DISTRICT WATERSHED DEVELOPMENT UNIT DAHOD
DETAILED PROJECT REPORT (DPR)
IWMP-15 (Dhapur) Limdi Medhari(2011-12)
PROJECT IMPLIMENTATION AGENCY
PROJECT DIRECTOR OF DISTRICT WATERSHED DEVELOPMENT UNIT, DAHOD
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 2
Declaration
Under Integrated Watershed Management Programme (IWMP) 2011-12, the Detailed Project Report (DPR) for the Limdi
Medhri cluster consisting of thirteen priority villages namely Amli, Charchoda, Devdha, Jesawada, Matva, Nandava, and
Nadhelav had been prepared based on priority map of district given by BISAG. The total project area proposed to be treated
under this cluster is 6544.9 hac with the total project cost 785.39 Lakhs & 233.065 Lakhs as conversion amount.
The DPR is successfully completed with joint efforts of District Watershed Development Unit (DWDU-Dahod) and Project
Implementation Agency (PIA). The PIA nominated from Gujarat State Watershed Management Agency (GSWMA) for IWMP-15
(Limdi Medhri) is Devgadh Bariya Forest Division.
The DPR is finally submitted to DWDU-Dahod for required corrections/amendments and for further procedures.
Project Director
District Watershed Development Unit, Dahod
Garbada- IWMP-15 (Limdi Medhri), District- Dahod
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 3
Declaration
Under Integrated Watershed Management Programme 2011-12, the DPR for IWMP-15 (Limdi Medhri) had been submitted by
PIA to DWDU-Dahod. The DPR is verified and necessary amendments were made to overcome technically limitations and to
carry out effective implementation.
The DPR is made online on website - http://www.ruraldev.gujarat.gov.in/ (Commissionerate of Rural Development Gujarat
State) and hereby put for the approval.
Project Director
District Watershed Development Unit
Dahod
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 4
Approval Letter
The Detailed Project Report of IWMP-15 (LimdiMedhari) prepared by DWDU - Dahod & PIA DWDU-Dahod had been designed
as per the New Common Guidelines, 2008.
It states briefly the need for implementing the watershed project in Limdi Medhri cluster and suggests the appropriate
solutions to overcome the water scarcity through holistic approach. It also put the emphasis on improving livelihood pattern
of the rural section.
I hereby approve the DPR of IWMP-15 (LimdiMedhari).
Chairman
District Watershed Development Unit, Dahod
&
District Development Officer
Dahod
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 5
Contents
CHAPTER 1 - PROJECT BACKGROUND ........................................................................................................................................................................ 12
1 1- PROJECT BACKGROUND ....................................................................................................................................................................................... 13
HISTORY – DAHOD ....................................................................................................................................................................................................... 13
Table no.1: Basic project information .......................................................................................................................................................................... 14
District's Population Information ................................................................................................................................................................................. 16
Climate .......................................................................................................................................................................................................................... 17
1.2 Area proposed to be treated .................................................................................................................................................................................. 18
Table no.2: Weightage of the project ........................................................................................................................................................................... 18
Table no.2.1: Criteria and weight-age for selection of watershed .............................................................................................................................. 18
Project type: Hilly /Other .............................................................................................................................................................................................. 20
Table no.3: Watershed information ............................................................................................................................................................................. 20
1.3 Other developmental projects/schemes running in the Nadhelav project ........................................................................................................... 20
Table no.4: Developmental programmes running in the project area ........................................................................................................................ 21
Table no. 5: Previous Watershed programmes in the project area............................................................................................................................. 21
CHAPTER 2 - PROJECT IMPLEMENTING AGENCY ...................................................................................................................................................... 23
2.1 Project Implementing Agency ................................................................................................................................................................................ 24
2.2 Roles and Responsibilities of the PIA as per New Common Guideline - 2008 ...................................................................................................... 24
2.3 About District Watershed Development Unit, as a PIA ......................................................................................................................................... 24
2.3.1 The organization and its objectives ...................................................................................................................................................................... 24
Table no. 6: PIA ............................................................................................................................................................................................................. 25
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 6
Table no. 7: Staff at PIA level ........................................................................................................................................................................................ 25
2.2.4.The organization and its objectives ...................................................................................................................................................................... 26
2.2.5 Programmes / Projects running in the district ..................................................................................................................................................... 26
2.3 SWOT Analysis of the PIA ....................................................................................................................................................................................... 26
Strength: ....................................................................................................................................................................................................................... 26
Weakness: ..................................................................................................................................................................................................................... 26
Opportunities: ............................................................................................................................................................................................................... 27
Threats: ......................................................................................................................................................................................................................... 27
CHAPTER 3 – BASIC INFORMATION OF THE PROJECT AREA .................................................................................................................................... 28
2.2.4 Field Visit at Garbada Project Area ........................................................................................................................... Error! Bookmark not defined.
3. DPR Process .............................................................................................................................................................................................................. 29
3.1 Geography and Geo-hydrology............................................................................................................................................................................... 29
3.1.1 Land Use Pattern .................................................................................................................................................................................................. 29
Table no. 8: Land use pattern ....................................................................................................................................................................................... 29
3.1.2 Soil type and topography ...................................................................................................................................................................................... 30
3.1.3 Topography .......................................................................................................................................................................................................... 30
Table no. 9: Soil type and topography ......................................................................................................................................................................... 30
Table no. 10: Flood and drought condition.................................................................................................................................................................. 31
Table no. 11.1: Soil Erosion .......................................................................................................................................................................................... 31
Table no. 11.2: Soil Salinity/Alkalinity (Salinity ingress)............................................................................................................................................ 32
Table no. 11.2: Soil Salinity/Alkalinity (Salinity ingress)............................................................................................................................................ 32
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 7
Table no. 11.3: Water logging Conditions .................................................................................................................................................................... 33
Table no. 11.3: Water logging Conditions .................................................................................................................................................................... 33
Table no. 12: Climatic conditions ................................................................................................................................................................................. 33
Table no. 13: Physiographic and relief......................................................................................................................................................................... 33
3.1.4 Land and Agriculture ........................................................................................................................................................................................... 34
Table no. 14: Land ownership details .......................................................................................................................................................................... 34
Table no. 17: Crop details ............................................................................................................................................................................................. 35
Table no. 18: Livestock ................................................................................................................................................................................................. 39
3.2 Socio – Economic Profile ........................................................................................................................................................................................ 39
3.2.1 Demographic Status ............................................................................................................................................................................................. 40
Table no. 19: Drinking water ....................................................................................................................................................................................... 40
Table no. 20: Details of Common Property Resources ................................................................................................................................................ 41
Table no. 21: Demographic information ...................................................................................................................................................................... 42
Table no. 22: Literacy rate............................................................................................................................................................................................ 43
Table no. 23: Migration details .................................................................................................................................................................................... 44
3.2.2 Migration Pattern: ................................................................................................................................................................................................ 44
Table no. 24: Poverty.................................................................................................................................................................................................... 45
Table no. 25: Village infrastructure ............................................................................................................................................................................. 45
3.2.3 Infrastructure Facilities: ....................................................................................................................................................................................... 46
Table no. 26: Facilities / HH assets .............................................................................................................................................................................. 47
Table no. 27: Per capita Income (In Rs.) ...................................................................................................................................................................... 47
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 8
Table no.28: Dependence on Forest/CPR .................................................................................................................................................................... 47
Table no.28: Dependence on Forest/CPR .................................................................................................................................................................... 47
3.3 Livelihood Pattern: ................................................................................................................................................................................................. 49
Table no. 29: Livelihood pattern (Occupational distribution) .................................................................................................................................... 49
CHAPTER 4 – WATERSHED ACTIVITIES PLANNED .................................................................................................................................................... 50
4. Watershed Activities ................................................................................................................................................................................................ 51
Table no. 30: Details of Scientific Planning and Inputs in IWMP projects .................................................................................................................. 51
Table no.31: Details of PRA Activities conducted in the project area ........................................................................................................................ 52
4.1 Problem tree analysis ............................................................................................................................................................................................. 53
4.2Object tree analysis ................................................................................................................................................................................................. 54
4.2 Institutions at Village Level .................................................................................................................................................................................... 55
4.2.1 Watershed Committee (WC) ................................................................................................................................................................................. 55
Table no. 32: Watershed Committee details ................................................................................................................................................................ 55
Table no. 33: SHG detail ............................................................................................................................................................................................... 61
4.2.3 User Group ............................................................................................................................................................................................................ 63
Table no. 34: UG detail ................................................................................................................................................................................................. 64
4.3 Physical activities to be undertaken under IWMP – 11 (Nadhelav Watershed) ........................................................ Error! Bookmark not defined.
4.3.1 Entry Point Activity (EPA) .................................................................................................................................................................................... 67
Entry Point Activities ........................................................................................................................................................ Error! Bookmark not defined.
Table no.35: Entry point activities (EPA) (All financial figures in lakh Rs.) ............................................................................................................... 67
Table no.37: Activities related to Surface water resources in the project areas (all financial figures in lakh Rs.) .................................................... 83
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 9
Table no.39: Details of activities related to livelihood, production system and micro- enterprise ........................................................................... 85
Table no. 40: Activities related to livelihoods by Self Help Groups (SHGs) in the project areas ................................................................................ 93
4.4 Vermi Composting unit for Nadhelav village ........................................................................................................................................................ 96
4.4.1 Introduction .......................................................................................................................................................................................................... 96
4.4.2 About the worms ................................................................................................................................................................................................... 96
4.4.3 Location ................................................................................................................................................................................................................ 96
4.4.4 Use ........................................................................................................................................................................................................................ 96
4.5 Components of a Commercial Unit......................................................................................................................................................................... 96
4.5.1 Sheds ..................................................................................................................................................................................................................... 96
4.5.2 Vermi-beds ............................................................................................................................................................................................................ 97
4.5.3 Land ...................................................................................................................................................................................................................... 97
4.5.4 Seed Stock ............................................................................................................................................................................................................. 97
4.5.5 Fencing ................................................................................................................................................................................................................. 97
4.5.6 Water Supply System ............................................................................................................................................................................................ 97
4.5.7 Machinery ............................................................................................................................................................................................................. 97
Table no. 41: Linkages developed at village level ........................................................................................................................................................ 98
Table no.42: Details of activities connected with vegetative cover in watershed works ......................................................................................... 103
Table no.43: Details of activities in the CPRs in the project areas ............................................................................................................................ 108
Table no. 45: Capacity Building plan .......................................................................................................................................................................... 111
Table no.46: Information, education and Communication Activities ....................................................................................................................... 112
CHAPTER 5 – BUGETING ............................................................................................................................................................................................ 113
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 10
Table no. 47: Budget at a glance for the project ........................................................................................................................................................ 114
Table no. 48: Village wise- component wise budget available under IWMP ............................................................................................................ 115
Table no. 49: Village wise gap in funds requirement ................................................................................................................................................ 115
Convergence Opportunities ....................................................................................................................................................................................... 115
Table no.50: Details of Convergence of IWMP with other Schemes ......................................................................................................................... 117
Table no. 51: Public-Private Partnership in the IWMP projects ............................................................................................................................... 118
CHAPTER 6 – EXPECTED OUTCOMES ....................................................................................................................................................................... 119
Table no. 52: Environmental Benefits........................................................................................................................................................................ 120
Table no. 53: Status of Drinking water ...................................................................................................................................................................... 120
Table no. 54: Details of Kharif crop area and yield in the project areas ................................................................................................................... 121
Table no. 55: Area under horticulture ....................................................................................................................................................................... 125
Table no. 56: Details of livestock in the project areas (for fluids please mention in liters, for solids please mention in kgs. and income in Rs.) . 126
Table no. 58: Details of seasonal migration from Project area ................................................................................................................................. 128
Table no.59: Per capita Income (In Rs) ...................................................................................................................................................................... 129
Table no. 61: Logical Framework analysis................................................................................................................................................................. 134
CHAPTER 7 – Quality and Sustainability Issues ........................................................................................................................................................ 135
7 Quality and Sustainability Issues ............................................................................................................................................................................ 136
7.1 Plans for Monitoring and Evaluation ................................................................................................................................................................... 136
7.2 Plans for Project management: ............................................................................................................................................................................ 137
7.3 Watershed Development Fund: ........................................................................................................................................................................... 137
7.4 User Charges: ........................................................................................................................................................................................................ 137
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 11
CHAPTER 8 – MAPS .................................................................................................................................................................................................... 138 Ground Water Map of Project Name: Nadhelav (Garbada)........................................................................................................................................................ 139
Land Use Map of Project Name: Nadhelav (Garbada) ................................................................................................................................................................ 140
River Water Body Map of Project Name: Nadhelav (Garbada) ................................................................................................................................................... 140
Slope Map of Project Name: Nadhelav (Garbada) ..................................................................................................................................................................... 141
Soil Map of Project Name: Nadhelav (Garbada) ............................................................................................................................... Error! Bookmark not defined.
Existing Structure / Baseline Map of Project Name: Nadhelav (Garbada).......................................................................................... Error! Bookmark not defined.
Action Plan Map of Village Name: Nadhelav (Nadhelav – Garbada) .................................................................................................. Error! Bookmark not defined.
Action Plan Map of Village Name: Amli (Nadhelav – Garbada) ......................................................................................................... Error! Bookmark not defined.
Action Plan Map of Village Name: Charchoda (Nadhelav – Garbada) ................................................................................................ Error! Bookmark not defined.
Action Plan Map of Village Name: Devdha (Nadhelav – Garbada) ..................................................................................................... Error! Bookmark not defined.
Action Plan Map of Village Name: Jesavada (Nadhelav – Garbada) ................................................................................................... Error! Bookmark not defined.
Action Plan Map of Village Name: Matva (Nadhelav – Garbada)....................................................................................................... Error! Bookmark not defined.
Action Plan Map of Village Name: Nandava (Nadhelav – Garbada) ................................................................................................... Error! Bookmark not defined.
Table no. 62: Abbreviations: ..................................................................................................................................................................................................... 143
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 12
CHAPTER 1 - PROJECT BACKGROUND
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 13
1 1- PROJECT BACKGROUND HISTORY – DAHOD Dahod District, also known as Dohad District, is located in Gujarat state in wastern India. The city of Dahod is the district's administrative headquarters. The district has an area of 3,642 KM2, and a population of 1, 636, 433 (2001 census), with a population density of 449 persons per KM2. Dahod District was created on 2nd October, 1997, and was formerly part of Panchmahal District. It's territory mostly consists of two former Princely State, namely Baria (Devgadh) and Sanjeli in addition to Fatepura Taluka of Sunth (Pampur) State, along with the two "eastern mahals" of Dahod and Jhalod from the former Panchmahals. It was 9.55% urban as of 2001 census.
The district is bounded by Panchmahal District to the west, Vadodara District to the south, Jhabua District and Alirajpur District of Madhya Pradesh State to the east and southeast respectively, and Banswara District of Rajasthan State to the north and northeast. The population of the district is mostly rural, and a majority of the district's residents are Tribals, mostly Bhils. Dahod District also has the second largest population of "Dawoodi Bohra" sect of Muslims in India.
The District of Dahod is further sub-divided into the following Talukas (Tehsils):-
1. Dahod 2. Jhalod 3. Devgadh Baria 4. Garbada 5. Limkheda 6. Fatepura 7. Dhanpur
The actual name is "Dohad", which later got transformed into Dahod. The Mughal Emperor Aurangzeb was born in a mosque within the fort of Dahod. There is a government polytechnic college since 1963 and it was started by Indian Prime Minister Mr. Moraraji Desai and now government degree engineering college is also there. The degree college is affiliated to Gujarat University.
As far as topography of the district is concerned Jhalod and Dahod are in plains. Normal slope is mainly in north of Jhalod and Fatepura Taluka and Steep slope is in Devgadh Baria, Dhanpur and Limkheda Taluka.
Geologically the Dahod district is composed of Rocks of Aravalli formation of Delhi systems. At some places Limestone and Basalt are exposed. The south, southwest and southeast part of Garbada, Dhanpur and Devgadh Baria Taluka comprises of metamorphic rocks like Granite, Phyllite, Schist, and Quartzite. The west portion of Limkheda Taluka is mainly composed of Quartzite rocks and North, Central and Southwest area covering Dahod & Jhalod is composed of Basalt and limestone. Rest of the area including Fatepura Taluka is composed of Phyllite and Quartzite rocks.
Geohydrologically, the Rocks of Dahod District have low porosity and permeability. In the district the compactness of rock formation increases with depth and overall yield in aquifers is low. In Dahod District water found at shallow depth i.e. 40 to 50 mts.
Limdi Medhri (IWMP - 15) project is situated in Dhanpur Taluka, of the Dahod District of Gujarat State. The project is a cluster of thirty four micro watersheds i.e, 5E1B8f2h, 5E1B8f2i, 5E1B8g2a, 5E1B8f3b, 5E1B8f3a, 5E1B8f2m, 5E1B8f2n, 5E1B8f3c, 5E1B8f3b, 5E1B8f2l, 5E1B8f2i, 5E1B8f2j, 5E1B8f2k, 5E1B8f2i, 5E1B8f2h, 5E1B8d2e, 5E1B8f2r, 5E1B8f2n, 5E1B8g2b, 5E1B8g2a, 5E1B8g2c, 5E1B8g2d , 5E1B8g1j, 5E1B8g2a , 5E1B8g1j, 5E1B8g2a, 5E1B8g1h, 5E1B8f2g, 5E1B8f2l,
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 14
5E1B8f2p, 5E1B8f2k, 5E1B8f2i, 5E1B8a3s, 5E1B8c2f , 5E1B8f3a, 5E1B8f3m, 5E1B8f2b, 5E1B8f2l, 5E1B8g2a, 5E1B8f3b, 5E1B8g1k, 5E1B8g1g, 5E1B8f2i, 5E1B8f2h, 5E1B8f2k. The total project area of the watershed is about 6544.9 hac. is proposed to be treated under Integrated Watershed Management Programme (IWMP).
The livelihood of the people of this area is primarily based on rain fed agriculture, labour work, agriculture labour work and animal husbandry. Mainly the people of this area are migrating to various cities to earn by doing Labour Work, viz. Agricultural Labour Work, Construction and Small Businesses to Rajkot, Valsad, Surat, Ahmedabad etc. places.
There are no irrigation facilities in the designated watershed area. Watershed may help for fodder development which will be helpful for animal husbandry. Due to less rain fall people had been migrated in various parts of Gujarat. To check the seasonal migration of the people, the main occupation farming is required to be strengthened.
Table no.1: Basic project information
Sl No. Name of the
project
Villages Gram Panchayats Taluka District Area of
the project
Area proposed to be treated
Total project cost PIA
Name Census code 1
IWMP 15(Limdi Medhri)
Ambli Menpur 180050131530000 Ambli Menpur
Dhanpur Dahod
963.56 819.03 98.28
Forest
144.53 2 Biliya 180050131670000 Biliya 265.71 225.85 27.10 39.86 3 Chari 180050131630000 Limdi Medhri 374.85 318.62 38.23 56.23 4 Dumka 180050131710000 Dumka 514.26 437.12 52.45 77.14 5 Kanakuwa 180050131810000 Biliya 201.16 170.99 20.52 30.17 6 Kantu 180050131760000 Kantu 950.61 808.02 96.96 142.59 7 Ladva Vad 1800501311560000 kotambi 112.66 95.76 11.49 16.9 8 Limdi Medhri 180050131540000 Limdi Medhri 1112.84 945.91 113.51 166.93 9 Nan Salai 180050131640000 Pipariya (To) 418.04 355.33 42.64 62.71
10 Pipariya (To) 180050131810000 Pipariya (To) 222.43 189.07 22.69 33.36 11 Rachhava 180050131570000 Rachhava 667.67 567.52 68.10 100.15 12 Sangasar 180050131680000 Biliya 223.27 189.78 22.77 33.49 13 Simamoi 180050131680000 Simamoi 620.32 527.27 63.27 93.05 14 Udhal Mahuda 180050131680000 Gumali 460.46 346.34 41.56 114.12 15 Ulkadar 180050131680000 Biliya 645.05 548.29 65.79 96.76
Total 7752.39 6544.9 785.39 1207.99
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 15
Figure1, Geographic location of Nadhelav Project
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 16
IWMP-15 (LIMDI MEDHRI)
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 17
District's Population Information Total seven talukas and 696 villages are covered in Dahod district. Total population of district is 16.35 lakh. (2001) Out of which men are 8.24 lakh and women are 8.11 lakh. Urban population is 1, 56,378.
No. Name of Taluka No. of Villages Population (2001) Literacy Ratio (in percentage) Geographical Area Woman Man Total 1 Dahod 86 368511 37.05 61.18 49.22 58190.69 2 Garbada 34 142391 22.91 49.67 36.30 23461.08 3 Dhanpur 90 131855 19.90 44.31 32.20 46638.71 4 D. Daria 87 208197 31.39 67.33 49.46 64480.86 5 Limkheda 152 239293 31.40 63.17 47.29 59718.48 6 Zalod 151 359759 33.43 58.49 46.04 79839.79 7 Fatepura 96 185368 33.39 62.16 47.81 30947.55
Total: 696 1635374 31.70 59.45 45.65 363277.20
Population of scheduled tribes in the newly formed Dahod district is 72 % and scheduled castes are 3 %. Urban population is 8 %, while percentage of rural population 92%.
Climate The climate of district is usually hot. This district is considered as rain fed area. The average rain of district is 739 mm. Sometimes rain delays and district has to face drought. It's very hot during March to June, while from November to February winter prevails in district
No. Year Dahod Garbada Dhanpur Devgadh Baria Limkheda Zalod Fatepura 1 1991 650 650 819 628 819 762 558 2 1992 549 549 742 616 742 742 678 3 1993 724 724 936 857 936 862 703 4 1994 1124 1124 1441 1380 1441 1376 1183 5 1995 441 441 400 570 400 691 814 6 1996 907 907 1207 1029 1207 1297 1925 7 1997 981 981 1250 1024 1250 820 1455 8 1998 715 715 546 795 840 1012 757 9 1999 352 338 330 402 411 633 506
10 2000 271 298 314 414 447 628 319
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 18
1.2 Area proposed to be treated Watershed Development Programme is selected on the basis of thirteen parameters namely (1.) Poverty Index, (2.) Percentage of SC/ST, (3.) Actual Wages, (4.) Percentage of small and marginal farmers, (5.) Ground water status, (6.) Moisture Index, (7.) Area under rain fed agriculture, (8.) Drinking water situation in the area, (9.) Percentage of degraded land, (10.) Productivity potential of the land, (11.) Continuity of another watershed that has already developed/treated, (12.) Cluster approach for plain (13.) Cluster approach for hilly terrain. Based on these thirteen parameter a composite ranking was been given to Chakliya watershed project as given in Table No. 2.
The total number of families under BPL is 4137, which is 80.47% of the total households of the village. Hence a score of 5 has been given. The percentages of (Schedule Tribes) STs in the village are about 99.1%, SCs are 0.89% to the total population. Hence a score of 10 has been given.
Rain fed agriculture forms the primary occupation of the village due to the fact that ground water is either unavailable or too deep to fetch and hence unfit for usage. In Chakliya project area there are more than 80% farmers are small and marginal hence the score of 10 has been given.
Table no.2: Weightage of the project Project name
Project type
Weightage Total:
IWMP - 15 (limadi
medhari) Other/Hilly
i ii iii iv v vi vii viii ix x xi xii Xiii
7.5 10 0 5 2 10 15 5 15 10 10 6 15 110.5 Table no.2.1: Criteria and weight-age for selection of watershed
Sr.No Criteria Maximum Score
Ranges & Scores
1 Poverty index (% of poor to population) 10 Above 80% (10) 80 to 50% (7.5) 50 to 20% (5) Below 20%
(2.5)
2 % of SC/ST population 10 More than 40% (10) 20 to 40% (5) Less than 20%(3)
3 Actual wages 5 Actual wages are significantly lower than minimum wages (5)
Actual wages are equal to or higher than minimum wages
(0) - -
4 % of small and marginal farmers 10 More than 80% (10) 50 to 80% (5) Less than 50% (3) -
5 Ground water status 5 Over exploited (5) Critical (3) Sub critical (2) Safe (0)
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 19
6 Moisture index/DPAP/DDP Block 15 -66.7 & below (15) DDP Block -33.3 to -66.6 (10) DPAP Block 0 to -33.2 (0) Non DPAP/DDP
Block -
7 Area under rainfed agriculture 15 More than 90% (15) 80 to 90% (10) 70 to 80% (5) Above 70%
(Rejected)
8 Drinking water 10 No source (10) Problematic village (7.5) Partially covered (5) Fully overed (0)
9 Degraded land 15 High – above 20% (15) Medium – 10 to 20% (10) Low – less than 10% of TGA (5) -
10 Productivity potential of the land 15
Lands with low production & where productivity can be
significantly enhanced with reasonable efforts (15)
Lands with moderate production & where
productivity can be enhanced with reasonable efforts (10)
Lands with high production & where productivity can be marginally enhanced with
reasonable efforts (5)
-
11 Contiguity to another
watershed that has already been developed/treated
10
Contiguous to previously treated watershed & contiguity within the microwatersheds in
the project (10)
Contiguity within the microwatersheds in the project
but non contiguous to previously treated watershed
(5)
Neither contiguous to previously treated watershed
nor contiguity within the microwatersheds in the project
(0)
-
12
Cluster approach in the plains (more than one contiguous
micro-watersheds in the project)
15 Above 6 micro-watersheds in cluster (15)
4 to 6 micro-watersheds in cluster (10)
2 to 4 micro-watersheds in cluster (5) -
13
Culster approach in the hills (more than one contiguous
micro-watersheds in the project)
15 Above 5 micro-watersheds in cluster (15)
3 to 5 micro-watersheds in cluster (10)
2 to 3 micro-watersheds in cluster (5) -
Total: 150 150 90 41 2.5
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 20
Project type: Hilly /Other Table no.3: Watershed information
Name of the project No. Of watersheds to be treated Name Of Village Watershed code Watershed
regime/type/order
IWMP 15(Limdi Medhri) 19
Ambli Menpur 5E1B8f2h
Micro-Watersheds
Biliya 5E1B8f2i Chari 5E1B8g2a, 5E1B8f3b, 5E1B8f3a Dumka 5E1B8f2m, 5E1B8f2n, 5E1B8f3c, 5E1B8f3b, 5E1B8f2l Kanakuwa 5E1B8f2i, 5E1B8f2j Kantu 5E1B8f2k, 5E1B8f2i, 5E1B8f2h, 5E1B8d2e Ladva Vad 5E1B8f2r, 5E1B8f2n Limdi Medhri 5E1B8g2b, 5E1B8g2a, 5E1B8g2c, 5E1B8g2d Nan Salai 5E1B8g1j, 5E1B8g2a Pipariya (To) 5E1B8g1j, 5E1B8g2a, 5E1B8g1h Rachhava 5E1B8f2g, 5E1B8f2l, 5E1B8f2p, 5E1B8f2k Sangasar 5E1B8f2i, 5E1B8a3s, 5E1B8c2f Simamoi 5E1B8f3a, 5E1B8f3m, 5E1B8f2b, 5E1B8f2l, 5E1B8g2a, 5E1B8f3b Udhal Mahuda 5E1B8g1k, 5E1B8g1g
Ulkadar 5E1B8f2i, 5E1B8f2h, 5E1B8f2k
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 21
1.3 Other developmental projects/schemes running in the Nadhelav project Table no.4: Developmental programmes running in the project area
Sl no Name of the programme/scheme Sponsoring
agency Objectives of the programme/scheme Year of commencement
Villages covered
Estimated number of beneficiaries
1 NREGS (National Rural Employment Guarantee Scheme) DRDA / NREGA
The main objective of this scheme is to provide 100 days employment to the local
people. 2005-2006 15
2 BRGF (Backward Region Grant Fund) DRDA The main objective of this scheme is to fulfil the missing link of the other rural schemes. 2008-2009 15 -
3 IAY (Indira Awas Yojna) DRDA Provides housing facility to BPL beneficiaries is the main objective of this scheme. - 15 -
4 Sardar Awas Yojna TASP / Takedari Provides housing facility to BPL beneficiaries. - 15 -
5 SGSY (Swarnjayanti Gram Swarojgar Yojna) DRDA
This scheme gives training, gives facilities to male and female by establishing a small
groups like SHG, UG etc. to the local villagers to make them capable to earn by growing
their capabilities.
- 15 -
6 IGNOAPS (Indira Gandhi National Old Age Pension Scheme) Zilla Panchayat In this scheme the government gives pension
to the old age peoples/villagers. - 15 -
7 Kuwarbai Nu Mameru SWO In this scheme government provides Rs. 5000 to BPL female during her marriage. - 15 -
8 Chiranjivi Yojna SWO This is a health care scheme to save girl child. - 15 -
9 Balika Samrudhi Yojna Jilla Panchayat In this scheme government gives female child the facilities like, bicycle, and scholarship to
get well educated. - 15 -
10 Vidhva Sahay Yojna Samaj Kalyan This scheme is mainly for widow women. The facilities provided by this scheme is like, cash
pension, etc. - 15 -
11 Ambedkar Awas Yojna To provide shelter or upgrade the existing
shelter for people living below poverty line in urban slums.
Jun-03 15 -
12 Sankat Mochan Yojna - 15 - 13 Pandit Dindayal Awas Yojna Zilla Panchayat Provides housing facility to BPL beneficiaries. - 15 -
14 Bajpai Bankebal Yojna Provides loan to unemployed educated peoples. 15 -
15 Tapak Sinchay Sahay Yojna Agriculture Department
In this scheme agricultural department gives irrigation facility to small / marginal farmers. - 15 -
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 22
Table no. 5: Previous Watershed programmes in the project area Sl no
Project name
Year Started Name of villages
No. Of micro
watershed
Watershed codes
Area under
treatment
Funding source
Nodal agency PIA Total
cost
Expenditure incurred up to start of IWMP
% financial completion
% physical completion
1 DPAP Back No-5
1999-00 Kanjeta
3 5E1B7 500
Govt. DRDA Dahod NGO
30 50.90 100.00% 100.00% Limdi mendri 500 30
Chorbaria 500 30
2 DPAP Block No-6
2000-01
Zabu
5 5E1B7
500
Govt. DRDA Dahod NGO
30
68.64 100.00% 100.00% Udar.Katu 500 30 Sangashar Kanakuva 500 30 Rachhava Dumaka 500 30
3 DPAP Block No-7
2001-02 Mador
2 5E1B7 500
Govt. DRDA Dahod NGO
30 32.90 97.92% 97.92% Kakdkhila 500 30
4 DPAP Block No-8
2002-03 Taram KachhGada
2 5E1B7 500
Govt. DRDA Dahod NGO
30 63.60 97.26% 97.26% Khokhara Khokhabed 500 30
5 DPAP Back No-9
2003-04
Rampur. Bogdava
4 5E1B7
500
Govt. DRDA Dahod
Taluka Panchayat Dhanpur
30
77.64 99.87% 99.87% Natki 500 30 Khalta Garabdi 500 30 Lakhanagujiya 500 30
6 DPAP Block No-10
2004-05
Pav.Adalvada
4
5E1B7c3f 500
Govt. DRDA Dahod
Taluka Panchayat Dhanpur
30
43.64 100.00% 100.00% Kodariya 5E1B7c3j 500 30 Khalta Garabdi 5E1B7a2k 500 30 Nanimalu 5E1B7b2c 500 30
7 DPAP Block No-11
2005-06
Bhidol
5
5E1B7b1b 500
Govt. DRDA Dahod
Taluka Panchayat Dhanpur
30
43.58 100.00% 100.00% Shimamoi.Chari 5E1B7c2f 500 30
5E1B7c2g 500 30 Gumli 5E1B7c2d 500 30 Panam 5E1B7c2j 500 30 Amali Menpur 5E1B7c3g 500 30
8 DPAP Block No-12
2006-07
Bhanpur.Kakdkhila
5
5E1B7a3e 500
Govt. DRDA Dahod
Taluka Panchayat Dhanpur
30
43.68 100.00% 100.00% VashiyaDugari.Gagdifdiya 5E1B7a3g 500 30 Bhorva 5E1B7f1h 500 30 Tokarva.Nanshlai 5E1B7fs 500 30 Vakota.Kalakhut 5E1B7fg 500 30
Total: 30 - 15000 - - - 900 424.58 99.38% 99.38%
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 23
CHAPTER 2 - PROJECT IMPLEMENTING AGENCY
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 24
2.1 Project Implementing Agency The Project Implementation Agency (PIA) is selected by an appropriate mechanism by Gujarat State Watershed Management Agency (GSWMA), the State Level Nodal Agency (SLNA) for Integrated Watershed Management Programme (IWMP) in Gujarat. The PIA is responsibl e for implementation of watershed project. This PIA may include relevant line department, autonomous organizations under State/ Central Government, Government Institutes/ Research bodies, Intermediate Pa nchayats, Voluntary Organizations (VOs). The PIA of IWMP-11 (Nadhelav) watershed project is Project Director, District Watershed Development Unit, Dahod.
2.2 Roles and Responsibilities of the PIA as per New Common Guideline - 2008 The Project Implementing Agency (PIA) will provide necessary technical guidance to the Gram Panchayat for preparation of development plans for the watershed through Participatory Rural Appraisal (PRA) exercise, undertake community organization and training for the village communities, supervise watershed development activities, inspect and authenticate project accounts, encourage adoption of low cost technologies and build upon indigenous technical knowledge, monitor and review the overall project implementation and set up institutional arrangements for post-project operation and maintenance and further development of the assets created during the project period. PIA, after careful scrutiny, shall submit the Action Plan for Watershed Development Project for approval of the DWDU/DRDA and other arrangements. (As per Para - 38)
The PIA shall submit the periodical progress report to DWDU. The PIA shall also arrange physical, financial and social audit of the work undertaken. It wil l facilitate the mobilization of additional financial resources from other government programmes, such as NREGA, BRGF, SGRY, National Horticulture Mission, Tribal Welfare schemes, Artificial Ground Water Recharging, Greening India, etc. (As per Para - 39)
2.3 About District Watershed Development Unit, as a PIA 2.3.1 The organization and its objectives
The District Watershed Development Unit (DWDU), Dahod is a district level nodal agency and was set up on 10th January, 2009 to oversee for the smooth imple mentation of watershed projects in the district. The District Development Officer (DDO) is the chairman of the DWDU. The DWDU has dedicated and experienced staff comprising one Project Director (Deputation from Gujarat Forest Department); two Technical Experts (on contractual basis) and Multidisciplinary Team (MDT) of civil Engineer, agriculture expert, and community mobilization expert, surveyor and computer operator. The remaining staff i.e. MIS coordinator, system analyst and accountant will be recruited for administration work. The DWDU Dahod staffs are temporarily located at DRDA Bhavan, Near District Panchayat Dahod, Zalod Road, Dahod.
The objective of the DWDU Dahod are surveying, planning, implementing, documenting, and promoting watershed development projects and related development activities in the district. Moreover, the DWDU Dahod will work as a PIA for some IWMP projects.
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 25
Table no. 6: PIA Sl. No. Names of project Details of PIA
1 Limdimedhari
(i) Type of organization Deputy Conservator of Forest (ii) Name of organization Shri A.C. JAAIN (iii) Designation & Address Deputy Conservator of Forest Dev. Baria (iv) Telephone 02678-220425 (v) Fax 02678-220425 (vi) E-mail [email protected]
Table no. 7: Staff at PIA level Sl no Name Age Sex Designation Qualification Experience Job assigned Monthly remuneration
1 Rathva Natavarbhai .M 55 M WDT(Agri) B.R.S. 1 Years 17/07/2012 8000/- 2 Rathva Sarjansinh .N 35 M WDT(CM) B.R.S. 6 Year 3/10/2012 11000/- 3 Bariya Amitaben . R 30 F WDT( Accountant ) B.COM 8 Year 3/10/2012 7000/- 4 Solanki Kishorkumar G. 30 M WDT( DEO ) B.A. PGDCA 0 9/3/2012 6000/-
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 26
2.2.4.The organization and its objectives The District Watershed Development Unit (DWDU), Dahod is district level nodal agency and was established as per GSWMA’s member Secretary and Secy. R D Gujarat State Gandhinagar’s order No. GVK/WSD/GSWMA/54-79 Dt. 1/05/2008, No. 84-119 Dt. 1/05/2008 and No. 111-115 Dt. 5/05/2008 Dahod district have formed District Watershed Development Unit, Dahod by Chairman’s Order No. DWDU/CELL/3271 to 3291/2008 Dt. 1/01/2009.
Present working status of watershed branch under DRDA has been converted into DWDU, and Sitting near DRDA in separate office. The necessary staffs are recruited. The required infrastructure is developing.
The object of the DWDU Dahod is supervising, planning, implementing, documenting, promoting watershed development projects, and mainly focusing on the things like,
- To stop the migration of village tribal people, - To stop erosion of land, - To develop the irrigation sources in well manner, - To provide healthy drinking water, and - To increase the lively hood of the village tribal people.
2.2.5 Programmes / Projects running in the district At present five IWMP projects has been sanctioned by Government of India for the Dahod district. The entry point activities of all the five IWMP projects have identified by the respective PIAs in the district. Devgadh Bariya Forest Division as a PIA for the five projects (IWMP 1 to 5).
2.3 SWOT Analysis of the PIA Strength:
- Dedicated and experience staffs and multidisciplinary team. - Independent District Level Nodal Agency. - Strong linkages with national and state level institutions, agricultural universities, North Gujarat University and NGOs for capacity building and technical
guidance. - Scientific planning in watershed projects with the help of BISAG, Gandhinagar. - District level monitoring, coordination & cooperation committee. - Well establishment of PRIs for social audits.
Weakness: - Insufficient funds for complete watershed projects per hectare
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 27
- No permanent staff - No permanent office building - No technical equipments facilities - No vehicle or TA is given to surveyor to perform job speedily
Opportunities: - Sustainable livelihood generation landless and asset less - Improvement of socio-economic status of poor - Awareness generation among the illiterates through IEC activities by usage of new ICT activities - Usage of new technologies of watershed modelling and GPS for monitoring the watershed activities
Threats: - Lack of sustainable agriculture development - Delay of releasing project fund from the higher authority - Lack of contribution and cooperation from local peoples - Low and irregular rainfall in the project area - Low literacy rate in the project area - Low availability of Water/Canal/Irrigation Sources - High migration ratio - Low land productivity, erratic and an even distribution of rain. - Undulating , hilly terrain
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 28
CHAPTER 3 – BASIC INFORMATION OF THE PROJECT AREA
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 29
3. DPR Process First village visit then village meeting, Transits walk, PRA (Participatory Rural Appraisal), WDC Formation, Bas e line survey, Net Planning, SHG, UG Formation, DPR preparation
3.1 Geography and Geo-hydrology
3.1.1 Land Use Pattern The net geographical area of the project Nadhelav(IWMP – 11) is 7097.14 ha. The total forest area is about 29.68% which is under cultivation under Nadhelav project and completely rain fed. The Kharif crop is mainly taken in the project area.
Table no. 8: Land use pattern
Sr. No. Names of villages Geographical
Area of the village
Forest Area Land under agricultural use Rainfed area Perm-anent
pastu-res Wasteland
Cultivable Non-cultivable 1 Ambli Menpur 963.56 521.11 277.2 129.73 1.35 25.85 8.32 2 Biliya 265.71 144.71 26.44 27.7 1.13 40.86 24.87 3 Chari 374.85 165.87 95.42 25.96 1.18 49.21 37.21 4 Dumka 514.26 211 104.25 98.25 0.71 52.23 47.82 5 Kanakuwa 201.16 145.1 28.755 31.76 0.82 1.862 1.87 6 Kantu 950.61 699.23 90.35 86.7 0.98 37.6 35.75 7 Ladva Vad 112.66 23 32.6 28.67 1.99 14.2 12.2 8 Limdi Medhri 1112.84 612.87 184.98 172.99 1.2 72.4 68.40 9 Nan Salai 418.04 201.82 88.87 30.35 1.73 49.61 45.66
10 Pipariya (To) 222.43 53.54 79.5 75.88 1.56 6.9 5.05 11 Rachhava 667.67 391.39 65.45 60.32 1.16 78.55 70.8 12 Sangasar 223.27 0 54.9 51.02 1.62 60.86 54.87 13 Simamoi 620.32 130.11 130.5 120.82 1.68 121.5 115.71 14 Udhal Mahuda 407.46 310.21 28.6 20.64 2.29 25.52 20.2 15 Ulkadar 645.05 608.82 12.1 6.21 1.04 11.2 5.68
Total 7699.89 4218.78 1299.915 967 20.44 648.352 554.408
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 30
3.1.2 Soil type and topography Nadhelav watershed project falls in Western/Southern Hills of Gujarat Agro-climatic zone. The soil is mainly Lateride, Calcareous, and Loamy. The soil is dark brown and black cotton in surface colour. The depth of soil is moderate to deep about 36 to 48 cm. The predominant texture of soil is loamy sand and silt and clay. The soil fertility is poor with low nitrogen, phosphorus and potash. The topography of the area is hilly with undulating plains and steep slopes ranging from 0 to 16% slope.
3.1.3 Topography Topography includes the physical features of the earth like altitude, slope, exposure, mountain chains, valleys, plains, etc.
Table no. 9: Soil type and topography
Sr no Village Flood (Incidence) Drought (Incidence)
1 Ambli Menpur
Not Affected 5 Years
2 Biliya 3 Chari 4 Dumka 5 Kanakuwa 6 Kantu 7 Ladva Vad 8 Limdi Medhri 9 Nan Salai
10 Pipariya (To) 11 Rachhava 12 Sangasar 13 Simamoi 14 Udhal Mahuda 15 Ulkadar
# Flat, undulating, moderate slope, Steep slope
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 31
Table no. 10: Flood and drought condition Sl no Village Flood (Incidence) Drought (Incidence)
1 Ambli Menpur
Not Affected 5 Years
2 Biliya 3 Chari 4 Dumka 5 Kanakuwa 6 Kantu 7 Ladva Vad 8 Limdi Medhri 9 Nan Salai
10 Pipariya (To) 11 Rachhava 12 Sangasar 13 Simamoi 14 Udhal Mahuda 15 Ulkadar
Table no. 11.1: Soil Erosion
Cause Type of erosion Area affected (ha) Run off Average soil loss (Tonnes/ ha/
year) (mm/ year)
Water erosion a Sheet
579.8
10
b Rill 10 c Gully 90 d Ravenous
Sub-Total 100 _ Wind erosion _
Total 100 579.8
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 32
Table no. 11.2: Soil Salinity/Alkalinity (Salinity ingress)
Sr.no Name of the Village Survey Number Soil pH Type of Salinity (Inherent/Ingress)
1 Ambli Menpur 278/2 7.1 0.16 161 7.1 0.19
2 Biliya 5 7.2 0.17
3 Chari 24/2 7.1 0.17 120 6.9 0.20 147 6.8 0.11
4 Dumaka 105 7.9 0.19
9 7.7 0.22 290 7.4 0.3
5 Kanakuva 7 7.6 0.13 11 7.2 0.12
6 Kantu
41 7.3 0.13 55 7.9 0.11
11p/1 7.8 0.13 65 7.4 0.14
7 Ladvavad 18 704 0.9
17/3 7.2 0.12 30 7.3 0.19
8 Limdimendhari
44 6.15 0.15 8 6.15 0.16
214/3 6.15 0.14 207/1 6.15 0.24
9 Nansalay 81 6.7 0.20 4 6.5 0.17
10 Pipriya 13 6.33 0.13
49/4 6.33 0.24 15 6.33 0.15
11 Rachhva 4 7.2 0.15 10/1 7.1 0.10
12 Sangasar 4 7.1 0.15 13 7.3 0.17
13 Simamoi 36/2 7.7 0.12
74 7.4 0.13 302/1 7.1 0.19
14 Udhalmahuda 1 7.1 0.21 5 7.1 0.19
15 Ulkadar 3 6.9 0.18 7 6.9 0.19
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 33
Table no. 11.3: Water logging Conditions
Name of the Village Survey Number Reasons Ambli Menpur
N/A Undual condition
Biliya Chari Dumka Kanakuwa Kantu Ladva Vad Limdi Medhri Nan Salai Pipariya (To) Rachhava Sangasar Simamoi Udhal Mahuda Ulkadar
Table no. 12: Climatic conditions Name of project Average rainfall- last 5 years Average temperature (celsius)
Limdi Medhri 1609 Summer Winter
Max Min Max Min 43 32 28 6
Table no. 13: Physiographic and relief
Project name Elevation Slope range (%) Major streams
Limdi Medhri Hilly 0 to 90 Panam
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 34
3.1.4 Land and Agriculture The area is completely dependent on rainfall. The rainfall is highly lacking in amplitude or quality which has resulted in recurrent phenomenon of draught. The average rainfall of this area is about 865 mm (according to the previous five year data). The rainy days area less than 40, this mismatched diffusion is directing to runoff of soil every year to the streams and a small streams.
Lack of surface water source and unavailability of ground water has decreased irrigation and drinking water. The average land holding is about 1 ha. Lack of irrigation source forces the majority of these farmers to migrate to ensure their livelihood. That affects directly the demographic profile of the village. The major crops cultivated in the area are Maize, Paddy, Soyaben, Wheat, Pigeon Pea and Gram in the village. If rain is good and proper irrigation source is available then the farmer can takes Rabi crops viz. Wheat and Gram in good quantity.
Table no. 14: Land ownership details
Sr. No Village Total owned land
HHs giving land on lease HHs taking land on lease Gen OBC SC ST
1 Ambli Menpur 0 14 2 311 0 0 2 Biliya 0 0 0 107 0 0 3 Chari 0 40 0 137 0 0 4 Dumka 0 0 0 345 0 0 5 Kanakuwa 0 0 0 67 0 0 6 Kantu 0 4 0 20 0 0 7 Ladva Vad 0 5 0 45 0 0 8 Limdi Medhri 0 328 0 89 0 0 9 Nan Salai 0 73 0 52 0 0
10 Pipariya (To) 0 8 2 98 0 0 11 Rachhava 0 0 0 172 0 0 12 Sangasar 0 0 0 94 0 0 13 Simamoi 0 267 0 24 0 0 14 Udhal Mahuda 0 0 0 21 0 2 15 Ulkadar 0 5 0 35 0 0
Total 0 342 0 1617 0 2
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 35
Table no. 15: Agriculture Sr. No. Village Net shown area
One time Two times Three times 1 Ambli Menpur 277.2 85 15 2 Biliya 55.27 10 0 3 Chari 122.56 35 0 4 Dumka 203.21 65 3 5 Kanakuwa 52.33 3 0 6 Kantu 178.03 15 0 7 Ladva Vad 28.39 7 0 8 Limdi Medhri 359.17 93 1 9 Nan Salai 120.95 25 1
10 Pipariya (To) 156.94 37 1 11 Rachhava 126.93 33 2 12 Sangasar 107.54 6 0 13 Simamoi 253 34 2 14 Udhal Mahuda 48.01 7 0 15 Ulkadar 19.35 8 0
Table no. 16: Irrigation
Sr. No. Village Source 1 : Canal Source 2 : Check dam / Pond Source 3 : Well
Availability months Net area Gross area Availability
months Net area Gross area Availability months Net area Gross area
1 Ambli Menpur 7 35 23 0 0 0 4 56.34 35 2 Biliya 0 0 0 0 0 0 3 9.4 5 3 Chari 0 0 0 2 8 6 4 20.58 15 4 Dumka 0 0 0 2 8 5 3 14 10 5 Kanakuwa 0 0 0 0 0 0 2 10.07 2 6 Kantu 0 0 0 0 0 0 2 16.08 12 7 Ladva Vad 0 0 0 0 0 0 4 9.21 7 8 Limdi Medhri 0 0 0 3 15 11 3 26.79 15 9 Nan Salai 0 0 0 4 19 12 3 13.02 9
10 Pipariya (To) 4 15 11 3 3 1 3 18.32 12 11 Rachhava 0 0 0 3 7 3 2 18 13 12 Sangasar 0 0 0 0 0 0 4 20.32 15 13 Simamoi 0 0 0 2 10 7 3 44 36 14 Udhal Mahuda 0 0 0 4 3 1 3 33.51 27 15 Ulkadar 0 0 0 0 0 0 2 8.2 5
Total: 0 0 0 23 73 46 45 317.84 218
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 36
Table no. 17: Crop details
Sr. No Village
Kharif (Monsoon) Crop 1 (Maize) Crop 2 (Paddy) Crop 3(Pigeon pea)
Area (Ha) Production(Kg) Productivity
(Kg/Ha) Area (Ha)
Production (Kg)
Productivity (Kg/Ha)
Area (Ha)
Production (Kg)
Productivity (Kg/Ha)
1 Ambli Menpur 170 243.6 1.43 60 60 0.92 10 3.6 0.30 2 Biliya 20 30.0 1.50 5 92.1 1.01 0 0 0.00 3 Chari 45 60.8 1.35 40 32 0.91 5 2.8 0.28 4 Dumka 65 97.5 1.50 30 21.5 0.93 18 2.24 0.28 5 Kanakuwa 16 23.0 1.44 5 30.6 1.00 6 1.56 0.26 6 Kantu 62 80.6 1.30 19 48.4 0.85 11 4.41 0.21 7 Ladva Vad 21 29.4 1.40 3 45.6 0.86 8 4 0.20 8 Limdi Medhri 95 118.8 1.25 42 35 0.88 47 4.42 0.26 9 Nan Salai 38 53.2 1.40 30 49 0.87 20 4.5 0.30
10 Pipariya (To) 39 50.7 1.30 31 15 0.88 9 1.5 0.30 11 Rachhava 35 46.7 1.33 20 0.8 0.80 15 0.14 0.14 12 Sangasar 37 51.8 1.40 10 75 0.88 7 4.5 0.30 13 Simamoi 70 87.5 1.25 40 42.4 0.90 20 3.6 0.30 14 Udhal Mahuda 17 28.9 1.70 7 20 0.80 4 0.8 0.20 15 Ulkadar 7 6.3 0.90 3 10 0.40 2 0.6 0.10
Total: 737 1008.657 20.453 345 577.4 12.9 182 38.67 3.43
Sr No Village
Rabi (Winter) Crop 1 (Maize) Crop 2 (Wheat) Crop 3 (Gram)
Area (Ha) Production(Qtl) Productivity
(Kg/Ha) Area (Ha) Production Productivity
(Kg) Area (Ha) Production Productivity (Kg)
1 Ambli Menpur 70 223.521 1.243 61 16400 0.269 21 8.00 0.400 2 Biliya 1 22.514 1.2 5 14827 2.965 0.00 0.000 3 Chari 35 45.111 1.15 20 9993 0.500 5 8.80 0.440 4 Dumka 55 82.14 1.3 5 9993 1.999 10 3.60 0.400 5 Kanakuwa 0 10.255 1.027 5 1600 0.320 0 2.00 0.500 6 Kantu 0 67.515 1.152 10 10500 1.050 0 4.56 0.380 7 Ladva Vad 10 29.4 1.24 5 29805 5.961 1 4.68 0.360 8 Limdi Medhri 35 94.412 1.25 15 7060 0.471 17 2.20 0.440 9 Nan Salai 15 46.141 1.4 7 18400 2.629 3 4.00 0.444
10 Pipariya (To) 25 45.417 1.3 5 8993 1.799 0 2.20 0.440 11 Rachhava 22 42.545 1.333 15 1200 0.080 12 0.80 0.800 12 Sangasar 0 46.254 1.18 8 0 0.001 25 12.00 0.480 13 Simamoi 41 73.545 1.155 9 9400 1.044 5 4.68 0.360 14 Udhal Mahuda 5 21.555 1.525 2 1700 0.850 2 0.40 0.100 15 Ulkadar 2 4.526 0.755 2 4000 2.000 0 0.60 0.200
Total: 316 854.851 18.21 174 143871 21.94 101 58.52 5.744
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 37
Sr No Village
Zaid (Summer) Crop 1(Water Melon) Crop 2(Vegetable) Crop 3
Area (Ha) Production(Kg) Productivity(Kg) Area
(Ha) Production Productivity (Kg)
Area (Ha) Production Productivity
(Kg) 1 Ambli Menpur 0 0 0 2 312 206 2 Biliya 0 0 0 0 0 0 3 Chari 0 0 0 1 150 112 4 Dumka 0 0 0 1 170 117 5 Kanakuwa 0 0 0 0 0 0 6 Kantu 0 0 0 0 0 0 7 Ladva Vad 0 0 0 0 0 0 8 Limdi Medhri 0 0 0 1 175 121 9 Nan Salai 0 0 0 0 0 0
10 Pipariya (To) 0 0 0 0 0 0 11 Rachhava 0 0 0 0 0 0 12 Sangasar 0 0 0 0 0 0 13 Simamoi 0 0 0 1 135 109 14 Udhal Mahuda 0 0 0 0 0 0 15 Ulkadar 0 0 0 0 0 0
Total: 0 0 0 6 942 665
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 38
Maize, Paddy (Danger), Soyaben, Pigeon Pea, Wheat, Gram, Black gram etc. are the crops in Jhalod Taluka (Chakliya Watershed). Crop details are well illustrated in Table No. 17 (Kharif, Rabi and Zaid). Crops area production and productivity are seasonal.
Kharif (Monsoon)
Ravi (winter)
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 39
Table no. 18: Livestock
Sr. No. Village
Buffalo Cow Total Milk (Buffalo+Cow) Goat Sheep Bullock Hen Others
No. milk No. Milk No. No Milk No. No. No. Donky 1 Ambli Menpur 59 12628 219 9482 22110 456 9531 0 276 230 0 2 Biliya 372 83201 100 4512 87713 226 5756 0 463 694 0 3 Chari 69 12473 83 4131 87713 233 5345 0 99 438 0 4 Dumka 161 31864 212 10221 42085 433 8462 0 565 904 0 5 Kanakuwa 37 9361 35 1482 10843 87 2175 0 80 288 0 6 Kantu 34 7206 24 1086 8292 40 760 0 59 952 0 7 Ladva Vad 15 3224 18 846 4070 41 762 0 56 520 0 8 Limdi Medhri 157 31467 241 11462 42929 557 11345 0 898 916 0 9 Nan Salai 68 11532 82 4168 15700 167 3955 0 331 798 0
10 Pipariya (To) 48 9265 62 2945 12210 130 3178 0 143 946 0 11 Rachhava 34 6428 36 1452 7880 162 3421 0 135 508 0 12 Sangasar 154 33429 47 2186 35615 216 4213 0 508 272 0 13 Simamoi 105 21483 212 8465 29948 434 8471 0 673 540 0 14 Udhal Mahuda 30 5429 12 384 5813 28 682 0 49 98 0 15 Ulkadar 14 2925 15 482 3407 36 846 0 89 70 0
Total: 1357 281915 1398 63304 416328 3246 68902 0 4424 8174 0 The project area has about 1398 cows and 1357 buffaloes out of which majority are local breed; there are 4424 bullocks, 68902 Goats, 8174 Hen. Majority of Adivasi community depends on Goat, Cow and Buffaloes rearing for their livelihood. Lack of rain and surface water has reduced the fodder and pasture area for their animals. This leads to heavy migration to other parts of the state with their family members and due to this animal husbandry is poor. The productivity of the milching animals is too low.
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 40
3.2 Socio – Economic Profile
3.2.1 Demographic Status
Table no. 19: Sr. No. Village Ground water table
(mt) Source of drinking water Availability in months Quality
1 Ambli Menpur 30-35
Open Well, Private Well, Handpump
10-12 Good
2 Biliya 45-50 6-8 Poor
3 Chari 30-35 8-10 Average
4 Dumka 30-35 8-10 Average
5 Kanakuwa 45-50 6-8 Poor
6 Kantu 45-50 6-8 Poor
7 Ladva Vad 35-40 9-11 Average
8 Limdi Medhri 30-35 8-10 Average
9 Nan Salai 30-35 8-10 Average
10 Pipariya (To) 30-35 8-10 Average
11 Rachhava 30-35 10-12 Good
12 Sangasar 45-50 6-8 Poor
13 Simamoi 30-35 10-12 Good
14 Udhal Mahuda 30-35 10-12 Good
15 Ulkadar 30-35 10-12 Good
Drinking water Limdi Medhari watershed project mainly covers Ambli Menpur, Biliya, Chari, Dumka, Kanakuwa, Kantu, Ladva Vad, Limdi Medhri, Na
Salai, Pipariya(To), Ranchhava, Sangasar, Simamoi, Udah Mahuda and Ulkadar villages which comprises of 29396 Population. Total Literacy is 35.96, Out of which Male Literacy rate is 40.24 and female literacy rate as low as 31.49 per cent.
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 41
Table no. 20: Details of Common Property Resources
S. No. Names of project
CPR Particulars
Total Area (ha) Area available for treatment (ha) Area owned/ In possession of
Pvt. persons
Govt.
PRI
Any other
(Pl. Specify)
Pvt. persons
Govt.
PRI
Any other
(Pl. Specify)
(specify deptt.)
(specify deptt.)
1 Limdi Medhri
Wasteland/ degraded land - - 2599.05 - - - 450.53 - Pastures - - 434.96 - - - 434.92 - Orchards - - - - - - - - Village Woodlot - - - - - - - - Forest - 4218.78 - - - 4218.78 - - Village Ponds/ Tanks - - 18.15 - - - 18.15 - Community Buildings - 35.26 - - - - - - Weekly Markets - - 3.5 - - - - - Permanent markets - - 2.45 - - - - Temples/ Places of worship 20.23 - - - - - - - Others (Pl. specify) - - - 9268.17 2804 - - -
Total/Average: 20.23 4254.04 3058.11 9268.17 2804 4218.78 903.6 0.00
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 42
Table no. 21: Demographic information
Sr.No. Village No. Of HH
Population Sex Ratio
SC ST Other Total Male Female Total Male Female % Total Male Female % Total Male Female %
1 Ambli Menpur 327 2018 1026 992 966.86 17 10 7 1.0 2001 1016 985 99.0 0 0 0 0.00
2 Biliya 107 842 451 391 866.96 0 0 0 0.0 842 451 391 100.0 0 0 0 0.00
3 Chari 177 950 547 403 736.75 0 0 0 0.0 666 338 303 75.0 284 209 100 29.89
4 Dumka 425 2258 1137 1121 985.93 0 0 0 0.0 2258 1137 1121 100.0 0 0 0 0.00
5 Kanakuwa 68 529 268 261 973.88 0 0 0 0.0 529 268 261 100.0 0 0 0 0.00
6 Kantu 256 1939 967 972 1005.17 0 0 0 0.0 1939 967 972 100.0 0 0 0 0.00
7 Ladva Vad 45 334 182 152 835.16 0 0 0 0.0 334 182 152 100.0 0 0 0 0.00
8 Limdi Medhri 417 2453 1276 1177 922.41 0 0 0 0.0 235 120 115 10.0 2218 1264 1062 90.42
9 Nan Salai 125 835 423 412 974.00 26 15 11 1.0 632 318 314 58.0 177 90 87 21.20
10 Pipariya (To) 108 644 344 300 872.09 0 0 0 0.0 435 228 207 70.0 209 116 93 32.45
11 Rachhava 239 1884 910 974 1070.33 0 0 0 0.0 1348 650 698 80.0 536 260 276 28.45
12 Sangasar 94 651 336 315 937.50 0 0 0 0.0 651 336 315 100.0 0 0 0 0.00
13 Simamoi 291 1579 810 769 949.38 0 0 0 0.0 0 0 0 0.0 1579 810 769 100.00
14 Udhal Mahuda 21 141 71 70 985.92 0 0 0 0.0 141 71 70 100.0 0 0 0 0.00
15 Ulkadar 35 362 169 193 1142.01 0 0 0 0.0 362 169 193 100.0 0 0 0 0.00
Total: 2735 17419 8917 8502 14224.36 43 25 18 2.0 12373 6251 6097 1192.0 5003 2749 2387 302.4
Demographic information Limdi Medhri watershed project mainly covers Ambli Menpur, Biliya, Chari, Dumka, Kanakuwa, Kantu, Ladva Vad, Limdi Medhri, Nan Salai, Pipariya(To), Ranchhava, Sangasar, Simamoi, Udah Mahuda and Ulkadar villages which comprises of 17419 households with a population of 17419 including 8917 males and 8502 female. The sex ratio is about 14244.4 female to 1000 male. There are about 6217 BPL families.
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 43
Table no. 22: Literacy rate Sl no Village Total Population Literacy Literacy %
above age 14 Literacy %
below age 14 Total % Male % Female % 1 Ambli Menpur 2018 562 27.8494 357 34.79 205 20.66 23 57 2 Biliya 842 257 30.5226 147 32.59 110 28.13 30 63 3 Chari 950 397 41.7895 267 48.81 130 32.25 25 62 4 Dumka 2258 799 35.3853 437 38.43 362 32.29 26 59 5 Kanakuwa 529 193 36.4839 120 44.77 73 27.96 21 59 6 Kantu 1939 961 49.5616 506 52.32 455 46.81 28 61 7 Ladva Vad 334 113 33.8323 74 40.65 39 25.65 23 62 8 Limdi Medhri 2453 992 40.4403 587 46 405 34.4 19 45 9 Nan Salai 835 366 43.8323 236 55.8 130 31.55 28 54 10 Pipariya (To) 644 181 28.1056 112 32.56 69 23 7 43 11 Rachhava 1884 931 49.4161 475 52.19 456 46.81 19 63 12 Sangasar 651 107 16.4363 68 20.23 39 12.38 21 52 13 Simamoi 1579 904 57.2514 561 69.25 343 44.6 15 40 14 Udhal Mahuda 141 51 36.1702 32 45.07 19 27.14 10 35 15 Ulkadar 362 138 38.1215 79 36.57 59 23.98 19 53
Total: 17419 6952 565.198 4058 650.03 2894 457.61 314 808 Limdi Medhri watershed project mainly covers thirteen villages Ambli Menpur, Biliya, Chari, Dumka, Kanakuwa, Kantu, Ladva Vad, Limdi Medhri, Nan Salai, Pipariya(To), Ranchhava, Sangasar, Simamoi, Udah Mahuda and Ulkadar villages which comprises of 5143 households with a population of 17419 including 8917 males and 8502 female. Total Literacy is 35.96, Out of which Male Literacy rate is 40.24 and female literacy rate as low as 31.49 per cent.
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 44
Table no. 23: Migration details Sr. No. Village Total Population
Migration Migration by months Main reason for migration
Income during migration / month Total Male Female Up to 3
months 3-6 months More than 6 months
1 Ambli Menpur 2018 1338 675 663 862 308 168
Low rainfall, Shortage of irrigation source
development, Scarcity of water, low potential
of land, Low rainfall, Degraded &
Undulating Terrain, Less education level.
267600 2 Biliya 842 575 290 285 422 103 50 115000 3 Chari 950 950 275 675 790 115 45 107400 4 Dumka 2258 1428 750 678 870 395 163 285600 5 Kanakuwa 529 373 190 183 194 109 70 74600 6 Kantu 1939 1413 710 703 943 375 95 282600 7 Ladva Vad 334 229 120 109 149 45 35 45800 8 Limdi Medhri 2453 1188 645 543 863 237 88 237600 9 Nan Salai 835 474 258 216 334 105 35 94800
10 Pipariya (To) 644 302 165 137 201 73 28 60400 11 Rachhava 1884 964 509 455 661 227 76 192800 12 Sangasar 651 467 255 212 180 184 103 93400 13 Simamoi 1579 846 428 418 609 199 38 169200 14 Udhal Mahuda 141 99 60 39 70 20 9 19800 15 Ulkadar 362 238 165 73 108 103 27 47600
Total 17419 10884 5495 5389 7256 2598 1030 2094200
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 45
3.2.2 Migration Pattern: Migration is during summer season to various parts of the state like Ahmedabad, Surat, Vadodara, Rajkot and Saurashtra as daily wages agricultural labors and construction workers. Lack of fodder availability and grazing land for smaller ruminant also forces these farmers to migrate to other places. Table no. 24: Poverty
Sr. No. Village Total Household BPL
% of BPL HH Total Land less HH
% of land less HH 0-16 16-20 Total
1 Ambli Menpur 593 283 334 617 104.0 42 7.1
2 Biliya 447 218 93 311 69.6 10 2.2
3 Chari 703 422 263 685 97.4 8 1.1
4 Dumka 807 390 345 735 91.1 25 3.1
5 Kanakuwa 460 108 151 259 56.3 2 0.4
6 Kantu 487 152 834 986 202.5 336 69.0
7 Ladva Vad 352 62 54 116 33.0 1 0.3
8 Limdi Medhri 493 284 90 374 75.9 15 3.0
9 Nan Salai 651 424 178 602 92.5 21 3.2
10 Pipariya (To) 189 143 28 171 90.5 0 0.0
11 Rachhava 404 90 153 243 60.1 2 0.5
12 Sangasar 205 131 31 162 79.0 10 4.9
13 Simamoi 692 377 246 623 90.0 33 4.8
14 Udhal Mahuda 189 143 28 171 90.5 0 0.0
15 Ulkadar 205 131 31 162 79.0 10 4.9
Total 6877 3358 2859 6217 1311.4 515 104.56
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 46
Table no. 25: Village infrastructure
Sr. No. Village
Pucca road to
the village (Y/N)
Schools
Colleges (Number)
Post Office
(Distance)
Banks (Number)
Distance from
nearest market
yard (Km)
Milk collection
centre (Number)
Milk cooperative (Number)
Other cooperatives
/ CBIs (Number)
Any other institution LP UP HS
1 Ambli Menpur Y 2 0 0 0 5 0 7 0 0 0 0 2 Biliya Y 1 0 0 0 4 0 5 0 0 0 0 3 Chari Y 1 0 0 4 0 8 1 0 0 0 4 Dumka Y 3 0 0 0 0 0 2 0 0 0 0 5 Kanakuwa Y 1 0 0 0 5 0 14 0 0 0 0 6 Kantu Y 2 0 0 0 4 0 12 0 0 0 0 7 Ladva Vad Y 1 0 0 0 2 0 4 0 0 0 0 8 Limdi Medhri Y 3 0 0 0 4 0 9 0 0 0 0 9 Nan Salai N 1 0 0 0 4 0 13 0 0 0 0
10 Pipariya (To) Y 1 0 0 0 3 0 12 0 0 0 0 11 Rachhava Y 2 1 0 0 1 0 2 0 0 0 0 12 Sangasar Y 1 0 0 0 3 0 15 0 0 0 0 13 Simamoi Y 2 0 0 0 0 0 3 0 0 0 0 14 Udhal Mahuda Y 1 0 0 0 4 0 14 0 0 0 0 15 Ulkadar N 1 0 0 0 8 0 8 0 0 0 0
Total 9 1 0 0 23 0 67 0 0 0 0
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 47
3.2.3 Infrastructure Facilities: Limdi Medhri watershed is well connected with Dhanpur Taluka with Kaccha and Pucca roads. The village has electricity connecting under Jyothigram
Yojana of Gujarat Government. Limdi Medhri watershed project mainly covers Fifteen villages viz Ambli Menpur, Biliya, Chari, Dumka, Kanakuwa, Kantu, Ladva Vad, Limdi Medhri, Nan Salai, Pipariya(To), Ranchhava, Sangasar, Simamoi, Udah Mahuda and Ulkadar villages having the facilities like Lower Primary Scool, Under Primary School and High Primary School, and other institutions (Anganwadi, Panchayat etc.).
Table no. 26: Facilities / HH assetsTable no.
Sr. No. Village HHs with
electricity
HHs with safety
latrines
HHs with phones HHs with vehicle HHs with TV set
HHs with cooking gas
HHs with Drinking
water
HHs with freedge Land line Mobile 2-wheeler 4-wheeler
1 Ambli Menpur 200 30 1 250 17 3 6 1 0 1 2 Biliya 90 0 0 90 9 1 1 0 0 0 3 Chari 103 0 0 95 8 1 1 0 0 0 4 Dumka 200 8 1 250 10 1 2 0 0 0 5 Kanakuwa 43 0 0 30 2 0 0 0 0 0 6 Kantu 170 0 0 42 8 1 1 0 0 0 7 Ladva Vad 35 0 0 26 6 0 1 0 0 0 8 Limdi Medhri 205 15 3 253 25 2 3 1 0 1 9 Nan Salai 45 0 0 70 7 0 1 0 0 0
10 Pipariya (To) 50 5 0 65 13 1 2 1 0 0 11 Rachhava 218 0 5 68 30 3 5 2 0 1 12 Sangasar 18 0 0 37 2 0 0 0 0 0 13 Simamoi 350 10 8 167 21 2 4 0 0 0 14 Udhal Mahuda 8 0 0 3 0 0 0 0 0 0 15 Ulkadar 25 0 0 5 0 0 0 0 0 0
Total 1760 68 18 1451 158 15 27 5 0 3
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 48
27: Per capita Income (In Rs.) Sr. No. Village Agriculture Animal Husbandry Casual labour Services Handicraft Others Total
1 Ambli Menpur 189 144 226 24 0 23 247850
2 Biliya 79 60 81 5 0 12 97457
3 Chari 89 68 95 8 0 21 106789
4 Dumka 210 161 198 8 0 40 154843
5 Kanakuwa 49 38 56 3 0 10 86479
6 Kantu 181 139 159 7 0 34 347932
7 Ladva Vad 31 24 34 2 0 7 10769
8 Limdi Medhri 229 175 210 27 0 49 368637
9 Nan Salai 78 60 88 4 4 17 241694
10 Pipariya (To) 62 47 45 35 0 7 89453
11 Rachhava 176 135 182 16 0 28 247148
12 Sangasar 61 47 76 1 0 8 0
13 Simamoi 148 113 167 8 0 25 138425
14 Udhal Mahuda 13 10 15 0 0 4 357654
15 Ulkadar 43 33 43 2 0 7 103573
Total 1639 1253 1675 150 4 292 2598703
Table no.28: Dependence on Forest/CPR Sr. No. Village Grass Fuel/ wood Total income % sells Income % sells Income
1 Ambli Menpur 7% 568 8% 243 811 2 Biliya 6% 503% 9% 325% 915% 3 Chari 10% 1546 14% 1674 3220 4 Dumka 8% 1110 7% 1292 2402 5 Kanakuwa 12% 1223 10% 1053 2276 6 Kantu 13% 1665 11% 1398 3063 7 Ladva Vad 7% 568 8% 243 811 8 Limdi Medhri 8% 1110 7% 1292 2402 9 Nan Salai 12% 896 10% 1110 2006
10 Pipariya (To) 10% 455 9% 789 1244 11 Rachhava 12% 1165 11% 1097 2262 12 Sangasar 0 0 0 0 0 13 Simamoi 13% 1665 11% 1398 3063 14 Udhal Mahuda 15% 1835 35% 3395 5230 15 Ulkadar 25% 2532 13% 1152 3684
Total - - - - 32483
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 49
3.3 Livelihood Pattern: The villagers earn their livelihood from animal husbandry and agriculture and during lean seasons they go as daily wages labourers at hilly fields of villages. Another noticeable occupation of the people is to create bucket, supdu (used for grain processing), etc. from the community and land or forest.
Table no. 29: Livelihood pattern (Occupational distribution) Sr. No. Village Total
workforce Agriculture Animal
husbandry (AH)
Agriculture + AH Casual labour Services Handicraft Others
1 Ambli Menpur 327 189 144 388 226 24 0 23 2 Biliya 107 79 60 162 81 5 0 12 3 Chari 177 89 68 183 95 8 0 21 4 Dumka 425 210 161 433 189 17 0 40 5 Kanakuwa 68 49 38 102 56 3 0 10 6 Kantu 256 181 139 373 158 8 0 34 7 Ladva Vad 45 31 24 64 29 7 0 7 8 Limdi Medhri 417 229 175 472 165 72 0 49 9 Nan Salai 125 78 60 161 80 12 4 17
10 Pipariya (To) 108 62 47 128 15 65 0 7 11 Rachhava 239 176 135 363 182 16 0 28 12 Sangasar 94 61 47 125 71 6 0 8 13 Simamoi 291 148 113 304 137 38 0 25 14 Udhal Mahuda 21 13 10 27 15 0 0 4 15 Ulkadar 35 43 33 89 43 2 0 7
Total 2735 1639 1253 3374 1542 283 4 292
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 50
CHAPTER 4 – WATERSHED ACTIVITIES PLANNED
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 51
4. Watershed Activities Table no. 30: Details of Scientific Planning and Inputs in IWMP projects Sr. No. Scientific criteria/ inputs used Whether scientific criteria was used
(A) Planning - Cluster approach Yes Whether technical back-stopping for the project has been arranged? If yes, mention the name of the Institute - Baseline survey Yes Hydro-geological survey Yes Contour mapping Yes Participatory Net Planning (PNP) Yes Remote sensing data-especially soil/ crop/ run-off cover Yes Ridge to Valley treatment Yes Online IT connectivity between Yes (1) Project and DRDA cell/ZP - (2) DRDA and SLNA - (3) SLNA and DoLR - Availability of GIS layers - 1. Cadastral map Yes 2. Village boundaries Yes 3. Drainage Yes 4. Soil (Soil nutrient status) Yes 5. Land use Yes 6. Ground water status Yes 7. Watershed boundaries Yes 8. Activity Yes Crop simulation models# No Integrated coupled analyzer/ near infrared visible spectroscopy/ medium spectroscopy for high speed soil nutrient analysis -
Normalized difference vegetation index (NDVI)# -
Weather Station - -
(B) Inputs Yes 1. Bio-pesticides Yes 2. Organic manures Yes 3. Vermicompost Yes 4. Bio-fertilizer Yes 5. Water saving devices Yes 6. Mechanized tools/ implements Yes 7. Bio-fencing Yes 8. Nutrient budgeting No 9. Automatic water level recorders & sediment samplers - Any other (please specify) -
#NDVI - Ratio of the differences of the response of vegetation in the near infrared & red regions of the electromagnetic spectrum
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 52
Table no.31: Details of PRA Activities conducted in the project area
Sr. No.
Name of village
Name of the PRA Activity
/ FGD Date
Number of
people present
Lessons learnt / Understanding of the problem/situation Understanding of the problem Situation
Specific problems of different villages to be narrated 1 Ambli Menpur
Social MappingSocial
Mapping, Resource Mapping,
Treatment Map,
Occupational Analysis,
Institutional Arrangement, Tree Matrix,
transect walk, Timeline, FGD, Seasonality of
Crop
25/9/2012 55
Mostly people are illiterate,they are believe in old culture of their behavier ,habitat and agriculter
2.they are obey oder particular men in their locality 3.lack of sanitation facility 4.unavailableble medical
facility under rural area 5.lack of irrigation facility 6. Most of farmer have small qauntity of land and
stragered 7. iregual rain fall 8.they require more domestic animal but prodution of mill are very poor
and un heathy animal
yes
After Giving inforamation
about watershe
benefit and utility and
project importance to villagers then they
are ready to joiin us
2 Biliya 23/9/2012 43
3 Chari 15/9/2012 65 4 Dumka 29/9/2012 56 5 Kanakuwa 19/9/2012 35 6 Kantu 21/9/2012 67 7 Ladva Vad 14/9/2012 38 8 Limdi Medhri 16/9/2012 92 9 Nan Salai 9/9/2012 48
10 Pipariya (To) 3/10/2012 42 11 Rachhava 13/11/2012 39 12 Sangasar 13/9/2012 42 13 Simamoi 28/9/2012 67 14 Udhal Mahuda 29/9/2012 35 15 Ulkadar 8/9/2012 42
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 53
4.1 Problem tree analysis
LOW AGRICULTURAL PRODUCTION LACK OF AGRICULTURAL
RESOURCES
INTERNAL EXTERNAL (POOR EXTENSION
RESOURCES)
LACK OF CAPITAL FRAGMENTED
LESS AVAILABLITY OF LABOUR DURING KHARRIF SEASON
LACK OF INTEREST
AT
BLOCK LEVEL
LACK OF TRAINING FACILITIES
LACK OF INFORMATION REGARDING GOVT.
SCHEMES
LESS CREDIT LINKAGE
DETERIORATION OF HEALTH STATUS
INCLINATION TOWARDS OTHER OCCUPATION SEASIONAL MIGRATION
POVERTY
DETERIORATION OF EDUCATIONAL
STATUS
DETERIORATION OF LIVING STANDARD
SPLIT IN FAMILIES
DETERIORATION OF THE CULTURE OF AB ORGINALS
LACK OF HUMAN RESOURCES
DETERIORATION OF NATURAL RESOURCES
POOR STATUS IN A & H DETERIRAION OF FOREST
UNEMPLOYMENT
OPEN GRAZING LACK OF IRRIGATION FACILITIES
INCLINATION TOWARDS OTHER OCCUPATION
LACK OF ORGANIZATION
CONFLICT OF INTEREST
NO PROPER DEMARCATION OF
PASTURE LAND
INFLUENCE OF LESS INTEREST OF EDUCATED PEOPLE IN
AGRICULTURE
CORRUPTION IN LINE DEPARTMENT
ROCKY SURFACE/ UNDULATING LAND
LACK OF CAPITAL FOR PURCHASE OF EQUIPMENT
MONO-CROPPING
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 54
4.2Object tree analysis
INCREASED AGRICULTURAL PRODUCTION
INCREASED INTEREST IN AGRICULTURE
MULTI-CROPPING ADEQUATE
AGRICULTURAL RESOURCES RESTRICTION ON OPEN
GRAZING IMPROVED IRRIGATION FACILITIES
INCREASED INCLINATION TOWARDS AGRICULTURE
STRENTHENING OF VILLAGE
ORGANIZATION
PROPER DEMARCATION OF
PASTURE LAND
AVAILABLITY OF CAPITAL INTEREST OF LINE DEPARTMENT
MAKING AGRI.
REMUNERATIVE
INTEREST OF EDUCATED PEOPLE IN
AGRICULTURE
INTERNAL EXTERNAL
(IMPROVED EXTENSION SERVICES)
ADEQUATE SAVING & CAPITAL
HIRING AGRICULTURE LABOUR & MACHINARY
PROPER CREDIT LINKAGE
IMPROVED DISEMINATION of GOVT.SCHEME OF
INFORMATION
TRAINING & CAPACITY BUILDING OF FARMERS
FACILITIES
AWARENESS AT
BLOCK LEVEL
PROSPERITY
RESERVED NATURAL RESOURCES
LESS DEFORESTATION
CHECK IN MIGRATION
IMPROVED HEALTH STATUS
IMPROVED EDUCATIONAL STATUS
ENHANCED LIVING STANDARD
SPLIT IN FAMILIES
PRESERVED CULTURE AND TRADITIONAL
ADEQUATE HUMAN RESOURCES
EMPLOYMENT
IMPROVED STATUS IN A & H
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 55
4.2 Institutions at Village Level
4.2.1 Watershed Committee (WC)
It is a committee that is constituted by Gram Sabha to implement the watershed project with technical support of WDTs in the village. This committee is registered under society Registration Act 1860. The Gram Sabha of the village selects the chairman of the watershed committee with the secretary who will be a paid functionary. A watershed committee was formed accordingly in Chakliya watershed project villages.
Table no. 32: Watershed Committee details
Sr. No.
Names of WCs
Date of Registration as a Society (dd/mm/
yyyy) Designation M/F SC ST SF MF LF Land-
less UG SHG GP Any other
Educa-tional
qualifi-cation
Function/s assigned#
1 Ambli Menpur SO/312648/10/1999
President M 0 1 0 1 0 0 0 0 1 0 12 th A.B.E.G.I. Secretary M 0 1 0 1 0 0 0 0 0 0 4th A.B.C.D.G.I. Member M 0 1 0 1 0 0 1 0 0 0 0 0 Member M 0 1 0 1 0 0 0 0 0 0 0 0 Member M 0 1 1 0 0 0 0 0 1 0 0 0 Member M 0 1 1 0 0 0 0 0 1 0 0 0 Member F 0 1 0 1 0 0 0 1 0 0 0 I Member M 0 1 0 1 0 0 0 0 0 0 0 I Member M 0 1 0 1 0 0 0 0 0 0 0 0 Member F 0 1 1 0 0 0 1 0 0 0 0 0
W.D.T M 0 1 1 0 0 0 0 0 0 0 B.R.S D.E.I.G.
2 Biliya F/2075
President M 0 1 0 1 0 0 0 0 0 0 B.A. A.B.E.G.I. Secretary M 0 1 0 1 0 0 0 0 1 0 10th A.B.C.D.G.I. Member M 0 1 1 0 0 0 1 0 0 0 0 0 Member F 0 1 1 0 0 0 1 1 0 0 5th 0 Member M 0 1 0 0 0 0 0 0 0 0 0 I Member F 0 1 0 0 0 0 0 1 0 0 0 I Member M 0 1 0 0 0 0 0 0 0 0 9th 0 Member M 0 1 0 0 0 0 0 0 0 0 0 0 Member F 0 1 0 0 0 0 1 1 0 0 0 0 Member M 0 1 0 0 0 0 1 0 0 0 0 0 Member M 0 1 0 0 0 0 0 0 0 0 0 0
W.D.T M 0 1 0 0 0 0 0 0 0 0 B.R.S D.E.I.G.
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 56
Sr. No.
Names of WCs
Date of Registration as a Society (dd/mm/
yyyy) Designation M/F SC ST SF MF LF Land-
less UG SHG GP Any other
Educa-tional
qualifi-cation
Function/s assigned#
3 Chari F/1649/Dahod 11/02/2010
President M 0 1 1 0 0 0 1 0 0 0 BA.BED A.B.E.G.I. Secretary M 0 1 0 1 0 0 0 0 0 0 BA.BED A.B.C.D.G.I. Member M 0 1 1 0 0 0 1 0 0 0 12th 0 Member M 0 1 0 1 0 0 1 0 0 0 0 0 Member M 0 1 1 0 0 0 0 0 1 0 12th 0 Member F 0 1 1 0 0 0 0 0 0 0 0 0 Member M 0 1 0 0 0 0 0 0 0 0 0 I Member M 0 1 0 0 0 0 0 0 0 0 0 I Member F 1 0 0 1 0 0 0 1 0 0 0 0 Member F 0 1 1 0 0 0 1 0 0 0 0 0
W.D.T M 0 1 0 0 0 0 0 0 0 0 B.R.S D.E.I.G.
4 Dumka SE/32466 22/01/2001
President M 1 0 0 1 0 0 1 1 0 0 10TH A.B.E.G.I. Secretary M 0 1 1 0 0 0 0 0 0 0 0 A.B.C.D.G.I. Member M 0 1 1 0 0 0 1 0 0 0 0 0 Member M 0 1 1 0 0 0 1 0 0 0 0 0 Member M 0 1 1 0 0 0 1 0 0 0 0 0 Member M 0 1 1 0 0 0 1 0 0 0 12 0 Member M 0 1 1 0 0 0 0 0 0 0 10 TH 0 Member F 0 1 0 0 0 0 0 1 0 0 0 0 Member F 0 1 0 0 0 0 0 0 0 0 0 0 Member M 0 1 1 0 0 0 0 0 1 0 4 0 Member M 0 1 1 1 0 0 0 0 0 0 0 0
W.D.T M 0 1 0 0 0 0 0 0 0 0 B.R.S D.E.I.G.
5 Kanakuwa F/2072 DAHOD 4/12/2012
President M 0 1 1 0 0 0 1 0 1 0 B.R.S A.B.E.G.I. Secretary M 0 1 1 0 0 0 1 0 0 0 5th A.B.C.D.G.I. Member M 0 1 1 0 0 0 1 0 0 0 10 th 0 Member F 0 1 1 0 0 0 1 0 0 0 7th 0 Member F 0 1 1 0 0 0 1 0 1 0 0 0 Member F 0 1 1 0 0 0 0 0 0 0 0 0 Member M 0 1 0 0 0 0 0 1 0 0 5 th I Member M 0 1 0 0 0 0 0 1 0 0 7th I Member M 0 1 0 0 0 0 0 0 0 0 2th 0 Member M 0 1 0 1 0 1 1 0 0 0 0 0
W.D.T M 0 1 0 0 0 0 0 0 0 0 B.R.S D.E.I.G.
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 57
Sr. No.
Names of WCs
Date of Registration as a Society (dd/mm/ yyyy) Designation M/F SC ST SF MF LF Land-less UG SHG GP Any
other
Educa-tional
qualifi-cation
Function/s assigned#
6 Kantu F/2071 DAHOD 4/12/2012
President M 0 1 0 1 0 0 1 0 1 0 10th A.B.E.G.I. Secretary M 0 1 1 0 0 0 1 0 0 0 12th A.B.C.D.G.I. Member M 0 1 0 1 0 0 0 1 0 0 5th 0 Member M 0 1 0 1 0 0 0 0 0 0 12th 0 Member M 0 1 1 0 0 0 1 0 0 0 5th 0 Member M 0 1 1 0 0 0 1 0 0 0 4th 0 Member M 0 1 1 0 0 0 1 0 0 0 0 I Member F 0 1 0 1 0 0 0 0 1 0 0 0 Member F 0 1 1 0 0 0 1 0 0 0 0 0 Member F 0 1 0 1 0 0 0 0 0 0 0 I
W.D.T M 0 1 0 0 0 0 0 0 0 0 B.R.S D.E.I.G.
7 Ladva Vad In Progress
President M 0 1 1 0 0 0 1 0 0 0 4th A.B.E.G.I. Secretary M 0 1 1 0 0 0 1 0 1 0 7th A.B.C.D.G.I. Member M 0 1 1 0 0 0 1 0 0 0 10th 0 Member M 0 1 1 0 0 0 1 0 0 0 9th 0 Member M 0 1 0 1 0 0 0 0 0 0 3th 0 Member F 0 1 0 1 0 0 0 1 0 0 0 I Member F 0 1 0 1 0 0 0 0 0 0 10th I Member F 0 1 0 1 0 0 1 0 1 0 0 0 Member M 0 1 1 0 0 0 0 0 0 0 0 0 Member M 0 1 1 0 0 0 0 0 0 0 0 0
W.D.T M 0 1 0 0 0 0 0 0 0 0 B.R.S D.E.I.G.
8 Limdi Medhri KHE/8629/ 29/3/2006
President M 1 0 1 0 0 0 0 0 0 0 10th A.B.E.G.I. Secretary M 1 0 1 0 0 0 0 0 0 0 BA A.B.C.D.G.I. Member M 1 0 0 1 0 0 0 0 0 0 PTC 0 Member M 1 0 1 0 0 0 1 0 0 0 7TH 0 Member M 1 0 0 1 0 0 1 0 0 0 12th 0 Member M 1 0 1 0 0 0 0 0 1 0 12th 0 Member M 1 0 1 0 0 0 1 0 0 0 12th 0 Member M 1 0 1 0 0 0 1 0 0 0 7th 0 Member M 1 0 0 1 0 0 0 0 0 0 0 0 Member M 1 0 1 0 0 0 0 0 0 0 0 0 Member M 0 1 0 1 0 0 0 0 0 0 0 0 Member M 0 1 0 1 0 0 0 0 0 0 0 0 Member F 1 0 0 0 0 0 0 1 0 0 12th 0 Member F 1 0 0 0 0 0 0 1 0 0 0 0 Member F 1 0 0 1 0 0 0 1 0 0 0 0
W.D.T M 1 0 0 0 0 0 0 0 0 0 B.R.S D.E.I.G.
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 58
Sr. No.
Names of WCs
Date of Registration as a Society (dd/mm/
yyyy) Designation M/F SC ST SF MF LF
Land-less
UG SHG GP Any other
Educa-tional
qualifi-cation
Function/s assigned#
9 Nan Salai F/1606 2/12/2009
President M 0 1 1 0 0 0 1 0 0 0 9th A.B.E.G.I. Secretary M 0 1 0 1 0 0 0 0 0 0 10th A.B.C.D.G.I. Member M 0 1 1 0 0 0 0 0 0 0 11th 0 Member M 1 0 0 0 1 0 0 0 0 0 11th 0 Member M 0 1 1 0 0 0 0 0 1 0 0 0 Member M 0 1 0 1 0 0 0 0 0 0 5th 0 Member M 1 0 0 0 1 0 1 0 0 0 12th 0 Member F 0 1 0 1 0 0 0 1 0 0 0 I Member F 0 1 0 1 0 0 0 0 0 0 10th I Member F 0 1 0 1 0 0 0 0 0 0 0 0
W.D.T M 0 1 0 0 0 0 0 0 0 0 B.R.S D.E.I.G.
10 Pipariya (To) F/1609 2/12/2009
President F 1 0 1 0 0 0 0 0 0 0 10th A.B.E.G.I. Secretary M 0 1 0 0 0 0 0 0 1 0 12th A.B.C.D.G.I. Member M 0 0 1 0 0 0 0 0 0 0 5th 0 Member F 1 0 1 0 0 0 0 0 0 0 5th 0 Member F 0 1 0 1 0 0 0 1 0 0 10th 0 Member M 0 1 1 0 0 0 0 0 0 0 12th 0 Member M 0 1 1 0 0 0 0 0 0 0 10th 0 Member F 0 1 0 1 0 0 0 1 0 0 0 I Member M 0 1 1 0 0 0 0 0 0 0 BA Member M 1 0 0 0 1 0 0 0 0 0 5th Member M 1 0 0 0 0 0 0 0 0 0 12th Member M 1 0 0 0 0 0 1 0 0 0 PTC Member M 1 0 0 0 0 0 0 0 0 0 7th Member M 1 0 1 0 0 0 0 0 0 0 12th I Member M 1 0 0 1 0 0 0 0 0 0 0 0
W.D.T M 0 1 0 0 0 0 0 0 0 0 B.R.S D.E.I.G.
11 Rachhava KHE/5627 10/3/2004
President M 0 1 1 0 0 0 0 0 0 0 10th A.B.E.G.I. Secretary M 0 1 1 0 0 0 0 0 0 0 12th A.B.C.D.G.I. Member M 0 1 0 0 1 0 0 0 0 0 0 0 Member M 0 1 1 0 0 0 1 0 0 0 0 0 Member M 0 1 1 0 0 0 0 0 0 0 0 0 Member M 0 1 1 0 0 0 0 0 0 0 0 0 Member F 0 1 1 0 0 0 0 0 0 0 0 0 Member F 0 1 0 1 0 0 0 1 0 0 0 I Member M 1 0 0 1 0 0 0 0 0 0 0 I Member M 0 1 0 1 0 0 0 0 0 0 0 0 Member M 0 1 0 1 0 0 0 0 0 0 4th
W.D.T M 0 1 1 0 0 0 0 0 0 1 B.R.S D.E.I.G.
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 59
Sr. No.
Names of WCs
Date of Registration as a Society (dd/mm/
yyyy) Designation M/F SC ST SF MF LF Land-
less UG SHG GP Any other
Educa-tional
qualifi-cation
Function/s assigned#
12 Sangasar F/1990 25/1/2011
President M 0 1 1 0 0 0 1 0 0 0 7th A.B.E.G.I. Secretary M 0 1 1 0 0 0 0 0 0 0 7th A.B.C.D.G.I. Member M 0 1 1 0 0 0 1 0 0 0 0 0 Member M 0 1 1 0 0 0 1 0 0 0 0 0 Member M 0 1 0 1 0 0 0 0 0 0 0 0 Member M 0 1 0 1 0 0 0 0 0 0 0 0 Member M 0 1 1 0 0 0 0 1 0 0 10th I Member F 0 1 1 0 0 0 0 0 0 0 0 I Member F 0 1 0 1 0 0 0 0 0 0 5th 0 Member F 0 1 0 1 0 0 1 0 1 0 0 0 Member M 0 1 0 0 0 0 0 0 0 0 0 0
W.D.T M 0 1 1 0 0 0 0 0 0 1 B.R.S D.E.I.G.
13 Simamoi F/1612/ 2/12/2009
President M 1 0 1 0 0 0 1 0 0 0 BA A.B.E.G.I. Secretary M 1 0 1 0 0 0 0 0 0 0 BA A.B.C.D.G.I. Member M 1 0 1 0 0 0 0 0 0 0 10th 0 Member M 1 0 1 0 0 0 0 0 0 0 10th 0 Member M 1 0 0 1 0 0 0 1 0 0 8th I Member M 1 0 0 1 0 0 0 0 0 0 0 I Member F 1 0 0 1 0 0 0 1 0 0 5th 0 Member M 1 0 1 0 0 0 0 0 1 0 12th 0 Member F 1 0 0 1 0 0 1 0 0 0 Member F 1 0 1 0 0 0 0 0 0 0 0 0
W.D.T M 1 0 0 0 0 0 0 0 0 0 B.R.S D.E.I.G.
14 Udhal Mahuda F/1610 2/12/2009
President M 0 1 1 0 0 0 0 0 0 0 7th A.B.E.G.I. Secretary M 0 1 1 0 0 0 0 0 0 0 2rh A.B.C.D.G.I. Member M 0 1 1 0 0 0 0 0 0 0 0 0 Member M 0 1 1 0 0 0 0 0 0 0 0 0 Member M 0 1 1 0 0 0 0 0 1 0 0 0 Member M 0 1 1 0 0 0 0 0 0 0 0 0 Member M 0 1 1 0 0 0 0 0 0 0 2th 0 Member M 0 1 0 1 0 0 0 0 0 0 0 I Member M 0 1 0 1 0 0 0 0 0 0 0 I Member M 0 1 0 1 0 0 0 0 0 0 0 0 Member F 0 1 1 1 0 1 0 0 0 0 0 0 Member F 0 1 1 0 0 0 0 1 0 0 0 0 Member M 0 1 0 1 0 0 1 0 0 0 0 0 Member M 1 0 1 0 0 0 0 0 0 0 12th 0
W.D.T M 0 1 0 0 0 0 0 0 0 0 B.R.S D.E.I.G.
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 60
Sr. No.
Names of WCs
Date of Registration as a Society (dd/mm/
yyyy) Designation M/F SC ST SF MF LF Land-
less UG SHG GP Any other
Educa-tional
qualifi-cation
Function/s assigned#
15 Ulkadar F/1581 15/10/2009
President M 0 1 1 0 0 0 0 0 0 0 11th A.B.E.G.I. Secretary M 0 1 1 0 0 0 0 0 1 0 4th A.B.C.D.G.I. Member M 0 1 1 0 0 0 0 0 0 0 4th 0 Member M 0 1 1 0 0 0 0 0 0 0 0 0 Member M 0 1 1 0 0 0 0 0 0 0 4th 0 Member M 0 1 1 0 0 0 0 0 0 0 0 0 Member F 0 1 1 0 0 0 0 1 0 0 0 0 Member F 0 1 0 1 0 0 0 1 0 0 0 I Member F 0 1 0 1 0 0 0 0 0 0 0 I Member M 0 1 0 1 0 0 0 0 0 0 0 0 Member M 0 1 0 0 0 0 0 0 0 0 10th D.E.I.G.
W.D.T M 0 1 1 0 0 0 0 0 0 0 B.R.S D.E.I.G.
# Only the letter assigned, as below, needs to be typed, except for `J’, where the type may be specifically mentioned.
A. PNP and PRA B. Planning C. Maintenance of Accounts D. Signing of cheques and making payments E. Supervision of construction activities F. Cost Estimation G. Verification & Measurement H. Record of labour employed I. Social Audit J. Any other (please specify).
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 61
4.2.2 Self Help Group
Self Help Groups are motivated, small homogenous groups organized together through credit and thrift activities. Self Help Group initiatives especially for women help uplift their livelihood. Generally Self Help Groups include landless and poor women.
Before formation of the SHGs, during PRA activities, Focused Group Discussions (FGDs) were held with the women, which came up with the following observations:
(a) Lack of proper credit facilities due to low intervention of formal financial credit institution. (b) Excessive exploitation of weaker section by money lenders. (c) Lack of attitude for saving among poor people. (d) Lack of knowledge on credit and thrift activity and banking.
With a detailed discussion with some of the local NGOs working in the area like Sadguru, Prakruti, GRISARV, GSRDC Vadodara, and Utthan Limkheda, it was planned to have some capacity building training regarding SHG activities. It was also proposed to have some livelihood activities which will promote women empowerment. Table no. 33: SHG detail
Sr. No. Name of village
Total no. of registered SHGs No. of members No. of SC/ST in each category
No. of BPL in each category
With only Men
With only
Women
With both Total Categories M F Total M F Total M F Total
1 Ambli Menpur 1 4 0 5
(i) Landless 0 0 0 0 0 0 0 0 0 (ii) SF 10 44 54 10 44 54 0 0 0
(iii) MF 0 0 0 0 0 0 0 0 0 (iv) LF 0 0 0 0 0 0 0 0 0
Total 1 4 0 5 10 44 54 10 44 54 0 0 0
2 Biliya 0 1 0 1
(i) Landless 0 0 0 0 0 0 0 0 0 (ii) SF 9 3 12 9 3 12 0 0 0
(iii) MF 0 0 0 0 0 0 0 0 0 (iv) LF 0 0 0 0 0 0 0 0 0
Total 0 1 0 1 9 3 12 9 3 12 0 0 0
3 Chari 0 2 0 2
(i) Landless 0 0 0 0 0 0 0 0 0 (ii) SF 0 21 21 0 21 21 0 0 0
(iii) MF 0 0 0 0 0 0 0 0 0 (iv) LF 0 0 0 0 0 0 0 0 0
Total 0 2 0 2 0 21 21 0 21 21 0 0 0
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 62
Sr. No. Name of village
Total no. of registered SHGs No. of members No. of SC/ST in each category
No. of BPL in each category
With only Men
With only
Women
With both Total Categories M F Total M F Total M F Total
4 Dumka 0 2 0 3
(i) Landless 0 0 0 0 0 0 0 0 0 (ii) SF 13 26 41 13 26 41 0 0 0
(iii) MF 0 0 0 0 0 0 0 0 0 (iv) LF 0 0 0 0 0 0 0 0 0
Total 0 2 0 3 13 26 41 13 26 41 0 0 0
5 Kanakuwa 0 1 0 1
(i) Landless 0 0 0 0 0 0 0 0 0 (ii) SF 0 11 11 0 11 11 0 0 0
(iii) MF 0 0 0 0 0 0 0 0 0 (iv) LF 0 0 0 0 0 0 0 0 0
Total 0 1 0 1 0 11 11 0 11 11 0 0 0
6 Kantu 1 4 0 5
(i) Landless 0 0 0 0 0 0 0 0 0 (ii) SF 22 33 55 22 33 55 0 0 0
(iii) MF 0 0 0 0 0 0 0 0 0 (iv) LF 0 0 0 0 0 0 0 0 0
Total 1 4 0 5 22 33 55 22 33 55 0 0 0
7 Ladva Vad 0 1 0 1
(i) Landless 0 0 0 0 0 0 0 0 0 (ii) SF 0 0 0 0 0 0 0 0 0
(iii) MF 0 11 11 0 11 11 0 11 11 (iv) LF 0 0 0 0 0 0 0 0 0
Total 0 1 0 1 0 11 11 0 11 11 0 11 11
8 Limdi Medhri 1 6 0 7
(i) Landless 0 0 0 0 0 0 0 0 0 (ii) SF 11 66 77 11 66 77 0 0 0
(iii) MF 5 0 0 0 0 0 0 0 0 (iv) LF 0 0 0 0 0 0 0 0 0
Total 1 6 0 7 16 66 77 11 66 77 0 0 0
9 Nan Salai 0 2 0 2
(i) Landless 0 0 0 0 0 0 0 0 0 (ii) SF 0 22 22 0 22 22 0 0 0
(iii) MF 0 0 0 0 0 0 0 0 0 (iv) LF 0 0 0 0 0 0 0 0 0
Total 0 2 0 2 0 22 22 0 22 22 0 0 0
Sr. No. Name of village
Total no. of registered SHGs No. of members No. of SC/ST in each category
No. of BPL in each category
With only Men
With only
Women
With both Total Categories M F Total M F Total M F Total
10 Pipariya (To) 1 2 0 2
(i) Landless 0 0 0 0 0 0 0 0 0 (ii) SF 0 22 22 0 22 22 0 0 0
(iii) MF 0 0 0 0 0 0 0 0 0 (iv) LF 0 0 0 0 0 0 0 0 0
Total 1 2 0 2 0 22 22 0 22 22 0 0 0
11 Rachhava 0 4 0 4
(i) Landless 0 0 0 0 0 0 0 0 0 (ii) SF 0 42 42 0 42 42 0 0 0
(iii) MF 0 0 0 0 0 0 0 0 0 (iv) LF 1 0 0 0 0 0 0 0 0
Total 0 4 0 4 1 42 42 0 42 42 0 0 0
12 Sangasar 0 2 0 2
(i) Landless 0 0 0 0 0 0 0 0 0 (ii) SF 0 22 22 0 22 22 0 0 0
(iii) MF 0 0 0 0 0 0 0 0 0 (iv) LF 0 0 0 0 0 0 0 0 0
Total 0 2 0 2 0 22 22 0 22 22 0 0 0
13 Simamoi 1 2 0 3
(i) Landless 0 0 0 0 0 0 0 0 0 (ii) SF 12 25 37 12 25 37 0 0 0
(iii) MF 0 0 0 0 0 0 0 0 0 (iv) LF 0 0 0 0 0 0 0 0 0
Total 1 2 0 3 12 25 37 12 25 37 0 0 0
14 Udhal Mahuda 1 1 0 2
(i) Landless 0 0 0 0 0 0 0 0 0 (ii) SF 10 10 20 10 10 20 0 0 0
(iii) MF 0 0 0 0 0 0 0 0 0 (iv) LF 0 0 0 0 0 0 0 0 0
Total 1 1 0 2 10 10 20 10 10 20 0 0 0
15 Ulkadar 0 2 0 2
(i) Landless 0 0 0 0 0 0 0 0 0 (ii) SF 0 20 20 0 20 20 0 0 0
(iii) MF 0 0 0 0 0 0 0 0 0 (iv) LF 0 0 0 0 0 0 0 0 0
Total 0 36 0 42 0 20 20 0 20 20 0 0 0
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 64
4.2.3 User Group
User Groups are normally formed to manage an activity or asset created under the programme on a long term basis. The user group collect user charges from their members, oversee the works and manage the benefits. It was decided that each group would formulate certain internal rules and have feeling of ownership with community spirit. Table no. 34: UG detail
Sr. No.
Name of village
Total no. of UGs No. of members No. of SC/ST in each category No. of BPL in each category
Men Women Both Total Categories M F Total M F Total M F Total
1 Ambli Menpur 8 0 0 8
(i) Landless 0 0 0 0 0 0 0 0 0 (ii) SF 31 0 31 31 0 31 13 0 13 (iii) MF 0 0 0 0 0 0 0 0 0 (iv) LF 0 0 0 0 0 0 0 0 0
Total 8 0 0 8 31 0 31 31 0 31 13 0 13
2 Biliya 4 0 0 4
(i) Landless 0 0 0 0 0 0 0 0 0 (ii) SF 13 0 13 13 0 13 8 0 8 (iii) MF 0 0 0 0 0 0 0 0 0 (iv) LF 0 0 0 0 0 0 0 0 0
Total 4 0 0 4 13 0 13 13 0 13 8 0 8
3 Chari 2 0 0 2
(i) Landless 0 0 0 0 0 0 0 0 0 (ii) SF 4 0 4 4 0 4 2 0 2 (iii) MF 0 0 0 0 0 0 0 0 0 (iv) LF 0 0 0 0 0 0 0 0 0
Total 2 0 0 2 4 0 4 4 0 4 2 0 2
4 Dumka 5 0 0 5
(i) Landless 0 0 0 0 0 0 0 0 0 (ii) SF 28 0 28 28 0 28 15 0 15 (iii) MF 0 0 0 0 0 0 0 0 0 (iv) LF 0 0 0 0 0 0 0 0 0
Total 6 0 0 2 28 0 28 28 0 28 15 0 15
5 Kanakuwa 2 0 0 2
(i) Landless 0 0 0 0 0 0 0 0 0 (ii) SF 10 0 10 10 0 10 7 0 7 (iii) MF 0 0 0 0 0 0 0 0 0 (iv) LF 0 0 0 0 0 0 0 0 0
Total 2 0 0 2 10 0 10 10 0 10 7 0 7
Sr. No.
Name of village
Total no. of UGs No. of members No. of SC/ST in each category No. of BPL in each category
Men Women Both Total Categories M F Total M F Total M F Total
6 Kantu 10 0 0 10
(i) Landless 0 0 0 0 0 0 0 0 0 (ii) SF 51 0 51 51 0 51 27 0 27 (iii) MF 0 0 0 0 0 0 0 0 0 (iv) LF 0 0 0 0 0 0 0 0 0
Total 10 0 0 10 51 0 51 51 0 51 27 0 27
7 Ladva Vad 1 0 0 1
(i) Landless 0 0 0 0 0 0 0 0 0 (ii) SF 6 0 6 6 0 6 3 0 3 (iii) MF 0 0 0 0 0 0 0 0 0 (iv) LF 0 0 0 0 0 0 0 0 0
Total 0 0 0 0 6 0 6 6 0 6 3 0 3
8 Limdi Medhri 7 0 0 7
(i) Landless 0 0 0 0 0 0 0 0 0 (ii) SF 24 0 24 24 0 24 15 0 15 (iii) MF 0 0 0 0 0 0 0 0 0 (iv) LF 0 0 0 0 0 0 0 0 0
Total 7 0 7 24 0 24 24 0 24 15 0 15
9 Nan Salai 5 0 0 5
(i) Landless 0 0 0 0 0 0 0 0 0 (ii) SF 17 0 17 17 0 17 9 0 9 (iii) MF 0 0 0 0 0 0 0 0 0 (iv) LF 0 0 0 0 0 0 0 0 0
Total 4 0 0 4 17 0 17 17 0 17 9 0 9
10 Pipariya (To) 2 0 0 2
(i) Landless 0 0 0 0 0 0 0 0 0 (ii) SF 8 0 8 8 0 8 5 0 5 (iii) MF 0 0 0 0 0 0 0 0 0 (iv) LF 0 0 0 0 0 0 0 0 0
Total 2 0 0 2 8 0 8 8 0 8 5 0 5
11 Rachhava 10 0 0 10
(i) Landless 0 0 0 0 0 0 0 0 0 (ii) SF 47 0 47 47 0 47 21 0 21 (iii) MF 0 0 0 0 0 0 0 0 0 (iv) LF 0 0 0 0 0 0 0 0 0
Total 8 0 0 8 47 0 47 47 0 47 21 0 21
12 Sangasar 2 0 0 2
(i) Landless 0 0 0 0 0 0 0 0 0 (ii) SF 10 0 10 10 0 10 7 0 7 (iii) MF 0 0 0 0 0 0 0 0 0 (iv) LF 0 0 0 0 0 0 0 0 0
Total 2 0 0 2 10 0 10 10 0 10 7 0 7
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 66
Sr. No.
Name of village Total no. of UGs No. of members No. of SC/ST in each
category No. of BPL in each category
13 Simamoi 6 0 0 6
(i) Landless 0 0 0 0 0 0 0 0 0
(ii) SF 24 0 24 24 0 24 13 0 13
(iii) MF 0 0 0 0 0 0 0 0 0
(iv) LF 0 0 0 0 0 0 0 0 0
Total 6 0 0 6 24 0 24 24 0 24 13 0 13
14 Udhal Mahuda 1 0 0 1
(i) Landless 0 0 0 0 0 0 0 0 0
(ii) SF 4 0 4 4 0 4 4 0 4
(iii) MF 0 0 0 0 0 0 0 0 0
(iv) LF 0 0 0 0 0 0 0 0 0
Total 1 0 0 1 4 0 4 4 0 4 4 0 4
15 Ulkadar 3 0 0 3
(i) Landless 0 0 0 0 0 0 0 0 0
(ii) SF 14 0 14 14 0 14 10 0 10
(iii) MF 0 0 0 0 0 0 0 0 0
(iv) LF 0 0 0 0 0 0 0 0 0
Total 3 0 0 3 14 0 14 14 0 14 10 0 10
Grand Total 65 0 0 61 291 0 291 291 0 291 159 0 159
4.3 Physical activities to be undertaken under IWMP – 15 (Limdi Medhri Watershed)
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 67
4.3.1 Entry Point Activity (EPA) EPA activities are certain important works which are in urgent demand of the local community. This helps in establishment of credibility of Watershed Development Team (WDT). It also acts as a rapport building activity of the village community. A group discussion was conducted with Watershed Development Committee (WDC) regarding EPA activity; it was conveyed to the amount of Rs.31.39 Lakh was allotted for EPA activity, which was a 4 per cent of total allocated budget. The villagers discussed various activities which they felt is important but after a brief discussion it was conveyed to them that only those activities can taken, which revive the common natural resources. It was also taken into priority that there should be an instrument of convergence which will result in sustainability of activities.
Table no.35: Entry point activities (EPA) (All financial figures in lakh Rs.)
Sr. No. Names of Villages
Amount earmarked for
EPA Entry Point Activities planned No. of EPA
undertaken Cost From Other
Scheme(Convergence) Name of the
Scheme Estimated cost Expected outcome
1 Ambli Menpur 3.931
Cause Way 1 - - 1.6 E Cause Way 1 - - 1.33 E
Check Wall Repairing 1 - - 0.8 B Cattle Camp 2 - - 0.2 M
Total 5 - - 3.931
2 Biliya 1.084 Cause Way 1 - - 1 E Cattle Camp 1 - - 0.84 M
Total 2 - - 1.084
3 Chari 1.53 Cattle Camp 1 - - 0.1 M
Check Wall Repairing 1 - - 0.43 B Well Repairing 4 - - 1
Total 6 - - 1.53
4 Dumka 2.098 Cattle Camp 1 - - 0.1 M
Check Wall Repairing 1 - - 0.788 B Well Repairing 4 - - 1.25
Total 6 - - 2.098
5 Kanakuwa 0.82 Cattle Camp 1 - - 0.1 M
Check Wall Repairing 1 - - 0.72 B Total 2 - - 0.82
6 Kantu 3.878
Cause Way 1 - - 1 E Dobhi Ghat 1 - - 0.678
Well Repairing 1 - - 0.6 Common Sanitation & Bathroom 1 - - 1.5
Cattle Camp 1 - - 0.1 M Total 5 - - 3.878
7 Ladva Vad 0.459 Well Repairing 2 - - 0.359 Cattle Camp 1 - - 0.1 M
Total 3 - - 0.459
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 68
Sr. No. Names of Villages Amount
earmarked for EPA Entry Point Activities
planned No. of EPA
undertaken Cost From Other
Scheme(Convergence) Name of the
Scheme Estimated cost Expected outcome
8 Limdi Medhri 4.54
Cause Way 1 - - 0.96 E Cause Way 1 - - 0.87 E Cause Way 1 - - 1.19 E Well Repairing 1 - - 1 Well Repairing 1 - - 0.42 Cattle Camp 1 - - 0.1 M
Total 6 - - 4.54
9 Nan Salai 1.7 Cause Way 1 - - 1.6 E Cattle Camp 1 - - 0.1 M
Total 2 - - 1.7
10 Pipariya (To) 0.9
Check Wall Repairing 1 - - 0.32 B Well Repairing 1 - - 0.24 Well Repairing 1 - - 0.24 Cattle Camp 1 - - 0.1 M
Total 3 - - 0.9
11 Rachhva 2.72
Well Repairing 5 - - 1.9 Hand Pump Repairing 5 - - 0.15 Cattle Camp 1 - - 0.1 M Check Wall Repairing 1 - - 0.57 B
Total 12 - - 2.72
12 Sangasar 0.91 Check Dam Repairing 1 - - 0.56 B Well Repairing 1 - - 0.25 Cattle Camp 1 - - 0.1 M
Total 3 - - 0.91
13 Simamoi 2.53
Well Repairing 5 - - 1.6 Hand Pump Repairing 5 - - 0.15 Cattle Camp 1 - - 0.1 M Check Wall Repairing 1 - - 0.68 B
Total 12 - - 2.53
14 Udhalmahuda 1.66
Well Repairing 2 - - 0.65 Cause Way 1 - - 0.24 E Dhobi Ghat 1 - - 0.67 Cattle Camp 1 - - 0.1 M
Total 5 - - 1.66
15 Ulkadar 2.63 Well Repairing 1 - - 1.39 Cause Way 1 - - 1.2 E Cattle Camp 1 - - 0.04 M
Total 3 - - 2.63 Grand Total 75 31.39
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 69
Table no.36: Details of engineering structures in watershed works*
S. No
.
Village name Name of structures
Type of treatment Type of land Target IWMP Conversion
(i) Ridg
e area (R)
(ii) Drainag
e line (D)
(iii) Lan
d dev. (L)
(i) Pri-vat
e (P)
(ii) Comm-unity
(C)
(iii) Fores
t (F)
No. of units (No./
cu.m./ rmt)
Estimated cost (Rs. in lakh)
Expected month & year of
completion
(mm/yyyy)
No. of units (No./
cu.m./ rmt)
Estimated cost (Rs. in lakh)
No. of units (No./ cu.m.
/ rmt)
Cost Department
M Unit T M Unit T
1 Amlimenpur
Contour Trench R - - - - F Rmt 5000 1.00 2013-14 Rmt 500
0 1.00
Gully Plug ( LBS) - D - P - F Cmt 59 0.07 2013-14 Cmt 59 0.07 Gully Plug Cementry D - - - F Cmt 95 1.33 2013-14 Cmt 99 1.33
Plantation R - - - - F Nos/Ha 305
0 0.61 2014-15 Nos/Ha 305
0 0.11 0.50 Social Forestry
Nala Plug ( LBS) - D L P - F cmt 310 0.37 2014-15 cmt 310 0.37 Cementry Nala Plug - - L P - - Nos 5 3.93 2014-15 Nos 5 3.93 Stone Bund ( LBS) - - L P - - Cmt 390 0.47 2014-15 Cmt 390 0.47 Stone Bund Cementry - - L P - - Cmt 275 3.85 2014-15 Cmt 275 3.85
Farm Bund - - L P - - Rmt 1200 0.78 2015-16 Rmt 1200 0.78 GLDC
Field Water Outlet - - L P - - Nos 14 1.05 2015-16 Nos 14 1.05 Check Wall - - L - C - Nos 4 18.00 2015-16 Nos 2 9.00 2 9.00 MGNREGA Check Wall Repairing - - L - C - Nos 2 1.40 2015-16 Nos 2 1.40
Check Wall Disilting - - L - C - Nos 3 1.20 2015-16 Nos 3 1.20 MGNREGA Earthen Bund - - L - C - Nos 1 3.40 2015-16 Nos 1 3.40 Stone Pitching - - - C - Nos 1 3.50 2015-16 Nos 1 3.50 deepning of pond - - L - C - Nos 1 1.00 2015-16 Nos 1 1.00 MGNREGA Protection Wall(30 m) - - L P - - Nos 1 2.10 2015-16 Nos 1 2.10
Total 0 44.06 0 31.58 0 12.48
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 70
Sr. No.
Village name
Name of structures
Type of treatment Type of land Target IWMP Convergence
(i) Ridge area (R)
(ii) Drainage
line (D)
(iii) Land dev. (L)
(i) Pri-vate (P)
(ii) Comm-unity
(C)
(iii) Forest
(F)
No. of units (No./
cu.m./ rmt)
Estimated cost (Rs. in lakh) Expected
month & year of
completion (mm/yyyy)
No. of units (No./
cu.m./ rmt)
Estimated cost (Rs. in lakh) No. of
units (No./
cu.m./ rmt)
Cost Department M W
Unit Cost (In Rs.)
T M W O T
2 Biliya
Gully Plug (Cement) 50 1400 0.70 50 1400 0.70
Stone Bund LBS 110 120 0.13 110 120 0.13
Nala Plug (Cement) 96 1400 1.34 96 1400 1.34
Protection Wall R L P F 2 2.1 4.20 0 0 0.00 2.00 4.20 MGNREGA
Farm Bund - L P 3700 2.405 2.41 0 0 0.00 3700.00 2.41 GLDC Check Dam - D P F 4 450000 18.00 2 4.5 9.00 2.00 9.00 MGNREGA
Earthen Dam - - L P - - 1 400000 4.00 1 400000 4.00 0.00
Total 30.78 15.18 15.61
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 71
Sr. No.
Village name
Name of structures
Type of treatment Type of land Target IWMP Convergence
(i) Ridge area (R)
(ii) Drainage
line (D)
(iii) Land dev. (L)
(i) Pri-vate (P)
(ii) Comm-
unity (C)
(iii) Forest
(F)
No. of units (No./
cu.m./ rmt)
Estimated cost (Rs. in lakh) Expected
month & year of
completion (mm/yyyy)
No. of units (No./
cu.m./ rmt)
Estimated cost (Rs. in lakh) No. of units (No./
cu.m./ rmt)
Cost Department M W
Unit Cost (In Rs.)
T M W O T
3 Chari
Contour Trench R - - - - F 3000 20 0.60 3000 20 0.60 0.00 0.00
Gully Plug LBS - D L P - F 100 120 0.12 100 120 0.12 0.00
Plantation R - - - - F 1500 20 0.30 1500 0.30 1500.00 0.30 MGNREGA Gully Plug (Cement) D L P 400 1400 5.60 400 1400 5.60
Nala Plug (Cement) - D L P 180 1400 2.52 180 1400 2.52 0.00
Stone Bund (Cement) R L P F 100 1400 1.40 1400 1400 1.4 0.00
Field Water Outlet
- L P 9 7500 0.68 9 7500 0.68 0.00
Check Dam - D P F 2 450000 9.00 1 450000 4.50 1.00 4.50 MGNREGA Farm Bund - - L P - - 1465 65 0.95 1465 65 0.95 0.00 Land Levelling L P 10 11000 1.10 10 11000 1.10 0.00
Cementry Nala Plug ( SmollCheck Wall)
4 7860 3.14 4 7860 0.31 0.00
Pond Renovition 1 80000 0.80 1 80000 0.80 0.00
Total 26.21 0 8070 0 0 0 21.41125 0.00 4.80 MGNREGA
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 72
Sr. No.
Village name
Name of structures
Type of treatment Type of land Target IWMP Convergence
(i) Ridge area (R)
(ii) Drainage
line (D)
(iii) Land dev. (L)
(i) Pri-vate (P)
(ii) Comm-unity
(C)
(iii) Forest
(F)
No. of units (No./
cu.m./ rmt)
Estimated cost (Rs. in lakh) Expected
month & year of
completion (mm/yyyy)
No. of units (No./
cu.m./ rmt)
Estimated cost (Rs. in lakh) No. of
units (No./
cu.m./ rmt)
Cost Department M W
Unit Cost (In Rs.)
T M W O T
4 Dumaka
Gully Plug LBS - D L P - F 100 120 0.12 100 120 0.12 0.00
Gully Plug (Cement) R L P F 70 1400 0.98 70 1400 0.98 0.00
Stone Bund LBS 10 7500 0.75 10 7500 0.75 0.00
Protection Wall L P 2 350000 7.00 0 0 0.00 2.00 7.00 MGNREGA
Farm Bund 3110 65 2.02 3110 65 2.02 0.00 Cementry Nala Plug ( SmollCheck Wall)
3 7860 2.36 3 7860 2.36 0.00
Check Dam 7 450000 31.50 4 4.5 18.00 3.00 13.50 MGNREGA Check Wall Disilting - D P F 1 44000 0.44 1 1 0.44 1.00 0.44
Total 45.17 0 3298 0 0 24.67 6.00 20.94
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 73
Sr. No
.
Village name
Name of structure
s
Type of treatment Type of land Target IWMP Convergence
(i) Ridg
e area (R)
(ii) Drainag
e line (D)
(iii) Lan
d dev. (L)
(i) Pri-vat
e (P)
(ii) Comm-unity
(C)
(iii) Fores
t (F)
No. of units (No./ cu.m.
/ rmt)
Estimated cost (Rs. in lakh)
Expected month & year of
completion
(mm/yyyy)
No. of units (No./ cu.m.
/ rmt)
Estimated cost (Rs. in lakh) No. of
units (No./ cu.m.
/ rmt)
Cost Department M W
Unit Cost (In Rs.)
T M W O T
5 Kanakuva
Gully Plug LBS - D L P - F 30 120 0.04 30 120 0.04 0.00
Gully Plug (Cement) - D L P 65 1400 0.91 65 1400 0.91 0.00
Stone Bund (Cement)
R L P F 100 1400 1.40 100 1400 1.40 0.00
Stone Bund LBS 120 120 0.14 120 120 0.14
Farm Bund - - L P - - 1000 65 0.65 0 0 0.00
1000.00 0.65 GLDC
Check Wall - D P F 3 45000
0 13.50 2 450000 9.00 1.00 4.50 MGNRE
GA Pond Renovition
2 100000 2.00 0 0 0.00 2.00 2.00
MGNREGA
Total 18.64 0 0 0 11.49 7.15
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 74
Sr. No
.
Village
name
Name of structure
s
Type of treatment Type of land Target IWMP Convergence
(i) Ridg
e area (R)
(ii) Drainag
e line (D)
(iii) Lan
d dev. (L)
(i) Pri-vat
e (P)
(ii) Comm-unity
(C)
(iii) Fores
t (F)
No. of units (No./
cu.m./ rmt)
Estimated cost (Rs. in lakh) Expected
month & year of
completion
(mm/yyyy)
No. of units (No./ cu.m.
/ rmt)
Estimated cost (Rs. in lakh)
No. of
units
(No./
cu.m./
rmt)
Cost Department
M W
Unit Cost (In Rs.)
T M W O T
6 Kantu
Nala Plug (Cement) - D L P 200 1400 2.80 200 1400 2.80
Stone Bund (Cement)
R L P F 100 1400 1.40 100 1400 1.40
Protection Wall L P 2 35000
0 7.00 0 0 0.00 2.00 7.00 MGNREGA
Farm Bund - - L P - - 2150 65 1.40 2150 65 1.40
Land Levelling - - L P - - 20 11000 2.20 20 11000 2.20
Check Dam - D P F 12 45000
0 54.00 9 450000 40.50 3.00 13.50 MGNREGA
Earthen Dam - - L P - - 2 30000
0 6.00 2 300000 6.00
Total 74.80 0 2481 0 0 54.30 5.00 20.50
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 75
Sr. No.
Village name
Name of structures
Type of treatment Type of land Target IWMP Convergence
(i) Ridge area (R)
(ii) Drainage
line (D)
(iii) Land dev. (L)
(i) Pri-vate (P)
(ii) Comm-unity
(C)
(iii) Forest
(F)
No. of units (No./
cu.m./ rmt)
Estimated cost (Rs. in lakh) Expected
month & year of
completion (mm/yyyy)
No. of units (No./
cu.m./ rmt)
Estimated cost (Rs. in lakh) No. of
units (No./
cu.m./ rmt)
Cost Department
M W
Unit Cost (In Rs.)
T M W O T
7 Ladvavad
Gully Plug LBS - - 0.00 0.00
Gully Plug (Cement) - D L P 15 1400 0.21 15 1400 0.21 0.00
Nala Plug (Cement) - D L P 50 1400 0.70 50 1400 0.70 0.00
Stone Bund (Cement)
R L P F 60 1400 0.84 60 1400 0.84
Protection Wall L P 6 350000 21.00 0 0 0.00 6.00 21.00 MGNREGA
Farm Bund - - L P - - 280 65 0.18 280 65 0.18 Check Dam - D P F 1 450000 4.50 1 450000 4.50
Total 27.43 0 406 0 0 454265 6.43 6.00 21.00
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 76
Sr. No
.
Village name
Name of structure
s
Type of treatment Type of land Target IWMP Convergence
(i) Ridg
e area (R)
(ii) Drainag
e line (D)
(iii) Lan
d dev. (L)
(i) Pri-vat
e (P)
(ii) Comm-unity
(C)
(iii) Fores
t (F)
No. of units (No./ cu.m.
/ rmt)
Estimated cost (Rs. in lakh)
Expected
month & year
of comple
tion (mm/y
yyy)
No. of units (No./ cu.m.
/ rmt)
Estimated cost (Rs. in lakh) No.
of units (No./ cu.m.
/ rmt)
Cost Department
M W
Unit Cost (In
Rs.)
T M W O T
8 Limdimendhri
Gully Plug LBS - D L P - F 400 120 0.48 400 120 0.04 0.00
Gully Plug (Cement) - D L P 600 1400 8.40 600 1400 8.40 0.00
Nala Plug LBS - D L P 400 120 0.48 400 120 0.48
Nala Plug (Cement) - D L P 700 1400 9.80 700 1400 9.80 0.00
Stone Bund LBS R L P F 620 120 0.74 620 120 0.74
Stone Bund (Cement)
R L P F 560 1400 7.84 560 1400 7.84
Field Water Outlet
- L P 49 7500 3.68 49 7500 3.68 0.00
Farm Bund - - L P - - 3080 65 2.00 3080 65 2.00
Cementry Nala Plug ( SmollCheck Wall)
- D P F 4 7860 3.14 4 7860 3.14 0.00
Check Dam - D P F 8 45000
0 36.00 6 450000 27.00 2.00 9.00
MGNREGA
Total 72.57 0 6419 0 0 63.12 2.00 9.00
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 77
Sr. No.
Village name
Name of structures
Type of treatment Type of land Target IWMP Convergence
(i) Ridge area (R)
(ii) Drainage
line (D)
(iii) Land dev. (L)
(i) Pri-vate (P)
(ii) Comm-unity
(C)
(iii) Forest
(F)
No. of units (No./
cu.m./ rmt)
Estimated cost (Rs. in lakh) Expected
month & year of
completion (mm/yyyy)
No. of units (No./
cu.m./ rmt)
Estimated cost (Rs. in lakh) No. of
units (No./
cu.m./ rmt)
Cost Department
M W
Unit Cost (In Rs.)
T M W O T
9 Nanslay
Gully Plug LBS - D L P - F 110 120 0.13 110 120 0.13 0.00
Gully Plug (Cement) - D L P - F 600 1400 8.40 600 1400 8.40 0.00
Nala Plug LBS - D L P 200 120 0.24 200 120 0.24
Nala Plug (Cement) - D L P 250 1400 3.50 250 1400 3.50 0.00
Stone Bund (Cement) R L P F 250 1400 3.50 250 1400 3.50 0.00
Farm Bund - - L P - - 3500 65 2.28 3500 65 2.28 Land Levelling - - L P - - 7 11000 0.77 7 11000 0.77
Cementry Nala Plug ( SmollCheck Wall)
- D P F 3 7860 2.36 3 7860 2.36 0.00
Check Dam - D P F 3 450000 13.50 2 450000 9.00 1.00 4.50 MGNREGA
Total 34.68 0 4922 0 0 473365 30.18 1.00 4.50 MGNREGA
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 78
Sr. No.
Village name
Name of structures
Type of treatment Type of land Target IWMP Convergence
(i) Ridge area (R)
(ii) Drainage
line (D)
(iii) Land dev. (L)
(i) Pri-vate (P)
(ii) Comm-
unity (C)
(iii) Forest
(F)
No. of units (No./
cu.m./ rmt)
Estimated cost (Rs. in lakh) Expected
month & year of
completion (mm/yyyy)
No. of units (No./
cu.m./ rmt)
Estimated cost (Rs. in lakh) No. of
units (No./
cu.m./ rmt)
Cost Department M W
Unit Cost (In Rs.)
T M W O T
10 Pipriya
Contour Trench R - - - - F 1140 20 0.23 1140 20 0.23 0.00 0.00
Plantation R - - - - F 1000 20 0.20 0 0.00 1000.00 0.20 Social Forest Gully Plug (Cement) - D L P - F 170 1400 2.38 170 1400 2.38 0.00
Stone Bund (Cement) R L P F 100 1400 1.40 100 1400 1.40 0.00
Field Water Outlet
- L P 35 7500 2.63 35 7500 2.63 0.00
Farm Bund - - L P - - 2100 65 1.37 0 0 0.00 2100.00 1.37 GLDC Cementry Nala Plug ( SmollCheck Wall)
- D P F 2 7860 1.57 2 7860 1.57 0.00
Check Dam - D P F 2 450000 9.00 1 450000 4.50 1.00 4.50 MGNREGA Total 18.77 0 1448 0 0 468180 12.71 3101.00 6.07 MGNREGA
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 79
Sr. No.
Village name
Name of structures
Type of treatment Type of land Target IWMP Convergence
(i) Ridge area (R)
(ii) Drainage
line (D)
(iii) Land dev. (L)
(i) Pri-vate (P)
(ii) Comm-unity
(C)
(iii) Forest
(F)
No. of units (No./
cu.m./ rmt)
Estimated cost (Rs. in lakh) Expected
month & year of
completion (mm/yyyy)
No. of units (No./
cu.m./ rmt)
Estimated cost (Rs. in lakh) No. of
units (No./
cu.m./ rmt)
Cost Department M W
Unit Cost (In Rs.)
T M W O T
11 Rachhva
Gully Plug (Cement) - D L P - F 100 1400 1.40 100 1400 1.40 0.00
Nala Plug LBS - D L P 300 120 0.36 300 120 0.36
Nala Plug (Cement) - D L P 600 1400 8.40 600 1400 8.40 0.00
Stone Bund (Cement) R L P F 185 1400 2.59 185 1400 2.59 0.00
Field Water Outlet
- L P 19 7500 1.43 19 7500 1.43 0.00
Farm Bund - - L P - - 690 65 0.45 690 65 0.45 0.00 0.00 Land Levelling - - L P - - 2 11000 0.22 2 11000 0.22
Cementry Nala Plug ( SmollCheck Wall)
- D P F 8 7860 6.29 8 7860 6.29 0.00
Check Dam - D P F 5 450000 22.50 3 450000 13.50 2.00 9.00 MGNREGA Cause Way 1 350000 3.50 1 350000 3.50 0.00
Total 47.13 0 0 0 830745 38.13 2.00 9.00 MGNREGA
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 80
Sr. No.
Village name
Name of structures
Type of treatment Type of land Target IWMP Convergence
(i) Ridge area (R)
(ii) Drainage
line (D)
(iii) Land dev. (L)
(i) Pri-vate (P)
(ii) Comm-unity
(C)
(iii) Forest
(F)
No. of units (No./
cu.m./ rmt)
Estimated cost (Rs. in lakh) Expected
month & year of
completion (mm/yyyy)
No. of units (No./
cu.m./ rmt)
Estimated cost (Rs. in lakh) No. of
units (No./
cu.m./ rmt)
Cost Department M W
Unit Cost (In Rs.)
T M W O T
12 Sangasar
Farm Bund - - L P - - 1000 65 0.65 0 0 0.00 1000.00 0.65 GLDC Check Dam - D P F 4 450000 18.00 2 450000 9.00 2.00 9.00 MGNREGA Checkwall Disiling - D P F 1 70000 0.70 0 0 0.00 1.00 0.70 MGNREGA
Cause Way 1 375000 3.75 1 375000 3.75 0.00
Total 28.61 12.75 10.35 MGNREGA
13 Simamoi
Contour Trench R - - - - F 3000 20 0.60 3000 20 0.60 0.00
Gully Plug (Cement) D L P - F 100 1400 1.40 100 1400 1.40 0.00
Plantation R - - - - F 1000 20 0.20 0 0 0.00 1000.00 0.20 Social Forest Nala Plug (Cement) - D L P 500 1400 7.00 500 1400 7.00 0.00
Stone Bund (Cement) R L P F 238 1400 3.33 238 1400 3.33 0.00
Field Water Outlet
- L P 20 7500 1.50 20 7500 1.50 0.00
Farm Bund - - L P - - 700 65 0.46 700 65 0.46 0.00 0.00 Cementry Nala Plug ( SmollCheck Wall)
- D P F 4 7860 3.14 4 7860 3.14 0.00
Check Dam - D P F 6 450000 27.00 4 450000 18.00 2.00 9.00 MGNREGA Total 44.63 0 0 0 35.43 1002.00 9.20 MGNREGA
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 81
Sr. No. Village name Name of
structures
Type of treatment Type of land Target IWMP Convergence
(i) Ridge area (R)
(ii) Drainage
line (D)
(iii) Land dev. (L)
(i) Pri-vate (P)
(ii) Comm-unity
(C)
(iii) Forest
(F)
No. of units (No./
cu.m./ rmt)
Estimated cost (Rs. in lakh) Expected
month & year of
completion (mm/yyyy)
No. of units (No./
cu.m./ rmt)
Estimated cost (Rs. in lakh) No. of
units (No./
cu.m./ rmt)
Cost Department M W
Unit Cost (In Rs.)
T M W O T
14 Udhalmahuda
Contour Trench R - - - - F 3000 20 0.60 3000 20 0.60 0.00
Plantation R - - - - F 1500 20 0.30 0 0 0.00 1500.00 0.30 Social Forest Gully Plug LBS - D L P 300 120 0.36 300 120 0.36
Gully Plug (Cement) D L P - F 350 1400 4.90 350 1400 4.90 0.00
Nala Plug LBS - D L P 400 120 0.48 400 120 0.48
Nala Plug (Cement) - D L P 450 1400 6.30 450 1400 6.30 0.00
Stone Bund (Cement) R L P F 170 1400 2.38 170 1400 2.38 0.00
Farm Bund - - L P - - 2140 65 1.39 2140 65 1.39 0.00 0.00 Cementry Nala Plug ( SmollCheck Wall)
- D P F 3 7860 2.36 3 7860 2.36 0.00
Check Dam - D P F 2 450000 9.00 1 450000 4.50 1.00 4.50 MGNREGA Checkwall Disiling - D P F 1 40000 0.40 0 0 0.00 1.00 0.40 MGNREGA
Total 28.47 0 6814 0 0 23.27 1502.00 5.20
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 82
Sr. No.
Village name
Name of structures
Type of treatment Type of land Target IWMP Convergence
(i) Ridge area (R)
(ii) Drainage
line (D)
(iii) Land dev. (L)
(i) Pri-vate (P)
(ii) Comm-unity
(C)
(iii) Forest
(F)
No. of units (No./
cu.m./ rmt)
Estimated cost (Rs. in lakh) Expected
month & year of
completion (mm/yyyy)
No. of units (No./
cu.m./ rmt)
Estimated cost (Rs. in lakh) No. of
units (No./
cu.m./ rmt)
Cost Department M W
Unit Cost (In Rs.)
T M W O T
15 Ulakadar
Gully Plug LBS - D L P 200 120 0.24 200 120 0.24
Nala Plug LBS D L P - F 630 120 0.76 630 120 0.76 0.00
Nala Plug (Cement) D L P - F 100 1400 1.40 100 1400 1.40 0.00
Stone Bund (Cement)
R L P F 460 1400 6.44 460 1400 6.44 0.00
Farm Bund - - L P - - 5500 65 3.58 0 0 0.00 5500.00 3.58 GLDC Check Dam - D P F 8 450000 36.00 4 450000 18.00 4.00 18.00 MGNREGA
Checkwall Repairing D P F 2 150000 3.00 2 150000 3.00 0.00
Cause Way 2 350000 7.00 2 350000 7.00 0.00 Total 58.41 1398 36.84 21.58
Grand Total 626.49 456.60 180.05
(M – Materials, W- wages, O- others, T – Total)
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 83
Table no.37: Activities related to Surface water resources in the project areas (all financial figures in lakh Rs.)
Sr. No. Village name Type of structures
Proposed target Augmentation/ repair of existing
structures Construction of new structures Total target
No. Area to be irrigated
(ha)
Storage capacity
Estimated cost No.
Area to be
irrigated (ha)
Storage capacity
Estimated cost
Area to be
irrigated (ha)
Storage capacity
Estimated cost
1 Ambli Menpur Check Dam/Earthen Band - - - - 4 40 20000 18 40 20000 18 Total - - - - 4 40 20000 18 40 20000 18
2 Biliya Check Dam/Earthen Band - - - - 2 20 8000 9 20 8000 9 Total - - - - 2 20 8000 9 20 8000 9
3 Chari Check Dam - - - - 1 5 3000 4.5 5 3000 4.5 Total 0 0 0 0 1 5 3000 4.5 5 3000 4.5
4 Dumka Check Dam 1 3 3000 0.44 4 40 20000 18 43 23000 18.44 Total 1 3 3000 0.44 4 40 20000 18 43 23000 18.44
5 Kanakuwa Check Dam - - - - 2 20 8000 9 20 8000 9 Total 2 20 8000 9 20 8000 9
6 Kantu Check Dam/Earthen Band - - - - 9 90 35000 54 90 35000 54 Total 9 90 35000 54 90 35000 54
7 Ladva Vad Check Dam - - - - 1 5 3000 4.5 5 3000 4.5 Total - - - - 1 5 3000 4.5 5 3000 4.5
8 Limdi Medhri Check Dam - - - - 6 60 28000 27 60 28000 27 Total - - - - 6 60 28000 27 60 28000 27
9 Nan Salai Check Dam - - - - 2 20 8000 9 20 8000 9 Total - - - - 2 20 8000 9 20 8000 9
10 Pipariya (To) Check Dam - - - - 1 5 3000 4.5 5 3000 4.5 Total - - - - 1 5 3000 4.5 5 3000 4.5
11 Rachhava Check wall - - - - 3 25 11000 13.5 25 11000 13.5 Total - - - - 3 25 11000 13.5 25 11000 13.5
12 Sangasar Check Dam/Earthen Band - - - - 2 20 8000 9 20 8000 9 Total - - - - 2 20 8000 9 20 8000 9
13 Simamoi Check Dam - - - - 4 40 20000 18 40 20000 18 Total - - - - 4 40 20000 18 40 20000 18
14 Udhal Mahuda Check Dam 1 3 3000 0.44 1 5 3000 4.5 5 3000 4.5 Total - - - - 1 5 3000 4.5 5 3000 4.5
15 Ulkadar Check Dam - - - - 4 40 20000 18 40 20000 18 Total - - - - 4 40 20000 18 40 20000 18
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 84
Table no.38: Activities related to recharging ground water resources in the project areas (all financial figures in lakh Rs.)
Sr. No. Name of Villages Type of structures
Proposed target Augmentation/ repair of existing recharging
structures Construction of new recharging
structures Total target
No. Area to be irrigated (ha)
Estimated cost No. Area to be
irrigated (ha) Estimated
cost
Area to be irrigated
(ha)
Estimated cost
1 Ambli Menpur (i)Check Dam/Earthen Bund - - - 6 60 20 60 20 Total for the village - - - 6 60 20 60 20 2 Biliya (i)Check Dam/Earthen Bund - - - 3 27 13 27 13 Total for the village - - - 3 27 13 27 13 3 Chari (i)Check Dam/Pond Renovation 1 2 0.8 2 16 9 10 9.8 Total for the village 1 2 0.8 2 16 9 10 9.8 4 Dumka (i)Check Dam 1 3 0.44 7 55 31.5 58 31.94 Total for the village 1 3 0.44 7 55 31.5 58 31.94 5 Kanakuwa (i)Check Dam/Pond Renovation 2 4 2 3 27 13.5 31 15.5 Total for the village 2 4 2 3 27 13.5 31 15.5 6 Kantu (i)Check Dam/Earthen Bund - - - 14 80 60 80 60 Total for the village - - - 14 80 60 80 60 7 Ladva Vad (i)Check Dam - - - 1 5 4.5 5 4.5 Total for the village - - - 1 5 4.5 5 4.5 8 Limdi Medhri (i)Check Dam - - - 8 45 36 45 36 Total for the village - - - 8 45 36 45 36 9 Nan Salai (i)Check Dam - - - 3 20 13.5 20 13.5 Total for the village - - - 3 20 13.5 20 13.5
10 Pipariya (To) (i)Check Dam - - - 2 15 9 15 9 Total for the village - - - 2 15 9 15 9
11 Rachhava (i)Check Dam - - - 5 40 22.5 40 22.5 Total for the village - - - 5 40 22.5 40 22.5
12 Sangasar (i)Check Dam/Earthen Bund 1 10 0.7 5 40 21.75 50 91.75 Total for the village 1 10 0.7 5 40 21.75 50 91.75
13 Simamoi (i)Check Dam - - - 6 45 27 45 27 Total for the village - - - 6 45 27 45 27
14 Udhal Mahuda (i)Check Dam 1 3 0.4 2 15 9 15 9 Total for the village 1 3 0.4 2 15 9 15 9
15 Ulkadar (i)Check Dam 2 6 3 8 45 36 45 36 Total for the village 2 6 3 8 45 36 45 36
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 85
Table no.39: Details of activities related to livelihood, production system and micro- enterprise
Sr. No.
Name of village Activity Name of
structure/ work
Type of land Executing agency Target
(i) Private
(ii) Community
(iii) Others
(pl. specify)
(i) UG (ii)SHG
(iii) Others
(pl. specify)
No. of plants/No
unit
Area (ha)
Unit Cost (In Rs.)
Estimated cost
(Lakh)
From IWMP
(In lakh)
Convergence (In Lakh) Scheme
Expected month & year of
completion (mm/ yyyy)
1 Amlimenpur
Agriculture Based
Crop Demonstration (Maize, Soyabean, SWI)
P 4 21000 0.84 0.84 Dec-16
Vegetable Kithen Garden P C UG/SHG 5 8500 0.43 0.43 Dec-16
Vegetable Kithen Garden (Mandva) P C UG/SHG 7 24000 1.68 1.68 Dec-16
Drip Irrigation P 10 100000 10.00 2.50 7.50 TASP ,GGRC Dec-16
Vermi Compost P C UG/SHG 15 18000 2.70 1.44 1.26 FOREST Dec-16 Floriculture P C UG/SHG 4 11000 0.44 0.44 Dec-16 Agro Centre P C UG/SHG 1 200000 2.00 2.00 Dec-16
Animal Husbandry
Based
Poultry Farm P C UG/SHG 1 125000 1.25 1.25 Dec-16 Animal Health Cattle Camp P UG/SHG 6 9900 0.59 0.59 Dec-16
Agro Processing Flour Mill P UG/SHG 1 75000 0.75 0.75 Dec-16
Other Minor activity
Tent P UG/SHG 1 200000 2.00 2.00 Dec-16 Cement Mixture P UG/SHG 1 150000 1.50 1.50 Dec-16 Provision Store P UG/SHG 1 200000 2.00 2.00 Dec-16 Tailoring P 5 15000 0.75 0.75 Dec-16 Leathering work P 2 25000 0.50 0.50 Dec-16
Total 64 0 125000 27.43 18.67 8.76
2 Biliya
Agriculture Based
Crop Demonstration (Maize, Soyabean, SWI)
P 2 21000 0.42 0.42 Dec-16
Vegetable Kithen Garden P C UG/SHG 5 8500 0.43 0.43 Dec-16
Animal Husbandry
Based
Poultry Farm P C UG/SHG 1 125000 1.25 1.25 Dec-16 Animal Health Cattle Camp P UG/SHG 3 9900 0.30 0.30 Dec-16
Agro Processing Flour Mill P UG/SHG 1 75000 0.75 0.75 Dec-16 Other Minor
activity Provision Store P UG/SHG 1 200000 2.00 2.00 Dec-16
Total 13 0 125000 5.14 5.14 0.00 Dec-16
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 86
Sr. No.
Name of
village Activity Name of structure/
work
Type of land Executing agency Target
(i) Private
(ii) Community
(iii) Others
(pl. specify)
(i) UG (ii)SHG
(iii) Others
(pl. specify)
No. of plants/No
unit
Area (ha)
Unit Cost (In
Rs.)
Estimated cost
(Lakh)
From IWMP
(In lakh)
Convergence (In Lakh) Scheme
Expected month & year of
completion (mm/ yyyy)
3 Chari
Agriculture Based
Crop Demonstration (Maize, Soyabean) P 2 21000 0.42 0.42 0.14 Dec-16
Vegetable Kithen Garden P C UG/SHG 4 8500 0.34 0.34 Dec-16
Vegetable Kithen Garden (Mandva) P C UG/SHG 3 24000 0.72 0.72 Dec-16
Drip Irrigation P C UG/SHG 3 100000 3.00 0.75 2.25 TASP ,GGRC Dec-16
Vermi Compost P C UG/SHG 5 18000 0.90 0.72 Dec-16 Animal
Husbandry Based
Animal Health Cattle Camp P
UG/SHG 3 9900 0.30 0.30 Dec-16
Agro Processing Flour Mill P UG/SHG 1 75000 0.75 0.75 Dec-16
Other Minor activity
Tent P UG/SHG 1 200000 1.25 1.25 Dec-16 Cement Mixture P UG/SHG 1 150000 1.50 1.50 Dec-16 Tailoring P 2 15000 0.30 0.30 Dec-16
Total 25 0 621400 9.48 7.05 2.25
4 Dumaka
Agriculture Based
Crop Demonstration (Maize, Soyabean) P 4 21000 0.84 0.84 Dec-16
Vegetable Kithen Garden P C UG/SHG 4 8500 0.34 0.34 Dec-16
Drip Irrigation P C UG/SHG 6 100000 6.00 1.50 4.50 TASP ,GGRC Dec-16
Vermi Compost P C UG/SHG 7 18000 1.26 1.26 Dec-16 Floriculture P C UG/SHG 2 11000 0.22 0.22 Dec-16 Nursery C UG/SHG 1 75000 0.75 0.75 Dec-16
Animal Husbandry
Based
Poultry Farm P C UG/SHG 1 125000 1.25 1.25 Dec-16 Animal Health Cattle Camp P UG/SHG 4 9900 0.46 0.46 Dec-16
Agro Processing Flour Mill UG/SHG 1 75000 0.75 0.75 Dec-16 Other Minor
activity Tent UG/SHG 2 200000 2.00 2.00 Dec-16 Tailoring P C UG/SHG 4 15000 0.60 0.60 Dec-16
Total 36 0 658400 14.47 9.97 4.50
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 87
Sr. No.
Name of village Activity Name of structure/
work
Type of land Executing agency Target
(i) Private
(ii) Community
(iii) Others
(pl. specify)
(i) UG (ii)SHG
(iii) Others
(pl. specify)
No. of plants/No
unit
Area (ha)
Unit Cost (In Rs.)
Estimated cost
(Lakh)
From IWMP
(In lakh)
Convergence (In Lakh) Scheme
Expected month & year of
completion (mm/ yyyy)
5 Kanakuva
Agriculture Based
Crop Demonstration (Maize, Soyabean) P 2 21000 0.42 0.42 Dec-16
Vermi Compost P C UG/SHG 2 18000 0.36 0.36 Dec-16 Animal
Husbandry Based
Poultry Farm P C UG/SHG 1 125000 1.25 1.25 Dec-16 Animal Health Cattle Camp P UG/SHG 1 9900 0.12 0.12 Dec-16
Agro Processing Flour Mill 1 75000 0.75 0.75 Dec-16
Other Minor activity Cattering 1 95000 1.00 1.00 Dec-16
Total 8 0 343900 3.90 3.90 0.00
6 Kantu
Agriculture Based
Crop Demonstration (Maize, Soyabean) P 4 21000 0.84 0.84 Dec-16
Vegetable Kithen Garden P C UG/SHG 9 8500 0.77 0.77 Dec-16
Drip Irrigation P C UG/SHG 4 100000 4.00 1.00 3.00 TASP ,GGRC Dec-16
Vermi Compost P C UG/SHG 8 18000 1.44 1.44 Dec-16 Nursery P C UG/SHG 1 75000 0.75 0.75 Dec-16 Agro Centre 1 200000 2.00 2.00 Dec-16
Animal Husbandry
Based
Poultry Farm P C UG/SHG 1 125000 1.25 1.25 Dec-16 Animal Health Cattle Camp P UG/SHG 3 9900 0.33 0.33 Dec-16
Agro Processing Flour Mill 2 75000 1.50 1.50 Dec-16
Other Minor activity
Tent P UG/SHG 1 200000 2.00 2.00 Dec-16 Cattering P UG/SHG 1 200000 2.00 2.00 Dec-16 Cement Mixture P C UG/SHG 1 150000 1.50 1.50 Dec-16 Provision Store P UG/SHG 1 200000 2.00 2.00 Dec-16 Tailoring P 4 15000 0.60 0.60 Bamboo work P 3 15000 0.45 0.45 Dec-16
Total 44 0 1412400 21.42 18.42 3.00
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 88
Sr. No.
Name of village Activity Name of
structure/ work
Type of land Executing agency Target
(i) Private
(ii) Community
(iii) Others
(pl. specify)
(i) UG (ii)SHG
(iii) Others
(pl. specify)
No. of plants/No
unit
Area (ha)
Unit Cost (In Rs.)
Estimated cost
(Lakh)
From IWMP
(In lakh)
Convergence (In Lakh) Scheme
Expected month & year of
completion (mm/ yyyy)
7 Ladvavad
Agriculture Based
Crop Demonstration (Maize, Soyabean)
P 2 21000 0.42 0.42 Dec-16
Vegetable Kithen Garden (Mandva) P C UG/SHG 1 24000 0.24 0.24 Dec-16
Drip Irrigation P C UG/SHG 4 100000 4.00 1.00 3.00 TASP ,GGRC Dec-16
Vermi Compost P C UG/SHG 5 18000 0.90 0.36 0.54 MGNREGA Dec-16 Animal
Husbandry Based
Animal Health Cattle Camp P C
UG/SHG 2 9900 0.16 0.16
Dec-16
Total 14 0 172900 5.72 2.18 3.54
8 Limdimendhri
Agriculture Based
Crop Demonstration (Maize, Soyabean)
P 6 21000 1.26 1.26 Dec-16
Fruit Orchard (Mango, Chiku, Lemon, Custard)
4 20000 0.80 0.80 Dec-16
Vegetable Kithen Garden P C UG/SHG 4 8500 0.34 0.34 Dec-16
Vegetable Kithen Garden (Mandva) P C UG/SHG 6 24000 1.44 1.44 Dec-16
Drip Irrigation P C UG/SHG 11 100000 11.00 2.75 8.25 TASP ,GGRC Dec-16
Vermi Compost P C UG/SHG 8 18000 1.44 1.44 Dec-16 Agro Centre P C UG/SHG 1 200000 2.00 2.00 Dec-16
Animal Husbandry
Based
Poultry Farm P C UG/SHG 1 125000 1.25 1.25 Dec-16 Animal Health Cattle Camp P UG/SHG 5 9900 0.54 0.54 Dec-16
Agro Processing Flour Mill UG/SHG 2 75000 1.50 1.50 Dec-16
Other Minor
activity
Tent P 1 200000 2.00 2.00 Dec-16 Cattering P C UG/SHG 1 200000 2.00 2.00 Dec-16 Cement Mixture P 1 150000 1.50 1.50 Dec-16 Provision Store P 1 200000 2.00 2.00 Tailoring P 5 15000 0.75 0.75
Total 57 0 1366400 29.82 21.57 8.25 Dec-16
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 89
Sr. No.
Name of
village Activity Name of structure/ work
Type of land Executing agency Target
(i) Private
(ii) Community
(iii) Others
(pl. specify)
(i) UG (ii)SHG
(iii) Others
(pl. specify)
No. of plants/No
unit
Area (ha)
Unit Cost (In
Rs.)
Estimated cost
(Lakh)
From IWMP
(In lakh)
Convergence (In Lakh) Scheme
Expected month & year of
completion (mm/ yyyy)
9 Nanslay
Agriculture Based
Crop Demonstration (Maize, Soyabean) P 2 21000 0.42 0.42 Dec-16
Fruit Orchard (Mango, Chiku, Lemon, Custard) P C UG/SHG 2 20000 0.40 0.40 Dec-16
Vegetable Kithen Garden P C UG/SHG 3 8500 0.26 0.26 Dec-16 Vegetable Kithen Garden (Mandva) P C UG/SHG 2 24000 0.48 0.48 Dec-16
Drip Irrigation P C UG/SHG 2 100000 2.00 0.50 1.50 TASP ,GGRC Dec-16
Vermi Compost P C UG/SHG 10 18000 1.80 1.08 0.72 MGNREGA Dec-16 Nursery C UG/SHG 1 75000 0.75 0.75 Dec-16
Animal Husbandry
Based Animal Health Cattle Camp P C
UG/SHG 3 9900 0.27 0.27 Dec-16
Agro Processing Flour Mill 1 75000 0.75 0.75 Dec-16
Other Minor
activity
Provision Store P 1 200000 2.00 2.00 Dec-16 Tailoring P C UG/SHG 6 15000 0.90 0.90 Dec-16 Bamboo work 2 15000 0.30 0.30 Dec-16
Total 35 0 581400 10.32 8.10 2.22 Dec-16
10 Pipriya
Agriculture Based
Crop Demonstration P 2 21000 0.42 0.42 Dec-16 Vegetable Kitchen Garden P C UG/SHG 7 8500 0.60 0.60 Dec-16 Vegetable Kitchen Garden (Mandva) P C UG/SHG 2 24000 0.48 0.48 Dec-16
Drip Irrigation P C UG/SHG 2 100000 2.00 0.50 1.50 TASP ,GGRC Dec-16
Vermi Compost P C UG/SHG 8 18000 1.44 0.00 1.44 MGNREGA Dec-16 Agro Centre P C UG/SHG 1 200000 2.00 2.00 Dec-16
Animal Husbandry
Based Animal Health Cattle Camp
3 9900 0.32 0.32 Dec-16
Total 25 0 381400 7.25 4.31 2.94 Dec-16
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 90
Sr. No.
Name of village Activity Name of structure/
work
Type of land Executing agency Target
(i) Private
(ii) Community
(iii) Others
(pl. specify)
(i) UG (ii)SHG
(iii) Others
(pl. specify)
No. of plants/No
unit
Area (ha)
Unit Cost (In
Rs.)
Estimated cost
(Lakh)
From IWMP
(In lakh)
Convergence (In Lakh) Scheme
Expected month & year of
completion (mm/ yyyy)
11 Rachhva
Agriculture Based
Crop Demonstration P 2 21000 0.42 0.42 Dec-16 Vegetable Kitchen Garden 4 8500 0.34 0.34 Dec-16
Vegetable Kitchen Garden (Mandva) P C UG/SHG 2 24000 0.48 0.48 Dec-16
Drip Irrigation P C UG/SHG 4 100000 4.00 1.00 3.00 TASP ,GGRC Dec-16
Vermi Compost P C UG/SHG 5 18000 0.90 0.90 Dec-16 Nursery P C UG/SHG 1 75000 0.75 0.75 Dec-16 Agro Centre P C UG/SHG 1 200000 2.00 2.00 Dec-16
Animal Husbandry
Based
Poultry Farm 1 125000 1.25 1.25 Dec-16 Animal Health Cattle Camp P C UG/SHG 3 10000 0.30 0.30 Dec-16
Agro Processing Flour Mill P UG/SHG 1 75000 0.75 0.75 Dec-16
Other Minor activity
Tent 1 200000 2.00 2.00 Dec-16 Provision Store 1 200000 2.00 2.00 Dec-16 Tailoring 5 15000 0.75 0.75 Dec-16
Total 15.94 12.94 3.00 Dec-16
12 Sangasar
Agriculture Based Nursery P C UG/SHG 1 75000 0.75 0.75 Dec-16
Animal Husbandry Based
Poultry Farm 1 125000 1.25 1.25 Dec-16 Animal Health Cattle Camp P C UG/SHG 3 10000 0.32 0.32 Dec-16
Agro Processing Flour Mill P UG/SHG 1 75000 0.75 0.75 Dec-16 Other Minor activity Tent 1 125000 1.25 1.25 Dec-16
Total 7 0 410000 4.32 4.32 0.00
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 91
Sr. No.
Name of village Activity Name of structure/
work
Type of land Executing agency Target
(i) Private
(ii) Community
(iii) Others
(pl. specify)
(i) UG (ii)SHG
(iii) Others
(pl. specify)
No. of plants/No
unit
Area (ha)
Unit Cost (In
Rs.)
Estimated cost
(Lakh)
From IWMP
(In lakh)
Convergence (In Lakh) Scheme
Expected month & year of
completion (mm/ yyyy)
13 Simamoi
Agriculture Based
Crop Demonstration P C UG/SHG 2 21000 0.42 0.42 Dec-16 Fruit Orchard (Mango, Chiku, Lemon, Custard)
P C
UG/SHG 2 20000 0.40 0.40 Dec-16
Vegetabel Kitchen Garden P C UG/SHG 12 8500 1.02 1.02 Dec-16
Vegetable Kitchen Garden (Mandva) P C UG/SHG 1 24000 0.24 0.24 Dec-16
Drip Irrigation 10 100000 10.00 2.50 7.50 TASP ,GGRC Dec-16
Vermi Compost P C UG/SHG 9 18000 1.62 1.62 Dec-16 Animal Husbandry Based
Animal Health Cattle Camp P
UG/SHG 3 10000 0.32 0.32 Dec-16
Other Minor
activity
Tent 1 200000 2.00 2.00 Dec-16 Cement Mixture 1 150000 1.50 1.50 Dec-16 Provision Store 1 200000 2.00 2.00
Total 6 0 560000 19.52 12.02 7.50
14 Udhalmahuda
Agriculture Based Crop Demonstration P C UG/SHG 2 21000 0.42 0.42 Dec-16
Vegetabel Kitchen Garden P C UG/SHG 3 8500 0.26 0.26 Dec-16
Drip Irrigation P C UG/SHG 2 100000 2.00 0.50 1.50 TASP ,GGRC Dec-16
Vermi Compost P C UG/SHG 5 18000 0.90 0.90 Dec-16 Animal
Husbandry Based
Poultry Farm P C UG/SHG 1 125000 1.25 1.25 Dec-16 Animal Health Cattle Camp P UG/SHG 3 10000 0.32 0.32 Dec-16
Agro Processing Flour Mill 1 75000 0.75 0.75 Dec-16
Other Minor
activity
Tent 1 150000 1.50 1.50 Dec-16
Provision Store 1 200000 2.00 2.00 Dec-16
Total 6 0 435000 9.40 7.90 1.50
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 92
Sr. No.
Name of village Activity Name of structure/
work
Type of land Executing agency Target
(i) Private
(ii) Community
(iii) Others
(pl. specify)
(i) UG (ii)SHG
(iii) Others
(pl. specify)
No. of plants/No
unit
Area (ha)
Unit Cost (In
Rs.)
Estimated cost
(Lakh)
From IWMP
(In lakh)
Convergence (In Lakh) Scheme
Expected month & year of
completion (mm/ yyyy)
15 Ulkadar
Agriculture Based
Crop Demonstration P C UG/SHG 2 21000 0.42 0.42 Dec-16 Fruit Orchard (Mango, Chiku, Lemon, Custard)
P C
UG/SHG 2 20000 0.40 0.40 Dec-16
Vegetabel Kitchen Garden P C UG/SHG 6 8500 0.51 0.51 Dec-16
Vegetable Kitchen Garden (Mandva) P C UG/SHG 3 24000 0.72 0.72 Dec-16
Drip Irrigation 8 100000 8.00 2.00 6.00 TASP ,GGRC Dec-16
Vermi Compost 5 18000 0.90 0.90 Dec-16 Animal
Husbandry Based
Poultry Farm 2 125000 2.50 2.50 Animal Health Cattle Camp 3 10000 0.30 0.30
Agro Processing Flour Mill 1 75000 0.75 0.75
Other Minor
activity
Tent 1 200000 2.00 2.00
Provision Store 1 200000 2.00 2.00
Total 22 0 150500 18.50 12.50 6.00 Grand Total 202.63 148.99 53.46 0
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 93
Table no. 40: Activities related to livelihoods by Self Help Groups (SHGs) in the project areas
Sr. No. Names of Villages Major activities of the SHGs
Name of activity No. of SHGs involved Average annual income from activity per SHG
1 Ambli Menpur
Agro Centre 1 125000.00 Poultry Farm 1 75000.00 Cement Mixuture 1 90000.00 Flour Mill 1 32000.00 Tailoring 1 30000.00 Tent 1 145000.00 Provision Store 1 120000.00
Total 7 617000.00
2 Biliya Poultry Farm 1 75000.00 Flour Mill 1 32000.00 Provision Store 1 120000.00
Total 3 227000.00
3 Chari
Nursery 1 35000.00 Poultry Farm 1 75000.00 Flour Mill 1 32000.00 Tailoring 1 30000.00 Tent 1 100000.00
Total 5 272000.00
4 Dumka
Nursery 1 35000.00 Poultry Farm 1 75000.00 Flour Mill 1 32000.00 Tailoring 1 30000.00 Tent 1 145000.00
Total 5 317000.00
5 Kanakuwa
Poultry Farm 1 75000.00 Flour Mill 1 32000.00 Cattering 1 50000.00 Tailoring 1 30000.00
Total 4 187000.00
6 Kantu
Agro Centre 1 125000.00 Nursery 1 35000.00 Poultry Farm 1 75000.00 Flour Mill 1 32000.00 Tailoring 1 30000.00 Tent 1 145000.00 Provision Store 1 120000.00 Bamboo work 1 30000.00
Total 8 592000.00
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 94
Sr. No. Names of Villages Major activities of the SHGs
Name of activity No. of SHGs involved Average annual income from activity per SHG
7 Ladva Vad Vegetable Kitchen Garden 1 25000.00 Vermi Compost 1 65000.00 Total 2 90000.00
8 Limdi Medhri
Agro Centre 1 125000.00 Poultry Farm 1 75000.00 Flour Mill 2 64000.00 Tailoring 1 30000.00 Provision Store 1 120000.00 Cattering 1 115000.00 Tent 1 145000.00 Total 8 674000.00
9 Nan Salai
Nursery 1 35000.00 Flour Mill 1 32000.00 Tailoring 1 30000.00 Provision Store 1 120000.00 Bamboo work 1 30000.00 Tent 1 145000.00
6 392000.00
10 Pipariya (To)
Vegetable Kitchen Garden 1 25000.00 Vermi Compost 1 65000.00 Agro Centre 1 125000.00 Nursery 1 35000.00 Total 4 250000.00
11 Rachhava
Agro Centre 1 125000.00 Nursery 1 35000.00 Poultry Farm 1 75000.00 Flour Mill 1 32000.00 Tailoring 1 30000.00 Provision Store 1 120000.00 Tent 1 145000.00 Total 7 562000.00
12 Sangasar
Nursery 1 35000.00 Poultry Farm 1 75000.00 Flour Mill 1 32000.00 Tent 1 100000.00 Total 4 242000.00
13 Simamoi Vegetable Kitchen Garden 1 25000.00 Tent 1 145000.00 Total 2 170000.00
14 Udhal Mahuda
Poultry Farm 1 75000.00 Flour Mill 1 32000.00 Tent 1 100000.00 Provision Store 1 120000.00 Total 4 327000.00
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 95
Sr. No. Names of Villages Major activities of the SHGs
Name of activity No. of SHGs involved Average annual income from activity per SHG
15 Ulkadar
Poultry Farm 1 75000.00 Flour Mill 1 32000.00 Provision Store 1 120000.00 Tent 1 145000.00 Total 4 372000.00
4.4 Vermi Composting unit for Chakliya village 4.4.1 Introduction
The process of composting crop residues using earthworms comprise spreading the agricultural wastes and cow dung in layers as 1.5 m wide and 0.9 m high beds of required length. Earthworms are introduced in between the layers @ 350 worms per m3 of bed volume. The beds are maintained at about 40 – 50% moisture content and a temperature of 20 – 30 oC by sprinkling water over the beds. The earthworms being voracious eaters consume the biodegradable matter and give out a part of the matter as excreta or vermi-castings. The vermi-casting containing nutrients are rich manure for the plants.
4.4.2 About the worms
Eisenia fetida, Eudrilus eugeniae, and Perionyx excavatius are some of the species for rearing to convert organic wastes into manure. The worms feed on any biodegradable matter ranging from coir waste to kitchen garbage and vermin composting units are ideally suited to locations / units with generation of considerable quantities of organic wastes. One earthworm reaching reproductive age of about six week lays one egg capsule (containing 7 embryos) every 7 – 10 days. Three to seven worms emerge out of each capsule. Thus, the multiplication of worms under optimum growth conditions is very fast. The worms live for about 2 years. Fully grown worms could be separated and dried in an oven to make ‘worm meal’ which a rich source of protein (70%) is for use ini animal feed.
4.4.3 Location
Nadhelav watershed villages have lots of animals so it can become good vermi compost centre as well as good source of livelihood. Vermi Compost is very suitable for fruit, flower and vegetable as well as cereal crops. It increases quality and quantity of product in per unit area.
4.4.4 Use
Put lack irrigation arid desert so chemical is not advisable so to increate nutritive value of soil and available farmyard manure vermi compost has more nutrient compare to other manures and fertilizer so by the use of vermi compost we can reduce use of chemical fertilizer. Vermi compost not only supply nutrient but also improve quantity of hormones for plant growth, improves the soil structure leading to increase in water and nutrient holding capacities of soil.
4.5 Components of a Commercial Unit
4.5.1 Sheds
Chakliya watershed villages have high temperature in summer so we need a shed structure for vermi compost unit. We can make it by the use of concrete pillars because this will act as a source of income for those in the village who produce pillars. It will prevent wetting of beds due to rain on a windy day.
While designing the sheds adequate room has to be left around the beds for easy movement of the labour attending to the filling and harvesting the beds.
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 97
4.5.2 Vermi-beds
Scientific bed size is 75 cm – 90 cm thick depending on the provision of filter for drainage of excess water. The whole bed area should be above the ground. The bed should have a uniform height over the entire width to the extent possible to avoid low production owing to low bed volumes. The proper bed width should not be more than 1.5 m to allow easy access to the centre of the bed.
4.5.3 Land
About 135 square meter of land will be required to set up a vermi compost production unit in Chakliya watershed villages. It should have at least 2 to 3 sheds each of about 180 – 200 sq feet. It should have a good watering arrangement and other equipments as required because moisture is very essential for vermi compost production. We can take land from Gram Panchayat and it can be taken on lease of at least 10 – 15 years.
4.5.4 Seed Stock
This is very important thing because worms multiply at the rate of 350 worms per m3 of bed space over a period of 6 month to a year.
4.5.5 Fencing
The entire area has to be fenced to prevent the animals and other unwanted elements. These could be estimated based on the length of the periphery of the farm.
4.5.6 Water Supply System We have to maintain always 50% moisture content, there is need to plan for a water source, lifting mechanism and a system of conveying and applying the water to the vermi-beds. Drippers with round the clock flow arrangement would be quite handy for continuous supply and saving on water. Such a water supply / application system requiring considerable initial investment, however, reduces the operational costs on hand watering and proves economical in the long run. The cost of these items depends on the capacity of the unit and the type of water supply chosen.
4.5.7 Machinery
Farm machinery and implements are required for cutting the raw material in small pieces, conveying shredded raw material to the vermi-sheds, loading, unloading, collection of compost, loosening of beds for aeration, shifting of the compost. Costs of providing necessary implements and the machinery have to be included in the project cost.
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 98
Table no. 41: Linkages developed at village level
Sr. No. Village Name of activity Forward/Backward linkage Linkage with Outcome
1 Amlimenpur
Crop Demonstration KVK APMC Vegetable Kitchen Garden KVK APMC Vegetable Kitchen Garden (Mandva) KVK APMC Drip Irrigation GGRC Vermi Compost Floriculture KVK Agro Centre Poultry Farm ANIMAL HUSBUNDARY Animal Health Cattle Camp ANIMAL HUSBUNDARY Flour Mill Tent Cement Mixture Provision Store Tailoring Leathering Work
2 Biliya
Crop Demonstration KVK APMC Vegetable Kithen Garden KVK APMC Poultry Farm ANIMAL HUSBUNDARY Animal Health Cattle Camp ANIMAL HUSBUNDARY Flour Mill
3 Chari
Crop Demonstration KVK Vegetable Kithen Garden KVK Vegetable Kithen Garden (Mandva) KVK Drip Irrigation GGRC Vermi Compost Animal Health Cattle Camp ANIMAL HUSBUNDARY Flour Mill Tent Cement Mixture Tailoring
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 99
Sr. No. Village Name of activity Forward/Backward linkage Linkage with Outcome
4 Dumka
Crop Demonstration KVK Vegetable Kithen Garden KVK Drip Irrigation GGRC Vermi Compost Floriculture Nursery Poultry Farm ANIMAL HUSBUNDARY Animal Health Cattle Camp ANIMAL HUSBUNDARY Flour Mill Tent Tailoring
5
Kanakuva
Crop Demonstration KVK Vermi Compost Poultry Farm ANIMAL HUSBUNDARY Animal Health Cattle Camp ANIMAL HUSBUNDARY Flour Mill
Cattering
6 Kantu
Crop Demonstration KVK Vegetable Kithen Garden KVK Drip Irrigation GGRC Vermi Compost Nursery Agro Centre Poultry Farm ANIMAL HUSBUNDARY Animal Health Cattle Camp ANIMAL HUSBUNDARY Flour Mill Tent Cattering Cement Mixture Provision Store Tailoring Bamboo work
7 Ladvavad
Crop Demonstration KVK Vegetable Kithen Garden (Mandva) KVK Drip Irrigation GGRC Vermi Compost Animal Health Cattle Camp ANIMAL HUSBUNDARY
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 100
Sr. No. Village Name of activity Forward/Backward linkage Linkage with Outcome
8 Limadi Mendhari
Crop Demonstration KVK Fruit Orchard (Mango, Chiku, Lemon, Custard) Horticulture Vegetable Kithen Garden KVK Vegetable Kithen Garden (Mandva) KVK Drip Irrigation GGRC Vermi Compost Agro Centre Poultry Farm ANIMAL HUSBUNDARY Animal Health Cattle Camp ANIMAL HUSBUNDARY Flour Mill Tent Cattering Cement Mixture Provision Store Tailoring
9 Nansalai
Crop Demonstration KVK Fruit Orchard (Mango, Chiku, Lemon, Custard) Vegetable Kithen Garden KVK Vegetable Kithen Garden (Mandva) KVK Drip Irrigation GGRC Vermi Compost Nursery Animal Health Cattle Camp ANIMAL HUSBUNDARY Flour Mill Provision Store Tailoring Bamboo work
10 Pipariya
Crop Demonstration KVK Vegetable Kitchen Garden KVK Vegetable Kitchen Garden (Mandva) KVK Drip Irrigation GGRC Vermi Compost Agro Centre Animal Health Cattle Camp ANIMAL HUSBUNDARY
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 101
Sr. No. Village Name of activity Forward/Backward linkage Linkage with Outcome
11 Rachava
Crop Demonstration KVK Vegetable Kitchen Garden KVK Vegetable Kitchen Garden (Mandva) KVK Drip Irrigation GGRC Vermi Compost Nursery Agro Centre Poultry Farm Animal Health Cattle Camp ANIMAL HUSBUNDARY Flour Mill Tent Provision Store Tailoring
12 Sangasar
Nursery Poultry Farm ANIMAL HUSBUNDARY Animal Health Cattle Camp ANIMAL HUSBUNDARY Flour Mill Tent
13 Simamoi
Crop Demonstration KVK Fruit Orchard (Mango, Chiku, Lemon, Custard) Horticulture Vegetabel Kitchen Garden KVK Vegetable Kitchen Garden (Mandva) KVK Drip Irrigation GGRC Vermi Compost Animal Health Cattle Camp ANIMAL HUSBUNDARY Tent Cement Mixture Provision Store
14 Udhalmahuda
Crop Demonstration KVK Vegetabel Kitchen Garden KVK Drip Irrigation GGRC Vermi Compost Poultry Farm ANIMAL HUSBUNDARY Animal Health Cattle Camp ANIMAL HUSBUNDARY Flour Mill Tent Provision Store
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 102
Sr. No. Village Name of activity Forward/Backward linkage Linkage with Outcome
15 Ulkadar
Crop Demonstration KVK Fruit Orchard (Mango, Chiku, Lemon, Custard) Horticulture Vegetabel Kitchen Garden KVK Vegetable Kitchen Garden (Mandva) KVK Drip Irrigation GGRC Vermi Compost Poultry Farm ANIMAL HUSBUNDARY Animal Health Cattle Camp ANIMAL HUSBUNDARY Flour Mill Tent Provision Store
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 103
Table no.42: Details of activities connected with vegetative cover in watershed works
Sr.no Name of village
Name of structure/ work
Type of treatment Type of land Executing agency Target
(i) Ridge area (R)
(ii) Drainage
line (iii) Land dev. (L)
(i) Private
(ii) Community
(iii) Others
(pl. specify)
(i) UG
Area (ha)
No. of plants/No.
Estimated cost Expected
month & year of
completion (mm/ yyyy)
(D) (ii)SHG (Rs. in lakh)
(iii) Others
(pl. specify)
1 Amlimenpur
Dripirrigation v L P C UG/SHG 10 10 10.00 Dec-16 Demonstration Plot v v L C UG/SHG 2 4 0.84 Dec-16 Horticulture Plant v v L P C UG/SHG 0 0 0.00 Dec-16 Vegetable Kitchen Gardening v v L P C UG/SHG 0.7 12 2.11 Dec-16
Plantation On Gauchar land v v L C UG/SHG 0 0 0.00 Dec-16
Floriculture v v L P C UG/SHG 0.8 4 0.44 Dec-16 Vermi Compost v v L P C UG/SHG 0.9 15 2.25 Dec-16 Nursery v v L P C UG/SHG 0 0 0.00 Dec-16
15.63500
2 Biliya
Dripirrigation v L P C UG/SHG 0 0 0.00 Dec-16 Demonstration Plot v v L C UG/SHG 1 2 0.42 Dec-16 Horticulture Plant v v L P C UG/SHG 0 0 0.00 Dec-16 Vegetable Kitchen Gardening v v L P C UG/SHG 0.3 5 0.43 Dec-16
Plantation On Gauchar land v v L C UG/SHG 0 0 0.00 Dec-16
Floriculture v v L P C UG/SHG 0 0 0.00 Dec-16 Vermi Compost v v L P C UG/SHG 0 0 0.00 Dec-16 Nursery v v L P C UG/SHG 0 0 0.00 Dec-16
0.84500
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 104
Sr.no Name of village Name of structure/ work
Type of treatment Type of land Executing agency Target
(i) Ridge area (R)
(ii) Drainage
line (iii) Land dev. (L)
(i) Private
(ii) Community
(iii) Others
(pl. specify)
(i) UG
Area (ha)
No. of plants/No.
Estimated cost
Expected month & year of
completion (mm/ yyyy)
(D) (ii)SHG (Rs. in lakh)
(iii) Others (pl. specify)
3 Chari
Demonstration Plot v v L C UG/SHG 1 2 0.42 Dec-16 Vegetable Kitchen Gardening v v L P C UG/SHG 0.3 7 1.06 Dec-16 Dripirrigation v v L C UG/SHG 3 3 3.00 Dec-16 Floriculture v v L P C UG/SHG 0 0 0.00 Dec-16 Vermi Compost v v L P C UG/SHG 0.2 5 0.90 Dec-16
5.380000
4 Dumaka
Dripirrigation v L P C UG/SHG 6 6 6.00 Dec-16 Demonstration Plot v v L C UG/SHG 2 4 0.60 Dec-16 Horticulture Plant v v L P C UG/SHG 0 0 0.00 Dec-16 Vegetable Kitchen Gardening v v L P C UG/SHG 0.3 4 0.34 Dec-16 Plantation On Gauchar land v v L C UG/SHG 0 0 0.00 Dec-16 Floriculture v v L P C UG/SHG 0.6 2 0.22 Dec-16 Vermi Compost v v L P C UG/SHG 0.5 7 1.26 Dec-16
8.42000
5 Kanakuva
Demonstration Plot v v L C UG/SHG 1 2 0.42 Dec-16 Horticulture Plant v v L P C UG/SHG 0 0 0.00 Dec-16 Vegetable Kitchen Gardening v v L P C UG/SHG 0 0 0.00 Dec-16 Plantation On Gauchar land v v L C UG/SHG 0 0 0.00 Dec-16 Floriculture v v L P C UG/SHG 0 0 0.00 Dec-16 Vermi Compost v v L P C UG/SHG 0.6 2 0.36 Dec-16 Nursery v v L P C UG/SHG 0 0 0.00 Dec-16
0.78000
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 105
Sr.no Name of village
Name of structure/ work
Type of treatment Type of land Executing agency Target
(i) Ridge area (R)
(ii) Drainage
line (iii) Land dev. (L)
(i) Private
(ii) Community
(iii) Others
(pl. specify)
(i) UG
Area (ha)
No. of plants/No.
Estimated cost Expected
month & year of
completion (mm/ yyyy)
(D) (ii)SHG (Rs. in lakh)
(iii) Others
(pl. specify)
6 Kantu
Demonstration Plot v v L C UG/SHG 0.8 4 0.84 Dec-16 Horticulture Plant v v L P C UG/SHG 0 0 0.00 Dec-16 Vegetable Kitchen Gardening v v L P C UG/SHG 0.04 9 0.77 Dec-16
Dripirrigation v v L C UG/SHG 4 4 1.00 Dec-16 Floriculture v v L P C UG/SHG 0 0 0.00 Dec-16 Vermi Compost v v L P C UG/SHG 0.08 8 1.44 Dec-16 Nursery v v L P C UG/SHG 0 0 0.00 Dec-16
4.05
7 Ladvavad
Demonstration Plot v v L C UG/SHG 1 2 0.42 Dec-16 Horticulture Plant v v L P C UG/SHG 0 0 0.00 Dec-16 Vegetable Kitchen Gardening v v L P C UG/SHG 0.02 1 0.24 Dec-16
Dripirrigation v v L C UG/SHG 4 4 4.00 Dec-16 Vermi Compost v v L P C UG/SHG 0.07 5 0.90 Dec-16
5.56
8 Limdimendhri
Dripirrigation v L P C UG/SHG 11 11 11.00 Dec-16 Demonstration Plot v v L C UG/SHG 0.3 6 1.26 Dec-16 Horticulture Plant v v L P C UG/SHG 0.4 4 0.80 Dec-16 Vegetable Kitchen Gardening v v L P C UG/SHG 1.02 10 1.78 Dec-16
Plantation On Gauchar land v v L C UG/SHG 0 0 0.00 Dec-16
Floriculture v v L P C UG/SHG 0 0 0.00 Dec-16 Vermi Compost v v L P C UG/SHG 0.004 8 1.44 Dec-16 Nursery v v L P C UG/SHG 0 0 0.00 Dec-16
16.28
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 106
Sr.no Name of village Name of structure/ work
Type of treatment Type of land Executing agency Target
(i) Ridge area (R)
(ii) Drainage
line (iii) Land dev. (L)
(i) Private
(ii) Community
(iii) Others
(pl. specify)
(i) UG
Area (ha)
No. of plants/No.
Estimated cost Expected
month & year of
completion (mm/ yyyy)
(D) (ii)SHG (Rs. in lakh)
(iii) Others
(pl. specify)
9 Nanslay
Demonstration Plot v v L C UG/SHG 0.1 2 0.42 Dec-16 Horticulture Plant v v L P C UG/SHG 0.02 2 0.40 Dec-16 Vegetable Kitchen Gardening v v L P C UG/SHG 0.5 5 0.74 Dec-16
Dripirrigation v v L C UG/SHG 2 2 2.00 Dec-16 Vermi Compost v v L P C UG/SHG 0.12 10 1.80 Dec-16
5.36
10 Pipriya
Demonstration Plot v v L C UG/SHG 0.1 2 0.42 Dec-16 Vermi Compost v v L P C UG/SHG 0.1 8 1.44 Dec-16 Dripirrigation v v L C UG/SHG 2 2 2.00 Dec-16 Vegetable Kitchen Gardening v v L P C UG/SHG 0.4 9 1.08 Dec-16
4.94
11 Rachhva
Dripirrigation v L P C UG/SHG 4 4 4.00 Dec-16 Demonstration Plot v v L C UG/SHG 0.1 2 0.42 Dec-16 Horticulture Plant v v L P C UG/SHG 0 0 0.00 Dec-16 Vegetable Kitchen Gardening v v L P C UG/SHG 0.3 6 0.82 Dec-16
Plantation On Gauchar land v v L C UG/SHG 0 0 0.00 Dec-16 Floriculture v v L P C UG/SHG 0 0 0.00 Dec-16 Vermi Compost v v L P C UG/SHG 0.1 5 0.90 Dec-16 Nursery v v L P C UG/SHG 0.02 1 0.75 Dec-16
6.89
12 Sangasar Dripirrigation v L P C UG/SHG 0 0 0.00 Dec-16 Nursery v v L P C UG/SHG 0.02 1 0.75 Dec-16
0.75
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 107
Sr.no Name of village Name of structure/ work
Type of treatment Type of land Executing agency Target
(i) Ridge area (R)
(ii) Drainage
line (iii) Land dev. (L)
(i) Private
(ii) Community
(iii) Others
(pl. specify)
(i) UG
Area (ha)
No. of plants/No.
Estimated cost
Expected month & year of
completion (mm/ yyyy)
(D) (ii)SHG (Rs. in lakh)
(iii) Others
(pl. specify)
13 Simamoi
Dripirrigation v L P C UG/SHG 10 10 10.00 Dec-16 Demonstration Plot v v L C UG/SHG 0.1 2 0.42 Dec-16 Horticulture Plant v v L P C UG/SHG 0.02 2 0.40 Dec-16 Vegetable Kitchen Gardening v v L P C UG/SHG 0.5 13 1.26 Dec-16 Plantation On Gauchar land v v L C UG/SHG 0 0 0.00 Dec-16 Floriculture v v L P C UG/SHG 0 0 0.00 Dec-16 Vermi Compost v v L P C UG/SHG 0.2 9 1.62 Dec-16 Nursery v v L P C UG/SHG 0 0 0.00 Dec-16
13.70
14 Udhalmahuda
Dripirrigation v L P C UG/SHG 2 2 2.00 Dec-16 Demonstration Plot v v L C UG/SHG 0.1 2 0.42 Dec-16 Horticulture Plant v v L P C UG/SHG 0 0 0.00 Dec-16 Vegetable Kitchen Gardening v v L P C UG/SHG 0.1 3 0.26 Dec-16 Plantation On Gauchar land v v L C UG/SHG 0 0 0.00 Dec-16 Floriculture v v L P C UG/SHG 0 0 0.00 Dec-16 Vermi Compost v v L P C UG/SHG 0.1 5 0.90 Dec-16 Nursery v v L P C UG/SHG 0 0 0.00 Dec-16
3.58
15 Ulkadar
Dripirrigation v L P C UG/SHG 8 8 2.00 Dec-16 Demonstration Plot v v L C UG/SHG 0.1 2 0.42 Dec-16 Horticulture Plant v v L P C UG/SHG 0.1 2 0.40 Dec-16 Vegetable Kitchen Gardening v v L P C UG/SHG 0.3 9 1.23 Dec-16 Plantation On Gauchar land v v L C UG/SHG 0 0 0.00 Dec-16 Floriculture v v L P C UG/SHG 0 0 0.00 Dec-16 Vermi Compost v v L P C UG/SHG 0 0 0.00 Dec-16 Nursery v v L P C UG/SHG 0 0 0.00 Dec-16
4.05
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 108
Table no.43: Details of activities in the CPRs in the project areas
Sr. No. Name(s) of the villages CPR particulars Activity proposed
Target Target area under the
activity (ha)
Estimated expenditure (Rs.)
Expected no. of beneficiaries
1 Amlimenpur
Gully Plug LBS 5 0.54 100 Gully Plug (Cement) 12 1.33 19 Nala Plug LBS 13 1.53 134 Nala Plug (Cement) 63 7.56 54 Check Dam 188 22.50 5 Earthen Dam 41 5.00 2
322 38.46000 314 2
Biliya
Gully Plug (Cement) 9 0.70 12 Nala Plug (Cement) 12 1.34 8 Check Dam 150 18 4 Earthen Dam 33 4 1
24.04400 25
3 Chari
Plantation 1.5 0.3 1 Contour Trench 2 0.60 1 Gully Plug (Cement) 47 5.60 100 Check Dam 20 9 2 Pond Renovition 2 0.80 1
16.300000 105
4 Dumaka Gully Plug (Cement) 9 0.98 30 Check Dam 260 31.50 7 Check Wall Disilting 4 0.44 1
32.92000 38
5 Kanakuva
Gully Plug LBS 3 0.036 10 Gully Plug (Cement) 8 0.91 15 Check Wall 30 13.5 3 Pond Renovition 10 2 2
16.44600 30
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 109
Sr. No. Name(s) of the villages CPR particulars Activity proposed
Target Target area under
the activity (ha) Estimated expenditure (Rs.) Expected no. of beneficiaries
6 Kantu Nala Plug (Cement) 24 2.80 25 Check Dam 150 54.00 12 Earthen Dam 10 6.00 2
62.80000 39 7 Ladvavad 2
Gully Plug (Cement) 3 0.21 5 Nala Plug (Cement) 6 0.70 6 Check Dam 7 4.50 1
5.41000 14 8 Limdimendhri Gully Plug LBS 8 0.48 93
Gully Plug (Cement) 70 8.40 140 Nala Plug LBS 10 0.48 40 Nala Plug (Cement) 85 9.80 80 Check Dam 50 36 8
55.16000 361
9 Nanslay
Gully Plug LBS 5 0.13 28 Gully Plug (Cement) 70 8.40 50 Nala Plug LBS 5 0.24 20 Nala Plug (Cement) 8 3.50 20 Check Dam 15 13.5 3
25.77200 121
10 Pipriya
Plantation 1 0.2 1 Contour Trench 1 0.228 1 Gully Plug (Cement) 20 2.38 47 Check Dam 15 9 2
11.80800 51
11 Rachhva
Gully Plug (Cement) 4 1.40 30 Nala Plug LBS 0.1 0.36 14 Nala Plug (Cement) 0 8.40 90 Check Dam 0.3 22.50 5 Cause Way 0 3.50 1
36.16000 140
12 Sangasar Check Dam 30 18.00 4
Checkwall Disiling 2 0.7 1 Earthen Dam 10 3.75 1
22.45000 6
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 110
Sr. No. Name(s) of the villages CPR
particulars Activity proposed
Target
Target area under the
activity (ha)
Estimated expenditure (Rs.)
Expected no. of beneficiaries
13 Simamoi
Plantation 1 0.30 1 Contour Trench 2 0.60 1 Gully Plug (Cement) 4 0.40 17 Nala Plug (Cement) 11 1.26 34 Check Dam 35 27 6
29.56000 59
14 Udhalmahuda
Plantation 1 0.30 1 Contour Trench 1 0.60 1 Gully Plug (Cement) 40 4.90 52 Nala Plug (Cement) 10 6.30 60 Check Dam 10 9.00 2
21.10000 116
15 Ulkadar
Gully Plug LBS 2 0.24 38 Nala Plug LBS 7 0.76 58 Nala Plug (Cement) 12 1.40 10 Check Dam 35 36 8
38.39600 114
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 111
Table no. 44: Capacity Building Institution
Sr. No. Name of the Training Institute
Full Address with contact no., website &
Type of Institute#
Area(s) of speciali-zation$
Accredita-tion details
Trainings
Reference Year No. of trainings assigned
No. of trainees to be trained
1 N.M Sadguru Water And Development
Foundation
Post Box – 71, Dahod – 389151, Gujarat, PH No –
0091-2673-238601, FAX-0091-2673-238604,
Email Address: [email protected]
Autonomous Body
Capacity Building, Training
Programme Under Watershed
Development Programme
NGO 2012-13 12 230
2 Krushi Vigyan Kendra (KVK)
Anand Agricultural University, Dahod –
389151, PH No – 02673-245659
Research Institute Capacity Building /
Training Programme
University 2012-13 5 42
# Central govt. Dept./ State govt. Dept./ Autonomous Body/ Research Institutes/ Universities/ Others (pl. specify)
$ Capacity Building/ Agriculture/ Horticulture/ Animal Husbandry/ Pisciculture/ Remote Sensing/ Water conservation/ Ground water/ Forestry/ livelihoods/ entrepreneurship development/ others (pl. specify) Table no. 45: Capacity Building plan
Sr. No. District Project Stakeholders Total no. of persons No. of persons to be trained
No. of training programmes Estimated cost
1 Dahod
PIA 4 5 8 12000 WDTs 6 6 8 14400
UGs 1281 1281 43 384300 SHGs 353 353 12 105900 WCs 207 207 7 62100 GPs 90 90 3 27000
Community 9000 3600 120 1080000 Others
(Pl. specify) Total: 10941 5542 201 1685700
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 112
Table no.46: Information, education and Communication Activities Sr. No. Activity Executing agency Estimated expenditure
(Rs.) Outcome
(may quantify, wherever possible) 1 Street Plays
DWDU - Dahod / Social Forestry
120000
Awarness regarding watershed projects to the village peoples.
2 Video Shows 120000 3 Pamphlets & Posters 220000 4 Banners & Hoardings 46014 5 Education 120000 6 wall Painting 350000
Total: 976014
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 113
CHAPTER 5 – BUGETING
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 114
Table no. 47: Budget at a glance for the project Sr.No. Budget component Cost requirement Cost requirement
1 Administrative costs 10 78.5388 2 Monitoring 1 7.85388 3 Evaluation 1 7.85388 4 Entry Point activity 4 31.41552 5 Institution and Capacity Building 5 39.2694 6 Detailed Project Report 1 7.85388 7 Watershed Development Works 56 439.81728 8 Livelihood activities for asset less 9 70.68492 9 Production systems and micro-enterprises 10 78.5388
10 Consolidation phase 3 23.56164 TOTAL 100 785.388
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 115
Table no. 48: Village wise- component wise budget available under IWMP
Sr. No Village Proposed
Area Cost in Lakh
Activity
EPA (4%)
Institution and CB (5%)
DPR (1%) Watershed
development Work (56%)
Watershed development Work (15%)
Livelihood for asset
less (9%)
Production system and
Microenterprises (10%)
Consolidation (3%) Total Total
Livelihood
1 Ambli Menpur 819.03 98.2836 3.931344 4.91418 0.982836 55.038816 8.2558224 8.845524 9.82836 2.948508 94.74539 18.67388 2 Biliya 225.85 27.102 1.08408 1.3551 0.27102 15.17712 2.276568 2.43918 2.7102 0.81306 26.12633 5.14938 3 Chari 318.62 38.2344 1.529376 1.91172 0.382344 21.411264 3.2116896 3.441096 3.82344 1.147032 36.85796 7.264536 4 Dumka 437.12 52.4544 2.098176 2.62272 0.524544 29.374464 4.4061696 4.720896 5.24544 1.573632 50.56604 9.966336 5 Kanakuwa 170.99 20.5188 0.820752 1.02594 0.205188 11.490528 1.7235792 1.846692 2.05188 0.615564 19.78012 3.898572 6 Kantu 808.02 96.9624 3.878496 4.84812 0.969624 54.298944 8.1448416 8.726616 9.69624 2.908872 93.47175 18.42286 7 Ladva Vad 95.76 11.4912 0.459648 0.57456 0.114912 6.435072 0.9652608 1.034208 1.14912 0.344736 11.07752 2.183328 8 Limdi Medhri 945.91 113.509 4.540368 5.67546 1.135092 63.565152 9.5347728 10.215828 11.35092 3.405276 109.4229 21.56675 9 Nan Salai 355.33 42.6396 1.705584 2.13198 0.426396 23.878176 3.5817264 3.837564 4.26396 1.279188 41.10457 8.101524 10 Pipariya (To) 189.07 22.6884 0.907536 1.13442 0.226884 12.705504 1.9058256 2.041956 2.26884 0.680652 21.87162 4.310796 11 Rachhava 567.52 68.1024 2.724096 3.40512 0.681024 38.137344 5.7206016 6.129216 6.81024 2.043072 65.65071 12.93946 12 Sangasar 189.78 22.7736 0.910944 1.13868 0.227736 12.753216 1.9129824 2.049624 2.27736 0.683208 21.95375 4.326984 13 Simamoi 527.27 63.2724 2.530896 3.16362 0.632724 35.432544 5.3148816 5.694516 6.32724 1.898172 60.99459 12.02176 14 Udhal Mahuda 346.34 41.5608 1.662432 2.07804 0.415608 23.274048 3.4911072 3.740472 4.15608 1.246824 40.06461 7.896552 15 Ulkadar 548.29 65.7948 2.631792 3.28974 0.657948 36.845088 5.5267632 5.921532 6.57948 1.973844 63.42619 12.50101
Total 6544.9 785.388 31.41552 39.2694 7.85388 439.81728 65.972592 70.68492 78.5388 23.56164 757.114 149.2237
Table no. 49: Village wise gap in funds requirement
Sr. No Village Total cost requirement Total funds available under IWMP Gap in funds requirement 1 Ambli Menpur 122.2036 98.2836 23.92 2 Biliya 42.712 27.102 15.61 3 Chari 45.2844 38.2344 7.05 4 Dumka 77.4544 52.4544 25 5 Kanakuwa 27.67 20.52 7.15 6 Kantu 120.46 96.96 23.5 7 Ladva Vad 36.03 11.49 24.54 8 Limdi Medhri 130.76 113.51 17.25 9 Nan Salai 49.36 42.64 6.72
10 Pipariya (To) 31.69 22.69 9.005 11 Rachhava 80.10 68.10 12 12 Sangasar 33.12 22.77 10.35 13 Simamoi 79.97 63.27 16.7 14 Udhal Mahuda 48.26 41.56 6.7 15 Ulkadar 93.37 65.79 27.58
Total 1018.44 785.39 233.075
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 116
Convergence Opportunities
Micro Irrigation Horticulture and
Bamboo Making
NRM Related
Irrigation Rural Development Forest Agriculture Tribal Development
State Finance Commission
NREGS TASP Sakhi Mandal, SGSY
(Self Employment)
Social Capital
IWMP
INTEGRATED
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 117
Table no.50: Details of Convergence of IWMP with other Schemes
Sr. No. Village Phase/ Type of
work* Activity to be carried out
Fund made available to IWMP due to
convergence (Rs. in lakh)
Scheme with which
convergence took place
Reference no. of activity/ task/
structure in DPR
Level at which decision for
convergence was taken
1 Ambli Menpur
EPA 0 0
WORK PHASE Protection Wall,Land levling, Check Dam Earthen Bund, 15.16 MGNREGA Table no. 36 PIA & DWDU
LIVELIHOOD 17 8.76 TASP/FOREST Table no. 39 PIA & DWDU
2 Biliya EPA 0 0
WORK PHASE Pretection Wall, Farm Bund, Check Dam 15.61 MGNREGA Table no. 36 PIA & DWDU LIVELIHOOD 0 0 PIA & DWDU
3 Chari
EPA 0 0
WORK PHASE Check Dam 4.8 SOCIAL FORES/MGNREGA Table no. 36 PIA & DWDU
LIVELIHOOD 3 2.25 TASP & GGRC Table no. 39 PIA & DWDU
4 Dumka EPA 0 0
WORK PHASE Protection Wall , Check Dam 20.5 MGNREGA Table no. 36 PIA & DWDU LIVELIHOOD 6 4.5 TASP & GGRC Table no. 39 PIA & DWDU
5 Kanakuva EPA 0 0
WORK PHASE Farm Bund, Check wall, Pond Renovation 7.15 GLDC/MGNREGA Table no. 36 PIA & DWDU LIVELIHOOD 0 0 PIA & DWDU
6 Kantu EPA 0 0 PIA & DWDU
WORK PHASE Protection Wall, Check Dam 20.5 MGNREGA Table no. 36 PIA & DWDU LIVELIHOOD 4 3 TASP & GGRC Table no. 39 PIA & DWDU
7 Ladvavad
EPA 0 0 WORK PHASE Protection Wall 21 MGNREGA Table no. 36 PIA & DWDU
LIVELIHOOD 7 3.54 TASP & GGRC/MGNREGA Table no. 39 PIA & DWDU
8 Limdi Mendhari EPA 0 0 PIA & DWDU
WORK PHASE Check Dam 9 MGNREGA Table no. 36 PIA & DWDU LIVELIHOOD 11 8.25 TASP & GGRC Table no. 39 PIA & DWDU
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 118
Sr. No. Village Phase/ Type of
work* Activity to be carried out
Fund made available to IWMP due to
convergence (Rs. in lakh)
Scheme with which
convergence took place
Reference no. of activity/ task/
structure in DPR
Level at which decision for
convergence was taken
9 Nan Salai
EPA 0 0 WORK PHASE Check Dam 4.5 MGNREGA Table no. 36 PIA & DWDU
LIVELIHOOD 6 2.22 TASP & GGRC/MGNREGA Table no. 39 PIA & DWDU
10 Pipariya (To)
EPA 0 0
WORK PHASE Plantation, Check Dam 6.065 SOCIAL FOREST GLDC/MGNREGA Table no. 36 PIA & DWDU
LIVELIHOOD 10 2.94 TASP & GGRC/MGNREGA Table no. 39 PIA & DWDU
11 Rachhava EPA 0 0
WORK PHASE Check Dam 9 MGNREGA Table no. 36 PIA & DWDU LIVELIHOOD 3 3 TASP & GGRC Table no. 39 PIA & DWDU
12 Sangasar EPA 0 0
WORK PHASE Farm Bund, Check Dam, Check Dam Dislting 10.35 GLDC/MGNREGA Table no. 36 PIA & DWDU LIVELIHOOD 0 0 PIA & DWDU
13 Simamoi
EPA 0 0
WORK PHASE Plantation, Check Dam 9.2 SOCIAL FORES/MGNREGA Table no. 36 PIA & DWDU
LIVELIHOOD 10 7.5 TASP & GGRC Table no. 39 PIA & DWDU
14 Udhal Mahuda
EPA 0 0 PIA & DWDU
WORK PHASE Plantation, Check Dam, Check Dam Dislting 5.2 SOCIAL FORES/MGNREGA Table no. 36 PIA & DWDU
LIVELIHOOD 2 1.5 TASP & GGRC Table no. 39 PIA & DWDU
15 Ulkadar EPA 0 0
WORK PHASE Farm Bund, Check Dam 21.58 GLDC/MGNREGA Table no. 36 PIA & DWDU LIVELIHOOD 8 6 TASP & GGRC Table no. 39 PIA & DWDU
Total 140 233.075
Table no. 51: Public-Private Partnership in the IWMP projects
S. No. Name of
Private Sector Partner Agency
Type of agreement signed Financial contribution Partnership
Interventions Expected Outcomes Comments
a)MoU b)Contract c) Any other (pl. specify) IWMP Private sector
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 119
CHAPTER 6 – EXPECTED OUTCOMES
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 120
Table no. 52: Environmental Benefits
Sr. No. Village
Soil loss (cmt) Water storage (Cmt) Ground water table (mt) Tree cover
Pre-project
Expected post-
project
Pre-project
Expected post-
project
Open well: pre-
project
Open well: post-
project
Bore well: pre-
project
Bore well: post-
project
Area in Ha.: pre- project
Area in Ha.:
post-project
Tree count:
pre-project
Tree count: post-
project 1 Ambli Menpur 8 6 12 20 6 3 8 5 450 475 8 17 2 Biliya 7 5 10 18 5 2.5 6 4 78 90 1.5 1.7 3 Chari 6.5 5 8 15 6 3 7 3.5 106 110 2 2.5 4 Dumka 7.5 4.5 11 18 7 3.5 8 7 315 320 6 6.1 5 Kanakuwa 7.5 4 12 18 7 4 8 4.5 250 260 2.5 2.7 6 Kantu 8 6.5 10 18 6.5 3 7.5 4 360 365 6.2 6.3 7 Ladva Vad 9 4.5 10 20 8 4 7 3.5 125 150 2.5 2.7 8 Limdi Medhri 10 5 9 17 7 3.5 8 4 330 340 6.2 6.25 9 Nan Salai 12 6 10 18 8 4 9 4 100 150 2.5 2.7
10 Pipariya (To) 11 5.5 12 18 8 4 9 4 125 150 2.5 2.7 11 Rachhava 10 5 10 20 7 4 8 3.5 250 255 4.5 4.7 12 Sangasar 12 6 11 21 7 3.5 7 4.5 0.15 0.2 0.2 0.3 13 Simamoi 10 5 10 20 8 4.5 9 4.5 70 75 0.8 0.9 14 Udhal Mahuda 12 6 9 18 7.5 5 8 4 160 190 3.5 3.7 15 Ulkadar 11 5.5 8.5 17 6.5 4 7 3 170 180 3.2 3.5 Average 141.5 79.5 152.5 276 104.5 55.5 116.5 63 2889.15 3110.2 52.1 63.75
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 121
Table no. 53: Status of Drinking water
Sr. No. Names of Villages
Availability of drinking water Quality of drinking water
Comments (no. of months in a year)
Pre-project Expected Post project Pre-project Expected Post-project
1 Ambli Menpur
6-9 10-12 Average, Poor Good
Availability will increase up to 3 to 4
months and quality will become good
2 Biliya 3 Chari 4 Dumka 5 Kanakuwa 6 Kantu 7 Ladva Vad 8 Limdi Medhri 9 Nan Salai
10 Pipariya (To) 11 Rachhava 12 Sangasar 13 Simamoi 14 Udhal Mahuda 15 Ulkadar
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 122
Table no. 54: Details of Kharif crop area and yield in the project areas
Sr. No. Name of village Name of crops Pre-project Expected Post-project
Area Production in Qtl Average Yield (Qtl) per ha.
Area Production in Qtl Average Yield per ha (qtl) (ha) (ha)
1 Amlimenpur
Kharif Maize 200 2160 10 230 2990 13 Paddy 75 600 8 85 850 10
Peageion Pee 30 241 8 35 350 10
Rabi Gram 120 1148 9 130 1300 10
Wheat 75 975 13 85 1360 16 Maize 0 0 0 0 0 0
Zaid 0 0 0 0 0 0 Village total 500 5124 48 565 6850 59
2 Biliya
Kharif Maize 50 500 10 59 767 13 Paddy 20 160 8 20 200 10 Peageion Pee 10 80 8 10 90 9
Rabi Gram 20 180 9 25 250 10 Wheat 7 390 13 11 176 16 Maize 0 0 0 0 0 0
Zaid Village total 107 1310 48 125 1483 58
3 Chari
Kharif Maize 955 9550 10 1050 13650 13 Paddy 185 1480 8 220 2200 10 Peageion Pee 120 960 8 160 1600 10
Rabi Gram 650 585 9 750 7500 10 Wheat 320 4160 13 380 680 16 Maize 110 1100 10 120 1560 13
Zaid Village total 2340 17835 58 2680 27190 72
4 Dumka
Kharif Maize 250 2500 10 260 3380 13 Paddy 100 800 8 103 1020 10 Peageion Pee 60 480 8 100 1000 10
Rabi Gram 100 900 9 105 1050 10 Wheat 70 910 13 72 1152 16 Maize 120 1200 10 125 1625 13
Zaid Village total 700 6790 58 765 9227 72
5 Kanakuva
Kharif Maize 280 2800 10 290 3770 13 Paddy 200 180 8 210 2100 10 Peageion Pee 110 880 8 225 2250 10
Rabi Gram 150 1350 9 165 1650 10 Wheat 75 975 13 85 1360 16 Maize 120 1200 10 130 1690 13
Zaid Village total 935 7385 58 1105 12820 72
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 123
Sr. No. Name of village Name of crops Pre-project Expected Post-project
Area Production in Qtl Average Yield (Qtl) per ha.
Area Production in Qtl Average Yield per ha (qtl) (ha) (ha)
6 Kantu
Kharif Maize 235 2350 `10 240 3210 13 Paddy 40 400 8 45 450 10 Peageion Pee 20 140 7 25 200 8
Rabi Gram 20 198 9 25 250 10 Wheat 5 65 13 10 160 16 Maize 15 150 10 20 280 13
Zaid Village total 335 3303 47 365 4550 70
7 Ladvavad
Kharif Maize 170 1700 10 183 2379 13 Paddy 25 200 8 35 350 10 Peageion Pee 34 64 8 43 334 9
Rabi Gram 50 500 10 73 730 10 Wheat 15 195 13 25 400 16
Zaid Village total 294 2659 49 359 4193 58
8 Limdimendhri
Kharif Maize 37 370 10 39 507 13 Paddy 10 80 8 12 120 10 Peageion Pee 15 75 7 16 160 10
Rabi Gram 10 90 9 15 150 10 Wheat 5 65 13 7 112 16 Maize 0 0 0 0 0 0
Zaid
Village total 77 680 47 89 1049 59
9 Nanslay
Kharif Maize 250 2500 10 105 13650 13 Paddy 100 800 8 84 840 10 Peageion Pee 80 56 7 105 480 8
Rabi Gram 100 900 9 75 750 10 Wheat 70 9100 13 72 1152 16 Maize 50 500 10 52 676 13
Zaid
Village total 650 13856 57 493 17548 70
10 Pipriya(To)
Kharif Maize 75 750 10 77 1001 13 Paddy 20 160 8 21 210 10 Peageion Pee 25 175 7 27 216 8
Rabi Gram 15 135 9 18 180 10 Wheat 5 65 13 7 112 16
Zaid
Village total 140 1285 47 150 1719 57
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 124
Sr. No. Name of village Name of crops Pre-project Expected Post-project
Area Production in Qtl Average Yield (Qtl) per ha.
Area Production in Qtl Average Yield per ha (qtl) (ha) (ha)
11 Rachhva
Kharif Maize 70 700 10 75 975 13 Paddy 20 160 8 25 250 10 Soyabean 20 180 9 22 220 10
Rabi Gram 30 270 9 35 350 10 Wheat 25 325 13 30 480 15 Maize 15 150 10 17 221 13
Zaid
Village total 180 1785 59 204 2496 71
12 Sangasar
Kharif Maize 90 900 10 110 1430 13 Paddy 20 160 8 25 250 10 Soyabean 20 180 9 25 200 10
Rabi Gram 30 270 9 40 400 10 Wheat 25 325 13 30 480 16 Maize 15 150 10 20 260 13
Zaid
Village total 200 1985 59 250 3020 72
13 Simamoi
Kharif Maize 41 410 10 50 650 13 Paddy 20 160 8 20 200 10 Peageion Pee 15 120 8 25 200 9
Rabi Gram 10 900 9 15 150 10 Wheat 5 65 13 7 112 16
Zaid 200 Village total 91 1655 48 117 1774 58
14 Udhalmahuda
Kharif Maize 41 410 10 50 650 13 Paddy 20 160 8 20 200 10 Peageion Pee 15 120 8 25 200 9
Rabi Gram 10 900 9 15 150 10 Wheat 5 65 13 7 112 16
Zaid 200 Village total 91 1655 48 117 1774 58
15 Ulkadar
Kharif Maize 41 410 10 50 650 13 Paddy 20 160 8 20 200 10 Peageion Pee 15 120 8 25 200 9
Rabi Gram 10 900 9 15 150 10 Wheat 5 65 13 7 112 16
Zaid 200 Village total 91 1655 48 117 1774 58 Project total
Table no. 55: Area under horticulture
Sr. No. Name of Village Crop Existing area under the crop
Area post project
1 Amlimenpur Mango, Guava, Pomogranate, Chiku, Aamla 3 7 2 Biliya Mango, Guava, Pomogranate, Chiku, Aamla 1 2 3 Chari Mango, Guava, Pomogranate, Chiku, Aamla 2 4 4 Dumka Mango, Guava, Pomogranate, Chiku, Aamla 2 4 5 Kanakuwa Mango, Guava, Pomogranate, Chiku, Aamla 1 2 6 Kantu Mango, Guava, Pomogranate, Chiku, Aamla 1 2 7 Ladva Vad Mango, Guava, Pomogranate, Chiku, Aamla 2 4 8 Limdi Medhri Mango, Guava, Pomogranate, Chiku, Aamla 4 10 9 Nan Salai Mango, Guava, Pomogranate, Chiku, Aamla 2 4
10 Pipariya (To) Mango, Guava, Pomogranate, Chiku, Aamla 2 4 11 Rachhava Mango, Guava, Pomogranate, Chiku, Aamla 2 4 12 Sangasar Mango, Guava, Pomogranate, Chiku, Aamla 2 4 13 Simamoi Mango, Guava, Pomogranate, Chiku, Aamla 2 4 14 Udhal Mahuda Mango, Guava, Pomogranate, Chiku, Aamla 2 4 15 Udhal Mahuda Mango, Guava, Pomogranate, Chiku, Aamla 2 4
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 126
Table no. 56: Details of livestock in the project areas (for fluids please mention in liters, for solids please mention in kgs. and income in Rs.) Sr. No. Name of Village Type of Animal Pre-Project Expected Post-project Remarks No. Yield Income No. Yield Income
1 Amlimenpur Milch-animals 1450 489 12225 1503 701 21030
Draught Purpose animals 120 0 0 0 0 0 Animals for other purpose 800 0 0 0 0 0
2 Biliya Milch-animals 270 90 2250 300 170 5100
Draught Purpose animals 45 0 0 0 0 0 Animals for other purpose 110 0 0 0 0 0
3 Chari Milch-animals 11298 4420 110500 11315 4488 134640
Draught Purpose animals 209 0 0 0 0 0 Animals for other purpose 7512 0 0 0 0 0
4 Dumka Milch-animals 452 150 3750 480 262 7860
Draught Purpose animals 87 0 0 0 0 0 Animals for other purpose 435 0 0 0 0 0
5 Kanakuwa Milch-animals 573 270 6750 600 378 11340
Draught Purpose animals 67 0 0 0 0 0 Animals for other purpose 456 0 0 0 0 0
6 Kantu Milch-animals 240 104 2600 270 224 6720
Draught Purpose animals 25 0 0 0 0 0 Animals for other purpose 734 0 0 0 0 0
7 Ladva Vad Milch-animals 860 320 8000 680 400 12000
Draught Purpose animals 89 0 0 0 0 0 Animals for other purpose 140 0 0 0 0 0
8 Limdi Medhri Milch-animals 135 42 1050 155 122 3660
Draught Purpose animals 23 0 0 0 0 0 Animals for other purpose 540 0 0 0 0 0
9 Nan Salai Milch-animals 380 157 3925 405 257 7710
Draught Purpose animals 63 0 0 0 0 0 Animals for other purpose 200 0 0 0 0 0
10 Pipariya (To) Milch-animals 281 100 2500 300 176 5280
Draught Purpose animals 17 0 0 0 0 0 Animals for other purpose 210 0 0 0 0 0
11 Rachhava Milch-animals 531 150 3750 542 194 5820
Draught Purpose animals 45 0 0 0 0 0 Animals for other purpose 230 0 0 0 0 0
12 Sangasar
Milch-animals 406 185 4625 429 277 8310 Draught Purpose animals 35 0 0 0 0 0 Animals for other purpose 156 0 0 0 0 0
Milch-animals 632 209 5225 655 297 8910 Draught Purpose animals 24 0 0 0 0 0 Animals for other purpose 430 0 0 0 0 0
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 127
Sr. No. Name of Village Type of Animal Pre-Project Expected Post-project Remarks
13 Simamoi
Milch-animals 406 185 4625 429 277 8310 Draught Purpose animals 35 0 0 0 0 0 Animals for other purpose 156 0 0 0 0 0
Milch-animals 632 209 5225 655 297 8910 Draught Purpose animals 24 0 0 0 0 0 Animals for other purpose 430 0 0 0 0 0
14 Udhalmahuda
Milch-animals 406 185 4625 429 277 8310 Draught Purpose animals 35 0 0 0 0 0 Animals for other purpose 156 0 0 0 0 0
Milch-animals 632 209 5225 655 297 8910 Draught Purpose animals 24 0 0 0 0 0 Animals for other purpose 430 0 0 0 0 0
15 Ulkadar
Milch-animals 406 185 4625 429 277 8310 Draught Purpose animals 35 0 0 0 0 0 Animals for other purpose 156 0 0 0 0 0
Milch-animals 632 209 5225 655 297 8910 Draught Purpose animals 24 0 0 0 0 0 Animals for other purpose 430 0 0 0 0 0
Table no. 57: Employment in Project area
Sr. NO. Names of Villages
Wage employment Self employment No. of mandays No. of beneficiaries No. of beneficiaries
SC ST Others Women Total SC ST Others Women Total SC ST Others Women Total 1 Ambli Menpur - 15570 0 5860 15570 - 160 - 16 160 2 17 - 30 49 2 Biliya - 4167 0 1530 4167 - 94 - 8 94 - 13 - 20 33 3 Chari 4162 1762 1578 5924 82 20 14 102 12 4 18 30 4 Dumka 7527 840 2648 8367 - 137 6 23 143 22 27 49 5 Kanakuwa - 3360 0 1230 3360 - 70 0 6 70 - 7 - 10 17 6 Kantu - 15642 0 5863 15642 - 200 - 24 200 - 12 - 28 40 7 Ladva Vad - 1860 0 689 1860 - 57 - 5 57 - 2 - 8 10 8 Limdi Medhri - 870 17026 348 17896 8 226 27 234 10 30 20 30 9 Nan Salai 68 6154 549 2146 6771 - 109 7 19 116 2 20 5 20 47
10 Pipariya (To) - 2210 1467 884 3677 - 81 7 10 88 - 12 2 11 25 11 Rachhava - 8706 2189 3381 10895 - 138 17 20 155 - 24 10 23 57 12 Sangasar - 3645 0 1458 3645 - 113 0 10 113 - 12 0 11 23 13 Simamoi 457 9481 3462 9938 - 14 156 10 170 - 4 27 16 47 14 Udhal Mahuda 6481 0 1983 6481 38 5 38 8 10 18 15 Ulkadar 10347 0 3645 10347 48 7 48 11 0 12 23
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 128
Table no. 58: Details of seasonal migration from Project area
Sl. No. Names of villages
No. of persons migrating No. of days per year of migration
Pre-project Expected post project Pre-project Expected post project 1 Ambli Menpur 1338 1008 85 60 2 Biliya 575 404 95 70 3 Chari 537 387 80 60 4 Dumka 1428 1045 90 60 5 Kanakuwa 373 266 90 65 6 Kantu 1413 1024 97 72 7 Ladva Vad 229 148 92 74 8 Limdi Medhri 1188 884 80 57 9 Nan Salai 474 346 85 60
10 Pipariya (To) 302 217 65 45 11 Rachhava 964 688 90 60 12 Sangasar 467 337 95 70 13 Simamoi 846 621 75 50 14 Udhal Mahuda 99 70 80 60 15 Ulkadar 238 191 90 60
Total 10471 7636 1289 923
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 129
Table no.59: Per capita Income (In Rs)
Sr. No. Village Source of Income Pre-project Expected post project
1 Amlimenpur
Agriculture 5000 7000 Forestry 6000 8000 Animal Husbandry 1500 2450 Casual Labour 5500 8100 Services 8000 11000 Handicraft 0 0 Business 2000 2500 Others 0
Total 28000 39050
2 Biliya
Agriculture 2760 3100 Forestry 3620 3970 Animal Husbandry 1400 1550 Casual Labour 3900 4900 Services 5000 6500 Handicraft 0 0 Business 2500 3000 Others 0
Total 19180 23020
3 Chari
Agriculture 6130 7200 Forestry 4150 5400 Animal Husbandry 1400 1640 Casual Labour 3500 5000 Services 7000 8000 Handicraft 0 0 Business 4000 5500 Others 0
Total 26180 32740
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 130
Sr. No. Village Source of Income Pre-project Expected post project
4 Dumka
Agriculture 10160 11060 Forestry 5275 6000 Animal Husbandry 1200 1350 Casual Labour 3700 4500 Services 6400 7000 Handicraft 0 0 Business 4000 5000 Others 0
Total 30735 34910
5 Kanakuva
Agriculture 2620 3000 Forestry 3630 4000 Animal Husbandry 1000 1200 Casual Labour 4000 4500 Services 5000 5250 Handicraft 0 0 Business 0 0 Others 0
Total 16250 17950
6 Kantu
Agriculture 8900 9500 Forestry 17480 18000 Animal Husbandry 1600 1800 Casual Labour 4000 5400 Services 6000 6500 Handicraft 0 0 Business 3500 3750 Others 0
Total 41480 44950
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 131
Sr. No. Village Source of Income Pre-project Expected post project
7 Ladvavad
Agriculture 1420 1500 Forestry 600 700 Animal Husbandry 2500 2750 Casual Labour 3500 4000 Services 5000 6000 Handicraft 0 0 Business 0 Others 0
Total 13020 14950
8 Limdimendhari
Agriculture 17960 6160 Forestry 15320 7000 Animal Husbandry 1500 1560 Casual Labour 3200 9000 Services 6000 12500 Handicraft 0 0 Business 4000 5000 Others 0
Total 47980 41220
9 Nanslay
Agriculture 6050 9627 Forestry 5050 6000 Animal Husbandry 1500 1300 Casual Labour 3400 8100 Services 5100 19900 Handicraft 2000 4000 Business 3000 3500 Others 0
Total 26100 52427
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 132
Sr. No. Village Source of Income Pre-project Expected post project
10 Pipriya(To)
Agriculture 7850 8500 Forestry 1340 1700 Animal Husbandry 1200 1400 Casual Labour 3700 4500 Services 6200 7000 Handicraft 0 0 Business 2500 3500 Others 0
Total 22790 26600
11 Rachhva
Agriculture 6350 7420 Forestry 9790 10000 Animal Husbandry 1000 1300 Casual Labour 3300 4000 Services 4500 5000 Handicraft 0 0 Business 2500 3500 Others 0
Total 27440 31220
12 Sangasar
Agriculture 5380 6000 Forestry #REF! 0 Animal Husbandry 1500 1800 Casual Labour 3000 4000 Services 6000 6500 Handicraft 0 0 Business 3000 3500 Others 0
Total #REF! 21800
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 133
Sr. No. Village Source of Income Pre-project Expected post project
13 Simamoy
Agriculture 12650 13000 Forestry 3250 3700 Animal Husbandry 2000 2400 Casual Labour 3200 4000 Services 6500 7500 Handicraft 0 0 Business 2500 3500 Others 0
Total 30100 13000
14 Udhalmahuda
Agriculture 2400 3500 Forestry 7750 8250 Animal Husbandry 1000 1200 Casual Labour 2500 3000 Services 0 0 Handicraft 0 0 Business Others 0
Total 13650 3500
15 Ulkadar
Agriculture 3000 3500 Forestry 15000 16000 Animal Husbandry 1000 1300 Casual Labour 3500 4000 Services 6000 7000 Handicraft 0 0 Business Others 0
Total 28500 31800
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 134
Table no. 60: Backward-Forward linkages
Sr. No. Project Type of Marketing Facility Pre-project (no.)
During the project (no.) Post-project (no.)
1 Limadimendhri
Backward linkages 0 - - Seed certification - - - Seed supply system Local Verity - Hybrid
Fertilizer supply system Uriya, DAP - Bio Fertilizer,
Vermi Compost Pesticide supply system 48.5 - 49.93
Credit institutions Money Lander - Bank, SHG
Water supply Rainy - Irrigation Extension services - KVK KVK Nurseries 30 - 30 Tools/machinery suppliers - - - Price Support system - - -
Labour - - Employment
Training Any other (please specify) - - - Forward linkages - - -
Harvesting/threshing machinery Nothing - Irrigation Facilities
Storage (including cold storage) - - - Road network - - - Transport facilities - - - Markets / Mandis - - - Agro and other Industries - - - Milk and other collection centres - - - Labour - - - Any other (please specify) - - -
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 135
CHAPTER 7 – Quality and Sustainability Issues
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 136
7 Quality and Sustainability Issues 7.1 Plans for Monitoring and Evaluation A Web-based GIS System is being developed for monitoring and evaluating the project in its planning & implementation phases. The system would be
available on a public domain and can be accessed by all the stakeholders of the project. The system shows the entire state of Gujarat and all of those
areas selected over the next 10 years. Filtering allows the user to zoom onto one particular project. Details related to soil type, Land-use classification,
inhabitation etc., can be obtained village-wise. Furthermore, survey-number wise details related to ownership, irrigation source, yield etc., can also be
accessed by the users of the system. This system is being used for pooling up the details obtained from the DPR. In other words, the DPR is made
available online in the form of a database which will help the stakeholders know areas of importance viz., already treated areas/historical works in
the area, proposed areas for treatment etc., for further treatment and planning. The system would also show the satellite imageries of various years
from the project inception stage to the project closing stages. This allows the user to evaluate the effectiveness of the treatment and thereby plan
corrective measures for the project area. The system would serve as an aiding tool to the planners and Evaluators for judging the efficacy of the
project.
Yet another component of the Web-based GIS system is the Mobile based Monitoring & Evaluation System, which will help the ground staff alias
WDTs (Watershed Development Team) to transmit information from the ground level to the central server. Also, any higher-up official in charge of
the project can obtain information regarding the project area on their mobile phone by means of an SMS. The system works in the following manner.
The WDT equipped with a GPS instrument marks the latitude-longitude information of various treatment areas during the DPR. The probable sites
are then transferred onto the central server. During the works phase, any progress in the treatment areas is reported to the server by means of an
SMS by the WDT. Similarly, any nodal officer or higher-up official can view the progress in a project by means of summarized reports generated over
frequent periods of time.
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 137
7.2 Plans for Project management:
The Project management of any watershed programme is very important. It mainly depends upon the community organization and the village
level institutes. In Jadakheriya project, watershed committee, various user groups and SHGs have been formulated for post project operation and
maintenance of assets created during project period. Major emphasis will be on equity and sustainable benefit of the project even after
implementation stage. A proper link-up will be built during project period with various institutes and capacity building organization. They will act as
a major kingpin during post implementation for scaling up the successful experience during project.
7.3 Watershed Development Fund:
The major source of financial assistance after post implementation period is watershed Development Fund.
7.4 User Charges:
Various user groups will be formed in village. These user groups will collect user charges according to the designated rules formed during the formation of
user group. These funds will be transferred to the WDF funds as per these formulated rules.
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 138
CHAPTER 8 – MAPS
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 139
Ground Water Body Map Project Name : IWMP-15 District Name : Dahod Taluka Name : Dhanpur
Ground Water Map of Project Name: Limdi Medhri (Dhanpur)
Ground Water Perspective
Built-up
Good
Good to moderate
Moderate
Moderate to Poor
Poor
Poor to Nil
River
Very good to good
Water Body
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 140
Landuse/Land Cover Map Project Name : IWMP-15 District Name : Dahod Taluka Name : Dhanpur
Land Use Map of Project Name: Limdi Medhri (Dhanpur)
Land Use & Land Cover
Agriculture
Built-up
Forest
Grass land/Grazing land
Others
Wastelands
Water bodies
Wetlands
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 141
Land Use Map of Project Name: Limdi Medhri (Dhanpur)
Slope Map of Project Name: Chakliya (Jhalod)
River / Water Body Map Project Name : IWMP-15 District Name : Dahod Taluka Name : Dhanpur
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 142
Soil Map of Project Name: Limdi Medhri (Dhanpur)
Soil Map Project Name : IWMP-15 District Name : Dahod Taluka Name : Dhanpur
Geomorphology
Built-up
Denudational Hills
Flood Plain
Pediplain
Plateau
River
Structural Hills
Water Bod
District Watershed Development Unit, Dahod
PIA: Forest Division Devgadh Bariya Page No: 143
Table no. 62: Abbreviations: Sr. No
Short Form Full Form
Sr. No
Short Form Full Form
1 IWMP Integrated Watershed Management Programme 14 PDAY Pandit Dindayal Awas Yojna
2 PIA Project Implementation Agency 15 SWOT Strength Weakness Opportunities and thread 3 SC Schedule Caste 16 BSY Balika Samrudhi Yojna 4 ST Schedule Tribe 17 VSY Vidhva Sahay Yojna 5 DPAP Drought Prone Areas Programme 18 AAY Ambedkar Awas Yojna 6 DDP Desert Development Programme 19 SMY Sankat Mochan Yojna
7 MGNREGS Mahatma Gandhi National Rural Employment Guarantee Scheme 20 IGNOAPS Indira Gandhi National Old Age Pension
Scheme 8 NREGS National Rural Employment Guarantee Scheme 21 BBY Bajpai Bankebal Yojna 9 DRDA District Rural Development Agency 22 TSSY Tapak Sinchay Sahay Yojna
10 BRGF Backward Rural Guarantee Fund 23 BPL Below Poverty Line 11 IAY Indira Awas Yojna 24 APL Above Poverty Line 12 TSP Total Sanitation Programme 25 NGO Non Governmental Organization 13 SGSY Swarnjayanti Gram Swarojgar Yojna 26 OBC Other Backward Class