PROJECT SCHEDULE
55
Activity ID Activity Description Plan Dur Plan Start Plan Finish 2 X 80 MW CPP - DARIBA SMELTER COMPLEX MAJOR MILESTONES Subtotal 761 18MAR08 17APR10 MIL001 ZERO DATE - PROJECT START 0 18MAR08 MIL002 RELEASE OF LOI TO BHEL 0 18MAR08 MIL003 KICK-OFF MEETING 0 02MAY08* MIL004 RELEASE OF LOI TO TPL 0 03JUL08* MIL006 CIVIL WORK START 0 02SEP08 MIL007 UNIT #1 - BOILER STRUCTURE ERECTION START 0 15JAN09 U2MIL007 UNIT #2 - BOILER STRUCTURE ERECTION START 0 15APR09 MIL008 UNIT #1 - BOILER DRUM LIFTING 0 30APR09 MIL010 UNIT #1 - CONDENSOR ERECTION START 0 30MAY09 MIL023 RAW WATER SYSTEM - COMMISSIONING 0 06JUL09 MIL029 DCS - FAT COMPLETION 0 20JUL09 U2MIL008 UNIT #2 - BOILER DRUM LIFTING 0 30JUL09 MIL018 UNIT #1 - STATION TRANSFORMER - CHARGING 0 16AUG09 U2MIL018 UNIT #2 - STATION TRANSFORMER - CHARGING 0 16AUG09 MIL009 UNIT #1 - TURBINE ERECTION START 0 19AUG09 MIL019 HT SWGR(STATION & UNIT) - COMMISSIONING COMPLN. 0 26AUG09 U2MIL010 UNIT #2 - CONDENSOR ERECTION START 0 30AUG09 MIL011 UNIT #1 - BOILER HYDRO-TEST COMPLETION 0 31AUG09 MIL020 LT SWGR(STATION & UNIT) - COMMISSIONING COMPLN. 0 15SEP09 MIL012 UNIT #1 - TURBINE BOX-UP 0 30SEP09 MIL028 CHIMNEY COMPLETION - BLU 0 13OCT09 MIL022 COMPRESSOR SYSTEM - COMMNG. & AIR AVAIL. TO EQPT 0 16OCT09 MIL032 UNIT #1 - TG OIL FLUSHING COMPLETION 0 24OCT09 MIL030 UNIT #1 - FUEL OIL SYSTEM - COMMISSIONING 0 25OCT09 MIL013 UNIT #1 - TURBINE ON BARRING GEAR 0 31OCT09 MIL014 UNIT #1 - BOILER LIGHT-UP 0 31OCT09 MIL027 ROADS & DRAINS - COMPLETION 0 15NOV09 U2MIL009 UNIT #2 - TURBINE ERECTION START 0 19NOV09 U2MIL011 UNIT #2 - BOILER HYDRO-TEST COMPLETION 0 30NOV09 MIL025 COAL HANDLING PLANT - COMMISSIONING 0 10DEC09 MIL031 FF , DETECTION & ALARM SYSTEMS - COMMG. COMPLN. 0 10DEC09 U2MIL012 UNIT #2 - TURBINE BOX-UP 0 30DEC09 MIL015 UNIT #1 - ROLLING & SYNCHRONIZATION 0 31DEC09 2008 MAR APR MAY JUN JUL AUG 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 ZERO DATE - PROJECT START RELEASE OF LOI TO BHEL KICK-OFF MEETING RELEASE OF LOI TO TPL © Primavera Systems, Inc. Start Date 01MAR08 Finish Date 17APR10 Data Date 18MAR08 Run Date 10SEP08 23:57 Early Bar Float Bar Progress Bar Critical Activity DAR7 2 X 80 MW CPP - DARIBA SMELTER COMPL Classic Schedule Layout Sheet 1 of 55 Date Revision Checked Approved PDF created with pdfFactory Pro trial version www.pdffactory.com
Transcript
Page 1: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

2 X 80 MW CPP - DARIBA SMELTER COMPLEXMAJOR MILESTONESSubtotal 761 18MAR08 17APR10

MIL001 ZERO DATE - PROJECT START 0 18MAR08

MIL002 RELEASE OF LOI TO BHEL 0 18MAR08

MIL003 KICK-OFF MEETING 0 02MAY08*

MIL004 RELEASE OF LOI TO TPL 0 03JUL08*

MIL006 CIVIL WORK START 0 02SEP08

MIL007 UNIT #1 - BOILER STRUCTURE ERECTION START 0 15JAN09

U2MIL007 UNIT #2 - BOILER STRUCTURE ERECTION START 0 15APR09

MIL008 UNIT #1 - BOILER DRUM LIFTING 0 30APR09

MIL010 UNIT #1 - CONDENSOR ERECTION START 0 30MAY09

MIL023 RAW WATER SYSTEM - COMMISSIONING 0 06JUL09

MIL029 DCS - FAT COMPLETION 0 20JUL09

U2MIL008 UNIT #2 - BOILER DRUM LIFTING 0 30JUL09

MIL018 UNIT #1 - STATION TRANSFORMER - CHARGING 0 16AUG09

U2MIL018 UNIT #2 - STATION TRANSFORMER - CHARGING 0 16AUG09

MIL009 UNIT #1 - TURBINE ERECTION START 0 19AUG09

MIL019 HT SWGR(STATION & UNIT) - COMMISSIONING COMPLN. 0 26AUG09

U2MIL010 UNIT #2 - CONDENSOR ERECTION START 0 30AUG09

MIL011 UNIT #1 - BOILER HYDRO-TEST COMPLETION 0 31AUG09

MIL020 LT SWGR(STATION & UNIT) - COMMISSIONING COMPLN. 0 15SEP09

MIL012 UNIT #1 - TURBINE BOX-UP 0 30SEP09

MIL028 CHIMNEY COMPLETION - BLU 0 13OCT09

MIL022 COMPRESSOR SYSTEM - COMMNG. & AIR AVAIL. TO EQPT 0 16OCT09

MIL032 UNIT #1 - TG OIL FLUSHING COMPLETION 0 24OCT09

MIL030 UNIT #1 - FUEL OIL SYSTEM - COMMISSIONING 0 25OCT09

MIL013 UNIT #1 - TURBINE ON BARRING GEAR 0 31OCT09

MIL014 UNIT #1 - BOILER LIGHT-UP 0 31OCT09

MIL027 ROADS & DRAINS - COMPLETION 0 15NOV09

U2MIL009 UNIT #2 - TURBINE ERECTION START 0 19NOV09

U2MIL011 UNIT #2 - BOILER HYDRO-TEST COMPLETION 0 30NOV09

MIL025 COAL HANDLING PLANT - COMMISSIONING 0 10DEC09

MIL031 FF , DETECTION & ALARM SYSTEMS - COMMG. COMPLN. 0 10DEC09

U2MIL012 UNIT #2 - TURBINE BOX-UP 0 30DEC09

MIL015 UNIT #1 - ROLLING & SYNCHRONIZATION 0 31DEC09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

ZERO DATE - PROJECT STARTRELEASE OF LOI TO BHELKICK-OFF MEETING

RELEASE OF LOI TO TPL

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:57

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 1 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 2: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

MIL033 UNIT #1 - BOILER COAL FIRING 0 06JAN10

U2MIL032 UNIT #2 - TG OIL FLUSHING COMPLETION 0 23JAN10

U2MIL030 UNIT #2 - FUEL OIL SYSTEM - COMMISSIONING 0 24JAN10

U2MIL013 UNIT #2 - TURBINE ON BARRING GEAR 0 30JAN10

U2MIL014 UNIT #2 - BOILER LIGHT-UP 0 31JAN10

MIL026 ASH HANDLING PLANT - COMMISSIONING 0 22FEB10

U2MIL015 UNIT #2 - ROLLING & SYNCHRONIZATION 0 31MAR10

U2MIL033 UNIT #2 - BOILER COAL FIRING 0 06APR10

MIL016 COMMISSIONING COMPLETION & PLANT HAND-OVER 0 17APR10

BASIC ENGINEERINGSubtotal 138 02MAY08 16SEP08

EN260 PREP & APPRL OF DBR - CIVIL 20 02MAY08 21MAY08

EN250 PREP & APPRL OF DBR - CHIMNEY 25 27MAY08 20JUN08

EN230 PREP & APPRL OF DBR - FUEL OIL SYSTEM 25 16JUN08 10JUL08

EN100 PLOT PLAN RELEASE FOR CONSTR. 50 04JUL08 22AUG08

EN110 LOAD LIST FINALISATION 25 04JUL08 28JUL08

EN140 PREP & APPRL OF DBR - ELECTRICAL SYS 45 09JUL08 22AUG08

EN130 PREP & APPRL OF DBR - WATER SYSTEM 35 14JUL08 17AUG08

EN150 PREP & APPRL OF DBR - COMPRESSED AIR SYS 25 14JUL08 07AUG08

EN200 PREP & APPRL OF DBR - FIRE PROT. & DETECT SYS 45 14JUL08 27AUG08

EN190 PREP & APPRL OF DBR - COAL HANDLING SYS 30 19JUL08 17AUG08

EN240 PREP & APPRL OF DBR - C&I 45 03AUG08 16SEP08

EN210 PREP & APPRL OF DBR - AC & VENTILATION 25 18AUG08 11SEP08

EN220 PREP & APPRL OF DBR - AHP 25 18AUG08 11SEP08

INTERFACESubtotal 652 12MAY08 22FEB10

TPL TO BHELTB001 UNIT #1 - BOILER FOUNDATION COMPLETION 0 25NOV08

TB002 UNIT #1 - ESP FOUNDATION COMPLETION 0 25JAN09

U2TB001 UNIT #2 - BOILER FOUNDATION COMPLETION 0 23FEB09

TB025 U#1 LP / HP HEATERS, DRAIN COOLER FOUND. COMPLN. 0 13MAR09

TB012 FUEL OIL PUMP SKID FOUNDATION READINESS 0 01APR09

U2TB002 UNIT #2 - ESP FOUNDATION COMPLETION 0 25APR09

TB020 EOT CRANE READINESS FOR EQUIPMENTS' ERECTION 0 21MAY09

TB014 UNIT #1 - BFP & CEP FOUNDATION COMPLETION 0 26MAY09

TB015 U#1 - AOP, JOP & EOP FOUNDATION COMPLETION 0 26MAY09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

PREP & APPRL OF DBR - CIVILPREP & APPRL OF DBR - CHIMNEY

PREP & APPRL OF DBR - FUEL OIL SYSTEMPLOT PLAN RELEASE FOR CONSTR.

LOAD LIST FINALISATIONPREP & APPRL OF DBR - ELECTRICAL SYS

PREP & APPRL OF DBR - WATER SYSTEMPREP & APPRL OF DBR - COMPRESSED AIR SYS

PREP & APPRL OF DBR - FIRE PROT. & DETECT SYSPREP & APPRL OF DBR - COAL HANDLING SYS

PREP & APPRL OF DBR - C&I

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:57

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 2 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 3: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

TB013 UNIT #1 CONDENSOR FOUNDATION COMPLETION 0 29MAY09

U2TB025 U#2 LP / HP HEATERS, DRAIN COOLER FOUND. COMPLN. 0 29MAY09

TB010 TG DECK READINESS FOR TG ERECTION - UNIT #1 0 05JUN09

TB016 U#1 - DEAERATOR FOUNDATION COMPLETION 0 05JUN09

TB026 U#1 OIL & AIR COOLER/EJECTOR SYSTEM FDN. COMPLN. 0 28JUN09

U2TB016 U#2 - DEAERATOR FOUNDATION COMPLETION 0 05JUL09

TB005 DM WATER FOR BOILER HYDRO-TEST (MANUAL MODE) 0 26JUL09

TB003 UNIT #1 - ID & FD FAN FOUNDATION COMPLETION 0 02AUG09

TB004 UNIT #1 - PA FAN FOUNDATION COMPLETION 0 09AUG09

TB011 TG BUILDING WITH SIDE & ROOF COVERING 0 09AUG09

TB027 U#1 FOUNDATION COMPLETION FOR OTHER AUX. & DUCTS 0 14AUG09

U2TB014 UNIT #2 - BFP & CEP FOUNDATION COMPLETION 0 24AUG09

U2TB015 U#2 - AOP, JOP & EOP FOUNDATION COMPLETION 0 24AUG09

TB028 HT SWITCH GEAR READINESS 0 26AUG09

U2TB013 UNIT #2 CONDENSOR FOUNDATION COMPLETION 0 29AUG09

U2TB010 TG DECK READINESS FOR TG ERECTION - UNIT #2 0 03SEP09

TB007 CHIMNEY READINESS FOR DUCT CONNECTION 0 08SEP09

TB019 ESP CONTROL ROOM READINESS 0 12SEP09

TB006 UNIT #1 - MILL FOUNDATION READINESS 0 13SEP09

TB017 LT SWITCH GEAR READINESS 0 15SEP09

TB029 READINESS OF CONTROL ROOM FOR PANEL ERECTION 0 17SEP09

U2TB026 U#2 OIL & AIR COOLER/EJECTOR SYSTEM FDN. COMPLN. 0 26SEP09

TB008 CHIMNEY READINESS FOR BOILER LIGHT-UP 0 28SEP09

TB018 AC SYSTEM READINESS 0 30SEP09

TB035 VENTILATION SYSTEM READINESS 0 13OCT09

TB024 AIR AVAILABILITY TO EQUIPMENTS 0 16OCT09

TB021 CW SYSTEM READINESS / EQUIPMENT CW AVAILABILITY 0 22OCT09

U2TB003 UNIT #2 - ID & FD FAN FOUNDATION COMPLETION 0 31OCT09

U2TB004 UNIT #2 - PA FAN FOUNDATION COMPLETION 0 07NOV09

U2TB027 U#2 FOUNDATION COMPLETION FOR OTHER AUX. & DUCTS 0 12NOV09

TB023 UNIT #1 - AHP READINESS FOR COAL FIRING 0 14NOV09

TB022 CHP READINESS FOR COAL SUPPLY TO BUNKERS 0 10DEC09

U2TB006 UNIT #2 - MILL FOUNDATION READINESS 0 12DEC09

U2TB023 UNIT #2 - AHP READINESS FOR COAL FIRING 0 22FEB10

BHEL TO TPLBT001 I/P FOR BOILER., FAN, MILL, CHIMNEY, ESP 0 11MAY08

BT003 I/P FOR ESP CONTROL ROOM 0 14MAY08

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

I/P FOR BOILER., FAN, MILL, CHIMNEY, ESPI/P FOR ESP CONTROL ROOM

U#1 - DEAERATOR FOUNDATION COMPLETION

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:57

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 3 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 4: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

BT004 UNIT #1 FOUNDATION BOLTS / INSERTS FOR BOILER 0 27AUG08

BT017 I/P DATA FOR PIPERACK 0 29AUG08

BT002 FUEL OIL PUMP SKID DETAILS 0 28SEP08

BT005 UNIT #1 - FOUNDATION BOLTS / INSERTS FOR ESP 0 30OCT08

U2BT004 UNIT #2 FOUNDATION BOLTS / INSERTS FOR BOILER 0 25NOV08

U2BT005 UNIT #2 - FOUNDATION BOLTS / INSERTS FOR ESP 0 28JAN09

BT015 UNIT #1 CLEARANCE FOR PA FAN FOUNDATION ABOVE GL 0 30APR09

BT009 UNIT #1 - BOILER AREA CLEARANCE FOR PAVING 0 11MAY09

BT0131 U#1 - FOUNDATION BOLTS / INSERTS FOR FD, ID FANS 0 10JUN09

BT012 UNIT #1RELEASE OF FRONT AFTER CONDENSOR ERECTION 0 21JUN09

BT0132 U#1 - FOUNDATION BOLTS / INSERTS FOR PA FANS 0 05JUL09

BT013 UNIT #1 - FOUNDATION BOLTS / INSERTS FOR MILLS 0 10JUL09

BT014 U#1CLRNCE FOR ERECT. OF CABLE TRAYS IN BLR. AREA 0 18JUL09

U2BT015 UNIT #2 CLEARANCE FOR PA FAN FOUNDATION ABOVE GL 0 30JUL09

U2BT009 UNIT #2 - BOILER AREA CLEARANCE FOR PAVING 0 10AUG09

BT011 UNIT #1COMPLETION OF PLACING OF TG ON FOUNDATION 0 17AUG09

BT016 U#1 CLRNCE.-CONST OF STG COOL AIR DUCT CONIC POR 0 18AUG09

BT006 U#1CLEARANCE FOR COMPLETION OF BOTTOM ASH HOPPER 0 31AUG09

BT008 UNIT#1 - BOILER HYDRO-TEST COMPLETION 0 31AUG09

U2BT0131 U#2 - FOUNDATION BOLTS / INSERTS FOR FD, ID FANS 0 08SEP09

BT010 UNIT #1 COMPLETION OF TG ERECTION 0 19SEP09

U2BT012 UNIT #2RELEASE OF FRONT AFTER CONDENSOR ERECTION 0 21SEP09

U2BT0132 U#2 - FOUNDATION BOLTS / INSERTS FOR PA FANS 0 03OCT09

U2BT013 UNIT #2 - FOUNDATION BOLTS / INSERTS FOR MILLS 0 08OCT09

BT007 U#1ESP/ECO/APH RELS FOR ERECT. OF FLY ASH SYSTEM 0 13OCT09

U2BT014 U#2CLRNCE FOR ERECT. OF CABLE TRAYS IN BLR. AREA 0 17OCT09

U2BT011 UNIT #2COMPLETION OF PLACING OF TG ON FOUNDATION 0 17NOV09

U2BT016 U#2 CLRNCE.-CONST OF STG COOL AIR DUCT CONIC POR 0 18NOV09

U2BT006 U#2CLEARANCE FOR COMPLETION OF BOTTOM ASH HOPPER 1 30NOV09 30NOV09

U2BT008 UNIT#2 - BOILER HYDRO-TEST COMPLETION 0 30NOV09

U2BT010 UNIT #2 COMPLETION OF TG ERECTION 0 22DEC09

U2BT007 U#2ESP/ECO/APH RELS FOR ERECT. OF FLY ASH SYSTEM 0 13JAN10

GENERALSubtotal 467 02MAY08 11AUG09

SITE PREPAREDNESSSSP100 SITE CLEARENCE TO START WORK 0 01MAY08

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:57

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 4 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 5: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

SSP120 CONST. WATER AVAILABILITY 0 01MAY08

SSP170 FURNISHING LOCATION FOR CRUSHER WITH POWER POINT 0 03MAY08

SSP110 CONST. POWER AVAILABILITY 0 05MAY08

SSP122 APPROACH ROAD FROM HZL BL. TO CPP 0 30MAY08

SSP130 DISTRIBUTION OF CONST. WATER 40 01JUN08 10JUL08

SSP140 READYNESS OF CONST POWER 50 01JUN08 20JUL08

SSP160 TPL - SITE STORE READINESS 80 11JUN08 29AUG08

SSP150 TPL - SITE OFFICE READINESS 60 01JUL08 29AUG08

SSPB001 BHEL - SITE OFFICE READINESS 60 15AUG08 13OCT08

SSPB002 BHEL - SITE STORE READINESS 50 21OCT08 09DEC08

SSP180 RAW WATER RESERVOIR AVAILABILITY 0 17MAR09

SSP210 SERVICE AIR AVAILABILITY 0 09MAY09

SSP190 POTABLE / FIRE WATER AVAILABILITY 0 15JUN09

SSP200 DM WATER AVAILABILITY 0 03JUL09

SSP230 SWITCHYARD AVAILABILITY 0 11AUG09

RESOURCE START-UPRSP125 TPL -SITE MOBILIZATION 80 12MAY08 30JUL08

RSPB014 CIVIL CONTRACT FINALIZATION 45 21JUN08 04AUG08

RSPB015 STRUCTURAL CONTRACT FINALIZATION 45 01JUL08 14AUG08

RSPB016 MOBILISATION OF CIVIL CONTRACTOR 25 05AUG08 29AUG08

RSPB017 MOBILISATION STRL CONTRACTOR 30 15AUG08 13SEP08

RSPB003 FINALIZATION OF BOILER ERECTION CONTRACTOR 0 16OCT08

RSPB011 FINALIZATION OF MATERIAL HANDLING AGENCY 0 16OCT08

RSP135 ORDERING OF BOP PIPING ERECTION CONTRACTOR 45 20OCT08 03DEC08

RSPB012 MOBILIZATION OF MATERIAL HANDLING AGENCY 25 01NOV08 25NOV08

RSPB005 FINALIZATION OF TG ERECTION CONTRACTOR 0 14NOV08

RSPB004 MOBILIZATION OF BOILER ERECTION CONTRACTOR 30 16NOV08 15DEC08

RSP175 BOP ELECT. ERECTION CONTRACT FINALISATION 60 28NOV08 26JAN09

RSP145 MOBILISATION OF BOP PIPING ERECTION CONTRACTOR 30 11DEC08 09JAN09

RSPB006 MOBILIZATION OF TG ERECTION CONTRACTOR 30 15DEC08 13JAN09

RSP185 MOBILISATION OF BOP ELECTRICAL ERE CONTRACTOR 45 27JAN09 12MAR09

RSP225 MOBILIZATION OF FF/FD SYSTEM ERECTION CONTRACTOR 30 14FEB09 15MAR09

RSP155 ORDERING - BOP C&I ERECTION CONTRACTOR 55 19FEB09 14APR09

RSPB007 FINALIZATION OF BTG ELECT. ERECTION CONTRACTOR 0 07MAR09

RSPB009 FINALIZATION OF BTG C&I ERECTION CONTRACTOR 0 12MAR09

RSPB008 MOBILIZATION OF BTG ELECT. ERECTION CONTRACTOR 25 23MAR09 16APR09

RSPB010 MOBILIZATION OF BTG C&I ERECTION CONTRACTOR 25 28MAR09 21APR09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11CONST. WATER AVAILABILITY

CONST. POWER AVAILABILITYAPPROACH ROAD FROM HZL BL. TO CPP

DISTRIBUTION OF CONST. WATERREADYNESS OF CONST POWER

TPL - SITE STORE READINESSTPL - SITE OFFICE READINESS

BHEL - SITE OFFICE READINESS

TPL -SITE MOBILIZATIONCIVIL CONTRACT FINALIZATION

STRUCTURAL CONTRACT FINALIZATIONMOBILISATION OF CIVIL CONTRACTOR

MOBILISATION STRL CONTRACTOR

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:57

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 5 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 6: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

RSP165 MOBILI OF BOP C&I ERECTION CONTRACTOR TO SITE 30 15APR09 14MAY09

UNIT I - BTGSubtotal 739 18MAR08 26MAR10

STEAM GENERATION BOILER FOUNDATION

ENGINEERING

EN450 BOILER FOUNDATION DRG 20 22MAY08 10JUN08

BBE001 BOILER FOUNDATION ENGG 30 16JUN08 15JUL08 PROCUREMENT

BBP001 INDENTIG/ORDERING/RECEIPT OF MATERIAL-Boiler 15 16JUL08 30JUL08

BBP002 MFG & DISPATCH OF FOUNDATION MATLS 28 31JUL08 27AUG08 CIVIL

BA100 FOUND FOR BOILER MAIN COLUMN 60 28AUG08 26OCT08

BA110 FOUND FOR BOILER AUXILIARY COLUMN 50 02OCT08 20NOV08

BA150 READINESS OF BOILER FOUNDATION 5 21NOV08 25NOV08

BOILER STRUCTURE ENGINEERING

BSE001 ENGINEERING- BOILER STR. 30 21JUN08 20JUL08 PROCUREMENT

BSP001 RECEIPT OF BOILER STR. MATERIAL AT WORKS 10 21JUL08 30JUL08

BSP002 MANUFACTURING - BOILER STRUCTURE 128 22JUL08 26NOV08

BSP003 DESPATCH MAIN BOILER STRUCTURE 120 29AUG08 26DEC08

BSP004 DESPATCH AUXILIARY STRUCTURE 180 31AUG08 26FEB09 ERECTION/COMMISSIONING

BSEC001 ERCN. OF MAIN BOILER STR. 90 15JAN09 14APR09

BSEC002 ERECTION OF AUX STR. 50 01MAR09 19APR09

BSEC003 STR. ERECTION BEFORE DRUM LIFTING 5 26MAR09 30MAR09

BOILER DRUM ENGINEERING

BDE001 ENGINEERING- BOILER DRUM 30 02MAY08 31MAY08 PROCUREMENT

BDP001 INTEND. & RECEIPT OF BOILER DRUM MTRL. AT WORKS 156 10MAY08 12OCT08

BDP002 MANUFACTURING & DISPATCH- BOILER DRUM 170 13OCT08 31MAR09 ERECTION/COMMISSIONING

BDEC001 BOILER DRUM LIFTING 0 30APR09

BOILER PRESSURE PARTS ENGINEERING

BPE001 ENGINEERING- BOILER PRESS PARTS 30 16JUL08 14AUG08 PROCUREMENT

BPP001 RECEIPT OF BOILER PRESS. PARTS MATERIAL AT WORKS 85 06AUG08 29OCT08

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

BOILER FOUNDATION DRGBOILER FOUNDATION ENGG

INDENTIG/ORDERING/RECEIPT OF MATERIAL-BoilerMFG & DISPATCH OF FOUNDATION MATLS

ENGINEERING- BOILER STR.

RECEIPT OF BOILER STR. MATERIAL AT WORKSMANUFACTURING - BOILER STRUCTURE

ENGINEERING- BOILER DRUM

ENGINEERING- BOILER PRESS PARTS

RECEIPT OF BOILER PRESS. PARTS MATERIAL AT WORKS

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:57

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 6 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 7: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

BPP002 MANUFACTURING- BOILER PRESS. PARTS 280 05SEP08 11JUN09

BPP003 DESPATCH- BOILER PRESS. PARTS 160 11JAN09 19JUN09 ERECTION/COMMISSIONING

BPEC001 BANK TUBES, WW HDR., WW PANEL & D' COMER ERECN. 90 01MAY09 29JUL09

BPEC002 SH HDR., SH TUBES ASSY. ERECN. 25 06MAY09 30MAY09

BPEC003 MAIN STEAM PIPG. ERECN 20 31MAY09 19JUN09

BPEC004 ECO.LINK,HDR & BANK ASSY., BLR. FEED PIPG. ERCN. 25 20JUN09 14JUL09

BPEC005 OTHER ACT. COMPLN. & READY FOR HT/IBR CLEARANCE 26 30JUL09 24AUG09

BPEC006 HYDRAULIC TEST OF BOILER 7 25AUG09 31AUG09

BPEC008 EDTA CLEANING / ALKALI BOIL-OUT 5 01NOV09 05NOV09

BPEC007 ACID CLEANING 4 06NOV09 09NOV09

BOILER INSULATION ENGINEERING

BIE001 ENGINEERING FOR INSULATION- BOILER INSULATION 15 20AUG08 03SEP08 PROCUREMENT

BIP001 RECEIPT OF MATERIAL AT WORKS- BOILER INSULATION 60 27APR09 25JUN09

BIP002 MANUFACTURING- BOILER INSULATION 85 28APR09 21JUL09

BIP003 DESPATCH- BOILER INSULATION 30 22JUL09 20AUG09 ERECTION/COMMISSIONING

BIEC001 INSULATION & LINING- BOILER 45 01SEP09 15OCT09

SHEETING ENGINEERING

BGE001 ENGINEERING-SHEETING 20 30AUG08 18SEP08 PROCUREMENT

BGP001 INDENTING & ORDERING-SHEETING 45 19SEP08 02NOV08

BGP002 DELIVERY AT SITE-SHEETING 210 17JAN09 14AUG09 ERECTION/COMMISSIONING

BGEC001 ERECTION-SHEETING 60 21OCT09 19DEC09

VALVE ENGINEERING

BVE001 ENGINEERING - VALVES 45 31JUL08 13SEP08 PROCUREMENT

BVP001 ORDERING - VALVES 90 14SEP08 12DEC08

BVP002 MANUFACTURING - VALVES 295 13DEC08 03OCT09

BVP003 DELIVERY AT SITE - VALVES FOR HT 150 27JAN09 25JUN09

BVP004 DELIVERY AT SITE - VALVES FOR LU 120 28MAR09 25JUL09

BVP005 DELIVERY AT SITE - VALVES FOR SYN 90 16JUL09 13OCT09ERECTION/COMMISSIONING

BVEC001 ERECTION - VALVES FOR HT 30 15JUL09 13AUG09

BVEC002 ERECTION - VALVES FOR LU 60 17AUG09 15OCT09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

ENGINEERING - VALVES

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:57

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 7 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 8: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

BVEC003 ERECTION - VALVES FOR SYN 35 05NOV09 09DEC09

ELECTRICAL ENGINEERING

TEE001 ENGINEERING - ELECTRICAL 50 30AUG08 18OCT08 PROCUREMENT

TEP001 ORDERING - ELECTRICAL 75 19OCT08 01JAN09

TEP002 MANUFACTURING - ELECTRICAL 225 18NOV08 30JUN09

TEP003 DELIVERY - ELECTRICAL 75 27APR09 10JUL09 ERECTION/COMMISSIONING

TEEC002 MCC ERECTION & COMMISSIONING 20 22AUG09 10SEP09

TEEC001 CABLE TRAY LAYING & CABLING 65 01SEP09 04NOV09

TEEC003 ERECTION & PRE-COMMISSIONING - REQD. FOR BLU 20 01SEP09 20SEP09

TEEC004 ERECTION & PRE-COMMISSIONING - REQD. FOR SYN. 50 21SEP09 09NOV09

C&I ENGINEERING

TIE001 ENGINEERING - C&I 50 09SEP08 28OCT08 PROCUREMENT

TIP001 ORDERING - C&I 85 29OCT08 21JAN09

TIP002 MANUFACTURING - C&I 250 28NOV08 04AUG09

TIP003 DELIVERY - C&I 90 06JUN09 03SEP09 ERECTION/COMMISSIONING

TIEC001 CABLING 75 06SEP09 19NOV09

TIEC002 ERECTION & PRE-COMMISSIONING - REQD. FOR BLU 22 24SEP09 15OCT09

TIEC003 ERECTION & PRE-COMMISSIONING - REQD. FOR SYN. 55 03OCT09 26NOV09

FUEL OIL SYSTEM ENGINEERING

FOE001 ENGINEERING - FUEL OIL SYSTEM 30 30AUG08 28SEP08PROCUREMENT

FOP001 ORDERING - FUEL OIL SYSTEM 45 29SEP08 12NOV08

FOP002 MANUFACTURING - FUEL OIL SYSTEM 190 13NOV08 21MAY09

FOP003 DELIVERY AT SITE - FUEL OIL SYSTEM 50 12MAY09 30JUN09 ERECTION/COMMISSIONING

FOEC001 ERECTION-FUEL OIL PUMP 30 31JUL09 29AUG09

FOEC002 ERECTION-FUEL OIL PIPING 50 27AUG09 15OCT09

FOEC003 PRE-COMMISSIONING-FUEL OIL PUMP 10 16SEP09 25SEP09

FOEC0021 HT - FUEL OIL PIPING 10 16OCT09 25OCT09

BOILER FURNACE & OTHER LU ACTIVITIES (MECH.) ENGINEERING

LUME001 ENGINEERING - BLR.FURNACE & OTHER LU ACT. (MECH) 40 16AUG08 24SEP08

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

ENGINEERING - BLR.FURNACE & OTHER LU ACT. (MECH)

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:57

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 8 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 9: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

PROCUREMENT

LUMP001 ORDERING - BLR.FURNACE & OTHER LU ACT.(MECH) 45 25SEP08 08NOV08

LUMP002 MANUFACTURING-BLR.FURNACE & OTHER LU ACT.(MECH) 350 25SEP08 09SEP09

LUMP003 DELIVERY - BLR.FURNACE & OTHER LU ACT.(MECH) 240 20JAN09 16SEP09 ERECTION/COMMISSIONING

LUMEC004 OTHER ACT. COMPLN. & READY FOR BLU 145 24MAY09 15OCT09

LUMEC001 BURNER ASSEMBLY 45 01SEP09 15OCT09

LUMEC002 FURNACE DOORS FIXING 45 01SEP09 15OCT09

LUMEC003 REFRACTORY & CASING/ENCLOSURE WORKS 40 01SEP09 10OCT09

LUMEC005 ERECTION - BLOWER SYSTEMS 55 01SEP09 25OCT09

BALANCE ACTIVITIES FOR CF & SYN. (MECH.) ENGINEERING

CSME001 ENGINEERING - BAL. ACT. FOR CF & SYN. (MECH.) 30 30AUG08 28SEP08 PROCUREMENT

CSMP001 ORDERING - BAL. ACT. FOR CF & SYN. (MECH.) 45 29SEP08 12NOV08

CSMP002 MANUFACTURING - BAL. ACT. FOR CF & SYN. (MECH.) 350 29OCT08 13OCT09

CSMP003 DELIVERY - BAL. ACT. FOR CF & SYN. (MECH.) 130 21JUN09 28OCT09 ERECTION/COMMISSIONING

CSMEC002 ERECTION - COAL SYSTEM 65 11OCT09 14DEC09

CSMEC003 OTHER ACT. COMPLN. & READY FOR SYN. 55 16OCT09 09DEC09

AIR & FLUE GAS HANDLING ESP

ENGINEERING

EN460 ESP FOUNDATION DGR 20 11JUN08 30JUN08

BEE001 ENGINEERING - ESP 60 18JUL08 15SEP08 PROCUREMENT

BEP002 MANUFACTURING- ESP 426 17AUG08 16OCT09

BEP001 ORDERING OF MATERIAL - ESP 150 16SEP08 12FEB09

BEP003 DELIVERY AT SITE - ESP 315 21DEC08 31OCT09 CIVIL

BA120 FOUND FOR ESP 75 11OCT08 24DEC08

BA160 READINESS OF ESP FOUNDATION 12 14JAN09 25JAN09 ERECTION/COMMISSIONING

BEEC001 ERECTION- ESP COLUMNS & PANELS 75 31JAN09 15APR09

BEEC0011 ERECTION-ESP ROOF, FUNNELS, INTERNALS & HOPPERS 195 01APR09 13OCT09

BEEC0012 ESP INSULATION 90 16JUL09 13OCT09

BEEC002 ESP BOX-UP & READINESS FOR BLU 0 13OCT09

BEEC0021 ERECTION-RECTIFIER SYSTEM & OTHER ACT. FOR CF/SY 60 14OCT09 12DEC09

BEEC003 ESP READINESS FOR CF 0 12DEC09

BEEC004 ESP READINESS FOR SYN. 0 12DEC09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

ESP FOUNDATION DGRENGINEERING - ESP

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:57

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 9 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 10: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

DAMPER, GATE & ACTUATOR ENGINEERING

BAE001 DAMPERS, GATES, ACTUATORS - ENGG. 30 22JUN08 21JUL08 PROCUREMENT

BAP001 ORDG. OF MTRL - DAMPERS, GATES, ACTUATORS 90 22JUL08 19OCT08

BAP002 MANUFACTURING - DAMPERS, GATES, ACTUATORS 330 22JUL08 16JUN09

BAP003 SITE DELIVERY - DAMPERS, GATES, ACTUATORS 36 26MAY09 30JUN09 ERECTION/COMMISSIONING

BAEC001 EREC. COMPLN. - DAMPERS, GATES, ACTUATORS 75 16JUL09 28SEP09

FAN ENGINEERING

EN470 FAN FOUNDATION ENGG 30 01JUL08 30JUL08

BRE001 FANS FD/ID/PA - ENGINEERING 30 16JUL08 14AUG08

FAME001 ENGINEERING - FAN MOTOR 35 21SEP08 25OCT08 PROCUREMENT

BRP001 ORDERING OF MATERIAL - FANS 60 15AUG08 13OCT08

BRP003 MANUFACTURING - FANS 400 15AUG08 18SEP09

FAMP001 MANUFACTURING - FAN MOTOR 150 26OCT08 24MAR09

BRP002 RECEIPT OF MATERIAL AT WORKS - FAN 90 13MAR09 10JUN09

BRP005 DELIVERY AT SITE - FD FAN 150 18MAR09 14AUG09

FAMP002 DELIVERY TO SITE - FAN MOTOR 15 25MAR09 08APR09

BRP004 DELIVERY AT SITE - ID FAN 75 17MAY09 30JUL09

BRP006 DELIVERY AT SITE - PA FAN 130 22MAY09 28SEP09 CIVIL

BA130 FOUND FOR FD,PA,ID FANS - UPTO GL 60 21NOV08 19JAN09

BA133 FOUND FOR FD,ID FANS - ABOVE GL 45 11JUN09 25JUL09

BA135 FOUND FOR PA FANS - ABOVE GL 30 06JUL09 04AUG09

BA165 READINESS OF FD & ID FAN FOUNDATION 8 26JUL09 02AUG09

BA170 READINESS OF PA FAN FOUNDATION 5 05AUG09 09AUG09 ERECTION/COMMISSIONING

BREC001 ERECTION OF ID FAN 60 11JUL09 08SEP09

FAMEC001 ERECTION - FAN MOTOR 20 03AUG09 22AUG09

BREC002 ERECTION OF FD FAN 60 08AUG09 06OCT09

BREC003 ERECTION OF PA FAN 60 20AUG09 18OCT09

FAMEC002 COMMISSIONING - FAN MOTOR 1 23AUG09 23AUG09

BREC005 ID FAN - PRECOMMISSIONING 2 23OCT09 24OCT09

BREC006 FD FAN - PRECOMMISSIONING 2 23OCT09 24OCT09

BREC007 PA FAN - PRECOMMISSIONING 2 23OCT09 24OCT09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

DAMPERS, GATES, ACTUATORS - ENGG.

ORDG. OF MTRL - DAMPERS, GATES, ACTUATORSMANUFACTURING - DAMPERS, GATES, ACTUATORS

FAN FOUNDATION ENGGFANS FD/ID/PA - ENGINEERING

ORDERING OF MATERIAL - FANSMANUFACTURING - FANS

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:57

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 10 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 11: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

AIR-HEATER ENGINEERING

BHE001 ENGG. - AIR HEATER 60 16JUL08 13SEP08 PROCUREMENT

BHP001 ORDERING OF MATERIAL - AIR HEATER 50 26JUL08 13SEP08

BHP003 MANUFACTURING - AIR HEATER 335 15AUG08 15JUL09

BHP002 RECEIPT OF MATERIAL AT WORKS - AIR HEATER 70 02JAN09 12MAR09

BHP004 DELIVERY AT SITE - AIR HEATER 130 23MAR09 30JUL09 ERECTION/COMMISSIONING

BHEC001 ERECTION- AIR HEATER 82 20MAY09 09AUG09

BHEC002 PRE-COMMISSIONING-AIRHEATER 35 25AUG09 28SEP09

BHEC003 READINESS FOR BLU- AIR HEATER 2 29SEP09 30SEP09

DUCTING ENGINEERING

BTE001 ENGINEERING - DUCTING 30 25AUG08 23SEP08 PROCUREMENT

BTP001 MANUFACTURING-DUCTING 360 24SEP08 18SEP09

BTP002 DESPATCH-DUCTING 162 22APR09 30SEP09 CIVIL

BA140 FOUND FOR OTHER AUX & DUCTS 45 01JUL09 14AUG09 ERECTION/COMMISSIONING

BTEC001 ERECTION - DUCTING 70 12AUG09 20OCT09

ELECTRICAL ENGINEERING

REE001 ENGINEERING - ELECTRICAL 25 05JUN08 29JUN08 PROCUREMENT

REP001 ORDERING - ELECTRICAL 75 30JUN08 12SEP08

REP002 MANUFACTURING - ELECTRICAL 415 30JUL08 17SEP09

REP003 DELIVERY - ELECTRICAL 90 30JUN09 27SEP09 ERECTION/COMMISSIONING

REEC001 CABLE TRAY LAYING & CABLING 70 15JUL09 22SEP09

REEC003 ERECTION & PRE-COMMISSIONING - REQD. FOR BLU 70 09AUG09 17OCT09

REEC004 ERECTION & PRE-COMMISSIONING - REQD. FOR SYN. 80 08SEP09 26NOV09

REEC002 MCC ERECTION & COMMISSIONING 20 18SEP09 07OCT09

C&I ENGINEERING

RIE001 ENGINEERING - C&I 45 16JUN08 30JUL08 PROCUREMENT

RIP001 ORDERING - C&I 50 31JUL08 18SEP08

RIP002 MANUFACTURING - C&I 420 30AUG08 23OCT09

RIP003 DELIVERY - C&I 125 03JUL09 04NOV09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

ENGG. - AIR HEATER

ORDERING OF MATERIAL - AIR HEATERMANUFACTURING - AIR HEATER

ENGINEERING - ELECTRICAL

ORDERING - ELECTRICALMANUFACTURING - ELECTRICAL

ENGINEERING - C&I

ORDERING - C&I

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:57

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 11 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 12: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

ERECTION/COMMISSIONING

RIEC001 CABLING 72 20JUL09 29SEP09

RIEC002 ERECTION & PRE-COMMISSIONING - REQD. FOR BLU 31 16SEP09 16OCT09

RIEC003 ERECTION & PRE-COMMISSIONING - REQD. FOR SYN. 84 16SEP09 08DEC09

PULVERIZING MILLS

ENGINEERING

MIE001 ENGINEERING- MILLS 30 06JUL08 04AUG08

MIME001 ENGINEERING - MILL MOTOR 35 21SEP08 25OCT08

EN520 CIVIL DRG FOR MILL FOUNDATION 30 09OCT08 07NOV08 PROCUREMENT

MIP001 INDENTING OF MATERIAL-MILLS 45 05AUG08 18SEP08

MIP002 ORDERING OF MATERIAL-MILLS 60 04SEP08 02NOV08

MIMP001 MANUFACTURING - MILL MOTOR 150 26OCT08 24MAR09

MIP003 RECEIPT OF MATERIAL AT WORKS-MILLS 150 03NOV08 01APR09

MIP004 MANUFACTURING-MILLS 285 03DEC08 13SEP09

MIMP002 DELIVERY TO SITE - MILL MOTOR 15 25MAR09 08APR09

MIP005 DESPATCH & DELIVERY AT SITE - MILLS 100 21JUN09 28SEP09 CIVIL

BU130 FOUNDATION OF MILLS ( UPTO GL ) 60 30JAN09 30MAR09

BU135 FOUNDATION OF MILLS ( ABOVE GL ) 40 26JUL09 03SEP09

BU150 RELEASE FRONT TO BHEL FOR MILL ERECTION 10 04SEP09 13SEP09 ERECTION/COMMISSIONING

MIEC002 MILLS ERECTION 85 14SEP09 07DEC09

MIMEC001 ERECTION - MILL MOTOR 30 14SEP09 13OCT09

MIMEC002 COMMISSIONING - MILL MOTOR 5 14OCT09 18OCT09

MIEC003 MILLS COMMISSIONING 7 08DEC09 14DEC09

POWER CYCLE STEAM TURBINE

ENGINEERING

STE001 ENGINEERING- STEAM TURBINE 198 28MAR08 11OCT08 PROCUREMENT

STP001 ORDERING OF MATERIAL- ST 135 29APR08 10SEP08

STP002 RECEIPT OF MATERIAL AT WORKS- ST 280 29MAY08 04MAR09

STP003 MANUFACTURING- ST 260 11SEP08 28MAY09

STP0031 AVL. SUB-ASSEMBLIES & PREPARATION FOR MRT 50 29MAY09 18JUL09

STP004 MECHANICAL RUN TEST COMPLETION 5 19JUL09 23JUL09

STP005 DESPATCH & DELIVERY AT SITE - ST 13 24JUL09 05AUG09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

ENGINEERING- MILLS

INDENTING OF MATERIAL-MILLS

ORDERING OF MATERIAL- STRECEIPT OF MATERIAL AT WORKS- ST

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:57

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 12 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 13: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

ERECTION/COMMISSIONING

STEC001 ERECTION- ST 40 19AUG09 27SEP09

STEC002 TURBINE - LIVE STEAM VALVE ERECTION 10 18SEP09 27SEP09

STEC003 TURBINE BOX UP 3 28SEP09 30SEP09

STEC0031 TURBINE - OTHER ACT. & READINESS FOR SYN. 30 01OCT09 30OCT09

GENERATOR & AUX. ENGINEERING

GEE001 ENGINEERING- GEN. & AUX. 140 28MAR08 14AUG08 PROCUREMENT

GEP001 ORDERING OF MATERIAL- GEN. & AUX. 80 07APR08 25JUN08

GEP002 RECEIPT OF MATERIAL AT WORKS- GEN. & AUX. 280 22MAY08 25FEB09

GEP003 MANUFACTURING- GEN. & AUX. 226 27NOV08 10JUL09

GEP004 ASSEMBLY & TESTING- GEN. & AUX. 35 07JUL09 10AUG09

GEP005 DESPATCH & DELIVERY AT SITE - GEN. & AUX. 6 11AUG09 16AUG09 ERECTION/COMMISSIONING

GEEC001 GENERATOR - ERECTION 33 17AUG09 18SEP09

GEEC002 GEN AUX. ERECTION INCLUDING GCP, GRP 20 27AUG09 15SEP09

GEEC003 GENERATOR PRE- & FINAL ALIGNMENT 5 26SEP09 30SEP09

BFP & BOOSTER PUMP ENGINEERING

BFE001 ENGINEERING- BFP & BOOSTER PUMP 120 12MAY08 08SEP08

BFME001 ENGINEERING - BFP MOTOR 35 21SEP08 25OCT08 PROCUREMENT

BFP001 ORDERING - BFP DD ITEMS 60 20MAY08 18JUL08

BFP002 MFRG / SITE DELIVERY - BFP SUB-VENDOR & DD ITEMS 326 30MAY08 20APR09

BFMP001 MANUFACTURING - BFP MOTOR 150 26OCT08 24MAR09

BFP003 MANUFACTURING - BFP & BOOSTER PUMP 84 28JAN09 21APR09

BFMP002 DELIVERY TO SITE - BFP MOTOR 15 25MAR09 08APR09

BFP004 ASSEMBLY & TESTING - BFP & BOOSTER PUMP 28 15APR09 12MAY09

BFP005 DESPATCH & DELIVERY AT SITE- BFP & BOOSTER PUMP 14 06MAY09 19MAY09 CIVIL

TG115 BFP FOUNDATION WORKS 45 11MAR09 24APR09

TG165 READINESS FOR BFP ERECTION 0 01MAY09 ERECTION/COMMISSIONING

BFMEC001 ERECTION - BFP MOTOR 10 27MAY09 05JUN09

BFEC001 ERECTION - BFP 22 01JUN09 22JUN09

BFEC002 ERECTION - BOOSTER PUMP 10 01JUN09 10JUN09

BFMEC002 COMMISSIONING - BFP MOTOR 2 06JUN09 07JUN09

BFEC003 PRE-COMMISSIONING - BFP & BOOSTER PUMP 3 23OCT09 25OCT09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

ORDERING - BFP DD ITEMS

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:57

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 13 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 14: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

CEP ENGINEERING

CEE001 ENGINEERING- CEP 120 09MAY08 05SEP08

CEME001 ENGINEERING - CEP MOTOR 35 21SEP08 25OCT08 PROCUREMENT

CEP001 ORDERING - CEP DD ITEMS 59 20MAY08 17JUL08

CEP002 MFRG & DELIVERY AT SITE - BFP SUB-VENDOR ITEMS 194 18JUL08 27JAN09

CEMP001 MANUFACTURING - CEP MOTOR 150 26OCT08 24MAR09

CEP003 MANUFACTURING- CEP 84 28JAN09 21APR09

CEMP002 DELIVERY TO SITE - CEP MOTOR 15 25MAR09 08APR09

CEP004 ASSEMBLY & TESTING- CEP 21 22APR09 12MAY09

CEP005 DESPATCH & DELIVERY AT SITE- CEP 7 13MAY09 19MAY09 CIVIL

TG160 CEP FOUNDATION WORKS 30 27APR09 26MAY09 ERECTION/COMMISSIONING

CEMEC001 ERECTION - CEP MOTOR 10 27MAY09 05JUN09

CEEC001 ERECTION- CEP 25 01JUN09 25JUN09

CEMEC002 COMMISSIONING - CEP MOTOR 2 06JUN09 07JUN09

CEEC002 PRE-COMMISSIONING - CEP 15 23OCT09 06NOV09

LUBE OIL PUMP & TANK ENGINEERING

LOE001 ENGINEERING- LUBEOILPUMPS & TANKS 30 16JUL08 14AUG08 PROCUREMENT

LOP001 INDENT&ORDER OF MATERIAL- LUBEOILPUMPS & TANKS 48 31JUL08 16SEP08

LOP002 MANUFACTURING- LUBEOILPUMPS & TANKS 256 17SEP08 30MAY09

LOP003 RECEIPT OF MATERIAL AT SITE- LUBEOILPUMPS & TANK 11 31MAY09 10JUN09 ERECTION/COMMISSIONING

LOEC001 ERECTION- LUBEOILPUMPS & TANKS 25 11JUN09 05JUL09

LOEC002 PRE-COMMISSIONING- LUBEOILPUMPS & TANKS 9 16SEP09 24SEP09

DRAIN COOLER ENGINEERING

DCE001 ENGINEERING - DRAIN COOLER 10 18MAR08 27MAR08 PROCUREMENT

DCP001 ORDERING - DRAIN COOLER 33 17APR08 19MAY08

DCP002 MFRG. & DELIVERY AT WORK - DRAIN COOLER MATERIAL 93 20MAY08 20AUG08

DCP003 MANUFACTURING - DRAIN COOLER 175 21AUG08 11FEB09

DCP004 TESTING - DRAIN COOLER 6 12FEB09 17FEB09

DCP005 DISPATCH & DELIVERY AT SITE - DRAIN COOLER 7 18FEB09 24FEB09 ERECTION/COMMISSIONING

DCEC001 ERECTION- DRAIN COOLERS 26 19MAR09 13APR09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

ENGINEERING- CEP

ORDERING - CEP DD ITEMSMFRG & DELIVERY AT SITE - BFP SUB-VENDOR ITEMS

ENGINEERING- LUBEOILPUMPS & TANKS

INDENT&ORDER OF MATERIAL- LUBEOILPUMPS & TANKS

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:57

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 14 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 15: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

DCEC002 PRE-COMMISSIONING- DRAIN COOLERS 2 14APR09 15APR09

AOP, JOP, EOP, OIL PURIFICATION ENGINEERING

JEE001 ENGINEERING - STG AUX( AOP,EOP,JOP,PURFN) 30 18MAR08 16APR08 PROCUREMENT

JEP001 ORDERING - STG AUX 69 02APR08 09JUN08

JEP002 MANUFACTURING - STG AUX 120 10JUN08 07OCT08

JEP003 INSPECTION - STG AUX 70 08OCT08 16DEC08

JEP004 DESPATCH & DELIVERY AT SITE - STG AUX 56 03DEC08 27JAN09 ERECTION/COMMISSIONING

JEEC001 ERECTION- STG AUX 40 01JUN09 10JUL09

JEEC002 PRE-COMMISSIONING-STG AUX 9 16SEP09 24SEP09

SURFACE CONDENSOR ENGINEERING

CHE001 ENGINEERING - COND. & HOTWELL 90 18MAR08 15JUN08 PROCUREMENT

CHP001 ORDERING OF MATERIAL - COND. & HOTWELL 62 08APR08 08JUN08

CHP002 RECEIPT OF MATERIAL AT WORKS - COND. & HOTWELL 162 09JUN08 17NOV08

CHP003 MANUFACTURING - COND. & HOTWELL 113 18NOV08 10MAR09

CHP004 TESTING - COND. & HOTWELL 7 11MAR09 17MAR09

CHP005 DESPATCH & DELIVERY AT SITE - COND. & HOTWELL 7 18MAR09 24MAR09 CIVIL

TG111 CONDENSER FOUNDATION WORKS 30 25APR09 24MAY09

TG170 READINESS FOR CONDENSER FOUNDATION 0 29MAY09ERECTION/COMMISSIONING

CHEC001 ERECTION - COND. & HOTWELL 23 30MAY09 21JUN09

CHEC002 PRE-COMMISSONING - COND. & HOTWELL 31 22JUN09 22JUL09

SCEC006 HP BYPASS STATION ERECTION 15 09SEP09 23SEP09

SCEC011 COMMISSIONING OF HP BYPASS SYSTEM. 1 27NOV09 27NOV09

GS CONDENSOR ENGINEERING

GSE001 ENGINEERING - GS CONDENSOR 10 18MAR08 27MAR08 PROCUREMENT

GSP001 ORDERING OF MATERIAL - GS CONDENSOR 73 28MAR08 08JUN08

GSP002 MFRG. & RECPT. OF MTRL. AT WORKS - GS CONDENSOR 162 09JUN08 17NOV08

GSP003 MANUFACTURING - GS CONDENSOR 113 18NOV08 10MAR09

GSP004 TESTING - GS CONDENSOR 7 11MAR09 17MAR09

GSP005 DESPATCH & DELIVERY AT SITE - GS CONDENSOR 7 18MAR09 24MAR09ERECTION/COMMISSIONING

GSEC001 ERECTION - GS CONDENSOR 45 25MAR09 08MAY09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

MANUFACTURING - STG AUX

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:57

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 15 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 16: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

GSEC002 COMMISSIONING - GS CONDENSOR 13 09MAY09 21MAY09

LP HEATERS I & II ENGINEERING

LPE001 ENGINEERING - LP HEATERS 10 18MAR08 27MAR08 PROCUREMENT

LPP001 ORDERING OF MATERIAL - LP HEATERS 74 28MAR08 09JUN08

LPP002 MFRG. & RECPT. OF MTRL. AT WORKS - LP HEATERS 106 10JUN08 23SEP08

LPP003 MANUFACTURING - LP HEATERS 168 24SEP08 10MAR09

LPP004 TESTING - LP HEATERS 7 11MAR09 17MAR09

LPP005 DESPATCH & DELIVERY AT SITE - LP HEATERS 7 18MAR09 24MAR09ERECTION/COMMISSIONING

LPEC001 ERECTION - LP HEATERS 40 25MAR09 03MAY09

LPEC002 PRE-COMMISSIONING - LP HEATERS 18 04MAY09 21MAY09

HP HEATERS IV & V ENGINEERING

HPE001 ENGINEERING - HP HEATERS 10 18MAR08 27MAR08 PROCUREMENT

HPP001 ORDERING OF MATERIAL - HP HEATERS 74 28MAR08 09JUN08

HPP002 MFRG. & RECPT. OF MTRL. AT WORKS - HP HEATERS 92 10JUN08 09SEP08

HPP003 MANUFACTURING - HP HEATERS 175 10SEP08 03MAR09

HPP004 TESTING - HP HEATERS 14 04MAR09 17MAR09

HPP005 DESPATCH & DELIVERY AT SITE - HP HEATERS 7 18MAR09 24MAR09 ERECTION/COMMISSIONING

HPEC001 ERECTION - HP HEATERS 21 25MAR09 14APR09

HPEC002 PRE-COMMISSIONING - HEATERS 18 15APR09 02MAY09

DE-AERATOR HEADER ENGINEERING

DHE001 ENGINEERING - DE-AERATOR HEADER 10 18MAR08 27MAR08 PROCUREMENT

DHP001 ORDERING OF MATERIAL - DE-AERATOR HEADER 74 28MAR08 09JUN08

DHP002 MFRG. & RECPT. OF MTRL. AT WORKS - DE-AER. HEAD. 78 10JUN08 26AUG08

DHP003 MANUFACTURING - DE-AERATOR HEADER 182 27AUG08 24FEB09

DHP004 TESTING - DE-AERATOR HEADER 14 25FEB09 10MAR09

DHP005 DESPATCH & DELIVERY AT SITE - DE-AERATOR HEADER 10 11MAR09 20MAR09CIVIL

TG175 DEAERATOR FOUNDATION 25 12MAY09 05JUN09ERECTION/COMMISSIONING

DHEC001 ERECTION - DE-AERATOR HEADER 30 06JUN09 05JUL09

DHEC002 PRE-COMMISSIONING - DE-AERATOR HEADER 2 06JUL09 07JUL09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

MFRG. & RECPT. OF MTRL. AT WORKS - LP HEATERS

MFRG. & RECPT. OF MTRL. AT WORKS - HP HEATERS

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:57

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 16 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 17: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

DE-AERATOR STORAGE TANK ENGINEERING

DSE001 ENGINEERING - DE-AERATOR STOR. TANK 10 18MAR08 27MAR08 PROCUREMENT

DSP001 ORDERING OF MATERIAL - DE-AERATOR STOR. TANK 74 28MAR08 09JUN08

DSP002 MFRG. & RECPT. OF MTRL. AT WORKS - DE-AR. SO. TK 78 10JUN08 26AUG08

DSP003 MANUFACTURING - DE-AERATOR STOR. TANK 182 27AUG08 24FEB09

DSP004 TESTING - DE-AERATOR STOR. TANK 14 25FEB09 10MAR09

DSP005 DESPATCH & DELIVERY AT SITE - DE-AR. SO. TK 11 11MAR09 21MAR09 CIVIL

TG175A DEAERATOR FOUNDATION 25 12MAY09 05JUN09 ERECTION/COMMISSIONING

DSEC001 ERECTION - DE-AERATOR STORAGE TANK 30 06JUN09 05JUL09

DSEC002 PRE-COMMISSIONING - DE-AREATOR STORAGE TANK 2 06JUL09 07JUL09

OIL & AIR COOLER ENGINEERING

OAE001 ENGINEERING - OIL & AIR COOLER 10 18MAR08 27MAR08 PROCUREMENT

OAP001 ORDERING OF MATERIAL - OIL & AIR COOLER 74 28MAR08 09JUN08

OAP002 MFRG. & RECPT. OF MTRL. AT WORKS - OIL & AIR COO 113 20MAY08 09SEP08

OAP003 MANUFACTURING - OIL & AIR COOLER 190 19AUG08 24FEB09

OAP004 TESTING - OIL & AIR COOLER 28 11FEB09 10MAR09

OAP005 DESPATCH & DELIVERY AT SITE - OIL & AIR COOLER 7 11MAR09 17MAR09ERECTION/COMMISSIONING

OAEC001 ERECTION - OIL & AIR COOLER 40 04JUL09 12AUG09

OAEC002 PRE-COMMISSIONING - OIL & AIR COOLER 1 13AUG09 13AUG09

STEAM JET AIR EJECTOR ENGINEERING

SJE001 ENGINEERING - SJAE 17 18MAR08 03APR08 PROCUREMENT

SJP001 ORDERING OF MATERIAL - SJAE 46 04APR08 19MAY08

SJP002 MFRG. & RECPT. OF MTRL. AT WORKS - SJAE 106 20MAY08 02SEP08

SJP003 MANUFACTURING - SJAE 145 03SEP08 25JAN09

SJP004 TESTING - SJAE 9 26JAN09 03FEB09

SJP005 DESPATCH & DELIVERY AT SITE - SJAE 7 04FEB09 10FEB09 ERECTION/COMMISSIONING

SJEC001 ERECTION - EJECTOR SYSTEM 40 04JUL09 12AUG09

SJEC002 PRE-COMMISSIONING - EJECTOR SYSTEM 1 13AUG09 13AUG09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:57

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 17 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 18: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

ELECTRICALENGINEERING

HEE001 ENGINEERING - ELECTRICAL 47 18MAY08 03JUL08PROCUREMENT

HEP001 ORDERING - ELECTRICAL 71 04JUL08 12SEP08

HEP002 MANUFACTURING - ELECTRICAL 330 24JUL08 18JUN09

HEP003 DELIVERY - ELECTRICAL 92 31MAR09 30JUN09 ERECTION/COMMISSIONING

HEEC001 CABLE TRAY LAYING & CABLING 166 17APR09 29SEP09

HEEC002 ERECTION & PRE-COMMISSIONING - REQD. FOR BLU 30 02MAY09 31MAY09

HEEC003 ERECTION & PRE-COMMISSIONING - REQD. FOR SYN. 119 01JUN09 27SEP09

C&IENGINEERING

HIE001 ENGINEERING - C&I 45 04JUN08 18JUL08PROCUREMENT

HIP001 ORDERING - C&I 45 19JUL08 01SEP08

HIP002 MANUFACTURING - C&I 360 13AUG08 07AUG09

HIP003 DELIVERY - C&I 180 11MAR09 06SEP09 ERECTION/COMMISSIONING

HIEC001 CABLING 166 22APR09 04OCT09

HIEC002 ERECTION & PRE-COMMISSIONING - REQD. FOR BLU 45 09JUN09 23JUL09

HIEC003 ERECTION & PRE-COMMISSIONING - REQD. FOR SYN. 60 24JUL09 21SEP09

PIPING & OTHER AUXILIARY SYSTEMSP&IDs & LAYOUTs

ENGINEERING

PDE003 ENGINEERING - TG HALL EQPT. LAYOUTS & OTHER ENGG 90 01JUN08 29AUG08

PDE002 ENGINEERING - TG HOUSE PIPING/TG INTEGRAL PIPING 90 08JUN08 05SEP08

PDE001 ENGINEERING - BOILER INTERG. PIPG 90 16JUN08 13SEP08

BOILER INTEGRAL PIPING & UTILITY PIPING (SG) ENGINEERING

PBE001 ENGINEERING - BLR. INTERG. & UTIL. PIPG. 90 01JAN09 31MAR09 PROCUREMENT

PBP001 MTRL. RCPT. AT WORKS-BLR. INTERG. & UTIL. PIPG. 57 25MAY09 20JUL09

PBP002 MANUFACTURING - BLR. INTERG. & UTIL. PIPG. 151 26MAY09 23OCT09

PBP003 DESPATCH & DELIVERY - BLR. INTERG. & UTIL. PIPG. 174 26MAY09 15NOV09ERECTION/COMMISSIONING

PBEC001 ERCN.,HT&INSUL OF BI PIPG & UTIL-ACW,SA,IA - BLU 115 10JUN09 02OCT09

PBEC002 ERCN., HT & INSULATION OF BI PIPING FOR SB/SVF 80 25JUL09 12OCT09

PBEC003 ERCN., HT & INSUL. OF OTHER UTILITY PIPG 60 02OCT09 30NOV09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

ENGINEERING - ELECTRICAL

ORDERING - ELECTRICALMANUFACTURING - ELECTRICAL

ENGINEERING - C&I

ORDERING - C&IMANUFACTURING - C&I

ENGINEERING - BOILER INTERG. PIPG

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:57

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 18 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 19: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

TG HOUSE PIPING & TG INTEGRAL PIPING (PCP) ENGINEERING

PHE001 ENGINEERING- TG HOUSE & TG INTEGRAL PIPG 90 01JAN09 31MAR09 PROCUREMENT

PHP001 INDG/ORDG OF MTRL- TG HOUSE & TG INTEGRAL PIPG 54 01APR09 24MAY09

PHP002 MTRL RCPT AT WORKS - TG HOUSE & TG INTEGRAL PIPG 57 25MAY09 20JUL09

PHP003 MANUFACTURING - TG HOUSE & TG INTEGRAL PIPG 154 25MAY09 25OCT09

PHP004 DESP &DLRY AT SITE - TG HOUSE & TG INTEGRAL PIPG 175 25MAY09 15NOV09ERECTION/COMMISSIONING

PHEC004 ERECTION OF FEED WATER PIPING 32 23JUN09 24JUL09

PHEC003 ERECTION OF CONDENSATE PIPING 38 08JUL09 14AUG09

PHEC008 HYDRO TEST OF FEED WATER PIPING 4 30JUL09 02AUG09

PHEC012 INSULATION OF FEED WATER PIPING 14 03AUG09 16AUG09

PHEC001 ERECTION OF MAIN STEAM PIPING 35 05AUG09 08SEP09

PHEC013 ERECTION OF AUX. STEAM PIPING 25 15AUG09 08SEP09

PHEC007 HYDRO TEST OF CONDENSATE PIPING 7 20AUG09 26AUG09

PHEC011 INSULATION OF CONDENSATE PIPING 7 25AUG09 31AUG09

PHEC024 PRE-BOILER FLUSHING 7 27AUG09 02SEP09

PHEC014 HYDRO TEST OF AUX. STEAM PIPING 6 09SEP09 14SEP09

PHEC022 ERCN,HT & INSUL. OF BALANCE PIPG - REQD. FOR BLU 34 12SEP09 15OCT09

PHEC005 HYDRO TEST OF MAIN STEAM PIPING 5 14SEP09 18SEP09

PHEC015 INSULATION OF AUX. STEAM PIPING 5 15SEP09 19SEP09

PHEC009 INSULATION OF MAIN STEAM PIPING 16 19SEP09 04OCT09

PHEC002 ERECTION OF EXTRACTION STEAM PIPING 38 06NOV09 13DEC09

PHEC016 ERECTION OF CONDENSOR AIR EVACUATION PIPING 35 16NOV09 20DEC09

PHEC019 ERECTION OF LUBE OIL PIPING 29 16NOV09 14DEC09

PHEC023 ERCN,HT & INSUL. OF BALANCE PIPG - REQD. FOR SYN 40 16NOV09 25DEC09

PHEC010 INSULATION OF EXTRACTION STEAM PIPING 12 14DEC09 25DEC09

PHEC018 INSULATION OF CONDENSOR AIR EVACUATION PIPING 5 21DEC09 25DEC09

HANGERS & SUPPORTS ENGINEERING

HSE001 ENGINEERING - HANGERS & SUPPORTS 90 01JAN09 31MAR09PROCUREMENT

HSP001 RECEIPT OF MTRL AT WORKS - HANGERS & SUPPORTS 57 25MAY09 20JUL09

HSP002 MANUFACTURING - HANGERS & SUPPORTS 154 25MAY09 25OCT09

HSP003 DESP & DLRY AT SITE - HANGERS & SUPPORTS 175 25MAY09 15NOV09ERECTION/COMMISSIONING

HSEC002 ERECTION OF H & S - REQD. FOR BLU 62 15AUG09 15OCT09

HSEC001 ERECTION OF ACCESSIBLE PLATFORMS TO ERECT H & S 110 28AUG09 15DEC09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:57

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 19 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 20: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

HSEC003 ERECTION OF H & S - REQD. FOR SYN. 25 01DEC09 25DEC09

HP DOSING SYSTEM ENGINEERING

HDE001 ENGINEERING- HP DOSING STN. 90 01JAN09 31MAR09PROCUREMENT

HDP001 INDENTING OF MATERIAL- HP DOSING STN. 24 01APR09 24APR09

HDP002 ORDERING OF MATERIAL- HP DOSING STN. 30 25APR09 24MAY09

HDP003 RECEIPT OF MATERIAL AT SITE- HP DOSING STN. 57 25MAY09 20JUL09

HDP004 MANUFACTURING - HP DOSING 90 26MAY09 24AUG09

HDP005 DESP & DLRY - HP DOSING 110 27MAY09 14SEP09ERECTION/COMMISSIONING

HDEC001 ERECTION- HP DOSING STN. 20 15SEP09 04OCT09

HDEC002 COMMISSIONING- HP DOSING STN. 8 05OCT09 12OCT09

TANKS & VESSELS REL. ENGINEERING

TVE001 ENGINEERING - TANKS & VESSELS 90 01JAN09 31MAR09 PROCUREMENT

TVP001 ORDERING - TANKS & VESSELS REL. 54 01APR09 24MAY09

TVP002 MANUFACTURING - TANKS & VESSELS REL. 93 25MAY09 25AUG09

TVP003 DESP & DLRY AT SITE - TANKS & VESSELS REL. 110 28MAY09 14SEP09ERECTION/COMMISSIONING

TVEC001 ERECTION & COMMISSIONING - REQD. FOR BLU 30 15SEP09 14OCT09

TVEC002 ERECTION & COMMISSIONING - REQD. FOR SYN. 45 15SEP09 29OCT09

C&I ENGINEERING

CIE001 ENGINEERING - CONTROL VALVES & FLOW ELEMENTS 25 06JUN08 30JUN08

PIE001 ENGINEERING - OTHER C&I 90 01JAN09 31MAR09PROCUREMENT

CIP001 INDENTING & ORDERING - CONTROL VALVES 60 01JUL08 29AUG08

CIP002 INDENTING & ORDERING - FLOW ELEMENTS 45 01JUL08 14AUG08

PIP001 ORDERING - OTHER C&I 54 01APR09 24MAY09

PIP002 MANUFACTURING - OTHER C&I 154 25MAY09 25OCT09

PIP003 DESP & DLRY AT SITE - OTHER C&I 170 29MAY09 14NOV09

CIP003 RECEIPT AT SITE - CONTROL VALVES 15 01JUN09 15JUN09

CIP004 RECEIPT AT SITE - FLOW ELEMENTS 15 16JUN09 30JUN09ERECTION/COMMISSIONING

CIEC001 ERCN. & COMMNG. - CONTROL VALVES REQD. FOR BLU 26 03OCT09 28OCT09

CIEC003 ERCN. & COMMNG. - FLOW ELEMENTS REQD. FOR BLU 22 07OCT09 28OCT09

PIEC001 ERECTION & COMMISSIONING - REQD. FOR SYN. 42 15NOV09 26DEC09

CIEC002 ERCN. & COMMNG. - CONTROL VALVES REQD. FOR SYN. 36 20NOV09 25DEC09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

INDENTING & ORDERING - CONTROL VALVESINDENTING & ORDERING - FLOW ELEMENTS

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:57

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 20 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 21: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

CIEC004 ERCN. & COMMNG. - FLOW ELEMENTS REQD. FOR SYN. 36 20NOV09 25DEC09

APRDS ENGINEERING

APE001 ENGINEERING-APRDS 25 11JUN08 05JUL08 PROCUREMENT

APP001 INDENTING & ORDERING OF MATERIAL-APRDS 55 06JUL08 29AUG08

APP002 MANUFACTURING-APRDS 80 30AUG08 17NOV08

APP003 RECEIPT OF MATERIAL AT SITE-APRDS 20 28MAR09 16APR09 ERECTION/COMMISSIONING

APEC001 ERECTION-APRDS 84 15AUG09 06NOV09

APEC002 COMM OF APRDC 10 07NOV09 16NOV09

LP DOSING SYSTEM ENGINEERING

LDE001 ENGINEERING- HP/LP DOSING STN. 10 13JUN08 22JUN08 PROCUREMENT

LDP001 INDENTING OF MATERIAL- LP DOSING STN. 10 28JUN08 07JUL08

LDP002 ORDERING OF MATERIAL- LP DOSING STN. 30 08JUL08 06AUG08

LDP003 RECEIPT OF MATERIAL AT SITE- LP DOSING STN. 45 15MAR09 28APR09ERECTION/COMMISSIONING

LDEC001 ERECTION - LP DOSING STN. 20 02AUG09 21AUG09

LDEC002 COMMISSIONING - LP DOSING STN. 8 05OCT09 12OCT09

MP ENGINEERING

MPE001 ENGINEERING - MP 20 06JUN08 25JUN08 PROCUREMENT

MPP001 INDENTING & ORDERING - ME BELLOWS 60 26JUN08 24AUG08

MPP002 INDENTING & ORDERING - POWER CYCLE VALVES 60 26JUN08 24AUG08

MPP003 INDENTING & ORDERING - STEAM TRAPS 45 26JUN08 09AUG08

MPP007 RECEIPT AT SITE - STEAM TRAPS 15 22JAN09 05FEB09

MPP004 INDENTING & ORDERING - THERMAL INSULATION 30 21FEB09 22MAR09

MPP006 RECEIPT AT SITE - POWER CYCLE VALVES 15 21FEB09 07MAR09

MPP005 RECEIPT AT SITE - ME BELLOWS 15 26FEB09 12MAR09

MPP008 RECEIPT AT SITE - THERMAL INSULATION 15 21JUN09 05JUL09 ERECTION/COMMISSIONING

MPEC004 ERECTION OF THERMAL INSULATION - REQD. FOR BLU 49 08SEP09 26OCT09

MPEC001 ERECTION OF ME BELLOWS- REQD. FOR BLU 25 17SEP09 11OCT09

MPEC002 ERECTION OF POWER CYCLE VALVES - REQD. FOR BLU 25 03OCT09 27OCT09

MPEC003 ERECTION OF STEAM TRAPS - REQD. FOR BLU 25 03OCT09 27OCT09

MPEC008 ERECTION OF THERMAL INSULATION - REQD. FOR SYN. 71 16OCT09 25DEC09

MPEC005 ERECTION OF ME BELLOWS- REQD. FOR SYN. 36 10NOV09 15DEC09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

ENGINEERING-APRDS

INDENTING & ORDERING OF MATERIAL-APRDS

ENGINEERING- HP/LP DOSING STN.

INDENTING OF MATERIAL- LP DOSING STN.ORDERING OF MATERIAL- LP DOSING STN.

ENGINEERING - MP

INDENTING & ORDERING - ME BELLOWSINDENTING & ORDERING - POWER CYCLE VALVES

INDENTING & ORDERING - STEAM TRAPS

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:57

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 21 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 22: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

MPEC006 ERECTION OF POWER CYCLE VALVES - REQD. FOR SYN. 45 11NOV09 25DEC09

MPEC007 ERECTION OF STEAM TRAPS - REQD. FOR SYN. 36 20NOV09 25DEC09

LUBE OIL TRANSFER ENGINEERING

LTE001 ENGINEERING - CLEAN OIL & DIRTY OIL PUMPS 30 18MAY08 16JUN08 PROCUREMENT

LTP001 ORDERING - CLEAN OIL & DIRTY OIL PUMPS 48 02JUN08 19JUL08

LTP002 MANUFACTURING - CLEAN OIL & DIRTY OIL PUMPS 256 20JUL08 01APR09

LTP003 DELIVERY AT SITE - CLEAN OIL & DIRTY OIL PUMPS 11 02APR09 12APR09 ERECTION/COMMISSIONING

LTEC001 ERECTION - CLEAN OIL & DIRTY OIL PUMPS 25 13APR09 07MAY09

LTEC002 PRE-COMMISSIONNG - CLEAN OIL & DIRTY OIL PUMPS 9 16SEP09 24SEP09

HP & LP FLASH TANKSENGINEERING

HLE001 ENGINEERING - HP & LP FLASH TANKS 20 26JUN08 15JUL08PROCUREMENT

HLP001 ORDERING - HP & LP FLASH TANKS 30 16JUL08 14AUG08

HLP002 MANUFACTURING - HP & LP FLASH TANKS 250 15AUG08 21APR09

HLP003 DELIVERY - HP & LP FLASH TANKS 21 22APR09 12MAY09ERECTION/COMMISSIONING

HLTEC001 ERECTION & COMMISSIONING - HP FLASH TANK 102 03SEP09 13DEC09

HLTEC002 ERECTION & COMMISSIONING - LP FLASH TANK 102 03SEP09 13DEC09

INSTRUMENTATION CONTROLS TG PACKAGE

ENGINEERING

ETE001 ENGINEERING - ATRS,.. 79 19DEC08 07MAR09 PROCUREMENT

ETP001 PROCUREMENT OF MATERIALS - ATRS,.. 116 08MAR09 01JUL09

ETP002 ASSEMBLY & TESTING COMPLETION - ATRS,.. 32 02JUL09 02AUG09

ETP003 FAT, DESP & DELIVERY TO SITE - ATRS,.. 18 04AUG09 21AUG09 ERECTION/COMMISSIONING

ETEC001 ERECTION - ATRS,.. 46 17SEP09 01NOV09

ETEC002 COMMISSIONING - ATRS,.. 25 02NOV09 26NOV09

SG PACKAGE ENGINEERING

ESE001 ENGINEERING - FLAME SCANNER, SADC, BMS 79 19DEC08 07MAR09 PROCUREMENT

ESP001 PROCUREM OF MATERIALS - FLAME SCANNER, SADC, BMS 100 08MAR09 15JUN09

ESP002 ASSEMBLY & TESTING - FLAME SCANNER, SADC, BMS 25 16JUN09 10JUL09

ESP003 FAT, DESP & DELIVERY - FLAME SCANNER, SADC, BMS 15 12JUL09 26JUL09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

ORDERING - CLEAN OIL & DIRTY OIL PUMPSMANUFACTURING - CLEAN OIL & DIRTY OIL PUMPS

ENGINEERING - HP & LP FLASH TANKS

ORDERING - HP & LP FLASH TANKSMANUFACTURING - HP & LP FLASH TANKS

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:57

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 22 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 23: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

ERECTION/COMMISSIONING

ESEC001 ERECTION - FLAME SCANNER, SADC, BMS 25 17SEP09 11OCT09

ESEC002 COMMISSIONING - FLAME SCANNER, SADC, BMS 5 19OCT09 23OCT09

HMI SYSTEM ENGINEERING

EHE001 ENGINEERING - TFT MONIT., COMPU., N/W PANEL 79 19DEC08 07MAR09 PROCUREMENT

EHP001 MTRLS. PROCUREME - TFT MONIT., COMPU., N/W PANEL 116 08MAR09 01JUL09

EHP002 ASSEMBLY & TEST. - TFT MONIT., COMPU., N/W PANEL 32 02JUL09 02AUG09

EHP003 FAT, DESP & DELI - TFT MONIT., COMPU., N/W PANEL 18 04AUG09 21AUG09 ERECTION/COMMISSIONING

EHEC001 ERECTION - TFT MONIT., COMPU., N/W PANEL 46 17SEP09 01NOV09

EHEC002 COMMISSIONING - TFT MONIT., COMPU., N/W PANEL 25 02NOV09 26NOV09

AVR SYSTEM ENGINEERING

EAE001 ENGINEERING - AVR 79 19DEC08 07MAR09 PROCUREMENT

EAP001 PROCUREMENT OF MATERIALS - AVR 116 08MAR09 01JUL09

EAP002 ASSEMBLY & TESTING - AVR 32 02JUL09 02AUG09

EAP003 FAT, DESP & DELIVERY - AVR 18 04AUG09 21AUG09 ERECTION/COMMISSIONING

EAEC001 ERECTION - AVR 46 17SEP09 01NOV09

EAEC002 COMMISSIONING - AVR 25 02NOV09 26NOV09

OVERALL COMMISSIONING BOILEROLBC001 BOILER LIGHT UP 3 29OCT09 31OCT09

OLBC002 STEAM BLOWING 10 17NOV09 26NOV09

OLBC003 SAFETY VALVE FLOATING COMPLETION 3 27NOV09 29NOV09

OLBC004 BOILER COAL FIRING 6 01JAN10 06JAN10

TGOLTC001 FINAL ALIGNMENT OF TG 9 01OCT09 09OCT09

OLTC002 TG - OIL FLUSHING 15 10OCT09 24OCT09

OLTC003 BARRING GEAR OPERATION 7 25OCT09 31OCT09

OLTC004 VACCUM PULLING- TG 2 14DEC09 15DEC09

OLTC005 STEAM DUMPING 1 16DEC09 16DEC09

OVERALLOLOC001 ROLLING, OCC SCC OF GEN & SYNCHRONISATION 5 27DEC09 31DEC09

OLOC002 COMMG./ STABILITY RUN/TRIAL OPERATION-TG 3 29DEC09 31DEC09

OLOC003 COMMG./ 72 hrs TRIAL OPERATION-TG 3 06MAR10 08MAR10

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:57

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 23 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 24: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

OLOC004 PROV. HANDING OVER OF PLANT 0 08MAR10

OLOC005 PLANT OPTIMISATION 8 09MAR10 16MAR10

OLOC006 LOAD REJECTION & ISLANDING TESTS 5 17MAR10 21MAR10

OLOC007 RELIABILITY RUN 3 22MAR10 24MAR10

OLOC008 PG TEST 2 25MAR10 26MAR10

OLOC009 FINAL HANDING OVER OF PLANT 0 26MAR10

UNIT II - BTGSubtotal 761 18MAR08 17APR10

STEAM GENERATION BOILER FOUNDATION

ENGINEERING

U2EN500 BOILER FOUNDATION DRG 20 22MAY08 10JUN08

U2BBE011 BOILER FOUNDATION ENGG 30 16JUN08 15JUL08 PROCUREMENT

U2BBP011 INDENTIG/ORDERING/RECEIPT OF MATERIAL-Boiler 15 16JUL08 30JUL08

U2BBP012 MFG & DISPATCH OF FOUNDATION MATLS 28 29OCT08 25NOV08 CIVIL

U2BA200 FOUND FOR BOILER MAIN COLUMN 60 26NOV08 24JAN09

U2BA210 FOUND FOR BOILER AUXILIARY COLUMN 50 31DEC08 18FEB09

U2BA250 READINESS OF BOILER FOUNDATION 5 19FEB09 23FEB09

BOILER STRUCTURE ENGINEERING

U2BSE011 ENGINEERING- BOILER STR. 30 21JUN08 20JUL08 PROCUREMENT

U2BSP011 RECEIPT OF BOILER STR. MATERIAL AT WORKS 10 21JUL08 30JUL08

U2BSP012 MANUFACTURING - BOILER STRUCTURE 128 19OCT08 23FEB09

U2BSP013 DESPATCH MAIN BOILER STRUCTURE 120 26NOV08 25MAR09

U2BSP014 DESPATCH AUXILIARY STRUCTURE 180 28NOV08 26MAY09 ERECTION/COMMISSIONING

U2BSEC011 ERCN. OF MAIN BOILER STR. 90 15APR09 13JUL09

U2BSEC012 ERECTION OF AUX STR. 50 30MAY09 18JUL09

U2BSEC013 STR. ERECTION BEFORE DRUM LIFTING 5 24JUN09 28JUN09

BOILER DRUM ENGINEERING

U2BDE011 ENGINEERING- BOILER DRUM 30 02MAY08 31MAY08 PROCUREMENT

U2BDP011 INTEND. & RECEIPT OF BOILER DRUM MTRL. AT WORKS 156 10MAY08 12OCT08

U2BDP012 MANUFACTURING & DISPATCH- BOILER DRUM 170 11JAN09 29JUN09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

BOILER FOUNDATION DRGBOILER FOUNDATION ENGG

INDENTIG/ORDERING/RECEIPT OF MATERIAL-Boiler

ENGINEERING- BOILER STR.

RECEIPT OF BOILER STR. MATERIAL AT WORKS

ENGINEERING- BOILER DRUM

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:57

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 24 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 25: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

ERECTION/COMMISSIONING

U2BDEC011 BOILER DRUM LIFTING 0 30JUL09

BOILER PRESSURE PARTS ENGINEERING

U2BPE011 ENGINEERING- BOILER PRESS PARTS 30 16JUL08 14AUG08 PROCUREMENT

U2BPP011 RECEIPT OF BOILER PRESS. PARTS MATERIAL AT WORKS 85 06AUG08 29OCT08

U2BPP012 MANUFACTURING- BOILER PRESS. PARTS 280 04DEC08 09SEP09

U2BPP013 DESPATCH- BOILER PRESS. PARTS 160 11APR09 17SEP09 ERECTION/COMMISSIONING

U2BPEC011 BANK TUBES, WW HDR., WW PANEL & D' COMER ERECN. 91 31JUL09 29OCT09

U2BPEC012 SH HDR., SH TUBES ASSY. ERECN. 25 05AUG09 29AUG09

U2BPEC013 MAIN STEAM PIPG. ERECN 20 30AUG09 18SEP09

U2BPEC014 ECO.LINK,HDR & BANK ASSY., BLR. FEED PIPG. ERCN. 25 18SEP09 12OCT09

U2BPEC015 OTHER ACT. COMPLN. & READY FOR HT/IBR CLEARANCE 25 30OCT09 23NOV09

U2BPEC016 HYDRAULIC TEST OF BOILER 7 24NOV09 30NOV09

U2BPEC018 EDTA CLEANING / ALKALI BOIL-OUT 5 01FEB10 05FEB10

U2BPEC017 ACID CLEANING 4 06FEB10 09FEB10

BOILER INSULATION ENGINEERING

U2BIE011 ENGINEERING FOR INSULATION- BOILER INSULATION 15 20AUG08 03SEP08 PROCUREMENT

U2BIP011 RECEIPT OF MATERIAL AT WORKS- BOILER INSULATION 60 27APR09 25JUN09

U2BIP012 MANUFACTURING- BOILER INSULATION 85 26JUL09 18OCT09

U2BIP013 DESPATCH- BOILER INSULATION 30 19OCT09 17NOV09 ERECTION/COMMISSIONING

U2BIEC011 INSULATION & LINING- BOILER 45 01DEC09 14JAN10

SHEETING ENGINEERING

U2BGE011 ENGINEERING-SHEETING 20 30AUG08 18SEP08 PROCUREMENT

U2BGP011 INDENTING & ORDERING-SHEETING 45 19SEP08 02NOV08

U2BGP012 DELIVERY AT SITE-SHEETING 210 17APR09 12NOV09 ERECTION/COMMISSIONING

U2BGEC011 ERECTION-SHEETING 60 19JAN10 19MAR10

VALVE ENGINEERING

U2BVE011 ENGINEERING - VALVES 45 31JUL08 13SEP08 PROCUREMENT

U2BVP011 ORDERING - VALVES 90 14SEP08 12DEC08

U2BVP012 MANUFACTURING - VALVES 295 13MAR09 01JAN10

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

ENGINEERING- BOILER PRESS PARTS

RECEIPT OF BOILER PRESS. PARTS MATERIAL AT WORKS

ENGINEERING - VALVES

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:58

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 25 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 26: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

U2BVP013 DELIVERY AT SITE - VALVES FOR HT 150 27APR09 23SEP09

U2BVP014 DELIVERY AT SITE - VALVES FOR LU 120 26JUN09 23OCT09

U2BVP015 DELIVERY AT SITE - VALVES FOR SYN 90 14OCT09 11JAN10ERECTION/COMMISSIONING

U2BVEC011 ERECTION - VALVES FOR HT 30 13OCT09 11NOV09

U2BVEC012 ERECTION - VALVES FOR LU 75 01NOV09 14JAN10

U2BVEC013 ERECTION - VALVES FOR SYN 35 04FEB10 10MAR10

ELECTRICAL ENGINEERING

U2TEE011 ENGINEERING - ELECTRICAL 50 30AUG08 18OCT08 PROCUREMENT

U2TEP011 ORDERING - ELECTRICAL 75 19OCT08 01JAN09

U2TEP012 MANUFACTURING - ELECTRICAL 225 16FEB09 28SEP09

U2TEP013 DELIVERY - ELECTRICAL 75 26JUL09 08OCT09 ERECTION/COMMISSIONING

U2TEEC012 MCC ERECTION & COMMISSIONING 20 21NOV09 10DEC09

U2TEEC011 CABLE TRAY LAYING & CABLING 65 01DEC09 03FEB10

U2TEEC013 ERECTION & PRE-COMMISSIONING - REQD. FOR BLU 20 01DEC09 20DEC09

U2TEEC014 ERECTION & PRE-COMMISSIONING - REQD. FOR SYN. 50 21DEC09 08FEB10

C&I ENGINEERING

U2TIE011 ENGINEERING - C&I 50 09SEP08 28OCT08 PROCUREMENT

U2TIP011 ORDERING - C&I 85 29OCT08 21JAN09

U2TIP012 MANUFACTURING - C&I 250 26FEB09 02NOV09

U2TIP013 DELIVERY - C&I 90 04SEP09 02DEC09 ERECTION/COMMISSIONING

U2TIEC011 CABLING 75 06DEC09 18FEB10

U2TIEC012 ERECTION & PRE-COMMISSIONING - REQD. FOR BLU 22 24DEC09 14JAN10

U2TIEC013 ERECTION & PRE-COMMISSIONING - REQD. FOR SYN. 55 02JAN10 25FEB10

FUEL OIL SYSTEM ENGINEERING

U2FOE011 ENGINEERING - FUEL OIL SYSTEM 30 30AUG08 28SEP08PROCUREMENT

U2FOP011 ORDERING - FUEL OIL SYSTEM 45 29SEP08 12NOV08

U2FOP012 MANUFACTURING - FUEL OIL SYSTEM 190 11FEB09 19AUG09

U2FOP013 DELIVERY AT SITE - FUEL OIL SYSTEM 50 10AUG09 28SEP09 ERECTION/COMMISSIONING

U2FOEC012 ERECTION-FUEL OIL PIPING 50 26NOV09 14JAN10

U2FOEC0031 HT - FUEL OIL PIPING 10 15JAN10 24JAN10

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:58

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 26 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 27: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

BOILER FURNACE & OTHER LU ACTIVITIES (MECH.) ENGINEERING

U2LUME011 ENGINEERING - BLR.FURNACE & OTHER LU ACT. (MECH) 40 16AUG08 24SEP08 PROCUREMENT

U2LUMP011 ORDERING - BLR.FURNACE & OTHER LU ACT.(MECH) 45 25SEP08 08NOV08

U2LUMP012 MANUFACTURING-BLR.FURNACE & OTHER LU ACT.(MECH) 350 24DEC08 08DEC09

U2LUMP013 DELIVERY - BLR.FURNACE & OTHER LU ACT.(MECH) 240 20APR09 15DEC09 ERECTION/COMMISSIONING

U2LUMEC014 OTHER ACT. COMPLN. & READY FOR BLU 145 23AUG09 14JAN10

U2LUMEC011 BURNER ASSEMBLY 45 01DEC09 14JAN10

U2LUMEC012 FURNACE DOORS FIXING 45 01DEC09 14JAN10

U2LUMEC013 REFRACTORY & CASING/ENCLOSURE WORKS 40 01DEC09 09JAN10

U2LUMEC015 ERECTION - BLOWER SYSTEMS 55 01DEC09 24JAN10

BALANCE ACTIVITIES FOR CF & SYN. (MECH.) ENGINEERING

U2CSME011 ENGINEERING - BAL. ACT. FOR CF & SYN. (MECH.) 30 30AUG08 28SEP08 PROCUREMENT

U2CSMP011 ORDERING - BAL. ACT. FOR CF & SYN. (MECH.) 45 29SEP08 12NOV08

U2CSMP012 MANUFACTURING - BAL. ACT. FOR CF & SYN. (MECH.) 350 27JAN09 11JAN10

U2CSMP013 DELIVERY - BAL. ACT. FOR CF & SYN. (MECH.) 130 19SEP09 26JAN10 ERECTION/COMMISSIONING

U2CSMEC012 ERECTION - COAL SYSTEM 65 09JAN10 14MAR10

U2CSMEC013 OTHER ACT. COMPLN. & READY FOR SYN. 55 15JAN10 10MAR10

AIR & FLUE GAS HANDLING ESP

ENGINEERING

U2EN570 ESP FOUNDATION DGR 20 11JUN08 30JUN08

U2BEE011 ENGINEERING - ESP 60 18JUL08 15SEP08 PROCUREMENT

U2BEP011 ORDERING OF MATERIAL - ESP 150 16SEP08 12FEB09

U2BEP012 MANUFACTURING- ESP 426 15NOV08 14JAN10

U2BEP013 DELIVERY AT SITE - ESP 315 21MAR09 29JAN10 CIVIL

U2BA220 FOUND FOR ESP 75 09JAN09 24MAR09

U2BA260 READINESS OF ESP FOUNDATION 12 14APR09 25APR09 ERECTION/COMMISSIONING

U2BEEC031 ERECTION- ESP COLUMNS & PANELS 75 01MAY09 14JUL09

U2BEEC0041 ERECTION-ESP ROOF, FUNNELS, INTERNALS & HOPPERS 195 30JUN09 13JAN10

U2BEEC0022 ESP INSULATION 90 14OCT09 13JAN10

U2BEEC032 ESP BOX-UP & READINESS FOR BLU 0 13JAN10

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

ENGINEERING - BLR.FURNACE & OTHER LU ACT. (MECH)

ESP FOUNDATION DGRENGINEERING - ESP

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:58

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 27 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 28: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

U2BEEC0051 ERECTION-RECTIFIER SYSTEM & OTHER ACT. FOR CF/SY 60 14JAN10 14MAR10

U2BEEC013 ESP READINESS FOR CF 0 14MAR10

U2BEEC014 ESP READINESS FOR SYN. 0 14MAR10

DAMPER, GATE & ACTUATOR ENGINEERING

U2BAE011 DAMPERS, GATES, ACTUATORS - ENGG. 30 22JUN08 21JUL08 PROCUREMENT

U2BAP011 ORDG. OF MTRL - DAMPERS, GATES, ACTUATORS 90 22JUL08 19OCT08

U2BAP012 MANUFACTURING - DAMPERS, GATES, ACTUATORS 330 20OCT08 14SEP09

U2BAP013 SITE DELIVERY - DAMPERS, GATES, ACTUATORS 36 24AUG09 28SEP09 ERECTION/COMMISSIONING

U2BAEC011 EREC. COMPLN. - DAMPERS, GATES, ACTUATORS 75 14OCT09 27DEC09

FAN ENGINEERING

U2EN580 FAN FOUNDATION ENGG 30 01JUL08 30JUL08

U2BRE011 FANS FD/ID/PA - ENGINEERING 30 16JUL08 14AUG08

U2FAME011 ENGINEERING - FAN MOTOR 35 21SEP08 25OCT08 PROCUREMENT

U2BRP011 ORDERING OF MATERIAL - FANS 60 15AUG08 13OCT08

U2BRP013 MANUFACTURING - FANS 400 13NOV08 17DEC09

U2FAMP011 MANUFACTURING - FAN MOTOR 150 24JAN09 22JUN09

U2BRP012 RECEIPT OF MATERIAL AT WORKS - FAN 90 13MAR09 10JUN09

U2BRP015 DELIVERY AT SITE - FD FAN 150 16JUN09 12NOV09

U2FAMP012 DELIVERY TO SITE - FAN MOTOR 15 23JUN09 07JUL09

U2BRP014 DELIVERY AT SITE - ID FAN 75 15AUG09 28OCT09

U2BRP016 DELIVERY AT SITE - PA FAN 130 20AUG09 27DEC09 CIVIL

U2BA230 FOUND FOR FD,PA,ID FANS - UPTO GL 60 19FEB09 19APR09

U2BA143 FOUND FOR FD,ID FANS - ABOVE GL 45 09SEP09 23OCT09

U2BA155 FOUND FOR PA FANS - ABOVE GL 30 04OCT09 02NOV09

U2BA175 READINESS OF FD & ID FAN FOUNDATION 8 24OCT09 31OCT09

U2BA270 READINESS OF PA FAN FOUNDATION 5 03NOV09 07NOV09 ERECTION/COMMISSIONING

U2BREC011 ERECTION OF ID FAN 60 27SEP09 25NOV09

U2FAMEC011 ERECTION - FAN MOTOR 20 01NOV09 20NOV09

U2BREC012 ERECTION OF FD FAN 60 06NOV09 04JAN10

U2BREC013 ERECTION OF PA FAN 60 18NOV09 16JAN10

U2FAMEC012 COMMISSIONING - FAN MOTOR 1 21NOV09 21NOV09

U2BREC015 ID FAN - PRECOMMISSIONING 2 26NOV09 27NOV09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

DAMPERS, GATES, ACTUATORS - ENGG.

ORDG. OF MTRL - DAMPERS, GATES, ACTUATORS

FAN FOUNDATION ENGGFANS FD/ID/PA - ENGINEERING

ORDERING OF MATERIAL - FANS

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:58

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 28 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 29: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

U2BREC016 FD FAN - PRECOMMISSIONING 2 15JAN10 16JAN10

U2BREC017 PA FAN - PRECOMMISSIONING 2 17JAN10 18JAN10

AIR-HEATER ENGINEERING

U2BHE011 ENGG. - AIR HEATER 60 16JUL08 13SEP08 PROCUREMENT

U2BHP011 ORDERING OF MATERIAL - AIR HEATER 50 26JUL08 13SEP08

U2BHP013 MANUFACTURING - AIR HEATER 335 13NOV08 13OCT09

U2BHP012 RECEIPT OF MATERIAL AT WORKS - AIR HEATER 70 02JAN09 12MAR09

U2BHP014 DELIVERY AT SITE - AIR HEATER 130 21JUN09 28OCT09 ERECTION/COMMISSIONING

U2BHEC011 ERECTION- AIR HEATER 82 18AUG09 07NOV09

U2BHEC012 PRE-COMMISSIONING-AIRHEATER 35 23NOV09 27DEC09

U2BHEC013 READINESS FOR BLU- AIR HEATER 2 28DEC09 29DEC09

DUCTING ENGINEERING

U2BTE011 ENGINEERING - DUCTING 30 25AUG08 23SEP08 PROCUREMENT

U2BTP011 MANUFACTURING-DUCTING 360 23DEC08 17DEC09

U2BTP012 DESPATCH-DUCTING 162 21JUL09 29DEC09 CIVIL

U2BA240 FOUND FOR OTHER AUX & DUCTS 45 29SEP09 12NOV09 ERECTION/COMMISSIONING

U2BTEC011 ERECTION - DUCTING 70 10NOV09 18JAN10

ELECTRICAL ENGINEERING

U2REE011 ENGINEERING - ELECTRICAL 25 05JUN08 29JUN08 PROCUREMENT

U2REP011 ORDERING - ELECTRICAL 75 30JUN08 12SEP08

U2REP012 MANUFACTURING - ELECTRICAL 415 28OCT08 16DEC09

U2REP013 DELIVERY - ELECTRICAL 90 28SEP09 26DEC09 ERECTION/COMMISSIONING

U2REEC011 CABLE TRAY LAYING & CABLING 70 13OCT09 21DEC09

U2REEC012 MCC ERECTION & COMMISSIONING 20 28OCT09 16NOV09

U2REEC013 ERECTION & PRE-COMMISSIONING - REQD. FOR BLU 70 28OCT09 05JAN10

U2REEC014 ERECTION & PRE-COMMISSIONING - REQD. FOR SYN. 80 27NOV09 14FEB10

C&I ENGINEERING

U2RIE011 ENGINEERING - C&I 45 16JUN08 30JUL08 PROCUREMENT

U2RIP011 ORDERING - C&I 50 31JUL08 18SEP08

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

ENGG. - AIR HEATER

ORDERING OF MATERIAL - AIR HEATER

ENGINEERING - ELECTRICAL

ORDERING - ELECTRICAL

ENGINEERING - C&I

ORDERING - C&I

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:58

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 29 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 30: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

U2RIP012 MANUFACTURING - C&I 420 28NOV08 21JAN10

U2RIP013 DELIVERY - C&I 125 01OCT09 02FEB10 ERECTION/COMMISSIONING

U2RIEC011 CABLING 72 18OCT09 28DEC09

U2RIEC012 ERECTION & PRE-COMMISSIONING - REQD. FOR BLU 31 15DEC09 14JAN10

U2RIEC013 ERECTION & PRE-COMMISSIONING - REQD. FOR SYN. 84 15DEC09 08MAR10

PULVERIZING MILLS

ENGINEERING

U2MIE011 ENGINEERING- MILLS 30 06JUL08 04AUG08

U2MIME011 ENGINEERING - MILL MOTOR 35 21SEP08 25OCT08

U2EN590 CIVIL DRG FOR MILL FOUNDATION 30 09OCT08 07NOV08 PROCUREMENT

U2MIP011 INDENTING OF MATERIAL-MILLS 45 05AUG08 18SEP08

U2MIP012 ORDERING OF MATERIAL-MILLS 60 04SEP08 02NOV08

U2MIP013 RECEIPT OF MATERIAL AT WORKS-MILLS 150 03NOV08 01APR09

U2MIMP011 MANUFACTURING - MILL MOTOR 150 24JAN09 22JUN09

U2MIP014 MANUFACTURING-MILLS 285 03MAR09 12DEC09

U2MIMP012 DELIVERY TO SITE - MILL MOTOR 15 23JUN09 07JUL09

U2MIP015 DESPATCH & DELIVERY AT SITE - MILLS 100 19SEP09 27DEC09 CIVIL

U2BU140 FOUNDATION OF MILLS ( UPTO GL ) 60 30APR09 28JUN09

U2BU145 FOUNDATION OF MILLS ( ABOVE GL ) 40 24OCT09 02DEC09

U2BU160 RELEASE FRONT TO BHEL FOR MILL ERECTION 10 03DEC09 12DEC09 ERECTION/COMMISSIONING

U2MIEC012 MILLS ERECTION 85 13DEC09 07MAR10

U2MIMEC011 ERECTION - MILL MOTOR 30 13DEC09 11JAN10

U2MIMEC012 COMMISSIONING - MILL MOTOR 5 12JAN10 16JAN10

U2MIEC013 MILLS COMMISSIONING 7 08MAR10 14MAR10

POWER CYCLE STEAM TURBINE

ENGINEERING

U2STE011 ENGINEERING- STEAM TURBINE 198 28MAR08 11OCT08 PROCUREMENT

U2STP011 ORDERING OF MATERIAL- ST 225 29APR08 09DEC08

U2STP012 RECEIPT OF MATERIAL AT WORKS- ST 380 29MAY08 12JUN09

U2STP013 MANUFACTURING- ST 260 12DEC08 28AUG09

U2STP0041 AVL. SUB-ASSEMBLIES & PREPARATION FOR MRT 35 05SEP09 09OCT09

U2STP014 MECHANICAL RUN TEST COMPLETION 7 10OCT09 16OCT09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

ENGINEERING- MILLS

INDENTING OF MATERIAL-MILLS

ORDERING OF MATERIAL- STRECEIPT OF MATERIAL AT WORKS- ST

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:58

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 30 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 31: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

U2STP015 DESPATCH & DELIVERY AT SITE - ST 13 17OCT09 29OCT09 ERECTION/COMMISSIONING

U2STEC011 ERECTION- ST 40 19NOV09 28DEC09

U2STEC012 TURBINE - LIVE STEAM VALVE ERECTION 10 19DEC09 28DEC09

U2STEC013 TURBINE BOX UP 2 29DEC09 30DEC09

U2STEC0041 TURBINE - OTHER ACT. & READINESS FOR SYN. 30 31DEC09 30JAN10

GENERATOR & AUX. ENGINEERING

U2GEE011 ENGINEERING- GEN. & AUX. 140 28MAR08 14AUG08 PROCUREMENT

U2GEP011 ORDERING OF MATERIAL- GEN. & AUX. 56 29APR08 23JUN08

U2GEP012 RECEIPT OF MATERIAL AT WORKS- GEN. & AUX. 365 10JUN08 09JUN09

U2GEP013 MANUFACTURING- GEN. & AUX. 322 19NOV08 06OCT09

U2GEP014 ASSEMBLY & TESTING- GEN. & AUX. 35 07OCT09 10NOV09

U2GEP015 DESPATCH & DELIVERY AT SITE - GEN. & AUX. 6 11NOV09 16NOV09 ERECTION/COMMISSIONING

U2GEEC011 GENERATOR - ERECTION 35 17NOV09 21DEC09

U2GEEC012 GEN AUX. ERECTION INCLUDING GCP, GRP 20 27NOV09 16DEC09

U2GEEC013 GENERATOR PRE- & FINAL ALIGNMENT 5 29DEC09 02JAN10

BFP & BOOSTER PUMP ENGINEERING

U2BFE011 ENGINEERING- BFP & BOOSTER PUMP 120 12MAY08 08SEP08

U2BFME011 ENGINEERING - BFP MOTOR 35 21SEP08 25OCT08 PROCUREMENT

U2BFP011 ORDERING - BFP DD ITEMS 60 20MAY08 18JUL08

U2BFP012 MFRG / SITE DELIVERY - BFP SUB-VENDOR & DD ITEMS 425 30MAY08 28JUL09

U2BFMP011 MANUFACTURING - BFP MOTOR 150 24JAN09 22JUN09

U2BFP013 MANUFACTURING - BFP & BOOSTER PUMP 84 11MAR09 02JUN09

U2BFP014 ASSEMBLY & TESTING - BFP & BOOSTER PUMP 28 27MAY09 23JUN09

U2BFP015 DESPATCH & DELIVERY AT SITE- BFP & BOOSTER PUMP 14 17JUN09 30JUN09

U2BFMP012 DELIVERY TO SITE - BFP MOTOR 15 23JUN09 07JUL09 CIVIL

U2TG145 BFP FOUNDATION WORKS 45 11MAR09 24APR09

U2TG185 READINESS FOR BFP ERECTION 0 08JUL09 ERECTION/COMMISSIONING

U2BFMEC011 ERECTION - BFP MOTOR 10 25AUG09 03SEP09

U2BFEC011 ERECTION - BFP 22 30AUG09 20SEP09

U2BFEC012 ERECTION - BOOSTER PUMP 10 30AUG09 08SEP09

U2BFMEC012 COMMISSIONING - BFP MOTOR 2 04SEP09 05SEP09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

ORDERING OF MATERIAL- GEN. & AUX.RECEIPT OF MATERIAL AT WORKS- GEN. & AUX.

ORDERING - BFP DD ITEMS

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:58

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 31 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 32: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

U2BFEC013 PRE-COMMISSIONING - BFP & BOOSTER PUMP 3 23OCT09 25OCT09

CEP ENGINEERING

U2CEE011 ENGINEERING- CEP 120 09MAY08 05SEP08

U2CEME011 ENGINEERING - CEP MOTOR 35 21SEP08 25OCT08 PROCUREMENT

U2CEP011 ORDERING - CEP DD ITEMS 59 20MAY08 17JUL08

U2CEP012 MFRG & DELIVERY AT SITE - BFP SUB-VENDOR ITEMS 286 18JUL08 29APR09

U2CEMP011 MANUFACTURING - CEP MOTOR 150 24JAN09 22JUN09

U2CEP013 MANUFACTURING- CEP 84 30APR09 22JUL09

U2CEMP012 DELIVERY TO SITE - CEP MOTOR 15 23JUN09 07JUL09

U2CEP014 ASSEMBLY & TESTING- CEP 21 23JUL09 12AUG09

U2CEP015 DESPATCH & DELIVERY AT SITE- CEP 7 13AUG09 19AUG09 CIVIL

U2TG180 CEP FOUNDATION WORKS 30 26JUL09 24AUG09 ERECTION/COMMISSIONING

U2CEMEC011 ERECTION - CEP MOTOR 10 25AUG09 03SEP09

U2CEEC011 ERECTION- CEP 25 30AUG09 23SEP09

U2CEMEC012 COMMISSIONING - CEP MOTOR 2 04SEP09 05SEP09

U2CEEC012 PRE-COMMISSIONING - CEP 15 23OCT09 06NOV09

LUBE OIL PUMP & TANK ENGINEERING

U2LOE011 ENGINEERING- LUBEOILPUMPS & TANKS 30 16JUL08 14AUG08 PROCUREMENT

U2LOP011 INDENT&ORDER OF MATERIAL- LUBEOILPUMPS & TANKS 48 31JUL08 16SEP08

U2LOP012 MANUFACTURING- LUBEOILPUMPS & TANKS 256 16DEC08 28AUG09

U2LOP013 RECEIPT OF MATERIAL AT SITE- LUBEOILPUMPS & TANK 11 29AUG09 08SEP09 ERECTION/COMMISSIONING

U2LOEC011 ERECTION- LUBEOILPUMPS & TANKS 25 09SEP09 03OCT09

U2LOEC012 PRE-COMMISSIONING- LUBEOILPUMPS & TANKS 9 04OCT09 12OCT09

DRAIN COOLER ENGINEERING

U2DCE011 ENGINEERING - DRAIN COOLER 10 18MAR08 27MAR08 PROCUREMENT

U2DCP011 ORDERING - DRAIN COOLER 33 17APR08 19MAY08

U2DCP012 MFRG. & DELIVERY AT WORK - DRAIN COOLER MATERIAL 184 20MAY08 19NOV08

U2DCP013 MANUFACTURING - DRAIN COOLER 175 20NOV08 13MAY09

U2DCP014 TESTING - DRAIN COOLER 7 14MAY09 20MAY09

U2DCP015 DISPATCH & DELIVERY AT SITE - DRAIN COOLER 7 21MAY09 27MAY09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

ENGINEERING- CEP

ORDERING - CEP DD ITEMSMFRG & DELIVERY AT SITE - BFP SUB-VENDOR ITEMS

ENGINEERING- LUBEOILPUMPS & TANKS

INDENT&ORDER OF MATERIAL- LUBEOILPUMPS & TANKS

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:58

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 32 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 33: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

ERECTION/COMMISSIONING

U2DCEC011 ERECTION- DRAIN COOLERS 26 04JUN09 29JUN09

U2DCEC012 PRE-COMMISSIONING- DRAIN COOLERS 2 30JUN09 01JUL09

AOP, JOP, EOP, OIL PURIFICATION ENGINEERING

U2JEE011 ENGINEERING - STG AUX( AOP,EOP,JOP,PURFN) 30 18MAR08 16APR08 PROCUREMENT

U2JEP011 ORDERING - STG AUX 69 02APR08 09JUN08

U2JEP012 MANUFACTURING - STG AUX 254 10JUN08 18FEB09

U2JEP013 INSPECTION - STG AUX 84 08JAN09 01APR09

U2JEP014 DESPATCH & DELIVERY AT SITE - STG AUX 42 19MAR09 29APR09 ERECTION/COMMISSIONING

U2JEEC011 ERECTION- STG AUX 40 30AUG09 08OCT09

U2JEEC012 PRE-COMMISSIONING-STG AUX 9 09OCT09 17OCT09

SURFACE CONDENSOR ENGINEERING

U2CHE011 ENGINEERING - COND. & HOTWELL 90 18MAR08 15JUN08 PROCUREMENT

U2CHP011 ORDERING OF MATERIAL - COND. & HOTWELL 62 08APR08 08JUN08

U2CHP012 RECEIPT OF MATERIAL AT WORKS - COND. & HOTWELL 255 09JUN08 18FEB09

U2CHP013 MANUFACTURING - COND. & HOTWELL 112 19FEB09 10JUN09

U2CHP014 TESTING - COND. & HOTWELL 7 11JUN09 17JUN09

U2CHP015 DESPATCH & DELIVERY AT SITE - COND. & HOTWELL 7 18JUN09 24JUN09 CIVIL

U2TG121 CONDENSER FOUNDATION WORKS 30 24JUL09 22AUG09

U2TG190 READINESS FOR CONDENSER FOUNDATION 0 29AUG09ERECTION/COMMISSIONING

U2CHEC011 ERECTION - COND. & HOTWELL 23 30AUG09 21SEP09

U2CHEC012 PRE-COMMISSONING - COND. & HOTWELL 31 22SEP09 22OCT09

U2SCEC016 HP BYPASS STATION ERECTION 15 09DEC09 23DEC09

U2SCEC021 COMMISSIONING OF HP BYPASS SYSTEM. 1 20FEB10 20FEB10

GS CONDENSOR ENGINEERING

U2GSE011 ENGINEERING - GS CONDENSOR 10 18MAR08 27MAR08 PROCUREMENT

U2GSP011 ORDERING OF MATERIAL - GS CONDENSOR 74 28MAR08 09JUN08

U2GSP012 MFRG. & RECPT. OF MTRL. AT WORKS - GS CONDENSOR 254 10JUN08 18FEB09

U2GSP013 MANUFACTURING - GS CONDENSOR 112 19FEB09 10JUN09

U2GSP014 TESTING - GS CONDENSOR 7 11JUN09 17JUN09

U2GSP015 DESPATCH & DELIVERY AT SITE - GS CONDENSOR 7 18JUN09 24JUN09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

MANUFACTURING - STG AUX

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:58

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 33 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 34: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

ERECTION/COMMISSIONING

U2GSEC011 ERECTION - GS CONDENSOR 45 25JUN09 08AUG09

U2GSEC012 COMMISSIONING - GS CONDENSOR 13 09AUG09 21AUG09

LP HEATERS I & II ENGINEERING

U2LPE011 ENGINEERING - LP HEATERS 10 18MAR08 27MAR08 PROCUREMENT

U2LPP011 ORDERING OF MATERIAL - LP HEATERS 74 28MAR08 09JUN08

U2LPP012 MFRG. & RECPT. OF MTRL. AT WORKS - LP HEATERS 196 10JUN08 22DEC08

U2LPP013 MANUFACTURING - LP HEATERS 168 23DEC08 08JUN09

U2LPP014 TESTING - LP HEATERS 7 09JUN09 15JUN09

U2LPP015 DESPATCH & DELIVERY AT SITE - LP HEATERS 7 16JUN09 22JUN09ERECTION/COMMISSIONING

U2LPEC011 ERECTION - LP HEATERS 40 23JUN09 01AUG09

U2LPEC012 PRE-COMMISSIONING - LP HEATERS 18 02AUG09 19AUG09

HP HEATERS IV & V ENGINEERING

U2HPE011 ENGINEERING - HP HEATERS 10 18MAR08 27MAR08 PROCUREMENT

U2HPP011 ORDERING OF MATERIAL - HP HEATERS 74 28MAR08 09JUN08

U2HPP012 MFRG. & RECPT. OF MTRL. AT WORKS - HP HEATERS 184 10JUN08 10DEC08

U2HPP013 MANUFACTURING - HP HEATERS 175 11DEC08 03JUN09

U2HPP014 TESTING - HP HEATERS 14 04JUN09 17JUN09

U2HPP015 DESPATCH & DELIVERY AT SITE - HP HEATERS 7 18JUN09 24JUN09 ERECTION/COMMISSIONING

U2HPEC011 ERECTION - HP HEATERS 21 25JUN09 15JUL09

U2HPEC012 PRE-COMMISSIONING - HEATERS 18 16JUL09 02AUG09

DE-AERATOR HEADER ENGINEERING

U2DHE011 ENGINEERING - DE-AERATOR HEADER 10 18MAR08 27MAR08 PROCUREMENT

U2DHP011 ORDERING OF MATERIAL - DE-AERATOR HEADER 74 28MAR08 09JUN08

U2DHP012 MFRG. & RECPT. OF MTRL. AT WORKS - DE-AER. HEAD. 170 10JUN08 26NOV08

U2DHP013 MANUFACTURING - DE-AERATOR HEADER 182 27NOV08 27MAY09

U2DHP014 TESTING - DE-AERATOR HEADER 14 28MAY09 10JUN09

U2DHP015 DESPATCH & DELIVERY AT SITE - DE-AERATOR HEADER 14 11JUN09 24JUN09CIVIL

U2TG195 DEAERATOR FOUNDATION 25 11JUN09 05JUL09ERECTION/COMMISSIONING

U2DHEC011 ERECTION - DE-AERATOR HEADER 30 06JUL09 04AUG09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

MFRG. & RECPT. OF MTRL. AT WORKS - LP HEATERS

MFRG. & RECPT. OF MTRL. AT WORKS - HP HEATERS

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:58

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 34 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 35: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

U2DHEC012 PRE-COMMISSIONING - DE-AERATOR HEADER 2 05AUG09 06AUG09

DE-AERATOR STORAGE TANK ENGINEERING

U2DSE011 ENGINEERING - DE-AERATOR STOR. TANK 10 18MAR08 27MAR08 PROCUREMENT

U2DSP011 ORDERING OF MATERIAL - DE-AERATOR STOR. TANK 74 28MAR08 09JUN08

U2DSP012 MFRG. & RECPT. OF MTRL. AT WORKS - DE-AR. SO. TK 170 10JUN08 26NOV08

U2DSP013 MANUFACTURING - DE-AERATOR STOR. TANK 182 27NOV08 27MAY09

U2DSP014 TESTING - DE-AERATOR STOR. TANK 14 28MAY09 10JUN09

U2DSP015 DESPATCH & DELIVERY AT SITE - DE-AR. SO. TK 14 11JUN09 24JUN09 CIVIL

U2TG175A10 DEAERATOR FOUNDATION 25 11JUN09 05JUL09 ERECTION/COMMISSIONING

U2DSEC011 ERECTION - DE-AERATOR STORAGE TANK 30 06JUL09 04AUG09

U2DSEC012 PRE-COMMISSIONING - DE-AREATOR STORAGE TANK 2 05AUG09 06AUG09

OIL & AIR COOLER ENGINEERING

U2OAE011 ENGINEERING - OIL & AIR COOLER 10 18MAR08 27MAR08 PROCUREMENT

U2OAP011 ORDERING OF MATERIAL - OIL & AIR COOLER 74 28MAR08 09JUN08

U2OAP012 MFRG. & RECPT. OF MTRL. AT WORKS - OIL & AIR COO 205 20MAY08 10DEC08

U2OAP013 MANUFACTURING - OIL & AIR COOLER 190 19NOV08 27MAY09

U2OAP014 TESTING - OIL & AIR COOLER 21 21MAY09 10JUN09

U2OAP015 DESPATCH & DELIVERY AT SITE - OIL & AIR COOLER 26 23MAY09 17JUN09ERECTION/COMMISSIONING

U2OAEC011 ERECTION - OIL & AIR COOLER 40 02OCT09 10NOV09

U2OAEC012 PRE-COMMISSIONING - OIL & AIR COOLER 1 11NOV09 11NOV09

STEAM JET AIR EJECTOR ENGINEERING

U2SJE011 ENGINEERING - SJAE 17 18MAR08 03APR08 PROCUREMENT

U2SJP011 ORDERING OF MATERIAL - SJAE 46 04APR08 19MAY08

U2SJP012 MFRG. & RECPT. OF MTRL. AT WORKS - SJAE 198 20MAY08 03DEC08

U2SJP013 MANUFACTURING - SJAE 147 04DEC08 29APR09

U2SJP014 TESTING - SJAE 7 30APR09 06MAY09

U2SJP015 DESPATCH & DELIVERY AT SITE - SJAE 7 07MAY09 13MAY09 ERECTION/COMMISSIONING

U2SJEC011 ERECTION - EJECTOR SYSTEM 40 02OCT09 10NOV09

U2SJEC012 PRE-COMMISSIONING - EJECTOR SYSTEM 1 11NOV09 11NOV09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:58

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 35 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 36: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

ELECTRICALENGINEERING

U2HEE011 ENGINEERING - ELECTRICAL 47 18MAY08 03JUL08PROCUREMENT

U2HEP011 ORDERING - ELECTRICAL 71 04JUL08 12SEP08

U2HEP012 MANUFACTURING - ELECTRICAL 330 22OCT08 16SEP09

U2HEP013 DELIVERY - ELECTRICAL 92 29JUN09 28SEP09 ERECTION/COMMISSIONING

U2HEEC011 CABLE TRAY LAYING & CABLING 166 14JUL09 26DEC09

U2HEEC012 ERECTION & PRE-COMMISSIONING - REQD. FOR BLU 30 29JUL09 27AUG09

U2HEEC013 ERECTION & PRE-COMMISSIONING - REQD. FOR SYN. 119 28AUG09 24DEC09

C&IENGINEERING

U2HIE011 ENGINEERING - C&I 45 04JUN08 18JUL08PROCUREMENT

U2HIP011 ORDERING - C&I 45 19JUL08 01SEP08

U2HIP012 MANUFACTURING - C&I 360 11NOV08 05NOV09

U2HIP013 DELIVERY - C&I 180 09JUN09 05DEC09 ERECTION/COMMISSIONING

U2HIEC011 CABLING 166 19JUL09 31DEC09

U2HIEC012 ERECTION & PRE-COMMISSIONING - REQD. FOR BLU 45 07SEP09 21OCT09

U2HIEC013 ERECTION & PRE-COMMISSIONING - REQD. FOR SYN. 60 22OCT09 20DEC09

PIPING & OTHER AUXILIARY SYSTEMSP&IDs & LAYOUTs

ENGINEERING

U2PDE013 ENGINEERING - TG HALL EQPT. LAYOUTS & OTHER ENGG 90 01JUN08 29AUG08

U2PDE012 ENGINEERING - TG HOUSE PIPING/TG INTEGRAL PIPING 90 08JUN08 05SEP08U2PDE011 ENGINEERING - BOILER INTERG. PIPG 90 16JUN08 13SEP08

BOILER INTEGRAL PIPING & UTILITY PIPING (SG) ENGINEERING

U2PBE011 ENGINEERING - BLR. INTERG. & UTIL. PIPG. 90 01JAN09 31MAR09 PROCUREMENT

U2PBP011 MTRL. RCPT. AT WORKS-BLR. INTERG. & UTIL. PIPG. 57 25MAY09 20JUL09

U2PBP012 MANUFACTURING - BLR. INTERG. & UTIL. PIPG. 151 24AUG09 21JAN10

U2PBP013 DESPATCH & DELIVERY - BLR. INTERG. & UTIL. PIPG. 174 24AUG09 13FEB10ERECTION/COMMISSIONING

U2PBEC011 ERCN.,HT&INSUL OF BI PIPG & UTIL-ACW,SA,IA - BLU 115 08SEP09 31DEC09

U2PBEC012 ERCN., HT & INSULATION OF BI PIPING FOR SB/SVF 80 23OCT09 10JAN10

U2PBEC013 ERCN., HT & INSUL. OF OTHER UTILITY PIPG 60 31DEC09 28FEB10

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

ENGINEERING - ELECTRICAL

ORDERING - ELECTRICAL

ENGINEERING - C&I

ORDERING - C&I

ENGINEERING - BOILER INTERG. PIPG

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:58

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 36 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 37: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

TG HOUSE PIPING & TG INTEGRAL PIPING (PCP) ENGINEERING

U2PHE011 ENGINEERING- TG HOUSE & TG INTEGRAL PIPG 90 01JAN09 31MAR09 PROCUREMENT

U2PHP011 INDG/ORDG OF MTRL- TG HOUSE & TG INTEGRAL PIPG 54 01APR09 24MAY09

U2PHP012 MTRL RCPT AT WORKS - TG HOUSE & TG INTEGRAL PIPG 57 25MAY09 20JUL09

U2PHP013 MANUFACTURING - TG HOUSE & TG INTEGRAL PIPG 154 23AUG09 23JAN10

U2PHP014 DESP &DLRY AT SITE - TG HOUSE & TG INTEGRAL PIPG 175 23AUG09 13FEB10ERECTION/COMMISSIONING

U2PHEC024 ERECTION OF FEED WATER PIPING 30 21SEP09 20OCT09

U2PHEC033 ERECTION OF CONDENSATE PIPING 38 22OCT09 28NOV09

U2PHEC028 HYDRO TEST OF FEED WATER PIPING 6 26OCT09 31OCT09

U2PHEC042 INSULATION OF FEED WATER PIPING 14 01NOV09 14NOV09

U2PHEC031 ERECTION OF MAIN STEAM PIPING 34 05NOV09 08DEC09

U2PHEC043 ERECTION OF AUX. STEAM PIPING 25 15NOV09 09DEC09

U2PHEC027 HYDRO TEST OF CONDENSATE PIPING 7 04DEC09 10DEC09

U2PHEC041 INSULATION OF CONDENSATE PIPING 7 09DEC09 15DEC09

U2PHEC034 HYDRO TEST OF AUX. STEAM PIPING 6 10DEC09 15DEC09

U2PHEC044 PRE-BOILER FLUSHING 7 11DEC09 17DEC09

U2PHEC052 ERCN,HT & INSUL. OF BALANCE PIPG - REQD. FOR BLU 34 11DEC09 13JAN10

U2PHEC025 HYDRO TEST OF MAIN STEAM PIPING 6 14DEC09 19DEC09

U2PHEC035 INSULATION OF AUX. STEAM PIPING 5 16DEC09 20DEC09

U2PHEC029 INSULATION OF MAIN STEAM PIPING 16 20DEC09 04JAN10

U2PHEC032 ERECTION OF EXTRACTION STEAM PIPING 38 04FEB10 13MAR10

U2PHEC036 ERECTION OF CONDENSOR AIR EVACUATION PIPING 31 14FEB10 16MAR10

U2PHEC039 ERECTION OF LUBE OIL PIPING 30 14FEB10 15MAR10

U2PHEC053 ERCN,HT & INSUL. OF BALANCE PIPG - REQD. FOR SYN 40 14FEB10 25MAR10

U2PHEC030 INSULATION OF EXTRACTION STEAM PIPING 12 14MAR10 25MAR10

U2PHEC038 INSULATION OF CONDENSOR AIR EVACUATION PIPING 5 17MAR10 21MAR10

HANGERS & SUPPORTS ENGINEERING

U2HSE011 ENGINEERING - HANGERS & SUPPORTS 90 01JAN09 31MAR09PROCUREMENT

U2HSP011 RECEIPT OF MTRL AT WORKS - HANGERS & SUPPORTS 57 25MAY09 20JUL09

U2HSP012 MANUFACTURING - HANGERS & SUPPORTS 154 23AUG09 23JAN10

U2HSP013 DESP & DLRY AT SITE - HANGERS & SUPPORTS 175 23AUG09 13FEB10ERECTION/COMMISSIONING

U2HSEC012 ERECTION OF H & S - REQD. FOR BLU 62 13NOV09 13JAN10

U2HSEC011 ERECTION OF ACCESSIBLE PLATFORMS TO ERECT H & S 110 26NOV09 15MAR10

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:58

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 37 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 38: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

U2HSEC013 ERECTION OF H & S - REQD. FOR SYN. 25 01MAR10 25MAR10

HP DOSING SYSTEM ENGINEERING

U2HDE011 ENGINEERING- HP DOSING STN. 90 01JAN09 31MAR09PROCUREMENT

U2HDP011 INDENTING OF MATERIAL- HP DOSING STN. 24 01APR09 24APR09

U2HDP012 ORDERING OF MATERIAL- HP DOSING STN. 30 25APR09 24MAY09

U2HDP013 RECEIPT OF MATERIAL AT SITE- HP DOSING STN. 57 25MAY09 20JUL09

U2HDP014 MANUFACTURING - HP DOSING 90 25AUG09 22NOV09

U2HDP015 DESP & DLRY - HP DOSING 110 26AUG09 13DEC09ERECTION/COMMISSIONING

U2HDEC011 ERECTION- HP DOSING STN. 20 14DEC09 02JAN10

U2HDEC012 COMMISSIONING- HP DOSING STN. 8 03JAN10 10JAN10

TANKS & VESSELS REL. ENGINEERING

U2TVE011 ENGINEERING - TANKS & VESSELS 90 01JAN09 31MAR09 PROCUREMENT

U2TVP011 ORDERING - TANKS & VESSELS REL. 54 01APR09 24MAY09

U2TVP012 MANUFACTURING - TANKS & VESSELS REL. 93 23AUG09 23NOV09

U2TVP013 DESP & DLRY AT SITE - TANKS & VESSELS REL. 110 26AUG09 13DEC09ERECTION/COMMISSIONING

U2TVEC011 ERECTION & COMMISSIONING - REQD. FOR BLU 30 14DEC09 12JAN10

U2TVEC012 ERECTION & COMMISSIONING - REQD. FOR SYN. 45 14DEC09 27JAN10

C&I ENGINEERING

U2CIE011 ENGINEERING - CONTROL VALVES & FLOW ELEMENTS 25 06JUN08 30JUN08

U2PIE011 ENGINEERING - OTHER C&I 90 01JAN09 31MAR09PROCUREMENT

U2CIP011 INDENTING & ORDERING - CONTROL VALVES 60 01JUL08 29AUG08

U2CIP012 INDENTING & ORDERING - FLOW ELEMENTS 45 01JUL08 14AUG08

U2PIP011 ORDERING - OTHER C&I 54 01APR09 24MAY09

U2PIP012 MANUFACTURING - OTHER C&I 154 23AUG09 23JAN10

U2PIP013 DESP & DLRY AT SITE - OTHER C&I 170 27AUG09 12FEB10

U2CIP013 RECEIPT AT SITE - CONTROL VALVES 15 30AUG09 13SEP09

U2CIP014 RECEIPT AT SITE - FLOW ELEMENTS 15 14SEP09 28SEP09ERECTION/COMMISSIONING

U2CIEC011 ERCN. & COMMNG. - CONTROL VALVES REQD. FOR BLU 28 01JAN10 28JAN10

U2CIEC013 ERCN. & COMMNG. - FLOW ELEMENTS REQD. FOR BLU 24 05JAN10 28JAN10

U2PIEC011 ERECTION & COMMISSIONING - REQD. FOR SYN. 42 13FEB10 26MAR10

U2CIEC012 ERCN. & COMMNG. - CONTROL VALVES REQD. FOR SYN. 36 14FEB10 21MAR10

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

INDENTING & ORDERING - CONTROL VALVESINDENTING & ORDERING - FLOW ELEMENTS

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:58

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 38 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 39: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

U2CIEC014 ERCN. & COMMNG. - FLOW ELEMENTS REQD. FOR SYN. 36 14FEB10 21MAR10

APRDS ENGINEERING

U2APE011 ENGINEERING-APRDS 25 11JUN08 05JUL08 PROCUREMENT

U2APP011 INDENTING & ORDERING OF MATERIAL-APRDS 55 06JUL08 29AUG08

U2APP012 MANUFACTURING-APRDS 80 28NOV08 15FEB09

U2APP013 RECEIPT OF MATERIAL AT SITE-APRDS 20 26JUN09 15JUL09 ERECTION/COMMISSIONING

U2APEC011 ERECTION-APRDS 50 15NOV09 03JAN10

U2APEC012 COMM OF APRDC 10 04JAN10 13JAN10

LP DOSING SYSTEM ENGINEERING

U2LDE011 ENGINEERING- HP/LP DOSING STN. 10 13JUN08 22JUN08 PROCUREMENT

U2LDP011 INDENTING OF MATERIAL- LP DOSING STN. 10 28JUN08 07JUL08

U2LDP012 ORDERING OF MATERIAL- LP DOSING STN. 30 08JUL08 06AUG08

U2LDP013 RECEIPT OF MATERIAL AT SITE- LP DOSING STN. 45 13JUN09 27JUL09ERECTION/COMMISSIONING

U2LDEC011 ERECTION - LP DOSING STN. 20 16NOV09 05DEC09

U2LDEC012 COMMISSIONING - LP DOSING STN. 8 03JAN10 10JAN10

MP ENGINEERING

U2MPE011 ENGINEERING - MP 20 06JUN08 25JUN08 PROCUREMENT

U2MPP011 INDENTING & ORDERING - ME BELLOWS 60 26JUN08 24AUG08

U2MPP012 INDENTING & ORDERING - POWER CYCLE VALVES 60 26JUN08 24AUG08

U2MPP013 INDENTING & ORDERING - STEAM TRAPS 45 26JUN08 09AUG08

U2MPP014 INDENTING & ORDERING - THERMAL INSULATION 30 21FEB09 22MAR09

U2MPP017 RECEIPT AT SITE - STEAM TRAPS 15 22APR09 06MAY09

U2MPP016 RECEIPT AT SITE - POWER CYCLE VALVES 15 22MAY09 05JUN09

U2MPP015 RECEIPT AT SITE - ME BELLOWS 15 27MAY09 10JUN09

U2MPP018 RECEIPT AT SITE - THERMAL INSULATION 15 19SEP09 03OCT09 ERECTION/COMMISSIONING

U2MPEC011 ERECTION OF ME BELLOWS- REQD. FOR BLU 25 05DEC09 29DEC09

U2MPEC014 ERECTION OF THERMAL INSULATION - REQD. FOR BLU 49 07DEC09 24JAN10

U2MPEC012 ERECTION OF POWER CYCLE VALVES - REQD. FOR BLU 25 01JAN10 25JAN10

U2MPEC013 ERECTION OF STEAM TRAPS - REQD. FOR BLU 25 01JAN10 25JAN10

U2MPEC018 ERECTION OF THERMAL INSULATION - REQD. FOR SYN. 71 14JAN10 25MAR10

U2MPEC015 ERECTION OF ME BELLOWS- REQD. FOR SYN. 36 04FEB10 11MAR10

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

ENGINEERING-APRDS

INDENTING & ORDERING OF MATERIAL-APRDS

ENGINEERING- HP/LP DOSING STN.

INDENTING OF MATERIAL- LP DOSING STN.ORDERING OF MATERIAL- LP DOSING STN.

ENGINEERING - MP

INDENTING & ORDERING - ME BELLOWSINDENTING & ORDERING - POWER CYCLE VALVES

INDENTING & ORDERING - STEAM TRAPS

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:58

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 39 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 40: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

U2MPEC016 ERECTION OF POWER CYCLE VALVES - REQD. FOR SYN. 45 05FEB10 21MAR10

U2MPEC017 ERECTION OF STEAM TRAPS - REQD. FOR SYN. 36 14FEB10 21MAR10

LUBE OIL TRANSFER ENGINEERING

U2LTE011 ENGINEERING - CLEAN OIL & DIRTY OIL PUMPS 30 18MAY08 16JUN08 PROCUREMENT

U2LTP011 ORDERING - CLEAN OIL & DIRTY OIL PUMPS 48 02JUN08 19JUL08

U2LTP012 MANUFACTURING - CLEAN OIL & DIRTY OIL PUMPS 256 18OCT08 30JUN09

U2LTP013 DELIVERY AT SITE - CLEAN OIL & DIRTY OIL PUMPS 11 01JUL09 11JUL09 ERECTION/COMMISSIONING

U2LTEC011 ERECTION - CLEAN OIL & DIRTY OIL PUMPS 25 12JUL09 05AUG09

U2LTEC012 PRE-COMMISSIONNG - CLEAN OIL & DIRTY OIL PUMPS 9 16SEP09 24SEP09

HP & LP FLASH TANKSENGINEERING

U2HLE011 ENGINEERING - HP & LP FLASH TANKS 20 26JUN08 15JUL08PROCUREMENT

U2HLP011 ORDERING - HP & LP FLASH TANKS 30 16JUL08 14AUG08

U2HLP012 MANUFACTURING - HP & LP FLASH TANKS 250 13NOV08 20JUL09

U2HLP013 DELIVERY - HP & LP FLASH TANKS 21 21JUL09 10AUG09ERECTION/COMMISSIONING

U2HLTEC011 ERECTION & COMMISSIONING - HP FLASH TANK 102 02DEC09 13MAR10

U2HLTEC012 ERECTION & COMMISSIONING - LP FLASH TANK 102 02DEC09 13MAR10

INSTRUMENTATION CONTROLS TG PACKAGE

ENGINEERING

U2ETE011 ENGINEERING - ATRS,.. 79 19DEC08 07MAR09 PROCUREMENT

U2ETP011 PROCUREMENT OF MATERIALS - ATRS,.. 116 07MAY09 30AUG09

U2ETP012 ASSEMBLY & TESTING COMPLETION - ATRS,.. 32 31AUG09 01OCT09

U2ETP013 FAT, DESP & DELIVERY TO SITE - ATRS,.. 18 03OCT09 20OCT09 ERECTION/COMMISSIONING

U2ETEC011 ERECTION - ATRS,.. 46 21OCT09 05DEC09

U2ETEC012 COMMISSIONING - ATRS,.. 25 06DEC09 30DEC09

SG PACKAGE ENGINEERING

U2ESE011 ENGINEERING - FLAME SCANNER, SADC, BMS 79 19DEC08 07MAR09 PROCUREMENT

U2ESP011 PROCUREM OF MATERIALS - FLAME SCANNER, SADC, BMS 100 07MAY09 14AUG09

U2ESP012 ASSEMBLY & TESTING - FLAME SCANNER, SADC, BMS 25 15AUG09 08SEP09

U2ESP013 FAT, DESP & DELIVERY - FLAME SCANNER, SADC, BMS 15 10SEP09 24SEP09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

ORDERING - CLEAN OIL & DIRTY OIL PUMPS

ENGINEERING - HP & LP FLASH TANKS

ORDERING - HP & LP FLASH TANKS

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:58

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 40 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 41: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

ERECTION/COMMISSIONING

U2ESEC011 ERECTION - FLAME SCANNER, SADC, BMS 46 25SEP09 09NOV09

U2ESEC012 COMMISSIONING - FLAME SCANNER, SADC, BMS 25 10NOV09 04DEC09

HMI SYSTEM ENGINEERING

U2EHE011 ENGINEERING - TFT MONIT., COMPU., N/W PANEL 79 19DEC08 07MAR09 PROCUREMENT

U2EHP011 MTRLS. PROCUREME - TFT MONIT., COMPU., N/W PANEL 116 07MAY09 30AUG09

U2EHP012 ASSEMBLY & TEST. - TFT MONIT., COMPU., N/W PANEL 32 31AUG09 01OCT09

U2EHP013 FAT, DESP & DELI - TFT MONIT., COMPU., N/W PANEL 18 03OCT09 20OCT09 ERECTION/COMMISSIONING

U2EHEC011 ERECTION - TFT MONIT., COMPU., N/W PANEL 46 21OCT09 05DEC09

U2EHEC012 COMMISSIONING - TFT MONIT., COMPU., N/W PANEL 25 06DEC09 30DEC09

AVR SYSTEM ENGINEERING

U2EAE011 ENGINEERING - AVR 79 19DEC08 07MAR09 PROCUREMENT

U2EAP011 PROCUREMENT OF MATERIALS - AVR 116 07MAY09 30AUG09

U2EAP012 ASSEMBLY & TESTING - AVR 32 31AUG09 01OCT09

U2EAP013 FAT, DESP & DELIVERY - AVR 18 03OCT09 20OCT09 ERECTION/COMMISSIONING

U2EAEC011 ERECTION - AVR 46 21OCT09 05DEC09

U2EAEC012 COMMISSIONING - AVR 25 06DEC09 30DEC09

OVERALL COMMISSIONING BOILERU2OLBC011 BOILER LIGHT UP 3 29JAN10 31JAN10

U2OLBC012 STEAM BLOWING 10 10FEB10 19FEB10

U2OLBC013 SAFETY VALVE FLOATING COMPLETION 3 20FEB10 22FEB10

U2OLBC014 BOILER COAL FIRING 6 01APR10 06APR10

TGU2OLTC011 FINAL ALIGNMENT OF TG 9 31DEC09 08JAN10

U2OLTC012 TG - OIL FLUSHING 15 09JAN10 23JAN10

U2OLTC013 BARRING GEAR OPERATION 7 24JAN10 30JAN10

U2OLTC014 VACCUM PULLING- TG 2 14MAR10 15MAR10

U2OLTC015 STEAM DUMPING 1 16MAR10 16MAR10

OVERALLU2OLOC011 ROLLING, OCC SCC OF GEN & SYNCHRONISATION 5 27MAR10 31MAR10

U2OLOC012 COMMG./ STABILITY RUN/TRIAL OPERATION-TG 3 29MAR10 31MAR10

U2OLOC013 COMMG./ 72 hrs TRIAL OPERATION-TG 3 07APR10 09APR10

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:58

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 41 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 42: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

U2OLOC014 PROV. HANDING OVER OF PLANT 0 09APR10

U2OLOC015 PLANT OPTIMISATION 2 10APR10 11APR10

U2OLOC016 LOAD REJECTION & ISLANDING TESTS 2 12APR10 13APR10

U2OLOC017 RELIABILITY RUN 2 14APR10 15APR10

U2OLOC018 PG TEST 2 16APR10 17APR10

U2OLOC019 FINAL HANDING OVER OF PLANT 0 17APR10

COMMON BOPSubtotal 689 12MAY08 31MAR10

TG BUILDING ENGINEERINGEN310 SPECIFICATION- EOT CRANE 25 17JUL08 10AUG08

EN300 CIVIL DRG FOR STG BUILDING 45 03AUG08 16SEP08

PROCUREMENTPR230 ORDERING - AGGREGATE PRODUCTION CRUSHER 30 01JUN08 30JUN08

PR240 MOBILIZATION & SET-UP OF AGGRERATE PRODN CRUSHER 60 01JUL08 29AUG08

PR200 ORDERING- EOT CRANE 35 11AUG08 14SEP08

PR210 MANUFACTURING- EOT CRANE 190 15SEP08 23MAR09

PR220 DISPATCH- EOT CRANE 25 24MAR09 17APR09

CIVILTG010 MAIN COLUMN FOUND 180 02SEP08 28FEB09

TG020 FABRICATION - STG BUILD STRUCTURE 240 14SEP08 11MAY09

TG110 TG FOUNDATION WORKS - UNIT #1 180 27SEP08 25MAR09

TG030 ERECTION OF STG BUILD STRUCTURE 300 24OCT08 19AUG09

TG040 CONCRETING OF BC BAY 3.5m FLOOR 60 23DEC08 20FEB09

U2TG110 TG FOUNDATION WORKS - UNIT #2 180 26DEC08 23JUN09

TG060 CONCRETING OF BC BAY 8m FLOOR 60 07JAN09 07MAR09

TG065 CONCRETING OF BC BAY 11m FLOOR 60 22JAN09 22MAR09

TG080 CONCRETING OF BC BAY 0.00m FLOOR 90 22JAN09 21APR09

TG075 CONCRETING OF BC BAY 16.5 m FLOOR 60 06FEB09 06APR09

TG125 READINESS FOR SWITCH GEAR ERECT @ 3.5 M 40 21FEB09 01APR09

TG120 UNIT BATTERY ROOM READINESS - UNIT #1 35 11MAR09 14APR09

TG100 ROOF & SIDE SHEETING 140 23MAR09 09AUG09

TG190 STATION BATTERY ROOM READINESS 45 23MAR09 06MAY09

U2TG120 UNIT BATTERY ROOM READINESS - UNIT #2 35 07APR09 11MAY09

TG015 AUX COLUMN FOUND 270 15APR09 09JAN10

TG135 READINESS FOR EOT ERECT 0 21APR09

TG050 CONCRETING OF AB BAY 5m FLOOR- PART 45 15MAY09 28JUN09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

SPECIFICATION- EOT CRANECIVIL DRG FOR STG BUILDING

ORDERING - AGGREGATE PRODUCTION CRUSHERMOBILIZATION & SET-UP OF AGGRERATE PRODN CRUSHER

ORDERING- EOT CRANE

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:58

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 42 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 43: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

TG140 READINESS FOR TG FOUNDATION - UNIT #1 0 05JUN09

TG070 CONCRETING OF AB BAY 11m FLOOR - PART 45 14JUN09 28JUL09

TG113 U#1CONCRETING OF STG COOLING AIR DUCT UPTO 7.5M 45 21JUN09 04AUG09

TG340 FINISHING WORKS OF TG BUILD 250 29JUN09 05MAR10

TG130 CONTROL ROOM READINESS INCL. FINISHING WORKS 75 24JUL09 06OCT09

TG114 U#1CONCRETING OF STG COOLING AIR DUCT ABOVE 7.5M 30 18AUG09 16SEP09

TG117 ACW PUMP FOUNDATION WORKS 15 18AUG09 01SEP09

TG132 READINESS OF CON ROOM FOR PANEL ERECT 25 23AUG09 16SEP09

U2TG140 READINESS FOR TG FOUNDATION - UNIT #2 0 03SEP09

TG167 READINESS FOR ACWP ERECTION 0 11SEP09

TG172 U#1 READINESS FOR STG COOLER ERECTION 0 16SEP09

U2TG113 U#2CONCRETING OF STG COOLING AIR DUCT UPTO 7.5M 45 19SEP09 02NOV09

TG082 CONCRETING OF AB BAY 0.00m FLOOR 75 16NOV09 29JAN10

U2TG114 U#2CONCRETING OF STG COOLING AIR DUCT ABOVE 7.5M 1 18NOV09 18NOV09

U2TG172 U#2 READINESS FOR STG COOLER ERECTION 0 18NOV09

TG052 CONCRETING OF AB BAY 5m FLOOR - BALANCE 30 10JAN10 08FEB10

TG072 CONCRETING OF AB BAY 11m FLOOR - BALANCE 25 09FEB10 05MAR10

ERECTION & COMMISSIONINGEC100 ERECTION- EOT CRANE 20 22APR09 11MAY09

EC110 COMMG. OF EOT CRANE (with temp power from client 10 12MAY09 21MAY09

TG BUILD - ELE WORKS ENGINEERINGEN370 SPEC - 6.6 kV HT SWITCH GEAR 30 29JUL08 27AUG08

EN350 SPEC - STATION BATTERY & CHARGER 25 31JUL08 24AUG08

EN360 SPEC - GEN BUS DUCT 20 20AUG08 08SEP08

EN380 SPEC - LT SWGR / MCC/ DB 30 23AUG08 21SEP08

EN410 SPEC - ELE INSTALLATION WORKS 30 30AUG08 28SEP08

EN400 SPEC - UNIT BATTERY/CHARGER & UPS 20 29SEP08 18OCT08

PROCUREMENTPR340 ORDERING-HT SWITCH GEAR 60 28AUG08 26OCT08

PR250 ORDERING OF STATION BATTERY & CHARGER 45 04SEP08 18OCT08

PR380 ORDERING-LTSWGR/MCC.DB 60 22SEP08 20NOV08

PR410 ORDERING- GEN BUS DUCT 50 09OCT08 27NOV08

PR260 MANUF - STATION BATTERY & CHARGER 120 19OCT08 15FEB09

PR280 ORDERING- UNIT BATTERY/CHARGER & UPS 30 19OCT08 17NOV08

PR350 ENGG & MANUF - HT SWITCH GEAR 220 27OCT08 03JUN09

PR290 MANUF - UNIT BATTERY/CHARGER & UPS 120 18NOV08 17MAR09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

SPEC - 6.6 kV HT SWITCH GEARSPEC - STATION BATTERY & CHARGER

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:58

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 43 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 44: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

PR390 MANUF - LTSWGR/MCC.DB 260 21NOV08 07AUG09

PR420 MANUFACTURING OF GEN BUS DUCT 180 18DEC08 15JUN09

PR270 DELIVERY TO SITE - STATION BATTERY & CHARGER 30 06FEB09 07MAR09

PR300 DELIVERY TO SITE - UNIT BATTERY/CHARGER & UPS 40 18MAR09 26APR09

PR391 DELIVERY AT SITE - UNIT & STATION DCDB & UPS DB 15 21MAR09 04APR09

PR393 DELIVERY AT SITE - LTSWGR (CT & PT MCC) 15 20APR09 04MAY09

PR360 DELIVERY - HT SWTCH GEAR - STATION 25 25APR09 19MAY09

PR395 DELIVERY AT SITE - BMCC, TMCC & NE SG 15 20MAY09 03JUN09

PR370 DELIVERY - HT SWTCH GEAR - UNIT 20 30MAY09 18JUN09

PR394 DELIVERY AT SITE - LTSWGR AC&VENT, FUEL OIL MCC 15 09JUN09 23JUN09

PR430 DELIVERY TO SITE - GEN BUS DUCT 30 16JUN09 15JUL09

PR396 DELIVERY AT SITE - CHP MCC, DG SG 15 08AUG09 22AUG09

ERECTION & COMMISSIONING BATTERY/CHARGER/UPS

EC150 ERECTION - UNIT BATTERY & CHARGER - UNIT #1 20 07APR09 26APR09

EC160 COMMG.- UNIT #1 BATTERY & UPS 5 27APR09 01MAY09

U2EC150 ERECTION - UNIT BATTERY & CHARGER - UNIT #2 20 02MAY09 21MAY09

EC152 ERECTION - STATION BATTERY & CHARGER 20 07MAY09 26MAY09

EC153 ERECTION - STATION DCDB 20 07MAY09 26MAY09

U2EC160 COMMG.- UNIT #2 BATTERY & UPS 5 22MAY09 26MAY09

EC151 COMMG. - STATION BATTERY & CHARGER 5 27MAY09 31MAY09

EC154 COMMG. - STATION DCDB 5 27MAY09 31MAY09

EC190 COMM OF UPS DB 5 27MAY09 31MAY09 BUS DUCT

EC220 U#1 - ERECTION OF BUSDUCT OUTSIDE TG BUILD 30 16JUL09 14AUG09

U2EC220 U#2 - ERECTION OF BUSDUCT OUTSIDE TG BUILD 30 10AUG09 08SEP09

EC219 U#1 - ERECT OF GEN BUS DUCT INSIDE TG BUILD 20 30SEP09 19OCT09

EC240 UNIT #1 - BUSDUCT ERECTION COMPELETION. 5 20OCT09 24OCT09

EC250 PRE-COMMG.- UNIT #1 GEN BUS DUCT 10 25OCT09 03NOV09

U2EC219 U#2 - ERECT OF GEN BUS DUCT INSIDE TG BUILD 20 02JAN10 21JAN10

U2EC240 UNIT #2 - BUSDUCT ERECTION COMPELETION. 5 22JAN10 26JAN10

U2EC250 PRE-COMMG.- UNIT #2 GEN BUS DUCT 10 27JAN10 05FEB10 HT SWITCHGEAR

EC300 ERECTION - HT SWITCH GEAR - STATION 20 20MAY09 08JUN09

EC305 ERECTION - HT SWITCH GEAR - UNIT 30 19JUN09 18JUL09

EC304 COMMG./CHARGING - HT SWGR - STATION 5 17AUG09 21AUG09

EC320 COMMG./CHARGING OF HT SWRS - UNIT 5 22AUG09 26AUG09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:58

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 44 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 45: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

LT SWITCHGEAR

EC330 ERECTION OF LT SWITCHGEAR - STATION 30 05APR09 04MAY09

EC340 ERECTION OF LT SWITCHGEAR - UNIT 30 04JUN09 03JUL09

EC355 ERECTION OF LV SWGR - BMCC, TMCC 45 04JUN09 18JUL09

EC335 COMMG./CHARGING OF LV SWGR - STATION 10 01SEP09 10SEP09

EC345 COMMG./CHARGING OF LV SWGR - UNIT 10 06SEP09 15SEP09

EC365 COMMG./CHARGING OF LV SWGR - BMCC, TMCC 20 16SEP09 05OCT09

BOILER AREA CIVIL ENGINEERINGEN480 CIVIL DRG FOR BOILER AREA 55 23AUG08 16OCT08

EN490 ESP CONTROL BUILDING DRG 55 17SEP08 10NOV08

CIVILBA145 ESP CONTROL BUILDING CIVIL WORKS 210 25MAR09 20OCT09

BA190 READINESS OF ESP BUILD FOR ERECTION 5 08SEP09 12SEP09

BA180 BOILER AREA PAVING 120 08NOV09 07MAR10

MILL & BUNKER BAY ENGINEERINGEN510 CIVIL& STRUL DRG FOR BUNKERS AREA 50 31JUL08 18SEP08

CIVILBU110 UNIT #1 - FAB. & ERN OF BUNKERS & STRUCTURE 150 03NOV08 01APR09

BU100 UNIT #1 - FOUNDATION OF BUNKER STRUCT 75 16NOV08 29JAN09

U2BU110 UNIT #2 - FAB. & ERN OF BUNKERS & STRUCTURE 150 02JAN09 31MAY09

BU120 UNIT #1 - CIVIL WORKS OF BUNKER SUPER STRUCTURE 85 11FEB09 06MAY09

U2BU100 UNIT #2 - FOUNDATION OF BUNKER STRUCT 75 14FEB09 29APR09

U2BU120 UNIT #2 - CIVIL WORKS OF BUNKER SUPER STRUCTURE 85 12APR09 05JUL09

TRANSFORMER YARD ENGINEERINGEN530 SPEC - GENERATOR TRANSFORMER 20 12MAY08 31MAY08

EN545 SPEC - STATION TRANSFORMER 30 01JUN08 30JUN08

EN540 SPEC - UNIT AUXILIARY TRANSFORMER 20 11JUN08 30JUN08

EN550 SPEC - SERVICE TRANSFORMER 20 03AUG08 22AUG08

EN560 FOUNDATION DRG - CIVIL 80 03AUG08 21OCT08

PROCUREMENTPR510 ORDERING OF GENERATOR TRANSFORMER 30 01JUN08 30JUN08

PR520 MANUF OF GENERATOR TRANSFORMER 400 01JUL08 04AUG09

PR540 ORDERING- UNIT AUXILIARY TRANSFORMER 30 01JUL08 30JUL08

PR562 ORDERING OF STATION TRANSFORMER 40 01JUL08 09AUG08

PR550 MANUF OF UNIT AUXILIARY TRANSF 240 31JUL08 27MAR09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

CIVIL& STRUL DRG FOR BUNKERS AREA

SPEC - GENERATOR TRANSFORMERSPEC - STATION TRANSFORMER

SPEC - UNIT AUXILIARY TRANSFORMERSPEC - SERVICE TRANSFORMER

FOUNDATION DRG - CIVIL

ORDERING OF GENERATOR TRANSFORMERMANUF OF GENERATOR TRANSFORMER

ORDERING- UNIT AUXILIARY TRANSFORMERORDERING OF STATION TRANSFORMER

MANUF OF UNIT AUXILIARY TRANSF

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:58

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 45 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 46: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

PR564 MANUF OF STATION TRANSFORMER 200 10AUG08 25FEB09

PR570 ORDERING OF SERVICE TRANSFORMER 40 23AUG08 01OCT08

PR580 MANUF OF SERVICE TRANSFORMER 250 02OCT08 08JUN09

PR560 U#1 - DELIVERY AT SITE - UNIT AUXILIARY TRANSF 15 27JAN09 10FEB09

PR566 UNIT #1 - DELIVERY AT SITE OF STATION TRANSF 15 01FEB09 15FEB09

PR590 UNIT #1 - DELIVERY AT SITE - SERVICE TRANSF 20 04FEB09 23FEB09

U2PR566 UNIT #2 - DELIVERY AT SITE OF STATION TRANSF 15 26FEB09 12MAR09

U2PR560 U#2 - DELIVERY AT SITE - UNIT AUXILIARY TRANSF 15 28MAR09 11APR09

PR530 DELIVERY AT SITE - U#1 GENERATOR TRANSFORMER 25 27APR09 21MAY09

U2PR590 UNIT #2 - DELIVERY AT SITE - SERVICE TRANSF 20 09JUN09 28JUN09

U2PR530 DELIVERY AT SITE - U#2 GENERATOR TRANSFORMER 25 05AUG09 29AUG09

CIVILTR100 UNIT #1 - FOUND OF GENERATOR TRANSFORMER 120 22OCT08 18FEB09

TR132 UNIT #1 - FOUND OF STATION TRANSF 120 06NOV08 05MAR09

TR140 UNIT #1 - FOUND OF SERVICE TRANSFORMER 140 01DEC08 19APR09

U2TR100 UNIT #2 - FOUND OF GENERATOR TRANSFORMER 120 21DEC08 19APR09

TR120 UNIT #1 - FOUND OF UNIT AUXILIARY TRANSF 80 20JAN09 09APR09

U2TR132 UNIT #2 - FOUND OF STATION TRANSF 120 20JAN09 19MAY09

TR110 UNIT #1 - FOUND READY FOR GT ERECTION 20 19FEB09 10MAR09

U2TR120 UNIT #2 - FOUND OF UNIT AUXILIARY TRANSF 80 19FEB09 09MAY09

U2TR140 UNIT #2 - FOUND OF SERVICE TRANSFORMER 140 01MAR09 18JUL09

TR134 UNIT #1 - FOUND READY FOR STATION TRANSF ERECT 10 06MAR09 15MAR09

TR150 U#1 FOUND READY FOR STATION SERVICE TRANSFORMER 20 21MAR09 09APR09

TR160 U#1 FDN READY FOR UNIT SERVICE TRANSFORMER 20 31MAR09 19APR09

TR130 U#1 - FOUND READY FOR UNIT AUXILIARY TRANSF 10 10APR09 19APR09

TR200 UNIT #1 - FOUND. OF ESP SERVICE TRANSFORMER 10 10APR09 19APR09

TR170 FOUND READY FOR CT & PT, CHP SERVICE TRANSFORMER 10 20APR09 29APR09

U2TR110 UNIT #2 - FOUND READY FOR GT ERECTION 20 20APR09 09MAY09

U2TR130 U#2 - FOUND READY FOR UNIT AUXILIARY TRANSF 10 10MAY09 19MAY09

TR180 MISC CIVIL WORKS LIKE FENCING, AGG FILLING 120 20MAY09 16SEP09

U2TR134 UNIT #2 - FOUND READY FOR STATION TRANSF ERECT 10 20MAY09 29MAY09

U2TR150 U#2 FOUND READY FOR STATION SERVICE TRANSFORMER 20 19JUN09 08JUL09

U2TR160 U#2 FDN READY FOR UNIT SERVICE TRANSFORMER 20 29JUN09 18JUL09

U2TR200 UNIT #2 - FOUND. OF ESP SERVICE TRANSFORMER 10 09JUL09 18JUL09

ERECTION & COMMISSIONINGEC416 UNIT #1 -ERECT OF STATION TRANSF 15 16MAR09 30MAR09

EC417 UNIT #1 - PRE-COMMG OF STATION TRANSF 5 31MAR09 04APR09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11MANUF OF STATION TRANSFORMER

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:58

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 46 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 47: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

EC200 UNIT #1 - ERECTION OF ESP SERVICE TRANSFORMER 10 20APR09 29APR09

EC435 UNIT #1 - ERECT OF UNIT SERVICE TRANSF 15 20APR09 04MAY09

EC205 UNIT #1 - PRE-COMMG. OF ESP SERVICE TRANSF 10 30APR09 09MAY09

EC420 UNIT #1 - ERECT OF STATION SERVICE TRANSF 15 30APR09 14MAY09

EC455 ERECTION OF CT & PT SERVICE TRANSF 10 30APR09 09MAY09

EC495 ERECTION OF CHP SERVICE TRANSF 10 30APR09 09MAY09

EC400 UNIT #1 - ERECT - GENERATOR TRANSFORMER 35 22MAY09 25JUN09

U2EC416 UNIT #2 -ERECT OF STATION TRANSF 15 30MAY09 13JUN09

U2EC417 UNIT #2 - PRE-COMMG OF STATION TRANSF 5 14JUN09 18JUN09

EC410 UNIT #1 - ERECT OF UNIT AUXILIARY TRANSF 30 22JUN09 21JUL09

EC405 UNIT #1 - PRE-COMMG - GENERATOR TRANSF 30 26JUN09 25JUL09

U2EC200 UNIT #2 - ERECTION OF ESP SERVICE TRANSFORMER 10 19JUL09 28JUL09

EC415 UNIT #1 - PRE-COMMG OF UNIT AUXILIARY TRANSF 10 22JUL09 31JUL09

U2EC205 UNIT #2 - PRE-COMMG. OF ESP SERVICE TRANSF 10 29JUL09 07AUG09

U2EC420 UNIT #2 - ERECT OF STATION SERVICE TRANSF 15 29JUL09 12AUG09

U2EC435 UNIT #2 - ERECT OF UNIT SERVICE TRANSF 15 08AUG09 22AUG09

EC418 UNIT #1 - CHARGING OF STATION TRANSF 5 12AUG09 16AUG09

U2EC418 UNIT #2 - CHARGING OF STATION TRANSF 5 12AUG09 16AUG09

EC425 UNIT #1 - COMM OF STATION SERVICE TRANSF 10 22AUG09 31AUG09

EC505 COMM OF CHP SERVICE TRANSF 10 22AUG09 31AUG09

U2EC425 UNIT #2 - COMM OF STATION SERVICE TRANSF 10 22AUG09 31AUG09

EC210 UNIT #1 - CHARGING OF ESP SERVICE TRANSF 2 27AUG09 28AUG09

EC445 UNIT #1 - COMM OF UNIT SERVICE TRANSF 10 27AUG09 05SEP09

EC465 COMMISSIONING OF CT & PT SERVICE TRANSFORMER 10 27AUG09 05SEP09

U2EC210 UNIT #2 - CHARGING OF ESP SERVICE TRANSF 2 27AUG09 28AUG09

U2EC445 UNIT #2 - COMM OF UNIT SERVICE TRANSF 10 27AUG09 05SEP09

U2EC400 UNIT #2 - ERECT - GENERATOR TRANSFORMER 35 30AUG09 03OCT09

U2EC410 UNIT #2 - ERECT OF UNIT AUXILIARY TRANSF 30 22SEP09 21OCT09

U2EC405 UNIT #2 - PRE-COMMG - GENERATOR TRANSF 30 04OCT09 02NOV09

U2EC415 UNIT #2 - PRE-COMMG OF UNIT AUXILIARY TRANSF 10 22OCT09 31OCT09

EC406 COMMG - UNIT #1 GENERATOR TRANSF 1 31DEC09 31DEC09

U2EC406 COMMG - UNIT #2 GENERATOR TRANSF 1 31MAR10 31MAR10

CHIMNEYENGINEERINGEN600 SPECIFICATION - CHIMNEY 10 01JUL08 10JUL08

EN610 CIVIL DRG - CHIMNEY 45 11JUL08 24AUG08

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

SPECIFICATION - CHIMNEYCIVIL DRG - CHIMNEY

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:58

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 47 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 48: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

PROCUREMENTPR610 ORDERING - CHIMNEY CONSTRUCTION 45 11JUL08 24AUG08

PR620 MOBILIS. OF CHIMNEY CONTRACTOR 60 25AUG08 23OCT08

CIVILCH100 CHIMNEY FOUNDATION 65 10AUG08 13OCT08

CH110 CIVIL WORK - SHELL COMPLITION 190 24OCT08 01MAY09

CH120 CIVIL WORK - INTERNAL 160 22MAY09 28OCT09

CH122 FLUE DUCT READNESS 10 30AUG09 08SEP09

CH130 FINISHING WORKS INCLU. ELE. OF CHIMNEY 75 09SEP09 22NOV09

CH123 CHIMNEY READY FOR ID PRE COMMG. (INCLU BRICK LIN 0 16SEP09

CH125 CHIMNEY READY FOR BLU 0 28SEP09

RAW WATER SYSTEMENGINEERINGEN680 SPECIF - RAW WATER PUMPS 40 03AUG08 11SEP08

EN685 CIVIL DRG FOR RW PUMP FOUND 30 06DEC08 04JAN09

PROCUREMENTPR830 ORDERING OF RAW WATER PUMPS 45 12SEP08 26OCT08

PR845 ORDERING OF RAW WATER PIPING 60 30SEP08 28NOV08

PR835 MANUF OF RAW WATER PUMPS 150 27OCT08 25MAR09

PR850 MANUF & DISPATCH OF RW PIPING 45 29NOV08 12JAN09

PR840 DISPATCH OF RAW WATER PUMPS 20 26MAR09 14APR09

CIVILRW110 CIVIL WORKS FOR RW PIPING 100 29DEC08 07APR09

RW100 CIVIL WORKS FOR RW PUMP FOUND 60 14FEB09 14APR09

ERECTION & COMMISSIONINGEC820 ERECT OF RAW WATER PIPING 60 08APR09 06JUN09

EC810 ERECT OF RAW WATER PUMPS 30 15MAY09 13JUN09

EC830 COMMG OF RW PUMPS 15 14JUN09 28JUN09

PRE-TREATMENT PLANTENGINEERINGEN770 SPEC FOR PT PLANT 30 17JUL08 15AUG08

EN790 CIVIL DRG FOR PTP 30 05OCT08 03NOV08

EN792 FDN DRG FOR DM & CS TANKS 30 05OCT08 03NOV08

PROCUREMENTPR990 ORDERING OF PT PLANT 30 16AUG08 14SEP08

PR993 MNFG & DELIVERY OF PT PLANT 180 15SEP08 13MAR09

PR995 SUPPLY OF STEEL PLATES 60 30OCT08 28DEC08

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

ORDERING - CHIMNEY CONSTRUCTION

CHIMNEY FOUNDATION

SPECIF - RAW WATER PUMPS

SPEC FOR PT PLANT

ORDERING OF PT PLANT

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:58

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 48 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 49: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

CIVILPTP100 CIVIL WORKS OF CLARIFIER 120 20OCT08 16FEB09

PTP105 CIVIL CONSTN OF CHEMICAL HOUSE 180 04NOV08 02MAY09

PTP107 DM & CS TANK FOUNDATIONS 60 04NOV08 02JAN09

PTP110 CLARIFIER READY FOR MECH ERECTION 5 29DEC08 02JAN09

PTP103 CIVIL WORKS OF CWST 100 21MAR09 28JUN09

PTP130 CHEMICAL HOUSE READY FOR ERECTION 15 24MAR09 07APR09

ERECTION & COMMISSIONINGDEC955 FAB & ERE OF DM STORAGE TANK 90 29DEC08 28MAR09

EC940 ERECTION OF PT PLANT 45 14MAR09 27APR09

EC941 ERECTION OF PTP DOSING EQPT. 55 14MAR09 07MAY09

EC975 TANKS READY FOR RECEIVING DM WATER 5 29MAR09 02APR09

DEC960 ERECTION OF PTP MCC 20 05MAY09 24MAY09

EC961 PRE-COMMISSIONING OF PTP MCC 10 01JUN09 10JUN09

DEC965 CHARGING OF PTP MCC 2 11JUN09 12JUN09

EC945 COMMG OF PT PLANT 15 07JUL09 21JUL09

DEC967 DM WATER FOR BOILER HYDRAULIC TEST 5 21JUL09 25JUL09

COOLING WATER SYSTEMENGINEERINGEN710 SPEC - CW PUMPS 20 17JUL08 05AUG08

EN720 SPEC - ACW PUMPS 30 06AUG08 04SEP08

EN730 SPEC - CW PIPING 10 06AUG08 15AUG08

EN750 CW PIPING CIVIL DRGS 25 20SEP08 14OCT08

EN740 CIVIL DRG FOR CW PUMP FOUND 45 05OCT08 18NOV08

EN780 SSF CIVIL DRGS 20 14DEC08 02JAN09

PROCUREMENTPR860 ORDERING- C W PUMPS 30 06AUG08 04SEP08

PR920 ORDERING - CW PIPING 35 16AUG08 19SEP08

PR870 MANUFACTURING - C W PUMPS 240 05SEP08 02MAY09

PR890 ORDERING OF ACW PUMPS 60 15SEP08 13NOV08

PR930 MANUFACTURING OF CW PIPING 100 20SEP08 28DEC08

PR900 MANUFACTURING OF ACW PUMPS 160 14NOV08 22APR09

PR940 DISPATCH TO SITE - C W PIPING 20 29DEC08 17JAN09

PR910 DISPATCH TO SITE - A C W PUMPS 15 23APR09 07MAY09

PR880 DISPATCH TO SITE - C W PUMPS 15 03MAY09 17MAY09

CIVILCW130 CIVIL WORKS FOR CW PIPING 100 19DEC08 28MAR09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

SPEC - CW PUMPSSPEC - ACW PUMPS

SPEC - CW PIPING

ORDERING- C W PUMPSORDERING - CW PIPING

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:58

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 49 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 50: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

CW100 CIVIL WORKS OF C W PUMP FOUND 90 29DEC08 28MAR09

CW140 CIVIL WORKS FOR SSF 90 03JAN09 02APR09

CW150 SSF FOUND READY FOR ERECT 10 14MAR09 23MAR09

CW110 FOUND READY FOR CW PUMPS ERECT 10 13APR09 22APR09

ERECTION & COMMISSIONINGEC890 ERECTION OF CW PIPING 100 18JAN09 27APR09

EC916 ERECTION OF SSF 45 24MAR09 07MAY09

EC900 HYDROTEST OF CW PIPING 30 18APR09 17MAY09

EC850 ERECTION OF C W PUMPS 20 28MAY09 16JUN09

EC926 COMM OF SSF 10 13JUN09 22JUN09

EC860 COMMG. OF C W PUMPS 15 30AUG09 13SEP09

EC870 ERECTION OF ACW PUMPS 15 07SEP09 21SEP09

EC880 COMM. OF ACW PUMPS 8 04OCT09 11OCT09

I D COOLING TOWERENGINEERINGEN760 SPEC OF INDUCED DRAFT COOLING TOWER 20 16JUN08 05JUL08

PR980 DRG FOR COOLING TOWER 50 09SEP08 28OCT08

PROCUREMENTPR960 ORDERING OF INDUCED DRAFT COOLING TOWER 45 06JUL08 19AUG08

PR970 MFG & DELIVERY OF COOLING TOWER EQPT 210 20AUG08 17MAR09

CIVILCT100 CIVIL CONSTN. OF IDCT 350 09OCT08 23SEP09

CT110 IDCT READY FOR MECH ERECTION 60 06JUN09 04AUG09

ERECTION & COMMISSIONINGEC922 ERECTION OF LV SWGR FOR CT 30 05MAY09 03JUN09

EC920 MECH ERECTION OF IDCT 110 26JUN09 13OCT09

EC915 BASIN READYNESS FOR WATER CIRCULATION 5 25AUG09 29AUG09

EC924 COMMG OF LV SWGR FOR CT 5 06SEP09 10SEP09

EC930 COMMG OF IDCT 25 14OCT09 07NOV09

COMPRESSOR SYSTEMENGINEERINGEN800 SPEC FOR COMPRESSOR / DYIER / RECEIVER 30 08AUG08 06SEP08

EN830 CIVIL DRG FOR COMPRESSOR BUILD 60 06DEC08 03FEB09

EN840 SA RECEIVER CIVIL DRG 45 16DEC08 29JAN09

PROCUREMENTPR1050 ORDERING OF COMPRESSOR / DRIER / RECEIVER 40 07SEP08 16OCT08

PR1080 MANUF - COMPRESSOR / DRIER / RECEIVER 180 17OCT08 14APR09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

SPEC OF INDUCED DRAFT COOLING TOWER

ORDERING OF INDUCED DRAFT COOLING TOWER

SPEC FOR COMPRESSOR / DYIER / RECEIVER

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:58

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 50 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 51: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

PR1090 DISPATCH - COMPRESSOR / DRIER / RECEIVER 30 15APR09 14MAY09

CIVILCO100 CIVIL & STRL WORK OF COMPRESSOR BUILD 175 26DEC08 18JUN09

CO105 SA RECEIVER FOUNDATION 45 01MAR09 14APR09

CO110 COMPRESSOR FOUND READY FOR MECH ERECTION 10 10MAY09 19MAY09

CO120 AC PLANT FOUND READY FOR MECH ERECTION 5 15MAY09 19MAY09

ERECTION & COMMISSIONINGEC1030 SA RECEIVER ERECTION 30 10MAY09 08JUN09

EC1000 ERECTION OF AIR COMPRESSOR, DRIER & RECIEVER 60 09JUN09 07AUG09

EC1010 COMM OF AIR COMPRESSOR 5 12OCT09 16OCT09

EC1020 INST. AIR AVAILABLE 0 16OCT09

AC & VENTILATION SYSTEMENGINEERINGEN1130 SPEC- A/C & VENT SYS 30 28AUG08 26SEP08

PROCUREMENTPR1400 ORDERING - A/C SYSTEM 50 27SEP08 15NOV08

PR1420 ORDERING - VENTILATION SYSTEM 50 27SEP08 15NOV08

PR1410 MANUF & DISPATCH - A/C SYSTEM 200 06DEC08 23JUN09

PR1430 MANUF & DISPATCH - VENT SYSTEM 190 16DEC08 23JUN09

ERECTION & COMMISSIONINGEC1401 ERECT OF VENTILATION SYSTEM 130 05MAY09 11SEP09

EC1400 ERECT OF AC SYSTEM 110 24JUN09 11OCT09

EC1403 ERECT OF LV SWGR AC & VENT SYS 25 24JUN09 18JUL09

EC1404 COMM OF LV SWGR AC & VENT SYS 10 16SEP09 25SEP09

EC1410 COMM OF VENTILATION SYSTEM 18 26SEP09 13OCT09

EC1420 COMM OF AIR CONDITIONING SYS.-BLU 5 26SEP09 30SEP09

EC1440 COMM OF AIR CONDITIONING SYS.-SYN 10 12OCT09 21OCT09

COAL HANDLING SYSTEMENGINEERINGEN860 SPEC FOR CHP 25 18AUG08 11SEP08

EN870 CIVIL DRG FOR CHP 120 26NOV08 25MAR09

PROCUREMENTPR1150 ORDERING OF CHP 45 12SEP08 26OCT08

PR1160 MANUFACTURING OF CHP EQUIPMENTS 300 27OCT08 22AUG09

PR1170 DISPATCH OF CHP EQUIP 140 25APR09 11SEP09

CIVILCHP100 CIVIL WORKS OF CHP 350 24FEB09 08FEB10

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:58

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 51 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 52: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

ERECTION & COMMISSIONINGEC1150 FABRICATION & ERECTION OF CHP 185 15MAY09 15NOV09

EC1152 ERECTION OF LV SWGR CHP 30 02OCT09 31OCT09

EC1154 COMMISIONING OF LV SWGR CHP 5 01NOV09 05NOV09

EC1160 TRIAL RUN & COMMG OF CHP 25 16NOV09 10DEC09

ASH HANDLING SYSTEMENGINEERINGEN900 SPEC FOR ASH HANDLING PLANT 30 18AUG08 16SEP08

EN910 CIVIL DRG FOR ASH HANDLING PLANT 50 21DEC08 08FEB09

PROCUREMENTPR1200 ORDERING OF AHP 45 17SEP08 31OCT08

PR1210 MNFG & DISPATCH OF ASH HANDLING SYSTEM 250 01NOV08 08JUL09

CIVILAHP100 CIVIL WORK FOR AHP 200 10JAN09 28JUL09

AHP110 AHP FOUND READY FOR MECH ERECTION 40 30MAY09 08JUL09

ERECTION & COMMISSIONINGEC1200 ERECTION OF ASH HANDLING SYSTEM 200 28JUL09 12FEB10

EC1202 UNIT #1 - ERECTION OF BOT ASH HOPPER 45 01SEP09 15OCT09

EC1203 ERECTION OF LV SWGR AHP 25 16SEP09 10OCT09

EC1204 COMMISIONING OF LV SWGR AHP 5 11OCT09 15OCT09

EC1205 UNIT #1 - COMPLN OF BOT ASH HOPPER - BLU 7 16OCT09 22OCT09

EC1206 UNIT #1 - TESTING OF AHS FOR CF 10 05NOV09 14NOV09

U2EC1202 UNIT #2 - ERECTION OF BOT ASH HOPPER 45 01DEC09 14JAN10

U2EV1205 UNIT #2 - COMPLN OF BOT ASH HOPPER - BLU 7 15JAN10 21JAN10

U2EC1206 UNIT #2 - TESTING OF AHS FOR CF 10 13FEB10 22FEB10

FUEL OIL SYSTEMENGINEERINGEN915 SPEC FOR UNLOADING SYSTEM 25 11JUL08 04AUG08

EN920 CIVIL DRAWING 60 29SEP08 27NOV08

PROCUREMENTPR1220 ORDERING OF PLATES 45 05AUG08 18SEP08

PR1230 MANUF & DESPATCH OF PLATES 130 19SEP08 26JAN09

CIVILFOS120 CIVIL WORKS FOR TANK FARM AREA 75 29OCT08 11JAN09

FOS130 CIVIL WORKS FOR UNLOADING AREA 95 28DEC08 01APR09

FOS100 CIVIL WORKS FOR FUEL OIL PUMP SKID 60 07JAN09 07MAR09

FOS110 READYINESS OF SKID FOUND FOR ERECT 5 28MAR09 01APR09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

SPEC FOR UNLOADING SYSTEM

ORDERING OF PLATES

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:58

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 52 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 53: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

ERECTION & COMMISSIONINGEC1220 FABRICATION & ERECT OF FUEL OIL TANK 110 27JAN09 16MAY09

EC1230 ERECTION OF UNLOADING SYSTEM 45 02APR09 16MAY09

EC1232 ERECTION OF FUEL OIL MCC 15 05MAY09 19MAY09

EC1235 COMMISSIONING OF FUEL OIL MCC 5 11SEP09 15SEP09

EC1240 COMM OF FUEL OIL UNLOADING SYS 5 16SEP09 20SEP09

LP PIPINGENGINEERINGEN940 LAYOUT - LP PIPING - RW, SW, PW 25 05SEP08 29SEP08

EN930 LAYOUT - LP PIPING - ACW 25 13SEP08 07OCT08

EN950 LAYOUT - LP PIPING - AIR IA, SA 25 13SEP08 07OCT08

EN630 CIVIL DRGS FOR PIPE/CABLE RACK / TRENCHES / SLEE 30 08OCT08 06NOV08

PROCUREMENTPR1270 ORDERING - LP PIPING - RW, SW, PW 45 30SEP08 13NOV08

PR1250 ORDERING - LP PIPING - ACW 45 08OCT08 21NOV08

PR1290 ORDERING - LP PIPING - AIR IA, SA 45 08OCT08 21NOV08

PR650 ORDERING OF STRL STEEL FOR PIPE RACKS 60 22OCT08 20DEC08

PR1280 MFG & DELVY - LP PIPING - RM, SW, PW 100 14NOV08 21FEB09

PR660 DELIVERY TO SITE - STRUL STEEL FOR PIPE RACK 90 21NOV08 18FEB09

PR1260 MFG & DELVY - LP PIPING - ACW 110 22NOV08 11MAR09

PR1300 MFG & DELVY - LP PIPING - AIR IA, SA 90 27NOV08 24FEB09

CIVILPC100 FOUNDATIONS FOR PIPE RACKS 120 18OCT08 14FEB09

PC110 FABRICATION OF PIPE RACK STRUCTURE 100 16DEC08 25MAR09

PC120 ERECTION OF PIPE RACKS 100 30JAN09 09MAY09

ERECTION & COMMISSIONINGEC1250 LP PIPING ERECTION OF COMP AIR 50 26MAR09 14MAY09

EC1290 LP PIPING ERECTION OF RW, SW, PW 50 16JUN09 04AUG09

EC1270 LP PIPING ERECTION OF ACW 45 20AUG09 03OCT09

FIRE FIGHTING & DETECTION SYSTEMENGINEERINGEN1000 SPEC FOR FIRE FIGHTING & DETECTION SYS 35 28AUG08 01OCT08

PROCUREMENTPR1350 ORDERING OF FIRE FIGHTING & DETECTION SYS 45 01NOV08 15DEC08

PR1355 MANUF & DISPATCH - FIRE FIGHTING & DETECTION SYS 200 16DEC08 03JUL09

ERECTION & COMMISSIONINGEC1370 ERECTION OF FIRE FIGHTING SYS 200 26MAR09 11OCT09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:58

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 53 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 54: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

EC1375 ERECTION OF FIRE DETECTION & ALARM SYS 75 24JUL09 06OCT09

EC1371 COMMG. OF FIRE FIGHTING SYS - REQD FOR BLU 60 13AUG09 11OCT09

EC1377 COMMISSIONING OF FIRE DETECTION & ALARM SYS 20 07OCT09 26OCT09

EC1372 COMMG. OF FIRE FIGHTING SYS - REQD FOR SYN. 60 12OCT09 10DEC09

ELECTRICAL WORKSENGINEERINGEN1160 SPEC - HT & LT POWER CABLING 60 22OCT08 20DEC08

PROCUREMENTPR1480 ORDERING - HT & LT POWER CABLE 55 21DEC08 13FEB09

PR1482 MANUF & DISPATCH - HT & LT POWER CABLE 150 14FEB09 13JUL09

ERECTION & COMMISSIONINGEC1450 U#1 - LAY & TERMI - HT/LT POWER CABLE FOR BLU 120 25MAY09 21SEP09

EC1470 U#1 LAY & TERMI - HT/LT POWER CABLE FOR ROLL&SYN 120 14JUN09 11OCT09

U2EC1450 U#2 - LAY & TERMI - HT/LT POWER CABLE FOR BLU 140 18AUG09 04JAN10

U2EC1470 U#2 LAY & TERMI - HT/LT POWER CABLE FOR ROLL&SYN 150 28AUG09 24JAN10

INSTRUMENTATIONENGINEERINGEN1210 SPEC - DCS FOR BOP 30 23AUG08 21SEP08

EN1220 SPEC - SWAS 20 17SEP08 06OCT08

EN1240 SPEC FOR C&I INSTRUMENTS 30 17SEP08 16OCT08

EN1250 SPEC - INSTRUMENTATION CABLES 30 07OCT08 05NOV08

EN1230 SPEC FOR C&I ERECTION CONTRACT 30 22OCT08 20NOV08

PROCUREMENTPR1600 ORDERING OF DCS - BOP 65 27SEP08 30NOV08

PR1620 ORDERING - SWAS 60 07OCT08 05DEC08

PR1615 ORDERING C & I INSTRUMENTS 60 17OCT08 15DEC08

PR1632 ORDERING - INSTRUMENTS CABLE 60 06NOV08 04JAN09

PR1616 MANUF & DISPATCH TO SITE - C&I INSTRUMENTS 120 16DEC08 14APR09

PR1610 MANUF & DISPATCH TO SITE - DCS BOP 222 21DEC08 30JUL09

PR1630 MANUF & DISPATCH TO SITE - SWAS 140 05JAN09 24MAY09

PR1634 MANUF & DISPATCH TO SITE - INSTRUMENTS CABLE 120 05JAN09 04MAY09

ERECTION & COMMISSIONINGEC1720 UNIT #1 - ERECTION OF C&I INSTRUMENTS - BLU 120 13MAY09 09SEP09

U2EC1720 UNIT #2 - ERECTION OF C&I INSTRUMENTS - BLU 120 13MAY09 09SEP09

EC1726 UNIT #1 - LAYING & TER OF C&I CABLE - BLU 65 07JUL09 09SEP09

U2EC1726 UNIT #2 - LAYING & TER OF C&I CABLE - BLU 65 07JUL09 09SEP09

EC1725 U#1 - ERECTION OF C&I INSTRUMENTS - ROLL & SYNC 110 01SEP09 19DEC09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:58

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 54 of 55Date Revision Checked Approved

PDF created with pdfFactory Pro trial version www.pdffactory.com

Page 55: Cpp Project Schedule

ActivityID

ActivityDescription

Plan Dur

Plan Start

Plan Finish

U2EC1725 U#2 - ERECTION OF C&I INSTRUMENTS - ROLL & SYNC 120 02SEP09 30DEC09

EC1700 ERECTION & COMM - SWAS 45 17SEP09 31OCT09

EC1705 ERECTION OF BOP DCS 25 17SEP09 11OCT09

EC1710 POWER ON - BOP DCS 2 12OCT09 13OCT09

EC1727 U#1 - LAYING & TER OF C&I CABLE - ROLL & SYNC 55 26OCT09 19DEC09

U2EC1727 U#2 - LAYING & TER OF C&I CABLE - ROLL & SYNC 65 27OCT09 30DEC09

ROADS & DRAINSENGINEERINGEN1350 DWG RELEASE LAYOUT- ROADS & DRAIN SYS 85 26NOV08 18FEB09

CIVILRD100 CIVIL WORKS OF PLANT ROADS & DRAINS 270 19FEB09 15NOV09

2008MAR APR MAY JUN JUL AUG

3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11

© Primavera Systems, Inc.

Start Date 01MAR08Finish Date 17APR10Data Date 18MAR08Run Date 10SEP08 23:58

Early Bar

Float Bar

Progress Bar

Critical Activity

DAR7

2 X 80 MW CPP - DARIBA SMELTER COMPL

Classic Schedule Layout

Sheet 55 of 55Date Revision Checked Approved