Open Workbench. By Wilmer Arellano Spring 2008. This is just an example, you can customize as you like. In Favorites Gantt Charts, double-click the little square and enter: A new Phase with: Name Category And ID Make sure to select phase. The first phase has been created. - PowerPoint PPT Presentation
Popular Tags:
39
Open Workbench By Wilmer Arellano Spring 2008
Transcript
Page 1: Open Workbench

Open Workbench

By Wilmer Arellano

Spring 2008

Page 2: Open Workbench
Page 3: Open Workbench

This is just an example, you can customize as you like.

Page 4: Open Workbench

In Favorites Gantt Charts, double-click the little square and enter:

• A new Phase with:

•Name

•Category

•And ID

Make sure to select phase

Page 5: Open Workbench

The first phase has been created

Page 6: Open Workbench

In Favorites Gantt Charts, double-click the little square and enter:

•The Tasks with:

•Names

•Category

•And ID

•Duration

Make sure to select task

Page 7: Open Workbench

The first task has been entered

Page 8: Open Workbench

This is how it would look after all tasks for the first phase have been entered

Page 9: Open Workbench

To indicate task’s dependencies drag from the end of one task to the beginning of the next one

Page 10: Open Workbench

Click here to auto-schedule

Page 11: Open Workbench

This is how it would look like

Red Color indicates the Critical Path

Page 12: Open Workbench

1.1 Antenna DesignTheorical Design 5%Antenna Construction 10%Antenna testing 5%

1. Transmiter Antenna Packaging 3%Antenna Design 25% Monitoring 2%

1. Transmiter Modulator Design 25% 1.2 Modulator DesignAudio interface Module 10%

Power Amplifier Design 50% Mixer Module 10%Output Stage Module 5%

1.3 Power Amplifier Design

Page 13: Open Workbench

Project with two phases included

It is a coincidence that the two phases have same duration

Page 14: Open Workbench

Click to see the PERT

The zoom commands were used to fit the chart in the window

Page 15: Open Workbench

On planning, Resource assignment, double click the little square to enter the resources and their costs

Page 16: Open Workbench

Do the same for non labor resources

Use Equipment for Space

Page 17: Open Workbench

You can add the cost of components as “material”

Page 18: Open Workbench

Right click on the tasks and select assignment to assign resources to the tasks

Page 19: Open Workbench

Right click on the tasks and select assignment to assign resources to the tasks.

Enter estimated hours in Estimate

Page 20: Open Workbench

As components were entered with a rate of $100, 1.5 will represent $150

Page 21: Open Workbench

The yellow color indicates that the task is low in resources, more hours or space or equipment, etc are needed

If you need to add a new task or phase in between tasks or phases, right click the square and select insert task

Page 22: Open Workbench

There will be a problem if you click schedule again

Page 23: Open Workbench

As the Audio Interface Module and the Mixer Module were using the same resources, they were converted to sequential.

You would need to add more resources to keep the tasks in parallel

The zoom commands were used to fit the chart in the window

Page 24: Open Workbench

•Another Low Frequency Engineer was included

•Two more Lab Spaces were included

•It was not necessary to increase the project duration

Page 25: Open Workbench

Click on controlling and then Revise Schedule to see the budget

Page 26: Open Workbench

Set The base Line

Updating The Project Status

Page 27: Open Workbench

Updating The Project Status

Page 28: Open Workbench

Updating The Project Status

Page 29: Open Workbench

Updating The Project Status

The task bar changes colour to reflect status (Red / Blue – Not Started)(Purple – Started)(Grey – Progress completed)The task name changes colour to reflect status (Red – Not Started)(Purple – Started)(Green – Completed)

Page 30: Open Workbench

Updating The Project Status

If the task is completed enter 0 in Estimate

Page 31: Open Workbench

Updating The Project Status

We reduced 20 hours but because of the weekend it appears to be a longer time

Page 32: Open Workbench

Milestones

Page 33: Open Workbench

Milestones

Drag the milestone to the desired location

Page 34: Open Workbench

Milestones

Page 35: Open Workbench

Copy and Paste

Table cells can be copied and pasted into excel

By the way, this is a representation of the WBS

Page 36: Open Workbench

Phase 1.1 Antenna Design HardwareTask 1.1.1 Theoretical Design HardwareTask 1.1.2 Antenna Construction HardwareTask 1.1.3 Antenna Testing HardwareTask 1.1.4 Antenna Packaging HardwareTask 1.1.5 Monitoring HardwarePhase 1.2 Modulator Design HardareTask 1.2.1 Audio Interface ModuleTask 1.2.2 Mixer Module HardwareTask 1.2.3 Output Stage ModuleMilestone Prototype Prototype Ready Hardware

Task 1.1.1 Theoretical Design HardwareTask 1.1.2 Antenna Construction Hardware

Phase 1.1 Antenna Design Hardware Task 1.1.3 Antenna Testing HardwareTask 1.1.4 Antenna Packaging HardwareTask 1.1.5 Monitoring Hardware

Task 1.2.1 Audio Interface ModuleTask 1.2.2 Mixer Module Hardware

Phase 1.2 Modulator Design Hardare Task 1.2.3 Output Stage ModuleMilestone Prototype Prototype Ready Hardware

Page 37: Open Workbench
Page 38: Open Workbench

The Budget

JohnSmith 15 $225.00

Circuits Lab 10 $70.00JohnSmith 10 $150.00

Circuits Lab 2 24 $24.00Mary Morrison 20 $300.00Circuits Lab 32 $224.00John Martinez 32 $480.00Comp Mod $150.00John Martinez 40 $600.00Lab Circuits 3 40 $280.00

$2,503.00

Even the Components are included here

Page 39: Open Workbench

&&QuestionsQuestions

AnswersAnswers