+ All Categories
Home > Documents > Double-Shell Tank Integrity Program Overview - … 9 DST...Double-Shell Tank Integrity Program...

Double-Shell Tank Integrity Program Overview - … 9 DST...Double-Shell Tank Integrity Program...

Date post: 04-May-2018
Category:
Upload: hoangnguyet
View: 234 times
Download: 4 times
Share this document with a friend
21
1 1 Presented by: Jeremy Johnson, Deputy Federal Project Director, Tank Farms September 26, 2016 Double-Shell Tank Integrity Program Overview Oregon Hanford Cleanup Board
Transcript
Page 1: Double-Shell Tank Integrity Program Overview - … 9 DST...Double-Shell Tank Integrity Program Overview ... Tank Farm under construction 9. ... Tank, Year, Report # % Thinning from

1

1

Presented by: Jeremy Johnson, Deputy Federal Project Director, Tank Farms September 26, 2016

Double-Shell Tank Integrity Program Overview

Oregon Hanford Cleanup Board

Page 2: Double-Shell Tank Integrity Program Overview - … 9 DST...Double-Shell Tank Integrity Program Overview ... Tank Farm under construction 9. ... Tank, Year, Report # % Thinning from

DST

Ultrasonic Testing

Visual Inspection

Chemistry Optimization

Structural Integrity

SST

Stabilization & Isolation

Single-Shell Tank Integrity

Project

Expert Panel

Integrity Assessment

Activities

RPP-28538 DST Integrity Assessment, HFFACO Milestone M-48-14

Update RPP-28538RPP-10435

SST Integrity Assessment Report (IQRPE)

1997 1998 2001 2002 2004 20061999 2000 2003 2005 2007

BNL-52527Tank Structural Integrity Panel

PNNL-13571DST Life Extension

1996 2008

BNL-52361Structural Analysis Guideline Panel

RPP-RPT-22162Waste Chemistry

Optimization

RPP-19438Waste Level Rise

RPP-31129Vapor Space Corrosion HLW Integrity Assessment

Panel (HIAP) Meetings

2009 2010 2011 20132012 2014 2015 2016

First Round of Inspection Second Round of Inspection

Limited Access Analog Cameras Digital Cameras

1st Generation Electro-Chemical Noise Probes

Electro-Chemical Noise Probes

Multi-Function Corrosion Probes

Potential Measurement Corrosion Probes

Replaceable Corrosion Monitoring Probes

DST Analysis of Record / Dome Deflection Surveys / and Dome Load Controls

Completed Saltwell Pumping of 29 Tanks

Structural Analysis / Forensic Testing

Expert Panel Oversight Committee for Corrosion Testing & MonitoringTank

Integrity Expert Panel

Tank Integrity Program History

2

Page 3: Double-Shell Tank Integrity Program Overview - … 9 DST...Double-Shell Tank Integrity Program Overview ... Tank Farm under construction 9. ... Tank, Year, Report # % Thinning from

Double-Shell Tank Overview

Tank Farm 241-AY 241-AZ 241-SY 241-AW 241-AN 241-AP

Constructed 1968-70 1971-74 1974-76 1977-80 1978-81 1983-86

Number of Tanks 2 2 3 6 7 8

Design Life (years) 25 20 50 50 50 50

Initial Service mid-1971 late-1976 1977 mid-1980 1981 1986

Years in Service as of 2012

41 36 35 32 31 26

Type of Steel A515 A515 A516 A537 A537 A537

Capacity (Mgal.) 1 1 1.16 1.16 1.16 1.25

Maximum Waste Depth (feet)

30.3 30.3 35.2 35.2 35.2 38.3

Maximum Specific Gravity

1.77 1.77 1.77 1.77 1.77 1.84

3

Page 4: Double-Shell Tank Integrity Program Overview - … 9 DST...Double-Shell Tank Integrity Program Overview ... Tank Farm under construction 9. ... Tank, Year, Report # % Thinning from

DST Design & Construction

4

Page 5: Double-Shell Tank Integrity Program Overview - … 9 DST...Double-Shell Tank Integrity Program Overview ... Tank Farm under construction 9. ... Tank, Year, Report # % Thinning from

DST Integrity Program Purpose & Objectives

Primary objectives of the DST Integrity Program include:

• Maintain DSTs to safely store and transfer 56 million gallons of high-level waste for treatment• Extend life of DSTs to support WTP operation• Monitor tank integrity to inform decisions for repair or replacement• Monitor tank corrosion• Meet RCRA requirements

Retractable Corrosion Monitoring Probe

5

Page 6: Double-Shell Tank Integrity Program Overview - … 9 DST...Double-Shell Tank Integrity Program Overview ... Tank Farm under construction 9. ... Tank, Year, Report # % Thinning from

DST Integrity Program Scope

• Primary tank wall and annulus floor inspected every ~10 years (video and ultrasonic inspections)

• Waste chemistry corrosion control studies

• Waste chemistry sampling and adjustments for corrosion mitigation

• Periodic testing, evaluation, certification of ancillary equipment (e.g., valve pits, piping)

• Structural analysis and studies for thermal, operating, and seismic loads

• Periodic testing and integrity assessment of 242-A Evaporator

Equipment

like this

crawler is

used to

inspect the

annulus of

DSTs.

6

Page 7: Double-Shell Tank Integrity Program Overview - … 9 DST...Double-Shell Tank Integrity Program Overview ... Tank Farm under construction 9. ... Tank, Year, Report # % Thinning from

DST Integrity Program Scope (cont.)

Tank AY-102 Leak • Visual inspection every 2 weeks• Corrosion testing shows leaked

waste poses no realistic threat to liner integrity

2016 IQRPE Assessment• Released report (RPP-RPT-

58441); 24 recommendations, no findings of greater significance

• Report concluded DST system is fit for use; reassessment required in 10 years (2026)

The annulus of AY-102 continues to be inspected every

two weeks.

7

Page 8: Double-Shell Tank Integrity Program Overview - … 9 DST...Double-Shell Tank Integrity Program Overview ... Tank Farm under construction 9. ... Tank, Year, Report # % Thinning from

Tank Integrity Expert Panel

• Panel is comprised of experts from a variety of private and government organizations including SRNL and PNNL

• Panel meets twice a year to provide independent advice and recommendations to DOE and WRPS on existing and emerging tank integrity issues with focus on safety

The Tank Integrity Expert Panel last met May 16-17 in Richland.

Expert Panel members• Andy Duncan, SRNL• Brenda Garcia-Diaz, SRNL• Russ Jones, GT Engineering• Leon Stock

• Glenn Light, Southwest Research Institute

• Mike Rinker, PNNL• Bob Sindelar, SRNL, Vice Chair• Todd Martin, Chair/Facilitator

8

Page 9: Double-Shell Tank Integrity Program Overview - … 9 DST...Double-Shell Tank Integrity Program Overview ... Tank Farm under construction 9. ... Tank, Year, Report # % Thinning from

Expert Panel Recommendations

• Continue existing corrosion and refractory testing

• Obtain a sample of the waste in the AY-102 annulus to determine corrosion threats to the secondary liner

• Utilize remote inspection techniques

• Confirm AY-102 secondary liner integrity

Summary of Current Expert Panel Recommendations:

Tank Farm under construction

9

Page 10: Double-Shell Tank Integrity Program Overview - … 9 DST...Double-Shell Tank Integrity Program Overview ... Tank Farm under construction 9. ... Tank, Year, Report # % Thinning from

DST Secondary Liner Analyses

• Ultrasonic scans on bottom of secondary liner (outer shell) performed in 7 DSTso Liner thinning >10% observed

in all but one tank (localized areas)

o One tank (AP-102) found to have small area with up to 70% thinning

o Thinning observed in tanks with no prior leak detection pit accumulation

• No indication primary DST containment is affected

UT crawler examining floor of AP-102

Leak Detection

Pit

Drain channels

Base pad under secondary liner

10

Page 11: Double-Shell Tank Integrity Program Overview - … 9 DST...Double-Shell Tank Integrity Program Overview ... Tank Farm under construction 9. ... Tank, Year, Report # % Thinning from

Riser 31

• Two areas of secondary shell floor thinning discovered above foundation drain slots

o Average thickness of these areas was 0.380”, or 24% loss vs nominal 0.500”

o Thinnest location was 0.156”, or 70% loss in small area

Riser 30

• No areas of floor thinning observed 270°

180°

SECONDARY TANK

PRIMARY TANK

90°

PLAN VIEW TANK 241-AP-102

RISER-061

RISER-060

+1/2"1'-0 3/8"

-0"+1/2"

1'-0 3/8"-0"

N

RISER-031

ApproximateAnnulus UT

Inspection Area

Drawing Adapted from H-14-010503 Rev. 9

LDP Drain Pipe

To LDP AP-03C

RISER-030

AP-102 Secondary Floor UT Scans

11

Page 12: Double-Shell Tank Integrity Program Overview - … 9 DST...Double-Shell Tank Integrity Program Overview ... Tank Farm under construction 9. ... Tank, Year, Report # % Thinning from

Tank, Year, Report #

% Thinning

from

Nominal

Additional Detail from Report

AN-105

1999, HNF-4816

2006, RPP-RPT-27467

2016, Report in preparation

0.2%

3.6%

29.8%

Small areas inspected from one riser in 1999 and 2006 (~10 ft2). No thinning, pitting, or crack-like indications detected. Scan area in 2016 as large as possible from two risers. Several areas of localized thinning detected under both risers. Note – these are 3 different areas at 3 different times.

AN-107

1999, HNF-335310.0%

Scan area ~1 ft × 8 ft in length. Minimal thickness of 0.450 in. indicates floor thinning. No

pitting or crack-like indications detected.

AP-106

2014, RPP-RPT-571272.20%

14” x 8.4’ of scanning revealed no areas of reportable wall thinning, no non-reportable pits,

no reportable indications of pitting, and no reportable linear indications.

AP-102

2014, RPP-RPT-5827670.2%

Inspected 13” x 25’ at Riser 30 and 15” x 20.4’ at Riser 31. Two localized areas of reportable

thinning (>10% loss), and reportable pits (>25% loss) were found through Riser 31.

AN-103

2015, RPP-RPT-5877623.8%

23’ x 17” each at Riser 25 and Riser 26. Two localized areas of reportable thinning, no

pitting (reportable or non-reportable).

AN-104

2015, RPP-RPT-5892439.6%

A total area of 49’ x 17” was scanned through Riser 25 (25’ x 17”) and Riser 26 (24’ x 17”).

Several areas of thinning were detected.

AW-103

2016, Scanning in Progress19.4%

Floor scans complete and reportable thinning >10% detected. Scan area as large as

possible with existing equipment.

UT Scans of Liner Floor

12

Page 13: Double-Shell Tank Integrity Program Overview - … 9 DST...Double-Shell Tank Integrity Program Overview ... Tank Farm under construction 9. ... Tank, Year, Report # % Thinning from

Path Forward

• Add secondary floor scans to inspection program – complete• Share info/baseline with Savannah River Site – complete• Develop investigation/mitigation strategy – complete • HQ EM-led programmatic risk evaluation in August – complete • Accelerate UT floor scans (minimum 3 scheduled for FY17)• Prioritize DSTs based on intrusion history • Develop capability for increased floor scan area and implement

new technologies• Eliminate/reduce/reverse annulus vacuum • Inspect additional leak detection pit drain lines and obtain

samples• Perform additional corrosion coupon testing

13

Page 14: Double-Shell Tank Integrity Program Overview - … 9 DST...Double-Shell Tank Integrity Program Overview ... Tank Farm under construction 9. ... Tank, Year, Report # % Thinning from

Questions?

14

Page 15: Double-Shell Tank Integrity Program Overview - … 9 DST...Double-Shell Tank Integrity Program Overview ... Tank Farm under construction 9. ... Tank, Year, Report # % Thinning from

Backup slides on SSTs

15

Page 16: Double-Shell Tank Integrity Program Overview - … 9 DST...Double-Shell Tank Integrity Program Overview ... Tank Farm under construction 9. ... Tank, Year, Report # % Thinning from

III

III

IVA

IVB

IVC

149 single-shell tanks were built between 1944 and 1965.

Various capacities• Type I 55 kgal• Type II 530 kgal• Type III 760 kgal• Type IV 1 million gal

Tank

SeriesI II III IVA IVB IVC

Farms

241-B

241-C

241-T

241-U

241-B

241-BX

241-C

241-T

241-U

241-BY

241-S

241-TX

241-TY

241-SX 241-A 241-AX

Total Tanks 16 Tanks 60 Tanks 48 Tanks 15 Tanks 6 Tanks 4 Tanks

Single-Shell Tank Overview

16

Page 17: Double-Shell Tank Integrity Program Overview - … 9 DST...Double-Shell Tank Integrity Program Overview ... Tank Farm under construction 9. ... Tank, Year, Report # % Thinning from

SST Design & Construction

17

Page 18: Double-Shell Tank Integrity Program Overview - … 9 DST...Double-Shell Tank Integrity Program Overview ... Tank Farm under construction 9. ... Tank, Year, Report # % Thinning from

SST Integrity Program Purpose & Objectives

Why do we have an SST Integrity Program?

• SSTs are well beyond design life (removed from service in 1980)

• Many tanks have leaked in past; 1 currently (T-111)

• SSTs contain about half (25M gal) of total volume of tank waste, including ~2.5M gal drainable liquid

• Maintenance of SST structural integrity will remain an important issue for decades until retrieval and closure of tanks is completed

Monitoring and

maintaining the

integrity of the

aging SSTs will

be a key issue

until waste

retrieval is

completed and

the tanks are

closed.

18

Page 19: Double-Shell Tank Integrity Program Overview - … 9 DST...Double-Shell Tank Integrity Program Overview ... Tank Farm under construction 9. ... Tank, Year, Report # % Thinning from

SST Integrity Program Purpose & Objectives (cont.)

Primary functions of the SST Integrity Program include:

• Periodic dome deflection surveys

• Waste liquid level evaluations

• Visual inspections• Intrusion mitigation • Evaporation of liquids

with exhausters • Corrosion testing• Evaluate new monitoring

technology

19

Page 20: Double-Shell Tank Integrity Program Overview - … 9 DST...Double-Shell Tank Integrity Program Overview ... Tank Farm under construction 9. ... Tank, Year, Report # % Thinning from

SST Integrity Program Scope

TPA Milestones and Targets• 17 TPA milestones and targets

completed (M-045-91)Analysis of Record (AOR) complete• Modern structural analysis of all

four SST types, tanks are soundC-107 dome plug (2011)• Cores taken from dome• Concrete material properties

shown to be higher than design specifications

A-106 core sample (2014)• Concrete material properties again

shown to be higher than design specifications

SX-106 In-Tank Image Composite

20

Page 21: Double-Shell Tank Integrity Program Overview - … 9 DST...Double-Shell Tank Integrity Program Overview ... Tank Farm under construction 9. ... Tank, Year, Report # % Thinning from

SST Integrity Program Scope

Leak Assessment Process• Utilize formalized process,

supports cost effective retrievalIn-Tank Visual Inspections• ~12 tanks per year, priorities given

to level trends, no signs of structural distress

Level Change and Intrusion Evaluations• Evaluated 20 tanks for level

increase and 20 tanks for level decrease between 2011 and 2014, continue to evaluate level change trends

Exhausting Tank Free Liquid• Exhauster operating on T-111

T-111 Portableexhauster

21


Recommended