GlaxoSmithKline 1061 Mountain Highway
PO Box 168, Boronia VIC 3155
Australia
STEAM AND CONDENSATE AUDIT REPORT
Audit Date: 25th
to 29th
June 2012
PROJECT 90181-AUS-BOR
1 Emission S. Raikar P. Provot 27/07/2012 Item Description Established Checked out Date
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 2 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
Acknowledgement
An Engineering Audit is a venture between Energy Experts and Plant Experts to define
opportunities for optimization. The contribution of the plant’s team is extremely important in this
venture. We sincerely acknowledge the contribution of the following dignitaries and site
engineering personnel whose co-operation helped to conclude to the quality of the data analysis
and conclusions.
� Mr. Phillip L Osborne - Environmental Sustainability Cluster Head
� Mr. John A. Giraud
� Mr. Gary Foley - Eng. Infrastructure Coordinator
� Mr. Robert Sedlins
We are also thankful to the all other staff members who were actively involved while collecting the
data and conducting the field trials.
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 3 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
TABLE OF CONTENTS
ACKNOWLEDGEMENT________________________________________________02
1. EXECUTIVE SUMMARY________________________________________________04
2. STEAM BUDGET AND SUMMARY OF POTENTIAL SAVINGS_______________________06
3.1 OPTIMIZATION PROJECT NO1___________________________________________12
OPTIMIZE BOILER OPERATION, IMPROVE BOILER HOUSE EFFICIENCY BY BETTER BOILER
CAPCITY UTILIZATION
3.2 OPTIMIZATION PROJECT NO2___________________________________________16
IMPROVE SYSTEM EFFICIENCY BY OPTIMIZING BOILER COMBUSTION, MAINTAIN CORRECT
OXYGEN IN BOILER STACK
3.3 OPTIMIZATION PROJECT NO3___________________________________________22
OPTIMIZE BOILER BLOWDOWN, MAINTAIN CORRECT BOILER BLOWDOWN WATER PARAMETER
3.4 OPTIMIZATION PROJECT NO4___________________________________________27
RECOVER HEAT FROM BOILER STACK TO PRE-HEAT BOILER FEED WATER
3.5 OPTIMIZATION PROJECT NO5___________________________________________31
AVOID FLOODING OF RADIATOR COIL FOR AHU – BLOCK 1AND NON STERILIZATION
PACKING AREA
3.6 OPTIMIZATION PROJECT NO6___________________________________________34
RECOVER FALSH STEAM FROM BFS PLANT TO HEAT CLARIFIER HOT WATER
4.0 COMPLETE CHECK LIST OF ALL VERIFICATIONS DONE DURING THE AUDIT ___________ 37
5.0 RECOMMENDED COMPLEMENTARY STUDIES _______________________________ 39
6.0 CONCLUSION AND RECOMMENDED NEXT STEP______________________________ 41
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 4 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
1 Executive summary
GlaxoSmithKline is a world-leading, research-based pharmaceutical company operating in
more than 100 countries and employing more than 100,000 people world-wide. It is a global
research-based pharmaceutical and healthcare company with a mission to improve the quality
of human life by enabling people to do more, feel better and live longer.
In Australia GSK have improved people’s wellbeing by delivering the highest quality
medicines, vaccines and over-the-counter healthcare products since 1886. GSK provide
about 1600 skilled jobs across the country, working with researchers and doctors to discover
new ways of treating and preventing disease. In 2011 GSK invested $58 million a year in local
research and development, and made significant contributions to Australia’s $4.2 billion
pharmaceutical and medicinal exports.
Boronia, Victoria facility was established in 1970 after being relocated from North Melbourne,
the Boronia head office houses employees working in marketing and sales, research and
development, regulatory affairs, government and corporate affairs, finance, IT and human
resources. The manufacturing plant is the largest GSK sterile facility globally. The site houses
world leading blow-fill-seal technology, featuring eight filling machines and six packaging
lines, as well as 10 tableting lines. The most recent edition is a second Relenza line
completed in 2006. The site has the capacity to produce 1.4 billion tablets per annum,
including products for migraine, herpes, peptic ulcers, treatment of epilepsy, smoking
cessation and anti-virals. Additional capsule products are manufactured for relief of asthma
and pain management.
A microbiology laboratory is also located at the Boronia site that tests 4,000 samples each
year and a chemistry laboratory that test 11,000 samples each year.
As a part of the energy conservation activity, Armstrong has conducted an Energy audit of
Steam and Condensate network from 25th
to 29th
June 2012.
The energy audit covers the 4 parts of the steam loop: boiler house, steam distribution, steam
consumption and condensate return.
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 5 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
As decided after the day on site, the initial issue we concentrated on was to check the boiler
house efficiency. Based upon our measurements and calculations during the audit, the overall
boiler house efficiency is a reasonable 82.91% on Lower Heating Value.
Since two boilers of capacity 3.4 TPH each are operated together to cater steam demand of
1.2 TPH radiation losses are high. Boiler stack oxygen is measured in the range of 5.2 – 6.8%
which is highr compared to industry standard. Both boilers are not provided with economizer.
Stack temperature is measured as 175 °C – 205 °C. With proper boiler pressure setting, fine
tuning burner and installation of economizer boiler flue gas path will help in reducing fuel
consumption by 6.0%. Boiler blowdown optimization will reduce losses by 0.4%.
Although the steam distribution system is old and oversized, during audit insulation surface
temperature was found within good operating practice. Insulation and leaking steam traps are
already being taken care of by other companies and are therefore not covered in this audit.
Presently all recoverable condensate from the process area along with hot water generated in
BFS plant is returned back to the boiler feed water tank. Makeup water consumption is
calculated as 6% of total steam generation. During audit, it was also observed that flash
steam form the plant is not recovered and is vented to atmosphere. Recovering this flash
steam for generating hot water can reduce heat load by 2 – 3%.
We estimate the potential energy savings of at least 9.7% of the current yearly steam
budget of 165,182 $, which represents a yearly saving of about 16,093 $, 730.2 MWh energy
and 133 tons of CO2 with payback period of 4.4 years
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 6 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
2 Steam budget and summary of potential savings
Total yearly steam consumption (in 2011): 9750 t/year
Steam cost (in 2011): 16.94 $/t of steam
Total yearly steam budget (in 2011): 165,182 $/year
During the audit, two3.2TPH (2MW) boilers were operated continuously to cater plant steam
demand. Natural gas is used as fuel. Average steam generated by the boiler is 26.7 T/day at
800 to 900 kPa pressure. Since gas flow readings were erronous, gas consumption is
estimated using boiler indirect efficiency. Gas consumption for boiler is estimated as 2016
Nm3/day. Low pressure steam is injected in feed water tank to maintain boiler feed water
temperature at 85 deg C.
Boiler steam load variation with time
As most of the processes in the plant are of batch type, steam demand varies considerably.
During audit average plant steam demand was measured as 949 kg/hr with peak steam
demand of 4065 kg/hr.
A summary of our calculations is given below:
Time
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 7 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
Boiler Efficiency – Indirect method
Flue gas analysis result
Boiler - B1 (Working) 1 2 3 4 5 6 7 8 9 10 Avg
O2 % 6.6 6.6 6.5 6.8 6.8 6.4 6.4 6.1 6.7 6.7 6.63
CO2 % 8.64 8.64 8.7 8.52 8.52 8.76 8.76 8.94 8.58 8.58 8.62
CO ppm 0 0 1 1 1 0 0 0 0 1 0.67
Ex Air % 45.8 45.8 44.8 47.9 47.9 43.8 43.8 40.9 46.9 46.9 46.13
Boiler - B2 (Standby) 1 2 3 4 Avg
O2 % 5.7 5.3 5.2 5.3 5.38
CO2 % 9.18 9.42 9.48 9.42 9.38
CO ppm 0 1 0 5 1.50
Ex Air % 37.3 33.8 32.9 33.8 34.45
EFFICIENCY CALCULATIONS FOR BOILER AS PER BS 845 PART I 1987
Fuel Natural Gas
Moisture in Fuel 1.5 %
Hydrogen in Fuel 23 %
Net Calorific Valve 9243 kCal/Nm3
1 Loss due to sensible heat in dry flue gases (L1)
= 7.97 %
where
Knet = const based on calorific value of fuel
= 0.39 Siegert constant
t3 = temp of flue gases leaving Boiler
= 205 deg C
ta = temp of air entering combustion system
= 21 deg C
Vco2 = Volume of CO2 in gases leaving boiler (dry)
= 9 %
( )
2
31Vco
tatknetL net
−⋅=
( )
2
31Vco
tatknetL net
−⋅=
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 8 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
2 Loss due to enthalpy in water in flue gases (L2)
= 2.98 %
where
mH2O = moisture in fuel
= 1.5 %
H = Hydrogen content of fuel
= 23 %
t3 = temp of flue gases leaving boiler
= 205 deg C
ta = temp of air entering combustion system
= 21 deg C
Qnet = NCV of fuel at constant pressure
= 9243 kcal/Nm3
3 Loss due to unburned gases in flue gases (L3)
= 0.00 %
where
k1 = constant
= 40
Vco2 =
= 9 %
Vco = Volume of CO in gases leaving boiler (dry)
= 0.001 %
Qnet = NCV of fuel at constant pressure
= 9242.89 kcal/Nm3
Qgr = GCV of fuel at constant pressure
= 10269.9 kcal/Nm3
4 Unbrunt Loss (L4)
L4net = For package boiler unbrunt loss are assumed as 0.5%
5 Radiation, conduction & convection losses (L5)
L5net = Boiler Rated Capacity
Qnet
ttHOmHL a
net
)1.22.4210()9(2 32
+−⋅+=
net
gr
Q
Q
VcoVco
VcoKnetL •
+
⋅=
2
13
Qnet
ttHOmHL a
net
)1.22.4210()9(2 32
+−⋅+=
net
gr
Q
Q
VcoVco
VcoKnetL •
+
⋅=
2
13
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 9 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
Boiler Operating Capacity
= 5.3 %
Boiler Rated Capacity 6.4 T/hr
Operating Capacity 1.2 T/hr
6 Total losses (Lt)
Ltnet L1+L2+L3+L4+L5+Blowdown loss (0.3%)
= 17.09 %
6 Thermal Efficiency η
= 82.91 %
LtnetEnet −= 100 LtnetEnet −= 100
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 10 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
Summary of identified energy-saving optimisations and their estimated yearly results:
Optimisation Project Energy
saving in
kWh
Energy
saving in
$.
Decreased CO2
emissions in
ton
Total project
investment
cost in $.
Payback
time in
years
Optimization N˚1
Optimize boiler operation, improve
boiler efficiency by better boiler
capacity utilization
98 885 2 065 18.0 500 0.2
Optimization N˚2
Improve system efficiency by
optimizing boiler combustion
maintain correct oxygen in boiler
stack
82 679 1 726 15.1 2 500 1.4
Optimization N˚3
Optimize boiler blowdown
maintain correct boiler blowdown
water parameters
38 644 1 103 7.0 1 000 0.9
Optimization N˚4
Recover heat from boiler stack to
pre-heat boiler feed water
293 249 6 123 53.4 36 000 5.9
Optimization N˚5
Avoid flooding of radiator coil for
AHU- Block 1 and Non
Sterilization packing area
-- -- -- 15 000 --
Optimization N˚6
Recover flash steam form BFS
plant to heat Clarifier hot water
216 755 5 076 39.5 15 000 1.8
Total 730 212 16 093 133 70 000 4.4
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 11 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
Note:
� Values marked as * imply a requirement of in-depth review to ascertain confirm saving potential
� Savings are calculated on only heat recovery basis.
� Savings are based on the data furnished by the plant head and data collected during the study period.
� Investment considered for the payback calculations are based on budgetary prices of the items considered and
may change depending upon implementation time & the prevailing market situation. At an Audit level
investments are calculated with an accuracy of ±25%.
The above investment and saving estimates are developed according to standard engineering
practices and are based on Armstrong’s extensive experience in steam and utility systems.
More accurate investment estimates will be available after the scope of work to be done by
AIPL is defined and jointly agreed upon by GSK and AIPL as well as upon completion of
Detailed Engineering Design.
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 12 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
3.1 Optimisation Project N°1:
Optimize boiler operation, improve boiler house efficiency by better boiler capacity utilization
Current System Description and Observed Deficiency
Presently two boilers of capacity 3.2TPH are operated continuously at 850 – 950 kPa to
cater the plant steam demand. Alternately, one boiler works as lead boiler and second boiler
is operated in auto mode just to maintain the steam pressure. Plant average steam demand
is measured as 1.1 TPH with peak steam load of 4.0 TPH. Plant steam load variation with
time is shown by below graph.
Plant steam load is quite fluctuating and it varies considerably with respect to the production.
During the audit, it was observed that irrespective of steam demand, the lag boiler comes on
line to make drop in pressure. This causes both boilers to operate on part load resulting in
considerable drop in boiler efficiency. Refer below graph
Time
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 13 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
During the audit, AIPL used temperature data loggers to understand boiler operation cycle.
For lag boiler cutin and cut out pressure were set at 800 – 900 kpa. From graph it’s clear
that every 2.5 to 3 hrs lag boiler fire to maintain drop in pressure.
Boiler MCR output
Peak Steam Demand
Gas Flow meter data not available 2
nd Boiler firing status in red
Plant Average steam load
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 14 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
Technical Discussion
Lag boiler is required to take care of the steam demand in case of failure of the operating
boiler to maintain required pressure or to meet peak steam demand. It is recommended to
operate lead boiler at maximum load to maximize boiler efficiency.
From records, plant average steam demand is measured as 1.1 TPH with peak demand of
4.0 TPH (very rare). Considering the plant requirement, one boiler operation at full load is
sufficient to cater the plant steam load.
Keeping the second boiler in operation will increase the radiation loss thereby reducing
boiler house efficiency. Also burner firing is associated with pre purge and post purge
losses, this consumes substancial energy and increase fuel consumption.
Operating one boiler at full load and reducing frequency of burner firing of second boiler
from present once every 3 hour to once in a shift, a considerable amount of fuel can be
saved. Estimated efficiency gain is 1.3%.
Recommended Optimization
It is recommended to reduce frequency of burner firing from present once every 3 hour to
once in a shift by
Resetting the burner cut-in and cut-out pressure to
a. Cut-in at 350 kPa g
b. Cut out at 900 kPa g
Estimated Benefit
By operating boiler at maximum load, using second boiler only in case of requirement can
improve boiler house efficiency by 1.3%. In monetary terms, savings are estimated as 2065
$ annually. The savings are calculated based on 2011 annual steam generation and the
respective calculated efficiencies.
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 15 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
Details of calculations
Present annual fuel consumption 735908 Nm3/annum
Rise in boiler efficiency 2.50 %
Net rise considered 50% 1.3 %
Reduction in fuel consumption 9199 Nm3/annum
Estimated annual monetary savings 2065 $/annum
Annual estimated energy saving 356 GJ/annum
98885 kWh/annum
Note: Since we cannot stop second boiler completely, only 50% gain gain in effieicy is considered for
the calculating savings.
The CO2 emissions reduction by optimizing boiler operation is estimated as 18.0 ton/year
Estimated Investment and Payback
The investment is estimated to be $ 500 it includes:
� Change in boiler pressure setting
� Service charges
The payback period for these investments would be 0.2 Year
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 16 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
3.2 Optimisation Project N°2:
Improve system efficiency by optimizing boiler combustion, maintain correct oxygen in boiler stack
Current System Description and Observed Deficiency
Presently two boilers of total capacity 3.2TPH are operated continuously to cater the plant
Steam demand. The average steam load on the boiler is 1.1 TPH with peak demand of
4.0TPH. During visit stack analysis was conducted for both the boiler to identify operating
efficiency. It was observed that the oxygen percentage in flue gases of heater for Boiler 1
was measured as 6.4 – 6.8% and for boiler to measured as 5.2 – 5.7% respectively
During study flue gas analysis was conducted for all boilers to check excess air level for
combustion. Results are as below
Boiler – B1 (Working) 1 2 3 4 5 6 7 8 9 10 Avg
O2 % 6.6 6.6 6.5 6.8 6.8 6.4 6.4 6.1 6.7 6.7 6.63
CO2 % 8.64 8.64 8.7 8.52 8.52 8.76 8.76 8.94 8.58 8.58 8.62
CO ppm 0 0 1 1 1 0 0 0 0 1 0.67
Ex Air % 45.8 45.8 44.8 47.9 47.9 43.8 43.8 40.9 46.9 46.9 46.13
Boiler - B2 (Standby) 1 2 3 4 Avg
O2 % 5.7 5.3 5.2 5.3 5.38
CO2 % 9.18 9.42 9.48 9.42 9.38
CO ppm 0 1 0 5 1.50
Ex Air % 37.3 33.8 32.9 33.8 34.45
Oxygen % indicated in the stack is a measure of “Stack Loss”. The higher the Oxygen
percentage in stack , the higher is the stack loss and lower the boiler efficiency. Present
combustion efficiencies of the boilers are as follows
Boiler house efficiency is calculated as 82.91 % on NCV
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 17 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
Technical Discussion
Combustion refers to the rapid oxidation of fuel accompanied by the production of heat, or
heat and light. Complete combustion of a fuel is possible only in the presence of an
adequate supply of oxygen.
Oxygen (O2) is one of the most common elements on earth making up 20.9% of our air.
Rapid fuel oxidation results in large amounts of heat. Solid or liquid fuels must be changed
to a gas before they will burn. Usually heat is required to change liquids or solids into
gases. Fuel gases will burn in their normal state if enough air is present.
Most of the 79% of air (that is not oxygen) is nitrogen, with traces of other elements.
Nitrogen is considered to be a temperature reducing dilutant that must be present to obtain
the oxygen required for combustion.
Nitrogen reduces combustion efficiency by absorbing heat from the combustion of fuels
and diluting the flue gases. This reduces the heat available for transfer through the heat
exchange surfaces. It also increases the volume of combustion by-products, which then
have to travel through the heat exchanger and up the stack faster to allow the introduction
of additional fuel air mixture.
This nitrogen also can combine with oxygen (particularly at high flame temperatures) to
produce oxides of nitrogen (NOx), which are toxic pollutants. Carbon, hydrogen and
sulphur in the fuel combine with oxygen in the air to form carbon dioxide, water vapour and
sulphur dioxide, releasing 8084 kcals, 28922 kcals & 2224 kcals of heat respectively.
Under certain conditions, Carbon may also combine with Oxygen to form Carbon
Monoxide, which results in the release of a smaller quantity of heat (2430 kcals/kg of
carbon) Carbon burned to CO2 will produce more heat per pound of fuel than when CO or
smoke are produced.
C + O2 → CO2 + 8084 kCals/kg of Carbon
2C + O2 → 2CO + 2430 kCals/kg of Carbon
2H2 + O2 → 2H2O + 28,922 kCals/kg of Hydrogen
S + O2 → SO2 + 2,224 kCals/kg of Sulphur
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 18 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
Each kilogram of CO formed means a loss of 5654 kCal of heat.
3 T’s of Combustion
The objective of good combustion is to release all of the heat in the fuel. This is
accomplished by controlling the "three T's" of combustion which are (1) Temperature high
enough to ignite and maintain ignition of the fuel, (2) Turbulence or intimate mixing of the
fuel and oxygen, and (3) Time sufficient for complete combustion.
Commonly used fuels like natural gas and propane generally consist of carbon and
hydrogen. Water vapor is a by-product of burning hydrogen. This robs heat from the flue
gases, which would otherwise be available for more heat transfer.
Natural gas contains more hydrogen and less carbon per kg than fuel oils and as such
produces more water vapor. Consequently, more heat will be carried away by exhaust
while firing natural gas. Too much, or too little fuel with the available combustion air may
potentially result in unburned fuel and carbon monoxide generation. A very specific amount
of O2 is needed for perfect combustion and some additional (excess) air is required for
ensuring good combustion. However, too much excess air will result in heat and efficiency
losses.
Not all of the heat in the fuel are converted to heat and absorbed by the steam generation
equipment.
Usually all of the hydrogen in the fuel is burned and most boiler fuels, allowable with
today's air pollution standards, contain little or no sulphur. So the main challenge in
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 19 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
combustion efficiency is directed toward unburned carbon (in the ash or incompletely
burned gas), which forms CO instead of CO2.
Major Factors affecting Combustion Efficiency are
Stack loss
• It is the sensible heat lost through the chimney. It depends on the excess oxygen in
the flue gas and the stack temperature at the boiler outlet.
• It occurs due to variations in the air to fuel ratio over the complete boiler operating
range
Enthalpy loss
• It is the heat carried away by the water vapour in the flue gas.
• As it depends upon the fuel composition the combustion equipment cannot control
this loss unless testing of fuel is done on regular basis.
Un-burnt loss
• It is caused by insufficient air supplied during combustion or improper air and fuel
distribution in furnace .It is calculated by measuring carbon monoxide and carbon
dioxide in the flue gas.
Radiation loss
• It is the heat lost through surface of the boiler.
• It depends on boiler insulation, loading pattern, boiler size and compactness.
• A higher loading pattern results in a lower radiation loss.
As per the standard the oxygen percentage in boiler stack (with NG) should be 1.0 – 2.5%.
As observed from the flue gas analysis oxygen in boilers stack varies considerably from 5.2
to 6.8%.
It was understood from GSK that the boiler maintenance is subcontracted to a local vendor;
presently they check the stack oxygen once every month however burner tuning is not
done. It is recommended to tune the burner continuously so as to maintain correct O2
parameter (3%, as burner is old) in boiler stack.
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 20 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
Below graph explain variation of boiler efficiency with change in stack oxygen
Recommended Optimization
It is recommended to tune boiler regularly and maintain boiler stack oxygen 2.5 – 3.5%.
Note: As per good engineering practice oxygen percentage in stack for NG fired boiler
should be between 1 to 2.5% refers above graph; however the installed boilers are 20
years old. Burners are also of old technology, achieving 1 – 2.5% stack oxygen with these
burners will be difficult.
Estimated Benefit
Maintaining correct oxygen in boiler stack efficiency can be improved by 1%. Estimated
monetary savings are 1726 $ annually. The savings are calculated based on 2011 annual
steam generation and the respective calculated efficiencies.
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 21 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
Details of calculations
Present annual fuel consumption 735908 Nm3/annum
Rise in boiler efficiency 1.31 %
Net rise in efficiency 1.05 %
Reduction in fuel consumption 7691 Nm3/annum
Estimated annual monetary savings 1726 $/annum
Annual estimated energy saving 298 GJ/annum
82679 kW/annum
Note: Since oxygen in the stack will be maintained by manually check 80% net rise is considered for
calculating savings.
The CO2 emissions reduction by optimizing combustion is 15.1 ton/year
Estimated Investment and Payback
The investment is estimated to be 2500 $ it includes:
� Portable handheld flue gas analyser
� Service charges for boiler tuning every 30 – 45 day
The payback period for these investments would be 1.4 years
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 22 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
3.3 Optimisation Project N°3:
Optimize boiler blowdown maintain correct boiler blowdown water parameters
Current System Description and Observed Deficiency
Currently soft water and plant returned condensate is used as boiler feed water. During
audit boiler water analysis was done, analysis report is as follows.
Boiler blowdown water average TDS variation for last six month. (Data is taken form
Hydroflow record)
It was observed that boiler blowdown water TDS is maintained less than 1000 ppm.
Estimated present boiler blowdown percentage is calculated as 3.5% which is high
compared to industry norms.
Boiler Water Feed Water
TDS ppm 890 30
pH 11.34 7.69
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 23 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
The raw water TDS entering softener plant is measured as 40 - 50 ppm. This water is then
mixed with plant returned condensate collected in condensate tank pumped to the boiler
drum. During the audit, feed water temperature at feed water tank is measured as 85˚C.
Presently conductivity based automatic blowdown controller is installed on both boiler
bottom blowdown valve. During the audit, automatic blowdown system was in operation
and blowdown was given based on drum water conductivity.
The boiler drum water sample was checked and conductivity was maintained in a range of
1200 - 1500 µS/cm.
Technical Discussion
Even with the best pre-treatment programs, boiler feed water contains some degree of
impurities such as suspended and dissolved solids. As water evaporates, these impurities
are left behind and accumulate inside the boiler. The increasing concentration of dissolved
solids leads to carryover of boiler water into the steam, causing damage to piping, steam
traps and even process equipment. The increasing concentration of suspended solids
forms sludge, which impairs boiler efficiency and heat transfer capability.
However maintaining boiler drum TDS lower then Maximum permissible value increases
blowdown loss as hot boiler water is drained off
To avoid boiler problems, water must be periodically discharged or “blowdown” from the
boiler to control the concentrations of suspended and total dissolved solids in the boiler
water. Bottom blowdown is performed periodically to remove sludge accumulated from the
bottom of the boiler.
The importance of boiler blowdown is often overlooked. If the blowdown rate is too high,
energy (water, fuel, chemicals) is wasted. If high concentrations are maintained, (too low
blowdown) it may lead to scaling, reduced efficiency and to water carryover into the steam
compromising its quality (wet steam). The blow down rate is calculated with the following
formula:
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 24 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
% Blowdown = C Feedwater
(C Boiler – C Feedwater)
Where
CFeedwater= the measured concentration of the selected chemical in the feed water
(Conductivity, TDS, Alkalinity, Chlorine)
CBoiler = the measured concentration of the same chemical in the boiler
Note that the feed water concentration depends on the make-up water quality and the
condensate return ratio.
The ASME guidelines "Consensus on Operating Practices for the Control of Feed water
and Boiler Water Quality in Modern Industrial Boilers," shown in the tables below, are
frequently used for establishing optimum blow down rate.
Water Chemistry for Water tube Boilers - ASME Guidelines
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 25 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
For installed water tube boiler as per boiler manual boiler blowdown water TDS is required
to be maintained as 2000 ppm
Recommended Optimization
It is recommended to reset boiler blowdown control system set point to 2500 µS/cm.
Estimated Benefit
Maintaining correct boiler water TDS not only save energy but also help in preserving
precious water. Estimated monetary savings are 1103 $ annually. The savings are
calculated based on 2011 annual steam generation and the respective calculated
efficiencies.
Details of calculations
Present annual Steam generation 9750000 kg/annum
Present Boiler water TDS 890 ppm
Boiler feed water TDS 30 ppm
Present Blowdown 3.5 %
Present Blowdown 340116 kg/annum
Expected Boiler water TDS 1700 ppm
Boiler feed water TDS 30 ppm
Expected Blowdown 1.8 %
Expected Blowdown 175150 kg/annum
Reduction in Blowdown quantity 164967 kg/annum
Reduction in fuel consumption 3595 Nm3/annum
Annual estimated energy saving 139 GJ/annum
38644 kW/annum
Annual estimated water saving 165 m3/annum
Estimated annual monetary savings 1103 $/annum
The CO2 emissions reduction by optimizing blowdown is 7.0 ton/year
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 26 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
Estimated Investment and Payback
The investment is estimated to be 1000 $ it includes:
� Service charges for resetting blowdown control system
The payback period for these investments would be 0.9 year
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 27 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
3.4 Optimisation Project N°4:
Recover heat from boiler stack to pre-heat boiler feed water
Current System Description and Observed Deficiency
There are two boilers of capacity 3.2TPH each installed in the plant. Both boilers are more
than 20 year old. During study it was observed that two boilers were operated continuously
to cater the plant steam demand. The average plant steam load was measured as 1.1 TPH
with peak steam demand of 4.1 TPH using existing installed steam flow meter. Boiler
steam pressure is maintained at 900 kpa g. Burner modulates according to plant steam
load variation to maintain the drum steam pressure.
During the study flue gas analysis was conducted for all boilers to check excess air level
for combustion. Results are as below
Boiler – B1 (Working) 1 2 3 4 5 6 7 8 9 10 Avg
O2 % 6.6 6.6 6.5 6.8 6.8 6.4 6.4 6.1 6.7 6.7 6.63
CO2 % 8.64 8.64 8.7 8.52 8.52 8.76 8.76 8.94 8.58 8.58 8.62
CO ppm 0 0 1 1 1 0 0 0 0 1 0.67
Ex Air % 45.8 45.8 44.8 47.9 47.9 43.8 43.8 40.9 46.9 46.9 46.13
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 28 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
Boiler - B2 (Standby) 1 2 3 4 Avg
O2 % 5.7 5.3 5.2 5.3 5.38
CO2 % 9.18 9.42 9.48 9.42 9.38
CO ppm 0 1 0 5 1.50
Ex Air % 37.3 33.8 32.9 33.8 34.45
Also in order to understand the variation in boiler stack temperature variation, data logging
has been done for 6hrs duration. Results are as below
Presently no heat recovery units are installed on the boiler flue gas outlet to recover heat.
From above graph it was observed that boiler stack temperature varies considerably from
175 – 215°C. Higher the stack temperature, higher stack losses and lower boiler efficiency.
Technical Discussion
It is required to clear boiler (fire side) every six months, any soot deposit on the tube
surface retard the heat transfer increasing stack temperature and reducing boiler
efficiency.
During combustion, the carbon from the fuel combines with the oxygen and gets converted
in to CO2. This oxidation reaction is exothermic and liberates heat. This heat is absorbed
by the water on the water-side of the boiler, which is converted into steam. The gases of
this reaction are exhausted via the stack of the boiler at a temperature close to the
saturation temperature of the steam. The energy contained in these exhaust gases
accounts for a major part of the efficiency loss of the boiler. It is therefore important to
recover the maximum amount of energy out of these gases by using economizers. An
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 29 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
indirect heating type economizer consists of a coil heat exchanger, with finned or un-finned
tubes, placed in the exhaust gas flow as a section of the ductwork or stack. With this type
of economizer, the water flows through the tubes and absorbs the excess heat from the
flue gas. Typically, a de-aerated feed water is used for this purpose as a heat sink. The
flue gas outlet temperature can be brought down to as low as 120 ˚C (for NG)
“Economizer” is a shell and tube type heat exchanger (radiator) places in the flue gas path
of the boiler. Flue gases are passed on shell side and water is passed on tube side. The
control valves maintain and modulate water flow as per the boiler requirement. Bypass
interlock ensures safety in case of low stack temperature. Natural gas being clean and
cheap fuel, using natural gas for boiler can reduce operating cost substantially. Reduction
in operating cost will help in reducing production cost thereby increasing profit margins.
Below is the basic schematic for installation of economizer on boiler
Recommended Optimization
Armstrong recommends to installing economizer on boiler stack to recover heat to pre heat
boiler feed water.
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 30 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
Estimated Benefits
Installing economizer on boiler flue gas path will improve boiler efficiency by 3 – 4%
thereby reduce fuel consumption. Estimated monetary savings are 1103 $ annually the
savings are calculated based on 2011 average steam production and the respective
efficiencies.
Details of calculations
Present annual fuel consumption 735908 Nm3/annum
Present boiler house efficiency 82.91 %
Rise in boiler efficiency 4.1 %
Net rise in efficiency considered 3.7 %
Reduction in Fuel Consumption 27280 Nm3/annum
Estimated annual monetary savings 6123 $/annum
Annual estimated energy saving 1056 GJ/annum
293249 kW/annum
The CO2 emissions reduction by using economizer is 53.4 ton/year
Estimated Investment and Payback
The investment is estimated at 36000 $ It includes:
� Economizer (one unit)
� Single element drum level control (control valve on water line)
� Piping and accessories
� Erecting And Commissioning
The payback of this installation is expected to be 5.9 years
Note:
Due to long payback cost of only one economizer is considered for pay back calculation.
Here assumption is lead boiler will be boiler installed with economizer.
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 31 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
3.5 Optimisation Project N°5:
Avoid flooding of radiator coil for AHU- Block 1 and Non Sterilization packing area
Current system description and observed deficiency
During the audit, it was observed that the steam coils used in AHU of block 1 and non
sterilization packing area found flooded. It was observed that steam supply pressure for
these AHU coils is 3 barg. Control valve installed after pressure reducing station modulates
steam flow as to maintain process temperature of 20 – 35 ˚C. Currently orifice traps are
installed to drain the condensate from the coil.
During the audit it was observed that trap was failed under flooding condition and thus AHU
was not able to maintain required air temperature. Below are thermography image of the
radiator coil are
Block 1 AHU Coil
Left side Coil Middle Coil Right Side coil
Non Sterilization packing area coil
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 32 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
The condensate temperature is measured in the range of 15 - 20˚C.
Technical Discussion
As the process side temperature is very low the control valve at the inlet modulate. When
process reaches required temperature, it causes valve to close. The steam inside the
radiator coil condenses causing vacuum. Though vacuum breaker are installed to break
the vacuum, to remove the condensate a positive differential pressure is required. With
negative differential pressure or zero differential pressure the condensate cannot come out
of the coil and cause temporary water logged condition. The condition is referred as “Stall
condition”. The condensate get sub cooled releasing CO2 thus causing corrosion and
leakages in condensate lines. Also two different temperature zones in heat exchanger
cause heat exchange to buckle causing steam and condensate leakage.
Below is the schematic for installing pumping trap for AHU coil
Recommended Optimization
Armstrong recommends installing pumping traps for AHU coil application where process
temperature is below 90°C.
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 33 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
Estimated Benefits
Installation of pumping trap will help in avoiding stall phenomenon for coil resulting better
condensate evacuation form the coil thus better process temperature control. Such benefits
cannot be estimated in monetary value however better process parameter will result in
huge intangible savings.
Estimated Investment and Payback
The investment is estimated as 15000 $ It includes:
� Double duty trap (5 units)
� Piping, Insulation, Erecting and Commissioning
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 34 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
3.6 Optimisation Project N°6:
Recover flash steam form BFS plant to heat Clarifier hot water
Current System Description and Observed Deficiency
In GSK, BFS plant is one of the major consumers of steam. Steam is cosumed in pure
steam generator at 3.0 barg, Distillation column at 7 barg and WFI PHE at 4 barg.
Condensate from all these equipmets is collected in a common tank located near clarifier.
The liquid condensate is pumped back to boiler feed
water tank and generated flash steam is vented to
atmosphere.
Steam load of these equipment is estimated as below
Pure Steam Generator – 950 kg/h
Distillation Colum – 250 kg/h
WFI PHE – 200 kg/h
Maximum flash steam generated is estimated as 65
kg/h
Technical Discussion
When steam heats the process liquid, around 75% of its energy is transferred to process
and steam condenses. Balance 25 % energy is held by the condensed water. The
condensate is distilled water, having almost zero TDS. Condensate when discharged
through steam trap from a higher to a lower pressure. Certain amount of condensate re-
evaporates, and is referred to a Flash Steam.
The proportion that evaporates varies according to the level of pressure reduction between
the ‘steam’ and ‘condensate’.
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 35 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
About half of the energy mentioned above is lost through flash steam if it is not recovered.
Flash Steam recovery is therefore an essential part of achieving an energy efficient
system.
Advantage of Recovering Flash Steam
� Flash Steam has high heat content.
� Using flash steam in heating feed water de-aerator or Hot water system will reduce live
steam injection.
� Conserve energy as well as precious water.
Recommended Optimization
Armstrong recommends using this flash steam to preheat water in clarifier using steam
coil. Since clarifier is located next to condensate tank the piping required is minimum.
Estimated Benefits
By recovering flash steam for hot water generation will save $ 5076 annually. The savings
are calculated based on 2011 average steam production and the respective efficiencies.
Approximate Amount of Flash Steam
in Condensate
Condensate
85%
Flash Steam
15%
Approximate Amount of Flash Steam
in Condensate
Condensate
85%
Flash Steam
15%
Approximate amount of Energy in Flash
Steam & Condensate
Flash Steam
50%
Condensate
50%
Approximate amount of Energy in Flash
Steam & Condensate
Flash Steam
50%
Condensate
50%
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 36 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
Details of calculations
Average flash steam loss from condensate tank
in BFS plant
35 kg/h
Estimated fuel Saving 2.3 Nm3/h
Estimated annual monetary savings 5076 $/annum
Annual estimated energy saving 780 GJ/annum
216755 kWh/annum
Annual estimated water savings 306.6 m3/annum
The CO2 emissions reduction by using flash steam is eastimated as 39.5 ton/year
Estimated Investment and Payback
The investment is estimated at $ 15,000. It includes:
� Steam coil for Clarifier
� Piping with insulation, Installation and commissioning
� Labour Costs
The payback of this installation is expected to be 1.8 years
* Note - Investment considered budgetary, detail costing has to be taken form supplier
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 37 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
4.0 Complete check list of all verifications done during the audit
Potential Optimization Status Comments
Boiler House
Boiler Pressure Setting Appropriate
Feed water temperature to the
boiler
Okay Measured 85 °C
Stack Temperature Not okay, to be
improved by
installing
economizer
Economizer not installed, Stack
temperature measured as 175 –
215 °C. Required stack
temperature is 120 °C.
Combustion air temperature Okay
Oxygen in boiler stack Not okay, to be
improved by burner
tuning
Stack oxygen is measured in the
range of 5.2 – 6.8%. Required
stack oxygen is 1 – 2.5%
Boiler Sizing Okay
Blowdown rate Not okay, to be
improved by
resetting automatic
blowdown
controller
Present boiler average drum
TDS is 890 ppm. Recommended
is 2000 ppm
Deaerator Pressure Okay Atmospheric Deaerator
Boiler blow-down recovery Not installed Not economically feasible
Steam Distribution
External leaks of steam or
condensate from pipes, flanges,
etc.
Good No steam leakages identified in
the plant
Steam Quality Okay No corrosion, erosion problem
reported
Sizing of steam lines Oversized Changing to correct sizing not
economically possible
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 38 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
Potential Optimization Status Comments
Steam Pressure drop Good No pressure drop observed in
the plant
Steam pipe insulation Okay Surface temperature checked
and found with permissible limits
Pressure reduction Okay All pressure reducing station
found working satisfactory
Steam Consumption
Condensate draining and air
venting for AHU
Not okay, to be
improved
Most of the AHU coil found
flooded with condensate
Steam Trap Survey Okay Orifice traps installed
Condensate and flash steam Recovery
Condensate recovery Good All recoverable condensate form
the plant and header traps is
recovered back to boiler feed
water tank
Sizing of condensate return line Okay No water hammering observed
Flash steam recovery Not okay, to be
improved
Flash steam from BFS plant to
be recovered for Clarifier water
heating
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 39 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
5.0 Recommended complementary studies
The initial energy audit did not allow us to study in details all identified potential
optimisations. Here is the list of projects that are still to be developed in details to identify
the best solution and allow its implementation.
5.1 Additional energy-saving optimisations
Heat recovery on compressor
Presently three 553.13 CFM (90kW) compressors are installed in the compressor house.
Both compressors are provided with VSD’s. One compressure is operated continuously to
cator plant air requirement. Average loading of the comperssure is 60 - 80% based on
plant load. During the audit the compressor power was measured form installed power
meter. The monthy average power consumption for the compressor is measured as 77.08
kW. The compressor is not provided with heat recovery unit, heat of compression is
dissipated to cooling tower. Currently plant is using refrigerent dryer to remove moisture
from compressed air.
As much as 80-93% of the electrical energy used by an industrial air compressor is
converted into heat. In many cases, a properly designed heat recovery unit can recover
anywhere from 50- 90% of this available thermal energy and put it to useful work heating
air or water. Oil-free rotary screw compressors offer a much better opportunity for heat
recovery. As typical with all compressors, the input electrical energy is converted into heat.
Discharge temperatures from the low and high pressure elements can be over 148°C. This
heat appears at the low-pressure and high-pressure compression elements, intercooler
and aftercooler.
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 40 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
Energy Recovery Opportunity
1. HOC dryer can be used to dry compressed air inplace of exisiting refrigerent dryer.
Energy Conservation by Heat of Compression type compressed air dryer is a
breakthrough in compressed air drying technology. The hot air from the oil-free air
Compressor at 120°C or higher temp, is used directly for regeneration of the desiccant
bed in the compressed air dryer. After regeneration, this air is cooled down to 40°C in
the water cooled after cooler and then it is dried in second tower. Thus the use of
heaters is eliminated. For eg. in the 6 + 6 Hrs. Cycle the hot air is fed for regeneration
of desiccant bed for 4 Hrs. and for balance 2 Hr. a changeover takes place where the
air is first cooled in an after cooler, then dried and before going to the outlet, cools the
regenerated desiccant bed, thus bringing it down to ambient temperature. This cycle is
reversed for the next 6 Hrs. where the Adsorber drying the air in the previous cycle
goes for regeneration and vice versa.
There is considerable power saving in these type of Compressed Air Dryers and the
dew point is also better than the Refrigerated type of Compressed Air Dryers.
Main Advantage of Heat of Compression Type Compressed air dryer is the energy
conservation and heat recovery achieved which is being wasted in After cooler in the
conventional air dryers is now used to reactivate the desiccant.
Optimization
Armstrong recommends to eveluate this opportunity with original HOC dryer
manufacturer.
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 41 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
6.0 Conclusions and Recommended Next Steps
The Steam and Condensate Engineering Audit has defined a total potential of $ 16 093
savings that are summarized in the following table.
Sr.
No Description
Energy
(GJ/Year)
Fuel
(kWh/year)
Water
(KL/Year)
Financial
Savings
($./annum)
CO2
Emission.
Reduction
(Ton/Year)
1
Optimization N˚1
Optimize boiler operation, improve
boiler efficiency by better boiler
capacity utilization
356 98 885 -- 2 065 18.0
2
Optimization N˚2
Improve system efficiency by
optimizing boiler combustion ,
maintain correct oxygen in boiler
stack
298 82 679 -- 1 726 15.1
3
Optimization N˚3
Optimize boiler blowdown maintain correct boiler blowdown water parameters
139 38 644 165 1 103 7.0
4
Optimization N˚4
Recover heat from boiler stack to
pre-heat boiler feed water
1056 293 249 -- 6 123 53.4
5
Optimization N˚5
Avoid flooding of radiator coil for
AHU- Block 1 and Non Sterilization
packing area
System
benefits -- -- -- --
6
Optimization N˚6
Recover flash steam form BFS plant
to heat Clarifier hot water
780 216 755 306 5 076 39.5
The savings only include utilities savings. Maintenance, safety and process optimizations are not
represented in those numbers. Armstrong would be glad to prepare a proposal for their
implementation. The other projects will need a step of further engineering to define the exact
solution and refine the investments in order to be able to provide a turnkey proposal.
STEAM AND CONDENSATE AUDIT
90181-AUS-BOR
GlaxoSmithKline, Boronia, Australia Date: 27/07/2012
Page 42 of 42
To the attention: Mr. Phillip Osborne Established by
S. Raikar
Confidentiality Notice
This engineering audit report has been submitted to M/s. GSK Boronia, Australia in confidence
and it contains trade secrets, as well as privileged information, and/or proprietary work product of
Armstrong International Pvt. Ltd. (AIPL), In consideration of the receipt of this report and the
information and data herein, Recipient agrees that it will use this document and the information
contained herein only for internal use and only for the purpose of evaluating a business transaction
with Armstrong Recipient agrees that it will not disclose this report or any part thereof to any third
parties and Recipient may only disclose this document to those employees involved in the
evaluation of a business transaction with AIPL, on a need basis. Recipient may make only those
copies needed for such internal review. Upon conclusion of business discussions, this document
and all copies shall be returned to AIPL upon its or their request.