Jose Chan
FAC Review- LTU-DUMP Installation Status & Schedule
11/11/081
LTU-Dump Installation Status&
Schedule
Jose Chan
FAC Review- LTU-DUMP Installation Status & Schedule
11/11/082
Linac Status and ScheduleInstallation Coordination
Installation TeamInstallation StatusScheduleSafetySummary
Jose Chan
FAC Review- LTU-DUMP Installation Status & Schedule
11/11/083
Installation TeamKathleen Ratcliffe LTU and E-Dump installation managerMike Zurawel Undulator installation managerPonce Rodriguez Cable installation managerRichard M. Boyce & Stuart Metcalfe installation coordination managersSupporting organizations
Building Inspection Office, Cable shop, Communications, Controls, Facility, LCLS CF, MFD and Purchasing Davis Bacon contractors: J D Collins Co., Harris Constructions, Palmer Electrics, TDN Electric, D.W. Nicholson and Rushford Contractions
Mechanical Engineers Carl Rago, Don Schafer, Eric Bong, Phil Cutino and Tim Montagne
Jose Chan
FAC Review- LTU-DUMP Installation Status & Schedule
11/11/084
Status: LTU Installation
June 2008 November 2008
Jose Chan
FAC Review- LTU-DUMP Installation Status & Schedule
11/11/085
Status: Undulator InstallationJune 2008
November 2008
Jose Chan
FAC Review- LTU-DUMP Installation Status & Schedule
11/11/086
Status : Dump InstallationNovember 2008
Jose Chan
FAC Review- LTU-DUMP Installation Status & Schedule
11/11/087
LTU-Dump Floor Settling
Jose Chan
FAC Review- LTU-DUMP Installation Status & Schedule
11/11/088
Undulator Temperature Monitoring
Jose Chan
FAC Review- LTU-DUMP Installation Status & Schedule
11/11/089
Undulator Temperature Monitoring
Fan Off
Jose Chan
FAC Review- LTU-DUMP Installation Status & Schedule
11/11/0810
Status: What Have Not Been Installed
LTUSingle Beam Dump and TDUND shielding150KG quadrupole electrical coversVacuum pump down section 82 (TDUND area)
Undulator HallUndulator beamline vacuum pump down5 ANL Beam Loss Monitors
DumpComplete interconnection of vacuum chambersSecure dump pit from personnel
Jose Chan
FAC Review- LTU-DUMP Installation Status & Schedule
11/11/0811
Installation Challenges and Issues
LTUBTM were just received from supplier for installationInstalling heavy pieces of marble shielding without overhead crane
Undulator During BFW checkout we found 5 units with broken carbon wire, these wire were replaced. Some Evac flanges leaked during installation, knife edges were inspected reworked at SLAC
DumpInstallation BYD magnet and chamber without overhead craneInterference between BYD magnet and chamber, solved by using smaller socket head screwVerification of BXPM magnet, Jim Turner developed a plan for this verificationMinor interference fit of supports that required modifications
Jose Chan
FAC Review- LTU-DUMP Installation Status & Schedule
11/11/0812
Schedule
LTU StatusMagnet Installation @95% (Davis Bacon) completeInstall Vacuum components (SLAC-MFD) completeTDUND, Single Beam Dump & Zero Degree Shielding in progressCable Installation (Davis Bacon) completeCheck Out in progress
UndulatorPedestal & Girder installation completeLeak Check & Pump Down in progressCable installation completeCheck Out in progressUndulator Magnet Installation 3/9/2009
E-DumpComplete Stand Installation (Davis Bacon) completeComplete Magnet Installation (Davis Bacon) completeInstall Dump Shielding (Davis Bacon) complete
Install Vacuum Components/drifts (SLAC-MFD) in progress Cable Installation (Davis Bacon) completeCheck Out in progress
Jose Chan
FAC Review- LTU-DUMP Installation Status & Schedule
11/11/0813
Installation Assurance & Safety
Tailgate meetings before every shift to discuss daily activities and any safety related issuesEveryone are safety trained before they are allowed to work in the construction areaEveryone are required to sign in and out of construction areaJob walk with contractors before start of each jobInstallation weekly meetingsInstituted Quality Control check list sign off for both components and post installationSafe Performance Observation walk (minimum once a week for managers)
Jose Chan
FAC Review- LTU-DUMP Installation Status & Schedule
11/11/0814
Safety Approval Documents
Statement of Work (SOW) – These documents are written by installation manager for Davis Bacon contractor and are submitted to Building Inspection Office, BIO, for approval. BIO requires 11 signatures for approvalDavis Bacon contractors are required to submit and approval of following documents:
Industrial Injury and Illness Prevention Plan (3 approval signatures)Site Specific Safety Plan (4 approval signatures)Job Safety Analysis (3 approval signatures)Rigging Plans (3 approval signatures)
Work Authorization Form (WAF) – this is approval for SLAC employee to work in installation site (8 approval signatures)
Jose Chan
FAC Review- LTU-DUMP Installation Status & Schedule
11/11/0815
Summary
Progress towards completion of 2008 installation is going well. Only few areas needed to complete in next two weeksBased on last three installations, 2008 installation was the longest and best organizedSuccessful collaboration with Argonne National Lab colleagues on Undulator Hall installationsPlans are in development to repair RFBM windows in an event they develop leaksPost E-beam installation:
Kathleen Ratcliffe will be supporting future installation managersMike Zurawel will be area manager for Undulator HallPhil Cutino and Don Schafer will be LTU-Dump area engineers