides the atomisation level. For

    satisfactory atomisation the viscosity shall be less than 28 centistokes.

    External mix type steam atomised oil guns suitable for both LFO and HFO have been

    provided. Atomisers of this type are widely known as J-tips. The atomiser assembly

    consists of nozzle body welded on to the gun body, back plate, spray plate and cap nut.

  • PMI, NTPC 46

    SYSTEM REQUIREMENT

    The maximum total output of oil burners is 30% of the boiler MCR. This meets the

    turbine synchronisation needs before firing coal burners.

    Each oil burner capacity is about 2% of boiler MCR.

    For coal burner ignition and coal flame stablisation a minimum oil burner output,

    equivalent to 10-20% of maximum coal burner capacity is required. This roughly

    corresponds to 40 to 50 % rating of an oil burner.

    The oil burner output is a function of oil pressure at the oil gun and the normal turndown

    range of the oil burner is 3:1.

    For steam atomised oil burner, the oil pressure at the oil gun shall not fall below 2.5

    kg/sq cm (g) to ensure good atomisation and stable flames.

    The oil burners have to be operated at loads, lower than the maximum rating for

    reasons mentioned below:

    a) during cold startups of the boiler, to have a controlled and gradually increasing

    heat loading, to avoid temperature stresses on pressure part materials, as

    dictated by boiler startup curves.

    b) To conserve fuel. oil by operating the oil burners just at the "Coal flame

    stabalisation" requirements.

    Igniters

    High Energy Arc type electrical igniters are provided, which can directly ignite the heavy

    fuel oil. The main features of this system are :

  • PMI, NTPC 47

    a. An exciter unit which stores up the electrical energy and releases the energy at a

    high voltage and short duration.

    b. A spark rod tip which is designed to convert the electrical energy into an

    intensive spark.

    c. A pneumatically operated retract mechanism which is used to position the spark

    rod in the firing position and retract to the non-firing position.

    Each discrete spark provides a large burst of ignition energy as the current reaches a

    peak value of the order of 2000 amps. These sparks are effective in lighting of a well

    atomised oil spray and also capable of blasting off any coke particle or oil muck on the

    surface of the spark rod.

    For a reliable ignition of oil spray by the HEA ignitorjt is very much necessary to

    maintain '.he following conditions:

    a. The atomisation is maintained at an optimum level. All the atomising parameters

    such as oil temperature, steam pressure, clean oil gun tips etc., are maintained

    without fail. The atomising steam shall be with 20C superheat minimum.

    b The cold legs are minimum. The burner fittings are well traced and insulated

    c The spark rod tip is located correctly at the optimum location.

    d The oil gun location with respect to the diffuser and the diffuser location with

    respect to the air nozzle, is maintained properly.

    e. The control system is properly tuned wit ignitor operation. The time of

    commencing of all the operational sequences is properly matched.

  • PMI, NTPC 48

    f. It may become necessary to close the air behind the ignitors, during the light of

    period for reliable ignition. This must be established during the commissioning of

    the equipment and proper sequences must be followed.

    The following facts must be borne in mind to understand the igniters and the system

    clearly:

    a. The spark rod life will be drastically reduced if left for long duration in the

    advanced condition when the furnace is hot.

    b. Too much retraction of spark rod inside the guide tube will interfere with nozzle

    tilts and may spoil the guide tube.

    c. A minimum discharge of 300 kg/hr of oil is essential for a reliable ignition.

    d. A plugged oil gun tip may result in an unsuccessful start.

    e. A cold oil gun and hoses cause quenching of oil temperatures and may lead to

    an unsuccessful start. In such cases warming up by Scavenging prior to start is

    necessary.

    Fuel Oil Gun Advance/Retract Mechanism

    The atomiser assembly of an operating oil gun is protected for the hot furnace radiation

    by the flowing fuel oil/steam which keeps it relatively cool. Once the burner is stopped

    there is no further flow of oil/steam. Under such situation it is required to withdraw the

    gun from firing position to save it from possible damage due to over healing.

    In the system provided, the oil gun is auto advance, auto retraceable. It is driven by a

    pneumatic cylinder and a 4 way dual coil solenoid pilot control valve, with a stroke

  • PMI, NTPC 49

    length of 330 mm. There are three position limit switches, one for, "gun engaged"

    position, another for "gun advanced" and the third for "gun retracted" position, which

    have been suitably interlocked into furnace safeguard supervisory System logics for

    safe and sequenced operation.

    Steam Scavenging Of Fuel Oil Guns

    Before stopping the oil burner, the oil gun is scavenged with steam to keep the small

    intricate passages of the atomiser parts clean.

    * In the auto programmed burner stop sequence, a planned shut down is followed

    by steam scavenging the oil side for quite sometime, to achieve this requirement.

    * During emergency tripping of the burners or boiler, the oil gun is neither

    scavenged nor retracted automatically. Normally such emergency trips may last

    only for a short while and the fuel oil guns shall be re-started or local manually

    scavenged immediately on resuming boiler operation.

    HFO Lumping System

    The screw pump is a constant quantity pump and when only a small quantity of oil is

    fired, the excess oil from the constant quantity pump should be by-passed. This is done

    automatically by pneumatic operated, pressure maintaining cum regulating valve by by-

    passing the excess quantity through the return oil line to storage tank. The delivery

    pressure of oil is maintained constant at the pump outlet, whatever be the quantity of oil

    fired,

    Set the pressure control valve for maintaining adequate and constant pressure at the

    upstream of the HFO flow control valve at maximum firing rate.

  • PMI, NTPC 50

    The flow control valve upstream pressure required is the sum of the following at

    maximum firing rate:

    a. Oil pressure at the gun inlet.

    b. Static head between flow control valve and top level of burners, and frictional

    pressure drop in these lines.

    c. Flow control valve pressure drop, for best turndown.

    HEAVY FUEL OIL HEATING SYSTEM

    Three 150% duty steam-oil heat exchangers and three duplex strainers are provided for

    operation in combination.

    The HFO temperature control valve and the trap station for heaters, steam jacket of

    strainers and line tracers are provided in the system.

    All these equipment are laid out on the floor The drain points are to be suitably piped up

    to the drain pit from the drain trays.

    Steam Heaters and Strainers

    The steam heaters are of fixed tube sheet, U tube type, with oil on shell side and steam

    on the tube side. The oil space is protected against exceeding of allowable pressure by

    low lifting spring loaded safety valve. The exchanger is equipped with the valves

    needed for air release and draining.

    The duplex basket type discharge strainers are at the heater outlet, with fine mesh of

    250 micron filtration. The fine filtering prevents chocking of lines, valves and burner

  • PMI, NTPC 51

    atomisers. The burner tip wearing rate is also reduced. When the pressure drop across

    the strainer exceeds about 0.5 kg/sq. cm. (corresponding to 60% clogged status), the

    standby strainer section is put into service and it is taken for cleaning.

    SCANNER AIR SYSTEM

    The scanner viewing heads are located in the burners and they are exposed to furnace

    radiation continuously. The scanner heads cannot withstand high temperatures that will

    arise due to this exposure. A constant cooling air is required around the scanner head

    to cool it to a safe working temperature to ensure a reliable operation and long life. The

    scanner head cannot be exposed to a continuous temperature of 175C without cooling

    air.

    PULVERIZED COAL SYSTEM GENERAL

    The system for direct firing of pulverised coal utilizes Pulverisers to pulverize the coal

    and a Tiling Tangential Firing System to admit the pulverized coal together with the air

    required for combustion (secondary air) to the furnance.

    As crushed coal is fed to each pulverizer by its feeder (at rate to suit the load demand)

    primary air is supplied from the primary air fans. The primary air dries the coal as it is

    being pulverized and transports the pulverized coal through the coal piping system to

    the coal nozzles in the windbox assemblies.

    A portion of the primary air is pre-heated in the bisector air heater. The hot and cold

    primary air are proportionally J-nixed, prior to admission to the pulveriser, to provide the

    required drying as indicated by the pulveriser outlet temperature. The total primary air

    flow is measured in the inlet duct and controlled to maintain the velocities required to

  • PMI, NTPC 52

    transport the coal through the pulveriser and coal piping. The total primary air flow may

    constitute from approximately 15% to 25% of the total unit combustion air requirement.

    The pulverised coal and air discharged from the coal nozzles is directed toward the

    centre of the furnace to form a firing circle. Fully preheated secondary air for

    combustion enters the furnace around the pulverised coal nozzles and through the

    auxiliary air compartments directly adjacent to the coal nozzle compartments. The

    pulverized coal and air streams entering the furnace are initially ignited by a suitable

    ignition source at the nozzle exit. Above a predictable minimum loading condition the

    ignition becomes self sustaining. Combustion is completed "as the gases spiral up in the

    furnace.

    A large portion of the ash is carried out of the furnace with the flue gas; the remainder is

    discharged through the furnace bottom into the ash pit.

    COMBUSTION OF PULVAREED COAL IN TANGENTSALLY RRED FURNACES

    The velocity of the primary air and coal mixture within the fuel nozzle tip exceeds the

    speed of flame propagation. Upon the nozzle tip the stream of coal and air rapidly

    spreads out with a corresponding decrease in velocity, especially at the outer fringes

    where eddies form as mixture occurs with the secondary air. Here flame propagation

    and fuel speeds equalize, resulting in ignition. As the stream advances in the furnace,

    ignition spreads until the entire mass is burning completely.

    The speed which the air and coal mixture ignites after leaving the windbox nozzles

    depends largely on the amount of volatile matter in the fuel. Heat released by oxidizing

    the volatile components in the coal accelerates of the fixed carbon to its ignition

    temperature.

    The key to complete combustion consists of bringing a successive stream of oxygen

  • PMI, NTPC 53

    molecules into contact with carbon particles, the smallest of which are relatively large by

    comparison with he oxygen molecules. As combustion of the carbon progresses it

    becomes increasingly difficult to bring about contact with the diminishing oxygen supply

    in the limited time available, which for this type of firing is in effect greater due to the

    longer travel taken by the gases.

    The cyclonic mixing action that is characteristic of this type of firing is most effective in

    turbulently mixing the burning coal particles in a constantly changing air and gas

    atmosphere. As the main part of the gases spiral upward in the furnace, the relatively

    dense solid particles are subjected to a sustained turbulence which is effective in

    removing the products of combustion from the particles and in assisting the natural

    diffusion of oxygen through the gas film that surrounds the particles.

    PULVERIZERS

    The pulverizer, exclusive of its feeder, consists essentially of a grinding chamber with a

    classifier mounted above it. The pulverizing takes place in a rotating bowl in which

    centrifugal force is utilized to move the coal. delivered by the feeder, outward against

    the grinding ring (buil ring) as shown in fig no. 10. Rolls revolving on journals that are

    attached to the mill housing pulverize the coal sufficiently to enable the air stream

    through the pulverizer to pick it up. Heavy springs, acting through the journal saddles,

    provide the necessary pressure between the grinding surfaces and the coal. The rolls

    do not touch the grinding rings, even when the pulveriser is empty. Tramp iron and

    other foreign material is discharged through a suitable spout.

  • PMI, NTPC 54

    R P PULVERIZER GENERAL ARRANGEMENT Figure No. 10

  • PMI, NTPC 55

    LEGEND 1. HOT AIR CONTROL DAMPER

    2. COLD AIR CONTROL DAMPER

    3. HOT AIR SHUTOFF GATE

    4. COLD AIR SHUTOFF GATE

    5. PULVERIZER DISCHARGE VALVES

    8. PULVERIZER DISCHARGE SEAL AIR VALVE

    7. FEEDER SEAL AIR SHUTOFF VALVE

    8. PULVERIZER SEAL AIR SHUTOFF VALVE

    9. FAN - ISOLATING VALVES

    SEAL AIR A. TO FEEDER

    B. TO PULVERIZER DISCHARGE VALVES (COAL PIPES)

    C. TO HOT AIR SHUT OFF GATE ft CONTROL DAMPER

  • PMI, NTPC 56

    The air and coal mixture passes upward the classifier with its deflector blades where the

    direction of the flow is changed abruptly, causing the coarse particles to be returned to

    the bowl for further grinding. The fine particles, remaining in suspension, leave the

    classifier and pass on through the coal piping to the windbox nozzles.

    FEEDERS

    The raw crushed coal is delivered from the bunkers to the individual feeders, which, in

    turn feed the coal at a controlled rate to the pulverisers.

    In order to avoid overloading the pulveriser motor due to overfeeding, an interrupting

    circuit should be used to reduce the coal feed if the motor should become overloaded

    and to start the coal feed again when the motor load becomes normal.

    PULVERISED COAL DRYING

    For satisfactory performance, the temperature of the primary air and coal mixture

    leaving the classifier should be kept at approximately 77C for our coals. To low a

    temperature may not dry the coal sufficiently; too high temperature may lead to fires in

    the pulveriser. The outlet temperature must not exceed 90C in any case. The moisture

    content of coals varies considerably. Therefore the best operating conditions for an

    particular installation must be determined by experience.

    Figure No. 11 shows the location of dampers, shutoff gates and valves generally

    utilised. The hot air control damper (No.1) and the cold air control damper (No.2)

    regulate the temperature entering the pulveriser, by proportioning the air flow from the

    hot air and cold air supply ducts. These dampers also regulate the total primary air flow

    to the pulveriser.

    The hot air shutoff gate (No.3) is used to shutoff the hot air to the pulveriser. The hot air

  • PMI, NTPC 57

    gate drive must be interlocked with the pulveriser motor circuit so that the gate will be

    closed any time the pulveriser is not in service. It must also be interlocked with the

    temperature controller to effect closing of the hot air gate when the pulveriser outlet

    temperature exceeds 90C.

    The pulverise discharge valves (No.5), the cold air shutoff gate (No.4) and the seal air

    shutoff valves (No.8) are always kept wide open. They are closed only when isolation of

    a pulveriser or feeder is required for maintenance. Pulveriser discharge valves are also

    closed on loaded, idle pulverisers when other pulverisers are being restarted after an

    emergency fuel trip.

    An adequate supply of clean seal air for the pulveriser trunion shaft bearing, etc.,

    normally is assured by installing two booster fans and a filter in the seal air system. One

    fan normally runs continuously, however it may be isolated for maintenance by closing

    its inlet shutoff damper (No.9). The filter in this system is an inertial separator type

    which discharges approximately 90% of its input as clean air. A bleed off system, with a

    control valve, will control the amount of air being bled from the filters, so that the

    differential pressure between the filter air outlet and the filter bleed air outlet is zero.

    The control valve should be installed so the valve fails open with a loss of instrument

    air.

    The coal pipe seal air valve (No.6) is utilized to admit seal air to the coal pipes for

    cooling when the pulveriser is isolated. The seal air valve is open whenever the

    pulveriser discharge valve air closed an vice versa.

    Primary air velocity requirements in the pulveriser and coal piping preclude wide

    variations in system air flows. Therefore a constant air flow is maintained over the entire

    pulveriser load range. The air flow should be low enough to avoid ignition instability and

    high enough at avoid settling and drifting in the pulverised coal piping or excessive

    spillage of coal from the pulveriser through the tramp iron spout.

  • PMI, NTPC 58

    Coal spillage may also be caused by overfeeding, insufficient heat Inputs for

    drying, too low a hydraulic pressure on the rolls or excessive wear of the grinding

    elements.

    GRAVIMETRIC FEEDERS

    The STOCK Model 7736 gravimetric feeder is designed-to supply 4366 to 76,408 Kgs.

    of coal to the pulveriser per hour while operating on 415 volt, 3-phase, 50 Hertz power

    supply.

    BELT AND DRIVE SYSTEM

    The feeder belt is supported by a machined drive pulley near the outlet, a slotted take-

    up pulley at the inlet end, six support rollers beneath* the feeder inlet, and a weighted

    idler in the middle of the feeder. A counterweighted scraper with replaceable rubber

    blade continuously cleans the carrying surface of the belt after the coal is delivered to

    the outlet. Proper belt tracking is accomplished by crowning the take-up pulley: in

    addition, all three pulley faces are grooved to accept the molded V-guide in the belt. The

    pulleys are easily removable for belt changing and bearing maintenance.

    Belt tension is applied through downward pressure exerted by the tensioning idler on

    the return strand of the belt. Proper tension is obtained when the round protrusion at the

    center of the tension roll is in line with the center indicator mark on the tension indicator

    plate. The tension roll indicator is found on the drive motor side of the feeder and is visible through the viewing port in the tension roll access door. Tension adjustments can

    be made with the feeder operating or at rest by turning the two belt take-up screws

    which protrude through the inlet and access door.

    CHANGES IN HUMIDITY OR TEMPERATURE MAY CAUSE VARIATIONS IN BELT

    LENGTH. BELT TENSION SHOULD ALWAYS BE MAINTAINED WITHIN THE TWO

    EXTREME MARKS ON THE TENSION INDICATOR PLATE.

  • PMI, NTPC 59

    The belt drive system consists of Louis-Allis 5 HP variable speed DC shunt wound

    motor with a speed range of 100-1750 rpm. The motor is housed in a totally-enclosed,

    non-ventilated enclosure with Class II epoxy coated insulation with tropical protection,

    severe duty house down provisions, and a 150 watt space healer wired for 240 VAC

    operation.

    The motor operates through a multiple-reduction gearbox to a total reduction of 149.6:1.

    A reluctance-type magnetic sensor is provided on the motor drive to detect motor

    speed. This data is used for motor speed control feed back information, for zero speed


Recommended