Mata Kuliah: Penjadwalan Produksi
Teknik Industri – Universitas Brawijaya
Flow Shop Scheduling
2
Definitions
• Contains m different machines.
• Each job consists m operators in different machine.
• The flow of work is unidirectional.
• Machines in a flow shop = 1,2,…….,m
• The operations of job i , (i,1) (i,2) (i ,3)…..(i, m)
• Not processed by machine k , P( i , k) = 0
3
Flow Shop Scheduling Baker p.136
The processing sequence on each machine are all the same.
1
2 . . . . . M
2 3 1 5 4
2 3 1 5 4
Flow shop
Job shop
n! - flow shop permutation schedule
n!.n! …….n! - Job shop
m)!n(k
)!n( m
k : constraint
(∵ routing problem)
1 3 2 4 5
or
4
Workflow in a flow shop
Machine
1
Machine
2
Machine
3
Machine
M-1
Machine
M
….
Input
output
Machine
1
Machine
2
Machine
3
Machine
M-1
Machine
M
….
Input
output output output output output
Input Input Input Input
Type 1.
Type 2.
Baker p.137
21/04/2014
2
5
Johnson’s Rule
Note:
Johnson’s rule can find an optimum with two machines
Flow shop problem for makespan problem.
Baker p.142
.filledaresequenceinpositions
alluntil1steptoreturnandionconsideratfromjobassignedtheRemove:3Step
.3steptogo.sequencein
positionavailablefirsttheinjobtheplace,2machinerequiresmintheIf:2Step
.3steptogo.sequencein
positionavailablefirsttheinjobtheplace,1machinerequiresmintheIf:2Step
Find:1Step
tb
ta
}t,{tmin i2i1i
6
Ex.
Stage U Min tjk Assignment Partial Schedule
1 1,2,3,4,5 t31 3=[1] 3 x x x x
2 1,2,4,5 t22 2=[5] 3 x x x 2
3 1,4,5 t11 1=[2] 3 1 x x 2
4 4,5 t52 5=[4] 3 1 x 5 2
5 4 t11 4=[3] 3 1 4 5 2
7
Ex.
Job
tj1
tj2
Job1 Job2 Job3 Job4 Job5
3 5 1 6 7
6 2 2 6 5
Job3 Job1 Job4 Job5 Job2
3
1 4 5 2
2 5 4 1 3
24
M=24
8
The B&B for Makespan Problem
The Ignall-Schrage Algorithm (Baker p.149)
- A lower bound on the makespan associated with any completion of the corresponding partial sequence σ is obtained by considering the work remaining on each machine. To illustrate the procedure for m=3.
For a given partial sequence σ, let
q1= the latest completion time on machine 1 among jobs in σ.
q2= the latest completion time on machine 2 among jobs in σ.
q3= the latest completion time on machine 3 among jobs in σ.
The amount of processing yet required of machine 1 is
'j
1jt
21/04/2014
3
9
The Ignall-Schrage Algorithm
In the most favorable situation, the last job
1) Encounters no delay between the completion of one operation and the start of its direct successor, and
2) Has the minimal sum (tj2+tj3) among jobs j belongs to σ’
Hence one lower bound on the makespan is
A second lower bound on machine 2 is
A lower bound on machine 3 is
The lower bound proposed by Ignall and Schrage is
}tt{mintqb 3j2j'j'j
1j11
}t{mintqb 3j'j'j
2j22
'j
3j33 tqb
}b,b,bmax{B 321
10
The Ignall-Schrage Algorithm
M1
M2
M3
tk1
tk2
tk3
……..
……..
……..
q1
q2
q3 b1
M2
M3
tk2
tk3
……..
……..
q2
q3 b2
Job in σ’
11
Ex. B&B
j 1 2 3 4
tj1 3 11 7 10
tj2 4 1 9 12
tj3 10 5 13 2
m=3 For the first node: σ =1
37)37,31,37max(B
372017b
312227b
376283b
boundlowerThe
17tttq
7ttq
3tq
3
2
1
1312113
12112
111
212
139
51
min6
12
Ex. Partial Sequence ( q1 , q2 , q3 ) (b1,b2,b3) B
1xxx ( 3 , 7 , 17 ) ( 37 , 31 , 37 ) 37
2xxx ( 11 , 12 , 17 ) ( 45 , 39 , 42 ) 45
3xxx ( 7 , 16 , 29 ) ( 37 , 35 , 46 ) 46
4xxx ( 10 , 22 , 24 ) ( 37 , 41 , 52 ) 52
12xx ( 14 , 15 , 22 ) ( 45 , 38 , 37 ) 45
13xx ( 10 , 19 , 32 ) ( 37 , 34 , 39 ) 39
14xx ( 13 , 25 , 27 ) ( 37 , 40 , 45 ) 45
132x ( 21 , 22 , 37 ) ( 45 , 36 , 39 ) 45
134x ( 20 , 32 , 34 ) ( 37 , 38 , 39 ) 39
1 2
1 2
1 2
0 3 14
7 15
17 22 45
212
139min)107(14
}tt{mintqb 3j2j'j'j
1j11
21/04/2014
4
13
Ex. B&B
P0
1xxx 2xxx 3xxx 4xxx
B=37 B=45 B=46 B=52
12xx 13xx 14xx
B=45 B=45 B=39
132x 134x
B=45 B=39
14
Hw.
a. Find the min makespan using the basic Ignall-Schrage algorithm. Count the nodes generated by the branching process.
b. Find the min makespan using the modified algorithm.
j 1 2 3 4
tj1 13 7 26 2
tj2 3 12 9 6
tj3 12 16 7 1
Consider the following four-job three-machine problem
15
Heuristic Approaches
Traditional B&B:
• The computational requirements will be severe for large problems
• Even for relatively small problems, there is no guarantee that the solution can be obtained quickly,
Heuristic Approaches
• can obtain solutions to large problems with limited computational effort.
• Computational requirements are predictable for problem of a given size.
16
CDS (Campbel, Dudek and Smith)
Its strength lies in two properties:
1.It use Johnson’s rule in a heuristic fashion
2.It generally creates several schedules from which a “best” schedule can be chosen.
The CDS algorithm corresponds to a multistage use if Johnson’s rule applied to a new problem, derived from the original, with processing times and . At stage 1, 1j't 2j't
jm2j1j1j t'tandt't
21/04/2014
5
17
CDS
In other words, Johnson’s rule is applied to the first and mth operations and intermediate operations are ignored. At stage 2,
1m,jjm2j2j1j1j tt'tandtt't
That is, Johnson’s rule is applied to the sums of the first two and last two operation processing times. In general at stage i,
i
1k1km,j2j
i
1kjk1j t'tandt't
18
Step 1. Set K=1. Hitung (m=jumlah mesin):
dan
Step 2. Gunakan Algoritma Johnson untuk penentuan urutan pekerjaan dengan menyatakan
dan
Step 3. Hitung makespan untuk urutan tersebut. Catat jadwal dan makespan yang dihasilkan
Step 4. Jika K=m-1 maka pilih jadwal dengan makespan terpendek sebagai jadwal yang digunakan, lalu stop. Jika K<m-1 maka K=K+1 dan kembali ke Step 1.
K
k
kii tt1
,
*
1,
K
k
kmii tt1
1,
*
2,
*
1,1, ii tt *
2,2, ii tt
CDS
19
Job i
Mesin 1 Mesin 3 Mesin 1 Mesin 2
1 4 5 7 8
2 3 4 6 7
3 2 6 3 7
4 5 2 8 5
5 6 7 10 11
6 1 3 9 11
K=1 K=2Job i Mesin 1 Mesin 2 Mesin 3
1 4 3 5
2 3 3 4
3 2 1 6
4 5 3 2
5 6 4 7
6 1 8 3
Set K=1
41,1
1
1
,1
*
1,1
tttk
k
53,1
1
1
13,1
*
2,1
tttk
k
Set K=2
7342,11,1
2
1
,1
*
1,1
ttttk
k
835
2,13,1
2
1
13,1
*
2,1
ttttk
k
CDS CDS
20
21/04/2014
6
CDS
21 22
Palmer
Palmer proposed the calculation of a slope index, sj, for each job.
1,j2,j2m,j1m,jm,jj t)1m(t)3m(t)5m(t)3m(t)1m(s
Then a permutation schedule is constructed using the job ordering
]n[]2[]1[ sss
23
Gupta
Gupta thought a transitive job ordering in the form of follows that would produce good schedules. Where
}tt,ttmin{
es
3j2j2j1j
j
j
Where
3j1j
3j1j
j ttif1
ttif1e
24
Gupta
Generalizing from this structure, Gupta proposed that for m>3, the job index to be calculated is
}tt{min
es
1k,jjk1mk1
j
j
Where
jm1j
jm1j
j ttif1
ttif1e
21/04/2014
7
25
Ex.
Palmer:
j 1 2 3 4 5
tj1 6 4 3 9 5
tj2 8 1 9 5 6
tj3 2 1 5 8 6
3712453
22468
2211
54321
1313
M
sssss
tttmtms jjjjj
Gupta:
36M2143511
1s
13
1s
12
1s
2
1s
10
1s 54321
CDS: 3-5-4-1-2 M=35
26
HW.
Let
1. Use Ignall-Schrage & McMahon-Burton to solve
2. Use Palmer, Gupta, CDS to solve this problem.
j 1 2 3 4 5
tj1 8 11 7 6 9
tj2 3 2 5 7 11
tj3 6 5 7 13 10 }3,1{
2 2
1 2 3 4 5 13 31, , , , ,xxx xxxb b b b b of P P
Referensi
• Introduction to Sequencing and Scheduling. Kenneth R. Baker. Duke University. John Wiley & Sons. 1974.
• Production Scheduling. PPT: Course Material. P.C. Chang. IEM. YZU.