+ All Categories
Home > Law > Hard Hat Forum case update April 2015

Hard Hat Forum case update April 2015

Date post: 15-Jul-2015
Category:
Upload: dentons
View: 232 times
Download: 2 times
Share this document with a friend
Popular Tags:
41
Hard Hat Forum Caselaw Update April 2, 2015 Dentons Canada LLP Stephen Coyle, Partner 604-443-7148 [email protected] Don Smith, Counsel 604-648-6551 [email protected] Karen Martin, Partner 604-691-6455 [email protected]
Transcript

Hard Hat Forum – Caselaw UpdateApril 2, 2015

Dentons Canada LLP

Stephen Coyle, Partner

604-443-7148

[email protected]

Don Smith, Counsel

604-648-6551

[email protected]

Karen Martin, Partner

604-691-6455

[email protected]

Procurement Cases

2

Todd Brothers Contracting Ltd. v. Algonquin

Highlands (Township) 2015 ONSC

3

• Township issued tender for airport runway construction

• Todd was lowest bidder, and agreed to extend bid acceptance date to

allow environmental assessment, and then agreed to phasing of the

project to allow first part to proceed in meantime

• Todd signed “compensation waiver acknowledgement” that it would:

• not seek any compensation … in the event that the Township cannot proceed

to any of the phases as a result of matters beyond the control of the Township

… or delays resulting from the review being completed by the CEAA… any

other public issues/concerns or the withdrawal of funding from applicable

sources

• Council passed Resolution accepting bid subject to CEAA

• Part 1 proceeded. Then a new Council cancelled the rest of the Project

Todd Brothers cont’d

4

• Todd sued, asserting Township’s failure to proceed was a breach of

Contract A

• Court found :

• Contract A arose when Todd submitted its compliant bid

• Contract B arose when Council accepted bid (even though acceptance not

communicated to Todd)

• Waiver provision barred Todd’s claim, as the wording covered those particular

circumstances

• Waiver of claims signed by bidder during a tender was enforced to defeat

contractor’s claim

Newfoundland and Labrador v. Marine Contractors,

2014, NLTD(G)

5

• Original tender form was revised by addendum

• IBs said “Tenders not submitted on Tender Form provided will not be

considered”

• Low bidder submitted bid on original tender form

• Owner sought declaration that low bid was compliant before award

• Court found bid was compliant. Test for compliance is whether bid is

responsive to the substantive requirements of the tender – the key

question is whether there has been substantial compliance with the

tender call. Tenders should not be rejected for a mere technical error

• Court concluded that all of the material information was included by the

bidder and its use of the original tender form did not prejudice or cause

unfairness to other bidders

Cobalt Construction Inc v. Kluane, 2014, YKSC

6

• Cobalt submitted lowest bid, but Owner awarded to its own development

corporation, who had failed to submit a bid bond until after closing

• Cobalt sued. Owner argued Cobalt’s bid was materially non-compliant,

so it had no Contract A and no claim, because it:

• failed to include a full list of its subcontractors as required by the tender

because did not list “Own Forces for the trades”

• failed to comply with tender requirement to make best efforts to invite local

business to bid on subcontracts related to the work

• Court rejected Owner’s arguments and awarded lost profits to Cobalt

• Cobalt was not required to seek local bids for subcontract work it did not need

to subcontract, or to list Own Forces acting as trades when it had no “Own

Forces” acting as trades

Pomerleau v. Newfoundland & Labrador,

2014, Nfld SC

• Low bidder failed to complete Appendix D, calculation of separate price;

though information could have been gleaned from rest of bid

• IBs said “incomplete tenders will be rejected”

• No discretion clause allowing waiver of irregularities

• Owner rejected and low bidder sued

• Court agreed owner had obligation to reject

• Test was strict compliance on the wording of these tender documents

7

Rankin Construction v. Ontario, 2013, ONSC &

2014, ONCA

8

• Rankin submitted lowest bid. Tender documents provided a 10% price

reduction for domestically sourced steel. Rankin mistakenly believed H-

Piles were available domestically, and failed to declare them as imported

• Another bidder complained. Owner investigated, Rankin’s bid was

declared non-compliant. Contract was awarded to second lowest bidder

• Issue: Can the Owner investigate a bid in response to a call for tenders

or must it take the bids at face value?

• ONSC: Owner is not obligated to investigate (Double N), but that does

not mean it is not permitted to investigate

• ONSC: failure to disclose the correct declared value of imported steel

was a material non-compliance and so no contract A was formed

between Rankin and Owner

Rankin Construction cont’d

9

• ONCA: held that Contract A was formed, but that under Contract A,

owner could choose not to award to a non-compliant bidder

• Must consider language of tender to determine whether parties intended

contractual relations to arise on submission of a non-compliant bid.

Here, the language suggested Contract A arose, but gave owner rights to

not award in certain cases and to waive formalities in others

• Court said on the facts, the owner could have waived non-compliance

because this was an informality and maintained integrity because price

was lower; but it could chose not to in order to avoid litigation

• ONCA upholds Owner’s right (but no obligation) to investigate a bid, so

long as it is fair and consistent in assessment of bidders.

• Exclusion clause protected the Owner even if it breached the tender

terms (it might not only where there is Tercon aberrant behaviour)

Eastern Regional Integrated Health Authority v

Olympic Construction, 2014, NLCA

10

• Tender instructions required mandatory site visit, which only one bidder

attended (Redwood)

• Owner then invited two other contractors, including Olympic, which it

induced to submit a bid by issuing addenda changing the closing date

and adding a second site visit

• Addenda did not state that second site visit was mandatory, or that first

site visit was no longer mandatory

• Olympic submitted lowest bid. Redwood complained that Olympic failed

to attend the mandatory first site visit, and that its bid should be

disqualified. Owner disqualified Olympic

• Olympic sued

Eastern Regional cont’d

11

• Court held: Owner breached of duty of fairness – Owner did not play by

its own rules

• Owner made the rules by issuing the addendum which induced Olympic

to submit a bid to the Owner’s benefit, and then broke the rules by

insisting that the addendum had no effect on Contract A

• Court noted that low bidder did not complain when addenda issued

• While TJ had held that Owner had breached a “duty of good faith”, CA

clarified that in procurement, we are concerned with the duty of fairness ,

not a broader duty of good faith

Other Construction Law Cases

12

Shafazand v. Whitestone Management,

2014, BCSC

Illegality Doctrine

Facts

• Whitestone retained Shafazand as the general contractor pursuant to a

fixed price contract to construct a single-family dwelling

• Both parties agreed to conceal from the City of Vancouver an illegal

basement suite in the plans that the parties submitted to the City

• Shafazand sued for extras and Whitestone denied that payment was

owed and counterclaimed for the amounts that it incurred to complete the

work

13

Shafazand cont’d

• The court found contractor had performed extra work and that the

developer had incurred extras to complete the work

• However, the court dismissed both claims on public policy grounds and

denied the developer judgment for the balance

• It found that because the developer set out to deliberately deceive the

municipal authorities and was involved in the construction of an illegal

suite, it would be against public policy to allow the developer to be

rewarded for such conduct

14

Shafazand cont’d

Application

• Business practices which are deceptive (for instance knowingly

undertaken against municipal building regulations) may negate recovery

on legitimate claims

15

Haebler Construction (2003) Inc. v. Condura Forming

Ltd., 2014, BCSC

Swearing a False Statutory Declaration

Facts

• The plaintiff contractor Haebler completed certain concrete formwork

after the defendant subcontractor Condura that it had engaged failed to

complete the work

• Haebler claimed for its cost of completing the work less the original

subcontract price

• Haebler also sought damages for allegedly fraudulent or negligent

misrepresentations that subcontractor’s principal made in a sworn

statutory declaration concerning payment of accounts for sub-trades:

• “all claims for wages and materials due and payable in respect of the building

to date have been fully paid and satisfied”

16

Haebler Construction cont’d

• Court rejected the misrepresentation claim on the basis that given the

principal’s limited understanding of the significance of the statutory

declarations, it was unclear that he knew his representations were false

• Court also emphasized that Haebler had continued to deal with the

subcontractor even after it became aware of the subcontractor’s

problems with its creditors, meaning there could not have been ongoing

reliance on the principal’s statements

• Finally, any reliance caused no loss as Haebler was fully compensated

for any extra expense by the Owner

17

Haebler Construction cont’d

Application

• Look beyond the Statutory Declaration to confirm that project funds are

properly flowing down the contractual claim

18

First Queensborough Shopping Centres v. Wales

McLelland Construction, 2014, BCSC

Facts

• During of the project the defendant owner had been late in paying

invoices, and interest accrued on unpaid amounts

• The fixed price DB contract contained the following waiver:

• “as of the date of the final certificate for payment, the [contractor] expressly

waives and releases the Owner from all claims against the Owner including

without limitation those that might arise from negligence or breach of contract

by the Owner except … those made in writing prior to the [Contractor’s]

application for final payment and still unsettled … ”

• Notwithstanding the waiver, the contractor successfully sued the owner

and the court awarded damages for the unpaid interest

19

First Queensborough cont’d

• In doing so, the Court found that the Waiver did not make “commercial

sense”, noting:

• Issuance of Certificate of Payment that would operate to expunge any debt the

Owner owed makes no commercial sense

• The Waiver did not intend to operate in the Owner’s favor to extinguish any

claim the DB had for amounts owing under the Contract, including interest

• Owner was contractually obliged to pay interest on amounts due and owing

(20 days after submission)

• Contract did not require DB to issue invoices for interest due

• The parties could not have intended that any outstanding balance the Owner

owed, which did not become due until 20 days after receiving the Certificate of

Payment, was vitiated

• Objectively, the parties intended that interest would have continued to accrue

until the full balance was paid

20

First Queensborough cont’d

• There is no commercial or sound reason that justifies construing the Contract to

deny the DB interest on amounts the Owner had not paid at the date of the

Payment Certificate

• The Contract required the Owner to pay the full Contract price at the end of the

Contract; this amount should rationally include the accrued interest and any

amounts that became due after the Final Payment Certificate was issued

21

Wood Buffalo Housing & Development Corporation v.

Flett, 2014, ABQB

Facts

• Fire occurred in 2007 in a multi-residential building owned by Wood

Buffalo. Certificate of Substantial Completion was issued in 2002

• Building had been designed and built by Liam Construction pursuant to a

CCA-14 Design Build contract

• Wood Buffalo commenced action against Liam, other subs and design

consultants for alleged construction and design deficiencies

22

Wood Buffalo cont’d

• DB Team brought Application to dismiss claim based on the following

“Waiver”:

• “As of the date of the Final Certificate for Payment, the Owner expressly waives

and releases the Design – Builder, the Consultant, all other Consultants, all

Subcontractors, all Suppliers and their agents and employees from all claims

against them including without limitation those that might arise from the

negligence or breach of contract by the Design-Builder, the Consultants, all

other Consultants, all Subcontractors, and their agents and employees except

one or more of the following:

.1 those made in writing prior to the date of the Final Certificate for Payment and still unsettled;

.4 those made in writing within a period of two years from the date of Substantial Performance of

the work…

06/04/2015 23

Wood Buffalo cont’d

• No claim in writing was made by Wood Buffalo against the DB prior to the

date of the Final Certificate of Payment, nor was any claim in writing

made by Wood Buffalo within a period of two years from the date of

Substantial Performance of the work

06/04/2015 24

Wood Buffalo cont’d

• Court essentially found waiver enforceable by stating that it would not

have dismissed the Application for dismissal:

• Fundamental principle of law that party cannot release/waive claims it is

unaware of at signing, but this clause expressly included future claims “without

limitation”

• The requirement to make claims in writing prior to certain dates does not, when

viewed in the context of the entire clause, import a knowledge requirement

(Contract does not incorporate the principle of discoverability)

25

First Queensborough/ Wood Buffalo

Application

• ONLY TRUST IN LITIGATION COUNSEL AND NOT YOUR SOLICITOR

• WAIVERS/ RELEASES within contracts subject to uncertain judicial

interpretation

26

Stanley Paulus Architect Inc. v. Windhill Holdings

Ltd., 2014, BCSC

Facts

• Architect sought a declaration of builder’s lien for the preparation of plans

and other architectural services for a project that was never constructed

• Owner had terminated the architect on the basis that its services were

not provided in a timely manner, and retained other architects to

complete the design and other architectural services

• The court dismissed the architect’s claim, finding that without an

improvement, there was nothing for which a claim of lien could attach

27

Stanley Paulus cont’d

Application

• Architects and other design consultants have valid lien rights , but those

rights, if any, do not materialize until construction has commenced on the

improvement

28

Duty of Good Faith

29

Duty of Good Faith pre Bhasin

• Duty of good faith implied in commercial contracts in many jurisdictions:

• Quebec; US; much of Europe – i.e. Germany, Austria, France

• In Canada (outside Quebec), no general duty of good faith in

commercial contracts – UK, Australia are similar

• EXCEPTIONS

• Insurance contracts

• Franchise & employment contracts

• Tender contracts

• In exercising contractual discretion

• Express contract terms

30

Bhasin v. Hrynew, 2014 SCC

Facts

• Bhasin and Hrynew were competitors with an acrimonious relationship

• Hrynew made attempts to take over Bhasin's business, urged Can-Am to

force a merger

• Can-Am developed a restructuring plan that involved Hrynew subsuming

Bhasin's business

• Dealership contract between Can-Am and Bhasin at heart of dispute

• Three-year term

• Automatic renewal unless either party gave 6 months' written notice

• Included an entire agreement clause

31

Bhasin cont’d

• Regulator (AB Sec. Comm.) required Can-Am to appoint a single person

to monitor compliance across the province – Can-Am chose Hrynew

• Bhasin resisted Hrynew’s oversight

• Refused to allow Hrynew access to confidential business records

• Can-Am issued non-renewal notice to Bhasin under the agreement

• Bhasin lost his ESP dealership business and Hrynew hired much of

Bhasin's former salesforce

• Bhasin sued Can-Am for breach of contract, Hrynew for inducing breach

of contract and both for civil conspiracy

32

Bhasin – Duty of Honesty

• SCC established a general duty of honest contractual performance

“… parties must not lie or otherwise knowingly mislead each other about

matters directly linked to the performance of the contract. This does not

impose a duty of loyalty or of disclosure or require a party to forego

advantages flowing from the contract; it is a simple requirement not to lie or

mislead the other party about one's contractual performance.”

• General doctrine of contract law that imposes a minimum standard of

behavior in every contract, not an implied term

• This means parties cannot contract out of the duty; but can modify and

'relax' it through express terms in contract so long as not manifestly

unreasonable and respects the core duty

33

Bhasin – Duty of Honesty cont’d

• The new duty of honest in contractual performance is NOT:

• a fiduciary duty or duty of loyalty (so not required to give up

contractual advantages, or look out for other party’s

interests)

• a duty to disclose material facts

• a duty in contract negotiations – just in performance

• to be used as a pretext for scrutinizing motives of other party

34

Bhasin – Court Findings

• SCC found that Can-Am had acted dishonestly with Bhasin

• The entire agreement clause not applicable as parties cannot contract

out of the duty of honest performance

• Bhasin awarded $87,000 to replace lost value of business

35

Bhasin – Implications

• More litigation! – relying on Quebec and US law

• Proactively address scope of duty in express terms in contract – e.g.

circumstances in which discretion will be exercised, or factors that will

be applied

• In any contract situation, including procurements, communications

cannot be actively misleading or deceptive

• Underlying context will inform the scope of the duty - so internal

communications relevant to motives may be examined

• Termination and exercise of discretion will attract particular attention

36

Bhasin - Implications re Preparing Draft Contracts

Preparing Draft Contracts to Accompany Tenders

• Clauses needed to designate standard of honest performance of

contractual obligations and provide some certainty for contract

administration and interpretation

• Parties may relax the requirement of honest performance by express

agreement, e.g. circumstances in which discretion will be exercised, or factors

that will be applied

• Standard used must (1) not be manifestly unreasonable and (2) respect the

core requirements of the duty.

37

Bhasin – Implications re Administration of Contracts

Implications for Administration of Construction Contracts

• Communications must not be actively misleading or deceptive

• Does not matter whether party making the communication intended for the

other party to rely on it

• Though underlying context will inform the scope of the duty - so internal

communications relevant to motives may be examined

• Documentation of process for arriving at discretionary decision and

exercising of contractual rights

• Duty of honesty may lead to challenges of discretionary decisions, which

cannot be made in an arbitrary manner under the duty of good faith

• Decision-makers should document the process through which a discretionary

decision was made to forestall any legal challenges

• Termination decisions will attract particular attention

38

Future Developments

39

Future Developments

• Revamping of Builders Lien Act

• Lobbying for prompt payment legislation

• J Cote v. Burnaby and related industry discussions – Claims history as a factor

in procurement decisions

• Ongoing bid rigging litigation in Ontario regarding federal computer services

contacts (follows on Envoy)

40

Thank you

Dentons Canada LLP

Stephen Coyle, Partner

604-443-7148

[email protected]

Don Smith, Counsel

604-648-6551

[email protected]

Karen Martin, Partner

604-691-6455

[email protected]


Recommended