Building for Learning ProjectPhoto Progress Report 4
November 2009 – December 2009
Project commencement 21st September 2009
AWCC Chairperson Kerryn Dwyer-Parish with Graeme Connelly undertaking site inspections
Kerryn braved the situation – high heels and all
The 65mm of rain made for 4 ‘internal swimming pools’ but
the task is completed
And no photographic record is complete without some ‘rabbit ears’
November Internal Refurbishments continue
Internal Refurbishments Administration Area
New ceilings, plaster, office and painting
Key workers without who the job could not be done.
December new on-site substation for power required.
December – carpet, ceilings and windows in modernised Administration area
December – steel, bond deck arrives for 1st Floor
December – underground cable boring and concrete footings for stairways and elevator
December – Company Directors tour with Graeme Connelly – girls were happy, boys were serious.
L-R. Chairperson Kerryn Dwyer-Parish, Director Jan Wyatt-Brown, Director Alison Mitchell, Corporate Services Manager Pauline Butler, Builder Graeme
Connelly, Director Rod Jones, Director David Ryan.
December – bracing underneath bond deck and steel ready for concrete floor above
Final preparations and then concrete pour starting 6am, 22nd December – 150 tonne concrete
22nd December – 11 truck loads of concrete