+ All Categories
Home > Documents > Power Sector Opportunities

Power Sector Opportunities

Date post: 04-Apr-2018
Category:
Upload: amit-sharma
View: 226 times
Download: 0 times
Share this document with a friend

of 81

Transcript
  • 7/29/2019 Power Sector Opportunities

    1/81

    Power Sector - Opportunities

  • 7/29/2019 Power Sector Opportunities

    2/81

    Agenda

    Evolution of the Indian Power Sector

    Industry Structure and Present Scenario

    Thermal Power Projects

    Hydro Power Projects

    Renewable Energy Projects

    Transmission

    Distribution

    Conclusion

  • 7/29/2019 Power Sector Opportunities

    3/81

    Evolution of the Indian Power Sector

    Industry Structure and Present Scenario

    Generation - Thermal Power Projects

    Generation - Hydro Power Projects

    Generation Renewable Energy Projects

    Transmission

    Distribution

    Conclusion

  • 7/29/2019 Power Sector Opportunities

    4/81

    Earlier Structure and Liberalisation

    Introduction of Independent Power Producers (IPPs)

    Facilitated Private Participation in Power sector

    Foreign ownership up to 100% was allowed

    Facilitated tapping of domestic and foreign capital markets, provided assured returnson investment and reduced legal hassles to allow the private investors to set-upgeneration capacities or operate as licensee in distribution segments, which werehitherto a monopoly of the SEBs

    Development of the power sector has traditionally been the responsibility of theCentral & State Utilities

    Govt. utilities (SEB) monopoly buyers

    Poor financial health of SEBs mainly due to Low tariff & High commercial losses (theft)

    Minimal Participation by Private Sector

    Earlier Structure failed

    Liberalised policy (post 1991)

  • 7/29/2019 Power Sector Opportunities

    5/81

    Post-liberalisation Developments

    1991

    Competitive

    Bidding

    Guidelines /

    UMPPsElectricity

    Act 2003CERC &

    SERCs set

    upMega

    Power

    Policy

    Liberalisation

    National

    Tariff

    policy

    National

    Hydro

    Policy

    1995

    1998

    2003

    2005

    2006

    2008

    Introduced

    Open Access

    Revised

    Mega

    Power

    Policy

    2009

  • 7/29/2019 Power Sector Opportunities

    6/81

    Mega Power Policy

    Mega power projects are entitled to several concessions and benefits, such as

    Exemption from customs duty on imports of equipment Refund of terminal excise duty paid by various domestic supplier on supply of equipments and

    material based on Deemed Export Benefit

    - In order to qualify for the mega power project status power to be sold to more than one state

    and thermal power projects would have to have power plant of a capacity of 1,000 MW or

    more located in states other than Jammu & Kashmir and NE states

    The power purchasing States have constituted the Regulatory commission with full powers to fixtariffs;

    The power purchasing States shall undertake to carry out distribution reforms as laid down by

    the Ministry of Power.

    Modification to the Mega Power Policy* (2009)

    The existing condition of privatization of distribution by power purchasing states has

    been replaced by the condition that power purchasing states shall undertake to carry

    out distribution reforms as laid down by the Ministry of Power.

    The conditions requiring inter-state sale of power for getting mega power status has

    been removed.

    *Another round of modification is being discussed, to be announced shortly.

  • 7/29/2019 Power Sector Opportunities

    7/81

    Electricity Act 2003

    Encouraging investment by introducing competition and reforming distribution

    Reduction in entry barriers by:

    Delicensing generation

    Freedom to the captive generation and group captives

    Recognition of trading as separate activity

    Introduction of Open Access

    Open access to consumers consuming more than 1 MW by January 2009; Multiple licenses in distribution;

    Setting up of regulatory commission to fix tariff and develop the sector

    Independent Regulatory Commissions in the States as well as in the Center

    Freeing up of thermal generation from the requirement of any prior approvals/

    license

    Full freedom for setting up captive power plants including group captive plants

    Competitively bid generation tariffs to be accepted by Regulatory Commissions.

    Power purchase costs of customers availing open access to be market determined.

  • 7/29/2019 Power Sector Opportunities

    8/81

    Competitive Bidding Guidelines

    Objective To ensure competitive tariffs, financial turnaround and commercial

    viability of state utilities and providing electricity at reasonable rate

    Opening the sector for private sector participation by introducing competitive

    bidding as the basis for all future projects (except for Central & State Utilities)

    Enforcing adoption of multi-year tariffs by all regulatory commissions

    Tariff benchmarks discovered through competitive bidding has primarily replaced

    the cost-plus method of tariff determination with effect from January 2011 Case 1: Plant location & Fuel independent

    Tariff in recent bids in Noida have been bid at Rs 4/unit

    Recent bids in Rajasthan, Maharashtra, Gujarat have been upwards of Rs 3/unit

    Adani Power bid Rs 3.25/ unit in Rajasthan; Adani Power, Indiabulls & GMR bid Rs 3.3/unit, Rs

    3.27/unit and Rs 2.88/unit resp. in Maharashtra

    Case 2: Plant location and Fuel type fixed

    Recent long term tariffs determined via Case 2 have also been around Rs 3/unit

    Many states have taken up the Case 2 bidding route for meeting their power requirements

    Some recent Case 2 bids won are: Jaypee groups winning bids of Rs 2.97/unit and Rs 3.02/unit

    for Karchana and Bara project in UP, and L&Ts Rs 2.89/unit bid for Rajapura project in Punjab

  • 7/29/2019 Power Sector Opportunities

    9/81

    Evolution of the Indian Power Sector

    Industry Structure and Present Scenario

    Generation - Thermal Power Projects

    Generation - Hydro Power Projects

    Generation Renewable Energy Projects

    Transmission

    Distribution

    Conclusion

  • 7/29/2019 Power Sector Opportunities

    10/81

    Industry Structure

    State Sector

    Generation

    Central Sector Private Sector

    SEBs, GENCOs NTPC, NHPC,

    NPCIL, DVC,

    Neyveli Lignite

    Torrent, Essar,

    Reliance,Tata, GMR,

    Jaypee, GVK, Jindal,

    JSW, Lanco, Adani

    PGCIL

    Inter State

    Transmission

    Intra State

    Transmission

    Trading

    SEBs, TRANSCOs

    PTC, Tata, NTPC,

    Adani, Reliance, GMR

    Distribution SEBs, DISCOMs Reliance, TATA,

    CESC, Torrent

    Policy &Regulation

    Ministry of Power / *Central Electricity Authority / Central & StateElectricity Regulatory Commissions

    *CERC is the regulatory body for matter related to tariff and other issues whereas CEA is the

    authority related to technical matters and overall planning

  • 7/29/2019 Power Sector Opportunities

    11/81

    Power Scenario in India

    0

    500

    1000

    1500

    2000

    2500

    3000

    1991 2001 2005 2006 2008 2010 2012 World

    Per Capita consumption of Power

    1991 2001 2005 2006 2008 2010 2012 World

    Total installed capacity as on

    December 2011 is 1,86,655

    MW

    Thermal (Coal + Gas + Diesel):

    122,964 MW (67% of total)

    Hydro: 38,748 MW (21% of total)

    Nuclear: 4,780 MW (3% of total)

    Renewable: 20,162 MW (11% oftotal)

    Per capita consumption in

    India is low at 733 kWh as

    compared to Chinas 2,180

    kWh, USAs ~13,000 kwh and

    current world average at 2,750kWh

    Under its Power for all by

    2012 initiative GoI aims to

    increase Indias per capita

    consumption to 1,000 kWh

    As on December 11

    Coal , 56%

    Gas, 10%

    Diesel,

    1%

    Nuclear, 3%

    Hydro, 21%

    Renewable

    11%

    Installed Capacity (MW)

    Coal

    Gas

    Diesel

    Nuclear

    Hydro

    Renewable

  • 7/29/2019 Power Sector Opportunities

    12/81

    1)SVL TPP, U-1 (63 MW) of SV Power Ltd. has beencommissioned successfully (i.e. Achieving of full load) on

    07-12-2011

    2) Kasaipalli TPP , U-1 (135 MW) of ACB India Ltd. has

    been commissioned successfully (i.e.Achieving of fullload) on 13-12-2011

    3)Sipat St-1 STPP, U-2 (660 MW) of NTPC Ltd. has been

    commissioned successfully ( Full load) on 24-12-11

    4) Coal based Rosa TPS, U-3 (300 MW) of Rosa PowerSupply Company Ltd has been commissioned successfully

    ( Full load) on 28-12-2011

    UNITS COMMISSIONED, DURING DECEMBER. 11

    12

  • 7/29/2019 Power Sector Opportunities

    13/81

    The total electricity

    generation in the countryincreased from 558 Billion

    Units (BU) during 2003-04 to

    788 BU during 2010-11

    However, the Deficit is still

    high at:

    Energy Deficit: 8.5%

    Peaking Deficit: 9.8%

    Deficit still at high levels due

    to

    Slow capacity addition owing to

    delay in equipment supply

    Heavy congestion on

    Transmission corridors

    Huge AT&C losses in

    distribution sector around

    27% at national level.

    Power shortages remain high

    0

    20

    40

    60

    80

    100

    0

    15,000

    30,000

    45,000

    60,000

    75,000

    90,000

    1st 2nd 3rd 4th 5th 6th 7th 8th 9th 10th 11th

    Sluggish historical performance

    in 5-yr plans

    Target Achieved % Shortfall

    0%

    5%

    10%

    15%

    20%

    0

    200

    400

    600

    800

    1000

    2005-06 2006-07 2007-08 2008-09 2009-10 2010-11

    Bn

    units

    Demand-Supply

    Demand Supply %Shortage %Peaking Shortage

  • 7/29/2019 Power Sector Opportunities

    14/81

    Power: Key Sector for Investment

    Targeted generation capacity addition

    for the 11th Five Year plan is 78,577

    MW

    Till December 2011, approx. 45,927

    MW (59.39% of planned capacity) has

    already been commissioned and

    around 63,000 MW of total capacity

    is expected to be commissioned by

    2012 with high level surety.

    Hydro, 15627

    Nuclear, 3380

    Coal, 52850

    Gas, 6843

    Thermal

    76%

    11th Plan: 78,577 MW to be added

    Year Target (MW) Achieved (MW) Achieved (%)

    2007-08 16,335 9,263 56.71%

    2008-09 11,061 3,454 31.23%

    2009-10 14,507 9,585 66.07%

    2010-11 21,441 12,160 56.71%

    2011-12* 13,989 11,465 81.96%

    *As on December 2011

  • 7/29/2019 Power Sector Opportunities

    15/81

    Punjab, Rajasthan, Haryana, Delhi

    Maharashtra and Andhra Pradesh

    have been among the top buyersof the traded power

    Presently there are two power

    exchanges in India namely Indian

    Energy Exchange (IEX) and Power

    Exchange of India (PXIL). The total

    number of power trading license

    holders in India as on March 2010

    is 45.

    High Volume of Power is Trading in

    price band Rs 4-6/unit in recent

    years

    From 2012-2017, huge peak

    shortage and capacity shortfall will

    lead to rise in merchant tariffs

    Power Trading & Merchant Tariffs

    0%

    1%

    2%

    3%

    4%

    5%

    0

    5

    10

    15

    20

    25

    30

    35

    40BUs

    Increasing Power trading volumes

    Traded Power (BUs)

    Traded Power as % of Generated

    4.16

    7.046.37

    7.57

    5.73

    6.89

    4.99

    0

    2

    4

    6

    8

    2007 2008 2009

    Price of Short term Transactions

    Traders Power Exchanges UI

  • 7/29/2019 Power Sector Opportunities

    16/81

    Generation Capacity in US

    US and India

    Coal , 30.06%

    Gas, 41.31%

    Nuclear,9.37%

    Oil, 5.49%

    Hydro, 8.67%Other, 5.10%

    Coal

    Gas

    Nuclear

    Oil

    Hydro

    Other

    Fuel Type Capacity in MW

    Coal 342,296Gas 470,344

    Nuclear 106,731

    Oil 62,504

    Hydro 98,742

    Other 58,021

    Total 1,138,638

    As on December 2010

    Coal , 56%

    Gas, 10%

    Diesel,

    1%

    Nuclear, 3%

    Hydro, 21%

    Renewable

    11%

    Generation Capacity in India

    Coal

    Gas

    Diesel

    Nuclear

    Hydro

    Renewable

    Fuel Type Capacity in MW

    Coal 1,04,021

    Gas 17,743

    Nuclear 4,780

    Oil (Diesel) 1,200

    Hydro 38,748

    Other 20,162

    Total 186,655As on December 2011

  • 7/29/2019 Power Sector Opportunities

    17/81

    197

    276

    387

    543

    762

    206

    303

    445

    655

    962

    215

    331

    510

    785

    1207

    0 200 400 600 800 1000 1200 1400

    2011-12

    2016-17

    2021-22

    2026-27

    2031-32

    Installed Capacity in GW

    Capacity addition by 2030: MoP

    9% GDP

    8% GDP

    7% GDP

    States like UP, Haryana, Bihar, Gujarat, Maharashtra faced huge peak deficit and this is

    likely to continue in future if capacity addition is not made on time.

    Indian Power Sector: Future Target

  • 7/29/2019 Power Sector Opportunities

    18/81

    To achieve the 11th and 12th Plan target, the required rate of capacity

    addition to be ~5 times the present rate.

    A total of about Rs. 650,000 Crore would be required by generation

    segment alone during the 12th plan period.

    Traded power volumes have grown at the CAGR of 59% and short term

    power are being traded in Rs. 4-6 /kWh

    Imported coal requirement will rise in future

    Gas based plants will increase in number subject to timely availability of

    domestic natural gas from various fields under development.

    Future Outlook

  • 7/29/2019 Power Sector Opportunities

    19/81

    Evolution of the Indian Power Sector

    Industry Structure and Present Scenario

    Generation - Thermal Power Projects

    Generation - Hydro Power Projects

    Generation Renewable Energy Projects

    Transmission

    Distribution

    Conclusion

  • 7/29/2019 Power Sector Opportunities

    20/81

    Overview of Thermal Power

    Thermal

    Coal

    Imported

    Domestic

    Captive Coal

    Linkage Coal

    Gas

    Domestic

    R-LNG

    Oil

    Key source of power in India with around 66% of installed Capacity contributing more

    than 70% of the units produced

  • 7/29/2019 Power Sector Opportunities

    21/81

    Key Challenges Thermal Power Projects

    Land Acquisition Issues and procedural delays

    Agricultural Land

    Land

    Domestic Coal Availability Volatile markets for Imported Coal

    Changing regulations in source countries (Indonesia / Australia)

    Domestic Gas Availability

    High costs of R-LNG

    Fuel

    Environmental Clearance

    Forest Clearance (Go / No-Go Areas for Coal)

    Clearances

  • 7/29/2019 Power Sector Opportunities

    22/81

    Large Coal Reserves are available in

    Orissa, Jharkhand & Chhattisgarh.

    Majority of the proven reserves has

    is of the Low Grade Non-Coking Coal

    suitable for power generation.

    Reserves in Mn tons

    Balance : Total reserves minus that given out as captive allocation and expectedrequirement for linkages upto 2012

    Fuel supply scenario: Coal Reserves in India

    Depth (m) Proved Indicated Inferred Total % share

    0-300 82,771 65,784 13,760 1,62,315 60.7%

    300-600 7,661 45,453 18,105 71,219 26.7%

    0-600 (for Jharia only) 13,710 502 0 14,212 5.3%

    600-1200 1,678 11,730 6,056 19,464 7.3%

    Total 1,05,820 1,23,469 37,921 2,67,210

    Category-wise & Depth-wise Resources as of Apr 2009

  • 7/29/2019 Power Sector Opportunities

    23/81

    India is the 3rd largest producer of coal in the world after China and USA

    Coal caters to 53% of the total countrys energy needs

    Domestic coal pricing is regulated by Ministry of Coal

    Coal India Ltd. produces around 80% of the total coal in the country.

    power sector is the major consumer of coal, consuming approximately 73% of the coal

    produced. In 2009-10, approximately 88% of the coal consumed was from domestic

    production and around 12 % was imported.

    Coal Production & Imports

    347.1 375.5398.7 422.6

    459.6 487.8

    1222

    25 28

    3544

    11%

    7% 6%

    10%

    8%

    0%

    5%

    10%

    15%

    0

    200

    400

    600

    FY05 FY06 FY07 FY08 FY09 FY10

    Million tonnesCoal Production

    Production (Mn MT) Imports (Mn MT) % Change

  • 7/29/2019 Power Sector Opportunities

    24/81

    Fuel supply scenario : Natural Gas

    Sector Total (Firm+Fall

    back (MMSCMD)

    Power 43.17

    Fertilizer 15.51

    CGD 2.83

    Steel 4.19

    Refineries 11.00

    Petrochemicals 1.918

    LPG 3.00

    Captive Power 10.00

    Total 91.61

    Gas Allocation from RILs KG D-6

    Going forward, natural gas supply in the country is expected to increase due to production

    from RILs KG D6 field, KG basin satellite fields, NEC field; GSPCs KG Block, ONGCs KG block

    and Mahanadi field and upcoming and expansion of LNG facilities

    Projected Gas Supply

  • 7/29/2019 Power Sector Opportunities

    25/81

    Financing Options

    Rupee term Loan

    Most widely used source of financing SBI is at the forefront of RTL financing

    NBFC

    IDFC, PFC, IL&FS, REC has been actively participating in funding of

    Power Projects

    ECA

    EXIM Banks financing the export of equipment

    KEXIM funding for Mundra UMPP

    BoC recently sanctioned ECA facility for Sasan UMPPs

    External Commercial Borrowing (ECB)

    Funding via ECB route permitted

    However, issues related to tenor / project risks has led to lessparticipation

  • 7/29/2019 Power Sector Opportunities

    26/81

    Key Risks & Mitigation

    Risk Mitigation

    Fuel Availability Conditions Precedents to Drawdown Timelines for fuel arrangement (Including transportation & handling) Adjustment of Debt Equity vis--vis increased fuel costs impact

    Land Acquisition

    R&R issues are extremely important Can lead to considerable delays if not addressed adequately Conditions Precedent for main plant, ash pond and green belt

    Approvals/

    Clearances

    Environment / Forest / Coastal Regulation Zone/ Pollution Control asconditions precedent

    Off-take risk Long term power purchase agreements crucial Minimum Quantum for long term tie-up to be assessed

    Cost overrun/Delays Fixed price lump sum construction contracts with adequate LDs preferred Cost overrun undertaking by promoters

    Performance Adequate Liquidated Damages / Rectification clauses in contracts

    Evacuation Assessment of available transmission network Adequate stipulations to cover evacuation risks

  • 7/29/2019 Power Sector Opportunities

    27/81

    Ultra Mega Power Projects

    Ministry of Power (MOP) initiated UMPP Process

    MoP, CEA and Power Finance Corporation working together for developmentof seven ULTRA MEGA POWER PROJECTS under tariff based competitive

    bidding route

    Awarded on Build, Own and Operate (BOO) basis

    Capacity of 4000MW each with scope of further expansion at Pithead or

    Coastal Locations Faster Capacity Addition with Crashed Timelines

    Lower Pollution on account of more efficient technology

    Economies of Scale and Availability of Power at Cheaper Rate

    Bid Process: Three stage bid process EoI, Request for Qualification and Request for Participation

  • 7/29/2019 Power Sector Opportunities

    28/81

    Ultra Mega Power Projects

    Projects Envisaged (Pithead as well as Imported Coal Based)

    4 Awarded:

    Coastal Gujarat Power Limited , Mundra (Gujarat)

    Transferred to Tata Power Limited in April 2007.

    Levellized Tariff : Rs. 2.26 per Unit.

    Financial Agreement Signed in April 2008.

    Sasan Power Limited, Sasan (Madhya Pradesh)

    Transferred to Reliance Power Limited in August 2007 Levellized Tariff : Rs. 1.196 per Unit.

    Financial Agreement Signed in April 2009.

    Coastal Andhra Power Limited, Krishnapatnam (Andhra Pradesh)

    Transferred to Reliance Power Limited in January 2008.

    Levellized Tariff : Rs. 2.33 per Unit. Jharkhand Integrated Power Limited, Near Tilaiya Dam (Jharkhand)

    LOI Awarded to Reliance Power Limited in February 2009.

    Levellized Tariff : Rs. 1.77 per Unit.

    2 in Bid Stage: Bedabahal, Sarguja

  • 7/29/2019 Power Sector Opportunities

    29/81

    Evolution of the Indian Power Sector

    Industry Structure and Present Scenario

    Generation - Thermal Power Projects

    Generation - Hydro Power Projects

    Generation Renewable Energy Projects

    Transmission

    Distribution

    Conclusion

  • 7/29/2019 Power Sector Opportunities

    30/81

    Development of Indian Hydropower Sector

    1897

    Sidrapong Hydel Power Station, Darjeeling

    (Oldest Hydel Power Plant in India)

    1991

    Private Sector Participation inGeneration

    1998

    Policy on HydropowerDevelopment

    CEA Vision Document &Ranking of Schemes totaling

    1,07,000 MW

    20012003

    PMs 50,000 MW

    Hydroelectric Initiative100% foreignparticipation

    1992

    Inter Institutional Group

    comprising SBI, ICICI, LIC, IDBI, IDFCformed

    2004

    2005

    Guidelines for determination ofTariff based on competitive

    bidding

    Guidelines for development by

    Private developers

    New Hydro Policy

    2008

  • 7/29/2019 Power Sector Opportunities

    31/81

    Hydropower constituted 37,567 MW (21%)

    Public sector has predominant share of ~96% State sector: 73% / Central sector: 23% / Private Sector: ~4%

    Hydro resources predominantly located in northern and north-eastern part of country

    0%

    5%

    10%

    15%

    20%

    25%

    30%

    35%

    40%

    45%

    50%

    0

    20,000

    40,000

    60,000

    80,000

    100,000

    120,000

    140,000

    160,000

    180,000

    1956

    1961

    1966

    1969

    1974

    1979

    1980

    1985

    1990

    1992

    1997

    2002

    2007

    2010

    Percentage

    Installed

    Capacity

    Growth of Hydropower

    Hydro Capacity (MW) Total Capacity (MW) Share of Hydro (%)

    Low hydro-thermal mix in India

    Share of Hydropower in the total installed capacity decreasing (from over 40% in 1960-61 to

    around 22% at present)

    Overview of Hydropower in India

  • 7/29/2019 Power Sector Opportunities

    32/81

    India ranks fifth in the world in terms of usable hydro potential

    Economically exploitable potential assessed at 84,044 MW at 60% load factor(corresponding to an installed capacity of ~149,000 MW)

    Additionally, total pumped storage capacity assessed at 94,000 MW

    RegionFeasible Installed

    Capacity (MW)

    Developed

    Capacity (MW)

    Balance

    Potential (%)

    Northern 53,405 13,623 74%

    Western 8,928 7,447 17%

    Southern 16,446 11,260 32%

    Eastern 10,965 3,882 65%

    North-Eastern 58,956 1,116 98%

    Total 148,700 37,328 75%

    Source: CEA

    Potential of Hydropower in India

  • 7/29/2019 Power Sector Opportunities

    33/81

    Longer gestation period and capital intensive nature of the projects

    Dearth of good contractors for construction Inter-state aspects (incl. issues regarding common river systems)

    Environmental impact and rehabilitation issues

    Valuation of forest land based on net present value

    Law and order problems (have affected projects such as Dulhasti, Upper Sindh, Doyang

    and Dhansiri)

    Land acquisition problems (have seriously affected Thein Dam, Doyang, Ghatgar)

    Geological surprises

    Inadequate power evacuation facilities

    Lack of private sector interest

    Tariff and regulatory issues (free power to state and cost plus approach)

    The barriers above pose higher risk, which is detrimental to private sector participation

    Challenges in Hydropower development

  • 7/29/2019 Power Sector Opportunities

    34/81

    Review by the Standing Committee on Energy, identified following project types

    for private participation: Extension projects where dam & major structures have already been constructed

    Projects at the toe of existing dams

    Run-of-river schemes involving minimum underground works

    Government Initiatives:

    Prime Ministers 50,000 MW Hydroelectric Initiative Streamlining of clearance procedures, provisions of open access and trading as per

    Electricity Act 2003

    guidelines for the development of hydropower project sites by private developers

    PFC is giving loans to private projects for up to 70% of the project cost with max

    repayment period of 20 years with moratorium for construction period + 6 months

    MOP constituted inter-institutional group of FIs with an objective to expedite financialclosure of private sector generation projects and to address last-minute issues

    impeding project development and financing

    MOP has also issued guidelines for tariff based bidding

    GoI initiatives - Encourage private sector

  • 7/29/2019 Power Sector Opportunities

    35/81

    Uttarakhand

    Projects are allocated for initial period of 45 years on a BOOT basis

    Developers of the project have the right to sell the power outside the state No guarantee for purchase of power by state agencies

    12% of electricity generated is to be made available free of cost to the state

    Sikkim

    State Govt has formed the Sikkim Power Development Corporation Ltd (SPDCL), to

    facilitate JV projects between a private developer and government 12% of electricity generated to be made available free of cost to the state

    For JV projects Govt participation ranges from 10% to 49%

    State initiatives - Encourage private sector

    Himachal Pradesh

    Projects up to 100 MW via MoU route and those above 100 MW via ICB route No clearances from CEA for projects, upto Rs 2,500 crores, selected on ICB basis

    Premium on peak power

    100% foreign equity permitted on the automatic approval route provided it exceed

    Rs1,500 crores

    Also for projects above 100 MW installed capacity, the government has reserved the right

    of equity participation up to 49% on a selective basis.

  • 7/29/2019 Power Sector Opportunities

    36/81

    Nepal

    Four hydro schemes Implemented with Indias technical and financial assistance -

    Pokhra, Trisuli, Western and Gandhak and Devighat

    PTC nominated as nodal agency to deal with matters relating to power exchange

    The bilateral exchange of power presently at a level of 50 MW

    Three major multi-purpose projects in Nepal presently under discussion Karnali

    (10,800 MW), Pancheshwar (5,600 MW), and Saptakoshi (3,000 MW)

    Bhutan

    Chukha hydropower project (336 MW) is the 1st Joint Venture between India and

    Bhutan. About 84% of energy generated from Chukha plant is exported to India

    Kurichu Hydroelectric Project (60 MW) implemented with Indian assistance

    Tala Hydroelectric Project (1020 MW) the biggest joint project between India and

    Bhutan. Entire Power is being supplied to India

    DPRs of Wangchu (900 MW) and Bunakha (180 MW) have also been prepared

    India has agreed to provide assistance for development of Mangdechhu (360/600

    MW) and Punatsangchhu (870/1000 MW)

    Regional Cooperation with Neighboring Countries

  • 7/29/2019 Power Sector Opportunities

    37/81

  • 7/29/2019 Power Sector Opportunities

    38/81

    Plant Load Factor(dependent on water

    flow of river)

    Plant Load Factor

    dependent on

    water flow of river

    Potential for

    secondary energy

    Peaking

    Cost & Reliabilityfactors

    Tariff Rates

    State Policies (for

    merchant sales)

    Reliable Surveys

    Access to Site

    Availability of

    Evacuation

    Arrangements

    Technical Aspects

    Overrating to tap

    excess flows

    Availability of land

    & Govt support for

    acquisition

    Environment and

    other clearances

    Regulatory Aspects

    R&R issues

    Investors Perspective

  • 7/29/2019 Power Sector Opportunities

    39/81

    Rupee Term Loan

    Most widely used source of financing

    World Bank

    10 hydropower schemes funded since 1980. Upper Indravati (600 MW),

    Indira Sarovar (500 MW), Sardar Sarovar (1,450 MW), Nathpa Jhakri (1,500

    MW), Lower Periyar (180 MW), Kalinadi River (270 MW), Gerusoppa (240

    MW), Srinagar (330 MW), Koyna IV (1,000 MW)

    IFC has funded 2 hydro projects in India - Allain Duhangan Hydro Project

    (carbon finance) and CF IHDC (small hydro)

    IREDA (Indian Renewable Energy Development Agency)

    Kotla Hydro Power Private Ltd, Punjab: Debt financed by IREDA through the

    World Bank 2nd line of Credit

    Financing Options

  • 7/29/2019 Power Sector Opportunities

    40/81

    ECA/Bilateral

    OECF/JBIC have approved 28 soft loans for hydropower projects since 1978

    incl. Srisailam Left Bank (900 MW), Dhauliganga (280 MW), Purulia (900 MW),

    Nagarjunasagar (960 MW), Teesta Canal (67.5 MW), Tuirial (60 MW), Ghatghar

    (250 MW)

    DFID (former ODA) and SIDA funded the Uri I HEP (480 MW)

    CIDA has granted loans for Idukki (780 MW), Lower Periyar (182 MW), and

    Kuttiyadi (75 MW)

    KFW has approved export credits for Nathpa Jhakri (1,500 MW) and Tehri

    (1,000 MW)

    Hermes covered contracts for Baspa II HEP (300 MW)

    NBFC

    PFC is funding private projects for up to 70% of the project cost with 20 yrsmax repayment period with moratorium for construction period + 6 months

    Teesta III (1200 MW) and Teesta IV (360 MW) promoted by Teesta Urja and

    Lanco respectively.

    Financing Options

  • 7/29/2019 Power Sector Opportunities

    41/81

    Structuring repayments to match

    generation profile

    Adequate cost over run undertaking

    from promoters

    DSCR in range of 1.3 to 1.5

    Structuring mechanisms for sharing

    potential upsides (secondary energy

    and CDM benefits)

    Assessing project viability at 90%

    dependability (primary energy)

    Assessing seasonal flow variation

    and peaking capability

    Secondary Energy and overrating as

    upsides

    CDM benefits for plants above 25

    MW highly unlikely

    Key considerations for financing

  • 7/29/2019 Power Sector Opportunities

    42/81

    Risk Mitigation

    Construction Only established developers with proven track record supported. Same is

    given high weightage during award/ financing

    Rehabilitation &

    Resettlement

    R&R issues are extremely important Can lead to considerable delays if not addressed adequately

    Off-take risk Long term power purchase agreements crucial Projects with dam/pondage can act as peaking stations

    Cost overrun/

    Delays

    Fixed price lump sum construction contracts with adequate LDs preferred Cost overrun undertaking by promoters

    Approvals/

    Clearances

    Implementation agreement, Environment Clearance / forest clearancefrom MoEF - levied as conditions precedent

    Seasonal Variation Repayments structured as per the projected variation and water flows Financing done at P90 / P75 dependability

    Geological

    Uncertainties Sound DPR and extensive site surveys required to be carried out

    Key Risks and Mitigation

  • 7/29/2019 Power Sector Opportunities

    43/81

    Evolution of the Indian Power Sector

    Industry Structure and Present Scenario

    Generation - Thermal Power Projects

    Generation - Hydro Power Projects

    GenerationRenewable Energy Projects

    Transmission

    Distribution

    Conclusion

  • 7/29/2019 Power Sector Opportunities

    44/81

    0 20000 40000 60000 80000 100000

    Solar Power

    Waste to EnergyBiomass

    Cogeneration - Bagasse

    Small Hydro Power

    Wind Power

    Installed Capacity Potential Capacity

    Source: Ministry of Power, Jan 2010

    Renewable Energy Potential in India

    10% of Indias installed capacity is through renewable sources

    Significant Potential for Solar Power in India

  • 7/29/2019 Power Sector Opportunities

    45/81

    Location specific potential

    Seasonal and Time of the Day variation

    Technology Risk

    Prevalent Build-Transfer-Operate model (for wind projects)

    Accelerated Depreciation Benefits

    Generation Based Incentive

    Availability of Carbon Emission Reduction

    Renewable Purchase Obligations

    Proposed Renewable Energy Certificates

    Unique studies like ornithological studies to be carried out in wind

    Salient aspects of Renewable Energy

  • 7/29/2019 Power Sector Opportunities

    46/81

    Benefits Zero cost of fuel and low O&M Cost

    Short gestation period

    Clean energy with no adverseenvironmental effects

    Opportunities

    Indias wind power potential~48.5 GW

    Planned Capacity addition

    11th Plan ~ 10,500 MW

    12th + 13th Plan ~ 22,500 MW

    India has 7,000 km long coast-line withimmense off-shore wind energy potential

    Global majors like Areva, Siemens and GEare queuing up to explore off-shoreopportunities

    India ranked 5th globally with installed capacity ~ 11,807 MW (Mar 31, 2010 )

    Wind energy share in Indias total installed power generation capacity ~ 7 %

    Overview of Wind Power in India

  • 7/29/2019 Power Sector Opportunities

    47/81

    Incentive of 50 paisa /unit supplied

    To be availed within a period of 10 years after commissioning with acap of Rs 62 lakhs per MW, with disbursements not to exceedRs.15.50 lakhs/MW/annum during the first four years

    Maximum capacity limited to the 1st 4000 MW installed upto March

    31, 2012

    Generation Based incentive

    Accelerated depreciation (80 %) on Written Down Value (WDV) basisfor wind mills

    Accelerated Depreciation

    Tax holiday available to an undertaking which begins to generate

    power before March 31, 2012

    Tax Holiday

    Central Govt.

    shall releaseFunds for GBI

    as advance to

    IREDA to

    ensure timely

    release offunds to the

    projects

    Policy Incentives

  • 7/29/2019 Power Sector Opportunities

    48/81

    Rupee term Loan

    Most widely used source of financing SBI is at the forefront of RTL financing First non recourse debt financing for a wind project done through RTL

    External Commercial Borrowing

    Funding via ECB route permitted

    ECB funding in power sector in India has reached USD 1.5 bn in the half yearended Sep 2010

    NBFC

    Active in the Wind Sector

    IDFC, IL&FS, REC, IFC etc have participated in Debt and Equity funding ofWind Energy Projects

    ECA

    EXIM Banks financing the export of equipment

    DEG granted a long-term loan of 15.3 million euros to Bhoruka PowerCorporation Ltd. (2010) in Karnataka

    Financing Options

  • 7/29/2019 Power Sector Opportunities

    49/81

    IREDA

    To give financial support to specific projects and schemes for generatingelectricity and / or energy through new and renewable sources andconserving energy through energy efficiency.

    Nodal Agency: Implementation of Generation Based Incentive andAccelerated Depreciation scheme

    ADB

    Rs 352 Crores to Tata Power Company Ltd. for projects in Maharashtra(2007) 100 MW (Facilities at Ahmednagar & Dhulia)

    Rs 445 Crores to Gujarat Paguthan Energy Corporation (GPEC) for projectsin Gujarat and Karnataka totaling 183 MW (2008)

    World Bank and IFC 37 MW wind project in India with a loan of $33 million for MSPL (16.2MW,

    Kutch, Gujarat & 20.4MW, Karnataka)

    Karnataka Wind Power Carbon Finance Project for Acciona (2009)

    IFC has also funded a number of wind projects globally

    Financing Options

    l b f d

  • 7/29/2019 Power Sector Opportunities

    50/81

    Equity thepromoter is

    willing tocontribute.

    Lenderscomfort level of

    debt to beprovided for the

    project

    Reduction inProject Cost &favorable O&M

    terms

    Debt to Equityratio of 65:35

    DSCR in therange of1.2 to

    1.3

    Optimal Debt: Equity Ratio for Wind Projects

    l h b l

  • 7/29/2019 Power Sector Opportunities

    51/81

    Availing GBI forshorter period

    than thenormal periodwhich is for 4-

    10 years.

    Structuringrepayment

    schedule sothat it is in linewith generation

    profile

    Contract forCERs (Certified

    EmissionReductions)should beentered.

    1 MWh energy generated from a Wind Energy Project is eligible for 0.93 CER

    Balancing ROI with sustainability

    K Ri k & Mi i i

  • 7/29/2019 Power Sector Opportunities

    52/81

    Key Risks & MitigationsRisk Mitigation Measures

    Technology Risk Only CWET certified turbines with proven track record supported.

    EPC contractors of repute with proven track-record in setting up Wind Farmssupported.

    Wind

    availability

    shortfall

    Comprehensive Wind mapping carried out by CWET

    Track record of established nearby wind farms analysed

    Wind assessment study carried out by independent and reputed wind consultants

    Financial appraisal at P75 generation levels

    Seasonality Repayments structured as per the seasonal wind profile

    Approvals &

    Clearances

    Aviation clearance from Airport Authority of India, forest clearance from MoEF, NOC

    from SEB & approval for power evacuation from Transco Incorporated as Pre

    Disbursement Conditions

    Off take risk DisCom Renewable purchase obligations

    High peak deficit in most states Prevailing peak power prices more than wind energy prices

    Introduction of Renewable Energy Certificates.

    Cost & Time

    Overrun

    Comprehensive provision for liquidated damages payable by the EPC contractor

    may be stipulated.

    Promoters undertaking to bear any cost overrun in the Project.

    Performance Stringent clauses for defect liability backed by guarantees

    O i f S l E i I di

  • 7/29/2019 Power Sector Opportunities

    53/81

    Overview of Solar Energy in India

    Most parts receive irradiance of 5-

    7 kWh per sq meter per day

    Average power generationpotential of 20 MW/ sq km

    Sites receiving higher levels of

    insolation: Rajasthan, TN, AP,

    Ladakh, Gujarat

    A i S l E P j Fi i

  • 7/29/2019 Power Sector Opportunities

    54/81

    Technology Risk: Is solar an experimental technology?

    Execution Risk: Can this be done in India?

    Off take Risk: How do we manage payment risk of expensive

    power?

    Obsolescence Risk: Will new low-cost technologies threaten

    payment on existing, high-cost technologies?

    Regulatory Risk: Will solar RPOs be in place and be

    enforceable?

    Assessing Solar Energy Project Financing

    T h l

  • 7/29/2019 Power Sector Opportunities

    55/81

    Photo-Voltaic SOLAR THERMAL

    Most Prevalent Technologies: Photo-Voltaic (PV) & Concentrated

    Solar Power (CSP or Solar Thermal)

    Technology

    S l Ph t lti (PV)

  • 7/29/2019 Power Sector Opportunities

    56/81

    Solar PV

    Crystalline

    Polycrystalline

    Monocrystalline

    Thin Film

    Amorphoussilicon

    CISCadmiumtelluride

    PV- Exposure to light generates electricity

    variants are Wafer Based & Thin Film

    Wafer Efficiency 13% to 20%;

    Thin film Efficiency 6% to 12%

    More than 21,000 MW of installed PV

    capacity worldwide

    Major Suppliers- QCells, FirstSolar, Sharp,

    Suntech, JA Solar, Kyocera, Yingli, Sanyo

    Solar Photovoltiac (PV)

    S l Th l

  • 7/29/2019 Power Sector Opportunities

    57/81

    57

    Efficiencies of about 15%.

    Storage of power using molten salts

    Captures the heat from solar radiation and

    uses BTG

    Physical moving partsWater requirement in dry areas

    Higher O&M

    Parabolic trough/Tower

    Over 700 MW installed capacity world over

    Major technologies

    E-Solar, Abengoa , Acciona, Iberdrola

    Major suppliers

    Solar Thermal

    T h l E l ti F t P fi

  • 7/29/2019 Power Sector Opportunities

    58/81

    CSPHigher-output receiver tubes (replaceable?)

    Low-cost reflectors (replaceable?)

    Higher-temperature, stable towers

    Dish, Fresnel and other technologies will mature

    Storage (low-cost) for 24-hours solar

    Hybrid (integrated with gas, coal, wind, biomass, etc.)

    PVHigher-efficiency C-Si

    Thin-films stabilised, and emergence of CIGS as leaderConcentrators in deployment

    Longer term, nano-dots, full-spectrum PV

    Chinese supply-chain

    Technology Evolution Future-Proofing

    G I I iti ti JNNSM

  • 7/29/2019 Power Sector Opportunities

    59/81

    20000

    MW

    by 2022

    Phase I

    7mn sqm solar collectors, 200 MW off grid capacity & 1000 MW grid power

    Phase II

    15mn sqm solar collectors, 1000 MW off grid capacity and 4-10000 MW grid power

    Phase III

    20mn sqm solar collectors, 2000 MW off grid capacity & 20000 MW grid power

    TARGETS

    MECHANISM

    PV: Rs17.91unit

    CSP: Rs15.31/unitRs2.5/unitx kWh 4x kWh

    Cost of bundled power to NVVN

    PV: (17.91x + 10x)/5x = Rs5.58/unit

    CSP: (15.31x + 10x)/5x = Rs5.06/unit

    Cost of Power to State Utilities for 50:50 ratio of PV and CSP = Rs

    5.32/unit

    5x kWh

    NTPC unallocated powerSolar power developers

    NVVN

    State Utility

    GoI Initiatives JNNSM

    State Initiatives Gujarat a leading state

  • 7/29/2019 Power Sector Opportunities

    60/81

    Minimum project capacity for availing benefits has been fixed at 5 MW for

    both Solar PV and Solar Thermal

    In the 1st round the State had received EoIs for 365MW PV and 351MW CSP

    projects from 34 national and international developers. GUVNL signed PPAs

    for 420MW projects (395MW PV and 25MW CSP) in May 2010

    For the solar thermal projects to be commissioned before Dec 2011, the

    tariff has been fixed at Rs 11 per unit for the first 12 years and Rs 4 per unitfor the rest of the period, for the projects commissioned thereafter up to

    Mar 31, 2014, it is proposed at Rs 9 per unit for first 12 years and Rs 3 per

    unit for the rest of the period

    For the solar PV projects commissioned before Dec 2011, the tariff has been

    fixed at Rs 15 per unit for the first 12 years and Rs 5 per unit for the rest ofthe period, for the projects commissioned thereafter up to Mar 31, 2014, it

    is proposed at Rs 12 per unit for first 12 years and Rs 3 per unit for the rest

    of the period

    State Initiatives Gujarat a leading state

    Financing Options Exploratory Stage

  • 7/29/2019 Power Sector Opportunities

    61/81

    Being a sunrise sector seen lots of investment from PE investors Investments in Azure Power, Sunborne, MoserBaer etc.

    Private Equity Developers

    Support export of materials(KfW, JBIC)

    ECA

    Supporting through direct financing and guarantees to promotethis sector

    Multilateral Agencies

    Have shown keen interest

    Payment security mechanism still being discussed to givegovernment support

    Indian Banks, NBFC (REC, PFC, IREDA)

    Financing Options Exploratory Stage

    Key Risks And Mitigation

  • 7/29/2019 Power Sector Opportunities

    62/81

    Key Risks And Mitigation

    Risk Mitigation

    Technology Only established technologies (compliant with IEC Technical Standard for Solar

    PV systems) and EPC contractors with proven track record supported.

    Offtake risk High risk due to high cost of the power producer. Strong offtaker and Power

    Purchase agreement crucial for development of this sector.

    Land Each MW requires about 5 to 8 acres. However most of this land is

    inhospitable and are in outlying areas.

    Gujarat, Rajasthan, MP developing Solar Park

    Approvals &

    Clearances

    Aviation clearance from AAI, forest clearance from MoEF & approval for power

    evacuation from TransCo Incorporated as Conditions precedent

    Cost & Time

    Overrun

    Comprehensive provisions for liquidated damages may be stipulated as part of

    EPC contract

    Promoters undertaking to bear additional costs stipulated.

    PerformanceShortfall

    Stringent clauses for defect liability. Temperature coefficient stipulated

    Performance Ratio Guarantee to be provided by EPC contractor

    Irradiance Risk Combination of various source of data including MNRE, NASA, Meteonorm at

    conservative levels to be used.

    Seasonal

    Variation

    Repayments structured as per the projected variation

  • 7/29/2019 Power Sector Opportunities

    63/81

    Evolution of the Indian Power Sector

    Industry Structure and Present Scenario

    Generation - Thermal Power Projects

    Generation - Hydro Power Projects

    Generation Renewable Energy Projects

    Transmission

    Distribution

    Conclusion

    Overview Indian Transmission Infrastructure

  • 7/29/2019 Power Sector Opportunities

    64/81

    Overview Indian Transmission Infrastructure

    Transmission Network in India

    Overview Indian Transmission Infrastructure

  • 7/29/2019 Power Sector Opportunities

    65/81

    Overview Indian Transmission Infrastructure

    The complex transmission system comprises236,500 ct. km lines and 305,600 MVA and14,000 MW of substation capacity at 220 kV &above voltages as of March 2010.

    400 KV 77000 ckm and 765 KV 700 ckm

    Transmission network and transformationcapacity grew at 6.4% and 7.5% respectivelyduring the first 3 years of XI plan. [X Plangrowth figures were 6% and 8%]

    Interregional transfer capacity increased to20,750 MW from 14,100 MW at end of X Plan.

    The XI Plan investment is proposed at Rs1,400 billion - Rs 550 billion by Powergrid, Rs

    650 billion by STUs and Rs 200 billion byprivate sector.

    During the first three years of the Plan,Powergrid invested Rs 252 billion (plannedanother Rs 130 billion in 2010-11). STUsinvested Rs 185.84 billion during the first twoyears.

    -

    50,000

    100,000

    150,000

    200,000

    250,000

    2005-06 2006-07 2007-08 2008-09 2009-10*

    59,314 66,579 73,13880,243 87,800

    125,347131,828 136,866

    142,503148,667

    Transmission Lines (ct. km)

    Intra-state Interstate

    -

    100

    200

    300

    400

    2005-06 2006-07 2007-08 2008-09 2009-10*

    39 45 53 60 65

    191 205216 228

    241

    Transformation Capacity ('000 MVA)

    Intra-state Interstate

    *interstate capacity includes 1,440 MVA of private capacity

    *interstate lines includes 1,250 ct. km of private line length

    XI & XII Five Year Plan Targets

  • 7/29/2019 Power Sector Opportunities

    66/81

    XI & XII Five Year Plan Targets

    Voltage Level (kV) XI Plan Target As on Mar 2011Achievement

    (%)XII Plan Target

    765 kV 5,666 2457 43.4 25000-30000HVDC & +/- 500 kV 5,400 3052 56.5 4000-6000

    400 kV 49,278 30611 62.1 50000

    230/220 kV 35,371 20009 56.6 40000

    Total 91875 56129 61.1 119000-126000

    Source: CEA

    XI Plan investments may not fully fructify given the lower than planned generation

    capacity addition expected

    Planned XII Plan investment is Rs 2,400 billion including Rs 1,400 billion in the

    central sector (interstate system) and Rs 1,000 billion in the state sector (intra-state

    system) Achieve synchronization of SR grid with NEW grid [to be achieved with the

    implementation of Synchronous Interconnection between SR and WR]

    Interregional transfer capacity to increase to 32,700 MW by 2011-12 (latest CEA

    estimates) further to 57,000 MW by 2015 and 75,000 MW by 2017

    Private Sector Participation

  • 7/29/2019 Power Sector Opportunities

    67/81

    Private Sector Participation

    Standalone private investment in transmission segment opened up in 1998

    One PPP project Tala transmission system in operation since May 2007

    First ITP (awarded in Oct 2007) under implementation by RPTL to come up by July 2011

    Private developers considering integrated approach to generation & transmission

    Handful of transmission projects being developed by private sector independently or

    in JV with CTU / STU.

    Projects Identified byEmpowered committee /STU

    Tariff basedCompetitive Bidding

    Private Players

    With PGCIL orSTUs

    Monopoly Integrated orUnbundled

    Cost Plus Tariff

    POWERGRID SEB/Transco Joint Ventures

    Centre State

    Private Sector Participation

  • 7/29/2019 Power Sector Opportunities

    68/81

    Year SPV Agency kV Km Developer

    2009 East North Interconnection Co Ltd PFC 400 450 Sterlite Technologies

    2010 North Karanpura Transmission Co Ltd REC 400 1,045 Reliance Power Transmission

    2010 Talcher-II Transmission Co Ltd REC 400 592 Reliance Power Transmission

    2011 Raichur Sholapur Transmission Co Ltd REC 765 210 Patel+Simplex+BS Transcomm*

    2011 Bhopal Dhule Transmission Co Ltd PFC 765 1,000 Sterlite Technologies

    2011 Jabalpur Transmission Co Ltd PFC 765 635 Sterlite Technologies

    Private Sector Participation

    PPP Transmission Projects Awarded

    Empowered Committee identified 14 Projects of which first 6 projects awarded

    Private sector likely to be involved in development of evacuation systems for future

    UMPPs

    Private Sector Participation Contd

  • 7/29/2019 Power Sector Opportunities

    69/81

    Private Sector Participation Cont d

    Joint Venture with PGCIL

    Joint Venture Private Partner Evacuation from

    Project MW Location

    Parbati Koldam Trans. Corpn. Ltd Reliance (ADA) GroupParbati-II 800 Himachal

    Koldam 800 Himachal

    Torrent Power Grid Ltd Torrent Power Sugen-II 1148 Gujarat

    Jaypee Power Grid Ltd Jaypee Group Karcham-Wangtoo 1000 Himachal

    Teestavalley Power Transmission Ltd Teesta Urja Ltd (Athena) Teesta III 1200 Sikkim

    North East Transmission Co Ltd ONGC + IL&FS Tripura 727 Tripura

    Powerlinks Transmission Ltd Tata Power Tala HEP 1020 Bhutan

    Project Ownership Mode State kV

    Jaigad Power Transco Ltd JSW Energy JV MAH 400

    Maharashtra Eastern Grid Transmission Co Ltd Adani JV MAH 765

    Jhajjar KT Transco KPTL+Techno DBFOT HAR 400

    Maru Transmission Service Co Ltd GMR Energy BOOM RAJ 400

    Aravali Transmission Service Co Ltd GMR Energy BOOM RAJ 400

    UPPTCL Package -1 (Mainpuri-Bara) Isolux Corsan BOOT UP 765

    UPPTCL Package-2 (Mainpuri-Hapur / Mainpuri-Noida) Cobra + Megha BOOT UP 765

    Intra-State Transmission Projects

    Issues faced by Developers

  • 7/29/2019 Power Sector Opportunities

    70/81

    Issues faced by Developers

    Right of Way & Crop Compensation

    A transmission line right-of-way (RoW) and Crop Compensation is the single largest

    issue faced by project executors. Other requirements like clearances, financial

    closures etc. are secondary.

    New private sector entrants face several problems.

    Generation capacities failing to achieve deadlines

    Delays in the commissioning of generation capacities resulting in risk of revenue

    loss

    if the transmission line is completed as planned, it would lead to the line being idle

    due to a delay in the commencement of power generation.

    Forest Clearances

    Although Environmental clearance not required, forest clearance is required, if the

    transmission line passes through any forest.

    Approval from Forest Officer required even for carrying out a route survey

    Time consuming process & lack of adequate clarity

    Poor creditworthiness of DISCOMs poses significant payment security risks

    Financing Options

  • 7/29/2019 Power Sector Opportunities

    71/81

    Financing Options

    Suitable on account of longer tenors

    Interest cost is not competitive vis--vis other sourcesRupee Loan Tenor may be a constraint

    May attempt with refinancing undertaking from promoterECB

    Dependent on selection of EPC / Supplier Higher upfront costs and time consumingECA

    ADB / IFC funding available to transmission projects

    Pre-sanction ESDD may be a constraintMultilateral

    Key factors for financing

    Longer tenor requirement (especially for Projects won with competitive bidding)

    Revenue stream - annuity type Interest expense is the most significant cost during operations

    Structured repayments with bullet is favoured

    Key Risks & Mitigation

  • 7/29/2019 Power Sector Opportunities

    72/81

    Key Risks & Mitigation

    Risk Mitigation

    Construction Challenge in terms of design, geography and terrain (River Crossings, Railway

    line crossings, Forest Areas etc.)

    Experienced contractor critical for successful implementation

    Offtake Risk High risk due to high cost of the power producer.

    Power Purchase agreement with adequate Payment Security Mechanism

    Right of Way Obtaining Right-of-Way in a phased manner

    Assistance of Government for PPP projects in resolution of crop compensationissues.

    Approvals &

    Clearances

    Environmental Clearance not required for Transmission Projects

    Majority of the clearances and approvals are obtained during implementation

    Forest clearance (if any) from MoEF for route survey may be Pre Disbusement

    Condition

    Cost & TimeOverrun

    Comprehensive provisions for liquidated damages may be stipulated as part ofEPC contract

    Promoters undertaking to bear additional costs stipulated.

    Performance

    Shortfall

    Stringent clauses for defect liability.

    Performance Guarantee to be provided by EPC contractor

    Opportunities

  • 7/29/2019 Power Sector Opportunities

    73/81

    Transmission

    Rs.140,000 crore (USD 28 billion) required for proposed 220 kV and above

    transmission schemes in XI Plan

    Transmission planning moved away from the earlier generation evacuation

    system planning to integrated system planning

    Power Grid and State Utilities Driving the Growth in Transmission

    Many Transmission Project planned to be awarded to Private Sector through

    Competitive Bidding

    6 Projects already awarded through Competitive bid

    Initiative driven by PFC / REC

    22 large transmission projects have been identified for competitive bidding

    (outlay in excess of Rs 30,000 Cr)

    Opportunities

  • 7/29/2019 Power Sector Opportunities

    74/81

    Evolution of the Indian Power Sector

    Industry Structure and Present Scenario

    Generation - Thermal Power Projects

    Generation - Hydro Power Projects

    Generation Renewable Energy Projects

    Transmission

    Distribution

    Conclusion

    Distribution

  • 7/29/2019 Power Sector Opportunities

    75/81

    Distribution

    Distribution System could not keep pace with Generation and TransmissionSystems

    Of the aggregate losses of the State Power Utilities, 93% were at the

    Discom Level

    Costs of generation and transmission companies are pushed to DISCOM

    level which are unable to recover the same from the consumers

    Aggregate Book loss of Discoms have doubled in FY 10 to Rs 274 billion

    since FY 07

    Unfavourable mix of consumer mix and pricing

    High AT&C losses Low realization of subsidy

    Due to weak financial profile fresh loans have been curtailed by banks and

    financial institutions

    Salient Features

    Distribution Performance

  • 7/29/2019 Power Sector Opportunities

    76/81

    Distribution PerformanceAggregate Technical & Commercial (AT&C) Losses (%) in Major States

    2007-08 2008-09 2009-10

    Maharashtra 31.37 31.64 28.23Uttar Pradesh 43.09 40.12 39.65

    Andhra Pradesh 16.19 12.99 16.43

    Gujarat 22.81 22.04 22.81

    Punjab 19.10 18.51 17.73

    Rajasthan 33.02 29.83 30.07

    Karnataka 32.13 24.94 25.34

    Madhya Pradesh 45.85 46.61 41.03

    Aggregate Technical & Commercial (AT&C) Losses (%) - Regionwise

    2007-08 2008-09 2009-10

    Eastern 37.19 36.62 33.92North Eastern 36.67 40.70 36.44

    Northern 32.59 31.12 30.83

    Southern 20.10 16.92 19.49

    Western 31.95 31.64 28.23

    Grand Total 29.24 27.74 27.15

    Distribution Performance

  • 7/29/2019 Power Sector Opportunities

    77/81

    Distribution Performance

    With the approval of the Prime Minister the Planning Commission in July 2010 appointed a

    High Level Panel (Shunglu Committee) to look into the financial problems of SEBs.

    This Committee recommended a plan of action to achieve financial viability in distribution of

    power by 2017:

    Review of accounts and financial projections of SEBs and Discoms; tracking of capital

    work-in-progress

    Review Electricity Tariff and role of State Governments, State Regulators and SEBs/

    Discoms in periodic revision of tariff

    Evaluation of functioning of SERCs

    Assess system improvement measures

    Energy to agricultural sector to be supplied through a separate feeder

    Series of anti-theft measures for urban and rural areas

    Way Forward

    Distribution being the last link in the value chain of the power industry needs to be

    healthy

    Sound health of Discom is essential for healthy and efficient functioning of thePower Sector

  • 7/29/2019 Power Sector Opportunities

    78/81

    Evolution of the Indian Power Sector

    Industry Structure and Present Scenario

    Generation - Thermal Power Projects

    Generation - Hydro Power Projects

    Generation Renewable Energy Projects

    Transmission

    Distribution

    Conclusion

    Conclusion

  • 7/29/2019 Power Sector Opportunities

    79/81

    Way Forward

    Diversifying the fuel mix and the source of supply

    Political stumbling blocks and change in social behaviour poses a challenge

    Long term tie up for power purchase

    Timely fixation of tariffs and timely truing up

    Lowering of transmission and distribution losses

    Timely receipt of subsidy Substantial opportunities emerging in power sector post the reforms being

    undertaken by government.

    Sector exposure by Banks brings new opportunities for capital raising for

    power sector.

    Foreign financial institutions are keenly observing the reforms beingundertaken and would participate.

    At last but not the least, for economic growth in the country, power sector

    growth should be robust and consistent.

    Conclusion

  • 7/29/2019 Power Sector Opportunities

    80/81

    Thank You

    Abbreviations

  • 7/29/2019 Power Sector Opportunities

    81/81

    Abbreviations

    AT&C Aggregate Technical & Commercial

    BOOT Build Own Operate Transfer

    CDM Clean Development Mechanism

    CEA Central Electricity AuthorityCERC Central Electricity Regulation Commission

    ckm circuit kilometres

    CTU Central Transmission Unit

    CWET Centre for Wind Energy Technology

    DISCOM Distribition Company

    DPR Detailed Project Report

    DVC Damodar Valley CorporationECA Export Credit Agencies

    EOI Expression of Interest

    GBI Generation Based Incentive

    GENCO Generation Company

    GOI Government of India

    GSPC Gujarat State Petroleum Corporation

    KG Krishna-Godavari

    kWh kilo Watt-hourMnMT Million Metric Tonnes

    MNRE Ministry of New & Renewable Energy

    MoEF Ministry of Environment and Forests

    MoP Ministry of Power

    MW Mega Watt

    NBFC Non Banking Financial CompaniesNE North east

    NEC North Eastern Coalfields

    NHPC Formerly known as National Hydroelectric PowerCorporation

    NPCIL Nuclear Power Corporation of India Limited

    NPV Net Present Value

    PFC

    Power Finance CorporationPGCIL Power Grid Corporation of India Limited

    R&R Resettlement and rehabilitation

    REC Rural Electrification Corporation Limited

    RIL Reliance Industries Limited

    SEB State Electricity Board

    SERC State Electricity Regulatory Commission

    STU State Transmission Unit

    TRANSCO Transmission CompanyUMPP Ultra Mega Power Plant


Recommended