7/31/2019 Annual Procurement Plan ~ Infra (CY 2012)
1/10
Procurement Form No. 2
2012 Continuing Appropriation - GF PROPER AND AIP
Code Procurement APPR
(PAP) Method J F M A M J J A S O N D FOR 1 Rehab. of Sto. Nino - Kibang Road
2 Barangay Energization Program
3 Repair of Lamtabong Hanging Bridge, Lambingi
4 Repair & Maintenance of Provl Roads & Bridges
5 Rural Development - Support Infrastructure Provincewide
6 Construction of UP School Bldg & Other Facilities
7 Completion of Mini Gym, Morales E/S Koronadal City
8 Completion of Mini Gym, Brgy. Buenavista, Surallah
9 Repair & Maint - Office Building
10 Communication Equipment
11 Other Structures
12 Furniture & Fixtures
13 3 Units Cellphone for PGO HOTLINE
14 Labor & Materials for Installation of Transformer @ Provl Jail
15 Completion of Lying-in Clinic (Phase II) Sto. Nio RHU
16 Armalite Riffle
17 (S&K Industrial)
18 (Chemical Alloy Corporation)
19 Seven Falls Clinic, CR, Landing Falls #5 Railings
TOTAL FOR PREVIOUS YEAR'S CONTINUING APPROPRIATION (AIP AND GF PROPER)
PROPOSED 2012 Continuing Approp. (2011 AB AIP)
20 Arts, Culture & Museum Support Program- Acquisition of artifacts
21 Barangay Assistance
22 Completion of Multi Purpose Gymnasium @ Brgy. Lamsalome
22A Veterinary Services
a. Construction of Concrete Pathway
b. Construction of Goat Shed
c. Completion of Milking Parlor
23 Lake Sebu Tourism Development Project
24 Rehab/Upgrading of NSR jct Lahit Canahay bndry Road Lake sebu
25 Rehb along Nhwy Silway 8-Klinan 6 - Upper Klinan Polomolok
ANNUAL PROCUREMENT PLAN
(Procurement Form No.2)
Procuring Entity / Units: Provincial Government of South Cotabato
Quantity
Unit of
Issue
Unit
Cost
Calendar Year: 2012
TIME SCHEDULE/qty. requirement
Type of Contract
Page 1 of 9
7/31/2019 Annual Procurement Plan ~ Infra (CY 2012)
2/10
26 Concreting of Concepcion-Tampakan Road
27 Repair & Maintenance Provl Roads & Bridges
28 Repair along Danlag-Palo 19 Road
29 Upgrading along Rang-ay - Lamba Road Section
30 Naci Bridge Abutement
31 Assistance to 199 Barangays
32 Counterpart Funds for the Implementation of Food Securiry Projects
33 Counterpart Funds for Foreign Assisted and other Projects
34 134 In.m 2.7mm x 311mm x3048mm metal Guardrail
35 Systems, Software Development & Acquisition
36 Philhealth Para sa Masa
37 Refurbishing & Improvement of Prov'l. Capitol Lobby38 Barangay Development Assistance Program
39 Brgy. Signage @ Brgy. Tubi-allah
40 Support to Local Health Program (1 unit Ambulance for Tampakan)
41 Construction of Box Culvert from National Highway to UP Compound
42 Provincial Counterpart to Foreign Assisted & Other Special Projects (GEM/MRDP)
42A Lake Sebu Seven Falls Eco-Tourism Development Project
a. Rehab of Wooden Design CR @ Falls #2
b. Rehab of Bamboo Design CR @ Landing Falls #2
c. Rehab of Wooden Design CR @ Entrance Gate Falls
43 Construction of Mini Gym (Phase I) @ Brgy. Simbo
44 Electrification & Power Energy Structure @ SCPH
45 Other Property, Plant & Equipment(Vacum Cleaner & Floor Polisher)
46 Concreting of Lamba Road
47 Repair & Maint - IT Equipment & Software
48 Filling of Provincial Capitol Covered Court
49 Renovation of PSWDO
50 Repair of Canopy & Comfort Room
51 One unit Tape Recorder (Felicitas Bigcas)
52 IT Equipment & Software
53 Communication Equipment
54 Repair & Improvement of Mini Conference Room @ 2nd flr. Of PPDO Bldg.(AB + SB#1)
55 Other MOE - Provl Investment Plan for Health (PIPH)
56 5HP Submersible Pump & Inst. Of Accessories & Fittings
57 Other Property, Plant & Equipment
58 Communication Equipment
59 1 unit 4x2 M/T Service Vehicle & etc
60 Repair of Capitol Water Pipelines
61 Repair of Health Center's Extension of BHS Silway 7
62 Repair Provincial Disaster Risk Reduction & Management Office
63 Repair of Office Building(PEO)
Calamity Fund (2011)
64 Inst. Of Spur Dike Protection along Silway River @ Magsaysay
Page 2 of 9
7/31/2019 Annual Procurement Plan ~ Infra (CY 2012)
3/10
65 Installation of Spur Dike Protection @ Brgy. Naci
66 1 pc. Portable Generator Set, 600 watts & etc
67 2 pcs. First Aid Kit
68 3 units 19" Wide Monitor & etc
69 2 pcs GPS(Garmin)
70 4 pcs OfficeTable
71 Installation of Spurdike Protection, Ambalgan
72 CALAMITY FUND BALANCE AS OF 12/31/11 (33,336,663.25-4,850,335.00)
MISCELLANEOUS
73 Repair & Expansion of Brgy. Silway 7 BHS
74 Repair of 1.20m x 2.4m Two Barrel Box Culvert along Silway 8 Road
75 Const. of One Public Toilet @ Ground Floor (P-2)76 Rehabilitation of Lamcade FMR
77 Rehabilitation of Canahay-Hanoon Farm to Market Road
78 Rehabilitation of Lower-Upper Maculan Farm to Market Road
79 Installation of 100l.m. Lined Canal (Stone Masonry), Brgy. Saravia
80 Renovation of Bgry. Hall, Brgy. Miasong
81 Const. of Private Consultation Clinic @ Paywing (P-2), SCPH Cmpd.
82 Repair & Maintenance of Prov'l. Road (2011 Cont. Appropriation)
83 Repair & MAintenance of Prov'l. Roads & Bridges
84 Repair/Expansion/Renov. Of SCPH Emergency Room
85 Conc. Of Jct. Prov'l. Road-Tubi-allah Bridge
86 Inst. Of Lined Canal (El Gawel to Talungon)
TOTAL FOR 2011 BALANCES FOR CONTINUING APPROPRIATION (AIP AND GF PROPER)
TOTAL CONTINUING APPROPRIATIONS (AIP AND GF PROPER)
Prepared by:
Recommended by:
REDELLA C. SALANGA
BAC Secretariat/TWG DANILO P. SUPE Approved by:
Prov'l. Planning & Dev't. Coordinator
BAC Chairman ARTHUR "DODO" Y. PINGOY, JR.
Provincial Governor
ANNUAL PROCUREMENT PLAN
(Procurement Form No.2)
Page 3 of 9
7/31/2019 Annual Procurement Plan ~ Infra (CY 2012)
4/10
Procurement Form No. 2
Code Procurement APPR
(PAP) Method J F M A M J J A S O N D FOR
2009 Continuing Approp. (2008 Approp)
87 Inst of Jetmatic Pump & Const of Tub Concrete Base-Dahal, Palian
88 Inst of Jetmatic Pump & Const of Tub Concrete Base-Salagidan, Palian
89 Water Testing and Analysis Kit with Comparator PH
90 Community Health and Living Standard Survey (CHLSS)
2010 Cont. Approp. (F1 Projects)
91 Equipment for 9 BEMOC Facilities (Resuscitator (adult) & etc)
92 Provision of IT Equipment and Software for HOMIS (360,000)
93 Civil Works for BHS Construction @ Ned
94 Civil Works for BCemoC Service Provider/Facilities @ LSMH
95 Civil Works for BHS Upgrading: Lusok, Upper Bianan T'boli ; Brgy Pob.
Sto Nio; Liberty, Simsiman, Dumaguil, Kibid, Norala
96 Water System Development: Aflek, Malu, Bianan, T'boli, Cadidang, Kor
2009 SB# 1 DOH/EC Annual Operational Plan
A . Public health Program Development
Disease Free Zone Initiatives
1.Basic Refresher course on Schistisomiasis
97 2.Training of Medtechs/Microscopist in the diagnostic of schistosomiasis
and other soil-transmitted helmintasis
Maternal and Child Health
98 1. Lifesaving Skills training for midwives
2. Community IMCI
Health Lifestyle and Risk Management
99 1. Enhance of KAS on Clinical incidence Management
100 2. TOT on Basic Oral Services for BHW's
101 3. Emergency Response Training
102 4. Training on CT scan, MRI and advanced Ultrasound
103 5. Training on Classification of diseases and databanking
104 6. Develop pool of consultants and trainer to cascade KAS in the health
organization
105 7. Flagship Course on HSR
106 8. Introductory Course on Health System for Key Personnel
ANNUAL PROCUREMENT PLAN
Unit of
Issue
Unit
Cost
LIST OF 2012 CONTINUING APPROPRIATIONS - Fourmula 1 for Health Projects
(Procurement Form No.2)
TIME SCHEDULE/qty. requirement
Type of Contract Quantity
Page 4 of 9
7/31/2019 Annual Procurement Plan ~ Infra (CY 2012)
5/10
Procurement Form No. 2
Code Procurement APPR
(PAP) Method J F M A M J J A S O N D FOR
ANNUAL PROCUREMENT PLAN
Unit of
Issue
Unit
Cost
LIST OF 2012 CONTINUING APPROPRIATIONS - Fourmula 1 for Health Projects
(Procurement Form No.2)
TIME SCHEDULE/qty. requirement
Type of Contract Quantity
2010 SB # 1 EC FUNDS
107 Renovation of Lam-afus BHS, Banga, South Cotabato
Renovation of Datal Dlanag BHS, Tboli, South Cotabato
Repair and Renovation of Katipunan BHS, Sto. Nio
Repair and Renovation of Roxas BHS, Sto. Nio
108 Repair and Renovation of San Vicente BHS, Sto. Nio
Renovation of Talahik BHS, Surallah
Repair and Renovation of Albagan BHS, Tampakan
Repair and Renovation of Kipalbig BHS, Tampakan
Repair and Renovation of Lampitak BHS, Tampakan
Repair and Renovation of Poblacion BHS,Tampakan South Cotabato
Repair of New Lambunao BHS, Tantangan
Renovation of Tantangan RHU TB-DOTS Center
Repair of New Tinungcup BHS, Tantangan
Renovation of Lambuling BHS, T'boli
Renovation of Lamhaku BHS, T'boli
Repair and Renovation of Maltana BHS, Tampakan
109 Repair and Renovation of Lapuz BHS, Norala
Renovation of Main Health Center, Norala
Renovation of Tupi RHU TB-DOTS Center
Renovation of Main Health Center, Tampakan
Repair and Renovation of Lopez Jaena BHS, Norala
110 Repair and Renovation of Matapol BHS, Norala
Repair and Renovation of San Jose BHS, Norala
Repair and Renovation of Kaliong Satellite-type BHS
111 Repair and Renovation of Maligo BHS, Polomolok
Repair and Renovation of Poblacion 1 Satellite-type BHS, Polomolok
Repair and Renovation of Guinsang-an BHS, Sto. Nino
Repair and Renovation of Ambalgan BHS, Sto. Nino
Repair and Renovation of Rang-ay BHS, Banga
Completion of Zone 3 BHS, Koronadal City
112 Renovation of Main Health Center, Polomolok
Renovation of SCPH ICUUpgrading of OPD clinical lab to include testing for Schisto, Malaria,
Leprosy & Fillariasis and water analysis
Page 5 of 9
7/31/2019 Annual Procurement Plan ~ Infra (CY 2012)
6/10
Procurement Form No. 2
Code Procurement APPR
(PAP) Method J F M A M J J A S O N D FOR
ANNUAL PROCUREMENT PLAN
Unit of
Issue
Unit
Cost
LIST OF 2012 CONTINUING APPROPRIATIONS - Fourmula 1 for Health Projects
(Procurement Form No.2)
TIME SCHEDULE/qty. requirement
Type of Contract Quantity
Repair and Renovation of San Jose BHS, Banga
113 Renovation of Banga RHU to include TB-DOTS Center
Renovation of SCPH Rehabilitation Medicine Center
114 2010 SB # 1 EC FUNDS (Taxes, Duties & Licenses- Lumpsum)
2010 SB#1 (2009 DOH Training)
115 Barangay Sanitary Inspectors Training
116 BEMOC training for Sto. Nio, Tantangan, Tampakan, Kor, Surallah,
Banga, T'boli, SCPH, NDH, PMH, LSMH, RISMH
117 Career Development & Management
118 Community IMCI
119 Community Managed Maternal & Newborn Care
Competency Based FP Clinical Standard
120 Emergency Response training for Hospital & RHUs
121 FP Basic Comprehensive training
122 Human Resource Planning
123 IMCI Clinical course (11 day course per batch)
124 PFM Plan Review (Office Supplies & Materials)
125 PFM Plan Review (Program Review)
126 PIPH/AOP 2009 Schedule Synchronization meeting with CHD
127 Project Management & Development Strategic Planning Course
128 Support Harmonization Planning and Budgeting Plan, Implementation evaluation
129 Support to Enhancement of HRMD Systems Reorganization & Reclassification of position
130 Support to Provincial Health board meetings/conferences
131 TB DOTS for children training for tribal leaders
132 TB DOTS for Children Training Groups at workplace(Jail, Industrial Companies, Deped, Academe)
133 TB DOTS for Untrained Health Personnel
134 Traiing Development Needs Assessment (TDNA) for Health Personnel
135 Workshop for Gender Responsiveness of Health Programs, Projects & Services of the Prov'l Govt
136 Residency Training
2010 EC FUNDS SB # 1
137 11 units inkjet printers for MESU/CESU for 1 city & 10 Municipalities
138 Provision of Cost of drugs and medicines (Norala & Sto. Nio)
139 Repair of New Iloilo BHS, Tantangan, South Cotabato140 Upgrading of Kibang, Brgy. Ned BEMOC, Lake Sebu, South Cotabato
141 Water System Development: Aflek, Malu, Bianan, T'boli, Cadidang, Kor
Page 6 of 9
7/31/2019 Annual Procurement Plan ~ Infra (CY 2012)
7/10
Procurement Form No. 2
Code Procurement APPR
(PAP) Method J F M A M J J A S O N D FOR
ANNUAL PROCUREMENT PLAN
Unit of
Issue
Unit
Cost
LIST OF 2012 CONTINUING APPROPRIATIONS - Fourmula 1 for Health Projects
(Procurement Form No.2)
TIME SCHEDULE/qty. requirement
Type of Contract Quantity
2010 EC/DOH Fund SB # 3
142 Other MOE - Consultative Meeting
143 Other MOE - Inception Study for IPHO Technical Staff/Prog. Coord.
144 Upgrading of Lusok BHS, Tboli
145 Upgrading of Upper Bianan BHS, Tboli
146 Repair of various Comfort Rooms and Ceiling Eaves & Repainting of IPHO Bldg.
147 Additional Equipt. For BEMOC Facilties.
2011 EC FUNDS SB # 3
148 Const. of Lamian Health Center (BEMOC)
149 Repair of Bukay Pait BHS
150 Water System Development-Cacub
TOTAL CONTINUING APPROPRIATIONS (F1HP)
TOTAL CONTINUING APPROPRIATIONS (F1HP, GF PROPER AND AIP)
Prepared by:Recommended by:
REDELLA C. SALANGA
BAC Secretariat/TWG DANILO P. SUPE Approved by:
Prov'l. Planning & Dev't. Coordinator
BAC Chairman ARTHUR "DODO" Y. PINGOY, JR.
Provincial Governor
Page 7 of 9
7/31/2019 Annual Procurement Plan ~ Infra (CY 2012)
8/10
Procurement Form No. 2
Code Procurement APPR
(PAP) Method J F M A M J J A S O N D FOR
ANNUAL PROCUREMENT PLAN
Unit of
Issue
Unit
Cost
LIST OF 2012 CONTINUING APPROPRIATIONS - Fourmula 1 for Health Projects
(Procurement Form No.2)
TIME SCHEDULE/qty. requirement
Type of Contract Quantity
Procurement Form No. 2
Code Procurement APPR(PAP) Method J F M A M J J A S O N D FOR
151 Renovation of Library Hub
152 Construction of 2 Room School Buildings (lumpsum)
TOTAL CONTINUING (SEF)
Prepared by:
Recommended by:
REDELLA C. SALANGA
BAC Secretariat/TWG DANILO P. SUPE Approved by:
Prov'l. Planning & Dev't. Coordinator
BAC Chairman ARTHUR "DODO" Y. PINGOY, JR.
Provincial Governor
ANNUAL PROCUREMENT PLAN
(Procurement Form No.2)
Type of Contract QuantityUnit of
Issue
Unit
Cost
TIME SCHEDULE/qty. requirement
LIST OF 2012 CONTINUING APPROPRIATIONS -Special Education Fund
Page 8 of 9
7/31/2019 Annual Procurement Plan ~ Infra (CY 2012)
9/10
Procurement Form No. 2
Code Procurement APPR
(PAP) Method J F M A M J J A S O N D FOR
ANNUAL PROCUREMENT PLAN
Unit of
Issue
Unit
Cost
LIST OF 2012 CONTINUING APPROPRIATIONS - Fourmula 1 for Health Projects
(Procurement Form No.2)
TIME SCHEDULE/qty. requirement
Type of Contract Quantity
Procurement Form No. 2
Code Procurement APPR(PAP) Method J F M A M J J A S O N D FOR
Prepared by:
Recommended by:
REDELLA C. SALANGA
BAC Secretariat/TWG DANILO P. SUPE Approved by:
Prov'l. Planning & Dev't. Coordinator
BAC Chairman ARTHUR "DODO" Y. PINGOY, JR.
Provincial Governor
ANNUAL PROCUREMENT PLAN
(Procurement Form No.2)
INFRA SB #1TIME SCHEDULE/qty. requirement
Type of Contract QuantityUnit of
Issue
Unit
Cost
Page 9 of 9
7/31/2019 Annual Procurement Plan ~ Infra (CY 2012)
10/10
Code Procurement Program/ PMO/End Mode of Pre-Procurement Ads/Post of Pre-Bid Eligibility Sub/Open Bid Post Notice of Contract Notice Delivery/ Acceptance/ Source of Total MOOE C
(PAP) Projects User Procurement Conference IEAB Conference Check of Bids Evaluation Qualification Award Signing to Proceed Completion Turnover Fund
INFRUSTRUCTURE
DEVELOPMENT PROGRAM
Construction of road Jct. Public Bidding Trust Fund 5,000,000.00
San Vicente-Malaya Road
Banga, So. Cot.
Repair of Brgy. San Vicente Public Bidding Trust Fund 5,000,000.00
Banga-Libas Road, Banga,
South Cotabato
Const. of Sch. Building of Public Bidding Trust Fund 5,000,000.00
Dept. of Science and Tech.
Kor. City, South Cot.
Repair of Brgy. Libertad Public Bidding Trust Fund 5,000,000.00
Brgy. Dajay Road, Surallah,
South Cotabato
Const. of Peace Center, Public Bidding Trust Fund 1,500,000.00
Brgy. Palian, Tupi, So. Cot.
21,500,000.00
Recommending Approval: APPROVED:
DANILO P. SUPE BERNARDITA I. VALLAR, CPA ALEX D. BASCO
Prov'l. Planning & Dev't. Coordinator Provincial Budget Officer Chief Administrative Officer
BAC Chairman BAC Vice-Chairman BAC Member
CONRADO M. BRANA JR., MD, MHA,CEO VI NOLI D. ROSETE
SCPH - Chief of Hospital Engineer IV
BAC Member BAC Member
Annual Procurement Plan for FY 2012
ARTHUR "DODO" Y. PINGOY, JR
Provincial Governor
Head of Procuring Entity
Schedule for Each Procurement Activity Estimated Budget (PhP)
Page 1 of 1