City Location Grandview Heights Location Plan Area
PLAN CONTEXT
NCP REDWOOD HEIGHTS NEIGHBOURHOOD CONCEPT PLAN
POND LOCATION CHANGES
NCP
POND LOCATION CHANGES PROPOSED
STAGE 2
REDWOOD HEIGHTS NEIGHBOURHOOD CONCEPT PLAN
Planning Slide Final Plan
RESIDENTIAL LAND USES
NCP
UPA = Residential Units Per Acre FAR = Floor Area Ratio
REDWOOD HEIGHTS NEIGHBOURHOOD CONCEPT PLAN
TYPES OF PARKS & OPEN SPACE
NCP REDWOOD HEIGHTS NEIGHBOURHOOD CONCEPT PLAN
Neighbourhood Parks Riparian Areas Natural Area Parks
ROAD NETWORK & TRAFFIC CONTROL
NCP REDWOOD HEIGHTS NEIGHBOURHOOD CONCEPT PLAN
Arterial Roads
Collector Roads
Local Roads
Special Rd Design
WATER INFRASTRUCTURE
NCP REDWOOD HEIGHTS NEIGHBOURHOOD CONCEPT PLAN
Limited water infrastructure exists in the NCP area.
Water supply will be from
the Grandview pump station and reservoir on 24 Ave / 168 St.
To service the NCP area,
new feeder mains, distribution mains and pressure zone boundaries are required.
WATER SERVICING
NCP REDWOOD HEIGHTS NEIGHBOURHOOD CONCEPT PLAN
Water Pressure Zones 142m zone - serviced from
Grandview Pump Station 110m zone - serviced from
Grandview Reservoir 90m zone - serviced from
110m zone and PRVs
WATER PHASING
NCP REDWOOD HEIGHTS NEIGHBOURHOOD CONCEPT PLAN
Implementation / Phasing High pressure (142m) feeder main is required
at start.
Local distribution network expands and PRVs are required as NCP area develops.
Low pressure (110m) feeder main is required when the high pressure main reaches capacity.
SANITARY SEWER INFRASTRUCTURE
NCP
No community-level sanitary sewer system in NCP area.
Existing development serviced by on-lot sewage disposal systems
To service the NCP area, a network of gravity sewers is required convey the sanitary sewer.
REDWOOD HEIGHTS NEIGHBOURHOOD CONCEPT PLAN
SANITARY SEWER SERVICING
NCP REDWOOD HEIGHTS NEIGHBOURHOOD CONCEPT PLAN
Implementation / Phasing A pump station, is then
required to pump sanitary sewer from Redwood Heights and the surrounding areas.
This pump station pumps the sewage to the North Grandview Interceptor at 2900 Block and 170 Street
DRAINAGE INFRASTRUCTURE
NCP REDWOOD HEIGHTS NEIGHBOURHOOD CONCEPT PLAN
The NCP area is currently serviced by open ditches and culverts, typical of rural and agricultural areas.
The existing system conveys stormwater to the Nicomekl River lowlands, to the north.
A servicing plan has been developed to: Protect downstream lands from prolonged flooding Protect receiving watercourses from erosion Maintain base flows in creeks Maintain water quality in creeks, ditches and storm systems Safely convey runoff to large river systems Protect the natural environment adjacent to watercourses
STORMWATER MANAGEMENT
NCP REDWOOD HEIGHTS NEIGHBOURHOOD CONCEPT PLAN
• 4 stormwater catchments require community detention ponds.
INFRASTRUCTURE COSTS/REVENUES
NCP REDWOOD HEIGHTS NEIGHBOURHOOD CONCEPT PLAN
Servicing Type
Estimated Cost
Stormwater $36,660,000
Sanitary Sewer $15,450,000
Water $11,510,000
Transportation $50,270,000 Wildlife Hubs/Corridors (BCS) Lands $83,400,000
INFRASTRUCTURE EXPENDITURES
Servicing Type
Estimated DCC Revenues
Stormwater $11,900,000
Sanitary Sewer $12,400,000
Water $9,400,000
Transportation $52,000,000 Wildlife Hubs/Corridors (BCS) Lands $0
INFRASTRUCTURE REVENUES
FINANCING TOOLS
NCP REDWOOD HEIGHTS NEIGHBOURHOOD CONCEPT PLAN
Establish an Area Specific Development Cost Charge (DCC) rates for infrastructure in the Redwood Heights NCP area.
OR
Utilize Development Works Agreements
(DWA) to fund any revenue shortfall.
GREEN SPACE LEVY
NCP REDWOOD HEIGHTS NEIGHBOURHOOD CONCEPT PLAN
• At present, there is no Citywide funding strategy to acquire these natural areas located on private land.
• Redwood Heights NCP area has 42 acres of
GIN land, which is identified as a wildlife corridor and hub.
• To acquire the land for the wildlife corridor
and hub within Redwood Heights, there will be a development cost charge of approximately $15,000 to $25,000 per unit, depending on land use.
EXAMPLE AREA SPECIFIC DCC
NCP REDWOOD HEIGHTS NEIGHBOURHOOD CONCEPT PLAN
Land Use Proposed 2018 DCC Rate
Potential Area Specific Rate
Increase
RF, RF-13 $41,220 $75,000 59%
RF-10 $36,193 $63,000 51%
RM10/15/23/30 (based on 1,550 sq.ft.)
$32,984 $56,000 52%
RM45/70 (based on 950 sq.ft.)
$22,971 $40,000 55%
Commercial $11.98 $25.00 74%
NCP COMMUNITY AMENITY FEE
WEST CLAYTON NEIGHBOURHOOD CONCEPT PLAN
NCP
*The surcharge fee per residential unit (or equivalent) is based on the projection of 4,542 units anticipated in the plan, and would result in a fee of $3,305.84 per unit.
* The amenity contributions noted above are payable upon subdivision for single-family subdivisions or upon issuance of building permits for multiple development and other uses.
REDWOOD HEIGHTS NCP #4 COMMUNITY AMENITY CONTRIBUTIONS
Per Unit Contribution All
Residential (Approx. 4,542 dwelling units @
average density)
Per Acre Contribution All
Non-Residential Uses (36.4 Acres)
Anticipated Total
Revenue at Build Out
Police Protection
$68.05 per dwelling
$408.30 per acre
$323,945.22
Fire Protection
$293.98 per dwelling
$1,763.88 per acre
$1,399,462.39
Parks & Pathways
$2,790.71 per dwelling
n/a
$12,675,422.00
Library Materials
$153.10 per dwelling
n/a
$695,380.20
Total Contribution (per unit or per acre)
$3,305.84 per dwelling
$2,172.18 per acre
Anticipated Total Revenue
$15,094,209.81
NCP SURCHARGE FEE
WEST CLAYTON NEIGHBOURHOOD CONCEPT PLAN
NCP
*The surcharge fee per residential unit (or equivalent) is based on the projection of 4,542 units anticipated in the plan, and would result in a fee of $126.03 per unit.
Cost Recovery of Redwood Heights NCP Preparation (Surcharge Fee)
Consultant Study Cost Per Unit Fee (Based on 4,542 units)
Stage 1 Planning & Engineering $334,351.59 $73.61
Environmental and Tree Studies $10,000.00 $2.20
Stage 2 Engineering Servicing Studies (Water, Sanitary, Drainage)
$195,402.00
$43.02
South Surrey Transportation Study *$130,756.00
(25% to be paid by NCP #4) $7.20
TOTAL CONSULTANT STUDY COSTS: $572,442.59 $126.03