P2 status, LS1 planning A.Tauro - W.Riegler
Transcript
Page 1: P2 status, LS1 planning A.Tauro - W.Riegler. Outline TS2 activities Detector activities during LS1 Proposal for ALICE recommissionig plan in 2014 Conclusions.

P2 status, LS1 planning

A.Tauro - W.Riegler

Page 2: P2 status, LS1 planning A.Tauro - W.Riegler. Outline TS2 activities Detector activities during LS1 Proposal for ALICE recommissionig plan in 2014 Conclusions.

Outline

• TS2 activities• Detector activities during LS1• Proposal for ALICE recommissionig plan in 2014• Conclusions

21/6/12 P2 status, LS1 planning - A.Tauro 2

Page 3: P2 status, LS1 planning A.Tauro - W.Riegler. Outline TS2 activities Detector activities during LS1 Proposal for ALICE recommissionig plan in 2014 Conclusions.

TS2 (25th to 29th June) – detector activitiesDetector Intervention

SDD Check pressure sensor (PP4)

SSD Replace LVPS (A and I side racks). Install thermostatic valve (cooling plant)

TPC RR cooling: replacement & rotation of the pump

TPC laser Investigate problem with RS232 communication with Laser 2

TRD Installation hardware for the ethernet multiplexer. LV connection check.Check TRD pretrigger TTCex board. Fix gas leak in SM6

TOF Replacement DC/DC converters in several sectors

SPD Electronics check. SR3 and 8 will not be drilled

MTG Maintenance electronics & RPC gas check. Decrease C2H2F4 consumption

MTK Replace Wiener LVPSs

PHO Add freon to the cooling plant (RP check)

EMC Commissioning of the 1/3 size EMCal supermodules (RO)

T0 Investigate width problem, inspection laser system, repair one amplifier

ACO Check electronics

BCM-BPTX Checks

21/6/12 P2 status, LS1 planning - A.Tauro 3TC meeting tomorrow: https://indico.cern.ch/conferenceDisplay.py?confId=196440

Page 4: P2 status, LS1 planning A.Tauro - W.Riegler. Outline TS2 activities Detector activities during LS1 Proposal for ALICE recommissionig plan in 2014 Conclusions.

ALICE LS1 plans - A.Tauro 4

LS1

• LS1: Nov.24th 2012 to Sept.1st 2014 92 weeks.

• There are no official plans to delay the LS1 start date. There is an option to start LS1 one week earlier, i.e. on Nov.17th, because in this way the LHe can be fully recovered before Xmas. The final decision will be taken in August. Beyond that time it will be more and more difficult and costly to move the LS1 start date (F.Bordry).

• LHC commissioning with beam: Sept. 1st 2014 to Nov. 2014 (no access to UX25).

• It is not planned to have a stop of LHC beam operation at Christmas 2014 (1 week of standby for LHC & Injectors).

6/15/12

Page 5: P2 status, LS1 planning A.Tauro - W.Riegler. Outline TS2 activities Detector activities during LS1 Proposal for ALICE recommissionig plan in 2014 Conclusions.

What is LS1?• Not a project, but a time-frame (Nov-2012 to Sept-2014)• Numerous projects and activities:

SMACC (Superconducting Magnets And Circuits Consolidation) R2E Massive shutdown maintenance after more than 3 years of operation Several major consolidations A lot of projects (Linac 4, HIE-Isolde, Elena, LIU, HL-LHC, 107, ….)

• Compared to previous shutdowns, an exceptional number of … Simultaneous activities (co-activities) – Planning and safety Non-CERN workers (FSU, collaborations, contracts,…)- Logistics: Registration, training,

transport, parking, access, film badge, EPI, catering, accommodation,…)

Expt. Areas(Isolde, nTof, AD, East & North areas,…) 5F.Bordry – LS1 day 12.06.2012

Page 6: P2 status, LS1 planning A.Tauro - W.Riegler. Outline TS2 activities Detector activities during LS1 Proposal for ALICE recommissionig plan in 2014 Conclusions.

S12 S23P2 S34P3 S45P4 S56P5 S67P6 S78P7 S81P8

Dec.

Jan.

Feb.Mar.Apr.

May

Jun.

Jul.

Aug.Sep.

Oct.

Nov.Dec.

EN

Jan.

Feb.Mar.Apr.

May

Jun.

Jul.

Aug.Sep.

Oct.

Nov.Dec.

Jan.

Dec.

Jan.

Feb.Mar.Apr.

May

Jun.

Jul.

Aug.Sep.

Oct.

Nov.Dec.

Jan.

Feb.Mar.Apr.

May

Jun.

Jul.

Aug.Sep.

Oct.

Nov.Dec.

Jan.

2013

2014

P1

2013

2014

7TeV

Complete LHC schedule

6

Cool-down

W-Up

SplicesSplices

Splices

SplicesSplices

SplicesSplices

Splices

Cool-down Cool-down

Cool-down

Cool-downCool-down

Cool-downCool-down

W-Up W-Up W-UpCSCMW-Up

W-UpW-Up W-Up W-Up

Beam Commissioning

MM

MM

K.Foraz LS1 day 12.06.2012

Page 7: P2 status, LS1 planning A.Tauro - W.Riegler. Outline TS2 activities Detector activities during LS1 Proposal for ALICE recommissionig plan in 2014 Conclusions.

ALICE LS1 plans - A.Tauro 7

ALICE plans for LS1

• Baseline sequence (MNF will not be removed):– Add 5 TRD modules– Add 6 DCal supermodules and 2 1/3 supermodules– Add 1 PHOS module

• Many things on top of this sequence:– LV consolidation (TRD/TPC cables BKF)– SAA3 extension– CO2 and N2 fire extinguisher systems consolidation

– New outlets for redundancy of Ethernet cables– …

• Services interruptions (detailed plan still under discussion):– EN-EL: 66vK and 18kV consolidation several equipment off for 8w– CV maintenance and upgrade 2-4 months no cooling 2013– L3: ventilation and cooling upgrades– UPS upgrade no UPS power (DAQ, DCS, cooling plant…)

6/15/12

Page 8: P2 status, LS1 planning A.Tauro - W.Riegler. Outline TS2 activities Detector activities during LS1 Proposal for ALICE recommissionig plan in 2014 Conclusions.

ALICE now vs. LS1

21/6/12 P2 status, LS1 planning - A.Tauro 8

Page 9: P2 status, LS1 planning A.Tauro - W.Riegler. Outline TS2 activities Detector activities during LS1 Proposal for ALICE recommissionig plan in 2014 Conclusions.

ALICE LS1 plans - A.Tauro 96/15/12

Two TRD modules ready in Aug.

PHOS ready end-2013

Page 10: P2 status, LS1 planning A.Tauro - W.Riegler. Outline TS2 activities Detector activities during LS1 Proposal for ALICE recommissionig plan in 2014 Conclusions.

Central systems availability in 2013-14

• DAQ. Several interventions foreseen:– Infrastructure (new racks, fibers, new UPS electrical distribution)– Network (replace central router)– Computers (new LDCs) DAQ down for most of 2013! Logbook will not be shut-down

• HLT. Computer farm replacement in early 2014. Old farm will be working at all times (except during power interruptions)

• DCS. Plan not yet discussed with TC. Possibility to keep a minimum of services operational at all times (e.g. monitoring,…)

21/6/12 P2 status, LS1 planning - A.Tauro 10

Page 11: P2 status, LS1 planning A.Tauro - W.Riegler. Outline TS2 activities Detector activities during LS1 Proposal for ALICE recommissionig plan in 2014 Conclusions.

ALICE recommissionig plan in 2014(proposal)

• March-April: standalone recommissioning• May-June: global recommissioning• July-August: 24h operation• 1st September: LHC beam commissioning

• Requests for running the central systems outside these periods should be discussed individually

21/6/12 P2 status, LS1 planning - A.Tauro 11

Page 12: P2 status, LS1 planning A.Tauro - W.Riegler. Outline TS2 activities Detector activities during LS1 Proposal for ALICE recommissionig plan in 2014 Conclusions.

LS1 activities TC reviews: ITS, TRD, TPC, Muons Reviews next week: T0, PMD, ZDC, FMD, HMP, PHO and TOF

21/6/12 P2 status, LS1 planning - A.Tauro 12

Page 13: P2 status, LS1 planning A.Tauro - W.Riegler. Outline TS2 activities Detector activities during LS1 Proposal for ALICE recommissionig plan in 2014 Conclusions.

ITS

• SPD:– Minor interventions (FEE)– Replace pump in cooling plant, reuse old inlet pipes, recalibrate T-P

sensors,…

• SDD:– Replace ISEC HV boards (drift problem)– Install SuperCarlosRX cards need DAQ for testing– Replace plastic pipes on cooling plant manifold (tbc)

• SSD:– CAEN LVPS modification (decrease CM) ~120 PS in total– Cooling plant: remove heaters (tbc), drain water (N2 permanent flush?)

21/6/12 P2 status, LS1 planning - A.Tauro 13

Page 14: P2 status, LS1 planning A.Tauro - W.Riegler. Outline TS2 activities Detector activities during LS1 Proposal for ALICE recommissionig plan in 2014 Conclusions.

TRD

• SM production:– All electronics will be produced by end 2012– Two SM ready by August 2013 (installed on top sectors)– Three (bottom) SMs ready before end of LS1 (but not in 2013)

• Other activities:– 20 HV problematic chambers possibility to take out one SM for repair– Replace LV patch panels for all sectors– New tank water cooling plant

• Gas: cryogenic recovery/cleaning at start of LS1 store Xe – Operate the detector for most of LS1 with Ar-CO2 (70-30) – Refill with Xe at some point in 2014– Find better CO2 analyzer, new gas chromatograph (TRD-TPC)

21/6/12 P2 status, LS1 planning - A.Tauro 14

Page 15: P2 status, LS1 planning A.Tauro - W.Riegler. Outline TS2 activities Detector activities during LS1 Proposal for ALICE recommissionig plan in 2014 Conclusions.

TPC

• FEE consolidation:– Replace FECs– Install and commission redundant ethernet system

• HV consolidation:– Maintenance Read Out Chambers– Possibly inspection of containment volumes in field cage

• Interventions on RR and FEE cooling plants

• Gas. New CO2 analyser and gas chromatograph, drift velocity monitor consolidation

• One upgrade option foresees an improvement of the readout capability with the current ROCs and FEE (under discussion):– Replace all RCUs with new ones (possibly) in CR1– Additional cabling and fibers between TPC and CR1

21/6/12 P2 status, LS1 planning - A.Tauro 15

Page 16: P2 status, LS1 planning A.Tauro - W.Riegler. Outline TS2 activities Detector activities during LS1 Proposal for ALICE recommissionig plan in 2014 Conclusions.

Muons

• Muon TRK:– Occupancy problem: repair slats (busbar connections):

• 90 slats to be repaired• will take ~10 months in 2013 (DAQ, DCS and gas needed)

– Replace one quadrant ST2

• Muon TRG:– Ordinary FEE and gas tightness maintenance– Replacement of a few RPCs, if needed– Full campaign of survey and photogrammetry– Gas modification to re-circulate freon (tbd)

21/6/12 P2 status, LS1 planning - A.Tauro 16

Page 17: P2 status, LS1 planning A.Tauro - W.Riegler. Outline TS2 activities Detector activities during LS1 Proposal for ALICE recommissionig plan in 2014 Conclusions.

André Augustinus

Perturbations at P2 Relatively stable operation for ALICE

• No (primary) cooling perturbations, no Level3 alarms

Several electrical perturbations[since last TB: 20/05 (2x), 26/05, 03/06, 06/06, 07/06, 08/06, 10/06, 11/06, 12/06, 13/06]• Propagated from perturbations on French 400kV power grid (thunderstorms)• Typically up to 10% drop on one or two phases for 2-4 cycles• Typically triggers beam dump, but LHC recovers relatively quick• 20/05 and 13/06 caused ALICE dipole trip, no other effects

Solenoid magnet:• 1 rampdown for access, 1 trip (16/06) due to failing Pt100 transducer (during

stable beams, LHC did not loose/dump beam)

Dipole magnet:• 1 rampdown for access, 2 trips (electrical perturbations)

ALICE Technical Board 21 June 2012

Page 18: P2 status, LS1 planning A.Tauro - W.Riegler. Outline TS2 activities Detector activities during LS1 Proposal for ALICE recommissionig plan in 2014 Conclusions.

SXL2 doors, crane…

• The replacement of the SXl2 big doors will start on July 16th, and will take approximately 2 weeks– Nobody inside cleanroom (TRD people

informed)– Cleanroom A/C probably off during work– Evacuation of material outside cleanroom

• New SXL2 crane foreseen for September 2012 (weeks 36-37)

• 2nd floor 3294 will be built in October 2012– 12 new offices (12m2 each) and 2

conference rooms (24m2 each)

21/6/12 P2 status, LS1 planning - A.Tauro 18

SXL2 door

Page 19: P2 status, LS1 planning A.Tauro - W.Riegler. Outline TS2 activities Detector activities during LS1 Proposal for ALICE recommissionig plan in 2014 Conclusions.

ALICE official schematics/photos

Available on CDS (thanks to Julie):• http://cdsweb.cern.ch/record/1451585 (Schematics)• http://cdsweb.cern.ch/record/1436208 (Saba’s photos)• http://cdsweb.cern.ch/record/1436153 (Saba’s photos)

21/6/12 P2 status, LS1 planning - A.Tauro 19

Page 20: P2 status, LS1 planning A.Tauro - W.Riegler. Outline TS2 activities Detector activities during LS1 Proposal for ALICE recommissionig plan in 2014 Conclusions.

Conclusions

• Several activities in TS2 – planning meeting tomorrow morning 9:00 at P2

• LS1: Nov 2012 to September 2014. ALICE plan to complete the TRD and install DCal – several other activities on top

• The ITS, TRD, TPC and Muon activities during LS1 have been presented. The plans for the other detectors will be presented in the next TB

• Services interruption during LS1: LHC plan still under discussion, we will be able to give more details in the coming weeks (restart weekly planning meetings)

• As a general consideration:– 2013 detector & central systems upgrade – several service disruptions– 2014 restart standalone and global commissioning

21/6/12 P2 status, LS1 planning - A.Tauro 20