+ All Categories
Home > Documents > Ficha Proy (Ingles)

Ficha Proy (Ingles)

Date post: 07-Aug-2018
Category:
Upload: alejandro425
View: 221 times
Download: 0 times
Share this document with a friend

of 52

Transcript
  • 8/21/2019 Ficha Proy (Ingles)

    1/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 1

    CLEAN DEVELOPMENT MECHANISM

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD)

    Version 03 - in effect as of: 28 July 2006

    CONTENTS

    A. General description of project activity

    B. Application of a baseline and monitoring methodology

    C. Duration of the project activity / crediting period

    D. Environmental impacts

    E. Stakeholders comments

    Annexes

    Annex 1: Contact information on participants in the project activity

    Annex 2: Information regarding public funding

    Annex 3: Baseline information

    Annex 4: Monitoring plan

  • 8/21/2019 Ficha Proy (Ingles)

    2/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 2

    SECTION A. General description of project activity

    A.1. Title of the project activity:

    Title: Za Hung Hydropower Project

    Version: 2.4

    Date: 29/11/2011

    A.2. Description of the project activity:

    The project activity is being developed by Za Hung Joint Stock Company. It involves the construction of

    a new gird connected hydropower plant including a dam, intakes, tunnels, power house with 02 units

    (each unit has a turbine and a power generator) and discharge channels located in Za Hung and Ma Cooihcommunes, Dong Giang district, Quang Nam province of Viet Nam.

    Electricity in Viet Nam is generated mainly from fossil fuel sources and is solely distributed to consumers

    via the unique national electricity grid.

    The projects purpose is to generate hydroelectricity by installation of water turbines and generators from

    a clean and renewable source (hydropower of the AVuong stream) to supply to the national grid via a

    Power Purchase Agreement (PPA) signed with the Electricity of Viet Nam (EVN). The project's installed

    capacity and estimated annual gross power generation is 30 MW and 122,700 MWh1, respectively. The

    net electricity generated (with an estimated annual volume of 120,246 MWh2) will be supplied to the

    national grid via a newly constructed 110kV transmission line which will connect the plant and the Thanh

    My transformer station.

    The baseline scenario of the project activity is the same as the scenario existing prior to the start of

    implementation of the project activity.

    The project activity will generate renewable power with negligible GHG emissions, which will displace

    part of the electricity otherwise supplied by grid-connected fossil fuel fired power plants. The project

    involves the construction of reservoir with area of 0.22993km

    2and the power density of the diversion

    reservoir of 130.54W/m

    2. As the power density of reservoir is above 10 W/m

    2, no GHG emissions from

    the reservoirs need to be accounted in the project activity as per the methodology applied ACM0002

    version 12.2.0. Thus, GHG emission reductions can be achieved via this proposed project activity. Total

    expected CO2emission reduction is 485,163 tCO2e over the first crediting period of 7 years.

    The projects contributions to the sustainable development of the local area as well as the host country are

    as follows:

    General contributions towards national sustainable development:

    In recent years, Viet Nam has suffered a critical electricity shortage as a consequence from rapidly

    increasing demand and insufficient supply, thereby imposing negative impacts on economic growth

    as well as on daily lives of people. This project activity will be a contribution towards balancing the

    supply and demand gap. By exporting electricity directly to the grid, it will help to reduce

    electricity losses across the national grid and to lessen the risks of cascading national grid collapse

    due to overload.

    Reducing reliance on exhaustible fossil fuel based power sources and also reducing the import of

    fuels for the purpose of power generation.

    1Technical Design Report, Explainable Additional Volume2 The gross power generation subtracts 2% for internal use, parasitic and loss load. Technical Design Report.3Technical Design Report, Explainable Additional Volume4Please refer to Section B.6

  • 8/21/2019 Ficha Proy (Ingles)

    3/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 3

    Modern and highly efficient turbines and generators are imported from China. The profession

    technicians and engineers will train the hydropower plant staffs on the operation and maintenance

    procedures before the starting operation of the project. The power transmission will also be at highvoltage to ensure low losses. The project will accelerate the deployment of renewable energy

    technologies in Viet Nam.

    Contributions towards local sustainable development:

    a) Economic well-being

    Once commissioning, this proposed project will increase the industrial share in the economic structure of

    Quang Nam province a poor province in the Central of Viet Nam. This proposed project will pay annual

    enterprises revenue tax and the natural resource tax5and CER tax6to the state budget.

    By supplying a stable electricity output, this project will facilitate the industrialisation process of the

    province and support economic development of local villages through fostering tourism, trade and

    services inside the province.

    b) Social well-being

    This project will contribute directly to improve the low-quality infrastructure systems of the Za Hung and

    Ma Cooih communes. The communes are categorised as a mountainous commune with thin population,

    less developed and autarky agricultural economy. The project will upgrade roads that then will be

    integrated into the traffic system of the communes. The project will construct a new 110 kV transmission

    line together with a hydropower plant, which will reduce electricity losses and improve the electricity

    quality supplied in the region.

    The project will newly construct and upgrade roads that then will be integrated into the traffic system of

    the communes. The project will construct a new 110kV transmission line to export electricity to national

    grid. The volume of Za Hung hydropower plant dispatches to grid will reduce electricity losses andimprove the electricity quality supplied in the region.

    The project activity could result in the employment of the local people for the construction and operation

    later on. Therefore, this project activity will contribute directly to alleviate poverty in the region.

    This demonstrates that the project activity will contribute positively towards sustainable

    development in term of environmental well-being (off setting fossil fuel use and lowering GHG

    emission), socially (upgrading infrastructure, ensuring reliable electricity supply, improving

    employment), technologically (technology transfer) and economically (satisfying growing energy

    demands to allow the country and region to develop and alleviate poverty). Thus the project

    activity is consistent with the energy policies set by the Government of Viet Nam andit satisfies the

    sustainable development criteria for CDM projects set by the DNA of Viet Nam.

    A.3. Project participants:

    Name of Party involved (*)

    ((host) indicates a host Party)

    Private and/or public entity(ies)

    project participants(*) (as

    applicable)

    Kindly indicate if the Party

    involved wishes to be

    considered as project

    participant (Yes/No)

    Viet Nam (host) Za Hung Joint Stock Company

    (Private Entity)

    No

    Switzerland Vietnam Carbon Assets Ltd. No

    5According to the Investment law and Natural resource law6According to Circular No. 58/2008/TTLT-BTC-BTN&MT issued by Ministry of Finance and Ministry of Natural Resource and

    Environment on 04 July 2008

  • 8/21/2019 Ficha Proy (Ingles)

    4/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 4

    (Private Entity)

    (*) In accordance with the CDM modalities and procedures, at the time of making the PDD public at the

    stage of validation, a Party involved may or may not have provided its approval. At the time of requestingregistration, the approval by the Party(ies) involved is required.

    A.4. Technical description of the project activity:

    A.4.1. Location of the project activity:

    A.4.1.1. Host Party(ies):

    Viet Nam

    A.4.1.2. Region/State/Province etc.:

    Quang Nam province

    A.4.1.3. City/Town/Community etc.:

    Za Hung and Ma Cooih communes, Dong Giang district

    A.4.1.4. Details of physical location, including information allowing the

    unique identification of this project activity (maximum one page):

    The proposed project activity involves the construction of Za Hung powerhouse which is located on the A

    Vuong stream in Za Hung and Ma Cooih communes, Dong Giang district, Quang Nam province of VietNam. The dam of project has the following coordinates:

    Coordinates Dam Power House

    Northern latitude 1505143 15

    05135

    Eastern longitude 10703915 107

    03912

    The site of the project is showed in Figure below:

  • 8/21/2019 Ficha Proy (Ingles)

    5/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 5

    Figure 1: Map of the location of the project activity

    A.4.2. Category(ies) of project activity:

    Sectoral scope/ Category: 1: Energy industries (renewable sources)

    Grid-connected electricity generation from renewable sources

    A.4.3. Technology to be employed by the project activity:

    Electricity in Viet Nam supplied to the national grid is generated by the operation of grid-connected

    power plants and mainly firing coal, oil or gas and is solely distributed via the unique national electricity

    grid. All fuel fired power plants connected to the national grid use boiler rooms, steam heating boilers and

    steam turbines to generate electricity so GHGs are emitted during these processes. By contrast, hydro

    power generation is a renewable electricity generation technology which does not generate significant

    GHG emissions and displaces electricity supplied to the grid from fossil-fuel-fired power generationsources. Therefore the implementation of this project activity will reduce GHGs emissions.

    The project activity involves the construction of a dam, intake, tunnel, power house containing two

    turbines and generators with a total capacity of 30MW and a discharge channel in order to convert

    potential flowing energy from A Vuong River into clean electrical energy, which will be supplied to the

    national grid though 110 kV transmission line. It also involves the construction of a reservoir with a

    power density of 130.5 W/m2. Accordingly, no GHG emissions from the reservoir need to be accounted

    under this project activity.

    At the connection point, the power meter systems will be installed. They are digital and bi-directional

    type to measure the export and import electricity of Za Hung hydropower plant.

    The project's installed capacity is 30 MW and the estimated annual gross and net power generation are

    122,700 MWh7 and 120,246 MWh8respectively.

    7Technical Design Report, Explainable Additional Volume8 The gross power generation subtracts 2% for internal use, parasitic and loss load. Technical Design Report.

    Pro ects site

  • 8/21/2019 Ficha Proy (Ingles)

    6/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 6

    Figure below shows the layout of the project.

    Figure 2: Project lay-out

    The main technical parameters of the Za Hung Hydropower Project are shown in Table below.

    Table 1: Main technical parameters of the proposed project activity9

    Main parameters Units Values

    1. Turbine

    Type Francis Vertical shaft

    Rated net head m 66.5

    Number of turbine set 02

    Turbine discharge m3/s 25.76

    Efficiency % 92.3

    Capacity MW 15.544

    Speed rpm 375

    Expected lifetime10 hour 150,000

    2. Generator

    Number set 02

    Type Synchronous, 3 phases, vertical axis

    Rated voltage kV 10.5

    Rated capacity MW 15.0

    Efficiency at 100% load, Cos= 0.8 % 96.8

    Expected lifetime11 year 30

    3. Transformer

    Number set 02

    9The contract on supplying equipment and technical equipment document

    10The default lifetime in the EB 50, Annex 1511The default lifetime in the EB 50, Annex 15

  • 8/21/2019 Ficha Proy (Ingles)

    7/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 7

    Primary voltage kV 10.5

    Secondary voltage kV 121

    Expected lifetime12 year 304. Annual river flow m

    3/s 34.1

    The main equipment utilized in this project is imported from China via Equipment Supply Contract

    No.08-ZH-TB1-CTZH dated 05 May 2007 between the Project Owner and Associate Representation

    LOGITIC Company Limited. All the turbines, alternators, transformers and other equipments are state-of-

    the-art technology and meeting the criteria of the tender document. The professional technicians and

    engineers from the equipment supplier will train the operational staff of the Za Hung Hydropower plant

    on the monitoring procedures, operation regulations, maintenance procedures, and other relevant

    operational knowledge before operating the power plant. Furthermore, there will be regularly internal

    training courses on monitoring and operation for the staff during the operation period. So the modern

    technology would be transferred to the host country.

    The baseline scenario of this project activity is identical to the existing scenario mentioned above, where

    electricity is generated Vietnamese national grid system which is mainly composed of GHG intensive

    fossil fuel based power station.

    A.4.4. Estimated amount of emission reductions over the chosen crediting period:

    The project activity will achieve GHG emission reduction by replacing part of power generated mainly by

    fossil fuel fired plants connected to the national grid. The project will apply three renewable seven-

    crediting-year periods. The estimated emission reductions of the first crediting period are presented in

    Table below.

    Table 2: Emission reduction of the proposed project during the first crediting period

    Years Annual estimation of emission reductions in

    tonnes of CO2 e

    2012 69,309

    2013 69,309

    2014 69,309

    2015 69,309

    2016 69,309

    2017 69,309

    2018 69,309

    Total estimated reductions

    (tonnes of CO2e)485,163

    Total number of crediting years 7

    Annual average over the crediting period of

    estimated reductions (tonnes of CO2e)

    69,309

    A.4.5. Public funding of the project activity:

    No public funds13

    from Annex I countries is involved in this project.

    SECTION B. Application of a baseline and monitoring methodology

    B.1. Title and reference of the approved baseline and monitoring methodology applied to the

    project activity:

    12The default lifetime in the EB 50 Annex 1513

    The Project owner has official letter to declare no ODA fund

  • 8/21/2019 Ficha Proy (Ingles)

    8/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 8

    Applied methodology:

    Version 12.2.0 of ACM0002: Consolidated baseline methodology for grid-connected electricitygeneration from renewable sources

    Related tools:

    Version 02.2.1 of the Tool to calculate the emission factor for an electricity system

    Version 06.0.0 of the Tool for the demonstration and assessment of additionality

    Version 02 of the Tool to calculate project or leakage CO2 emission from fossil fuelconsumption

    The methodology and the related tools are available on the UNFCCC website:

    http://cdm.unfccc.int/methodologies/DB/C505BVV9P8VSNNV3LTK1BP3OR24Y5L

    B.2. Justification of the choice of the methodology and why it is applicable to the project activity:

    This proposed project is a grid-connected renewable power generation that is then eligible to apply

    Version 12.2.0 of ACM0002. More details of the comparison of the projects characteristics and the

    applicability criteria as specified in, Version 12.2.0 of ACM0002 is given in Table below.

    Table 3: Comparison of projects characteristics and eligibility criteria of Version 12.2.0 of

    ACM0002

    Applicability conditions in Version 12.2.0 of

    ACM0002

    Characteristics of the project

    activity

    Applicability

    criterion met?

    This methodology is applicable to grid-connected

    renewable power generation project activities that

    (a) install a new power plant at a site where no

    renewable power plant was operated prior to the

    implementation of the project activity (green field

    plant); (b) involve a capacity addition; (c) involve a

    retrofit of (an) existing plant(s); or (d) involve a

    replacement of (an) existing plant(s).

    The project activity consists in

    the installation of a new grid

    connected renewable power

    plants at a site where no

    renewable power plant was

    operated prior to the

    implementation of the project

    activity (green field plant).

    Yes

    The project activity is the installation, capacity

    addition, retrofit or replacement of a power

    plant/unit of one of the following types: hydro

    power plant/unit (either with a run of river reservoiror an accumulation reservoir), wind power

    plant/unit, geothermal power plant/unit, solar

    power plant/unit, wave power plant/unit or tidal

    power plant/unit;

    The project activity involves the

    installation of a new

    hydropower plant.

    Yes

    In the case of the capacity additions, retrofits or

    replacements (except for wind, solar, wave or tidal

    power capacity addition projects which use Option

    2: on page 11 to calculate the parameter EGPJ,y): the

    existing plant started commercial operation prior to

    the start of a minimum historical reference period

    of five years, used for the calculation of baseline

    emissions and defined in the baseline emissionsection, and no capacity expansion or retrofit of the

    plant has been undertaken between the start of this

    minimum historical reference period and the

    The project activity is to install

    a new hydro power plant.

    Not applicable

  • 8/21/2019 Ficha Proy (Ingles)

    9/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 9

    implementation of the project activity;

    In case of hydro power plants, one of the following

    conditions must apply:

    The project activity is implemented in anexisting single or multiple reservoirs, with no

    change in the volume of any of reservoirs; or

    The project activity is to create

    a new reservoir.Not applicable

    The project activity is implemented in anexisting single or multiple reservoirs, where

    the volume of any of reservoirs is increased

    and the power density of each reservoir, as

    per definitions given in the project emissions

    section, is greater than 4 W/m2; or

    The project activity is to create

    a new reservoir.

    Not applicable

    The project activity results in new single or

    multiple reservoirs and the power density ofeach reservoir, as per definitions given in the

    project Emissions section, is greater than 4

    W/m2.

    The project activity results in a

    new reservoir, with a powerdensity of 130.5 W/m

    2, which is

    greater than 4 W/m2.

    Yes

    In case of hydro power plants using multiple

    reservoirs where the power density of any of the

    reservoirs is lower than 4 W/m2

    all the following

    conditions must apply:

    The project activity results in a

    new reservoir, with a power

    density of 130.5 W/m2, which is

    greater than 4 W/m2.

    Not applicable

    The power density calculated for the entireproject activity using equation 5 is greater

    than 4 W/m2;

    Multiple reservoirs and hydro power plantslocated at the same river and where are

    designed together to function as an

    integrated project1 that collectively

    constitute the generation capacity of the

    combined power plant;

    Water flow between multiple reservoirs isnot used by any other hydropower unit

    which is not a part of the project activity;

    Total installed capacity of the power units,which are driven using water from the

    reservoirs with power density lower than 4

    W/m2, is lower than 15MW;

    Total installed capacity of the power units,which are driven using water from

    reservoirs with power density lower than 4

    W/m2, is less than 10% of the total

    installed capacity of the project activity

    from multiple reservoirs.

    This methodology is not applicable to the

    following:

    Project activities that involve switchingfrom fossil fuels to renewable energy

    sources at the site of the project activity,since in this case the baseline may be the

    continued use of the fossil fuels at the site.

    It is a renewable energy project

    with no fuel-switch involved.

    Yes

  • 8/21/2019 Ficha Proy (Ingles)

    10/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 10

    Biomass fired power plants. The project activity is to installa new hydro power plant.

    Yes

    Hydropower plants that result in new singlereservoirs or in the increase in an existing

    single reservoir where the power density of

    the power plant is less than 4 W/m2.

    The project activity results in anew reservoir, with a power

    density of 130.5 W/m2, which is

    greater than 4 W/m2.

    Yes

    This comparison shows clearly that Version 12.2.0 of ACM0002 is applicable to the proposed project

    activity.

    B.3. Description of the sources and gases included in the project boundary:

    According to Version 12.2.0 of ACM0002, the spatial extent of the project boundary includes the Za

    Hung hydro power plant and all power plants connected physically to the national electricity grid towhich the proposed project is also connected.

    The flow diagram of the project boundary is shown in Figure below.

    Figure 3: Project boundary

    The GHGs and emission sources included in or excluded from the project boundary are shown in Table

    below.

    Table 4: Sources and gases included in or excluded from the project boundary

    Source Gas Included? Justification/Explanation

    Baseline

    CO2 emission

    from electricity

    generation in

    fossil fuel fired

    power plants that

    is displaced due

    to the project

    activity

    CO2 Yes Main emission source

    CH4 No Minor emission source

    N2O No Minor emission source

    GHGs Emission represent by EFCM

    Viet NamNational

    Electricity grid

    Turbines

    Generators

    Transformers

    Fossil fuel fired power

    plants

    ReservoirsGHGs Emission

    Water flow

    Electric Energy

    Kinetic Energy

  • 8/21/2019 Ficha Proy (Ingles)

    11/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 11

    ProjectActivity

    For hydro power

    plants, emissions

    of CH4 from theReservoir

    CO2 No Minor emission source

    CH4 No Main emission source.

    However, the power density of the project isgreater than 10 W/m

    2 so CH4 emissions are

    neglected, according to ACM0002, Version

    12.2.0.

    N2O No Minor emission source

    B.4. Description of how the baseline scenario is identified and description of the identified baseline

    scenario:

    According to Version 12.2.0 of ACM0002, if the project activity is the installation of a new grid-

    connected renewable power plant, the baseline scenario is the following:

    Electricity delivered to the grid by the project activity would have otherwise been generated by the

    operation of grid-connected power plants and by the addition of new generation sources, as reflected in

    the combined margin calculations described in the Tool to calculate the emission factor for an electricity

    system.

    The Viet Nam national electricity grid, which is operated and monopolized by the EVN and is the unique

    transmission and distribution line, to which all power plants in Viet Nam are physically connected is the

    project electricity system.

    Thus the baseline scenario of the proposed project is the delivery of equivalent amount of annual power

    output from the Viet Nam national grid to which the proposed project is also connected. The database for

    calculating the baseline is published by the DNA of Vietnam.

    The analysis and description in B.6 will support the baseline scenario shown above.

    B.5. Description of how the anthropogenic emissions of GHG by sources are reduced below those

    that would have occurred in the absence of the registered CDM project activity (assessment and

    demonstration of additionality):

    According to Version 12.2.0 of ACM0002, the latest version of the Tool for the demonstration andassessment of additionality shall be used to demonstrate the additionality of this project activity. Version

    06.0.0of the additionality tool includes the following steps:

    Step 1: Identification of alternatives to the project activity consistent with current laws and

    regulations

    Sub-step 1a: Define alternatives to the project activity

    Version 06.0.0 of the additionality tool states: Project activities that apply this tool in context of

    approved consolidated methodology ACM0002, only need to identify that there is at least one credible

    and feasible alternative that would be more attractive than the proposed project activity.

    We will therefore consider the two scenarios in the following analysis:

    Alternative 1: the proposed project undertaken without the CDM

    Alternative 2: continuation of the current situation. In this case, the proposed project will not be

    constructed and the power will be solely supplied from the Vietnam national grid.

    Sub-step 1b: Consistency with mandatory laws and regulations

    The alternative 2 continuation of the current situation alternative does not face with any barrier from

    the current law and regulation in Vietnam because it is the do-nothing alternative. The project owner of

  • 8/21/2019 Ficha Proy (Ingles)

    12/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 12

    a proposed project has no obligation to build or invest in the power plant to supply electricity for the local

    area. Hence this alternative is consistent with mandatory laws and regulations.

    The alternative 1 is consistent with mandatory laws and regulations of Vietnam14.

    Step 2: Investment analysis

    Sub-step 2a: Determine appropriate analysis method

    The proposed project activity generates financial and economic benefits other than CER revenues, so the

    simple cost analysis (Option I) is not applicable. Out of the two remaining options, Option II is also not

    applicable as there are no other credible and realistic baseline scenario alternatives other than electricity

    supply from the grid. Thus, the benchmark analysis (Option III) is chosen to prove additionality.

    Sub-step 2b Option III: Apply benchmark analysis

    In the following, Project IRR is used to demonstrate the Additionality of the project. Provided that the

    proposed project is financed by both equity and loan sources, the appropriate benchmark is WACC

    which represents the weighted average of the costs of various sources of financing in the financing

    structure. This benchmark represents the minimal required project IRR of the project to be economically

    attractive.

    The WACC benchmark is indicated in Annex: Guidance on Assessment of Investment Analysis, Version

    05, Annex 05, EB62, Local commercial lending rates or weighted average costs of capital (WACC) are

    appropriate benchmarks for a project IRR. Thus the project participant applies the following WACC

    equation to estimate the required return on capitalas a benchmark for this project IRR:

    eR R (1 )d cWACC E D T = + (1)

    Where:

    Re : cost of equity

    Rd : cost of debt

    E : equity ratio

    D : debt ratio

    Tc : average enterprise tax rate

    This WACC is the the cost of financing and required return on capital which is based on private

    equity investors/fundrequired return on comparable projects as presented in Option III, Item (30)(b) ofTool for the demonstration and assessment of additionality version 06.0.0

    Determine the equity ratio

    Decision No 30/2006/QD-BCN issued on 31 August 2006 by the Ministry of Industry requires that the

    investment capital of project owner (equity) in an IPP project must be accounted for at least 30%. So the

    average industry equity ratio is determined as 30%.

    E= 0.3Determine the debt ratio

    Because industry projects are financed by equity and debt so D = 1-E

    D= 0.7

    14This project owner received the investment license for this project on 16 May 2007. This proved that this project complies withthe law and regulation in Viet Nam.

  • 8/21/2019 Ficha Proy (Ingles)

    13/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 13

    Determine the cost of debt

    The cost of debt is the interest rate for a long-term loan prevailed at the time of making the investment

    decision. The project participant chooses the lowest value of the range from 12.6% to 16.2% of the

    interest rates for long-term credit published in the Annual Report of the State Bank of Viet Nam in 2005.

    This report is published at the website of the State Bank annually (www.sbv.gov.vn/). So the cost of debt

    used for benchmark derivation is conservative and standard value.

    The applied cost of debt is 12.6% at the date of making the investment decision.

    Determine the cost of equity

    To derive an appropriate cost of equity for electricity generation project type in Vietnam, the following

    well-known CAPM15

    standard formula, which describes the relationship between risk and expectedreturn, is employed:

    Re = Rf+ *(Rm,- Rf) (2)

    Where:

    Re, cost of equity for electricity generation project type

    Rf Risk free rate return

    Beta of the security for electricity generation project type

    Rm,- Rf, Market risk premium

    Risk free rate:

    The risk free rate is understood as the rate of return on an asset that is theoretically free of any risks,

    therefore the rate of interest on government bonds are considered as risk free rates. Accordingly the risk

    free rate has been taken from long term Vietnamese government bond rates available at the date of

    making the investment decision. The data on government bond rates is published on Asia Commercial

    Bank securities company website.

    The risk free rate applied is 9.25% for 15 years term16

    .

    Beta:

    Beta () indicates the sensitivity of the company to market risk factors. Beta represents the market risk for

    an asset and is calculated as the statistical measure of volatility of a specific asset/investment relative to

    the movement of a market group. The conventional approach for estimating beta of an investment is a

    regression of returns on investment against returns on a market index. For companies that are not publicly

    listed like Za Hung Joint Stock Company, the beta is determined by referring to beta values of publicly

    listed companies that are engaged in similar types of business. The project activity type is power

    15In finance, the Capital Asset Pricing Model (CAPM) is used to determine a theoretically appropriate required rate of returnof an asset, if that asset is to be added to an already well-diversified portfolio, given that asset's non-diversifiable risk. The model

    takes into account the asset's sensitivity to non-diversifiable risk (also known as systemic risk or market risk), often represented

    by the quantity beta () in the financial industry, as well as the expected return of the market and the expected return of atheoretical risk-free asset.16

    http://hnx.vn/Danhsach_TCDKGD_TraiPhieu.asp?actType=1&menuup=402000&TypeGrp=1&menuid=114000&menulink=400000&menupage=Danhsach_TCDKGD_TraiPhieu.asp&stocktype=1

  • 8/21/2019 Ficha Proy (Ingles)

    14/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 14

    generation; therefore the applied beta for this project should be based on the beta values of listed power

    generation companies in Vietnam.

    Due to the difference in capital structure (Debt/Equity) between these companies and Za Hung JointStock Company, the Beta applied for this CDM project has to be adjusted according to the following

    steps:

    Step 1 It is obtained the Levered Betas of hydropower companies published in stock market withits own capital structures;

    Step 2 The Beta is Unlevered according the average capital structure of the companies; Theunlevered beta is the beta of a company without any debt. Unlevering a beta removes the financial

    effects from leverage17

    .

    Step 3 The Unlevered Beta is levered again according to the capital structure of the Za HungHydropower project. This Levered Beta was used for calculation of cost of equity of the Za Hung

    Project

    Table 5: Betas of similar companies in hydro power generation18

    Company nameLevered Beta

    of similar

    projects

    D/EUnlevered

    Beta

    Levered

    Beta for

    CDM

    project

    Vinh Son Song Hinh

    Hydropower Company

    0.75 0.44 0.57 1.52

    According to the source from Bloomberg19

    , the average beta of electricity generation companies in from

    other companies in emerging countries (which are in the process of rapid growth and industrializationhaving similar economic conditions to Viet Nam) in the year 2002, 2003, 2004, 2005 is 0.83, 0, 91, 0.97,

    1.39 respectively.

    So conservative, the project participant chose 0.83 as the applied beta for return on equity calculation.

    Risk Premium:

    The most common approach for estimating the risk premium is to base it on historical data, in the CAPM

    model, the premium is estimated by looking at the difference between average return on stocks and the

    risk free rate return. The average return on stocks is defined as the compounded annual return.

    Table 6: Market expected return calculation.

    Market index (VN Index) as on 28-

    Jul-2000 100.00

    Market index (VN Index) as on 17-

    July-2006 506.10

    No. of years 5.97

    Market Expected Return 31.19%

    17http://www.investopedia.com/terms/u/unleveredbeta.asp 18 At time of decision making, there was only one hydropower generation company which was listed. The betas of Vinh SonSong Hinh HPP has been calculated by the project developer based on the published daily data. The link of sources is

    http://www.cophieu68.com/incomestatementq.php?id=VSH 19http://www.stern.nyu.edu/~adamodar/

  • 8/21/2019 Ficha Proy (Ingles)

    15/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 15

    Substituting

    Rf = 9.25%;

    Rm = 31.19%;

    = 0.83

    in(2), we get the cost of equity for power generation projects in Viet Nam at the date of decision

    making of the proposed projectas follows:

    Re = 27.46%

    This rate of the cost of equity for power generation sector meets the EB rules because it reflects a sector

    specific approach. It is calculated based on similar companies operating in power generation sector in

    Viet Nam therefore it reflects standard in the market, considering the specific characteristics of the

    project type () as stipulated in the guidance given in the latest additionality tool under sub-step 2b(29).

    Another survey by a securities company in Viet Nam recommends the range of 25% to 30% for cost of

    equity for power generation companies in Vietnam market20

    . Therefore, the rate of 27.46% applied as

    the cost of equity for power generation projects in Viet Nam at the date of decision making of the

    proposed project is the appropriate benchmark.

    The table below presents key assumption to calculate the benchmark - WACC according to formula (1)

    Table 7: Key assumptions to calculate the benchmark

    No Parameter Symbol Unit Value

    1 Average industry equity ratio E % 30

    21

    2 Cost of equity Re % 27.46

    3 Average industry debt ratio D % 7022

    5 Cost of debt Rd % 12.623

    6Average enterprise revenue tax during the

    lifetimeTc % 18.68

    24

    7Weighted Average Financial Discounting

    Rate of Capital (Benchmark)WACC % 15.41

    Sub-step 2c: Calculation and comparison of financial indicators

    The key assumptions used to calculate the project IRR of the proposed project are presented in Table

    below:

    Table 8: Key assumption for investment analysis

    No Parameter Unit Value Source

    20The report by Anpha Securities Company has been submitted to the DOE.21Decision No. 709/QD-NLDK issued by the Ministry of Industry provides temporary guidelines for conducting the economic,financial and investment analysis and providing the purchasing-selling price frame for power generation projects.22Calculated from Equity ratio D = 1- E23The Annual Report 2005. The Annual Report 2005 is published at the website of the State Bank annually in 200624Based on Decree No 164/2003/ND-CP issued on 22 Dec 2003 by the Government

  • 8/21/2019 Ficha Proy (Ingles)

    16/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 16

    1 Gross capacity MW 30 Technical Design Report,

    Explainable Additional Volume

    2Annual net electricity

    generationMWh 122.246

    The gross power generation subtracts

    2 % for parasitic and loss load.

    Technical Design Report,

    Explainable Additional Volume

    3 Total investment costbillion

    VND507.087

    Technical Design Report,

    Explainable Additional Volume

    4 Total annual O&M cost % 1.5Technical Design Report,

    Explainable Additional Volume

    5Preparation and

    construction periodyear 4

    Technical Design Report,

    Explainable Additional Volume

    6 Life time year 37

    Tool to determine the remaining

    lifetime of equipment/ Annex 15, EB50.

    7Depreciation period for

    constructionyear 20

    Decision No. 206/2003/QD-BTC

    issued on 12 December 2003by the

    Ministry of Finance

    8Depreciation period for

    equipmentyear 10

    Decision No. 206/2003/QD-BTC

    issued on 12 December 2003by the

    Ministry of Finance

    9 Fair value 0

    The project participants chose a

    lifetime of 37 years to assess the cash

    flows for the project IRR while a

    linear depreciation over 20 yearsperiod is chosen as regulated by the

    government. Full value of assets has

    been completely depreciated.

    No fair value remains.

    10 Electricity price. VND/kWh 608

    The estimation of tariff for the

    proposed project is based on the

    electricity price of the other

    hydropower plants which are

    accessible by the project owner at the

    time of making the investment

    decision. The project owner expected

    to negotiate with EVN to get thehighest price among the prices

    available. The applied electricity price

    is mentioned the same value in

    Explainable Additional report.

    11 Resources tax % 2

    The Circular No 05/2006/TT-BTC

    was issued by Ministry of Finance on

    19 Jan 2006 regulates that the resource

    tax will be calculated as the net

    electricity outputs supplied to the

    national electricity grid x 2% x 700

    VND.

    12 Project IRR % 9.43

  • 8/21/2019 Ficha Proy (Ingles)

    17/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 17

    This table shows that the project IRR of the project was lower than the benchmark at the time of decision

    making which is defined as the date of issuing the Decision to pursue the CDM application for the

    investment project by the Board of Director on 17 July 2006.All financial data are available to the DOE for Validation.

    Sub-step 2d: Sensitivity analysis

    A sensitivity analysis of the project activity has been conducted to test the robustness of the above

    calculations. Because the O&M cost accounted less than 20% of total investment cost, thus according to

    EB 62, Annex 05, paragraph 20:only variables, including the initial investment cost, that constitute more

    than 20% of either total project costs or total project revenue should be subjected to reasonable variation

    this parameters was ignored in the project sensitivity analysis. So the following parameters are used in the

    sensitivity analysis of the project activity:

    Annual amount of electricity exported to the national grid

    Investment costs

    Electric price set by EVN

    Table below shows the impact of variations in key factors on the project IRR considering a 10%

    variation in the parameters.

    Table 9: Sensitivity analysis

    No Parameter Variation25

    Project

    IRRLikelihoods to happen

    1Annual amount of electricity

    exported to the national grid

    10.00% 10.47% Lower than the benchmark

    63.26% 15.41%

    The probability of a 63.26%

    increase in annual export to the

    national grid is very unlikely. This

    is because the potential hydrology

    has been surveyed in long term

    basis. It is concluded that the

    hydrological condition is not

    possible to sustain a 63.24%

    annual increase compared with the

    current estimation for the entire

    crediting period. This option shallbe discarded.

    -10% 8.34% Lower than the benchmark

    2 Investment costs 10.00% 8.54% Lower than the benchmark

    25 10% is selected according to the Decision No. 709/Q NLDK issued by the Ministry of Industry, dated 13 April 2004 toprovide temporary guidelines for conducting the economic, financial and investment analysis and providing the purchasing-

    selling price frame for power generation projects. It is also common-practice for sensitivity analysis for additionalitydemonstration. Furthermore, 10% is also a common practice rate for sensitivity analysis of a CDM project

  • 8/21/2019 Ficha Proy (Ingles)

    18/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 18

    -41.06% 15.41%

    The probability of a 41.06%

    decrease in the total investment

    cost is not likely to happen becausethe inflation, average consumer

    prices 200826

    show an annual

    increase of 24% respectively.

    -10.00% 10.48% Lower than the benchmark

    3 Electric price set by EVN

    10.00% 10.50% Lower than the benchmark

    61.80% 15.41%

    The probability of a 61.80%

    increase in feed in tariff annually is

    very unlikely because the PPA

    contract will be signed with EVN

    with a fixed feed in tariff for longterm. However it should be

    comparable with the tariffs applied

    for other hydropower projects

    under fixed feed-in tariffs applied

    for long-term PPAs for other

    hydropower projects that are

    around 602 VND/kWh27

    . This

    option shall be discarded.

    -10.00% 8.32% Lower than the benchmark

    The sensitivity analysis shows that there is unlikely to be happened the case in which the variation of a

    parameter can improve the Project IRR without CDM above the benchmark.

    In conclusion, the proposed CDM project activity is unlikely to be financially attractive.

    Step 3: Barrier analysis

    Not applied.

    Step 4: Common practice analysis

    Sub-step 4a: Analyse other activities similar to the proposed project activity

    Government Decree No 45/2001/ND-CP on power generation and consumption, which was issued on 2

    August 2001 and was entered into force 15 days after the issuance date, created a legal basis to allow

    other entities to invest in and generate electricity rather than only state-owned entities as previously

    regulated. Before that time, all power plants have been invested from the state budget sources and

    operated by state owned companies. Hence, any hydropower projects that have started the construction

    activities before August 2001 are not subject to this analysis.

    26http://www.imf.org/external/pubs/ft/weo/2008/02/weodata/weoreptc.aspx?sy=1980&ey=2013&scsm=1&ssd=1&sort=country&d

    s=.&br=1&c=582&s=PCPIPCH&grp=0&a=&pr1.x=77&pr1.y=10 27The statistic data of the feed-in tariffs applied for other hydropower projects is submitted to the DOE

  • 8/21/2019 Ficha Proy (Ingles)

    19/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 19

    According to Vietnam Construction Code - TCXDVN 285:2002 "Irrigation projects - Major standards on

    designing"28

    hydropower projects are categorized as follows:

    Table 10: Groups of hydropower projects according to Vietnam Construction Code - TCXDVN285:2002

    Group Installed capacity

    I equal and larger 300 MW

    II equal and larger 50 MW but smaller 300 MW

    III smaller 50 MW but equal and larger 5MW

    IV smaller 5 MW but equal and larger 0.2MW

    V up to 0.2MW

    According to Table above, this proposed project activity falls into Group III which are similar scale and

    take place in a comparable environment to the proposed project activity.

    Table 11: Hydropower plants which belong to range (5MW to 50MW) were developed in Viet

    Nam29

    No NameCapacity

    MW

    Construction

    starting year

    Commissioning

    year

    Developed as CDM

    project

    1 Nam Mu 12 2002 2004 No

    2 Ea Krong Rou 28 2003 2007 No

    3 Suoi Sap 14.4 2004 2007 No

    4 Nam Tha 6 6.0 2006 2007 Yes

    5 Ngoi Xan 1 8.1 2006 2007 Yes

    6 Na Loi 9.3 2000 2003 No

    Because the Na Loi hydropower project started construction from 2000, it is excluded from this common

    practise analysis. It is also applied to Nam Tha 6 and Ngoi Xan 1 as they are developed as CDM projects.

    Thus, only 3 projects are relevant in this analysis.

    The comparison of the three remaining hydropower plants and the proposed project activity is presented

    in Table below.

    Table 12: Hydropower plants which belong to group III (5 < Pdm30 MW) were developed in

    Vietnam

    No Name Capacity

    MW

    Elec.

    outputs

    103MWh

    Load

    factor

    Construc-

    tion

    starting

    year

    Commi-

    ssioning

    year

    Investor during the investment

    and construction period

    0 The

    propos

    ed

    project

    30 122.7 46.69% 2006 2009 Za Hung Joint Stock Company

    (private owned company)

    28Construction Code regulates the basic technical standards that are mandatory for construction activities in Viet Nam 29

    List of powerplants supplied by Institute of Energy

  • 8/21/2019 Ficha Proy (Ingles)

    20/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 20

    A. Invested and constructed by state-owned companies or joint stock companies which are either state-

    owned or whose major shares held by the government

    1 Nam

    Mu

    12 55.7 53.0 Jan.

    2002

    2004 Song Da Construction

    Corporation - one of the largest

    state-owned construction

    corporation belongs to Ministry

    of Construction (Nam Mu

    Hydropower JSC was set up on

    29 May 2003 to take over the

    continuing construction and to

    operate the Nam Mu plant)30

    2 Ea

    Krong

    Rou

    28 110.7 45.1 Otc.

    2003

    2007 Mien Trung Power Investment

    and Development Joint Stock

    Company (Song Da

    Construction Corporation and

    Power Company No.3 hold

    85% of shares. Power Company

    No.3 belongs to EVN)31

    . In

    addition, this project has

    received ODA loan from

    India32

    B. Invested and constructed by private companies

    3 Suoi

    Sap

    14.4 65.7 52.1 Jul. 2004 2007 Truong Thanh Construction

    Company Limited

    Sub-step 4b: Discuss any similar options that are occurring

    The existence of these hydropower plants does not contradict the result of the benchmark analysis stating

    that the proposed project is financially unattractive, because of the following reasons:

    For projects from 1 - 2: As can be seen in the Table above, these projects have been invested in byeither large state-owned corporations or joint stock companies whose majority shares held by large

    state-owned corporations. These projects do not face the barriers that the proposed project faces

    because:

    1. The state-owned corporations mentioned above are among the largest state-owned power and

    construction corporations in Vietnam. They are financed by the state budget as well as theirinvestment activities. In 1990s, Song Da Construction Corporation have been assigned by

    the government to construct national hydropower plants like Hoa Binh - Song Da (1920

    MW), Yaly (720 MW), Tri An (400 MW), Ham Thuan (300 MW), Thac Ba (108 MW). ).

    And from 2000, Song Da Corporation had been studying and investing in a series of

    hydropower plants like: Ry Ninh 2, Na Loi, Can Don, Se San 3A33

    Therefore, they have

    substantial experiences in designing, investing, constructing and operating hydropower

    plants.

    2. The state-owned corporations mentioned above were established according to the PrimeMinister's Decisions No 90/TTg and 91/TTg dated on 07th March 1994. The formulation of

    30 Prospectus of Nam Mu Hydropower Joint Stock Companyhttp://images1.cafef.vn/Images/Uploaded/DuLieuDownload/Ban%20Cao%20Bach/HJS_BCB.doc

    31http://vincomsc.com.vn/vi/Pages/ReportFileDownload.aspx?id=8338 32 http://www.mientrungpid.com.vn/?page=13 33http://www.songda.com.vn/info/info.do?info=intro

  • 8/21/2019 Ficha Proy (Ingles)

    21/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 21

    these corporations is to aim at developing power and construction industries in order to meet

    national socio-economical development goals and strategies and to implement development

    tasks assigned by their ministries and/or Prime Minister in certain development periods.Therefore, the key target of these corporations is to serve as the governmental tool for

    macroeconomic interferences rather a profit making34

    .

    Project 3: The initial main objective of this project by the government was to invest in an irrigation

    project to provide water for 700 ha commercial plantation and rice fields in order to alleviate

    poverty and to develop local agriculture and rural targeted communes in Phu Yen District, Son La

    Province. Then the project owner decided to synergise this objective with the construction of a

    hydropower plant. According to the Government Decree No. 17/2001/N-CP, this project is givenpriorities to access ODA. Therefore, this project has borrowed ODA soft-loan from India at a very

    favourable interest rate35

    while the proposed project has to take loans from domestic banks without

    such a favourable condition. The circumstances of this project thus clearly show that this project

    has not been facing a similar barrier as the proposed project.

    As can be seen from the above analysis, no similar projects facing the same barriers as the proposed

    project have been developed without the aid of CDM.

    Implementation timeline of the proposed project activity

    The incentive from the CDM was seriously considered in the official letter to notify and request the

    People Committee of Quang Nam province (the highest provincial authority) and DNA Viet Nam on 30

    December 2005 by Za Hung Joint Stock Company (Project owner). Later on, the Peoples Committee

    sent an official letter to the DNA Viet Nam on 05 January 2006 for verifying and supporting CDM

    project development. Subsequently, the CDM development contract was signed between Project owner

    and Asia Carbon International B.V on 14 April 2006. The Letter of Endorsement was issued on 05 May

    2006. After that the project owner officially decided to pursue CDM implementation project on 17 July2006.

    This was prior to the starting date of the project which is defined as the date of signing the contract for

    construction tunnel on 28 December 2006.

    CDM Consideration

    CDM early consideration and the serious actions to secure the CDM status for the project are reflected in

    the key milestones in the development of the project listed below:

    Table 13: Major milestones in developing the investment project and CDM application

    NoItem

    Date NoteInvestment project

    developmentCDM project development

    1

    Approving Environment

    Protection Commitment

    report by Quang Nam

    People Committee

    18 May 2005

    2Finalizing Technical

    design report20 Dec 2005

    3Submitting a formal letter by

    the project sponsor to notify 30 Dec 2005CDM early

    consideration

    34http://vi.wikipedia.org/wiki/Tng_cng_ty_9135Source: Interview with Truong Thanh Construction Company Limited and confidential documentation provided to DOE

  • 8/21/2019 Ficha Proy (Ingles)

    22/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 22

    the CDM project activity and

    to request the People

    Committee for theirverification and support

    evidence

    4

    Submitting a formal letter by

    the project sponsor to notify

    the CDM project activity and

    to request the DNA Viet Nam

    for their verification and

    support

    30 Dec 2005

    CDM early

    consideration

    evidence

    5

    Submitting an official letter by

    Provinces People Committee

    to DNA to verify and support

    for the CDM development

    5 Jan 2006

    CDM early

    consideration

    evidence

    Signing the CDM developmentcontract with the first

    consultant

    14 Apr 2006CDM earlyconsideration

    evidence

    6Issuing the Letter of

    Endorsement5 May 2006

    CDM early

    consideration

    evidence

    7

    Finalizing the adjusted

    design project report by the

    technical consultant

    20 Jun 2006

    9 Issuing the Decision on CDM 17 Jul 2006

    Date of

    makingInvestment

    Decision

    10 Signing the credit contract 26 Jul 2006

    11

    Starting the validation

    process: uploading the PDD

    for global stakeholder

    comment

    7 Sep 2006

    13 Signing the Contract forconstruction of tunnel

    28 Dec 2006 Start date ofthe project

    activity

    14 Issuing the LoA 29 Dec 2006

    15

    Signing the Contract for

    construction of dams and

    power house

    30 Dec 2006

    16Signing the ERPA with the

    first Buyer9 Mar 2007

    17 Starting date of construction 22 Mar 2007

    18

    Signing the Contract for

    supply of technological

    equipment and technicalservices

    05 May 2007

    19Issuing Certificate of

    Investment by Provincial16 May 2007

  • 8/21/2019 Ficha Proy (Ingles)

    23/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 23

    Peoples Committee

    20

    Responding to the Draft

    Validation Report from DOEby the first CDM consultant

    09 April

    2008

    21Signing the Power Purchase

    AgreementJun 2009

    22

    Terminating the CDM

    development and registration

    contract with the first CDM

    consultant

    29 Jun 2009

    23Terminating the ERPA with

    the CDM buyer29 Jun 2009

    24

    Signing the CDM

    development and registration

    contract with the new CDMconsultant (CDM

    consultancy contract) -

    The Project Design

    Document (PDD) started to

    develop again

    02 Jul 2009

    25

    Starting the commercial

    operation of the project of

    unit 1 (commissioning)

    28 Jul 2009

    26Negotiating the ERPA with

    the second Buyer22 Dec 2009

    27 Signing the ERPA with thesecond Buyer 07 Jul 2010

    In conclusion, the proposed project is additional.

    B.6. Emission reductions:

    B.6.1. Explanation of methodological choices:

    The reduced emission is calculated in accordance with the approved consolidated baseline methodology

    Version 12.2.0 of ACM0002.

    I. Project emissions (PEy)

    According to the ACM0002 Version 12.2.0, for most renewable power generation project activities, PEy

    = 0. However, some project activities may involve project emissions that can be significant. These

    emissions shall be accounted for as project emissions shall be accounted for as project emissions by using

    the following equation:

    PEy = PEFF,y + PEGP,y + PEHP,y

    Where:

    PEy = Project emissions in year y (tCO2e/yr)

    PEFF,y = Project emissions from fossil fuel consumption in year y (tCO2/yr)

    PEGP,y = Project emissions from the operation of geothermal power plants due to the

  • 8/21/2019 Ficha Proy (Ingles)

    24/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 24

    release of non-condensable gases in year y (tCO2e/yr)

    PEHP,y = Project emissions from water reservoirs of hydro power plants in yeary (tCO2e/yr)

    Fossil Fuel Combustion (PEFF,y)

    This proposal project is hydropower project, so the project does not use fossil fuels for electricity

    generation, CO2 emissions from the combustion of fossil fuels is not relevant.

    PEFF,y= 0

    Emissions of non-condensable gases from the operation of geothermal power plants (PEGP,y)

    This emissions only apply for geothermal project activities, so this emissions (PEGP,y) is not relevant.

    Therefore, the project emissions are:

    PEy= PEHP,y

    Where:

    PEHP,y Emission from water reservoirs (tCO2/year)

    Emission from water reservoir:

    For hydropower project activity that results in new single or multiple reservoirs and/or the increase of

    single or multiple existing reservoirs, the power density (PD) of the project activity shall be calculated as

    follows:

    PJ

    PJ BL

    BL

    Cap CapPD

    A A

    =

    Where:

    PD Power density of the project activity, in W/m2.

    CapPJ Installed capacity of the hydro power plant after the implementation of the project activity (W).

    CapBL Installed capacity of the hydro power plant before the implementation of the project activity (W).

    For new hydro power plants, this value is zero.

    APJ Area of the single or multiple reservoirs measured in the surface of the water, after the

    implementation of the project activity, when the reservoir is full (m2).

    ABL Area of the single or multiple reservoirs measured in the surface of the water, before the

    implementation of the project activity, when the reservoir is full (m2). For new reservoirs, this value

    is zero.

    If thePDis greater than 4 W/m2and less than or equal to 10 W/m

    2:

    Re,

    1000

    s YHP y

    EF TEGPE

    =

    Where:

    PEy Project emissions from water reservoirs expressed as tCO2e/year

    EFRes Default emission factor for emissions from reservoirs of hydropower plants in year y, and

  • 8/21/2019 Ficha Proy (Ingles)

    25/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 25

    the default value as per EB23 is 90 Kg CO2e /MWh.

    TEGy Total electricity produced by the project activity, including the electricity supplied to the

    grid and the electricity supplied to internal loads, in yeary (MWh).

    IfPDis greater than 10 W/m2, then:

    PEHP,y = 0

    II. Baseline emissions (BEy)

    The project activity is the installation of a new baseline emissions include only CO2 emissions from

    electricity generation from fossil fuel fired power plants that are displaced due to the project activity,

    calculated as follows:

    BEy= EGPJ,y. EFgrid,CM,y

    Where:

    BEy Baseline emissions in yeary (tCO2/yr).

    EGPJ,y Quantity of net electricity generation that is produced and fed into the grid as a result

    of the implementation of the CDM project activity in yeary (MWh/yr)

    EFgrid,CM,y The combined margin CO2emission factor for grid connected power generation in

    year y and the applied value36

    Calculation of EGPJ,y

    Because the project activity is the installation of a new grid-connected renewable power plant/unit at a

    site where no renewable power plant was operated prior to the implementation of the project activity,

    then:

    EGPJ,y= EGfacility,y

    Where:

    EGPJ,y = Quantity of net electricity generation that is produced and fed into the grid as a result of

    the implementation of the CDM project activity in year y (MWh/yr)

    EGfacility,y = Quantity of net electricity generation supplied by the project plant/unit to the grid in year y

    (MWh/yr)

    Therefore, the baseline emissions are calculated as follows:

    BEy= EGfacility,y .EFgrid,CM,y

    Calculation of the emission factor (EF) of the national electricity grid

    The Version 02.2.1 of Tool to calculate the emission factor for an electricity system determines the CO 2

    emission factor for the displacement of electricity generated by power plants in an electricity system, by

    calculating the operating margin and build margin as well as the combined margin, including 6

    steps as follows:

    STEP 1. Identify the relevant electric power system.

    STEP 2. Choose whether to include off-grid power plants in the project electricity system (optional).

    STEP 3. Select a method to determine the operating margin (OM)

    36EFCM has been published by DNA Viet Nam according to the link:http://www.noccop.org.vn/Data/vbpq/Airvariable_ldoc_vnHe%20so%20phat%20thai.pdf

  • 8/21/2019 Ficha Proy (Ingles)

    26/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 26

    STEP 4. Calculate the operating margin emission factor according to the selected method.

    STEP 5. Calculate the build margin (BM) emission factor.

    STEP 6. Calculate the combined margin (CM) emission factor.

    Step 1. Identify the relevant electricity systems

    This hydropower project will be connected to the national electricity grid of Viet Nam, which is operated

    and monopolized by the EVN. This national electricity grid is the unique transmission and distribution

    line, to which all power plants in Viet Nam are physically connected. Hence the national electricity grid is

    the project electricity system.

    There are electricity imports to the national electricity grid from China - another host country, thus the

    China Power Grid is the connected electricity system and the emission factor for the imported electricity

    is zero tons CO2per MWh by default.

    Step 2: Choose whether to include off-grid power plants in the project electricity system (optional)

    There are 2 options in the tools to choose, including:

    Option I: Only grid power plants are included in the calculation.

    Option II: Both grid power plants and off-grid power plants are included in the calculation.

    Because only the data of grid connected power plants is available, so Option I will be chosen for

    calculating the grid emission factor.

    Step 3. Select a method to determine the operating margin (OM)

    The calculation of the operating margin emission factor (EFgrid,OM,y) is based on one of the following

    methods:a) Simple OM; or

    b) Simple adjusted OM; or

    c) Dispatch data analysis OM; or

    d) Average OM.

    The method (a) can be used in the project because low-cost/must-run resources in Viet Nam is 34.77 %

    that constitute less than 50% of total grid generation in average of the five most recent years (details see

    the table below).

    Table 14: Rate of low cost/must-run sources based on generation37

    Year 2004 2005 2006 2007 2008

    Total

    Value for

    2004-2008

    Hydro Power

    (MWh) 17,858,651 16,365,438 19,508,244 22,385,232 25,933,762

    102,051,32

    7

    Total Power

    (MWh) 44,974,169 50,330,468 57,160,493 66,348,589 74,689,636

    293,503,35

    5

    Low-

    cost/Must-run

    Ratio 39.71% 32.52% 34.13% 33.74% 34.72% 34.77%

    37Data source from DNA Viet Nam

  • 8/21/2019 Ficha Proy (Ingles)

    27/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 27

    The data vintage which is used to calculation the Simple OM emission factor is the Ex-ante option of a 3-

    year generation-weighted average (2006, 2007 and 2008) that is the most recent data available at the time

    of submission of the CDM-PDD to the DOE for validation, without requirement to monitor andrecalculate the emissions factor during the crediting period.

    Step 4. Calculate the OM emission factor according to the selected method

    The simple OM emission factor is calculated as the generation-weighted average CO2emissions per unit

    net electricity generation (tCO2/MWh) of all generating power plants serving the system, not including

    low-cost/must-run power plants units.

    There are two Options proposed, including:

    Option A: Based on data on the net electricity generation and a CO2 emission factor of each power unit,

    or

    Option B: Based on the total net electricity generation of all power plants serving the system and the fueltypes and total fuel consumption of the project electricity system.

    Because the data for Option A is available, Option A Calculation based on average efficiency and

    electricity generation of each plant is used and then the simple OM emission factor is calculated as

    follows:

    , ,

    , , ,

    ,

    grid OMsimple y

    m y EL m ym

    m ym

    EG EFEF

    EG

    =

    Where:

    EFgrid,OM,y

    = Simple operating margin CO2emission factor in yeary(tCO

    2/MWh)

    EGm,y

    = Net quantity of electricity generated and delivered to the grid by power unit

    min yeary(MWh)

    EFEL,m,y

    = CO2emission factor of power unit min yeary(tCO

    2/MWh)

    m = All power plants/units serving the grid in yearyexcept low-cost/must-run

    power plants/units

    y Either the three most recent years for which data is available at the time of

    submission of the CDM-PDD to the DOE for validation (ex ante option)

    Because the data on fuel consumption and electricity generation of power unit m is available, so the

    emission factor (EFEL,m,y) should be determined as Option A1:

    , ,

    , , , 2, ,

    ,

    EL m y

    i m y i y CO i yi

    m y

    FC NCV EFEF

    EG

    =

    Where:

    EFEL,m,y

    = CO2emission factor of power unit min yeary(tCO

    2/MWh)

    FCi,m,y

    = Amount of fossil fuel type i consumed by power plant/unit m in year y (mass or

    volume unit)

    NCVi,y

    = Net calorific value (energy content) of fossil fuel type iin yeary (GJ/mass or volume

    unit)

    EFCO2,i,y

    = CO2emission factor of fossil fuel typeiin yeary(tCO

    2/GJ)

  • 8/21/2019 Ficha Proy (Ingles)

    28/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 28

    EGm,y

    = Net electricity generated and delivered to the grid by all power sources serving the

    system, not including low-cost/must-run power plants/units,in yeary (MWh)

    i = All fossil fuel types combusted in power unit m in yeary

    y = The relevant year as per the data vintage chosen in Step 3

    Table 15: OM emission factor in 2008

    Year Total output (MWh) Total emission (tCO2e) OM 2008 (tCO2e/MWh)

    A B (B/A)

    2006 37,618,199.00 25,702,918.00

    2007 43,921,501.00 28,544,173.00

    2008 48,719,874.00 29,963,699.00

    Total 130,259,574.00 84,210,790.00 0.6465

    SoEFgrid,OMsimple,y

    is derived as follows:

    EFgrid,OMsimple,y

    = 0.6465 tCO2/MWh

    Step 5. Calculate the BM emission factor

    In terms of vintage of data, one of the following two options can be chosen:

    Option 1:For the first crediting period, calculate the build margin emission factor ex antebased on themost recent information available on units already built for sample group m at the time of CDM-PDD

    submission to the DOE for validation. For the second crediting period, the build margin emission factor

    should be updated based on the most recent information available on units already built at the time of

    submission of the request for renewal of the crediting period to the DOE. For the third crediting period,

    the build margin emission factor calculated for the second crediting period should be used. This option

    does not require monitoring the emission factor during the crediting period, or

    Option 2:For the first crediting period, the build margin emission factor shall be updated annually, ex

    post, including those units built up to the year of registration of the project activity or, if information up to

    the year of registration is not yet available, including those units built up to the latest year for which

    information is available. For the second crediting period, the build margin emissions factor shall be

    calculated ex ante, as described in Option 1 above. For the third crediting period, the build marginemission factor calculated for the second crediting period should be used..

    The most recent information on units already built for sample group mis available, so Option 1 shall be

    chosen for the proposed project.

    The sample group of power units mused to determine as per the following procedure, consistent with the

    data vintage selected above:

    (a) Identify the set of five power units, excluding power units registered as CDM project activities,that started to supply electricity to the grid most recently (SET5-units) and determine their annual

    electricity generation (AEGSET-5-units, in MWh);

    In 2008, the set of five power units that have been built most recently (SET5-units) is indicated in

    Annex 3 has annual generation (AEGSET-5-units) of 7,829,812.02 MWh.

    (b) Determine the annual electricity generation of the project electricity system, excluding powerunits registered as CDM project activities (AEGtotal, in MWh). Identify the set of power units,

  • 8/21/2019 Ficha Proy (Ingles)

    29/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 29

    excluding power units registered as CDM project activities, that started to supply electricity to the

    grid most recently and that comprise 20% of AEG total(if 20% falls on part of the generation of a

    unit, the generation of that unit is fully included in the calculation) (SET 20%) and determine theirannual electricity generation (AEGSET-20%, in MWh);

    The total output of Viet Nam electricity grid (AEGtotal) in 2008 is 74,689,635.97 MWh then 20%

    of the total output of Viet Nam electricity grid in 2008 is 14,937,927.19 MWh.

    Most recent-built power plants (SET20%) addition in the electricity system that comprise 20% of

    the system generation in 2008 is shown in the annex 3 have annual electricity generation

    (AEGSET-20%) of 16,514,761.12 MWh.

    (c) From SET5-units and SET20% select the set of power units that comprises the larger annualelectricity generation (SETsample).

    The comparison carried out by the project participants shows that the set of power capacity

    additions in the electricity system that comprise 20% of the system generation (in MWh) that havebeen built most recently has the larger annual generation (14,937,927.19 MWh) than the set of

    five power units that have been built most recently in 2008 does (7,829,812.02 MWh), and hence

    it is employed and SETsample.

    There is no plant in SETsampleis started to supply electricity to the grid more than 10 years ago, then use

    SETsample to calculate the build margin.

    The BM emissions factor is the generation-weighted average emission factor (tCO2/MWh) of all power

    units m during the most recent year y for which power generation data is available. It is calculated as

    follows:

    , , ,

    , ,

    ,

    m y EL m y

    m

    grid BM y

    m y

    m

    EG EF

    EF EG

    =

    Where:

    EFgrid,BM,y

    = Build margin CO2emission factor in yeary(tCO

    2/MWh)

    EGm,y

    = Net quantity of electricity generated and delivered to the grid by power unit min yeary

    (MWh)

    EFEL,m,y

    = CO2emission factor of power unit min yeary(tCO

    2/MWh)

    m = Power units included in the build margin

    y = Most recent historical year for which electricity generation data is available

    ThenEFgrid,BM,y

    is derived as follows:

    EFgrid,BM,y

    = 0.5064 tCO2/MWh

    Step 6. Calculate the combined margin emissions factor

    According to the tool, the calculation of the combined margin (CM) emission factor (EFgrid, CM,y) is based

    on one of the following methods:

    (a) Weighted average CM; or

    (b) Simplified CM

    As the project is located in Viet Nam a developing country and having more than 10 registered projects at

    starting date of validation, the PP chooses the weighted average CM method to calculate CM emissionfactor for the proposed project.

    The CM emissions factor is calculated as follows:

  • 8/21/2019 Ficha Proy (Ingles)

    30/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 30

    grid,CM,y grid,OM,y OM grid,BM,y BMEF = EF w + EF w

    Where:

    EFgrid,BM,y = Build margin CO2emission factor in yeary (tCO2/MWh)

    EFgrid,OM,y = Operating margin CO2emission factor in yeary (tCO2/MWh)

    wOM

    = Weighting of OM emissions factor (%)

    wBM

    = Weighting of BM emissions factor (%)

    For the proposed project, the following default values are used: wOM

    = 0.5 and wBM

    = 0.5 in the first

    crediting period, and wOM

    = 0.25 and wBM

    = 0.75 in the second and third crediting period.

    So in the first crediting period, the CM emission factor is derived as follows:

    EFgrid,CM,y= 0.5 0.6465 + 0.5 0.5064 = 0.5764 tCO2/MWh

    The baseline emission factor EF shall be fixed for the crediting period.

    III. Leakage (LEy)

    According to ACM0002, version 12.2.0, no leakage emissions are considered. These emission sources are

    neglected orLEy = 0.

    IV. Emission reductions (ERy)

    Emission reductions are calculated as follows:

    ERy = BEy - PEy- LEy

    Where:

    ERy Emission reductions in yeary (tCO2e/yr).

    BEy Baseline emissions in yeary (tCO2e/yr)

    PEy

    LEy

    Project emissions in yeary (tCO2/yr).

    Leakage emissions in yeary (tCO2/yr).

    B.6.2. Data and parameters that are available at validation:

    Data / Parameter: CapBL

    Data unit: MW

    Description: Installed capacity of hydropower plant before the implementation of the project

    activity.

    Source of data used: This is a green-field project. This value does not exist prior to the

    implementation of the project activity

    Value applied: 0

    Justification of the

    choice of data or

    description of

    measurement methods

    and procedures actuallyapplied :

    The project activity constructs a new hydropower plant, so CapBLis considered

    by zero according to Version 12.2.0 of ACM0002.

    Any comment: Use for calculating the power density (PD)

  • 8/21/2019 Ficha Proy (Ingles)

    31/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 31

    Data / Parameter: ABL

    Data unit: m2

    Description: Area of the single or multiple reservoirs measured in the surface of the water,before the implementation of the project activity, when the reservoir is full. For

    new reservoirs, this value is zero.

    Source of data used: This is a green-field project. This value does not exist prior to the

    implementation of the project activity.

    Value applied: 0

    Justification of the

    choice of data or

    description of

    measurement methods

    and procedures actually

    applied :

    The project activity builds a new reservoir, so ABL is considered by zero

    according to Version 12.2.0 of ACM0002.

    Any comment: Use for calculating the power density

    Data / Parameter: EFgrid,OM,y

    Data unit: tCO2/MWh

    Description: Operating margin CO2emission factor for grid connected power generation

    in year y calculated using the Tool to calculate the emission factor for an

    electricity system

    Source of data used: Data published by DNA Viet Nam

    Value applied: 0.6465

    Justification of the

    choice of data or

    description of

    measurement methods

    and procedures actually

    applied:

    As per the Tool to calculate the emission factor for an electricity system

    Any comment: For calculation ofEFgrid,CM,y

    Data / Parameter: EFgrid,BM,y

    Data unit: tCO2/MWh

    Description: Build margin CO2 emission factor for grid connected power generation in

    year y calculated using the Tool to calculate the emission factor for an

    electricity system

    Source of data used: Data published by DNA Viet Nam

    Value applied: 0.5064

    Justification of the

    choice of data or

    description of

    measurement methods

    and procedures actually

    applied:

    As per the Tool to calculate the emission factor for an electricity system

    Any comment: For calculation ofEFgrid,CM,y

  • 8/21/2019 Ficha Proy (Ingles)

    32/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 32

    Data / Parameter: EFgrid,CM,y

    Data unit: tCO2/MWh

    Description: Combined margin CO2emission factor for grid connected power generation

    in year y calculated using the Tool to calculate the emission factor for an

    electricity system

    Source of data used: Data published by DNA Viet Nam

    Value applied: 0.5764

    Justification of the

    choice of data or

    description of

    measurement methods

    and procedures actually

    applied:

    As per the Tool to calculate the emission factor for an electricity system

    Any comment: Fixed for crediting period.

    B.6.3. Ex-ante calculation of emission reductions:

    Project emissions (PEy)

    Emission from reservoir:

    The proposed project activity involves the construction of a new hydropower plant with capacity (CapPJ)

    of 30 MW and two new reservoirs with total surface (APJ) of 22.99 ha, thusABL= 0 andCapBL= 0.

    The power density of the project activity is derived as follows:

    2

    4

    6

    /5.13001099.22

    01030mW

    AA

    CapCapPD

    BLPJ

    BLPJ =

    =

    =

    As power density of two reservoirs is greater than 10 W/m2, thus the project emission is zero:PEHP,y= 0

    Baseline emissions (BEy)

    Baseline emissions are calculated as follows:

    ,y facility y grid,CM,y

    BE = EG EF

    Where: EGfacility,y= 120,246 MWh;

    EFgrid,CM,y= 0.5764 tCO2/MWh

    Therefore:

    BEy= 69,309 tCO2e

    Leakage (LEy)

    According to ACM0002, version 12.2.0, no leakage emissions are considered. These emission sources are

    neglected orLEy = 0.

    Reduction emissions (ERy)

    Emission reductions are calculated as follows:

  • 8/21/2019 Ficha Proy (Ingles)

    33/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 33

    ERy= BEy- PEy= 69,309 tCO2e/year

    B.6.4. Summary of the ex-ante estimation of emission reductions:

    The estimated emission reduction of the project activity is provided in Table below.

    Table 16: Emission reduction of the project activity

    Year Estimation of

    project activity

    emissions

    (tonnes of CO2 e)

    Estimation of

    baseline

    emissions

    (tonnes of CO2e)

    Estimation of

    leakage

    (tonnes of CO2e)

    Estimation of

    overall emission

    reductions

    (tonnes of CO2e)

    2012 0 69,309 0 69,309

    2013 0 69,309 0 69,3092014 0 69,309 0 69,309

    2015 0 69,309 0 69,309

    2016 0 69,309 0 69,309

    2017 0 69,309 0 69,309

    2018 0 69,309 0 69,309

    Total

    (tonnes of CO2e)0 485,163 0 485,163

    B.7. Application of the monitoring methodology and description of the monitoring plan:

    B.7.1 Data and parameters monitored:

    The power densities of the proposed project are larger than 10 W/m2so it is no need to monitor the TEGy

    of this proposed project.

    Data / Parameter: EGy,export

    Data unit: MWh/yrDescription: Electricity supplied by the proposed hydropower plant to the national grid

    Source of data to be

    used:

    Direct measurement at the project connection point

    Value of data appliedfor the purpose of

    calculating expected

    emission reductions in

    section B.6.3.

    120,246

    Description of

    measurement methods

    and procedures to be

    applied:

    Two-way power meters will be installed at the grid-connected point to measure

    the amount of electricity supplied by the proposed hydropower plant to the grid

    in the positive direction. The electricity will be continuously measured by the

    power meters and monthly recorded. Double checking by the invoice issued by

    project owner to ensure the consistency. Electronic data will be archived within

    the crediting period and 2 years after the end of the crediting period.

    Monitoring frequency Continuous measurement and at least monthly recording

    QA/QC procedures tobe applied:

    The uncertainty level of this data is low. The measurement/ monitoringequipment should adopt the colligated automation system complying with

    national standard and technology. These equipment and systems should be

    calibrated and checked every 2 year.

  • 8/21/2019 Ficha Proy (Ingles)

    34/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 34

    Any comment: Use for calculatingEG acility,y, = EGy, export- EGy, import

    Data / Parameter: EGy, importData unit: MWh/yrDescription: Electricity imported from the grid to the proposed hydropower plant

    Source of data to be

    used:Direct measurement at the project site

    Value of data applied

    for the purpose of

    calculating expected

    emission reductions in

    section B.6.3.

    0

    Description of

    measurement methods

    and procedures to be

    applied:

    The power meters will be installed at the grid-connected point to measure the

    amount of electricity supplied by the 110 kV grid to the proposed hydropower

    plant. The readings of electricity meter will be monthly recorded. Double

    checking by the invoice issued by EVN to ensure the consistency. Hardcopy of

    invoice from EVN will be archived within the crediting period and 2 years after

    the end of the crediting period.

    Monitoring frequency Continuous measurement and at least monthly recording

    QA/QC procedures to

    be applied:

    The uncertainty level of this data is low. The measurement/ monitoring

    equipment should adopt the colligated automation system complying with

    national standard and technology. These equipment and systems should be

    calibrated and checked every 2 year.

    Any comment: Use for calculatingEGfacility,y, = EGy, export- EGy, import

    Data / Parameter: APJData unit: m

    2

    Description: Area of the single or multiple reservoirs measured in the surface of the water,

    after the implementation of the project activity, when the reservoir is full.

    Source of data to be

    used:

    Project site.

    Value of data applied

    for the purpose of

    calculating expected

    emission reductions in

    section B.6.3.

    Reservoir area: 229,900

    Description of

    measurement methodsand procedures to be

    applied:

    Measured by the observation equipment

    Monitoring frequency Yearly

    QA/QC procedures to

    be applied:

    The uncertainty level of this data is low.

    Any comment: Use for calculating the power density

    Data / Parameter: CapPJ

    Data unit: W

    Description: Installed capacity of the hydro power plant after the implementation of theproject activity.

    Source of data to be

    used:

    Project site

  • 8/21/2019 Ficha Proy (Ingles)

    35/52

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD) - Version 03

    CDM Executive Board page: 35

    Value of data applied

    for the purpose of

    calculating expectedemission reductions in

    section B.6.3.

    30,000,000

    Description of

    measurement methods

    and procedures to be

    applied:

    Manufactures nameplate

    Monitoring frequency Yearly

    QA/QC procedures to

    be applied:

    Any comment: Use for calculating the power density

    Data / Parameter: EGfacility,y

    Data unit: MWh/yrDescription: Net electricity supplied by the proposed hydropower plant in year y

    Source of data to be

    used:Calculating from EGy, importand EGy, export

    Value of data applied

    for the purpose of

    calculating expected

    emission reductions in

    section B.6

    120,246

    Description of

    measurement methodsand procedures to be

    applied:

    Calculating by subtracting EGy, importfrom EGy,export. Double checking by the joint

    balance sheet issued by EVN and project owner to ensure the consistency. Datawill be archived within the crediting period and 2 years after the end of the

    crediting period.

    Monitoring frequency Continuous measurement and at least monthly recording

    QA/QC procedures to

    be applied:

    The data will be crosschecked with records for sold electricity.These equipment

    and systems should be calibrated and checked every 2 year.

    Any comment: For CERs calculation

    B.7.2. Description of the monitoring plan:

    According to Version 12.2.0 of ACM0002, there is no need to monitor project emissions and leakage

    under this project activity.

    The baseline emission factor of Vietnam National Grid (EFgrid,CM,y) is fixed ex-ante (detail in Section B.6),

    the main data to be monitored isEGfacility,y. EGfacility,ywill be calculated according to this formula below:

    EGfacility,y


Recommended