    Version 2011-01-20

    European CO2 Capture and Storage (CCS) Demonstration Project Network

    Information and experience gathering form

  • 8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202

    2/32

  • 8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202

    3/32

  • 8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202

    4/32

    European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering

    Version 2011-01-20 4

    Baseline

    Form

    Periodic

    Update

    Period: 2010-2

    Periodic

    Update

    Period: 2010-1

    Baseline

    Form

    Periodic

    Update

    Period: 2010-2

    Periodic

    Update

    Period: 2010-1

    Baseline

    Form

    Periodic

    Update

    Period: 2010-2

    Periodic

    Update

    Period: 2010-1

    Webform logic

    The current implementation model foreseen is:

    Each project completes a baseline form orstart form, i.e. the first time that they add content to theinformation and experience gathering application. The form aims to capture all planned figures in thecategory project progress and other data that are unlikely to change much over the course of reporting.

    Thereafter, a periodic update form is completed, according to the tables in this document. Thiscontinues for each reporting period (projects will be able to access information submitted for previousperiods, but will not be able to change them).

    The system will provide the Network Team with some tools for generating graphs and overviews peritem on the form with which to illustrate reports. We have chosen not to have report-generationfunctionality, aiming to prevent uncontrolled dissemination of detailed information.

  • 8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202

    5/32

    European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering

    Version 2011-01-20 5

    Structure of the tables

    The tables presented below contain the following columns: ID: unique identifier for the sharing item (each item is grouped into a main, sub- and subsubcategory) Level: designation of the sharing level of the item (level 0: to be shared with the European Commission only, level 1: to be shared within

    the Network membership, level 2: to be shared beyond the Network membership) Item Description: description of the item as it will be used in the online form Q1: question as it will appear on the online form (Q1 typically seeks information regarding planned values in a certain area) Value1: the value the respondent enters against Q1. Unit1: the unit of Value1. Unit1 will be shown on the form to aid completion. Q2: question as it will appear on the online form (Q2 typically seeks information regarding actual or forecasted values in a certain area).

    Where Q2 is empty, no Q2 is envisaged (nor Value2 and Unit2) Value2: the value the respondent enters against Q2. Unit2: the unit of Value2. Unit2 will be shown on the form to aid completion. Baseline: this column identifies whether or not an item is part of the baseline form (and is to be submitted once, during first use of the

    tool). Within the Network: this column describes what information will be shared within the Network Beyond the Network: this column identifies what information will be shared beyond the Network for this item, as part of reports

    prepared by the Network Team.

  • 8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202

    6/32

    European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering

    Version 2011-01-20 6

    1. Technical set-up and performance

    ID Level Item Description Q1 Value1 Unit1 Q2 Value2 Unit2 BaseLine?

    Within theNetwork

    Beyond the

    NetworkPower PlantThe items in this section arevalid also for industrialplants as far as they areapplicable

    1.1 Fuel Type

    1.1.1 2 Fuel used in power plantto which CCS is applied

    Fuel type used inpower plant

    y Full, notanonymised

    Full, notanonymised

    1.2 Carbon content in fuel

    1.2.1 2 Carbon content in fuelused

    Percent of carbon infuel

    % Full, notanonymised

    Full, notanonymised

    1.3 Electricity production

    1.3.1 2 Electricity productionfrom power plant withoutCCS

    Planned for last6 month period,annualised

    MWh/yr Actual over last 6month period,annualised

    MWh/yr Full, notanonymised

    Full, notanonymised

    1.3.2 2 Electricity productionfrom power plant withCCS

    Planned for last6 month period,annualised

    MWh/yr Actual over last 6month period,annualised

    MWh/yr Full, notanonymised

    Full, notanonymised

    1.4 Availability, operatinghours and shutdowns

    1.4.1 2 Availability of the powerplant, for operation withCCS, relative to wall-clock time

    Plannedavailability for thelast 6 monthperiod

    % Actual availability forthe last 6 month period

    % Full, notanonymised

    Full, notanonymised

    1.4.2 2 Operating hours of thepower plant (includingboth with and withoutCCS)

    Plannedoperating hoursfor the last 6month period

    hrs Actual operating hoursin last 6 months

    Hrs Full, notanonymised

    Full, notanonymised

    1.4.3 1 Number ofunintended/unplannedshut downs

    Number ofunintended/unplannedshut downs in last 6

    Full, notanonymised

    Full, notanonymised

  • 8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202

    7/32

    European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering

    Version 2011-01-20 7

    month period

    1.5 Process efficiency

    1.5.1 2 Net efficiency of thepower plant without CCS

    Planned netefficiency of thepower plant forthe last 6 monthperiod, full loadvalue

    % Actual net efficiency ofthe power plant for thelast 6 month period,full load value

    % Full, notanonymised

    Full, notanonymised

    1.5.2 2 Planned netefficiency of thepower plant forthe last 6 monthperiod, averagevalue

    % Actual net efficiency ofthe power plant for thelast 6 month period,average value

    % Full, notanonymised

    Full, notanonymised

    1.5.3 2 Net efficiency of thepower plant with CCS

    Planned netefficiency of thepower plant forthe last 6 monthperiod, full load

    value

    % Actual net efficiency ofthe power plant for thelast 6 month period,full load value

    % Full, notanonymised

    Full, notanonymised

    1.5.4 2 Planned netefficiency of thepower plant forthe last 6 monthperiod, averagevalue

    % Actual net efficiency ofthe power plant for thelast 6 month period,average value

    % Full, notanonymised

    Full, notanonymised

    Capture

    1.6 Increase in fuelconsumption

    1.6.1 2 Percentage increase in

    fuel consumption due toimplementation ofcapture, i.e. the part ofthe power plant withCCS, includingcompression. Theconsumption ofsecondary energy inputs

    Planned for last

    6 month period

    % Actual for last 6 month

    period

    % Full, notanonymised

    Full, notanonymised

  • 8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202

    8/32

    European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering

    Version 2011-01-20 8

    shall be included asequivalents to theprimary fuel.

    1.7 Capture performance

    1.7.1 2 Average rate of CO2capture

    Planned averagecapture rate forlast 6 monthperiod

    % Actual averagecapture rate over last6 month period

    % Full, notanonymised

    Full, not

    anonymised

    1.7.2 Planned full loadcapture rate forlast 6 monthperiod

    % Actual full load capturerate in last 6 months

    %

    1.8 Capture energyrequirement

    1.8.1 2 Totalenergy requirement forcapturing CO2 (energyconsumption of allelements associated withcapture, excludingcompression)

    Planned averageenergyrequirement forlast 6 monthperiod

    MWh/tCO2captured

    Actual average energyrequirement in last 6month period

    MWh/ tCO2captured

    Full, notanonymised

    Full, notanonymised

    1.9 Heat demand

    1.9.1 1 Heat demand of thecapture system

    Planned heatdemand for thelast 6 monthperiod

    MWh/tCO2captured

    Actual heat demand inlast 6 month period

    MWh/ tCO2captured

    Full, notanonymised

    Aggregated,e.g. ranges

    andaverages forplanned andactual and

    deltasbetween thetwo, and with

    comments asappropriate

    1.10 Cooling demand

    1.10.1 1 Cooling demand of thecapture system

    Planned coolingdemand for thelast 6 month

    MWh/tCO2captured

    Actual cooling demandin last 6 month period

    MWh/tCO2captured

    Full, notanonymised

    Ranges andaverages forplanned and

  • 8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202

    9/32

    European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering

    Version 2011-01-20 9

    period actual anddeltas

    between thetwo

    1.11 Compression energyrequirement

    1.11.1 2 Totalenergy requirement forcompressing CO2(energy consumption ofall elements associatedwith compression)

    Planned averageenergyrequirement forlast 6 monthperiod

    MWh/tCO2compressed

    Actual average energyrequirement in last 6month period

    MWh/tCO2compressed

    Full, notanonymised

    Full, notanonymised

    1.12 Availability, operatinghours and shutdowns

    1.12.1 2 Availability of capturesystem, relative to wall-clock time

    Plannedavailability for thelast 6 monthperiod

    % Actual availability forthe last 6 month period

    % Full, notanonymised

    Full, notanonymised

    1.12.2 2 Operating hours ofcapture system

    Plannedoperating hoursfor last 6 monthperiod

    hrs Actual operating hoursin last 6 months

    hrs Full, notanonymised

    Full, notanonymised

    1.12.3 1 Number ofunintended/unplannedshut downs

    Number ofunintended/unplannedshut downs in last 6month period

    Full, notanonymised

    Aggregated,e.g. ranges

    andaverages forplanned andactual and

    deltasbetween thetwo, and withcomments as

    appropriate

    1.13 CO2 captured

    1.13.1 2 Amount of CO2 capturedannually

    Planned CO2captured for last6 months,

    tCO2/yr Actual CO2 capturedin last 6 months,annualised

    tCO2/yr Full, notanonymised

    Full, notanonymised

  • 8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202

    10/32

    European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering

    Version 2011-01-20 10

    annualised

    1.14 Composition of CO2stream

    1.14.1 2 Composition of the

    CO2 stream beforetransportation withconcentrations

    List the most

    relevantcomponents inthe CO2stream beforetransportation,withconcentrations(ppm).

    ppm Full, notanonymised

    Full, notanonymised

    Transport(pipeline)

    1.15 Flow rates

    1.15.1 1 Maximum flow rate(transient)

    Plannedmaximum flowrate for last 6month period

    kg/sec Actual maximum flowrate in last 6 monthperiod

    kg/sec Full, notanonymised

    Ranges andaverages forplanned andactual and

    deltasbetween the

    two

    1.15.2 1 Average flow rate(transient)

    Planned averageflow rate for last6 month period

    kg/sec Actual average flowrate in last 6 months

    kg/sec Full, notanonymised

    Ranges andaverages forplanned andactual and

    deltasbetween the

    two

    1.16 Inlet pressure

    1.16.1 1 Inlet operating pressure(absolute)

    Planned inletoperatingpressure for last6 month period

    bara Actual (average) inletoperating pressure inlast 6 month period

    bara Full, notanonymised

    Ranges andaverages forplanned andactual and

    deltas

  • 8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202

    11/32

    European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering

    Version 2011-01-20 11

    between thetwo

    1.17 Inlet temperature

    1.17.1 1 Maximum inlettemperature

    Plannedmaximum inlettemperature forlast 6 monthperiod

    C Actual maximum inlettemperature in last 6month period

    C Full, notanonymised

    Ranges andaverages forplanned andactual and

    deltasbetween the

    two

    1.18 Water dew point

    1.18.1 1 Water dew point Plannedmaximum waterdew point for last6 month period

    ppm Actual maximum waterdew point in last 6month period

    ppm Full, notanonymised

    Ranges andaverages forplanned andactual and

    deltasbetween the

    two

    1.19 Transport energyrequirement

    1.19.1 2 Totalenergy requirement fortransporting CO2(energy consumption ofall elements associatedwith transport)

    Planned averageenergyrequirement forlast 6 monthperiod

    MWh/tCO2transported

    Actual average energyrequirement in last 6month period

    MWh/tCO2transported

    Full, notanonymised

    Full, notanonymised

    1.20 Availability, operatinghours and shutdowns

    1.20.1 2 Availability of transport

    system, relative to wall-clock time

    Planned

    availability for thelast 6 monthperiod

    % Actual availability for

    the last 6 month period

    % Full, not

    anonymised

    Full, not

    anonymised

    1.20.2 2 Operating hours oftransport system

    Plannedoperating hoursfor last 6 monthperiod

    hrs Actual operating hoursin last 6 months

    hrs Full, notanonymised

    Full, notanonymised

  • 8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202

    12/32

    European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering

    Version 2011-01-20 12

    1.20.3 1 Number ofunintended/unplannedshut downs

    Number ofunintended/unplannedshut downs in last 6month period

    Full, notanonymised

    Aggregated,e.g. ranges

    andaverages forplanned andactual and

    deltasbetween thetwo, and withcomments asappropriate

    Storage

    1.21 Average injection rate

    1.21.1 2 Average injection rate Planned averageinjection rate forlast 6 monthperiod

    kg/sec Actual averageinjection rate in last 6month period

    kg/sec Full, notanonymised

    Full, notanonymised

    1.22 Maximum injection rate

    1.22.1 2 Maximum injection rate Plannedmaximuminjection rate forlast 6 monthperiod

    kg/sec Actual maximuminjection rate in last 6month period

    kg/sec Full, notanonymised

    Full, notanonymised

    1.23 Mass of CO2 injected

    1.23.1 2 Mass of CO2 injected Planned massinjection for last6 month period,annualised

    tCO2/yr Average actual massinjected over last 12month period,annualised

    tCO2/yr Full, notanonymised

    Full, notanonymised

    1.24 Storage energyrequirement

    1.24.1 2 Totalenergy requirement forstoring CO2 (energyconsumption of allelements associated withstorage)

    Planned averageenergyrequirement forlast 6 monthperiod

    MWh/tCO2stored

    Actual average energyrequirement in last 6month period

    MWh/tCO2transported

    Full, notanonymised

    Full, notanonymised

  • 8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202

    13/32

    European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering

    Version 2011-01-20 13

    1.25 Availability, operatinghours and shutdowns

    1.25.1 2 Availability of storagesystem, relative to wall-clock time

    Plannedavailability for thelast 6 month

    period

    % Actual availability forthe last 6 month period

    % Full, notanonymised

    Full, notanonymised

    1.25.2 2 Operating hours of thestorage facility

    Plannedoperating hoursfor last 6 monthperiod

    hrs Actual operating hoursin last 6 month period

    hrs Full, notanonymised

    Full, notanonymised

    1.25.3 1 Number ofunintended/unplannedshut downs

    Number ofunintended/unplannedshut downs in last 6month period

    Full, notanonymised

    Aggregated,e.g. ranges

    andaverages forplanned andactual and

    deltasbetween thetwo, and with

    comments asappropriate

    1.26 Injection pressure

    1.26.1 2 Injection pressure, atbottom hole

    Planned averageinjectionpressure for last6 month period

    bara Actual averageinjection pressure forlast 6 month period

    bara Full, notanonymised

    Full, notanonymised

    1.27 Reservoir pressure

    1.27.1 2 Reservoir pressure, atbottom hole

    Planned averagereservoirpressure for last6 month period

    bara Actual averagereservoir pressure forlast 6 month period

    bara Full, notanonymised

    Full, notanonymised

    Value Chain

    1.26 Transient performance

    1.26.1 1 Start-up and shut-down Planned start-up hrs Actual start-up time of hrs Full, notanonymised

    Ranges and

  • 8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202

    14/32

    European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering

    Version 2011-01-20 14

    times time of valuechain (duration)

    value chain (duration)in last 6 month period

    averages forplanned andactual and

    deltasbetween the

    two

    1.26.2 1 Planned shut-down time ofvalue chain(duration)

    hrs Actual shut-down timeof value chain(duration) in last 6month period

    hrs Full, notanonymised

    Ranges andaverages forplanned andactual and

    deltasbetween the

    two

    1.27 Further research

    1.27.1 2 Identified research needswithin CCS technologies.

    Have youidentified anyareas or issuesthat need moreresearch?

    Full, notanonymised

    Full, notanonymised

    1.28 Date of baseline

    1.28.1 2 Date of the technicalbaseline, i.e. date ofplanned/budget values

    Date of baselinefor plannedvalues in thissection 1

    y Full, notanonymised

    Full, notanonymised

    NOTE: All planned values to be according to the projects currently valid baseline

  • 8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202

    15/32

    European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering

    Version 2011-01-20 15

    2. Cost levels

    IDno.

    Level ItemDescription

    Q1 Value1 Unit1 Q2 Value2 Unit2 Baseline Within the Network Beyond the Network

    Capture2.1 Additional

    investment costsdue to applicationof CO2 capture

    2.1.1 0 CAPEX for thecapture system, inclcompressing

    Planned totalCAPEX

    Current forecastfor actual totalCAPEX

    y (forplanned)

    Aggregated, e.g.ranges and averagesfor planned and actualand deltas between the

    two, and withcomments asappropriate

    Aggregated, e.g.ranges and averagesfor planned and actualand deltas between the

    two, and withcomments asappropriate

    2.2 Additionaloperating costsdue to applicationof CO2 capture

    2.2.1 0 OPEX for thecapture system, inclcompression

    Planned OPEX(fixed andvariable) for last 6month period pertCO2 captured

    /tCO2 Actual OPEX(fixed andvariable) in last 6month period pertCO2 captured

    /tCO2 Aggregated, e.g.ranges and averagesfor planned and actualand deltas between the

    two, and withcomments asappropriate

    Aggregated, e.g.ranges and averagesfor planned and actualand deltas between the

    two, and withcomments asappropriate

    Transport

    2.3 Additionalinvestment costsdue to CO2transport

    2.3.1 0 CAPEX for thetransport system

    Planned totalCAPEX

    Current forecastfor actual totalCAPEX ()

    y (forplanned)

    Aggregated, e.g.ranges and averagesfor planned and actualand deltas between the

    Aggregated, e.g.ranges and averagesfor planned and actualand deltas between the

  • 8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202

    16/32

    European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering

    Version 2011-01-20 16

    two, and withcomments asappropriate

    two, and withcomments asappropriate

    2.4 Additionaloperating costs

    due to CO2transport

    2.4.1 0 OPEX for thetransport system

    Planned OPEX(fixed andvariable) for last 6month period pertCO2 transported

    /tCO2Actual OPEX(fixed andvariable) in last 6months per tCO2transported

    /tCO2 Aggregated, e.g.ranges and averagesfor planned and actualand deltas between the

    two, and withcomments asappropriate

    Aggregated, e.g.ranges and averagesfor planned and actualand deltas between the

    two, and withcomments asappropriate

    Storage2.5 Additional

    investment costsdue to CO2 storage

    2.5.1 0 CAPEX for thestorage system

    Planned totalCAPEX

    Current forecastfor actual totalCAPEX ()

    y (forplanned)

    Aggregated, e.g.ranges and averagesfor planned and actualand deltas between the

    two, and withcomments asappropriate

    Aggregated, e.g.ranges and averagesfor planned and actualand deltas between the

    two, and withcomments asappropriate

    2.6 Additionaloperating costsdue to CO2 storage

    2.6.1 0 OPEX for thetransport system Planned OPEX(fixed andvariable) for last 6month period pertCO2 stored

    /tCO2 Actual OPEX(fixed andvariable) in last 6months per tCO2stored

    /tCO2 Aggregated, e.g.ranges and averagesfor planned and actualand deltas between the

    two, and withcomments asappropriate

    Aggregated, e.g.ranges and averagesfor planned and actualand deltas between the

    two, and withcomments asappropriate

  • 8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202

    17/32

    European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering

    Version 2011-01-20 17

    Value chain

    2.7 Design life

    2.7.1 0 Design life of theCCS installationused for costcalculations.

    Design life of theCCS installationused for costcalculationsabove.

    yrs Y Aggregated, e.g.ranges and averagesfor planned and actualand deltas between the

    two, and withcomments asappropriate

    Aggregated, e.g.ranges and averagesfor planned and actualand deltas between the

    two, and withcomments asappropriate

    2.8 Date of baseline

    2.8.1 0 Date of the costbaseline, i.e. date ofplanned/budgetvalues

    Date of the costbaseline forplanned values inthis section 2

    Y Aggregated, e.g.ranges and averagesfor planned and actualand deltas between the

    two, and withcomments asappropriate

    Aggregated, e.g.ranges and averagesfor planned and actualand deltas between the

    two, and withcomments asappropriate

    NOTE: All planned values to be according to the projects currently valid baseline

  • 8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202

    18/32

    European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering

    Version 2011-01-20 18

    3. Project progress

    ID no. Level ItemDescription

    Q1 Value1 Unit1 Q2 Value2 Unit2 Baseline Within theNetwork

    Beyond the Network

    Capture3.1 Main milestone dates

    capture plant

    3.1.1 1 Detail Design Planned completion date Currentforecast /actualcompletiondate

    y (forplanned)

    Full, notanonymised

    Anonymised datesAggregated info,e.g. ranges and

    averages forplanned and actual

    and deltasbetween the two,

    and with commentsas appropriate

    3.1.2 1 Fabrication Planned completion date Currentforecast /actualcompletiondate

    y (forplanned)

    Full, notanonymised

    Anonymised datesAggregated info,

    e.g. ranges andaverages for

    planned and actualand deltas

    between the two,and with comments

    as appropriate

    3.1.3 1 Installation Planned completion date Currentforecast /actualcompletiondate

    y (forplanned)

    Full, notanonymised

    Anonymised datesAggregated info,e.g. ranges and

    averages forplanned and actual

    and deltasbetween the two,

    and with commentsas appropriate

    3.1.4 1 Commissioning Planned completion date Currentforecast /actualcompletiondate

    y (forplanned)

    Full, notanonymised

    Anonymised datesAggregated info,e.g. ranges and

    averages forplanned and actual

    and deltas

  • 8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202

    19/32

    European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering

    Version 2011-01-20 19

    between the two,and with comments

    as appropriate

    3.1.5 1 Operation Planned start date Currentforecast /actual start

    date

    y (forplanned)

    Full, notanonymised

    Anonymised datesAggregated info,e.g. ranges and

    averages forplanned and actual

    and deltasbetween the two,

    and with commentsas appropriate

    3.2 Other milestone dates

    3.2.1 2 Permit(s) issued Planned completion date Currentforecast /actualcompletiondate

    y (forplanned)

    Full, notanonymised

    Full, not anonymised

    3.2.2 1 Environment Impact

    Assessment

    Planned completion date Current

    forecast /actualcompletiondate

    y (for

    planned)

    Full, not

    anonymised

    Anonymised dates

    Aggregated info,e.g. ranges and

    averages forplanned and actual

    and deltasbetween the two,

    and with commentsas appropriate

    Transport

    3.3 Main milestone datestransport system

    3.3.1 1 Detail Design Planned completion date Current

    forecast /actualcompletiondate

    y (for

    planned)

    Full, not

    anonymised

    Anonymised dates

    Aggregated info,e.g. ranges and

    averages forplanned and actual

    and deltasbetween the two,

    and with commentsas appropriate

  • 8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202

    20/32

    European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering

    Version 2011-01-20 20

    3.3.2 1 Fabrication Planned completion date Currentforecast /actualcompletiondate

    y (forplanned)

    Full, notanonymised

    Anonymised datesAggregated info,e.g. ranges and

    averages forplanned and actual

    and deltas

    between the two,and with comments

    as appropriate

    3.3.3 1 Installation Planned completion date Currentforecast /actualcompletiondate

    y (forplanned)

    Full, notanonymised

    Anonymised datesAggregated info,e.g. ranges and

    averages forplanned and actual

    and deltasbetween the two,

    and with commentsas appropriate

    3.3.4 1 Commissioning Planned completion date Currentforecast /

    actualcompletiondate

    y (forplanned)

    Full, notanonymised

    Anonymised datesAggregated info,

    e.g. ranges andaverages forplanned and actual

    and deltasbetween the two,

    and with commentsas appropriate

    3.3.5 1 Operation Planned start date Currentforecast /actual startdate

    y (forplanned)

    Full, notanonymised

    Anonymised datesAggregated info,e.g. ranges and

    averages forplanned and actual

    and deltasbetween the two,

    and with comments

    as appropriate

    3.4 Other milestone dates

    3.4.1 2 Permit(s) issued Planned completion date Currentforecast /actualcompletion

    y (forplanned)

    Full, notanonymised

    Full, not anonymised

  • 8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202

    21/32

    European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering

    Version 2011-01-20 21

    date

    3.4.2 1 Environment ImpactAssessment

    Planned completion date Currentforecast /actualcompletiondate

    y (forplanned)

    Full, notanonymised

    Anonymised datesAggregated info,e.g. ranges and

    averages forplanned and actual

    and deltasbetween the two,

    and with commentsas appropriate

    3.4.3 1 Definition of routing Planned completion date Currentforecast /actualcompletiondate

    y (forplanned)

    Full, notanonymised

    Anonymised datesAggregated info,e.g. ranges and

    averages forplanned and actual

    and deltasbetween the two,

    and with commentsas appropriate

    3.4.4 1 Permissions from

    landowners/acquisition ofland

    Planned completion date Current

    forecast /actualcompletiondate

    y (for

    planned)

    Full, notanonymised

    Anonymised dates

    Aggregated info,e.g. ranges andaverages for

    planned and actualand deltas

    between the two,and with comments

    as appropriate

    3.5 Transport concept

    3.5.1 2 Transport concept Type of concept(s) Pipeline/Ship/Other

    Y Full, notanonymised

    Non-anonymisedpoint values

    3.5.2 -if OTHER, describe

    3.5.3 1 Selection of concept Planned completion date Currentforecast /actualcompletiondate

    y (forplanned)

    Full, notanonymised

    Anonymised datesAggregated info,e.g. ranges and

    averages forplanned and actual

    and deltasbetween the two,

    and with commentsas appropriate

  • 8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202

    22/32

    European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering

    Version 2011-01-20 22

    3.6 CO2 streamcompositionspecification

    3.6.1 1 Development of thespecification of CO2

    stream composition

    Planned completion date Currentforecast /

    actualcompletiondate

    y (forplanned)

    Full, notanonymised

    Anonymised datesAggregated info,

    e.g. ranges andaverages for

    planned and actualand deltas

    between the two,and with comments

    as appropriate

    3.7 Transport concept ship

    3.7.1 1 A suitable fleet of ships issecured

    Planned completion date Currentforecast /actualcompletiondate

    y (forplanned)

    Full, notanonymised

    Anonymised datesAggregated info,e.g. ranges and

    averages forplanned and actual

    and deltasbetween the two,and with comments

    as appropriate

    Storage

    3.8 Main milestone datesstorage

    3.8.1 1 Concept selection Planned completion date Currentforecast /actualcompletiondate

    y (forplanned)

    Full, notanonymised

    Anonymised datesAggregated info,e.g. ranges and

    averages forplanned and actual

    and deltasbetween the two,

    and with commentsas appropriate

    3.8.2 1 Final well design Planned completion date Currentforecast /actualcompletion

    y (forplanned)

    Full, notanonymised

    Anonymised datesAggregated info,e.g. ranges and

    averages for

  • 8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202

    23/32

    European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering

    Version 2011-01-20 23

    date planned and actualand deltas

    between the two,and with comments

    as appropriate

    3.8.3 1 Drilling and well

    completion

    Planned completion date Current

    forecast /actualcompletiondate

    y (for

    planned)

    Full, not

    anonymised

    Anonymised dates

    Aggregated info,e.g. ranges and

    averages forplanned and actual

    and deltasbetween the two,

    and with commentsas appropriate

    3.8.4 1 Commissioning Planned completion date Currentforecast /actualcompletiondate

    y (forplanned)

    Full, notanonymised

    Anonymised datesAggregated info,e.g. ranges and

    averages forplanned and actual

    and deltas

    between the two,and with commentsas appropriate

    3.8.5 1 Begin injection Planned start date Currentforecast /actual startdate

    y (forplanned)

    Full, notanonymised

    Anonymised datesAggregated info,e.g. ranges and

    averages forplanned and actual

    and deltasbetween the two,

    and with commentsas appropriate

    3.9 Other milestone dates

    3.9.1 2 Storage permit(s) issued Planned completion date Currentforecast /actualcompletiondate

    y (forplanned)

    Full, not

    anonymised

    Full, not anonymised

    3.9.2 1 Environment ImpactAssessment

    Planned completion date Currentforecast /actual

    y (forplanned)

    Full, notanonymised

    Anonymised datesAggregated info,e.g. ranges and

  • 8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202

    24/32

    European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering

    Version 2011-01-20 24

    completiondate

    averages forplanned and actual

    and deltasbetween the two,

    and with commentsas appropriate

    3.10 Screening

    3.10.1 1 Screening (no explorationpermit required)

    Planned completion date Currentforecast /actualcompletiondate

    y (forplanned)

    Full, notanonymised

    Anonymised datesAggregated info,e.g. ranges and

    averages forplanned and actual

    and deltasbetween the two,

    and with commentsas appropriate

    3.10.2 2 Number of potential storagelocations screened

    Full, notanonymised

    Full, not anonymised

    3.10.3 1 Number of potential storage

    locations taken forwards into sitecharacterization

    Full, not

    anonymised

    Anonymised point

    values

    3.11 Site characterization

    3.11.1 1 Site characterization(exploration permittypically required)completed

    Planned completion date whenstorage concept selection canbe made

    Currentforecast /actualcompletiondate

    y (forplanned)

    Full, notanonymised

    Anonymised datesAggregated info,e.g. ranges and

    averages forplanned and actual

    and deltasbetween the two,

    and with commentsas appropriate

    3.11.2 1 Type of

    exploration/characterizationundertaken (seismic, explorationdrilling, appraisal drilling, welltests, etc)

    Full, notanonymised

    Anonymisedsummary

    3.11.3 1 Brief description of the static anddynamic models used fordefining the storage complex

    Full, notanonymised

    Anonymisedsummary

  • 8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202

    25/32

    European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering

    Version 2011-01-20 25

    and well engineering solution

    3.12 Storage solution

    3.12.1 1 Storage complex and wellengineering solution

    defined for primarystorage location

    Storage complex and wellengineering solution defined for

    primary storage location

    Y/N Full, notanonymised

    Percentage ofprojects that answer

    Y

    3.12.2 1 Final choice of storagecomplex and wellengineering solutionmade

    Final choice of storage complexand well engineering solutionmade

    Y/N Full, notanonymised

    Percentage ofprojects that answer

    Y

    3.12.3 2 Modelled capacity of the storagecomplex over the project lifetimeusing the defined injection andoperating plan

    MtCO2 Full, notanonymised

    Full, not anonymised

    3.12.4 1 Flowline and surface/sub-sea infrastructure conceptselected for developingthe site

    Planned completion date Currentforecast /actualcompletion

    date

    y (forplanned)

    Full, notanonymised

    Anonymised datesAggregated info,e.g. ranges and

    averages for

    planned and actualand deltas

    between the two,and with comments

    as appropriate

    3.13 Monitoring

    3.13.1 1 Baseline monitoringinitiated

    Planned start date Currentforecast /actual startdate

    y (forplanned)

    Full, notanonymised

    Anonymised datesAggregated info,e.g. ranges and

    averages forplanned and actual

    and deltasbetween the two,

    and with commentsas appropriate

    3.13.2 1 Preliminary monitoringplan submitted toregulator

    Planned completion date Currentforecast /actualcompletiondate

    y (forplanned)

    Full, notanonymised

    Anonymised datesAggregated info,e.g. ranges and

    averages forplanned and actual

    and deltas

  • 8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202

    26/32

    European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering

    Version 2011-01-20 26

    between the two,and with comments

    as appropriate

    3.13.3 1 Risk levels andperformance targetsdefined and agreed with

    regulator

    Planned completion date Currentforecast /actual

    completiondate

    y (forplanned)

    Full, notanonymised

    Anonymised datesAggregated info,e.g. ranges and

    averages forplanned and actual

    and deltasbetween the two,

    and with commentsas appropriate

    3.13.4 1 Plan for the followingactivities produced:1) monitoring of thestorage site2) verification of themonitoring3) accounting ofemissions reductions

    4) reporting of each andall of the above items of3.13.4

    Planned completion date Currentforecast /actualcompletiondate

    y (forplanned)

    Full, notanonymised

    Anonymised datesAggregated info,e.g. ranges and

    averages forplanned and actual

    and deltasbetween the two,

    and with comments

    as appropriate

    Value chain

    3.14 Overall Project progress

    3.14.1 1 Progress against projectplan at time of reporting

    Planned aggregated totalprogress

    % Actualaggregatedtotalprogress

    % y (forplanned)

    Full, notanonymised

    Anonymised datesAggregated info,e.g. ranges and

    averages forplanned and actual

    and deltasbetween the two,

    and with commentsas appropriate

    3.15 Overall milestone dates

    3.15.1 1 FEED study for the fullproject

    Planned completion date Currentforecast /

    y (forplanned)

    Full, notanonymised

    Anonymised datesAggregated info,e.g. ranges and

  • 8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202

    27/32

    European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering

    Version 2011-01-20 27

    actualcompletiondate

    averages forplanned and actual

    and deltasbetween the two,

    and with commentsas appropriate

    3.15.2 2 Start-up of operation ofthe integrated (full valuechain) CCS system

    Planned start date Currentforecast /actual startdate

    y (forplanned)

    Full, notanonymised

    3.16 Date of baseline

    3.16.1 2 Date of the time baseline,i.e. date ofplanned/budget values

    Date of the time baseline forplanned values in this section 3

    y Full, notanonymised

    Full, not anonymised

    NOTE: All planned values to be according to the projects currently valid baseline

  • 8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202

    28/32

    European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering

    Version 2011-01-20 28

    4. Environment

    ID no. Level ItemDescription

    Q1 Value1 Unit1 Q2 Value2 Unit2 Baseline Within theNetwork

    Beyond the Network

    4.1 Chemicals

    4.1.1 2 Decision on solventtaken

    Planned completiondate

    Current forecast /actual completion date

    Full, notanonymised

    Full, not anonymised

    4.1.2 2 Solvent volumes etc Type/category ofsolvent

    4.1.3 2 Volume of solvent(m3) in use duringthe capture process

    m3

    Y (forplanned)

    Full, notanonymised

    Full, not anonymised

    4.1.4 1 Turnover of solvent Planned turnover ofsolvent for last 6month period,annualised

    % peryr

    Actual turnover ofsolvent in last 6 monthperiod, annualised

    % peryr

    Full, notanonymised

    Aggregated, e.g.ranges andaverages for

    planned and actualand deltas between

    the two, and withcomments as

    appropriate4.1.5 2 Planned recycling

    rate% Actual recycling rate in

    last 6 month period% Y (for

    planned)

    Full, notanonymised

    Full, not anonymised

    4.2 Emissions to air

    4.2.1 1 Gaseous emissions(other than CO2), asfractions of the CO2stream

    Planned emission ofH2O, H2S, SOx,NOx, H2, O2, otherfor last 6 monthperiod

    %(ppmv)

    Actual emission in thelast 6 months of H2O,H2S, SOx, NOx, H2,O2, other

    % Full, notanonymised

    Aggregated, e.g.ranges andaverages for

    planned and actualand deltas between

    the two, and withcomments asappropriate

    4.3 Consumables

    4.3.1 1 Consumption of waterdue to CO2 capture

    Plannedconsumption ofwater for last 6month period

    kg/MWh Actual consumption inlast 6 months of water

    kg/MWh Full, notanonymised

    Aggregated, e.g.ranges andaverages for

    planned and actual

  • 8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202

    29/32

    European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering

    Version 2011-01-20 29

    and deltas betweenthe two, and with

    comments asappropriate

    4.3.2 2 Consumption ofsolvents due to CO2

    capture

    Plannedconsumption of

    solvents for last 6month period

    kg/MWh Actual consumption inlast 6 months of

    solvents

    kg/MWh Full, notanonymised

    Full, not anonymised

    4.4 CO2 loss/leakage

    4.4.1 1 Losses and leakages ofCO2 throughoutcapture operations

    Losses andleakages in last 6months fromcapture, annualised

    tCO2/yr Full, notanonymised

    Aggregated, e.g.ranges andaverages for

    planned and actualand deltas between

    the two, and withcomments asappropriate

    4.4.2 1 Losses and leakages of

    CO2 throughouttransport operations

    Losses and

    leakages in last 6months fromtransport,annualised

    tCO2/yr Full, not

    anonymised

    Aggregated, e.g.

    ranges andaverages for

    planned and actualand deltas between

    the two, and withcomments asappropriate

    4.4.3 1 Losses and leakages ofCO2 throughoutstorage operations

    Losses andleakages in last 6months fromstorage, annualised

    tCO2/yr Full, notanonymised

    Aggregated, e.g.ranges andaverages for

    planned and actualand deltas between

    the two, and withcomments as

    appropriate

    4.5 Plot sizes

    4.5.1 2 Plot size required forcapture, transport andstorage.

    Planned plot sizeused for the facilitiesin each step of thevalue chain forprevious 6 months

    m2

    Actual/forecasted plotsize for the facilities ineach step of the valuechain for previous 6months

    m2 Full, not

    anonymisedFull, not anonymised

  • 8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202

    30/32

    European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering

    Version 2011-01-20 30

    4.6 Storage monitoringresults

    4.6.1 2 Report the main resultsfrom the baselinemonitoring results from

    the storage complex

    Main results frombaseline monitoring

    Full, notanonymised

    Full, not anonymised

    4.6.2 2 Results from monitoringof the storage site andassessment of theresults.

    Results frommonitoring of thestorage site andassessment of theresults, in the last 6month period.

    Full, notanonymised

    Full, not anonymised

    4.7 CO2 migration

    4.7.1 2 Report andassess/interpretdevelopment in CO2plume anddisplacement of brine.

    Contamination of soil orfreshwater?

    How does CO2migrate in thestorage site?

    Full, notanonymised

    Full, not anonymised

    4.8 Observed storage sitedevelopment vssimulations

    4.8.1 2 Report lessons learnedfrom calibration andhistory matching ofstorage site models

    Main lessonslearned from historymatching of thereservoir model

    Full, notanonymised

    Full, not anonymised

    4.9 Other impacts

    4.9.1 2 Other environmentalimpacts

    Have youexperienced any

    undesiredenvironmentalimpact incidents inthe last 6 months?If yes, mitigating,emergency and/orevasive actions to

    Y/N

    Full, notanonymised

    Full, not anonymised

  • 8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202

    31/32

    European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering

    Version 2011-01-20 31

    deal with theincidents

    4.10 Further research

    4.10.1 2 Identified researchneeds within

    environmental impactof CCS.

    Have you identifiedany areas or issues

    that need moreresearch?

    Full, notanonymised

    Full, not anonymised

    NOTE: All planned values shall be according to the projects currently valid baselineNOTE: All values in this section 4 will be moved to sharing Level 2 at the latest when the project goes into operation

  • 8/6/2019 European Ccs Project Network Knowledge Sharing Template 201101202

    32/32

    European CO2 Capture and Storage (CCS) Demonstration Project NetworkInformation and experience gathering

    Version 2011-01-20 32

    5. Health and safety

    IDno.

    Level ItemDescription

    Q1 Value1 Unit1 Q2 Value2 Unit2 Baseline Within theNetwork

    Beyond theNetwork

    5.1 Health and safety plan

    5.1.1 2 Health and SafetyManagementPlan/System

    Lessons learnt during safety planningspecifically relating to CCS

    Y/N Full, notanonymised

    Full, notanonymised

    5.2 Undesireable incidents

    5.2.1 2 Health and safetyincidents

    Have you had any accidents, near missesand/or hazardous conditions that are related toCCS in the last 6 months?

    Y/N Full, notanonymised

    Full, notanonymised

    5.2.2 2 If yes; mitigating, emergency and/or evasiveactions to deal with the incidents.

    Full, notanonymised

    Full, notanonymised


Recommended