GREEN MILL RUN GREENWAY/BIKEWAY - PHASE 2 EXTENSION FROM EVANS PARK TO CHARLES BOULEVARD CITIZEN’S INFORMATIONAL WORKSHOP MAY 30, 2012 PROPOSED 10’ HIGH- VISIBILITY CROSSWALK WITH REFUGE ISLAND ON ARLINGTON BOULEVARD REMOVE EXISTING CROSSWALK REMOVE EXISTING CROSSWALK 500 YEAR FLOODPLAIN 500 YEAR FLOODPLAIN 100 YEAR FLOODPLAIN 100 YEAR FLOODPLAIN FEMA FLOODPLAIN FEMA FLOODPLAIN CSX RAILROAD PROPOSED 10’ HIGH-VISIBILTY CROSSWALK ON EVANS STREET WITH PEDESTRIAN AMENITIES PROPOSED 8’ ASPHALT MULTI-USE PATH PROPOSED 10’ WIDE BOARDWALK PROPOSED TRAIL HEAD AT CANTERBURY PROPOSED 8’ ASPHALT MULTI-USE PATH CONNECTION GREEN MILL RUN END PROJECT CSX RAILROAD EVANS STREET CLIFTON STREET PIRATE’S PLACE APARTMENTS EAST CAROLINA UNIVERSITY EVANS PARK ARLINGTON BOULEVARD PROPOSED 10’ CROSSWALK ACROSS SCHOOL DRIVEWAY REMOVE EXISTING 5’ CONCRETE SIDEWALK AND REPLACE WITH 2’ GRASS VERGE AND 10’ WIDE ASPHALT PATH BEGIN PROJECT J.H. ROSE HIGH SCHOOL CONSTRUCT 10’ ASPHALT MULTI-USE PATH WITH 2’ GRASS VERGE AT EXISTING BACK OF CURB ALONG EVANS STREET SULGRAVE ROAD CANTERBURY ROAD CHARLES BOULEVARD FICKLEN DRIVE PROPOSED 10’ WIDE PEDESTRIAN BRIDGE PROPOSED 10’ WIDE BOARDWALK PROPOSED 10’ ASPHALT MULTI-USE PATH WITH 2’ GRAVEL SHOLDER GREEN MILL RUN GREENWAY, PHASE 1 EAST CAROLINA UNIVERSITY CHALLENGE COURSE TIE INTO EXISTING PATH EAST CAROLINA UNIVERSITY ATHLETIC FIELDS MULTI-USE PATH TYPICAL SECTION 0 100 200 400 N
Transcript
Page 1: GREEN MILL RUN GREENWAY/BIKEWAY - PHASE 2 EXTENSION

GREEN MILL RUN GREENWAY/BIKEWAY - PHASE 2 EXTENSIONFROM EVANS PARK TO CHARLES BOULEVARD

CITIZEN’S INFORMATIONAL WORKSHOP MAY 30, 2012

PROPOSED 10’ HIGH-VISIBILITY CROSSWALK

WITH REFUGE ISLAND ON ARLINGTON BOULEVARD

REMOVE EXISTING CROSSWALK

REMOVE EXISTING CROSSWALK

500 YEAR FLOODPLAIN

500 YEAR FLOODPLAIN

100 YEAR FLOODPLAIN

100 YEAR FLOODPLAIN

FEMA FLOODPLAIN

FEMA FLOODPLAIN

CSX R

AILROAD

PROPOSED 10’ HIGH-VISIBILTY CROSSWALK ON EVANS STREET WITH

PEDESTRIAN AMENITIES

PROPOSED 8’ ASPHALT MULTI-USE PATH

PROPOSED 10’ WIDE BOARDWALK

PROPOSED TRAIL HEAD AT CANTERBURY

PROPOSED 8’ ASPHALT MULTI-USE PATH

CONNECTIONGREEN MILL RUN

END PROJECT

CSX RAILROAD

EVANS STREET

CLIFTON STREET

PIRATE’S PLACE APARTMENTS

EAST CAROLINA UNIVERSITY

EVANS PARK

ARLINGTON BOULEVARD

PROPOSED 10’ CROSSWALK ACROSS SCHOOL DRIVEWAY

REMOVE EXISTING 5’ CONCRETE SIDEWALK AND REPLACE WITH 2’ GRASS VERGE AND 10’ WIDE ASPHALT PATH

BEGIN PROJECT

J.H. ROSE HIGH SCHOOL

CONSTRUCT 10’ ASPHALT MULTI-USE PATH WITH 2’ GRASS VERGE AT EXISTING BACK OF CURB ALONG EVANS STREET

SULG

RAV

E RO

AD

CA

NTE

RBU

RY R

OA

D

CHA

RLES

BO

ULE

VARD

FICKLEN DRIVE

PROPOSED 10’ WIDE PEDESTRIAN BRIDGE

PROPOSED 10’ WIDE BOARDWALK

PROPOSED 10’ ASPHALT MULTI-USE PATH WITH 2’ GRAVEL SHOLDER

GREEN MILL RUN GREENWAY, PHASE 1

EAST CAROLINA UNIVERSITY CHALLENGE COURSE

TIE INTO EXISTING PATH

EAST CAROLINA UNIVERSITY ATHLETIC FIELDSMULTI-USE PATH TYPICAL SECTION

0 100 200 400

N