+ All Categories
Home > Documents > Bangladesh Nuclear Power Program Challenges & Opportunities 5/Group... · 2019-09-10 · country....

Bangladesh Nuclear Power Program Challenges & Opportunities 5/Group... · 2019-09-10 · country....

Date post: 10-Mar-2020
Category:
Upload: others
View: 2 times
Download: 0 times
Share this document with a friend
43
INFRASTRUCTURE IN BANGLADESH 8th INPRO Dialogue Forum: Toward Nuclear Energy System Sustainability: Economics, Resource Availability, and Institutional Arrangements 26-29 August 2014, IAEA, Vienna, Austria Engr. Md. Monirul Islam Chairman (Current Charge) BANGLADESH ATOMIC ENERGY COMMISSION
Transcript

INFRASTRUCTURE

IN

BANGLADESH

8th INPRO Dialogue Forum:

Toward Nuclear Energy System Sustainability: Economics, Resource Availability, and Institutional Arrangements

26-29 August 2014, IAEA, Vienna, Austria

Engr. Md. Monirul Islam

Chairman (Current Charge)

BANGLADESH ATOMIC ENERGY COMMISSION

Outline • Introduction

• Bangladesh Overview

• Present Power Situation

• Current & Future plans for NP development

• RNPP overview

• Structure of NEPIO

• Public & Political Support

• Recent Progress

• General Communication Program

• Public Awareness Program

Introduction

Bangladesh has long since been using atomic energy and related technology in different fields for the overall socio-economic development of the country and their uses are increasing gradually.

3

Bangladesh: Basic Facts

• Official Name : People’s Republic of Bangladesh

• Capital City : Dhaka

• Area : 147,570 sq. km

• Total Population : 150 million

• Population Density : 833/sq. km

• Literacy : 50%

• Main Contributors to GDP : Agriculture and Garments Industries

• Natural Resources : Natural Gas, Coal & Hard rock

Basic Information

Bangladesh: Overview

Fig.1:Political Map of Bangladesh with Neighboring Countries

China

Rooppur NPP site Country without Nuclear Power Reactor Country with Nuclear Power Reactor

Present Power Situation Electricity Generation Scenario

Electricity Generation Capacity: 8525 MW (December, 2013)

Public Sector : 4794(56%)

Private Sector: 3731(44%)

Fuel Type Contribution

Natural Gas 67.21%

Furnace Oil 22.33 %

Diesel 5.52 %

Hydro 2.58 %

Domestic Coal 2.35 %

Natural Gas 67%

Furnace Oil

22%

Diesel 6%

Hydro 3%

Domestic Coal 2%

Imported

Max. Demand Served : 6080 MW(March15, 2013)

(aged plants, poor capacity factor)

Renewable Energy :

Renewable energy is environment-friendly. At present, the different categories of renewable energy that are being used in limited ways in our country are as follows:

• Hydro-electricity

• Solar power generation using solar rays

• Wind-mill power generation using wind power

• Production of bio-gas using waste

• Electricity produced by Biomass Gasification Method using wood, rice husk, etc.

Non-Renewable Energy

The proven reserve of natural gas which is the principal source of non-renewable energy of the country is gradually depleting. The supply of gas as a primary source of energy will be dried out soon if immediate steps are not taken for exploration of new gas fields and extraction . In the use of commercial energy, the notable ones include the following:

• Natural gas

• Oil from minerals and other sources

• Coal and coal like substance

• Compressed natural gas (CNG)

• Natural Gas Liquid (NGL)

Power System Master Plan-2010 (PSMP – 2010) proposes long-term fuel-mix as follows [4000 MWe from NPP by 2030]:

By 2021, the share of nuclear will be 10% of 20,000 MW = 2000 MW (2X1000 MW) from the Rooppur NPP.

PSMP-2010 also proposes addition of another

2000 MW from Rooppur nuclear plant

9

Energy 2010 2021 (20,000 MW)

Gas 87.50% 30%

Oil 06.00% 03%

Coal 03.70% 53%

Hydro 02.70% 01%

Nuclear 0% 10%

Renewable 00.50% 03%

Current & Future Plans for NPP Deployment

This share is about 28% now !!

Strategic Position of NPP

Source: Power System Master Plan

Nuclear Power Plant

Cross Border Import

Imported Coal Power Plant

Establishment of Roopur NPP will boost

power generation as well as industrialization

in the Western zone of Bangladesh.

Rooppur NPP Site Overview

Rooppur Nuclear Power

Plant (RNPP) Project

NEPIO has been formed.

A bill to install Nuclear Power Plant has been passed in the National Parliament- ensuring the strong national commitment.

.

River Padma

RNPP Site

Rooppur NPP Site Overview Satellite picture of Site Area: GPS Position : 24.06502, 89.045391 1

Main channel

Flow direction of Ganges River

Hardinge Bridge

Lalon Shah Bridge

Left bank channel

Proposed Power Plant Site

Intake point

Outfall point

Highway & Railway

Structure of NEPIO - Bangladesh

13 13

Working Group

Secretary MOST

Technical Committee

BAEC

Coordination Committee

Nuclear Power and Energy Division (NPED)

NEPIO

Minister MOST

National Committee

8 Working Sub-Groups (Ministry)

Development of Human Resources

Funding and Financing

National Participation

Nuclear Fuel Cycle, Waste Management and

Environ Monitoring

Legal and Regulatory Aspects, International

Obligations

Heavy Equipment Transportation Planning

Ownership, Project execution and Project

Management

Grid System

Prime Minister

BAERA

7 Sub-Committees on RNPP (BAEC)

Ownership, Project

execution & Management

Legal and Regulatory

International Obligations

Development of Human

Resources

Grid System

Development

Funding and Financing

Nuclear FC, WM and Environ

Monitoring

National Participation & Procurement

Nuclear Power Project Stakeholders

NPP Project

Financing entities

Government Regulations &Licensing

Financial commitments

Treaty Commitments & National Law

Government Used Fuel mgmt.

Decommissioning

NSSS Supplier

Fuel Supply EPC

Contractor Owners

Human Capital

Operator

Off taker

Public

Subcontractors Labor

Equipment &Material Suppliers

ECAs

Commercial Banks

BAEC is a Government entity, which is responsible for promoting peaceful uses of atomic energy in the country.

[

Total manpower of BAEC stands at more than 2000, which includes about 500 professionals having wide experience in various fields of nuclear science and technology.

About 100 of these personnel have good exposure on various aspects of NP program.

Nuclear Power Infrastructure

Nuclear Road Map of Bangladesh

• 2013-2016

• Finalization of Site evaluation

• Engineering Survey

• Feasibility Evaluation for Rooppur Nuclear Power Project and design as well as working documentation for the first priority construction & erection base.

• Preparation of EIA report

• Establishment of Independent Regulatory Body

• Signing of Essential Agreement / Contracts with the Vendor country

• EPCM-Turnkey Agreement with Vendor

• Achievement of IAEA Milestone

• By the end of 2021

• Construction, commissioning and test operation and acceptance of the plant

• 2021 Commercial Operation

16

17

Activities to implement first NPP,

the RNPP

Preparatory work for RNPP construction;

negotiating and Concluding contract (s)

Pre-Project activities to make a knowledgeable

decision on NPP

Consideration to include nuclear energy

and initiatives to implement RNPP since

1960s

PHASE 0 PHASE 1 PHASE 2 PHASE 3

Mai

nte

nan

ce a

nd

co

nti

nu

ou

s in

fras

tru

ctu

re im

pro

vem

en

t

Infr

astr

uct

ure

de

velo

pm

en

t p

rogr

amm

e

Pre-project RNPP definition

RNPP Construction Ops

Commissioning

Nuclear power is considered as a possible

option

MILESTONE 0 Ready to include nuclear as

realistic national energy strategy option

MILESTONE 1 Ready to make commitment to a

nuclear

MILESTONE 2 Ready to negotiate the contract.

MILESTONE 3 Ready to commission and operate

first NPP

Pre-policy

2008 2010 2014 2018-2021

RNPP Project Timeline (Sixth Five Year Planning of Bangladesh and PSMP 2010)

Preparation for RNPP

1960s

IAEA Milestone 2 “ready to invite bids” is termed as “ready to negotiate the contract”

IAEA Milestone Approach of Nuclear Power Programme

Operation / decommissioning

•Preparing for assuming commitments & obligations

Commissioning

Nuclear power option included

within the national energy strategy

10 – 15 years

PHASE 2 PHASE 3 PHASE 1

MILESTONE 1 Ready to make a knowledgeable commitment to

a nuclear programme

MILESTONE 2 Ready to negotiate the contractor the

first NPP

•MILESTONE 3 •Ready to commission and operate the

first NPP

negotiate contract

Pre project Project decision making Construction

Maintenance and continuous infrastructure improvement

Preparatory study Feasibility Study

18

Preparation of Infrastructure

Commissioning and Operation

• Project Decision Making

• Site Evaluation • Engineering Survey • Environment Impact Analysis(EIA) • Feasibility Study • Negotiation of Contract • Closure of EPCM Turnkey/ EPC contract

• Establishing competent Nuclear Regulatory Authority

• Public information and understanding

IAEA Milestone Approach of Nuclear Power Infrastructure of Bangladesh

Mongla Port

• The port provides facilities and services to the international shipping lines and maintaining adequate water depth in the channel as well as making provision for safe day and night shipping.

• Present government has given top priority for developing port facilities up to international standard which is necessary for the implementation of RNPP.

Mongla Port is situated (Lat. 21026.9` N. long. 890 34.4 E) in the Bay of Bengal.

COMMUNICATION: contd.

• The entire coast along the Bay of Bengal is 710 Kilometer long. There are two major ports in the country. Chittagong Port , the oldest port, and the Mongla Port in Khulna region serves the western part of Bangladesh . There are now 11 operational airports in Bangladesh . Of these, the airports at Dhaka, Chittagong, and Sylhet serve international routes.

Political & Public Support for NPP

2000: Bangladesh Nuclear Energy Action Plan was approved by the

government.

2008: Implementation of Rooppur NPP had become an Election Pledge of

the present ruling party including all major political parties.

2013: Government has taken Rooppur NPP as one of the five fast-track

projects.

BAEC also conducted a limited survey on public acceptance/awareness

about nuclear power programme that clearly described the unique public

acceptance level of the project

Recent Progress

2009: An MOU between BAEC and the ROSATOM was signed for cooperation in the “Peaceful Uses of Nuclear Energy” on 13 May.

2010: A National Committee on RNPP headed by the Prime Minister was formed.

2010: “In order to overcome the increasing power crisis in the country nuclear power plant shall be established immediately” -Resolution was passed unanimously by the National Parliament in November.

2010: Hon’ble DG of IAEA, Mr. Amano visited Bangladesh during 14–15 December and assured his kind support for implementation of Rooppur NPP.

Recent Progress

2011: The Cabinet approved the Interagency agreement between the

Russian Regulatory Body and the Ministry of Science and Technology

on cooperation in the areas of Nuclear Safety Regulation on 31 October

,2011.

IAEA-INIR mission conducted during November 2011, which

concluded that Bangladesh Nuclear Power Program in general has

progressed into Phase 2, being in the stage of preparation to negotiate

agreement(s)/contract(s).

Cooperation Agreement between GoB and Russian Federation

concerning the construction of ‘Rooppur NPP’ was signed on 02 Nov,

2011.

Recent Progress

Bangladesh Atomic Energy Regulatory Authority (BAERA) Act was

enacted in the National Parliament on 31 May 2012.

An independent regulatory body has been established under the

provision of BAERA Act;

A MOU for the training of the staff of nuclear power sector was

signed on 4 June 2012

A MOU for the establishment of Information Centre of Nuclear

Energy in Bangladesh was signed on 4 June 2012.

Bilateral consultation meeting between Russian Federation and

GoB for determining potential NPP cost and defining the terms and

conditions of the borrowed loans/credit financing from the vendor

sources conducted in July,2012.

Recent Progress

Bilateral consultation on main terms and conditions of the draft

contract (Legal and technical) for carrying out engineering survey

and environmental studies of Rooppur NPP) was held in Dhaka,

1~7 September, 2012.

Loan agreement has been signed with Russian Federation for

financing of for 2× 1000 MW for the preparatory stage of works

(Ist phage) for the construction of RNPP on 15th January 2013.

The Hon’ble Prime Minister of the People’s Republic of Bangladesh

has inaugurated the Construction of Rooppur Nuclear Power Plant

(First Phase) on 2 October, 2013.

Ground Breaking Ceremony of the Construction of Rooppur Nuclear Power Plant (First Phase)

The Hon’ble Prime Minister of the People’s Republic of Bangladesh has inaugurated the Construction of Rooppur Nuclear Power Plant

(First Phase) on 2 October, 2013.

Construction of Rooppur Nuclear Power Plant (First Phase)

Development of the Feasibility Evaluation, Environmental Impact Assessment for Rooppur NPP site

and the performance of the necessary Engineering Survey and

Environmental Studies

Development of design documentation and first-

priority working documentation for

construction of Rooppur NPP

Performance of first-priority construction and erection works of preparatory stage

Completion of remaining works for the Performance of first-priority construction

and erection works of preparatory stage

Contract-1 (Signed) Contract-4

(Under Negotiation)

Contract-3 (Signed)

Contract-2 (Signed)

General Communication Program

• Scientific Information Division:

Under BAEC, this division is working for dissemination of information regarding Nuclear applications and Nuclear Power projects through

Publishing Booklets/ Brochures,

Press release for news media (local & International) etc.

Response to queries placed by phone/letter/email.

attending Science Fairs/Exhibition (focused on Students and Common People),

• TV Shows; Dialogue and Open discussion with News Media :

• Officials from BAEC, NPP key personnel enjoys attending TV/Radio Shows regarding Nuclear

Aspects.

• Seminar and Round Table discussion with Print & Electronic Media also held often.

Interaction with Media at Site and National Forum

Recent round table discussion among BAEC officials and other national experts on

Nuclear Power Programme

Interaction with Media at Site and National Forum

International Seminar on Nuclear Power: A chance of successful economic and socio-political development held on 29-30 May, 2013 at Dhaka.

Interaction with Media at Site and National Forum

Interaction between ROSATOM and students of the Nuclear Engineering department of Dhaka University

Interaction with Media at Site and National Forum

Interaction with Media at Site and National Forum

General Communication Program

• Interaction with Universities, Research Institutes and Academia: • Educational and Research Organizations are considered as Key Stakeholder of

Rooppur NPP.

• Representatives from these institution are part of Policy making and implementation of the NPP.

• Discussion and Exchange of information/ opinion takes place in various events.

Public Awareness Program

• Reaching Students through TEXTbooks and Hands-on-Experience: • Initiative for addition of Facts about Nuclear Power Plant has been

taken and expected to be included in upcoming revision Secondary/Higher Secondary Textbooks

Public Awareness Program

• Engagement with Local Community

Public Information issues Radiation Application.

Nuclear Safety & Environment protection.

Nuclear Power Program Development Plan.

Benefits of NPP project to local community.

Continuing on Media / Methodology Nation wide TV / Radio / Newspaper.

Local cable TV / Radio / Newspaper.

Invite local people to visit “TINT Research Reactor” & radiation utilization – food, agriculture, medical.

Invite local leaders to visit NPP & nearby community in China, Japan.

Future Plan of PI Activities

A Round Table Discussion on N-power plant discussion organized by the Daily Star Newspaper 2009-05-10 A Meeting with local public and people's

representatives in August 2010

Dialogues with the public, the people's representatives at various levels and the decision makers are being conducted and Round Table Discussion on NPP are being organized different media and professional bodies these activities establish the public acceptance level of the Project

BAEC also conducted a limited survey on public acceptance/awareness about nuclear power programme that clearly described the unique public acceptance level of the project 42

Thank you for your kind attention


Recommended