Issued by ACA Communications. To submit an item for inclusion in please email : [email protected]
ACA Monthly News April 2015
Commissioning progress on HMS Queen Elizabeth
The HMS Queen Elizabeth team have been celebrating
the important milestone of finishing the installation of all
the blown fibre microduct on the entire ship.
Andrew Harris, Mission
System Platform
Manager, explained:
“The microduct is
the main cable
conduit for the
optical fibre that will
carry all the
information across the
ship between the 30 main
systems and 90 sub-systems
onboard. To have completed all
83,000 metres of cable is a great achievement. All we
have to do now is patch the internal microduct tubes
together and complete the blowing of the optical fibres
across Damage Control (DC) Zones 4 and 5.”
The blown fibre – similar to that which carries superfast
broadband to homes and businesses across the UK – is
helping clear the path for other Mission System
installations.
Indeed, Andrew adds that the Mission System team is
now continuing to expand the hardware installation
across the forward sections of the ship. “The installation
of the ship’s camera system is well underway with the
main servers now in-situ as we set to work and connect
the cameras via the ship’s network.”
“The entire management
team is proud of the work
carried out by the
installation teams and this
demonstrates that the ship
is very quickly coming to
life.” Andrew Harris,
Mission System Platform
Manager.
This is an important part of the operability of the vessel,
with approximately 680 RN personnel monitoring and
maintaining more than 3,000 compartments, remote
systems with cameras and automation are a key design
feature of the Queen Elizabeth Class Carriers.
“The entire management team is proud of the work
carried out by the installation teams and this
demonstrates that the ship is very quickly coming to life. ”
concludes Andrew.
Elsewhere onboard, with first Diesel Generators (DG) set
to work due to commence next month, preparation
continues at pace, according to Mike Cox, Head of
Commissioning. “Diesel Generator Lube Oil embarkation
is now complete in the aft and forward tanks and the fuel
transfer system has been tested with fuel moved around
the double bottom diesel tanks.”
Other steps have been the set to work for the shaft
brakes and the fuel centrifuges, as Mike and his team
target May for the DGs to fire-up for the first time.
“There’s no doubt that there’s a lot to get through before
we can start the diesels but we’re working our way
through and we’re all confident that we’ll hit our target
date.”
Blown fibre installation allows Mission
Systems to complete vital commissioning
First Diesel Generators set to work is due to commence next month.
Issued by ACA Communications. To submit an item for inclusion in please email : [email protected]
This document is available online at http://www.aircraftcarrieralliance.co.uk/delivering-the-nations-flagships/programme-update/yr-2014.aspx
The most iconic section of
the second Queen
Elizabeth Class
aircraft carrier has
set sail from
Glasgow on its first
sea voyage to
Rosyth.
Upper Block 07 is
where HMS Prince of
Wales will be commanded
atop the flight
deck and is known as the Forward Island. As the main hub
of the ship it contains the bridge and approximately 100
vital mission systems compartments.
Angus Holt, QEC Prince of Wales Delivery Director, said:
“The Forward Island is a remarkable feat of engineering
designed to command one of the UK’s largest ever
warships for more than half a century to come so the last
Commanding Officer who will take the helm is not even
born yet. I’d like to congratulate everyone involved in
building and delivering this iconic aircraft carrier section
ahead of schedule and to an incredibly high standard.”
HMS Prince of Wales sets sail for Rosyth
“I’d like to congratulate
everyone involved in
building and delivering this
iconic aircraft carrier
section ahead of schedule
and to an incredibly high
standard.” Angus Holt,
Prince of Wales Delivery
Director.
UB07 has commenced her nine day journey from Glasgow to
Rosyth.
Did you know…
The Queen Elizabeth Class are the first aircraft
carriers to use an innovative twin island design.
The second ‘Aft Island’ operates as an airport
control tower to co-ordinate aircraft movements,
but both islands are designed with the ability to
incorporate the other’s role in an emergency,
thus increasing the survivability of the ship.
Fun fact…
The Forward Island has deck-to-deck windows,
which are up to two metres tall to ensure a level
of visibility far beyond previous aircraft carriers
and are designed to withstand a significant
impact, such as a helicopter’s spinning rotor
blade.
The block left its dock hall in Govan for the first time on
Friday 24 April before being driven onto a barge using a
single remote control and 144 wheels beneath it.
The tug delivering the Forward Island blasted its horn
passing Ferguson Marine Engineering in Greenock as a
final farewell to Glasgow and a salute to shipbuilders along
the Clyde.
Due to inclement weather, the carrier team transporting
UB07 to Rosyth, cautiously decided to take an alternative
route south when it departed from Govan. This means the
Forward Island is travelling via the Irish Sea, Lands End
and the English Channel, before entering the Firth of Forth,
expecting to arrive in Rosyth on 3 May. You can follow the
journey by visiting www.marinetraffic.com and searching
for the tug, which is called Strathdon.
We are running an internal photography competition for
friends and family of ACA employees only. Top prize is a
VIP Rosyth Visitor Experience for the winner and one
guest, plus we’ve got QE Class branded goodies for the
runners up. Photographs must be emailed using the
subject ‘QE Class Prince of Wales Carrier Block UB07’ to
[email protected]. Entries must be
received by 1000hrs on Tuesday, 5 May 2015. For more
information and terms and conditions see the 27 April
internal newsletter.
UB07 is expected to arrive in Rosyth on 3 May.
Issued by ACA Communications. To submit an item for inclusion in please email : [email protected]
This document is available online at http://www.aircraftcarrieralliance.co.uk/delivering-the-nations-flagships/programme-update/yr-2014.aspx
What was your first role working
on the QEC programme?
This one! I only joined DE&S from
the Welsh Government in March
2015.
What did you do before you
joined the ACA?
After studying for my degree, I
moved to Glasgow to train to be a
journalist; I had a career in radio
journalism in the Bristol area before
I joined a housing company as a
Communications Officer. I then
moved to a marketing agency and
What are the key challenges in your role?
At the moment the challenge is to digest as much
information as possible, it is such an enormous
programme to get your head around. But I can see that it’ll
be a really challenging and interesting role.
What has been the highlight of working on the QEC
programme for you?
I went up to Rosyth to see HMS Queen Elizabeth in my
first couple of weeks and I was awestruck at the size of
the ship and what a privilege it is to be involved in such a
programme. My granddad and great-granddad were both
in the Royal Navy so I feel some sort of affiliation with the
work I am doing now. My other highlights have been just
how welcoming everyone has been.
Finally, tell us more about what you do in your spare
time?
I have a 14 month old at home who certainly keeps me on
my toes! I love spending time as a family; she’s so much
fun and is amazed by everything at the moment. I enjoy
pilates and swimming and enter a couple of 5k runs each
year, the next one is in July.
Laura Guppy,
QC Secretariat and
Communications Manager
finally joined the Civil Service in 2011. I worked at the
Welsh Government in Cardiff before moving to the MOD
this year. So I’ve done a few different things!
What does your current role involve?
It is really varied; my role is to oversee parliamentary
business relating to the QE Carrier Programme, such as
Parliamentary Questions, Ministerial Correspondence,
Treat Officials and Senior and Ministerial Briefings and
also Freedom of Information requests. As part of the wider
team I will be working with the secretariat on the Type 26
and OPV programmes.
I am heavily involved in the development of the approvals
and assurance plans and with the review processes.
I am also the focal point for external communications
about the carriers and liaise with other communications
officers across the organisation to ensure that our
message is consistent. I will be the working on the naming
ceremony of the HMS Prince of Wales as well, so I am
looking forward to sinking my teeth into that project.
Diesel Generator Flushing
on HMS Queen Elizabeth
The last four months has seen
the completion of an
extremely challenging
flushing programme
which came to an
end on 31 March to
agreed programme
dates. Flushing is a
key process in
preparing pipework
systems for Commissioning
by removing all industrial
arising’s and any corrosion that
may have occurred since installation/preservation.
The team involved included sub-contractors Q serve, HB
who were supported by the operations, commissioning and
engineering teams.
David Arthur, QEC Wholeship Integration Manager said “The
way the works were carried out and the success of these
activities provides an example of all parties working
collaboratively to achieve the end result. Indeed to meet the
programmed date Q serve chemically flushed 3 systems
concurrently. The chemical flushing process had risks
associated however these were carefully planned with risks
mitigated allowing activities to be carried out in safe and well
managed manner. This process included toolbox talks and
robust risk assessments.”
The picture below gives an example of before and after flush
operation within the fuel transfer system prior to being blown
back and dried.
The systems flushed were fuel, lube oil, diesel generator
fresh water cooling totalling circa 2500 pipes with a volume
of 150 tonnes. The completion of these activities have now
allowed the commissioning teams to fuel HMS Queen
Elizabeth and embark lube oil in preparation for diesel
generator commissioning planned to commence in May.
“The way the works were
carried out and the
success of these activities
provides an example of all
parties working
collaboratively to achieve
the end result.” David
Arthur, QEC Wholeship
Integration Manager
Before and after the flush operation
Issued by ACA Communications. To submit an item for inclusion in please email : [email protected]
This document is available online at http://www.aircraftcarrieralliance.co.uk/delivering-the-nations-flagships/programme-update/yr-2014.aspx
HMS Prince of Wales build update
Glasgow
Lower Block 04
Behind lining scope SSSL are continuing to focus on the remaining voids,
tanks and sea chests to complete build scope, while
also taking an opportunity to spray paint the hull in
Govan.
The team are continuing to target the completion of
behind lining scope across the block, with the medical
area in 5M being submitted in stages as the team
work together to complete this scope.
LB04 making steady progress
Upper Block 07
Team meets milestone With the Forward Island setting sail from Glasgow
on Friday on its first sea voyage to Rosyth, it is an
opportunity to recognise the great work everyone
involved with the programme has done in order to
achieve this significant milestone.
Construction of the Forward Island began in
December 2013. It left its dock hall in Govan
before being driven onto a barge using a single
remote control and 144 wheels beneath it. The
Forward Island of the carrier was an impressive
sight as it sailed down the Clyde from Govan
towards Rosyth.
To view more pictures of the Forward Island
departure visit
www.flickr.com/photos/qeclasscarriers. .
Lower Block 05
Painting and insulation Painting on LB05 is continuing to make steady progress
with four compartments now sprayed and preparation
continuing into other areas. Insulation will start in the
coming weeks, working through the painted areas in the
lower deck levels.
Another area being progressed is the weatherproofing for
both Ring U and T.
Painting continues with steady progress
UB07 passes the BAE Systems Scotstoun site on her voyage to
Rosyth from Govan.
Upper Block 14
Cable basket commenced AI07 Lower has been lifted into place with work
underway to pull the unit into position. There have
been six compartments fully painted on one deck and
good progress continues with the pinning and
insulation off the back of these areas. Cable basket
has also started with progress already being made to
start in a second compartment.
UB14 cable basket starting
Issued by ACA Communications. To submit an item for inclusion in please email : [email protected]
This document is available online at http://www.aircraftcarrieralliance.co.uk/delivering-the-nations-flagships/programme-update/yr-2014.aspx
HMS Prince of Wales build update continued
Merseyside
Central Block 07
Ring progress CHOI inspections are now complete within CB04 A
ring with outstanding observations being cleared
daily. CHOI inspections have commenced within
CB04 B ring with the first three compartments
inspected and achieved. CB04 C ring is now
structurally complete at berth. CB04 D ring three
deck units are erected at berth with two deck units in
manufacture at unit stage with the first two units now
erected at berth onto three deck.
Rosyth
VB block progress The VB blocks delivered to Roysth mid-April have
now been aligned for the joining operation prior to
lifting. On blocks VB003 and 004 the cutting of the
green material is now complete, with VB005 and
VB006 not far behind. The blocks have already
been marked up and the cutting is underway. The
Gun Sponson for SP02 FWD has also been
erected. Preparations are also underway for the
imminent arrival of the Forward Island, UB07.
LB01 completed its load in from the finishing its
journey from Appledore. The block has also been
transported to its holding area at the head of No.1
Dock awaiting final preparation ahead of its
scheduled lift date in June. The Catwalk installation
programme is progressing well with all catwalks
delivered to Rosyth having been lifted into their final
positions on the ship.
CHOI inspected compartment 2MY0
All catwalks and sponson delivered to Rosyth having been lifted
into their final positions
Load out of LB01 in Appledore before her journey to Rosyth
www.aircraftcarrieralliance.co.uk
www.flickr.com/photos/qeclasscarriers.
https://www.youtube.com/user/QEClassCarriers
https://twitter.com/QEClassCarriers
https://www.facebook.com/queenelizabethclasscarrier
Connect with us…
Issued by ACA Communications. To submit an item for inclusion in please email : [email protected]
This document is available online at http://www.aircraftcarrieralliance.co.uk/delivering-the-nations-flagships/programme-update/yr-2014.aspx
Aim update – productivity improvements
Roasfosdgsdgijs\
AIM April Mini Roadshow
April 2015 saw in the first anniversary of the
AIM Roadshows and it was therefore
considered an apt time to chart how far we
have come since April 2014.
The regular monthly roadshows usually provide
an update to the ACA community on the work
done in the previous month. This roadshow
however looked back at where the programme
was in April 2014 and the challenges the AIM
team were tasked with helping improve
demonstrating just how far we have come
together to improve the areas of planning,
change, supply chain and productivity. This was
well received by the good turnout of attendees
at both the on and off ship roadshows.
On Ship Off Ship
Paint Store improvements at J/K Berth
As part of the relentless drive for continuous
productivity improvement across the
programme, the AIM team have been looking at
ways of reducing the need to go off ship and
also reducing the duration of essential trips off
ships.
The painting teams in particular have the
requirement to go off ship and can be faced with
a lengthy walk to get paint refills and materials
on a regular basis.
AIM has been working with Babcock and the
SSSL team to develop an area behind K berth to
re-house the paint store and mixing areas and
we are happy to announce that this area is now
operational. A further management office will be
added which will assist the management and
control of the teams closer to the ship.
Hot-desks rollout continues…
By popular demand, hot desks have now
been made available in the aft end of HMS
Queen Elizabeth with a similar working area
having already been established mid-ship.
Hot desks have also been established mid-
ship on HMS Prince of Wales. Supervisors
will be able to work alongside engineering
liaison and representatives from the planning
and material control departments as part of
the information hub development on this
ship.
Hot desks have been proven to be very
useful as they allow supervisors to remain on
the ship and therefore be closer to their
teams whilst still being able to carry out other
aspects of their job that previously required
periods of time off ship.
AIM Quarterly Engagement Survey
The second quarter AIM Engagement Survey
commenced in the last two weeks of April.
This survey helps the AIM team understand
how engaged the ACA workforce are in relation
to the AIM programme and furthermore help
shape future engagement based on feedback.
The responses on the survey have increased
quarter on quarter since the first survey in April
2014. Awareness of the AIM programme and
its objective increased from 22% to 78% and
positive responses are up from 25% to 62%.