GEOTHERMAL REGULATION AND POLICY IN INDONESIA Presented at: Workshop on Geothermal Bussiness Opportunity in Indonesia Bandung, February 19 th , 2013 DIRECTORATE GENERAL OF NEW RENEWABLE ENERGY AND ENERGY CONSERVATION MINISTRY OF ENERGY AND MINERAL RESOURCES by: Directorate of Geothermal
Transcript
Page 1: GEOTHERMAL REGULATION AND POLICY IN INDONESIA · GEOTHERMAL REGULATION AND POLICY IN INDONESIA Presented at: Workshop on Geothermal Bussiness Opportunity in Indonesia Bandung, February

GEOTHERMAL REGULATION AND POLICY IN INDONESIA

Presented at:

Workshop on Geothermal Bussiness Opportunity in Indonesia

Bandung, February 19th, 2013

DIRECTORATE GENERAL OF NEW RENEWABLE ENERGY AND ENERGY CONSERVATION

MINISTRY OF ENERGY AND MINERAL RESOURCES

by:

Directorate of Geothermal

Page 2: GEOTHERMAL REGULATION AND POLICY IN INDONESIA · GEOTHERMAL REGULATION AND POLICY IN INDONESIA Presented at: Workshop on Geothermal Bussiness Opportunity in Indonesia Bandung, February

©2012

Ministry of Energy and Mineral Resources

Directorate General of New Renewable Energy and Energy Conservation

Sustainable, Green, Clean and Environmental Friendly

Page 3: GEOTHERMAL REGULATION AND POLICY IN INDONESIA · GEOTHERMAL REGULATION AND POLICY IN INDONESIA Presented at: Workshop on Geothermal Bussiness Opportunity in Indonesia Bandung, February

Direktorat Jenderal

EBTKEMinistry of Energy and Mineral Resources

Directorate General of New Renewable Energy and Energy Conservation

I. Background

II. Geothermal Policy

III. Geothermal Development

IV. Feed in Tariff Mechanism

OUTLINE

Page 4: GEOTHERMAL REGULATION AND POLICY IN INDONESIA · GEOTHERMAL REGULATION AND POLICY IN INDONESIA Presented at: Workshop on Geothermal Bussiness Opportunity in Indonesia Bandung, February

Direktorat Jenderal

EBTKEMinistry of Energy and Mineral Resources

Directorate General of New Renewable Energy and Energy Conservation

I. BACKGROUND

Page 5: GEOTHERMAL REGULATION AND POLICY IN INDONESIA · GEOTHERMAL REGULATION AND POLICY IN INDONESIA Presented at: Workshop on Geothermal Bussiness Opportunity in Indonesia Bandung, February

Direktorat Jenderal

EBTKEMinistry of Energy and Mineral Resources

Directorate General of New Renewable Energy and Energy Conservation

• Driven by concerns about the sustainability of environment and the security of energy supply, interest in renewable energy is growing all over the world. Indonesia as a country that is highly dependent on fossil fuels to meet its energy needs, has forced to seek for other energy resources to maintain national security of energy supply.

• Geothermal has became a priority energy to ensure national energy security, reducing Indonesia's dependence on fossil fuel and also provide added value in energy diversification.

• Based on latest survey, Indonesia has 28.8 GWe geothermal potential which distributed in 299 locations along the country, yet its utilization has not been optimized. Up to now total installed capacity of geothermal power plant is only reached 1,341 MW.

• The Government of Indonesia (GoI) is concerned in energy development based on green energy, mainly geothermal. Presidential Decree No. 5 / 2006 on National Energy Policy (KEN) has targeted in 2025 electricity from geothermal energy will reach 9500 MW or contribute 5% of national energy consumption

Background

Page 6: GEOTHERMAL REGULATION AND POLICY IN INDONESIA · GEOTHERMAL REGULATION AND POLICY IN INDONESIA Presented at: Workshop on Geothermal Bussiness Opportunity in Indonesia Bandung, February

©2012

Ministry of Energy and Mineral Resources

Directorate General of New Renewable Energy and Energy Conservation

INDONESIA’S GEOTHERMAL POTENTIAL

Source : Geological Agency, MEMR 2012

RESOURCES

(MWe)%

RESERVE

(MWe)%

Speculative Hypothetical

42.84%

Possible Probable Proven

57.16%7.472 4.881 13.371 823 2.288

12.353 16.482

28.835

Page 7: GEOTHERMAL REGULATION AND POLICY IN INDONESIA · GEOTHERMAL REGULATION AND POLICY IN INDONESIA Presented at: Workshop on Geothermal Bussiness Opportunity in Indonesia Bandung, February

Direktorat Jenderal

EBTKEMinistry of Energy and Mineral Resources

Directorate General of New Renewable Energy and Energy Conservation

Road Map of Geothermal Development 2006 – 2025

Current Condition

2006

852 MW

(Produksi)

2008 2012 2016 2020

2000 MW 3442 MW 4600 MW 6000 MW 9500 MW

(Target)

1148 MW

Existing WKP

1442 MW

Existing WKP

1158 MW

Existing WKP

+ New WKP

1400 MW

New WKP

3500 MW

New WKP

2025

1341 MW

(based on Presidential Decree No. 5/2006 on National Energy Policy)

Page 8: GEOTHERMAL REGULATION AND POLICY IN INDONESIA · GEOTHERMAL REGULATION AND POLICY IN INDONESIA Presented at: Workshop on Geothermal Bussiness Opportunity in Indonesia Bandung, February

Direktorat Jenderal

EBTKEMinistry of Energy and Mineral Resources

Directorate General of New Renewable Energy and Energy Conservation

II. GEOTHERMAL POLICY

Page 9: GEOTHERMAL REGULATION AND POLICY IN INDONESIA · GEOTHERMAL REGULATION AND POLICY IN INDONESIA Presented at: Workshop on Geothermal Bussiness Opportunity in Indonesia Bandung, February

Direktorat Jenderal

EBTKEMinistry of Energy and Mineral Resources

Directorate General of New Renewable Energy and Energy Conservation

President Decree No 45/1991, No 49/1991, and No 23/1992

Business structure based on JOC and ESC

34% of Net Operating Income (NOI), that had included all kinds of taxes and retribution, except personal tax.

Project Management : Under Pertamina (JOC) and PLN (ESC)

Project Type: Total (Integrated) Project Partial Project

Law No. 27/2003

Business structure in the form of Permit: Geothermal Mining Permit Enterprise Permit for Electricity

Obligation to pay for taxes and royalty

Project Management : Under Permit Holder

Project Type:Total (Integrated) ProjectGWA holder will be granted as generally plan operation

Implementation of Geothermal Policies

Existing GWA New GWA

9

Page 10: GEOTHERMAL REGULATION AND POLICY IN INDONESIA · GEOTHERMAL REGULATION AND POLICY IN INDONESIA Presented at: Workshop on Geothermal Bussiness Opportunity in Indonesia Bandung, February

Direktorat Jenderal

EBTKEMinistry of Energy and Mineral Resources

Directorate General of New Renewable Energy and Energy Conservation

GEOTHERMAL POLICIES1. Improvement and harmonization of regulations in Geothermal Business.

1). Revising the law No. 27/2003 on Geothermal. The main purpose of this revision are:

- Geothermal activities can be carried out in conservation forest area.

- To accomadate “Participating Interest “ issue which demanded by local goverment.

- To amend GWA’s tender mechanism.

2). Revising GR No. 59/2007 on Geothermal Business Activities, mainly to revise GWA’s tender mechanism. Based on proposed regulation, the winner of GWA’s tender is determined by work programs and exploration commitments.

3). Preparing Technical Guidelines as the implementation of the MR no 22/2012.

2. The government provides fiscal incentives for geothermal development (based on Government Regulation No. 62/2008 jo No. 1/2007; MR of MoF No. 177/PMK.011/2007; and MR of MoF No. 22/PMK.011/2011)

• 30% of corporate income tax;• 10% of added-value tax paid by the GoI;• Custom duties exemption for geothermal developer;• 25% per year depreciation for 8 years with double declining balance method; and• Investment tax credit 5% per year for 6 years

3. Related to Forestry Issues, currently MEMR and Ministry of Forest have signed the MoU regarding the acceleration of geothermal utilization permit within production forest, protected forest, and conservation forest

Page 11: GEOTHERMAL REGULATION AND POLICY IN INDONESIA · GEOTHERMAL REGULATION AND POLICY IN INDONESIA Presented at: Workshop on Geothermal Bussiness Opportunity in Indonesia Bandung, February

Direktorat Jenderal

EBTKEMinistry of Energy and Mineral Resources

Directorate General of New Renewable Energy and Energy Conservation

GEOTHERMAL POLICIES ............(2)

4. Feed-in Tariff MechanismGovernment sets the price of electricity from geothermal power plant which is final and can not be negotiated by PT. PLN. This mechanism is expected to reduce the main obstacle in geothermal development related to price uncertainty that usually requires a long time for negotiation.

5. Financial support and Government guaranteeGovernment guarantee on the feasibility of PT. PLN; “Geothermal Fund" for geothermal exploration; Green Banking Program, etc

Page 12: GEOTHERMAL REGULATION AND POLICY IN INDONESIA · GEOTHERMAL REGULATION AND POLICY IN INDONESIA Presented at: Workshop on Geothermal Bussiness Opportunity in Indonesia Bandung, February

Direktorat Jenderal

EBTKEMinistry of Energy and Mineral Resources

Directorate General of New Renewable Energy and Energy Conservation

1. Law No. 27/2003 on Geothermal

2. Government Regulation No. 59/2007 on Geothermal Business Activities, asamanded in GR No. 70/2010

3. Government Regulation No. 62/2008 jo. GR No. 1/2007 on Income Tax Facilitiesfor Investment in Certain Business Areas and / or in Specific Regions

4. GR No. 9/2012 on Types And Tariffs On Non-tax State Revenue Applicable to TheMinistry Of Energy And Mineral Resources

5. GR No. 04/2010 on Assignment to PT. PLN (Persero) to Accelerate TheDevelopment of Power Plant from Renewable Energy, Coal and Gas

6. Ministry Regulation of Minister Energy And Mineral Resources

1). MR No. 11/2008 on the Procedure for Determination GWA2). MR No. 02/2009 on Guidelines for Geothermal Preliminary Survey

Assignment (as amendment of MR. 05/2007)3). MR No. 11/2009 on Guidelines for Implementation of Geothermal Business ,

jo. MR No. 18/2012

GEOTHERMAL REGULATION(After Law No. 27/2003)

Page 13: GEOTHERMAL REGULATION AND POLICY IN INDONESIA · GEOTHERMAL REGULATION AND POLICY IN INDONESIA Presented at: Workshop on Geothermal Bussiness Opportunity in Indonesia Bandung, February

Direktorat Jenderal

EBTKEMinistry of Energy and Mineral Resources

Directorate General of New Renewable Energy and Energy Conservation

4). MR No. 01/2012 on Revision of MR No. 15/2010 on The List of Power Plant Acceleration Projects Using Renewable Energy, Coal, and Gas and Related Transmission

5). MR No. 22/2012 on Assignment to PT PLN (Persero) to Purchase Electricity from Geothermal Power Plant and Geothermal Power Purchase Benchmark Price by PT PLN (Persero)

7. Ministry Regulation of Minister of Finance

1). No. 139/PMK.011/2011 on Procedures for Granting Business-Feasibility Guarantee to PT PLN (Persero) for The Development or Renewable Energy, Coal and Gas-Fueled Power Plants Through Cooperation With The Independent Power Producers

2) No. 03/PMK.011/2012 on Procedures for the Management and Accountability Geothermal Facility Fund

GEOTHERMAL REGULATION..Continue

Page 14: GEOTHERMAL REGULATION AND POLICY IN INDONESIA · GEOTHERMAL REGULATION AND POLICY IN INDONESIA Presented at: Workshop on Geothermal Bussiness Opportunity in Indonesia Bandung, February

Direktorat Jenderal

EBTKEMinistry of Energy and Mineral Resources

Directorate General of New Renewable Energy and Energy Conservation

III. GEOTHERMAL DEVELOPMENT

Page 15: GEOTHERMAL REGULATION AND POLICY IN INDONESIA · GEOTHERMAL REGULATION AND POLICY IN INDONESIA Presented at: Workshop on Geothermal Bussiness Opportunity in Indonesia Bandung, February

Direktorat Jenderal

EBTKEMinistry of Energy and Mineral Resources

Directorate General of New Renewable Energy and Energy Conservation

Development 2010 2011 2012 2013 2014 2015

Geothermal Development

1. Added Capacity (MW) 37 115 3 375 1.797

2. Installed Capacity (MW) 1.189 1.226 1.341 1.344 1.719 3.516

GEOTHERMAL PROGRAMPOWER PLANT DEVELOPMENT 2010 – 2015

Note:

- Capacity Factor of Geothermal Power Plant = 90%

Page 16: GEOTHERMAL REGULATION AND POLICY IN INDONESIA · GEOTHERMAL REGULATION AND POLICY IN INDONESIA Presented at: Workshop on Geothermal Bussiness Opportunity in Indonesia Bandung, February

Direktorat Jenderal

EBTKEMinistry of Energy and Mineral Resources

Directorate General of New Renewable Energy and Energy Conservation

No Geothermal Working Area (GWA) LocationPotential

Capacity (MW)

1 Gn. Talang West Sumatera 36

2 Songa Wayaua North Maluku 140

3 Danau RanauLampung & South

Sumatera210

4 Mataloko East Nusa Tenggara 63

5 Gn. Endut Banten 80

6 Way Ratai Lampung 105

7 Candi Umbul Telomoyo Central Java 120

8 Simbolon Samosir North Sumatera 155

9 Bora Pulu Central Sulawesi 123

10 Gn. Lawu Central Java 195

11 Kepahiang Bengkulu 180

12 Sembalun NTB 100

13 Oka ile Ange NTT 40

GEOTHERMAL WORKING AREA FOR TENDER

Page 17: GEOTHERMAL REGULATION AND POLICY IN INDONESIA · GEOTHERMAL REGULATION AND POLICY IN INDONESIA Presented at: Workshop on Geothermal Bussiness Opportunity in Indonesia Bandung, February

Direktorat Jenderal

EBTKEMinistry of Energy and Mineral Resources

Directorate General of New Renewable Energy and Energy Conservation

PRELIMINARY SURVEY ASSIGNMENT’S AREA

NoGeothermal Working Area

(GWA)District/ City Province

1 Sungai Betung Kerinci and Pesisir SelatanJambi and West

Sumatera

2 Sungai Tenang Merangin Jambi

3 Ciseeng Bogor and Lebak West Java and Banten

4 MalawaMaros, Pangkajene Kepulauan, Bone and

BarruSouth Sulawesi

5 Gn. Dua Saudara Bitung North Sulawesi

6 Ulumbu Manggarai NTT

7 Gn. Gede/Pangrango* Bogor, Sukabumi, and Cianjur West Java

8 Gn. Hamiding West Halmahera, North Halmahera North Maluku

9 Pentadio Gorontalo, Bone Bolango, Gorontalo City Gorontalo

10 Graho Nyabu Merangin, Kerinci, Muko-Muko Jambi and Bengkulu

11 Gn. WilisPonorogo, Madiun, Nganjuk, Kediri,

Tulungagung, TrenggalekEast Java

12 Gn. Geureudong Central Aceh, Bener Meriah, North AcehNanggroe Aceh

Darussalam

* Pre Survey Assignment is being carried out

Page 18: GEOTHERMAL REGULATION AND POLICY IN INDONESIA · GEOTHERMAL REGULATION AND POLICY IN INDONESIA Presented at: Workshop on Geothermal Bussiness Opportunity in Indonesia Bandung, February

Direktorat Jenderal

EBTKEMinistry of Energy and Mineral Resources

Directorate General of New Renewable Energy and Energy Conservation

18

ACEH 2 WKP

Jaboi: 70 MW

Seulawah Agam: 130 MW

NORTH SUMATERA 5 WKP

Sibayak – Sinabung: 130 MW

Sibual – Buali: 750 MW

Sipaholon Ria-ria: 75 MW

Sorik Marapi: 200 MW

Simbolon Samosir : 155 MW

JAMBI 1 WKP

Sungai Penuh: 70 MW

SOUTH SUMATERA 3 WKP

Lumut Balai: 250 MW

Rantau Dedap: 106 MW

Danau Ranau: 210 MW

BANTEN 2 WKP

Kaldera Danau Banten: 115 MW

G. Endut: 80 MW

WEST SUMATERA 4 WKP

Bukit Kili: 83 MW

Gn Talang: 35 MW

Liki Pinangawan: 400 MW

Bonjol: 200 MW

BENGKULU 2 WKP

Tmbg Sawah-Hululais: 873 MW

Kepahiyang : 180 MW

LAMPUNG 4 WKP

Gn.Rajabasa: 91 MW

Suoh Sekincau: 230 MW

Waypanas – Ulubelu: 556 MW

Danau Ranau: 210 MW

Way Ratai :105 MW

WEST JAVA 10 WKP

Ciater - Tgkban Perahu: 60 MW

Cibeureum–Parabakti: 485 MW

Cibuni: 140 MW

Cisolok Cisukarame: 45 MW

Gn. Tampomas: 50 MW

Gn. Tgkuban Perahu: 100 MW

Kamojang-Darajat: 1465 MW

Karaha Cakrabuana: 725 MW

Pangalengan: 1106 MW

G. Ciremai: 150 MW

CENTRAL JAVA 5 WKP

Baturaden: 175 MW

Dataran Tinggi Dieng: 780 MW

Guci: 79 MW

Gn. Ungaran: 100 MW

Umbul Telomoyo : 120 MW

EAST JAVA 4 WKP

Blawan – Ijen: 270 MW

Gn. Iyang Argopuro: 295 MW

Telaga Ngebel: 120 MW

Gn. Lawu: 195 MW

BALI 1 WKP

Tabanan: 276 MW

WEST NUSA

TENGGARA 2 WKP

Hu'u Daha: 65 MW

Sembalun : 100 MW

EAST NUSA TENGGARA 5 WKP

Atadei: 40 MW

Sokoria: 30 MW

Ulumbu: 199 MW

Mataloko: 63 MW

Oka Ile Ange : 40 MW

MALUKU 1 WKP

Tulehu: 100 MW

NORTH MALUKU 2 WKP

Jailolo: 75 MW

Songa Wayaua: 140 MW

NORTH SULAWESI 2 WKP

Kotamobagu: 410 MW

Lahendong-Tompaso: 358 MW

GORONTALO 1 WKP

Suwawa: 110 MW

CENTRAL SULAWESI 2 WKP

Marana: 35 MW

Bora Pulu : 152 MW

Total : 58 GWA

Distribution of GWA

GEOTHERMAL DEVELOPMENT

Lisence – Issued : 38 GWAs

Tender on Progress : 2 GWAs

Tender Preparation : 13 GWAs

Tender – Failed : 5 GWAs

Page 19: GEOTHERMAL REGULATION AND POLICY IN INDONESIA · GEOTHERMAL REGULATION AND POLICY IN INDONESIA Presented at: Workshop on Geothermal Bussiness Opportunity in Indonesia Bandung, February

Direktorat Jenderal

EBTKEMinistry of Energy and Mineral Resources

Directorate General of New Renewable Energy and Energy Conservation

Presidential Regulation No. 04/2010 on Assignment to PT. PLN to Accelerate Power

Plant Development Using Renewable Energy, Coal and Gas

MEMR Regulation No. 01/2012 as revised in Ministerial Regulation No. 15/2010 on

Projects List of Power Plant Accelerated Development using Renewable Energy, Coal

and Gas as well as Related Transmission

Target for Geothermal Power Plant Development on Crash Program 10.000 MW

Phase II

Existing field : 2000 MW

New Geothermal Working Area : 2925 MW

Total of Geothermal Development 4925 MW

GEOTHERMAL DEVELOPMENT TARGET

(2010 - 2014)

Page 20: GEOTHERMAL REGULATION AND POLICY IN INDONESIA · GEOTHERMAL REGULATION AND POLICY IN INDONESIA Presented at: Workshop on Geothermal Bussiness Opportunity in Indonesia Bandung, February

Direktorat Jenderal

EBTKEMinistry of Energy and Mineral Resources

Directorate General of New Renewable Energy and Energy Conservation

GEOTHERMAL POWER PLANT PROJECTS

INCLUDED IN CRASH PROGRAM PHASE II

(Based on MEMR Regulaton No. 01/2012)

NO.GEOTHERMAL POWER

PLANT PROJECTSTATUS PROVINCE

ESTIMATION OF

CAPACITY (MW)

INSTALLED

CAPACITY

2014 (MW)

REQUIRED

FINANCING

2014 (US$

MILLION)

1 Sungai Penuh Existing WKP Jambi 2x55 110 330

2 Hululais Existing WKP Bengkulu 2x55 110 330

3 Kotamobagu 1 and 2 Existing WKP North Sulawesi 2x20 40 120

4 Kotamobagu 3 and 4 Existing WKP North Sulawesi 2x20 40 120

5 Sembalun Open Area West Nusa Tenggara 2x10 20 60

6 Tulehu Existing WKP Maluku 2x10 20 60

7 Tangkuban Perahu I New WKP West Java 2x55 110 330

8 Kamojang 5 and 6 Existing WKP West Java 1 x30 1 x60 90 270

9 Ijen New WKP East Java 2x55 110 330

10 Iyang Argopuro Existing WKP East Java 1 x55 55 165

11 Ngebel New WKP East Java 3x55 165 495

12 Gunung Endut New WKP Banten 1 x55 55 165

13 Rawa Dano New WKP Banten 1 x 110 110 330

14 Cibuni Existing WKP West Java 1 x 10 10 30

15 Cisolok-Cisukarame New WKP West Java 1 x50 50 150

16 Karaha Bodas Existing WKP West Java 1 x30 2x55 140 420

17 Patuha Existing WKP West Java 3x60 180 540

18 Tampomas New WKP West Java 1 x45 45 135

19 Tangkuban Perahu II Existing WKP West Java 2x30 60 180

20 Wayang Windu Unit 3 and 4 Existing WKP West Java 2x 110 220 660

21 Gunung Ciremai New WKP West Java 2 x 55 110 330

22 Baturaden New WKP Central Java 2x 110 220 660

23 Dieng Existing WKP Central Java 1 x55 1 x60 115 345

24 Guci New WKP Central Java 1 x55 55 165

25 Ungaran New WKP Central Java 1 x55 55 165

26 Seulawah Agam New WKP Aceh 1X55 55 165

NO.

GEOTHERMAL

POWER PLANT

PROJECT

STATUS

INSTALLED

CAPACITY

(MW)

REQUIRED

FINANCING

(US$

MILLION)

27 Jaboi New WKP 10 30

28 Sarulla 1 Existing WKP 330 990

29 Sarulla 2 Existing WKP 110 330

30 Umbul Telumoyo New WKP 55 165

31 Simbolon Samosir Open Area 110 330

32 Sipoholon Ria-Ria New WKP 55 165

33 Sorik Marapi New WKP 240 720

34 Muaralaboh New WKP 220 660

35 Bonjol New WKP 165 495

36 Lumut Balai Existing WKP 220 660

37 Rantau Dadap New WKP 220 660

38 Rajabasa New WKP 220 660

39 Ulubelu 3 and 4 Existing WKP 110 330

40 Suoh Sekincau New WKP 220 660

41 Wai Ratai Open Area 55 165

42 Danau Ranau New WKP 110 330

43 Lahendong 5 dan 6 Existing WKP 40 120

44 Bora Open Area 5 15

45 Marana/Masaingi New WKP 20 60

46 Hu'u New WKP 20 60

47 Atadei New WKP 5 15

48 Sokoria New WKP 15 45

49 Mataloko New WKP 5 15

50 Jailolo New WKP 10 30

51 Songa Wayaua New WKP 5 15

4.925 14.775TOTAL PLANNED INSTALLED CAPACITY

GEOTHERMAL PROGRAM

Page 21: GEOTHERMAL REGULATION AND POLICY IN INDONESIA · GEOTHERMAL REGULATION AND POLICY IN INDONESIA Presented at: Workshop on Geothermal Bussiness Opportunity in Indonesia Bandung, February

Direktorat Jenderal

EBTKEMinistry of Energy and Mineral Resources

Directorate General of New Renewable Energy and Energy Conservation

V. FEED IN TARIFF MECHANISM

Page 22: GEOTHERMAL REGULATION AND POLICY IN INDONESIA · GEOTHERMAL REGULATION AND POLICY IN INDONESIA Presented at: Workshop on Geothermal Bussiness Opportunity in Indonesia Bandung, February

Direktorat Jenderal

EBTKEMinistry of Energy and Mineral Resources

Directorate General of New Renewable Energy and Energy Conservation

• In order to encourage the utilization of geothermal in national electricity supply, GoI have

made some efforts to increase investment by creating competitive and attractive business

climate, including simplifying GWA tender process and improve geothermal energy price

structure through Feed In Tariff (FIT) Mechanism.

• In FIT mechanism, the Government set the price of electricity from geothermal power plant

which is final and can’t be negotiated by PT. PLN. The FIT mechanism is determined with

consideration of:

1. Energy resources avaibility;

2. Environment capacity;

3. Economics.

• Feed-in Tariff is applied for new GWA and for extensions or capacity additions.

• This mechanism is expected to reduce the main obstacle in geothermal development related

to price uncertainty that usually requires a long time for negotiation.

• The tariff is applied based on location and available transmission of a certain area.

GEOTHERMAL FEED-IN TARIFF MECHANISM(Based On Ministrial Regulation of MEMR No. 22 / 2012)

Page 23: GEOTHERMAL REGULATION AND POLICY IN INDONESIA · GEOTHERMAL REGULATION AND POLICY IN INDONESIA Presented at: Workshop on Geothermal Bussiness Opportunity in Indonesia Bandung, February

Direktorat Jenderal

EBTKEMinistry of Energy and Mineral Resources

Directorate General of New Renewable Energy and Energy Conservation

The Feed-in Tariffs mechanism will be applied to :

a. geothermal license holders (IUP holder) after the issuance of MinisterRegulation No. 22/2012;

b. mining right holders, license holder or concession holder that existed beforethe enactment of Law No. 27 Year 2003 on Geothermal who already havePower Purchase Agreement (PPA), which will increase power plant capacityon the existing agreement (PPA);

c. mining right holders, license holder or concession holder that existed beforethe enactment of Law No. 27 Year 2003 on Geothermal who will extendtheir expired PPA;

d. mining right holders, license holder or concession holder that existed before the enactment of Law No. 27 Year 2003 on Geothermal who already have PPA, for both who have produced or not yet produced electricity or steam, as long as all parties involved agree upon the amendment on sales price of electricity or steam; or

e. IUP holder who will undertake PPA, as long as agreed by the partiesinvolved and allowed by PPA to be agreed by the parties.

Feed in Tariff Mechanism

Page 24: GEOTHERMAL REGULATION AND POLICY IN INDONESIA · GEOTHERMAL REGULATION AND POLICY IN INDONESIA Presented at: Workshop on Geothermal Bussiness Opportunity in Indonesia Bandung, February

Direktorat Jenderal

EBTKEMinistry of Energy and Mineral Resources

Directorate General of New Renewable Energy and Energy Conservation

No Area

Price

(cent US$/kWh)

High Voltage Medium Voltage

1 Sumatera 10 11,5

2 Java, Madura and Bali 11 12,5

3South Sulawesi, West Sulawesi, and Southeast

Sulawesi

12 13,5

4 North Sulawesi, Central Sulawesi, and Gorontalo 13 14,5

5 West Nusa Tenggara, and East Nusa Tenggara 15 16,5

6 Maluku and Papua 17 18,5

GEOTHERMAL FEED-IN TARIFF

Page 25: GEOTHERMAL REGULATION AND POLICY IN INDONESIA · GEOTHERMAL REGULATION AND POLICY IN INDONESIA Presented at: Workshop on Geothermal Bussiness Opportunity in Indonesia Bandung, February

Direktorat Jenderal

EBTKEMinistry of Energy and Mineral Resources

Directorate General of New Renewable Energy and Energy Conservation

`

Go Green Indonesia !Geothermal, Energy Solution for Better Future

www.ebtke.esdm.go.idwww.indogeothermal.or.id

Jalan Jenderal Gatot Subroto, Kav. 49 Jakarta 12950; Telp/Faks : 021-5250575

MINISTRY OF ENERGY AND MINERAL RESOURCES

DIRECTORATE GENERAL OF NEW RENEWABLE ENERGY AND ENERGY CONSERVATION

THANK YOU

Page 26: GEOTHERMAL REGULATION AND POLICY IN INDONESIA · GEOTHERMAL REGULATION AND POLICY IN INDONESIA Presented at: Workshop on Geothermal Bussiness Opportunity in Indonesia Bandung, February

Direktorat Jenderal

EBTKEMinistry of Energy and Mineral Resources

Directorate General of New Renewable Energy and Energy Conservation

ATTACHMENTS

Page 27: GEOTHERMAL REGULATION AND POLICY IN INDONESIA · GEOTHERMAL REGULATION AND POLICY IN INDONESIA Presented at: Workshop on Geothermal Bussiness Opportunity in Indonesia Bandung, February

Direktorat Jenderal

EBTKEMinistry of Energy and Mineral Resources

Directorate General of New Renewable Energy and Energy Conservation

No. Geothermal Working

Area/ LocationLicense Holder Developer Power Plant

Installed

Capacity

(MW)

1Sibayak – Sinabung, NORTH

SUMATERA

PT. Pertamina Geothermal

Energy (PGE)

PT. Pertamina Geothermal

Energy (PGE)Sibayak 12

2Cibeureum – Parabakti,

WEST JAVA

PT. Pertamina Geothermal

Energy (PGE)

KOB - Chevron Geothermal

Salak, Ltd (CGS)Salak 377

3Pangalengan,

WEST JAVA

PT. Pertamina Geothermal

Energy (PGE)

KOB - Star Energy Geothermal

Wayang Windu, Ltd (SEGWWL)Wayang Windu 227

4Kamojang – Darajat, WEST

JAVA

PT. Pertamina Geothermal

Energy (PGE)

PT. Pertamina Geothermal

Energy (PGE)Kamojang 200

5Kamojang – Darajat, WEST

JAVA

PT. Pertamina Geothermal

Energy (PGE)

KOB - Chevron Geothermal

Indonesia, Ltd (CGI)Darajat 270

6Dataran Tinggi Dieng,

CENTRAL JAVA

PT. Pertamina Geothermal

Energy (PGE)PT. Geo Dipa Energi (GDE) Dieng 60

7Lahendong – Tompaso,

NORTH SULAWESI

PT. Pertamina Geothermal

Energy (PGE)

PT. Pertamina Geothermal

Energy (PGE)Lahendong 80

8Ulubelu,

LAMPUNG

PT. Pertamina Geothermal

Energy (PGE)

PT. Pertamina Geothermal

Energy (PGE)Ulubelu 110

9Ulumbu,

NTTPT. PLN Geothermal PT. PLN Geothermal Ulumbu 5

1.34127

INSTALLED GEOTHERMAL POWER PLANT CAPACITY 2012

Page 28: GEOTHERMAL REGULATION AND POLICY IN INDONESIA · GEOTHERMAL REGULATION AND POLICY IN INDONESIA Presented at: Workshop on Geothermal Bussiness Opportunity in Indonesia Bandung, February

Direktorat Jenderal

EBTKEMinistry of Energy and Mineral Resources

Directorate General of New Renewable Energy and Energy Conservation

MEMR

Prov.

Govmt.

Corporation

PLN

WKP

DeterminationPre-SurveyWKP

Tendering

IUP

Issuance

Electricity

Price

Rep

ort o

f

Ten

derin

g

Pro

cess

Geo

therm

al

Po

tential

Potential

MapSurvey

APBN

Survey

APBD

Prov.

Other

Parties

Assignment

Evaluation WKPReport WKP-N

WKP-P

WKP-K

(S3-N)

(S3-P)

(S3-K)

IUP-N

IUP-P

IUP-K

(S4-N)

(S4-P)

(S4-K)

Tender Winner

GEOTHERMAL VALUE CHAIN

(S-1) (S-2) (S-3) (S-4) (S-5)

PPA

(S-6)

Assignment

Exp

loratio

n

(S-7)

Exp

lora

tio

n

(Current Regulations)

(S-0)

BUSINESS STADIUM (S-X)

Survey

APBD

Kab./

Kota

Local

Govmt.

(Regent/

City)

© DJEBTKE – KESDM 2010

Units

Potential/

Stadium Exp

loitatio

n

FSProduction/

Utilization

(S-8) (S-9) (S-10)

FS

Exp

loit

atio

n

Pro

du

ctio

n/

Uti

liza

tio

n

Updated : 6 Sept 2010

Tender Winner

Tender Winner

Report

Page 29: GEOTHERMAL REGULATION AND POLICY IN INDONESIA · GEOTHERMAL REGULATION AND POLICY IN INDONESIA Presented at: Workshop on Geothermal Bussiness Opportunity in Indonesia Bandung, February

©2012

Ministry of Energy and Mineral Resources

Directorate General of New Renewable Energy and Energy Conservation

No. GWA POWER PLANT REGION / CITY PROVINCEPOTENTIAL

(MW)

INSTALLED CAP.

(MW)

1 Sibayak-Sinabung Sibayak Karo North Sumatera 124 12

2 Cibeureum - Parabakti (Gn. Salak) Gunung Salak Bogor & Sukabumi West Java 952 377

Wayang Bandung West Java 400 227

Patuha Bandung West Java 706 -

Kamojang Garut West Java 855 200

Darajat Garut West Java 610 270

5 Dieng Dieng Wonosobo & Banjarnegara Central Java 780 60

6 Lahendong-Tompaso Lahendong Tomohon & Minahasa North Sulawesi 358 80

7 Sibual-Buali Sibual-Buali North Tapanuli & South Tapanuli North Sumatera 1146 -

8 Tambang Sawah - Hululais Hululais Rejang Lebong Bengkulu 873 -

9 Lumut Balai Lumut Balai Ogan Komering Ulu South Sumatera 1066 -

10 Sungaipenuh Sungaipenuh Kerinci Jambi 208 -

11 Ulubelu Ulubelu Tanggamus Lampung 556 110

12 Karaha-Cakrabuana Karaha-Cakrabuana Bandung & Tasikmalaya West Java 725 -

13 Buyan Bratan (Bedugul) Bedugul Tabanan Bali 276 -

14 Ulumbu Ulumbu Manggarai East Nusa Tenggara 199 -

15 Tulehu Tulehu Ambon Maluku 100 -

16 Cibuni Cibuni Bandung West Java 140 5

17 Iyang-Argopuro Iyang-Argopuro Porbolinggo East Java 295 -

18 Kotamobagu Kotamobagu Bolaang Mongondow & Minahasa North Sulawesi 410 -

19 Ciater Ciater Subang West Java 90 -

10,869 1,341Total

GWAs BEFORE LAW NO. 27/2003

4 Kamojang-Darajat

3 Pengalengan

Page 30: GEOTHERMAL REGULATION AND POLICY IN INDONESIA · GEOTHERMAL REGULATION AND POLICY IN INDONESIA Presented at: Workshop on Geothermal Bussiness Opportunity in Indonesia Bandung, February

©2012

Ministry of Energy and Mineral Resources

Directorate General of New Renewable Energy and Energy Conservation

1 LIKI PINANGAWAN MUARALABOH,

WEST SUMATERA

400 220 9.4 ¢ USD License - Issued PT. Supreme Energy Muaralaboh

2 GN. RAJABASA,

LAMPUNG

91 220 9.5 ¢ USD License - Issued PT. Supreme Energy Rajabasa

3 JABOI,

NAD

50 10 Rp. 1705 License - Issued PT. Sabang Geothermal Energi

4 SORIK MARAPI-ROBURAN-

SAMPURAGA, NORTH SUMATERA

200 240 8.10 ¢ USD License - Issued PT. Sorik Marapi Geothermal Power

5 CISOLOK CISUKARAME,

WEST JAVA

30 - 45 40 Rp. 630,00 License - Issued PT. Jabar Rekind Geothermal

6 GN. TANGKUBAN PERAHU,

WEST JAVA

100 120 Rp. 533,60 License - Issued PT. Tangkuban Perahu

Geothermal Power

7 GN. TAMPOMAS,

WEST JAVA

20 - 50 45 Rp. 598,00 License - Issued PT. Wijaya Karya Jabar Power

8 GN. UNGARAN,

CENTRAL JAVA

100 110 8.09 ¢ USD License - Issued PT. Giri Indah Sejahtera

9 SOKORIA,

EAST NUSA TENGGARA

30 30 Rp. 1.250,69 License - Issued PT. Sokoria Geothermal Indonesia

10 ATADEI,

EAST NUSA TENGGARA

40 10 9.5 ¢ USD License - Issued PT. Westindo Utama Karya

11 JAILOLO,

NORTH MALUKU

75 10 Rp. 1.727,54 License - Issued PT. Star Energy Geothermal Halmahera

12 SUOH SEKINCAU,

LAMPUNG

230 220 6.9 ¢ USD License - Issued PT. Chevron Geothermal Suoh

Sekincau

Proposed

Capacity (MW)No. GWA, LOCATION

Possible Reserve

(MWe)Price (/KWh) Status Licence Holder

GWAs AFTER LAW Np. 27/2003

Page 31: GEOTHERMAL REGULATION AND POLICY IN INDONESIA · GEOTHERMAL REGULATION AND POLICY IN INDONESIA Presented at: Workshop on Geothermal Bussiness Opportunity in Indonesia Bandung, February

©2012

Ministry of Energy and Mineral Resources

Directorate General of New Renewable Energy and Energy Conservation

13 RANTAU DEDAP, SOUTH SUMATERA 106 220 8.86 ¢ USD License - Issued PT. Supreme Energy Rantau Dedap

14 BATURADEN, CENTRAL JAVA 175 220 9.47¢ USD License - Issued PT. Sejahtera Alam Energy

15 GUCI, CENTRAL JAVA 79 55 9.09 ¢ USD License - Issued PT. Spring Energi Sentosa

16 HU'U DAHA, WEST NUSA TENGGARA 65 20 9.65 ¢ USDLooking forward for the

licensePT. Pacific Geo Energy

17 KALDERA DANAU BANTEN, BANTEN 115 110 8.39 ¢ USDLooking forward for the

licenseKonsorsium PT. Banten Global Sinergi

18 BLAWAN - IJEN, EAST JAVA 270 110 8.58 ¢ USDLooking forward for the

licensePT. Cahaya Ijen Energy

19 TELAGA NGEBEL, EAST JAVA 120 165 7.55 ¢ USDLooking forward for the

licensePT. Bakrie Power

20 SEULAWAH AGAM, NAD 160 55 - Tender on proggress -

21 SUWAWA, GORONTALO 110 - Tender - Failed -

22 GUNUNG TALANG, WEST SUMATERA 36 - Tender preparation -

23 SONGA WAYAUA, NORTH MALUKU 140 - Tender preparation -

24SIPAHOLON RIA-RIA,

NORTH SUMATERA75 - Tender - Failed -

25 MARANA, CENTRAL SULAWESI 36 - Tender - Failed -

26 BUKIT KILI, WEST SUMATERA 83 - Tender - Failed -

27 BONJOL, WEST SUMATERA 200 - - Tender - Failed -

28 DANAU RANAU, WEST JAVA 210 - - Tender preparation

29 MATALOKO, EAST NUSA TENGGARA 63 - - Tender preparation

30 GN. CIREMAI, WEST JAVA 150 - - Tender on proggress

31 GN. ENDUT, BANTEN 80 - - Tender preparation

No. GWA, LOCATIONPossible Reserve

(MWe)

Proposed

Capacity (MW)Price (/KWh) Status Licence Holder

Continued…………GWAs AFTER LAW NO. 27/2003

Page 32: GEOTHERMAL REGULATION AND POLICY IN INDONESIA · GEOTHERMAL REGULATION AND POLICY IN INDONESIA Presented at: Workshop on Geothermal Bussiness Opportunity in Indonesia Bandung, February

©2012

Ministry of Energy and Mineral Resources

Directorate General of New Renewable Energy and Energy Conservation

32 SIMBOLON SAMOSIR, SUMUT 155 - Tender preparation -

33 WAY RATAI, LAMPUNG 105 - Tender preparation -

34CANDI UMBUL TELOMOYO,

JATENG 72 - - Tender preparation -

35 BORA PULU, SUMUT 123 - - Tender preparation

36 GN.LAWU,JATENG-JATIM 195 - - Tender preparation

37 KEPAHIYANG, BENGKULU 180 - - Tender preparation

38OKA ILE ANGE, EAST NUSA

TENGGARA40 - - Tender preparation

39SEMBALUN, WEST NUSA

TENGGARA100 - - Tender preparation

No. GWA, LOCATIONPossible

Reserve (MWe)

Proposed

Capacity (MW)Price (/KWh) Status Licence Holder

Continued…………GWAs AFTER LAW NO. 27/2003


Recommended