Date post: | 11-Nov-2014 |
Category: |
Documents |
Upload: | parmeshwar-nath-tripathi |
View: | 51 times |
Download: | 4 times |
Design Basis Report for BTG Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248C-J01-01 Page 1
DOCUMENT CONTROL SHEET
PROJECT:DCR THERMAL POWER PROJECT
2 X 300 MW UNITS
CLIENT: RELIANCE ENERGY LIMITED/ SHANGHAI ELECTRIC (GROUP)
CORPORATION
DOCUMENT TITLE:DESIGN BASIS REPORT FOR BTG MECHANICAL PART
DOCUMENT NO.: 50-F248C-J01-01
REV. NO. : 1
ENDORSEMENTS
1 27/12/2
005
Revised as per
HPGC
comments
REV.
NO.
DATE DESCRIPTION PREP. BY
SIGN.(INITIAL)
REVW. BY
SIGN.(INITIAL)
APPD BY
SIGN.(INITIAL)
SOUTHWEST ELECTRIC POWER DESIGN INSTITUTE
18dongfengRoad,chengdu,China
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248C-J01-01 Page
2
CONTENTS
1 GENERAL.................................................................................................................................1 1.1 Major design principle.........................................................................1
1.2 Boiler…...............................................................................................2
1.2.1 Introduction......................................................................................2
1.2.2 Steam Drum , Furnace and Water-wall............................................3
1.2.3 Superheater, Reheater and Attemperator........................................8
1.2. 4 Economizer...................................................................................10
1.2. 5 Combustion equipment.................................................................11
1.2.6 Air Preheaters.................................................................................14
1.2.7 Boiler steel Structure, Platform and Stairs .....................................20
1.2.8 Casing, Refractory and Insulation..................................................21
1.2.9 Soot Blower System and Temperature Probe................................22
1.2.10 The Main Design Features of the boiler .......................................24
1.2. 11 Boiler unit anticipated performance ............................................26
1.2.12 Construction characteristics of boiler unit ....................................28
1.2.13 Piping system ..............................................................................30
1.3 Steam turbine with auxiliaries ...........................................................32
1.3.1 General ..........................................................................................32
1.3.2 Main component (per unit) ..............................................................33
1.3.3 Description for main components .................................................41
1.3.3.1 Combined HP/IP Turbine............................................................41
1.3.3.2 Double flow low pressure turbines ..............................................50
1.3.3.3 Gland Sealing System ................................................................59
1.3.3.4 Turbine Drain System .................................................................60
1.3.3.5 Exhaust Hood Spray System......................................................61
1.3.3.6 Bearings......................................................................................61
1.3.3.7 Rotor turning gear .................................................................62
1.3.3.8 Lubrication Oil System Introduction ......................................64
1.3.3.9 Lubrication Oil Supply System..................................................68
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248C-J01-01 Page 3
1.3.4 Turbine HBD..................................................................................90
1.4 Generator ..........................................................................................92
1.4.1 General ...........................................................................................92
1.4.2 Introduction of QFSN-300-2 generator ...........................................93
2 FUEL........................................................................................................109 2.1 Fuel characteristics.........................................................................110
2.1.1 Coal Analysis ................................................................................110
2.1.2 Fuel Oil ........................................................................................111
3 COMBUSTION SYSTEM AND SELECTION OF AUXILIARY EQUIPMENT............112 3.1 Boiler Fuel Consumption ................................................................113
3.2 Design principle of Flue gas and air system & pulverized coal system................113
3.3 System Description........................................................................113
3.3.1 Pulverized Coal System...............................................................113
3.3.2 Flue Gas and Air System..............................................................114
3.4 Calculation results .........................................................................118
3.4.1 Pulverized coal system .................................................................118
3.4.2 Flue gas and air system...............................................................119
3.5 Major Auxiliary Equipments Selection.............................................119
3.5.1 Pulverized coal system ................................................................120
3.5.2 Flue gas and air system...............................................................121
3.5.3 Boiler Igniting and Fire Stabilizing Oil System .............................129
4 THERMAL SYSTEM AND SELECTION OF AUXILIARY EQUIPMENT...130 4.1 Design principle of Thermal System ...............................................130
4.2 System Description.........................................................................130
4.2.1 Main steam, reheat steam and bypass system.............................130
4.2.2 Feed-water system ......................................................................135
4.2.3 Extraction steam system..............................................................139
4.2.4 Condensate water system ...........................................................139
4.2.5 Heater drains and vents system ..................................................140
4.2.6 Auxiliary steam system ................................................................141
4.2.7 Vacuum system ...........................................................................142
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248C-J01-01 Page 4
4.2.8 Condenser tube cleaning system.................................................143
4.2.9 Closed cycle DM water system.....................................................143
4.2.10 Boiler blowdown and drain system ............................................144
4.2.11 Steam turbine lube oil and Lube oil handling system.................145
4.2.12 Lubrication Oil System...............................................................145
4.3 Major Auxiliary Equipment Selection ..............................................149
4.3.1 Feed-water pump.........................................................................149
4.3.2 Heaters ........................................................................................154
4.3.3 Condensate extraction pump.......................................................167
4.3.4 Vacuum pump..............................................................................170
4.3.5 Condenser ....................................................................................172
4.4 Table of economic index..................................................................176
5 INSULATING MATERIAL.................................................................................176
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248C-J01-01 Page
1
1 GENERAL
1.1 Major design principle
This project is designed to be the coal-fired power plant located in India, with
nominal generator output capacity of 2X300MW.
Main design basis codes and standards will be international codes &
standards, IBR or equivalent standards subject to owner’s approval as below
(refer to contract technical specification.)
1) American society of testing & materials;
2) ASME Test codes;
3) Technical code for designing fossil fuel power plant
4) Technical code for design of thermal power plant air & flue gas ducts/raw
coal & puliverizaed coal piping;
5) Code for design of thermal power plant steam/water piping.
6) Guaranteed availability of each unit is higher than 91%.
7) Unit start-up time from ignition to full load <7.5 Hr,<4 Hr, <1.5 Hr for Cold,
Warm and Hot start respectively.
8) Plant makeup water<3%.
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
2
9) The steam turbine, turbine generator and all equipments and auxiliaries are
suitable for continuous operation in the frequency range of 47.5Hz to 51.5Hz.
Also, for all equipments, noise level measured at a distance of 1 m from the
equipment will not exceed 85dBA except for places as mentioned in 1 to 3
below:
For HP & LP bypass valves and other intermittently operating control valves,
the noise level will be within 85 dBA
1) Safety valves and associated vent pipes for which it will not exceed 105
dBA;
2) Regulating drain valves for which it is limited to 90 dBA;
3) TG unit in which case it will not exceed 90 dBA;
1.2 Boiler
1.2.1 Introduction
The boiler is a natural circulation, subcritical pressure with single steam drum
and single reheat. It is semi outdoor arranged and has a single furnace of
reverse u-form (∏-type, Double pass) arrangement and full pendant steel
structure, dry bottom type water-cooled, balanced draft furnace and is
designed with tangential firing arrangement of burners. There are six
pulverizers with 24 coal nozzles in different elevations in the furnace zone of
the boiler. Light diesel oil will be used for start-up. The light diesel oil will be
designed for 10 % BMCR load and mechanical atomization. The steam
generator shall be designed for firing heavy fuel oil up to 30 % BMCR load.
The minimum load without oil support is 30 % BMCR with design coal and 40
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
3
% BMCR with worst coal with two adjacent mill in service. The HFO will be
steam atomization.
Main superheater steam temperature will be controlled by two stage of spray
water attemperation and reheater steam temperature will be controlled by
tilting the burners and two stage spray water attemperation in case of
emergency condition.
All the designs will be in accordance with ASME “boiler and pressure vessel
code” and “National fire protection association code”
The design of steam generator pressure parts will meet or exceed all the
requirements of latest additions of IBR and specific approved of concerned in
the state Chief Inspector of Boiler. 1.2.2 Steam Drum , Furnace and Water-wall
Steam drum
Design pressure 19.81 Mpa(202kg/cm2g)
Number of supply one (1)
Inside diameter 1743 mm
Total Length 22000 mm
Material SA299
Water Separating System Turbo Separator, Corrugate Dryer
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
4
And Drying Screen
Number of turbo separator 94 pcs
The drum will be of fusion welded construction fabricated form carbon steel
plate and equipped with two (2) 406.4mm diameter manholes. The inside
surface of the drum will be shop shot blasted leaving smooth, clean surface.
When the boiler is operated within the visible range of drum gauge glass,
standard steam quality and reliable water circulation is ensured.
Saturated steam is separated in drum from water/steam mixture of waterwall
and is led into superheater. Saturated water mixes with feeding water at the
bottom of drum from economizer outlet piping and continues to circulate.
Drum Internals
Necessary internals shall be provided for limiting the solid carryover in the
steam leaving the drum to that specified herein.
Drum Connections
The necessary welding end inlet and outlet connections and nozzles to
accommodate the required valves and accessories are provided for
connecting up piping for acid cleaning, nitrogen capping during boiler shut
down, hydrostatic test, chemical injection, continuous blowdown, sampling of
steam and water, emergency drain, safely valves and vent valves.
Drum Supports
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
5
The necessary drum supports will be provided on both sides of the drum,
ample space provided for maintenance persons.
The design and manufacture of the drum conforms to ASME boiler and
pressure vessel code.
Water quality
Item Feed water Boiler water
PH @25 degC 9.2~9.4 9.2~9.4
Oxygen(O2) ppb < 7
Iron(Fe) ppb < 5
Copper(Cu) ppb < 1
Hydrazine(N2H4)ppb < 15 ppb
Silica(SiO2) ppb < 15 250
Cation Conductivity @25 degC 0.15 micro siemens / cm
Phosphate residual ,ppm 0.5 – 3 ppm
Salt, ppm < 20
Furnace and water wall
Type Water-cooled fusion welded wall, hopper bottom type
Furnace dimension:
Width 16100mm
Depth 14120 mm
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
6
Height 53208 mm (lower water header to roof tube)
Volume 10426 m3
Net heat input per plan area 3.25 x 106 kcal/m2h
Furnace cooling factor – 147,200 kacl / hr – m2
Design press. ±660 mm H2O at 67% yield strength
Withstanding press ±1080 mmH2O
The membrane type construction for water wall is employed to ensure air
tightness of the furnace. The water distribution and heating of the water wall
tubes are uniform to ensure even steam production along the width of the
furnace and even water level along the full length of the drum. Sufficient
dynamic head is produced to prevent stagnation, reverse flow, unstable
hydrodynamic values etc. due to abnormal water circulation.
The boiler design ensure sufficient weight flow velocity in water wall tubes
under various loading to prevent departure from nucleate boiling (DNB). A part
of tubes with internal spirals are used (Rifle tubes).
When burning the coal specified in owner’s bid documents under all operating
conditions, the furnace design and burner arrangement ensure that no part of
water wall tube panels, superheaters and reheaters will be impinged by the
flame and no interference of flames between burners.
The boiler design shall ensure complete combustion and no detrimental
slagging in furnace and fouling in the superheater / reheater zone.
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
7
The average flue gas temperature at the furnace exit under BMCR output of
the boiler is 1011℃ while the initial ash deformation temperature is equal to
1100 deg C. Flue gas temperature at the furnace exit is therefore lower than
initial ash deformation temperature by more than 60 deg C.
The design of the furnace employs balanced draft, and provides adequate
sustaining capability of explosion and implosion. The boiler has an expansion
center to permit free expansion of boiler parts. The thermal expansion of
water walls and main headers of other heating surfaces is indicated by three-
dimensional indicators.
The boiler roof employs gas-tight, all welded metallic construction, ensuring
the free expansion of various heating surfaces without cracking and leaking
under variable pressure operation.
The junctions of water wall and ash slag hopper employ qualified sealing
construction, ensuring the free expansion of water walls .in the sealing water
through effective washing equipment is provided to prevent ash accumulation
that affects expansion.
Doors and holes are installed to facilitate the operator’s inspection and the
access of maintenance personnel, and be able to withstand the thermal
radiation without deformation. During operation, these accesses are shut tight
and opening should be avoided. The clearance at the throat of ash hopper is
1400 mm. The hopper slope is 55 degrees, the water wall tubes near the
hopper and its supporting structure can withstand the impingement of large
clinker and sustain dead weight of an accumulation of clinkers up to the
lowest level of burners during abnormal conditions .
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
8
The boiler employs suspended type construction. The steam/water pipes, flue
gas ducts and steel structure connected with the boiler proper ensure the free
thermal expansion of boiler water walls and the rear flue gas shaft.
1.2.3 Superheater, Reheater and Attemperator
Design criteria
Superheater and reheater tubes are made of seamless steel tubes, and
arranged in non-staggering pattern.
The superheater includes low temperature SH(1STstage SH),division
panel(2nd stage SH), SH platen ( 3rd stage ) and SH finish. The reheater
includes radiant RH(1st stage RH) , RH Platen ( 2nd stage) and high
temperature reheater finish (3rd stage RH).
Gas temperature and steam temperature unbalance along the width of the
furnace exit do not exceed the value, which causes metal temperature rise
exceeding allowable temperature.
The associated radiation with convection arrangement of superheaters and
reheaters produce good and flat load-steam temperature curves to relieve the
burden of temperature regulating devices .
In order to meet the requirements of steam temperature under various
working conditions during starting-up of steam turbine and to adapt the
variations of coal qualities, a two-stage water-spray attemperator is installed
before the inlet of division panel and inlet of final superheater. The spray
water system is designed for a spray quantity of 6% BMCR flow with all HP
heaters in service and maximum 10% BMCR flow with all HP heaters out of
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
9
service while generating BMCR steam output.
The attemperator is installed in the steam pipe.
The average velocity of flue gas in superheater area will be: LTSH-9.6 m/s;
platen SH-7.1m/s; final SH-9.94m/s.
The reheater steam temperature will be normally controlled by tilting burners,
whereas the first water sprayer is arranged at the inlet of reheater for
emergency purposes and second water sprayer is arranged at between platen
and final reheater. The reheater spray water system is designed for 3% of
reheat steam flow. For quick cold/hot start up this unit also employs a bypass
starting up steam tapped off from the inlet of backpass lower wall header (S-
10、S-11、S-13,900898-E1-03) to HP heater emergency drain flash tank with
a capacity of 5%BMCR.
The control range of steam temperature is as follows.
Nominal steam temperature must be kept on 50-100%BMCR load for SH and
60-100%BMCR load for RH.
Heat resisting spacer tubes are employed for vertical suspended SH and RH
to guard against oscillation of tube panels.
Anti-abrasion plates made of stainless steel are provided on SH and RH tubes
within the effective range of soot blowers to protect the tubes from erosion.
The lower temperature superheater horizontal tubes are located in the boiler
rear shaft and is suspended from steam cooled water walls.
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
10
Steam temperature deviation at the two ends of SH is lower than 5
Deg.C ,and RH is lower than 5 Deg.C.
1.2. 4 Economizer
Design criteria
Economizer tubes are made of seamless steel tube in non-staggering
arrangement. The net spacing between tubes of the economizer is 102mm,
the average flow velocity of flue gas in economizer at boiler BMCR load is
lower than 8m/s. The temperature difference of flue gas at left and right side
economizer is lower than 2 Deg.C.
Special attention for ash erosion protection will be paid for economizer design.
Anti-abrasion plates are installed on the upper rows of the economizer.
Baffle plates will be provided at adequate place to even out the gas velocity
distribution.
Protection plates will be provided on economizer within the effective range of
soot blowers to protect the tubes from erosion.
Tube nozzles and valves are provided for filling nitrogen and venting air.
Boiler water recirculation system with motorized stop valve provides for
protecting the economizer during starting up of the boiler.
A economizer recirculating piping is located between furnace downcomes
and economizer inlet header. Two motorized isolation valves are set on the
economizer re-circulation line. During boiler start-up, the motorized valve on
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
11
the economizer recirculating piping must be opened to prevent water
evaporating in economizer, closing the motorized valve on the economizer
recirculating piping until certain continuous feed-water flow is established.
1.2. 5 Combustion equipment
Tilting tangential firing system
The tangential firing system is based on the concept of a single flame
envelope; both the fuel and air streams for each corner of the furnace are
aimed tangent to the circumference of a circle in the center of the furnace.
The resulting flame pattern forms a large swirl in the furnace.
Fuel and air nozzles tilt in unison to raise or lower the flame in the furnace to
control furnace heat absorption and heat absorption in the superheater and
reheater sections.
Wind box Assembles
Windbox assemblies are installed in each of the four corners . Each windbox
will be divided into several compartments numbered from the bottom to the
top housing pulverized coal burners, mechanical air atomized light oil burners,
steam atomized heavy fuel oil burners and strategically located auxiliary air
nozzles. The high energy arc (HEA) ignitors will be located in all elevations of
oil gun. They are of class 2 category as defined in NFPA code 85. The top
compartments are used to admit overfire air.
Air and fuel nozzle tilts
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
12
The air and fuel streams are vertically adjustable by means of the movable
nozzle tips in each wind box compartment. The oil and auxiliary air
compartment nozzle tips can be tilted upward or downward through a total
angle of approximately 60degrees (30degrees up, 30degrees down). The coal
compartment nozzle tips can be tilted upward or downward through a total
angle of 40degree (20degrees up, 20degrees down) when operated in parallel
mode.
Offset concentric firing concept
The pulverized coal streams are opposite from auxiliary streams in offset
concentric firing. When fired in this manner, the pulverized coal streams
entering the furnace are introduced in a direction counter to the rotation of the
auxiliary streams. As the fuel and air are essentially in opposed stream the
mixing between them is highly turbulent substantially increasing the ability of
the coal to completely combust before exiting the furnace.
In addition there is a benefit by directing the auxiliary air toward the water
walls, the fuel-rich combustion zone is confined to the center of the furnace,
this maintains an oxidizing atmosphere along the water walls, thereby
minimizing slag formation and corrosion.
The other advantage is that the counter rotationally injected flue also result in
a reduction on the flue gas angular momentum in the upper furnace, hence
improving the furnace exit plan side-to-side gas flow imbalance.
Wide range coal nozzle design
The wide range coal nozzle assembly is the advance design for improving
ignition stability throughout a greater load range and can be made to achieve
a low load operation while maintaining a stable coal flame without the use of
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
13
support fuels on tangential fired boiler. This unique design works by inducing
both turbulence and recirculation to the discharging coal/air mixture. As a
result, the coal particles ignite and provide stability local to the coal nozzle tip
discharge.
Each assembly consists of a coal nozzle tip similar in appearance to the
standard coal nozzle/nozzle tip design. The wide range coal nozzles contain
an internal horizontal splitter plate, which separates the coal/air mixture into
fuel-rich and lean streams.
This ensures that the proper air to fuel ratios required for combustion are
available over a greater range of pulverizer operation.
The wide range coal nozzle tips differ from the standard design by
incorporating an irregular “V-” shaped bluff body diffuser. The diffuser
produces a lower pressure zone, which induces turbulence and causes a high
recirculation pattern to form. The trailing edge of the bluff body is equipped
with a raised surface which shears the coal/air stream in the furnace
increasing the fuel eddy formation into a recircrulation zone .It is these
features which enhance the formation of the stable ignition point over a wide
range of unit load.
Low NOx Coal Burners
There are two methods for controlling NOx emission in this coal burners .one
of them, as described above, the overfire air (OFA) is the remaining auxiliary
air that is introduced to the furnace through OFA ports located at the top of
the windbox, another is the offset concentric firing system (CFS), both OFA
and CFS can be referred to as “staging” techniques. OFA is a type of “vertical
staging” for controlling emissions, while CFS can be thought of as a
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
14
“horizontal staging ”technique-unique to tangential firing .The CFS and OFA
retard the conversion of fuel bound nitrogen at different times during the
combustion history of coal particle within the furnace, thereby the low NOx
coal burners can control NOx emissions not more than 260 gms per gigajoule.
Light Oil Burners and High Energy Arc (HEA)
The 4 numbers light oil burners located at the bottom elevation are the wide-
range mechanical atomizing type with air operated retractable mechanisms. ,
will be provided to maintain 10% percent BMCR load. The oil gun is a double-
barreled gun; the inner barrel supplies oil to the atomizer and the outer barrel
conveys the fuel oil away from the atomizer.
The minimum turndown ratio is 4:1 without changing the size of the burner tips.
The boiler load can be controlled automatically while maintaining good
combustion conditions.
When the atomizer is withdrawn completely from the burner, the fuel oil is to
be automatically shutoff. The safety shutoff valve is to be arranged so that it is
not possible to remove the atomizer.
Without first shutoff the fuel, a quick automatic closing valve, solenoid
operated, is to be provided in the oil supply line to each burner arranged to
shutoff the supply of oil to the unit on flame failure, draft failure, low oil
pressure or low drum water level, or any cause of master fuel trip.
The 4 numbers high engrgy arc(HEA )ignitors will ignite the light oil burners..
1.2.6 Air Preheaters
Ljungstorm trisector air preheater separates both primary and secondary air
flow from one another .The new type double sealing structure reduces direct
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
15
radial and axial air leakage. In addition, the hot end radial sealing of air
preheater adopts leakage control system (LCS) which can automatically
approximate and control the radial sealing clearance, that permits effectively
to reduce the air leakage.
(1) General technical data
Number of supply Two (2)
Type Regenerative vertical
Shaft type
Size 2- 29-VI (65 deg) – 84(96) inch
Heat transfer surface
(Hot end) Carbon steel
(Intermediate sections) Corten (equivalent ASTM A588 or ASTM A606)
(Cold end) Low alloy Corten steel
The rate of air leakage on BMCR is less than 6% and after one year of
operation will be less than 7%.
Scope of supply per air preheater
*Driving mechanism including speed reducer and motor
*Auxiliary motor drive
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
16
* Air motor drive
*Infrared detection system
*Two stationary water-washing devices
*Two additional stationary water-washing devices for fire fighting
*Modular rotor
*Corrosion-resistant steel for cold end protection
*Radial circumferential and axial seals including automatic leakage control
system
*Observation ports and light
*Bearing with oil circulation system
*Rotor stoppage alarm
*Six (6) access doors
Description of equipment for air preheater
(a) Heat transfer surface
The heat transfer surface supplied will consist of hot end element fabricated
from carbon steel, hot intermediate element fabricated from Corten
(equivalent ASTM A588 or ASTM A606), and cold end element fabricated
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
17
from low alloy corrosion resistant steel. . The element will be in easy-to-handle
baskets and shipped from the point of manufacture in the rotor modules .The
element will be sprayed with a water-soluble rust inhibiting oil prior to
shipment. Module covers will be supplied for protection during storage. The
hot end and hot intermediate baskets will be arranged for removal through the
ductwork adjacent to the air preheater .The cold end baskets supplied will be
arranged for side removal through a door in the side of the air preheater
housing structure.
The rotor and the air heating elements of the air heater will be constructed to
allow a feature increase in the depth of the elements at the hot end is 300mm.
(b) Driving mechanism including speed reducer with main drive and auxiliary
drive the main drive consists of a drive motor, coupling, speed reducer and
pinion gear. This system drives the rotor through a pin rack mounted on the
periphery of the rotor.
The auxiliary drive insures the continued operation of the air preheater if
power to the main drive motor is interrupted. The auxiliary drive may also be
used to control the speed of the rotor during water washing of the heat
transfer surface and also for maintenance of the rotor seals and heat transfer
surface
(c) Bearings
The air preheater rotor is supported by a self-aligning thrust bearing assembly
capable of accepting horizontal loads. The air preheater rotor is guided at the
top of the rotor by a spherical roller bearing .All bearings are lubricated by an
oil bath .An oil circulation system for filtering and cooling the oil is supplied for
both the support and guide ends of the air preheater.
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
18
(d) Two stationary water-washing devices
Each device consists of a straight pipe with spray nozzles spaced to distribute
wash water, evenly over the heat transfer surface. One pipe is located in the
gas inlet duct and one is in the gas outlet duct. These devices are integral with
the furnished air preheater and strainers. These devices are to be used for
normal washing of the air preheater.
(e) Two additional stationary water-washing devices
Two additional stationary water washing devices which can be used as part of
deluge system are included.
(f) Automatic leakage control system (LCS)
An automatically adjustable sealing surface is incorporated into the hot end
sealing system. This unit will include a movable sealing surface, a drive
system and a rotor position sensor for each sector plate and a control
package.
The automatically controlled system minimizes the direct air-to gas leakage at
the hot end of the air preheater during transient and full-load operation
conditions .The system keeps the sealing surface of the sector plate in close
proximity to the rotating sealing members.
(g) Rotor stoppage alarm
This device will be comprised of vanes, mounting brackets, and electrical
components.
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
19
The alarm device, i. e. annunciator is to be provided.
(h) Infrared detection system
A three-head infrared detection system is included for each air preheater.
Modular rotor design
A modular rotor design will provide a maximum amount of shop assembly
which will minimize field welding .with a modular rotor, the structural welds
required on the rotor at erection are limited to the pin rack installation. The
heat transfer surface will be shipped in the modules ,reducing the time
required to assemble the rotor in the field.
(j) Observation ports and light
One glass-faced observation port and vapor proof light are included for
installation in the air inlet duct ,adjacent to the air preheater, the location of
these components is determined in the field to best suit viewing of the cold
end heat transfer surface. An additional glass-faced observation ports is
included for installation in the air outlet duct at a point best suited for viewing
the hot end heat transfer surface. These items are shipped unattached for the
installation in the field .
(k) Six (6) access doors
Six access doors for installation in air and gas ducts are included, three (3)
are located integral with the hot end connecting plate and three are shipped
loose for field installation in the cold end duck work.
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
20
1.2.7 Boiler steel Structure, Platform and Stairs
Boiler steel structure mainly includes: supports to each vertical planes,
horizontal supports, supporting plane on boiler roof, each floor platform,
walkways, stairs and other needed supporting structures.
The vertical supporting plane consists of steel columns and bracing between
columns, arranged along the boiler depth and width direction respectively. Some rows are arranged respectively at the front, middle and rear parts along
the furnace depth direction. Some are arranged respectively at the both sides
along the boiler width direction.
The seismic effect, wind load and other horizontal loads will at last be
transferred to the boiler steel structure foundation through vertical support.
The horizontal support consists of beam and bar supports, the rigid plane
consist of seven tiers which are arranged respectively at altitude of the boiler.
They are important parts to transfer horizontal force to fix and control the
boiler expansion direction, guarantee the rigidity of the boiler steel structure
and maintain the steel structure stability.
The supporting and suspending plane on boiler roof consists of the roof steel
frame, supporting and suspending plane for pressure parts and roof
superheater tube supports. The supporting and suspending plane for pressure
parts is made up of double paneled bar beams. Boiler heating surface is
suspended under this plane. Roof steel frame consists of ceiling beam which
is main beam, secondary beam and plane supports forming a rigid plane.
Roof supports mainly consist of beam and bar supports, which is to maintain
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
21
the stability of the main beam.
Steel structure of boiler house
Permanent enclosures will be supplied to give protection against the weather
for plant and personnel in areas where considered necessary e.g. drum,
burner, and galleries.
Platforms, walkways and stairs
All walkways and stairs will be constructed and provided and will be supported
entirely from frames and steelwork. Checkered plating of 5mm thickness will
provided in front of each burner.
Two (2) sets of stairs and walkways are provided for the boiler on each
side .They are to extend from the ground level to the highest part of the
units .Walkways are also provided along the front and rear of the unit as
necessary.
1.2.8 Casing, Refractory and Insulation
The casing made of aluminum material is divided into kinds of ribbed panel
and flat sheet. The installer shall furnish all the necessary labors, tools,
scaffolding, ladders, and some odd scraps of material required to install the
casing. The installer shall field fabricate some element that do not determine
for dimension in the works. The casing drawings do not indicate every small
fabrication detail of the casing, it is up to the casing installer to take care of
the installation in these areas to the satisfaction.
Surface temperature higher than 60 ℃ will be insulated for the protection of
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
22
personnel. Thickness of the insulation will be determined by the material used
and that the surface temperature will not exceed 60 deg C at an ambient
temperature of 40℃
Aluminum sheets (stucco pattern embossed) will be employed to protect the
insulation layer; the thickness of aluminum sheets will be 1mm for the boiler,
and for equipment and ductwork. Piping lagging shall be 0.5 mm for
application up to 330 mm OD and 0.6 mm on other applications.
1.2.9 Soot Blower System and Temperature Probe
The boiler will be provided with a complete set of a programmable automatic
sequential steam operated sootblowing equipment for cleaning the furnace
waterwall, superheater, reheater, economizer and air heater while boiler is in
operation.
The sootblowing system will include the following .
Steam and drain piping system including valves, fitting, supports, steam
pressure reducing valve and thermal drain valve .
A microprocessor based programmable type controller with color CRT monitor
and operator keyboard.
Sootblower
Wall deslagger
Long retractable sootblower
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
23
AH sootblower
Temperature probe
Retractable furnace temperature probe with approximate travel of 6 meters
complete with totally enclosed motor, limit switches, position transmitters and
position indicator, remote control switches, local push-button station.
Soot-blowing piping and air preheater soot-blowing piping. Manual stop valve
and motorized stop valve are set before pressure reducing valve and safety
valve.
The steam of sootblower system come from panel SH outlet header for boiler
soot blowing and from platen SH outlet header for AH soot blowing flowing
through pressure reducing valve, is divided into two branches to enter boiler
proper is set behind pressure reducing valve in order to protect whole soot-
blowing system from exceeding pressure. Pressure measuring point is set to
control the pressure behind pressure reducing valve.
To guarantee the proper dryness of soot-blowing media, there is a drain
system for two branches of boiler proper individually. Each drain system has a
motorized valve self-drain, and its horizontal piping shall at least be kept
gradient for drainage.
Air pre-heater soot-blowing steam consists of two branches, one is from
pressure reduce station for above 10% BMCR load, and the other is from
auxiliary steam for below 10% BMCR load.
A drain system with a pneumatic valve in piping is able to self-drain.
Horizontal piping shall at least be kept gradient drainage.
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
24
1.2.10 The Main Design Features of the boiler
Firing
Burners are arranged at the four corners of furnace for tangential firing, wide
range (WR) tilting burners are utilized, which feature for wide adaptability to
various coals , complete combustion, effective reduction of NOx formation.
The tilting nozzles are designed to regulate the furnace exit temperature,
which provides an auxiliary means to regulate the reheat steam temperature.
The coal preparation system employs a pressurized direct-fired circulating
system with HP mill with high primary air (PA) pressure and low secondary air
(SA) pressure. The coal pipes are installed with orifice to balance the flow of
air/coal mixture to ensure uniform coal –air flow at four corners.
* Water Circulation
This boiler is designed for natural circulation. The minimum circulation ratio is
2.6 under any operating condition. As the drum is designed with large volume,
the boiler can adapt to the load variations easily. The waterwall is constructed
with rifled tube on proper location to increase safety allowance control.
The boiler is equipped with furnace safeguard supervisory system (FSSS),
which provide functions including controlling the purges of the pulverized
system in /out of operation, detecting the fireball in furnace and the flame of
individual oil gun, offering the trip protection in emergent case of fuel failure.
Therefore, FSSS ensures the boiler unit operating safely and reliably.
The turbine – boiler coordinated control system (CCS) also control the
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
25
following items including firing, the exit temperature of pulverizers and the air
flow, the primary air flow, the deviation-limit of fuel and air flow, the secondary
air flow, the furnace draft, the feed water flow, the superheat steam
temperature and the reheat steam temperature. Consequently, CCS ensures
the turbine-boiler operating in a coordinated fashion and helps to improve the
operation.
In addition, the following systems are used; programmable sootblowing
control system, boiler water level/furnace flame CCTV monitoring system,
which improve the operation of the boiler unit.
Flue and Air System
The boiler is designed with a balance draft system by using FD and ID fans.
The air required for combustion in the boiler is supplied by FD fans to the air
preheater of trisector design. The pressurized primary air system acts as the
drying agent and primary air for the HP mill direct –fired system .The primary
air system is designed with a bypass, used to regulate the air/coal mixture
temperature. The secondary air from air preheater outlet is discharged to the
boiler windbox to provide secondary air for the burners
The flue gas from furnace outlet will pass through the panel-and platen-type
superheaters, high-temperature superheater, high-temperature reheater and
the deflection chamber (over the arch nose), low –temperature superheater,
economizer, air preheater. Then the flue gas will pass through the ESP before
being discharged to the stack by ID fan.
Piping system
The piping system mainly consists of the piping for drain, discharge blowdown,
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
26
vent, steam discharge and chemical dosing etc.
The piping system also includes a 5% BMCR drain system for bypass of
saturated steam from backpass lower wall header to HP heater emergency
drain flash tank, which can control the superheat steam temperature
effectively, quicken startup speed, and improve the operation flexibility.
The drum emergency drain system can prevent the drum from being fully filled
with water.
The safety valve discharge system with silencer can control the steam
discharging noise within acceptable level.
1.2. 11 Boiler unit anticipated performance
Boiler Max. Continuous Rating (BMCR)
The boiler can adapt to the design coal and worst coal. When fired with design
coal and under rated load ranges the steam temperature at the rated value
are :
For superheater steam between 50- 100% load range, the steam temperature
imbalance ±5℃
For reheat steam between 60-100% load range, the steam temperature
imbalance ±5℃
The boiler is designed to carry base load and can also be used for cycling
operation .
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
27
Boiler operation
*The boiler can accommodate for combined sliding –pressure (fixed-sliding –
fixed pressure) operation.
*The boiler can accommodate for various start-up/shutdown operation
patterns of the turbine. The boiler can be started up in cold, warm, hot and
extremely hot conditions.
*With normal startup, the time duration needed for the unit to carry full load
from the ignition are:
Cold startup <7.5 hr
Warm startup <4 hr
Hot startup <1.5 hr
Allowable boiler load change rate
Fixed pressure operation 5%/min
Siding pressure operation 3%/min
Air leakage rate of air preheater
Within the first year of boiler operation 6%
After the first year of boiler operation 7%
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
28
Low Nox combustion technology is being incorporated in the design of furnace
and coal burners.
NOx emission 260 gm /gigajoules
Service life
*The main pressure parts of the boiler are designed for a service life not less
than 30 years .
The boiler can stand for the following expected number of annual start-ups:
Cold startup: 20 times. (after 72 hours of unit shutdown.)
Warm startup: 40 times (after 36 hours of unit shutdown)
Hot startup: 180 times (after 8 hours of unit shutdown)
1.2.12 Construction characteristics of boiler unit
*The boiler is designed for semi-outdoor arrangement provided with rainproof
measures as light metal house cover over the furnace roof. *The boiler utilized
complete pendant steel structure, which provides space for all the
components to expand freely when heated.
*The boiler is designed with an expansion center, from which the components
will expand in order. This is conducive for stress analysis and seal design of
pressure parts and can help prevent pressure parts and seal parts from
tearing due to excess thermal stress, thus to improve boiler safety and
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
29
reliability.
*Using fully sealed internal casing
In order to prevent boiler unit from gas-and air-leakage, all the areas without
gas –tight membrane heating surfaces are fully sealed by internal casings,
absolutely reliable expansion joints and special sealing structure on the
furnace roof penetration, which provide the unit with great safety and
economy.
Design Basis:
1) Such parameters of pressure, temperature and flow etc. for main steam
and reheat steam will match those required for steam turbine.
2) Boiler nameplate, namely Max. Continuous Rating (BMCR) is higher than
steam flow at valves wide open (VWO) of steam turbine.
3) Boiler capacity and main parameters
Boiler type: SG1025/17.5-M898
Items Unit BMCR
Boiler Max. Continuous rating (BMCR) t/h 1025
Superheater outlet steam pressure MPa.(a) 17.6
Superheater outlet steam temperature ° C 541
Reheat steam flow t/h 822.7
Reheater inlet steam pressure Mpa(a) 3.84
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
30
Items Unit BMCR
Reheater outlet steam pressure Mpa(a) 3.66
Reheater inlet steam temperature ℃ 326
Reheater outlet steam temperature ℃ 541
Economizer inlet feed water temperature ℃ 280
1.2.13 Piping system
1.2.13.1 Drain, vent and chemical Injection piping
To ensure the safety and reliability for boiler operation, drain and vent point
are set at necessary position of pressure parts.
The position of chemical feed is located on downcomes.
The piping system also includes a 5% BMCR drain system for bypass of
saturated steam from lower header in the second pass to the HP emergency
drain flash tank, which can control the superheater steam temperature
effectively, quicken startup speed, and improve the operation flexibility.
The drum emergency drain system can prevent the drum from being fully filled
with water.
1.2.13.2 Blow-down piping With improvement of steam parameter, higher purity feed-water is required.
Boiler blow-down system is used for controlling boiler water concentration and
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
31
removing sediment. Under condition of high solid content and worse treated
feed-water, periodical blow-down is carried out be furnace lower water drum.
Under condition of good feeding water quality, it is generally recommended to
use continuous blow-down if water/steam quality requirement can be met, and
periodic blow-down isn’t needed.
1.2.13.3 Sampling piping Boiler is fitted with saturated steam and boiler water sampling points.
Saturated steam sampling is taken from steam relief tubes between drum and
roof SH inlet header. Six (6) points of saturated steam sampling are set along
the drum length direction.
Furnace water sampling is taken from continuous blow-down piping, one (1)
point is set, sampling piping is equipped with two (2) manual stop valves.
1.2.13.4 Safety valve and discharging piping for safety valve In order to ensure the boiler operation safety and to prevent pressure parts
from overpressure, boiler is equipped with ten (10) safety valves, of which
three (3) are on drum, two (2) are on SH outlet, two (2) are on RH inlet piping,
three (3) are on RH outlet piping. In addition, two (2) pneumatic control valves,.
Two (2)Pressure sensed pneumatic relief valves are arranged on SH outlet
piping. Total relief capacity of pneumatic control valves is more than 15% max.
main steam flow.
Each safety valve and pneumatic vent valve is fitted with discharging piping,
going upward from upper of drip pan at discharging bent of safety valve and
passing through roof housing. In order to reduce noise, each safety valve and
pneumatic pressure controlled valve is equipped with silencer.
The safety valve discharge system with silencer can control the steam
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
32
discharging noise within acceptable level.
1.3 Steam turbine with auxiliaries
1.3.1 General
The steam turbine will be of a tandem compound, single reheat, and axial flow
type with steam exhausting from one double flow low-pressure cylinder to
condenser.
The unit will be capable of producing rated output of 300mw when operating
with rated steam conditions and design ambient conditions.
Main specification
Type: Subcritical, Reheat, Tandem compound, Two cylinder, Double flow,
Condensing
Rated Power (TMCR Condition): 300MW
Rated Speed: 3000r/min
Direction of Rotation: Clockwise viewing from Governing End
Steam Inlet Pressure: 16.7MPa(a)
STEAM INLET TEMPERATURE 538℃
STEAM REHEAT TEMPERATURE538℃
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
33
REGENERATIVE 3H+1D+4L
CONDENSER PRESSURE: 10.05 KPa (a)
FREQUENCY RANGE FOR CONTINUIUS OPERATION: 47.5-51.5HZ
FINAL FEED WATER TEMPERATURE: 275.8℃
LAST STAGE BLADE SENGTH 905mm
ROTOR:
NUMBER 2
TYPE SOLID FORGED TYPE
COUPLING RIGID COUPLED WITH BOLT
CASING: 2 NUMBER , CAST TYPE
1.3.2 Main component (per unit)
One (1) complete combined HP-IP steam turbine.
One (1) complete double flow LP turbine with bottom exhaust.
One (1) set of cross-over piping
Control and protective valve systems including the following.
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
34
A) separate mounted steam chests with two(2) stop-throttle valves and six(6)
governing control valves, each including:
1) Servo-actuator
2) Electrical contacts at each end of each stop-throttle valve
3) Provision for testing while unit is in operation
4) Removable temporary fine mesh and permanent heavy mesh strainers for
each stop-throttle valve
B) Flexible inlet piping between the steam chests and HP turbine casing.
C) Two (2) reheat stop valves and two (2) interceptor valves, each including.
*Actuator
*Electrical contacts at each end of each valve mechanism
*Provision for testing while unit is in operation
*Removable temporary fine mesh &permanent heavy mesh strainers.
D) Piping between interceptor valves and intermediate pressure Turbine
Digital Electrohydraulic (DEH) control system
Emergency trip system including:
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
35
A) Mechanical hydraulic overspeed trip with oil test gauge for local manual
overspeed trip test.
B) Emergency trip system with local and remote testability including:
1) Trip control block
2) Low bearing oil test block
3) Low EH fluid pressure test block
4) Low condenser vacuum test block
5) Electrical overspeed sensing
6)Thrust bearing trip device
7) ETS controller cabinet
8) Operator/test panel
9) Remote operator/test panel
10) High pressure hydraulic fluid supply system which include:
A) Fluid reservoir
B) Fluid supply system components mounted at the reservoir and consisting
of:
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
36
1) AC motor driven variable displacement pumps
2) Suction strainers and pump discharge filters
3) Relief valve
4) Check valve
5) Heat exchangers
6) Appropriate gauges, pressure transmitters, pressure switches
thermometers, thermocouples, and flow meters.
C) Hydraulic high and low pressure accumulators
D) Suitable interlocks and alarms
E) All interconnecting piping between the fluid supply system and the
actuators, stainless steel tubing and manifolds will be used where applicable.
F) Fluid transfer pump
G) Fuller’s earth fluid conditioning unit
Complete lubricating oil system which include:
A) Main oil pump on turbine shaft
B) Oil reservoir of sufficient operating capacity
1) Float-type oil level indicator
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
37
2) High and low level alarm device
3) Top-mounted relief and access doors
4) AC motor driven bearing oil pump
5) DC motor driven Emergency oil pump
6) Oil Ejector
7) Motor-operated vapor extractors
8) Oil strainers located at each motor-driven pump and Oil Ejector suction
and at the oil return to the reservoir
9) AC motor driven seal oil backup pump
C) Twin full-size oil coolers with Interconnecting oil piping and a manual
three-way valve
D) Pressure switches with test valves for automatic starting of the bearing oil
pumps and emergency oil pump
E) Complete interconnecting oil piping to and from all bearings ,oil reservoir
and oil coolers .pressure oil piping in high temperature areas will be guarded
F) Oil demister and exhaust head
G) Bearing lift system for LP bearing
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
38
Gland sealing system ,consisting of the following :
A) Steam sealed glands
B) Pneumatically operated gland steam regulators
C) Manual shutoff and bypass valves for high pressure regulator
D) Manual shutoff and bypass valves for the spill-over regulator
E) Manual shutoff valve for the cold reheat regulator
F) Surface-type gland steam condenser
G) Low pressure desuperheater system
H) Steam seal piping from the regulators to the turbine and from the turbine
to the gland condenser.
I) Gland header relief valve
Turbine drain system including air-operated drain valves and piping from
Exhaust hood spray system including nozzles, piping, pressure switch and
pneumatic-operated control valve for the low-pressure turbine element
Motor-operated rotor turning gear
Protective devices, consisting of the following
A) Turbine exhaust casing relief diaphragms
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
39
B) Exhaust casing high temperature alarm thermocouple
C) Loss of vacuum
D) Loss of governing fluid pressure
E) Low lube oil pressure
Turbine supervisory instruments consisting of following:
A) Recording type
1) Turbine rotor eccentricity
2) Turbine rotor vibration
3) Turbine rotor position
4) Turbine casing expansion
5) Turbine casing and rotor differential expansion
6) Speed and governor valve position
7) Steam and metal temperatures for turbine operation
B) Vibration phase angle meter and selector switch
C) Instantaneous eccentricity run-out indicator
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
40
D) Supervisory indicating panel with lights for alarm signals
Thermocouples consisting of the following:
A) For measurement of turbine steam and metal temperatures for the
purpose of turbine operation
B) For thrust bearing
C) For journal bearings (metal)
D) For each main bearing oil drain
E) For the thrust bearing oil drain
F) For the oil inlet and outlet of the oil coolers
Thermometers, consisting of the following:
A) For each main bearing drain
B) For the thrust bearing drain
C) For the oil inlet and outlet of the oil coolers
Pressure gauges mounted on the equipment ,or loose for purchase is
mounting, for the following
A) Bearing header
B) Main oil pump suction
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
41
C) Main and backup bearing oil pump discharge
D) Emergency bearing oil pump discharge
Miscellaneous instruments, consisting of the following:
A) Electric transmitter for steam seal pressure
B) Electric transmitter for inlet steam pressure
C) Electric transmitter for reheat steam pressure
D) Pressure gauge for the gland exhauster vacuum
Set of lifting gear and special tools and wrenches
Leveling wedges ,seating and soleplates
1.3.3 Description for main components 1.3.3.1 Combined HP/IP Turbine
The combined HP-IP turbine design is based on the latest in design
technologies.
The major design features included are high efficiency reaction blade and
rugged inlet features with low maintenance valves.
The HP-IP turbine is housed in an enclosure which helps reduce the noise
level in the power plant. The enclosure has access doors to allow operating
personnel to enter the enclosure and inspect the HP-IP turbine during
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
42
operation. Large grated openings in the enclosure top provide ventilation. The
enclosure is constructed in several sections, which are mated together to from
the complete enclosure. During turbine maintenance periods, sections of the
enclosure can be removed as needed to provide crane access over the
turbines.
The HP-IP turbine has an outer cylinder made up of two sections joined at the
horizontal centerline. The outer cylinder provides structural support for the HP
and IP section internal stationary components.
The outer cylinder base provides support for the stationary turbine parts .,the
outer cylinder cover can be removed for access to internal parts. The
horizontal joint is a precision-machined surface area on both the cover and
base .the surfaces are bolted together without a gasket to form a metal-to –
metal steam-tight joint
DESIGN FEATURES/BENEFITS
Optimized HP&IP Blade path
The HP and IP blade paths are optimized for each application. This results in
the most efficient blade path for the available space that meets the
mechanical requirements. Many recent advances in blade path design have
been incorporated into this element. The efficiency enhancements
incorporated into the reaction path include:
Overall blade path thermodynamic optimization
Enhanced airfoil design
Improved aerodynamic analysis
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
43
Enhanced sealing
Integral shroud blade for IP
Reduced windage losses and secondary –flow losses
Operating flexibility
This turbine design incorporates into a single unit, the capability for a wide
range of operation strategies. The unit is capable of operating efficiently in
sequential, single, or hybrid valve mode of operation. The turbine is capable of
either two-shift, load follow or some combination of these operating strategies
Components description
The outer cylinder is suspended on two support paws at each end. The
support paws rest on pedestals that transfer the turbine weight to the building
foundation. Large studs through the support paws help keep the turbine from
lifting off the pedestals but allow longitudinal and transverse movement for
thermal expansion. The HP-IP turbine expands about 25mm from the cold to
the hot condition.
The turbine rotor extends through the outer cylinder housing at both ends of
the turbine and gland-sealing system prevents steam leakage into the turbine
room
The rotor is supported on bearings in the pedestal housing at the governor
end and in the bearing house of LP outer cylinder at the generator end
Blade path design
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
44
The HP and IP blade paths are optimized for each application using advanced
high efficiency reaction blade. This results in the most efficient blade path for
the available space that meets our mechanical requirements. The design
process uses new concepts to reduce pressure losses both externally and
internally to the turbine elements. The work split between the control stage
and the reaction blade path have been optimized to maximize overall HP
component efficiency.
HP Rotating Blades
The HP rotating blades will be of the grouped shrouded design. The excellent
mechanical performance of this design results directly from the smaller mass
and the related lower stress levels of the HP blades. The lighter mass, the
thinner shroud and the reduced tip velocity due to the shorter length relative to
the IP blades combine to virtually eliminate tenon creep in HP blade. This
design also assures obtaining the necessary damping effect of shroud contact
which is of a concern in the HP application of integral shroud T-root blades.
The HP blades use “T” blade root design because of its inherent lower steam
leakage characteristics. This is important in the HP blade path where
pressures are higher relative to the IP blade path.
IP Rotating blades
Each integral shroud IP rotating blade is machined from a single piece of
metal.
The elimination of separate shrouds significantly reduces vibratory stress,
high cycle fatigue and the stress concentrations that can be created by riveted
IP tenons. The centrifugal loads created by the massive shroud are now
distributed across the entire cross section of the blade.
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
45
The tips of IP blades in the first stage of the intermediate pressure turbine
must withstand both centrifugal forces and bending forces while operating in
high temperature reheated steam. Those forces which can create creep in the
blade material are not prevalent in HP blades because their shorter length
reduces blade tip velocity. The potential for creep in the integral shroud blades
is significantly less because the maximum steady stress at the intersection of
the shroud and airfoil is reduced by 67% compared to a riveted IP blade tenon.
The improved IP blade design also promotes contact between the shrouds of
adjacent blades ,alleviating vibratory deflection. At the same time, all blades
are designed so that the first mode frequency is above the sixth harmonic.
Full-scale laboratory testing conclusively demonstrated that the vibratory
stresses in the integral shroud IP blade design are 50% lower than those in an
IP riveted blade. The integral shroud IP blade design offers one other
significant advantage: the blades operate with maximum reliability. Because
there are no concealed surfaces, the blades can be thoroughly inspected with
greater ease.
Removable “contoured end wall” nozzle blocks
The nozzle blocks are made from a forged ring using Electro discharge
machining (EDM) to create the nozzle vanes with a contoured end wall .The
contoured end wall minimizes secondary flow (steam swirl), reducing the
secondary flow and turning the flow before it is accelerated greatly reduces
the potential for steam erosion in the nozzle blocks.
HP-IP Rotor
The HP-IP rotor is a CrMoV alloy forged rotor without center bore.The finite
element analysis indicates that rotor creep strength is much low ,so the life of
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
46
rotor is prolonged.
Rotor steeple design
The rugged rotor uses two proven designs to secure the rotating blades: the
“T” root design is used in the HP, and the multiple serration side entry root
design is used in the IP. Both designs have proven to be highly reliable for
their respective applications.
The riveted shroud “T” blade root that is being used in the HP permits more
efficient use of the available area for blade on the rotor, the grouped riveted
shroud design is the best combination for a “T” root has the added advantage
of providing better sealing under high pressure conditions, eliminating
efficiency losses that result from steam leaking through a side entry root.
Stationary blades
All stationary blades feature the twisted blade design. This design offers
substantial efficiency gains over the older designs because the proper foil
orientation is maintained over the entire height of the blade rather than only at
the mean diameter. The use of twisted stationary blades allows the use of
parallel sided rotating blades with minimum incidence .The twisted blades are
both stronger and more efficient than previous. By varying the gauging of the
stationary blade, the stage reactions are more uniform from the base to the tip.
Additionally the increased reaction at base in conjunction with the reduced
reaction at the blade tip reduces secondary blades
Twisted stationary blades are most frequently used in low-pressure turbine
because of the sizable difference between the base and tip velocities. When
fuel prices were low ,the use of twisted stationary blades in HP/IP turbines
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
47
was difficult to justify economically. Today high fuel prices and improved
manufacturing processes make the extensive use of twisted stationary blades
in the HP/IP section very cost effective
Rotor balance provisions
The rotor has provisions for balance holes at six locations. three locations are
for factory balance and three are for field balance of the rotor . At each field
balance location, there is a series of equally spaced holes for balance plugs
for rotor balancing . The factory balance locations are drilled only if needed to
remove metal to balance the rotor , Before shipping ,the rotor is balanced in
the factory at operating speed . Therefore, the rotor should need only
minimum touchup balance at initial installation
Rotor thrust balance
All pressure forces that could cause a turbine component to move in the axial
direction are called thrust forces. Thrust forces are produced by the pressure
drops as the steam moves through the blade path. These axial pressure drops
exert thrust forces on the rotating parts. Thrust forces on rotating parts
attempt to move the rotor in the direction of steam flow.
The HP-IP turbine is an asymmetrical, opposed-flow element. Steam passes
first over one set of blades ,then another in series . This causes thrust forces
in opposite directions in the HP and IP sections of the rotor.
The two opposing forces acting on the rotor cancel each other if the two are
equal .If one force is greater, the difference between the two is the resultant
thrust force on the rotor toward the lower opposing force. Several features are
included in the turbine design to help control and balance the opposing thrust
forces as closely as possible.
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
48
The following major features are provided to help balance the various
opposing thrust
Rotor thrust balance pistons (areas)
Pressure equalizing flow passages
Thrust bearing
The first two features allow use of a relatively small thrust bearing for the
turbine generator
Rotor thrust balance pistons
The two major sources of thrust forces on the rotor are the HP blade area and
the IP blade area .To balance the thrust forces on both sets of blade, the rotor
body is designed with certain opposing areas of known cross section exposed
to known pressures.
These areas provide a predictable force to resist or help balance the thrust in
the blade path. Such an area generally can be thought of as a balance
piston .The forces acting on it are similar to those in a piston engine.
The HP-IP rotor has three balance pistons that are integral parts of the rotor,
The diameter of each of the three balance pistons is sized so that most of the
axial thrust is balance out. Generally, the thrust is balanced when the
diameters of the balance pistons are nearly equal to the average diameters of
the corresponding blade groups.
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
49
The rotor balance pistons are subjected to the same pressure differentials as
the sections they balance. The HP and IP blade paths are independently
balanced by their own dummies (thrust pistons ) opposing the blade path .The
HP blade thrust is balanced out by the HP balance piston .The IP blade thrust
is balanced out by IP balance pistons . Buildup of excessive deposits in the
turbine could eventually affect this balance of opposing forces.
Pressure equalizing flow passages
To provide the correct balancing forces, balancing areas must be subjected to
the same pressure differentials as the sections they balance .Three pressure
equalizing passages allow this to occur in the turbine.
One pressure equalizing passage is actually the HP impulse chamber. Here,
the control –stage exit pressure becomes the inlet pressure for the HP blade
path and HP balance piston.
The second pressure equaling passage consists of two equilibrium pipes
these pipes connect the IP exhaust area at the generator end of the turbine
and the cavity between the HP exhaust dummy ring and the inner gland at the
governor end. The equilibrium pipes are routed outside the outer cylinder and
equalize the pressure on both ends of the rotor .
Outer cylinder
The outer cylinder of the HP-IP turbine is constructed in two parts (cover and
base). The base of the outer cylinder supports the entire HP-IP turbine
cylinder and it is larger than the cover .The outer cylinder is not only a
structural support and housing but also a pressure vessel subjected to steam
pressures and thermal loads
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
50
Steam turbine cylinders have widely varying zone temperatures, so metal
temperature gradients between zones also vary widely. The outer cylinder is
covered with insulation to help reduce heat loss and to help minimize radial
temperature gradients.
The HP-IP outer cylinder provides structural support for the HP&IP blades
rings, HP-IP and HP exhaust glands
The HP-IP turbine has inner and outer glands at both the governor end
generator end of the outer cylinder .The glands confine the steam in the
turbine and prevent steam leakage to the atmosphere and air leakage into
turbine.
Thermocouples
Turbine temperatures are measured by thermocouples. The thermocouples
are installed in special protecting tubes that penetrate the cylinder wall and
welded to the cylinder .The HP-IP cylinder is manufactured with thermocouple
wells installed at standard locations on the turbine, based on the history of
turbine temperature monitoring needs .
1.3.3.2 Double flow low pressure turbines
The LP turbine element is of a double-flow design .The primary design
features of this design include lashing blades ,integral shroud blades ,and a
mono block rotor forging ,this turbine element is capable of frequency
operation up to 50Hz+1.5,-2.5Hz,continuous high load operation up to
backpressures of 5.5”HgA and cyclic operation up to 10000 start –up/stop
cycles
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
51
Design features and benefits
Fully integral monoblock rotor body
Benefits :
*No disk-to –shaft inter faces
*No shrunk –on coupling
*Cyclic duty capability
*Complete system torsional and dynamic stability analysis and compatibility
High efficiency integral shrouded blades: benefits:
·Improved efficiency
·Cyclic duty capability of over 10000 cycles
·Reduced maintenance through elimination of rivets and tenons
·Increased inspection intervals
Lower blade excitation high efficiency blading of last three stages: benefits :
·Improved efficiency
·Cyclic duty capability of over10000 cycles
·Reduced maintenance through elimination of rivets and shroud
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
52
·Capability of operation at up to 5.5in Hg backpressure.
·Enhanced corrosion resistance
Main components description
Rotor and steeple designs
The rugged fossil LP turbine rotor has low operating stresses and has integral
couplings .This design allows for rugged one – piece blade in combination
with low stress steeple designs
This rotor strength provides greater resistance to stress corrosion cracking
one-piece rugged blade reduces the vibratory load transfer to rotor steeples
and also help eliminate steeple high cycle fatigue.
Side entry blade roots are used for attaching all of the rotating blade. This
design maximizes the contact area between the blade root and rotor steeple
and minimizes stresses in both the rotor steeple and blade root serration .The
large blades have curved roots whereas, the small blades have straight roots .
The side entry steeple is located above the bulk lf the rotor body, thereby,
steeple thermal transient stresses are reduced rotor stress concentrations at
the steeples have been significantly reduced through an effective steeple
contour developed through finite element analysis.
LP Rotor Forging Manufacture
LP rotor forgings are made of 3.5%NiCrMoV alloy steel having high impact
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
53
strength.
Inlet flow guide
The inlet flow guide is a cylindrical component located at the center of the
turbine and consists of 180 segments. This construction allows easy assembly
and minimizes thermal stresses .The inlet flow guide improves the turbine
efficiency by reducing inlet pressure drop and leakage losses across the first
row of stationary blades. Steam leakage is minimized by zero-leakage spring-
back seals at the governor and generator ends.
Exhaust flow guides
Each LP turbine has exhaust flow guides, one at the governor end of the inner
cylinder and one at the generator end, each exhaust flow guide is constructed
in two halves .The halves form a complete ring when installed to the inner
cylinder structure .The flow guide is designed to utilize the velocity leaving the
last row blade to experience a pressure recovery .this will allow the steam to
expand to a pressured bellow the condenser pressure and the blade to
generate additional work .
LP outer cylinder
The LP turbine rotor is housed in an outer cylinder, which functions as an
airtight containment vessel. The carbon steel outer cylinder structure provides
support for the LP turbine inner components and transfers the loading to the
foundation .The outer cylinder’s main function is to convey the exhaust flow, at
nearly ideal vacuum conditions from the last row blade to the condenser as
efficiently as possible .It is designed to withstand normal and emergency
structural loads without undergoing deflections great enough to disturb the
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
54
running clearances. The outer cylinder is composed of two parts-the outer
cylinder cover and the outer cylinder base .Because of the large size of the LP
turbine, the outer cylinder cover and base are each made in sections to
meet ,transportation limitations .The segments are joined at vertical and
horizontal joints to made a steam-tight unit .
The outer cylinder base includes a support foot structure on all sides .The
support foot rests on seating plates, which are grouted on the foundation. The
bottom of support foot which rests on the seating plates, is the turbine
baseline, the top of the support foot structure is the turbine horizontal
joint .The base structure below the support foot acts as the exhaust opening
for the LP turbine .The fabricated-steel structure has a minimum of internal
support braces, to help limit disturbance in the flow path and allow smoother
flow through the structure.
Two pads on each side of the outer cylinder base structure support the inner
cylinder and related stationary turbine parts
The fabricated-steel outer cylinder cover can be removed for access to
internal turbine parts for maintenance. Each outer cover also has four
manholes, two on each side, to allow access for internal inspection without
removing the cover.
The turbine is protected from overpressure by two breakable diaphragms in
the end sections of the outer cylinder cover. These diaphragms are designed
to rupture if the pressure in the outer cylinder reaches 0.34 to 0.55bar (5to
8psig).
LP Inner Cylinder.
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
55
The inner cylinder provides the support structure along the blade path for the
inlet flow guide, stationary blades and exhaust flow guides .The inner cylinder
consist of cover and base sections bolted together at the horizontal joint.
The fabricated LP inner cylinder is designed using the experience and
information gained from continual application of the latest technology and
design techniques which specifically address the issues of cycling, moisture
and hard particle erosion and reliability.
Three-dimensional finite element analysis is used as an integral part of the
design process, an example of which is shown below.
Three-dimensional finite element analysis has allowed design engineers, by
using more accurate calculation of stresses, to quantify the deflections that
the inner cylinder experience during various transient events. This allows for
structural streamlining of the inner cylinder design which eliminates the
negative aspects of differential thermal expansion .It also allows more
accurate prediction of thermal gradients and their effect on cylinder
stresses .The overall benefits of this design process include improved LP
reliability, maintainability. and efficiency .The LP inner cylinder is fabricated
out of carbon steel plate
The inner cylinder is structurally optimized to eliminate the potential for
cylinder distortion, and joint and bolt distress caused by thermal expansion
and contraction .The fabricated design improves the fatigue life of the inner
cylinder because of the appropriately sized cylinder walls .The fabricated
design also provides the correct amount of flexibility to better accommodate
thermal transients
Rotor glands
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
56
The rotor glands at the governor and generator end of LP turbine are alike.
They are bolted to the outer cylinder to seal the rotor openings .The glands
are part of the gland steam sealing system, which maintains the correct
sealing steam flow to the glands and helps keep air out of, and main steam in,
the turbine. Each rotor gland consists of a gland base, gland cover, four seal
ring retainers, four seal rings and the support keys ,screws ,and dowels
needed to assemble the major parts .
Rotor balance provisions
The rotor has balance provisions in the form of three drilled and tapped
balance planes and two separate drill balances .The drilled and tapped planes
are located at the ends and center of the rotor. Each end of the rotor has a
drill plane. Shop balance is completed using the three drill and tapped balance
planes .A minimum number of balance plugs is always used for each plane .
Excess balance corrections are made by drilling .The drill and tap planes are
designed with sufficient balance capability to permit the normal shop balance
while reserving additional field balance capability .Access holes in the outer
cylinder allow balance plugs to be installed in the field in the two ends of the
rotor ,when required .A record of all balance plugs installed or removed from
the rotor must be kept throughout the service life of each rotor .
Stationary blade
Stationary blade upstream of the L-1stage are of the welded diaphragm type
configuration. The L-0 and L-1 stationary rows are a segmental type
construction.
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
57
Diaphragm blade is inherently easier to install and maintain than the existing
riveted shrouded blade .The existing stationary design uses individual
stationary blades fitted one by one into the blade ring grooves. These blades
are then shrouded and riveted and caulked into place .In contrast, a half ring
diaphragm assembly is simply slid into the blade ring and locked. Should
maintenance be necessary, the diaphragm assembly can be easily removed
and serviced.
Blade path sealing
In the Rugged design ,leakage loss is reduced considerably .STC has used
two blade path sealing features to improve long-term efficiency .
Honey comb seals
Honeycomb seals are installed over all freestanding blades, (except over the
last stage which utilizes and exhaust flow guide) .STC has a broad experience
base with this design .The individual honeycomb cells collect moisture which
is removed by annular grooves in the backing rings. This type of seal
enhances the moisture removal capability in the blade path.
Springback seals
Springback seals are be used in the stages upstream. They reduce the
potential for hard seal rubs, therefore, seal clearances are maintained and
long term efficiency is enhanced .
Crossover pipe adapter
The crossover pipe adapter extends from the steam inlet opening of inner
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
58
cylinder to the crossover pipe. The cross over pipe adapter is bolted directly to
the steam inlet flange of inner cylinder
Erosion resistant design features
Operating experience has proven that moisture droplet and hard particle
erosion of LP turbine blades adversely affects thermal performance and unit
availability due to increased maintenance requirements. While it is recognized
that moisture and hard particle induced erosion cannot always be entirely
avoided, STC fully understands this phenomena and has incorporated design
features in the blade path to minimize its effects .Thus ,in an effort to increase
unit availability and sustain unit thermal performance ,STC has enhanced the
erosion resistance of the LP turbine by including the following erosion
resistant features :
1) Addition of Moisture Collectors Throughout The Blade Path.
This feature reduces the amount of moisture available for impingement on
rotating and stationary components
2) Protection of L-0 R Blades (last stage blades in LP cylinder) With Stellite
Shields, use of stellite shields on a blade in leading edge has proven to be the
most off frequency operation.
The primary operating consideration of an LP turbine under load at either
greater or less than normal system frequency is the protection of the long
tuned blade so that harmonic resonance do not occur .In the design
verification process, great care is taken to properly tune the tapered and
twisted blades that constitute the last several LP stages.The result of our
improved manufacturing techniques ,combined with our more rugged tuned
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
59
blades is a greater off frequency capability.
1.3.3.3 Gland Sealing System
The function of the rotor gland sealing steam system is to prevent the leakage
of air into or steam out of the turbine cylinders along the rotor and valve stems.
The system consists of the following major components:
Gland condenser
Safety valves
Desuperheaters
Steam strainers
Interconnecting piping
The regulating valves supplied for this system consist of HP gland steam
supply, Cold reheat steam supply and spillover to condenser. During lower
loads, sealing steam is controlled by the Cold Reheat gland steam-regulating
valve. Finally, at higher turbine loads, pressure in the gland steam system is
controlled by the Spillover regulating valve.
The gland condenser is a surface type heat exchanger of shell and tube
construction .It prevents the escape of sealing steam to atmosphere from the
HP, IP and LP turbines by condensing the steam that leaks off from the zone
between the air seal and outermost steam seal of each steam gland of the
turbine .The condenser also helps to seal the main steam valve stems by
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
60
maintaining a slight vacuum at the valve stems. Condensate is circulated
through the tubes to condense the gland and valve stem leak off steam. After
almost all the steam is condensed, air, noncondensible vapors and any
uncondensed water vapor are removed by an air exhauster mounted on the
gland condenser .
A desuperheater is used to lower the temperature of the steam required for
sealing the LP turbine glands. The desuperheater consists of a reduced
diameter pipe section into which a spray nozzle has been inserted .The flow of
cooling water is controlled at the spray nozzle by a diaphragm control valve
responsive to an air signal from a temperature controller which senses the
temperature at one of the LP glands.
Two safety valves are required in the gland sealing system to prevent the
occurrence of excessive pressure .The safety valve is a direct pressure
actuated relieving valve characterized by pop action.
Steam strainers are mounted in each of the gland steam supply pipes for the
HP, IP and LP turbines .the strainers are positioned to filter the steam
supplied to the turbine glands.
1.3.3.4 Turbine Drain System
The function of the drain system is to prevent ingress of water into the turbine
and the safe removal of water from steam turbine .The system consist of air-
operated drain valves and drain piping .The drain valves for the turbine are
mounted directly in the drain piping of the following drains :
Main Steam inlet Drains
HP-IP Cylinder Drains
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
61
Reheat steam inlet drains
All these drains are opened or closed by air-operated drain valves that are
automatically or manually controlled by the operator .On loss of supply air
resulting from shutdown, trip, or loss of electrical signal to the solenoid valve
in the supply line, the drain valves are arranged to open to protect the turbine.
1.3.3.5 Exhaust Hood Spray System
High exhaust temperature of LP turbine must be avoided to minimize chances
of contact between stationary and rotating parts from thermal distortion or
excessive differential expansion. Such contact above turning gear speed can
cause serious damage resulting in forced or extended outages. The exhaust
hood spray system is turned on automatically as the rotor speed reached
2600 rpm. The spray turns off automatically at approximately 10-15% rated
load. The exhaust hood spray system consist of an exhausted hood spray
control station that supplies condensate to nozzles mounted two exhaust flow
guide assemblies for the LP turbine.
1.3.3.6 Bearings
The HP-IP turbine bearings are of the four-tilt-pad design, the LP turbine
bearings are of the sleeve design. These bearings are inherently stable and
are not susceptible to oil whip. All bearings area self-aligning type designed to
withstand loads transmitted in both normal and unusual opening condition.
Thrust bearing will be flexible pad type (Kingsbury). The thrust bearing is
installed in an adjustable housing which allows the axial position the rotor
adjusted during maintenance outages.
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
62
1.3.3.7 Rotor turning gear The rotor turning gear is used to rotate the rotor at a low speed while the
turbine is shut down, so as to reduce a minimum the distortion of the rotor due
to uneven cooling of the turbine parts. In general, it is recommended that the
turning gear be used continuously during shut down periods. Its use will vary,
depending upon the size and type of turbine and the local operating conditions.
In general, it is recommended that the turning gear be used continuously
during shut down periods. If the shutdown period is to be of long duration ,the
turning gear should be operated for a sufficient period to prevent distortion
before the rotor is brought to rest.
In every case, the turning gear should be operated for a short time before
starting the turbine with steam. The best procedure for any particular unit can
be determined only by actual operating experience and the shaft deflection
shown by the truth indicators.
The turning gear motor mounted on the housing is so connected through
gears and pinions to the pinion that it is capable of turning the rotor at a speed
of approximately 3 rpm.
Its principle parts are the motor, the train of gears and pinions to reduce the
speed and the engaging lever with the necessary linkage for engaging and
disengaging the pinion with the coupling spacer ring. Turning Gear can be
engaged and disengaged automatically and manually.
To Engage the Automatic Turning Gear
1) When the Turbine is Being Shut Down
Turn the control switch to the automatic turning gear position to initiate the
automatic sequence. The control switch is normally left in this position
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
63
thereafter.
With the control switch in the " Auto" position and when the speed of the rotor
decreases to approximately 200 rpm, the automatic sequence circuit will be
activated, thereby supplying sufficient lubricating oil to the turning gear. When
the rotor comes to rest the pressure switches shown in the " Zero Speed
Indicator" leaflet will close. The air supply valves will be energized and engage
air will be supplied to the engaging mechanism.
With the engage air on, the air cylinder will move the turning gear lever un-
til tooth contact is made between the pinion and the coupling spacer. At this
point the operating lever will stop moving, however, the air cylinder will
continue to move and compress the spring of the elastic link. This will operate
the switch, starting the turning gear motor. If the pinion is not fully engaged it
will slip one tooth and become engaged.
Following engagement, the rotor will turn at turning gear speed, which will
cause the zero speed indicator pressure switches to open and shut off the
engage air. The unit is now ready for extended turning gear operation.
To Disengage the Automatic Turning Gear
2) When the Turbine is Being Started Up
As the speed of the rotor increases above the speed of the turning gear, the
pinion will be disengaged automatically.
As the operating lever is moving toward the disengaged position, the switch
will close and disengage air will be supplied to insure total disengagement.
When the operating lever reaches the total disengaged position, a limit switch
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
64
will shut off both the turning gear motor and the disengage air. After a speed
rise of approximately 200 rpm,the automatic sequence will be deactivated, to
isolate the turning gear from operation and shut off the turning gear lubricating
oil. All turning gear operations will then be complete.
The "Control Circuit" is capable of being transferred from " Automatic" to "
Manual" during any phase of the operation.
1.3.3.8 Lubrication Oil System Introduction
The Lubrication Oil System furnished for this unit provides two backup
sources of seal oil for the hydrogen seal oil system; provides a medium for
operation of the mechanical overspeed trip device; and provides oil to
lubricate the turbine and generator bearings, the thrust bearing, and the
turning gear. The system consists of several major components listed below.
1.3.3.8.1 Lubrication Oil Reservoir
The lubrication oil reservoir is a large carbon steel tank in which the lubrication
oil is stored. The reservoir is usually located below the centerline of the
turbine-generator unit. From the reservoir, the oil pumps furnish the required
amounts of oil to satisfy the various oil requirements ,and since the lubrication
system is a closed system, all oils returned to the reservoir. Mounted on the
top of the reservoir are the auxiliary motor driven pumps, vapor extraction
system, terminal box, heaters, level alarms, etc. Inside the reservoir, the
piping connects the discharges of the various pumps to the appropriate oil
header supply piping. Check valves prevent backflows from the system. An oil
ejector mounted below the oil level in the main oil pump discharge piping,
utilizes high pressure oil to pick up oil from the reservoir when the unit is
operating at or near rated speed. Strainers on the oil ejector intake, the
bearing oil pump suction, and in the return piping help to keep contaminants
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
65
out of the system. The reservoir is provided with access openings in the top
and with a drain in the bottom.
1.3.3.8.2 Main Oil Pump
The main oil pump is a volute type, centrifugal pump mounted on the turbine
rotor in the governor pedestal. It has a large capacity and a stable discharge
head. It has a large capacity and a stable discharge head. At or near rated
turbine speed, the main oil pump supplies all the oil requirements of the
lubrication system, and in addition, provides two sources of back up for the
hydrogen seal oil system of the generator. The main oil pump is not self-
priming and must constantly be supplied with oil under pressure. During
starting and shutdown periods, this is done by the auxiliary oil pumps. At or
near rated speed, priming oil is supplied by the oil ejector as described in the
leaflet covering of the lubrication oil supply system. The main oil pump
discharge is piped back into the reservoir where it is connected to the oil
ejector, inlet and to the HP Seal Oil Backup Header from which the
Mechanical overspend and Manual Trip Header is orificed.
1.3.3.8.3 Auxiliary Oil Pumps
The bearing oil pump is an AC motor driven, vertical pump mounted on top of
the reservoir. It is used during start-up and shut-down procedures and also
serves as a backup to the main oil pump during contingency conditions. It is
capable of supplying all the LP seal oil backup and bearing oil requirements.
During normal operation at rated speed, the bearing oil pump is off and the
main oil pump supplies all of the oil requirements. The bearing oil pump is
controlled by a pressure switch that senses the bearing oil pressure. If the
bearing oil pressure decreases to 0.77-0. 84bar(g) such as occurs during a
shutdown or contingency condition the bearing oil pump will turn on and bring
the pressure back up to requirements. However the pump will not
automatically shut off on rising pressure and must be turned off manually from
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
66
the control. During start-up procedures the bearing oil pump is put into service
before the unit goes on turning gear and is not taken out of service until the
main 0il pump is capable of satisfying all of the oil requirements
(approximately 90% of rated speed).
The emergency oil pump is identical in construction and operation to the
bearing oil pump except that it is operated by a DC motor powered by station
batteries, and the controlling pressure switch' s set point is below the set point
of the pressure switch which controls the bearing oil pump. During start-up
procedures the emergency oil pump is put into service after the bearing oil
pump establishes sufficient bearing oil pressure. The emergency oil pump' s
control switch is then set on "Automatic," and the pump will turn on if the
bearing oil pressure decreases to 0.70-0.77bar(g). Thus, the emergency oil
pump serves as a backup to the bearing oil pump and is the final backup to
the bearing oil system. The station batteries are sized to provide sufficient
power to operate the pump during a normal coast down, and it is imperative
that the batteries are kept sufficiently charged to maintain this capability.
CAUTION: An insufficient charge on the batteries may not allow the
emergency oil pump to operate properly thereby resulting in an insufficient
supply of lubricating oil to the bearings. This will result in serious damage to
the bearings, journals, and associated components.
The seal oil backup pump is an AC motor driven, horizontal pump mounted on
top of the reservoir. It provides oil to the HP Seal Oil Backup Header and is,
used anytime the main oil pump cannot satisfy the HP seal oil requirements,
including the requirements of the Mechanical Overspeed and Manual Trip
Header. During normal operation at rated speed ,the seal oil backup pump :is
off, and the main oil pump supplies all of the oil requirements. The seal oil
backup pump is controlled by the same pressure switch that controls the
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
67
bearing oil pump by monitoring the bearing oil pressure. If the bearing oil
pressure decreases to 0. 70- 0. 77bar (g) such as occurs during a shut-down
or contingency condition, the seal oil backup pump automatically starts and
brings the HP Seal Oil Backup Header up to the required pressure. The pump
will not stop on rising pressure, however, and must be turned off manually
from the control room. During start-up procedures the seal oil backup pump is
put into service before the unit is started and should not be taken out of
service until the main oil pump is capable of satisfying all of the oil
requirements (approximately 90% of rated speed). A relief valve in the
discharge piping prevents overpressures.
1.3.3.8.4 Jacking Oil System
The bearing jacking oil system, which is used during a turbine start-up or
shutdown, prevents turbine damage and ensures a smooth transition to
turning gear operation.
1.3.3.8.5 Oil Coolers
The temperature of the lubrication oil is regulated by the oil coolers. Two oil
coolers are normally provided. Under normal operating conditions, one is in
use and the other is on a standby status ;although in some special conditions,
both coolers may be in service simultaneously. The coolers are connected to
the discharge sides of both the bearing oil pump and the oil ejector; thus the
bearing oil, no matter what the source, passes through the coolers before
flowing to the bearings. The oil is circulated within the oil cooler shell around
the tube bundles while the cooling water passes through the tubes. The oil
flow to the coolers is controlled by a manually operated three-way valve which
directs the flow to either cooler and permits switching coolers without
interrupting the flow of oil to the bearings. The oil inlets to the coolers are
connected through a crossover pipe and an interchange valve which permits
the inactive cooler to be filled with oil and ready for immediate operation. The
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
68
flow of water to the coolers is adjustable by means of a manually operated
valve in the water supply liner hence the temperature of the oil leaving the
coolers is also adjustable. The valve is normally adjusted to provide an oil
temperature of 60℃. 43℃-49℃ measured at the oil cooler discharge.
1.3.3.8.6 Emergency Trip Functions
Lubrication oil is used as the control medium for the interface-diaphragm valve.
Mounted on the governor pedestal the interface-diaphragm valve provides an
interface between the mechanical overspeed and manual trip portion of the
lubrication oil system and the autostop emergency trip portion of the control
system. Lubrication oil from the Mechanical overspeed and Manual Trip
Header supplied to the diaphragm valve acts to overcome a spring ~rce to
hold the valve closed and thereby block a bath to drain of the fluid in the
Autostop emergency Trip Header. Any decay in the mechanical Overspeed
and Manual Trip Header Pressure, such as could be caused by either a
manual trip or an overspeed trip, allows the spring to open the interface-
diaphragm valve releasing the emergency trip fluid to drain and tripping the
turbine.
The condition of the lubrication oil system's bearing oil supply is monitored by
the emergency trip system. Four pressure switches (63/LBO) monitor the
condition of the Bearing oil Header. If the header pressure decreases to the
set point contact closures from the pressure switches cause the autostop trip
(20/AST) solenoid valves to open and trip the turbine.
1.3.3.9 Lubrication Oil Supply System
1.3.3.9.1 General Function And Arrangement
The function of the lubrication oil supply system is to provide lubrication to the
turbine and generator main bearings, to provide lubrication to the thrust
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
69
bearing and turning gear, to provide oil for sealing the hydrogen seal oil
system and to provide a medium for the operation of the mechanical
overspeed trip mechanism.
The lubrication system consists of a turbine shaft driven main oil pump, oil
coolers, a vapor extraction system, an oil reservoir which includes an oil
ejector, motor driven oil pumps ,strainers ,heaters ,filters, etc. , various trip
and control devices and the interconnecting piping.
NOTE: he settings, pressures, and alarm points included in this leaflet are
approximate values.
1.3.3.9.2 Lubrication Oil Supply System
1.3.3.9.2.1 Oil
The oil used in the lubrication system must be a refined mineral oil of the
highest quality and uniformity and must contain additives to inhibit corrosion
and oxidation. Also, it must not contain any substances that will interfere with
the lubricating properties or will be detrimental to the oil or to the metals with
which it comes in contact.
It must be recognized that the oil characteristics require special considerations
to maintain the integrity of the oil and thereby the integrity of the lubrication
system components and the lubricated turbine components. Some of the
essential considerations are oil cleanliness, the physical and chemical
characteristics, proper storage and handling, and the proper method of adding
oil. A comprehensive program should be developed to assure that the oil and
the system are properly maintained and all harmful contaminants are avoided.
This is essential to maximizing the life of these components and assuring
trouble free operation. Harmful contaminants can result in damage to the
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
70
bearings ,seals ,and other vital components.
The oil should not be circulated in the system if its temperature is below 10℃
at the oil reservoir. Also, if the temperature of the bearing oil Supply cannot be
regulated to produce a bearing oil temperature of less than 82.2℃ at the
discharge of the hottest bearing, the unit should be tripped until the oil
temperature can be reduced and maintained in the proper temperature range.
1.3.3.9.2.2 Supply System Equipment
The lubrication oil supply system consists essentially of the following items:
1) One oil reservoir of 25 m3 capacity constructed of carbon steel and usually
located below the elevation of the axial centerline of the turbine-generator unit.
Two access openings on the top of the reservoir are fitted with gaskets and
manhole covers. Safety bars traverse the covers and are secured to mounting
blocks welded to the reservoir shell. The bottom of the reservoir contains a
flanged drain hole which is plugged during shipment but which may be
connected to the Purchaser' spiping system at his discretion.
2) One turbine shaft driven main oil pump is volute type ,centrifugal pump
mounted horizontally on the turbine extension shaft in the governor pedestal.
The impeller is not self-priming and must be supplied with oil under pressure
during start-up and shutdown periods. The suction piping extends down
through the top of the reservoir and is connected to the oil ejector discharge.
The main oil pump discharge is piped back into the reservoir where it is
connected to the oil ejector inlet and to the HP Seal Oil Backup Header. When
operating at normal speed, the main oil pump supplies all of the oil
requirements of the turbine generator, including the Bearing Oil Header, the
Mechanical Overspeed and Manual Trip Header,the HP and LP Seal Oil
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
71
Backup Headers, and the boiler feed pump control oil and lubrication oil
system headers on units with combined lubrication system.
3) One AC motor driven seal oil backup pump(SOB) mounted on top of the
reservoir. The SOB is a horizontally mounted, double helical gear, rotary type
pump designed for continuous duty. It is securely bolted to the top of the
reservoir and is connected to the AC motor with a rigid coupling. The suction
side of the pump is connected to piping that extends down through the top of
the reservoir to a point below the oil level to insure continuous positive suction.
The discharge side of the pump is connected to piping that also extends down
into the reservoir where it is connected to the HP Seal Oil Backup Header
piping. This is part of the main oil pump discharge (oil ejector inlet side) piping.
One check valve prevents backflow into the pump from the system, and
another prevents the pump discharge from flowing through the oil ejector. An
adjustable relief valve in the discharge piping inside the reservoir above the oil
level limits the discharge pressure to 8.08-8.78 bar (g). This relief valve is
accessible by removing an access cover in the top plate. The SOB pump is
used on start-up and shutdown when the main oil pump' s discharge pressure
is low and cannot supply all of the oil requirements. The SOB is controlled by
a pressure switch, 63/BOP, and by a three-position ( ON, OFF,AUTOMATIC)
switch mounted in the control room.
4) One AC motor driven bearing oil pump (BOP) mounted on top of the
reservoir. The BOP is a vertically mounted, centrifugal type pump designed for
continuous duty. The pump is completely submerged in the oil and is driven
by a vertical motor through a flexible coupling. A thrust bearing on the motor
support absorbs any hydraulic thrust and supports the weight of the rotor.
Provisions integral to the motor support isolate the motor from rising oil vapors
and prevent foreign matter from leaking into the reservoir. The BOP draws oil
through a strainer at the bottom of the pump and discharges it through piping
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
72
to the main oil pump suction, through the oil coolers to the Bearing Oil Header,
and to the LP Seal Oil Backup Header. The BOP is used on start-up and
shutdown when the main oil pump' s discharge pressure is low. The BOP is
controlled by a pressure switch 63/BOP,and by a three position (ON, OFF,
AUTOMATIC) switch mounted in the control room. A swing check valve
prevents back flow from the system.
5) One DC motor driven emergency oil pump (EOP) mounted on top of the
reservoir. The EOP is a vertically mounted, centrifugal type pump designed for
continuous duty. It is of identical construction to the BOP described above and
serves as a backup to the BOP. The EOP is used in emergency conditions
such as when AC power is lost or whenever the bearing oil pressure cannot
be maintained no matter what the reason. It is powered by the stationr s
battery system and is controlled by a pressure switch63/EOP,and by a three-
position (ON, OFF, AUTOMATIC ) switch mounted in the control room. See
the operation and pressure switch description sections of this leaflet. A swing
check valve prevents backflow from the system.
6) One oil ejector mounted in the piping below the oil level. The oil ejector
consists, essentially, of a nozzle, pickup chamber, throat, and a diffuser. The
nozzle inlet is connected to the main oil pump discharge which provides
motive oil. The oil passes through the nozzle, is directed through the pickup
chamber into the ejector throat, and finally passes into the diffuser. As the oil
passes through the nozzle ,its velocity increases. When this high velocity oil
passes through the pickup chamber, it creates a low pressure zone in the
pickup chamber and causes the oil from the reservoir to be drawn into the
pickup chamber and be carried with the high velocity oil into the ejector throat
area. The quantity of oil picked up from the reservoir is approximately equal
to the quantity provided to the nozzle inlet by the main oil pump. After passing
through the ejector throat area, the oil enters the diffuser where the oil velocity
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
73
is converted to pressure. The oil is then piped through the oil coolers to the
Bearing Oil Header, to the main oil pump suction, and to the LP Seal Oil
Backup Header. A swing check valve, mounted after the diffuser, prevents
backflow from the system. A cheek plate mounted above the pickup chamber
inlets from the reservoir, prevents a backflow into the reservoir when the
bearing oil pump is running. A removable perforated, steel plate(mesh)
strainer mounted on the ejector' s suction side, prevents foreign matter from
entering the ejector.
7) One motor driven vapor extraction system mounted on top of the reservoir.
The vapor extraction system consists of a demister, an adjustable "blast gate"
butterfly valve, an AC motor driven turbo-blower, a check valve mounted in
the Purchaser’ s piping on the discharge side ,and the interconnecting piping
between the reservoir and the blower. The turbine blower is a single stage gas
blower designed for continuous operation. It is securely bolted to the top of the
reservoir and the motor is mounted on the side of the blower. The manually
adjusted butterfly valve is mounted on the suction side of the blower and
regulates the flow through the blower. The demister is mounted in the suction
side piping, and it extracts entrained liquid from the vapors flowing through it.
The extracted liquid is piped to drain. The suction piping extends through the
top of the reservoir to the area above the oil level where vapors accumulate.
The blower discharge piping is connected to the Purchaser' s piping which is
usually vented to the atmosphere. When operating, the blower creates a
slightly negative pressure in the suction side piping and the interconnected
parts of the oil reservoir and oil drain piping. This draws the oil vapors up
through the demister where any oil droplets are removed. After passing
through the demister, the vapors are discharged through the blower.
8) One 150 mesh strainer mounted in the oil return trough inside the reservoir.
The strainer is cylindrical and is made with perforated metal plate overlaid by
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
74
metal screen. It fits down into an opening cut into the bottom of the trough.
The return oil in the trough is gravity fed into the top of the strainer,and it
passes through the bottom and sides of the strainer into the reservoir. The
strainer is fitted with a handle on top and can be removed through one of the
top access openings without disturbing the adjacent components. If removed
for any purpose ,the strainer should be thoroughly cleaned before returning it
to the reservoir. The strainer may be replaced while the unit is in service
however ,the unit should not be operated any longer than absolutely
necessary without the strainer in place and properly sealed with the gasket.
To minimize the period of time that the strainer is out, a clean, spare strainer
and gasket should be readily available.
9) Two oil coolers mounted in the vicinity of the reservoir. The oil supplied to
the Bearing Oil Header, no matter which pump provides the oil,is passed
through a cooler to regulate its temperature. The oil is circulated within the oil
cooler shell around the tube bundles while the cooling water passes through
the tubes. Only one oil cooler is normally in service at any time with the other
one on inactive status. The oil flow to the coolers is controlled by a manually
operated three-way valve which directs the flow to either cooler and permits
switching coolers without interrupting the flow of oil to the bearings. The oil
inlets to the coolers are connected through a crossover pipe and an
interchange valve which permits the inactive cooler to be filled with oil and
ready for immediate operation. Each oil cooler shell is vented back to the
reservoir through piping which enters the reservoir through the top and
extends to the area above the normal oil level. A vented sight flow gauge in
each line enables the operator to determine if oil is flowing through the cooler.
Note that with the inter change valve open ,both sight flows are full of oil.
10) Two immersion type heaters, mounted on the side of the reservoir, heat
the oil as required to maintain a sufficient temperature. The heaters are
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
75
controlled by a three position (ON ,OFF,AUTO) switch which is usually located
near the reservoir. In the ON position, the heaters are energized continuously.
Normally, however, the switch is in the AUTO position and the heaters
operate automatically as controlled by a thermostat (23/ORR) which is
mounted in the side of the reservoir opposite of the oil cooler connections. For
safety, the heaters are normally interlocked with the oil level switches to
interrupt power to the heaters before the heater elements are uncovered. The
thermostat is adjustable by means of an externally mounted knob, and it
should be set to regulate the oil temperature in the normal operating range of
26.7℃- 37.8℃.
CAUTION:Whenever the oil level is below the normal operating level or
before draining any oil from the reservoir, ensure that the power to the heaters
is shut off. Energized heater elements that are not covered with oil will ignite
the oil vapors in the reservoir.
11) other controllers and pressure switches
1.3.3.10 Turbine Control System Summary
1.3.3.10.1 Introduction
The turbine control system adopts Digital Electro-Hydraulic (DEH) control
system. The DEH control system can suffice high reliable requirement for
turbine generator unit’s control. The DEH control system consists of five major
components that are listed below:
The controller of data collection and data processing
Operator interface (include CRT, operator keyboard, mouse and printer)
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
76
Steam valve servo-actuators (include throttle valve actuator, governor
valve actuator, reheat stop valve actuator, interceptor valve actuator)
DEH oil supply system
Emergency trip system
The following information is offered as a general description of and an
introduction to the DEH system apparatus.
1.3.3.10.2 DEH controller
The electronic controller cabinets contain all circuits and memory for the
system, such as logic, reference, signal input cards, amplifiers, automatic and
manual controllers, redundant power supply and terminal strips etc. It
performs basic computation on reference and turbine feedback signals and
generates an output signal to the steam valve actuators. The controller
includes workstation, control processor unit, I/O card etc. The control
processor unit adopts redundancy configure. The control processor unit are
programmed so that each performs a specific function of the turbine control
process (include Over-speed Protection/Operator Auto Controller).
1.3.3. 10.3 DEH function
DEH control system controls turbine start, rolling procedure, synchronize
interface and load through CRT in operation.
The DEH control device has the following function:
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
77
Speed Control
The logic of turbine speed control will perform the entire loop control from the
turning gear to synchronize or over-speed trip test. It is of a wide speed
control function (0-3500r/min, control precision is±1r/mn)
Over-speed Protection Function
DEH have over-speed protection control function, when the turbine speed
reaches 103% rated speed, over-speed protection controller (OPC) will close
all of the governor valve and interceptor valve rapidly to protect turbine speed,
avoiding turbine over-speed. After a few seconds, the governor valve will
automatically reopen. When the turbine speed is above the trip speed (110%
of rated speed), DEH control system will send trip signal, and close all steam
valve rapidly.
Over-speed Trip Test
Over-speed trip test must be performed in DEH control mode, over-speed trip
test have two-test mode mainly, and they are mechanical over-speed trip test
and electric over-speed test.
Synchronize the Unit
When the turbine speed reaches 3000r/min, operator access automatically
synchronize control from custom graphic, the turbine that accept
increase/decrease signal from synchronizing device control the turbine speed,
and perform synchronizing.
Load Control
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
78
After the turbine speed is at rated speed, synchronize interface, load, operator
will control load according to pre-given target load and acceleration rate.
The function of Initial Load
When the generator breaker is closed, an initial load of approximately 5% is
automatically taken by DEH.
Remote control mode
In remote control mode, DEH will accept 4~20mA signals from CCS, and
control turbine load, to achieve harmonious control between boiler and turbine.
The function of Valve Management
During the turbine start up, the turbine runs in single valve control mode. Six-
governor valve and two reheat governor valve all open at the same time. In
this way, the rotor and cylinder will gain symmetrical quantity of heat, avoiding
heat expansion. After the turbine carry certain load, the sequence valve
control mode will be selected, according to the quantity of load, six-governor
valves open in sequence, thus the control mode reduce valve’s throttle loss,
raise efficiency. Meantime opening valve gain less shock from steam flow, the
longevity of valves gains to rise. When valve control mode transfer, the
influence of load is less.
The function of Valve Test
A function of the turbine valve test is to be performed and can be made while
the unit is carrying load. The purpose of this test is to ensure proper, safety
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
79
operation, to supervise valve flexible. When the turbine is run, the turbine
steam valve can test for certain period.
The function of Throttle Pressure Limiter
A function of the throttle pressure limiter is to be performed. Operator sets the
throttle pressure limiter value. When the throttle pressure is less than the
throttle pressure’s setpoint, the governor valve will close to maintain the
throttle pressure.
1.3.3. 10.4 Operator interface
The operator’s interface, which is usually located in the control room, is the
unit’s control center. The interface consists of a CRT, operator keyboard and
printer. Through the use of the keyboard various, pre-designed graphic pages
can be accessed. Each of these pages provides the operator with access to
different areas of turbine operation. For example, there is a page to change
the status of feedback loops, to select speed or load target.
Operator settings made at the keyboard are used by the electronic controller
to position the steam valves by comparing the turbine speed, first stage steam
pressure, and megawatts signals to the target settings selected by the
operator.
The printer, which is usually located in the control room, operator can watch
alarm and turbine message.
1.3.3. 10.5 Steam Valve servo-actuators
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
80
Each of steam valve servo-actuators controls each of steam valve. The
opening of hydraulic cylinder of actuator is moved by EH fluid pressure and its
closing be by springing force. The signal side entrance hydraulic cylinder
connects with a control block on which shutoff valves unload valves and check
valves are mounted. In addition to different assemblies, two fundamental type
actuators are consisted.
General, reheat stop valve actuator belongs to open-close type, which control
the steam valve. The high-pressure fluid entrances the bottom chamber of
hydraulic cylinder, the high-pressure fluid of the chamber can be controller by
rapidly unload valve, which is controlled by the pilot valve. When the turbine
control system is reset, the pilot valve control the unload valve to close. The
high-pressure fluid of the chamber will build up gradually to open the reheat
stop valve actuator,
The governor valve actuator control the steam valve at any intermediate
position and control the steam flow in proportional to meet the requirement.
The actuator is equipped with EH transformer and linear variable differential
transformer (LVDT). The high-pressure fluid supply to EH transformer by a 3
micron cartridge. The EH transformer accept servo amplifier’s valve signal
and control the actuator position. The LVDT output an analogy signal
proportional as a feedback signal, and form a closed loop.
Isolating valve can maintain the part of executive (including hydraulic cylinder)
online. The check valve can prevent the high-pressure fluid flow to return by
the drain fluid an emergency trip system.
1.3.3.10.5.1 Throttle valve actuator
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
81
The actuator operates the throttle valve. It is mounted on the side of each
throttle valve spring house and its piston rod is connected to the throttle valve
operating lever. This lever is so fulcrumed that upward movement opens the
valve. The actuator is single acting and provides the force for opening the
valve and closing springs provide the force to close the valve.
The principal components of the actuator are hydraulic cylinder, block, servo
valve, relief valve, LVDT, shutoff valve, check valves and filter. The block
provides a means for mounting and connecting all the components together
and is also a terminal for all electrical and hydraulic connections.
The flow of high pressure fluid through an isolation valve and a 3 micron metal
mesh filter to the actuator is controlled by a servo valve. The position control
and LVDT position feedback signals are summed at the servo amplifier
resulting in a position error signal. The servo amplifer positions the servo
valve in response to this error signal to accurately position the actuator and
steam valve. The servo valve admits high pressure fluid to the hydraulic
cylinder to open the steam valve and release operating fluid from the hydraulic
cylinder to allow the steam valve to close. The servo valve is mechanically
biased to assure fail safe operation for loss of electrical signal.
A pilot operated relief valve is used as a dump valve. The pilot is actuated by
the emergency trip header to provide quick closing independent of the
electrical system. When the dump valve is activated it release all operating
fluid to drain. The drain is also connected to the upper end of the hydraulic
cylinder and accommodates the released fluid so that the drain line is not
overloaded. Heavy springs on the valve assembly provide the force for quick
closing.
1.3.3. 10.5.2 Governor valve actuator
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
82
The actuator operates the steam chest control valves. It is mounted on the
side of each steam chest and its piston rod is connected through a pair of
links to the control valve operating lever. This lever is so fulcrumed that
upward movement opens and provides the force for opening the valve and
closing springs provide the force to close the valve.
The principal components of the actuator are hydraulic cylinder, block, servo
valve, relief valve, LVDT, shutoff valve, check valves and filter. The block
provides a means for mounting and connecting all the components together
and is also a terminal for all electrical and hydraulic connections.
The flow of high pressure fluid through an isolation valve and a 3 micron metal
mesh filter to the actuator is controlled by a servo valve. The position control
and LVDT position feedback signals are summed at the servo amplifier
resulting in a position error signal. The servo amplifer positions the servo
valve in response to this error signal to accurately position the actuator and
steam valve. The servo valve admits high pressure fluid to the hydraulic
cylinder to open the steam valve and release operating fluid from the hydraulic
cylinder to allow the steam valve to close. The servo valve is mechanically
biased to assure fail safe operation for loss of electrical signal.
A pilot operated relief valve is used as a dump valve. The pilot is actuated by
the auxiliary governor trip to provide quick closing independent of the
electrical system. When the dump valve is activated it release all operating
fluid to drain. The drain is also connected to the upper end of the hydraulic
cylinder and accommodates the released fluid so that the drain line is not
overloaded. Heavy springs on the valve assembly provide the force for quick
closing.
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
83
1.3.3. 10.5.3 Reheat stop valve actuator
The actuator is provided to operate the reheat stop valve. It is mounted on
each stop valve spring house and its piston rod is connected directly to the
stop valve piston rod. Therefore, upward movement of the operating piston
opens the valve and downward movement closes the valve. This valve
operates in a full open or full closed position. The actuator is single acting and
provides the force for opening the valve and closing springs provide the force
to close the valve.
The principal components of the actuator are hydraulic cylinder, block,
solenoid valve, relief valve, shutoff valve and check valves. The block
provides a means for mounting and connecting all the components together
and is also a terminal for all electrical and hydraulic connections.
The flow of high pressure fluid through an isolation valve to the actuator is
controlled by an orifice. The high pressure fluid is admitted through an orifice
to the hydraulic cylinder to open the steam valve, and the dump valve
releases the operating fluid from the hydraulic cylinder to allow the steam
valve to close.
A pilot-operated relief valve is used as a dump valve. The pilot is actuated by
the emergency trip header to provide quick closing independent of electrical
system. When the dump valve is activated it release all high pressure
operating fluid to drain. The drain is also connected to the upper end of the
hydraulic cylinder and accommodates the released fluid so that the drain line
is not overloaded. Heavy springs on the valve assembly provide the force for
quick closing.
1.3.3.10.5.4 Interceptor valve actuator
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
84
The interceptor valve servoactuator positions the interceptor valve. It is a
single acting, pull type actuator, utilizing high pressure fluid to rapidly and
precisely position the interceptor valve in response to signals from the
electronic controller. The servo actuator is mounted on the interceptor valve
spring housing, and its piston rod is connected to the interceptor valve stem
with a coupling. Upward movement of the piston rod opens the interceptor
valve, and downward movement closes it. Heavy closing springs hold the
interceptor valve in the closed position, and the servo actuator overcomes the
spring force to position the interceptor valve in any open position.
The principal components of the servo actuator are the hydraulic cylinder,
block, servo valve, dump valve, test solenoid valve, LVDT and a manifold
block that includes a shutoff valve and check valves. The actuator block
provides a means for mounting and hydraulically connecting all the
components together and is also a terminal for all electrical and hydraulic
connections.
High pressure fluid is admitted to the servo valve through a filter. Within the
servo valve, the fluid enters a chamber containing a shifting spool whose
movement uncovers ports that direct the fluid flow to or from the chamber
beneath the operating piston of the hydraulic cylinder. As the fluid pressure
increases beneath the piston, it overcomes the force of the interceptor valve’s
closing springs and opens the valve.
The filtered high pressure fluid is also supplied through the de-energized test
solenoid valve to the upper chamber of the dump valve. This fluid seats the
dump valve which, in the closed position, blocks a path to drain of the fluid
beneath the hydraulic cylinder’s operating piston.
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
85
The servo valve is electrically controlled and responds to signals from the
electronic controller which supplies a positioning signal that is based upon the
desired valve position. The servo valve spool shifts accordingly to direct either
more or less fluid to the hydraulic cylinder in order to move the interceptor
valve to the required position. The LVDT provides a feedback signal of the
actual interceptor valve position to the controller. The controller then
continually adjusts the positioning signal to the servo valve in order to reduce
the error between the desired valve position and actual valve position(which is
from the LVDT feedback signal).
When the desired valve position is reached the servo valve spool shifts to a
position where it directs only a slight amount of high pressure fluid to the
hydraulic cylinder. This slight flow compensates for leakage past the dump
valve and the hydraulic cylinder’s operating piston. With the spool in this
position, the servo valve also function as an orifice, effectively damping any
servoactuator movement resulting from pressure fluctuations in the high
pressure fluid supply.
The servo actuator closes the interceptor valve if either the servo valve
completely stops, the flow of fluid to the hydraulic cylinder, or the isolation
valve closes. In either case, system leakage from around the operating piston
and past the seated dump valve causes the fluid pressure beneath the
operating piston to decay sufficiently to allow the springs to close the
interceptor valve. The servo actuator will also close the interceptor valve if the
dump valve unseats. The dump valve unseats if either the test solenoid valve
is energized during testing, the high pressure fluid supply pressure is too low,
or the emergency trip fluid header pressure is lost.
1.3.3.10.6 EH fluid supply portion
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
86
The control system ‘s overall function is to position the turbine steam inlet
valves in order to regulate the flow of steam through the turbine. The control
system is separated into two parts: the EH fluid supply portion and the control
portion which are interconnected with stainless steel tubing and fittings.
The control portion of this system positions the steam inlet valves in response
to electrical commands from the solid state electronic controller. It positions
the valves by means of servo actuators which use high pressure EH fluid as a
motive force. Provisions are also included for automatically closing the valves
in emergency conditions. The control portion consists of the various servo
actuators which are mounted on the steam inlet valves, an emergency trip
control block and solenoid operated valves, an EH fluid test block assembly, a
fluid operated air pilot valve, an interface diaphragm valve, and the electronic
controller.
The EH fluid supply portion provides the fluid and pressure requirements of
the control portion while maintaining the integrity of the fluid. It consists of a
fluid filter, high pressure accumulators, low pressure accumulators, various
pressure control valves and fluid pumps and motors.
To ensure reliability of supplying oil, the supply oil system include stainless
steel reservoir, piston pumps, control book, filters and heat exchangers. The
system is arranged so that one pump and one set of various control
component function while duplicate set serves as a standby system.
Motive fluid for the EH control system is provided by a fluid supply system
consisting of an EH fluid supply said, high-pressure accumulators, fluid
conditioning system, and interconnecting turbine. Supply header pressure is
maintained at a constant 14Mpa by duple variable displacement pressure
compensated pumps in conjunction with high-pressure accumulators located
near the steam valve actuators. The variable displacement pump
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
87
compensated maintains constant header pressure for normal steady state and
transient fluid flow demands that can’t be supplied by the pump. A relief valve,
set at 16.7Mpa , prevents system over-pressurization.
A separate lubrication oil system supplies lubricant to the turbine and
generator bearings and provides a medium to hydraulically operate the
mechanical overspeed trip mechanism and manual trip lever. It is interlocked
with the control system through the interface diaphragm valve.
1.3.3. 10.7 Emergency Trip System
The emergency trip system monitors certain turbine parameters and close all
turbine steam inlet valves when the operating limits of these parameters are
exceeded. The parameters monitored are the following:
Turbine overspeed
Thrust bearing wear
Low bearing oil pressure
Low condenser vacuum
Low EH fluid pressure
A remote trip which accepts all additional ex ternal trips is also provided.
The system utilizes a two-channel concept which permits on-line testing with
continuous protection afforded during the test sequence.
The system consists of an emergency trip control block with trip solenoid
valves and status pressure switches, three test trip blocks with pressure
switches and test solenoid valves, rotor position pickups, speed pickups, a
cabinet containing electrical and electronic hardware and a test panel.
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
88
The sensing devices at the turbine transmit electrical signals to the trip cabinet
where logic determines when to trip the auto stop emergency trip header.
EMERGENCY TRIP CONTROL BLOCK
The auto stop emergency trip header, pressure is established when the auto
stop trip solenoid vlaves (20/AST) are energized closed. The valves are
arranged in two channels for testing purposes. The odd numbered pair
correspond to channe 1 and the even numbered pair correspond to channel 2.
This convention is carried throughout the emergency trip system in
designating all devices ,e.g. channel 1 devices are odd numbered, and
channel 2 devices are even numbered. Both valves in a channel will open to
trip that channel. It can be seen that both channels must trip before the auto
stop trip header pressure collapses to close the turbine steam inlet valves.
On-line testing can be ac complished by "tripping" one channel at a time.
The 20/AST solenoid valves are externally piloted two-stage valves. EH Fluid
pressure is applied to the pilot piston to close the main valve. The pilot
pressure of each channel is monitored by a 63/AST pressure switch. The
pressure switch is used to determine the tripped or latched status and as
an interlock to prevent testing one channel when the other channel is being
tested.
TEST BLOCKS
The schematic of test blocks for bearing oil pressure、EH fluid pressure and
condenser vacuum are following: each test block assembly consists of a steel
test block, two prssure gauges, two shut off valves, two solenoid valves and
three needle valves. Each assembly is arranged into two channels. The
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
89
assemblies, mounted on the governor pedestal, are connected to pressure
switches mounted in a nearby terminal box. (The assemblies are orificed off
from the system supply on one side and connected the drain or vent on the
other side). An orifice is provided in each channel so that the measured
parameter is not affected during testing. An isolation valve on the supply side
allows the test block assembly to be serviced without contamicating the rest of
the system.
If the medium (pressure or vacuum)reaches a trip level, then the pressure
switches would function and cause the auto-stop emergency trip header to
trip. When testing, the medium is reduced to the trip level in that channel
either locally through the hand test valves or remotely from the trip test panel
via the test solenoid valves.
THRUST BEARING TRIP DEVICE
Position pickups, which are part of the turbine supervisory instrument package,
monitor movement of a dIsc mounted on the rotor near the thrust bearing
collar. Any axial movement of this collar will also be reflected in movement of
the disc. Excessive movement of the disc is an indication of thrust bearing
wear. Should excessive movement occur. relay contacts from the supervisory
in strument modules colse to effect a turbine trip.
The thrust bearing trip function can be tested by a test device on which the
pickups are mounted. A trip condition is simulated by moving the pickups
toward or away from the disc or the rotor.
ELECTRICAL OVERSPEED TRIP
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
90
The electrical overspeed channel consists of three magnetic pickups mounted
at the turning gear and a speed cage mounted in the trip system cabinet. The
output frequency of the pick up is proportional to the shaft speed. This
frequency is converted to an analogue signal which is compared with the trip
set point voitage. As long as the shaft is less than the trip set point, the output
of comparator is a positive voltage. If the voltage corresponding to shaft
speed exceeds the trip set point, the comparator output voltage goes negative
which turns on transistor QI picking up relay OST. Contacts from this relay
cause both auto stop channels to trip.
MECHANICAL OVERSPEED TRIP
A mechanical overspeed trip device is provided. Both mechanical and
electrical speed trips are set at the same trip speed. The mechanical
overspeed trip mechanism consists of a spring loaded trip weight mounted in
a transverse hole in the rotor ex tension shaft. Under normal operating
conditions, the trip weight is held in the inner position by the compression of
the spring. When the turbine speed reaches the trip set point, the increased
centrifugal force overcomes the compression force of the spring which throws
the trip weight outward striking a trigger. As the trigger moves , it unseats a
cup vlave which drains the mechanical overspeed and manual trip header. As
the header pressure collapses, the interface deaphragm valve unseats,
tripping the auto stop emergency trip header. The mechanical overspeed and
manual trip header can be tripped manually via a trip handle mounted on the
governor pedestal.
1.3.4 Turbine HBD
Type:N300-16.7/538/538
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
91
1) VWO (valve wide open) condition
Items Unit VWO
Maximum output MW 315.136
Steam pressure at the inlet of MSV MPa.a 16.7
Steam temperature at the inlet of MSV ℃ 538
Reheat steam temperature at combined valves ℃ 538
Steam flow for main steam t/h 987.523
Steam flow for hot reheat steam t/h 794.676
Back pressure of condenser kPa(a) 10.05
Final feed water temperature ℃ 279.5 2) Heat Rate Guarantee Condition
Items Unit Heat Rate Guarantee
Rate output MW 300.083
Steam pressure at the inlet of MSV MPa.(a) 16.7
Steam temperature at the inlet of MSV ℃ 538
Reheat steam temperature at combined valves ℃ 538
Steam flow for main steam t/h 926.617
Steam flow for hot reheat steam t/h 753.271
Back pressure of condenser kPa(a) 10.05
Final feed water temperature ℃ 275.8
3) All HP Heater out of service Condition
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
92
Items Unit All HP Heater out
of service
Rate output MW 300.215
Steam pressure at the inlet of MSV MPa.(a) 16.7
Steam temperature at the inlet of MSV ℃ 538
Reheat steam temperature at combined valves ℃ 538
Steam flow for main steam t/h 802.687
Steam flow for hot reheat steam t/h 772.975
Back pressure of condenser KPa(a) 10.05
Final feed water temperature ℃ 175.1
An ac motor operated rotor turning gear for automatic and local-remote &
manual operation shall be provided. A zero speed sensing device shall be
provided for control of automatic operation. The turbine generator unit shall be
designed to withstand the stresses due to an over-speed of 20 percent above
normal synchronous speed, without reducing the life of the machine.
1.4 Generator
1.4.1 General
The generator is a two-pole, cylindrical rotor type synchronous machine,
directly coupled with steam turbine.
Generator type: QFSN-300-2
Rated output 353MVA/300 MW
Rated voltage 20 kV
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
93
Rated current 10189 A
Power factor 0.85 (Lagging)
Speed 3000 r/min
Frequency 50 Hz
No. of phase 3
Cooling method
Stator winding Direct Water cooled
Rotor winding Direct Hydrogen cooled
Exciter method Brushless excitation system
1.4.2 Introduction of QFSN-300-2 generator
a. INTRODUCTION The generator supplied was designed and manufactured under the licence of
Westinghouse Electrical Corp.(WEC) in accordance with ANSI C50.10, ANSI
C50.13, IEC34-1 and IEC34-3. It is an updated hydrogen and water inner -
cooled generator, joint - developed by Shanghai Electrical Machinery
Manufacturing Works (SEMMW) (now STGC) and Westinghouse Electric
Corp. (WEC) in 1985.
b. GENERATOR VENTILATION AND COOLING SYSTEM
The ventilation system provides uniform cooling of the entire generator frame using hydrogen as the cooling medium. This time-proven system, supplied on
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
94
large steam turbine-driven generators for decades, permits a generator to be designed for optimum physical size and electrical capacity.
Hydrogen gas circulates in a closed circuit inside the generator by two single-stage axial blowers, mounted on both ends of the rotor. The blowers are located immediately ahead of the coolers so that the gas temp. rise due to the blower losses will not be added to the total temperature rises of the electrical components. All generator components, rotor winding, stator core, end region flux shield structures and lead box, except the stator winding, are hydrogen cooled. The hydrogen is cooled by the hydrogen-to-water coolers located vertically at both ends of the generator. Cold gas from the coolers flows in two symmetrical paths, with the exception that there is gas flow in the lead box on the exciter end.
The stator core and rotor winding are cooled by separate but parallel flow circuits. The air gap serves as a plenum to return the gas back to the axial blower.
For the rotor, the cold gas is admitted at each end of the rotor through the annular space under the rotor winding retaining rings. The most part of the flow enters the main rotor body sub-slots machined underneath each rotor winding slot. From these sub-slots the gas flows into the radial vent ducts on rotor winding and discharges into the air gap through holes in the rotor wedges. A fraction of gas flow is diverted to cool the rotor end turn, This flow is divided into two paths, the straight and the arc path. For the straight path, it flows axially towards the main rotor body and discharges through radial ducts into the air gap. The arc portion of the end turns are cooled by hydrogen flowing circumferentially towards the pole centerline and discharging into the air gap through scooped passages at the end of the rotor body.
The stator core is radially ventilated. The cooling gas is forced to the space between the core and the generator frame by the axial blowers on both ends. From this space it flows radially inwards through radial vents and towards the air gap.
The stator coils , parallel rings, main leads and terminal bushings are cooled directly with de - ionized water. Cooling water flows from main inlet pipe into the inlet water manifold, then enters the teflon hose of each coil bar at exciter end, passes through the whole length of the hollow conductors in coils and
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
95
the teflon hoses at the other ends, then exits to the water outlet manifold at the turbine end where it picks up the drain water from the phase leads and terminal bushings and returns to the water tank. Hot water is cooled by water coolers before pumped back to the stator winding.
c. FRAME
The generator is of an integral frame construction, reducing erection expenses and giving protection to the internal components during transportation and erection. It may be splitted into 3 sections for shipment in order to reduce the max. weight and dimensions for transportation in conformity with those specified by customers, and is then site - assembled to be an integral piece, having a good gas-tight frame and maximum protection to the internal components.
The generator frame is a heavily ribbed cylinder which supports the stator core and windings, bearing brackets, and rotor assembly. The frame and the enclosing bearing brackets are fabricated from steel plates .
The generator frame is designed to be “explosion-safe”. This means that the frame will contain and withstand an internal explosion of the most explosive mixture of hydrogen and air at the most probable conditions of occurrence, i.e., at atmospheric pressures during gas changing operations, without damage to life or property external to the machine. Some internal damage may occur with such an explosion.
Four hydrogen coolers each of which has two sections, are mounted vertically at each corner of the generator frame.
The generator frame is supported by frame feet along its length on foundation seating plates. Foundation bolts resist short-circuit torques applied to the frame. Shims between frame feet and seating plates are provided for generator alignment with respect to the steam turbine generator shaft system. A number of jack screws are also provided in the generator frame feet for vertical alignment. Axial anchors for the frame feet and also for the seating plates allow for thermal expansion of the generator in both axial directions from the centerline of the generator. Transverse anchors engage the bearing
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
96
brackets on each end of the generator to maintain the generator lateral position while allowing the axial expansion.
d. STATOR CORE DESIGN
The stator core is composed of high permeability, low loss silicon steel laminations coated on both side with an effective class F varnish. The laminations are aligned and held together by dovetail key bars at the outside diameter which also serve as tension members to clamp the core axially by means of cast austenitic steel end plates. The end plates are sufficiently rigid to apply pressure evenly over the core cross section when loaded by the key bars at the outside diameter. The end plates are non - magnetic and with sufficient yield strength. The key bars are attached to the spring beams. The core is thus attached to the frame via the spring beams which reduce the amplitude of the double frequency core vibratory force transmitted to the generator frame and foundation. The mounting is such that very little of the core vibratory force is transmitted to the housing, but the core is rigidly restrained against load and short circuit torques. The stator core is tested for integrity during the manufacturing operation using a "loop testing" procedure. This procedure which simulates actual operation consists of circulating rated magnetic flux through the core laminations and inspecting the core for local hot spots by using a thermal vision camera capable of detecting small temperature differences. Any local hot spots, which are indications of deterioration in progress, are to be repaired. The lack of core problems in SEMMW (now STGC) generators is attributed to attention to core design and testing for core integrity as described above.
At the bore diameter equally spaced slots run the entire length of the stator core. These slots extend into the core for assembly of the stator coils.
A copper end-shield with a laminated magnetic shield protects the end plate and the core tooth area from end region flux.
e STATOR WINDING DESIGN
e.1 Water cooled stator coils
The stator winding consists of water inner-cooled, single turn, half coils wound in open slots and secured in place by glass-epoxy wedges. Each
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
97
stator coil is made up of two half coils shaped on a former and joined together after assembly in the slots. The stator coils of this generator are composed of insulated solid copper strands and insulated hollow copper conductors. Each strand and hollow conductor are wrapped with an electrical grade continuous filament type epoxy resin glass fiber to form a smooth continuous uniform insulation at all points. The strands together with hollow conductors undergo 540°Robel transposition in the slot portion of the coil.. This glass covering is then treated to give a smooth surface finish which is tough and flexible and will withstand abrasion from each other in the coil of the stator winding during operation.
Effective cooling of the stator coils is achieved by the cold deionized water. The water flows from the inlet manifold at the exciter end of generator into the coil ends thru teflon insulating hoses, then discharges from the stator coil at other end, where it is collected by teflon insulating hoses on a discharge manifold. The parallel rings and lead terminals are composed of insulated hollow copper conductors for direct water cooling. All six terminals of the three phase winding are brought out at the exciter end of the lead box beneath the floor level through gas tight porcelain bushings.
Resistance temperature detectors are provided to measure the temperature of the stator coils and their hot water discharge and to detect any abnormal conditions. Leads from the temperature detectors are connected to terminal boards.
e.2 Stator Coil Insulation
Epoxy-Mica insulation is used to provide the ground wall insulation on the stator coil. To give good dielectric and mechanical strength, the ground insulation is continuously wound with several layers of epoxy resin mica-paper tape then cured at high pressure and temperature in the former. Epoxy-Mica insulation is a tough, yet thermally flexible dielectric barrier with excellent electrical and physical properties. The excellent dielectrical properties of the resin, coupled with good insulation consolidation, results in Epoxy-Mica with lower dielectric loss tan( , increased dielectric strength, and remarkable improvement of voltage endurance. Its consistently low dielectric loss is less affected by temperature and voltage variation than other types of insulation. Epoxy-Mica insulation has great thermal endurance and long life.
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
98
The character of the resin provides solid, yet elastic physical bonds between mica papers. The resilient nature of the resinbond permits elastic cyclic displacement of adjacent mica papers and provides restoring force within the insulation ground-wall. This makes Epoxy-Mica insulation ideally suitable for cyclic duty operation. The insulation is also inert to ordinary chemicals, oils, and solvents and has an unusually high moisture resistance. It was developed in the late 1960's, and first placed in service in 1966. Continued improvements have made Epoxy-Mica insulation a superior insulation for high-voltage coils, satisfying the requirement of class F insulation.
Effective corona suppression is provided by the use of a low-resistance, conducting varnish on the coil slot section to contain the dielectric stress within the solid insulation and a combine process of a low resistance conducting varnish and a high-resistance, semi-conducting varnish in the end-turns to grade voltage stress along the coil surface.
Quality Assurance checks are performed on each coil and the complete winding to verify insulation integrity. Each coil is given a high-potential test well in excess of final winding high-potential test values before being wound into the machine. Each set of coils includes extras which are chosen at random from the set for testing to destruction, thus giving further verification of insulation integrity. Additional high-potential tests are performed both during and after completion of the stator winding.
e.3 Stator Winding Bracing
Of equal importance with the insulation system is the method of slot-fill and bracing used to protect the stator coils from the vibratory stresses experienced during steady-state operation and from the transient disturbances which can be experienced during abnormal operating conditions. The ANSI and IEC Standards set the requirements for steady-state operation and define the abnormal operating conditions which must be met.
Each coil is secured in the slot by a glass-epoxy wedge assembled in wedge grooves in the slot. Epoxy impregnated conforming materials are placed under the bottom coil and between the bottom and the top coils to suit the coil in slot. The tightness is maintained by the prestressed driving strip ( PSDS or
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
99
ripple spring )-- a wave glass fiber epoxy strip-- directly below the slot wedge, maintaining radial pressure on coils and slot wedges.
Flat glass-epoxy filler strips are assembled above the coils in the slots to distribute the load of the PSDS.
Flat filler strips are also utilized on one side of the coil to provide a tight fit in the slot. These supporting members virtually eliminate potentially damaging coil vibration caused by the electromagnetic forces that are present. The entire stator is thermally cured under pressure to consolidate slot contents and reduce vibratory stresses due to coil motion. The consolidation of ground wall and filler materials and the use of ripple spring between coils and wedges gives unsurpassed slot compactness for long service life.
The radial winding clamp composed of high-strength glass epoxy clamping plates and non-magnetic bolts together with support rings and bracing brackets provides radial, structural consolidation of the end winding. The radial clamps provide clamping forces well in excess of the vibratory forces between the top and bottom coils. This reduces vibration of the individual coils relative to the strain blocks used between top and bottom coils, as well as to the diamond spacer assemblies used between adjacent coils. This reduced radial vibration will prevent relative motion and wear between the coils and the strain blocks. Clamping plates and non-magnetic bolts secure the coils to the bracing brackets.
De-coupled end winding support bracing consist of bracing brackets, teflon slip layers and spring structure through which the bracing brackets attach to the core end plates so as to de-couple the end windings from the core and to improve the end winding to radial brace attachment. The brace provides for dynamic isolation between the coils and core to permit detuning of the end winding natural frequency well below 100 Hz, the exciting frequency.
There are Fluoroelastomer rubber layers with good physical and dielectric properties placed between the insulating clamp plates and coils for protecting coil from wear of insulation, as well as for damping coil vibration.
This end-winding bracing system has effectively controled the forces which result from both steady and short circuit conditions and also allows axial motion for thermal expansion. as proved by long operation practice.
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
100
This bracing design is found in the fact that, by isolating the stiffness of the core from the end winding support, the end winding dynamics can be favorably changed.
e.4 MAIN LEADS
Stator parallel rings, phase leads and main lead bushings are directly cooled by the water. The main lead bushings are assembled in a gas-tight main lead box located underneath the frame at the exciter end. Bushings can be replaced without removing the generator rotor. The six main lead bushings extend from the lead box, three of which are used for the main leads connecting to the main transformer and three of which are used to form the neutral tie. Each bushing can be provided with up to four bushing mounted current transformers. Current transformers are suitable for metering, relaying, or voltage regulator service. The current transformers have a secondary current level of five amperes.
f. GENERATOR ROTOR
The cylindrical type rotor forging is made from chromium, nickel, molybdenum, vanadium alloy steel and is poured with the vacuum degassing process. Forging materials are ultrasonically tested for compliance with rigid quality assurance specifications. A bore hole is provided to remove centerline indications. The bore hole may then be used in later years for examination of forging integrity. Two pole rotors have their pole faces slotted so as to equalize flexibility and to reduce double-frequency vibration.
Rotor winding components are subjected to stresses both from rotation and from thermal expansion and contraction. It is essential that these stresses be accounted for and limited in the rotor design. During startups, shutdowns, and load changes the rotor winding will move relative to the rotor structural parts. Built-in clearances and slip layers allow for this motion while reducing the frictional forces which could cause distress or shaft vibration. Hard-drawn, creep resistant, silver-bearing copper and glass-laminate turn-to-turn insulation reduces the chance of permanent winding deformation or shorted rotor turns. The winding is held firmly against rotational forces by nonmagnetic retaining rings and high-strength rotor slot wedges. In the rotor end turn area, customarily fitted glass epoxy blocking and spacers maintain
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
101
alignment of the winding components. The end winding curved sections potentially high stress areas are arranged with brazed connections located well away from the curves. Axial expansion is controlled by allowing for expansion to occur and by including teflon slip layers in the rotor slots and under the retaining ring, to limit the friction that opposes axial motion.
The field winding is manufactured from high-strength alloy copper. This silver-bearing alloy copper contains the necessary metallurgical creep-resistant properties to minimize distortion during operation. The individual turns of the rotor winding are made up of two conductors. On the end turns each consisting of two copper channel sections, which form a gas passage for the hydrogen. For turns inside slots, there are two parallel rows of slim vent ducts evenly distributed along the winding slots to form radial vent holes over the sub-slots. The field winding insulation is provided with extra creepage distance on the top turns. The windings are placed in rectangular slots which are lined with one piece, molded insulating slot cells. The slot cells are teflon lined on the inner surface to permit the rotor copper to move axially due to thermal expansion and contraction. The insulation between turns consists of glass laminate bonded to the copper. The glass laminate exhibits excellent wear characteristics and has a high coefficient of friction, which reduces relative slippage between coil turns that causes wear and copper dusting. Instead, the entire coil slot structure acts as a unit rather than individual turns. After the rotor is pressed and cured, fitted, high-strength slot wedges are driven into the top of the slots.
The rotor end turns are supported radially against rotational forces by 18Mn18Cr nonmagnetic retaining rings shrunk onto the rotor body. This alloy is highly resistant to corrosion and stress corrosion cracking in the presence of moisture and other corrodents. These retaining rings are nonmagnetic steel forgings. These floating-type retaining rings, with teflon surfaced insulating liners, prevent distortion of the rotor copper and abrasion of the rotor coil insulation. The rings are shrunk and keyed onto machined sections at the ends of the rotor body with a firm fit at overspeed and rated temperature. The heavy shrink fit provides a low-resistance electrical path for induced rotor surface currents, thereby reducing heating due to rotor surface currents. A circumferential locking ring is provided to prevent axial movement of the retaining ring. This method of support permits the shaft to flex without causing
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
102
fretting at the joint or overstressing the rotor winding and is used to eliminate the effect of shaft deflection on the rotor end winding assembly.
An amortisseur winding is provided which uses copper damper bars in each rotor slot connected at the ends by beryllium copper wedges to the retaining rings. This design meets the requirements of the industry standards for negative-phase-sequence current capability.
This machine has two single stage blowers, mounted on the rotor shaft at both ends. The outside diameter of the blower blades is smaller than that of the retaining ring. The blower hub outside diameter is designed to be small enough to allow removal of the retaining ring over it, if necessary, for winding inspection. After unshrunk from the retaining ring, the end plate can be slided over the spacer ring and attached to the blower hub during repairing.
The completed rotor is dynamically balanced. It is carefully baked and seasoned at running speed to promote lasting stability of the rotor winding components. Standard equality control tests are made on every rotor before and after over-speed tests to verify that no shorted rotor turns have developed. It is performed by means of a continuous impedance test as the rotor speed is increased from rest up to rated speed and back to rest. The rotor is then carefully inspected and a final high-potential test is performed.
g. BEARING, GLAND SEAL AND BEARING BRACKETS
The bearings, supported in rugged fabricated bearing brackets, are insulated and may be removed without removing the hydrogen seals from the machine. Bearing and gland seal insulation is provided at the following places on both ends of the generator to prevent shaft currents from flowing through the bearings: between the bearing pad and the bearing seat; between the gland seals and the brackets; between the bearing oil seals and the brackets; and at the stop dowel and bearing key. In addition, the pieces on the exciter end are "double insulated" with terminals for checking the insulation resistance of the bearing and gland seal insulation during operation. Only the exciter end bearing is "double insulated". Since the combination of insulation and the shaft grounding brushes, which are located on the turning gear pedestal, is considered satisfactory for preventing bearing currents in the turbine end bearing of the generator. The ring type gland seals are also housed in the bearing brackets to maintain a gas-tight shaft seal. The shaft seals are of
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
103
double oil flow construction with separate air and hydrogen side oil supplies to reduce hydrogen consumption. Vibration detector probes are provided at each bearing. The bearings are forced lubricated and visual oil flow gauges are supplied in the bearing bracket oil piping.
h. LUBRICATING SUPPLY SYSTEM
The generator shares a common lubrication system with the turbine. Fewer subsystems means less complexity and reduced installation costs.
i. SEAL OIL SYSTEM
The function of the seal oil system is to lubricate the seals and prevent hydrogen escaping from the genetator, without introducing air and moisture into the generator. The same oil is used in the turbine and generator bearing lubrication oil system and the gland seal oil system. Under normal operating conditions the seal oil is completely separated from the lubrication oil. Independent seal oil systems for air-side and gas-side oil eliminate the need for an oil vacuum treating unit and reduce hydrogen consumption by preventing the air-side oil which contains moisture from contacting the hydrogen gas in the generator. Part of the reliability of the system is the back-ups provided. Emergency seal oil back-up pumps, interconnected with the lubrication oil system, automatically provide continuous operation of the seal oil supply in the event that the main air side oil fails.
j. HYDROGEN GAS SYSTEM
Hydrogen pressure is maintained at the design pressure by a pressure regulator located in the hydrogen system. Continuous circulation of the hydrogen is maintained by the shaft-mounted axial blowers. The hydrogen gas system is designed for the following functions:
To provide means of safely putting hydrogen in and taking hydrogen out of the generator, using carbon dioxide as a scavenging medium.
To maintain the gas pressure in the generator at the desired level.
To continuously monitor the condition of the machine with regard to gas pressure, temperature, and purity, and to provide alarm signals in the event of abnormal conditions in the gas system. The pressence of liquid in the machine is also indicated by an alarm.
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
104
To dry the gas and remove any water vapor which might get into the machine from the seal oil system or other sources.
To provide control to secure the system in the event of an abnormal condition.
— GAS DRYER
A gas dryer is connected across the generator fan so that gas is circulated thru the dryer whenever the machine is running.
— LIQUID DETECTORS
Float operated switches in small housings are provided under the generator frame and under the main lead box to indicate the presence of any liquid in the generator which might be due to leakage or condensation from the cooler. Openings are provided in each frame ring at the bottom of the frame so that any liquid collected will drain to these water detectors. Each detector is provided with a vent return line to the generator frame so that the drain line from the generator frame will not become air bound. Isolating valves are provided in both the vent and drain lines so that the switches can be inspected at anytime,and a drain valve is provided for the removal of any accumulated liquid.
— HYDROGEN PURITY MONITORING EQUIPMENT
The purity of the gas in the generator is determined by the use of the purity blower, the hydrogen purity electronic differential pressure transmitter, the hydrogen pressure electronic transmitter,and the hydrogen gas instrumentation package.
An induction motor, loaded very lightly so as to run at practically constant speed, drives the purity blower and circulates the gas drawn from the generator housing. Thus,the pressure developed by the purity blower varies directly with the density of the sampled gas.The hydrogen purity differential pressure transmitter measures the pressure developed by the purity blower. Gas density is dependent upon the ambient pressure and temperature as well as the purity.
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
105
The hydrogen monitoring system combines the purity blower differential pressure and the machine gas pressure signals to provide a compensated density signal,which is a true reading of machine gas purity.
The purity indicator scale is divided into three sections. Near the center of the scale is a point marked "100% Air" . This point provides a means of calibrating the indicator without removing the gas from the generator. The upper end of the dial consists of a scale showing the percentage of carbon dioxide present in a mixture of carbon dioxide and air. This portion of the scale is used during scavenging operation when carbon dioxide is being introduced into the generator.The lower end of the dial consists of a scale indicating the percentage of hydrogen present in a mixture of hydrogen and air. It is this portion of the scale which is used during normal opration of the machine to determine the purity of the hydrogen in the generator housing.
The hydrogen purity signal, an electrical output signal, may be carried to a remotely located receiver provided with a dial similar to the purity indicator on the generator auxiliaries control enclosure.
Two switch assemblies are provided with the hydrogen monitoring system which are set to produce a "hydrogen purity high or low" alarm when the purity signal falls below exceeds predetermined limits.
— GENERATOR FAN DIFFERENTIAL PRESSURE MONITORING EQUIPMENT
An electronic differential pressure transmitter is connected directly to the generator housing and senses the pressure developed by the fan mounted on the generator rotor. The hydrogen monitoring system transmits the generator fan differential pressure signal to an indicator in the generator auxiliaries control enclosure.
This pressure can be used as a check on the purity indicator or can be used to indicate the hydrogen purity if the purity indicator is taken out of service while the generator is running.
— HYDROGEN PRESSURE MONITORING EQUIPMENT
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
106
The electronic hydrogen pressure transmitter is connected directly to generator housing an senses the pressure within the generator. The transmitted pressure signal is used by the hydrogen monitoring system, not only to compensate the density for purity as mentioned above, but also to supply the electrical signals for the following:
( The hydrogen pressure indicator in the generator auxiliaries control enclosure.
B. A remotely located indicator with dial simialr to the previous indicator and
( High and low,pressure alarm switches located in the generator auxiliaries control enclosure.
( The high and low pressure alarm switches provide an indication when the gas pressure in the machine exceeds or goes below predetermined limits.
— HYDROGEN TEMPERATURE ALARM
A hydrogen cold gas thermostat is located in the generator to provide a source of alarm in case the temperature of the hydrogen in the generator becomes excessive.
— SUPPLY PRESSURE SWITCH AND GAUGES
All generators are equipped with a hydrogen pressure control,which has a supply pressure switch and two pressure gauges. The top gauge indicated the machine gas pressure and also the setting of the regulator on the hydrogen pressure control. The bottom gauge gives an indication of the amount of pressure available from the hydrogen supply system.
A pressure switch is located on the supply side of the hydrogen pressure control manifold and gives and alarm when the supply pressure is low. A drop in pressure at this point would mean that the available pressure from the hydrogen supply was to low, or that the regulators in the hydrogen supply are set at too low a pressure.
k. STATOR COIL WATER SYSTEM
The stator coil water system is a closed loop system having the following features:
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
107
Circulation of high purity water thru the stator coil hollow conductors for removal of heat due to the stator coil losses.
Dissipation of heat from the high purity water. Filtering of water to remove foreign material. Demineralization of the water to control its electrical conductivity. Instrumentation and alarms to continuously monitor and advise conditions
of conductivity, flow, pressure, and temperature of water. All piping and components are made of corrosion resistant materials.
Cold water is piped thru the generator shell into a circumferential manifold in the exciter end of the generator. The cold water inlet piping is e quipped with a temperature detector for temperature monitoring and a thermostat for alarm purposes. An inline strainer is installed for startup to prevent admission of dirt into the hollow stator conductors.
Inside the generator, water flows from the inlet manifold into the coil ends thru teflon insulating tubes. Water discharging from the stator coil at the other end, is collected by teflon hoses and a discharge manifold, and then returns to the water tank.
The two inlet and discharge manifolds are interconnected at the high point with a vent line which also serves as an anti-siphoning line. This vent is continued to the water tank. The two manifolds are connected to a differential pressure gauge to indicate pressure drop across the stator coils. They are also connected to differential pressure switches for alarms for abnormal pressure drops across the stator coils. The inlet end of the water manifold is also connected to an inlet water pressure gauge and to the low pressure side of a differential pressure switch. The high pressure side of this switch is connected to the generator (gas pressure). When the generator gas pressure drops to 0.35 bar above the inlet water pressure, an alarm is actuated. l. AUXILIARY ALARMS
An alarm signal system is associated with the seal oil, stator coil water and hydrogen gas systems to indicate abnormal operating conditions. A Generator Auxiliary Control Enclosure has been supplied to indicate these alarms. A recent improvement has been made to supply the alarm signals dependent upon whether or not DEH is supplied and on the level of DEH supplied standard option. The traditionally supplied Generator Auxiliary Control Enclosure with local panel/announciator with limited contacts for
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
108
Customer's use in addition to contact and analog signals going to DEH. DEH makes all calculations and displays on CRT under appropriate conditions.
m. HYDROGEN COOLERS Each hydrogen cooler consists of a number of finned tubes arranged within a suitable open frame structure, thus providing a layer heat transfer surface for cooling the hydrogen gas circulating within the generator. Technically a hydrogen cooler is classified as 1-2 cross flow heat exchanger. That is the hydrogen gas makes a single pass through the cooler on finned side of tubing and the cooling water makes two passes on the tubes. Generally hydrogen coolers are divided into 2 "sections", each section being an independent heat exchanger. The sections are arranged in tandem such that the hydrogen gas makes a single pass through all the tandem sections, whereas the cooling water flows in parallel in each section and makes two passes in each.
There are generally two arrangements of hydrogen coolers used in generators: one is with coolers vertically mounted; and the other is with cooler horizontally mounted. This design uses the vertical arrangement. In the vertical arrangement. there are four hydrogen coolers, mounted in the frame of the generator at four corners. Each cooler consists of two separate, tandem sections, making a total of eight sections, each of which can be isolated by valving. Each cooler is attached to the generator frame at one end only to permit expansion and contraction within the generator. The inlet water chamber, which extends beyond the generator frame, is bolted to the generator frame. A thin steel diaphragm is secured to the cooler and to the generator frame at the opposite end of the cooler. This diaphragm allows relative thermal expansion between the generator frame and the hydrogen cooler without allowing hydrogen gas to escape. The water makes two passes through each section in a counter flow manner by means of a reversing chamber at one end. The heat is transferred from the gas to the cooling water flowing through the finned tubes of the cooler. Temporary operation at reduced load is permitted with one or two of the eight cooler sections out of service. The permitted load to see the generator instruction book in detail.
n. BRUSHLESS EXCITATION SYSTEM
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
109
Westinghouse in USA began to develop the brushless excitation system in the sixties. Since then more than 400 units have been produced. The proposed BLE excitation system was Westinghouse technology which is fully transferred to STGC.
The features of brushless excitation system:
♦ The electric power source of excitation comes from the directly driven AC exciter and permanent magnet pilot exciter to avoid system interference.
♦ Slip ring and brushes are no longer used. Thus pollution caused by carbon dust is eliminated, noise level lowered, and maintenance becomes easier.
♦ The modular structure of rectifier, fuse and etc, is easy for maintenance.
♦ Enough back up capacities are available for critical components such as the rotating diodes, firing circuit, power amplifying circuit and stable voltage source to ensure the safe operation.
♦ With better protection devices (such as over excitation, low excitation and low frequency protection) the generator can be operated at the maximum output.
♦ Internal connection: Rotating elements are solidly connected together. No outer connection is needed between the generator field and the exciter, the only outer connection being those between the stator of the AC exciter, the stator of the pilot exciter and the control circuit.
♦ With the performance of high initial response, the excitation system can reach 95% of the difference between ceiling voltage and rated excitation voltage within 0.1 second. Thus the stability of generator and power system can be raised.
♦ The field current of generator can be indirectly measured.
♦ De-excitation is realized by field inversion of the AC exciter and then open of its field connection to PMG.
2 FUEL
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
110
2.1 Fuel characteristics
The fuel and its characteristic data is listed below.
2.1.1 Coal Analysis
PARAMETER Performance CoalWorst Coal
(for ESP & MILL)
★Proximate Analysis
Moisture(AR) 15.0% 15.0%
Ash(AR) 34.0% 46.0%
Fixed Carbon(AR) 21.0% 19.73%
Volatile matter(AR) 30% 19.27%
★Ultimate Analysis
Carbon(AR) 41.22% 31.88%
Hydrogen(AR) 2.81% 2.13%
Sulphur(AR) 0.35% 0.28%
Nitrogen(AR) 0.71% 0.59%
Oxygen (AR)(by difference) 5.90% 4.12%
Moisture(AR) 15.0% 15.0%
Gross calorific value(AR) 4000 Kcal/Kg 3150 Kcal/kg
★Grindability Index 50 50
★Typical ash analysis
Silica 58.95% 59%
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
111
PARAMETER Performance CoalWorst Coal
(for ESP & MILL)
Alumina 28.5% 28%
Iron oxide 5.5% 6%
Titania 1.8% 2%
Phosphoric anhydride 0.7% 0.6%
Lime 1.5% 1.2%
Magnesia 1.3% 1.5%
Sulphuric anhydride 0.5% 0.6%
Alkalies (by difference) 1.25% 1.1%
Total 100% 100%
★ Ash fusion range
Initial deformation temperature 1100 deg .c 1100 deg .c
Hemispherical temperature 1300 deg .c 1250 deg .c
Fusion temperature 1400 deg .c 1400 deg .c
·AR = As Received
2.1.2 Fuel Oil
2.1.2.1 LIGHT DIESEL OIL ANALYSIS
Meets Indian Standard IS 1460-197
Analysis by Weight (percent)
-Sulfur 1.8
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
112
-Ash 0.02
-Relative Density @ 15℃ 0.86-0.90
Pour Point (℃ max.) 12(W)/18(S)
Kinematic Viscosity (centistokes at 38℃) 2.5/15.7
Water (Volume percent) 0.10
Gross Calorific Value (kcal/kg, avg) 10,600
Flash Point (℃ min) 66
2.1.2..2 HEAVY FUEL OIL ANALYSIS
No. Heavy Furnace Oil IS-1593-71 Grade HV
Low Sulphur Heavy Stock (LSHS)
1. Total sulphur content 4.5% max 1.0% max
2. Gross calorific value (Kcal/kg) Of the order of 11,000 Of the order of 11,000
3. Flash point (min) 66℃ 93℃
4. Water content by volume (max) 1.0% 1.0%
5. Sediment by weight (max) 0.25% 0.25%
6. Asphaltene content by weight (max.) 2.5% 2.5%
7. Kinematic viscosity in centistokes at 50℃ (max) 370 500
8. Ash content by weight (max) 0.1% 0.1%
9. Acidity (inorganic) Nil Nil
10. Pour point (max) 24oC 57oC
3 COMBUSTION SYSTEM AND SELECTION OF AUXILIARY EQUIPMENT
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
113
3.1 Boiler Fuel Consumption
The fuel consumption is about 180.2t/h (performance coal) and 230.7t/h
(worst coal) per unit at boiler maximum operation condition (BMCR). At TMCR
condition it is 166.0 t/h for performance coal and 213.2t/h for worst coal per
unit.
3.2 Design principle of Flue gas and air system & pulverized coal system Considering the high volatile matter and easy burning character of the raw
coal, medium speed mill (MSM) (positive pressure)& direct-firing pulverizing
system with cold primary air fan will be adopted based on our heat calculation
of coal pulverizing system.
3.3 System Description
3.3.1 Pulverized Coal System
Direct firing, pressurized cold primary air, pulverized coal system with MSM
will be adopted in this project. Six (6) sets of HP1003 type MSMs, electric
gravimetric coal feeders (EGCF) and raw coal bunkers will be matched with
each boiler. The output of four (4) MSMs will meet the requirement of boiler
capacity at BMCR with performance coal, and has suitable margin, the output
of five MSMs will meet the requirement of boiler capacity at BMCR with worst
coal, and has suitable margin.
Raw coal from raw coal bunker via EGCF will be pulverized and dried in the
MSM, then be separated in the MSM separator. There are four (4) pulverized
coal pipes on each separator connected to four corners of boiler burners in
the same layer. Six (6) sets of MSMs correspond to six (6) layer burners of
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
114
each boiler. Diameter adjustable device will be placed at pulverized coal
pipes, so that the resistance of each pipe is the same.
Each MSM will be equipped with one EGCF. Inlet and outlet motor operated
coal gates with good seal of the feeder can endure the exploding pressure of
0.35MPa, and have the function of self-clean. At the outlet of the bunker there
is rod gate, and the bunker emptying chute will be equipped between the two
gates. The EGCFs have alarms of coal flow break and block, coal flow
monitor etc, so that operator can handle emergency and ensures safe
operation.
Six (6) bunkers will be set for each boiler. The capacity of series of bunkers
per each unit will be normal sufficient to provided 16 hours requirement at
boiler maximum continuous rate with worst coal firing.
System design scope will include raw coal pipe and pulverized coal pipe.
3.3.2 Flue Gas and Air System
Direct firing, pressurized cold primary air system with MSM shall be adopted
in the project. The boiler manufactured by Shanghai Boiler Works Co. Ltd
(SBWL) in China shall be of natural circulation, drum type, double pass, water
tube, direct pulverized coal tangential fired, dry bottom, single reheat, balance
draft, and each boiler will be equipped with two (2) axial flow forced draft fans
(FDF) with adjustable moving-blade, three (3) centrifugal induced draft fans
(IDF) with hydraulic coupling, two (2) centrifugal primary air fans (PAF) and
two (2) sealing air fans. During operation, pressurized air shall be forced into
furnace. Fuel gas from the furnace shall be induced to atmosphere.
Lube oil system (with 2x100% capacity pumps, filters, and associated piping/
accessories) is provided wherever forced lubrication is envisaged for each of
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
115
the above fans.
Online vibration monitoring system and bearing metal temperature
measurement system shall be provided for all fans and their drive motors
3.3.2.1 Primary air system
Main function of the system is to feed pulverized coal and primary hot air
heated by air preheater to MSMs. Primary hot air will be acted as dry medium,
and cold primary air to MSMs (boosted by sealing air fan) and EGCFs will be
acted as seal medium. The inlet vanes of centrifugal primary air fan can adjust
air flow and pressure automatically.
Primary air will be heated in air preheater, and be sent to MSMs via common
manifold. Primary air damper will be placed at air preheater outlet. When air
preheater failure happen, the damper will be closed.
Pressurized cold air from PAFs will be regarded as regulating temperature for
MSMs and sealing air for belt feeders. The former will be mixed with hot
primary air. Mixed air can meet the temperature requirement of coal dried in
the MSM and pulverized coal at the MSM outlet.
When one MSM failure happens and shuts down, the corresponding
pneumatic damper on primary hot air duct shall be closed immediately. To
avoid primary hot air enter into the duct of primary cold air, motorized damper
on the cold duct will be also closed immediately. Mixed air flow measurer will
be installed on the mixed duct.
The air velocity in air ducts will be 10-12m/s for cold air and 15-25m/s for hot
air.
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
116
3.3.2.2 Secondary air system
The system shall provide air for furnace combustion. Cold air from FDFs shall
be forced into trisector regenerative air preheater through the steam coil air
heater which is located in the bypass duct, and hot air shall be sent into
secondary air box and be distributed to furnace for combustion.
Two (2) FDFs will be equipped for each boiler. Cold air liaison duct, which
connect two ducts between FDFs downstream and steam coil air heater
upstream will be set, and hot air liaison duct arranged at air preheater outlet.
Secondary hot air box is special design, when one FDF out of operation, hot
air flow to the boiler four corners will be almost equal, so that stable
combusting and reasonable temperature field in the furnace can be ensured,
and will reduce temperature deviation at two sides of boiler.
Damper and air flow measurer shall be placed at hot air duct of air preheater
outlet, when air preheater is out of operation, the damper shall be closed
automatically.
Two trisector regenerative air preheater will be equipped which primary and
secondary air will be heated in it. Also, water washing system and fire
protection system and soot blowing system will be equipped for GAH.
Forced lubrication oil system (with 2x100% capacity pumps, filters, and
associated piping/ accessories) is provided for air preheater.
The air velocity in air ducts will be 10-12m/s for cold air and 15-25 m/s for hot
air.
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
117
3.3.2.3 Sealing air system
2x100% centrifugal sealing air fans will be equipped in the system, one in
operation and another standby. Sealing air from cold primary air manifold will
be sent into MSMs via seal fan boost. At sealing air fans inlet, air filters and
motorized dampers will be arranged, when one fan is in operation, another’s
inlet damper is closed. If pressure difference of the filter inlet & outlet reaches
to setting value, the filter will clean itself via pressure difference.
3.3.2.4 Flue gas system
The system consists of two ESP and three centrifugal induced draft fans (IDF)
with hydraulic coupling.
Flue gas from economizer will enter into two (2) air preheater, one isolating
damper will set at the inlet of each air preheater. When emergency happens
to one air preheater, the respective damper will be closed. During air
preheater start up or shut down, the damper will be opened or closed.
Flue gas from air preheater enters into ESP with double path, seven electric-
fileds. Each boiler will be equipped with two ESPs. Isolating Guillotine type
gates will be placed at ESP inlet & outlet. Flue gas via ESP, ID Fan & chimney
will be vented into atmosphere.
Isolating dampers will be placed at ID Fan inlet & outlet. When ID Fan failure
happens, it will be overhauled after the dampers closed. During ID Fans
starting up or shutting down, the damper will be opened or closed.
Three (3) ID fans are 2 in operation and 1 standby.
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
118
The fuel gas velocity in gas ducts will be 10-15m/s.
The range of flue gas velocity in flue path in convective heat transfer areas
within the boiler is maximum 10m/s and maximum 9m/s through the air
preheater.
3.4 Calculation results
The results are based on performance coal for one boiler at MCR and it can
adapt the characteristic data range of the coal.
3.4.1 Pulverized coal system
NO. Item Symbol UnitValue
(For one unit)
1 Boiler coal consumption (BMCR) Bg t/h 180.2
2 Hard grove grindability index HGI / 50
3 Maximum Size of raw coal at inlet of mill dmax mm <32
4 Fineness of coal powder mesh 200 % 70
5 Medium speed mill quantity(operate/install) / set 4/6
6 Medium speed mill operating output BF1 t/h 45.05
7 Medium speed mill max output BSJ t/h 60
8 Medium speed mill rated inlet air flow Qv t/h 96.9
9 Primary air temperature at outlet of GAH tkr °C 300
10 Air temperature at inlet of medium speed mill t1 °C 241
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
119
NO. Item Symbol UnitValue
(For one unit)
11 Ratio of air and coal mass at inlet of medium speed mill / kg/kg 2.15
12 Temperature at outlet of medium speed mill tm °C 77
13 Mill reject rate % 1.025
14 Effective volume of each raw coal bunker m3 945
15 Duration for boiler burning at BMCR condition with worst coal– bunker storage h 16.2
3.4.2 Flue gas and air system
NO. Item (one unit) Symbol Unit Value
(For one unit)
1 Theoretical air volume for combustion V° Nm3/kg 4.2243
2 Volume of combustion result at the outlet of furnace V
°y Nm3/kg 5.7535
3 Air temperature at inlet of GAH(PA/SA) t 'kg °C 35/30
4 Air temperature at outlet of GAH(PA/SA) tⅠky/tⅡky °C 300/310
5 Flue gas temperature at outlet of GAH ( corrected) tpy °C 136
6 Flue gas volume at outlet of GAH Vy m3/s 475.3
7 Flue gas excess air coefficient at outlet of GAH Apy / 1.344
3.5 Major Auxiliary Equipments Selection
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
120
3.5.1 Pulverized coal system
Six (6) medium speed mills and six (6) coal feeders will be furnished for each
boiler. These will be of sufficient capacity to attain the MCR of the steam
generator when boiler firing any specified coal with any one (or two) mill out of
service. In other words, when firing the performance coal, four (4) mills will be
in operation and two (2) will be standby, and when firing the worst coal, five (5)
mills will be in operation and one (1) will be standby, together with its
associated feeders. Because of the positive pressure in the mill and coal
feeder, two (2) sealing air fan are furnished to supply the sealing air to avoid
the powder leaking.
The maximum capacity of mill shall be 60 TPH corresponding to 50 HGI, 70%
through 200 mesh and moisture content 15 %.
NO. Item Unit Value
(design coal)
1 Type of MSM HP1003
2 Grindability Index HGI 50
3 Moisture(AR) 15%
4 Powder fineness mesh 200 70%
5 Maximum capacity of mill(HGI=50, 70% through 200 mesh)
t/h 60
6 Minimum capacity of mill t/h 15
7 Mill loading % 76
8 Max. air flow rate t/h 107.2
9 Max. resistance kPa 4.0
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
121
NO. Item Unit Value
(design coal)
10 Inlet temperature of mill ℃ 241
11 Outlet temperature of mill ℃ 77
12 Inlet air/ inlet coal Kg/Kg 2.15
13 Rotary speed r/min 33.01
14 Shaft power of mill (BMCR) KW 366
15 Rated power of motor KW 560
16 Voltage KV 6.6
17 Gravimetric coal feeder t/h 60
18 Coal feed distance (from feeder inlet to feeder outlet) mm 2200
3.5.2 Flue gas and air system
Each boiler will be furnished with two (2) sets of primary air fan,two (2) sets
of forced draft fan and three (3) sets of induced draft fan. These fans will be
designed for outdoor installation. Under normal operation, all of PA Fans and
FD Fans will be in operation, while two (2) of three (3) ID Fans will be in
operation.
The fans sizing are based on the flow and total pressure at BMCR conditions
with a specific margin as below:
PAF, FDF& IDF SIZING DATA SHEET
Design coal worst coal
Sl. No. Segment/ Location sizing
capacity (TB)
two fans operation with 100% BMCR
one fan operation with 60% BMCR
two fans operation with 100% BMCR
one fan operation with 60% BMCR
unit
A PA fan sizing
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
122
Design coal worst coal
Sl. No. Segment/ Location sizing
capacity (TB)
two fans operation with 100% BMCR
one fan operation with 60% BMCR
two fans operation with 100% BMCR
one fan operation with 60% BMCR
unit
calculation
1 Air pressure drops
1.1 PA Fan inlet duct (include the silencer) 248.1 432.5 270.5 517.7 Pa
1.2
Duct & dampers from PA Fan outlet to RAPH inlet 457.6 794 679.9 1316 Pa
1.3
Duct & Dampers from SCAPH to RAPH ( if SCAPH envisaged) NA NA NA NA
1.4 Thru RAPH air side 800 1047 800 1570 Pa
1.5
Duct & Dampers from RAPH outlet to pulverizer 1178.6 1882.8 1638.3 2671.5 Pa
1.6 Thru pulverizer 3500 3280 3600 3180 Pa
1.7
Duct & Dampers from pulverizer outlet to coal burner 4422 4089.6 4553 3948.9 Pa
1.8
Between inlet & throat of air flow measuring device 0 0 0 0 Pa
1.9
Unrecoverable loss across air flow measuring device 0 0 0 0 Pa
1.10 Burner 500 500 500 500 Pa
1.11 furnace negative pressure 40 40 40 40 Pa
1.12 Total loss through system 11067 11986 12003 13665 Pa
2 Air flow calculation 2.1 Coal firing 180.2 117.7 230.7 150.7 t/h 2.2 No of mill in operation 4 3 5 4
2.3
coal flow per mill (inlet/outlet), considering 1.025% mill reject
45.52/45.05
39.75/39.33
46.63/46.14
38.18/37.78 t/h
2.4 HGI 50 50 50 50
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
123
Design coal worst coal
Sl. No. Segment/ Location sizing
capacity (TB)
two fans operation with 100% BMCR
one fan operation with 60% BMCR
two fans operation with 100% BMCR
one fan operation with 60% BMCR
unit
2.5 moisture in coal 15 15 15 15 %
2.6 finess through 200 mesh 70 80 70 80 %
2.7 design mill outlet temperature 77 77 77 77 ℃
2.8 ambient temperature 47 47 47 47 ℃
2.9 cold air density 1.06 1.06 1.06 1.06 kg/m3
2.10 air temperature at outlet of APH 300 259 301 262 ℃
2.11 air coal ratio at mill inlet for transportation of coal (per kg coal)
2.15 2.47 2.12 2.53 kg/kg
2.12 air flow at inlet of each mill 26.92 26.94 27.16 26.56 kg/s
2.13 total air flow to mills 387648 290952 488880 382464 kg/h2.14 mill inlet temperature 241 223 250 220 ℃
2.15 Tempering air for each pulverizer 5.48 3.5 4.61 4.18 kg/s
2.16 total tempering air to mills 78912 37800 82980 60192 kg/h
2.17 air flow at the outlet of APH 308671 253208 405859 322249 kg/h
2.18 APH leakage 76680 36360 82440 36720 kg/h
2.19 air flow at the inlet of APH 385351 289568 488299 358969 kg/h
2.20 feeder sealing total air flow 3084 2313 3855 3084 kg/h
2.21 mills sealing total air flow 30456 15228 30456 20304 kg/h
2.22 total air flow at outlet of PA fan 497803 344909 605590 442549 kg/h
2.23 No of operation fan 2 1 2 1
2.24 PA Fan outlet flow for each fan 65.2 90.4 79.3 116
m3/s
3 PA fan sizing
3.1 PA Fan flow 99.2 m3/s
3.2 flow margin 25 based on worst coal 100%BMCR condition %
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
124
Design coal worst coal
Sl. No. Segment/ Location sizing
capacity (TB)
two fans operation with 100% BMCR
one fan operation with 60% BMCR
two fans operation with 100% BMCR
one fan operation with 60% BMCR
unit
3.3 PA fan pressure sizing 16804 Pa 3.4 pressure margin 40 based on worst coal 100%BMCR condition % 3.5 fan efficiency 85 % 3.6 fan shaft power 1974.2 KW 3.7 motor rating 2500 KW 3.8 fan speed 1480 rpm 3.9 Power supply 50 Hz
B FD fan sizing calculation
1 Air pressure drops (after corrected)
1.1 FD Fan inlet duct (include the silencer) 326.55 341.5 317.03 321.2 Pa
1.2 Duct & Dampers from FD Fan outlet to RAPH 453.3 576.07 408 459.8 Pa
1.3 Thru RAPH air side 800 1071 800 748 Pa
1.4
Duct & Dampers from RAPH to furnace windbox 764.6 539.24 539.2 300.65 Pa
1.6
Between inlet & throat of air flow measuring device 0 0 0 0 Pa
1.7
Unrecoverable loss across air flow measuring deivce 0 0 0 0 Pa
1.8 burner pressure drop (second air) 1100 1000 1100 1000 Pa
1.9 furnace negative pressure 40 40 40 40 Pa
1.10 Total loss through system 3404.4 3487.9 3124.2 2789.6 Pa
2 Air flow calculation 2.1 Coal firing 180.2 117.7 230.7 150.7 t/h
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
125
Design coal worst coal
Sl. No. Segment/ Location sizing
capacity (TB)
two fans operation with 100% BMCR
one fan operation with 60% BMCR
two fans operation with 100% BMCR
one fan operation with 60% BMCR
unit
2.2 ambient temperature 47 47 47 47 ℃
2.3 cold air density 1.06 1.06 1.06 1.06 kg/m3
2.4 theoretic air flow (per kg coal) 4.2243 4.2243 3.2707 3.2707
nm3/kg
2.5 excess air at outlet of furnace (by volume) 1.25 1.26 1.25 1.25
2.6 total air flow at mill outlet 111.6 83.8 140.7 110.2 kg/s
2.7
total combusion air flow at the inlet of furnace (considering 20% excess air at furnace inlet) 323.3 211.6 320.1 208 kg/s
2.8 air temperature at outlet of APH 310 273 314 279 ℃
2.9 air flow at the outlet of APH 211.6 127.8 179.4 97.8 kg/s
2.10 APH leakage 5.4 3.3 4.5 3.2 kg/s
2.11 air flow at the inlet of APH 217 131.1 183.9 101 kg/s
2.12 No of operation fan 2 1 2 1
2.13 FD Fan outlet flow for each fan 102.3 123.7 86.7 95.2
m3/s
3 FD fan sizing
3.1 FD Fan flow 122.8 m3/s
3.2 flow margin 20 based on design coal 100%BMCR condition %
3.3 FD fan pressure sizing 4426 Pa 3.4 pressure margin 30 based on design coal 100%BMCR condition % 3.5 fan efficiency 81.28 % 3.6 fan shaft power 678 KW 3.7 motor rating 800 KW 3.8 fan speed 1470 rpm
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
126
Design coal worst coal
Sl. No. Segment/ Location sizing
capacity (TB)
two fans operation with 100% BMCR
one fan operation with 60% BMCR
two fans operation with 100% BMCR
one fan operation with 60% BMCR
unit
3.9 Power supply 50 Hz
C ID fan sizing calculation
1 Flue Gas pressure & Pressure Drops
1.1 Furnace Pressure (Suction)
1.2 Drop across Superheater
1.3 Drop across Reheater
1.4 Drop across economizer
1.5 Drop across RAPH ( Gas side)
Total: Max. 2400
Total: max. 3570
Total: Max. 2400
Total: max. 3582
Pa
1.6 Drop across ESP 245 245 245 245 Pa
1.7 Drop thru Ducts & Dampers from
1.7.1 RAPH outlet to ESP Inlet 226.4 129.7 232.2 131.1 Pa
1.7.2 ESP Outlet to ID fan inlet 357.5 436.9 345.5 431.6 Pa
1.7.3
ID Fan outlet to stack outlet (include stack effect of chimney) 336.4 93 314 60 Pa
1.8 furnace negative pressure 40 40 40 40 Pa
1.9 Total drop through system 3605.4 4514.5 3576.7 4489.6 Pa
2 Flue gas flow calculation
2.1 theoretic flue gas flow (per kg coal) 4.6804 4.6804 3.6605 3.6605
nm3/kg
2.2 Flue gas at RAPH Inlet 666 408.1 666 405.6 m3/s
2.3 Flue gas at RAPH Outlet 475.3 297.9 478.9 299
m3/s
2.4 total No of fans 3 3 3 3
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
127
Design coal worst coal
Sl. No. Segment/ Location sizing
capacity (TB)
two fans operation with 100% BMCR
one fan operation with 60% BMCR
two fans operation with 100% BMCR
one fan operation with 60% BMCR
unit
2.5 ambient temperature 47 47 47 47 ℃
2.6 flue gas temperature at the outlet of APH (corrected) 136 128 140 133 ℃
2.7 EA at the outlet of APH 1.35 1.328 1.35 1.317
2.8 gas flow at the outlet of APH 475.3 297.9 478.9 299
m3/s
2.9 EA at the inlet of ESP 1.38 1.338 1.38 1.327
2.10 gas flow at the inlet of ESP 482.9 299.6 486.4 300.6
m3/s
2.11 EA at the outlet of ESP 1.39 1.348 1.39 1.337
2.12 gas flow at the oltlet of ESP 485.5 301 488.9 302
m3/s
2.13 EA at the inlet of ID fan 1.42 1.348 1.42 1.337
2.14 gas flow at the inlet of ID fan 493.1 301 496.4 302
m3/s
2.15 gas temperature at the inlet of ID fan 131.6 126.8 135.4 131.7
2.16 gas density 0.8422 0.8469 0.8319 0.8341 kg/m3
2.17 No of operation fan 2 1 2 1
2.18 ID Fan inlet flue Gas flow per fan 247 301 248 302
m3/s
3 ID fan sizing
3.1 ID Fan flow 303.2 m3/s
3.2 flow margin (considering 10 deg.C temperature margin) 20 based on design coal 100%BMCR condition %
3.3 ID fan pressure sizing 4787 Pa 3.4 pressure margin 30 based on design coal 100%BMCR condition % 3.5 fan efficiency 87.9 89.3 87.4 89.3 87.4 % 3.6 fan shaft power 1747.8 1051.7 1653.6 1047.9 1649.6 KW 3.7 motor rating 2240 KW 3.8 fan speed 950 rpm
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
128
Design coal worst coal
Sl. No. Segment/ Location sizing
capacity (TB)
two fans operation with 100% BMCR
one fan operation with 60% BMCR
two fans operation with 100% BMCR
one fan operation with 60% BMCR
unit
3.10 Power supply 50 Hz
D Excess Air
1.1 At burners 20 19 20 18 %
1.2 At Econimizer Outlet 25 26 25 25 %
1.3 At RAPH Outlet 35 32.8 35 31.7 %
1.4 At ID Fan inlet 42 34.2 42 33.7 %
For PA fans, FD fans and ID fans, the bearing of rotor will be ball bearing,
and this technology is from TLT, Germany. The bearing for the fans will be
imported from SKF or FAG. The blade of PA fans is flat plate blade, which is
suitable for low flux and high pressure media. Materials adopted for fans as
below:
component FD fans PA fans ID fans
Fan housing and inlet box Q235-A Q235-A Q235-A
Shaft 42CrMo 35CrMo 35CrMo
Impeller hub 15MnV - -
Impeller blade HF-1(TLT standard) - -
Two (2) electrostatic precipitators (double-pass, seven electric field) is
equipped for each boiler, The ESP remove particulate from the boiler flue gas
to achieve a guaranteed outlet emission of less than 70 mg/Nm3 with (n-1)
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
129
fields in each stream of ESP in operation when fired with design coal and flue
gas flow rates from 25 to 110 percent of maximum continuous rating (MCR),
and less than 100 mg/Nm3 when fired with worst coal and flue gas flow rates
from 25 to 110 percent of MCR with one field out of service. The collection
efficiency of ESP with (n-1) field of each stream in service is not less than
99.94% when firing worst coal. Air in leakage through ESP of the total gas
flow is less than 1%.
No Electrostatic precipitator Unit Value
(design coal)
Value
(worst coal)
1 Double-pass, 7 electric fields
2 Flue gas flow (including 10% marginand 10℃ margin)
m3/h/set 979669 986524
3 flue gas temperature(including 10 ℃margin) ℃ 144 148
4 Inlet dust concentration g/Nm3 45.8 79.4
5 Outlet dust concentration mg/Nm3 20 23.8
6 Specific collecting area (Based on 400 mm spacing)
m2/m3/sec
220.7 (294.3, with 300 spacing)
7 Max Pressure drop across ESP at the guarantee (operating) point flow
mmwc 25 25
8 Efficiency of ESP
A With (n-1) field in service % 99.94 99.94
B With n field in service % 99.96 99.97
3.5.3 Boiler Igniting and Fire Stabilizing Oil System
The oil of the boiler igniting is diesel oil and fire stabilizing is HFO/LSHS, and
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
130
the boiler ignition mode is high-energy ignition.
The system will be furnished with two 200m3 HFO/LSHS daily oil tank, one
50m3 LDO daily tank for both units, Two motor-driven HFO oil transfer pumps
per unit (one operation and another standby), two motor-driven LDO oil
transfer pumps per unit and other associated equipments per unit. They are
located in the daily oil tank area.
HFO/LSHS screw type pump: Q=30t/h (2x100%)
Motor-driven LDO feed pump (centrifugal type): Q=10t/h (2x100%).
4 THERMAL SYSTEM AND SELECTION OF AUXILIARY EQUIPMENT
4.1 Design principle of Thermal System
The thermal system will ensure the security, economy and flexibility of the unit.
All of the systems are unit system except auxiliary steam system.
4.2 System Description 4.2.1 Main steam, reheat steam and bypass system
The pipe sizing shall be as per ASME B31.1 and velocities shall be limited to
the values mentioned in specification.
In addition to above, pressure drop in main steam line shall not be more than
90% of the allowable pressure differential between superheater outlet header
and HP turbine inlet valves at BMCR. Similarly, combined pressure drop in
cold and hot reheat piping will not exceed 90% of the pressure differential
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
131
between HP turbine exhaust and IP turbine inlet valves minus the reheater
drop. The pressure drop in the complete reheat line from HPT exhaust to IPT
inlet shall not be more than 10% of the pressure at HPT exhaust.
4.2.1.1 Main steam system
Main steam system will convey superheated steam from the superheater
outlet to the HP main steam stop valve. Main steam is unit system. Main
steam flow through single pipe from outlet of boiler superheater header, and
then divided into two branches and connects to left and right main HP steam
stop valve separately.
1) A Motor operated Main steam isolation valve with motor operated integral
bypass valve is set on main steam pipe near boiler outlet for boiler hydraulic
test as well as for normal operation.
2) One branch leads to gland steam system as HP steam source when normal
gland steam pressure is too low and one branch leads to turbine casing steam
heating header as heating steam source before turbine startup, another
branch leads to auxiliary steam header when the cold reheat pipe pressure is
inadequate or not available..
3) To prevent water from entering turbine, drain system is set to discharge
condensate water of main steam pipe during warm-up and shut-down. Drain
points are set at the lowest points on main steam pipe. A pneumatic drain
valve and a hand-operated valve are set on drain pipe of each drain point.
Drain water is led to drain flash tank. All drains including drain pot shall be
checked with respect to ASME TDP guideline for turbine water damage
protection.
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
132
4) Two spring safety valves, one solenoid PCV and two motorized venting
valves are set on main steam pipe near superheater outlet.
4.2.1.2 Reheat steam system
Reheat steam system will convey cold-reheat steam from HP casing exhaust
spout to inlet of boiler reheater and convey hot-reheat steam from outlet of
reheater to IP main steam stop valve. Reheat steam is unit system.
One cold reheat steam pipe is connected from turbine HP casing exhaust pipe
and divided into two pipes in front of boiler, then connect to two inlets of boiler
reheater header separately.
Two hot reheat steam pipes are connected at two end of outlet header of
boiler reheater and join one pipe at front of boiler, and divided into two pipes
again in front of turbine, then connect with left and right IP steam stop valve.
1) To prevent steam from flowing back into turbine, one pneumatic check
valves is provided on cold-reheat pipes;
2) Desuperheaters are set on the pipe of reheater inlet, to adjust steam
temperature of reheater outlet under emergency condition. Desuperheating
water come from intermediate stage extraction of BFP.
3) Hydraulic test valve is set on each cold-reheat steam pipe near reheater
inlet to prevent pressurized water entering cold-reheat pipe during hydraulic
test of boiler.
4) To prevent water entering turbine, one drain pot is set on the pipe near HP
casing exhaust spout. A pneumatic valve is set on drain pipe to automatically
control drain water into condenser in time.
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
133
5) Two spring safety valves are set on each cold-reheat pipe near reheater
inlet.
6) A hydraulic test valve is set on each hot-reheat pipe near reheater outlet to
make sure that the pressurized water is stopped during boiler reheater
hydraulic test and can’t enter into the hot reheat pipes.
7) One pipe connecting the outlet of HP bypass valve and the inlet of LP
bypass valve is set to form the heat circuit by pressure difference which is
able to warm the outlet of HP bypass valve and pipe, the inlet of LP bypass
valve and pipe.
8) Spring safety valves are set on hot-reheat pipe near reheater outlet, its set
pressure is lower than the spring safety valve on cold-reheat steam pipe near
reheater inlet, so the former will open before the later when over pressure
happens to ensure enough steam through reheater and avoid over heating of
reheater.
9) Drain points are set on hot-reheat steam pipe branches after tee to remove
condensate water during startup and shut-down. Drain water enters into
condenser. A pneumatic valve and a hand-operated valve are set on each
drain pipe.
4.2.1.3 Bypass steam system
The capacity of HP bypass system is 60% BMCR. High-pressure (HP) bypass
stations shall be preferably DRE type CCI make HP & LP bypass valves shall
be of angle type and combined throttle cum spray valve. This system can
convey main steam bypass HP-casing to cold-reheat piping and convey hot-
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
134
reheat steam bypass IP&LP-casing to condenser when unit startup, shutdown
and other various operating modes. TG set is capable of operating on house
load during sudden total export load throw-off and in the event of turbine trip
and generator breaker open HP-LP bypass system will open automatically.
The leakage class of valves shall be minimum class V. For Spray valve Trim
exit velocity of liquid shall not exceed 30m/s.
1) Desuperheating water of HP bypass is from feed water system, one control
valve and one stop valve are set on desuperheating water pipe.
2) LP-bypass system is connected with HP-bypass system in series to
achieve the function of whole bypass system.
3) One drain pot is set at the lowest point downstream of LP-bypass valve. A
pneumatic valve is set on each drain pipe.
4) Desuperheating water of LP-bypass is from condensate water system.
Table 4.2.1
Item Name Diameter Material Maximum velocity as
allowable in table 5.10-1 (m/min)
1 Main steam pipe ID368.3×41.275 A335P91 5300
ID273.05x30 A335P91 3700
2 Hot reheated steam pipe ID635X31 A335P22 5600
ID508×24.8 A335P22 5600
3 Cold reheated steam pipe φ812.8×22.225 A106B 5600
φ558.8×16 A106B 5600
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
135
4.2.2 Feed-water system
HP feedwater system is unit system. The function of this system is to pump
deaerated feed-water from deaerator water tank to inlet header of boiler
economizer. Feed water is heated to the given temperature in HP-heaters by
turbine extraction steam to improve heat efficiency of the units. There are
three 50% capability motorized variable speed feedwater pump in this system,
during normal operation, two pumps work and one pump is standby.
The main boiler feed pump and booster boiler feed pump shall be manufac-
tured of following or superior materials
a) Casing barrel: Forged carbon steel ASTM A266 C1 I or 1-1/4 chromium
STM A217 WC6
b) Discharge head: Forged carbon steel ASTM A266 Cl I or carbon steel plate
ASTM A515 Gr.55
c) Casing: SS ASTM A743 Gr.A-6NM or CA-15 (booster boiler feed pump)
d) Pressure retaining bolting:
i) External: Alloy steel ASTM A193 Gr.B5,B7, or B7M
ii) Internal: SS ASTM A193 Gr.B8
e) Pressure retaining nuts:
i) External: Alloy steel ASTM A194 Gr.1,2, 2H or 7
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
136
ii) Internal: SS ASTM A194 Gr.8
f) Shaf: SS ASTM A276 Type 410 Condition T.
g) Impeller: SS ASTM A743 Gr.CA-6NM or CA-15
h) Wearing rings, throttle bushings, shaft sleeves:
i) Stationary: SS ASTM A582 Type 416 Condition H parts
ii) Rotating: SS ASTM A582 Type 416. parts
High-pressure sealing joint surfaces on the forged steel barrel and head, and
areas subject to high water velocity, shall be lined with an overlay of AWS
A5.9, filler metal Type ER309, stainless steel deposited by welding.
The full flow regulating valve is located in the major pipe of feed water control
station, which shall be used in conjunction with the variable speed drive to
provide adequate flow control. A full flow bypass line with adjustable orifice
and motorized inching will be provided also.
30% BMCR bypass control valve is provided for low load operation and
startup.
There are three HP heaters. HP heaters are horizontal type. Bypass piping
will be provided to divert feedwater flow around any of the high-pressure
heater for heater isolation of the respective each unit. All bypass and isolation
valves will be motor operated.
Feedwater system can be divided into three parts: LP feedwater, IP feedwater,
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
137
and HP feedwater pipes.
1) LP feedwater pipes
Pipes between the outlets of feedwater tank and the inlets of booster pumps
are called “LP feedwater pipes”. There are motorized valve and strainer on
each pipe. When startup, the strainer can separate the welding slag,
impurities etc., which were accumulated in feedwater tank, and LP feedwater
pipes during erection and maintenance to protect feedwater booster pumps.
2) IP feedwater pipes
Pipes between the outlets of booster pumps and the inlets of feedwater
pumps are called “IP feedwater pipes”. Each pipe has a flow metering nozzle
to measure the feedwater flow at the inlet of feedwater pump in order to
control opening and closing of minimum flow unit at the outlet of feedwater
pump. There are also filters in these pipes in order to protect feedwater
pumps.
3) HP feedwater pipes
Pipes between the outlets of feedwater pumps and inlet header of boiler
economizer are called “HP feedwater pipes”, which pass through HP heaters.
There are one check valve and one motorized gate valve at the outlet of each
feedwater pump. In order to prevent cavitation of booster pump, one
recirculation pipe is extracted from the feedwater pipe and connected to the
deaerator which has one minimum flow unit including a pneumatic control
valve, two manual valves and one check valve. Signal of the minimum flow
unit comes from the flow metering nozzle at the outlet of booster pipe. Each
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
138
feedwater pump has a recirculation pipe which is connected to deaerator.
The interstage extractions from each feedwater pump are collected together
and flow to the reheater attemperator as emergency desuperheating water to
adjust steam temperature of reheater. Superheater and Reheater spray at
100% TMCR condition shall be Max. 6% of main steam flow & Max. 3% of
reheat flow within the specified range of coal and entire operating range
One pipe is branched from outlet manifold of feedwater pumps and connected
to boiler superheater primary and secondary spray attemperator. Another pipe
is branched for HP bypass control valve. The former adjust superheating
steam temperature and the latter adjust main steam temperature to cold
reheat steam system.
The feedwater control station is located between outlet of HP heaters and inlet
header of boiler economizer.
The full flow regulating valve is located in the major pipe of feed water control
station, and a full flow bypass line with adjustable orifice and motorized
inching will be provided also. One check valve is located at inlet pipe of
economizer.
The capacity of bypass is 30% rated feedwater flow which adjusts feedwater
flow when unit startup and low load operation.
One pipe is branched from the economizer inlet heater to drum as the
economizer recirculating water pipe.
Table 4.2.2
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
139
Item Name Diameter Material Range of velocity(m/s)
1 HP feed water common pipe φ355.6×30 WB36 2-6
2 HP feed water branch pipe φ244.5x20 WB36 2-6
4.2.3 Extraction steam system
The system extracts steam from steam turbine to specified heating device and
increases the temperature of condensate water and feed-water so as to raise
thermal efficiency of the power plant.
There are 8 stages non-adjustable extraction of the steam turbine. Extraction
No.8&7&6 supply steam to three (3) HP heaters, extraction No.5 supplies
steam to deaerator. Extraction No.4&3&2&1 supply steam to four (4) LP
heaters. LP heaters No.2 and No.1 are combined heaters which are located at
neck of condenser.
Power assisted check valve and motor-driven isolation valve are set in each
extraction pipe except No2&1 extraction pipes. To prevent condensate water
entering into steam turbine to harm it during startup, shutdown & low load,
drain water pipe is set at the low point of each extraction pipe, near the valves.
4.2.4 Condensate water system
The system conveys condensate water from hot well of condenser to
deaerator through polishing unit, gland steam condenser and four LP heaters
to ensure safe operation and enhance circulation heat efficiency. Beside these,
the system also provides desuperheating water, make-up cooling water and
other miscellaneous water requirements.
The system is unit system. There are three (3) 50% capability vertical
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
140
Condensate extraction pumps and one condensate polishing unit in the
system.
Main control valve, auxiliary control valve and their bypass valve are set on
condensate water pipe before No.1 LP heater to ensure water level control of
deaerator under all kinds of condition.
Recirculation pipe at the gland steam condenser outlet pipe is set for the
minimum flow when Condensate extraction pump is startup or the unit runs at
the low load. One water discharge pipe branches from No.4 LP header outlet
pipe is set to discharge unqualified water during startup.
Return water pipe to condenser make-up water tank (surge tank) from the
outlet of polishing plant is set for collecting water when the condenser hot well
water level is high.
There are branches at the low pressure desuperheating water pipe such as
desuperheating water pipe to fuel oil sweeping steam desuperheater turbine
gland steam desuperheater, LP-bypass desuperheater, third-stage pressure
and temperature reducer, LP casing spray, HP emergency drain flash tank;
and also the make-up water pipe of closed circuit cooling water expansion
tank.
Pipe is set to generator stator cooling water tank and vacuum pump from
condensate water.
4.2.5 Heater drains and vents system
The functions of the system is recovering condensed water from heating
steam of each HP heater and overflow & drain water of the deaerator,
recovering condensed water of LP heater and gland steam condenser,
removing non-condensable gas in HP heaters, LP heaters and deaerator. The
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
141
normal cascade HP heater drain pipes from No.8, No.7 and No.6 HP heater to
deaerator, LP heater drain pipes from No.4,No.3,No.2 and No.1 LP heater to
condenser. Emergency drain pipe from each HP heater to HP emergency
drain flash tank, and LP heaters to condenser. Non-condensable gas pipes
from each HP heaters to deaerator and from each LP heaters to condenser
and from deaerator vent to atmosphere. Over flow pipe will maintain normal
water level of feed-water tank and discharge pipe can empty water in case of
maintenance. Control valve is designed in each drain pipe to control water
level.
Normal drain water from HP heaters cascade to deaerator. Emergency drain
pipes are set for each heater and respectively led to HP emergency drain
flash tank in order to ensure smooth drain and keep normal level in case that
high water level in HP heaters appears or HP heater is out of service.
Normal drain water from LP heaters cascade to condenser; Pipes for
emergency drain water of each LP heater can ensure smooth drain to
condenser when water level in LP heater is high or at low load or its
downstream LP heater(s) is (are) out of service.
Control valve is designed in each drain pipe of HP&LP heaters to control
water level.
Multi-stage water sealing device is set in the drain piping of gland steam
condenser to ensure smooth drain to main condenser in all operating
conditions.
4.2.6 Auxiliary steam system
Auxiliary steam system provide steam to deaerator when start-up, low-load
and trip, provide steam to boiler bottom heating, provide steam to turbine
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
142
gland steam system when start-up and standby, provide steam to soot-blower
when air preheater start-up, and provide steam to steam air heater and fuel oil
system.
Auxiliary steam is taken from cold reheat pipe at normal operation. During unit
startup, shutdown and when cold reheat pipe pressure is inadequate, the
steam is taken from main steam pipe. When the unit 1 start up, start-up steam
will be provided. There is a interconnection of auxiliary steam headers
between the two units, so the auxiliary steam can be provided when one unit
is startup and another is in service. Steam header has continuous drain pipes,
it can drain condensed water of header to condenser.
One auxiliary steam header is provided for each unit. The pressure of auxiliary
steam header is about 1.20MPa and temperature is about 320 0C in normal
operation. Two safety valves are set on the header with different pressure
setting.
The source of auxiliary steam come from cold reheat steam pipe at normal
condition and main steam pipe when unit startup, shutdown or cold reheat
pipe pressure is inadequate. However if steam is required for pre
commissioning/ commissioning of first unit, auxiliary steam source shall be
arranged.
4.2.7 Vacuum system
The function of this system is extracting the non-condensable gas from
condenser and maintain rated vacuum in condenser during normal operating
condition. The vacuum will be break to protect turbine during emergency. Two
vacuum pumps are set in this system. Before unit startup, two pumps will
operate in parallel to establish vacuum as fast as possible (25 minutes).
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
143
Under normal operation, one pump is in operation and another is standby.
Mixture of steam and air is extracted from condenser. Uncondensed gas
exhaust to atmosphere.
There is one vacuum breaker pipe at neck of condenser. During the unit load
rejection, air admission valve will be opening to break vacuum in condenser
and decrease rotating speed of turbine, then shorten time of turning by inertia
to protect turbine. This will be used only in emergency case.
4.2.8 Condenser tube cleaning system
Debris filters and condenser on load tube cleaning system are provided before
each circulating water inlet to condenser. The complete condenser tube
cleaning system shall be provided for each pass of condenser (Total two sets
per unit) each set comprising of one rubber ball recirculating pump, one ball
screen and one ball collector and other accessories including common PLC
for two sets.
4.2.9 Closed cycle DM water system
Closed cooling water shall be used to turbine auxiliary equipments and boiler
auxiliary equipments such as generator hydrogen cooler, turbine lube oil
cooler, generator stator water cooler, BFP motor cooler, the bearing of
equipments, etc
The closed cooling water for auxiliary equipments is demineralized water
Chemical department will guarantee the water quality. The demineralized
water is pumped by the closed cooling water pumps and is sent to the heat
exchanger in which the demineralized water is cooled by the Aux. cooling
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
144
water. Demineralized water will be sent to the equipments and return to the
inlet of the cooling water pumps. An expansion water tank with volume 10m3
is set to meet the needs of volume change of cooling water caused by water
temperature. The water tank will be arranged at a high place to gives the
closed cooling water pump sufficient NPSH. Make-up water of the system is
from outlet of condensate water pump in normal condition and from
condensate make-up water system in emergency condition. The make-up
water is led to expansion water tank with control valve for water tank level set
in the pipe.
4.2.10 Boiler blowdown and drain system
1) Continuous blowdown system
Drum will continuously blowdown some unqualified boiler water to continuous
blowdown tank to separate steam and water, steam flow into deaerator and
water is discharged to intermittent blowdown flash tank. When continuous
blowdown flash tank is failure during operation, blowdown water will flow
through bypass to intermittent blowdown flash tank directly. If quality of boiler
water is getting worse, this bypass can also be used to increase continuous
blowdown water flow.
2) Boiler intermittent blowdown system
According to quality of boiler water, the water accumulated in bottom headers
of boiler with some deposits will be discharged intermittently. This water will
be discharged to intermittent blowdown flash tank directly. After steam water
separate in tank, steam is exhausted to atmosphere. The water in intermittent
blowdown flash tank then discharge to a concrete pit underground and mixed
with cooling water there, then discharged out.
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
145
3) Drainage and discharge system
Drainage and discharge pipes of each header would collect together to
drainage manifold in boiler house during startup and shutdown, and then
water is discharged to boiler intermittent blowdown flash tank.
4.2.11 Steam turbine lube oil and Lube oil handling system
Steam turbine lube oil system will supply lube oil to the bearing of steam
turbine and generator, with main oil tank, oil pumps, oil coolers etc.
4.2.12 Lubrication Oil System
The function of the lubrication system is to :
Provide oil to lubricate the turbine and generator journal bearings .
Provide oil to lubricate the thrust bearing
Provide oil to lubricate the turning gear .
Provide oil pressure for the generator hydrogen seal oil system .
Provide oil pressure for the governor system
The lubrication oil system is a closed system using oil stored in a reservoir
which is pumped to various points of use .the lubrication system uses both
shaft-driven and motor-driven pumps .A shaft-driven pump in the turbine
governor pedestal ,together with oil ejector in the reservoir ,pumps the oil
when the turbine is operating at or near rated speed .Motor-driven pumps are
used when the main oil pump and oil ejector cannot supply sufficient oil
pressure. The system uses two shell-and-tube oil coolers to regulate the
temperature of the lubricating oil system for the turbine generator unit consists
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
146
of the following major components:
Lubrication oil reservoir :
Turbine shaft driven main oil pump oil ejector
Auxiliary motor driven oil pumps
Vapor extractors
oil coolers
Oil piping
Protective devices
Bearing lift oil system
The lubrication oil reservoir is a steel tank in which the lubrication oil is stored.
Mounted on the reservoir are the auxiliary motor driven pumps, vapour
extraction system, level sensors, pressure transducers, and pressure
gages .the oil ejector uses high-pressure oil from the main oil pump discharge
to pick up oil from the reservoir when the unit is operating at or near rated
speed .Strainers on the oil ejector intake ,auxiliary oil pump suctions ,and oil
return drain help to prevent particle contaminants from circulating through the
system. The Reservoir is provided with man way access openings on the top
of the shell and a drain connection on the bottom.
The main oil pump is a volute-type centrifugal pump mounted horizontally on
the turbine extension shaft in the governor pedestal area. At or near rated
turbine speed, the main oil pump supplies all of the oil requirements of the
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
147
lubrication system. Provide oil pressure for the governor system and provides
two source of backup for the generator hydrogen seal oil system.
The oil ejector is mounted inside the oil reservoir. The inlet is supplied with
high-pressure oil from the discharge of the main oil pump when the turbine
generator is at or near rated speed. One outlet, the oil is directed through the
oil coolers to the turbine generator bearings. The other outlet supplies the inlet
side of the mail oil pump with oil.
The bearing oil pump (BOP) is an AC motor-driven centrifugal pump, vertically
mounted on the top of plate of the oil reservoir which is used at startup and
shutdown. During startup, the BOP is placed in service before the unit is put
on turning gear operation. It stays in service until the main oil pump can
satisfy the system oil requirements.
The emergency oil pump (EOP) is a DC motor-driven centrifugal pump which
is identical to the BOP except for the motor. The EOP serves as a backup to
the BOP in case of AC power failure.
The seal oil backup pump (SOB) is an AC motor-driven gear pump,
horizontally mounted on the top of the oil reservoir which is used during
startup and shutdown of the turbine generator when main oil pump discharge
pressure is too low to meet the oil pressure for the governor system and the
generator seal system high-pressure oil backup requirements.
Two vapor extractors are supplied for the reservoir, one vapor extractor is
normally operating and the other vapor extractor is on standby. The main
function is to remove oil vapors and maintain a slight vacuum at the turbine
pedestal, bearing housings, oil reservoir, and oil guard piping system.
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
148
The lubrication oil system includes two full-size oil coolers to maintain an
acceptable temperature range of oil to the bearings while the system is in
operation. The coolers are identical in construction. One cooler is used during
normal operation and the other cooler is kept on standby. A three-way transfer
valve between the two coolers director oil flow from reservoir to the selected
cooler.
Design basis of oil system
The Main oil tank capacity shall provide a minimum of 8 minutes retention
time. There shall be a minimum of 0.023 m2 of free oil surface for each lpm of
normal oil flow.
Turbine unit oil purification system shall be of centrifuge type. The hourly
conditioning capacity shall be equivalent to 20 percent of the combined
capacity of the main oil tank at operating level plus the oil in the lubricator
system that flows back into the main oil tank during a shutdown of the turbine
each hour. The equipment shall be designed to meet all lube oil purity
requirements established by the turbine generator manufacturer and ASME
Standard 118. The oil conditioning equipment shall be designed to provide for
removal of particulate matter greater than 10 microns absolute and all free
water in accordance with ASME.
In addition to unit oil purification ( centrifuge type) , a common turbine oil
purification system for both unit comprising of Dirty oil tank, Clean oil tank,
Purification system, 2x100% capacity pumpsets shall be provided.
Lube oil handling system will handle the unqualified lube oil before unit startup
or under normal operation. The lube oil volume of steam turbine is 32m3, so a
48m3 dirty oil tank and a 48m3 clean oil tank is set in this system, with oil
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
149
purifier and lube oil transfer pump.
A permanently mounted lubricating oil flushing pump shall be provided. This
pump shall be integral with to the lubricating oil reservoir. All accessories
including motor, piping, valves shall be included along with duplex filters
having online cleaning facility.
4.3 Major Auxiliary Equipment Selection 4.3.1 Feed-water pump
Each unit will be furnished with three 50% capacity motor-driven variable
speed feed-water pump with hydraulic coupling. Two pumps are working at
normal operation and one pump is standby. Three booster pumps are set for
each feed-water pump.
The capacity of the pumps is regulated by throttling pump discharge across a
feedwater regulator. The pumps are capable of operating satisfactorily at
deliveries ranging from minimum recirculation flow to the maximum specified.
The pumps furnished for each installation is operate satisfactorily both in two
pump parallel operation and single pump operation and when bringing in or
taking a pump out of service with one or two other pumps in service.
During startup and low load operation, when the variable speed drive cannot
provide the required feedwater flow control, a low load regulating valve is
used. The low load regulating valve is bypassed, and the full flow regulating
valve is used in conjunction with the variable speed drive to provide adequate
flow control.
Boiler feed pumps design is based on 105% of BMCR flow and the pressure
is corresponding to 103% of highest safety valve set pressure plus other
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
150
losses of the system. Pump is designed for complete frequency range of 47.5
to 51.5 Hz during normal operation. Pump and motor are provided with online
vibration monitoring system and bearing metal temperature measurement.
BFP SIZING DATA SHEET
No Name Symbol Unit Calculation & Remark BMCR TMCR
(3%MU)
Technical evaluation sheet
A BFP inlet suction flow
1 Maximun steam flow G1 t/h
HBD from Shanghai steam turbine works
1025 935.696
2 BFP galnd seal discharge and injection flow difference
G2 t/h 2 2
3 Interstage flow for RH spray G3 t/h
Data from Shanghai boiler works Co.ltd
42 42
4 Total suction flow of BFPs G4 t/h G4=G1*110%+
G2+G3 1171.5 1073.2656
5 Feedwater specific volume υ m3/kg
According to HBD 0.00110 0.00110
6 Feedwater density ρ kg/m3 ρ =1/υ 909.09 909.09 7 Capacity of each BFP G t/h G=G4/2 585.75 536.6328 Q m3/h Q=G*υ *1000 644.33 590.30 BFP suction flow m3/h 650.00 590.00
8 Interstage flow of BFP Q1 m3/h
Q1=G3*υ*1000/2 23.10 23.10
m3/h 30.00 30.00
9 BFP booster pump suction flow Q2 m3/h
650 590
*** According to technical evaluation sheet,BFP outlet flow shall be 105%BMCR flow.
BFP outlet flow G‘ t/h G=1.05x1025/2 538 Q’ m3/h Q=G'*υ *1000 592 BFP suction flow Q m3/h Q=Q'+Q1 615 m3/h 620
B BFP head 1 Pipe and equipments pressure drop
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
151
No Name Symbol Unit Calculation & Remark BMCR TMCR
(3%MU)
Technical evaluation sheet
a Pipe pressure drop from deaerator tank outlet to economizer inlet
△ PPIPE Mpa △ PLP+△ PIP+△PHP
1.327 1.327
Mpa Considering 20% margin 1.592 1.592
Coefficient for pressure drop calculation
Gate valve 8.4 8.4 Control valve 50 50 Suction strainer 2.5 2.5 Flow nozzle 9.33 9.33 b Equipment pressure drop
HP heaters △PEQUIP
Mpa 0.1*3 (3 HP heaters) 0.3 0.3
Total pressure drop from deaerator tank outlet to ecoonmizer inlet
△ P1 Mpa △ PPIPE+△PEQUIP
1.892 1.892
2
Water differential pressure between economizer inlet and deaerator tank normal water level
△ P2 Mpa (34.6-16.4)/100 0.182 0.182
3 Economizer inlet feedwater pressure at MCR condition
△ P3 Mpa According to data sheet from boiler works
19.27 18.83
4 Rated working pressure of deaerator(neagative) △ P4 Mpa
From HBD -0.8346 -0.7703
Total head of BFP △ P Mpa
△ P=△ P1+△P2+△ P3+△ P4 20.510 20.134
*** According to technical evaluation sheet,BFP discharge head shall be 103% of highest safety valve set value plus other losses.
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
152
No Name Symbol Unit Calculation & Remark BMCR TMCR
(3%MU)
Technical evaluation sheet
Discharge pressure P MPa
1.03*20.4+1.892+0.182+0.392 23.48
Head △ P MPa 23.48-0.8346 22.64
C BFP sizing result Head H MPa 20.510 20.134 22.64 Suction flow Q m3/h 650.00 590.00 620.00 Note: all these data shall be submitted to manufacturer for the selection of BFP.
Below data is furnished by BFP vendor. 1 Pump
a Booster pump Style FA1D56A
Flow m3/h 650 590 620 Head m 102.15 104.58 103.41 Efficiency % 81.91 80.31 81.2 NPSHr m 3.79 3.55 3.66 Speed r/min 1490 Shaft power kW 197.32 187.89 192.2 b feed pump Style FK6D32M Inlet flow m3/h 650 590 620 Outlet flow m3/h 620 560 590 Head m 2239.3 2182.9 2481.66
Efficiency % 82.02 82.48 82.7
NPSHr m 34.81 30.03 33.1
Speed r/min 5357 5167 5491
Discharge pressure MPa(g) 21.51 21.06 23.64
Shaft power kW 4215.86 3718.92 4416.9
Interstage pressure MPa(g) 11.51 11.29 12.59
Interstage flow m3/h 30 30 30
2 Motor
Rated power Kw 5600
Rated voltage Kv 6.6
Speed r/min 1490
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
153
No Name Symbol Unit Calculation & Remark BMCR TMCR
(3%MU)
Technical evaluation sheet
Frequency Hz 50
The pump shall be designed to operate satisfactorily under the following
conditions:-
a) During rapid load pickup, when the feedwater at the motor driven boiler
feed pump inlet changes from the minimum to the maximum operating
feedwater temperature within 8 minutes.
b) During rapid load rejection, when the feedwater at the motor driven boiler
feed pump inlet changes from the maximum to the minimum operating
feedwater temperature within 15 seconds.
c) During hot restart after a unit trip.
d) During cold startup of the pump.
The suction specific speed of both the booster and main boiler feed pumps
shall be limited to the more restrictive of the following :
a) 12,000 based on NPSH required at 3 percent reduction in first stage head
while operating at the pump best efficiency point with maximum diameter
impeller and at the design speed.
b) 9,000 based on NPSH required at 0 percent reduction in first stage head
while operating at the pump best efficiency point with maximum diameter
impeller and at the design speed.
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
154
1x100% Forced Lube oil system is provided for Boiler feed pump.
Online vibration monitoring system and bearing metal temperature
measurement system.shall be provided for BFPs, booster pumps and their
motors
4.3.2 Heaters
The extraction system of each unit will be set with three HP heaters, four LP
heaters, one deaerator, and one gland steam condenser.
All of the heaters are horizontal type and are designed in accordance with HEI
standard. Shell wall thickness shall be determined in accordance with the
ASME code utilizing the allowable stress value for the shell material at the
design pressure and temperature. They are arranged indoors. Two LP heaters
are arranged at the neck of condenser.
The deaerator water tank has enough volume to ensure the boiler working at
the maximum operation condition for about 10 minutes. The deaerator storage
tank is also sized in conjunction with the deaerator outlet piping and height to
provide a storage volume which allow adequate transient NPSH for the boiler
feed due to a sudden full load rejection and prevent flashing at the pump
suction.
Deaerator shall remove dissolved oxygen from the condensate in excess of
0.005 cc per liter at any load from 5 percent to and including rated capacity.
HP heaters:
Closed feedwater heaters are used in a regenerative steam cycle to improve
the thermodynamic gain. This is accomplished by extracting system at various
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
155
points from the turbine and condensing kit using boiler feedwater. The
resultant heating of the feed water aids in avoiding thermal shock to the boiler
and reduces the fuel consumption required to convert the feedwater to steam.
Since the work lost by extracting the steam is derived from sensible heat, i.e.
no change of phase, the much greater latent heat recovered in the feedwater
heater by changing phase from steam to water result in a net energy gain.
Without a feedwater heater, the latent heat is wasted or thrown out in the
main condenser or cooling tower. Therefore, feedwater heaters also help to
reduce thermal pollution.
The high pressure heater is essentially an all-welded assembly. A special
stainless steel insert is assembled in the inlet end of every heater-transfer U
tube. Each high pressure heater has indicating, regulating and alarming
devices of level. When accident has taken place, automatic regulating of drain
level can fast bypass high pressure heater. Heater shell is provided with relief
valves to protect the shell in case of tube failure. On tube side, relief valve is
provided to prevent excessive pressure. Each high pressure heater contains
three zones, (i.e. desuperheating zone, condensing zone and subcooling
zone).
The welded seams are radiographed to insure the quality of the joint.
Stainless steel impingement plates have been installed in these heaters of
steam and other drains inlets to avoid direct impingement of steam and drains
upon the tubes to prevent tube erosion.
HP HEATER Nos. 8 DATA SHEET Parameter SL.
No DESCRIPTION
Tube side Shell side Unit
1 Sort Class 3rd pressure Class 2nd pressure
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
156
Parameter SL.
No DESCRIPTION
Tube side Shell side Unit
vessel vessel
2 Type JG-1370
3 Heating area 1370 m2
4 Design pressure 27.87 7.58 MPa(a)
5 Design temperature 295 420/295 oC
6 Max. operating
pressure
27.87 7.58 MPa(a)
7 Operating pressure 21.5 6.2145 MPa(a)
8 Operating
temperature
279.5 393.4/277.9 oC
9 Max. pressure drop 0.06 0.06 MPa
10 Flow 1056 85.89 T/h
11 Medium Water Steam & Water
12 Weld coefficient 1 1
13 Corrosion allowable 1
14 Estimated weight
Net weight 64956 Kg
Operating weight 70861 Kg
Flooded weight 82717 Kg
Manhole weight 120 Kg
15 Estimated Volume
Volume of water in sub-cooler zone at
normal water level
1.40 m3
Volume of water in shell at normal water
level outside sub-cooler zone
0.86 m3
Volume of steam in shell operating 12.1 m3
Volume of tube side 3.78 m3
HP HEATER Nos. 7 DATA SHEET
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
157
Parameter SL.
No DESCRIPTION
Tube side Shell side Unit
1 Sort Class 3rd pressure
vessel
Class 2nd pressure
vessel
2 Type JG-1575
3 Heating area 1575 m2
4 Design pressure 27.87 4.81 MPa(a)
5 Design temperature 265 360/265 oC
6 Max. operating
pressure
27.87 4.81 MPa(a)
7 Operating pressure 21.5 3.6542 MPa(a)
8 Operating
temperature
245 324/245 oC
9 Max. pressure drop 0.07 0.07 MPa
10 Flow 1056 85.65 T/h
11 Medium Water Steam & Water
12 Weld coefficient 1 1
13 Corrosion allowable 1
14 Estimated weight
Net weight 62121 Kg
Operating weight 69767 Kg
Flooded weight 81407 Kg
Manhole weight 120 Kg
15 Estimated Volume
Volume of water in sub-cooler zone at
normal water level
2.23 m3
Volume of water in shell at normal water
level outside sub-cooler zone
1.27 m3
Volume of steam in shell operating 11.9 m3
Volume of tube side 4.3 m3
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
158
HP HEATER Nos. 6 DATA SHEET Parameter
SL.No DESCRIPTION Tube side Shell side
Unit
1 Sort Class 3rd pressure
vessel
Class 2nd pressure
vessel
2 Type JG-1230
3 Heating area 1230 m2
4 Design pressure 27.87 2.07 MPa(a)
5 Design temperature 215 470/215 oC
6 Max. operating
pressure
27.87 2.07 MPa(a)
7 Operating pressure 21.5 1.6697 MPa(a)
8 Operating
temperature
203.4 435.3/203.4 oC
9 Max. pressure drop 0.07 0.05 MPa
10 Flow 1056 40.16 T/h
11 Medium Water Steam & Water
12 Weld coefficient 1 1
13 Corrosion allowable 1
14 Estimated weight
Net weight 48739 Kg
Operating weight 55961 Kg
Flooded weight 69272 Kg
Manhole weight 120 Kg
15 Estimated Volume
Volume of water in sub-cooler zone at
normal water level
2.55 m3
Volume of water in shell at normal water
level outside sub-cooler zone
1.32 m3
Volume of steam in shell operating 13.6 m3
Volume of tube side 3.50 m3
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
159
The high-pressure feedwater heaters shall be manufactured of following
materials or superior materials:-
a) Channel and channel: Carbon steel ASTM A515 Gr 70, cover carbon steel
ASTM A516 Gr 70, or forged steel ASTM A350 Gr LF2.
b) Shel: Carbon steel ASTM A515 Gr.70 or carbon steel ASTM A516 Gr70.
c) Shell skirt: Carbon steel ASTM A515 Gr 70, carbon steel ASTM A516 Gr 70,
or alloy steel ASTM A387 Gr 6, 11, or 12--Class 1.
d) Tubes: Stainless steel ASTM A688Type 304N
e) Tubesheet: Carbon steel ASTM A516 Gr. 70 or forged steel ASTM A350 Gr
LF2.
Feed pump hydraulic coupling shall be rated up to lower operating range of
20% of the maximum output speed.
LP Heaters:
The low pressure heater system adopts single string arrangement, which
consists of four low pressure feedwater heaters. The low-pressure feedwater
heaters shall increase the temperature of the condensate in stages by the use
of extraction steam. The low pressure heaters contain two zones(condensing
zone and subcooling zone). Heat transfer tubes are stainless steel U-tubes.
Heater shell is provided with relief valves to protect the shell in case of tube
failure. On tube side, relief valve is provided to prevent excessive pressure.
Each channel of low pressure heaters consists of a cylindrical shell and an
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
160
ellipsoidal head. LP heaters 1 & 2 are located in the neck of the condenser.
The maximum tube side flow shall be the condensate flow at turbine valves
wide open and a design margin of no less than 10 percent.
LP HEATERS Nos. 1 & 2 DATA SHEET Parameter
SL.
No DESCRIPTION Tube
side
Shell
side
Tube
side
Shell
side
Unit
1 Heater No. #1 #2
2 Type JD-840-5-2 JD-740-5-3
3 Heating area 840 740 m2
4 Design pressure 3.92 0.206 3.92 0.206 MPa(a)
5 Design temperature 130 130 130 130 oC
6 Max. operating
pressure
3.92 0.206 3.92 0.206 MPa(a)
7 Operating pressure 1.724 0.024 1.724 0.0752 MPa(a)
8 Operating
temperature
61.3 64.1 89.1 91.9 oC
9 Max. pressure drop across heater
0.04 <0.03 0.04 <0.02 MPa
10 Flow 791.56 18.22 791.56 35.94 T/h
11 Medium Water
Steam &
Water Water
Steam &
Water
12 Weld coefficient 1 0.85 1 0.85
13 Corrosion allowance 1
14 Estimated weight Heaters #1 & #2 combined
Net weight 36320 Kg
Operating weight 48345 Kg
Flooded weight 69555 Kg
15 Estimated Volume
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
161
Parameter SL.
No DESCRIPTION Tube
side
Shell
side
Tube
side
Shell
side
Unit
Volume of water in sub-cooler zone
at normal water level
1.92 m3
Volume of water in shell at normal
water level outside sub-cooler zone
3.86 m3
Volume of steam in shell operating 21.2 m3
Volume of tube side 6.24 m3
LP HEATER No. 3 DATA SHEET Parameter SL.
No DESCRIPTION
Tube side Shell side Unit
1 Sort 2nd Class pressure
vessel
1st Class pressure
vessel
2 Type JD-530-3-2
3 Heating area 530 m2
4 Design pressure 3.92 0.48 MPa(a)
5 Design temperature 150 266/150 oC
6 Max. operating
pressure
3.92 0.48 MPa(a)
7 Operating pressure 1.724 0.1403 MPa(a)
8 Operating
temperature
106.6 145.8/109.4 oC
9 Max. pressure drop across heater
0.06 0.015 MPa
10 Flow 791.56 23.63 T/h
11 Medium Water Steam & Water
12 Weld coefficient 1 0.85
13 Corrosion allowable 1
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
162
Parameter SL.
No DESCRIPTION
Tube side Shell side Unit
14 Estimated weight
Net weight 11850 Kg
Operating weight 14920 Kg
Flooded weight 20980 Kg
Manhole weight 275 Kg
15 Estimated Volume
Volume of water in sub-cooler zone at
normal water level
0.37 m3
Volume of water in shell at normal water
level outside sub-cooler zone
0.77 m3
Volume of steam in shell operating 6.2 m3
Volume of tube side 2.00 m3
LP HEATER No. 4 DATA SHEET Parameter SL.
No DESCRIPTION
Tube side Shell side Unit
1 Sort 2nd Class pressure
vessel
1st Class pressure
vessel
2 Type JD-580-8-4
3 Heating area 580 m2
4 Design pressure 3.92 0.686 MPa(a)
5 Design temperature 164 003/164 oC
6 Max. operating
pressure
3.92 0.686 MPa(a)
7 Operating pressure 1.724 0.3357 MPa(a)
8 Operating
temperature
134.6 232/137.6 oC
9 Max. pressure drop 0.06 0.01 MPa
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
163
Parameter SL.
No DESCRIPTION
Tube side Shell side Unit
across heater
10 Flow 791.56 38.52 T/h
11 Medium Water Steam & Water
12 Weld coefficient 1 0.85
13 Corrosion allowable 1
14 Estimated weight
Net weight 12820 Kg
Operating weight 16380 Kg
Flooded weight 22620 Kg
Manhole weight 275 Kg
15 Estimated Volume
Volume of water in sub-cooler zone at
normal water level
0.65 m3
Volume of water in shell at normal water
level outside sub-cooler zone
0.84 m3
Volume of steam in shell operating 6.36 m3
Volume of tube side 2.16 m3
10% Design margin shall be kept.
The low-pressure feedwater heaters shall be manufactured of following
materials or superior materials:-
a) Channel and: Carbon steel ASTM A515 Gr. 70, channel cover or forged
steel ASTM A350 Gr LF2.
b) Shell: Carbon steel ASTM A515 Gr. 70
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
164
c) Shell skirt: Carbon steel ASTM A515 Gr. 70 or alloy steel ASTM A387 Gr 6,
11, or 12 Class 1.
d) Tubes: Stainless steel ASTM A688 Type 304
e) Tubesheet: Carbon steel ASTM A516 Gr 70 or forged steel ASTM A350 Gr
LF2.
Deaerator:
The horizontal deaerator &storage tank is one of the main auxiliary equipment
in feedwater regenerative system for steam generating units. The primary use
of deaerator & storage tank is to remove noncondensable gases such as
oxygen, carbon dioxide, etc. The boiler water is to reduce oxygen content
below 0.005 cc/l. In addition, with extraction on the low pressure side of the
turbine and other resideual steam and drain, the deaerator shall heat the
boiler feedwater to saturated temperature under operating pressure of
deaerator so as to raise the thermal efficiency of the unit. The storage tank
can store a definite amount of saturated water at deaerator pressure and
conform to the standard of oxygen content to meet the needs of the boiler and
guarantee its safe operation.
Feature
1. Deaerator employs a two-stage system of heating and deaerating
feedwater.
1.1 Stage one
The prime element in our vent condenser zone is the self-adjusting spray
valve that allows incoming water, which is to be deaerated, to discharge as a
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
165
thin-walled, hollow cone spray. Because steam flows countercurrent, intimate
water to steam contact occurs with consequent latent heat transfer. As the
falling water reaches the spray stack, most of the dissolved oxygen and free
carbon dioxide have been removed at this point. Since nearly all of the steam
has been condensed, the non-condensable gases and the small amount of
“transport” steam exits through the vent piping.
1.2 Stage two
The partially deaerated water enters the tray stack at saturation temperature.
The heated water flow down over the trays, zigzagging through counterflow
steam. This arrangement provides additional retention time to allow oxygen
strip by the purest steam. The two-stage tray deaeration technique is the most
reliable method for meeting critical performance over a complete load range.
2. The deaerator is provided with constant speed spray valves and every
spray valve has great flow changes, which makes deaerator suitable to the
changing-load operation of turbine unit and insures the operation following the
sliding condition that vary with change of the turbine load to reduce the throttle
loss of the system and raise the thermal efficiency of the system.
3. The horizontal deaerator seats on the storage tank, thus the room
occupied by the equipment is minimal.
4. The amount of steam is large and the operation is convenient, thus
guaranteeing stable operation on the tank.
Modern internal vacuum ring construction is adopted, thus removing the
welding stress at vacuum ring.
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
166
Necessary free board shall be ensured.
DEAERATOR AND TANK DATA SHEET Parameter
SL.No DESCRIPTION Deaerator Deaerator tank
Unit
1 Sort Class 1st pressure
vessel
Class 1st pressure
vessel
2 Type GC-1056 GS-210
3 Design pressure 1.02/full vacuum 1.02/full vacuum MPa(a)
4 Design temperature 350 350 oC
5 Max. working
pressure
0.8346 0.8346 MPa(a)
6 Working
temperature
337 337 oC
7 Effective Volume 210 m3
8 Total volume 263 m3
9 Rated capacity 1056 t/h
10 Weld coefficient 1 1
11 Corrosion allowable 3.2 1.6 mm
12 Medium Steam & Water Steam & Water
13 Nozzle pressure
drop
0.014 MPa
14 Max. capacity 1109 t/h
15 Set pressure of
safety valve
0.88 0.88 MPa(a)
16 Others TOTAL DISCHARGE CAPACITY OF
SAFTY VALVES ON DEAERATOR AND
TANK IS 105821Kg/h
The deaerator shall be manufactured of following materials or superior
materials:-
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
167
i) Shell & Deaerating: Carbon steel ASTM A516 Gr 70.
section
ii) Storage section: Carbon steel ASTM A516 Gr 70.
iii) Shell supports: Carbon steel ASTM A36.
iv) Trays & Nozzles: Stainless steel ASTM A176 Type 430 or Stainless steel
ASTM A167 Type 304.
v) Tray supports: Stainless steel AS TM A176 Type 430 or Stainless steel
ASTM A167 Type 304.
vi) Baffles and liners: Stainless steel ASTM A167 Type 304.
vii) Vent & distribution: Stainless steel ASTM A312 Type 304.piping
viii) Spray valves : Stainless steel ASTM A276 Type 316.
4.3.3 Condensate extraction pump
Three 50% capacity constant speed motor driven Condensate extraction
pumps are set for each unit, two operate and one standby. The Condensate
extraction pump is “can” type with single suction impeller and with derivational
stage.
Each Condensate extraction pump shall be sized to supply 120 percent of the
flow requirements at VWO operation with 3% makeup for each unit.
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
168
The design of pump shafts shall be such that no critical speed shall occur at
less than 50 percent above the operating speed range.
The material for impeller and derivation stage is CA-6NM, which has good
ability to avoid cavitation during operation.
The Condensate extraction pump & motor shall be provided with online
vibration measurement system and bearing metal temperature measurement
system.
CEP SIZING DATA SHEET
No Name Symbol Unit Calculation & Remark VWO TMCR
(3%MU)
Technical evaluation sheet
A Capacity of CEP
1 Condensate steam flow at VWO
G1 t/h
HBD from Shanghai steam turbine works 616.08 589.457
2 Normal drain to condenser G2 t/h " " 117.048 109.304
3 Normal makeup water to condenser G3 t/h " " 29.625 28.07
4 Other flow to condenser G4 t/h " " 2.828 2.683
5 Maximum condensate flow
G' t/h G'=G1+G2+G3+G4 765.581 729.514
6 Capacity of each CEP G t/h G=1.1*G'/2 421.07 401.23
7 Condensate water specific volume
υ m3/Kg According to HBD 0.00101 0.00101
8 CEP flow Q' m3/h Q=G*υ *1000 425.28 405.25 Q m3/h 450 410 505
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
169
No Name Symbol Unit Calculation & Remark VWO TMCR
(3%MU)
Technical evaluation sheet
***
According to technical specification G t/h 1.2×VWO flow 459.35
Q m3/h 464
B CEP head
1
Pipe pressure drop from condenser hotwell outlet to deaerator inlet
△ P1 Mpa Calculation result 0.907 0.69
Mpa Considering 20% margin 1.09 0.83
Coefficient for pressure drop calculation
Deaerator level control valve
66.600 66.600
Deaerator inlet flow nozzle
7.660 7.660
Suction strainer 2.500 2.500
2 Equipments pressure drop
Mpa Including CPU, GSC, 4 LP heaters & spring nozzle 0.789 0.789
LP heaters Mpa each 0.100 0.100 GSC Mpa 0.025 0.025 CPU Mpa 0.350 0.350
Spring nozzle of deaerator inlet
Mpa 0.014 0.014
3
Water differential pressure between deaerator inlet and condenser hotwell lowest water level
△ P2 Mpa 20.96-(-0.662) 0.2162 0.2162
4 Deaerator max. working pressure △ P3 Mpa 0.8346*1.15 0.960 0.960
5 Condenser highest vacuum △ P4 Mpa 735x133.3/1000-
10.05 0.088 0.088
6 CEP discharge head △ P Mpa
△ P=△ P1+△ P2+
△ P3+△ P4 3.14 2.88 2.80
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
170
No Name Symbol Unit Calculation & Remark VWO TMCR
(3%MU)
Technical evaluation sheet
C CEP sizing result 1 Discharge pressure H Mpa 3.14 2.88 2.82 Flow Q m3/h 465.00 410 505
Note: above calculation result are based on China criteria and have been submitted to manufacturer for the selection of CEP.
Below data is furnished by CEP vendor
1 Pump
Condition Unit
Design condition
Max. continuou
s operation
Technical evaluation sheet
Style NLT300-400X7
inlet emperature ℃ 46 46 46
inlet pressure kPa 10.05 10.05 10.05
flow m3/h 410 465 505
head M 335 322.5 312.8
effiency % 77 80 81
NPSHr of pump first stage impeller
M
3.1 3.3 3.4
speed r/min 1480
Pump minimum flow
m3/h
125
Discharge pressure MPa(g) 3.26 3.14 3.04
Shaft power kW 481 505.4 526
2 Motor Rated power Kw 630
Rated voltage Kv 6.6
Guaranteed effiency %
92
Synchronous speed r/min
1500
Frequency Hz 50
To counter the surging effect on hotwell 100 m3 size surge tank is provided.
4.3.4 Vacuum pump
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
171
2X100% capacity vacuum pumps will be furnished in the system. Two pumps
will be in operation for establish vacuum in condenser fast to shorten the start-
up time before the unit starting. During normal operation, one operates for
maintain the vacuum in condenser and another standby.
The vacuum pumps are of liquid ring type, and are sized in accordance with HEI
standards. Each vacuum pump designed capacity is of 25.0 SCFM (52Kg/h)
approximately of dry air plus associated water vapor to saturate at 1 inch (25.4
m/sec.) Hg atm. Besides, the pump capacity is also such that at starting, with
both pumps working in parallel, it is possible to create within 25 minutes sufficient
vacuum in the condenser suitable for raising the steam turbine to its full speed.
The design capacity of each pump shall be selected to meet the above
requirements with a margin of 10%.
The pumps shall not cavitate under all operating conditions including part
loads and design point, at max. CW temperature of 36 Deg.C.
The heat exchanger tubes shall be of SS-304 (welded). The shell of heat
exchangers and the tube plates shall be of mild steel corresponding to ASTM
A-285 Grade C. Material of construction of other components are as below or
superior:-
i) Casing: Nickel cast iron
ii) Shaft: Carbon steel EN-8
iii) Impeller :Nodular iron/stainless steel
iv) Shaft sleeves : Nodular iron/stainless steel
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
172
4.3.5 Condenser
4.3.5.1 Structural Characteristic
The condenser is designed in the form single shell, divided water boxes Two
pass and installed in transversal arrangement. The condenser mainly consists
of neck, shell, waterbox, exhaust expansion joint and so on.
Four fixed base supports are arranged at the four angles at bottom of the
condenser. Each fixed base support with three slot holes is connected to the
foundation with M36 anchor bolt in order to satisfy the requirements of
condenser expansion. Four sliding base supports are arranged at middle at
the bottom of the condenser, so that the complete condenser can steadily
upon the eight base supports. The condenser is connected to turbine exhaust
hood with expansion joint.
4.3.5.2 Neck
Condenser neck is made of welded carbon steel plates and steel plate is
applied for inside supporting and ribbed plates for reinforcement. T-type beam
steel are applied inside each sideplate of neck to increase transversal rigidity
of sideplates so that the complete neck could be rigid enough. Extraction lines
go through neck. Stainless steel lagging is adopted to cover the outside of
extraction lines in order to avoid erosion. All extraction lines are equipped with
stainless steel waveform expansion joints to absorb thermal expansion in the
lines.
In order to protect abnormal higher temperature caused by turbine bypass
inlet steam. Water screen spray protection device is equipped inside neck.
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
173
4.3.5.3 Shell
Shell made of full welded structure is the main part of condenser and
possesses reliable tightness.
Two tube bundles are set up in shell. Triangular conventional layout is
adopted for the arrangement of tube bundle. All tubes are seam welded. Air
extracting line in cooling area are evenly distributed at cooling water entrance.
Support plates are distributed between front and back tube sheets to support
cooling tubes. So that tubes could contact support plates closely to improve
the vibration property of tubes and avoid resonance. Tube sheets are welded
to two ends of shell and thinner steel plate is applied for flexible transition to
compensate thermal expansion difference between cooling the and shell.
Proper access manhole and other connections are provided on the shell.
An access manhole is provided on the tube bundle. Access openings or
manhole is provided on the interior of the condenser to provided access to the
tube support plates.
In some place where steam of water enters the condenser shell provided
suitable approved baffle to prevent impingement on the tube and shell, and
proper distribution of condensate and steam.
Hot well is designed below tube bundles with enough space so that
subcooling could be minimized in the process for reheating transfer and raise
deaerating effect as well. The hotwell has enough space for the requirements
of condensate level change.
A flash box is for absorbing drain. In this way, draining water can be
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
174
temperature-reduced and pressure breakdown and then drained into
condenser so that tube bundle could be protected from erosion of steam and
water higher temperature and pressure.
4.3.5.4 Waterboxes
Waterboxes are designed in the form of semicircle and cone-type. Thus
resulting in good rigidity of the hole waterbox body, lightweight and favorable
flowing property of cooling water. The water box is provided cathodic
protection equipment. Inside of this condenser safety ladder is assembled to
the inside wall of waterbox and both vacuum extracted outlet and air vent
displaced at the top of waterbox. Manhole is equipped outlet the lower part of
waterbox for maintenance personnel easy access.
Sufficient tube extract space shall be kept in the front of tubesheets for taking
out of tubes if tubes are required to be taken out.
4.3.5.5 Exhaust expansion joint
Stainless steel waveform expansion joint is arranged at the exhaust expansion
joint to absorb thermal expansion from turbine low pressure exhaust cylinder
and condenser at vertical centerline direction of flow pressure exhaust cylinder.
The surface condenser is a double pass design with divided water boxes
which will facilitate operation of one half of the condenser while the other half
is under maintenance. The bottom of the condenser serves as a hot well for
condensate storage.
Design Basis:
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
175
The thermal design of surface condenser is based on HEI standard
considering 33°C cooling water temperature for a temp rise of 10°C
corresponding to heat load for VWO, 3% makeup and 10.05MPa(a)back
pressure. The condenser has the capability in thermal design to operate at
36°C maximum cooling water temperature.
The condenser hot well minimum storage capacity at the normal water level
shall be 5 minutes of condensate storage when operating at the turbine valves
wide open. The oxygen content of the condensate leaving the hot well shall
not exceed 0.015 cc per liter at all conditions
CONDENSER DATA SHEET
Sl.No Description Parameter Unit
1 Type N-18300
2 Model Single pressure divided two passes surface
3 Condenser effective surface area 18300m2
4 Condenser back pressure 10.05 KPa(a)
5 Condenser design pressure
Shell side 0.1/Full vacuum MPa(g)
Waterbox side 0.4 MPa(g)
Waterbox side test pressure 0.6 MPa(g)
6 Condenser design temperature
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
176
Sl.No Description Parameter Unit
Shell side Less than 121 oC
Waterbox side Less than 60 oC
7 Inlet temperature of cooling water 33 °C
8 Max. inlet temperature of cooling water
36 °C
9 Design flow of cooling water 34020 m3/h
10 Cleanliness factor 0.85
11 Water velocity in condenser tubes 2.087 m/s
12 Tube thickness 0.7 mm SS 304 seam welded in both condensing and air
cooling sections
13 Tube plugging margin 5%
14 Tube sheet material TP304+SA516Gr70
4.4 Table of economic index
Heat consumption rate of turbine 8024.5 KJ/kW.h
(1916.6 Kcal/kw.h)
Guarantee efficiency of boiler (high heating value) 87.1%
Note : The above results are based on TMCR (Heat Rate Guarantee)
condition. Turbine cycle heat rate is 1916.6 Kcal/kW.h based on with 0%
makeup, 33 Deg CCW inlet temp & 10.05 kPa(a) back pressure of condenser.
5 INSULATING MATERIAL
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
177
According to different temperature and pressure, different layout of
equipments and pipes in the BTG, the insulation material is considering as
follows (Code for designing insulation and painting of fossil and fuel power
plant DL/T 5072-1997) taking care of the following design data:
a) Design ambient temperature: 40℃
b) Maximum cladding temperature: 60 ℃
c) Wind speed: 0.5m/s for inside and 0.25m/s for outside the plant
buildings0.5 m/sec for inside and 0.25 m/sec for outside the plant area
1) Temperature over 350 degree’s equipments and pipes will adopt silicate or
aluminium silicate material.
Silicate: conductivity factor λ=0.031+0.00015tm W/m·℃
Density 80Kg/m3
aluminium silicate: conductivity factor λ=0.035+0.00018tm W/m·℃
Density 150kg/m3
2) Temperature under 350 degree’s equipments and pipes will adopt rock
wool or glass wool material.
rock wool: conductivity factor λ=0.032+0.00018 tm W/m·℃
Density 150kg/m3
Design Basis Report for Mechanical Part
HPGC : 2 x 300 MW Deenbandhu Chhotu
Ram TPP, Yamunanagar
DOCUMENT NO.: 50-F248-J01-01 Page
178
glass wool: conductivity factor λ=0.029+0.00011tm+7.65x10-10tm3 W/m·℃
Density 48kg/m3
3) Valves will adopt insulating sleeve and abnormities will adopt slurry of
silicate.
4) Aluminum material will adopt for protecting layer.