+ All Categories
Home > Documents > Consultant Forum - King County

Consultant Forum - King County

Date post: 04-Oct-2021
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
41
Consultant Forum February 17, 2016
Transcript
Page 1: Consultant Forum - King County

Consultant Forum

February 17, 2016

Page 2: Consultant Forum - King County

Today’s Presentation

King County’s LEAN Initiative- Progress Report

Sustainability, Equity and Social Justice

Treatment and Conveyance Improvements

Planning for Treatment and Conveyance

CSO Control Program

Resiliency and Recovery

Construction Management

Work Order Contracts

Page 3: Consultant Forum - King County

LEAN

Creating a Lean Capital Delivery Program

Significant increase in number of projects in next 10 years

Project complexity increasing

Improve business practices and delivery of projects

Continuous improvement – where can we be better?

Increase capacity to deliver projects by reducing “waste”

Page 4: Consultant Forum - King County

LEAN A/E Procurement: Reduce time to select consultants

Streamlined proposal evaluation criteria now active

Scope of Work and Negotiation phase under evaluation

Alternatives Analysis

Targets alternatives analysis, development and selection process

Perform initial assessment internally to identify information gaps then provide to design team to guide more realistic and feasible alternatives (2-4) development

Reduce time to 11 months or less

Page 5: Consultant Forum - King County

Sustainability, Equity and Social Justice

Page 6: Consultant Forum - King County

Sustainability All Capital Projects Incorporate Environmental

Sustainability & Equity and Social Justice

Green Building Ordinance

Strategic Climate Action Plan (SCAP)

Rating Systems Used

WTD Alternative Sustainability Scorecard

Envision Sustainable Infrastructure Rating System

LEED

Page 7: Consultant Forum - King County

Equity and Social Justice Equity and Social Justice (ESJ)

Ordinance

ESJ is a core component of WTD project delivery

WTD considers the triple-bottom line of sustainability: environment, economy, and equity

A project is not holistically sustainable without incorporating equity and social justice

Page 8: Consultant Forum - King County

Treatment and Conveyance Improvements

West Point Secondary Mixed Liquor Channel Aeration

Coal Creek Trunk Capacity Upgrade

North Lake Sammamish Flow Diversion

Page 9: Consultant Forum - King County

West Point Secondary Mixed Liquor Channel Aeration Evaluate alternatives for providing oxygen within the

secondary mixed liquor channel

Analyze existing oxygen usage and alternatives that reduce energy consumption

RFP advertised February 3rd

Proposals due February 24th

Total estimated project cost = $1.5 million

Project Manager: Ann Grothe

Page 10: Consultant Forum - King County

Coal Creek Siphon and Trunk

Increase the capacity of 7,100 lf of 15 to 21-inch Coal Creek Trunk

Existing interceptor is adjacent to or under Coal Creek.

Construction methods may include open cut, and trenchless technologies

Alternatives will evaluate construction methods, parallel vs. upsize, and alignment

Total Project Cost estimated at $70 million

Request for Proposals anticipated Q1 2016

Project Manager: MaryBeth Gilbrough

Page 11: Consultant Forum - King County

North Lake Sammamish Flow Diversion

Diversion up to 29 mgd peak flow from the North Lake Sammamish Basin to the Brightwater Service area by 2021, and 43 mgd by 2050

Alternatives analysis completed

RFP to include predesign, final design, and services during construction

Total Project Cost - $25 million

RFP advertised in March 2016

Project Manager: Liz Gaskill

Page 12: Consultant Forum - King County

North Lake Sammamish Flow Diversion

Page 13: Consultant Forum - King County

Planning For Future Treatment and Conveyance Upgrades

Presenting: Mark Buscher

Page 14: Consultant Forum - King County

Treatment Plant Flow and Loadings Study Study to assess wastewater flow and loadings as they

impact each treatment plant service area

Establish process capacity requirements

Develop planning level capacity expansion options

including schedule and conceptual cost

RFP anticipated for Q2 2016

Cost estimated at $900,000

Project Manager: Sue Kaufman-Una

Page 15: Consultant Forum - King County

CSI Program Update

Guide major improvements to the separated portion of the conveyance system to ensure capacity for regional growth and 20-year peak flow

Project Manager: Steve Tolzman

Page 16: Consultant Forum - King County

Anticipated Upcoming Projects (next 10 years) Sammamish Plateau Diversion

Richmond Beach Pump Station

Thornton Creek Trunk

Richmond Beach-Edmonds Interceptor

Tukwila Freeway Crossing

Kent-Cascade Relief Interceptor

ULID #1 Contract #4 – Kent

Boeing Creek Trunk

Page 17: Consultant Forum - King County

Infiltration and Inflow (I/I) WTD and the Cities and Sewer Districts that deliver

wastewater to the regional system are discussing additional I/I reduction efforts

I/I reduction concepts identified include:

Evaluation of Sewer and Side Sewer Standards

Regional Sewer and Side Sewer Standards Construction Inspection Program

Private Side Sewer Programs: including certification and insurance programs

Page 18: Consultant Forum - King County

Potential RFP in 2017: Evaluation of I/I Reduction Concepts

Potential RFP for the following services in 2017

Engineering: technical standards , effectiveness analysis

Legal/Policy: authority to implement, program framework

Economic/Financial: cost estimating, funding

Program Manager: Steve Tolzman

Page 19: Consultant Forum - King County

CSO Control Program

Project Manager: John Phillips

Page 20: Consultant Forum - King County

Adopted 2012 Long-Term Control Plan

• 9 projects to control 14 remaining uncontrolled CSOs by 2030 (planning-level cost of $711 million)

• Incorporate Green Stormwater Infrastructure where cost-effective

• Long-Term Control Plan update currently in progress

Page 21: Consultant Forum - King County

University and Montlake Green Stormwater Infrastructure (GSI) (2016)

West Michigan/T-115 Wet Weather Storage (if needed) (2017)

University Wet Weather Storage (2020)

Montlake Wet Weather Storage (2020)

Hanford #2, Lander, King and Kingdome Wet Weather Treatment (2021)

Consent Decree driven projects completed by 2030

Page 22: Consultant Forum - King County

University and Montlake GSI RFP 4th Quarter 2016

Scope of Work Design GSI in these neighborhoods:

South Green Lake

East Ravenna

Capitol Hill

Central

Reduce peak flow to Montlake and University Wet Weather Storage

Consultant Services Geotechnical services

GSI design (as per SPU/WTD templates)

Community outreach

Hydraulic/hydrologic modeling

Page 23: Consultant Forum - King County

Chelan Avenue Combined Sewer Overflow (CSO) Control Project

Evaluate CSO Control alternatives developed by WTD Planning Determine appropriate site or sites Assist in siting, environmental review, and permitting Provide design engineering services, develop construction documents,

engineering services during construction Draft Facility Plan submitted to Ecology by December 31, 2017 RFP to be advertised Q2 2016

Project Manager: Michael Popiwny

Page 24: Consultant Forum - King County

SPU/WTD Joint Tunnel Project

Page 25: Consultant Forum - King County

SPU/WTD Joint Tunnel Project Upcoming Consultant Procurements

151 Outfall Design: Q1 2016

Utility Relocation Design: Q1 2016

Program Manager/Construction Manager: Q2 2016

Ballard Conveyance Design: Q1 2018

SPU A/E Business Opportunity Event, Bertha Knight Landes Room, Wednesday, February 24, 8:30 AM-1:00 PM, Contact: Kathy Peterson , [email protected]

McMillan Jacobs Associates: Selected as Tunnel/PS designer

King County Contact: John Komorita

Page 26: Consultant Forum - King County

Resiliency and Recovery

Page 27: Consultant Forum - King County

System-Wide Master Plan for Resiliency and Recovery of King County’s Wastewater Treatment Facilities Project Scope:

Develop a comprehensive strategy for preparing WTD’s System to reduce the impacts of a major earthquake

Identify specific vulnerabilities and mitigation to reduce impacts, recovery time, and increase system resiliency

Page 28: Consultant Forum - King County

Resiliency and Recovery

Develop with WTD our strategic resiliency plan to include:

Assessment of individual WTD facilities

Prioritized plan and projects to address vulnerabilities

Recommended actions for rapid recovery of the system following a major seismic event

RFP Advertised Q2 2016

Master Plan to be completed by 4th Quarter of 2017

Project Manager: Michael Popiwny

Page 29: Consultant Forum - King County

Interbay Pump Station Force Main Assessment and Replacement Section of force main failed in 2013 Scope of project is to assess force main and identify

repair/rehabilitation alternatives Provide engineering design services RFP anticipated 2Q 2016 Total estimated project cost $30 million Project Manager: Shahrzad Namini

Page 30: Consultant Forum - King County

Construction Management Services

Page 31: Consultant Forum - King County

Georgetown - Construction Management Services

EPA Consent Decree project

Superfund, poor soils, traffic congestion

High rate treatment facility

Capacity of 70 MGD peak CSO flow

Facility consists of:

Screenings , 1.1 MG flow equalization tank

70 MGD pump station

HRC(ballasted sedimentation) and UV disinfection

Odor control and ancillary facilities

Conveyance piping (~2,000LF)

New and modification of existing regulators

Outfall structure (200LF @ the Duwamish)

Schedule

RFP – 2Q 2016

Constructability reviews during design

Construction – 1/2017-12/2022

Page 32: Consultant Forum - King County

Georgetown Station - Construction Management Services Scope

CM services during design - constructability reviews

CM services during construction

Project manager – CM contract management

Resident Engineers and Inspectors - all disciplines

Project controls, cost estimating, scheduling

Project Manager: Will Sroufe WTD Project Representative for construction: Chris Mack

Page 33: Consultant Forum - King County

West Point Treatment Plant OGADS Replacement - Construction Management Services

Oxygen Generation System – Replace existing Vacuum Swing Adsorption Units (VSA) two 40 Tons per Day VSAs.

Oxygen Dissolution System – Replace existing surface aerators, motors and gearboxes with new aerators, motors and gearboxes and install new variable frequency drives and motor control centers.

Page 34: Consultant Forum - King County

West Point Treatment Plant OGADS Replacement - Construction Management

CM Services during Design: • Design reviews • Cost Estimate and Schedule Reviews CM services during construction: • CM contract management • Design documents, cost estimate and schedule review • Inspection – disciplines TBD • Scheduling, cost analysis/estimating • Construction contract administration Final Design: Q3 2016 – Q2 2017 Construction: Q3 2017 – Q4 2021

Project Manager: Crystal Fleet

Page 35: Consultant Forum - King County

Kent/Auburn CSI Phase B

Open trench and trenchless construction methods

Utility relocations

Restoration of wetlands

Restoration of backyards of private properties

Page 36: Consultant Forum - King County

Kent/Auburn CSI Phase B

Construction Management Services

Schedule Review and Analysis

Cost Analysis and Estimating

Inspection Services

Environmental Services

Monitoring and testing of soils for disposal characterization

Environmental and Sustainability Reporting

Request for Proposals estimated Q3 2016

Project Manager: Sue Hildreth

Page 37: Consultant Forum - King County

Work Order Contracts

Page 38: Consultant Forum - King County

Mechanical / Electrical Engineering Services on a Work Order Basis

Engineering services and design for the Wastewater Treatment Division

SCOPE: • Project management and coordination • Mechanical and Electrical Engineering design • Associated services - Structural/Civil engineering; Architectural services • Engineering services during construction

EXAMPLES: • Power system modeling • Evaluation of design alternatives • Troubleshooting I&C systems • Preparing 30/60/90% drawings/specs • Construction cost estimating • Reviewing contractor submittals/shop drawings

RFP Q1 2016 ------------

Contract Amount $1.5M split

(2 contracts)

Project Manager: Lori Larkin

Page 39: Consultant Forum - King County

Six Year Plan Asset Management Projects

Less than $1M Total Project Cost

2 – 3 year average project duration

Focus is on existing assets

Generally suitable for Work Order Consultant Generally less than $50K Work Order

Fill in disciplines WTD lacks or provide additional engineering resources

Provide the entire engineering team or a portion of a hybrid WTD/consultant engineering team

Prioritized Plan – projects released periodically

Contact: Jacquelynn Roswell

Page 40: Consultant Forum - King County

Recommended