+ All Categories
Home > Documents > Construction Technologies and Management of NPP

Construction Technologies and Management of NPP

Date post: 05-Jan-2022
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
41
IAEA International Atomic Energy Agency Construction Technologies and Management of NPP Nuclear Power Division Ki Sig Kang
Transcript
Page 1: Construction Technologies and Management of NPP

IAEA International Atomic Energy Agency

Construction Technologies and

Management of NPP

Nuclear Power Division

Ki Sig Kang

Page 2: Construction Technologies and Management of NPP

IAEA

Operation / decommissioning

•Preparing for

assuming

commitments &

obligations

Commissionin

g

Nuclear power option

included within the

national energy strategy

10 – 15 years

PHASE 2 PHASE 3 PHASE 1

MILESTONE 1 Ready to make a knowledgeable

commitment to a nuclear

programme

MILESTONE 2 Ready to invite bids

for the first NPP

•MILESTONE 3 •Ready to commission and

operate the first NPP

Bidding process

Pre project Project decision making Construction

Considerations before a decision to launch a nuclear power programme is taken

Preparatory work for the construction of a NPP after a policy decision has been taken

Activities to implement a first NPP

Maintenance and continuous infrastructure

improvement

•www.pub.iaea.org/MTCD/publications/ninfrastructure.asp

Pre- Feasibility Study Feasibility Study

10/12/2011 2

Preparation

of

Infrastructure

Commissioning

and Operation

• Project Decision Making

• Feasibility Study

• Environment Impact

Analysis(EIA)

• Site Evaluation

• Bid information

Specification

• Bidding and Evaluation

• EPC contract

• Construction

Page 3: Construction Technologies and Management of NPP

IAEA

Structure of the Feasibility Study

• Executive summary

1. Introduction

2. Analysis of electric power

supply, justification of new

units

3. NPP capacity

4. Site characterization

5. NPP technology options

6. Summary of the results of the

preliminary EIA

7. Implementation of the new

build project

8. Procurement concept

9. Construction, operation, and

human resources

10. Localization

11. Licensing

12. Economic evaluation

13. Financing

14. Public Acceptance

Page 4: Construction Technologies and Management of NPP

IAEA

Possible reactor types

4

AES

ATMEA

Page 5: Construction Technologies and Management of NPP

IAEA

Possible reactor types

EPR

Page 6: Construction Technologies and Management of NPP

IAEA International Atomic Energy Agency

Construction Status

Page 7: Construction Technologies and Management of NPP

IAEA

Current Status of the Nuclear Power Plant

• 439 nuclear power reactors in operation 374 GW(e)

• 65 nuclear power reactors under construction, 62.9 GW(e), 14 MS

Page 8: Construction Technologies and Management of NPP

IAEA

Estimation of Nuclear Capacity

0

200

400

600

800

1000

Low High

Low 372 445 511

High 380 543 807

1 2 32010 2020 2030

37 % increase

112 % increase

Page 9: Construction Technologies and Management of NPP

IAEA

Number of New Construction Initiation

0

2

4

6

8

10

12

14

16

1 2 3 4 5 6 7

GW 1.03 3.4 3.3 7.6 10.5 14 14.8

No 2 4 4 7 10 14 15

GW

No

2004 2005 2006 2007 2008 2009 2010

Page 10: Construction Technologies and Management of NPP

IAEA

Average Duration for Past NPP Construction 1969 to

1977 in USA

Since 1972,

rapidly

increase

construction

period

Why ??

Page 11: Construction Technologies and Management of NPP

IAEA

Construction Schedule of Japan NPPs

Improve Construction Method

’ 80 ’ 85 ’ 90 ’ 95 ’ 00 ’ 05 ’ 70 ’ 75

50 M

60 M

70 M

80 M

90 M

100 M

110 M

120 M

130 M

US BWR

Japan BWR

Japan ABWR

Year of Fuel Loading ’ 80 ’ 85 ’ 90 ’ 95 ’ 00 ’ 05 ’ ’

Co

ns

tru

cti

on

Du

rati

on

(m

on

th)

40 M

50 M

60 M

70 M

80 M

90 M

100 M

110 M

120

130 M TMI

US BWR

Japan BWR

Japan ABWR

US BWR

Japan BWR

Japan ABWR

3D-CAD Drawing Plastic Model 6D-CAD

Page 12: Construction Technologies and Management of NPP

IAEA

Construction Time Span

Categories 1970-1995

[month]

1996-Now

[month]

1970-1995

[year]

1996-Now

[year]

Median 80 83 6.67 6.92

Minimum 41 47 3.42 4.08

1 Quartile 67 61 5.58 5.08

3 Quartile 105.5 176 8.79 14.67

Maximum 283 302 23.58 25.17

Resource : Power Reactor Information System in the IAEA database

Page 13: Construction Technologies and Management of NPP

IAEA

The Shortest Construction Period

• Construction Schedule at 1350 Mwe

• From F/C to CO : 62 49 Months

• Construction Schedule at 1000 Mwe

• From F/C to C/O : 64 47 Months

• C/O: Commercial Operation

• F/C : First concrete pouring

Page 14: Construction Technologies and Management of NPP

IAEA International Atomic Energy Agency

Case Studies

Page 15: Construction Technologies and Management of NPP

IAEA

Construction Scheudle in Gen III+ NPPs

Site preparation : 12~18 M

Construction : 36~42 M

Start-up : 6~ 7 M

Total : 60 M

Page 16: Construction Technologies and Management of NPP

IAEA

More Safety Requirements

Trabant

New Volvo

Page 17: Construction Technologies and Management of NPP

IAEA

Manufacturing High Quality

Page 18: Construction Technologies and Management of NPP

IAEA

Professional Staff high nuclear knowledge, safety culture

Page 19: Construction Technologies and Management of NPP

IAEA

Assumptions to meet 60 months schedule

• Fundamental Project Assumptions • First-of-a-Kind (FOAK) or Nth

of a Kind (NOAK)

• Labour Resource Availability

• Cash Flow

• Labour Shift Structure

• Reference Location

• Labour Agreements

•Site-Specific Assumptions • Site Conditions

• Seismic Requirements

• Accessibility

• Transportation

• Engineering & Procurement Assumptions • Engineering

• Procurement Relationships and Contracts

• Long-Lead Components

• Manufacturing Durations

• Construction Assumptions • Extent of Modular Approach

• Specialized Equipment

• Shift of Work Load

• Licensing and Permitting Assumptions • Licensing Environment

• Changes in the Licensing Process

Page 20: Construction Technologies and Management of NPP

IAEA

USA Npps Construction Experiences

0

20

40

60

80

100

120

140

160

180

200

St.L

ucie 2

Pal

o Ver

de 1

Gra

nd Gulf

1

Wolf

Cre

ek 1

Sea

brook

1

Susq

uehhan

na

Sum

mer

1

Byro

n 1

San

Onofr

e 2

Wate

rford

3

LaSal

le

Com

anch

e Pea

k 1

Per

ry 1

McG

uire

Shore

ham 1

Mid

land 2

Cata

wba 1

Watts

Bar 1

Harr

is 1

Wash

ingto

n Nucle

ar 2

Enric

o Fer

mi 2

Limer

ick 1

Page 21: Construction Technologies and Management of NPP

IAEA

KEDO 1&2

Bataan Npp in

Philippines

Westinghouse 2 Loop

600 Mwe

95% completed,

Political reason

Page 22: Construction Technologies and Management of NPP

IAEA

Cernavoda NPP, Romania

Right: Unit 1 /2 (in operation), Unit 3 (in preservation)

Left: Unit 4 and 5 (in preservation)

Page 23: Construction Technologies and Management of NPP

IAEA Atucah II Npp-

Installation of Moderator Tank, June 2009

Page 24: Construction Technologies and Management of NPP

IAEA 10/12/2011 24

Angra 3 NPP, Brazil

Page 25: Construction Technologies and Management of NPP

IAEA

Olkiluoto 3 at the end of April 2009

Source: TVO

Core thermal power

Net power output

Net efficiency

4300 MWth

1577 MWel

37 %

May 2005 : First Concrete for Reactor

Building

May 2007 : RPV installed,

May 2008 : Start Hot Functional Tests

Aug. 2008 : First Fuel Loading

Nov. 2008 : First Criticality

April 2009 : Start Demo-Run

Electricity Production in 2013

Page 26: Construction Technologies and Management of NPP

IAEA

If NPP construction is delayed,

• Increased

- Financing fee and Interest

- More oil power plants – Electric cost

- Decreased & Lost

- Confidentiality from Gov & People

- Engineers, technicians, workers

- Equipment, documents

Page 27: Construction Technologies and Management of NPP

IAEA International Atomic Energy Agency

Construction Management

Page 28: Construction Technologies and Management of NPP

IAEA

Site

Construction

Management

support system

Modularization

with very

large crane

On-site

Work

reduction)

Site Support

work

efficiency

Open-top

&

parallel

construction

Work Leveling

(Peak

Reduction)

Early and

Detailed

engineering

before on-site

work

Work

Efficiency

Strategies for shortening Con. period

With Modularization Method

Construction Period = 38M (actual First ABWR)

Milestones S/C R/I M/C O/C P/S RPV H/T F/L C/O F/C

Page 29: Construction Technologies and Management of NPP

IAEA

40

100

’ 80 ’ 85 ’ 90 ’ 95 ’ 00 ’ 05

100

60

80

40

現地工数(出

力比

) (2

F -

1

=1

00

)

燃料装荷年度

Manhour Reduction with Early Engineering

Past

Design Start

Detailed engineering completed before construction start

Construction Start CO

Design/Engineering

Construction

Reduced Site Manpower to 40%

Man

ho

ur

‘80 ‘90 ‘00 ‘85 ‘95 ‘05

Current

Design Start Design Freeze

Design/Engineering

Construction

Early finish of Engineering

Page 30: Construction Technologies and Management of NPP

IAEA

Front-Loaded Construction Engineering

Basic Design

Detailed Design

Construction

Construction Engineering

Previous Design Process

Front-Loaded Construction Engineering

Basic Design

Detailed Design

Construction

Construction Engineering

Requirements from Construction Engineering Inputs from Plant Design

(BOQ, Composite Design, etc.)

Source : From Hitachi construction experiences

Page 31: Construction Technologies and Management of NPP

IAEA

建設工程

3D-model linked with Schedule

Construction Schedule with 6D

Page 32: Construction Technologies and Management of NPP

IAEA

Construction Schedule with 6D

3D-model by construction area

Quantities based

on 3D-model

Assign Labor

resource

Schedule loaded with Quantities and Resource

3D-model + Quantities + Resource + Time = 6D Database

• Develop detailed and precise Construction schedule by construction area based on Quantities and Labor resource

• Simulate the schedule with 3D-model

Page 33: Construction Technologies and Management of NPP

IAEA

RPV

Upper Condenser Module RCCV Lower Liner Module

Lower Condensor Unit RPV Pedestal Module Base Mat Module HPU Module

Stator Upper Drywell Module RCCV Top Slab

(420 ton)

(410 ton) (460 ton) (260 ton)

630 ton) (270 ton)

(650 ton) (900 ton) (550 ton)

(270 ton)

On-site Work Reduction - Modularization Method -

Page 34: Construction Technologies and Management of NPP

IAEA

Man P

ow

er

Construction Progress

(month)

Level-off

Manpower Peak

Based on previous ABWR (Conventional Method) (a

rb.)

Manpower Peak Reduction Effort

- Construction & Module Experience-

4

3

2

1

1 6 11 16 21 26 31 36 41 (month)

Manpower Distribution

Based on Latest ABWR

Page 35: Construction Technologies and Management of NPP

IAEA International Atomic Energy Agency

Discussion on Deployment

Page 36: Construction Technologies and Management of NPP

IAEA

How can we balance main poles to

meet requirements

Project

Management

Quality

Schedule

Budget

Risk

Page 37: Construction Technologies and Management of NPP

IAEA

Topics to be issued

• Role and Responsibility of Owner in each

stage

• Feasibility Study

• Contract type ( Turn Key, Split, Component)

• Bid Evaluation (Technical parts and Generic part)

• Selection of EPC contractor

• Selection of Vendor

• Procurement and Erection

• Commissioning

Page 38: Construction Technologies and Management of NPP

IAEA

• Defence in depth

• Inherent and

passive safety

features

• Safety design

concepts

Page 39: Construction Technologies and Management of NPP

IAEA

Two Guidelines under printing

Construction Management

• CM - Preparatory Phase

• CM - Construction

Phase (after concrete

pouring)

• CM- Commissioning

Phase

• CM issues and lessons

learned

Construction Technology

• Open Top Construction

using VHL

• Modular Construction

• All Weather

Construction

• Steel-Plate Reinforced

Structure

Page 40: Construction Technologies and Management of NPP

IAEA

When we find an Iceberg

If we simply see the Surface…

Page 41: Construction Technologies and Management of NPP

IAEA

We could be in a Big Problem

When we find an Iceberg


Recommended