Integrated Anaerobic Digester SystemProgram and RFP Overview
Clint FandrichRFP Seminar – University of Wisconsin-Oshkosh
February 1, 2017
Presentation Contents
• Introduction to the Program• Details of the Request for Proposals
(RFP)• Project Guidelines• Document Corrections and
Clarifications
1
Program Introduction
• OEI is housed at the Public Service Commission of Wisconsin (PSC)
• The Interagency Working Group is also comprised of the Department of Natural Resources (DNR) and the Department of Agriculture, Trade and Consumer Protection (DATCP)
2
OEI and the Interagency Group
Program Introduction
• Commissioned studies in early 2016
• The Interagency WG then worked on a plan and engaged stakeholders
• The PSC made $20 million available through Focus on Energy
• The RFP was crafted to address 3 primary challenges…
3
How did we arrive at the RFP?
RFP Project Details
• Biogas Energy Production and Utilization
• Water Treatment and Recovery• Nutrient Management
Improvements• Formation of consortia
• Customer Cost-Effectiveness
6
Evaluation Criteria
RFP Project Details
10
Evaluation Criteria
• There is a section in the RFP dedicated to Customer Cost-Effectiveness starting on pg. 25
RFP Project Details
• Biogas Energy• 50 points, 25 required
• Water Treatment• 50 points, 25 required
• Nutrient Management• 50 points, 25 required
• Customer Cost-Effectiveness & Focus Impact• 75 points
• System Design and Optimization• 25 points
• Project Location• 50 points, 20 required
• Capability of Vendor• 50 points, 25 required
• 350 points total, 235 min.15
Evaluation Criteria - Overview
Project Guidelines
• A proposed project must result in a reduction in demand of electricity and/or natural gas at a Focus-participating utility service territory• Questions about forming consortia
• A proposal can leverage existing AD infrastructure under certain circumstances• Increasing the output of a system• Reducing the parasitic load• Adding renewable cogeneration
16
Eligibility – pg. 9-12, 24
Project Guidelines
• Focus incentives act as a reimbursement of eligible costs (pg 2) after installation, operation and verification
• Reporting requirements• Reporting is for project progress, not
operations• Once the project has been evaluated and
verified as ‘operational’ by Focus staff, the reporting period and requirements end
• After the Date of Award and contracting, changes to the project scope could change the incentive amount
17
Payment and Reporting – pg. 5-8
Project Guidelines
• Cost-Effectiveness is:
Proposed annual kWh and/or kBTUproduced or offset
Eligible project costs
• Other cost-effectiveness considerations: Capital expense of water treatment technologies and annual operation and maintenance
• Project economics must include interconnection studies and costs, if the applicant is proposing electricity generation
18
Customer Cost-Effectiveness – pg. 25
Project Guidelines
• Utilization of the proposed system to meet Customer’s energy needs
• Optimization of engineering design• waste heat utilization/management, for example
• Reduction in total manure transport mileage OR reduced piping mileage
• System production aligns with peak demand schedule (if applicable)
• System reduces energy use by systems upstream or downstream of the project • Parasitic loads
• Use of off-farm substrates• Efficiency of pathogen removal• Treatment of waste streams to allow alternative
disposal methods
19
System Design and Opt – pg. 24
• Instead of “kBTU or Thermsproduced” it should say “kWh or Therms produced”.• Project eligibility: Must result in a
reduction in demand of electricity and/or natural gas in a Focus-participating utility service territory
22
Focus Incentive Levels – pg. 5
Corrections and Clarifications
• The statement “Total energy produced can exceed a customer’s annual demand” is true!• Applicants should provide relevant
utility data to demonstrate annual energy consumption before the proposed project is implemented
23
System Size – pg. 11
Corrections and Clarifications
• Soft deadline of December 31, 2018• This is a preferred completion date
by Program Administrators, but not a hard deadline for a project’s installation and verification
• Within 120 days of Date of Award, project managers will be expected to “Ramp-up Activities”• Ramp-up activities refer to the first step(s)
taken toward implementation of a renewable energy Project. Examples include issuing Purchase or Work Orders, filing for Building Permits, and soliciting bid proposals.
24
Project Deadlines
Corrections and Clarifications
• There are no requirements in the RFP for technologies proposed to be manufactured in Wisconsin or the US
• Evaluation will not consider the origin of the components of the proposed project
25
Made in Wisconsin
Corrections and Clarifications
• “Can the proposal be the initial steps of the so-called ‘Phoenix Project’?”• While the Interagency WG does not
explicitly endorse the findings of the study, applicants are welcome to use it as a tool in building their proposals
26
In Relation to Previous Studies
Corrections and Clarifications