  • 5/26/2018 PMP QUIZ 4

    1/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    1

    If the NPV is $30,000 for project X and $50,000 for project Y, what is the opportunity costif project Y is selected in preference to project X

    A. $50,000

    B. $20,000

    C. $30,000

    D. $75,000

  • 5/26/2018 PMP QUIZ 4

    2/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    2

    Which of the following is notthe primary objective of Integrated Change Control?

    A. Managing change as it occurs

    B. Denying change whenever possible

    C. Influencing factors that cause change

    D. Determining that a change has occurred

  • 5/26/2018 PMP QUIZ 4

    3/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    3

    The outputs of Direct and Manage Project Execution include:

    A. Deliverables and work performance information

    B. Deliverables and performance reports

    C. Performance reports and requested changes

    D. Deliverables and corrective action

  • 5/26/2018 PMP QUIZ 4

    4/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    4

    Which of the following is true regarding NPV?

    A. NPV assumes reinvestment at the prevailing rate

    B. NPV assumes reinvestment at the NPV rate

    C. NPV assumes reinvestment at the cost of capital

    D. NPV decisions should be made based on the highest value for all of the selections

  • 5/26/2018 PMP QUIZ 4

    5/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    5

    Which definition best describes cost aggregation?

    A. Aggregating the costs associated with work packages back to a single point

    in time to eliminate the time value of money

    B. Multiplying the costs with each work package by a multiplier to calculate

    the needed reserve

    C. Adding the costs associated with each work package back up to the

    parent nodes on the WBS to ultimately get a total project cost

    D. A risk management technique to view costs and their risks by an

    aggregated group instead of by an individual work package

  • 5/26/2018 PMP QUIZ 4

    6/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    6

    Which of the following makes up the project scope baseline?

    A. The WBS, project scope statement, and WBS dictionary

    B. The project scope statement

    C. The scope management plan, the WBS, and the WBS dictionary

    D. The scope management plan and WBS

  • 5/26/2018 PMP QUIZ 4

    7/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    7

    The Project Management Plan contains all the following except:

    A. Project Scope Statement

    B. Cost baseline

    C. Resource calendar

    D. Risk register

  • 5/26/2018 PMP QUIZ 4

    8/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    8

    A technical decision is causing conflict with the project team which in turn, is affectingteam performance. What is the best source of power the project manager could use to

    bring about cooperation?

    A. Referent

    B. Expert

    C. Penalty

    D. Legitimate

  • 5/26/2018 PMP QUIZ 4

    9/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    9

    You have been brought in to take over a project that is already underwayand iscurrently executing the work. Some of the deliverables are being done by sub-

    contractors, and you want to know what performance metrics are to be tracked for these

    contractors. Where would you find this information?

    A. The work breakdown structure

    B. The project charter

    C. The organization chart

    D. The procurement management plan

  • 5/26/2018 PMP QUIZ 4

    10/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    10

    Which of the following best characterizes Six Sigma?

    A. Asserts that quality must be a continuous way of doing business

    B. Stipulates that quality must be managed in

    C. Focuses on improving the quality of people first, then improving the quality of the

    process or project

    D. Focuses on process improvement and variation reduction by using a measurement-

    based strategy

  • 5/26/2018 PMP QUIZ 4

    11/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    11

    If there is more than one critical path on a project, which of the following must also betrue?

    A. The schedule should be crashed in order to resolve the conflict

    B. The situation should be fast-tracked in order to resolve the conflict

    C. Only one path will ultimately emerge as the true critical path

    D. The schedule risk will be higher with multiple critical paths than with one

  • 5/26/2018 PMP QUIZ 4

    12/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    12

    The Delphi technique is used primarily to provide:

    A. Analytical hierarchy process

    B. Intuitive expert opinion

    C. Extrapolated guess

    D. Extrapolation from historical records

  • 5/26/2018 PMP QUIZ 4

    13/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    13

    Your company is soliciting bids for your projects product sales material and advertising. Arepresentative from one of the bidding organizations invites you to attend a sports event

    at their expense to ask questions about your product. How should you respond?

    A. Accept his offer, but tell him in advance that you cant answer questions about the

    product

    B. Reject the offer and invite the sales representative to pose his questions at the

    bidders conference

    C. Attend the event, answer all questions, then write a report on the questions andanswers and submit to the other bidders

    D. Attend the event and discuss the project as requested

  • 5/26/2018 PMP QUIZ 4

    14/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    14

    One of your team members has an attendance problem. You have scheduled severalmeetings to discuss this with them, but they always give a reason why they cannot

    attend. Which conflict management technique is the member exhibiting?

    A. Covering up

    B. Aggressive-avoiding

    C. Withdrawing

    D. Diverting

  • 5/26/2018 PMP QUIZ 4

    15/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    15

    Which of the following is a process within the Execution process group?

    A. Define Activities

    B. Develop Schedule

    C. Report Performance

    D. Distribute Information

  • 5/26/2018 PMP QUIZ 4

    16/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    16

    Senior management has requested that your project use an extra copyrighted documentthey obtained via the internet. It will not be sold or read outside of your organization. As

    the project manager, you should:

    A. As the document is outside the scope, continue the project without it

    B. Investigate obtaining permission from the author to use the document

    C. Use the document as requested by senior management

    D. Submit the request to the change control board

    PMP E P i Q i

  • 5/26/2018 PMP QUIZ 4

    17/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    17

    A project plan is:

    A. A formal, approved document used to guide both project execution and project

    control

    B. A document issued by senior management that provides the project manager with

    the authority to apply organizational resources to project activities

    C. A narrative description of products or services to be supplied

    D. A document describing the organizational breakdown structure of the company

    PMP E P i Q i

  • 5/26/2018 PMP QUIZ 4

    18/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    18

    You are managing two projects, each for a different customer. While working with one,you discover a sensitive piece of information that would save the other customer

    significant cost on their project budget. What should you do?

    A. Excuse yourself from both projects if possible

    B. Share the information with the other customer if it increases project value

    C. Disclose your conflict of interest and keep the information confidential

    D. Act in accordance with any legal documents you have signed

    PMP E P i Q i

  • 5/26/2018 PMP QUIZ 4

    19/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    19

    Which of the following would a project manager employ to ensure the team know clearlywhat work is included in their activities?

    A. A WBS dictionary

    B. A project charter

    C. A project scope of work

    D. A risk management plan

    PMP E P i Q i

  • 5/26/2018 PMP QUIZ 4

    20/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    20

    Communication via email is considered:

    A. Formal written communication

    B. Informal non-verbal communication

    C. Informal written communication

    D. Formal electronic communication

    PMP E P i Q i

  • 5/26/2018 PMP QUIZ 4

    21/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    21

    Control charts are:

    A. Used to define a statistical sample

    B. Used to chart a projects expected value

    C. Used in product review

    D. Used to determine if a process is in control

    PMP E P i Q i

  • 5/26/2018 PMP QUIZ 4

    22/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    22

    What is the difference between a standard and a regulation?

    A. A standard usually should be followed, and a regulation must be followed

    B. There is no appreciable difference between a standard and a regulation

    C. A standard is issued by ANSI and a regulation is issued by the government

    D. A standard is an input into quality planning, while a regulation is an input intoinitiation

    PMP E P i Q i

  • 5/26/2018 PMP QUIZ 4

    23/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    23

    Progressive elaboration is defined as:

    A. Developing in steps and continuing by increments

    B. Increasing the accuracy of estimates from phase to phase

    C. Estimating detailed product specifications at the lowest level of work

    D. Increasing the scope of work over time

    PMP E P i Q i

  • 5/26/2018 PMP QUIZ 4

    24/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    24

    An unplanned risk has just occurred on your project. You meet with experts anddetermine a workaround to keep the project on track. In which process are you engaged?

    A. Plan Risk Responses

    B. Perform Qualitative Risk Analysis

    C. Perform Quantitative Risk Analysis

    D. Monitor and Control Risks

    PMP E P i Q i

  • 5/26/2018 PMP QUIZ 4

    25/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    25

    A parametric estimate would be achieved by applying:

    A. Consensus

    B. An educated guess

    C. Historic data

    D. A mathematical formula

    PMP E P i Q i

  • 5/26/2018 PMP QUIZ 4

    26/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    26

    Three-sigma deviation from the mean is equal to:

    A. 97%

    B. 73%

    C. 99.7%

    D. 97%

    PMP E am Primer Q i

  • 5/26/2018 PMP QUIZ 4

    27/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    27

    When, in project planning, would you decide to change the project scope in order toavoid certain high-risk activities?

    A. Plan Risk Responses

    B. Risk Qualification

    C. Risk Identification

    D. Risk Monitoring

    PMP Exam Primer Quiz

  • 5/26/2018 PMP QUIZ 4

    28/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    28

    A list of the risks that could affect the project is developed as part of which process?

    A. Plan Risk Management

    B. Identify Risks

    C. Plan Risk Responses

    D. Monitor and Control Risks

    PMP Exam Primer Quiz

  • 5/26/2018 PMP QUIZ 4

    29/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    29

    A statement of work is:

    A. Necessary for every project

    B. A description of the projects product

    C. A type of contract

    D. A description of the part of a product to be obtained from an outside vendor

    PMP Exam Primer Quiz

  • 5/26/2018 PMP QUIZ 4

    30/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    30

    A disadvantage of a cost reimbursable contract for the seller is that the buyer needs to:

    A. Audit sellers costs

    B. Write a detailed scope of work

    C. Pay more per month

    D. Constantly evaluate the fee it is paying

    PMP Exam Primer Quiz

  • 5/26/2018 PMP QUIZ 4

    31/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    31

    How does PMI define leadership?

    A. The ability to get things done

    B. Developing a vision and strategy

    C. Communicating the vision and leading from the front

    D. Creating critical results to shareholder satisfaction

    PMP Exam Primer Quiz

  • 5/26/2018 PMP QUIZ 4

    32/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    32

    You are responsible for a project being carried out under a time and materials contract,and you are forecasting its completion well below the original contracts estimated cost

    hence reducing your organization's revenue. What will you do?

    A. Implement additional checks to improve the delivered product quality

    B. Complete the project for the reduced cost

    C. Recommend a number of extra functions that could be added to increase the cost

    D. Organize training events for the project to utilise the surplus

    PMP Exam Primer Quiz

  • 5/26/2018 PMP QUIZ 4

    33/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    33

    During cost control, performance reviews areprimarilyused to:

    A. Review the status of cost information against the plan

    B. Meet with the customer to evaluate and enforce satisfaction

    C. Evaluate new budget change requests to determine if they would have an adverse

    effect on the project performance

    D. Discuss the project and give the team a chance to voice any concerns

    PMP Exam Primer Quiz

  • 5/26/2018 PMP QUIZ 4

    34/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    34

    During executing the work packages, one of your team expresses concern about thevalidity of the estimates for her activities. What action should you takefirst?

    A. Ask another team member with appropriate expertise to perform a peer review on

    the estimates to establish the validity of the concern

    B. Advise the team member that planning has been completed, and ask them to do

    their best to keep to the original estimates

    C. Review the supporting detail for those estimates contained in the project plan to

    remind yourself how they were originally derived

    D. Temporarily stop execution and ask the team member for updated estimates

    PMP Exam Primer Quiz

  • 5/26/2018 PMP QUIZ 4

    35/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    35

    During the execution phase of your project, your company starts to make use of controlchartscontrol charts will help you to:

    A. Determine if a process is performing within its operational tolerances

    B. Explore a desired future outcome

    C. Focus on most critical issues to improve quality

    D. Focus on stimulated brainstormed thinking

    PMP Exam Primer Quiz

  • 5/26/2018 PMP QUIZ 4

    36/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    36

    In a cost plus fixed fee-contract, the fee:

    A. Is waivered

    B. Never changes

    C. Will always decrease

    D. May change as a result of change orders

    PMP Exam Primer Quiz

  • 5/26/2018 PMP QUIZ 4

    37/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    37

    Which of the following statements is trueregarding risk management?

    A. All known risks should be listed in the risk management plan

    B. Identified risks should be added to the risk register

    C. Negative risks should be qualified, while positive risks should be quantified

    D. The risks that cannot be mitigated should be removed from the register

    PMP Exam Primer Quiz

  • 5/26/2018 PMP QUIZ 4

    38/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    38

    _____________ is notemphasised in project quality management

    A. Prevention over inspection

    B. Processes split within phases

    C. Team responsibility

    D. Customer satisfaction

    PMP Exam Primer Quiz

  • 5/26/2018 PMP QUIZ 4

    39/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    39

    What level of authority does a project manager have in a Balanced Matrix structure?

    A. Low to moderate

    B. Little or none

    C. Moderate to high

    D. Limited to within a Stage

    PMP Exam Primer Quiz

  • 5/26/2018 PMP QUIZ 4

    40/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    40

    The system that supports all aspects of the project management processes frominitiating through to closing is:

    A. The work authorization system

    B. Information technology system

    C. The information distribution system

    D. The project management information system

    PMP Exam Primer Quiz

  • 5/26/2018 PMP QUIZ 4

    41/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    41

    It has been discovered that a risk was not identified during risk planning.What must you dofirst?

    A. Look for ways to mitigate the risk

    B. Assess the risk

    C. Stop work on the project

    D. Modify the risk management plan accordingly

    PMP Exam Primer Quiz

  • 5/26/2018 PMP QUIZ 4

    42/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    42

    Who issues the quality policy?

    A. A standards body

    B. The stakeholders

    C. The project manager

    D. The performing organization

    PMP Exam Primer Quiz

  • 5/26/2018 PMP QUIZ 4

    43/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    43

    The verification of scope should occur:

    A. Once during planning

    B. During each phase of the project

    C. At the beginning of the project

    D. At the end of the project

    PMP Exam Primer Quiz

  • 5/26/2018 PMP QUIZ 4

    44/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    44

    The work results of the project:

    A. Are only considered work results if quality standards have been met

    B. Are an output of the work authorization system

    C. Are always products

    D. Are products, services, or results

    PMP Exam Primer Quiz

  • 5/26/2018 PMP QUIZ 4

    45/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    45

    You have received the sponsors approval for the scope statement.What is the nextstep to be taken?

    A. Create the network diagram

    B. Create a work breakdown structure

    C. Develop the product description

    D. Hold the kickoff meeting

    PMP Exam Primer Quiz

  • 5/26/2018 PMP QUIZ 4

    46/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    46

    You have been waiting for several days for a status report from a project team member.You get it one hour before you meet with your manager for a status meeting. After

    quickly scanning the report, you realize it contains bogus information. What action

    should you now take?

    A. Cancel the meeting, fix the report yourself, and circulate the new report to senior

    management in lieu of the meeting

    B. Reschedule the meeting for a later date and get the team member to

    rewrite the report

    C. Bring your team member with you to the meeting, and confront them with the report

    inaccuracies

    D. Fix what you can in the report before the meeting, and try to steer the meeting away

    from the incorrect areas.

    PMP Exam Primer Quiz

  • 5/26/2018 PMP QUIZ 4

    47/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    47

    Project Management is the application of:

    A. Knowledge, skills, experience and techniques

    B. Knowledge, skills, processes and techniques

    C. Knowledge, experience, processes and techniques

    D. Knowledge, skills, tools and techniques

    PMP Exam Primer Quiz

  • 5/26/2018 PMP QUIZ 4

    48/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    48

    The concept of optimal quality level being reached at the point where the incrementalrevenue from product improvement equals the incremental cost to secure it is:

    A. Conformance analysis

    B. Standard quality analysis

    C. Quality control analysis

    D. Marginal analysis

    PMP Exam Primer Quiz

  • 5/26/2018 PMP QUIZ 4

    49/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    49

    A project charter will always include:

    A. A detailed budget

    B. Historical information

    C. The detailed business need underlying the project

    D. The scope management plan

    PMP Exam Primer Quiz

  • 5/26/2018 PMP QUIZ 4

    50/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    50

    The schedule activity list:

    A. Is synonymous with the work breakdown structure

    B. Is included in the project charter

    C. Serves as an extension of the work breakdown structure

    D. Is used to create the project scope statement

    PMP Exam Primer Quiz

  • 5/26/2018 PMP QUIZ 4

    51/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    51

    The quality policy is important in quality management because:

    A. It provides specific quality standards that may be used to measure the

    output of the project

    B. It details the constraints and assumptions the project must take into consideration

    C. It defines the performing organizations formal position on quality

    D. It helps benchmark the project against other similar projects

    PMP Exam Primer Quiz

  • 5/26/2018 PMP QUIZ 4

    52/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    52

    You are dealing with the risks on your project by developing options to enhance theopportunities and reduce the threats to the project objectives. Which process are you

    using?

    A. Identify Risks

    B. Plan Risk Responses

    C. Risk Management Planning

    D. Perform Qualitative Risk Analysis

    PMP Exam Primer Quiz

  • 5/26/2018 PMP QUIZ 4

    53/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    53

    The peak point of Maslows hierarchy is called:

    A. Self-actualization

    B. The need for association

    C. Attainment of survival

    D. Physiological satisfaction

    PMP Exam Primer Quiz

  • 5/26/2018 PMP QUIZ 4

    54/80

    david shillito david litten

    PMP Exam Primer QuizPass First

    Time

    54

    If a project has a 60% chance of a $100,000 profit and a 40% chance of a $100,000 loss,the expected monetary value for the project is:

    A. $40,000 loss

    B. $20,000 profit

    C. $100,000 profit

    D. $60,000 loss

    PMP Exam Primer Quiz

  • 5/26/2018 PMP QUIZ 4

    55/80

    david shillito david litten

    QPass First

    Time

    55

    Which of the following is not a Project Management Knowledge Area?

    A. Time Management

    B. Risk Management

    C. Change Management

    D. Integration Management

    PMP Exam Primer Quiz

  • 5/26/2018 PMP QUIZ 4

    56/80

    david shillito david litten

    QPass First

    Time

    56

    If the Optimistic duration of an activity = 21 days, and the Pessimistic estimate is 29 days,what is the realistic estimate?

    A. 24

    B. 25

    C. 26

    D. Unknown Sneaky!you needed the most likely

    figure to complete the calculation!

    PMP Exam Primer Quiz

  • 5/26/2018 PMP QUIZ 4

    57/80

    david shillito david litten

    QPass First

    Time

    57

    Bringing the whole project team and the customer onto the same site to work together,is an example of:

    A. Active partnerships

    B. Non-distributed working

    C. Collocation

    D. Single-point communication

    PMP Exam Primer Quiz

  • 5/26/2018 PMP QUIZ 4

    58/80

    david shillito david litten

    Pass First

    Time

    58

    The key roles of the Steering Group has in a project is to:

    A. Discuss the technical issues

    B. Help plan the tasks

    C. Ensure the right resources are available

    D. Help prevent changes to the project deliverables

    PMP Exam Primer Quiz

  • 5/26/2018 PMP QUIZ 4

    59/80

    david shillito david litten

    Pass First

    Time

    59

    Activity estimates should be developed by:

    A. The person or team doing the work

    B. Senior Management

    C. The Project Manager

    D. The Customer

    PMP Exam Primer Quiz

  • 5/26/2018 PMP QUIZ 4

    60/80

    david shillito david litten

    Pass First

    Time

    60

    Herzberg identified factors which, if present, will lead to increased motivation. A typicalfactor would be:

    A. Good salary

    B. Regular promotions

    C. Good supervision

    D. Health care

    PMP Exam Primer QuizP Fi

  • 5/26/2018 PMP QUIZ 4

    61/80

    david shillito david litten

    Pass First

    Time

    61

    Whose job is it to resolve competing objectives and goals between parties on theproject?

    A. The project manager

    B. Senior management

    C. The stakeholders

    D. The sponsor

    PMP Exam Primer QuizP Fi t

  • 5/26/2018 PMP QUIZ 4

    62/80

    david shillito david litten

    Pass First

    Time

    62

    Which of the following is nota constructive team role?

    A. Clarifier

    B. Gate keeper

    C. Withdrawer

    D. Information seeker

    PMP Exam Primer QuizP Fi t

  • 5/26/2018 PMP QUIZ 4

    63/80

    david shillito david litten

    Pass First

    Time

    63

    A project is best defined as:

    A. A collection of tasks and products with a beginning and an objective

    B. A significant change with objectives and a time frame

    C. A temporary endeavour undertaken to provide a unique product,

    service or result

    D. A set of activities carried out by a project manager

    PMP Exam Primer QuizP Fi t

  • 5/26/2018 PMP QUIZ 4

    64/80

    david shillito david litten

    Pass First

    Time

    64

    A risk register is created during:

    A. Identify Risks

    B. Risk Assessment

    C. Risk Monitoring and Control

    D. Risk Management Planning

    PMP Exam Primer QuizP Fi t

  • 5/26/2018 PMP QUIZ 4

    65/80

    david shillito david litten

    Pass First

    Time

    65

    The organization type where the project manager is in charge of the projects and has

    primary responsibility for the resources is:

    A. Matrix

    B. Projectized

    C. Hierarchical

    D. Functional

    PMP Exam Primer QuizPass First

  • 5/26/2018 PMP QUIZ 4

    66/80

    david shillito david litten

    Pass First

    Time

    66

    The Create WBS process belongs to which group:

    A. Planning Process Group

    B. Initiation Process Group

    C. Executing Process Group

    D. Monitoring and Controlling Process Group

    PMP Exam Primer QuizPass First

  • 5/26/2018 PMP QUIZ 4

    67/80

    david shillito david litten

    Pass First

    Time

    67

    Approved budget increases should be:

    A. Added to the projects cost baseline

    B. Added to the contingency budget reserve fund

    C. Added to the variance budget

    D. Added to the schedule management plan

    PMP Exam Primer QuizPass First

  • 5/26/2018 PMP QUIZ 4

    68/80

    david shillito david litten

    Pass First

    Time

    68

    Your customer, your sponsor, and senior management have directed you to manage a

    project that will have a large negative impact upon the economy and society. Despite

    sharing your concerns, all parties still insist that you proceed. What should you do?

    A. Contact PMI

    B. Manage the project, but document your objections

    C. Manage the project because all parties agree

    D. Refuse to manage the project

    PMP Exam Primer QuizPass First

  • 5/26/2018 PMP QUIZ 4

    69/80

    david shillito david litten

    Pass First

    Time

    69

    Which of the following contract types places the greatest risk upon the seller?

    A. Cost-plus-fixed-fee contract

    B. Fixed-price-incentive-fee contract

    C. Firm-fixed-price contract

    D. Cost-plus-incentive-fee contract

    PMP Exam Primer QuizPass First

  • 5/26/2018 PMP QUIZ 4

    70/80

    david shillito david litten

    Pass First

    Time

    70

    Who should the project manager consult if they are unsure who has the

    authority to approve changes?

    A. The scope statement

    B. The sponsor

    C. The customer

    D. The scope management plan

    PMP Exam Primer QuizPass First

  • 5/26/2018 PMP QUIZ 4

    71/80

    david shillito david litten

    Pass First

    Time

    71

    Which of the following is not used in Perform Quality Control?

    A. Histograms

    B. Benchmarking

    C. Pareto charts

    D. Statistical sampling

    PMP Exam Primer QuizPass First

  • 5/26/2018 PMP QUIZ 4

    72/80

    david shillito david litten

    Pass First

    Time

    72

    Which of the following techniques is used to control the project schedule?

    A. Statistical sampling

    B. Parametric modelling

    C. Performance measurement

    D. Pareto diagram

    PMP Exam Primer QuizPass First

  • 5/26/2018 PMP QUIZ 4

    73/80

    david shillito david litten

    Pass First

    Time

    73

    Which of the following process sequences are correct?

    A. Cost Budgeting, Cost Estimating, then Create WBS

    B. Create WBS, Determine Budget, then Plan Costs

    C. Create WBS, Estimate Costs, then Determine Budget

    D. Estimate Costs, Determine Budget, then Create WBS

    PMP Exam Primer QuizPass First

  • 5/26/2018 PMP QUIZ 4

    74/80

    david shillito david litten

    Pass First

    Time

    74

    If earned value is $12,000, planned value is $9,000, and actual cost is $4,000, what is the

    schedule variance?

    A. $5,000

    B. $3,000

    C. $1000

    D. -$1000

    PMP Exam Primer QuizPass First

  • 5/26/2018 PMP QUIZ 4

    75/80

    david shillito david litten

    Pass First

    Time

    75

    If budgeted at complete is $1000, estimate to complete is $900, earned value is $250,

    and actual cost is $250, what is the estimate at complete?

    A. $500

    B. $750

    C. $1000

    D. $300

    PMP Exam Primer QuizPass First

  • 5/26/2018 PMP QUIZ 4

    76/80

    david shillito david litten

    Pass First

    Time

    76

    Which of the following would not be a strategy for dealing with negative risk?

    A. Share

    B. Avoid

    C. Mitigate

    D. Transfer

    PMP Exam Primer QuizPass First

  • 5/26/2018 PMP QUIZ 4

    77/80

    david shillito david litten

    Pass First

    Time

    77

    Which of the following is a constructive team role?

    A. Devils advocate

    B. Information seeker

    C. Recognition seeker

    D. Blocker

    PMP Exam Primer QuizPass First

  • 5/26/2018 PMP QUIZ 4

    78/80

    david shillito david litten

    Pass First

    Time

    78

    Your product has been reviewed against the scope, and now needs formal acceptance by

    the customer. Which process is the project in?

    A. Scope Closure

    B. Scope Auditing

    C. Scope Closure

    D. Verify Scope

    PMP Exam Primer QuizPass First

  • 5/26/2018 PMP QUIZ 4

    79/80

    david shillito david litten

    Pass First

    Time

    79

    Crashing differs from fast-tracking because crashing:

    A. Usually increases the cost

    B. Usually saves more time

    C. Usually increases value

    D. Usually saves more money

    PMP Exam Primer QuizPass First

  • 5/26/2018 PMP QUIZ 4

    80/80

    david shillito david litten

    Time

    Which quality process is performed first?

    A. Define Quality

    B. Perform Quality Control

    C. Plan Quality

    D. Perform Quality Assurance