European CO2 Capture and Storage (CCS) Demonstration Project Network
Information and experience gathering form
8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202
2/32
8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202
3/32
8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202
4/32
European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering
Version 2011-01-20 4
Baseline
Form
Periodic
Update
Period: 2010-2
Periodic
Update
Period: 2010-1
Baseline
Form
Periodic
Update
Period: 2010-2
Periodic
Update
Period: 2010-1
Baseline
Form
Periodic
Update
Period: 2010-2
Periodic
Update
Period: 2010-1
Webform logic
The current implementation model foreseen is:
Each project completes a baseline form orstart form, i.e. the first time that they add content to theinformation and experience gathering application. The form aims to capture all planned figures in thecategory project progress and other data that are unlikely to change much over the course of reporting.
Thereafter, a periodic update form is completed, according to the tables in this document. Thiscontinues for each reporting period (projects will be able to access information submitted for previousperiods, but will not be able to change them).
The system will provide the Network Team with some tools for generating graphs and overviews peritem on the form with which to illustrate reports. We have chosen not to have report-generationfunctionality, aiming to prevent uncontrolled dissemination of detailed information.
8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202
5/32
European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering
Version 2011-01-20 5
Structure of the tables
The tables presented below contain the following columns: ID: unique identifier for the sharing item (each item is grouped into a main, sub- and subsubcategory) Level: designation of the sharing level of the item (level 0: to be shared with the European Commission only, level 1: to be shared within
the Network membership, level 2: to be shared beyond the Network membership) Item Description: description of the item as it will be used in the online form Q1: question as it will appear on the online form (Q1 typically seeks information regarding planned values in a certain area) Value1: the value the respondent enters against Q1. Unit1: the unit of Value1. Unit1 will be shown on the form to aid completion. Q2: question as it will appear on the online form (Q2 typically seeks information regarding actual or forecasted values in a certain area).
Where Q2 is empty, no Q2 is envisaged (nor Value2 and Unit2) Value2: the value the respondent enters against Q2. Unit2: the unit of Value2. Unit2 will be shown on the form to aid completion. Baseline: this column identifies whether or not an item is part of the baseline form (and is to be submitted once, during first use of the
tool). Within the Network: this column describes what information will be shared within the Network Beyond the Network: this column identifies what information will be shared beyond the Network for this item, as part of reports
prepared by the Network Team.
8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202
6/32
European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering
Version 2011-01-20 6
1. Technical set-up and performance
ID Level Item Description Q1 Value1 Unit1 Q2 Value2 Unit2 BaseLine?
Within theNetwork
Beyond the
NetworkPower PlantThe items in this section arevalid also for industrialplants as far as they areapplicable
1.1 Fuel Type
1.1.1 2 Fuel used in power plantto which CCS is applied
Fuel type used inpower plant
y Full, notanonymised
Full, notanonymised
1.2 Carbon content in fuel
1.2.1 2 Carbon content in fuelused
Percent of carbon infuel
% Full, notanonymised
Full, notanonymised
1.3 Electricity production
1.3.1 2 Electricity productionfrom power plant withoutCCS
Planned for last6 month period,annualised
MWh/yr Actual over last 6month period,annualised
MWh/yr Full, notanonymised
Full, notanonymised
1.3.2 2 Electricity productionfrom power plant withCCS
Planned for last6 month period,annualised
MWh/yr Actual over last 6month period,annualised
MWh/yr Full, notanonymised
Full, notanonymised
1.4 Availability, operatinghours and shutdowns
1.4.1 2 Availability of the powerplant, for operation withCCS, relative to wall-clock time
Plannedavailability for thelast 6 monthperiod
% Actual availability forthe last 6 month period
% Full, notanonymised
Full, notanonymised
1.4.2 2 Operating hours of thepower plant (includingboth with and withoutCCS)
Plannedoperating hoursfor the last 6month period
hrs Actual operating hoursin last 6 months
Hrs Full, notanonymised
Full, notanonymised
1.4.3 1 Number ofunintended/unplannedshut downs
Number ofunintended/unplannedshut downs in last 6
Full, notanonymised
Full, notanonymised
8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202
7/32
European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering
Version 2011-01-20 7
month period
1.5 Process efficiency
1.5.1 2 Net efficiency of thepower plant without CCS
Planned netefficiency of thepower plant forthe last 6 monthperiod, full loadvalue
% Actual net efficiency ofthe power plant for thelast 6 month period,full load value
% Full, notanonymised
Full, notanonymised
1.5.2 2 Planned netefficiency of thepower plant forthe last 6 monthperiod, averagevalue
% Actual net efficiency ofthe power plant for thelast 6 month period,average value
% Full, notanonymised
Full, notanonymised
1.5.3 2 Net efficiency of thepower plant with CCS
Planned netefficiency of thepower plant forthe last 6 monthperiod, full load
value
% Actual net efficiency ofthe power plant for thelast 6 month period,full load value
% Full, notanonymised
Full, notanonymised
1.5.4 2 Planned netefficiency of thepower plant forthe last 6 monthperiod, averagevalue
% Actual net efficiency ofthe power plant for thelast 6 month period,average value
% Full, notanonymised
Full, notanonymised
Capture
1.6 Increase in fuelconsumption
1.6.1 2 Percentage increase in
fuel consumption due toimplementation ofcapture, i.e. the part ofthe power plant withCCS, includingcompression. Theconsumption ofsecondary energy inputs
Planned for last
6 month period
% Actual for last 6 month
period
% Full, notanonymised
Full, notanonymised
8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202
8/32
European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering
Version 2011-01-20 8
shall be included asequivalents to theprimary fuel.
1.7 Capture performance
1.7.1 2 Average rate of CO2capture
Planned averagecapture rate forlast 6 monthperiod
% Actual averagecapture rate over last6 month period
% Full, notanonymised
Full, not
anonymised
1.7.2 Planned full loadcapture rate forlast 6 monthperiod
% Actual full load capturerate in last 6 months
%
1.8 Capture energyrequirement
1.8.1 2 Totalenergy requirement forcapturing CO2 (energyconsumption of allelements associated withcapture, excludingcompression)
Planned averageenergyrequirement forlast 6 monthperiod
MWh/tCO2captured
Actual average energyrequirement in last 6month period
MWh/ tCO2captured
Full, notanonymised
Full, notanonymised
1.9 Heat demand
1.9.1 1 Heat demand of thecapture system
Planned heatdemand for thelast 6 monthperiod
MWh/tCO2captured
Actual heat demand inlast 6 month period
MWh/ tCO2captured
Full, notanonymised
Aggregated,e.g. ranges
andaverages forplanned andactual and
deltasbetween thetwo, and with
comments asappropriate
1.10 Cooling demand
1.10.1 1 Cooling demand of thecapture system
Planned coolingdemand for thelast 6 month
MWh/tCO2captured
Actual cooling demandin last 6 month period
MWh/tCO2captured
Full, notanonymised
Ranges andaverages forplanned and
8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202
9/32
European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering
Version 2011-01-20 9
period actual anddeltas
between thetwo
1.11 Compression energyrequirement
1.11.1 2 Totalenergy requirement forcompressing CO2(energy consumption ofall elements associatedwith compression)
Planned averageenergyrequirement forlast 6 monthperiod
MWh/tCO2compressed
Actual average energyrequirement in last 6month period
MWh/tCO2compressed
Full, notanonymised
Full, notanonymised
1.12 Availability, operatinghours and shutdowns
1.12.1 2 Availability of capturesystem, relative to wall-clock time
Plannedavailability for thelast 6 monthperiod
% Actual availability forthe last 6 month period
% Full, notanonymised
Full, notanonymised
1.12.2 2 Operating hours ofcapture system
Plannedoperating hoursfor last 6 monthperiod
hrs Actual operating hoursin last 6 months
hrs Full, notanonymised
Full, notanonymised
1.12.3 1 Number ofunintended/unplannedshut downs
Number ofunintended/unplannedshut downs in last 6month period
Full, notanonymised
Aggregated,e.g. ranges
andaverages forplanned andactual and
deltasbetween thetwo, and withcomments as
appropriate
1.13 CO2 captured
1.13.1 2 Amount of CO2 capturedannually
Planned CO2captured for last6 months,
tCO2/yr Actual CO2 capturedin last 6 months,annualised
tCO2/yr Full, notanonymised
Full, notanonymised
8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202
10/32
European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering
Version 2011-01-20 10
annualised
1.14 Composition of CO2stream
1.14.1 2 Composition of the
CO2 stream beforetransportation withconcentrations
List the most
relevantcomponents inthe CO2stream beforetransportation,withconcentrations(ppm).
ppm Full, notanonymised
Full, notanonymised
Transport(pipeline)
1.15 Flow rates
1.15.1 1 Maximum flow rate(transient)
Plannedmaximum flowrate for last 6month period
kg/sec Actual maximum flowrate in last 6 monthperiod
kg/sec Full, notanonymised
Ranges andaverages forplanned andactual and
deltasbetween the
two
1.15.2 1 Average flow rate(transient)
Planned averageflow rate for last6 month period
kg/sec Actual average flowrate in last 6 months
kg/sec Full, notanonymised
Ranges andaverages forplanned andactual and
deltasbetween the
two
1.16 Inlet pressure
1.16.1 1 Inlet operating pressure(absolute)
Planned inletoperatingpressure for last6 month period
bara Actual (average) inletoperating pressure inlast 6 month period
bara Full, notanonymised
Ranges andaverages forplanned andactual and
deltas
8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202
11/32
European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering
Version 2011-01-20 11
between thetwo
1.17 Inlet temperature
1.17.1 1 Maximum inlettemperature
Plannedmaximum inlettemperature forlast 6 monthperiod
C Actual maximum inlettemperature in last 6month period
C Full, notanonymised
Ranges andaverages forplanned andactual and
deltasbetween the
two
1.18 Water dew point
1.18.1 1 Water dew point Plannedmaximum waterdew point for last6 month period
ppm Actual maximum waterdew point in last 6month period
ppm Full, notanonymised
Ranges andaverages forplanned andactual and
deltasbetween the
two
1.19 Transport energyrequirement
1.19.1 2 Totalenergy requirement fortransporting CO2(energy consumption ofall elements associatedwith transport)
Planned averageenergyrequirement forlast 6 monthperiod
MWh/tCO2transported
Actual average energyrequirement in last 6month period
MWh/tCO2transported
Full, notanonymised
Full, notanonymised
1.20 Availability, operatinghours and shutdowns
1.20.1 2 Availability of transport
system, relative to wall-clock time
Planned
availability for thelast 6 monthperiod
% Actual availability for
the last 6 month period
% Full, not
anonymised
Full, not
anonymised
1.20.2 2 Operating hours oftransport system
Plannedoperating hoursfor last 6 monthperiod
hrs Actual operating hoursin last 6 months
hrs Full, notanonymised
Full, notanonymised
8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202
12/32
European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering
Version 2011-01-20 12
1.20.3 1 Number ofunintended/unplannedshut downs
Number ofunintended/unplannedshut downs in last 6month period
Full, notanonymised
Aggregated,e.g. ranges
andaverages forplanned andactual and
deltasbetween thetwo, and withcomments asappropriate
Storage
1.21 Average injection rate
1.21.1 2 Average injection rate Planned averageinjection rate forlast 6 monthperiod
kg/sec Actual averageinjection rate in last 6month period
kg/sec Full, notanonymised
Full, notanonymised
1.22 Maximum injection rate
1.22.1 2 Maximum injection rate Plannedmaximuminjection rate forlast 6 monthperiod
kg/sec Actual maximuminjection rate in last 6month period
kg/sec Full, notanonymised
Full, notanonymised
1.23 Mass of CO2 injected
1.23.1 2 Mass of CO2 injected Planned massinjection for last6 month period,annualised
tCO2/yr Average actual massinjected over last 12month period,annualised
tCO2/yr Full, notanonymised
Full, notanonymised
1.24 Storage energyrequirement
1.24.1 2 Totalenergy requirement forstoring CO2 (energyconsumption of allelements associated withstorage)
Planned averageenergyrequirement forlast 6 monthperiod
MWh/tCO2stored
Actual average energyrequirement in last 6month period
MWh/tCO2transported
Full, notanonymised
Full, notanonymised
8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202
13/32
European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering
Version 2011-01-20 13
1.25 Availability, operatinghours and shutdowns
1.25.1 2 Availability of storagesystem, relative to wall-clock time
Plannedavailability for thelast 6 month
period
% Actual availability forthe last 6 month period
% Full, notanonymised
Full, notanonymised
1.25.2 2 Operating hours of thestorage facility
Plannedoperating hoursfor last 6 monthperiod
hrs Actual operating hoursin last 6 month period
hrs Full, notanonymised
Full, notanonymised
1.25.3 1 Number ofunintended/unplannedshut downs
Number ofunintended/unplannedshut downs in last 6month period
Full, notanonymised
Aggregated,e.g. ranges
andaverages forplanned andactual and
deltasbetween thetwo, and with
comments asappropriate
1.26 Injection pressure
1.26.1 2 Injection pressure, atbottom hole
Planned averageinjectionpressure for last6 month period
bara Actual averageinjection pressure forlast 6 month period
bara Full, notanonymised
Full, notanonymised
1.27 Reservoir pressure
1.27.1 2 Reservoir pressure, atbottom hole
Planned averagereservoirpressure for last6 month period
bara Actual averagereservoir pressure forlast 6 month period
bara Full, notanonymised
Full, notanonymised
Value Chain
1.26 Transient performance
1.26.1 1 Start-up and shut-down Planned start-up hrs Actual start-up time of hrs Full, notanonymised
Ranges and
8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202
14/32
European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering
Version 2011-01-20 14
times time of valuechain (duration)
value chain (duration)in last 6 month period
averages forplanned andactual and
deltasbetween the
two
1.26.2 1 Planned shut-down time ofvalue chain(duration)
hrs Actual shut-down timeof value chain(duration) in last 6month period
hrs Full, notanonymised
Ranges andaverages forplanned andactual and
deltasbetween the
two
1.27 Further research
1.27.1 2 Identified research needswithin CCS technologies.
Have youidentified anyareas or issuesthat need moreresearch?
Full, notanonymised
Full, notanonymised
1.28 Date of baseline
1.28.1 2 Date of the technicalbaseline, i.e. date ofplanned/budget values
Date of baselinefor plannedvalues in thissection 1
y Full, notanonymised
Full, notanonymised
NOTE: All planned values to be according to the projects currently valid baseline
8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202
15/32
European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering
Version 2011-01-20 15
2. Cost levels
IDno.
Level ItemDescription
Q1 Value1 Unit1 Q2 Value2 Unit2 Baseline Within the Network Beyond the Network
Capture2.1 Additional
investment costsdue to applicationof CO2 capture
2.1.1 0 CAPEX for thecapture system, inclcompressing
Planned totalCAPEX
Current forecastfor actual totalCAPEX
y (forplanned)
Aggregated, e.g.ranges and averagesfor planned and actualand deltas between the
two, and withcomments asappropriate
Aggregated, e.g.ranges and averagesfor planned and actualand deltas between the
two, and withcomments asappropriate
2.2 Additionaloperating costsdue to applicationof CO2 capture
2.2.1 0 OPEX for thecapture system, inclcompression
Planned OPEX(fixed andvariable) for last 6month period pertCO2 captured
/tCO2 Actual OPEX(fixed andvariable) in last 6month period pertCO2 captured
/tCO2 Aggregated, e.g.ranges and averagesfor planned and actualand deltas between the
two, and withcomments asappropriate
Aggregated, e.g.ranges and averagesfor planned and actualand deltas between the
two, and withcomments asappropriate
Transport
2.3 Additionalinvestment costsdue to CO2transport
2.3.1 0 CAPEX for thetransport system
Planned totalCAPEX
Current forecastfor actual totalCAPEX ()
y (forplanned)
Aggregated, e.g.ranges and averagesfor planned and actualand deltas between the
Aggregated, e.g.ranges and averagesfor planned and actualand deltas between the
8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202
16/32
European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering
Version 2011-01-20 16
two, and withcomments asappropriate
two, and withcomments asappropriate
2.4 Additionaloperating costs
due to CO2transport
2.4.1 0 OPEX for thetransport system
Planned OPEX(fixed andvariable) for last 6month period pertCO2 transported
/tCO2Actual OPEX(fixed andvariable) in last 6months per tCO2transported
/tCO2 Aggregated, e.g.ranges and averagesfor planned and actualand deltas between the
two, and withcomments asappropriate
Aggregated, e.g.ranges and averagesfor planned and actualand deltas between the
two, and withcomments asappropriate
Storage2.5 Additional
investment costsdue to CO2 storage
2.5.1 0 CAPEX for thestorage system
Planned totalCAPEX
Current forecastfor actual totalCAPEX ()
y (forplanned)
Aggregated, e.g.ranges and averagesfor planned and actualand deltas between the
two, and withcomments asappropriate
Aggregated, e.g.ranges and averagesfor planned and actualand deltas between the
two, and withcomments asappropriate
2.6 Additionaloperating costsdue to CO2 storage
2.6.1 0 OPEX for thetransport system Planned OPEX(fixed andvariable) for last 6month period pertCO2 stored
/tCO2 Actual OPEX(fixed andvariable) in last 6months per tCO2stored
/tCO2 Aggregated, e.g.ranges and averagesfor planned and actualand deltas between the
two, and withcomments asappropriate
Aggregated, e.g.ranges and averagesfor planned and actualand deltas between the
two, and withcomments asappropriate
8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202
17/32
European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering
Version 2011-01-20 17
Value chain
2.7 Design life
2.7.1 0 Design life of theCCS installationused for costcalculations.
Design life of theCCS installationused for costcalculationsabove.
yrs Y Aggregated, e.g.ranges and averagesfor planned and actualand deltas between the
two, and withcomments asappropriate
Aggregated, e.g.ranges and averagesfor planned and actualand deltas between the
two, and withcomments asappropriate
2.8 Date of baseline
2.8.1 0 Date of the costbaseline, i.e. date ofplanned/budgetvalues
Date of the costbaseline forplanned values inthis section 2
Y Aggregated, e.g.ranges and averagesfor planned and actualand deltas between the
two, and withcomments asappropriate
Aggregated, e.g.ranges and averagesfor planned and actualand deltas between the
two, and withcomments asappropriate
NOTE: All planned values to be according to the projects currently valid baseline
8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202
18/32
European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering
Version 2011-01-20 18
3. Project progress
ID no. Level ItemDescription
Q1 Value1 Unit1 Q2 Value2 Unit2 Baseline Within theNetwork
Beyond the Network
Capture3.1 Main milestone dates
capture plant
3.1.1 1 Detail Design Planned completion date Currentforecast /actualcompletiondate
y (forplanned)
Full, notanonymised
Anonymised datesAggregated info,e.g. ranges and
averages forplanned and actual
and deltasbetween the two,
and with commentsas appropriate
3.1.2 1 Fabrication Planned completion date Currentforecast /actualcompletiondate
y (forplanned)
Full, notanonymised
Anonymised datesAggregated info,
e.g. ranges andaverages for
planned and actualand deltas
between the two,and with comments
as appropriate
3.1.3 1 Installation Planned completion date Currentforecast /actualcompletiondate
y (forplanned)
Full, notanonymised
Anonymised datesAggregated info,e.g. ranges and
averages forplanned and actual
and deltasbetween the two,
and with commentsas appropriate
3.1.4 1 Commissioning Planned completion date Currentforecast /actualcompletiondate
y (forplanned)
Full, notanonymised
Anonymised datesAggregated info,e.g. ranges and
averages forplanned and actual
and deltas
8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202
19/32
European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering
Version 2011-01-20 19
between the two,and with comments
as appropriate
3.1.5 1 Operation Planned start date Currentforecast /actual start
date
y (forplanned)
Full, notanonymised
Anonymised datesAggregated info,e.g. ranges and
averages forplanned and actual
and deltasbetween the two,
and with commentsas appropriate
3.2 Other milestone dates
3.2.1 2 Permit(s) issued Planned completion date Currentforecast /actualcompletiondate
y (forplanned)
Full, notanonymised
Full, not anonymised
3.2.2 1 Environment Impact
Assessment
Planned completion date Current
forecast /actualcompletiondate
y (for
planned)
Full, not
anonymised
Anonymised dates
Aggregated info,e.g. ranges and
averages forplanned and actual
and deltasbetween the two,
and with commentsas appropriate
Transport
3.3 Main milestone datestransport system
3.3.1 1 Detail Design Planned completion date Current
forecast /actualcompletiondate
y (for
planned)
Full, not
anonymised
Anonymised dates
Aggregated info,e.g. ranges and
averages forplanned and actual
and deltasbetween the two,
and with commentsas appropriate
8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202
20/32
European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering
Version 2011-01-20 20
3.3.2 1 Fabrication Planned completion date Currentforecast /actualcompletiondate
y (forplanned)
Full, notanonymised
Anonymised datesAggregated info,e.g. ranges and
averages forplanned and actual
and deltas
between the two,and with comments
as appropriate
3.3.3 1 Installation Planned completion date Currentforecast /actualcompletiondate
y (forplanned)
Full, notanonymised
Anonymised datesAggregated info,e.g. ranges and
averages forplanned and actual
and deltasbetween the two,
and with commentsas appropriate
3.3.4 1 Commissioning Planned completion date Currentforecast /
actualcompletiondate
y (forplanned)
Full, notanonymised
Anonymised datesAggregated info,
e.g. ranges andaverages forplanned and actual
and deltasbetween the two,
and with commentsas appropriate
3.3.5 1 Operation Planned start date Currentforecast /actual startdate
y (forplanned)
Full, notanonymised
Anonymised datesAggregated info,e.g. ranges and
averages forplanned and actual
and deltasbetween the two,
and with comments
as appropriate
3.4 Other milestone dates
3.4.1 2 Permit(s) issued Planned completion date Currentforecast /actualcompletion
y (forplanned)
Full, notanonymised
Full, not anonymised
8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202
21/32
European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering
Version 2011-01-20 21
date
3.4.2 1 Environment ImpactAssessment
Planned completion date Currentforecast /actualcompletiondate
y (forplanned)
Full, notanonymised
Anonymised datesAggregated info,e.g. ranges and
averages forplanned and actual
and deltasbetween the two,
and with commentsas appropriate
3.4.3 1 Definition of routing Planned completion date Currentforecast /actualcompletiondate
y (forplanned)
Full, notanonymised
Anonymised datesAggregated info,e.g. ranges and
averages forplanned and actual
and deltasbetween the two,
and with commentsas appropriate
3.4.4 1 Permissions from
landowners/acquisition ofland
Planned completion date Current
forecast /actualcompletiondate
y (for
planned)
Full, notanonymised
Anonymised dates
Aggregated info,e.g. ranges andaverages for
planned and actualand deltas
between the two,and with comments
as appropriate
3.5 Transport concept
3.5.1 2 Transport concept Type of concept(s) Pipeline/Ship/Other
Y Full, notanonymised
Non-anonymisedpoint values
3.5.2 -if OTHER, describe
3.5.3 1 Selection of concept Planned completion date Currentforecast /actualcompletiondate
y (forplanned)
Full, notanonymised
Anonymised datesAggregated info,e.g. ranges and
averages forplanned and actual
and deltasbetween the two,
and with commentsas appropriate
8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202
22/32
European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering
Version 2011-01-20 22
3.6 CO2 streamcompositionspecification
3.6.1 1 Development of thespecification of CO2
stream composition
Planned completion date Currentforecast /
actualcompletiondate
y (forplanned)
Full, notanonymised
Anonymised datesAggregated info,
e.g. ranges andaverages for
planned and actualand deltas
between the two,and with comments
as appropriate
3.7 Transport concept ship
3.7.1 1 A suitable fleet of ships issecured
Planned completion date Currentforecast /actualcompletiondate
y (forplanned)
Full, notanonymised
Anonymised datesAggregated info,e.g. ranges and
averages forplanned and actual
and deltasbetween the two,and with comments
as appropriate
Storage
3.8 Main milestone datesstorage
3.8.1 1 Concept selection Planned completion date Currentforecast /actualcompletiondate
y (forplanned)
Full, notanonymised
Anonymised datesAggregated info,e.g. ranges and
averages forplanned and actual
and deltasbetween the two,
and with commentsas appropriate
3.8.2 1 Final well design Planned completion date Currentforecast /actualcompletion
y (forplanned)
Full, notanonymised
Anonymised datesAggregated info,e.g. ranges and
averages for
8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202
23/32
European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering
Version 2011-01-20 23
date planned and actualand deltas
between the two,and with comments
as appropriate
3.8.3 1 Drilling and well
completion
Planned completion date Current
forecast /actualcompletiondate
y (for
planned)
Full, not
anonymised
Anonymised dates
Aggregated info,e.g. ranges and
averages forplanned and actual
and deltasbetween the two,
and with commentsas appropriate
3.8.4 1 Commissioning Planned completion date Currentforecast /actualcompletiondate
y (forplanned)
Full, notanonymised
Anonymised datesAggregated info,e.g. ranges and
averages forplanned and actual
and deltas
between the two,and with commentsas appropriate
3.8.5 1 Begin injection Planned start date Currentforecast /actual startdate
y (forplanned)
Full, notanonymised
Anonymised datesAggregated info,e.g. ranges and
averages forplanned and actual
and deltasbetween the two,
and with commentsas appropriate
3.9 Other milestone dates
3.9.1 2 Storage permit(s) issued Planned completion date Currentforecast /actualcompletiondate
y (forplanned)
Full, not
anonymised
Full, not anonymised
3.9.2 1 Environment ImpactAssessment
Planned completion date Currentforecast /actual
y (forplanned)
Full, notanonymised
Anonymised datesAggregated info,e.g. ranges and
8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202
24/32
European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering
Version 2011-01-20 24
completiondate
averages forplanned and actual
and deltasbetween the two,
and with commentsas appropriate
3.10 Screening
3.10.1 1 Screening (no explorationpermit required)
Planned completion date Currentforecast /actualcompletiondate
y (forplanned)
Full, notanonymised
Anonymised datesAggregated info,e.g. ranges and
averages forplanned and actual
and deltasbetween the two,
and with commentsas appropriate
3.10.2 2 Number of potential storagelocations screened
Full, notanonymised
Full, not anonymised
3.10.3 1 Number of potential storage
locations taken forwards into sitecharacterization
Full, not
anonymised
Anonymised point
values
3.11 Site characterization
3.11.1 1 Site characterization(exploration permittypically required)completed
Planned completion date whenstorage concept selection canbe made
Currentforecast /actualcompletiondate
y (forplanned)
Full, notanonymised
Anonymised datesAggregated info,e.g. ranges and
averages forplanned and actual
and deltasbetween the two,
and with commentsas appropriate
3.11.2 1 Type of
exploration/characterizationundertaken (seismic, explorationdrilling, appraisal drilling, welltests, etc)
Full, notanonymised
Anonymisedsummary
3.11.3 1 Brief description of the static anddynamic models used fordefining the storage complex
Full, notanonymised
Anonymisedsummary
8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202
25/32
European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering
Version 2011-01-20 25
and well engineering solution
3.12 Storage solution
3.12.1 1 Storage complex and wellengineering solution
defined for primarystorage location
Storage complex and wellengineering solution defined for
primary storage location
Y/N Full, notanonymised
Percentage ofprojects that answer
Y
3.12.2 1 Final choice of storagecomplex and wellengineering solutionmade
Final choice of storage complexand well engineering solutionmade
Y/N Full, notanonymised
Percentage ofprojects that answer
Y
3.12.3 2 Modelled capacity of the storagecomplex over the project lifetimeusing the defined injection andoperating plan
MtCO2 Full, notanonymised
Full, not anonymised
3.12.4 1 Flowline and surface/sub-sea infrastructure conceptselected for developingthe site
Planned completion date Currentforecast /actualcompletion
date
y (forplanned)
Full, notanonymised
Anonymised datesAggregated info,e.g. ranges and
averages for
planned and actualand deltas
between the two,and with comments
as appropriate
3.13 Monitoring
3.13.1 1 Baseline monitoringinitiated
Planned start date Currentforecast /actual startdate
y (forplanned)
Full, notanonymised
Anonymised datesAggregated info,e.g. ranges and
averages forplanned and actual
and deltasbetween the two,
and with commentsas appropriate
3.13.2 1 Preliminary monitoringplan submitted toregulator
Planned completion date Currentforecast /actualcompletiondate
y (forplanned)
Full, notanonymised
Anonymised datesAggregated info,e.g. ranges and
averages forplanned and actual
and deltas
8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202
26/32
European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering
Version 2011-01-20 26
between the two,and with comments
as appropriate
3.13.3 1 Risk levels andperformance targetsdefined and agreed with
regulator
Planned completion date Currentforecast /actual
completiondate
y (forplanned)
Full, notanonymised
Anonymised datesAggregated info,e.g. ranges and
averages forplanned and actual
and deltasbetween the two,
and with commentsas appropriate
3.13.4 1 Plan for the followingactivities produced:1) monitoring of thestorage site2) verification of themonitoring3) accounting ofemissions reductions
4) reporting of each andall of the above items of3.13.4
Planned completion date Currentforecast /actualcompletiondate
y (forplanned)
Full, notanonymised
Anonymised datesAggregated info,e.g. ranges and
averages forplanned and actual
and deltasbetween the two,
and with comments
as appropriate
Value chain
3.14 Overall Project progress
3.14.1 1 Progress against projectplan at time of reporting
Planned aggregated totalprogress
% Actualaggregatedtotalprogress
% y (forplanned)
Full, notanonymised
Anonymised datesAggregated info,e.g. ranges and
averages forplanned and actual
and deltasbetween the two,
and with commentsas appropriate
3.15 Overall milestone dates
3.15.1 1 FEED study for the fullproject
Planned completion date Currentforecast /
y (forplanned)
Full, notanonymised
Anonymised datesAggregated info,e.g. ranges and
8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202
27/32
European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering
Version 2011-01-20 27
actualcompletiondate
averages forplanned and actual
and deltasbetween the two,
and with commentsas appropriate
3.15.2 2 Start-up of operation ofthe integrated (full valuechain) CCS system
Planned start date Currentforecast /actual startdate
y (forplanned)
Full, notanonymised
3.16 Date of baseline
3.16.1 2 Date of the time baseline,i.e. date ofplanned/budget values
Date of the time baseline forplanned values in this section 3
y Full, notanonymised
Full, not anonymised
NOTE: All planned values to be according to the projects currently valid baseline
8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202
28/32
European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering
Version 2011-01-20 28
4. Environment
ID no. Level ItemDescription
Q1 Value1 Unit1 Q2 Value2 Unit2 Baseline Within theNetwork
Beyond the Network
4.1 Chemicals
4.1.1 2 Decision on solventtaken
Planned completiondate
Current forecast /actual completion date
Full, notanonymised
Full, not anonymised
4.1.2 2 Solvent volumes etc Type/category ofsolvent
4.1.3 2 Volume of solvent(m3) in use duringthe capture process
m3
Y (forplanned)
Full, notanonymised
Full, not anonymised
4.1.4 1 Turnover of solvent Planned turnover ofsolvent for last 6month period,annualised
% peryr
Actual turnover ofsolvent in last 6 monthperiod, annualised
% peryr
Full, notanonymised
Aggregated, e.g.ranges andaverages for
planned and actualand deltas between
the two, and withcomments as
appropriate4.1.5 2 Planned recycling
rate% Actual recycling rate in
last 6 month period% Y (for
planned)
Full, notanonymised
Full, not anonymised
4.2 Emissions to air
4.2.1 1 Gaseous emissions(other than CO2), asfractions of the CO2stream
Planned emission ofH2O, H2S, SOx,NOx, H2, O2, otherfor last 6 monthperiod
%(ppmv)
Actual emission in thelast 6 months of H2O,H2S, SOx, NOx, H2,O2, other
% Full, notanonymised
Aggregated, e.g.ranges andaverages for
planned and actualand deltas between
the two, and withcomments asappropriate
4.3 Consumables
4.3.1 1 Consumption of waterdue to CO2 capture
Plannedconsumption ofwater for last 6month period
kg/MWh Actual consumption inlast 6 months of water
kg/MWh Full, notanonymised
Aggregated, e.g.ranges andaverages for
planned and actual
8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202
29/32
European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering
Version 2011-01-20 29
and deltas betweenthe two, and with
comments asappropriate
4.3.2 2 Consumption ofsolvents due to CO2
capture
Plannedconsumption of
solvents for last 6month period
kg/MWh Actual consumption inlast 6 months of
solvents
kg/MWh Full, notanonymised
Full, not anonymised
4.4 CO2 loss/leakage
4.4.1 1 Losses and leakages ofCO2 throughoutcapture operations
Losses andleakages in last 6months fromcapture, annualised
tCO2/yr Full, notanonymised
Aggregated, e.g.ranges andaverages for
planned and actualand deltas between
the two, and withcomments asappropriate
4.4.2 1 Losses and leakages of
CO2 throughouttransport operations
Losses and
leakages in last 6months fromtransport,annualised
tCO2/yr Full, not
anonymised
Aggregated, e.g.
ranges andaverages for
planned and actualand deltas between
the two, and withcomments asappropriate
4.4.3 1 Losses and leakages ofCO2 throughoutstorage operations
Losses andleakages in last 6months fromstorage, annualised
tCO2/yr Full, notanonymised
Aggregated, e.g.ranges andaverages for
planned and actualand deltas between
the two, and withcomments as
appropriate
4.5 Plot sizes
4.5.1 2 Plot size required forcapture, transport andstorage.
Planned plot sizeused for the facilitiesin each step of thevalue chain forprevious 6 months
m2
Actual/forecasted plotsize for the facilities ineach step of the valuechain for previous 6months
m2 Full, not
anonymisedFull, not anonymised
8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202
30/32
European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering
Version 2011-01-20 30
4.6 Storage monitoringresults
4.6.1 2 Report the main resultsfrom the baselinemonitoring results from
the storage complex
Main results frombaseline monitoring
Full, notanonymised
Full, not anonymised
4.6.2 2 Results from monitoringof the storage site andassessment of theresults.
Results frommonitoring of thestorage site andassessment of theresults, in the last 6month period.
Full, notanonymised
Full, not anonymised
4.7 CO2 migration
4.7.1 2 Report andassess/interpretdevelopment in CO2plume anddisplacement of brine.
Contamination of soil orfreshwater?
How does CO2migrate in thestorage site?
Full, notanonymised
Full, not anonymised
4.8 Observed storage sitedevelopment vssimulations
4.8.1 2 Report lessons learnedfrom calibration andhistory matching ofstorage site models
Main lessonslearned from historymatching of thereservoir model
Full, notanonymised
Full, not anonymised
4.9 Other impacts
4.9.1 2 Other environmentalimpacts
Have youexperienced any
undesiredenvironmentalimpact incidents inthe last 6 months?If yes, mitigating,emergency and/orevasive actions to
Y/N
Full, notanonymised
Full, not anonymised
8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202
31/32
European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering
Version 2011-01-20 31
deal with theincidents
4.10 Further research
4.10.1 2 Identified researchneeds within
environmental impactof CCS.
Have you identifiedany areas or issues
that need moreresearch?
Full, notanonymised
Full, not anonymised
NOTE: All planned values shall be according to the projects currently valid baselineNOTE: All values in this section 4 will be moved to sharing Level 2 at the latest when the project goes into operation
8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202
32/32
European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering
Version 2011-01-20 32
5. Health and safety
IDno.
Level ItemDescription
Q1 Value1 Unit1 Q2 Value2 Unit2 Baseline Within theNetwork
Beyond theNetwork
5.1 Health and safety plan
5.1.1 2 Health and SafetyManagementPlan/System
Lessons learnt during safety planningspecifically relating to CCS
Y/N Full, notanonymised
Full, notanonymised
5.2 Undesireable incidents
5.2.1 2 Health and safetyincidents
Have you had any accidents, near missesand/or hazardous conditions that are related toCCS in the last 6 months?
Y/N Full, notanonymised
Full, notanonymised
5.2.2 2 If yes; mitigating, emergency and/or evasiveactions to deal with the incidents.
Full, notanonymised
Full, notanonymised