Acadiana Load Pocket Project. Summer of 2002 load growth, changes to generation dispatch in the Acadiana Load Pocket (ALP) and reduced ratings on lines which were damaged during Hurricane Lili result in TLR’s with in the ALP Summer of 2005 - PowerPoint PPT Presentation
Popular Tags:
14
Acadiana Load Pocket Project
Transcript
Page 1: Acadiana Load Pocket Project

Acadiana Load PocketProject

Page 2: Acadiana Load Pocket Project
Page 3: Acadiana Load Pocket Project

Project Background• Summer of 2002

– load growth, changes to generation dispatch in the Acadiana Load Pocket (ALP) and reduced ratings on lines which were damaged during Hurricane Lili result in TLR’s with in the ALP

• Summer of 2005 – Wells Substation was built which provided an additional

source to the ALP and provided more import capability into the ALP

• Summer of 2007 – Company specific imports are established which reduce the

number of TLR level 5’s

Page 4: Acadiana Load Pocket Project

Project Background Continued

• SPP coordinates a joint planning effort with Cleco, Entergy and LUS

• Group evaluates multiple options to fix reliability concerns and provide possible economic benefits

• In January 2009 Cleco, Entergy, LUS reach agreement on a project to be built with each party having some responsibility for the construction.

Page 5: Acadiana Load Pocket Project

ALP Reliability Concerns• Difficult to perform maintenance on

transmission system even during off peak conditions (N-2)

• Catastrophic loss of Teche 3– Operationally the configuration is N-1,G-1– Rolling blackouts within the ALP– Voltage concerns

• 2012 N-1 Summer Peak overloads with all generation in the ALP online.– Rolling blackouts within the ALP.

Page 6: Acadiana Load Pocket Project

ALP Project

Page 7: Acadiana Load Pocket Project

Reliability Benefits

• Plans the ALP to N-1, G-1 which will prevent load shed in the event of a extended outage on Teche 3 or Bonin 3.

• Creates additional 230 kV sources into the ALP which will provide maintenance and operational flexibility.

Page 8: Acadiana Load Pocket Project

Economic Benefits

• Majority of economic benefit will be in fuel cost savings for Cleco and LUS who currently have must run requirements on generation within the ALP during certain times of the year.

Page 9: Acadiana Load Pocket Project

Construction Time line

Page 10: Acadiana Load Pocket Project

Construction Time line

Page 11: Acadiana Load Pocket Project

Construction Time line

Page 12: Acadiana Load Pocket Project

Construction Time line

Page 13: Acadiana Load Pocket Project

Construction Time line

Page 14: Acadiana Load Pocket Project

Questions