+ All Categories
Home > Documents > MONTHLY PROJECT REPORTS - Project Groundworkprojectgroundwork.org/downloads/l3... · MONTHLY...

MONTHLY PROJECT REPORTS - Project Groundworkprojectgroundwork.org/downloads/l3... · MONTHLY...

Date post: 16-Apr-2018
Category:
Upload: danghanh
View: 220 times
Download: 2 times
Share this document with a friend
13
MONTHLY PROJECT REPORTS As of June 30, 2016 Mill Creek Watershed Excluding Lower Mill Creek Partial Remedy (LMCPR) Projects
Transcript
Page 1: MONTHLY PROJECT REPORTS - Project Groundworkprojectgroundwork.org/downloads/l3... · MONTHLY PROJECT REPORTS . As of June 30, 2016 . Mill Creek Watershed . Excluding Lower Mill Creek

MONTHLY PROJECT REPORTS

As of June 30, 2016

Mill Creek Watershed

Excluding Lower Mill Creek Partial Remedy (LMCPR) Projects

Page 2: MONTHLY PROJECT REPORTS - Project Groundworkprojectgroundwork.org/downloads/l3... · MONTHLY PROJECT REPORTS . As of June 30, 2016 . Mill Creek Watershed . Excluding Lower Mill Creek

Monthly Project Reports Mill Creek Watershed Dashboard

Project Status as of June 30, 2016

Project Name Float (Least) to Milestone

Schedule Health Indicator

Change in Schedule Health Indicator from

Last Month

Current Budgeted Project Cost

Estimated Cost at Completion

Projected (Over-run) or

Under-run

Budget Health Indicator

Change in Budget Health Indicator from

Last Month

Daly Road to Compton Road 126 days Change $7,940,176 $7,842,896 $97,280 No change

Northside Upper Bundle 0 days No change $5,398,368 $5,145,764 $252,604 No change

Westwood Northern Bundle -100 days No change $7,643,979 $6,734,153 $909,826 No change

Mayhew and Leath Sewer Replacement N/A No change $689,075 $689,075 - No change

MCWWTP Plant Influent and Headworks Odor Control N/A No change $1,468,200 $1,468,200 --- No change

MCWWTP Septage Receiving Station Odor Control Improvements N/A No change $1,193,400 $1,193,400 --- No change

MCWWTP Service Water Reliability and Service Upgrade N/A No change $3,817,043 $3,820,302 ($3,259) No change

MCWWTP Solids Handling Improvements N/A No change $21,690,257 $21,570,925 $119,332 No change

Mt. Airy Forest Sewer Replacement N/A No change $6,974,655 $6,789,896 $184,759 No change

Sanitary Sewer Overflows 603 and 704 Improvements N/A No change $9,782,481 $8,313,925 $1,468,556 No change

MCWWTP Dewatering Polymer System Replacement N/A No change $6,677,900 $6,653,482 $24,418 No change

Page 3: MONTHLY PROJECT REPORTS - Project Groundworkprojectgroundwork.org/downloads/l3... · MONTHLY PROJECT REPORTS . As of June 30, 2016 . Mill Creek Watershed . Excluding Lower Mill Creek

Daly Road to Compton Road Project Status as of June 30, 2016

Project ID 10142020

Municipality Springfield Township

Basin Mill Creek

Project Phase Construction

Planner N/A

Project Manager Bill Lutz

Construction Manager Steve Jones

Construction Inspector Rob Apel

Design Consultant CH2M Hill

Contractor Cincinnati Tunnel Partners

Project Manager Daniel Anderson

Design Consultant Black & Veatch Corporation

Construction Manager Efrain Quinones

Construction Inspector Rick Holmes

Contractor Brackney, Inc.

Milestone Dates Float Status

PTI Submittal 12/31/2014 -- Met

Start Construction 12/31/2015 --- Met

Complete Construction 12/31/2016 126 days No delay

Current Activities and Accomplishments

The Contractor remobilized in May 2016 in coordination with the county road department. The Contractor has completed the new 30” line in Daly Road and is currently working at MH26A, 26B, and 26C. Look Ahead The Contractor will complete the laterals on personal properties. Restoration will complete as needed with seeding forecasted to start in the fall. Issues There are no issues at this time.

This project will replace the severely deteriorated Sanitary Sewer #161. Approximately 4,500 feet of new sewer will be constructed from the Daly Road CSO Treatment facility east of the intersection of Daly Road and Compton Road where it will discharge into an existing 30-inch-diameter sewer. Area residents will be less impacted by surcharging and flooding that occurs during wet weather. This project was classified as a “Phase 1” Wet Weather Improvement Plan project because it has the ability to reduce the volume of sanitary flow discharged from old sewers during wet weather events. All work associated with this project will be substantially complete by the Consent Order Milestone date of December 31, 2016 (Attachment 1A – Final WWIP).

Current Estimated Project Cost $7,842,896

Legislated Funds $7,940,176

Actual Cost To-Date $5,408,140

% Complete Current Estimated Project Cost 69%

Project Phase

Project Activities

Schedule for Completion

Actual Date of Completion

Planning & Design

Project Legislated

July 9, 2014 (Construction)

June 25, 2008 July 9, 2014

(Construction)

100% Planning October 2007 October 17, 2007

100% Design May 2014 May 29, 2014

Permitting (PTI Submittal) January 2010 Renewed

August 14, 2013

ROW Acquisition June 2014 April 30, 2014

Bidding & Construction

Bidding October 2014 October 29, 2014

Start Construction January 2015 January 5, 2015

Complete Construction August 2016

This project was legislated again in June 2008 after the scope was revised. For this reason, planning was performed before the legislation date shown.

Construction activities at manhole #28.

Page 4: MONTHLY PROJECT REPORTS - Project Groundworkprojectgroundwork.org/downloads/l3... · MONTHLY PROJECT REPORTS . As of June 30, 2016 . Mill Creek Watershed . Excluding Lower Mill Creek

Northside Upper Bundle Project Status as of June 30, 2016

Project IDs 10141080 and 10143220

Municipality Cincinnati (Clifton)

Basin Mill Creek

Project Phase Design

Current Activities and Accomplishments CSO 179 (10143220) Construction Legislation was appropriated December 16, 2015. The MOU with CDOTE was finalized.

Ludlow & Lafayette Parallel Sewer (10141080) The Professional Service Agreement to complete design was executed by the City Manager on April 12, 2016. The 90% Design Deliverable was received June 22, 2016.

Look Ahead CSO 179 (10143220) The project will advertise for construction bids in August 2016 once right of way issues are solved.

Ludlow & Lafayette Parallel Sewer (10141080)

ROW expected to take one year. Construction legislation will be requested in 2017. Issues CSO 179 (10143220) An agreement with the Mill Creek Conservancy District may be needed to cross the Mill Creek.

Ludlow & Lafayette Parallel Sewer (10141080)

The right-of-way group will negotiate the necessary agreements with the Parks Department to replace a storm sewer on their property once the final plans are received. There is no remaining float to complete the project.

Milestone Dates 10141080 10143220

PTI Submittal 12/31/2016 MET MET

Start Construction 12/31/2017 0 days 396 days

Complete Construction 12/31/2018 0 days 459 days

This

Bundle Phase

Bundle Activities

Schedule

Ludlow & Lafayette 10141080

CSO 179 10143220

Planning & Design

Project Legislated March 23,2011

September 2016 (Construction)

March 23, 2011 December 2015 (Construction)

100% Planning September 30, 2011 July 8, 2011

100% Design September 2016 October 1, 2012

ROW Acquisition June 2017 October 2015

Permitting (PTI Submittal) December 2016

September 30, 2012 April 30, 2015

(renewal)

Bidding & Construction

Bidding September 2017 August 2016

Start Construction December 2017 November

2016

Complete Construction December 2018 September 2017

The Mill Creek Basin lies in the heart of Hamilton County stretching from the Ohio River to the northern Hamilton County border and from Reed Hartman Highway west to Colerain Avenue. The Mill Creek basin contains portions of 32 cities, villages, and townships including: the City of Cincinnati, Springfield Township, Colerain Township, Forest Park, Glendale, Wyoming, Springdale, Sharonville, Blue Ash, Amberley Village, Norwood, and others.

10141080 – Ludlow and Lafayette

10143220 – CSO 179 Sewer Separation

The Northside Upper Bundle includes two projects intended to reduce both combined sewer and sanitary sewer wet weather overflow events. Sanitary sewer surcharging and overflows occurring at SSO 645 and SSO 225A will be reduced through construction of 1,700 feet of new parallel sewer in the Clifton neighborhood. The new parallel sewer will enable more sanitary flow to be captured in lieu of discharging to surface waters. The bundle will reduce combined sewer overflows through construction of separate sanitary and storm water sewers in the area of CSO 179. These projects were classified under the “Phase 1” Wet Weather Improvement Plan because they provide MSD with the ability to eliminate existing overflows. All work associated with these bundle project will be substantially complete by the Consent Order Milestone date of December 31, 2018 (Attachment 1A – Final WWIP).

Bundle Project Project Number

Legislated Funds

Actual Costs

Current Estimated

Project Cost

Ludlow & Lafayette Parallel Sewer 10141080 $427,222 $205,138 $3,498,400

CSO 179 Sewer Separation 10143220 $1,810,146 $354,250 $1,647,364

Totals $2,237,368 $559,388 $5,145,764

Planner Ian Grimes

Project Manager 10141080 – Andrew Spurgeon 10143220 – Sohail Saeed

Construction Manager In-house

Planning Consultant In-house

Design Consultant 10141080 – RA Consultants LLC 10143220 – ARCADIS

Contractor TBD

Page 5: MONTHLY PROJECT REPORTS - Project Groundworkprojectgroundwork.org/downloads/l3... · MONTHLY PROJECT REPORTS . As of June 30, 2016 . Mill Creek Watershed . Excluding Lower Mill Creek

Westwood Northern Bundle Project Status as of June 30, 2016

Project IDs 10143920/10143923 10143940 10143960/10143962

Municipality Cincinnati (Westwood)

Basin Mill Creek

Project Phase Design

Planner Casey Walter

Project Manager Julie Schroeder

Design Consultant RA Consultants LLC

Milestone Dates FLOAT BY PROJECT

Status Contract 3 Contract 2 Contract 1

PTI Submittal 6/30/15 MET MET MET No delay

Start Construction 6/30/16 MET MET MET No delay

Complete Construction 6/30/17 Dropped -100 MET DELAY

Current Activities and Accomplishments The three projects comprising this bundle include: CSO 194 Sewer Separation (10143920), CSO 195 Sewer Separation (10143960), and CSO 525 Sewer Separation (10143940). Substantial Completion was issued for the CSO 525 Sewer Separation Project on May 31, 2013.

Design task orders for the remaining scope of work had a Notice to Proceed June 1, 2016.

Look Ahead Revisions to the Design Documents reflecting the reduced scope to be completed in 2 months from Design Notice to Proceed. Right of Way requirements will need to be verified upon design completion.

Issues No Float remains for CSO 194 and 195. The West Fork Model submitted in January illustrates that the bundle has some additional work to be done to meet the Final WWIP overflow requirements.

The Westwood Northern Bundle is located along the western side of the Mill Creek Basin. The Mill Creek basin lies in the heart of Hamilton County stretching from the Ohio River to the northern Hamilton County border and from Reed Hartman Highway west to Colerain Avenue. The Mill Creek basin contains portions of 32 cities, villages, and townships including: the city of Cincinnati, Springfield Township, Colerain Township, Forest Park, Glendale, Wyoming, Springdale, Sharonville, Blue Ash, Amberley Village, Norwood, and others.

The Westwood Northern Bundle includes projects intended to improve the quality of the headwaters of West Fork Creek by separating the sanitary flows from storm water. Storm water inlets, ravines, driveway drains, and parking lot drains will be diverted from the combined sewer system. Separating the storm and sanitary flows will reduce the combined sewage overflow events that occur during wet weather. This bundle will address combined sewer overflows at CSOs 194, 195, and 525 by separating existing combined sewers and installing storm sewers as a separate system. All work associated with this project will be substantially complete by the Consent Order Milestone date of June 30, 2017 (Attachment 1A – Final WWIP). The Westwood Northern Bundle (WNB)’s current designs for these projects provide a higher level of control than required by the Final WWIP. To fully comply with the Final WWIP requirements for this bundle, smaller scaled project designs are needed to be constructed for Project 10143920 (CSO 194) and Project 10143940 (CSO 195), compared to the currently designed projects. Project 10143960 (CSO 525) is currently in full compliance with the Final WWIP and has reached Substantial Completion. As confirmed by the 2016 West Fork model, Project 10143923 CSO 194 and 10143962 CSO 525 additional separations would not be needed and has been dropped.

Bundle Project Project Number Current Estimated Project Cost

Legislated Funds

Actual Cost To-Date

CSO 194 High Point Sewer Separation (Contract 2)

10143920 $1,637,837 $1,610,777 $1,024,245

CSO 195 Westwood Northern Sewer Separation (Contract 2)

10143940 $1,910,560 $1,051,137 $725,710

CSO 525 Mt. Airy Grating Sewer Separation (Contract 1 )

10143960 $3,185,756 $3,457,865 $3,185,756

Totals $6,734,153 $6,119,779 $4,935,711

Project Phase Activities

Schedule for Completion

10143923 10143962

(Contract 3)

10143940 10143920

(Contract 2)

10143960

(Contract 1)

Planning & Design

Project Legislated

September 2015

(Construction)

February 2016 (Construction)

100% Planning March 2010 June 2009 June 2009

100% Design August 2015 3/29/2013 December 2011

ROW Acquisition August 2015 April 2013 November 2011

Permitting (PTI Submittal) March 2013

March 2013 July 2016 revised

January 2012

Bidding & Construction

Bidding Dropped November 2016 June 2012

Start Construction Dropped March 2017 July 2012

Complete Construction Dropped September 2017 May 2013

Note: The construction start milestone was met with Contract 1.

Page 6: MONTHLY PROJECT REPORTS - Project Groundworkprojectgroundwork.org/downloads/l3... · MONTHLY PROJECT REPORTS . As of June 30, 2016 . Mill Creek Watershed . Excluding Lower Mill Creek

Mayhew and Leath Avenues Sewer Replacement Project Status as of June 30, 2016

Project ID 10240515

Municipality Delhi Township

Basin Mill Creek

Project Phase Design

Planner N/A

Project Manager Bill Lutz

Construction Manager Steve Jones

Construction Inspector Rob Apel

Design Consultant CH2M Hill

Contractor Cincinnati Tunnel Partners

Project Manager Daniel Anderson

Design Consultant HDR

Construction Manager TBD

Construction Inspector TBD

Contractor TBD

Current Activities and Accomplishments Work on the 90% design was submitted August 24, 2015. Look Ahead

Negotiations for required Right of Way easements are anticipated to complete in March 2017. Issues: No issues at this time.

This project involves realigning and replacing approximately 300 feet of existing 24-inch combined sewer pipe and four associated manholes. The existing pipes are in such poor condition that they could collapse resulting in backup and creating water-in-basement issues. Of greater concern is the possibility that the pipe segment in close proximity to the residence could collapse and result in damage to the house. The work requires the abandonment of approximately 128 feet of sewer and the removal of three manholes and a special chamber. This project is located in Delhi Township.

Current Estimated Project Cost $689,075

Legislated Funds $155,375

Actual Cost To-Date $99,459

% Complete Current Estimated Project Cost 14%

Project Phase

Project Activities

Schedule for Completion

Actual Date of Completion

Planning & Design

Project Legislated

December 2017 (Construction) 2014 (Design)

100% Planning May 31, 2013

100% Design March 2017

ROW Acquisition March 2017

Permitting (PTI Submittal) January 2017

Bidding & Construction

Bidding July 2017

Start Construction October 2017

Complete Construction July 2018

The Mill Creek Basin lies in the heart of Hamilton County stretching from the Ohio River to the northern border of Hamilton County and from Reed Hartman Highway west to Colerain Avenue. The Mill Creek basin contains portions of 32 cities, villages, and townships including: the City of Cincinnati, Springfield Township, Colerain Township, Forest Park, Glendale, Wyoming, Springdale, Sharonville, Blue Ash, Amberley Village, Norwood, and of course, Westwood.

Milestone Date

PTI Submittal January 2017

Start Construction October 2017

Complete Construction July 2018

Page 7: MONTHLY PROJECT REPORTS - Project Groundworkprojectgroundwork.org/downloads/l3... · MONTHLY PROJECT REPORTS . As of June 30, 2016 . Mill Creek Watershed . Excluding Lower Mill Creek

Mill Creek Wastewater Treatment Plant Plant Influent and Headworks Odor Control

Improvements Project Status as of June 30, 2016

Project ID 10240635

Municipality City of Cincinnati

Basin Mill Creek

Project Phase Planning

Planner N/A

Project Manager Bill Lutz

Construction Manager Steve Jones

Construction Inspector Rob Apel

Design Consultant CH2M Hill

Contractor Cincinnati Tunnel Partners

Planner Bruce Smith

Project Manager Sara Cramer

Design Consultant TBD

Construction Inspector TBD

Contractor TBD

Current Activities and Accomplishments The Design Consultant was selected by RFQ in the first Quarter of 2016. MSD received BCE approval May 19, 2016. Look Ahead Design Contract negotiations are in progress with design is anticipated to start in August 2016. Construction funding for this project was included in the 2016 CIP, however design start delays will likely push construction into 2017.

Issues It is a community priority to replace the old outdated equipment and provide a secondary feed line for additional odor control.

Current Estimated Project Cost $1,468,200

Legislated Funds $209,200

Actual Costs to Date $1,501

% Complete Current Estimated Project Cost 1%

Project Phase Project Activities Schedule for Completion

Actual Date of Completion

Planning & Design

Project Legislated February 2016

100% Planning July 2015 March 2015

100% Design January 2017

Permitting (PTI Submittal) December 2016

ROW Acquisition N/A

Bidding & Construction

Bidding January 2017

Start Construction April 2017

Complete Completion September 2017

MSDGC has been working closely with the Lower Price Hill community groups for many years to improve its relationship with the community by reducing odors from the Mill Creek Wastewater Treatment Plant. Odor control facilities have been installed at various odor sources to reduce and treat plant emissions. However, the odor control systems for the plant influent and headworks need improvements in order to continue to provide reliable odor control and improve the performance of the existing systems. This proposed project will replace existing chemical feed equipment for the headworks chemical scrubber and provide new ferrous chloride feed system bulk tanks, containment area, piping, valves and automation. This project will also provide a new pumping system and secondary feed point for improved odor control throughout the primary and secondary treatment process.

.

Milestone Date

Start Construction April 2017

Complete Construction September 2017

The Mill Creek basin lies in the heart of Hamilton County stretching from the Ohio River to the northern Hamilton County border and from Reed Hartman Highway west to Colerain Avenue. The Mill Creek basin contains portions of 32 cities, villages, and townships including: the City of Cincinnati, Springfield Township, Colerain Township, Forest Park, Glendale, Wyoming, Springdale, Sharonville, Blue Ash, Amberley Village, Norwood, and others.

Page 8: MONTHLY PROJECT REPORTS - Project Groundworkprojectgroundwork.org/downloads/l3... · MONTHLY PROJECT REPORTS . As of June 30, 2016 . Mill Creek Watershed . Excluding Lower Mill Creek

Mill Creek Wastewater Treatment Plant Septage Receiving Station Odor Control Improvements Project Status as of June 30, 2016

Project ID 10240665

Municipality City of Cincinnati

Basin Mill Creek

Project Phase Planning

Planner N/A

Project Manager Bill Lutz

Construction Manager Steve Jones

Construction Inspector Rob Apel

Design Consultant CH2M Hill

Contractor Cincinnati Tunnel Partners

Planner Bruce Smith

Project Manager Sara Cramer

Design Consultant TBD

Construction Inspector TBD

Contractor TBD

Current Activities and Accomplishments The draft Business Case Evaluation was revised and submitted with Design Legislation in May 2016. Look Ahead Design Legislation approval is anticipated in July 2016, pending County approval. Issues Odor control study monitoring in 2015 determined that the Septage Receiving Station is in need of enhancement. There have been on-going conversations related to the operation and maintenance of the Septage Receiving Station.

Current Estimated Project Cost $1,193,400

Legislated Funds $0

Actual Costs to Date $0

% Complete Current Estimated Project Cost 0%

Project Phase Project Activities Schedule for Completion

Actual Date of Completion

Planning & Design

Project Legislated June 2016

100% Planning July 2015 March 2015

100% Design April 2017

Permitting (PTI Submittal) March 2017

ROW Acquisition N/A

Bidding & Construction

Bidding July 2017

Start Construction October 2017

Complete Completion March 2018

MSDGC has been working closely with the Lower Price Hill community groups for many years to improve its relationship with the community by reducing odors from the Mill Creek Wastewater Treatment Plant. Odor control facilities have been installed at various odor sources to reduce and treat plant emissions. However, the Septage Receiving Station building space, where the trucks deliver wastewater from commercial septage haulers, does not have an odor control system for the air in the truck bays. The existing odor control system only treats the air from the channels below ground in the building. This project will provide an odor control system to treat the odorous air from the truck bays. The recommended alternative calls for two new 9,000 ft³/min dry media units to treat 18,000 ft³/min of odorous air from the Septage Receiving Station truck bays. As part of this alternative, new ductwork will be installed in the Septage Receiving Station to convey airflow to the new dry media units.

.

Milestone Date

Start Construction October 2017

Complete Construction March 2018

The Mill Creek basin lies in the heart of Hamilton County stretching from the Ohio River to the northern Hamilton County border and from Reed Hartman Highway west to Colerain Avenue. The Mill Creek basin contains portions of 32 cities, villages, and townships including: the City of Cincinnati, Springfield Township, Colerain Township, Forest Park, Glendale, Wyoming, Springdale, Sharonville, Blue Ash, Amberley Village, Norwood, and others.

Page 9: MONTHLY PROJECT REPORTS - Project Groundworkprojectgroundwork.org/downloads/l3... · MONTHLY PROJECT REPORTS . As of June 30, 2016 . Mill Creek Watershed . Excluding Lower Mill Creek

Mill Creek Wastewater Treatment Plant Service Water Reliability and Service Upgrades

Project Status as of June 30, 2016

Project ID 10240245

Municipality City of Cincinnati

Basin Mill Creek

Project Phase Design

Planner N/A

Project Manager Bill Lutz

Construction Manager Steve Jones

Construction Inspector Rob Apel

Design Consultant CH2M Hill

Contractor Cincinnati Tunnel Partners

Planner Jason Lee

Project Manager Jeff Dean

Design Consultant Burgess & Niple

Construction Inspector TBD

Contractor TBD Current Activities and Accomplishments A 90 % design set was completed in November 2015.

Look Ahead Construction legislation was recommended by MSD but not approved to be included in the 2016 CIP. Construction legislation is now anticipated in January of 2017.

Issues The pumps are not running at an efficient operating point on their curves, new piping arrangement is needed in order to operate all three incinerators at once while shunting ash slurry to lagoons. The need for the new piping arrangement was discovered during 90% design. MSD is awaiting funding approval to finish this additional piping design. Five of the seven pumps are currently available, four of which are new. Of the remaining two unavailable pumps, one is undersized and not available for use and the other is awaiting some piping modifications before it can be operated.

Current Estimated Project Cost $3,820,302

Legislated Funds $673,743

Actual Costs to Date $531,582

% Complete Current Estimated Project Cost 14%

Project Phase Project Activities Schedule for Completion

Actual Date of Completion

Planning & Design

Project Legislated May 2017 Construction

December 2011 Design

100% Planning October 2011 October 3, 2011

100% Design March 2016 On-going

Permitting (PTI Submittal) December 2015 December 2015

ROW Acquisition N/A N/A

Bidding & Construction

Bidding February 2017

Start Construction June 2017

Complete Completion June 2018

The project will provide upgrades to the Mill Creek Wastewater Treatment Plant’s non-potable water system to meet projected flow and pressure demands and to ensure an adequate level of service reliability for treatment processes at the plant to ensure their optimum operation. The current non-potable water system does not provide adequate service to the Fluidized Bed Incinerators to prevent sulfur dioxide emissions. In February 2011, MSD committed to evaluating the scrubber tray water feed system and to make adjustments as necessary to provide adequate non-potable water flow as part of an agreement with the Hamilton County Department of Environmental Services.

.

Milestone Date

Start Construction June 2017

Complete Construction June 2018

The Mill Creek basin lies in the heart of Hamilton County stretching from the Ohio River to the northern Hamilton County border and from Reed Hartman Highway west to Colerain Avenue. The Mill Creek basin contains portions of 32 cities, villages, and townships including: the City of Cincinnati, Springfield Township, Colerain Township, Forest Park, Glendale, Wyoming, Springdale, Sharonville, Blue Ash, Amberley Village, Norwood, and others.

Page 10: MONTHLY PROJECT REPORTS - Project Groundworkprojectgroundwork.org/downloads/l3... · MONTHLY PROJECT REPORTS . As of June 30, 2016 . Mill Creek Watershed . Excluding Lower Mill Creek

Mill Creek Wastewater Treatment Plant Solids Handling Improvements Phase 1

Project Status as of June 30, 2016

Project ID 10240291

Municipality City of Cincinnati

Basin Mill Creek

Project Phase Design

Planner N/A

Project Manager Bill Lutz

Construction Manager Steve Jones

Construction Inspector Rob Apel

Design Consultant CH2M Hill

Contractor Cincinnati Tunnel Partners

Planner Sohail Saeed

Project Manager Jeff Dean

Design Consultant Black and Veatch

Construction Inspector TBD

Contractor TBD Current Activities and Accomplishments Scope and budget were added to this project for the replacement of the sludge feed and transfer piping in the digester tank control room and the replacement of the sludge transfer pump in this area for the two southernmost digester tanks.

The PTI was submitted to EPA in December 2015. 100% design deliverable was completed in March 2016. This project requested Construction Legislation in April 2016 which contained justification for the Construction budget increase. Look Ahead

This project is expected to advertise to bid for construction in September 2016 upon Legislation approval.

Issues Construction legislation is critically needed and is at risk of not meeting schedule. County has been provided the requested solids management plan which was holding approval; failure to authorize construction may result in increased risk of odor and solids handling issues over the next few years.

Current Estimated Project Cost $21,570,925

Legislated Funds $2,221,957

Actual Costs to Date $1,871,257

% Complete Current Estimated Project Cost 9%

Project Phase Project Activities

Schedule for Completion

Actual Date of Completion

Planning & Design

Project Legislated December 2015 Construction

March 2011 Design

100% Planning October 2011 October 13, 2011

100% Design November 2015 March 11, 2016

Permitting (PTI Submittal) December 2015 December 31, 2015

ROW Acquisition N/A N/A

Bidding & Construction

Bidding September 2016

Start Construction December 2016

Complete Completion April 2018

.

Milestone Date

PTI Received December 2015

Start Construction December 2016

Complete Construction April 2018

The Mill Creek basin lies in the heart of Hamilton County stretching from the Ohio River to the northern Hamilton County border and from Reed Hartman Highway west to Colerain Avenue. The Mill Creek basin contains portions of 32 cities, villages, and townships including: the City of Cincinnati, Springfield Township, Colerain Township, Forest Park, Glendale, Wyoming, Springdale, Sharonville, Blue Ash, Amberley Village, Norwood, and others.

This project will provide the basis for a long term approach to optimize and improve the reliability of the Mill Creek WWTP solids handling facility. The project is located in the Lower Price Hill neighborhood of Cincinnati. The purpose of this project is to provide improved solids handling facilities at the Mill Creek WWTP. In particular, it is important to ensure solids processing reliability over the useful life of the incinerators is maintained. MSDGC proposes a phased approach for the improvements so the most immediate upstream solids handling needs can be addressed first. The first phase of this project will include the following improvements: construction of larger sludge feed wells, upgrade of sludge feed piping, upgrade of support structures and equipment, emergency storage and pumping, and odor control.

Page 11: MONTHLY PROJECT REPORTS - Project Groundworkprojectgroundwork.org/downloads/l3... · MONTHLY PROJECT REPORTS . As of June 30, 2016 . Mill Creek Watershed . Excluding Lower Mill Creek

Mt. Airy Forest Sewer Replacement Project Status as of June 30, 2016

Project ID 10240150

Municipality Cincinnati (Westwood/Mt. Airy)

Basin Mill Creek

Project Phase Construction

Planner N/A

Project Manager Bill Lutz

Construction Manager Steve Jones

Construction Inspector Rob Apel

Design Consultant CH2M Hill

Contractor Cincinnati Tunnel Partners

Project Manager Julie Schroeder

Design Consultant Parsons Brinkerhoff

Construction Manager Len Bauer

Construction Inspector Rob Apel

Contractor Rack and Ballauer Current Activities and Accomplishments The tree felling to eliminate bat nesting trees is complete. Construction award was February 2, 2016. The Construction Notice to Proceed was May 31, 2016. Site clearing started in June 2016. Look Ahead

The Contractor will complete site preparation and start laying pipe. Issues No issues at this time.

This project includes construction and rehabilitation of approximately 10,000 linear feet of 12-inch to 24-inch sewer. Detailed planning and design considered alternate alignments to minimize impacts to the park. This project is located in the Westwood neighborhood of Cincinnati. This project proposes to replace or rehabilitate numerous segments of sanitary interceptor sewer constructed in Mt. Airy Forest Park in the 1930s. The segments that are undersized and in need of continued maintenance are not candidates for lining. Failure to address this failing sewer could result in collapse and sewage discharges to the park. The project will provide the benefit of reducing sanitary sewer overflows in this area.

Current Estimated Project Cost $6,789,896

Legislated Funds $7,858,000

Actual Cost To-Date $858,611

% Complete Current Estimated Project Cost 13%

Project Phase

Project Activities

Schedule for Completion

Actual Date of Completion

Planning & Design

Project Legislated

June 2015 (Construction)

June 3, 2015 2008

100% Planning May 22, 2008

100% Design May 2015 May 11, 2015

ROW Acquisition April 2015 April 15, 2015

Permitting (PTI Submittal) March 2015 March 10, 2015

Bidding & Construction

Bidding December 2015 December 2015

Start Construction May 2016 May 2016

Complete Construction November 2017

The Mill Creek Basin lies in the heart of Hamilton County stretching from the Ohio River to the northern border of Hamilton County and from Reed Hartman Highway west to Colerain Avenue. The Mill Creek basin contains portions of 32 cities, villages, and townships including: the City of Cincinnati, Springfield Township, Colerain Township, Forest Park, Glendale, Wyoming, Springdale, Sharonville, Blue Ash, Amberley Village, Norwood, and of course, Westwood.

This project was legislated again in June 2008 after the scope was revised. For this reason, planning was performed before the legislation date shown.

Milestone Date

PTI MET

Start Construction May 2016

Complete Construction November 2017

Mt. Airy Forest

CSOs to be eliminated under the Westwood Northern Bundle are marked, and are separate projects. Harvest Home Park is located to the west.

Page 12: MONTHLY PROJECT REPORTS - Project Groundworkprojectgroundwork.org/downloads/l3... · MONTHLY PROJECT REPORTS . As of June 30, 2016 . Mill Creek Watershed . Excluding Lower Mill Creek

Sanitary Sewer Overflows 603 and 704 ImprovementsProject Status as of June 30, 2016

Project ID 10240275

Municipality Sycamore Township

Basin Mill Creek

Project Phase Design

Planner N/A

Project Manager Bill Lutz

Construction Manager Steve Jones

Construction Inspector Rob Apel

Design Consultant CH2M Hill

Contractor Cincinnati Tunnel Partners

Planner Casey Walter

Project Manager Jeff Dean

Design Consultant AECOM USA, Inc.

Construction Inspector TBD

Contractor TBD

Current Activities and Accomplishments

All contracts for easement acquisition are signed, excluding the easements for access through the school.

Look Ahead

Construction legislation is on hold awaiting verification of project needs with SSO 700 IWAP.

Issues

Since the project continues to be on hold, the construction start will have to be delayed until the summer of 2017. This delay increases the risk of greater temporary easement costs and greater USACE 404 and OEPA 401 permitting costs. A Notice to Proceed will have to be issued prior to these permits expiring March 18, 2017. MSD continues to work with the County for approval.

Current Estimated Project Cost $8,313,925

Legislated Funds $8,052,581

Actual Costs to Date $870,486

% Complete Current Estimated Project Cost 11%

Project Phase Project Activities

Schedule for Completion

Actual Date of Completion

Planning & Design

Project Legislated January 2016 Construction

2012Design

100% Planning August 2009 August 10, 2009

100% Design October 2015 Ongoing

Permitting (PTI Submittal) September 2011

June 26, 2013February 6, 2015

(renewal)

ROW Acquisition December 2014 December 6, 2014

Bidding & Construction

Bidding February 2017

Start Construction May 2017

Complete Completion November 2018

.

Milestone Date

Start Construction May 2017

Complete Construction November 2018

The Mill Creek basin lies in the heart of Hamilton County stretching from the Ohio River to the northern Hamilton County border and from Reed Hartman Highway west to Colerain Avenue. The Mill Creek basin contains portions of 32 cities, villages, and townships including: the City of Cincinnati, Springfield Township, Colerain Township, Forest Park, Glendale, Wyoming, Springdale, Sharonville, Blue Ash, Amberley Village, Norwood, and others.

The purpose of this project is to improve SSO 603 and SSO 704. SSO 603 is active about eight – seventeen times per year, and SSO 704 is active about ten-nineteen times per year. This project will replace 6,000 feet of 15-inch and 18-inch sewer with 21-inch to 36-inch pipe to increase capacity; resulting in the elimination of SSO 704 overflows for a 2 year storm, and physically removing SSO 603.

Page 13: MONTHLY PROJECT REPORTS - Project Groundworkprojectgroundwork.org/downloads/l3... · MONTHLY PROJECT REPORTS . As of June 30, 2016 . Mill Creek Watershed . Excluding Lower Mill Creek

Mill Creek Wastewater Treatment Plant Dewatering Polymer System Replacement

Project Status as of June 30, 2016

Project ID 10240480

Municipality City of Cincinnati

Basin Mill Creek

Project Phase Design

Planner N/A

Project Manager Bill Lutz

Construction Manager Steve Jones

Construction Inspector Rob Apel

Design Consultant CH2M Hill

Contractor Cincinnati Tunnel Partners

Planner N/A

Project Manager Sara Cramer

Design Consultant Black & Veatch

Construction Inspector TBD

Contractor TBD Current Activities and Accomplishments MSD has requested construction legislation for this project. This project was highlighted as a significant risk in the updated Solids Management Plan.

Look Ahead Legislation has not yet been approved to add this Project to the 2016 CIP for Construction.

Issues This project was highlighted as a significant risk in the updated Solids Management Plan. This system continues to have issues with polymer unloading, mixing, aging, and feed systems.

Current Estimated Project Cost $6,653,482

Legislated Funds $75,000

Actual Costs to Date $48,730

% Complete Current Estimated Project Cost 1%

Project Phase Project Activities Schedule for Completion

Actual Date of Completion

Planning & Design

Project Legislated November 2015 Construction

December 2011 Design

100% Planning October 2011 October 3, 2011

100% Design September 2014 September 2015

Permitting (PTI Submittal) N/A N/A

ROW Acquisition N/A N/A

Bidding & Construction

Bidding August 2016

Start Construction October 2016

Complete Completion February 2018

The dewatering polymer system is integral to the successful operation of the dewatering and incineration facilities at Mill Creek WWTP. Over the last several years, the reliability of the dewatering and incineration facilities and causing operations staff to rely more on the former digesters for standby sludge storage capacity. Much of the polymer system equipment is beyond its useful service life and is no longer supported by the system manufacturer, making maintenance repairs increasingly more frequent, difficult, and expensive. This project will replace the dewatering polymer system at the Mill Creek WWTP.

.

Milestone Date

Start Construction October 2016

Complete Construction February 2018

The Mill Creek basin lies in the heart of Hamilton County stretching from the Ohio River to the northern Hamilton County border and from Reed Hartman Highway west to Colerain Avenue. The Mill Creek basin contains portions of 32 cities, villages, and townships including: the City of Cincinnati, Springfield Township, Colerain Township, Forest Park, Glendale, Wyoming, Springdale, Sharonville, Blue Ash, Amberley Village, Norwood, and others.


Recommended