8/3/2019 Lifting Sequence Boiler Steel Structure
1/18
PT. SEMEN TONASA INDONESIA
PROJECT
:
:
CONTRACTOR :
LOCATION : PART NO. :
DRAWING NO. :
SCALE :
:DATECLIENT
2 x 35 MW TONASA COAL FIRED POWER PLANT
PT. REKAYASA INDUSTRI
BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA
JULY 22, 2011
RIGGING PLAN
RIGGING ENGINEER SITE MANAGER
H GUNAWAN
PREPARED BY PT. GAKA KARYA ENGINEERING
DIMENSIONS IN MILLIMETERS
CONSTRUCTION MANAGER
APPROVED. BY
PT SEMEN TONASA
SITE MANAGERCONSTRUCTION MANAGER
S T
RIGGING DEPARTMENT
THINK SAFEDO SAFELY
SAFETY FIRST
G2001-HG-2.35-SS-1.1
1 : 1
/ 4
INSTALLATION STEEL STRUCTURE
01
8/3/2019 Lifting Sequence Boiler Steel Structure
2/18
PT. SEMEN TONASA INDONESIA
PROJECT
:
:
CONTRACTOR :
LOCATION : PART NO. :
DRAWING NO. :
SCALE :
:DATECLIENT
2 x 35 MW TONASA COAL FIRED POWER PLANT
PT. REKAYASA INDUSTRI
BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA
JULY 22, 2011
RIGGING PLAN
RIGGING ENGINEER SITE MANAGER
H GUNAWAN
PREPARED BY PT. GAKA KARYA ENGINEERING
DIMENSIONS IN MILLIMETERS
CONSTRUCTION MANAGER
APPROVED. BY
PT SEMEN TONASA
SITE MANAGERCONSTRUCTION MANAGER
S T
START
DATA MATERIAL1. DIMENSION
2. WEIGHT
RIGGING DEPARTMENTANALYZE AND PLANED ACTIVITY FOR
LIFTING AND ERECTION WORK
REFERENCE1. RIGGING BOOK
2. EQUIP. MANUAL3. B30.24-2003 Safety Standard
4. B30.21-2005 manually lever operated hoist5. Australian Standard, AS 3569--1989, Wire ropes6. Australian Standard, AS 2759--1985, Wire ropes
7. NAVFAC P-307, June 20038. Construction Industry Crane Safety Summit, 2009
NEED DUO CRANEYes
No
MONO CRANETAILING DESIGN
JOB SAFETY ANALISYS
Safe
Risk
FINISH
Final Inspection byGKE & REKIN
Prepare Final Report for ApprovaL
Handover
No
Yes
RIGGING PLAN
ACTION
CONTROL
G2001-HG-2.35-SS-1.1
1 : 1
/ 4
INSTALLATION STEEL STRUCTURE
01
8/3/2019 Lifting Sequence Boiler Steel Structure
3/18
RIGGING PROCEDURE
01. OBJECTIVERigging Study Steel Structure Component
02. SCOPE OF APPLICATIONRigging study is describe the guidelines and operating step of lifting Steel Structure Componentat Boiler 2 x 35 MW TONASA COAL FIRED POWER PLANT Project.
03. REFERENCE1. RIGGING BOOK
2. EQUIP. MANUAL
3. B30.24-2003 Safety Standard
4. Australian Standard, AS 3569--1989, Wire ropes
5. Australian Standard, AS 2759--1985, Wire ropes
04. EQUIPMENTNo Equipment Qty Capacities Remark
01 CRANE CRAWLER 1 unit 150 ton NEW
02 CRANE CRAWLER 1 unit 80 ton NEW
03 MOBILE CRANE 1 unit 45 ton NEW
04 LOW BAD 1 unit
05. RIGGING TOOLSNo Equipment Qty Capacities Remark
01 Wire Sling 1.5 inch x 5.500m 4 pcs 17.7 ton
02 Omega Type Shackle 4 pcs 10 ton
03 Chain BLock 4 pcs 10 ton
06. SAFETY REQUIREMENTSNo Equipment Qty
01 Safety Barricade Red White 75 mtr
02 Safety Cone 7 pcs
PT. SEMEN TONASA INDONESIA
PROJECT
:
:
CONTRACTOR :
LOCATION : PART NO. :
DRAWING NO. :
SCALE :
:DATECLIENT
2 x 35 MW TONASA COAL FIRED POWER PLANT
PT. REKAYASA INDUSTRI
BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA
JULY 22, 2011
RIGGING PLAN
RIGGING ENGINEER SITE MANAGER
H GUNAWAN
PREPARED BY PT. GAKA KARYA ENGINEERING
DIMENSIONS IN MILLIMETERS
CONSTRUCTION MANAGER
APPROVED. BY
PT SEMEN TONASA
SITE MANAGERCONSTRUCTION MANAGER
S T
G2001-HG-2.35-SS-1.1
1 : 1
/ 4
INSTALLATION STEEL STRUCTURE
01
8/3/2019 Lifting Sequence Boiler Steel Structure
4/18
START
Steel Structure Component INSTALLATION
Move Steel Structure Component by Trailer to Site
Moving Preparation by Rigger Crew
LAYDOWNACT
IVITY
Inspection Quality
by QC & SafetyNo
Yes
Connected all Sling
for LiftingPREPARINGACTIVITYINSITE
Lifting Steel Structure Component
Lifting Equipmentto Target Elevation
From ELev. 0.000To ELev. 47.800
Connected Steel Structure Component
to Column by Bolt
FINISH
Cleaning Steel Structure Component
PT. SEMEN TONASA INDONESIA
PROJECT
:
:
CONTRACTOR :
LOCATION : PART NO. :
DRAWING NO. :
SCALE :
:DATECLIENT
2 x 35 MW TONASA COAL FIRED POWER PLANT
PT. REKAYASA INDUSTRI
BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA
JULY 22, 2011
RIGGING PLAN
RIGGING ENGINEER SITE MANAGER
H GUNAWAN
PREPARED BY PT. GAKA KARYA ENGINEERING
DIMENSIONS IN MILLIMETERS
CONSTRUCTION MANAGER
APPROVED. BY
PT SEMEN TONASA
SITE MANAGERCONSTRUCTION MANAGER
S T
ERECTIONACTIVITY
Control Position of Steel Structure Component
to be Lifted by Rigging Supervisor
G2001-HG-2.35-SS-1.1
1 : 1
/ 4
INSTALLATION STEEL STRUCTURE
01
8/3/2019 Lifting Sequence Boiler Steel Structure
5/18
PT. SEMEN TONASA INDONESIA
PROJECT
:
:
CONTRACTOR :
LOCATION : PART NO. :
DRAWING NO. :
SCALE :
:DATECLIENT
2 x 35 MW TONASA COAL FIRED POWER PLANT
PT. REKAYASA INDUSTRI
BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA
JULY 22, 2011
RIGGING PLAN
RIGGING ENGINEER SITE MANAGER
H GUNAWAN
PREPARED BY PT. GAKA KARYA ENGINEERING
DIMENSIONS IN MILLIMETERS
CONSTRUCTION MANAGER
APPROVED. BY
PT SEMEN TONASA
SITE MANAGERCONSTRUCTION MANAGER
S T
G2001-HG-2.35-SS-1.1
1 : 500
/ 21
INSTALLATION FOR STEEL STRUCTURE
01
EQUIPMENT:CRANE CRWLER 1 UNIT
MOBILE CRANE 1 UNIT
LOW BAD 1 UNIT
TOOLS:OHMEGA SHACLE 4 UNIT
WIRE SLING 1 INCH x 8.8 METER 4 PCS
SECTION 1:1. Install firs column by rough terrain crane 45 ton.2. Install 2nd tier by crawler crane 80 ton.
3. Completed steel structure 1st & 2nd tier by
crawler crane 80 ton.
8/3/2019 Lifting Sequence Boiler Steel Structure
6/18
PT. SEMEN TONASA INDONESIA
PROJECT
:
:
CONTRACTOR :
LOCATION : PART NO. :
DRAWING NO. :
SCALE :
:DATECLIENT
2 x 35 MW TONASA COAL FIRED POWER PLANT
PT. REKAYASA INDUSTRI
BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA
JULY 22, 2011
RIGGING PLAN
RIGGING ENGINEER SITE MANAGER
H GUNAWAN
PREPARED BY PT. GAKA KARYA ENGINEERING
DIMENSIONS IN MILLIMETERS
CONSTRUCTION MANAGER
APPROVED. BY
PT SEMEN TONASA
SITE MANAGERCONSTRUCTION MANAGER
S T
G2001-HG-2.35-SS-1.1
1 : 500
/ 21
INSTALLATION FOR STEEL STRUCTURE
01
EQUIPMENT:CRANE CRWLER 1 UNIT
MOBILE CRANE 1 UNIT
LOW BAD 1 UNIT
TOOLS:OHMEGA SHACLE 4 UNIT
WIRE SLING 1 INCH x 8.8 METER 4 PCS
SECTION 1:1. Install firs column by rough terrain crane 45 ton.2. Install 2nd tier by crawler crane 80 ton.
3. Completed steel structure 1st & 2nd tier by
crawler crane 80 ton.
8/3/2019 Lifting Sequence Boiler Steel Structure
7/18
PT. SEMEN TONASA INDONESIA
PROJECT
:
:
CONTRACTOR :
LOCATION : PART NO. :
DRAWING NO. :
SCALE :
:DATECLIENT
2 x 35 MW TONASA COAL FIRED POWER PLANT
PT. REKAYASA INDUSTRI
BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA
JULY 22, 2011
RIGGING PLAN
RIGGING ENGINEER SITE MANAGER
H GUNAWAN
PREPARED BY PT. GAKA KARYA ENGINEERING
DIMENSIONS IN MILLIMETERS
CONSTRUCTION MANAGER
APPROVED. BY
PT SEMEN TONASA
SITE MANAGERCONSTRUCTION MANAGER
S T
G2001-HG-2.35-SS-1.1
1 : 500
/ 21
INSTALLATION FOR STEEL STRUCTURE
01
EQUIPMENT:CRANE CRWLER 1 UNIT
MOBILE CRANE 1 UNIT
LOW BAD 1 UNIT
TOOLS:OHMEGA SHACLE 4 UNIT
WIRE SLING 1 INCH x 8.8 METER 4 PCS
SECTION 2:1. Continue Install 2nd tier by crawler crane 80 ton.
2. Completed steel structure 2nd tier by crawler
crane 80 ton.
3. Preparing material for 3rd tier.
8/3/2019 Lifting Sequence Boiler Steel Structure
8/18
PT. SEMEN TONASA INDONESIA
PROJECT
:
:
CONTRACTOR :
LOCATION : PART NO. :
DRAWING NO. :
SCALE :
:DATECLIENT
2 x 35 MW TONASA COAL FIRED POWER PLANT
PT. REKAYASA INDUSTRI
BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA
JULY 22, 2011
RIGGING PLAN
RIGGING ENGINEER SITE MANAGER
H GUNAWAN
PREPARED BY PT. GAKA KARYA ENGINEERING
DIMENSIONS IN MILLIMETERS
CONSTRUCTION MANAGER
APPROVED. BY
PT SEMEN TONASA
SITE MANAGERCONSTRUCTION MANAGER
S T
G2001-HG-2.35-SS-1.1
1 : 500
/ 21
INSTALLATION FOR STEEL STRUCTURE
01
EQUIPMENT:CRANE CRWLER 1 UNIT
MOBILE CRANE 1 UNIT
LOW BAD 1 UNIT
TOOLS:OHMEGA SHACLE 4 UNIT
WIRE SLING 1 INCH x 8.8 METER 4 PCS
SECTION 2:1. Continue Install 2nd tier by crawler crane 80 ton.
2. Completed steel structure 2nd tier by crawler
crane 80 ton.
3. Preparing material for 3rd tier.
8/3/2019 Lifting Sequence Boiler Steel Structure
9/18
PT. SEMEN TONASA INDONESIA
PROJECT
:
:
CONTRACTOR :
LOCATION : PART NO. :
DRAWING NO. :
SCALE :
:DATECLIENT
2 x 35 MW TONASA COAL FIRED POWER PLANT
PT. REKAYASA INDUSTRI
BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA
JULY 22, 2011
RIGGING PLAN
RIGGING ENGINEER SITE MANAGER
H GUNAWAN
PREPARED BY PT. GAKA KARYA ENGINEERING
DIMENSIONS IN MILLIMETERS
CONSTRUCTION MANAGER
APPROVED. BY
PT SEMEN TONASA
SITE MANAGERCONSTRUCTION MANAGER
S T
G2001-HG-2.35-SS-1.1
1 : 500
/ 21
INSTALLATION FOR STEEL STRUCTURE
01
EQUIPMENT:CRANE CRWLER 1 UNIT
MOBILE CRANE 1 UNIT
LOW BAD 1 UNIT
TOOLS:OHMEGA SHACLE 4 UNIT
WIRE SLING 1 INCH x 8.8 METER 4 PCS
SECTION 3:1. Continue Install 2nd and 3rd tier by crawler
crane 80 ton.
2. Completed steel structure 2nd and 3rd tier by
crawler crane 80 ton.
3. Preparing material for 4th tier.
8/3/2019 Lifting Sequence Boiler Steel Structure
10/18
PT. SEMEN TONASA INDONESIA
PROJECT
:
:
CONTRACTOR :
LOCATION : PART NO. :
DRAWING NO. :
SCALE :
:DATECLIENT
2 x 35 MW TONASA COAL FIRED POWER PLANT
PT. REKAYASA INDUSTRI
BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA
JULY 22, 2011
RIGGING PLAN
RIGGING ENGINEER SITE MANAGER
H GUNAWAN
PREPARED BY PT. GAKA KARYA ENGINEERING
DIMENSIONS IN MILLIMETERS
CONSTRUCTION MANAGER
APPROVED. BY
PT SEMEN TONASA
SITE MANAGERCONSTRUCTION MANAGER
S T
G2001-HG-2.35-SS-1.1
1 : 500
/ 21
INSTALLATION FOR STEEL STRUCTURE
01
EQUIPMENT:CRANE CRWLER 1 UNIT
MOBILE CRANE 1 UNIT
LOW BAD 1 UNIT
TOOLS:OHMEGA SHACLE 4 UNIT
WIRE SLING 1 INCH x 8.8 METER 4 PCS
SECTION 3:1. Continue Install 2nd and 3rd tier by crawler
crane 80 ton.
2. Completed steel structure 2nd and 3rd tier by
crawler crane 80 ton.
3. Preparing material for 4th tier.
8/3/2019 Lifting Sequence Boiler Steel Structure
11/18
PT. SEMEN TONASA INDONESIA
PROJECT
:
:
CONTRACTOR :
LOCATION : PART NO. :
DRAWING NO. :
SCALE :
:DATECLIENT
2 x 35 MW TONASA COAL FIRED POWER PLANT
PT. REKAYASA INDUSTRI
BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA
JULY 22, 2011
RIGGING PLAN
RIGGING ENGINEER SITE MANAGER
H GUNAWAN
PREPARED BY PT. GAKA KARYA ENGINEERING
DIMENSIONS IN MILLIMETERS
CONSTRUCTION MANAGER
APPROVED. BY
PT SEMEN TONASA
SITE MANAGERCONSTRUCTION MANAGER
S T
G2001-HG-2.35-SS-1.1
1 : 500
/ 21
INSTALLATION FOR STEEL STRUCTURE
01
EQUIPMENT:CRANE CRWLER 1 UNIT
MOBILE CRANE 1 UNIT
LOW BAD 1 UNIT
TOOLS:OHMEGA SHACLE 4 UNIT
WIRE SLING 1 INCH x 8.8 METER 4 PCS
SECTION 4:1. Continue Install 3nd tier by crawler crane 80 ton.
2. Completed steel structure 3rd tier by crawler
crane 80 ton.
3. Continue Install 4th tier by crawler crane 150 ton.
8/3/2019 Lifting Sequence Boiler Steel Structure
12/18
PT. SEMEN TONASA INDONESIA
PROJECT
:
:
CONTRACTOR :
LOCATION : PART NO. :
DRAWING NO. :
SCALE :
:DATECLIENT
2 x 35 MW TONASA COAL FIRED POWER PLANT
PT. REKAYASA INDUSTRI
BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA
JULY 22, 2011
RIGGING PLAN
RIGGING ENGINEER SITE MANAGER
H GUNAWAN
PREPARED BY PT. GAKA KARYA ENGINEERING
DIMENSIONS IN MILLIMETERS
CONSTRUCTION MANAGER
APPROVED. BY
PT SEMEN TONASA
SITE MANAGERCONSTRUCTION MANAGER
S T
G2001-HG-2.35-SS-1.1
1 : 500
/ 21
INSTALLATION FOR STEEL STRUCTURE
01
EQUIPMENT:CRANE CRWLER 1 UNIT
MOBILE CRANE 1 UNIT
LOW BAD 1 UNIT
TOOLS:OHMEGA SHACLE 4 UNIT
WIRE SLING 1 INCH x 8.8 METER 4 PCS
SECTION 4:1. Continue Install 3nd tier by crawler crane 80 ton.
2. Completed steel structure 3rd tier by crawler
crane 80 ton.
3. Continue Install 4th tier by crawler crane 150 ton.
8/3/2019 Lifting Sequence Boiler Steel Structure
13/18
PT. SEMEN TONASA INDONESIA
PROJECT
:
:
CONTRACTOR :
LOCATION : PART NO. :
DRAWING NO. :
SCALE :
:DATECLIENT
2 x 35 MW TONASA COAL FIRED POWER PLANT
PT. REKAYASA INDUSTRI
BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA
JULY 22, 2011
RIGGING PLAN
RIGGING ENGINEER SITE MANAGER
H GUNAWAN
PREPARED BY PT. GAKA KARYA ENGINEERING
DIMENSIONS IN MILLIMETERS
CONSTRUCTION MANAGER
APPROVED. BY
PT SEMEN TONASA
SITE MANAGERCONSTRUCTION MANAGER
S T
G2001-HG-2.35-SS-1.1
1 : 500
/ 21
INSTALLATION FOR STEEL STRUCTURE
01
EQUIPMENT:CRANE CRWLER 1 UNIT
MOBILE CRANE 1 UNIT
LOW BAD 1 UNIT
TOOLS:OHMEGA SHACLE 4 UNIT
WIRE SLING 1 INCH x 8.8 METER 4 PCS
SECTION 5:1. Continue Install 4th tier by crawler crane 150 ton.
2. Completed steel structure 4th tier by crawler
crane 150 ton.
3. Continue Install 4th tier by crawler crane 150 ton.
4. Install main girder by crawler crane 150 ton.
8/3/2019 Lifting Sequence Boiler Steel Structure
14/18
PT. SEMEN TONASA INDONESIA
PROJECT
:
:
CONTRACTOR :
LOCATION : PART NO. :
DRAWING NO. :
SCALE :
:DATECLIENT
2 x 35 MW TONASA COAL FIRED POWER PLANT
PT. REKAYASA INDUSTRI
BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA
JULY 22, 2011
RIGGING PLAN
RIGGING ENGINEER SITE MANAGER
H GUNAWAN
PREPARED BY PT. GAKA KARYA ENGINEERING
DIMENSIONS IN MILLIMETERS
CONSTRUCTION MANAGER
APPROVED. BY
PT SEMEN TONASA
SITE MANAGERCONSTRUCTION MANAGER
S T
G2001-HG-2.35-SS-1.1
1 : 500
/ 21
INSTALLATION FOR STEEL STRUCTURE
01
EQUIPMENT:CRANE CRWLER 1 UNIT
MOBILE CRANE 1 UNIT
LOW BAD 1 UNIT
TOOLS:OHMEGA SHACLE 4 UNIT
WIRE SLING 1 INCH x 8.8 METER 4 PCS
SECTION 5:1. Continue Install 4th tier by crawler crane 150 ton.
2. Completed steel structure 4th tier by crawler
crane 150 ton.
3. Continue Install 4th tier by crawler crane 150 ton.
4. Install main girder by crawler crane 150 ton.
8/3/2019 Lifting Sequence Boiler Steel Structure
15/18
PT. SEMEN TONASA INDONESIA
PROJECT
:
:
CONTRACTOR :
LOCATION : PART NO. :
DRAWING NO. :
SCALE :
:DATECLIENT
2 x 35 MW TONASA COAL FIRED POWER PLANT
PT. REKAYASA INDUSTRI
BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA
JULY 22, 2011
RIGGING PLAN
RIGGING ENGINEER SITE MANAGER
H GUNAWAN
PREPARED BY PT. GAKA KARYA ENGINEERING
DIMENSIONS IN MILLIMETERS
CONSTRUCTION MANAGER
APPROVED. BY
PT SEMEN TONASA
SITE MANAGERCONSTRUCTION MANAGER
S T
G2001-HG-2.35-SS-1.1
1 : 500
/ 21
INSTALLATION FOR STEEL STRUCTURE
01
EQUIPMENT:CRANE CRWLER 1 UNIT
MOBILE CRANE 1 UNIT
LOW BAD 1 UNIT
TOOLS:OHMEGA SHACLE 4 UNIT
WIRE SLING 1 INCH x 8.8 METER 4 PCS
SECTION 6:1. Completed steel structure 4th tier by crawler
crane 150 ton.
2. Install CycLone by crawler crane 150 ton. Tiling by
Rough terrain crane 45 ton.
8/3/2019 Lifting Sequence Boiler Steel Structure
16/18
PT. SEMEN TONASA INDONESIA
PROJECT
:
:
CONTRACTOR :
LOCATION : PART NO. :
DRAWING NO. :
SCALE :
:DATECLIENT
2 x 35 MW TONASA COAL FIRED POWER PLANT
PT. REKAYASA INDUSTRI
BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA
JULY 22, 2011
RIGGING PLAN
RIGGING ENGINEER SITE MANAGER
H GUNAWAN
PREPARED BY PT. GAKA KARYA ENGINEERING
DIMENSIONS IN MILLIMETERS
CONSTRUCTION MANAGER
APPROVED. BY
PT SEMEN TONASA
SITE MANAGERCONSTRUCTION MANAGER
S T
G2001-HG-2.35-SS-1.1
1 : 500
/ 21
INSTALLATION FOR STEEL STRUCTURE
01
EQUIPMENT:CRANE CRWLER 1 UNIT
MOBILE CRANE 1 UNIT
LOW BAD 1 UNIT
TOOLS:OHMEGA SHACLE 4 UNIT
WIRE SLING 1 INCH x 8.8 METER 4 PCS
SECTION 6:1. Completed steel structure 4th tier by crawler
crane 150 ton.
2. Install CycLone by crawler crane 150 ton. Tiling by
Rough terrain crane 45 ton.
8/3/2019 Lifting Sequence Boiler Steel Structure
17/18
PT. SEMEN TONASA INDONESIA
PROJECT
:
:
CONTRACTOR :
LOCATION : PART NO. :
DRAWING NO. :
SCALE :
:DATECLIENT
2 x 35 MW TONASA COAL FIRED POWER PLANT
PT. REKAYASA INDUSTRI
BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA
JULY 22, 2011
RIGGING PLAN
RIGGING ENGINEER SITE MANAGER
H GUNAWAN
PREPARED BY PT. GAKA KARYA ENGINEERING
DIMENSIONS IN MILLIMETERS
CONSTRUCTION MANAGER
APPROVED. BY
PT SEMEN TONASA
SITE MANAGERCONSTRUCTION MANAGER
S T
G2001-HG-2.35-SS-1.1
1 : 550
/ 21
INSTALLATION FOR STEEL STRUCTURE
01
EQUIPMENT:CRANE CRWLER 1 UNIT
MOBILE CRANE 1 UNIT
LOW BAD 1 UNIT
TOOLS:OHMEGA SHACLE 4 UNIT
WIRE SLING 1 INCH x 8.8 METER 4 PCS
SECTION 7:1. Completed install CycLone by crawler crane 150 ton.
Tiling by Rough terrain crane 45 ton.
2. Completed installation by crawler crane 150 ton and
Rough terrain crane 45 ton.
3. Preparing for steam drum lifting.
8/3/2019 Lifting Sequence Boiler Steel Structure
18/18
PT. SEMEN TONASA INDONESIA
PROJECT
:
:
CONTRACTOR :
LOCATION : PART NO. :
DRAWING NO. :
SCALE :
:DATECLIENT
2 x 35 MW TONASA COAL FIRED POWER PLANT
PT. REKAYASA INDUSTRI
BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA
JULY 22, 2011
RIGGING PLAN
RIGGING ENGINEER SITE MANAGER
H GUNAWAN
PREPARED BY PT. GAKA KARYA ENGINEERING
DIMENSIONS IN MILLIMETERS
CONSTRUCTION MANAGER
APPROVED. BY
PT SEMEN TONASA
SITE MANAGERCONSTRUCTION MANAGER
S T
G2001-HG-2.35-SS-1.1
1 : 550
/ 21
INSTALLATION FOR STEEL STRUCTURE
01
EQUIPMENT:CRANE CRWLER 1 UNIT
MOBILE CRANE 1 UNIT
LOW BAD 1 UNIT
TOOLS:OHMEGA SHACLE 4 UNIT
WIRE SLING 1 INCH x 8.8 METER 4 PCS
SECTION 7:1. Completed install CycLone by crawler crane 150 ton.
Tiling by Rough terrain crane 45 ton.
2. Completed installation by crawler crane 150 ton and
Rough terrain crane 45 ton.
3. Preparing for steam drum lifting.