Date post: | 15-Oct-2015 |
Category: |
Documents |
Upload: | rasputin0780803494 |
View: | 46 times |
Download: | 0 times |
of 80
5/26/2018 PMP QUIZ 4
1/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
1
If the NPV is $30,000 for project X and $50,000 for project Y, what is the opportunity costif project Y is selected in preference to project X
A. $50,000
B. $20,000
C. $30,000
D. $75,000
5/26/2018 PMP QUIZ 4
2/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
2
Which of the following is notthe primary objective of Integrated Change Control?
A. Managing change as it occurs
B. Denying change whenever possible
C. Influencing factors that cause change
D. Determining that a change has occurred
5/26/2018 PMP QUIZ 4
3/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
3
The outputs of Direct and Manage Project Execution include:
A. Deliverables and work performance information
B. Deliverables and performance reports
C. Performance reports and requested changes
D. Deliverables and corrective action
5/26/2018 PMP QUIZ 4
4/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
4
Which of the following is true regarding NPV?
A. NPV assumes reinvestment at the prevailing rate
B. NPV assumes reinvestment at the NPV rate
C. NPV assumes reinvestment at the cost of capital
D. NPV decisions should be made based on the highest value for all of the selections
5/26/2018 PMP QUIZ 4
5/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
5
Which definition best describes cost aggregation?
A. Aggregating the costs associated with work packages back to a single point
in time to eliminate the time value of money
B. Multiplying the costs with each work package by a multiplier to calculate
the needed reserve
C. Adding the costs associated with each work package back up to the
parent nodes on the WBS to ultimately get a total project cost
D. A risk management technique to view costs and their risks by an
aggregated group instead of by an individual work package
5/26/2018 PMP QUIZ 4
6/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
6
Which of the following makes up the project scope baseline?
A. The WBS, project scope statement, and WBS dictionary
B. The project scope statement
C. The scope management plan, the WBS, and the WBS dictionary
D. The scope management plan and WBS
5/26/2018 PMP QUIZ 4
7/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
7
The Project Management Plan contains all the following except:
A. Project Scope Statement
B. Cost baseline
C. Resource calendar
D. Risk register
5/26/2018 PMP QUIZ 4
8/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
8
A technical decision is causing conflict with the project team which in turn, is affectingteam performance. What is the best source of power the project manager could use to
bring about cooperation?
A. Referent
B. Expert
C. Penalty
D. Legitimate
5/26/2018 PMP QUIZ 4
9/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
9
You have been brought in to take over a project that is already underwayand iscurrently executing the work. Some of the deliverables are being done by sub-
contractors, and you want to know what performance metrics are to be tracked for these
contractors. Where would you find this information?
A. The work breakdown structure
B. The project charter
C. The organization chart
D. The procurement management plan
5/26/2018 PMP QUIZ 4
10/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
10
Which of the following best characterizes Six Sigma?
A. Asserts that quality must be a continuous way of doing business
B. Stipulates that quality must be managed in
C. Focuses on improving the quality of people first, then improving the quality of the
process or project
D. Focuses on process improvement and variation reduction by using a measurement-
based strategy
5/26/2018 PMP QUIZ 4
11/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
11
If there is more than one critical path on a project, which of the following must also betrue?
A. The schedule should be crashed in order to resolve the conflict
B. The situation should be fast-tracked in order to resolve the conflict
C. Only one path will ultimately emerge as the true critical path
D. The schedule risk will be higher with multiple critical paths than with one
5/26/2018 PMP QUIZ 4
12/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
12
The Delphi technique is used primarily to provide:
A. Analytical hierarchy process
B. Intuitive expert opinion
C. Extrapolated guess
D. Extrapolation from historical records
5/26/2018 PMP QUIZ 4
13/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
13
Your company is soliciting bids for your projects product sales material and advertising. Arepresentative from one of the bidding organizations invites you to attend a sports event
at their expense to ask questions about your product. How should you respond?
A. Accept his offer, but tell him in advance that you cant answer questions about the
product
B. Reject the offer and invite the sales representative to pose his questions at the
bidders conference
C. Attend the event, answer all questions, then write a report on the questions andanswers and submit to the other bidders
D. Attend the event and discuss the project as requested
5/26/2018 PMP QUIZ 4
14/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
14
One of your team members has an attendance problem. You have scheduled severalmeetings to discuss this with them, but they always give a reason why they cannot
attend. Which conflict management technique is the member exhibiting?
A. Covering up
B. Aggressive-avoiding
C. Withdrawing
D. Diverting
5/26/2018 PMP QUIZ 4
15/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
15
Which of the following is a process within the Execution process group?
A. Define Activities
B. Develop Schedule
C. Report Performance
D. Distribute Information
5/26/2018 PMP QUIZ 4
16/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
16
Senior management has requested that your project use an extra copyrighted documentthey obtained via the internet. It will not be sold or read outside of your organization. As
the project manager, you should:
A. As the document is outside the scope, continue the project without it
B. Investigate obtaining permission from the author to use the document
C. Use the document as requested by senior management
D. Submit the request to the change control board
PMP E P i Q i
5/26/2018 PMP QUIZ 4
17/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
17
A project plan is:
A. A formal, approved document used to guide both project execution and project
control
B. A document issued by senior management that provides the project manager with
the authority to apply organizational resources to project activities
C. A narrative description of products or services to be supplied
D. A document describing the organizational breakdown structure of the company
PMP E P i Q i
5/26/2018 PMP QUIZ 4
18/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
18
You are managing two projects, each for a different customer. While working with one,you discover a sensitive piece of information that would save the other customer
significant cost on their project budget. What should you do?
A. Excuse yourself from both projects if possible
B. Share the information with the other customer if it increases project value
C. Disclose your conflict of interest and keep the information confidential
D. Act in accordance with any legal documents you have signed
PMP E P i Q i
5/26/2018 PMP QUIZ 4
19/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
19
Which of the following would a project manager employ to ensure the team know clearlywhat work is included in their activities?
A. A WBS dictionary
B. A project charter
C. A project scope of work
D. A risk management plan
PMP E P i Q i
5/26/2018 PMP QUIZ 4
20/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
20
Communication via email is considered:
A. Formal written communication
B. Informal non-verbal communication
C. Informal written communication
D. Formal electronic communication
PMP E P i Q i
5/26/2018 PMP QUIZ 4
21/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
21
Control charts are:
A. Used to define a statistical sample
B. Used to chart a projects expected value
C. Used in product review
D. Used to determine if a process is in control
PMP E P i Q i
5/26/2018 PMP QUIZ 4
22/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
22
What is the difference between a standard and a regulation?
A. A standard usually should be followed, and a regulation must be followed
B. There is no appreciable difference between a standard and a regulation
C. A standard is issued by ANSI and a regulation is issued by the government
D. A standard is an input into quality planning, while a regulation is an input intoinitiation
PMP E P i Q i
5/26/2018 PMP QUIZ 4
23/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
23
Progressive elaboration is defined as:
A. Developing in steps and continuing by increments
B. Increasing the accuracy of estimates from phase to phase
C. Estimating detailed product specifications at the lowest level of work
D. Increasing the scope of work over time
PMP E P i Q i
5/26/2018 PMP QUIZ 4
24/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
24
An unplanned risk has just occurred on your project. You meet with experts anddetermine a workaround to keep the project on track. In which process are you engaged?
A. Plan Risk Responses
B. Perform Qualitative Risk Analysis
C. Perform Quantitative Risk Analysis
D. Monitor and Control Risks
PMP E P i Q i
5/26/2018 PMP QUIZ 4
25/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
25
A parametric estimate would be achieved by applying:
A. Consensus
B. An educated guess
C. Historic data
D. A mathematical formula
PMP E P i Q i
5/26/2018 PMP QUIZ 4
26/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
26
Three-sigma deviation from the mean is equal to:
A. 97%
B. 73%
C. 99.7%
D. 97%
PMP E am Primer Q i
5/26/2018 PMP QUIZ 4
27/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
27
When, in project planning, would you decide to change the project scope in order toavoid certain high-risk activities?
A. Plan Risk Responses
B. Risk Qualification
C. Risk Identification
D. Risk Monitoring
PMP Exam Primer Quiz
5/26/2018 PMP QUIZ 4
28/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
28
A list of the risks that could affect the project is developed as part of which process?
A. Plan Risk Management
B. Identify Risks
C. Plan Risk Responses
D. Monitor and Control Risks
PMP Exam Primer Quiz
5/26/2018 PMP QUIZ 4
29/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
29
A statement of work is:
A. Necessary for every project
B. A description of the projects product
C. A type of contract
D. A description of the part of a product to be obtained from an outside vendor
PMP Exam Primer Quiz
5/26/2018 PMP QUIZ 4
30/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
30
A disadvantage of a cost reimbursable contract for the seller is that the buyer needs to:
A. Audit sellers costs
B. Write a detailed scope of work
C. Pay more per month
D. Constantly evaluate the fee it is paying
PMP Exam Primer Quiz
5/26/2018 PMP QUIZ 4
31/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
31
How does PMI define leadership?
A. The ability to get things done
B. Developing a vision and strategy
C. Communicating the vision and leading from the front
D. Creating critical results to shareholder satisfaction
PMP Exam Primer Quiz
5/26/2018 PMP QUIZ 4
32/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
32
You are responsible for a project being carried out under a time and materials contract,and you are forecasting its completion well below the original contracts estimated cost
hence reducing your organization's revenue. What will you do?
A. Implement additional checks to improve the delivered product quality
B. Complete the project for the reduced cost
C. Recommend a number of extra functions that could be added to increase the cost
D. Organize training events for the project to utilise the surplus
PMP Exam Primer Quiz
5/26/2018 PMP QUIZ 4
33/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
33
During cost control, performance reviews areprimarilyused to:
A. Review the status of cost information against the plan
B. Meet with the customer to evaluate and enforce satisfaction
C. Evaluate new budget change requests to determine if they would have an adverse
effect on the project performance
D. Discuss the project and give the team a chance to voice any concerns
PMP Exam Primer Quiz
5/26/2018 PMP QUIZ 4
34/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
34
During executing the work packages, one of your team expresses concern about thevalidity of the estimates for her activities. What action should you takefirst?
A. Ask another team member with appropriate expertise to perform a peer review on
the estimates to establish the validity of the concern
B. Advise the team member that planning has been completed, and ask them to do
their best to keep to the original estimates
C. Review the supporting detail for those estimates contained in the project plan to
remind yourself how they were originally derived
D. Temporarily stop execution and ask the team member for updated estimates
PMP Exam Primer Quiz
5/26/2018 PMP QUIZ 4
35/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
35
During the execution phase of your project, your company starts to make use of controlchartscontrol charts will help you to:
A. Determine if a process is performing within its operational tolerances
B. Explore a desired future outcome
C. Focus on most critical issues to improve quality
D. Focus on stimulated brainstormed thinking
PMP Exam Primer Quiz
5/26/2018 PMP QUIZ 4
36/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
36
In a cost plus fixed fee-contract, the fee:
A. Is waivered
B. Never changes
C. Will always decrease
D. May change as a result of change orders
PMP Exam Primer Quiz
5/26/2018 PMP QUIZ 4
37/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
37
Which of the following statements is trueregarding risk management?
A. All known risks should be listed in the risk management plan
B. Identified risks should be added to the risk register
C. Negative risks should be qualified, while positive risks should be quantified
D. The risks that cannot be mitigated should be removed from the register
PMP Exam Primer Quiz
5/26/2018 PMP QUIZ 4
38/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
38
_____________ is notemphasised in project quality management
A. Prevention over inspection
B. Processes split within phases
C. Team responsibility
D. Customer satisfaction
PMP Exam Primer Quiz
5/26/2018 PMP QUIZ 4
39/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
39
What level of authority does a project manager have in a Balanced Matrix structure?
A. Low to moderate
B. Little or none
C. Moderate to high
D. Limited to within a Stage
PMP Exam Primer Quiz
5/26/2018 PMP QUIZ 4
40/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
40
The system that supports all aspects of the project management processes frominitiating through to closing is:
A. The work authorization system
B. Information technology system
C. The information distribution system
D. The project management information system
PMP Exam Primer Quiz
5/26/2018 PMP QUIZ 4
41/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
41
It has been discovered that a risk was not identified during risk planning.What must you dofirst?
A. Look for ways to mitigate the risk
B. Assess the risk
C. Stop work on the project
D. Modify the risk management plan accordingly
PMP Exam Primer Quiz
5/26/2018 PMP QUIZ 4
42/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
42
Who issues the quality policy?
A. A standards body
B. The stakeholders
C. The project manager
D. The performing organization
PMP Exam Primer Quiz
5/26/2018 PMP QUIZ 4
43/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
43
The verification of scope should occur:
A. Once during planning
B. During each phase of the project
C. At the beginning of the project
D. At the end of the project
PMP Exam Primer Quiz
5/26/2018 PMP QUIZ 4
44/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
44
The work results of the project:
A. Are only considered work results if quality standards have been met
B. Are an output of the work authorization system
C. Are always products
D. Are products, services, or results
PMP Exam Primer Quiz
5/26/2018 PMP QUIZ 4
45/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
45
You have received the sponsors approval for the scope statement.What is the nextstep to be taken?
A. Create the network diagram
B. Create a work breakdown structure
C. Develop the product description
D. Hold the kickoff meeting
PMP Exam Primer Quiz
5/26/2018 PMP QUIZ 4
46/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
46
You have been waiting for several days for a status report from a project team member.You get it one hour before you meet with your manager for a status meeting. After
quickly scanning the report, you realize it contains bogus information. What action
should you now take?
A. Cancel the meeting, fix the report yourself, and circulate the new report to senior
management in lieu of the meeting
B. Reschedule the meeting for a later date and get the team member to
rewrite the report
C. Bring your team member with you to the meeting, and confront them with the report
inaccuracies
D. Fix what you can in the report before the meeting, and try to steer the meeting away
from the incorrect areas.
PMP Exam Primer Quiz
5/26/2018 PMP QUIZ 4
47/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
47
Project Management is the application of:
A. Knowledge, skills, experience and techniques
B. Knowledge, skills, processes and techniques
C. Knowledge, experience, processes and techniques
D. Knowledge, skills, tools and techniques
PMP Exam Primer Quiz
5/26/2018 PMP QUIZ 4
48/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
48
The concept of optimal quality level being reached at the point where the incrementalrevenue from product improvement equals the incremental cost to secure it is:
A. Conformance analysis
B. Standard quality analysis
C. Quality control analysis
D. Marginal analysis
PMP Exam Primer Quiz
5/26/2018 PMP QUIZ 4
49/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
49
A project charter will always include:
A. A detailed budget
B. Historical information
C. The detailed business need underlying the project
D. The scope management plan
PMP Exam Primer Quiz
5/26/2018 PMP QUIZ 4
50/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
50
The schedule activity list:
A. Is synonymous with the work breakdown structure
B. Is included in the project charter
C. Serves as an extension of the work breakdown structure
D. Is used to create the project scope statement
PMP Exam Primer Quiz
5/26/2018 PMP QUIZ 4
51/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
51
The quality policy is important in quality management because:
A. It provides specific quality standards that may be used to measure the
output of the project
B. It details the constraints and assumptions the project must take into consideration
C. It defines the performing organizations formal position on quality
D. It helps benchmark the project against other similar projects
PMP Exam Primer Quiz
5/26/2018 PMP QUIZ 4
52/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
52
You are dealing with the risks on your project by developing options to enhance theopportunities and reduce the threats to the project objectives. Which process are you
using?
A. Identify Risks
B. Plan Risk Responses
C. Risk Management Planning
D. Perform Qualitative Risk Analysis
PMP Exam Primer Quiz
5/26/2018 PMP QUIZ 4
53/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
53
The peak point of Maslows hierarchy is called:
A. Self-actualization
B. The need for association
C. Attainment of survival
D. Physiological satisfaction
PMP Exam Primer Quiz
5/26/2018 PMP QUIZ 4
54/80
david shillito david litten
PMP Exam Primer QuizPass First
Time
54
If a project has a 60% chance of a $100,000 profit and a 40% chance of a $100,000 loss,the expected monetary value for the project is:
A. $40,000 loss
B. $20,000 profit
C. $100,000 profit
D. $60,000 loss
PMP Exam Primer Quiz
5/26/2018 PMP QUIZ 4
55/80
david shillito david litten
QPass First
Time
55
Which of the following is not a Project Management Knowledge Area?
A. Time Management
B. Risk Management
C. Change Management
D. Integration Management
PMP Exam Primer Quiz
5/26/2018 PMP QUIZ 4
56/80
david shillito david litten
QPass First
Time
56
If the Optimistic duration of an activity = 21 days, and the Pessimistic estimate is 29 days,what is the realistic estimate?
A. 24
B. 25
C. 26
D. Unknown Sneaky!you needed the most likely
figure to complete the calculation!
PMP Exam Primer Quiz
5/26/2018 PMP QUIZ 4
57/80
david shillito david litten
QPass First
Time
57
Bringing the whole project team and the customer onto the same site to work together,is an example of:
A. Active partnerships
B. Non-distributed working
C. Collocation
D. Single-point communication
PMP Exam Primer Quiz
5/26/2018 PMP QUIZ 4
58/80
david shillito david litten
Pass First
Time
58
The key roles of the Steering Group has in a project is to:
A. Discuss the technical issues
B. Help plan the tasks
C. Ensure the right resources are available
D. Help prevent changes to the project deliverables
PMP Exam Primer Quiz
5/26/2018 PMP QUIZ 4
59/80
david shillito david litten
Pass First
Time
59
Activity estimates should be developed by:
A. The person or team doing the work
B. Senior Management
C. The Project Manager
D. The Customer
PMP Exam Primer Quiz
5/26/2018 PMP QUIZ 4
60/80
david shillito david litten
Pass First
Time
60
Herzberg identified factors which, if present, will lead to increased motivation. A typicalfactor would be:
A. Good salary
B. Regular promotions
C. Good supervision
D. Health care
PMP Exam Primer QuizP Fi
5/26/2018 PMP QUIZ 4
61/80
david shillito david litten
Pass First
Time
61
Whose job is it to resolve competing objectives and goals between parties on theproject?
A. The project manager
B. Senior management
C. The stakeholders
D. The sponsor
PMP Exam Primer QuizP Fi t
5/26/2018 PMP QUIZ 4
62/80
david shillito david litten
Pass First
Time
62
Which of the following is nota constructive team role?
A. Clarifier
B. Gate keeper
C. Withdrawer
D. Information seeker
PMP Exam Primer QuizP Fi t
5/26/2018 PMP QUIZ 4
63/80
david shillito david litten
Pass First
Time
63
A project is best defined as:
A. A collection of tasks and products with a beginning and an objective
B. A significant change with objectives and a time frame
C. A temporary endeavour undertaken to provide a unique product,
service or result
D. A set of activities carried out by a project manager
PMP Exam Primer QuizP Fi t
5/26/2018 PMP QUIZ 4
64/80
david shillito david litten
Pass First
Time
64
A risk register is created during:
A. Identify Risks
B. Risk Assessment
C. Risk Monitoring and Control
D. Risk Management Planning
PMP Exam Primer QuizP Fi t
5/26/2018 PMP QUIZ 4
65/80
david shillito david litten
Pass First
Time
65
The organization type where the project manager is in charge of the projects and has
primary responsibility for the resources is:
A. Matrix
B. Projectized
C. Hierarchical
D. Functional
PMP Exam Primer QuizPass First
5/26/2018 PMP QUIZ 4
66/80
david shillito david litten
Pass First
Time
66
The Create WBS process belongs to which group:
A. Planning Process Group
B. Initiation Process Group
C. Executing Process Group
D. Monitoring and Controlling Process Group
PMP Exam Primer QuizPass First
5/26/2018 PMP QUIZ 4
67/80
david shillito david litten
Pass First
Time
67
Approved budget increases should be:
A. Added to the projects cost baseline
B. Added to the contingency budget reserve fund
C. Added to the variance budget
D. Added to the schedule management plan
PMP Exam Primer QuizPass First
5/26/2018 PMP QUIZ 4
68/80
david shillito david litten
Pass First
Time
68
Your customer, your sponsor, and senior management have directed you to manage a
project that will have a large negative impact upon the economy and society. Despite
sharing your concerns, all parties still insist that you proceed. What should you do?
A. Contact PMI
B. Manage the project, but document your objections
C. Manage the project because all parties agree
D. Refuse to manage the project
PMP Exam Primer QuizPass First
5/26/2018 PMP QUIZ 4
69/80
david shillito david litten
Pass First
Time
69
Which of the following contract types places the greatest risk upon the seller?
A. Cost-plus-fixed-fee contract
B. Fixed-price-incentive-fee contract
C. Firm-fixed-price contract
D. Cost-plus-incentive-fee contract
PMP Exam Primer QuizPass First
5/26/2018 PMP QUIZ 4
70/80
david shillito david litten
Pass First
Time
70
Who should the project manager consult if they are unsure who has the
authority to approve changes?
A. The scope statement
B. The sponsor
C. The customer
D. The scope management plan
PMP Exam Primer QuizPass First
5/26/2018 PMP QUIZ 4
71/80
david shillito david litten
Pass First
Time
71
Which of the following is not used in Perform Quality Control?
A. Histograms
B. Benchmarking
C. Pareto charts
D. Statistical sampling
PMP Exam Primer QuizPass First
5/26/2018 PMP QUIZ 4
72/80
david shillito david litten
Pass First
Time
72
Which of the following techniques is used to control the project schedule?
A. Statistical sampling
B. Parametric modelling
C. Performance measurement
D. Pareto diagram
PMP Exam Primer QuizPass First
5/26/2018 PMP QUIZ 4
73/80
david shillito david litten
Pass First
Time
73
Which of the following process sequences are correct?
A. Cost Budgeting, Cost Estimating, then Create WBS
B. Create WBS, Determine Budget, then Plan Costs
C. Create WBS, Estimate Costs, then Determine Budget
D. Estimate Costs, Determine Budget, then Create WBS
PMP Exam Primer QuizPass First
5/26/2018 PMP QUIZ 4
74/80
david shillito david litten
Pass First
Time
74
If earned value is $12,000, planned value is $9,000, and actual cost is $4,000, what is the
schedule variance?
A. $5,000
B. $3,000
C. $1000
D. -$1000
PMP Exam Primer QuizPass First
5/26/2018 PMP QUIZ 4
75/80
david shillito david litten
Pass First
Time
75
If budgeted at complete is $1000, estimate to complete is $900, earned value is $250,
and actual cost is $250, what is the estimate at complete?
A. $500
B. $750
C. $1000
D. $300
PMP Exam Primer QuizPass First
5/26/2018 PMP QUIZ 4
76/80
david shillito david litten
Pass First
Time
76
Which of the following would not be a strategy for dealing with negative risk?
A. Share
B. Avoid
C. Mitigate
D. Transfer
PMP Exam Primer QuizPass First
5/26/2018 PMP QUIZ 4
77/80
david shillito david litten
Pass First
Time
77
Which of the following is a constructive team role?
A. Devils advocate
B. Information seeker
C. Recognition seeker
D. Blocker
PMP Exam Primer QuizPass First
5/26/2018 PMP QUIZ 4
78/80
david shillito david litten
Pass First
Time
78
Your product has been reviewed against the scope, and now needs formal acceptance by
the customer. Which process is the project in?
A. Scope Closure
B. Scope Auditing
C. Scope Closure
D. Verify Scope
PMP Exam Primer QuizPass First
5/26/2018 PMP QUIZ 4
79/80
david shillito david litten
Pass First
Time
79
Crashing differs from fast-tracking because crashing:
A. Usually increases the cost
B. Usually saves more time
C. Usually increases value
D. Usually saves more money
PMP Exam Primer QuizPass First
5/26/2018 PMP QUIZ 4
80/80
david shillito david litten
Time
Which quality process is performed first?
A. Define Quality
B. Perform Quality Control
C. Plan Quality
D. Perform Quality Assurance